1 MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014
2 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2
3 Project Count ATC A in MTEP14 Project Summary 30 Projects by type Other - Other - Move Other - Economic Other - Distribution Other - Condition BaseRel - (blank) 0 $1M- $1M-5M $5M+ Project Cost Range 3
4 Project Cost Millions ATC A in MTEP14 Project Summary $160 Projects by in-service date $140 $120 $100 $80 $60 $40 $20 $ Years to in-service date 4
5 Construct Spring Valley-North Lake Geneva 138 New 25 mi x 138 kv line, 138/69 kv SS Rebuild 14 mi x 138 kv + 6 mi x 69 kv Expected In Service Date: Estimated Cost: $82M Project Type: Other N Reconductor Reconductor 5
6 Construct Spring Valley-North Lake Geneva 138 New 25 mi x 138 kv line, 138/69 kv SS Rebuild 14 mi x 138 kv + 6 mi x 69 kv Expected In Service Date: Estimated Cost: $82M Project Type: Other N Geneva 6
7 Construct Spring Valley-North Lake Geneva 138 P3808: Construct Bain-Spring Valley-North Lake Geneva 138 Reconductor Bain-Spring Valley 138 kv Reconductor Katzenberg-Richmond-Twin Lakes 69 kv Construct Geneva 138/69 kv substation Construct Spring Valley-Geneva 138 kv Construct Geneva-North Lake Geneva 138 kv Construct Twin Lakes-Geneva 69 kv Expected In Service Date: Estimated Cost: $83,850,000 System Needs: Network radial substations Assist LSE backing up load Allow transformer maintenance Project Type: Other 7
8 Rebuild Colley Road-Brick Church 69 kv Rebuild 21 mi x 69 kv Expected In Service Date: Estimated Cost: $35M Project Type: Other N Colley Road Brick Church 8
9 Rebuild Colley Road-Brick Church 69 kv P2031: Rebuild Colley Road-Brick Church 69 kv Reconductor 21 miles with T2 477 Add sectionalizing Replace weakened poles Expected In Service Date: Estimated Cost: $34,900,000 System Needs: Thermal overloading occurs under N-1 Sectionalizing capability Age and condition Project Type: Other 9
10 Uprate Oak Creek-Bluemound 230 kv ck 1&2 N OAC-BMD Uprate (29 mi + 39 mi) x 230 kv Expected In Service Date: 2016 and 2021 Estimated Cost: $12M + $2M Project Type: Other and BaseRel 10
11 Uprate Oak Creek-Bluemound 230 kv ck 1&2 P4337: Line 862 (ckt 2) Uprate 29 mi x 230 kv line to 1193/1397A SN/SE Clearances Jumpers, terminal equipment ISD: Estimated Cost: $4.9M System Needs: Study-Based Ratings Methodology Project Type:, Other P3486: Line 873 (ckt 1) Uprate 39 mi x 230 kv line to 1442/1792A SN/SE Clearances Jumpers ISD: Estimated Cost: $1.4M System Needs: Thermal Overloads under Category B contingencies Project Type: BaseRel Alternative Oak Creek spare transformer 11
12 Uprate Oak Creek-Pennsylvania 138 kv N OAC-PEN P2056: Uprate 4.5 mi x 138 kv Expected In Service Date: 2015 Estimated Cost: $19k Need: SBRM derated Project Type: BaseRel 12
13 Rebuild several older 138 kv lines N P3961 P3958 P3510 Rebuild ( mi) x 138 kv Expected In Service Date: Estimated Cost: $20 + $9 + $8M Project Type: Other 13
14 Rebuild several older 138 kv lines P3691: Rebuild Merrill Hills-Summit 138 kv Replace 7.4 miles of decaying 1953 H-frame with monopole; Reconductor with 477 T2, run OPGW $9.3M P3958: Rebuild Merrill Hills-Waukesha 138 kv Rebuild 7.3 miles of decaying 1953 H-frame with monopole; Reconductor with 477 T2, run OPGW $8.3M P3510: Rebuild Mukwanago-Edgewood-St.Martins 138 kv Rebuild 14 miles of 1925 lattice towers with monopole Reconductor with 477 T2, run OPGW Replace jumpers $19.9M Project Type: Other 14
15 Uprate Portage-Trienda 138 kv N POR-TRI Reconductor 4.3 mi x 138 kv Expected In Service Date: Estimated Cost: $2.2M Project Type: Other 15
16 Uprate Portage-Trienda 138 kv P1624: Uprate Portage-Trienda 138 kv Reconductor 4.25 miles with T2 477 Uprate equipment Expected In Service Date: Estimated Cost: $2,210,000 System Needs: SBRM derated Project Type: Other 16
17 N Install Fitzgerald kv Transformer T2 FITZ Install Fitzgerald kv Transformer T2 Expected In Service Date: Estimated Cost: $8.7M Project Type: BaseRel 17
