GLAST Large Area Telescope: Planning Meeting September 3, 2003 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6
|
|
- Leona Townsend
- 5 years ago
- Views:
Transcription
1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Planning Meeting September 3, 2003 AntiCoincidence Detector (ACD) Subsystem WBS: David J. Thompson Thomas E. Johnson NASA Goddard Space Flight Center Subsystem Manager/Instrument Manager AntiCoincidnce Detector 1
2 CRITICAL MILESTONE CHART 1 Critical Milestone Jul 03 Aug 03 Sep 03 Oct 03 Nov 03 Dec 03 Jan Feb Ma r Apr Ma y Jun Jul Aug Sep Oct Nov Shell Subassembly Analog ASIC 1 3. Digital ASIC 4. Base Frame Assembly 5. HVBS Flight Unit 6. PMT Flight Unit 7. Tile Detector Assemblies Clear Fiber Cables Mechanical Subsystem (ready for I&T) Free Flt Unit Functional Test ACD Functional Test ACD Pre- Environmental Review ACD Vibration Test ACD TVAC Test ACD Pre-Ship Review ACD Ship 17. ACD Ready for Integration AntiCoincidnce Detector 2
3 Lat Instrument ACD Milestones Tile Shell Assembly GLAST LAT ACD Summary Schedule Task Tile Detector Assembly 7/31/ CDR (S) I&T CDR EM2 CAL PER PSR Flt 10/15/04 Flt Spares Shell Assembly Flt Base Electronic Assembly Base Frame Assembly High Voltage Bias Supply Analog ASIC Digital ASIC Front End Elec. Cards DU DU TU EU (Rec V-6) (Rec V-2) Flt EU Test Flt Test Flt (GARC) Flt (GAFE) Flt Photo Multiplier Tubes Micrometeroid Sh./Th. Blkt Mech Subsys (ready for I&T) ACD I&T TSA Integration BEA Integration Flt (240) CAL Flt ACD Integration/Env. Test ACD Prep, Ship, RFI Env. Testing ACD Ready for Integration 10/15/04 ACD to LAT Integration AntiCoincidnce Detector 3 ACD to LAT Integration (ND Date) 10/25/04
4 Near Term Milestones - 3 Month Plan Milestone Description First System Test w/ one FREE Board, HVBS, PMTs and TDAs Base Frame Channel Fabrication start Complete Fab of TDA tiedowns Receive/Test Flight ASICs (rapid-package) Fab Flight HVBS PCBs Complete Flight Mechanical Drawings Complete Design on MGSE and EGSE Complete Assembly of Flight Shell Start Testing on BEA EU Date 8/15/2003 8/29/2003 9/30/2003 9/30/ /13/ /31/ /31/ /31/ /10/2003 Completed Ready for fabrication Status/Notes Drawings, procedures in signoff Test procedures and test equipment ready Vibration Testing complete. Currently in TVAC testing. New designer just started Receive Sep03; Strength test Oct03. We will test 3 HVBS eus during this test. Complete Fab of Clear Fiber Cables System Test w/ two FREE Boards, HVBS, PMTs and TDAs Complete Fab of Flight TDAs 11/20/ /28/ /31/2003 Connectors complete; work started on assembly Preliminary test Sept Completion December 03 by Fermi. Delay due to manpower Fermi. PMT Housings and Bonding to complete 9/5. Complete PMT Assembly 1/30/2004 PMT assembly area is ready. PMT Assembly to start 9/8. AntiCoincidnce Detector 4
5 Interdependencies 1. Funding IPO, availability of LAT resources, GLAST Project, FY03 carryover 2. ASICs LAT Electronics group support, Product Assurance (packaging, qual, screen, and test). Status on rapid package as well as flight packaging? 3. Delivery of FREE Boards and Parts to Electronics 4. EGSE/G3 Ongoing development with I&T and electronic groups 5. ACD/GASU Cable details and system clock testing. Need signed off and configuration controlled drawing for cables. 6. Grid to Base Frame installation Outline drawing and available date for installation AntiCoincidnce Detector 5
6 Flight Hardware Procurements 1. TDA s December completion, design problem could impact delivery. 2. ASICs Receive rapid packaged ASICs on?, Submit ASICs for flight packaging 1-2 weeks after receiving rapid packaged chips 3. FREE PWBs September/October procure, available November 4. Electronic parts Completed, problem with HV capacitor 5. HVBS Assy August Start February Completion. Problem with HV capacitor causes minor (~ 1 week) delay. 6. Shell Panels Late September completion 7. PMT parts All parts procured, all housings completed next week, RN PCB s due in soon, HV Cap will delay assembly completion. 8. Base Frame Mechanical Parts July-August, complete December 9. TSA Mechanical Parts July-August, complete December AntiCoincidnce Detector 6
7 Manufacturing Plans 1. TDA s Completed 2. ASICs qual, screen and test plan In review 3. FREE and HVBS using standard process 4. PMT Assy Plan In sign off 5. Mechanical Parts Using standard plans 6. Clear Fiber Cables Procedure in final review, beginning fab of EU units as well as training techs. AntiCoincidnce Detector 7
8 Unresolved Assumptions 1. Thermal Blanket interface (outline drawing) 2. Grounding (outline drawing and grounding plan) 3. Rates data (resolved in principle) 4. Link up date for Grid to Base Frame interface 5. EGSE cable lengths GASU to EGSE ~14m 6. GASU has to work in TVac and Vibration (with isolation) AntiCoincidnce Detector 8
9 New Issue #1 TDA design problem Interference between WFS and TDA tiedown at this point Three Potential Solutions identified. Move some TDA tiedowns Reduce bending radius of WSF Decrease size of TDA tiedown Potential impact to shell panels and TDA Tiedowns Good news is that Fermi staffing issue is under control, bad news is they have to refocus their efforts to helping solve this problem. AntiCoincidnce Detector 9
