Protection Technology. Challenges of protection power grids with distributed generating units. Technical Article
|
|
- Quentin Stevens
- 5 years ago
- Views:
Transcription
1 Protection Technology Challenges of protection power grids with distributed generating units Technical Article
2 The energy transition changes power grids Challenges of protecting power grids with distributed generating units The energy transition implies a paradigm shift in the energy system and has an impact on the generation, transmission and distribution of electricity. An increasing number of distributed generating units based on renewable energies have to be integrated. Wind energy and photovoltaics systems are the fastest growing suppliers. This calls for a protection concept that is tailored to the new conditions, the selection of appropriate protection devices including the functions and protective settings adjusted to the changed grid conditions. This essay presents possible consequences for the protection technology. As the energy transition is being put into practice, energy is generated at all voltage levels which entails a change of classic grid tasks. A distribution grid contributes significantly to the generation of electricity and assumes transport tasks. The protection system makes a major contribution to the supply security. Marginal conditions Distributed generating units have to observe guidelines and they are subject to certification. The following guidelines have to be complied with: Gridcode (for example transmission code TC 2007) which specifies the feed-in conditions (for example, also feed-in during a fault fault ride through, reactive power provision for voltage stabilization)) [1] Guidelines for generating units at the medium-voltage grid 2008; EEC generating units at the high- and extra high-voltage grid 2004 and their update in the technical connection conditions TAB [2, 3] System service provision ordinance on wind energy farms (SDLWindV) [4]. General requirements for the protection technology Power grid studies found the following: Existing protection principles and schemes are basically suitable. However, protective settings have to be adjusted to the changed grid conditions. The contribution of converter-controlled generating units to the short-circuit current is low and is within the range of the generating unit's rated current (1 Irated) and in some cases even below, for example under weak wind conditions. This has an impact on the selection of protection principles and protective settings. It is recommended to make sample calculations to distribute the short-circuit fault during a fault. In case of unbalanced faults, the fault current contribution depends on control procedures of the inverter or frequency converter (for example only feed-in of a positive-sequence current). To cope with unbalanced faults, a negative-sequence current has to be injected. The inverter operating principle has to be inquired with the manufacturer. Due to the distributed feed-ins, the distribution grid's topology and tasks are similar to the transmission grid. For example, there are multi-end feed-ins or intermediate feed-ins. This requires established protection concepts and graded protection principles from the transmission grid to be implemented. In addition to protection tasks, grid disconnection and load shedding have to be implemented, taking the feed-in conditions into account. Digital protection devices are the optimum solution for many applications Figure 1. single-pole earth fault and no infeed of short circuit through wind farm The multifunctional digital device technology and the functions including state-of-the-art communication features are designed to enable solutions tailored to the application.
3 x Figure 2. example of additional infeed of synchronous generator into the medium-voltage grid a) situation of infeed and failure; b) impedance trajectory depending on duration of failure They are supported by a powerful engineering tool (for example Digsi 5 from Siemens). Siprotec 5, the new family of protection devices from Siemens, combines protection, control, automation, measurement, regulation and communication in one device [5] and has the following typical properties: A modular hardware and software concept enables the devices to be tailored to the grid conditions (for example free selection of the measuring points, of the I/O quantity structure, the protection functions and the communication infrastructure). Identical functions are used in various devices, increasing the flexibility of application (communication of protection data between the devices). High-precision measurements (class 0.2 for U, I and class 0.5 for P, Q, S) make additional measuring transducers redundant and additionally enable a wide setting range of the protection functions. Powerful fault recording and evaluation tools support fault recovery. Different protocols and communication infrastructures provide for the optimal connection to the substation control and protection system. The devices support IEC Edition 1 and 2. Applications We have selected some representative examples from the application options. They give an overview of possible changes: Feed-in of a wind farm Figure 1 shows a wind farm connected to the grid with a phase-to-ground fault occurring in the grid. The individual wind energy units feed energy to the grid through the frequency converter. No zero-sequence system is transmitted in case of a transformer in the star delta vector group. A phase-to-ground fault at the star side results in a 2-phase short circuit with a