1 Air-insulated withdrawable switchboard Medium Voltage Switchgear Instruction Manual MVRD30024A Dispatch Installation Start-up Operation Maintenance

2 Contents 1. Description 1.1 Safety Precautions..... Page Technical Characteristics..... Page Electrical Characteristics..... Page 5 2. Cubicles of Normacel range.... Page 6 3. Instructions for Erection and Installation 3.1 Transport..... Page Dispatch..... Page Handling..... Page Storage..... Page Installation..... Page Connecting cables..... Page Fastening Cubicles together..... Page Assembly of end panels at the side end cubicles..... Page Connections 4. Start-up Connecting busbars..... Page Connecting the earthing circuit between cubicles.... Page Connecting the earthing circuit at the side ends of the switchgear..... Page Connecting MV cables..... Page General..... Page Putting into operation..... Page Operation 5.1 Cubicle Control Panel.... Page Operation of the Circuit Breaker Compartment Circuit Breaker Operation in the Cubicle Putting the circuit breaker withdrawable part into operation.. Page 33 Interlockings... Page 34 Operation Sequence... Page Putting the circuit breaker withdrawable part into test position... Page 35 2

3 Circuit breaker operation out of the Cubicle Putting the circuit breaker withdrawable part into the Cubicle Page 35 Operation Sequence... Page Putting the circuit breaker withdrawable part out of the Cubicle.. Page 37 Operation Sequence..... Page Interlock for draw out/insertion of the circuit breaker withdrawable part.. Page Manual reset (Help Control)... Page Operating the voltage transformer compartment Withdrawable Voltage Transformers... Page Putting withdrawable voltage transformers into service position. Page Putting withdrawable voltage transformers into test position... Page Replacing fuses.... Page Fixed Voltage Transformers... Page Operation of the Earthing Switch... Page 43 Operation sequence to close the earthing switch... Page 44 Operation sequence to open the earthing switch... Page Maintenance 6.1 Cleaning the circuit breaker poles..... Page Changing the transformation ratio of the current transformers..... Page Replacing a voltage Transformer fuse..... Page Cleaning and lubrication... Page Checking the condition of the earthing switch... Page Accessories 7.1 Lever for earthing switch operation.... Page Handle for insertion of withdrawable parts: Circuit breaker and Voltage Transformers. Page Keys for interlocking the earthing switch, withdrawable part (optional)... Page Transport carriage for circuit-breakers... Page Lever for circuit breaker manual reset... Page 47 3

4 1. Safety Precautions! This equipment can be remote controlled and contains current-carrying parts and mechanical elements moving at high speed. The non compliance with these safety precautions may result in severe physical and property damages. Carefully read this manual before proceeding to any handling, operation or maintenance action. The equipments described in this manual have been designed and tested to operate within their rated values. Their use out of those values may result in maloperations which may cause severe physical and property damages. In the cubicles with withdrawable circuit breakers: -Never proceed to checking s on the circuit breaker control (in the cubicles with circuit breakers) when it is closed or when the locking springs are charged. The circuit breaker should be open and the locking springs should be discharged. (See DIVAC Instruction Manual, Tab I-A) - Always leave the circuit breaker either on Service or Test Position, and never in an intermediate position in the cubicle. - Do not use the circuit breaker as the only way to break the circuit in service. Place it also on test position. - Withdraw the circuit breaker from the cubicle before proceeding to any maintenance action. The good performance and the life time of the circuit breaker depend on its correct application, installation and maintenance. Check that these operations are carried out by qualified personnel only, duly aware of precautions and instructions contained in this manual and acquainted with installation and maintenance of Medium Voltage nets and equipments. The circuit breakers are equipped with several security interlocks allowing a simple and safe use. Do not force them. This manual should be easy to access by everyone connected to installation, operation and maintenance of the equipment. 4

5 1.2 - TECHNICAL CHARACTERISTICS Electrical Rated voltage Insulation level Frequency Rated current of busbar Rated current of tee-offs Rated peak withstand current 7, ,5 kv Impulse 95 kv Power frequency 38 kv - 1 minute 50 Hz 630 to 3150 A 630 to 3150 A ka Rated short-time withstand current ka (1 or 3 s) Mechanical Protection degree (IEC 529) Enclosure IP3 (IP4 under request) High quality multifolded 2 mm aluminium galvanised stell sheet sections bolted together. The doors and the side wall cladding are electrostatically coated witn an epoxy-polyester primer and then stove enamelled. Standard colors RAL 7032 RAL 7026 (front control panel) Normal service conditions Minimum ambient temperature -5 C Maximum ambient temperature 40 C Maximum 24 h average temperature 35 C Maximum relative humidity 95 % Maximum site altitude Applicable standards CEI 298, 694, 517, 529, 56, 129 Dimensions Height (H) Depth (D) Width (W): - Tee-off current up to 1250 A - Tee-off current up to 2500 A - Tee-off current up to 3150 A ELECTRICAL CHARACTERISTICS 1000 m (BS standards also applicable) 2100 mm 1500 mm 700 mm 850 mm 1000 mm Rated Voltage Impulse Power frequency (1 min.) Rated current Rated shortcircuit breaking current Rated voltage Impulse Power frequency (1 min.) Rated current Rated shortcircuit breaking current kv kv kv A ka kv kv kv A ka ,

6 2 - Cubicles of Normacel range Incoming/Outgoing Cubicle Legend: A - Busbar compartment 6 - Cables B - Circuit-breaker compartment 7 - Internal arc cover C - Cable compartment 8 - Shutter D - Low voltage compartment 9 - General busbar 1 - Circuit-breaker 10 - Tee-offs 2 - Busbar support 11 - Voltage Capacitor Divider 3 - Bushing 12 - Earthing switch control 4 - Current transformer 5 - Earthing switch Front View Lateral View Fig 1 - Incoming/Outgoing Cubicle 6

7 Fig 2 - Incoming/Outgoing Cubicle optionally with withdrawable cables VT s, with withdrawable busbar VT s and with cables CT s Fig 3a - Busbar Coupling Cubicle optionally with withdrawable VT s at the two half busbar 7

8 Fig 3b - Busbar Coupling Cubicle optionally with busbar Earthing Switch and with Voltage Indicators Fig 4a - Busbar Rising Cubicle optionally with CT s 8

9 Fig 4b - Busbar Rising Cubicle optionally with CT s, with busbar Earthing Switch and with Voltage Indicators Fig 5 - Metering Cubicle optionally with Surge Arrester, with Earthing Switch and with Voltage Indicators 9

10 Fig 6 Fuse Switch Feeder Cubicle Fig 7 Direct Incoming/Outgoing Cubicle optionally with cables CT s and with Earthing Switch 10

11 Fig 8a Double Tier Cubicle (Un=12kV) optionally with withdrawable Vacuum Circuit Breaker or with withdrawable Vacuum Contactor Fig 8b Incoming Cubicle (Un=12kV) suitable to the Double Tier Cubicle on busbar compartment level optionally with withdrawable cables VT s Note: The Busbar Coupling and the Busbar Rising Cubicles with this busbar compartment configuration are available. 11

12 Fig 9 - Incoming/Outgoing Cubicle with busbar CT s and with cables CT s. Optionally for this solution is available the withdrawable cables VT s and the withdrawable busbar VT s (see Fig 2). Note: The Busbar Coupling and the Busbar Rising Cubicles with this busbar compartment configuration are available. 12

13 3- INSTALLATION AND ERECTION INSTRUCTIONS 3.1- Packing information The cubicles will normally be packed for truck or container transport. Fig 10 Special packing Fig 11 Standard packing Dimensions and weights: Cubicles type External packing In Weight dimensions (mm) (A) (kg) W H D Incoming/Outgoing 750 Direct incoming 500 In 1250A 800 Bus section 750 Bus rising Incoming/Outgoing 900 Direct incoming A < In 2500A Bus section 900 Bus rising Incoming/Outgoing 1050 Direct incoming 700 In = 3150A 1100 Bus section 1050 Bus rising

14 3.2 - Delivery The Normacel cubicles are deliveried with the movable circuit breakers immobilized in the "test position". One or several cubicles forming a packing unit will be covered by a thin plastic and are firmly secured on wooden pallets to enable individual transportation and fork lifting.when required by the destination of the cubicles and the type of means of transport other packages are possible. The Fig. 10 and 11 show two types of packages. A package with accessories contains all the material necessary to the site installation: other. A set of screws for the busbar, the earthing connector and for screwing the cubicles to each Several busbar components. A set of copper liners for the busbar junctions. All the necessary accessories for the cubicles expoitation. A plastic bag with the following documentation: -This Instructions Manual ; - The Divac circuit breakers Instructions Manual. After the equipment reception : To check the material list. To check the presence of accessories bag. If anomalies are detected, please inform the transporter. Important :The cubicles must be unpacked only at the installation site. Cubicles unpacking To remove the plastic cap. To dismount the wooden platform (fixed to the cubicle with 4 screws) - 2 at the front compartment and - 2 at the rear compartment. In the case of the cubicles with drawout voltage transformers, the following operations must be done in order to have access to the 2 screws at the front compartment : - To withdraw the truck to the cubicle outside (see Fig 12); - To unscrew the 2 frontal screws; - To introduce the truck in the test position; - To immobilize the truck in the that position; - To lift the cubicle and to remove the wooden pallet. 14

15 Note : This equipment is completely identified by the manufacturing order number and by the layout drawing number indicated in the signaletic plate (see fig. 13), located in the switchboard right upper part: Fig 12 Cubicle with drawout cables VT s Type Manufacturing order Manufacturing year Layout drawing Service voltage Rated voltage Rated frequency kv kv Hz Rated busbar current A Rated short time current ka s Auxiliaries rated voltage Protection degree: IP Applicable standard: CEI Handling Fig 13 Signaletic plate for the switchboard All the cubicles are equipped with a base plate suitable to move the cubicles over rollers. When they are lifting means, it must be used the lifting equipments mounted in the cubicles roof (see fig 14): As the cubicles with circuit breaker are delivered with this in immobilized in the test position, its handling must be done with it in the test position (like in the expedition). 15

