Nogales Transmission, L.L.C. and Nogales Frontier Operations, L.L.C., Docket No. EL Second Supplement to Petition for Declaratory Order

Size: px
Start display at page:

Download "Nogales Transmission, L.L.C. and Nogales Frontier Operations, L.L.C., Docket No. EL Second Supplement to Petition for Declaratory Order"

Transcription

1 Eversheds Sutherland (US) LLP 700 Sixth reet,, Suite 700 ashington, DC D: F: eversheds-sutherland.com June 30, 2017 Via Electronic Filing Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First.,.E. ashington, DC Re: ogales Transmission, L.L.C. and ogales Frontier Operations, L.L.C., Docket o. EL Second Supplement to Petition for Declaratory Order Dear Ms. Bose: ogales Transmission, L.L.C. ( ogales Transmission ) and ogales Frontier Operations, L.L.C. ( ogales Operations ) (collectively Applicants ) hereby provide this second supplement to their December 21, 2016 Petition for Declaratory Order ( Petition ) to reflect a recent electrical reconfiguration of the Project s interconnection with the US Electric, Inc. ( USE ) grid. This reconfiguration is not material to the relief requested in the Petition, but Applicants are providing this information to ensure the accuracy of the technical information contained in the Petition. I. Purpose of the Reconfiguration The purpose of the electrical reconfiguration is to make the Project more costeffective. Specifically, a detailed engineering analysis conducted by USE as part of the Project interconnection study determined that USE would avoid approximately $11 million in costs if the Project connected to its transmission system from the Gateway Substation rather than, as originally proposed, USE s Valencia Substation. That engineering analysis determined that the Valencia Substation could not accommodate an additional circuit, and connecting the Project there would require a complete rebuild of the Valencia Substation on a larger footprint. The cost for this rebuild would be approximately $15 million. In contrast, terminating the existing USE transmission line at the Gateway Substation would require additional facilities that would cost approximately $4 million but would avoid the need for a rebuild of the Valencia Substation. II. Description of the Reconfiguration Conceptually, the new configuration connects the Project to the USE system at the planned Gateway Substation rather than, as originally proposed, at the existing Valencia Eversheds Sutherland (US) LLP is part of a global legal practice, operating through various separate and distinct legal entities, under Eversheds Sutherland. For a full description of the structure and a list of offices, please visit

2 Hon. Kimberly D. Bose June 30, 2017 Page 2 Substation. That connection will be accomplished by severing the existing USE Vail-to- Valencia 138-kV transmission line and connecting it to one circuit of a new, approximately 3-mile long, overhead double-circuit 138-kV line, to be constructed and owned by USE. This circuit will originate at an existing pole 1,900 feet west of the existing Valencia Substation and terminate at the new Gateway Substation, thereby converting the existing Vail-to-Valencia transmission line to a new Vail to Gateway transmission line. The second circuit will originate at the Gateway Substation and proceed in an easterly direction, utilizing the other side of the new double-circuit 138-kV line, to a pole 1,900 feet west of the existing Valencia Substation, where it will connect with the existing portion of the USE 138-kV transmission line that travels east to the Valencia Substation. This circuit will constitute the new Gateway to Valencia transmission line. The reconfiguration is shown on the map included as Attachment 1. The reconfiguration does not change the proposed Project route or right-of-way requirements, and as compared to the original configuration would have equal or better reliability. III. Conclusion The updated electrical configuration contained in this Second Supplement is provided to ensure the continued accuracy of the technical information provided in the Application. Please contact us should you have any additional questions or need additional information. Respectfully submitted, /s/ Daniel E. Frank James M. Bushee Daniel E. Frank Counsel for ogales Transmission, L.L.C. and ogales Frontier Operations, L.L.C.

