TRANSMISSION PROJECTS MODELED IN PHASE IIA DELIVERABILITY STUDY BASECASE

Size: px
Start display at page:

Download "TRANSMISSION PROJECTS MODELED IN PHASE IIA DELIVERABILITY STUDY BASECASE"

Transcription

1 TRANSMISSION PROJECTS MODELED IN PHASE IIA DELIVERABILITY STUDY BASECASE Reconductor 2.74 miles of 4/0 Al with 715 Al from Lompoc City Jct 2 - Lompoc Tap Gen IC ISO16 # Reconductor Birds Landing to CCPP with mi of 1113 ACSS Gen IC ISO24 # Reconductor CC Sub to CCPP with 1.77 mi of 1113 ACSS Gen IC ISO24 # Re-conductor East Shore - San Mateo #1 230 kv line with 954 SSAC (coastal) Gen IC ISO45 # Re-conductor East Shore - Dumbarton 115 kv line 6.83 miles of 795 SSAC (coastal) Gen IC ISO45 # Re-conductor Newark - Dumbarton 115 kv line 7.16 miles of 795 SSAC (coastal) Gen IC ISO45 # Add third East Shore 230/115 kv Bank Gen IC ISO45 # Reconductor Oro Loma to Dos Palos with 7.09 mi of 397 AL Gen IC ISO54 Re-conductor Panoche - SJVEC 230 kv line with 1113 SSAC interior 25 miles Gen IC ISO55 Re-conductor Helm - SJVEC 230 kv line with 1113 SSAC interior.4 miles Gen IC ISO55 Re-conductor Panoche - Helm 230 kv line with 795 SSAC interior 25 miles Gen IC ISO55 Re-conductor Herndon - Kearney (Herndon - P0429)230 kv line with 795 SSAC interior Gen IC ISO55 Re-conductor Wilson - Gregg 230 kv line (STOREY 1 - GREGG) with 954 ACSR interior 10 miles Gen IC ISO55 Re-conductor Bellota - Melones 230 kv line with 1113 AAC interior Gen IC ISO55 Re-conductor Bellota - Warnerville 230 kv line with 795 ACSR interior Gen IC ISO55 Reconductor the Oro Loma - Canal #1 70 kv Line (Oro Loma - Dos Palos) section Gen IC ISO55 Reconductor line section from existing Ripon Cogen Tap to new Ripon Cogen Tap mi /0 Gen IC ISO37 Re-conductor Herndon - P kv line 1.6 miles of 1113 SSAC (Interior) 2 ft/s Gen IC ISO47 # Re-conductor Glass - Madera 70 kv line 2.6 miles of 397 AAL (interior) 2 ft/s Gen IC ISO47 # Re-conductor Glass - Biola 70 kv line section between Canandga and Glass 0.8 miles of 397 AAL (interior) 2 ft/s Gen IC ISO47 Reconductor MorroBay - Templeton 230 kv Line Gen IC ISO9 Reconductor SanLuis Obispo - Atascadero 70 kv Line Gen IC ISO9 Re-conductor Midway - Belridge (12 miles) and Belridge - Temblor (3 miles) 115 kv line with 715 AAC Gen IC ISO16 Birds Landing-Contra Costa PP 230 kv Line Reconductoring Gen IC ISO22 Reconductor Contra Costa-Las Positas 230 kv line Gen IC ISO2 T670A Tesla Newark 230 kv Reinforcement 2005 T759A Atlantic 230/60 kv Transformer 2005 T346 Cortina 230/115 kv Capacity Increase 2005 T316 Borden Second 230/70 kv Transformer 2005 T907 California Avenue 115 kv Line 2005 T773 Kern 230/115 kv Transformer 2005 T920 Ravenswood Ames 115 kv Reinforcement 2005 T717A Reedley 115/70 kv Second Transformer 2005 T680 Tesla Tracy 115 kv Line Reconductoring 2005 T941 Tesla Tracy 230 kv reconductoring LARS T654C Eagle Rock Cortina 115 kv Line Swap 2005 T010A Northern Scott 115 kv Reconductoring 2005 T783 Vaca Dixon 230/115 kv Transformer Replacement 2005 T678 Lockeford 230/60 kv Transformers 2005 T654A Mendocino 115 kv Capacitors 2005 T653A Fulton 230 kv Capacitors /30/06 1 of 5