16 Fig 15 Normacel cubicle handling Fig 14 Lifting equipment 16

17 3.4 - Storage While the cubicles are not mounted, we recommend its sotrage in a well ventilated place, protected from dust and water. Storage temperature : -5 to 40 ºC, depending on the hygrometric conditions. -5 ºC to hygrometry 30% R.H.(Relative Humidity) +40 ºC to hygrometry 70%R.H. If these limits cannot be guaranteed in the storage place. it is necessary to assure that the equipment is well conditionned before delivery. It must be avoided to keep the equipment in places with high and fast temperature variations. It must be checked the completely absence of aggressive vapours like, for exemple, the sulphur anhydride (SO 2 ). Recommendations depending on the storage type : Plastic packing : to remove the plastic in order to avoid condensation phenomena. Thermally welded tissu packing with dehumidifier sacs: the equipment must be stored within its original packing which must not be cutted in any case Installation For a confortable exploitation the cubicles need: mm in the front corridor, for handling the circuit breaker truck to 100 mm at the rear for ventilation purpose to 100 mm between the switchboard ends and the wall. Cubicles installation The self supported frame, the cables connecting high and the circuit breakers position at the middle of the cubicle reduce the implantation exigences: - to a simple floor plate levelness. - to a floor fastenning, after the installation of all cubicles. Width (A) mm In B (mm) A <In 3150 A

18 Implantation and MV and LV crossing cables ( dimensions in mm ) Fig 16 Implantation drawing for Normacel 17,5 Incoming/Outgoing cubicle 18

19 The cubicles floor fastening will depend on the floor levelness. So: - if the floor levelness is regular: - 2 fixing points at the intermediate cubicles - 4 fixing points at the end cubicles - if the floor levelness is irregular: - 4 fixing points in all cubicles. See the following sketch, A = 450 mm Fig 17 Sketch for fixing points A Fig 18 Side view Fig 19 Front view Fig 20 Top view 19

20 Checking the screws fastening It is advisable to check periodically the screws fastening of the main circuit and auxilliaries. - Screws for the switchboard fitting and fastening to the floor - Screws for main circuit fastening (electrical contacts) - Screws for fastening the copper bars to the support insulators All the screws are 8.8 class. The recommended fastening couples are indicated in the following table: General fastening and electrical contacts Fastening couple Oil or mass (Nm) mass MOS2 (Nm) Without Oil (Nm) Mechanical fastening in metal insertions of moulded epoxy resin components (Nm) M M M M M

21 Cables installation In the Fig 21 are indicated the cables position (exemple of 4 cables/ phase). Fig 21 Solution for 4 cables instalation per phase Width (A) mm In B (mm) C (mm) D (mm) A <In 3150 A Fastening the cubicles to each other To remove the circuit breakers trucks from the cubicles inside. To dismount the 4 lifting equipment (spanner 13). The cubicles are fastened to each other through 5 M8 screws and nuts, in the points indicated below: - 3 points at the front compartment; - 2 points at the cables compartment. Fig 22 Fastening cubicles to each other Fig 23 Sketch detail 21

22 3.5.3 End panels fitting At the end cubicles it is necessary to obturate the busbar compartment with the panel (1) and the front compartment with the panel (2). These panels are fastened from the outside with 8 M8x50 screws. If there is no auxilliary cabinet at the end of the switchboard, it is necessary to obturate the LV cables gutter (see Fig 24) LV end panel Obturador 1 2 Fig 24 Skech for end panels fitting 22

23 3.6 - Connections General information and connection instructions In the busbar, earthing circuit and cables bars connection, it is necessary to respect the assembling sense of all parts and to fasten the screws with the right couple. To use the screws delivered within the accessories pack or screws with the same reference. Contact surface preparation instructions When one connect copper with copper or tinned alluminium with tinned alluminium, there is not necessary any surface preparation. Nevertheless, when one connect alluminium with copper, it is necessary to polish those surfaces with a metallic brush and to lubrificate them with "contactal" or with neutarl vaseline (see references in page 42) Busbar connections After removing the internal arc plate for accessing to the busbar (M6 screws, 10 spanner), make the busbar connections between cubicles as indicated in the following pages.. The bars/phase quantity depends on the busbar rated current (see connections table in the following pages). Components references for the busbar connection between cubicles In order to assemble the different components in the correct position, use the Table 1. The round bracket figures (Fig 25a) are related to the busbar connections skeches. Table 1 Junction/ Fase Busbar/ phase InBG 630A 1 bar (63x5) 630<InBG 1250A 2 bars (63x5) 1250<InBG 1600A 3 bars (80x5) 1600<InBG 2500A 2 bars (80x10) InBG=3150A 3 bars (100x10) In 630A 1 connection (63x5) See table 25a See table 25a See table 25a See table 25a See table 25a 630<In 1250A 2 connections (63x5) - See table 25a See table 25a See table 25a See table 25a 1250<In 1600A 3 connections (80x5) - - See table 25a See table 25a See table 25a 1600<In 2500A 2 connections (80x10) See table 25a See table 25a In=3150A 3 connections (100x10) See table 25a 23

24 1 bar (63x5) In Busbar=630A 1 connection (63x5) In Panel=630A (2)+(5)+ Screws M10x30H 2 bars (63x5) In Busbar =1250A 1 connection (63x5) In Panel =630A (2)+(3)+(5)+(9)+ Screws M10x40H 2 bars (80x10) In Busbar =2500A 1 connection (63x5) In Panel =630A (2)+(3)+(5)+(9)+ Screws M10x55H 2 bars (63x5) In Busbar =1250A 2 connections (63x5) In Panel =1250A 2 bars (80x10) In Busbar =2500A 2 connections (63x5) In Panel =1250A 2 bars (80x10) In Busbar =2500A 2 connections (80x10) In Panel =2500A (2)+(3)+(5)+(6)+ Screws M10x40H (2)+(3)+(5)+(6)+ Screws M10x55H (2)+(3)+(5)+(6)+ Screws M10x55H 2 bars (80x10) In Busbar =2500A 3 connections (80x5) In Panel =1600A (2)+(3)+(5)+(6)+(7)+ Screws M10x55H 3 bars (80x5) In Busbar =1600A 1 connections (63x5) In Panel =630A (2)+(3)+(4)+(5)+(9)+(10)+(12)+ Screws M10x45H 3 bars (100x10) In Busbar =3150A 1 connections (63x5) In Panel =630A (2)+(3)+(4)+(5)+(9)+(10)+(12)+ Screws M10x90H 3 bars (80x5) In Busbar =1600A 2 connections (63x5) In Panel =1250A 3 bars (100x10) In Busbar =3150A 2 connections (63x5) In Panel =1250A 3 bars (100x10) In Busbar =3150A 2 connections (80x5) In Panel =2500A 3 bars (80x5) In Busbar =1600A 3 connections (80x5) In Panel =1600A 3 bars (100x10) In Busbar =3150A 3 connections (80x5) In Panel =1600A 3 bars (100x10) In Busbar =3150A 3 connections (100x10) In Panel =3150A (2)+(3)+(4)+(5)+(6)+(10)+(12)+ Screws M10x45H (2)+(3)+(4)+(5)+(6)+(10)+(12)+ Screws M10x90H (2)+(3)+(4)+(5)+(6)+(10)+(12)+ Screws M10x90H (2)+(3)+(4)+(5)+(6)+(7)+(12)+ Screws M10x45H (2)+(3)+(4)+(5)+(6)+(7)+(12)+ Screws M10x90H (2)+(3)+(4)+(5)+(6)+(7)+(12)+ Screws M10x90H Fig 25a Skecth for the main busbar connections between cubicles 24

25 Components references for the busbar ends connection In order to assemble the different components in the correct position, use the Table 2 The round bracket figures (Fig 25b) are related to the busbar connections skeches. In the switchboard end cubicles case or in the busbar section case (bus coupling and bus rising cubicles), one can fit in the phase one or two reinforcements in orde to maitain the shunt busbar in the insulating support. Table 2 Junction /Phase Busbar /Phase InBG 630A 1 bar (63x5) 630<InBG 1250A 2 bars (63x5) 1250<InBG 1600A 3 bars (80x5) 1600<InBG 2500A 2 bars (80x10) InBG=3150A 3 bars (100x10) In 630A 1 connection (63x5) See table 25b See table 25b See table 25b See table 25b See table 25b 630<In 1250A 2 connections (63x5) - See table 25b See table 25b See table 25b See table 25b 1250<In 1600A 3 connections (80x5) - - See table 25b See table 25b See table 25b 1600<In 2500A 2 connections (80x10) See table 25b See table 25b In=3150A 3 connections (100x10) See table 25b 25