18 Install Fitzgerald kv Transformer T2 P3965: Install Fitzgerald kv Transformer T2 Install a 2nd 336 MVA transformer Expand Fitzgerald 345 bus into a 4 section ring bus Split the Fitzgerald 138 bus into 2 sections with breaker Expected In Service Date: Estimated Cost: $8,720,000 System Needs: Thermal and voltage violations for N-1 during a scheduled construction outage in 2020 Project Type: Other 18
19 N Construct Fairwater-Mackford Prairie 69 kv Construct 7 mi x 69 kv Expected In Service Date: Estimated Cost: $22M Project Type: Other Retire Mackford Prarie-Ripon 19
20 N Construct Fairwater-Mackford Prairie 69 kv Construct 7 mi x 69 kv Expected In Service Date: Estimated Cost: $22M Project Type: Other Build Mackford Prairie-Fairwater Add Ripon- Metomen ckt 2 20
21 Construct Fairwater-Mackford Prairie 69 kv P1708: Construct Fairwater-Mackford Prairie 69 kv Construct Fairwater-Mackford Prairie 69 kv line Reconfigure the North Randolph-Ripon 69 kv line to form a second Ripon-Metomen 69 kv line Retire the circuit between Metomen and the Mackford Prairie tap Expected In Service Date: Estimated Cost: $22,200,000 System Needs: Asset renewal Loop service to Fairwater 69 kv Better sectionalizing Project Type: Other 21
22 Install South Sheboygan Falls 138 kv cap banks Install 2 x Mvar on 138 kv Expected In Service Date: Estimated Cost: $3.0M Project Type: BaseRel N SSF 22
23 Install South Sheboygan Falls 138 kv cap banks P4356: Install South Sheboygan Falls 138 kv cap banks 2 x Mvar x 138 kv Expected In Service Date: Estimated Cost: $2,970,000 System Needs: Prevent voltage collapse for N-1-1 Required for Edgewater 3 retirement Project Type: Other 23
24 Rebuild Munising-Blaney Park 69 kv N Inland Line Close, uprate Inland 53 mi x 69 kv Expected In Service Date: Estimated Cost: $16M Project Type: Other UPMI WI LPMI 24
25 Rebuild Munising-Blaney Park 69 kv P3096: Rebuild Munising-Blaney Park 69 kv and close Increase ground clearance for 167 F operation Replace 284 poles Reinsulate 494 structures Install arresters and grounding on 686 wood poles Expected In Service Date: Estimated Cost: $16,000,000 System Needs: Insulators are end-of-life Poor lightning performance Close in at Blaney Park to provide better service and flexibility to Munising Project Type: Other 25
26 ATC: A in MTEP14 reactive projects PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4420 Install expanded cap bank at Hillman 69 kv Increase the existing Hillman 69 kv cap bank size from 5.4 to 8.1 Mvar, voltage concerns during Hillman - Eden (Y-105) 69 kv line $40,000 Other, 4355 Install Montello 69 kv mobile cap bank Install mobile cap bank 1x8.17 Mvar at Montello 69 kv substation rebuild $200,000 Other, 26
27 ATC: A in MTEP14 breaker projects PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4351 Replace Portage 138 kv Replace Portage 138 kv Asset Management $820,000 Other, bus tie breaker bus tie breaker, CT's and Condition disconnect switches 4354 Install Neenah Creek 69 kv line breakers Add line breakers to line Y-100 at Neenah Creek 69 kv $4,620,000 Other, 4352 Install Berlin 69 kv bus tie Add a 69 kv bus tie Asset Management $3,930,000 Other, breaker 3815 Install East Rockton 69 kv breakers breaker at Berlin 69 kv breaker addition and T-D rebuild Condition $340,000 Other, 27
28 ATC: A in MTEP14 rebuild projects 1/3 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 3524 Rebuild Rubicon-Butler 138 kv Rebuild 3.1 mile section of the Rubicon-Butler Asset Management, Maintenance $2,550,000 Other, Condition Ridge 138 kv 3890 Reconductor Port Washington-Saukville 138 kv 4 Reconductor Port Washington-Saukville 138 kv line, SBRM $13,000 Other, 3891 Reconductor Port Washington-Saukville 138 kv Rebuild Hartford-Butler Ridge 138 kv 3900 Reconductor Bain-Albers 138 kv Reconductor Port Washington-Saukville 138 kv line Rebuild 2.5 mile section of the Butler Ridge- Hartford 138 kv Reconductor Bain-Albers 138 kv line, SBRM $22,000 Other, Asset Management/Maintenanc e $1,850,000 Other, Condition, SBRM $1,100,000 Other, 28