3 Attachment 1 Map of Project Reconfiguration

4 Dr Ave Jose Gallego Dr MariposaRanch Frank Reed Paul Bond Dr Shell Loop Mariposa Mastick ay VALECIA SUBSTATIO Ln Smokey E Cll Sonora OPTIO 3 MAY, 2017 OGALES ITERCOECTIO!( PROPOSED GATEAY SUBSTATIO AB 189 Bell Manor Dr Industrial Park Dr Grand Ave! Phoenix! Tucson PATH: \\MSPE-GIS-FILE\GISPROJ\HUT\244842\MAP_DOCS\DRAFT\DOE\OPTIO3_11X17L.MXD - USER: STUOHEY - DATE: 5/31/2017 Target Range Freeport Mariposa Mariposa Cam la Quinta de Mariposa lapaloma Vista Dr Linda Industrial Park Cll Canada Quinta Cimarron Canada Target Range Target Range U n i t e d S t a t e s M e x i c o 19 estern Ave Macnab Dr Anthony Dr alnut oon Crawford Curtis est International Hughes Elm Kelsey Ave estern Pl Dr Highland Plum Oak Terrace Ave Grand Ave Loma Quarry estern Ave Hwy Blvd Arroyo Tucson-ogales elson Ave Cam del Pajarito Smelter Sonoita Ave Grand Court ;=19 Plz E Court E East Anza Dr Sage Ellis Sol EscaladaDr Martinez 2nd Burk 2nd Kolver E Beck 1st First Kino Potrero Ave E Hudgins Grand Ave Morley Ave 3rd E Adams E International Tucson-ogales Hwy Hohokam Dr Tyler Perkins E Edward Perkins Ave Bankerd Ave E Grant!( Origination Point Substation Site 230 kv Route Alternative 138 kv Double Circuit Route Alternative Existing UniSource Energy Services Vail to Valencia 138 kv Access Road International Border Interstate / US / ate Highway Other Road Coronado ational Forest OTES: 1.. TARGET RAGE RD IS A PUBLIC ROAD AD CA BE SURVEYED. 2. EXISTIG EASEMETS CA BE SURVEYED BY RIGHT OF EASEMET. O 0 Miles 0.5

5 Certificate of Service I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at ashington, DC this 30th day of June, /s/ Daniel E. Frank Daniel E. Frank

Re: California Independent System Operator Corporation

Re: California Independent System Operator Corporation California Independent System Operator October 21, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION The Nevada Hydro Company, Inc. Docket No. EL18-131-000 SOUTHERN CALIFORNIA EDISON COMPANY'S COMMENTS AND PROTEST TO THE NEVADA HYDRO

More information

April 6, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

April 6, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 414 Nicollet Mall Minneapolis, MN 55401 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 RE: Public Service Company of Colorado Docket

More information

February 13, Docket No. ER ; ER Response to Request for Additional Information

February 13, Docket No. ER ; ER Response to Request for Additional Information California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

September 2, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

September 2, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. TEXAS EASTERN TRANSMISSION, LP Mailing Address: 5400 Westheimer Court P. O. Box 1642 Houston, TX 77056-5310 Houston, TX 77251-1642 713.627.5400 main Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Salt River Project Agricultural ) Improvement and Sacramento ) Municipal Utility District ) ) Docket No. EL01-37-000 v. ) ) California

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

October 1, Docket: ER Energy Imbalance Market Special Report Transition Period June 2018 for Powerex Corp.

October 1, Docket: ER Energy Imbalance Market Special Report Transition Period June 2018 for Powerex Corp. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 October 1, 2018 Re: California

More information

Designated Entity Pre-Qualification Materials. Exelon Corporation

Designated Entity Pre-Qualification Materials. Exelon Corporation Designated Entity Pre-Qualification Materials By Exelon Corporation On behalf of its affiliates Baltimore Gas and Electric Company, Commonwealth Edison Company, PECO Energy Company and Exelon Transmission

More information

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES EXHIBIT JC-2 BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE OCEANVIEW

More information

July 24, Docket No EI FPL s Petition for Approval of a New Depreciation Class and Rate for Energy Storage Equipment

July 24, Docket No EI FPL s Petition for Approval of a New Depreciation Class and Rate for Energy Storage Equipment John T. Butler Assistant General Counsel-Regulatory Florida Power & Light Company 700 Universe Boulevard Juno Beach, FL 33408-0420 (561) 304-5639 (561) 691-7135 (Facsimile) John.Butler@fpl.com July 24,

More information

Docket No. ER June 2018 Informational Report Energy Imbalance Market Transition Period Report Idaho Power Company

Docket No. ER June 2018 Informational Report Energy Imbalance Market Transition Period Report Idaho Power Company California Independent System Operator Corporation August 21, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO. Direct Testimony and Schedules Grant Stevenson STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION FOR A ROUTE PERMIT FOR THE PLEASANT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Regional Reliability Standards ) VAR-002-WECC-2 and VAR-501-WECC-2 ) Docket No. RD15-1-000 COMMENTS OF DOMINION RESOURCES SERVICES,