distinct negative-sequence current. But since the wind farm in its present design does not feed in any negative-sequence current (no negative-sequence impedance available), the wind farm neither supplies a fault current. This is equivalent to an open circuit breaker in the wind farm. The fault current is solely fed through the remaining grid. The behavior (open circuit breaker at the transformer delta side) is known as the Bauch phenomenon in protection technology. Figure 1 depicts the situation and shows the currents and voltages at the measuring point at the transformer star side. The distinct zero-sequence current in all three phases is typical of the Bauch phenomenon. A distance protection must recognize this situation, select the proper measuring loop and trip selectively. As feed-ins through inverters or frequency converters will increase, these also have to be capable of supplying a negative-sequence current during a fault from a protection perspective [6, 7]. Simulations have shown that when inverter controllers are not set correctly, inverters are capable of delivering harmonics during a fault as a result. When the setting is correct, the feeding quantities are sinusoidal (fundamental component). As faults cannot be ruled out entirely, the protection has to be resistant towards harmonics. Additional feed-in of synchronous generators in a medium-voltage grid In this example, a synchronous generator (biomass, hydro-electric power plant) additionally feeds energy into the grid. The grid connection design is depicted in Figure 2a. The busbar is fed through a strong grid. The protection in the outgoing feeders is implemented as a directional time overcurrent protection. The selected delay time t results from the grading time. Now if a short-circuit occurs on the line of protection equipment A, this fault is fed both by the grid and by the synchronous generator. Upon fault inception, a forward fault is recognized in A and timing element t is started. Protection device B, in contrast, recognizes the reverse direction. In the event of a fault, the synchronous generator is relieved in terms of active power, causing the generator to accelerate and the angular displacement to change. The current/voltage vector will thus offset over time. In line B that is feeding the fault current, the protection device will recognize the reverse fault as a forward fault after a certain period of time and also start the timing element. Depending on the fault duration and the set grading time, the outgoing feeder B may also trip. To prevent this non-selective tripping, the tripping time in outgoing feeder A has to be reduced. This can be achieved by replacing the so far directional overcurrent protection with a distance protection.
4 Figure 4 shows a connection example, the most important protection and disconnection functions and their settings. Other well-known disconnection criteria such as the phase angle jump of the voltage vector (vector jump) and the frequency rate of change function df/dt) are not recommended, because they require complex settings (grid calculations with variant consideration) and involve the risk of over- or underfunctioning (practical experience). The threshold values of the frequency functions correspond to the requirements from [1] and are identical to those of conventional power plants (type 1 acc. to [1]). Figure 3. load shedding by taking into account infeed conditions But there are other approaches to reducing the tripping time: Using the line differential protection that needs an additional backup protection to respond when the upstream protection device fails. Possible backup protection functions include a time overcurrent protection (also directional depending on the application) and a distance protection at higher voltage levels [8]. Expanding the directional time overcurrent protection to ensure protection data communication and implementation of directional comparison protection. The latter has to be designed so as to require no infeed from the remote end. This means that if the infeed side protection device picks up and the opposite side is not blocked, the device will trip short time [9]. Load shedding If consumed and generated active power are out of balance, the previous solution has been to shed loads with underfrequency based on a fixed frequency stage plan (5-stage plan [1]). If, however, distributed generating units supply at the grid connection point, these are lost. This exacerbates the situation between generation and consumption. Therefore, the international and national guidelines were adapted accordingly without any further development towards more flexibility [8]. If there are distributed feed-ins besides loads at the grid connection point, the circuit breaker must not open when energy is fed back (Figure 3). The frequency protection has to be connected to the power directional protection. This automation environment in particular contains modern, digital devices that offer various possibilities, such as the function itself, high-precision measurements and flexible communication. Adaptive load shedding becomes reality. Grid disconnection Given the rapid increase of distributed feed-ins (in particular type 2 according to [1]), the disconnection strategy has changed over the years. The goal is to keep generating units connected to the grid for as long as possible. Besides grid disconnection specifications, the guidelines also define marginal conditions for the feed-in behavior. For example, the fault ride-through capability is required. This means that during a 3-pole short-line