29 ATC: A in MTEP14 rebuild projects 2/3 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4728 Reconfigure University 138 kv area Reconfigure the University area lines of Whitewater-University, Bluff Creek-University and Mukwonago- Whitewater, SBRM $1,080,000 Other, 4711 Rebuild Wautoma- Montello Tap 69 kv line Rebuild 13.1 miles with T2 4/0 Penguin. Rebuild 6.1 miles with T2 4/0 Asset Management $20,450,000 Other, Condition 3909 Rebuild Fitchburg-Nine Springs 69 kv 3904 Reconductor McCue- Lamar 69 kv Penguin. Rebuild and Reconductor Fitchburg-Nine Springs 69 kv line Reconductor McCue- Lamar 69 kv line, SBRM $3,950,000 Other,, SBRM $2,670,000 Other, 29
30 ATC: A in MTEP14 rebuild projects 3/3 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 3902 Reconductor Waunakee- Westport 69 kv Reconductor Waunakee- Westport 69 kv line, SBRM $2,830,000 Other, 3910 Rebuild Royster-Pflaum 69 kv Rebuild and Reconductor, SBRM Royster-Pflaum 69 kv $1,820,000 Other, 4731 Rebuild Horicon 69 kv Bus line Replace the 4/0 Copper Main Strin Bus, Jumpers and lugs. Asset Management - Age and condition $210,000 Other, Condition 30
31 ATC: A in MTEP14 rating projects 1/4 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4350 Rerate Pleasant Prairie- Racine 345 kv line Fix line clearances to bring line rating to 200/275F, Racine terminal limitations removed Economic, SBRM $1,770,000 Other, Economic 4357 Rerate Brick Church- Beloit Gateway 138 kv line Fix several line clearance sections to bring line rating to 1172 amps all $190,000 Other, Condition 3899 Uprate Rock Springs Tap- Kirkwood 138 kv 3887 Uprate Ramsey-Barland 138 kv 4348 Rerate Freeman-National 138 kv line seasons Increase line conductor clearances Rock Springs Tap-Kirkwood 138 kv line Uprate Ramsey-Barland 138 kv line Fix several line clearance sections to bring line rating to 167F Economic $1,520,000 Other, Economic, SBRM $1,340,000 Other,, SBRM $610,000 Other, 31
32 ATC: A in MTEP14 rating projects 2/4 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4705 Uprate Rock River - Marine Tap (X-23) 138 kv line Uprate Rock River - Marine Tap (X-23) 138 kv line to 200/300 deg F, SBRM $440,000 Other, 4423 Uprate 20th Street - Northgate Sheboygan Tap (X-64) 138 kv line 3889 Uprate Morrison Ave- Sherman 115 kv 3915 Uprate Rocky Run-Plover 115 kv 4706 Rerate Highway 8 - Skanawan (I-9) 115kV line 3167 Uprate North Monroe- South Monroe 69 kv Line Uprate 20th Street - Northgate Sheboygan Tap (X-64) 138 kv line to original limits under SBR ratings Uprate Morrison Ave- Sherman 115 kv line Replace jumpers at Plover 115 kv Rerate Highway 8 - Skanawan (I-9) 115kV line to 300 deg F Uprate North Monroe- South Monroe 69 kv Line (Y-87), SBRM $12,000 Other,, SBRM $170,000 Other,, SBRM $230,000 Other,, SBRM $1,190,000 Other, : N-1 thermal $2,160,000 Other, 32
33 ATC: A in MTEP14 rating projects 3/4 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 3885 Uprate Crystal Falls- Aspen 69 kv Uprate Crystal Falls- Aspen 69 kv line, SBRM $4,470,000 Other, 3907 Uprate Danz Ave- University 69 kv Replace jumper at Danz Ave 69 kv, SBRM $2,890,000 Other, 3903 Uprate Wautoma-ACEC Wild Rose Pump 69 kv Uprate Wautoma-ACEC Wild Rose Pump 69 kv, SBRM $2,570,000 Other, 1726 Uprate Royster- Sycamore 69 kv line Uprate Royster- Sycamore 69 kv line to, SBRM $2,180,000 Other, 3914 Uprate Coloma Tap- Chaffee Creek 69 kv 115 MVA Uprate Chaffee Creek- Acec Coloma Tap 69 kv, SBRM $970,000 Other, 4708 Rerate 9 Mile-Portage Street 69 kv line (6901) Rerate the main line segment of 6901 to allow operation at 168 deg F $570,000 Other, 4710 Rerate Sheepskin- Evansville Tap 69 kv line Rerate the main line segment of Y-158 to allow operation at 200 deg F $250,000 Other, 33
34 ATC: A in MTEP14 rating projects 4/4 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4707 Rerate 3 Mile-Portage Street 69 kv line (6902) Rerate the main line segment of ESE_6902 to $270,000 Other, allow operation at 168 deg F 4709 Rerate Lincoln Pumping Station-McKenna 69 kv line Rerate the main line segment of Y-145 to allow operation at 200 deg F normal and $180,000 Other, 4733 Rerate Twin Falls- Randville Tap 69 kv line deg F emergency Rerate Twin Falls - Randville Tap (6730) 69kV line to a rating of 200 degrees F $170,000 Other, 34
35 MISO West Region DAIRYLAND POWER COOPERATIVE 35
36 Rebuild N Marshland-Briggs Road 161 kv Rebuild Rebuild 15 mi x 161 kv Expected In Service Date: Estimated Cost: $13M Project Type: Other Condition 36
