Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

Size: px
Start display at page:

Download "Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report"

Transcription

1 Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report 260 TO: FROM: SUBJECT: ECAC Members Jamie Asbury, deputy energy manager, Business/Regulatory Five (5) Generator Interconnection Agreements: SEPV Imperial, LLC West 3 MW Solar Generating Facility SEPV Imperial, LLC East 2 MW Solar Generating Facility Green Light Energy Corp. - 3 MW Valencia No.1 Solar Generating Facility Green Light Energy Corp. - 3 MW Valencia No. 2 Photovoltaic Project Imperial Water Ventures, LLC - 3 MW Photovoltaic Project DATE: April 4, 2016 Staff Recommendation/Motion: These items are being presented for information only. SEPV Imperial, LLC West 3MW Solar Generating Facility IID Contract No. GIA Financial Analysis: The total estimated cost of the project is $136,044; the customer will make a single milestone payment totaling $136,044 to cover IID s cost of the project during development and construction. No network upgrades were identified. IID will not be required to reimburse any portion of the interconnection costs via the issuance of rate credits. Background SEPV Imperial, LLC interconnection request was processed through IID s open access transmission tariff as a feed-in-tariff project. IID s planning and engineering consultant conducted studies to determine the impact of the generation project on the reliability of IID s grid as well as identify the infrastructure necessary to interconnect the project to the IID system. The 3 MW SEPV Dixieland west solar project seeks interconnection to IID s kV Dixieland Substation distribution circuit L-66. The planned in-service date is June The total estimated cost of the project includes interconnection facilities and a relay coordination study. The agreement has been reviewed and approved by legal counsel.

2 261 SEPV Imperial, LLC East 2 MW Solar Generating Facility IID Contract No. GIA Financial Analysis: The total estimated cost of the project is $129,622; the customer will make a single milestone payment totaling $129,622 to cover IID s cost of the project during development and construction. No network upgrades were identified. IID will not be required to reimburse any portion of the interconnection costs via the issuance of rate credits. Background SEPV Imperial, LLC interconnection request was processed through IID s open access transmission tariff as a feed-in-tariff project. IID s planning and engineering consultant conducted studies to determine the impact of the generation project on the reliability of IID s grid, as well as identify the infrastructure necessary to interconnect the project to the IID system. The 2 MW SEPV Dixieland east solar project seeks interconnection to IID s kV Dixieland Substation distribution circuit L-67. The planned in-service date is June The total estimated cost of the project includes interconnection facilities and a relay coordination study. The agreement has been reviewed and approved by legal counsel. Green Light Energy Corporation - 3 MW Valencia No.1 Solar Generating Facility IID Contract No. GIA Financial Analysis: The total estimated cost of the project is $188,312; the customer will make a single milestone payment of $188,312 to cover IID s cost of the project during development and construction. No network upgrades were identified. IID will not be required to reimburse any portion of the interconnection costs via the issuance of rate credits. Background Green Light Energy Corporation s interconnection request was processed through IID s open access transmission tariff as a feed-in-tariff project. IID s planning and engineering consultant conducted studies to determine the impact of the generation project on the reliability of IID s grid, as well as identify the infrastructure necessary to interconnect the project to the IID system. The 3 MW Valencia 1 solar project seeks interconnection to IID s 12.47kV distribution circuit B36 out of the Westmorland Substation. The planned in-service date is September The interconnection customer will be responsible for engineering, procurement and construction of its facility and the system protection equipment. The total estimated cost of the project includes interconnection facilities and a relay coordination study. The agreement was reviewed and approved by legal counsel.

