R, M&U OF GENERATING UNITS OF NPH. A Case Study

Size: px
Start display at page:

Download "R, M&U OF GENERATING UNITS OF NPH. A Case Study"

Transcription

1 R, M&U OF GENERATING UNITS OF NPH A Case Study

2 KARNATAKA POWER CORPORATION LIMITED(KPCL) HYDRO THERMAL SOLAR WIND STATE OWNED PUBLIC LIMITED COMPANY IN THE BUSINESS OF GENERATION OF ELECTRIC POWER. THE COMPANY HAS A WORK FORCE EXCEEDING 5000 PEOPLE INCLUDING ABOUT 1800 ENGINEERS. THE CUSTOMERS OF KPCL ARE HESCOM, BESCOM, GESCOM, CHESCOM AND MESCOM FOR SALE OF ENERGY. KPCL HAS A TOTAL INSTALLED CAPACITY OF ABOUT MW CONSISTING OF HYDRO- ELECTRIC STATIONS, THERMAL POWER PLANTS, WINDMILLS AND SOLAR PV PLANTS.

3 HYDRO MW THERMAL 3528 MW SOLAR 24 MW WIND MW Thermal Units at Yermarus are at final stages of commissioning TOTAL KPCL MW RES Hydro Thermal Solar Wind

4 KPCL has 21 Hydro Power Stations: Shivasamudram years Shimsha - 76 years MGHE - 68 years SGS - 52 years Bhadra - 54 years Munirabad - 54 years NPH - 38 years Linganamakki - 38 years Supa - 31 years Varahi - 27 years Mani - 23 years Kadra - 19 years Kodasalli - 18 years Gerusoppa - 15 years Almatti - 12 years Shivasamudram Power House

5 Kalinadhi Hydro Electric Scheme was developed in stages. First stage- 6x135MW at Nagjhari Power House. 2x50MW Supa dam power house. Second Stage: 3x40MW at Kodasalli Power House 3x50MW Kadra Power House. NPH -Commissioned during Turbine: Vertical Francis. Rated rpm: 375 Rated Net head : 347m First time 375 rpm units with Francis turbine installed. Very few units with 375rpm Francis type turbines were in operation at that time. Design energy of the project was 4082 MU.

6 Performance of the units Generating units were prone to vibration since commissioning Detailed analyses to find the cause of vibration were carried out Various experts were involved in analyzing the problems Tests conducted by Dr. Mahern Holtz of Hamberg University during 1984 showed that critical speed is in the vicinity of rated speed of 375 RPM

7 Analysis of the results The analyses by various experts indicates that transient vibrations are basically due to following reasons: Periodical residual mechanical and magnetic unbalanced pulls causing excitation and resonance to the rotor system at sub-synchronous speeds Unacceptable Stator and rotor form, resulting in very high UMP (unbalanced magnetic pull) Resonance close to normal speed due to insufficient stiffness of bearing support structure Drawal of higher than designed/rated excitation current at 135MW. Excitation current was exceeding 1250 Amp as against rated 1140 Amp for 135 MW The stiffness of present bearing brackets are as follows: Upper Bracket 0.2x 109 N/m Lower Bracket 0.5x109N/m Recommendations: Stiffness of both upper and lower brackets have to be higher than 1.0x109 N/m and UMP to be reduced by improving the circularity of stator and rotor

8 Expert committee consisting of members from CEA, OEM and KPCL recommended to take up Renovation, Modernization & Uprating of one unit on a pilot basis and carry out the modifications based on the results of analyses. R, M&U OF U#1,2&3 Subsequently, Contract was awarded to the OEM for R, M & U of one unit at NPH on Since, Unit-2 was under shut down due to stator coil failure, it was taken up for R, M & U works on at a cost of Rs Lakhs and re-commissioned on (16months) Major works carried out includes replacement of stator, modification of top bracket housing and arm assembly, guide bearing support ring for bottom guide bearings, slip rings, etc

9 Based on the results of R, M & U of Unit-2, R, M & U of units 1& 3 was taken up in the second phase and OEM was awarded the Contract through competitive bidding at a total cost of Rs.1639 Lakhs for two units. Scope of work mainly covers only generator portion as done for unit-2. Turbine: Self lubricated bushed were provided. No major works on turbine carried out. Additional HP lubrication system provided which would operate whenever thrust bearing temperature shows raising tendencies. The performance of the Units after R, M & U is generally satisfactory.