37 MISO West Region XCEL ENERGY 37
38 Project Count Xcel A in MTEP14 Project Summary 7 Projects by cost and type $1M- $1M-5M $5M+ Other - Other - Condition BaseRel - (blank) 38
39 N Reconductor Split Rock-Lakefield Jct 345 kv Split Rock- Nobles-Lkfld Jct Reconductor 35 mi x 345 kv x 477 T2 Expected In Service Date: Estimated Cost: Project Type: Other 39
40 Reconductor Split Rock-Lakefield Jct 345 kv P4697: Reconductor Split Rock-Lakefield Jct 345 kv Replace approximately 35 miles of 954 ACSS with 477 T2 between the Split Rock and Lakefield Junction substations Expected In Service Date: Estimated Cost: System Needs: Galloping Project Type: Other 40
41 N Install reactor at Lawrence Creek 161/115 kv Lawrence Creek Install 1 x 25 Mvar reactor Expected In Service Date: Estimated Cost: Project Type: BaseRel 41
42 N Install reactor at Lawrence Creek 161/115 kv Lawrence Creek Install 1 x 25 Mvar reactor Expected In Service Date: Estimated Cost: Project Type: BaseRel 42
43 Install reactor at Lawrence Creek 161/115 kv P4691: Install reactor at Lawrence Creek 161/115 kv 1 x 25 Mvar on 161 kv Expected In Service Date: Estimated Cost: System Needs: High voltages on the Xcel 115 kv, 161 kv and DPC 161 kv system during light load Project Type: BaseRel 43
44 N Install Gravel Island 161 kv Capacitor Banks Gravel Island Install 2 x 30 Mvar on 161 kv Expected In Service Date: Estimated Cost: Project Type: Other 44
45 Install Gravel Island 161 kv Capacitor Banks P4694: Install Gravel Island 161 kv Capacitor Banks 2 x 30 Mvar on 161 kv Expected In Service Date: Estimated Cost: System Needs: Low voltage relief during N-1-1 Project Type: Other 45
46 N Install Souris 115 kv Capacitor Bank Manitoba Souris Install 2 x 15 Mvar on 115 kv Expected In Service Date: Estimated Cost: Project Type: Other ND Coal 46
47 Install Souris 115 kv Capacitor Bank P4690: Install Souris 115 kv Capacitor Bank 2 x 15 Mvar on 115 kv Expected In Service Date: Estimated Cost: System Needs: Voltage support for Souris 115 kv Project Type: Other 47
48 N Install Ft. Ridgley 115 kv Cap Banks Granite Falls Metro Install Mvar on 115 kv Expected In Service Date: Estimated Cost: Project Type: Other New Ulm Mankato 48
49 Install Ft. Ridgley 115 kv Cap Banks P4692: Install Ft. Ridgley 115 kv Cap Banks Expand existing 14 Mvar cap bank to 21 Mvar Add a second 20 Mvar bank expandable to 40 Mvar Expected In Service Date: Estimated Cost: System Needs: Low voltages at Swan Lake for N-1 before CapX N-1-1 after CapX Project Type: Other BaseRel 49
50 Xcel: Other MTEP14 projects 1/2 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4689 Install Cartwright 69 kv capacitor bank Installing a 8.5 Mvar capacitor bank at Cartwright Due to the large forcasted load growth in the area, it is necessary $480,000 Other, 4685 Install Tremval 2nd kv Transformer 4687 Install Jim Falls 2nd kv Transformer Add a 2nd kv transformer at Tremval substation and convert the substation to a 3 row breaker and a half configuration. Add a 2nd 115/69 kv transformer and breakers at Jim Falls substation. for voltage support Sand mine load growth $6,000,000 Other, Sand mine load growth $3,700,000 Other, 4686 Construct Dovre 69 kv Breaker Station Install a new distribution substation tapping the 69 kv line 3424 in the Jim Falls/Barron area. Sand mine load growth $2,600,000 Other, 50
51 Xcel: Other MTEP14 projects 2/2 PrjID Project Name Project Description System_Need ISD Cost Estimate Type 4688 Construct Harstad County Install a new distribution The sub is needed for $40,000 Other, Park 69 kv Sub substation between Falls Creek and DPC Bear Grass; install 7.2 Mvar capacitor bank load growth/distribution and the cap is needed for voltage support 4684 Rebuild Alma Center- DPC Merrillian 69 kv 4693 Rebuild Douglas County- West Union 69 kv Rebuild 8.1 miles of 1/0 ACSR conductor between Alma Center and DPC Merrillan Tap to TW Rebuild the Douglas County - West Union 69 kv line to 477 ACSR and transfer Osakis substation load to Douglas County Sand mine load growth $2,950,000 Other, This line overloads during peak conditions Other, 51