26 1 bar (63x5) In Busbar=630A 1 connection (63x5) In Panel=630A (2)+(5)+(11)+ Screws M10x30H 2 bars (63x5) In Busbar=1250A 1 connections (63x5) In Panel=630A (2)+(3)+(5)+(9)+(11)+ Screws M10x40H 2 bars (80x10) In Busbar=2500A 1 connection (63x5) In Panel=630A (2)+(3)+(5)+(9)+(11)+ Screws M10x55H 2 bars (63x5) In Busbar=1250A 2 connections (63x5) In Panel=1250A 2 bars (80x10) In Busbar=2500A 2 connections (63x5) In Panel=1250A 2 bars (80x10) In Busbar=2500A 2 connections (80x10) In Panel=2500A (2)+(3)+(5)+(6)+(11)+ Screws M10x40H (2)+(3)+(5)+(6)+(11)+ Screws M10x55H (2)+(3)+(5)+(6)+(11)+ Screws M10x55H 2 bars (80x5) In Busbar=2500A 3 connections (63x5) In Panel=1600A (2)+(3)+(5)+(6)+(7)+(11)+(12)+ Screws M10x55H 3 bars (80x5) In Busbar=1600A 1 connection (63x5) In Panel=630A (2)+(3)+(4)+(5)+(9)+(10)+(11)+(12)+ Screws M10x45H 3 bars (100x10) In Busbar=3150A 1 connection (63x5) In Panel=630A (2)+(3)+(4)+(5)+(9)+(10)+(11)+(12)+ Screws M10x90H 3 bars (80x5) In Busbar=1600A 2 connections (63x5) In Panel=1250A 3 bars (100x10) In Busbar=3150A 2 connections (63x5) In Panel=1250A 3 bars (100x10) In Busbar=3150A 2 connections (80x5) In Panel=1600A 3 bars (80x5) In Busbar=1600A 3 connections (80x5) In Panel=1600A 3 bars (100x10) In Busbar=3150A 3 connections (80x5) In Panel=1600A 3 bars (100x10) In Busbar=3150A 3 connections (100x10) In Panel=3150A (2)+(3)+(4)+(5)+(6)+(10)+(11)+(12)+ Screws M10x45H (2)+(3)+(4)+(5)+(6)+(10)+(11)+(12)+ Screws M10x90H (2)+(3)+(4)+(5)+(6)+(10)+(11)+(12)+ Screws M10x90H (2)+(3)+(4)+(5)+(6)+(7)+(8)+(11)+(12) Screws M10x45H (2)+(3)+(4)+(5)+(6)+(7)+(8)+(11)+(12) Screws M10x90H (2)+(3)+(4)+(5)+(6)+(7)+(8)+(11)+(12) Screws M10x90H Fig 25b Sketch for the main busbar ends connection 26

27 Busbar position In Busbar = 630 A 1 bar 63 x 5 In Busbar = 1250 A 2 bars 63 x 5 or In Busbar = 2500 A 2 bars 80 x 10 In Busbar = 1600 A 3 bars 80 x 5 or In Busbarl = 3150 A 3 bars 100 x 10 Fig 25c Main busbar compartment with busbar position 27

28 Connection of the earthing circuit between cubicles The cubicles main earthing conductor is placed at the bottom of the rear socket. After coupling the cubicles, connect the two portions of the earthing conductor. Fig 26 Connection of the earthing circuit between cubicles Connection of the earthing conductor at the end of the switchboard At the end of the switchboard the main earthing conductor is connected to the earth pit. The connection cable must be connected to the cubicles earthing circuit as shown below. Fig 27 End of the switchboard Fig 28 Connection of the earthing conductor Legend: 1 - Screw M 8x Washer cfa Washer cfa Main earth collector 5 - Plait for the switchboard connection to the substation 6 - Flat washer M Screw M 8x NutH M Nut MM

29 MV cables connection Connection options allowed by the equipment - Cubicle In 1250A (700 mm wide) 1 or 2 cables per phase with 500 mm 2 maximum section - Cubicle 1250A < In 3150A (1000 mm wide) 2 or 4 cables per phase with 500 mm 2 maximum section General and connection instructions We guarantee the basic characteristics, within the limits below stated: - The maximum usable cable section is of 500 mm 2 ; - The maximum with permitted for connection is of 60 mm (700mm wide); - When connecting the MV cables the correct positioning of the terminals, the fastening plates and the screws as well as the proper fastening torques, must be respected; - The connection locations are delivered undrilled. Thus being, it is necessary to drill them on the spot according to the type of terminals used. The drilling information below indicated is according to terminals in compliance with current manufacturing standards. The use of 500 mm 2 Aluminium terminals (6 holes) or above is not possible. Anyhow, the use of other kind of terminals is possible as long as their dimensions are kept within the limits defined above in the basic characteristics guarantee. In order to permit a simple and effective drilling to obtain a correct spacing between holes, the following solution can be adopted : - immobilise the terminal at the connection location with the help, of quickacting clamps, respecting the positioning measures; - centre-plot the drilling positions using the terminal as a template; - remove the terminal; - remove the connection location; - drill the holes and remove chipped edges, if necessary; - assemble the connection Connection locations drilling information according to the type of terminal used Fig 29a Connections for ail terminals not exceeding 240 and 300 and 400 mm 2 AI-Cu terminals Fig 29b Connections for 500 and 630 mm 2 AI-Cu terminals and 300 and 400 mm 2 Al terminals 29

30 Contact surfaces preparation instructions If the connections are in copper and the terminals are in copper or tinned aluminium, no preparation of the contact surfaces is needed-however when connecting bare aluminium terminals, it is recommended to polish the surfaces with a wire brush or emery paper followed by "contactal" or neutral vaseline greasing. Fig 29c Cable termination Legend: 1 - Washer CFA Cable connection bar 3 - Cable 4 - Cable 5 - Cable passage 6 - Cable clamping 7 - Middle cables screen plates 8 - Side cables screen plates 9 - Support plate of the cables screen plates 10 - Screw M 8x Screw M8x Rivet nut M NutHM8 Fig 30 - Sketch showing cable connection 30

31 The cables passage must be cut as shown in figure 32 Fig 31 PVC cable passage Fig 32 Cut-out process Assembly sequence - After having cut the cable passages (5) (in case of one cable/phase cut only one) fit them to the cables; - Connect the terminals (3) and (4) to the connection locations (2), respecting the correct position indicated on the sketch; - Insert the bottom cables screen plate (8); - Locate the cables passage (5) over the cables screen plates (7) and (8); - Place the clamping assemblies (6) and (11) on each side of the cables, under the cable passages. The assembly is fixed over the bottom plates as shown in sketch, with 2 screws M8x50, 1 nut A, M8H and 1 washer CFA 8; - Connect the cables screen plaits to the cables screen plates. In case of 4 cables/phase assembly, insert 3 double punching bottom plates (7) between the two side plates. 4 - SETTING TO WORK 4.1- General The Normacel cubicles are mechanically and electrically inspected before despatch. If the equipment should be stored in a damp spot, it is recommended to warm up the premises or to feed the cubicles heating elements, if supplied, during 24 hours before setting to work. In any case it is necessary to carry out a certain number of checking procedures before any operation: - Checking of the withdrawable circuit-breaker, in particular the contact fingers; - The ease of the plugging/unplugging operations; - Operation of the mechanical interlocks; - Before connecting the cables, measure the insulation resistance of the switchboard with a megaohmimeter (Disconnect any existing external circuits). - Proper execution of the cable connections; - Absence of any strange object inside the cubicles. Do not try under any circumstance to operate a lever or link inside the control mechanism, if either the dosing spring is armed, either the circuit-breaker is closed (opening spring armed) or if the LV feeding circuits are not interrupted (AC or DC). For greater safety, remove the fuses from the recharging motor of the control mechanism. If necessary perform a triple manual operation, opening - closing - opening, to disarm the opening and closing springs of the control mechanism. For any intervention on the circuit-breaker or its control mechanism, look it up in the respective manual. 31

32 4.2 - Voltage feeding For the first voltage feeding of the switchboard proceed as following description: - Make sure all the circuit-breakers are open and in the sectioning position, the earthing switches are open and the cable access panels are fastened. First incoming cubicle: - Feed the cables. Check if the neon lamps from the voltage indicator case lighten; - Feed the busbar by plugging, locking and closing the circuit-breaker (see "Operation" chapter). Second incoming cubicle: - Feed the cables. Check if the neon lamps from the voltage indicator case lighten; - Check if the incoming supplies are in phase. To check the good performance of the phase agreement case, connect the case between the two phases of the first incoming: The lamp should lighten. - Insert the phase agreement case in the upper socket (L1) of the voltage indicator case of one of the cubicles; - Insert the male plug of the phase agreement case's wire in the upper socket (L1) of the voltage indicator case of the other cubicle. If there is a phase agreement the neon lamp of the phase agreement case does not lighten; - Repeat the same operations for phases L2 and L3. First Incoming cubicle Second Incoming cubicle Fig 33 Phase agreement control in Incoming cubicles 32

33 5 - OPERATION Control panel of the cubicle. Legend: Fig 34 Frontal control panel of Normacel Incoming/Outgoing cubicle 1 - Door locker of the circuit-breaker compartment 2 - inserting hole for the maneuver lever of the earthing switch 3 - Mimic diagram of the earthing switch condition (Open/Closed) 4 - Anti-return handle 5 - Earthing switch key lock in the closed position 6 - Earthing switch key lock in the opened position 7 - Voltage indicators 8 - Interdiction lock for the circuit-breaker insertion in the cubicle 9 - Coupling Latches of the transport carriage to the cubicle 5.2- Operation of the circuit-breaker compartment The Circuit-breaker has 2 working positions: - Plugged in (Service Position) - Withdrawn (Test Position) Operation of the circuit-breaker at the cubicle Placing the movable part in the service position The circuit-breaker movable part can be leaded to the service position both with the circuit-breaker compartment door closed and opened, see photographs 35 and 36. To insert the circuit-breaker (with the door open), use the lever referred in the Accessories section, inserting the tool in the square head of the worm screw and while pressing, rotate the tool clockwise. See Fig 35. Note: Placing the circuit-breaker in the service position with the door closed is identical to the open door situation, having now to insert the lever through the door hole. See Fig

34 Fig 35 - Circuit-breaker movable part with the compartment door opened Fig 36 - Circuit-breaker movable part with the compartment door closed The signal that the circuit-breaker arrived its inserted position is signalized by the "click" that sounds in the clutch when the lever turns in false. INTERLOCKINGS The circuit-breaker can not be leaded to the service position if: a) The earthing switch is closed. Otherwise, when the circuit-breaker starts its movement, there is a interlock that acts on the clutch, preventing the circuit-breaker insertion; b) The LV plug is not pulled in. The associated interlock provokes the clutch actuation, preventing thus the circuit-breaker insertion, c) It's closed. When trying to insert it closed, an interlock provokes its tripping, just after the start of the movement; Operating sequence to place the circuit-breaker in the service, position 1º- Assure that the earthing switch is open; 2º- Assure that the LV plug is pulled in. See Fig 38 To pull in the LV plug, push the interlocking piece and pull in the plug. After pulled in rotate the plug fixation lever and let the interlocking piece return to the initial position; 3º- Assure that the circuit-breaker is opened; 4 - Insert the circuit-breaker. 34