10 New Issue #2 High Voltage Capacitor does not meet requirements. Dielectric strength out of spec. Predicted life time of capacitor would be reduced by a factor of ~2.5 No life testing results available to verify predictions. Engineers expect that actual would be worse than predicted Long lead part (original quote of 12 weeks) Ordered ~16 weeks ago. Parts came in a little late and screening on first batch has just been completed Manufacture has agreed to replace part at no cost. Negotiating for a shorter lead time (~7 weeks may be possible) as well as keeping 40 of the original parts so that testing program can continue. Part is used in PMT assembly as well as HVBS s. Used on 2 nd (middle) resistor network board. This will delay PMT assembly completion. Work-a-rounds include installing all 1 st boards as well a reshuffling work for assembly techs. Will assemble qual PMTs using non-spec parts. Impact to HVBS will be minimal. Proceed with qual unit HVBS using non-spec part. AntiCoincidnce Detector 10
11 Issues and Concerns - updates Need for a final Qualification and Screening Plan for ASICs is a concern LAT has a general Q&S Plan for ASICs Issue has been the specific implementation (particularly testing) needed for the ACD ASICs Working with LAT Parts Control Board in consultation with Goddard parts engineers to finalize details of the plan. Agreed in principle, but documentation is still needed. Test boards are being designed. Shortage of test equipment at Goddard is a concern In particular, equipment needed for the ASIC Q&S program seems to be in short supply Working with Goddard local laboratory and Engineering Directorate to locate or repair needed equipment. Not much success so far. Requested Goddard funding (~$60K) for additional equipment. None provided yet, requiring unbudgeted expenditures to keep testing program on schedule. AntiCoincidnce Detector 11
12 Issues and Concerns - new Reduction of support for ACD TDA production at Fermilab is an issue. Accelerator shutdown, required vacation, and extended medical leave have seriously reduced the staffing available to continue the TDA fabrication. Issue appears to be resolved. Axiom operator (actually 2 this week) vacancy has been resolved. They will work a second shift if required to maintain schedule. Have been assured that this job is a high priority, second only to the beam shutdown. Alex and I will be going to Fermi next week. Reduction of support for ACD mechanical engineering at GSFC is an issue. Problem in another flight project (XRS on Astro E2) has siphoned off some of the time of ACD mechanical engineers Working with Goddard management to retain enough support to maintain schedule. Receiving additional support to backfill support lost to XRS ASIC Yield 50% yield at ambient temperature prior to thermal cycling or burn-in AntiCoincidnce Detector 12
13 Issues and Concerns - updated Late delivery of G3 Test Stand/EGSE from LAT Electronics and I&T is a concern Scheduled for August, recently slipped to November/December Planned for testing of multiple FREE cards and Electronic Chassis, scheduled for August - November Developing workarounds, using older G2 Test Stands and bench electronics. Interfaces are less like the flight interface, but should allow much of the testing. Developing the G3 software before the arrival of the hardware, to minimize the startup delay once the G3 Test Stands arrive. G2 will be testing flight hardware, need documentation. ACD cost increases and availability of FY03 funding is an issue Cost to Complete exercise identified increased costs for ACD Goddard Engineering Directorate has provided additional Civil Service support, replacing contractors with CS personnel wherever a qualified Civil Servant could be found. GLAST Project has offered some support. Additional ACD funding included in the current LAT request. AntiCoincidnce Detector 13
14 Open Design Issues - update OPEN: Outline drawing that defines some interfaces with LAT is still not complete (blanket attachment, grounding, cable tie-downs, optical survey mounts). Action Plan: Work with LAT mechanical design team to resolve open issues by August 29. Status unchanged. CLOSED: LAT Electronics group requested a change in the backshell of the connector to the ACD. This change requires a change in the bracket that holds the connector, and this bracket is a structural element. Modification should be straightforward, but must be analyzed. Action: Decided to stick with original design. CLOSED: FREE Board design updates and finalization. Action: Design complete and in fabrication. OPEN: Need updated interface loads following Grid design changes. Action Plan: Review ACD analysis when updated loads are received. ACD will not delay fabrication of mechanical components due to this open issue (slight risk in doing so). Status unchanged. OPEN: Discovered interference between some wave shifting fibers and TDA flexures. Action Plan: Re-design and re-analyze to resolve. AntiCoincidnce Detector 14