2 T936 Notre Dame Substation Interconnection 2005 T658 Humboldt Arcata Jct. 60 kv Line 2005 T654B Mendocino 115/60 kv Transformer 2005 T253A Pueblo Voltage Support 2005 T706a Wilson 230 kv Loop 2005 T243 Colgate Smartville 60 kv Reconductoring 2005 T744 Hunters Point Potrero 115 kv Line 2005 T646A Panoche Mendota Dairyland 115 kv Reconductoring 2005 T177 West Sacramento Davis 115 kv Reinforcement 2006 T082 Jefferson Martin 230 kv 2006 SF LT Study T128 Arco Twisselman 70 kv Reconductoring 2006 T177A Davis UC Davis 115 kv Conversion 2006 T697 Moss Landing Salinas 115 kv Reconductoring 2006 T101 Atlantic Del Mar 60 kv line 2006 Pipeline T314 Colgate 230/60 kv Transformer Capacity Increase 2006 T157 Tri Valley: Long Term Project 2006 Pipeline T653B Fulton 230 kv Line 2006 T725 Midway 230/115 kv Transformer Capacity Increase 2006 T933 Table Mountain 230/115 kv Transformer 2006 T783A Vaca Dixon 115/60 kv Transformer 2006 T846A Dumbarton Newark 115 kv Reconductoring 2006 T655 Jefferson 230/60 kv Transformer Capacity 2006 T867 Metcalf Moss Landing 230 kv Reinforcement 2007 T081A Bair Belmont 115 kv Reconductoring 2007 T647A Metcalf Monta Vista 230 kv Line Nos. 1 and 2 Reconductoring 2007 T790B Ravenswood Reactive Support 2007 T680A Kasson Lammers 115 kv Reconductoring 2007 T944 Newark - Newark Distribution 230 kv Line 2007 T815 Pease Marysville 60 kv Line A Henrietta Gregg 230 kv Reconductoring 2007 T778 Henrietta 230/70 kv Transformer Capacity Increase /30/06 2 of 5

3 T253 Lakeville Sonoma 115 kv Line Project 2007 T737 Mesa 230/115 kv Transformer 2007 T686B Palermo 230/115 kv Transformer 2007 T444 Placer Gold Hill 115 kv Reinforcement 2007 T141 Lone Tree 230 kv Distribution Substation 2007 T897 Martin Hunters Point 115 kv Underground Cable 2007 T844 Stagg 230/60 kv Transformers 2007 T634A Tulucay 230/60 kv Transformer 2007 T783B Vaca Dixon 500/230 kv Transformer 2007 T571 Lakeville 230/60 kv Transformer 2008 T686 Palermo Rio Oso 115 kv Reconductoring 2008 T122 Herndon Bullard 115 kv Reconductoring 2008 Mc Call Bus Breaker-And-Half Project Kern Bank 4 was replaced with a new 420 MVA bank. add a second 200 MVA transformer at Henrietta Rerate Cortina-Eagle Rock 115 kv Rerate on Humboldt Bay - Eureka 60 kv line for coastal 4 fps emergency rating Rerate on Lakeville - Peteluma C 60 kv line for interior 4 fps emergency rating Rerate Transmission Line: San Mateo - Martin 115 kv No. 4 (San Mateo-Burlingame) Rerate Transmission Line: Newark - Ames Dist 115 kv No. 1 Rerate Transmission Line: Newark - Ames 115 kv No. 3 Rerate Transmission Line: Green Valley - Llagas 115 kv (Llagas-Morgan Hill J2) Rerate Transmission Line: Newark - Tesla 230 kv No. 2 (Newark-ADCC) Rerate Transmission Line: Tesla - Newark 230 kv No. 2 (Tesla - ADCC) Monta Vista 115/60 kv Bank Project Reconductor and Rerate Moss Landing-Green Valley #1&2 with 477 ACSS Reconfigure Pease-Colgate-Marysville-East Nicolaus area Rerate on Sonoma - Pueblo 115 kv line for interior 4 fps emergency rating Install 16 ohm reactor between Tesla bus section C and D 6/30/06 3 of 5