35 Placing the movable part in the test position To place the circuit-breaker in the test position makes use of the same lever used to place it in the service position. The rotation direction is for the left (the reverse of the insertion). As in placing in service, the signal that the circuit-breaker arrived its test position is signalized by the "click" that sounds in the clutch when the lever turns in false. To remove de circuit-breaker, there must be previously the care of opening it. Otherwise the circuit-breaker will trip before the start of the withdrawal movement Operating the circuit-breaker out of the cubicle Placing the circuit-breaker inside the cubicle To place the circuit-breaker inside the cubicle, use the transport carriage referred in the «Accessories» section. Operating sequence for the circuit-breaker insertion in the cubicle - After placing the circuit-breaker upwards the transport carriage, move it up to the circuit-breaker compartment, - Open the circuit-breaker compartment door - See Fig 37; - Connect the transport carriage to the cubicle. Tighten the latches (located at the side handles) and make them fit in the cubicle spangles. In case the latches do not easily fit or the circuit-breaker is over or under the circuit-breaker compartment level, the transport carriage levelers must be rotated - See Fig 42 e 64; - Uncouple the circuit-breaker transport carriage. Move the circuit-breaker inside the cubicle and couple the circuit-breaker latches in the cubicle - See Fig 40 and 41; - Uncouple the transport carriage of the cubicle tightening the appropriated latches. Fig 37 Circuit-breaker compartment door Fig 38 LV circuit-breaker connection 35

36 Fig 39 Circuit-breaker transport carriage connect to the cubicle Fig 40 Extract the circuit-breaker up to the transport carriage Fig 41 Extract the circuit-breaker from the cubicle Fig 42 Extract the circuit-breaker from the cubicle 36

37 Withdrawing the circuit-breaker out of the cubicle The operating sequence is like placing the circuit-breaker inside Withdrawing operating sequence - Open the circuit-breaker compartment door - Couple the transport carriage with the cubicle (Fig. 39) - Pull circuit-breaker upwards transport carriage and connect the clicks (fig. 40 e 41) - Remove the transport carriage (fig. 42) Removal impediment / Circuit-breaker insertion in the cubicle An optional interlock against circuit-breaker insertion exist. Fig 43 Interlock against Circuit-breaker insertion Circuit-breaker manual rearming (Emergency control) Without voltage in the electrical motor of the control mechanism, or during mechanical tests, the circuit-breaker rearming can be done manually with an emergency crank handle, making suave vertical movements, in any position of the circuit-breaker. The crank handle must be removed before the electrical closing of the circuit-breaker. To connect the circuit-breaker set the green button - See Fig 46 To disconnect the circuit-breaker set the red button - See Fig 47 37

38 Fig 44 Closing spring recharge system Fig 45 Closing spring recharge system Fig 46 To connect the circuit-breaker set the green button Fig 47 To disconnect the circuit-breaker set the red button 38

39 5.3 - Voltage Transformers exploration Normacel cubicles are able to use fixed or withdrawable voltage transformers Withdrawable Transformers Withdrawable transformers can be moved with voltage in the cubicle. The down picture represents the VT s truck Fig 48 Withdrawable truck-mounted voltage transformers Placing VT s in the operating position For the insertion of VT s the door must be closed Fig 49 Voltage Transformers in the operating position 39

40 Fig 50 Withdrawn Voltage Transformer position For the VT s insertion use the correct crank handle indicated in the acessories. The insertion is like the circuit-breaker. After begin the insertion, the door is interlocked so can't be opened. In picture 51 we can see the insertion of VT s to the operating position in a cable compartment and in the 52 in a busbar compartment (of a busbar coupler cubicle). Fig 51 Insertion of Cables VT s Fig 52 Insertion of Busbar VT s Placing VT's in the test position To place the VT's in the test position must use the same crank handle, but now with a inverse rotation To open the door compartment, the VT's must be in the test position Fuses changing Sequence operation for the changing - Place the VT's in the withdrawn position - Remove the voltage compartment door (Fig 53) - Remove the insulating PVC protections (Fig 54) - Fuses changing (Fig 55) - Replace the Insulating PVC protections in the same position and tigthen the screws. 40

41 Fig 53 Cables compartment door opening Fig 54 Fuses changing Fig 55 Fuse changing 41

42 5.3.2 Fixed Voltage Transformers In this version we can have fuses or not and to open the transformer door compartment the earthing switch must be closed. Fuses changing: - Put the cubicle out of service disconnecting the circuit-breaker. - Place the circuit-breaker in the test position. - Close the earthing switch. - Open the door compartment. - Remove the insulating PVC protection. - Change the fuses. - Replace the PVC protections in the rigth position and tighten the screws. - Close the door. - Open the earthing switch. - Setting the cubicle to work again 42

43 5.4 - Earthing switch manoeuvre The earthing switch mouvement is independent of the operator action. Interloking The earthing switch can't be closed if : - circuit breaker isn't in the test position; - Key interlock isn't in the open position, (in the cubicles with this option). Fig 56 ES in open position Introduce handle to close the ES Fig 57 ES open position interlock Fig 58 ES in close position The handle position to open the ES Fig 59 ES close position interlock 43

44 Sequence operations Earthing switch closing: - Check if the circuit breaker is in the test position; - Check if the earthing switch isn't interlocked in the opened position (Fig 57); - Introduce the operating handle in the opening, with the extremity turned up (Fig 56); - Push down and maintain during the beginning of the earthing switch closing, the anti-return handle, placed by the side of the opening (Fig 56); - Turn around the operating handle with the clock pointers orientation; - Must be a complete mouvement with approximately 180º (Fig 58); - Take out the operating handle. Earthing switch opening: - Check if the earthing switch isn't interlocked in the closed position; - Introduce the operating handle in the opening, with the extremity turned down (Fig 58); - Push down and maintain during the beginning of the earthing switch openning, the antireturn handle, placed by the side of the opening (Fig 56); - Turn around the operating handle with the clock pointers contrary orientation; - Must be a complete mouvement with approximately 180º (Fig 58); - Take out the operating handle. 6 - MAINTENANCE For all instructions referring to maintenance of circuit-breaker or control mechanism, report to correspondent instructions manuals Cleaning of the circuit-breaker chambers - It is advisable to clean the outside of the circuit-breaker chambers when the switchgear truck is withdrawn; - Clean the dust with a dry cloth or slightly soaked in a degreasing agent ( trichloretane, for example) in case of being much greasy; - The cleaning frequency must be deternined according to the atmospheric pollution of the environment which may considerably from one place to another; - In case the circuit-breaker chambers are much dirty then it is advisable to verify the other circuit-breakers and their cleaning if dirty; Changing the transformation ratio of the Current Tranformers The changing of the CT s ratio can be done in two different ways, depending on type transformers: - Primary serial/parallel connection. Must access the cable compartment. - By secondary tapping. Changing must be done in the low voltage compartment. 44

45 6.3 - Voltage Transformers fuse replacement See Fuses changing Cleaning and lubrication - Electrical contacts: The sectioning contacts are prepared in the factoty. In normal operating conditions they do not need to be lubricated again. In case of severe operating conditions ( corrosive atmosphere, dust, frequent plugging and unplugging, etc.) we advise that the condition of the parts should be checked once a year, cleaned and lubricated if necessary. For that purpose: Degrease completely using a solvent of the tetrachloretane type (under no circunstance should a detergente be used); Lubrify with a thin layer of neutral vaseline. To avoid over-lubrication: Lubrify the plug-in contacts but not the contact fingers; Clean the excess of vaseline with a dry cloth. - Articulated mechanical parts lubrication. Reference of the suitable products Product Type Reference Contactal grease (electrical parts) Neutral industrial vaseline Contactal Neutral industrial vaseline Molybdenum Disulphide grease (Mechanical parts) Lubrymoly M1Type Solvent - 45

46 6.5- Checking the conditions of the earthing switches contacts The earthing switches contacts do not suffer any erosion in normal operation.however, if a closing operation is made onto a short-circuit with a high fault current peak, or some operations with a medium value current, it is necessary to check the state of the contacts and remove any pearling with a soft emery paper. 7. Acessories Earthing switch operating handle - See Fig Crank handle for withdrawable circuitbreaker and Voltage transformers trucks - See Fig 61. Fig Keys for interlocking the earthing switch, withdrawable part (optional)-see Fig 62. Fig 61 Fig 62 46

47 7.4 - Circuit-breaker truck transport carriage One circuit-breaker transport carriage by Normabloc. To introduce or remove the circuit-breaker, should couple the transport carriage to the cubicle, introducing the interlock clicks. Only after that, be able to introduce or remove the circuit-breaker. Interlocking If the couple isn t correct, a interlock impede the circuit-breaker mouvement on the transport carriage - See Fig 63. Fig Circuit-breaker manually rearming handle - See Fig 64. Fig 64 47

48 EFACEC AMT Aparelhagem de Média Tensão, S.A. Porto Arroteia Leça do Bailio Apartado S.Mamede de Infesta Codex Portugal Telef: (+351) Fax: (+351) Exportação Arroteia Leça do Bailio Apartado S.Mamede de Infesta Codex Portugal Telef: (+351) Fax: (+351) Lisboa Rua da Garagem, 1 Apartado 527 Carnaxide 2796 Linda-a-Velha Codex Portugal Telef: (+351) Fax: (+351)

1. Safety practices General Introduction Standards...3

1. Safety practices General Introduction Standards...3 1. Safety practices...2 2. General...3 2.1 Introduction...3 2.2 Standards...3 3. Technical data...3 3.1 Designation...3 3.2 Electrical ratings and dimensions...4 3.3 Fixation...6 3.4 Connecting terminals...6

More information

PIX-H Metal-clad switchgear up to 17.5kV

PIX-H Metal-clad switchgear up to 17.5kV AIR INSULATED SWITCHGEAR PIX-H Metal-clad switchgear up to 17.5kV for high rated applications Technical Specifications AREVA T&D Summary - Technical description... 3 - Standards... 6 - PIX in detail...