10 R, M&U OF U#4,5&6 Based on the experience of the R, M & U of Units-1, 2 & 3, R, M & U of Unit-4, 5 & 6 was taken up in the next phase in 2003 Contract was awarded to a Non-OEM through an ICB Modernization of Governors and Static Excitation systems were also taken up. Total cost for lakhs of supply was Rs.2430Lakhs and Rs. 790 lakhs for erection, testing and commissioning of equipment Delivery period was 33 months (Staggered deliver period for three units) and erection period was 8 months from handing over of each unit It was planned to take up works on one unit at a time so that other units are available to support the grid and optimum utilization of water

11 New technologies adopted for R, M&U of U#4,5&6 Floating rim technology used instead of the earlier floating Rim technology for rotor spider. Stator frame supplied in 3 segments and built as joint less ring at site to eliminate core sector joints and to improve rigidity of stator core The stator core supplied of silicon alloy sheet steel(low loss material) On line monitoring system used to monitor the Air gap, vibration and partial discharge of the units Epoxy insulation Disc between thrust collar and runner disc provided to avoid entry of leakage current to runner disc Over-speed device with latest technology Digital excitation system Digital Governor system Flow measuring device

12 R, M&U of unit-4 Dynamic Shaft Analysis was conducted at NPH during December Contractor recommended to have modified rotor structure with rigid rim technology instead of existing floating rim technology for improving performance and reducing vibrations. The subject was discussed with experts in the field including experts in IITs. Based on the studies, it rotor spider. was decided to retain the exist

13 R, M&U of unit-4 Erection works on Unit-4 was taken up from After dismantling, ND tests on rotor spider showed 40 Nos of weld cracks Considering need for long term performance, detailed review to reduce vibrations, modification of rotor structure was taken up and it was decided to provide new modified rotor spider for shrunk fitting on rotor shaft. Price of Rs.837 Lakhs for supply and Rs. 93 Lakhs for erection for all 3 units during June 2006 Delivery period for 4th unit was 9 months Unit No.4 commissioned on after completion of R, M & U works NEW MODIFIED ROTOR SPIDER

14 Various stages during Rotor Rim Building 1 Rotor Rim Building 3 Pre-heating of Rotor Spider 2 Lifting of Rotor Spider 4 Shrink Fitting of Rotor Spider with Generator Shaft

15 R, M&U of unit-4 Performance of unit was satisfactory with Vibration levels within limits. But oil splashing problem from UGB oil sleeve noticed. Modifications carried out on thrust collar assembly and other accessories in the Bearing Housing to solve the problem. Total time period taken for R, M&U works is 35 months. Main reasons for delay : Major defects noticed after opening of the unit. Non-availability of machine drawing, Time taken for reverse engineering, Manufacturing of equipment after opening of unit for supply of new modified rotor spider as cracks were noticed only after opening unit, etc.