4 Rerate on Tulucay-Vaca 230 kv line for interioir 4 fps emergency rating SCE 1 Install 4th Mira Loma 500/230 kv transformer bank Annual Exp SCE SCE 2 New Viejo 230/66 kv substation. Connect to 230 kv system by looping into San Onofre - Chino 230 kv Annual Exp SCE SCE 3 Install 4th Valley 500/115 kv transformer bank Annual Exp SCE SCE 4 Install South of Lugo N-2 SPS. (SOB 286) 2005 Annual Exp SCE SCE 5 Install new 28.8 MVAR capacitor bank at Antelope 66 kv Annual Exp SCE SCE 6 Upgrade Antelope 230/66 kv No. 2 transformer bank from 120 MVA to 280 MVA. Turn off No. 3 transformer bank due to mismatch 2005 Annual Exp SCE impedance. SCE 7 Upgrade 66 kv circuit breakers at Bailey to permit parallel operation of 230/66 kv transformers Annual Exp SCE SCE 8 Install 2 X 165 MVAR shunt caps at Valley 500 kv Annual Exp SCE SCE 9 Loop in Lugo - Serrano 500 kv into Mira Loma. SOL maintained at 5,600 MW. Not modelled after in service of Rancho Vista Annual Exp SCE SCE 10 Reconductor Pastoria - Pardee ( 598 MVA normal & emergency ), Pardee - Bailey ( 494 MVA normal & 598 MVA emergency ), Bailey Annual Exp SCE Pastoria ( 494 MVA normal & 598 MVA emergency ) 230 kv as part of infrastructure replacement. SCE 11 Upgrade amp rating of series capacitors on Palo Verde -Devers 500 kv No. 1 ( 2338 MVA normal & 2988 MVA emergency ) and 2006 Annual Exp SCE SWPL to increase Path 49 by 505 MW. Also second 500/230 kv transformer at Devers. SCE 12 New Antelope - Pardee 230 kv line Annual Exp SCE SCE 13 Install 2nd 230/115 kv transformer at Mirage Annual Exp SCE SCE 14 Intall 175 MVAR SVC at Rector to remove need to drop load for N-1. Dynamic support only, full range not modelled for load flow Annual Exp SCE SCE 15 Split Devers - Mirage 115 kv system. Includes new Mirage - Santa Rosa - Tamarisk 115 kv line Annual Exp SCE SCE 16 Install 3rd 230/115 kv transformer at Mirage Annual Exp SCE SCE 17 Loop in Big Creek 3 - Springville 230 kv into Rector to relieve base case generation limitation and load dropping under contingency Annual Exp SCE SCE 18 New second Palo Verde - Devers 500 kv line to provide a new economic path of 1,200 MW Annual Exp SCE SCE 19 New Rancho Vista 500/230 kv substation to accommodate load growth. Unloop Lugo - Serrano 500 kv from Mira Loma and loop into 2009 Annual Exp SCE Rancho Vista. SCE 20 Upgrade terminal equipment of Alamitos - Barre 230 kv line 1 & 2. ( 1195 MVA normal & emergency ) 2006 Phase 1 Deliv. SCE SCE 21 Upgrade terminal equipment of Alamitos - Center 230 kv. ( 1195 MVA normal & emergency ) 2006 Phase 1 Deliv. SCE SCE 22 Upgrade terminal equipment of Hinson - Lighthipe 230 kv. ( 472 MVA normal & 797 MVA emergency ) 2006 Phase 1 Deliv. SCE SCE 23 Upgrade terminal equipment of La Fresa - Redondo 230 kv line 1 & 2. ( 1195 MVA normal & emergency ) 2006 Phase 1 Deliv. SCE SCE 24 Reconductor Etiwanda - Mira Loma 230 kv. ( 988 MVA normal & 1195 MVA emergency ) 2005 RMR elimination SCE SCE 25 Upgrade Vincent - Mesa 230 kv wavetrap. ( 988 MVA normal & 1195 MVA emergency ) 2005 RMR elimination SCE SCE 26 Upgrade terminal equipment of Eagle Rock - Pardee 230 kv. ( 494 MVA normal & 665 MVA emergency ) 2006 RMR elimination SCE SCE 27 Upgrade terminal equipment of Goodrich - Gould 230 kv. ( 988 MVA normal & 1195 MVA emergency ) 2006 RMR elimination SCE SCE 28 Upgrade terminal equipment of Rio Hondo - Vincent 230 kv line 1 & 2. ( 1195 MVA normal & emergency ) 2006 RMR elimination SCE SCE 29 Upgrade terminal equipment of Eagle Rock - Mesa 230 kv. ( 1195 MVA normal & emergency ) 2006 RMR elimination SCE SCE 30 Upgrade terminal equipment of Eagle Rock - Sylmar 230 kv. ( 1195 MVA normal & 1374 MVA emergency ) 2006 RMR elimination SCE SCE 31 Upgrade terminal equipment of Antelope - Mesa 230 kv. ( 474 MVA normal & emergency ) 2006 RMR elimination SCE SCE New Antelope - Tehachapi 230 kv line Gen IC ISO18/SCE SCE New Antelope - Vincent 500 kv line Gen IC Tehach. SCE Pastoria second 230 kv line Gen IC??? SCE New Julian Hinds-Buck Blvd 230 kv transmission line merchant trans TOT094 SCE New 500/161 kv transformer connection to Palo Verde-Devers 500 kv line and Buck Blvd merchant trans TOT101 SCE Upgrades to Devers-Valley 500 kv line terminal equipment at Valley substation merchant trans TOT101 SCE New Devers-Blythe 500 kv transmission line merchant trans TOT104 SCE Reconductor Devers-San Bernadino 230 kv #1 &2, Devers-Vista #1 & 2 Annual Exp SCE SCE Mt. Pass-Eldorado Reconductoring Gen IC ISO15 SCE Eldorado 230/115 kv transformer replacement to 280 MVA Gen IC ISO15 SCE Eldorado-Merchant 230 kv line #2 Gen IC ISO56 SCE Oxbow 230/115 kv transformer replacement Gen IC ISO58 SCE Inyo phase shifter upgrade to 60 degree tap range Gen IC ISO58 SCE Kramer-Inyokern 115 kv to 230 kv conversion Gen IC ISO58 SCE Expand Bishop RAS (e.g. cover the N-1 Control-Inyokern No. 1 or 2) Gen IC ISO58 SCE El Segundo RAS (e.g. cover El Nido-La Fresa N-2) Gen IC ISO7 SCE Daggett Shunt capacitor Gen IC WDT164 SDGE P04137 Division to Naval Station Metering Annual Exp SDGE SDGE P04141 Reconductor TL6913, Poway to Pomerado Annual Exp SDGE SDGE P04135 Superior Renewable Interconnection Gen IC Superior 6/30/06 4 of 5