More information

MEDIUM VOLTAGE CE-B36 METAL CLAD SWITCHBOARDS. CE - B36 - C - en - REV

MEDIUM VOLTAGE CE-B36 METAL CLAD SWITCHBOARDS. CE - B36 - C - en - REV CE - B36 - C - en - REV.00 2011.9 EDIU VOLTAGE EDIU VOLTAGE APPLICATION CE-B etal Clad switchboards are designed for use in public and industrial distribution system up to 36kV for the operation and protection

More information

SYSclad switchboard equipped with draw out type vacuum circuit breaker closed dooroperationoperation. SYSclad 12 17,5kV A.

SYSclad switchboard equipped with draw out type vacuum circuit breaker closed dooroperationoperation. SYSclad 12 17,5kV A. SYSclad switchboard equipped with draw out type vacuum circuit breaker closed dooroperationoperation 630 3150A SYSclad 12 17,5kV 16 31,5kA Generalities SYSclad is a medium voltage switchboard metal clad

More information

Metal Clad Air Insulated Switchgear

Metal Clad Air Insulated Switchgear Metal Clad Air Insulated Switchgear 1/ SecoGear Metal Clad Switchgear Features Fully metal-clad Equipped with Embedded pole VCB Full Front access (can be installed against wall) Perfect interlocking system

More information

MEDIUM VOLTAGE CE-B METAL CLAD SWITCHBOARDS. CE - B - C - en - REV

MEDIUM VOLTAGE CE-B METAL CLAD SWITCHBOARDS. CE - B - C - en - REV MEDIUM VOLTAGE MEDIUM VOLTAGE APPLICATION CE-B Metal Clad switchboards are designed for use in public and industrial distribution system up to 24kV for the operation and protection of lines, generators,

More information

KYN28A-12 (GZS1) A.C METALCLAD REMOVABLE SWITCHGEAR FOR INDOOR USE CHINATCS

KYN28A-12 (GZS1) A.C METALCLAD REMOVABLE SWITCHGEAR FOR INDOOR USE CHINATCS KYN28A-12 (GZS1) A.C METALCLAD REMOVABLE SWITCHGEAR FOR INDOOR USE CHINATCS 2001.09 KYN28A-12 (GZS1) A.C Metalclad Removable Switchgear for Indoor Use --------The Leader in Switchgear Up to 12kV 1. The

More information

MEDIUM VOLTAGE CE-B METAL CLAD SWITCHBOARDS. CE-B-C-en-REV

MEDIUM VOLTAGE CE-B METAL CLAD SWITCHBOARDS. CE-B-C-en-REV CE--C-en-REV.04 2016.1 MEDIUM VOLTAGE MEDIUM VOLTAGE APPLICATION CE- Metal Clad switchboards family are designed for use in public and industrial distribution system up to 40,5kV for the operation and

More information

with Vacuum Circuit Breaker HAF

with Vacuum Circuit Breaker HAF M E T A L - C L A D S W I T C H G E A R Safety and Reliability with Vacuum Circuit Breaker HAF Flexible Design and Compact with Vacuum Circuit Breaker HVF Easy Installation and Maintenance We build a better

More information

GE Industrial Solutions. User/Installation Manual for 4.76kV -15kV SecoBloc

GE Industrial Solutions. User/Installation Manual for 4.76kV -15kV SecoBloc GE Industrial Solutions User/Installation Manual for 4.76kV -15kV SecoBloc Index General Scope...3 Standards...3 Operating conditions...3 Technical specification...3 Basic structure Features...4 Operation...4

More information

UniGear. Technical Guide

UniGear. Technical Guide UniGear Technical Guide CONTENTS 0 CONTENTS 1.1 Compartments 1/2 1.2 Components of the structure 1/3 1.2.1 Hot-galvanized steel sheet 1/3 1.2.2 Painted steel sheet 1/4 1.2.3 Copper 1/5 1.2.4 Insulating

More information

GE Consumer & Industrial Power Protection. New. SecoGear kV Metal-clad Switchgear. GE imagination at work

GE Consumer & Industrial Power Protection. New. SecoGear kV Metal-clad Switchgear. GE imagination at work GE Consumer & Industrial Power Protection New SecoGear 12-24kV GE imagination at work General SecoGear metal-clad switchgear is designed and manufactured with advance technology and has been comprehensively

More information

Air-insulated switchgear UniGear type ZS1

Air-insulated switchgear UniGear type ZS1 Air-insulated switchgear UniGear type ZS1 ABB Power Technologies / 1-7074 D 12-03-2003 - Air-insulated switchgear UniGear type ZS1 ABB Power Technologies / 2-7075 D 1 2-03-2003 - Rated voltage kv 12 17.5

More information

Medium Voltage Distribution PIX. Air Insulated Switchgear up to 24 kv PARS TABLEAU

Medium Voltage Distribution PIX. Air Insulated Switchgear up to 24 kv PARS TABLEAU Medium Voltage Distribution PIX Air Insulated Switchgear up to kv PIX Air Insulated Switchgear up to kv The PIX system has been designed in accordance with international (IEC) standards, and gives an optimal

More information

MCset 4-24 kv Withdrawable SF6 circuit breaker

MCset 4-24 kv Withdrawable SF6 circuit breaker Medium Voltage switchgear MCset 4-24 kv Withdrawable SF6 circuit breaker Instruction for use Contents General 2 Glossary 2 Symbols 2 Recommendations 3 General description 4 AD4 unit 4 AD4 unit with toroidal

More information

MESG 12 / 17.5 / 24 / 36 KV

MESG 12 / 17.5 / 24 / 36 KV MESG 12 / 17.5 / 24 / 36 KV Medium Voltage Air Insulated Metal Enclosed Switchgear up to 36 kv- up to 1250 A - up to 25 ka for 1 sec. with SF6 or vacuum circuit breakers. 750 METAL ENCLOSED 1 1 ) GENERAL

More information

General. Main electric circuits Fuses compartment Operating mechanisms Cables connection compartment

General. Main electric circuits Fuses compartment Operating mechanisms Cables connection compartment General The switchgear must be suitable for 36 kv rated voltage and specifically conceived for the secondary distribution substations in M.V. with either ring or radial type networks. The switchgear must

More information

NXPLUS C Single busbar. Maintenance-free for lifetime

NXPLUS C Single busbar. Maintenance-free for lifetime NXPLUS C Single busbar Maintenance-free for lifetime Energy Distribution Welcome! Page 2 Content Overview Technical data Typicals Panel design Circuit-Breaker panel Busbar Operation Metering Low-voltage

More information

METAL-CLAD SWITCHGEAR TYPE SRUP 12, SRP kv A...25 ka. Manual for mounting, operation and maintenance. ABB Power Distribution

METAL-CLAD SWITCHGEAR TYPE SRUP 12, SRP kv A...25 ka. Manual for mounting, operation and maintenance. ABB Power Distribution METAL-CLAD SWITCHGEAR TYPE SRUP 12, SRP 12 12 kv...1250 A...25 ka Manual for mounting, operation and maintenance ABB Power Distribution Your safety first - always! WARNING Always observe the instruction

More information

All rights reserved. Neither this catalogue nor any part of it may be copied using any method or for any purposes. Most studies are legally protected.

All rights reserved. Neither this catalogue nor any part of it may be copied using any method or for any purposes. Most studies are legally protected. Issued: January 2013 Copyright by ZPUE Katowice S.A. All rights reserved. Neither this catalogue nor any part of it may be copied using any method or for any purposes. Most studies are legally protected.

More information

Vacuum Circuit Breaker

Vacuum Circuit Breaker Vacuum Circuit Breaker 12/24kV VECTOR series Vacuum Circuit Breaker VMS series Metal-clad Switchgear Medium Voltage Systems 003 FM 73638 12/24kV VECTOR VCB Features of the VECTOR Vacuum Circuit Breaker:

More information

AIR INSULATED EXTENDABLE SWITCHGEAR UP TO 12KV GUIDE

AIR INSULATED EXTENDABLE SWITCHGEAR UP TO 12KV GUIDE AIR INSULATED EXTENDABLE SWITCHGEAR UP TO 12KV GUIDE Certificate Number FM35831 APPLICATION Typical Uses and Classification The MSGair switchgear is used in transformer and switching substations mainly

More information

COMPACT SUBSTATION GUIDE

COMPACT SUBSTATION GUIDE COMPACT SUBSTATION GUIDE Certificate Number FM35831 1 The substation is a compact enclosure consisting of MV switchgear, a transformer and an LV switchboard located in three separate compartments which

More information

VD4. Installation and service instructions kv A ka

VD4. Installation and service instructions kv A ka VD4 Installation and service instructions 12... 24 kv - 630... 2500 A - 16... 31.5 ka For your safety! Make sure that the installation room (spaces, divisions and ambient) is suitable for the electrical

More information

Energy Australia Chamber Substation indoor switchgear. installation,operation and maintenance instructions version 1.