fault generating units have to stay connected to the grid for at least 150 ms and feed in again once the fault has been cleared by the protection device (e.g. the differential protection). Moreover, the systems have to contribute to voltage stabilization resulting from the requirement to inject reactive power in the event of a fault. A pragmatic approach was chosen for the definition of the disconnection criteria. In addition to overfrequency and underfrequency (f>, f<), overvoltage and undervoltage (U>, U<) are required. The directional reactive power function with additional undervoltage release in all three phases is a new feature (evaluation of the phase-to-phase voltage). This function aims to prevent the voltage from being reduced further when reactive power is imported. The selectivity of the disconnection functions is implemented by different threshold values and timer settings. Different variants of the plant design and special cases to be considered were discussed in detail in [10]. For this reason, we will go into Figure 4 by way of example. It depicts a typical constellation: Supply to a medium-voltage grid and connection to the high-voltage grid through a radial-line connection. The solutions to protect the tapped line on the high-voltage side are sufficiently known. There is one special aspect in this application. If faults occur in the high-voltage grid, the circuit-breaker in the radial-line connection remains closed. But the circuit-breaker of the feed-in into the medium-voltage grid will be intertripped by distance protection A. The goal is to assure the supply reliability of the consumers in the medium voltage, since most faults in high voltage can be cleared by automatic reclosing. In medium-voltage faults, distance protection A assumes the function of a backup protection. Distance protection B fulfils the same function with the reverse zone. The forward zone of distance protection B clears faults on the line towards the generating unit. It is crucial for the distance protection setting that fault currents inside or below the rated current range have to be mastered. A U/I and Z pickup is a mandatory requirement. The overvoltage disconnection function protects a grid against overvoltage and in doing so contributes to the power quality. The undervoltage function protects the grid against inadmissible undervoltage and is the backup protection of the distance protection if the latter fails to pick up. The grid connection U< stage assures the grid disconnection and it is the backup protection for the undervoltage protection of the generating unit. The U< stage assures the grid disconnection in the event of undervoltage conditions and simultaneously assumes a backup function for the short-circuit protection of the generating unit (for type 2) and the U<< stage. The U<< stage is the main protection for low-current faults. The QU protection monitors the appropriate post-fault behavior and performs the separation at the grid connection point.
5 Summary We have used examples to show that the energy transition with its distributed generating units has an impact on the protection technology. Existing protection principles still have a right to exist. The significant changes in the feed-in situation call for a reassessment of existing protection concepts and settings. Hence, it is insufficient to simply connect the generating unit (as certified). A holistic consideration of the system has to be performed at any rate. In this context, generating units are not all the same. Type 1 units, feed-in via synchronous generators, behave in the well-known way. In contrast, type 2 units, such as feed-in via frequency converter/inverter, exhibit a different behavior. In particular, the low short-circuit current has to be coped with in the event of a fault. As a result, distance or differential protection schemes and modified settings (pickup and rated current) are required. Modern digital protection devices have the potential to tackle the new challenges. Future solutions will be based not only on the implementation of new functions, but also on flexible communication features including high-precision measurement technology. It is crucial that both grid operators and device manufacturers exchange their experiences and work together on developing a new and reliable electrical energy system. References [1] Transmission Code 2007: Netz-und Systemregeln der deutschen Übertragungsnetzbetreiber. VDN Berlin, Version 1.1, August [2] Technische Richtlinie Erzeugungsanlagen am Mittelspannungsnetz. Regelungen und Übergangsfristen für bestimmte Anforderungen in Ergänzung zur technischen Richtlinie. BDEW, Berlin, January 2013 edition. [3] EEG-Erzeugungsanlagen am Hoch- und Höchstspannungsnetz. VDN Berlin, August 2004 und TAB Hochspannung, VDE-AR-N 4120, VDN Berlin, January [4] Verordnung zu Systemdienstleistungen durch Windenergieanlagen (SDLWindV). German Federal Environment Ministry, Berlin, 3 July 2009, and amendments in [5] Siprotec 5 Schutz, Automatisierung und Überwachung. Übersichtskatalog C1000G220-A221, Siemens AG, Nürnberg, [6] Erlich, I.; Schegner, P.: Wind Turbine Negative Sequence Current Control and its Effect on Power System Protection. IEEE PES GM, Vancouver [7] Kühn, H.: Der Einfluss regenerativer Erzeugungsanlagen auf den Kurzschlussstrom. 7. ETG/FNN-Tutorial Schutz- und Leittechnik, Mainz, February [8] Hülshorst, H.-G.: Auswirkung der dezentralen Einspeisung auf das Lastabwurfkonzept. ETG-Tagung Schutz- und Leittechnik, Düsseldorf, February [9] Siprotec-5-Distanzschutz, Leitungsdifferentialschutz und Schaltermanagement für einpolige und dreipolige Auslösung 7SA87, 7SD87, 7SL87, 7VK87. Handbuch C53000G5000-C011-6, Siemens AG, [10] Siprotec 5 Überstromzeitschutz 7SJ82,7SJ85, Handbuch C53000G5000-C017-5, Siemens AG, [11] Hinz., K.; Schossig, W.: Schutzkonzeptionen für Verteilnetze dezentrale Energieerzeugungsanlagen. Anwendertagung Omicroncamp, Ulm, June Author Dipl. Ing. habil. Hans-Joachim Herrmann, Product Lifecycle Manager, Protection and Substation Automation, Principa Key Expert Energy Management Division, Energy Automation, Siemens AG, Nuremberg