5 SDGE P04130 Reconductor TL664, Miramar GT substation to Eastgate Tap (Ramco Interconnection) Gen IC Ramco SDGE P04195 Lake Hodges Pumped Storage Project Gen IC Lake Hodges SDGE P02161 Build New 69 kv line between Sycamore Canyon and Miramar Substations (new line) Annual Exp SDGE SDGE P03170 Silvergate New 138/69kV Substation (takes place for new mainstreet) Annual Exp SDGE SDGE P03176 Reconductor TL 640, Chollas-Paradise Annual Exp SDGE SDGE P03179 Reconductor TL658, Sampson-Division Annual Exp SDGE SDGE P03188 Reconductor TL642 Sweetwater-Montgomery Tap-South Bay Annual Exp SDGE SDGE P01144 Construct Miguel-Mission 230kV line #2 Annual Exp SDGE SDGE P03190 Rebuild Old Town Substation Annual Exp SDGE SDGE P03191 Otay Mesa Power Purchase Agreement Transmission Project Gen IC SDGE SDGE P01142 Reconductor TL683, Lilac-Rincon Annual Exp SDGE SDGE P00153 Reconductor TL13837, Capistrano-Laguna Niguel Annual Exp SDGE SDGE P03183 Reconductor TL678, Los Coches-Alpine and TL6914, Los Coches-Loveland Annual Exp SDGE SDGE P03192 Various Projects for Palomar Interconnection Gen IC Palomar SDGE P04193 Install a New 230/138 kv Transformer at Sycamore Canyon Substation Annual Exp SDGE SDGE P98192 Reconductor TL696, Escondido-Ash Annual Exp SDGE SDGE P95144 Build a New 69 kv line between Torrey Pines and UCM Substation Annual Exp SDGE SDGE P00146 Reconductor TL688, Escondido-Lilac Annual Exp SDGE SDGE P01141 Reconductor TL13836, Talega-Pico Annual Exp SDGE SDGE Loop-in Encina-San Luis Rey-Escondido 230 kv line into Palomar Sub 2007 Annual Exp SDGE 6/30/06 5 of 5

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

Background Information

Background Information Background Information On Local Capacity Areas: Import Facilities Substations LSTobias / ISO Grid Planning 1 Humboldt Area Import Facilities 1) Humboldt-Bridgeville-Cottonwood 115 kv line #1 2) Humboldt-Trinity

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

APPENDIX F: 2012 Request Window Submittals

APPENDIX F: 2012 Request Window Submittals APPENDIX F: 2012 Request Window Submittals Table F-1: 2012 Request Window Submittals Project Name Service Submitted by 1 Lockeford-Lodi 230 kv Development City of Lodi, Electric Utility Department 5/31/2017

More information

Pacific Gas and Electric Company s 2013 Annual Progress Report

Pacific Gas and Electric Company s 2013 Annual Progress Report March 14, 2013 Mr. David Franklin Chair, WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System. Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019