Energy Australia Chamber Substation indoor switchgear. installation,operation and maintenance instructions version 1. Energy Australia Chamber Substation indoor switchgear installation,operation and maintenance instructions version 1.6 / February 2009 1 Details of revision Version Comment Date 1.0 First Draft Issue May

More information

MV Air Insulated Switchgear TAP17. Technical Data TGOOD

MV Air Insulated Switchgear TAP17. Technical Data TGOOD MV Air Insulated Switchgear TAP17 Technical Data TGOOD 2017.1 Operating environmental conditions Place of installation: Indoor or outdoor Ambient temperature: 25 ~ +40 (higher or lower temperature optional)

More information

Medium voltage products UniSec DY800 New 24 kv air-insulated medium voltage switchgear to e-distribuzione specifications

Medium voltage products UniSec DY800 New 24 kv air-insulated medium voltage switchgear to e-distribuzione specifications Medium voltage products UniSec Y800 New 24 kv air-insulated medium voltage switchgear to e-istribuzione specifications UniSec Y800 ubicles available Unit e-istribuzione specifications (Ed. 4) UniSec IS/1

More information

Our brand POWER DYNAMIC PASSION COMMITMENT CREATIVITY. A strong brand for strong products: 8PU Premium. MV Energy

Our brand POWER DYNAMIC PASSION COMMITMENT CREATIVITY. A strong brand for strong products: 8PU Premium. MV Energy Our brand A strong brand for strong products: The ENERGOLINE brand represents our product portfolio of INDUSTRIAL SWITCHGEAR SYSTEMS. Our products are characterized by a high degree of safety, flexibility

More information

33KV INDOOR SWITCHGEAR

33KV INDOOR SWITCHGEAR 33KV INDOOR SWITCHGEAR September 2017 Engineering Department WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED Regd. Office: VidyutBhawan, Block DJ, Sector-II, Bidhannagar, Kolkata 700091. CIN:

More information

SM6. instructions for use. SM cubicle. MV distribution factory built assemblies at your service. Anglais

SM6. instructions for use. SM cubicle. MV distribution factory built assemblies at your service. Anglais SM6 Anglais MV distribution factory built assemblies at your service instructions for use SM cubicle foreword... 3 symbols and conventions... 3 as per iso 3864---2... contact the Schneider Electric service

More information

For your safety! Foreword

For your safety! Foreword Medium voltage products UniSec DY800 in accordance with Enel specifications Installation, service and maintenance instructions for 24 kv prefabricated assemblies with arc-proof metal enclosures and multi-function

More information

Key features. DESIGNS: - Conservator type - Hermetically sealed

Key features. DESIGNS: - Conservator type - Hermetically sealed Package Substations OTDS manufactures a large range of oil filled hermitically sealed and conservator type transformers to be used in conjunction with our package substations. We are able to utalise the

More information

Metal Clad Switchgears

Metal Clad Switchgears SNC Series Metal Clad Switchgears > up to 36 kv Rated Voltage > up to 2500 A Rated Current > up to 40 ka Rated Short Time Withstand Current > LSC-2B, PM, AFLR > In Confirmity with IEC 62271-1, 100, 102,

More information

AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR

AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR ANGLER SWITCHING DEVICES CONTENTS 1. General 2. Switchgear Types - Switch Disconnector - Disconnector 3. Cubicle Types - Cubicle with Switch Disconnector

More information

Instruction for Installation and Operation

Instruction for Installation and Operation KYN79 (i-ax) Metalclad Removable AC Metal-Enclosed Switchgear Instruction for Installation and Operation K 15 24 SM 01 02 Tianshui Changcheng Switchgear Factory January, 2007 Warning: This instruction

More information

Type SIMOPRIME A4, up to 24 kv, Air-Insulated Medium-Voltage Switchgear

Type SIMOPRIME A4, up to 24 kv, Air-Insulated Medium-Voltage Switchgear Circuit-Breaker www.siemens.com/energy Switchgear Type SIMOPRIME A4, up to 24 kv, Air-Insulated Medium-Voltage Switchgear s Technology Circuit-Breaker Switchgear Type SIMOPRIME, up to 17.5 kv, Air-Insulated

More information

BHARAT HEAVY ELECTRICALS LIMITED, JHANSI

BHARAT HEAVY ELECTRICALS LIMITED, JHANSI BHARAT HEAVY ELECTRICALS LIMITED, JHANSI DESIGN, MANUFACTURING, TESTING, SUPPLY INSTALLATION AND COMMISSIONING OF 11KV VACUUM CIRCUIT BREAKER NOTE : 1 VENDOR must submit complete information against clause

More information

Voltage Rated operating voltage [kv] Rated power frequency withstand voltage [kv] Rated lightning impulse withstand voltage [kv]

Voltage Rated operating voltage [kv] Rated power frequency withstand voltage [kv] Rated lightning impulse withstand voltage [kv] BasisBlock MC 1 Standards and Regulations IEC 62271-200 ; VDE 0671-200 ; BS EN 62271-200 Technical Data MC1-12 MC1-24 Voltage Rated operating voltage [kv] 12 24 Rated power frequency withstand voltage

More information

MCset kv Medium voltage equipment

MCset kv Medium voltage equipment Maintenance Guide PE90014 PE90006 MCset 1-2 - 3 17.5 kv Medium voltage equipment Air-insulated switchboards Metal-enclosed switchgear with moving parts PE90007 PE90008 PE90009 PE90007 Maintenance Guide

More information

UniSec Operation and maintenance manual

UniSec Operation and maintenance manual Medium voltage products UniSec Operation and maintenance manual Safety 3 For your safety! 3 Skilled personnel 3 Critical messages 3 Contact us! 3 1. Introduction 4 1.1 General aspects 4 1.2 Operation and

More information

Medium voltage NEX switchgear Withdrawable circuit breaker. Quite simply efficient

Medium voltage NEX switchgear Withdrawable circuit breaker. Quite simply efficient Medium voltage NEX switchgear Withdrawable circuit breaker Quite simply efficient NEX, a simple and flexible solution NEX is the result of worldwide acquired experience and provides you with a high level

More information

with Vacuum Circuit Breaker HAF

with Vacuum Circuit Breaker HAF M E T A L - C L A D S W I T C H G E A R Safety and Reliability with Vacuum Circuit Breaker HAF Flexible Design and Compact with Vacuum Circuit Breaker HVF Easy Installation and Maintenance We build a better

More information

GAE CLAD. Catalogue Metal - Clad Switchgear Up To 24 kv. Vacuum Circuit Breaker With Embedded Poles. PT Guna Era Manufaktura

GAE CLAD. Catalogue Metal - Clad Switchgear Up To 24 kv. Vacuum Circuit Breaker With Embedded Poles. PT Guna Era Manufaktura GAE CLAD \ METALCLAD SWITCHGEAR up to 24 kv \ M600204.15 PT Guna Era Manufaktura Catalogue 2015 GAE CLAD Vacuum Circuit Breaker With Embedded Poles Metal - Clad Switchgear Up To 24 kv General Description

More information

SafeGear Motor Control Center Arc Resistant Metal-Clad Construction Brochure

SafeGear Motor Control Center Arc Resistant Metal-Clad Construction Brochure 2017 SafeGear Motor Control Center Arc Resistant Metal-Clad Construction Brochure SafeGear Motor Control Center Arc resistant Metal-Clad construction Brochure Table of Contents 1. Description 1 1 2. SafeGear

More information

VOLUME: IIIC SCHEDULE IIIC/4 11 KV AND 3.3 KV SWITCHGEARS

VOLUME: IIIC SCHEDULE IIIC/4 11 KV AND 3.3 KV SWITCHGEARS VOLUME: IIIC SCHEDULE IIIC/4 11 KV AND 3.3 KV SWITCHGEARS A. 11 KV SWITCHGEAR 1.0 SWITCHGEAR ASSEMBLY 1.1 Make : 1.2 Type : 1.3 Reference Standard : 1.4 Voltage (Nom./Max.) KV : 1.5 Phase, Frequency No,Hz.

More information

CPG.1 Gas insulated, single busbar cubicle range Up to 27 kv / 2000 A / 31.5 ka Up to 38 kv / 2000 A / 31.5 ka IEEE Standards

CPG.1 Gas insulated, single busbar cubicle range Up to 27 kv / 2000 A / 31.5 ka Up to 38 kv / 2000 A / 31.5 ka IEEE Standards Medium Voltage Switchgear Primary Distribution CPG.1 Gas insulated, single busbar cubicle range Up to 27 kv / 2000 A / 31.5 ka General description Presentation Ormazabal s CPG System includes the CPG.1

More information

ormaset-m PREFABRICATED METALLIC TRANSFORMER SUBSTATION

ormaset-m PREFABRICATED METALLIC TRANSFORMER SUBSTATION IG-199-GB GENERAL INSTRUCTIONS FOR IG-199-GB General Instructions ormaset-m Transformer Substations Primary Distribution Switchgear Secondary Distribution Switchgear Protection and Automation Low Voltage

More information

CPG.0 Single busbar gas-insulated cubicles

CPG.0 Single busbar gas-insulated cubicles MV Switchgear Primary Distribution CPG.0 Single busbar gas-insulated cubicles Up to 36 kv CPG System The quality of products designed, manufactured and installed by Ormazabal is underpinned by the implementation

More information

CGMCOSMOS. Reliable innovation. Personal solutions. Fully gas insulated modular and compact (RMU)system.

CGMCOSMOS. Reliable innovation. Personal solutions. Fully gas insulated modular and compact (RMU)system. MV Switchgear for CGMCOSMOS Fully gas insulated modular and compact (RMU)system Up to 24 kv Up to 27 kv mediumvoltage mediumvoltageag AG Langackerstrasse Langackerstrasse 25 25 CH CH 6330 6330 Cham Cham

More information

SWITCHCRAFT. Switchcraft Europe GmbH SWITCHCRAFT

SWITCHCRAFT. Switchcraft Europe GmbH SWITCHCRAFT SWITCHCRAFT Switchcraft Europe GmbH Switchgear Product Overview igis Gas Insulated Switchgear isis Solid Insulated Switchgear icb - Vacuum Circuit Breaker iair - Air insulated switchgear panel Switchcraft

More information

ME Switchgear with Vacuum Circuit Breaker and Auto-jet II Switch with Ground Position

ME Switchgear with Vacuum Circuit Breaker and Auto-jet II Switch with Ground Position LET S BE PACIFIC November 0 Volume Number 5 ME Switchgear with Vacuum Circuit Breaker and Auto-jet II Switch with Ground Position Federal Pacific has the capability to engineer, fabricate and assemble

More information

Safe and Reliable. Flexible, Compact Design. Easy Installation and Maintenance

Safe and Reliable. Flexible, Compact Design. Easy Installation and Maintenance M E T A L - C L A D S W I T C H G E A R Safe and Reliable Flexible, Compact Design Easy Installation and Maintenance We build a better future! Hyundai HMS medium-voltage metal-clad switchgears and control-gears,

More information

10/2015 CUBICLE AND METAL-CLAD MEDIUM VOLTAGE SWITCHGEARS WEGA 07 WEGA 12 WEGA 17 WEGA 24 WEGA 36

10/2015 CUBICLE AND METAL-CLAD MEDIUM VOLTAGE SWITCHGEARS WEGA 07 WEGA 12 WEGA 17 WEGA 24 WEGA 36 10/2015 CUBICLE AND METAL-CLAD MEDIUM VOLTAGE SWITCHGEARS WEGA 07 WEGA 12 WEGA 17 WEGA 24 WEGA 36 Gdańsk, October 2015 Improving the competitiveness of the company ELMOR through investments introducing

More information

TECHNICAL SPECIFICATION OF 11KV SF6 / VCB METAL ENCLOSED, INDOOR (PANEL TYPE) / OUTDOOR RING MAIN UNIT (RMU). (IEC standard equipment)

TECHNICAL SPECIFICATION OF 11KV SF6 / VCB METAL ENCLOSED, INDOOR (PANEL TYPE) / OUTDOOR RING MAIN UNIT (RMU). (IEC standard equipment) TECHNICAL SPECIFICATION OF 11KV SF6 / VCB METAL ENCLOSED, INDOOR (PANEL TYPE) / OUTDOOR RING MAIN UNIT (RMU). (IEC standard equipment) 1 SCOPE OF SUPPLY This specification covers design, manufacture, shop

More information

Air Insulated Switchgear NXAirS, 40.5kV Answers for infrastructure and cities.