16 R, M & U of unit-5 U#5 was handed over from for erection and commissioning works. Problems in U#5 After opening of the unit, the following observations were made: Generator Shaft was found with varying diameter from DE side to NDE side During inspection, undercuts found due to welding of plates near aeration holes at 4 places on NDE side flange of turbine shaft (rotor shaft coupling side) Pitting in Lower Labyrinth Welded Region of Turbine Shaft Generator Shaft

17 R, M & U of unit-5 The inner diameter of the MIV Main seal found corroded, ovality (2 to 2.5 mm) and found in damaged condition Eccentric and Concentric Pin for GV Lever and Regulating Ring were found eroded Coupling Bolts Coupling bolts and nuts between Turbine and Generator Shaft Coupling were found damaged Eroded Central Part of Gland Seal Assembly of MIV Main seal

18 R, M & U of unit-5 It was necessary to repair Labyrinth rings, replace housing of shaft gland seal, eccentric pins for guide vane lever and regulating rings, rotor rim studs, etc. Additional price of Rs.99.9 Lakhs with a delivery period of 6 months for supply and erection period of 3 months there after Unit 5 was synchronized with the grid after the completion of R, M&U works on

19 R, M & U of unit-6 Based on experience of unit 4 & 5 and inspection of Unit-6 carried out in dewatered condition(without dismantling). Additional orders were placed for supply of pivot ring based on inspection for unit-6 to save time Unit-6 was handed over on After opening of the unit, ND tests were carried out ND test results showed presence of crack in turbine shaft, erosion beyond permissible limits in top cover, high erosion and corrosion in runner and other under water parts

20 NDT test results DP test on turbine shaft Damages observed in poles Runner under DP test before refurbishment Cracks observed during MP test on pole end plates

21 Some of the Eroded/Damaged parts after opening of unit 6 Regulating ring Shaft Sleeve plate assembly Labyrinth ring Base metal erosion near labyrinth and liner plate area

22 List of Eroded/Damaged parts after opening of unit 6 GV body pitting Guide Vane Levers Pivot Ring Turbine Shaft

23 List of Eroded/Damaged parts after opening of unit 6 Regulation Ring Metal chipped out from vane exit area of Runner. Top Cover Top Cover Shaft gland housing Base metal erosion near labyrinth and liner plate area Eroded top cover

24 Additional orders placed for U#6 after inspection of components and discussions with OEM: OEM Repairs to turbine shaft and supply of modified shaft sleeve in August 2013 Supply of new top cover in October Top cover has been supplied in 6 months Contractor Refurbishment of runner Refurbishment of labyrinth ring Supply of new epoxy runner insulation disc Line boring works for assembly of top cover and pivot ring

25 Components after refurbishmentt Regulating ring MIV Guide Vane Levers New top Cover supplied by OEM New Pivot Ring

26 Pivot ring Order placed on Contractor for supply of pivot ring Noticed difference in flange thickness by 4.5mm during inspection Contractor proposed to provide additional plate of 4.5mm thickness of stainless steel-304 with rigid counter shank screw locking Contractor informed that they would fillet weld the SS plate with the base of pivot ring on the whole periphery Old Pivot Ring New Pivot Ring

27 Top Cover It was observed that the base metal has eroded more than 75% at critical areas and most of the eroded areas were beyond refurbish/repair. Contractor and OEM recommended for replacement of top cover. Old Top Cover Both recommended for replacement of top cover. The offer obtained from OEM was less and also time period offered was also less. Top Cover was supplied in six months New Top Cover

28 Turbine Shaft 2 Nos. cracks of size 170mm and 42mm found in Shaft at shaft seal machining area during DP test Around 7mm deep penetration of crack observed through traverse length of 50 60mm at Shaft sleeve seating area through Ultrasonic test OEM was consulted in the matter OEM informed that the defective portion of turbine shaft would be machined and diameter of the shaft shall be reduced in the entire portion where the shaft sleeve is to be fitted New SS shaft sleeve with reduced ID shall be fitted on the shaft & its OD machined Additional order placed on OEM for refurbishment of turbine shaft along with new SS shaft sleeve Time taken was about 4 months Turbine shaft under DP test