2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System. Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019 2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019 ARIZONA San Diego Non-Bulk LCR Area CHINO [SCE] SERRANO [SCE]

More information

2019 & 2023 Final LCR Study Results San Diego-Imperial Valley non-bulk sub-areas

2019 & 2023 Final LCR Study Results San Diego-Imperial Valley non-bulk sub-areas 2019 & 2023 Final LCR Study Results San Diego-Imperial Valley non-bulk sub-areas Luba Kravchuk Senior Regional Transmission Engineer Frank Chen - Regional Transmission Engineer Lead Stakeholder Call May

More information

Full Network Model Scope for FNM DB61

Full Network Model Scope for FNM DB61 Transmission Projects PG&E SCE 1. Cornerstone Bk. 6 Phase 1 2. Carrizo Plain Solar Generation Phase 1 3. Carrizo Plain Solar Generation Phase 3 4. Contra Costa Sub DPA Capacity Phase 1 5. Bridgeville -

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

Decision on the ISO Transmission Plan

Decision on the ISO Transmission Plan Decision on the 2013-2014 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 19-20, 2014 Approving the plan means approving

More information

SDG&E Valley-Rainbow Project

SDG&E Valley-Rainbow Project SDG&E Valley-Rainbow Project Presentation to Grid Reliability/Operations Committee Steven Mavis ISO Grid Planning Department May 24, 2000 1 Background SDG&E s 1999 Expansion Plan for 2000-2004 indicated

More information

Full Network Model Scope for FNM DB2016Q1

Full Network Model Scope for FNM DB2016Q1 Transmission Projects PG&E SCE 1. Aera Energy (San Ardo), phase # 1 2. Embarcadero 230kV Sub- Convert to BAAH, phase # 1a 3. Embarcadero-Potrero 230 kv Transmission Project, phase # 1A 4. Frontier Solar(

More information

2018 & 22 Final LCR Study Results Greater Bay Area

2018 & 22 Final LCR Study Results Greater Bay Area 2018 & 22 Final LCR Study Results Greater Bay Area Bryan Fong Senior Regional Transmission Engineer Stakeholder Call April 13, 2017 Greater Bay Area Map Slide 2 Greater Bay Area Transmission System Slide

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

PG&E s 2017 Request Window Proposals CAISO 2017/2018 Transmission Planning Process

PG&E s 2017 Request Window Proposals CAISO 2017/2018 Transmission Planning Process 1 PG&E s 2017 Request Window Proposals CAISO 2017/2018 Transmission Planning Process September 22, 2017 Transmission Projects Overview 2 Projects Seeking CAISO Approval: Yosemite/Fresno Herndon-Bullard

More information

Contingency Description

Contingency Description DRAFT Phase IIA Baseline Deliverability Study s Table 2.2. Deliverability Limitations Impacting Proposed Generation Only Humboldt Solano- Contra Costa 300 HMBLT TM 5 3080 HUMBOLDT 60 3000 HUMBOLDT 5 3080

More information

2019 & 2023 Final LCR Study Results Greater Bay Area

2019 & 2023 Final LCR Study Results Greater Bay Area 2019 & 2023 Final LCR Study Results Greater Bay Area Binaya Shrestha Regional Transmission Engineer Lead Stakeholder Call May 1, 2019 Greater Bay Area Transmission System Contra Costa Subarea Oakland Subarea

More information

PG&E s 2012 Request Window Proposals

PG&E s 2012 Request Window Proposals 1 PG&E s 2012 Request Window Proposals Central Valley Patrick Tan Transmission System Planning PG&E September 27, 2012 Transmission Projects Overview 2 Projects Seeking CAISO Approval Pease 115/60 kv Transformer

More information

2016 SDG&E Grid Assessment Results

2016 SDG&E Grid Assessment Results 2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year

More information

Introduction and Overview

Introduction and Overview Introduction and Overview Neil Millar Generation Deliverability Assessment Methodology Proposal Call December 18, 2018 Generation Deliverability Methodology Revision Process November 16, 2018: CAISO presented

More information

ISO Transmission Plan February 2, 2015 APPENDIX H: Contingencies on the ISO System that may Impact Adjacent Systems

ISO Transmission Plan February 2, 2015 APPENDIX H: Contingencies on the ISO System that may Impact Adjacent Systems 2014-2015 ISO Transmission Plan February 2, 2015 APPENDIX H: Contingencies on the ISO System that may Impact Adjacent Systems California ISO/MID Study Area: PG&E Bulk files: Switch_PGE_Bulk.zip 1 CptJ_Olinda_ns_slo.swt