Working like a power plant The P-Q behaviour of wind power stations has to meet the grid connection rules
Working like a power plant The P-Q behaviour of wind power stations has to meet the grid connection rules Dr. Ing. Steffen Prinz Prof. Dr.-Ing. habil. Dietrich Stade 1. Introduction In wind power stations,
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationUnit Protection System for Pumped-Storage Power Stations
Unit Protection System for Pumped-Storage Power Stations 1. Introduction In many power systems, pumped-storage power stations are used in addition to run-of-river power stations. These power stations serve
More informationTechnical Guidelines for Power Generating Units and Systems
Technical Guidelines for Power Generating Units and Systems PART 8 (TG 8) Certification of the Electrical Characteristics of Power Generating Units and Systems in Low-, Medium-, Highand Extra-High Voltage
More informationSummary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System
Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System This document is intended to be a general overview of PG&E s current technical
More informationAdvanced Protective Relay Training
Advanced Protective Relay Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq A properly designed protection
More informationDynamic Grid Support in Low Voltage Grids Fault Ride-Through and Reactive Power/Voltage Support during Grid Disturbances
Dynamic Grid Support in Low Voltage Grids Fault Ride-Through and Reactive Power/Voltage Support during Grid Disturbances Gustav Lammert University of Kassel Department of Energy Management and Power System
More informationTesting Renewable Power Plants on High-Voltage-Ride-Through Capability
Testing Renewable Power Plants on High-Voltage-Ride-Through Capability Grid Code Requirements and Testing Procedure Dipl.-Wirt.-Ing. Julian Langstädtler Division Manager Innovation & Consulting FGH GmbH
More informationDesign Considerations to Enhance Safety and Reliability for Service Entrance Switchboards
Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Robert P. Hansen, P.E., PhD GE Specification Engineer Introduction Switchboards are a widely used type of equipment
More informationPower Systems Trainer
Electrical Power Systems PSS A self-contained unit that simulates all parts of electrical power systems and their protection, from generation to utilisation Key Features Simulates generation, transmission,
More informationPV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies
PV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies Roland Bründlinger Operating Agent IEA-PVPS Task 14 UFTP & IEA-PVPS Workshop, Istanbul, Turkey 16th February
More informationEnergy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration
Energy Security Electrical Islanding Approach and Assessment Tools Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration Dr. Bill Kramer - 2 Electricity, Resources, & Building
More informationJemena Electricity Networks (Vic) Ltd
Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...
More informationCIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems
CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,
More informationA Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design
A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the
More information23 rd International Conference on Electricity Distribution Lyon, June Paper 0130 ABSTRACT INTRODUCTION. Maschinenfabrik Reinhausen GmbH
INCREASE OF THE GRID INTEGRATION OF DECENTRALIZED POWER PLANTS BY THE APPLICATION OF CERTIFIED GRID REGULATION UNITS IN SECONDARY SUBSTATIONS AND POWER GENERATION UNITS Dr.-Ing. Thomas SMOLKA, Dr. Manuel
More informationThe behavior of the cycloconverter fed gearless drive under abnormal electrical conditions
Mining The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions Reprint Authors: Kurt Tischler Siemens AG, Mining Technologies, Erlangen, Germany Reprint: WORKSHOP SAG
More informationTECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008
NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0
More informationProtection with distributed generation, experience with the Mont-Soleil wind farm project
Protection with distributed generation, experience with the Mont-Soleil wind farm project Florian Romanens IEEE Workshop 28 April 2011 Kursaal Bern Content BKW FMB Energie AG Mont-Soleil project Overview
More informationCHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM
106 CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 5.1 INTRODUCTION Inherent characteristics of renewable energy resources cause technical issues not encountered with conventional thermal,
More informationGuideline for Using IEEE 1547 for Solar PV Interconnection Page 1
Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1 A Guide for Iowa s Municipal Electric Utilities On the How the IEEE 1547 Distributed Generation Interconnection Standard Affects Solar
More informationGuidelines for connection of generators:
Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...