15 Mechanical and EEE Parts - update Mechanical Parts and Materials - ALL APPROVED PMTs Qualified, tested, and screened (final report in draft form now) EEE Parts FREE - 36 different part types; approximately 830 parts per board. All parts approved by PCB with the following exceptions. MAX145 and MAX5121 being qualified by GSFC parts group (chips provided by Calorimeter). ASICs in fabrication. S&Q plan is complete and has been reviewed by members of the PCB. Detailed GARC test procedure in review and draft GAFE test procedure is being circulated MAX494 was recently approved following radiation testing HVBS - 38 different parts types; 108 total parts per board 4 parts are not yet approved (DPA needed on 3 capacitors, screening needed for one wire) High voltage capacitor was rejected, did not meet specification Resistor network - 9 different parts types; 26 total parts One connector is not yet approved, waiting for screening AntiCoincidnce Detector 15
GLAST Large Area Telescope: Planning Meeting December 10, 2003 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Planning Meeting December 10, 2003 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 David J. Thompson Thomas E. Johnson NASA Goddard
More informationGLAST Large Area Telescope: Cost/Schedule Review June 30, 2005 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Cost/Schedule Review June 30, 2005 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 David J. Thompson Thomas E. Johnson NASA Goddard
More informationGLAST Large Area Telescope:
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: AntiCoincidence Detector (ACD) Mechanical Ground Support Equipment Thomas E. Johnson, ACD Instrument Manager Thomas.E.Johnson@nasa.gov (301)
More informationMonthly Cost/Schedule/Mission Review. GLAST LAT Calorimeter May 24, Gamma-ray Large Area Space Telescope. GLAST Calorimeter.
Gamma-ray Large Area Space Telescope Monthly Cost/Schedule/Mission Review GLAST LAT Calorimeter May 24, 2005 W Neil Johnson neil.johnson@nrl.navy.mil wnjohnson 1 Outline Technical Status: Last Month's
More informationGLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 01/05/06
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 01/05/06 Ken Fouts SU-SLAC Subsystem Engineering Manager kfouts@slac.stanford.edu
More informationGLAST Large Area Telescope:
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Calorimeter (CAL) Subsystem WBS: 4.1.5 W. Neil Johnson Naval Research Lab, Washington DC Calorimeter Subsystem Manager neil.johnson@nrl.navy.mil
More informationGLAST LAT Project Subsystem Managers Meeting, May 13, Introduction. Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Introduction Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 Rev B 1 Two towers
More informationGLAST LAT Project Monthly Status Review, September 30, Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Project Status Overview Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 Rev.
More informationGLAST Large Area Telescope:
GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope MGSE Integration Readiness Status Two Tower Operations Eric Gawehn SU-SLAC LAT I&T MGSE Dept. Manager egawehn@slac.stanford.edu 650 926
More informationGLAST Mission - LAT Project DOE/NASA Review, March 31, 2004
Gamma-ray Large Area Space Telescope GLAST Mission Large Area Telescope Project Project Status March 31, 2004 Lowell A. Klaisner, Project Manager Stanford Linear Accelerator Center klaisner@slac.stanford.edu
More informationElectrical Ground Support Equipment Schedule and Cost. EGSE Schedule and Cost
Electrical Ground Support Equipment Schedule and Cost Scott Williams Stanford University scott.williams@stanford.edu S. Williams 1 Schedule The schedule is driven by the delivery of electronics hardware
More informationCommercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow
Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107
More informationCalorimeter Subsystem. Status and Issues. W. Neil Johnson Naval Research Laboratory. Gamma-ray Large Area Space Telescope
Gamma-ray Large Area Space Telescope Calorimeter Subsystem Status and Issues W. Neil Johnson Naval Research Laboratory neil.johnson@nrl.navy.mil W N Johnson Calorimeter Subsystem Status Outline Introduction
More informationMonthly Progress Report January 2005
Heliosiesmic & Magnetic Imager Doc# HMI00823 Contract #: PY-2223 Cage Code: 65113 Total Pages: 7 Monthly Progress Report January 2005 Lockheed Martin Space Systems Company Advanced Technology Center Lockheed
More informationGLAST LAT Project 3-4 May MGSE Design. LAT Environmental Test PDR 1
LAT LAT Environmental Environmental Test Test Planning Planning and and Design Design Review Review 3-4 3-4 4 May May 2005 2005 MGSE Design Martin Martin Nordby Nordby Mike Mike Foss Foss Marc Marc Campell
More informationCommuter Rail Update. October 25, 2018
Commuter Rail Update October 25, 2018 2 page page 3 State of Commuter Rail Network, July 2014 The 2014 Commuter Rail network had multiple issues and a history of neglect & under-investment FIRST UP? UPGRADES
More informationNJ Solar Market Update
NJ Solar Market Update April 16, 20 Renewable Energy Committee Meeting Trenton, NJ Prepared by Charlie Garrison Solar Installed Capacity Data The preliminary installed solar capacity as of 3/31/ is approximately
