Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Size: px
Start display at page:

Download "Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016"

Transcription

1 Public Service Company of Colorado Transmission Projects Status CCPG May 5,

2 Transmission Ownership Colorado 2016

3 Transmission Planning Drivers Load Service / Near-Term (1-5 years) TPL Studies (5 year capital budget) Longer-Term (5-10 years) WestConnect, CCPG, Public Policy Resource Accommodation PSCo Resource Plans Generator Interconnection Requests Public Policy Senate Bill (SB-100) Clean Air Clean Jobs Act (CACJA) Other Tariff Studies Transmission Service 3

4 Generation Name Interconnection Owner Net MW Type ISD Arapahoe 3 (retired) Arapahoe PSCo -44 Coal 2014 Limon 3 Missile Site 345 kv NextEra 200 Wind 2014 Zuni 2 (retired) Zuni PSCo -65 Coal 2015 Golden West Jackson Fuller 230 kv Golden West 250 Wind 2015 Hooper 1 San Luis Valley 230 kv Solar Star 52 Solar (PV) 2015 Comanche Solar Comanche 230 kv Comanche Solar 120 Solar (PV) 2016 Cherokee 3 (retired) Cherokee 115kV PSCo -152 Coal 2016 Cherokee 5,6, 7 Cherokee 115kV PSCo 570 Gas (CC) 2016 Rush Creek Missile Site 345 kv PSCo 600 Wind

5 Rush Creek Generation Project CPUC Rule MW of New Wind Generation 90 Miles of 345 kv Transmission PSCo-Owned Interconnect at Missile Site In-Service Date: 2018 Need Pawnee Daniels Project Filing with the Commission on May 13,

6 Rush Creek Map 6

7 New Substations 2016 Happy Canyon (IREA Wholesale Load) Cloverly (Pleasant Valley - Retail Load) 2019 Husky (New Ault) Graham Creek (New Eaton) 2022 Beebe Draw (LaSalle Replacement) Box Elder Replacement Distribution Avery (2017) Thornton (2017) Moon Gulch (2018) Barker (2021) Conceptual: New Castle () Wilson () National Western () Sterling Ranch () Surrey Ridge () : Bluestone Valley 7

8 New Transmission Planned 2016 Rifle Parachute 230 kv # Rush Creek Missile Site 345 kv 2019 Ault Cloverly 230/115 kv Pawnee Daniels Park 345 kv 2021 Avon Gilman 115 kv 2022 Weld Rosedale 230 kv Milton Rosedale 230 kv Conceptual San Luis Valley Glenwood Rifle Upgrade Parachute Cameo 230 kv Lamar Front Range Weld County Expansion (Greeley East) Hayden Foidel Gore Pass 230 kv Loop

9 Denver/Boulder # Thornton 4 Moon Gulch Project Comments ISD* Drivers 1 Moon Gulch Substation Proposed new Distribution Substation in either the City of Arvada or Jefferson County to serve distribution loads 2017 Distribution 2 Pawnee Daniels Park 345 kv Transmission Line Add an additional 345 kv line between the Pawnee and Daniels Park substations CherokeeArvada-Ridge 230kV Conversion Convert the existing 115kV line between the Cherokee and Ridge substations to a 230kV line and Distribution 4 Thornton Substation New substation in Thornton to serve distribution loads. Replaces the Brantner Substation project Distribution 5 Barker Substation New Substation in Denver Area to serve distribution load growth in Historic Ballpark Area 2021 Distribution DENVER 2 *All project in-service dates subject to change 9