More informationLarge Scale Solar Integration
Large Scale Solar Integration Experiences and Coming Changes in Distributed Energy Resource Interconnections October 26 th, 2017 Overview Background on Xcel Energy Expansion of Solar in Minnesota Changes
More informationFull-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA
Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA Philippe Maibach, Alexander Faulstich, Markus Eichler, Stephen Dewar ABB Switzerland Ltd CH-5300 Turgi, Switzerland Phone: +41
More informationCost Benefit Analysis of Faster Transmission System Protection Systems
Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract
More informationSitras SCS, -RCI, -FFP, -TTU
Sitras SCS, -RCI, -FFP, -TTU control system for traction power supply Remote control interface Frame fault protection Transfer trip unit siemens.com/rail-electrification The Sitras SCS station control
More informationApplication Note: Protection of Medium-Power Motors With SIPROTEC Compact 7SK80
Application Note: Protection of Medium-Power Motors With SIPROTEC Compact 7SK80 Motor settings using the SIPROTEC Compact motor protection relay 7SK80 is explained below. Information is given on how to
More informationFuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators
Fuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators Abstract: G. Thrisandhya M.Tech Student, (Electrical Power systems), Electrical and Electronics Department,
More informationModular Standardized Electrical and Control Solutions for Fast Track Projects
Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive
More informationCOMPARISON OF DIFFERENT METHODS FOR EXCITATION OF SYNCHRONOUS MACHINES
Maszyny Elektryczne Zeszyty Problemowe Nr 3/2015 (107) 89 Stefan Schmuelling, Christian Kreischer TU Dortmund University, Chair of Energy Conversion Marek Gołȩbiowski Rzeszow University of Technology,
More informationTechnical information No. 01. IT systems. The basis for reliable power supply
IT systems The basis for reliable power supply FA01en/01.2004 IT systems The basis for reliable power supply in critical areas The advantages of sophisticated industrial systems can only be of use, if
More informationGENERATOR & SINGLE-FUNCTION PROTECTION
PGR-4300 Generator Ground-Fault Relay No CTs required Provides a simple method for tripping a groundfault condition on generators Use with 3- or 4-pole transfer switches Monitors neutral-to-ground integrity
More informationPLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION
PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH
More informationUkujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances
Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1 Characteristics of the Project Parameter Detail
More informationSINAMICS S120 Cabinet Modules Application Shaft Generator Drive
SINAMICS S120 Cabinet Modules Application Shaft Generator Drive For energy-efficient and reliable marine solutions siemens.com/sinamics-s120-cabinet-modules Answers for industry. SINAMICS S120 Cabinet
More informationSiemens Power System Consulting
Siemens Power System Consulting Построение умных сетей распределения электроэнергии Intelligent Distribution Grids Minsk 10th of Restricted Siemens AG 2017 siemens.com/power-technologies Siemens Power
More informationControl System for a Diesel Generator and UPS
Control System for a Diesel Generator and UPS I. INTRODUCTION In recent years demand in the continuity of power supply in the local distributed areas is steadily increasing. Nowadays, more and more consumers
More informationImplementing a Microgrid Using Standard Utility Control Equipment
Implementing a Microgrid Using Standard Utility Control Equipment Tom Fenimore Duke Energy Andy Gould and Larry Wright Schweitzer Engineering Laboratories, Inc. Copyright Duke Energy and SEL 2016 Overview
More informationWhite Paper. Ground Fault Application Guide. WL Low Voltage Power Circuit Breakers
White Paper Ground Fault Application Guide WL Low Voltage Power Circuit Breakers Table of Contents Introduction 3 Need for ground fault tripping 3 Requirements from industry standards 3 National Electrical
More informationUse of Microgrids and DERs for black start and islanding operation
Use of Microgrids and DERs for black start and islanding operation João A. Peças Lopes, FIEEE May 14 17, 17 Wiesloch The MicroGrid Concept A Low Voltage distribution system with small modular generation
More informationA TRIAL OF ALTERNATIVES TO DIRECTIONAL OVERCURRENT PROTECTION ON GRID TRANSFORMERS TO IMPROVE THE NETWORK CAPACITY TO ACCOMMODATE REVERSE POWER FLOW
A TRIAL OF ALTERNATIVES TO DIRECTIONAL OVERCURRENT PROTECTION ON GRID TRANSFORMERS TO IMPROVE THE NETWORK CAPACITY TO ACCOMMODATE REVERSE POWER FLOW Paul PRETLOVE Azzam AL-RIYAMI UK Power Networks UK UK
More informationGrid-Integration of High Power Charging Infrastructure. Johannes Brombach Innovation for ENERCON
Grid-Integration of High Power Charging Infrastructure Johannes Brombach Innovation for ENERCON 1 Agenda 1 Motivation I Electrification of Transport Sector Typical Use Patterns 2 Motivation II Today and
More informationTargeted Application of STATCOM Technology in the Distribution Zone
Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric
More informationRenewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015
Renewables from a TSO Perspective M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015 RTE in Europe 8500 employees Owner and Operator of the Assets 100 000 km UHV and HV lines (400 kv -> 63
More informationAhead of the challenge, ahead of the change. A comprehensive power transmission & distribution with Totally Integrated Power
Ahead of the challenge, ahead of the change A comprehensive power transmission & distribution with Totally Integrated Power siemens.com/energy-management A comprehensive power transmission & distribution
More informationIntegration of Large Wind Farms into Electric Grids
Integration of Large Wind Farms into Electric Grids Dr Mohammad AlZoubi Introduction Development WHAT IS NEXT!! Over the next 12 years, Europe must build new power capacity equal to half the current total.