3 262 Green Light Energy Corporation - 3 MW Valencia No. 2 Photovoltaic Project IID Contract No. GIA Financial Analysis: The total estimated cost of the project is $582,692; the customer will make milestone payments totaling $198,082 to cover IID s cost of the project during development and construction; the customer will design, engineer, procure and construct certain relay protection equipment. No network upgrades were identified. IID will not be required to reimburse any portion of the interconnection costs via the issuance of rate credits. Background Green Light Energy Corporation s interconnection request was processed through IID s open access transmission tariff as a feed-in-tariff project. IID s planning and engineering consultant conducted studies to determine the impact of the generation project on the reliability of IID s grid as well as identify the infrastructure necessary to interconnect the project to the IID system. The 3 MW Valencia No. 2 solar project seeks interconnection to IID s 34.5-kV transmission system between El Centro and Brawley via a tap configuration. The planned in-service date is September The interconnection customer will be responsible for engineering, procurement and construction of its facility and the system protection equipment. The total estimated cost of the project includes interconnection facilities and a relay coordination study. The agreement has been reviewed and approved by legal counsel. Imperial Water Ventures, LLC - 3 MW Photovoltaic Project IID Contract No. GIA Financial Analysis: The total estimated cost of the project is $891,250; the customer will make milestone payments of $341,250 to ensure IID s internal costs are covered during development and construction of the project. No network upgrades were identified. IID will not be required to reimburse any portion of the interconnection costs via the issuance of rate credits. Background Imperial Water Ventures interconnection request was processed through IID s open access transmission tariff as a feed-in-tariff project. IID s planning and engineering consultant conducted studies to determine the impact of the generation project on the reliability of IID s grid as well as identify the infrastructure necessary to interconnect the project to the IID system. The 3 MW Imperial Water Ventures solar project seeks interconnection to IID s 92-kV J Line between the El Centro Switching Station and Rockwood Substation via a tap configuration. The planned in-service date is October The interconnection customer will be responsible for engineering, procurement and construction of its facility

4 263 and the system protection equipment. The total estimated cost of the project includes interconnection facilities and a relay coordination study. The agreement has been reviewed and approved by legal counsel.

5 264 Generator Interconnection Agreements Feed-In-Tariff Projects Jamie Asbury Deputy Energy Manager, Business/Regulatory April 4, 2016

6 Background Information All Projects Projects with generation intended for wholesale sale are subject to and processed under IID s tariff. Two studies performed: System Impact Study (reliability impacts on the grid) Facilities Study (infrastructure to mitigate impacts) Planning and Engineering ensured reliable grid: 265 Reliable but less costly interconnections are cost saving for both IID and the developer Makes for more robust grid thereby attracting additional development. 2

7 IID s Feed-In-Tariff Background In 2009, Senate Bill 32 required large utilities to implement a feed-in-tariff program. Subsequent adoption of SB 1332 in 2012, requires publicly-owned utilities serving 75,000 or more customers to offer an FIT program by July 1, SB 1332 set the processing of requests on a first-come, first-served basis. SB 1332 set a state-wide cap of 750 MW; IID s share of the 750 MW cap was set at 14 MW. IID board received an informational FIT program presentation on May 28, 2013 and subsequently approved the FIT program and rate on June 11, IID board received an informational item reference amendment to the open access transmission tariff on June 11, 2013 to accommodate a small generator interconnection process; subsequent approval on June 25, IID processed the requests in the order received pursuant to SB

8 Basic Feed-In-Tariff Rate Components IID developed a pro forma purchase power agreement. Utilities offer 10, 15 and 20 year standard power purchase agreements (no negotiation of terms and conditions); IID opted for a 20-year term. Seasonal time-of-delivery tariff based on the following cost components: Renewable Energy Greenhouse Gas Reduction Peak Demand Reduction Avoided Transmission and Distribution Improvements IID s board adopted a PPA rate based on a time-of-day delivery period and contains a 1.5 percent fixed annual escalation factor

9 IID Feed-In-Tariff Rates per kwh 268 Time of Day Summer Winter On Peak $ $ Mid Peak $ $ Off Peak $ $

10 Generator Interconnection Projects Feed-In-Tariff 269 Project Capacity (MW) Load Cost to Interconnect Annual Wheeling Revenue Imperial Water Ventures 3 MW IID FIT $891,250 $0.00 Serves IID Load Green Light Valencia 1 3 MW IID FIT $188,312 $0.00 Serves IID Load Green Light Valencia 2 3 MW IID FIT $582,692 $0.00 Serves IID Load SEPV Dixieland East 2 MW IID FIT $129,622 $0.00 Serves IID Load SEPV Dixieland West 3 MW IID FIT $136,044 $0.00 Serves IID Load 6

11 FIT Project Purchase Power Agreement Board Approval History 270 Project Presented for Information to IID Board IID Board Approval of PPA Imperial Water Ventures January 13, 2015 January 25, 2015 Green Light Valencia 1 September 16, 2014 September 23, 2014 Green Light Valencia 2 September 16, 2014 September 23, 2014 SEPV Dixieland East April 14, 2015 May 12, 2015 SEPV Dixieland West April 14, 2015 May 12,

12 This page is intentionally left blank.

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013 Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation

More information

IID BOARDROOMS 1285 Broadway, El Centro, CA Avenue 58, La Quinta, CA Web Access: Supplemental Agenda