10 Foothills/Greeley Area # Rosedale 1 10 *All project in-service dates subject to change Project Comments ISD* Drivers 1 Southwest Weld Transmission Project (SWEP) Participate with Tri-State Project to improve reliability, increase load-serving and resource injection capability 2017 Load Growth Resource 2 Milton Rosedale 230 kv New line from Rosedale Substation to Milton Substation Combined with Weld Rosedale 230kV line creates 230kV backbone south of Greeley Load Growth 3 Rosedale Weld 230 kv Beebe Draw Substation (La Salle Upgrade) New line from Rosedale Substation to Ault Substation. Build a new 230 kv substation (Beebe Draw) to replace the existing 44kV La Salle Substation. Combined with Milton Rosedale 230kV to create 230kV backbone south of Greeley Load Growth 4 Weld County Expansion High voltage transmission from Ault to Greeley Resource 5 Avery Substation New distribution substation to serve loads in the area 2017 Distribution 6 Wilson Substation New 115kV substation to serve distribution loads. This project will tap PRPA s 115kV Horseshoe West transmission line Distribution 7 Ault Cloverly 230/115kV Subs: Husky, Graham Ck. New line from Ault Substation to Cloverly Substation. Create new substations near PSCo Ault and Eaton to move 44 kv loads to higher voltage Load Growth Resource 8 Severence Substation Add in a new 230 kv substation by tapping the Weld Ft. St. Vrain line to service a retail customer Retail Load 9 Barnesville Substation / DCP Lucerne 2 Barnesville 115 kv Add in a new 115 kv Substation via a new line from DCP Lucerne to the Barnesville Substation to service a retail load Retail Load 10 Box Elder Replacement Convert 44kV Box Elder Substation to a 115kV substation to service growing loads in the area. Might tie into SWEP Load Growth 10

11 Current System Future System

12 Western Slope / Mountain Area # *All project in-service dates subject to change Comments ISD* Drivers 1 Grand Jct 138/115kV Replace 50 MVA TX with 100 MVA TX Bluestone Valley Substation New 230/69 kv transformer at Bluestone. New 4 mile 69 kv line from Bluestone to Debeque 3 Rifle Parachute 230 kv Line New, second 230 kv line between Rifle and Parachute 2016 Load Growth 4 Hayden Foidel Gore Pass 230kV Loop loop Hayden-Gore Pass 230kV line into Foidel Creek Substation creating a Hayden-Foidel Creek 230kV Line #2 and a Foidel Creek-Gore Pass 230kV line. 5 Glenwood-Rifle 69 to 115kV Replace existing Glenwood-Rifle 69 kv transmission system with 115 kv system 6 Gilman Avon 115kV Line New 10-mile 115kV line in Eagle County for reliability and alternate source to Holy Cross customers Parachute Cameo 230kV Line New 230 kv line from the Parachute substation to Cameo substation 8 New Castle Substation Construct a new 115 kv substation to service Distribution loads in New Castle Distribution 9 Wolcott Reactor Install 40 MVAR reactor at Wolcott Project 12

13 Rifle -Parachute 230kV Project (#2) Purpose: Serve anticipated load growth (electric-driven compressors) in the Piceance Basin Description 20 mile 230kV line Electrically parallel to existing 230kV line Status Filed CPCN in Dec 2012 CPCN Granted Feb 2013 ISD

14 Rifle -Parachute 230kV Line #2 Location Map 14

15 South Denver/CO Springs Area # 1 Project IREA Happy Canyon Comments Construct a new 115 kv substation for IREA ISD* 2016 Drivers Wholesale Customer 1 *All project in-service dates subject to change 15

16 PSCo Public Policy Senate Bill Designate Energy Resource Zones (ERZ) Develop plans for the construction or expansion of transmission facilities necessary to deliver electric power consistent with the timing of the development of beneficial energy resources located in or near such zones Consider how transmission can be provided to encourage local ownership of renewable energy facilities Submit proposed plans, designations, and applications for certificates of public convenience and necessity to the commission 16 16

17 Public Service Company of Colorado SB-100 projects 17

18 Senate Bill 100 Project List Item Project Zone In Service Date* Project Status 2 Nov 2010 In Service No CPCN Required 3,4,5 Jun 2011 In Service CPCN: July 2009 Planned 1. Missile Site 230kV Switching Station 2. Midway-Waterton 345kV Transmission Project 3. Missile Site 345kV Switching Station 2 October 2012 In service CPCN: June Pawnee-Smoky Hill 345kV Transmission Project 1 June 2013 IN Service CPCN: Feb Pawnee-Daniels Park 345kV Transmission Project CPCN: April , 3 Studies Complete. No plans for full build-out at this time Conceptual 6. Lamar-Front Range 345kV Transmission Project 7. Lamar-Vilas 230kV Transmission Project 3 See Lamar Front Range 8. Weld County Expansion Project 1 Studies Ongoing 9. San Luis Valley ? *All project in-service dates subject to change Ongoing CCPG SLV Subcommittee 18