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2014) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 10, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

March 14, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

March 14, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 March 14, 2017 Re: California

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Ms. Kristine Schmidt ITC Great Plains, LLC 3500 SW Fairlawn Road Topeka, KS 66614 RE: Notification to Construct Approved Priority Projects Dear Ms. Schmidt,

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0 SouthWestern

More information

December 4, Docket: ER Energy Imbalance Market Special Report Transition Period July 2018 for Idaho Power Company

December 4, Docket: ER Energy Imbalance Market Special Report Transition Period July 2018 for Idaho Power Company California Independent System Operator Corporation December 4, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 August 15, 2017 Re: California

More information

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 07-071 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Petition for License to Construct and Maintain Electric Lines and a Fiber Optic Communications Cable

More information

September 9, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E., Room 1A Washington, DC 20426

September 9, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E., Room 1A Washington, DC 20426 Mark D. Patrizio Attorney at Law 77 Beale Street, B30A San Francisco, CA 94105 Mailing Address P.O. Box 7442 San Francisco, CA 94120 (415) 973.6344 Fax: (415) 973.5520 E-Mail: MDP5@pge.com September 9,

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

What is the Peninsula Corridor Electrification Project (PCEP)?

What is the Peninsula Corridor Electrification Project (PCEP)? What is the Peninsula Corridor Electrification Project (PCEP)? Project Purpose and Need Improve Train Performance Increase Service and Ridership Increase Revenue and Reduce Cost Reduce Environmental Impacts

More information

August 1, Amended Attachment S under Southern Companies Open Access Transmission Tariff, effective January 1, 2014

August 1, Amended Attachment S under Southern Companies Open Access Transmission Tariff, effective January 1, 2014 August 1, 2014 Ms. Kimberly D. Bose, Secretary Mr. Nathaniel J. Davis, Jr., Deputy Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Amended Attachment S under

More information

~ p bl' S E. S 4,781 (ADA ComQiiance Program) $ 32,006 TOTAL $119,100 (Meadowbrook Rd Pathway) $108,600 (Taft Rd Pathway)

~ p bl' S E. S 4,781 (ADA ComQiiance Program) $ 32,006 TOTAL $119,100 (Meadowbrook Rd Pathway) $108,600 (Taft Rd Pathway) CITY of NOVI CITY COUNCIL Agenda Item K August 27, 2012 SUBJECT: Approval to award an amendment to the engineering services agreement with Spalding DeDecker Associates, Inc. related to the 2012 Pathway

More information

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period August 2018 for Idaho Power Company

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period August 2018 for Idaho Power Company California Independent System Operator Corporation January 18, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Great Oaks Water Company (U-162-W for an Order establishing its authorized cost of capital for the period from July 1, 2019

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Requirements for Frequency and Voltage Ride Through Capability of Small Generating Facilities Docket No. RM16-8-000 COMMENTS OF

More information

ATLANTA CLEVELAND DAYTON WASHINGTON, D.C. CINCINNATI

ATLANTA CLEVELAND DAYTON WASHINGTON, D.C. CINCINNATI HOMPSON LINE ATLANTA CLEVELAND DAYTON WASHINGTON, D.C. CINCINNATI COLUMBUS NEW YORK Via Electronic Filing Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. At a session of the Public Service Commission held in the City of Albany on June 26, 2014

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. At a session of the Public Service Commission held in the City of Albany on June 26, 2014 COMMISSIONERS PRESENT: Audrey Zibelman, Chair Patricia L. Acampora Garry A. Brown Gregg C. Sayre Diane X. Burman STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission

More information

Arizona-Sonora Border Master Plan. Plan Maestro para la Frontera Arizona-Sonora

Arizona-Sonora Border Master Plan. Plan Maestro para la Frontera Arizona-Sonora Arizona-Sonora Border Master Plan Plan Maestro para la Frontera Arizona-Sonora Project Objectives Develop and implement a plan for identifying, prioritizing, and promoting land port of entry (LPOE), multi-modal

More information

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT Supplemental Municipal Consultation Filing The Interstate Reliability Project 1. DESCRIPTION OF THE PROPOSED PROJECT The Connecticut Light and Power Company

More information

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period September 2018 for Idaho Power Company

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period September 2018 for Idaho Power Company California Independent System Operator Corporation January 18, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