29 Runner After opening of unit 6, the following observations were made: Multiple pitting on runner vanes Metal chipped out 30 to 50mm from Runner vane exit area After NDT tests at factory, it was observed that runner had 236 indications on outside of 4-30mm and inside 85nos. indications of 4-20mm Both OEM and Contractor recommended for replacement of runner After detailed studies and need to put back the unit at the earliest, additional order for refurbishment of runner was placed on the Contractor. Metal Chipped out Turbine shaft under DP test Runner after refurbishment

30 Line boring Works Challenges: Stay ring refurbished in site. New Pivot ring with tolerance for line boring 0.25mm Machined in separate CNC machine. New top cover with tolerance of 2 mm for line boring Machined in separate CNC machine. Refurbished runner Observed that dia of top cover at regulating ring seating area was excess by 6mm. Pilot holes were provided for doweling. It was necessary to have proper matching for concentricity of holes with different parts and matching of dimensions of holes with close tolerances 0.05 mm/ m. An additional order placed for line boring works order value 24 Lakhs. Delivery period 45 days.

31 Matching of top cover and pivot ring at site This is a rare case of matching different components to achieve required results Top cover and pivot ring were manufactured by two different machines. Re-engineering took considerable amount of time The clearance between Labyrinth ring and top cover was maintained by 4 dowels and complete load of static labyrinth taken by bolts and transferred to top cover Unit 6 was synchronized to grid after completion of R, M&U works on Main reason for delay is non-availability of as built drawings and surprises noticed after opening of the unit Higher capacity oil coolers provided to bring down thrust bearing temperature and its performance after commissioning is satisfactory

32 Benefits Derived after R,M&U Works: Addition of 90 MW peaking capacity to the grid Life extension of 10 to 15 years Problem of over drawal of field current has been resolved by achieving circularity in stator and rotor forms Performance of the unit with respect to vibration and temperature rise of thrust bearing is generally satisfactory and is under observation Online monitoring of vibration levels and PD Analyser has become a safety tool to monitor the units at any instant of time

33 CONCLUSION R, M & U of the units provide opportunity for correcting some of the inherent problems and adopting new technology Challenging considering the requirement to match with many old parts for which neither machine drawings nor design calculations are available Undertaking timely RM&U & Life extension programme, life of generators has been extended Major works has been carried out only in Generator portion and higher output is achieved through higher guide vane opening utilizing the margins available in old machines It is clear from the experience of R, M & U that extent of refurbishment/replacement required in respect of turbine could not be assessed before opening of the unit

34 CONCLUSION After opening of the unit, reverse engineering will take considerable time which will affect the schedule of erection and commissioning OEM will have the advantage of having the initial designs and hence has the advantages with respect to manufacturing and delivery of new components NON-OEM manufacture may have a different solution for solving the problems. It may be difficult to bench mark the prices especially with respect to refurbishment works and with two differing technologies. These aspects have to be factored while executing the works to adhere to planned schedule

35 CONCLUSION We have taken up preparation of DPR for R&M works of turbine of Unit-1,2 & 3 in association with IIT Roorkee. DPR prepared and submitted to Hon ble KERC.

36 Rotor Turbine shaft Runner

37 Cross section of turbine with location of runner and top cover Top Cover Pivot ring Runner

38 THANK YOU

Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014

Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014 Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project NWHA Spokane October 30, 2014 0 The Wells Project WELLS Chief Joseph Rocky Reach East Wenatchee Wells Dam Location Columbia

More information

Generators for the age of variable power generation

Generators for the age of variable power generation 6 ABB REVIEW SERVICE AND RELIABILITY SERVICE AND RELIABILITY Generators for the age of variable power generation Grid-support plants are subject to frequent starts and stops, and rapid load cycling. Improving

More information

McNary Northshore Fishway Hydro Project. History & Lessons Learned

McNary Northshore Fishway Hydro Project. History & Lessons Learned McNary Northshore Fishway Hydro Project History & Lessons Learned May 6, 2017 21 th Annual TECHNICAL SEMINAR Machines, Maintenance, and Management: Keeping Hydro Facilities Up and Running History & Lessons