More informationPresented By: Bob Uluski Electric Power Research Institute. July, 2011
SMART DISTRIBUTION APPLICATIONS &THEIR INTEGRATION IN A SMART GRID ENVIRONMENT Presented By: Bob Uluski Electric Power Research Institute July, 2011 Key Smart Distribution Applications What are the major
More informationSIMULATING ELECTRICAL PERFORMANCE OF STATIONARY FUEL CELLS FOR DISPERSED GENERATION
SIMULATING ELECTRICAL PERFORMANCE OF STATIONARY FUEL CELLS FOR DISPERSED GENERATION Dirk Audring, Gerd Balzer Darmstadt University of Technology Department of Electrical Power Systems Darmstadt, Germany
More informationMicrogrid solutions Delivering resilient power anywhere at any time
Microgrid solutions Delivering resilient power anywhere at any time 2 3 Innovative and flexible solutions for today s energy challenges The global energy and grid transformation is creating multiple challenges
More informationConsequences on Grid Operation by Decentralized Renewable Power Generators
Fakultät für Informations- Medien- und Elektrotechnik Consequences on Grid Operation by Decentralized Renewable Power Generators Consideration in the German Low Voltage and Medium Voltage Directive and
More informationCommercialized storage solutions for enhanced grid operation
Commercialized storage solutions for enhanced grid operation Dr. Andreas Luxa Principal Expert, Low and Medium Voltage Division, Amsterdam The power grid is in transformation: Increasingly complex source/generation
More informationReliable, economical and safe siemens.com/rail-electrification
AC Traction Power Supply Reliable, economical and safe siemens.com/rail-electrification More people, new challenges, one solution: Integrated mobility. Demographic change, urbanization and climate change:
More informationDual Power. Protection. Protection
54 Fault Clearing Systems by Damien Tholomier., AREVA T&D Automation, Canada Dual Power Single Battery What if it? Short circuits and other abnormal power system conditions are very rear, but may result
More informationDocument Requirements for Engineering Review- PV Systems v1.1 12/6/2018
Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Outlined below are the engineering documents and their associated minimum detail requirements for a Distributed Energy Resource (DER)
More informationQCF level: 4 Credit value: 15
Unit 63: Electrical Power Unit code: H/601/1408 QCF level: 4 Credit value: 15 Aim This unit will develop learners understanding of electrical power systems and power distribution and the advantages and
More informationTEST REPORT DIN V VDE V
Test Report issued under the responsibility of: TEST REORT DIN V VDE V 0126-1-1 Report Number....: EFSH16041203-IE-01-L12 Date of issue...: 2016-11-28 Total number of pages... 25 pages Testing Laboratory...
More informationTEST REPORT DIN V VDE V
Test Report issued under the responsibility of: TEST REORT DIN V VDE V 0126-1-1 Report Number....: EFSH16041203-IE-01-L21 Date of issue...: 2016-11-28 Total number of pages... 26 pages Testing Laboratory...
More informationStatic frequency converter couples US paper mill s 25-Hz and 60-Hz electricity grids
Static frequency converter couples US paper mill s 2-Hz and 0-Hz electricity grids Before 0 Hz was adopted as the standard frequency for electricity distribution in the USA, power companies across the
More informationMiniature Circuit-Breakers (MCBs)
Product Overview Miniature Circuit-Breakers (MCBs) Design Tripping characteristics Rated current I n Rated breaking capacity Power supply company product range 5SP3 E 16 - A Standard product range 5SQ2
More informationDER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.
Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations
More information(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)
Technical Paper: Low voltage ride-through testing of wind turbine converters at ABB helps wind turbines meet the requirements of IEC 61400-21 more quickly (by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka
More informationADHERING TO UTILITY INTERCONNECTION STANDARDS MAY NOT GUARANTEE DG SECURITY Wayne G. Hartmann Beckwith Electric Co., Inc. Product Manager, Protection
ADHERING TO UTILITY INTERCONNECTION STANDARDS MAY NOT GUARANTEE SECURITY Wayne G. Hartmann Beckwith Electric Co., Inc. Product Manager, Protection Introduction Interconnection Standards are created and
More informationMVDC PLUS Managing the future grid
MVDC PLUS Managing the future grid Bridge the distance How should we connect Islands, platforms, and remote areas? Connecting weak or unstable grids How will we integrate and stabilize grids? Reduce footprint
More informationDynamic Study of Bonaire Island Power System: Model Validation and Project Experience
Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience Y. Sun 1, 2,*, W. G. Kuijpers 3, E. C. W. de Jong 1,2, and H. Pustjens 3 1 Electrical Energy System, Eindhoven University
More informationProtection of Power Electronic Multi Converter Systems in AC and DC Applications
Protection of Power Electronic Multi Converter Systems in AC and DC Applications Prof. Norbert Grass Technische Hochschule Nürnberg, Institute for Power Electronic Systems, Nuremberg, Germany, Norbert.Grass@th-nuernberg.de
More informationElectronic Load Sensing for Tractors
Electronic Load Sensing for Tractors Dipl.-Ing. U. Lenzgeiger, Dipl.-Ing. (FH) U. Maier, Dipl.-Ing. (FH) P. Schmuttermaier Bosch Rexroth AG Systems Engineering Glockeraustraße 2 89275 Elchingen E-Mail:
More informationComments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules
Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules Submitted to New Jersey Board of Public Utilities By Qado Energy Power Engineering Team August 12, 2011 1 Table of
More informationExperience the Hybrid Drive
Experience the Hybrid Drive MAGNA STEYR equips SUV with hybrid drive Hybrid demo vehicle with dspace prototyping system To integrate components into a hybrid vehicle drivetrain, extensive modification
More informationRegenerative Utility Simulator for Grid-Tied Inverters
Regenerative Utility Simulator for Grid-Tied Inverters AMETEK s RS & MX Series with the SNK Option provides the solution Testing of grid-tied inverters used in solar energy systems is emerging as a major
More informationINTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY
INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,
More informationFeed-in management with Solar-Log
Feed-in management with Solar-Log 1 Publisher: Solare Datensysteme GmbH Fuhrmannstr. 9 72351 Geislingen-Binsdorf Germany International Support Tel.:+49 7428 9418-640 Fax:+49 7428 9418-280 E-mail: support@solar-log.com
More informationExperiences with Wind Power Plants with Low SCR
1 Experiences with Wind Power Plants with Low SCR Lessons learned from the analysis, design and connection of wind power plants to weak electrical grids IEEE PES General Meeting Denver CO, 26 March 2015
More informationCONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation
CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent
More informationGRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS
GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS Prof. Suryanarayana Doolla Department of Energy Science and Engineering Indian Institute of Technology Bombay OUTLINE Intoduction Grid
More informationReal-time Simulation of Electric Motors
Real-time Simulation of Electric Motors SimuleD Developments in the electric drive-train have the highest priority, but all the same proven development methods are not consequently applied. For example
More informationAccidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies
CIGRÉ-EPRI Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS Boston, MA, October 20-22, 2013 http : //www.cigre.org Accidental Islanding of Distribution Systems with Multiple Distributed Generation
More informationDesign Modeling and Simulation of Supervisor Control for Hybrid Power System
2013 First International Conference on Artificial Intelligence, Modelling & Simulation Design Modeling and Simulation of Supervisor Control for Hybrid Power System Vivek Venkobarao Bangalore Karnataka
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationSolutions for Distributed Generation Protection and Control Issues IPCGRID March 28, 2018
Solutions for Distributed Generation Protection and Control Issues IPCGRID March 28, 2018 Mike Jensen 1 Pacific Gas and Electric (PG&E) 40,000 Protective Relays 100+ RAS and SPS 300,000 Solar Connections