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section

More information

Agenda Draft Transmission Plan and transmission project approval recommendations

Agenda Draft Transmission Plan and transmission project approval recommendations Agenda Draft 2017-2018 Transmission Plan and transmission project approval recommendations Kristina Osborne Senior Stakeholder Engagement and Policy Specialist 2017-2018 Transmission Planning Process Stakeholder

More information

Report of Gary DeShazo

Report of Gary DeShazo ATTACHMENT ALT-45 Attachment ALT-45 documents that the CAISO has recently agreed to accept 29 MW of projected demand response impacts for purposes of determining the amount of in-area generation that is

More information

APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems

APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems 2016-2017 ISO Transmission Plan March 17, 2017 APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems California ISO/MID G-1 2016-2017 ISO Transmission Plan March 17, 2017 Intentionally

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Valley - Rainbow Interconnection Project Feasibility Study Report

Valley - Rainbow Interconnection Project Feasibility Study Report Attachment A Valley - Rainbow Interconnection Project Feasibility Study Report A Joint Study Effort of San Diego Gas & Electric (SDG&E) and Southern California Edison (SCE) in Cooperation with the California

More information

2017 Final LCR Study Results Fresno. Vera Hart Regional Transmission Engineer Stakeholder Call April 14, 2016

2017 Final LCR Study Results Fresno. Vera Hart Regional Transmission Engineer Stakeholder Call April 14, 2016 2017 Final LCR Study Results Fresno Vera Hart Regional Transmission Engineer Stakeholder Call April 14, 2016 Fresno LCR Area Kern Area Slide 2 Greater Fresno Area Electrical Boundaries and LCR Sub-Areas

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (OCTOBER 2016) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Agenda Less than $50 Million Projects and Preliminary Economic Assessment Results

Agenda Less than $50 Million Projects and Preliminary Economic Assessment Results Agenda Less than $50 Million Projects and Preliminary Economic Assessment Results Kim Perez Stakeholder Engagement and Policy Specialist 2017-2018 Transmission Planning Process Stakeholder Meeting November

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Full Network Model Scope for FNM DB59

Full Network Model Scope for FNM DB59 Transmission Projects PG&E SCE 1. Cottle 230 kv Ring Bus Project 2. Carrizo Plain Solar Generation 3. Calpine Russell City Energy Center (Eastshore - San Mateo & Dumbarton-Newark) 4. Bridgeville Bk. #2

More information

PACI RAS Updates. Vahid Madani Pacific Gas and Electric Co. August 2, 2017

PACI RAS Updates. Vahid Madani Pacific Gas and Electric Co. August 2, 2017 1 PACI RAS Updates Vahid Madani Pacific Gas and Electric Co. August 2, 2017 2 Outline PACI RAS Pacific AC Intertie RAS Overview of PACI RAS Mosher New Substation & Stagg Updates Gates Substation 230kV

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2014) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

CPUC TRANSMISSION PROJECTS AND CONCEPTS-- SCE TERRITORY Third Quarter 2011

CPUC TRANSMISSION PROJECTS AND CONCEPTS-- SCE TERRITORY Third Quarter 2011 LOCATION CPUC TRANSMISSION PROJECTS AND CONCEPTS-- SCE TERRITORY Third Quarter 2011 PROJECT DESCRIPTION Segment #1 : Construct a new 26.5 mile 500kV transmission line from Santa Clarita to Lancaster (between

More information

Agenda Day 2 Preliminary Reliability Assessment Results

Agenda Day 2 Preliminary Reliability Assessment Results Agenda Day 2 Preliminary Reliability Assessment Results Kristina Osborne Stakeholder Engagement and Policy Specialist 2014-2015 Transmission Planning Process Stakeholder Meeting September 24-25, 2014 2014-2015

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

2018 & 22 Final LCR Study Results Sierra and Stockton Areas. Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13, 2017

2018 & 22 Final LCR Study Results Sierra and Stockton Areas. Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13, 2017 2018 & 22 Final LCR Study Results Sierra and Stockton Areas Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13, 2017 Sierra Area Load and Resources (MW) 2018 2022 Load = 1,862

More information

Agenda Day 2 Preliminary Reliability Assessment Results

Agenda Day 2 Preliminary Reliability Assessment Results Agenda Day 2 Preliminary Reliability Assessment Results Tom Cuccia Senior Stakeholder Engagement and Policy Specialist 2013/2014 Transmission Planning Process Stakeholder Meeting September 25-26, 2013