More information

LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines. Marcio Gennari ABB Brazil Automation Products Machines Service Osasco

LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines. Marcio Gennari ABB Brazil Automation Products Machines Service Osasco LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines Marcio Gennari ABB Brazil Automation Products Machines Service Osasco LEAP - Introduction ABB India (excellence center in insulation

More information

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT Electro-Mechanical Works Guidelines for Erection, Testing and Commissioning of SHP Plants Sponsor: Ministry of New and Renewable Energy Govt. of

More information

Douglas County PUD. Wells Dam Turbine Refurbishment

Douglas County PUD. Wells Dam Turbine Refurbishment Douglas County PUD Wells Dam Turbine Refurbishment Project Background Commissioned 1967-1969 Ten vertical, 5-bladed, Kaplan units 120,700 hp, 81.5 MVA rated generator output 292.25 in Runner diameter Original

More information

1. HVOF Coating. Tungsten Carbide Typical Chemical Composition Typical HVOF Parameters

1. HVOF Coating. Tungsten Carbide Typical Chemical Composition Typical HVOF Parameters 1. HVOF Coating Tungsten Carbide Typical Chemical Composition Typical HVOF Parameters Innovations of SJVN Hard coating plant installed at NJHPS which is 1 st ever hard coating plant provided at a Hydel

More information

The Magazine of the North American Hydroelectric Industry HYDRO REVIEW. NHA Annual Conference details pg. 69

The Magazine of the North American Hydroelectric Industry HYDRO REVIEW. NHA Annual Conference details pg. 69 March 2012 www.hydroworld.com The Magazine of the North American Hydroelectric Industry HYDRO REVIEW NHA Annual Conference details pg. 69 Rehabilitation What began as a unit inspection at a vintage hydroelectric

More information

AGN 076 Alternator Bearings

AGN 076 Alternator Bearings Application Guidance Notes: Technical Information from Cummins Generator Technologies AGN 076 Alternator Bearings BEARING TYPES In the design of STAMFORD and AvK alternators, the expected types of rotor

More information

Excitation system is of Static Silicon Excitation System, including excitation transformer, thyristors, and AVR.

Excitation system is of Static Silicon Excitation System, including excitation transformer, thyristors, and AVR. Turbo - Generator Type: QF Series 1. General The generator is a two pole, cylindrical rotor type synchronous machine, directly coupled with steam turbine. It has a closed-circuit cooling system to cool

More information

MECHANICAL INTEGRITY CHECKING OF GENERATOR STATOR OVERHANG BY NATURAL FREQUENCY MEASUREMENT

MECHANICAL INTEGRITY CHECKING OF GENERATOR STATOR OVERHANG BY NATURAL FREQUENCY MEASUREMENT MECHANICAL INTEGRITY CHECKING OF GENERATOR STATOR OVERHANG BY NATURAL FREQUENCY MEASUREMENT R.K.Bhatnagar, A.K.Mukherjee, National Thermal Power Corp., India akmukherjee04@ntpceoc.co.in INTRODUCTION Reliable

More information

EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model

EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model Contents Model A0553 C1125 V0494 A0713 C1285 V0554 A0843 C1455 V0754 A03 C15 V0854 C1915 V0974 C2185 V1154 C2905 Section Page Specifications 3-3 Model Designation 3-6 Impeller Data 3-8 Material Specifications

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT Electro-Mechanical Works Guidelines for Specifications for Procurement of SHP Generating Equipment Sponsor: Ministry of New and Renewable Energy

More information

PLACE FOR TITLE AUTHORS. Potassium Carbonate Pump Failure High Axial Movement due to Uncontrolled (unbalanced) forces.