19 Pawnee to Daniels Park Cost $152 million In-service date: 2019 Purpose:, SB ; Infrastructure: 124-mile transmission from Pawnee Substation to Daniels Park Substation and from Smoky Hill Substation to Daniels Park Substation Open House Meetings in September 19

20 PSCo Regulatory Activities Rule 3206 Rule 3627 Zinn Photography/Courtesy of SunEdison 20

21 CPUC Rule 3206 Construction or Extension of Transmission Facilities Filed Annually end of April Commission Determines: Ordinary Course of Business CPCN Required PSCo Filed Projects: SWEP Participation Ault Cloverly 230/115 kv Weld Rosedale 230 kv Rosedale Milton 230 kv Rush Creek Missile Site 345 kv Wolcott 40 MVAR Reactor 21

22 CPUC Rule 3627 Requires Regulated Utilities to File Transmission Report 10-Year Plan, 20-Year Scenario; 2-year cycle Black Hills, Tri-State, Public Service Use CCPG as Forum Proactive Stakeholder Participation Report Filed February 2016 Proceeding Consolidated with SB Comments Received from OCC and IEA Responses Filed April 29 ALJ Assigned to Facilitate Expect Workshop Q Goal: Ruling of Adequacy 22

23 23

24 Patrick Corrigan (303) Tom Green (303)

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016 Public Service Company of Colorado Transmission Projects Status CCPG August 18, 2016 1 Transmission Ownership Colorado 2016 Generation Additions/Reductions Name Interconnection Owner Net MW Type ISD Zuni

More information

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects

More information

RULE 3206 REPORT PROPOSED CONSTRUCTION OR EXTENSION OF TRANSMISSION FACILITIES 2013 THROUGH Docket No. 12M-165E

RULE 3206 REPORT PROPOSED CONSTRUCTION OR EXTENSION OF TRANSMISSION FACILITIES 2013 THROUGH Docket No. 12M-165E RULE 3206 REPORT PROPOSED CONSTRUCTION OR EXTENSION OF TRANSMISSION FACILITIES 2013 THROUGH 2015 Docket No. 12M-165E April 30, 2012 P.O. Box 840 Denver, Colorado 80201-0840 April 30, 2012 Mr. Doug Dean,

More information

PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO.

PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO. PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL 07-100 DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO. 15M- E October 30, 2015 TABLE OF CONTENTS Section Page I. INTRODUCTION...

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Tri-State December 2013 Board Meeting

Tri-State December 2013 Board Meeting 1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Proposed New Construction for

Proposed New Construction for Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado System Impact Study T-2007-3 Final.doc System Impact Study Report Request # T-2007-3 900 MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado Executive Summary PSCo Transmission

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

WestConnect Regional Planning Update

WestConnect Regional Planning Update WestConnect Regional Planning Update WRP Energy Committee May 4, 2015 Webinar Outline WestConnect Overview Membership, Structure & Footprint Planning process and regulatory status Order 890 Update (2014)

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

VERMONT ELECTRIC POWER COMPANY (VELCO)

VERMONT ELECTRIC POWER COMPANY (VELCO) TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

Michigan Thumb Loop Transmission Line Project

Michigan Thumb Loop Transmission Line Project Michigan Thumb Loop Transmission Line Project ITC Holdings Corp. Simon Whitelocke VP., Regulatory and External Affairs October 30, 2013 What is Transmission? The electric transmission system is the network

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO IN THE MATTER OF THE APPLICATION OF TRI-STATE GENERATION AND TRANSMISSION ASSOCIATION, INC. FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Pacific Gas and Electric Company s 2013 Annual Progress Report