Air Insulated Switchgear NXAirS, 40.5kV Answers for infrastructure and cities. www.siemens.com.cn/medium-voltage-switchgear Air Insulated Switchgear NXAirS, Answers for infrastructure and cities. Applications Page Application Type 2 Typical uses 3 Classification 3 Type NXAirS withdrawable

More information

ormaset-m Prefabricated metallic transformer substation

ormaset-m Prefabricated metallic transformer substation Prefabricated metallic transformer substation General Instructions IG-199-EN, version 03; 6/11/2013 Legal Deposit: BI-1401/2013 CAUTION! When medium-voltage equipment is operating, certain components are

More information

UP TO 17,5 kv LSC 2B PM (METAL-CLAD) WITHDRAWABLE VACUUM CIRCUIT BREAKER MEDIUM VOLTAGE CUBICLES

UP TO 17,5 kv LSC 2B PM (METAL-CLAD) WITHDRAWABLE VACUUM CIRCUIT BREAKER MEDIUM VOLTAGE CUBICLES UP TO 17,5 kv LSC 2B PM (METAL-CLAD) WITHDRAWABLE VACUUM CIRCUIT BREAKER MEDIUM VOLTAGE CUBICLES 1 TABLE OF CONTENTS 1. SCOPE 2. GENERAL 2.1 STANDARDS AND REGULATIONS 2.2 OPERATING CONDITIONS 2.3 DOCUMENTATION

More information

CBGS-0. Medium voltage distribution

CBGS-0. Medium voltage distribution Medium voltage distribution CBGS-0 Gas Insulated metal-enclosed Switchgear SF6 circuit breaker technology Up to 24/36 kv - 1250/1600/2000 A - 25/31.5 ka Transmission Wind Airports Oil & Gas Mining & Distribution

More information

36kV Gas Insulated Medium Voltage Switchgear

36kV Gas Insulated Medium Voltage Switchgear GE Industrial Solutions 36kV Gas Insulated Medium Voltage Switchgear User Manual Safety first! Important recommendations: Switchgear should be installed in a clean, dry, ventilated room suitable for electrical

More information

MEDIUM VOLTAGE AIR INSULATED ARC-RESISTANT LOAD BREAK AND DISCONNECT SWITCHES

MEDIUM VOLTAGE AIR INSULATED ARC-RESISTANT LOAD BREAK AND DISCONNECT SWITCHES MEDIUM VOLTAGE AIR INSULATED ARC-RESISTANT LOAD BREAK AND DISCONNECT SWITCHES Description JRS arc-resistant fused/non-fused load break and fused/non-fused disconnect switches are available for applications

More information

24kV Medium Voltage Switchgear Metal-Enclosed (LSC2A)

24kV Medium Voltage Switchgear Metal-Enclosed (LSC2A) M6 24kV Medium Voltage Switchgear MetalEnclosed (LSC2A) GENERAL FEATURES GENERAL DESCRIPTION The structure of the cubicles, of considerable strength, has selfsupporting structure and is made of steel sheet

More information

Benefits, typical uses

Benefits, typical uses R-HA26-013. eps Switchgear Type 8BT1, up to 24kV,Air-Insulated Contents Application Page Application Benefits 2 Typical uses 2 and 3 Technical Data Ratings 4 Classification, dimensions, 5 room planning

More information

MCset 17.5 kv. Civil engineering guide April Medium Voltage Distribution

MCset 17.5 kv. Civil engineering guide April Medium Voltage Distribution Medium Voltage Distribution MCset 17.5 kv ir insulated switchboard Withdrawable switchgear SF6 or vaccum technology Civil engineering guide pril 2012 Contents General 2 Glossary 2 Dimensions and weights

More information

Circuit-Breaker Switchgear Type SIMOPRIME, up to 17.5 kv, Air-Insulated Medium-Voltage Switchgear.

Circuit-Breaker Switchgear Type SIMOPRIME, up to 17.5 kv, Air-Insulated Medium-Voltage Switchgear. Circuit-Breaker Switchgear Type SIMOPRIME, up to 17.5 kv, Air-Insulated Medium-Voltage Switchgear www.siemens.com/energy Technology s Contents Application Page Benefits 2 Typical uses 2 and 3 Technical

More information

PT Guna Era Manufaktura. Catalogue GAE TPS \ Medium Voltage Switchgear 12kV - 24kV \ M GAE TPS. Medium Voltage Switchgear 12kV - 24kV

PT Guna Era Manufaktura. Catalogue GAE TPS \ Medium Voltage Switchgear 12kV - 24kV \ M GAE TPS. Medium Voltage Switchgear 12kV - 24kV PT Guna Era Manufaktura Catalogue 2015 GAE TPS Medium Voltage Switchgear 12kV - 24kV General Description Introduction Safety GAE TPS is a complete unit range which can be equipped with SF6 disconnector

More information

SF 6 Gas Insulated Switchgear Type SDH314 / SDHa314 for 72.5 to 145 kv

SF 6 Gas Insulated Switchgear Type SDH314 / SDHa314 for 72.5 to 145 kv Three Phase Encapsulated Type SF 6 Gas Insulated Switchgear Type SDH314 / SDHa314 for 72.5 to 145 kv 06B1-E-0002 Small Space Requirement, High Reliability and Safety ー 72.5 to 145 kv GIS, SDH314/SDHa314

More information

AIR INsULATeD switchgear >> PIX. up to 24 kv. Air-insulated switchgear with vacuum circuit-breaker. system configuration.

AIR INsULATeD switchgear >> PIX. up to 24 kv. Air-insulated switchgear with vacuum circuit-breaker. system configuration. IR INsULTeD switchger >> PIX up to 24 kv ir-insulated switchgear with vacuum circuit-breaker system configuration ReV T&D Delivery conditions The General Conditions of Delivery as amended shall apply.

More information

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable www.siemens.com/medium-voltage-switchgear Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear Catalog HA 41.43 2012 Answers for infrastructure and cities. Neue Bilder

More information

KYN28-12(GZSI-12Z)Armoured Middle-Mounted Metal. Enclosed Switch. 1.General. 2.Model Definition

KYN28-12(GZSI-12Z)Armoured Middle-Mounted Metal. Enclosed Switch. 1.General. 2.Model Definition KYN28-12(GZSI-12Z)Armoured Middle-Mounted Metal Enclosed Switch 1.General KYN28-12 armoured middle-mounted metal enclosed switchgear (hereinafter referred to as switchgear) is a new product with own design

More information

e 2 ALPHA -2S Medium Voltage Double Busbar Switchgear K Catalogue EN

e 2 ALPHA -2S Medium Voltage Double Busbar Switchgear K Catalogue EN e 2 ALPHA -2S Medium Voltage Double Busbar Switchgear K-11.1.2 Catalogue EN We Create Ideas With Power! e 2 ALPHA-2S double busbar switchgear is designed for use in primary and secondary electric energy

More information

VD4 Installation and service instructions kv A ka

VD4 Installation and service instructions kv A ka Medium voltage products VD4 Installation and service instructions 12... 36 kv - 630... 3150 A - 16... 50 ka Index For your safety! 1 I. Introduction 2 II. Programme for environmental protection 2 1. Packing

More information

MNS Light F. Low-voltage switchgear with fixed units. ABB LV Systems

MNS Light F. Low-voltage switchgear with fixed units. ABB LV Systems MNS Light F Low-voltage switchgear with fixed units ABB LV Systems Cubicle design MNS Light F switchgear is a flexible system with a large selection of cubicle variants that can be built together in optional

More information

Medium Voltage Metal-Enclosed Switches

Medium Voltage Metal-Enclosed Switches Medium Voltage Metal-Enclosed Switches Outdoor Medium Voltage Switch.1 Medium Voltage Switch MVS Product Description............................................. 2 Application Description..........................................

More information

11kV Compact Switchgear. tec - range. Minimum to Zero SF6 Insulation Gas. Outec Controls

11kV Compact Switchgear. tec - range. Minimum to Zero SF6 Insulation Gas. Outec Controls 11kV Compact Switchgear tec - range Minimum to Zero SF6 Insulation Gas. Outec Controls 1 tec xx - 11kV Switchgear Contents 1 tec CB - SF6 Free Switchgear... 3 1.1 Description:... 3 1.2 1.3 Features the

More information

Medium-Voltage Switchgear OPERATING INSTRUCTIONS

Medium-Voltage Switchgear OPERATING INSTRUCTIONS Medium-Voltage Switchgear Circuit-Breaker Switchgear Type NXAIR: Factory-Assembled, Type-Tested and Metal- Enclosed Switchgear for Indoor Installation, Air-Insulated Loss of Service Continuity Category:

More information

PC3.0/MNS R 690 V A Main low voltage distribution switchgear

PC3.0/MNS R 690 V A Main low voltage distribution switchgear Technical catalogue PC3.0/MNS R 690 V - 6300 A Main low voltage distribution switchgear 1TTB900001D0201 PC3.0/MNS R main low voltage distribution switchgear Index General Introduction...2 Technical data...3

More information

Unitole UP kv Primary substations Motor control centres

Unitole UP kv Primary substations Motor control centres Unitole UP 3.6-17.5 kv Primary substations Motor control centres Product Focus Air-insulated withdrawable switchgear with vacuum circuit-breakers and contactors Creating Solutions Eaton Holec creates power-engineering

More information

UniSwitch Withdrawable type Circuit Breaker Cubicles. Installation, service and maintenance instruction manual

UniSwitch Withdrawable type Circuit Breaker Cubicles. Installation, service and maintenance instruction manual UniSwitch Withdrawable type Circuit Breaker Cubicles Installation, service and maintenance instruction manual 1 Your safety first at all times! This is why our instruction manual begins with the following

More information

Metal-Enclosed Switches. Medium Voltage. Medium Voltage Metal-Enclosed Switches Contents

Metal-Enclosed Switches. Medium Voltage. Medium Voltage Metal-Enclosed Switches Contents January 2003 Vol. 1, Ref. No. [1011] -1 Medium Voltage Metal-Enclosed Switches Contents Description Page MVS................................... -2 and Breaker MSB........................ -3 Metal-Enclosed

More information

M-RING 24. SF6 Insulated Ring Main Unit Metal-Enclosed (LSC2A)

M-RING 24. SF6 Insulated Ring Main Unit Metal-Enclosed (LSC2A) M-RING 24 SF6 Insulated Ring Main Unit Metal-Enclosed (LSC2A) Contents General Description Advanced facilities and process Advanced design philosophy Definition of M-RING 24 Standards Service conditions

More information

Product Specification

Product Specification KYN28-12 Series H.V Metal Clad Switchgear Product Specification 10/08/2015 Electrical Treasure One-Stop Supplier Of Electrical Equipment 1 KYN28-12 Series With Prevent Wrong Operation Of Metal Clad Switchgear

More information

0MV vacuum circuit breaker. 0Evolis 24 kv. 0User 0Manual. Creation Printed on 2008/07/17

0MV vacuum circuit breaker. 0Evolis 24 kv. 0User 0Manual. Creation Printed on 2008/07/17 0MV vacuum circuit breaker 0Evolis 24 kv 0User 0Manual 02008 07897530EN-C0.book Page 1 Jeudi, 15. mai 2008 11:34 11 Contents Evolis description 2 Front view circuit breaker 2 Front view lateral circuit

More information

Switchgear Type 8BT1, up to 24 kv, air-insulated. Medium Voltage Switchgear Catalog HA 26.

Switchgear Type 8BT1, up to 24 kv, air-insulated.   Medium Voltage Switchgear Catalog HA 26. www.siemens.com/medium-voltage-switchgear Switchgear Type 8BT1, up to 24 kv, air-insulated Medium Voltage Switchgear Catalog HA 26.31 2012 Answers for infrastructure and cities. R-HA26-013. eps Contents

More information

SafeGear TM Motor Control Center Arc resistant metal-clad construction

SafeGear TM Motor Control Center Arc resistant metal-clad construction SafeGear TM Motor Control Center Arc resistant metal-clad construction Contents Description 2 SafeGear TM MCC applications 3 Electrical features 3 Standards 3 Standard service conditions 4 HCV vacuum contactor

More information

Modular medium-voltage switchgear. NorMax

Modular medium-voltage switchgear. NorMax Modular medium-voltage switchgear NorMax NorMax MODULAR MEDIUM-VOLTAGE SWITCHGEAR 2 NorMax Modular medium-voltage switchgear Contents Subject Page Table of contents 2 Introduction and main features 2 Technical

More information

8DJ. Maintenance-free for lifetime

8DJ. Maintenance-free for lifetime 8DJ Maintenance-free for lifetime Energy Distribution Welcome! Page 2 October 1 st 2008 8DJ Main Applications for Medium-Voltage Switchgear Power generation Power stations G Power transmission High and

More information

SION Vacuum Circuit-Breakers. Answers for energy. Medium-Voltage Equipment Selection and Ordering Data. Catalog HG

SION Vacuum Circuit-Breakers. Answers for energy. Medium-Voltage Equipment Selection and Ordering Data. Catalog HG Medium-Voltage Equipment Selection and Ordering Data Catalog HG 11.02 2011 Answers for energy. R-HG11-172.tif 2 Siemens HG 11.02 2011 Contents SION Vacuum Circuit-Breakers Medium-Voltage Equipment Catalog

More information

DISTRIBUTION SOLUTIONS. GSec Gas-insulated switching and isolating apparatus

DISTRIBUTION SOLUTIONS. GSec Gas-insulated switching and isolating apparatus DISTRIBUTION SOLUTIONS GSec Gas-insulated switching and isolating apparatus GSec is a three-position SF6 gas-insulated switchdisconnector designed for use in medium voltage switchgear for secondary distribution

More information

VD4/R - VD4/L - VD4/UniAir - VD4/UniMix

VD4/R - VD4/L - VD4/UniAir - VD4/UniMix VD4/R - VD4/L - VD4/UniAir - VD4/UniMix Installation and maintenance instructions 12... 24 kv - 630... 1250 A - 12... 25 ka 1 For your safety! Make sure that the installation room (spaces, divisions and

More information

PowerCube type PB. Pre-assembled modules and enclosures for constructing medium voltage switchgear

PowerCube type PB. Pre-assembled modules and enclosures for constructing medium voltage switchgear PowerCube type PB Pre-assembled modules and enclosures for constructing medium voltage switchgear GENERAL CHARACTERISTICS MAIN COMPONENTS TYPES AVAILABLE AND APPARATUS OVERALL DIMENSIONS AND WEIGHTS ELECTRIC

More information

SUBSTATION VACUUM CIRCUIT BREAKER (38KV)

SUBSTATION VACUUM CIRCUIT BREAKER (38KV) SUBSTATION VACUUM CIRCUIT BREAKER (38KV) For more than four decades, Myers Power Products has led the switchgear market in quality for the electric industry, delivering highly reliable products for utilities

More information

cgm.3 system Fully SF6 gas insulated medium voltage switchgear up to 40.5 kv in accordance with IEC Standards

cgm.3 system Fully SF6 gas insulated medium voltage switchgear up to 40.5 kv in accordance with IEC Standards Fully SF6 gas insulated medium voltage switchgear up to 40.5 kv in accordance with IEC Standards General instructions IG-136-EN, version 10; 23/06/2016 CAUTION! When medium-voltage equipment is operating,

More information

CONTENT. EPE METALCLAD SWITCHGEARS AMS SERIES 12kV AMS METALCLAD SWITCHGEAR 24kV AMS METALCLAD SWITCHGEAR 40.5KV AMS METALCLAD SWITCHGEAR

CONTENT. EPE METALCLAD SWITCHGEARS AMS SERIES 12kV AMS METALCLAD SWITCHGEAR 24kV AMS METALCLAD SWITCHGEAR 40.5KV AMS METALCLAD SWITCHGEAR CONTENT EPE METLCLD SWITCHGERS SERIES EPE 1220 / - 12KV METLCLD SWITCHGER EPE 10D - 12KV METLCLD SWITCHGER EPE 24-24KV METLCLD SWITCHGER EPE 36-36KV METLCLD SWITCHGER EPE METLCLD SWITCHGERS MS SERIES 12

More information

Gas Insulated Switchgear

Gas Insulated Switchgear Gas Insulated Switchgear Your partner in energy solutions CG Electric Systems Hungary CG Electric Systems Hungary (previously known as Ganz Electric) has a history of over a 130 years as a high technology

More information

Gas Insulated Metal-clad Switchgear, HMGS!

Gas Insulated Metal-clad Switchgear, HMGS! Medium Voltage HMGS-G10 HYUNDAI Medium Voltage Gas Insulated Metal-clad Switchgear, HMGS! SF6 Gas Insulated Metal-clad Switchgear is an integrated assembly of vacuum circuit breaker, 3-position switch,

More information

Power/Vac OEM Express Switchgear

Power/Vac OEM Express Switchgear g Power/Vac OEM Express Switchgear Metalclad Switchgear 4.16kV-250 MVA through 13.8kV-1500 MVA DEA-275 FULLY ASSEMBLED MECHANICALLY COMPLETE SWITCHGEAR WITHOUT DEVICES AND WIRE. POWER/VAC OEM EXPRESS SWITCHGEAR

More information

SUBSTATION VACUUM CIRCUIT BREAKER (15.5KV)

SUBSTATION VACUUM CIRCUIT BREAKER (15.5KV) SUBSTATION VACUUM CIRCUIT BREAKER (15.5KV) For more than four decades, Myers Power Products has led the switchgear market in quality for the electric industry, delivering highly reliable products for utilities

More information

EMC 24 SERIES METAL CLAD SWITCHGEAR. We engineer, we assure. Up to 24 kv - 25 ka With Withdrawable, Air-Insulated, Medium Voltage Distribution Panel

EMC 24 SERIES METAL CLAD SWITCHGEAR. We engineer, we assure. Up to 24 kv - 25 ka With Withdrawable, Air-Insulated, Medium Voltage Distribution Panel We engineer, we assure. EMC 24 SERIES METAL CLAD SWITCHGEAR Up to 24 kv - 25 ka With Withdrawable, Air-Insulated, Medium Voltage Distribution Panel Saudi Cable Company REF: EMC24-EN-16-04 2 www.elimsan.com

More information

SUBSTATION VACUUM CIRCUIT BREAKER (25.8 / 27KV)

SUBSTATION VACUUM CIRCUIT BREAKER (25.8 / 27KV) SUBSTATION VACUUM CIRCUIT BREAKER (25.8 / 27KV) For more than four decades, Myers Power Products has led the switchgear market in quality for the electric industry, delivering highly reliable products

More information

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear Totally Integrated Power SIMOSEC Catalog HA 41.43 Edition Sept. 2014 Answers for infrastructure and cities. Neue

More information