FOR SALE OR FOR LEASE SALE PRICE: $2,000, & 2950 Garnet Avenue

FOR SALE OR FOR LEASE SALE PRICE: $2,000, & 2950 Garnet Avenue FOR SALE OR FOR LEASE SALE PRICE: $2,000,000 2946 & 2950 Garnet Avenue 6165 GREENWICH DRIVE, SUITE 110 SAN DIEGO, CA 92122 619.280.2600 FLOCKEAVOYER.COM *DISCLAIMERS The Opportunity 2946 & 2950 Garnet

More information

Pacific Gas and Electric Company TM

Pacific Gas and Electric Company TM Pacific Gas and Electric Company TM Evelyn C. Lee Mailing Address P.O. Box 7442 San Francisco, CA 94120 Street/Courier Address Law Department 77 Beale Street San Francisco, CA 94105 (415) 973-2786 Fax:

More information

STATE OF NEW HAMPSHIRE Inter-Department Communication

STATE OF NEW HAMPSHIRE Inter-Department Communication STATE OF NEW HAMPSHIRE Inter-Department Communication DATE: February 11, 2010 AT (OFFICE): NHPUC FROM: Torn Frantz Director, Electric Division SUBJECT: DE 09-277: Petition by Public Service Company of

More information

Re: Application for Approval of Route Permit Amendment, Spans 89-93, 95-97, and

Re: Application for Approval of Route Permit Amendment, Spans 89-93, 95-97, and January 11, 2011 VIA ELECTRONIC FILING and U.S. MAIL Dr. Burl W. Haar Executive Secretary Minnesota Public Utilities Commission 350 Metro Square Building 121 Seventh Place East St. Paul, MN 55101 Dear

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Plan and Profile for the Black Dog Natural Gas Pipeline Project Docket No. G002/GP

Plan and Profile for the Black Dog Natural Gas Pipeline Project Docket No. G002/GP 414 Nicollet Mall Minneapolis, MN 55401 March 13, 2017 Daniel P. Wolf Executive Secretary Minnesota Public Utilities Commission 121 7 th Place East, Suite 350 St. Paul, MN 55101 Via Electronic Filing RE:

More information

BILLING CODE P DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM ]

BILLING CODE P DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM ] This document is scheduled to be published in the Federal Register on 03/29/2013 and available online at http://federalregister.gov/a/2013-06820, and on FDsys.gov BILLING CODE 6717-01-P DEPARTMENT OF ENERGY

More information

Included in this Stakeholder Information Package:

Included in this Stakeholder Information Package: Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink

More information

November 16, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

November 16, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. November 16, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ANR Pipeline Company 717 Texas Street, Suite 2400 Houston, Texas 77002-2761

More information

: : : : : : : Commonwealth Edison Company ( ComEd ), pursuant to Section of the Public

: : : : : : : Commonwealth Edison Company ( ComEd ), pursuant to Section of the Public STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION Commonwealth Edison Company Verified Petition for approval of Rider POGCS Parallel Operation of Retail Customer Generating Facilities Community Supply and

More information

RE: January 9, Electronic Service Only. Marc Weintraub, Esq. Counsel, Applicants Bailey & Glasser, LLP 209 Capitol Street Charleston, WV 25301

RE: January 9, Electronic Service Only. Marc Weintraub, Esq. Counsel, Applicants Bailey & Glasser, LLP 209 Capitol Street Charleston, WV 25301 c IC 201 Brooks Street, P.O. Box 812 Phone: (304) 340-0300 Charleston, West Virginia 25323 Fax: (304) 340-0325 Electronic Service Only Marc Weintraub, Esq. Counsel, Applicants Bailey & Glasser, LLP 209

More information

DEPARTMENT OF TRANSPORTATION. National Highway Traffic Safety Administration. [Docket No. NHTSA ; Notice 2]

DEPARTMENT OF TRANSPORTATION. National Highway Traffic Safety Administration. [Docket No. NHTSA ; Notice 2] This document is scheduled to be published in the Federal Register on 08/14/2014 and available online at http://federalregister.gov/a/2014-19190, and on FDsys.gov DEPARTMENT OF TRANSPORTATION National

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects

More information

Regular Meeting and Public Hearing of the Zoning Subcommittee

Regular Meeting and Public Hearing of the Zoning Subcommittee Regular Meeting and Public Hearing of the Zoning Subcommittee Tuesday, October 02, 2018 7:00 PM Council Chambers, City Hall, 2nd Floor, 27 West Main Street, New Britain, Connecticut NOTICE - The Common

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

PUBLIC REDACTED VERSION

PUBLIC REDACTED VERSION PUBLIC REDACTED VERSION BEFORE THE MARYLAND PUBLIC SERVICE COMMISSION CASE NO. 9208 IN THE MATTER OF BALTIMORE GAS AND ELECTRIC COMPANY FOR AUTHORIZATION TO DEPLOY A SMART GRID INITIATIVE AND TO ESTABLISH

More information

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report 260 TO: FROM: SUBJECT: ECAC Members Jamie Asbury, deputy energy manager, Business/Regulatory Five (5) Generator Interconnection

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Supply Margin Assessment (SMA) test announced in the SMA Order 2 with

Supply Margin Assessment (SMA) test announced in the SMA Order 2 with . UNITED STATE OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Duke Energy Marketing America, LLC ) Motion to Intervene and Comments of the California Independent System Operator Corporation

More information

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 October 17, 2017 Re: California

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER A19 ADMINISTRATIVE REPORT Report Date: July 10, 2007 Author: Chris Darwent Phone No.: 604.873.7358 RTS No.: 6866 VanRIMS No.: 13-1400-20 Meeting Date: July 24, 2007 TO: FROM: SUBJECT:

More information

Directions to Grand Lake, CO 625 mi about 13 hours 10 mins. Loading... 1 of 5 2/13/09 8:26 AM

Directions to Grand Lake, CO 625 mi about 13 hours 10 mins. Loading... 1 of 5 2/13/09 8:26 AM Directions to Grand Lake, CO 625 mi about 13 hours 10 mins Loading... 1 of 5 2/13/09 8:26 AM Yellowstone East Entrance 1. Head east on E Entrance Rd/US-14/US-16/US-20 Continue to follow US-14/US-16/US-20

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (OCTOBER 2016) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

II pepco. February 6, 2018

II pepco. February 6, 2018 Wendy E. Stark Office 202.872.2347 Deputy General Counsel Fax 202.331.6767 pepco.com EP1006 westark@pepcoholdings.com 70 1 Ninth Street NW Washington, DC 20068-0001 II pepco. An Exelon Company February

More information

RETAIL DELIVERY Q1 2017

RETAIL DELIVERY Q1 2017 RETAIL DELIVERY Q1 2017 A MEETING OF MINDS AND MAKERS One Hundred Hooper is a LEED Gold Certified, Class A, mixed-use commercial project offering THE SQUARE ~400,000 rentable square feet of office, workshops

More information

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909 Amy C. Monopoli Counsel Regulatory & Legislative Phone: 774-452-4227 amonopoli@itctransco.com May 11, 2017 Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5 ALANNA GILLIS ACTING COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660 4700 BC TOLL

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

AUSLEY MCMULLEN ATTORNEYS AND COUNSELORS AT LAW 123 SOUTH CALHOUN STREET. P.O. BOX 391 (ztp 32302) TALLAHASSEE, FLORIDA 32301

AUSLEY MCMULLEN ATTORNEYS AND COUNSELORS AT LAW 123 SOUTH CALHOUN STREET. P.O. BOX 391 (ztp 32302) TALLAHASSEE, FLORIDA 32301 AUSLEY MCMULLEN ATTORNEYS AND COUNSELORS AT LAW 123 SOUTH CALHOUN STREET P.O. BOX 391 (ztp 32302) TALLAHASSEE, FLORIDA 32301 (850) 224 9 115 FAX 18501 222 7560 August 25, 201 7 VIA: ELECTRONIC FILING Ms.

More information

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009 State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Directions to Estes Park, CO 1,242 mi about 20 hours 56 mins. Loading... 1 of 8 2/13/09 9:21 AM

Directions to Estes Park, CO 1,242 mi about 20 hours 56 mins. Loading... 1 of 8 2/13/09 9:21 AM Directions to Estes Park, CO 1,242 mi about 20 hours 56 mins Loading... 1 of 8 2/13/09 9:21 AM Phoenix, AZ 1. Head north on N Central Ave toward E Adams St go 0.2 mi total 0.2 mi 2. Turn right at E Van

More information

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION THE CITIZENS UTILITY BOARD ) and ) THE ENVIRONMENTAL DEFENSE FUND ) ) Docket No. 14- Proceeding to Adopt a GHG Metric for ) Smart Grid Advanced Metering Infrastructure

More information

Plan Check Policies and Guidelines

Plan Check Policies and Guidelines VIII. TRAFFIC SIGNING AND STRIPING PLANS A. INTRODUCTION Traffic signing and striping plans are required for all General Plan Roads and any roadway that is 56-foot wide curb-to-curb (78 R/W) or wider.

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

The Green Line Project

The Green Line Project The Green Line Project Presentation to the ISO-NE Planning Advisory Committee New England Independent Transmission Company, LLC December 18, 2007 1 500 kv DC transmission system with transfer capability

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

JCP&L Verbatim Response to Middletown Township s Questions

JCP&L Verbatim Response to Middletown Township s Questions JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 07-097 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Petition for Adjustment of Stranded Cost Recovery Charge Order Following Hearing O R D E R N O. 24,872

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Concerning Energy Efficiency Rolling Portfolios, Policies, Programs, Evaluation, and Related Issues. R.13-11-005

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

GATTIS SCHOOL RD / SH 130 SUBDIVISION

GATTIS SCHOOL RD / SH 130 SUBDIVISION AMISTAD DR MEADOWILD DR NO. DESCRIPTION INDEX ROYAL BURGESS DR. E NAKOMA SITE SH 130 CITY LIMITS LITTLE LAKE RD KAATZ LN ESTATE DR DANA DR MARJORIE DR 1 COVER 2 PRELIMINARY PLAT 3 EXISTING CONDITIONS 4

More information

Proposed Program of Interrelated Projects

Proposed Program of Interrelated Projects DALLAS AREA RAPID TRANSIT Proposed Program of Interrelated Projects Federal Transit Administration Capital Investment Program Summer 204 INTRODUCTION The current federal transportation bill, Moving Ahead

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP January 29, 2014 201 South Main, Suite 2300 Salt Lake City, Utah 84111 VIA ELECTROl.fiC FILI1VG AND OVERNIGHT DELIVERY Wyoming Public Service Commission 2515

More information

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Noe Bargas, PE Supervising Senior Civil Engineer Southern

More information

SOUTHWEST CALGARY RING ROAD (SWCRR)

SOUTHWEST CALGARY RING ROAD (SWCRR) PROJECT OVERVIEW Alberta Transportation has started planning for the construction of the SW portion of the road that will complete the Calgary Ring Road. The completion of the SWCRR requires the relocation

More information

Danger CAUTION - RR tracks (2 sets) Food SERVICES - Quik Mart on left

Danger CAUTION - RR tracks (2 sets) Food SERVICES - Quik Mart on left Dist Day Leg PAC TOUR 600k Dist (km) Type Instruction ORGANIZER - Susan Notorangelo - (612) 804-9970 START - TUCSON 0.0 0.0 0.0 Country Inn and Suites - 6681 South Tucson Boulevard, Tucson, AZ 85756-0.0

More information

best to you all Gail Carbiener Page 1 of 5

best to you all Gail Carbiener Page 1 of 5 Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page

More information

East Avenue and Queen City Substation Improvement Project

East Avenue and Queen City Substation Improvement Project East Avenue & Queen City Substation Improvement Project VIA FIRST CLASS MAIL August 29, 2017 Judith C. Whitney, Clerk Vermont Public Utility Commission 112 State Street, 4 th Floor Montpelier, VT 05620-2701

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the 9 th Annual Transmission Summit West October 13, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT OCTOBER 13, 2017 0 SouthWestern Power Group

More information

Addendum StartPage: 0

Addendum StartPage: 0 Control Number : 42698 Item Number : 2 Addendum StartPage: 0 ^20x de.i^ WA OCI solar power November 4, 2015 -;, - L Li { Sent via Overnight UPS Delivery Public Utility Commission of Texas 1701 N. Congress

More information

M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD

M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: FROM: Commissioners Brown, Carlson, Mital, Simpson and Helgeson Rod Price, Chief Electric Engineering & Operations Officer, Tony McCallum, Line Crew

More information

Plan Check Policies and Guidelines

Plan Check Policies and Guidelines Plan Check Policies and Guidelines VII. A. INTRODUCTION Traffic signing and striping plans are required for all General Plan Roads and any roadway that is 56-foot wide curb-to-curb (78 R/W) or wider. Transportation

More information