Pacific Gas and Electric Company s 2013 Annual Progress Report March 14, 2013 Mr. David Franklin Chair, WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake

More information

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran System Impact Study_50 MVA Load Interconnnection Request Near Collbran.doc Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran PSCo Transmission

More information

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013 Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation

More information

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets

More information

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Energy Storage Policies Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Storage Law and Policy l California has supported energy storage through

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009 State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

Minnesota Biennial Transmission. Zone Meeting 8

Minnesota Biennial Transmission. Zone Meeting 8 Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives

More information

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center

More information

Arizona Transmission Challenges

Arizona Transmission Challenges Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368

More information

SDG&E Customer Distributed Generation Programs. Steve Jaffe Senior Market Advisor Customer Innovations Group September 14, 2009

SDG&E Customer Distributed Generation Programs. Steve Jaffe Senior Market Advisor Customer Innovations Group September 14, 2009 SDG&E Customer Distributed Generation Programs Steve Jaffe Senior Market Advisor Customer Innovations Group September 14, 2009 About SDG&E... A regulated public utility that provides service in San Diego

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn Transmission Planning for Wind Energy Resources in the Eastern United States Dale Osborn Layered Design Typical utility planning Distribution delivery to loads Lower voltage transmission delivery from

More information

California and the Western Grid: Transmission Challenges

California and the Western Grid: Transmission Challenges California and the Western Grid: Transmission Challenges IEEE PES May 11, 2006 Stewart Ramsay, Vice President, Asset Management & Electric Transmission, Pacific Gas and Electric Company California s RPS

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (OCTOBER 2016) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Consumers Energy Net Metering

Consumers Energy Net Metering Consumers Energy Net Metering ELODY SAMUELSON September 20, 2016 Consumers Energy About Us Territory Overview 2 FOURTH-LARGEST COMBINATION UTILITY IN THE UNITED STATES Electric Utility 1.8 million electric

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Eyre Peninsula electricity supply options investigation

Eyre Peninsula electricity supply options investigation 20 November 2017 South Australia s electricity transmission specialist Eyre Peninsula electricity supply options investigation Project Assessment Draft Report Port Lincoln Public Forum electranet.com.au

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. John Fulton Southwestern Public Service Company P.O. Box 1261 Amarillo, TX 79105 RE: Notification to Construct Approved Reliability Network Upgrades

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

California Independent System Operator. Memorandum

California Independent System Operator. Memorandum California Independent System Operator Memorandum To: ISO Board of Governors From: Armie Perez, Vice President of Planning and Infrastructure Development Date: Re: Decision on Tehachapi Project This memorandum

More information

2016 SDG&E Grid Assessment Results

2016 SDG&E Grid Assessment Results 2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year

More information

Interconnection and Net Metering Service in Ohio

Interconnection and Net Metering Service in Ohio Interconnection and Net Metering Service in Ohio Partnership between National Association of Regulatory Utility Commissioners and The National Commission for Energy State Regulation of Ukraine June 20,

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009)

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009) COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI-2007-12, RESTUDY 1 (August 6, 2009) On June 15, 2009 Xcel Energy released a restudy of a System Impact

More information

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications 1. Who is a self-generation or Net Metering Member? This is a Member who has installed grid-connected renewable generation, such

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and RESOLUTION NO. WHEREAS, the City of Los Angeles (City) Department of Water and Power (LADWP) will be further accelerating its efforts to replace its aging Power System infrastructure, much of which was

More information

2011 LOCAL TRANSMISSION PLAN:

2011 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2011 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report 260 TO: FROM: SUBJECT: ECAC Members Jamie Asbury, deputy energy manager, Business/Regulatory Five (5) Generator Interconnection

More information

for DRECP Alternatives

for DRECP Alternatives Transmission Technical Group Conceptual Transmission Plan for DRECP Alternatives DRECP WebEx Meeting January 9, 2013 Overview Purpose, Participants, and Timeline Generation Assumptions Transmission Assumptions