More informationAsynchronous generators
Asynchronous generators Contents Product description 13/2 Overview of technical data 13/3 Motor selection data Series G4.R on the basis of Premium Efficiency IE3 13/4 Series GE.R on the basis of High Efficiency
More informationElectrical Energy Engineering Program EEE
Faculty of Engineering Cairo University Credit Hours System Electrical Energy Engineering Program EEE June 2018 Electrical Engineers: What they do? Electrical engineers specify, design and supervise the
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements
Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner
More informationABB Automation World 2012, V. Knazkins, 6 June 2012 Smart Grids and Modern Excitation Systems. ABB Group June 4, 2012 Slide 1
ABB Automation World 2012, V. Knazkins, 6 June 2012 Smart Grids and Modern Excitation Systems June 4, 2012 Slide 1 Agenda The Smart Grid The Modern Excitation Systems Smart Grid Enablers An Example June
More informationEarthing Principles. Symmetra PX 250/500 kw
Earthing Principles Symmetra PX 250/500 kw Table of Contents Earthing Principles... 1 Decoding the Earthing Types... 1 TN Systems... 2 Characteristics... 2 Reference to IEC/EN 60364-4-41 413.1.3... 2
More informationRAPTOR DEFAULT TEST TEMPLATES
RAPTOR DEFAULT TEST TEMPLATES www.smcint.com PAGE 1 OF 12 The Raptor Default Test Templates in Raptor HH June 2015 General parts of main screen: TEST TEMPLATES: Default test templates are factory configured
More informationDistributed Energy Resources
Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired
More informationAswan high dam - Distributed control system AUTOMATION
Aswan high dam - Distributed control system AUTOMATION Power System Overview Aswan High Dam (AHD) -Hydro Power Plant was erected and commissioned in 1972. At the time it was the world's greatest, as well
More informationCabo Verde s new Renewable-Energy-Friendly Grid Code
Cabo Verde s new Renewable-Energy-Friendly Grid Code Bernd Weise DIgSILENT GmbH International Workshop on Renewable Energy Development in Macaronesia and West Africa Praia, Cabo Verde, May 30-31, 2016
More informationDate Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS
Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationElectric Power Delivery To Big Cities
Problem Definition Electric Power Delivery To Big Cities a) Socio-economic incentives are a major factor in the movement of population to big cities b) Increasing demand of electric power has strained
More information34 th Hands-On Relay School
34 th Hands-On Relay School Generation Track Overview Lecture Generator Design, Connections, and Grounding 1 Generator Main Components Stator Core lamination Winding Rotor Shaft Poles Slip rings Stator
More informationCHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM
61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this
More informationRESEARCH PROJECT VERBUNDNETZSTABIL
RESEARCH PROJECT VERBUNDNETZSTABIL Grid control for inverter dominated power systems Soenke Rogalla Fraunhofer Institute for Solar Energy Systems ISE IRED Side Event Workshop Vienna, 17.10.2018 www.ise.fraunhofer.de
More information2006 IEEE PES General Meeting June 2006, Montreal, Canada Paper 06GM0613. Fault Current Limiters - Report on the Activities of Cigre WG A3.
18-22 June 2006, Montreal, Canada Paper 06GM0613 Fault Current Limiters - Report on the Activities of Cigre WG A3.16 presented by: Heino Schmitt, Siemens AG on behalf of Cigre WG A3.16 heino.schmitt@siemens.com
More informationSEVILLA, APRIL Microgeneration and Microgrids (modeling, islanding operation, black start, multi-microgrids) J. Peças Lopes Power Systems Unit
SEVILLA, APRIL 2010 Campus da FEUP Rua Dr. Roberto Frias, 378 4200-465 Porto Portugal T +351 222 094 000 F +351 222 094 050 cmoreira@inescporto.pt www.inescporto.pt Microgeneration and Microgrids (modeling,
More informationSmart Inverter Technology for High PV Penetration
Smart Inverter Technology for High PV Penetration Roland Bründlinger Senior Engineer AIT Austrian Institute of Technology, IEA-PVPS Task 14 International workshop on PV and the electricity grid Sydney,
More informationResearch on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC
Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,
More informationGRID MODERNIZATION INITIATIVE PEER REVIEW
GRID MODERNIZATION INITIATIVE PEER REVIEW GMLC 1.3.29 Grid Frequency Support from Distributed Inverter-based Resources in Hawaii ANDY HOKE, NREL April 18-20, 2017 Sheraton Pentagon City Arlington, VA Devices
More informationDG system integration in distribution networks. The transition from passive to active grids
DG system integration in distribution networks The transition from passive to active grids Agenda IEA ENARD Annex II Trends and drivers Targets for future electricity networks The current status of distribution
More information