52 Contact Information David Duebner Manager, Expansion Planning Tyler Giles Engineer, Expansion Planning 52
ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --
ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20
More informationATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition
TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372
More informationTwin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN
Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie
More informationAppendix B. Summary of Changes to the Year Assessment
Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from
More informationMTEP13 SPM #2- Central Region. March 25, 2013
MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for
More informationATC Planning Zone 3 Generation Integration Screening Study. December, 2018
Page 1 ATC Planning Zone 3 Generation Integration Screening Study December, 2018 ATC voluntarily performed a high level, steady-state screening of transmission facilities in ATC Planning Zone 3, which
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationHighly Constrained Elements Within ATC Footprint
Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market
More informationChapter 7 - Appendix A
Chapter 7 - Appendix A Transmission and Distribution Supplemental Information Table 7A.1 MTEP Transmission Projects in Missouri 1 Project Approved Project Title Project Description Category Estimated Cost
More informationEntergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects
Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability
More informationMTEP14 South SPM #2. MISO Texas Project Information. April 7, 2014
MTEP14 South SPM #2 MISO Texas Project Information April 7, 2014 MISO Southern Region EAST TEXAS ELECTRIC COOPERATIVE 2 East Texas Electric Cooperative (ETEC) No projects submitted for moving to Appendix
More informationSub Regional RTEP Committee - Southern. August 19, 2011
Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic March 23, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEC Transmission Zone: Supplemental Project 69/12kV Wenonah Substation Retire/Bypass
More informationImpacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities
Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432
More informationSection III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment
Section III STATUS OF PROJECTS This section identifies transmission projects that were completed in 200, are under construction or are in the approval stage. This section also provides a list of projects
More informationEast. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission
Southeastern Region Transmission Planning East Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Southeastern Region Transmission
More informationGeneration Deactivation Notification Update
Generation Deactivation Notification Update Transmission Expansion Advisory Committee November 8, 2018 Generation Deactivations for 2018 2 Generation Deactivation ATSI Transmission Zones Bruce Mansfield
More informationSouth Dakota 890 Study
South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationEntergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects
Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill
More informationEast. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission
Southeastern Region Transmission Planning East Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Southeastern Region Transmission
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic September 24, 2014 1 Reliability Analysis Update 2 AE Transmission Zone Generation Deliverability Violation: The Middle 230/69 kv is overloaded for line fault stuck
More informationSoutheastern Region Transmission Planning. 10 Year Transmission Expansion Plan
10 Year Transmission Expansion Plan Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More information2016 SPP Transmission Expansion Plan Project List Kansas Projects
WR Zonal Reliability $9,308,090 Build 6.7 mile Clay Center Switching Station to TC Riley 115 kv line 6/1/2018 10/1/2012 115 6.7 Install a 2000 Amp bus system, GOAB switches, metering and WR Zonal Reliability