IID BOARDROOMS 1285 Broadway, El Centro, CA Avenue 58, La Quinta, CA Web Access:   Supplemental Agenda IMPERIAL IRRIGATION DISTRICT Energy Consumers Advisory Committee Regular Meeting: Monday, July 9, 2018, 6 p.m. IID BOARDROOMS 1285 Broadway, El Centro, CA 81-600 Avenue 58, La Quinta, CA Web Access: www.iid.com

More information

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy

More information

IMPERIAL IRRIGATION DISTRICT Energy Consumers Advisory Committee

IMPERIAL IRRIGATION DISTRICT Energy Consumers Advisory Committee IMPERIAL IRRIGATION DISTRICT Energy Consumers Advisory Committee 81-600 Avenue 58 Meeting Locations: Bill Condit Auditorium IID Boardroom 1285 Broadway Avenue 81-600 Avenue 58 El Centro, CA La Quinta,

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 17-058 LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES Request for Approval of Energy Supply Solicitation and Resulting Rates

More information

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019.

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019. NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service Effective: For bills rendered on and after February 1, 2019. SEDC:60/7/8/9 SECTION 1. AVAILABILITY AND APPLICABILITY 1.1

More information

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014.

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014. NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service Effective: For bills rendered on and after January 1, 2014. SECTION 1. AVAILABILITY AND APPLICABILITY 1.1 This Rate Schedule

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: The Trustees are being requested to approve a resolution adopting modifications to the Long Island Power Authority

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE Effective: April 2015 Billing Cycle AVAILABILITY: The E-27 Price Plan is subject

More information

Overview of S.L Competitive Energy Solutions for North Carolina

Overview of S.L Competitive Energy Solutions for North Carolina Overview of S.L. 2017-192 Competitive Energy Solutions for North Carolina JENNIFER MCGINNIS CHRIS SAUNDERS STAFF AT TORNEYS, LEGISLATIVE ANALYSIS DIVISION 1 Overview Product of extensive stakeholder process

More information

Agricultural Service Rate Schedule AG

Agricultural Service Rate Schedule AG I. Applicability Agricultural Service This Rate Schedule 1-AG applies to single- or three-phase nonresidential agricultural service, delivered at standard voltages designated by SMUD as available at the

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD SCHEDULED ITEM TO: FROM: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD GEORGE F. MORROW, DIRECTOR OF UTILITIES DATE: JANUARY 28, 2013 SUBJECT: APPROVAL OF POWER SALES AGREEMENT ( PSA ) WITH

More information

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential

More information

Kansas Legislator Briefing Book 2009

Kansas Legislator Briefing Book 2009 Kansas Legislator Briefing Book 2009 Agriculture, Natural Resources, and Energy B-5 Net Metering Other reports available B-1 The Kansas Animal Health Department and Foreign Animal Diseases B-2 Water Litigation

More information

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: LIPA Staff proposes revisions to the Tariff for Electric Service under Service Classification No. 11 ( SC-11 ),

More information

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-21 PRICE PLAN FOR RESIDENTIAL SUPER PEAK TIME-OF-USE SERVICE

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-21 PRICE PLAN FOR RESIDENTIAL SUPER PEAK TIME-OF-USE SERVICE SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-21 PRICE PLAN FOR RESIDENTIAL SUPER PEAK TIME-OF-USE SERVICE Effective: April 2015 Billing Cycle Supersedes: November 2012 Billing Cycle

More information

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone.

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone. Meeting Objective 1. Who are we? 2. Review Commercial Solar Industry 3. Who are the ideal candidates for solar? 4. Key Site Conditions 5. Typical Upfront and On-going Costs Grasshopper Vision Accelerate

More information

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load Memorandum To: Municipal Light Advisory Board; Municipal Light Board; file From: Belmont Light Staff Date: June 19, 2014 Re: Solar PV Distributed Generation 1. Background & Summary Belmont Light supports

More information

Buy All Sell All Rider for Interconnection of Renewable Generation

Buy All Sell All Rider for Interconnection of Renewable Generation for Interconnection of Renewable Generation I. Availability Available to each Customer of Fayetteville Public Works Commission (PWC) that purchases retail electricity from PWC and that owns and operates

More information

From: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor

From: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor AGENDA ITEM NO: 4.I.1 MEETING DATE: 12/10/2012 ADMINISTRATIVE REPORT NO.: 2013-28 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM Engineering and Operations From: Tito R. Nagrampa

More information

Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014

Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Net Metering in Illinois Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Topics What is Net Metering Benefits of Net Metering Net Metering in US Net Metering in Illinois

More information

EXHIBIT A ORDINANCE NO. O CITY OF LAURINBURG, NORTH CAROLINA SCHEDULES OPR RESIDENTIAL TIME-OF-USE SERVICE

EXHIBIT A ORDINANCE NO. O CITY OF LAURINBURG, NORTH CAROLINA SCHEDULES OPR RESIDENTIAL TIME-OF-USE SERVICE ORDINANCE NO. O-2017-14 CITY OF LAURINBURG, NORTH CAROLINA SCHEDULES OPR RESIDENTIAL TIME-OF-USE SERVICE AVAILABILITY This schedule is closed to new customers. Available to Residential Consumers being

More information

January 1, 2018 RATE SCHEDULE. 395 Southgate Drive, Guelph, ON N1G 4Y1. Billing: Admin: Fax:

January 1, 2018 RATE SCHEDULE. 395 Southgate Drive, Guelph, ON N1G 4Y1. Billing: Admin: Fax: January 1, 2018 RATE SCHEDULE 395 Southgate Drive, Guelph, ON N1G 4Y1 Billing: 519-822-3010 Admin: 519-822-3017 Fax: 519-822-0960 Time-of-Use rates for electricity came into effect for the majority of

More information

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS 1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the

More information

HOUSE BILL 589: Competitive Energy Solutions for NC.

HOUSE BILL 589: Competitive Energy Solutions for NC. 2017-2018 General Assembly HOUSE BILL 589: Competitive Energy Solutions for NC. Committee: Date: August 8, 2017 Introduced by: Prepared by: Jennifer McGinnis Analysis of: S.L. 2017-192 Staff Attorney OVERVIEW:

More information

Interdepartmental Memorandum

Interdepartmental Memorandum Interdepartmental Memorandum Office of President and CEO AB/01-522 Phone: 528-4470 Fax: 528-4321 To: From: Board of Commissioners Lisa Osborn Administrative Assistant Date: April 27, 2016 Subject: President

More information

24. SOLAR INCENTIVE PROGRAM II

24. SOLAR INCENTIVE PROGRAM II 24. SOLAR INCENTIVE PROGRAM II A. General California Senate Bill 1 requires publicly owned utilities that sell electricity at the retail level, to adopt, implement, and fund a solar incentive program for

More information

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016 Considerations for Municipal Solar Projects Ben Frevert Larsen Engineers November 16, 2016 Topic Areas Benefits of going green / solar Actions local governments can take Programs and incentives Implementation

More information

Plug-in Electric Vehicle Program. Wisconsin Public Utility Institute Transportation Fuels Program July 14, 2011

Plug-in Electric Vehicle Program. Wisconsin Public Utility Institute Transportation Fuels Program July 14, 2011 Plug-in Electric Vehicle Program Wisconsin Public Utility Institute Transportation Fuels Program July 14, 2011 Company Profile The Utility Principal subsidiary of CMS Energy 7,000+ employees $6.8B in annual

More information

Guideline on Energy Storage

Guideline on Energy Storage Purpose Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs DEPARTMENT OF ENERGY RESOURCES SOLAR MASSACHUSETTS RENEWABLE TARGET PROGRAM (225 CMR 20.00) GUIDELINE Guideline

More information

SCHEDULE NO. ACG33 NET METERING SERVICE

SCHEDULE NO. ACG33 NET METERING SERVICE Approved by Decision No.: 75408 Effective: January 19, 2016 Applicability Applicable to "Net Metering Facility" as defined below, or applicable Arizona Corporation Commission ("Cmnn1ission") Decision,

More information

Senate Substitute for HOUSE BILL No. 2101

Senate Substitute for HOUSE BILL No. 2101 Senate Substitute for HOUSE BILL No. 2101 AN ACT concerning utilities; relating to renewable energy resources; amending K.S.A. 2013 Supp. 66-1,184, 66-1265, 66-1266, 66-1267 and 66-1271 and repealing the

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

Small General Service Time-of-Use Rate Schedule GS-TOU3

Small General Service Time-of-Use Rate Schedule GS-TOU3 I. Applicability Small General Service Time-of-Use This Rate Schedule 1-GS-TOU3 applies to single- or three-phase service, delivered at standard voltages designated by SMUD as available at the customer

More information

Douglas Electric Cooperative Roseburg, Oregon

Douglas Electric Cooperative Roseburg, Oregon Douglas Electric Cooperative Roseburg, Oregon Policy Bulletin 30-8 Net Metering Services Policy: Net metering service is available, on an equal basis, to Customers who own and operate a net metering generating

More information

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014 City Power Johannesburg: Response to Potential Load Shedding Presented by : Stuart Webb General Manager : PCM October 2014 Topics to be discussed Background Challenges Options Available Summary 2 Background

More information

ROANOKE ELECTRIC COOPERATIVE RATE SCHEDULES

ROANOKE ELECTRIC COOPERATIVE RATE SCHEDULES ROANOKE ELECTRIC COOPERATIVE P. O. DRAWER 1326 AHOSKIE, NORTH CAROLINA 27910 RATE SCHEDULES EC 31 SUB. 44 APPROVED BY BOARD OF DIRECTORS: August 7, 2018 EFFECTIVE FOR BILLS RENDERED ON OR AFTER November

More information

UPPER CUMBERLAND ELECTRIC MEMBERSHIP CORPORATION. RESIDENTIAL RATE--SCHEDULE RS (March 2019) Availability. Character of Service.

UPPER CUMBERLAND ELECTRIC MEMBERSHIP CORPORATION. RESIDENTIAL RATE--SCHEDULE RS (March 2019) Availability. Character of Service. UPPER CUMBERLAND ELECTRIC MEMBERSHIP CORPORATION RESIDENTIAL RATE--SCHEDULE RS () Availability This rate shall apply only to electric service to a single-family dwelling (including its appurtenances if

More information

RESOLUTION NO Residential Service Schedule No. 2: Effective for billings rendered on or after September 1, 2013

RESOLUTION NO Residential Service Schedule No. 2: Effective for billings rendered on or after September 1, 2013 RESOLUTION NO. 1567 A Resolution of the Board of Commissioners of Public Utility District No. 1 of Okanogan County Revising the District's Electric Service Rate Schedules WHEREAS, District Resolution No.

More information

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT January 1, 2016 CA Public Utilities Commission Energy Division Attention: Tariff Unit 505 Van Ness Avenue, 4thFloor San Francisco, CA 94102-3298 Advice Letter LCE 001-E RE: LANCASTER CHOICE ENERGY S BIENNIAL

More information

To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning. From: Alan Hanger Approved by: /s/

To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning. From: Alan Hanger Approved by: /s/ AGENDA ITEM NO.: 4.J.1 To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning From: Alan Hanger Approved by: /s/ Senior Energy Resource Analyst Glenn O. Steiger

More information

PENINSULA CLEAN ENERGY JPA Board Correspondence

PENINSULA CLEAN ENERGY JPA Board Correspondence PENINSULA CLEAN ENERGY JPA Board Correspondence DATE: June 22, 2016 BOARD MEETING DATE: June 23, 2016 SPECIAL NOTICE/HEARING: None VOTE REQUIRED: Majority Present TO: FROM: SUBJECT: Honorable Peninsula

More information

Solar Project Development in Regulated Markets. Smart and Sustainable Campuses Conference 2017

Solar Project Development in Regulated Markets. Smart and Sustainable Campuses Conference 2017 Solar Project Development in Regulated Markets Smart and Sustainable Campuses Conference 2017 Session Outline Overview of renewable energy procurement options Market structure and policy impacts on solar

More information

is attached to and becomes a part of a agreement dated, 20

is attached to and becomes a part of a agreement dated, 20 Electric Process Heat Schedule Designation R1.2 Standard Contract Rider No. 1.2 DE 963-1635 8/18 THIS RIDER, dated, 20 is attached to and becomes a part of a agreement dated, 20 between (Legal Entity and

More information

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only Overview of Electricity Trade Agreement between Québec and Ontario May 10, 2017 For Information Purposes Only Purpose To provide an overview of the electricity trade agreement between the Independent Electricity

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 27, 2017

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 27, 2017 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 27, 2017 Item 6, Report No. 26, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan on

More information

Per Meter, Per Month. Effective July 1, 2018 Customer Charge Flat Charge $8.86

Per Meter, Per Month. Effective July 1, 2018 Customer Charge Flat Charge $8.86 SCHEDULE D TOU TIERED DOMESTIC TIME OF USE SERVICE TIERED (This rate schedule is closed to new customers as of July 1, 2018. On July 1, 2019, existing customers will be transitioned to their otherwise

More information

Legal Considerations Related to Distributed Energy Resources

Legal Considerations Related to Distributed Energy Resources Legal Considerations Related to Distributed Energy Resources Steve Pincus Associate General Counsel Steve Shparber Counsel Markets & Reliability Committee April 18, 2016 Overview of FERC Jurisdiction FERC

More information

FLORENCE ELECTRICITY DEPARTMENT. GENERAL POWER RATE--SCHEDULE GSC (October 2015) Availability

FLORENCE ELECTRICITY DEPARTMENT. GENERAL POWER RATE--SCHEDULE GSC (October 2015) Availability FLORENCE ELECTRICITY DEPARTMENT GENERAL POWER RATE--SCHEDULE GSC () Availability This rate shall apply to the firm electric power requirements where a customer s currently effective onpeak or offpeak contract

More information

is attached to and becomes a part of a agreement dated, 20,

is attached to and becomes a part of a agreement dated, 20, Electric Metal Melting (Alternative) Schedule Designation R1.1 Standard Contract Rider No. 1.1 DE 963-7033 8/18 THIS RIDER, dated, 20, is attached to and becomes a part of a agreement dated, 20, between

More information

Schedule DP-1 SMALL GENERAL SERVICE (EXPERIMENTAL)

Schedule DP-1 SMALL GENERAL SERVICE (EXPERIMENTAL) I. APPLICABILITY This schedule is applicable only to a Customer who qualifies for Electric Service in accordance with Schedule GS-1 as of the Customer s effective date for billing under this schedule.

More information

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which: DATE: July 16,2007 TO: FROM: SUBJECT: CITY COUNCIL CITY MANAGER CONSIDERATION OF ADOPTION OF NEW FEDERAL STANDARDS RELATING TO ELECTRIC UTILITIES UNDER THE PUBLIC UTILITIES REGULATORY POLICIES ACT AND

More information

California s RPS Program: Progress Towards California s 33% RPS Goal and the Role of Concentrating Solar Power CSP Conference

California s RPS Program: Progress Towards California s 33% RPS Goal and the Role of Concentrating Solar Power CSP Conference California s RPS Program: Progress Towards California s 33% RPS Goal and the Role of Concentrating Solar Power CSP Conference Presented by Edward Randolph Energy Division Director, California Public Utilities

More information

To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning

To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning AGENDA ITEM NO: 5.E.1 ADMINISTRATIVE REPORT NO. 2013-02 To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning From: Alan Hanger Senior Energy Resources Analyst

More information

Within the service area of the District from lines of 115,000 volts or 34,500 volts.

Within the service area of the District from lines of 115,000 volts or 34,500 volts. Rate Schedule LP-4 Lo u p La r g e Li g h t a n d Po w e r - Su b t r a n s m i s s i o n De l i v e r y w i t h Cu s t o m e r Ge n e r a t i o n Un d e r Buy/Sell Concept Loup River Public Power District

More information

RENEWABLE ENERGY IN JORDAN What had to be done 8 Oct 2017

RENEWABLE ENERGY IN JORDAN What had to be done 8 Oct 2017 RENEWABLE ENERGY IN JORDAN What had to be done 8 Oct 2017 Structure of Electricity Sector Generation & Policy Maker Regulator Power Transmission Distribution Producers Ministry of Energy & Mineral Resources

More information

Appendix 6.7 January 23, 2015 SURPLUS ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS

Appendix 6.7 January 23, 2015 SURPLUS ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS Appendix 6.7 SUR ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS SUR ENERGY PROGRAM INDUSTRIAL LOAD - OPTION 1 TABLE OF CONTENTS Page No. Eligibility...1 Reference Demand...1 Billing...2 Interruptions...3

More information

To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning

To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning AGENDA ITEM NO: 6.A.1 MEETING DATE: 11/17/2010 ADMINISTRATIVE REPORT NO.: 2011-24 To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning From: Suzie Shin Energy

More information

Group 3: Pricing from 1 April 2018 and load management

Group 3: Pricing from 1 April 2018 and load management Group 3: Pricing from 1 April 2018 and load management This document is intended to provide background to Network Tasman s Group 3 pricing, in particular the Regional Coincident Peak Demand (RCPD) price,

More information

SMALL POWER PRODUCER RIDER

SMALL POWER PRODUCER RIDER Minnesota Public Utilities ommission ELETRI RATE SHEDULE Page 1 of 5 Thirty-ninth Revision SMALL POWER PRODUER RIDER () DESRIPTION RATE ODE Firm Power 32-981 Non-Firm Power 32-984 Renewable Energy redit

More information

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets

More information

RATE 765 RENEWABLE FEED-IN TARIFF

RATE 765 RENEWABLE FEED-IN TARIFF NORTHERN INDIANA PUBLIC SERVICE COMPANY Original Sheet No. 104 TO WHOM AVAILABLE Sheet No. 1 of 12 This Rate Schedule is a voluntary offer available to any Customer that operates within the Company s service

More information

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. First Revision of Sheet No. 135.1 P.S.C.U. No. 50 Canceling Original Sheet No. 135.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 135 STATE OF UTAH Net Metering Service Closed to Applications for

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee

Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee November 3, 2009 Sara Birmingham Director of Western Policy The Solar Alliance -1- Who We Are An Alliance of PV manufacturers,

More information

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE Sheet 1 AVAILABILITY Electric delivery service shall be taken under this rate for all purposes by any customer who is placed on the rate by the Company in accordance with this paragraph. The Company shall

More information

ELECTRIC POWER BOARD OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY. Availability

ELECTRIC POWER BOARD OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY. Availability ELECTRIC POWER BOARD OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY GENERAL POWER RATE--SCHEDULE GSB Availability This rate shall apply to the firm electric power requirements where a

More information

CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS

CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS CHOPTANK ELECTRIC COOPERATIVE, INC. TERMS AND CONDITIONS TABLE OF CONTENTS PAGE NO. GENERAL 1 100 ELECTRIC SERVICE 101 Application

More information

Thank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing.

Thank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing. Mary L. Cottrell, Secretary March 27, 2009 Page 1 Stacey M. Donnelly Counsel September 23, 2009 Mark D. Marini, Secretary Department of Public Utilities One South Station Boston, MA 02110 Re: D.P.U. 09-03

More information

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Residential Solar Workshop May 7 th 2008 Thomas Alston Director of Business and Policy Development Presented By 1475 N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Workshop Agenda An Overview of

More information

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G.Road, Bangalore-560 001 Present: Shri M.R. Sreenivasa Murthy Chairman Shri H. D. Arun Kumar Shri D.B. Manival

More information

THE PUBLIC SERVICE COMMISSION OF WYOMING

THE PUBLIC SERVICE COMMISSION OF WYOMING NAME: Powder River Energy Corporation WY PSC Tariff No. 7 ADDRESS:, Sundance, WY 82729 THE PUBLIC SERVICE COMMISSION OF WYOMING TARIFF RATE RIDER 5th Revised Sheet No. 1 Cancels 4th Revised Sheet No. 1

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of San Diego Gas & Electric Company (U902E) for Authority to Implement Optional Pilot Program to Increase Customer Access to

More information

Agreement with Enbridge for the Installation of Compressed Natural Gas Refuelling Stations at City Facilities

Agreement with Enbridge for the Installation of Compressed Natural Gas Refuelling Stations at City Facilities PW9.3 STAFF REPORT ACTION REQUIRED Agreement with Enbridge for the Installation of Compressed Natural Gas Refuelling Stations at City Facilities Date: October 20, 2015 To: From: Wards: Reference Number:

More information

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK Grid Operations and the Increasing Challenges of Balancing Renewable Energy JANUARY 18 ALBUQUERQUE QUALITY NETWORK JANUARY 18, 2018 AGENDA Overview and History of PNM Grid Operation Challenges Generation

More information

250kW Solar PV System Poultry Shed Solution - Gatton

250kW Solar PV System Poultry Shed Solution - Gatton 250kW PV System Poultry Shed Solution - Gatton Document Created by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L www.smartconsult.com.au 14 June 2013 Key Points for a PV System 250kW System at

More information

Net Energy Metering and Interconnections. Community Solar in the District of Columbia

Net Energy Metering and Interconnections. Community Solar in the District of Columbia Net Energy Metering and Interconnections Community Solar in the District of Columbia Presented by: Virginia Burginger August 4, 2016 1 Welcome Overview of Community Net Metering in the District of Columbia

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

Large General Service Time-of-Use Storage Program

Large General Service Time-of-Use Storage Program Large General Service Time-of-Use Storage Program AVAILABILITY Available throughout the Company s entire electric service area where the facilities of the Company are of adequate capacity and are adjacent

More information

ELECTRIC SERVICE RATES UPDATED NOVEMBER 2016

ELECTRIC SERVICE RATES UPDATED NOVEMBER 2016 ELECTRIC SERVICE RATES UPDATED NOVEMBER 2016 RESIDENTIAL SERVICES (RS) EFFECTIVE: OCTOBER 1, 2008 AVAILABILITY - Available exclusively to residential customers for residential use within the service area

More information

COMMUNITY SOLAR PROGRAM

COMMUNITY SOLAR PROGRAM Original Sheet No. D-22.00 COMMUNITY SOLAR PROGRAM The Cooperative's generation and transmission Cooperative ("G&T") has created a standing offer for 10 MW ofrenewable energy, produced by solar and wind

More information

PUBLIC SERVICE ELECTRIC AND GAS COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016

PUBLIC SERVICE ELECTRIC AND GAS COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016 IN THE MATTER OF THE PROVISION OF : BASIC GENERATION SERVICE FOR BASIC : GENERATION SERVICE REQUIREMENTS : Docket No. ER15040482 EFFECTIVE JUNE 1, 2016 : PUBLIC SERVICE ELECTRIC AND GAS COMPANY PROPOSAL

More information

The Gambia National Forum on

The Gambia National Forum on The Gambia National Forum on Renewable Energy Regulation Kairaba Hotel, The Gambia January 31 February 1, 2012 Tariff and Price Regulation of Renewables Deborah Erwin Public Service Commission of Wisconsin

More information

Renewable Portfolio Standard Procurement Plan. November 12, 2013 Docs No:

Renewable Portfolio Standard Procurement Plan. November 12, 2013 Docs No: Renewable Portfolio Standard Procurement Plan November 12, 2013 Docs No: 337455 SECTION 1: INTRODUCTION In the fall of 2002, the Governor signed into law Senate Bill 1078 (SB 1078). This legislation set

More information

Street Address. City-Village-Township

Street Address. City-Village-Township Schedule Designation D11 Primary Supply Agreement D11 963-1816 77/15 THIS AGREEMENT, dated, 20, by and between (Name) a, (Legal Entity and State of Organization) herein called the "Customer", and DTE Electric

More information

6 York Region Transit (YRT/Viva) On-board Security Camera System Upgrade Contract Award

6 York Region Transit (YRT/Viva) On-board Security Camera System Upgrade Contract Award Clause 6 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 25, 2015. 6 York Region Transit (YRT/Viva)

More information

2015 GENERAL FIRM POWER SERVICE RATE STUDY SUMMARY REPORT

2015 GENERAL FIRM POWER SERVICE RATE STUDY SUMMARY REPORT 2015 GENERAL FIRM POWER SERVICE RATE STUDY SUMMARY REPORT SECTION 1. AVAILABILITY Sheet No.: 1 Of 21 Sheets A. This General Firm Power Service Rate Schedule (GFPS Rate Schedule) is available to any

More information

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1). Ken Duke Solicitor & Counsel Phone: 604-623-3623 Fax: 604-623-3606 bchydroregulatorygroup@bchydro.com April 30, 2014 Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: (BCUC) British

More information

ATTACHMENT 14 RESOLUTION NO. 5888(14) Supersedes Schedule NEM of Resolution No. 5592(09) Schedule NEM NET ENERGY METERING

ATTACHMENT 14 RESOLUTION NO. 5888(14) Supersedes Schedule NEM of Resolution No. 5592(09) Schedule NEM NET ENERGY METERING APPLICABILITY ATTACHMENT 14 RESOLUTION NO. 5888(14) Supersedes Schedule NEM of Resolution No. 5592(09) Schedule NEM NET ENERGY METERING This net metering schedule applies to residential and/or small commercial

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

HOW NET METERING OF ELECTRICITY WORKS

HOW NET METERING OF ELECTRICITY WORKS HOW NET METERING OF ELECTRICITY WORKS POWER THE FUTURE REGIONAL PROGRAM Armen Arzumanyan July 13, 2018 Tashkent, Uzbekistan 1 CONTENTS Introduction History Basic Principle Related Mechanisms Costs and

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public

More information

S T A F F R E P O R T

S T A F F R E P O R T S T A F F R E P O R T DATE: December 11, 2012 TO: FROM: Honorable Mayor and City Council Superintendent, Brandon Graham SUBJECT: Net Metering Policy Section A 2. b. (Change the maximum installation capacity

More information

Portland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No.

Portland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No. Portland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No. 7-1 AVAILABLE In all territory served by the Company. APPLICABLE To Residential

More information

Community Shared Solar Opportunities in Massachusetts Emma Krause Rooftop Solar Challenge Coordinator MA DOER

Community Shared Solar Opportunities in Massachusetts Emma Krause Rooftop Solar Challenge Coordinator MA DOER Community Shared Solar Opportunities in Massachusetts Emma Krause Rooftop Solar Challenge Coordinator MA DOER What is CSS? Homeowner wants to install solar on their roof, but cannot due to site constraints

More information