PLACE FOR TITLE AUTHORS. Potassium Carbonate Pump Failure High Axial Movement due to Uncontrolled (unbalanced) forces. PLACE FOR TITLE Potassium Carbonate Pump Failure High Axial Movement due to Uncontrolled (unbalanced) forces. AUTHORS Ibrahim AbdAl-Wahab Ammonia Sector Head Misr Fertilizer Production Company Hatem AbdelRahman

More information

GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED MTPA PAC PROJECT SECTION 6 ANNEXURE 4.7 SPARES, INSP AGENCY & DOCUMENTATION

GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED MTPA PAC PROJECT SECTION 6 ANNEXURE 4.7 SPARES, INSP AGENCY & DOCUMENTATION A. SPARE PARTS Outline for the supply of Spare Parts for various items is as elaborated below: A-1 MACHINERY Commissioning spares will be as per the manufacturer s recommendations. For 2 years of normal

More information

Technical Notes by Dr. Mel

Technical Notes by Dr. Mel Technical Notes by Dr. Mel April 2009 Solving Ring-Oiled Bearing Problems In recent years, TRI has encountered and resolved a number of problems with ring-oiled bearings for fans, motors, and pumps. Oiling

More information

APPLICATION OF VARIABLE FREQUENCY TRANSFORMER (VFT) FOR INTEGRATION OF WIND ENERGY SYSTEM

APPLICATION OF VARIABLE FREQUENCY TRANSFORMER (VFT) FOR INTEGRATION OF WIND ENERGY SYSTEM APPLICATION OF VARIABLE FREQUENCY TRANSFORMER (VFT) FOR INTEGRATION OF WIND ENERGY SYSTEM A THESIS Submitted in partial fulfilment of the requirements for the award of the degree of DOCTOR OF PHILOSOPHY

More information

STEAM TURBINE MODERNIZATION SOLUTIONS PROVIDE A WIDE SPECTRUM OF OPTIONS TO IMPROVE PERFORMANCE

STEAM TURBINE MODERNIZATION SOLUTIONS PROVIDE A WIDE SPECTRUM OF OPTIONS TO IMPROVE PERFORMANCE STEAM TURBINE MODERNIZATION SOLUTIONS PROVIDE A WIDE SPECTRUM OF OPTIONS TO IMPROVE PERFORMANCE Michael W. Smiarowski, Rainer Leo, Christof Scholten, Siemens Power Generation (PG), Germany John Blake,

More information

Inspection Testing Repair

Inspection Testing Repair Inspection Testing Repair Generator Technical Services 1810 Blackwell Lane Penascola, FL 32514 Phone (850) 471-1101 Fax (850) 471-1104 Email: info@gentechservices.com Power Generation Generator Technical

More information

Primary Heat Transport (PHT) Motor Rotor Retaining Ring Failure

Primary Heat Transport (PHT) Motor Rotor Retaining Ring Failure 1 Primary Heat Transport (PHT) Motor Rotor Retaining Ring Failure Ali Malik Components & Equipment Eng. Ontario Power Generation - Darlington Nuclear 2 Ontario Power Generation Darlington Darlington Nuclear

More information

Large Air Cooled Generator Failure

Large Air Cooled Generator Failure Large Air Cooled Generator Failure Henry Tarnecky AVP - Sr. Engineering Specialist, FM Global 2017 IRIS Rotating Machinery Conference FM Global Basics Commercial/Industrial Property Insurer Mutual Co.,

More information

VACUUM PUMP-3A. Running Hour: 8646 Ref Speed: 660 RPM OBSERVATION. Peakvue reading was 0.3 at Vacuum Pump NDE bearing.