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationEast. Georgia Integrated Transmission System (ITS) Jointly Planned ITS. Dalton Utilities. GTC (Georgia Transmission Corporation)
East Georgia Integrated Transmission System (ITS) Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Jointly Planned ITS Southern Company Transmission Expansion
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the
More informationSPP Notification to Construct
February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationWestern Area Power Administration
2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,
More informationState Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009
State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under
More informationEntergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects
Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 13, 2006 1 Approved 2006 2010 ELL-South Transmission
More informationPJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G
PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated
More informationEast. Georgia Integrated Transmission System (ITS) GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA)
East Georgia Integrated Transmission System (ITS) Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Expansion Item E-1 Daniel
More informationMinnesota Biennial Transmission. Zone Meeting 8
Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives
More informationATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M
of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is
More informationKey to Status Fields in the Project List
Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning
More informationSub-Regional RTEP Committee PJM South
Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates
More informationMinnesota Biennial Transmission. Zone Meeting 8
Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 24 Queensboro 115 kv Switching Station: Construct 0062A,B,C,D Build 4-terminal 115 kv switching station at Queensboro substation. Terminate the existing Queensboro St. Andrews, Church Creek
More informationTEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY
TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More information7.7 Southeast Zone. Transmission Projects Report Section 7: Needs
7.7 Southeast Zone The following table provides a list of transmission needs identified in the Southeast Zone and the map on the following page shows the location of each item in the table. Southeast Zone
More informationIllinois State Report
July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:
More informationPG&E s 2012 Request Window Proposals
1 PG&E s 2012 Request Window Proposals Central Valley Patrick Tan Transmission System Planning PG&E September 27, 2012 Transmission Projects Overview 2 Projects Seeking CAISO Approval Pease 115/60 kv Transformer
More informationProposed New Construction for
Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationFirst Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012
First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7
More informationOCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC
OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,
More informationATC Report Aug 14, 2003 Event Part 1. Edina Bajrektarević Transmission Operations
ATC Report Aug 14, 2003 Event Part 1 Edina Bajrektarević Transmission Operations ATC Overview 1. ATC owns, plans, maintains and operates transmission assets in portions of Wisconsin, Michigan and Illinois
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationSub Regional RTEP Committee - Southern
Sub Regional RTEP Committee - Southern March 03, 2011 www.pjm.com 2010 RTEP Analysis Summary Review of ongoing projects Stakeholder request 2015 Analysis Update Review of NOVA Reliability Deficiencies
More informationLarge Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project
Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationCapX 2020 Technical Update: Identifying Minnesota s Electric Transmission Infrastructure Needs May 2005