More informationANNUAL SUMMARY REPORT FY 2005 PERFORMANCE REPORT SUMMARY COMPARATIVE ANALYSIS
ANNUAL SUMMARY REPORT FY 2005 PERFORMANCE REPORT SUMMARY COMPARATIVE ANALYSIS RAIL OPERATIONS: Rail Passenger injuries increased from 34 in FY04 to 41 in FY05. The Woodley Park collision accounted for
More informationLate Starter. Tuesday, November 6, 2018
Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,
More informationNJ Solar Market Update As of 6/30/15
NJ Solar Market Update As of 6/30/ Prepared by Charlie Garrison July 17, 20 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 6/30/ is approximately 1,500.7 MW. Approximately
More informationDDG 51 Program. Sea, Air, Space Exposition Washington, DC 04 April Presented by: CAPT Casey Moton, USN DDG 51 Program Manager PMS 400D
Sea, Air, Space Exposition Washington, DC 04 April 2017 DDG 51 Program Presented by: CAPT Casey Moton, USN DDG 51 Program Manager PMS 400D 1 Agenda DDG 51 Shipbuilding Profile DDG 113-123 Production Status
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates For Internal Use Only. FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationM234 / M235 / M236 SELF-DESTRUCT FUZES
M234 / M235 / M236 SELF-DESTRUCT FUZES OUTLINE Self-Destruct (SD) Fuze Objectives SD Fuze Requirements KDI SD Fuze Design and Operation Safety Test and Army Certification Type Classification Test Results
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationToo Good to Throw Away Implementation Strategy
Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend
More informationINTECH AUGUST QHSE PERFORMANCE
INTECH QHSE PERFORMANCE - MONTHLY QHSE PERFORMANCE Goal Zero Days ( worked days without Lost Time Injury (LTI)) 751 This Month Minor Accidents or Incidents 01 This Month Major Accidents or Incidents 00
More informationCustomer Service, Operations and Security Committee. Information Item III-A. January 12, 2017
Customer Service, Operations and Security Committee Information Item III-A January 12, 2017 Train Reliability Program Page 4 of 19 Washington Metropolitan Area Transit Authority Board Action/Information
More informationINTECH JUNE QHSE PERFORMANCE
INTECH QHSE PERFORMANCE - MONTHLY QHSE PERFORMANCE Goal Zero Days ( worked days without Lost Time Injury (LTI)) 689 This Month Minor Accidents or Incidents This Month Major Accidents or Incidents Last
More informationRESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council
RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES January 10, 2011 Presentation to Arvada City Council CONSULTANT TEAM LBA Associates MSW Consultants Denver based recycling and waste management consultant
More informationCommuter Rail Performance. October
Commuter Rail Performance October 31 2016 1 Background - overall performance Year To Date: 89.67% YTD 125,629 trains North: 90.79% YTD 48,426 trains South: 89.07% YTD 77,203 trains 2 Background - overall
More informationFOR IMMEDIATE RELEASE
Article No. 7845 Available on www.roymorgan.com Roy Morgan Unemployment Profile Friday, 18 January 2019 Unemployment in December is 9.7% and under-employment is 8.8% FOR IMMEDIATE RELEASE Australian unemployment
More informationUp and Down Months of the Stock Market
Up and Down Months of the Stock Market 1926-2017 Positive years (66) in the stock market were not good all year long and losing years (24) were not losers throughout the year. Winning years produce losing
More informationGLAST Large Area Telescope:
DRAFT Rev 3 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Calorimeter Overview WBS 4.1.5 W. Neil Johnson Naval Research Lab, Washington DC Calorimeter Subsystem Manager johnson@gamma.nrl.navy.mil
More informationSolar Electric Propulsion Benefits for NASA and On-Orbit Satellite Servicing
Solar Electric Propulsion Benefits for NASA and On-Orbit Satellite Servicing Therese Griebel NASA Glenn Research Center 1 Overview Current developments in technology that could meet NASA, DOD and commercial
More informationNJ Solar Market Update As of 10/31/15
NJ Solar Market Update As of 10/31/15 Prepared by Charlie Garrison Renewable Energy Committee Meeting November 10, 2015 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 10/31/15
More informationPredict Future Failures From Your Maintenance Records
Predict Future Failures From Your Maintenance Records Presented by: Paul Barringer, P.E. Barringer & Associates, Inc. Reliability, Engineering, and Manufacturing Consultants Humble, Texas 77347, USA Phone:
More informationD G A G R I D A S H B O A R D : A P P L E S
75 79 60 56 49 74 65 59 54 42 76 63 58 53 78 55 42 43 79 44 81 63 47 83 64 59 53 48 Sources: Eurostat, MSs notifications, DG Agri, Comext, Comtrade, GTA, ITC, AMI, Expert groups, Freshfel, Wapa. 89 68
More informationSprinkler System Waiver Application Packet
Sprinkler System Waiver Application Packet According to the City s municipal code, use of sprinklers is conditional upon use of a water budget and the City continues to discourage customers from irrigating
More informationTECHNICAL SERVICE BULLETIN
TECHNICAL SERVICE BULLETIN To: Minuteman Dealers and Customers From: Minuteman Technical Support Date: 1/12/2011 Subject: TSB for the KIT # K-FRSPEEDSWT. For the FR17115, FR17220, FR20115 and FR20220 models.
More informationGAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case
Overview A consensus forecast is used to estimate the prime rate charged by commercial banks. As the prime rate is subject to competitive pressures faced by individual lenders and is set on an individual
More informationNJ Solar Market Update As of 2/29/16
NJ Solar Market Update As of 2/29/16 Prepared by Charlie Garrison March 24, 2016 SOLAR INSTALLED CAPACITY DATA The installed solar capacity as of 2/29/16 is approximately 1,644.3 MW. Approximately 20.3
More informationCreating a Lean and Productive Processing Facility
Creating a Lean and Productive Processing Facility Amsterdam 31st May 2013 Nick Tandy EBA Flying Squad Operational Improvement Lead, Filton, until May 2011 Sarah Raymond Head of Operations Filton, NHS
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY JULY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for e FY FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues
More informationSystem Management Principles Statement
System Management Principles Statement Compliance report for June 214 to August 214 Summary of balancing actions and breaches for June 214 to Aug 214 Performance compared to last year Summary Report Jun-14
More informationThe CU Beam Test at CERN Status Report and highlights from workshop II
The CU Beam Test at CERN Status Report and highlights from workshop II Luca Latronico luca.latronico@pi.infn.it LAT C&A Meeting May 22 2006 GLAST LAT Project LAT C&A Meeting 5/22/2006 Beam Test Schedule
More informationRFP No. P3010 New l.i ght Rail Vehicles
rr Los Angeles County Metropolitan Transportation Authority RFP No. P3010 New l.i ght Rail Vehicles Source Selection Committee Award Recommendation Light Rail Transit Project Requirements end P30i 0 Delivery
More informationPhoto by Bert van Dijk - Creative Commons Attribution-NonCommercial-ShareAlike License
Photo by Bert van Dijk - Creative Commons Attribution-NonCommercial-ShareAlike License https://www.flickr.com/photos/75478114@n00 Photo by Timothy Wildey - Creative Commons Attribution-NonCommercial License
More informationP.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)
P.O BOX 429, NUKU ALOFA, Tel: (676) 27-390 Fax: (676) 23-047 Email: jvanbrink@tongapower.to 22 October 2012 Lord Dalgety Electricity Commission Tu atakilangi Nuku alofa Dear Lord Dalgety Compliance Reporting
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationPast Due. Account Charges. Contract Charges Security Deposit Due - Jun 09, , Customer Service. Jun 19, PAST DUE $1,693.
11983978 Jun 19, 217 1 124 958 PAST DUE $1,693.97 Meter Reading Information Meter # 55271 May 3 655 Jun 15 6642 17 days 1397 on or about Aug 15 82 Past Due Balance payable includes an amount which is payable
More informationCHEVROLET CASTING NUMBERS 1924 to 1928; 1929 to 1931 Revised April PART 2: 1929 to 1931
CHEVROLET CASTING NUMBERS 1924 to 1928; 1929 to 1931 Revised April 16 2001 PART 2: 1929 to 1931 SECTION 1 1929 U.S. AND CANADIAN CHEVROLET ENGINE PARTS AND CASTING NUMBERS: MOTOR ASSEMBLY US PART # CANADIAN
More informationFAA Aging Electrical Systems Research Program Update Prepared for: Aging Transport Systems Rulemaking Advisory Committee January 23, 2002
FAA Aging Electrical Systems Research Program Update Prepared for: Aging Transport Systems Rulemaking Advisory Committee January 23, 2002 Robert A. Pappas Federal Aviation Administration Aging Electrical
More informationUnits of Instruction MISD Pacing Guide Days Date Range Test Date
MISD Pacing Guide Date Range Test Date Introduction: Processes of Investigations (1 day) Aug. 21 Unit 01: Matter (12 days) Aug. 22-Sept. 7 Sep. 10 Unit 02: Atomic Structure and the Periodic Table (15 days)
More informationCS/EE/ME 75 FSAE Electric 12 October 2015
CS/EE/ME 75 FSAE Electric 12 October 2015 Guillaume Blanquart Azita Emami Richard Murray Joseph Bowkett Cibele Halasz Noah Olsman Shenghan Yao Engineering and Applied Science California Institute of Technology
More informationWIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA APRIL 2014 MONTHLY REPORT
WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA APRIL 2014 MONTHLY REPORT In order to understand the vehicle classes and groupings, the MnDOT Vehicle Classification Scheme and the Vehicle Classification
More informationSTRATEGIC BUSINESS PLAN QUARTERLY KPI REPORT FOR: FISCAL YEAR 2015, QUARTER 1 (JULY THROUGH SEPTEMBER 2014)
STRATEGIC BUSINESS PLAN QUARTERLY KPI REPORT FOR: FISCAL YEAR 215, QUARTER 1 (JULY THROUGH SEPTEMBER ) CONTENTS BALANCED SCORECARD OF KEY PERFORMANCE INDICATORS SAFETY & SECURITY SLIDE VEHICLE, PASSENGER
More informationBalance from your previous bill $0.00 Meter # Basic Charge: 17 $ /day 3.23* Energy charge:¹ 2
11983979 Jun 19, 217 1 124 962 Jul 11, 217 $24.34 Meter Reading Previous Bill. Balance from your previous bill $. Meter # 552711 May 3 19813 Account Account charge 12.4* Charges 17 days 82 Jun 15 19895
More informationSUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update
MEETING DATE: August 31, 2005 SUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update RECOMMENDATION It is recommended that the Commission: i) Receive for information
More informationNovember 2017 Customer Switching Report for the Electricity and Gas Retail Markets
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities November 2017 Customer Switching Report for the Electricity and Gas Retail Markets Information Paper Reference: CRU18011 Date Published:
More informationPresented by B. Nelson for the QPS team QPS Conceptual Design Review June 23-24, 2003 ORNL
QPS Project Implementation Presented by B. Nelson for the QPS team QPS Conceptual Design Review June 23-24, 2003 ORNL Presentation Outline Fabrication Plans How we plan to build QPS R&D, primarily Modular
More informationReport of 3rd meeting of QRTV informal group
Report of 3rd meeting of QRTV informal group (Focusing on 1 st day: Tuesday, July 13 2010 at MEGAWEB) Opening Welcome and Opening Remarks by Mr. Shima, Director, Engineering Planning Division, Ministry
More informationMEDIA PACK 2019 MAGAZINE WINDOWS DOORS CONSERVATORIES GLASS FABRICATORS DISTRIBUTORS INSTALLERS. October 2018 Issue
MEDIA PACK 2019 WINDOWS DOORS CONSERVATORIES GLASS FABRICATORS DISTRIBUTORS INSTALLERS CLEARZINE CLEARVIEW-UK.COM MAGAZINE 733 ALUMINIUM WINDOW & DOOR FABRICATORS MAGAZINE DISTRIBUTION 12,606 2,356 14,889
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MARCH 21 MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for uary FY 21 FINANCIAL HEALTH Standard and Poor s Bond Rating Current AA AA Budget Based Revenues
More informationFOR IMMEDIATE RELEASE
Article No. 5842 Available on www.roymorgan.com Roy Morgan Unemployment Profile Thursday, 2 October 2014 Unemployment climbs to 9.9% in September as full-time work lowest since October 2011; 2.2 million
More informationNEWS Release. U.S. Manufacturing Technology Orders. Year-to-date U.S. manufacturing technology orders up 4.1% over 2011
U.S. Manufacturing Technology Orders A statistical program of AMT NEWS Release FOR RELEASE: October 8, 2012 Contact: Pat McGibbon, AMT, 703-827-5255 Year-to-date U.S. manufacturing technology orders up
More informationUNCLASSIFIED R-1 ITEM NOMENCLATURE
Exhibit R-2, RDT&E Budget Item Justification: PB 214 Army DATE: April 213 24: Research, Development, Test & Evaluation, Army COST ($ in Millions) Years FY 212 FY 213 # Base PE 23752A: Aircraft Engine Component
More information7 Habits of Highly Effec3ve Product Development
7 Habits of Highly Effec3ve Product Development September 5, 2014 ASTR 2014, Sep 10-12, St. Paul, MN 1 John Lenss John has over 18 years of experience in performing HALT. He has produced excellent results
More informationStatus report / Activity Plan of OBD Task Force
-20-12e Status report / Activity Plan of OBD Task Force 26 th Sep., 2017 Mayumi Sophie Morimoto (JASIC) OBD TF Goal agreed at 1 st OBD TF (15 th Dec. 2016) Develop harmonized OBD GTR by end of 2018*. *Approved
More informationTotal Production by Month (Acre Feet)
Production by Month (acre-feet) 2008 2009 2010 2011 2012 2013 2014 2015 2016 January 25 339.10 228.90 249.50 297.99 243.06 327.14 247.66 212.37 February 234.00 218.80 212.10 241.52 245.82 279.08 234.16
More informationTENTH DISTRICT MANUFACTURING SURVEY REBOUNDED MODERATELY Federal Reserve Bank of Kansas City Releases January Manufacturing Survey
FOR RELEASE Thursday, January 23, 2014 EMBARGOED FOR 10 A.M. CENTRAL TIME CONTACT: Bill Medley 816-881-2556 Bill.Medley@kc.frb.org TENTH DISTRICT MANUFACTURING SURVEY REBOUNDED MODERATELY Federal Reserve
More informationEnergy Performance Information Request Timeline
Energy Performance Information Request Timeline Project Title: UT Project # Project Manager: Submitted by: Day Submitted: The timeline below outlines a comprehensive list of required documents and when
More informationCALL FOR IDEAS FOR THE RE-USE OF THE MARS EXPRESS PLATFORM PLATFORM CAPABILITIES. D. McCoy
Mars Express Reuse: Call for Ideas CALL FOR IDEAS FOR THE RE-USE OF THE MARS EXPRESS PLATFORM PLATFORM CAPABILITIES D. McCoy PARIS 23 MARCH 2001 page 1 Mars Express Reuse: Call for Ideas PRESENTATION CONTENTS
More informationCOMET: Colorado Mini Engine Team Manufacturing Status Review February 3, 2014
COMET: Colorado Mini Engine Team Status Review February 3, 2014 Team members: Julia Contreras-Garcia Emily Ehrle Eric James Jonathan Lumpkin Matthew McClain Megan O Sullivan Benjamin Woeste Kevin Wong
More informationArtesis MCM Case Studies. March 2011
Artesis MCM Case Studies March 2011 Case 1 Automotive Company: Automobile Manufacturer A Equipment: Pump Stator Isolation Breakdown Decreasing current unbalance level Case 1 Automotive Company: Automobile
More informationCopyright 2016 Boeing. All rights reserved.
Boeing s Commercial Crew Program John Mulholland, Vice President and Program Manager International Symposium for Personal and Commercial Spaceflight October 13, 2016 CST-100 Starliner Spacecraft Flight-proven
More informationAppendix G Examples and Recommended Methods
Reporting Outages to the Generating Availability Data System (GADS) Introduction The examples in this appendix illustrate the reporting of outages and deratings to GADS. They are based on a fictional 600
More informationDecember 2018 RenewableGenerations Monthly Report
2018 RenewableGenerations Monthly Report Ecosystem of Clean Energy Programs Contractor Training Webinar Table of Contents Solar Electric... 3 Solar Thermal Heating (Northern Nevada Gas Customers)... 5
More informationFOR IMMEDIATE RELEASE
Article No. 7761 Available on www.roymorgan.com Roy Morgan Unemployment Profile Monday, 8 October 2018 Unemployment down to 9.4% in September off two-year high Australian employment has grown solidly over
More informationRegulation Update. Operating Committee September 12, PJM 2017
Regulation Update Operating Committee September 12, 2017 Regulation Market Clearing Price *Data up to Aug 22 2 Mileage Ratio Mileage Ratio has increased since the new signal implementation Larger Utilization
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for uary FY 219 FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues
More informationAviation S&T: Future Vertical Lift & JMR Tech Demonstrator
Presented to: Cribbins Symposium, Leadership Panel Aviation S&T: Future Vertical Lift & JMR Tech Demonstrator Approved for public release; distribution unlimited. Review completed by the AMRDEC Public
More informationHorseshoe Bay Terminal Open House
Horseshoe Bay Terminal Open House July 5, 2007 Welcome Aboard The purpose of this Open House is to provide you with information and to receive your input for consideration on the Horseshoe Bay Terminal
More informationExhibit R-2, RDT&E Budget Item Justification
PE NUMBER: 0207138F PE TITLE: F-22 SQUADRONS Exhibit R-2, RDT&E Budget Item Justification BUDGET ACTIVITY PE NUMBER AND TITLE 07 Operational System Development 0207138F F-22 SQUADRONS Cost ($ in Millions)
More informationFactory activity accelerated further in our region this month, posting its highest composite reading since 2011, said Wilkerson.
FOR RELEASE Thursday, October 26, 17 EMBARGOED FOR A.M. CENTRAL TIME CONTACT: Pam Campbell 45-27-8617 Pam.Campbell@kc.frb.org TENTH DISTRICT MANUFACTURING ACTIVITY POSTS STRONG GROWTH Federal Reserve Bank
More informationD G A G R I D A S H B O A R D : A P P L E S
Sources: Eurostat, MSs notifications, DG Agri, Comext, Comtrade, GTA, ITC, AMI, Expert groups, Freshfel, Wapa. 000 tonnes 39 41 31 22 29 22 32 27 17 18 9 27 15 12 6 6 6 4 5 6 5 4 11 25 15 9 9 93 62 51
More informationDate Event or Holiday :Sun, 2:Mon North Orchard Delong Preschool North Orchard Delong Preschool
2018 6 1 1:Sun, 2:Mon 2018-2019 Date Event or Holiday Aug 16 Board Meeting 6pm Aug 23 Open House June 2018 July 2018 August 2018 Sep 06 Board Meeting 6pm Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th
More informationANCR CRU Statistics February 2007 to December 2007
ANCR CRU Statistics February 2007 to December 2007 o Jan/07 Feb/07* Mar/07 Apr/07 May/07 Jun/07 Jul/07 Aug/07 Sep/07 Oct/07 Nov/07 Dec/07 Total notes data from Perimeter phone system unavailable prior
More informationAutomated Occupancy Detection October 2015 (Phase I) Demonstration Results Presented by Kathy McCune
Automated Occupancy Detection October 2015 (Phase I) Demonstration Results Presented by Kathy McCune 2016 TRB Managed Lanes Conference May 5th, Session 6 Presentation Background Outline Metro ExpressLanes
More informationNovember 2018 Customer Switching Report for the Electricity and Gas Retail Markets
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities November 2018 Customer Switching Report for the Electricity and Gas Retail Markets Information Paper Reference: CRU18266 Date Published:
More informationSTRATEGIC BUSINESS PLAN QUARTERLY KPI REPORT FOR: FISCAL YEAR 2015 THROUGH QUARTER 4 (JULY 2014 THROUGH JUNE 2015)
STRATEGIC BUSINESS PLAN QUARTERLY KPI REPORT FOR: FISCAL YEAR THROUGH QUARTER 4 (JULY THROUGH JUNE ) CONTENTS BALANCED SCORECARD OF KEY PERFORMANCE INDICATORS SAFETY & SECURITY SLIDE VEHICLE, PASSENGER
More informationBulk Storage Containers
UCSB AST SPCC SELF-INSPECTION CHECKLIST Year: Responsible Department: Tank Location: Tank ID: Bulk Storage Containers Total tank capacity: Petroleum type and amount: Secondary containment type: (diesel,
More information100kW GROUND MOUNTED SOLAR PHOTOVOLTIC POWER PLANT DETAILED PROJECT REPORT AERO SPACE MATERIALS PVT LTD
EXECUTIVE SUMMARY 100kW GROUND MOUNTED SOLAR PHOTOVOLTIC POWER PLANT 1. Location i) State : TAMIL NADU, ii) Locality : KOVILPALAYAM, POLLACHI iii) Latitude : 10 45 16.22 N iv) Longitude : 77 01 15.27 E
More informationincrease of over four per cent compared to the average of $409,058 reported in January 2010.
SINGLE FAMILY RESIDENTIAL BREAKDOWN uary 211 26.8 % 1.7 % 7.%.4%.1 % Good Start to 211 TORONTO - February 4, 211 Greater Toronto REALTORS reported 4,337 transactions through the TorontoMLS system in uary
More informationFINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010
FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009
More informationFOR IMMEDIATE RELEASE
Article No. 7433 Available on www.roymorgan.com Roy Morgan Unemployment Profile Friday, 12 January 2018 2.6m Australians unemployed or under-employed in December The latest data for the Roy Morgan employment
More informationWIM #37 was operational for the entire month of September Volume was computed using all monthly data.
SEPTEMBER 2016 WIM Site Location WIM #37 is located on I-94 near Otsego in Wright county. The WIM is located only on the westbound (WB) side of I-94, meaning that all data mentioned in this report pertains
More informationPresentation to the Customer Service, Operations and Safety Committee OPERATIONS PERFORMANCE INDICATORS
Presentation to the Customer Service, Operations and Safety Committee OPERATIONS PERFORMANCE INDICATORS May 19, 2005 Department of Operations 100 95 90 85 80 75 70 65 A B C D RAIL PERFORMANCE INDEX FY
More informationLocal Market Update February 2013
Local Market Update February 213 February sales of single-family homes reported in Lucas and Upper Wood County by the Toledo Board of REALTORS totaled 315. This was unchanged compared to February of 212.
More informationWIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA MAY 2013 MONTHLY REPORT
WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA MAY 2013 MONTHLY REPORT In order to understand the vehicle classes and groupings the Mn/DOT Vehicle Classification Scheme and the Vehicle Classification Groupings
More information