VACUUM PUMP-3A. Running Hour: 8646 Ref Speed: 660 RPM OBSERVATION. Peakvue reading was 0.3 at Vacuum Pump NDE bearing. VACUUM PUMP-3A Machine Component Vacuum Pump NDE Bearing Spectrum, Vol-1, Oct-2013 ISO 10816 Severity level for class III Machine Vibration Level NORMAL MARGINAL CRITICAL Up to 4.5 mm/sec 4.5 to 11.2 mm/sec

More information

Steampath Services Capabilities. The Turbine-Generator Engineering & Outage Services Company

Steampath Services Capabilities. The Turbine-Generator Engineering & Outage Services Company Steampath Services Capabilities The Turbine-Generator Engineering & Outage Services Company Steampath Engineering Services Mechanical Dynamics & Analysis is one of the world s leading suppliers of steampath

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Brochure. Wind turbine generators Reliable technology for all turbine applications

Brochure. Wind turbine generators Reliable technology for all turbine applications Brochure Wind turbine generators Reliable technology for all turbine applications 2 ABB Wind turbine generators We provide motors and generators, services and expertise to save energy and improve customers

More information

Generator. Jason S DiSanto. 6B Users Conference San Antonio, TX June 19-22, 2017

Generator. Jason S DiSanto. 6B Users Conference San Antonio, TX June 19-22, 2017 Generator Jason S DiSanto 6B Users Conference San Antonio, TX June 19-22, 2017 GE Power 2017, General Electric Company. GE Proprietary Information - The information contained in this document is General

More information

DSZ3. EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model

DSZ3. EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model Contents Model A0553 C1125 V0494 A0713 C1285 V0554 A0843 C1455 V0754 A1003 C1605 V0854 C1915 V0974 C2185 V1154 C2905 Section Page Specifications 3-203 Model Designation 3-206 Impeller Data 3-208 Material

More information

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand.

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. WHAKAMARU POWER STATION REHABILITATION PROJECT Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. ABSTRACT Whakamaru Power Station in the North Island of New Zealand

More information

Voith Hydro Services Generating Results for you. On Site. On Time. On Budget.

Voith Hydro Services Generating Results for you. On Site. On Time. On Budget. Voith Hydro Services Generating Results for you. On Site. On Time. On Budget. 1 2 Voith Hydro Services The Voith Hydro Difference Combining the engineering reliability Voith with the speed and expertise

More information

Rosa Power Supply Company Limited (RPSCL) Rosa Unit-2 AVR Sensitivity

Rosa Power Supply Company Limited (RPSCL) Rosa Unit-2 AVR Sensitivity Rosa Unit-2 AVR Sensitivity Features of Automatic Voltage Regulator The control of excitation power to the generator is the primary function of AVR. The measure of reactive power demand in the Grid is

More information

Rolls-Royce Corporation 501-D22 COMMERCIAL ENGINE BULLETIN (CEB) Technical Publications Index

Rolls-Royce Corporation 501-D22 COMMERCIAL ENGINE BULLETIN (CEB) Technical Publications Index Corporation 501-D22 COMMERCIAL ENGINE BULLETIN (CEB) Technical Publications Index May 1. 2018 72-- ENGINE 72--1001 Engine -- Reduction Gear Prop Recommended No Later Than 11--01--66 No. 2, 11--15--68 Brake

More information

Extended requirements on turbogenerators

Extended requirements on turbogenerators , Siemens AG, Mülheim/Ruhr, Germany Extended requirements on turbogenerators due to changed operational regimes siemens.com Table of Content Evaluation of current operation regimes Extended requirements

More information

Sub:EE6604/DESIGN OF ELECTRICAL MACHINES Unit V SYNCHRONOUS MACHINES. 2. What are the two type of poles used in salient pole machines?

Sub:EE6604/DESIGN OF ELECTRICAL MACHINES Unit V SYNCHRONOUS MACHINES. 2. What are the two type of poles used in salient pole machines? SRI VIDYA COLLEGE OF ENGINEERING & TECHNOLOGY DEPARTMENT OF EEEE QUESTION BANK Sub:EE6604/DESIGN OF ELECTRICAL MACHINES Unit V SYNCHRONOUS MACHINES 1. Name the two types of synchronous machines. 1. Salient

More information

Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4 Stroke Engine

Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4 Stroke Engine IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 08, 2015 ISSN (online): 2321-0613 Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4