More information

2019 & 23 Final LCR Study Results Sierra and Stockton Areas. Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call May 1, 2018

2019 & 23 Final LCR Study Results Sierra and Stockton Areas. Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call May 1, 2018 2019 & 23 Final LCR Study Results Sierra and Stockton Areas Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call May 1, 2018 Sierra Area Load and Resources (MW) 2019 2023 Load = 1,768 1,819

More information

CPUC TRANSMISSION PROJECTS AND CONCEPTS-- SCE TERRITORY First Quarter 2011 CAPACITY/ VOLTAGE LEVEL

CPUC TRANSMISSION PROJECTS AND CONCEPTS-- SCE TERRITORY First Quarter 2011 CAPACITY/ VOLTAGE LEVEL Segment #1 : Construct a new 26.5 mile 500kV transmission line from Santa Clarita to Lancaster (between existing Pardee & Antelope Stations) CPUC TRANSMISSION PROJECTS AND CONCEPTS-- SCE TERRITORY First

More information

PREPARED DIRECT TESTIMONY

PREPARED DIRECT TESTIMONY Application No.: A.0-04- Exhibit No.: SDG&E-4 Witness: William V. Torre In the Matter of San Diego Gas & Electric Company s Application for Authorization to (1) to Participate in the Steam Generator Replacement

More information

Tehachapi Renewable Transmission Project 3.1 OVERVIEW OF PROPOSED PROJECT

Tehachapi Renewable Transmission Project 3.1 OVERVIEW OF PROPOSED PROJECT 3.1 OVERVIEW OF PROPOSED PROJECT This section provides a detailed description of Southern California Edison s (SCE) (TRTP), which includes a series of new and upgraded high-voltage electric transmission

More information

Second Report of the Tehachapi Collaborative Study Group

Second Report of the Tehachapi Collaborative Study Group Development Plan for the Phased Expansion of Electric Power Transmission Facilities in the Tehachapi Wind Resource Area Second Report of the Tehachapi Collaborative Study Group Volume 2: Appendices California

More information

Single Family Detached

Single Family Detached MLS Statistics By Code - Monthly and YTD Report Dates: August 01, 2011 - August 31 2011 Current Year - 2011 Previous Year - 2010 Code Market Area Single Family Detached 91901 Alpine 13 107 61 92 $385,000

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Single Family Detached

Single Family Detached MLS Statistics By Code - Monthly and YTD Report Dates: June 01, 2007 - June 30 2007 Current Year - 2007 Previous Year - 2006 Code Market Area Single Family Detached 91901 Alpine 16 61 76 88 $637,500 $610,000

More information

Agenda Day 2. Tom Cuccia Lead Stakeholder Engagement and Policy Specialist

Agenda Day 2. Tom Cuccia Lead Stakeholder Engagement and Policy Specialist Agenda Day 2 Tom Cuccia Lead Stakeholder Engagement and Policy Specialist 2015-2016 Transmission Planning Process Stakeholder Meeting September 21-22, 2015 2014-2015 Transmission Planning Process Stakeholder

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Agenda Day 1 Preliminary Reliability Assessment Results

Agenda Day 1 Preliminary Reliability Assessment Results Agenda Day 1 Preliminary Reliability Assessment Results Tom Cuccia Senior Stakeholder Engagement and Policy Specialist 2013/2014 Transmission Planning Process Stakeholder Meeting September 25-26, 2013

More information

for DRECP Alternatives

for DRECP Alternatives Transmission Technical Group Conceptual Transmission Plan for DRECP Alternatives DRECP WebEx Meeting January 9, 2013 Overview Purpose, Participants, and Timeline Generation Assumptions Transmission Assumptions

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- -- ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

Agenda. Draft ISO Transmission Plan Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist February 12, 2014

Agenda. Draft ISO Transmission Plan Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist February 12, 2014 Agenda Draft 2013-2014 ISO Transmission Plan Stakeholder Meeting Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist February 12, 2014 2013-2014 Draft Transmission Plan Stakeholder Meeting - Today

More information

Opening Transmission Planning Process Stakeholder Meeting Tom Cuccia Lead Stakeholder Engagement and Policy Specialist November 19-20, 2014

Opening Transmission Planning Process Stakeholder Meeting Tom Cuccia Lead Stakeholder Engagement and Policy Specialist November 19-20, 2014 Opening 2014-2015 Transmission Planning Process Stakeholder Meeting Tom Cuccia Lead Stakeholder Engagement and Policy Specialist November 19-20, 2014 Yesterday s Agenda November 19 th Topic Opening Introduction