CapX 2020 Technical Update: Identifying Minnesota s Electric Transmission Infrastructure Needs May 2005 EXECUTIVE SUMMARY Background Minnesota s electric transmission infrastructure, a network of transmission
More informationPJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:
PJM SRTEP Meeting 2-13-2018 Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: The problem statement states two 138kV CB s will be installed at Ambler Ridge, however the potential solution
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationSub Regional RTEP Committee Western Region ATSI
Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationSPP Notification to Construct
SPP Notification to Construct SPP-NTC-20123 February 14, 2011 Mr. Sam McGarrah Empire District Electric Company PO Box 127 Joplin, MO 64802 RE: Notification to Construct Approved Reliability Network Upgrades
More informationInterconnection Feasibility Study Report Request # GI
A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationTransmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board
Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper October 2013 EXECUTIVE SUMMARY On December 5, 2012 the PJM Board of Managers approved changes to the
More informationWestern Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04
Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic May 25, 2018 First Review Baseline Reliability and Supplemental Projects 2 Aging Infrastructure The 20.7 mile Five Forks Windy Edge 110511/110512 115kV Circuit
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationAMERICAN TRANSMISSION COMPANY
AMERICAN TRANSMISSION COMPANY UPDATE 2003 10-YEAR TRANSMISSION SYSTEM ASSESSMENT March 2004 Table of Contents Page No. Executive Summary...1 Section I ATC s Public Planning Process...5 Introduction...5
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South October 30, 2017 Baseline Reliability and Supplemental Projects First Preliminary Review 2 Dominion: Baseline Violation 115 kv Line #43 Staunton to Harrisonburg End of
More information2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)
2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017) May 2018 This report reflects information for the portion of Indiana within the PJM service territory. Table of Contents 1.
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationQ0044 interconnection at
Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description
More informationNational Grid s 2018 Local Transmission Plan
National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationSERTP rd Quarter Meeting
2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please
More informationAPPENDIX F: 2012 Request Window Submittals
APPENDIX F: 2012 Request Window Submittals Table F-1: 2012 Request Window Submittals Project Name Service Submitted by 1 Lockeford-Lodi 230 kv Development City of Lodi, Electric Utility Department 5/31/2017
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationTri-State December 2013 Board Meeting
1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)
More informationPublic Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016
Public Service Company of Colorado Transmission Projects Status CCPG May 5, 2016 1 Transmission Ownership Colorado 2016 Transmission Planning Drivers Load Service / Near-Term (1-5 years) TPL Studies (5
More informationVERMONT ELECTRIC POWER COMPANY (VELCO)
TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first
More information2016 SDG&E Grid Assessment Results
2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year
More informationSub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting
Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting November 28, 2018 JCP&L Transmission Zone Need Number: JCPL-2018-001 Process Stage: Solution Meeting Need Presented: 9/21/2018
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationMay 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909
Amy C. Monopoli Counsel Regulatory & Legislative Phone: 774-452-4227 amonopoli@itctransco.com May 11, 2017 Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection