1 Reducing Losses in Power Distribution through Improved Efficiency of Distribution Transformers (EWG A) Analysis of IEC Recommendations in Selected APEC Economies 18 December 2017 Bangkok, Thailand Sommai PhonAmnuaisuk International Institute for Energy Conservation

2 Outline Introduction IEC Technical Specification Analysis approach and methodology Findings from surveys and analysis Conclusions and Recommendations

3 Introduction Project title: Reducing Losses in Power Distribution through Improved Efficiency of Distribution Transformers Objective: To build awareness and capacity of policy makers on impacts of adopting IEC TS (Energy Efficiency Technical Specification) in terms of energy loss and GHG emission reductions To come up with key recommendations (in consultation with key stakeholders) on the next steps Timeline: November 2016 January 2018

4 IEC Technical Specification Published in January 2017 Power Transformers Part 20: Energy Efficiency Provides methods for efficiency and efficiency index calculation Provides two levels of recommendations Level 1 is for basic energy performance Level 2 is for high energy performance Energy performance MAY be specified in one of the following ways: Minimum PEI (Peak Efficiency Index) Maximum load losses and maximum noload losses Minimum Efficiency Index at a load factor of 50%

5 IEC Recommendations Observations Energy Performance Indicator 50Hz DT 60Hz DT Minimum PEI (Method A) Maximum load losses & noload losses Minimum Efficiency Index at a load factor of 50% (Method B) Energy efficiency recommendations for 50Hz and 60Hz DTs not harmonized Any 50Hz DTs meeting max. load losses & noload losses also meet minimum PEI and EI B50 EI B50 recommendations for 60Hz DTs harmonized with DOE 2010 and 2016 regulations Details of a loss capitalization method provided Additional requirements suggested, e.g., total losses, efficiency at another load factor and/or power factor

6 Efficiency at 50% Load Factor World Practices on DT Efficiency Survey vs IEC Recommendations Efficiency values based on equations developed from an analysis of existing world standards and regulations in 2013 for DTs (15 kva to 3,150 kva threephase DTs) LiquidFilled, ThreePhase (50Hz) LiquidFilled, ThreePhase (60Hz) % % Efficiency at 50% Load Factor (Method A) 99.50% 99.00% 98.50% 98.00% Tier 1 Tier 2 Tier 3 Tier 4 Tier 5 EIA50 Level 1 EIA50 Level % 99.00% 98.50% 98.00% Tier 1 Tier 2 Tier 3 Tier 4 Tier 5 EIB50 Level 1 EIB50 Level % 97.50% kva Rating kva Rating

7 ANALYSIS APPROACH & METHODOLOGY

8 Estimation of Energy Savings by Energy Efficient DTs Several studies for APEC and ASEAN have been conducted since 2013 Previous APEC Study in 2013 Average load factors were used for estimation of total energy losses and savings DT efficiencies based on EI B50 Popular kva ratings were considered in potential efficiency improvements Operational parameters not considered in the previous analysis: Diversity of daily load profiles (load curves) and load factor in different enduse sector Different DT designs at the same energy efficiency index

9 Diversity of Daily Load Profiles/ Load Factors 1 Ideal Case Average loading factor Average RMS loading factor % 50% :00:00 02:00:00 04:00:00 06:00:00 08:00:00 10:00:00 12:00:00 14:00:00 16:00:00 18:00:00 20:00:00 22:00:00 00:00:00 Worst Case % 71% :00:00 02:00:00 04:00:00 06:00:00 08:00:00 10:00:00 12:00:00 14:00:00 16:00:00 18:00:00 20:00:00 22:00:00 00:00:00 Realistic Case % 57% :00:00 02:00:00 04:00:00 06:00:00 08:00:00 10:00:00 12:00:00 14:00:00 16:00:00 18:00:00 20:00:00 22:00:00 00:00:00

10 Efficiency (%) Different DT Designs for the same Efficiency Index Design NoLoad Losses (W) Load Losses (W) Design A Design B Design C % 99.10% 98.90% 98.70% 98.50% 98.30% 98.10% 97.90% Design A Design B Design C 97.70% 97.50%

11 Daily Energy Losses (Wh) Diversity of Daily Load Profiles Ideal Case Worst Case Realistic Case :00:00 02:00:00 04:00:00 06:00:00 08:00:00 10:00:00 12:00:00 14:00:00 16:00:00 18:00:00 20:00:00 22:00:00 00:00: :00:00 02:00:00 04:00:00 06:00:00 08:00:00 10:00:00 12:00:00 14:00:00 16:00:00 18:00:00 20:00:00 22:00:00 00:00: :00:00 02:00:00 04:00:00 06:00:00 08:00:00 10:00:00 12:00:00 14:00:00 16:00:00 18:00:00 20:00:00 22:00:00 00:00:00 6,000 5,000 4,000 3,000 2,000 1,000 26%74% Higher 9%24% Higher Ideal Case Worst Case Realistic Case Design A (NL=30W, LL=408W) 3,102 5,397 3,854 Design B (NL=66W, LL=264W) 3,102 4,587 3,588 Design C (NL=96W, LL=144W) 3,102 3,912 3,367 Source: Estimation by ICA

12 Daily Energy Losses (Wh) Daily Energy Losses (Wh) Daily Energy Losses (Wh) Diversity of Loading Factors 6,000 5,000 4,000 3,000 2,000 1,000 50% Average loading factor 3,500 3,000 35% Average loading factor 2,500 2,000 1,500 1, Ideal Case Worst Case Realistic Case Design A (NL=30W, LL=408W) 1,880 3,004 2,248 Design B (NL=66W, LL=264W) 2,311 3,039 2,549 Design C (NL=96W, LL=144W) 2,671 3,067 2,801 Ideal Case Worst Case Realistic Case Design A (NL=30W, LL=408W) 3,102 5,397 3,854 Design B (NL=66W, LL=264W) 3,102 4,587 3,588 Design C (NL=96W, LL=144W) 3,102 3,912 3,367 9,000 8,000 7,000 6,000 5,000 4,000 3,000 2,000 1,000 75% Average loading factor Ideal Case Worst Case Realistic Case Design A (NL=30W, LL=408W) 6,098 6,621 7,790 Design B (NL=66W, LL=264W) 5,041 5,379 6,135 Design C (NL=96W, LL=144W) 4,160 4,344 4,756

13 Analysis Approach and Methodology Step A: Compiling DT Data Classifications by kv/kva Step B: Defining DT Losses/ Efficiency Step C: Defining Analysis Parameters Step D: Estimating Per Unit Annual Energy Losses Step E: National Impact Analysis Baseline Scenario MEPS/ Utilities Procurements Typical Load Profiles for Different End Use Sectors x PG&E DTs for Residential Customers Annual Load Factor Baseline Scenario Per Unit Annual Energy Losses Extrapolation at the APEC Economy Level Baseline IEC Savings Energy Demand of PEA GWh 12,000 11,500 11, ,500 10,000 9, IEC Scenario Load losses/no load losses Efficiency at 50% load Peak efficiency index 9,000 8,500 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec DT designs to meet efficiency requirements IEC Scenario Per Unit Annual Energy Losses Key Variables: Electricity Tariff (current/ projection), Emission Factor, discount rate, service life

14 Comprehensive Data Required Stock of installed DTs classified by kv and kva Popular kva rating, Expected lifetime of DTs Typical load profiles of different enduse sectors, seasonal variation and load factors Average loading factor or average RMS loading Current energy performance standards National Standards and Utility Procurement Specifications Electricity tariff, electricity emission factor Data collection activities include: Review of secondary resources Questionnaire distribution Direct interview with utilities

15 Key Parameters and Assumptions (1) Baseline (businessasusual) scenario Energy performance levels based on either the national MEPS or the utilities procurement documents. IEC scenario Level 1 recommendations are not used due to their less stringentcies. For 50Hz DTs level 2 energy performance recommendations on noload and load losses and EI B50 For 60 Hz DTs level 2 energy performance recommendations on EIB50 The PEI recommendations referenced as indicators not as EE options

16 Key Parameters and Assumptions (2) Per unit analysis characteristics of the most common kva rating represent the whole DT population (Utilityowned, liquidimmersed) Focus on three major enduse sectors: Residential, Commercial and Industrial (Three sets of daily load profile) Annual average loading factors based either on feedback from APEC/ASEAN economies or historical energy consumption statistics Maximum loading factor for DTs is 100% (at any time of the day) no overloaded! Two analysis points annual average loading factors (per data collection) & 50% loading factor

17 Baseline Scenario Baseline Scenario LiquidImmersed DT (50Hz, 24 kv, 3,150 kva) LiquidImmersed DT (60Hz, 2,500 kva) MEPS or maximum noload/ load losses requirements of utilities MEPS or efficiency index a specific % loading MEPS or efficiency index a specific % loading Baseline Model Noload/load losses Baseline Model With noload/load losses that deliver the required efficiency Index Baseline Model With noload/load losses that deliver the required efficiency Index Annual energy loss analysis Not implemented in selected economies Flat/Constant Daily Load Profile (no peak demand) Residential Sector Daily Load Profile (evening peak demand) Commercial Sector Daily Load Profile (afternoon & evening peak demand) Industrial Sector Daily Load Profile (multiple peak demand) % Load Factor Variation Analysis results per model

18 Energy Efficiency Scenario IEC Scenario LiquidImmersed DT (50Hz, 24 kv, 3,150 kva) LiquidImmersed DT (60Hz, 2,500 kva) Scenario IEC LL50: IEC , Table 4, Max noload losses & load losses Level 2 for 50Hz Scenario IEC EI50: IEC , Table 6, EIB50 Level 2 for 50Hz Scenario IEC EI60: IEC , Table 5, EIB50 Level 2 for 60Hz Two DT models with different load vs efficiency the same EI B50 Level 2 for 50Hz Multiple DT models with different load vs efficiency the same EI B50 Level 2 for 60Hz Model A Noload/load losses Model B Noload/load losses (high total loss) Model C Noload/load losses (low total loss) Model D Noload/load losses (high total loss) Model E Noload/load losses (med total loss) Model XX Noload/load losses (low total loss) PEI (%) of each model for comparison & reporting Annual energy loss analysis Flat/Constant Daily Load Profile (no peak demand) Residential Sector Daily Load Profile (evening peak demand) Commercial Sector Daily Load Profile (afternoon & evening peak demand) Industrial Sector Daily Load Profile (multiple peak demand) % Load Factor Variation Analysis results per model

19 FINDINGS FROM DATA COLLECTION/SURVEY

20 DT Performance Standards in APEC

21 Data Collection Results Sufficient data obtained from the Philippines, Thailand, USA (only PG&E) and Vietnam Vietnam s national MEPS is based on EI but it is less stringent than utilities requirements excluding from the analysis 50Hz DTs (Thailand & Vietnam) max. noload and load losses requirement 60 Hz DTs (Philippines & USA) EI B50 (Guideline on noload/load losses also available for electric cooperatives)

22 Maximum NoLoad Losses in Thailand and Vietnam

23 Maximum Load Losses in Thailand and Vietnam

24 Minimum Efficiency Index (EI B50 ) Single Phase DT in Philippines and USA

25 Minimum Efficiency Index (EI B50 ) Three Phase DT in Philippines and USA

26 Diversity of Daily Load Profiles and Loading Factors Residential Sector Max. Loading Factor: 58% 84% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Commercial Sector Max. Loading Factor: 81% 88% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % IndustrialSector Max. Loading Factor: 48% 91% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%

27 PER UNIT ANALYSIS

28 Efficiency Efficiency Four DTs Designs 50Hz Baseline: 3Phase, 160 kva DT, PEA, Thailand % % % % Baseline: based on existing losses requirements % Baseline Model Design A % Design B % Design C % % Loading Factor Baseline: 3Phase, 250 kva DT, SPC & HCMC, Vietnam % % % % % Baseline Model Design A % Design B % Design C IEC : based on level 2 EI B50 for 50Hz Design A max. IEC noload/load losses Design B low noload losses and high load losses Design C High noload losses and low load losses % % Loading Factor

29 Efficiency Efficiency Four DTs Designs 60Hz Baseline: 1Phase, 50kVA DT, Philippines % % % Baseline Model % Design A Design B Design C % % Loading Factor Baseline: 1Phase, 25 kva DT, PG&E, USA % % % % % % Baseline Model % Design A Design B % Design C % % % Baseline: based on DOE 2010 requirements, NEMA TP1 compliant IEC : based on level 2 EI B50 for 60Hz (or DOE 2016) Design A Medium noload losses and high load losses Design B low noload losses and high load losses Design C High noload losses and low load losses Loading Factor

30 Unit Installed MVA Installed Per Unit Analysis Philippines (1) Utility Owned DT Population 50,000 40,000 1Phase, 50 kva DT selected for per unit analysis 2,500 2,000 30,000 1,500 20,000 3phase 1,000 3phase 10,000 1phase 500 1phase kva Rating kva Rating Distribution Transformer Efficiency Profile 50 kva, SinglePhase, 60Hz NoLoad Losses (W) PEI gained = 0.025%0.38% EI B50 gained = 0.03% Load Losses (W) Total Losses (W) PEI (%) Baseline Model % 99.08% Design A % 99.11% Design B % 99.11% Design C % 99.11% EI B50

31 Per Unit Annual Savings (kwh) Per Unit Annual Savings (kwh) Per Unit Analysis Philippines (2) Loading factors: 48% to 78% Typical Loading Factors 50% Loading Factor Design A Design B Design C Flat Residential Commercial Industrial Design A Design B Design C Flat Residential Commercial Industrial , Savings = 1% to 2% Savings = 4% to 5% Savings = 7% to 20% Savings = 2% to 3% Savings = 3% to 4% Savings = 1% to 12%

32 Per Unit Analysis Thailand Metropolitan Electricity Authority (MEA) PEI gained = 0.035%0.145% EI B50 gained = 0.005% Distribution Transformer 500 kva, Three Phase, 50Hz, 24kV Efficiency Profile NoLoad Losses (W) Load Losses (W) Total Losses (W) PEI (%) Baseline Model 670 3,030 3, Design A 459 3,900 4, Design B 230 4,913 5, Design C 918 1,887 2, EI B50 Provincial Electricity Authority (PEA) PEI gained = 0.35%0.52% EI B50 gained = 0.31% Distribution Transformer 160 kva, ThreePhase 50Hz, 22kV Efficiency Profile NoLoad Losses (W) Load Losses (W) Total Losses (W) PEI (%) Baseline Model 360 2,100 2, % % Design A 189 1,750 1, % % Design B 95 2,167 2, % % Design C , % % EI B50

33 Per Unit Annual Savings (kwh) Per Unit Annual Savings (kwh) Per Unit Analysis Thailand, MEA Loading factors: 66% Typical Loading Factors 50% Loading Factors 3, , , ,000 2,000 Design A Design B Design C Flat Residential Commercial Industrial Design A Design B Design C Flat Residential Commercial Industrial 3, , Savings = 9% to 13% Savings = 5% to 9% Savings = 12% to 19% Savings = 2% to 4% Savings 1% Savings = 1% to 4%

34 Per Unit Annual Savings (kwh) Per Unit Annual Savings (kwh) Per Unit Analysis Thailand, PEA Loading factors: 73% Typical Loading Factors 50% Loading Factor 6,000 2,600 5,000 2,500 4,000 3,000 2,000 Flat Residential Commercial Industrial 2,400 2,300 2,200 2,100 Flat Residential Commercial Industrial 1,000 2, ,900 Design A Design B Design C Design A Design B Design C Savings = 24% to 27% Savings = 36% to 41% Savings = 29% Savings = 31% to 32% Savings = 27% to 28% Savings = 15% to 22%

35 Per Unit Analysis USA, PG&E (1) 1Phase, 25 kva DT selected for per unit analysis Source: Electric Program Investment Charge (EPIC), PG&E, December 2016 PEI gained = 0.042%0.385% EI B50 gained = 0.04% Distribution Transformer 25 kva, SinglePhase, 60Hz Efficiency Profile NoLoad Losses (W) Load Losses (W) Total Losses (W) PEI (%) Baseline Model % 98.91% Design A % 98.95% Design B % 98.95% Design C % 98.95% EI B50

36 Per Unit Annual Savings (kwh) Per Unit Annual Savings (kwh) Per Unit Analysis USA, PG&E (2) Loading factors: 40% to 70% Typical Loading Factors 50% Loading Factors Design A Design B Design C Flat Residential Flat Residential Commercial Industrial Design A Design B Design C Commercial Industrial Savings = 3% to 4% Savings = 2% to 8% Savings = 13% to +14% Savings = 4% Savings = 1.2% to +0.8% Savings = 4%

37 % Share Per Unit Analysis Vietnam (1) 20.00% 18.00% 16.00% 14.00% 12.00% 10.00% 8.00% 6.00% 4.00% 2.00% 0.00% Utility Owned Distribution Transformers 3Phase, 250 kva DT selected for per unit analysis Others kva Rating Source: Market Study for Utility Distribution Transformer Vietnam, ICA, 2015 PEI gained = 0.115%0.247% EI B50 gained = 0.1% Distribution Transformer 250 kva, ThreePhase, 50Hz, 22kV Efficiency Profile NoLoad Losses (W) Load Losses (W) Total Losses (W) PEI (%) Baseline Model 340 2,600 2, % % Design A 270 2,350 2, % % Design B 135 2,946 3, % % Design C 540 1,166 1, % % EI B50

38 Per Unit Annual Savings (kwh) Per Unit Annual Savings (kwh) Per Unit Analysis Vietnam (2) Loading factors: 84%88% Typical Loading Factors 50% Loading Factors 9,000 1,600 8,000 1,400 7,000 6,000 5,000 4,000 3,000 2,000 1,000 Flat Residential Commercial Industrial 1,200 1, Flat Residential Commercial Industrial 0 0 1,000 Design A Design B Design C Design A Design B Design C Savings = 11% Savings = 38% to 39% Savings = 13% Savings = 16% Savings = 12% Savings = 2% to 3%

39 Summary of Potential Energy 50% Loading Factor 35% 30% 25% 20% 15% Design A 10% Design B 5% Design C 0% 5% 10% Philippines Thailand (MEA) Thailand (PEA) USA Vietnam 15%

40 Annual Energy Loss (kwh) Annual Energy Loss (kwh) Annual Energy Loss (kwh) Annual Energy Loss (kwh) PEI vs Annual Energy 50% Loading Factor 1Phase, 50 kva DT, 60Hz, Philippines 3Phase, 160 kva DT, 50Hz, Thailand (PEA) 4, % 14, % 3,500 3,000 2,500 2,000 1,500 1, % % % % % % Flat Residential Commercial Industrial PEI (%) EIB50 (%) 12,000 10,000 8,000 6,000 4,000 2, % % % % % % % % Flat Residential Commercial Industrial PEI (%) EIB50 (%) % % Baseline Model Design A Design B Design C Baseline Model Design A Design B Design C 1Phase, 25 kva DT, 60Hz, USA (PG&E) 3Phase, 250 kva DT, 50Hz, Vietnam (SPC & HCMC) 1, % 9, % 1,300 1,280 1,260 1, % % % Flat Residential 8,500 8, % % % % Flat Residential 1,220 1,200 1,180 1, % % % Commercial Industrial PEI (%) EIB50 (%) 7,500 7, % % % % Commercial Industrial PEI (%) EIB50 (%) 1, % 6, % Baseline Model Design A Design B Design C Baseline Model Design A Design B Design C

41 NATIONAL IMPACT ANALYSIS

42 Key Parameters and Assumptions for National Impact Analysis % share of DT kva installed in each enduse sector based on % share of national electricity consumption Growth of annual DT installation based on historical data Daily load profiles, loading factors, annual installed capacity growth constant throughout the analysis period

43 DT Stock (MVA) Replacement of Existing DT Stock 90,000 80,000 70,000 60,000 50,000 40,000 30,000 20,000 10,000 0 Projection of DT Stock in Vietnam New Installation Replacement Baseline Model Stock With an estimated lifetime of 20 years, all existing DT stock will be replaced by new DTs by 2037

44 Estimated Annual Energy Savings and GHG Emission Reduction Country Philippines Thailand USA Vietnam Popular UtilityOwned DTs SinglePhase, 60 Hz, 50 kva ThreePhase, 50 Hz, 160 kva (PEA) & 500 kva (MEA) SinglePhase, 60 Hz, 25 kva ThreePhase, 50 Hz, 250 kva Utility Owned DT Installed Capacity (MVA) EI B50 Level 2 (Design C) Annual Energy Savings (GWh) GHG Emission Reduction (ktco2e) ,200 * ,655 1,394 2, , ,000 ** 652 1, ,015 1,578 2, ,412 Note: * Estimated installed capacity of DTs in three distribution utilities (two in Luzon, one large and one small, and one in Mindanao) ** Aggregated capacity of DTs installed in the PG&E system

45 CONCLUSIONS & RECOMMENDATIONS

46 Conclusions (1) IEC high energy performance (level 2) for noload and load losses are not necessarily applicable for all utilities in APEC and ASEAN Already less stringent than the procurement specifications of some utilities (e.g. MEA) Diversity of daily load profiles (or load curves) for different enduses (e.g., residential, commercial and industrial applications) results in variations of energy losses in DTs. Within 5% range Variation of average loading factors has greater impacts on energy losses than diversity of daily load profiles Energy losses of a DT at a specific loading factor cannot be estimated using PEI.

47 Conclusions (2) EI B50 will be meaningful and more accurate for determination of energy performance when comparing DTs at loading factors close to 50%. It is virtually impossible to predict uncertainty of EI B50 as it depends on DT designs (noload and load loss values). Noload and load losses allow for better estimation of the actual energy losses of DTs under different operating conditions. Most utility load profile data show high loading factor of more than 50% DTs with lower load losses (Design C) are generally more effective in reducing energy losses than adoption of DTs with lower noload losses, higher PEI or higher EI B50 with high load losses.

48 General Recommendations More stringent energy performance requirements than level 2 should be included in IEC More resources in collecting demand data and understanding typical loading factors in major enduse sectors needed These will assist in determination of the energy performance parameters for DTs that best reflect the actual situation. With limited data on energy demand profiles, noload and load losses requirements for procurement of DTs should be adopted as estimation of energy losses & savings will be made easier.

49 Specific Recommendations for Policy Makers (Utility & NonUtility) Focusing on common DT ratings Implementation of MEPS can focus on specific DT ratings Identifying typical load factors for each common rating Using IEC as a guide, and selecting the energy performance criteria that facilitate the impact assessment and respond to the typical load factors. Either noload/load losses or Efficiency two loading factors (e.g. 50% and 100%) recommended Use mix of losses, i.e. low noload losses for light load ratings and low load losses for high load ratings

50 QUESTION & ANSWER

51 THANK YOU FOR YOUR ATTENTION

Reducing Losses in Power Distribution through Improved Efficiency of Distribution Transformers

Reducing Losses in Power Distribution through Improved Efficiency of Distribution Transformers Reducing Losses in Power Distribution through Improved Efficiency of Distribution Transformers APEC Energy Working Group January 2018 APEC Project: EWG 05 2016A Produced by International Institute for

More information

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107

More information

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014 Distribution Capacity Impacts of Plug In Electric Vehicles Chris Punt, P.E. MIPSYCON 2014 1 Outline EV Benefits EV Growth Where are we today? Where are we going? Potential Distribution Capacity Issues

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates For Internal Use Only. FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options

The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options Electricity demand in France: a paradigm shift Electricity

More information

Manitoba Hydro Customer Consultation. Industrial Rates Workshop

Manitoba Hydro Customer Consultation. Industrial Rates Workshop Manitoba Hydro Customer Consultation Industrial Rates Workshop Industrial Rates Workshop Engage g Customers in Rate Development Increase understanding of rate-setting process Solicit feedback and input

More information

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering

More information

INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM

INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM Paper 129 INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM Arindam Maitra Jason Taylor Daniel Brooks Mark Alexander Mark Duvall EPRI USA EPRI USA EPRI USA EPRI USA EPRI USA amaitra@epri.com

More information

University of Michigan Eco-Driving Index (EDI) Latest data: October 2017

University of Michigan Eco-Driving Index (EDI)   Latest data: October 2017 University of Michigan Eco-Driving Index () http://www.ecodrivingindex.org Latest data: October 2017 Developed and issued monthly by Michael Sivak and Brandon Schoettle Sustainable Worldwide Transportation

More information

Technology - Regulations Nexus for Higher Efficiency Transformers

Technology - Regulations Nexus for Higher Efficiency Transformers Technology - Regulations Nexus for Higher Efficiency Transformers International Energy Efficient Transformers Workshop 2013 By Mayur Karmarkar 13 th Nov 2013 Distribution Transformer Energy Efficiency

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 7353 Available on www.roymorgan.com Roy Morgan Unemployment Profile Wednesday, 11 October 2017 2.498 million Australians (18.9%) now unemployed or under-employed In September 1.202 million

More information

Used Vehicle Supply: Future Outlook and the Impact on Used Vehicle Prices

Used Vehicle Supply: Future Outlook and the Impact on Used Vehicle Prices Used Vehicle Supply: Future Outlook and the Impact on Used Vehicle Prices AT A GLANCE When to expect an increase in used supply Recent trends in new vehicle sales Changes in used supply by vehicle segment

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 7845 Available on www.roymorgan.com Roy Morgan Unemployment Profile Friday, 18 January 2019 Unemployment in December is 9.7% and under-employment is 8.8% FOR IMMEDIATE RELEASE Australian unemployment

More information

Operational Opportunities to Minimize Renewables Curtailments

Operational Opportunities to Minimize Renewables Curtailments Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance

More information

ANCR CRU Statistics February 2007 to December 2007

ANCR CRU Statistics February 2007 to December 2007 ANCR CRU Statistics February 2007 to December 2007 o Jan/07 Feb/07* Mar/07 Apr/07 May/07 Jun/07 Jul/07 Aug/07 Sep/07 Oct/07 Nov/07 Dec/07 Total notes data from Perimeter phone system unavailable prior

More information

Cost, energy and climate performance assessment of Split-type ACs in Asian countries

Cost, energy and climate performance assessment of Split-type ACs in Asian countries Valentyn Volkov / Shutterstock.com Olga Kashubin / Shutterstock.com Andrii Zhezhera/ Shutterstock.com Cost, energy and climate performance assessment of Split-type ACs in Asian countries Philipp Munzinger

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 7761 Available on www.roymorgan.com Roy Morgan Unemployment Profile Monday, 8 October 2018 Unemployment down to 9.4% in September off two-year high Australian employment has grown solidly over

More information

Economic & Steel Market Development in Japan

Economic & Steel Market Development in Japan 1 Economic & Steel Market Development in Japan 68 th OECD Steel Committee Paris May 6-7, 2010 The Japan Iron & Steel Federation 2 Macro-economic overview Steel Supply and Demand v v v Steel Production

More information

Total Production by Month (Acre Feet)

Total Production by Month (Acre Feet) Production by Month (acre-feet) 2008 2009 2010 2011 2012 2013 2014 2015 2016 January 25 339.10 228.90 249.50 297.99 243.06 327.14 247.66 212.37 February 234.00 218.80 212.10 241.52 245.82 279.08 234.16

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 5842 Available on www.roymorgan.com Roy Morgan Unemployment Profile Thursday, 2 October 2014 Unemployment climbs to 9.9% in September as full-time work lowest since October 2011; 2.2 million

More information

Up and Down Months of the Stock Market

Up and Down Months of the Stock Market Up and Down Months of the Stock Market 1926-2017 Positive years (66) in the stock market were not good all year long and losing years (24) were not losers throughout the year. Winning years produce losing

More information

Residential Load Profiles

Residential Load Profiles Residential Load Profiles TABLE OF CONTENTS PAGE 1 BACKGROUND... 1 2 DATA COLLECTION AND ASSUMPTIONS... 1 3 ANALYSIS AND RESULTS... 2 3.1 Load Profiles... 2 3.2 Calculation of Monthly Electricity Bills...

More information

September 2016 Water Production & Consumption Data

September 2016 Water Production & Consumption Data September 2016 Water Production & Consumption Data September 2016 monthly water production (288.48 AF) was lowest in at least 17 years. Monthly water production has increased slightly each month since

More information

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015 PDR Energy Baseline Alternative Proposal for Discussion October 27, 2015 Update Since Last Meeting Since the October 12 th Working Group Meeting Stem, Solar City, AMS and CESA have had over a half-dozen

More information

NJ Solar Market Update As of 10/31/15

NJ Solar Market Update As of 10/31/15 NJ Solar Market Update As of 10/31/15 Prepared by Charlie Garrison Renewable Energy Committee Meeting November 10, 2015 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 10/31/15

More information

November 2017 Customer Switching Report for the Electricity and Gas Retail Markets

November 2017 Customer Switching Report for the Electricity and Gas Retail Markets An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities November 2017 Customer Switching Report for the Electricity and Gas Retail Markets Information Paper Reference: CRU18011 Date Published:

More information

EV - Smart Grid Integration. March 14, 2012

EV - Smart Grid Integration. March 14, 2012 EV - Smart Grid Integration March 14, 2012 If Thomas Edison were here today 1 Thomas Edison, circa 1910 with his Bailey Electric vehicle. ??? 2 EVs by the Numbers 3 10.6% of new vehicle sales expected

More information

MARKET RATES UPDATE Paula Gold-Williams Cory Kuchinsky

MARKET RATES UPDATE Paula Gold-Williams Cory Kuchinsky MARKET RATES UPDATE I N T R O D U C T I O N BY: Paula Gold-Williams President & Chief Executive Officer (CEO) P R E S E N T E D BY: Cory Kuchinsky Interim Vice President, Financial Services September 24,

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 7433 Available on www.roymorgan.com Roy Morgan Unemployment Profile Friday, 12 January 2018 2.6m Australians unemployed or under-employed in December The latest data for the Roy Morgan employment

More information

Storage in the energy market

Storage in the energy market Storage in the energy market Richard Green Energy Transitions 216, Trondheim 1 including The long-run impact of energy storage on prices and capacity Richard Green and Iain Staffell Imperial College Business

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 6928 Available on www.roymorgan.com Roy Morgan Unemployment Profile Wednesday, 17 August 2016 Australian real unemployment jumps to 10.5% (up 0.9%) in July during post-election uncertainty

More information

System Status Briefing

System Status Briefing System Status Briefing Phakamani Hadebe Interim Group Chief Executive 3 May 2018 Contents 1 Performance summary 2 Operational highlights 3 Generation performance 4 Distribution overview 5 Transmission

More information

Appendix E Water Supply Modeling

Appendix E Water Supply Modeling Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over

More information

ELECTRICITY TARIFFS 2013/2014

ELECTRICITY TARIFFS 2013/2014 ELECTRICITY TARIFFS 2013/2014 Presented by Cobus Kritzinger Leon Swanepoel Deputy Director Finance Head Electro Technical Services CONTENTS BACKROUND ELECTRICITY SALES BULK PURCHASES SALARY INCREASE TARIFF

More information

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys Irrigation energy efficiency How to analyse your energy costs Nick Bullock The Energy Guys March 2017 1 PILOT Energy Audits: Pivots AIM: data on energy use simple field data How energy efficient is system?

More information

January Manufacturing Technology Orders Off After a Strong December

January Manufacturing Technology Orders Off After a Strong December Contact: Bonnie Gurney, AMT, 703-827-5277 bgurney@amtonline.org For Release: March 9, 2015 January Manufacturing Technology Orders Off After a Strong December January U.S. manufacturing technology orders

More information

Electric Power Industry. Team XXXXX: Names of team members omitted on purpose

Electric Power Industry. Team XXXXX: Names of team members omitted on purpose Electric Power Industry Team XXXXX: Names of team members omitted on purpose Objectives Electricity quick Facts Brief History of Electricity in US Industry Analysis Firm Analysis: Georgia Power A Coal

More information

RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council

RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES January 10, 2011 Presentation to Arvada City Council CONSULTANT TEAM LBA Associates MSW Consultants Denver based recycling and waste management consultant

More information

November 2018 Customer Switching Report for the Electricity and Gas Retail Markets

November 2018 Customer Switching Report for the Electricity and Gas Retail Markets An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities November 2018 Customer Switching Report for the Electricity and Gas Retail Markets Information Paper Reference: CRU18266 Date Published:

More information

Dave Carroll Capital Markets Day Markets Update

Dave Carroll Capital Markets Day Markets Update Dave Carroll Capital Markets Day 2004 Markets Update Tomkins Operates in Diverse End Markets Breakdown 2003 Sales ( 3,150m, US$4,795m) Non-Residential Construction 11% Other 9% Automotive OE 27% Residential

More information

ELECTRIC VEHICLE MARKET UPDATE

ELECTRIC VEHICLE MARKET UPDATE 16TH ANNUAL ENERGY FORECASTING MEETING / EFG AUSTIN, TX APRIL 26-28, 2018 ELECTRIC VEHICLE MARKET UPDATE MIKE RUSSO, ITRON, INC. MONTHLY U.S. EV SALES Source: Monthly Plug-in Sales Scorecard, Inside EVs.

More information

ANCR CRU Statistics Februa.. to December 2007

ANCR CRU Statistics Februa.. to December 2007 ANCR CRU Statistics Februa.. to December 2007 Jan/07 Feb/07* Mar/07 Apr/07 May/07 Jun/07 Jul/07 Aug/07 Sep/07 Oct/07 Nov/07 Dec/07 Total notes Answered dato from Perimeter phone system unavailable prior

More information

TABLE C-43. Manufacturers' new and unfilled orders, {Amounts in millions of dollars] Nondurable. Capital goods. Total. goods.

TABLE C-43. Manufacturers' new and unfilled orders, {Amounts in millions of dollars] Nondurable. Capital goods. Total. goods. TABLE C-43. Manufacturers' new and unfilled orders, -74 {Amounts in millions of dollars] New orders t, I960. 27, 559 26, 903 30,672 30,115 31,086 33,005 35,322 37,952 41, 803 45, 944 46,763 50, 243 53,

More information

CVRP: Market Projections and Funding Needs

CVRP: Market Projections and Funding Needs CVRP: Market Projections and Funding Needs Public Workshop: Update to the 3-Year Plan for LDV & Transportation Equity Investments (4 Dec. 2018, El Monte CA) Brett Williams, PhD Senior Principal Advisor,

More information

Past Due. Account Charges. Contract Charges Security Deposit Due - Jun 09, , Customer Service. Jun 19, PAST DUE $1,693.

Past Due. Account Charges. Contract Charges Security Deposit Due - Jun 09, , Customer Service. Jun 19, PAST DUE $1,693. 11983978 Jun 19, 217 1 124 958 PAST DUE $1,693.97 Meter Reading Information Meter # 55271 May 3 655 Jun 15 6642 17 days 1397 on or about Aug 15 82 Past Due Balance payable includes an amount which is payable

More information

Growth cycles in Industrial production (IIP) (percentage deviation from trend*, seasonally adjusted) Sep 88 Sep 94. Dec 96. Mar 96

Growth cycles in Industrial production (IIP) (percentage deviation from trend*, seasonally adjusted) Sep 88 Sep 94. Dec 96. Mar 96 China The reference series The reference series used for constructing OECD Composite Leading (CLI) for China is the monthly index of industrial production (IIP). The IIP series starts in 1978, it is timely

More information

Balance from your previous bill $0.00 Meter # Basic Charge: 17 $ /day 3.23* Energy charge:¹ 2

Balance from your previous bill $0.00 Meter # Basic Charge: 17 $ /day 3.23* Energy charge:¹ 2 11983979 Jun 19, 217 1 124 962 Jul 11, 217 $24.34 Meter Reading Previous Bill. Balance from your previous bill $. Meter # 552711 May 3 19813 Account Account charge 12.4* Charges 17 days 82 Jun 15 19895

More information

Presented by Eric Englert Puget Sound Energy September 11, 2002

Presented by Eric Englert Puget Sound Energy September 11, 2002 Results from PSE s First Year of Time of Use Program Presented by Eric Englert Puget Sound Energy September 11, 2002 Puget Sound Energy Overview 973,489 Total Electric Customers 908,949 are AMR Capable

More information

Energy use in potato stores

Energy use in potato stores Energy use in potato stores Adrian Cunnington PCL Sutton Bridge Potato Council Energy Forum Huntingdon 11 February 2010 Storage costs Fixed (capital) costs Variable (running) costs Finance costs Potato

More information

2016 U.S. ETHANOL EXPORTS AND IMPORTS

2016 U.S. ETHANOL EXPORTS AND IMPORTS 2016 U.S. ETHANOL EXPORTS AND IMPORTS STATISTICAL SUMMARY Copyright 2017 Renewable Fuels Association. All Rights Reserved 2016 U.S. ETHANOL EXPORTS U.S. Ethanol Exports, 2006-2016 1,200 1,000 800 600 396

More information

State of the Industry: U.S. Classes 3-8 Used Trucks

State of the Industry: U.S. Classes 3-8 Used Trucks Americas Commercial Transportation Research Co., LLC www.actresearch.net State of the Industry: U.S. Classes 3-8 Used Trucks November 212 Data Published December 24, 212 State of the Industry: U.S. Classes

More information

FY H1 Financial Results

FY H1 Financial Results FY2011 1 H1 Financial Results November 8, 2010 1 Copyright(C) 2010 Isuzu Motors Limited All rights reserved Contents Ⅰ. President and Representative Director : Susumu Hosoi :FY2011 H1 Financial Summary

More information

Electric Vehicle Program

Electric Vehicle Program Cause No. 43960 INDIANAPOLIS POWER & LIGHT COMPANY Electric Vehicle Program Year 3 2013 Report May 2, 2014 Contents Background... 2 Project Objectives... 3 Current Status... 3 Significant Milestones...

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 Project Manager: Chris Hayes Advisor: Paul I-Hai Lin 1 BACKGROUND Kraft Foods 35 uction of Energy Costs Over The Next 5 Yrs. (2005

More information

Impact of Increasing Electric Mobility on a Distribution Grid at the Medium Voltage Level. Julia Vopava

Impact of Increasing Electric Mobility on a Distribution Grid at the Medium Voltage Level. Julia Vopava Impact of Increasing Electric Mobility on a Distribution Grid at the Medium Voltage Level Julia Vopava Agenda Introduction Methodology Cellular Approach Determining load profiles for charging stations

More information

Electricity Subsidy in Oman

Electricity Subsidy in Oman Electricity Subsidy in Oman Hassan Taqi Authority for Electricity Regulation, Oman GCCIA Conference Abu Dhabi, UAE 17 December, 2015 Presentation Outline Overview Regulatory challenge Market structure

More information

Ergon Energy s experience in meeting the challenges of increasing peak demand and customer expectation.

Ergon Energy s experience in meeting the challenges of increasing peak demand and customer expectation. Ergon Energy s experience in meeting the challenges of increasing peak demand and customer expectation. Smart Utilities 2012, Melbourne Glenn Walden GM Emerging Opportunities & Technology Development Ergon

More information

Analysis and/or Testing of Polices and Technologies: General Guidelines

Analysis and/or Testing of Polices and Technologies: General Guidelines Developing Integrated Emission Strategies for Existing Land Transport (DIESEL) Analysis and/or Testing of Polices and Technologies: General Guidelines Paul Procee World Bank Second Planning Meeting Bangkok,

More information

Energy Markets in Turmoil The Consumer Perspective

Energy Markets in Turmoil The Consumer Perspective Energy Markets in Turmoil The Consumer Perspective Sonny Popowsky Consumer Advocate of Pennsylvania Illinois State University Institute for Regulatory Policy Studies 63682 Springfield, IL May 17, 2001

More information

Cost Reflective Tariffs

Cost Reflective Tariffs Cost Reflective Tariffs for Large Government,Commercial and Industrial Customers Customer Guide Introduction On September 2016, the Council of Ministers had approved the introduction Cost of Reflective

More information

Price Category Breakdown - February 2010

Price Category Breakdown - February 2010 SINGLE FAMILY RESIDENTIAL BREAKDOWN ruary 21 ruary Sales and Average Price Increase Annually TORONTO - Wednesday, March 3, 21 7.3 % 24.6 % 1.8 % 7.3%.2%.1 % Greater Toronto REALTORS reported 7,291 sales

More information

Fuel Economy Policy Pathways for the ASEAN Region

Fuel Economy Policy Pathways for the ASEAN Region Fuel Economy Policy Pathways for the ASEAN Region Fuel economy standards in Asia Few Asian countries have fuel economy standards but growing over the years! Standards for passenger cars (LDV) are given

More information

Energy Performance Information Request Timeline

Energy Performance Information Request Timeline Energy Performance Information Request Timeline Project Title: UT Project # Project Manager: Submitted by: Day Submitted: The timeline below outlines a comprehensive list of required documents and when

More information

Cambodia. East Asia: Testing Times Ahead

Cambodia. East Asia: Testing Times Ahead Key Indicators Cambodia 68 East Asia: Testing Times Ahead 2002 2003 2004 2005 2006 2007 /e 2008 /p 2009 /p Year Year Year Year Year Year Year Year Real GDP (% change, previous year) 6.5 8.5 10.0 13.5 10.8

More information

[Title] Crop report - Pepper. China Spice Conference 1 November 2018 Wuxi, China

[Title] Crop report - Pepper. China Spice Conference 1 November 2018 Wuxi, China [Title] Crop report - Pepper [Date] Jos van Gulick China Spice Conference November 28 Wuxi, China US$ US$ / / MT MT US$ / MT Have we seen the bottom yet? 6, 6, 6, 4, 4, 4, Black pepper peaks at US$9,976/MT

More information

Australian Solar Cooling Interest Group (ausscig) Conference Queensland Solar City

Australian Solar Cooling Interest Group (ausscig) Conference Queensland Solar City Townsville: Queensland Solar City ausscig Conference 2011 1 The Townsville: Queensland Solar City project is part of the Australian Government Solar Cities program. Ergon Energy would like to acknowledge

More information

ENERGY SLIDESHOW. Federal Reserve Bank of Dallas

ENERGY SLIDESHOW. Federal Reserve Bank of Dallas ENERGY SLIDESHOW Updated: January 16, 2019 ENERGY PRICES www.dallasfed.org/research/energy Brent & WTI & Crude Brent Oil Crude Oil Dollars per barrel 140 120 100 Brent (Jan 11 = $58.64) WTI (Jan 11 = $50.78)

More information

Flexible Capacity Needs and Availability Assessment Hours Technical Study for 2020

Flexible Capacity Needs and Availability Assessment Hours Technical Study for 2020 Flexible Capacity Needs and Availability Assessment Hours Technical Study for 2020 Clyde Loutan Principal, Renewable Energy Integration Hong Zhou Market Development Analyst, Lead Amber Motley Manager,

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE Article No. 7137 Available on www.roymorgan.com Roy Morgan Unemployment Profile Wednesday, 8 February 2017 Over 12 million Australians have jobs for the first time including over 8 million full-time jobs,

More information

TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies. Gerald Johns, P.E. Power Utilization Engineer, TVA

TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies. Gerald Johns, P.E. Power Utilization Engineer, TVA TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies Gerald Johns, P.E. Power Utilization Engineer, TVA 1 TVA Comprehensive Services Power Factor Studies/Recommendations

More information

increase of over four per cent compared to the average of $409,058 reported in January 2010.

increase of over four per cent compared to the average of $409,058 reported in January 2010. SINGLE FAMILY RESIDENTIAL BREAKDOWN uary 211 26.8 % 1.7 % 7.%.4%.1 % Good Start to 211 TORONTO - February 4, 211 Greater Toronto REALTORS reported 4,337 transactions through the TorontoMLS system in uary

More information

Solar photovoltaic research: Drakenstein Municipality

Solar photovoltaic research: Drakenstein Municipality Rooftop Solar PV Solar photovoltaic research: Drakenstein Municipality Karin Kritzinger and Imke Meyer, Date 22/04/2015 Dialogue on Utility and Local Scale Renewable Energy in South Africa 22 April 2015-1

More information

U.S. manufacturing technology orders kick off 2018 on a high note

U.S. manufacturing technology orders kick off 2018 on a high note Contact: Penny Brown, AMT, 703-827-5275 pbrown@amtonline.org For Release: March 12th, 2018 U.S. manufacturing technology orders kick off 2018 on a high note Orders for manufacturing technology in January

More information

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng Smarter Network Storage UK first multi-purpose application of grid scale storage Dr. Panos Papadopoulos, PhD, CEng UK Power Networks GENERATION TRANSMISSION DISTRIBUTION SUPPLY INDUSTRIAL COMMERCIAL RESIDENTIAL

More information

October 23, September year. in 1Q confidence in our. exacerbated by the. 0.3 percent. outpu. (over) Index of Sales. Mar 12.

October 23, September year. in 1Q confidence in our. exacerbated by the. 0.3 percent. outpu. (over) Index of Sales. Mar 12. October 23, 20122 REPORT ON BUSINESSS TRENDS September 20122 Industry Performance Reverts to Pace off GDP in Broad Economy Index of Sales September 2011 - September 2012 140 130 125 127 125 120 114 117

More information

May ATR Monthly Report

May ATR Monthly Report May ATR Monthly Report Minnesota Department of Transportation Office of Transportation Data and Analysis May 2011 Introduction The purpose of this report is to examine monthly traffic trends on Minnesota

More information

GROWTH IN TENTH DISTRICT MANUFACTURING WAS SLIGHTLY POSITIVE Federal Reserve Bank of Kansas City Releases February Manufacturing Survey

GROWTH IN TENTH DISTRICT MANUFACTURING WAS SLIGHTLY POSITIVE Federal Reserve Bank of Kansas City Releases February Manufacturing Survey FOR RELEASE Thursday, February 27, 2014 EMBARGOED FOR 10 A.M. CENTRAL TIME CONTACT: Pam Campbell 405-270-8617 Pam.Campbell@kc.frb.org GROWTH IN TENTH DISTRICT MANUFACTURING WAS SLIGHTLY POSITIVE Federal

More information

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL Project Manager: Chris Hayes BACKGROUND Kraft Foods 35 Reduction of Energy Costs Over The Next 5 Yrs. (5 Benchmark) Kraft Foods Financial Model

More information

Monthly Operating Report. February 2018

Monthly Operating Report. February 2018 Monthly Operating Report February 2018 February overview» For the month of February 2018 Contact recorded: Electricity and gas sales of 534 GWh (February 20: 551 GWh) Netback of $82.16/MWh (February 20:

More information

ELECTRICITY GENERATION AND DISTRIBUTION. Electricity Generation & Distribution Q2,

ELECTRICITY GENERATION AND DISTRIBUTION. Electricity Generation & Distribution Q2, Contact Statistician: Otsile Chelenyane Industry Statistics Unit Email: ochelenyane@statsbots.org.bw Tel: (+267) 367 1300; Ext. 333 ELECTRICITY GENERATION AND DISTRIBUTION Stats Brief, Quarter 2, 2018

More information

Massachusetts Electric Company and Nantucket Electric Company, Docket No. D.T.E

Massachusetts Electric Company and Nantucket Electric Company, Docket No. D.T.E Amy G. Rabinowitz Counsel April 3, 2003 By Hand Mary L. Cottrell, Secretary Department of Telecommunications and Energy One South Station, 2 nd Floor Boston, MA 02110 Re: Massachusetts Electric Company

More information

Factory activity accelerated further in our region this month, posting its highest composite reading since 2011, said Wilkerson.

Factory activity accelerated further in our region this month, posting its highest composite reading since 2011, said Wilkerson. FOR RELEASE Thursday, October 26, 17 EMBARGOED FOR A.M. CENTRAL TIME CONTACT: Pam Campbell 45-27-8617 Pam.Campbell@kc.frb.org TENTH DISTRICT MANUFACTURING ACTIVITY POSTS STRONG GROWTH Federal Reserve Bank

More information

The Electric Power System

The Electric Power System The Electric Power System - Thailand - Thailand Power System 1 Basic facts Area: 513,000 km 2 (198,000 sq mi), Population: 65,931,550 (2016) Number of electricity consumers (2016): 22.5 million households

More information

Growth cycles in Industrial production (IIP) (percentage deviation from trend*, seasonally adjusted) Jan-00 Aug-06 Sep-94. Dec-01.

Growth cycles in Industrial production (IIP) (percentage deviation from trend*, seasonally adjusted) Jan-00 Aug-06 Sep-94. Dec-01. Chile The reference series The reference series used for constructing OECD Composite ing Indicator (CLI) for Chile is the index of production in total manufacturing, which is a proxy for the monthly index

More information

GAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case

GAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case Overview A consensus forecast is used to estimate the prime rate charged by commercial banks. As the prime rate is subject to competitive pressures faced by individual lenders and is set on an individual

More information

Overview of Global Fuel Economy Policies

Overview of Global Fuel Economy Policies Overview of Global Fuel Economy Policies Zifei Yang Researcher 2018 APCAP Joint Forum and Clean Air Week Theme: Solutions Landscape for Clean Air Bangkok, Mar 20, 2018 What is ICCT? ICCT is an independent

More information

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance Ahmed R. Abul'Wafa 1, Aboul Fotouh El Garably 2, and Wael Abdelfattah 2 1 Faculty of Engineering, Ain

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

40KW Solar System for Apple Sauce Co

40KW Solar System for Apple Sauce Co 2012 40KW Solar System for Apple Sauce Co Document Created for The Apple Sauce Co by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L For further details please contact Luke M Hardy SunUp Solar Pty

More information

NEWS Release. U.S. Manufacturing Technology Orders. Year-to-date U.S. manufacturing technology orders up 4.1% over 2011

NEWS Release. U.S. Manufacturing Technology Orders. Year-to-date U.S. manufacturing technology orders up 4.1% over 2011 U.S. Manufacturing Technology Orders A statistical program of AMT NEWS Release FOR RELEASE: October 8, 2012 Contact: Pat McGibbon, AMT, 703-827-5255 Year-to-date U.S. manufacturing technology orders up

More information

ENERGY SLIDESHOW. Federal Reserve Bank of Dallas

ENERGY SLIDESHOW. Federal Reserve Bank of Dallas ENERGY SLIDESHOW Updated: March 13, 2018 ENERGY PRICES www.dallasfed.org/research/energy Brent & WTI & Crude Brent Oil Crude Oil Dollars per barrel 140 Brent (Mar 9 = $65.12) WTI (Mar 9 = $61.65) 120 100

More information

STEEL IMPORTS UP 15% IN 2017 Finished Import Market Share Increased to 27%

STEEL IMPORTS UP 15% IN 2017 Finished Import Market Share Increased to 27% News Release FOR IMMEDIATE RELEASE January 26, 2018 CONTACT Lisa Harrison 202.452.7115/lharrison@steel.org STEEL IMPORTS UP 15% IN 2017 Finished Import Market Share Increased to 27% Washington, D.C. Based

More information

COMPILED BY GLASS S. Auction Report - LCV November 2013

COMPILED BY GLASS S. Auction Report - LCV November 2013 GLASS S Auction Report - LCV November 2013 Contents Market Commentary Page 3 Whole Market Summary Page 8 Average Sales Price Year on Year Page 9 Sales Price Compared to Number of Entries (all ages) Page

More information

Progress and Challenges in Philippine Energy Sector Reform

Progress and Challenges in Philippine Energy Sector Reform Progress and Challenges in Philippine Energy Sector Reform A Presentation by: Lily Gutierrez Energy Policy Advisor Office of Energy and Environment Infrastructure for Rebuilding and Developing Countries

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Electric Vehicles: Opportunities and Challenges

Electric Vehicles: Opportunities and Challenges Electric Vehicles: Opportunities and Challenges Henry Lee and Alex Clark HKS Energy Policy Seminar Nov. 13, 2017 11/13/2017 HKS Energy Policy Seminar 1 Introduction In 2011, Grant Lovellette and I wrote

More information

December. Next release: 13 February Oct/Sep Nov/Oct Dec/Nov Janu19 January Febru13 February 2018 Oct/Sep Nov/Oct Dec/Nov 2017

December. Next release: 13 February Oct/Sep Nov/Oct Dec/Nov Janu19 January Febru13 February 2018 Oct/Sep Nov/Oct Dec/Nov 2017 Oct/Sep Nov/Oct Dec/Nov 2017 19 Janu19 January 2018 13 Febru13 February 2018 Oct/Sep Nov/Oct Dec/Nov 2017 Next release: 13 February 2018 DecembDecember December TABLE OF CONTENTS Page Charts 1 Latest IEA

More information

STATISTICS BOTSWANA ELECTRICITY GENERATION & DISTRIBUTION 2016/2 STATS BRIEF, FIRST QUARTER Copyrights Statistics Botswana 2016

STATISTICS BOTSWANA ELECTRICITY GENERATION & DISTRIBUTION 2016/2 STATS BRIEF, FIRST QUARTER Copyrights Statistics Botswana 2016 2016/2 ELECTRICITY GENERATION & DISTRIBUTION STATS BRIEF, FIRST QUARTER 2016 Copyrights Statistics Botswana 2016 Statistics Botswana. Private Bag 0024 Botswana Tel: (267) 367 1300. Fax: (267) 395 2201.

More information