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

Report of Registration - State Reporting Districts Run Date : 5/1/2015 SAN DIEGO COUNTY

Report of Registration - State Reporting Districts Run Date : 5/1/2015 SAN DIEGO COUNTY POLITICAL SUBDIVISION COUNTY TOTALS... 371001 2011 1ST SUPERVISORIAL DIST 106,529 60,561 6,686 956 1,530 1,001 933 72,095 250,291 371002 2011 2ND SUPERVISORIAL DIST 101,015 129,828 12,912 1,444 2,892 774

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (U 39 E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (U 39 E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. Rulemaking

More information

Wheeling Access Charges

Wheeling Access Charges May Wheeling Access Charges The following tables contain Wheeling Access Charges at the scheduling points. The Wheeling Access Charge is applicable for Wheeling on the ISO Controlled Grid. No Wheeling

More information

Marketing Analysis. A report on the accessibility of the. CFMC Network. Sample. Thursday, February 04, 2016

Marketing Analysis. A report on the accessibility of the. CFMC Network. Sample. Thursday, February 04, 2016 Thursday, February 04, 2016 Marketing Analysis A report on the accessibility of the CFMC Network for the PPO of Sample Table of Contents i Accessibility summary...................... 1 Sample Facility

More information

North Gila Generator Interconnection

North Gila Generator Interconnection A subsidiary of Pinnacle West Capital Corporation North Gila Generator Interconnection System Impact Study APS Contract Nos. 52107 By Arizona Public Service Company Transmission Planning October 2, 2009

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

California Independent System Operator. Memorandum

California Independent System Operator. Memorandum California Independent System Operator Memorandum To: ISO Board of Governors From: Armie Perez, Vice President of Planning and Infrastructure Development Date: Re: Decision on Tehachapi Project This memorandum

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

California Independent. System Operator. Market Overview and Design Construct

California Independent. System Operator. Market Overview and Design Construct California Independent Market Overview and Design Construct Kyle Hoffman 916-608-1127 khoffman@caiso.com The ISO Vision Preferred Provider of Superior Electric Transmission Services Ensure reliable transmission

More information

TRANSMISSION CONTROL AGREEMENT APPENDIX A. Facilities and Entitlements

TRANSMISSION CONTROL AGREEMENT APPENDIX A. Facilities and Entitlements TRANSMISSION CONTROL AGREEMENT APPENDIX A Facilities and Entitlements (The Diagrams of Transmission Lines and Associated Facilities Placed Under the Control of the ISO were submitted by the ISO on behalf

More information

California ISO DG Deliverability Study Results - PGE Area February, A B C D E F G H I J K L DG Node Unassigned PDGD.

California ISO DG Deliverability Study Results - PGE Area February, A B C D E F G H I J K L DG Node Unassigned PDGD. California ISO DG Deliverability Study Results - PGE Area February, 2018 FULTON 230 2.55 1.60 2.60 6.72 6.72 4.15 = WDAT EO + Existing EO BAHIA 230 0.47 Constrained by Contra Costa-Brentwood 230kV Line

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

National Grid s 2017 Local Transmission Plan

National Grid s 2017 Local Transmission Plan National Grid s 2017 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Key to Status Fields in the Project List

Key to Status Fields in the Project List Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served

More information

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012 First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Southeastern Region Transmission Planning East Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Southeastern Region Transmission

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

National Grid s 2018 Local Transmission Plan

National Grid s 2018 Local Transmission Plan National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan 10 Year Transmission Expansion Plan Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised

More information

Proposed New Construction for

Proposed New Construction for Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects

More information

Board of Vocational Nursing and Psychiatric Technicians

Board of Vocational Nursing and Psychiatric Technicians Department of Consumer Affairs Board of Vocational and Psychiatric Technicians The table below represents the performance of all first - time program graduates who completed the NCLEX/PN during the last

More information

Circuit Reliability Review

Circuit Reliability Review Circuit Reliability Review Twenty-Nine Palms Reservation January 2017 1 Providing Safe, Reliable, and Affordable Power Southern California Edison is modernizing the power grid to meet the changing needs

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

2016 SPP Transmission Expansion Plan Project List Kansas Projects

2016 SPP Transmission Expansion Plan Project List Kansas Projects WR Zonal Reliability $9,308,090 Build 6.7 mile Clay Center Switching Station to TC Riley 115 kv line 6/1/2018 10/1/2012 115 6.7 Install a 2000 Amp bus system, GOAB switches, metering and WR Zonal Reliability

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information