More information

Alternatives to Utility-scale Renewable Energy in the Desert. Basin & Range Watch

Alternatives to Utility-scale Renewable Energy in the Desert. Basin & Range Watch Alternatives to Utility-scale Renewable Energy in the Desert Basin & Range Watch www.basinandrangewatch.org What is Net Energy Metering?! Policy to support residential rooftop solar system connected to

More information

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR Ameren Missouri AMENDED Renewable Energy Standard Compliance Report 2015 Prepared in Compliance with 4 CSR 240-20.100 June 23, 2016 NP Table of Contents Page INTRODUCTION...4 SECTION (8) (A) 1 A: TOTAL

More information

SPP Notification to Construct

SPP Notification to Construct SPP Notification to Construct SPP-NTC-20123 February 14, 2011 Mr. Sam McGarrah Empire District Electric Company PO Box 127 Joplin, MO 64802 RE: Notification to Construct Approved Reliability Network Upgrades

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant

More information

Energy Policy Implications: PJM Planning

Energy Policy Implications: PJM Planning Energy Policy Implications: PJM Planning Chicago, Illinois November 14, 2012 Steven R. Herling Vice President, Planning PJM Interconnection PJM as Part of the Eastern Interconnection 26% of generation

More information

Local Transmission Plan. Rev. 1: April 2018

Local Transmission Plan. Rev. 1: April 2018 Local Transmission Plan Rev. 1: April 2018 1 Central Hudson s Service Territory Own & Operate approximately 610 miles of 69 kv, 115 kv & 345 kv transmission lines and three 345 kv substations 2 Central

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Pacific Gas and Electric Company TM

Pacific Gas and Electric Company TM Pacific Gas and Electric Company TM Evelyn C. Lee Mailing Address P.O. Box 7442 San Francisco, CA 94120 Street/Courier Address Law Department 77 Beale Street San Francisco, CA 94105 (415) 973-2786 Fax:

More information

What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center

What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center bclips@ncsu.edu About the 50 States of Solar Quarterly publication detailing state and utility distributed

More information

SPP Notification to Construct

SPP Notification to Construct August 13, 2015 SPP Notification to Construct Mr. John Fulton Southwestern Public Service Company P.O. Box 1261 Amarillo, TX 79105 RE: Notification to Construct Approved Reliability Network Upgrades Dear

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

The Development of Competitive Renewable Energy Zones in Texas

The Development of Competitive Renewable Energy Zones in Texas The Development of Competitive Renewable Energy Zones in Texas Warren Lasher Manager, System Assessment 4/23/2008 North American Electric Grids The ERCOT Region is one of 3 NERC grid interconnections.

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

The Gambia National Forum on

The Gambia National Forum on The Gambia National Forum on Renewable Energy Regulation Kairaba Hotel, The Gambia January 31 February 1, 2012 Tariff and Price Regulation of Renewables Deborah Erwin Public Service Commission of Wisconsin

More information

Western NY Public Policy Transmission Report

Western NY Public Policy Transmission Report Western NY Public Policy Transmission Report Dawei Fan Supervisor, Public Policy and Interregional Planning ESPWG/TPAS July 20, 2017, KCC Agenda Public Policy Transmission Planning Process Western NY Public

More information

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources Customer Name Basin Electric Cheyenne Power and Light City of Fort Morgan & Estimated Maximum Resource MW Point of Receipt Delivering Party & Voltage Antelope Valley 2 Yellowtail Basin Electric 115 kv

More information

BC Hydro System 2016 Annual Progress Report

BC Hydro System 2016 Annual Progress Report March 11, 2016 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING GENERATOR INTERCONNECTION REQUEST BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING May 28, 201 Table of Contents 1. Introduction... 6 1.1. Study

More information

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority

More information

The Transmission Lay of the Land

The Transmission Lay of the Land The Transmission Lay of the Land Overview Energy Markets Transmission Planning Beth Soholt John Moore April 21, 2010 Overview Regional Transmission Organizations Organizations of transmission owners, users,

More information

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any Draft Version 1 Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation,

More information