More information

APPENDIX B SPECIFICATION FOR GENERATOR OVERHAUL EMD MODEL AR10 D18... B-1

APPENDIX B SPECIFICATION FOR GENERATOR OVERHAUL EMD MODEL AR10 D18... B-1 Table of Contents APPENDIX B SPECIFICATION FOR GENERATOR OVERHAUL EMD MODEL AR10 D18... B-1 B.01 SCOPE... B-1 B.02 GENERAL... B-1 B.03 ELECTRICAL QUALIFICATION... B-1 B.04 EQUIPMENT RECONDITIONING... B-2

More information

Electrical Machine Service. Overhaul, Conditioning, On-Site Service and Diagnostics. Excellent Technology, Efficiency and Quality

Electrical Machine Service. Overhaul, Conditioning, On-Site Service and Diagnostics. Excellent Technology, Efficiency and Quality World Class Power Solutions Excellent Technology, Efficiency and Quality Electrical Machine Service Overhaul, Conditioning, On-Site Service and Diagnostics 2 3 Your partner for Electrical Machine Service

More information

ME High Pressure Stage Casing Pump

ME High Pressure Stage Casing Pump Sulzer Pumps ME High Pressure Stage Casing Pump The Heart of Your Process Sulzer Pumps Your Partner for Pumping Solutions Sulzer Pumps is one of the world leaders in state-of-the-art pumping solutions.

More information

ESIA Study for 1,050MW Coal Fired Power Plant, Lamu County, Kenya Need for the Project. 3 Need for the project... 2

ESIA Study for 1,050MW Coal Fired Power Plant, Lamu County, Kenya Need for the Project. 3 Need for the project... 2 Contents 3 Need for the project... 2 3.1. Project Background... 2 3.2. Energy mix and demand forecast... 2 3.3. 5000+ Project... 4 List of tables Table 3-1: Electric power generation sources and energy

More information

Dynamic Balancing. Need a high-speed balance? No problem.

Dynamic Balancing. Need a high-speed balance? No problem. Dynamic Balancing TOSHIBA is one of North America s leading turbine/generator service providers. Our unique highspeed balance and overspeed facility assures that proper balance is achieved prior to returning

More information

Report on Major Achievements, Significant Developments and Important events for The Month of September-2018

Report on Major Achievements, Significant Developments and Important events for The Month of September-2018 Report on Major Achievements, Significant Developments and Important events for The Month of September-2018 Following are the details of major achievements, significant developments and important events

More information

WMDA Series WMDA. Seal-less Mag-Drive Pumps. MAG-DRIVE ANSI-B73.1 ISO-2858 or API-685 CENTRIFUGAL PUMPS

WMDA Series WMDA. Seal-less Mag-Drive Pumps. MAG-DRIVE ANSI-B73.1 ISO-2858 or API-685 CENTRIFUGAL PUMPS Seal-less Mag-Drive Pumps Seal-less Mag-Drive Pump Specialists WORKING LIMITS QMAX = 1800 USGPM @ 3500RPM; 350 cm/h @ 2900 RPM HMAX = 700 ft @ 3500RPM; 150 m @ 2900RPM T = -212 F (-100 C) up to 662 F (350

More information

Global VPI Insulated Indirectly Hydrogen-Cooled Turbine Generator for Single-Shaft Type Combined Cycle Power Generation Facilities

Global VPI Insulated Indirectly Hydrogen-Cooled Turbine Generator for Single-Shaft Type Combined Cycle Power Generation Facilities Global VPI Insulated Indirectly Hydrogen-Cooled Turbine Generator for Single-Shaft Type Combined Cycle Power Generation Facilities YAMAZAKI Masaru NIIKURA Hitoshi TANIFUJI Satoshi ABSTRACT Fuji Electric

More information

Enhanced Process Efficiency Hot gas expander replacement

Enhanced Process Efficiency Hot gas expander replacement Enhanced Process Efficiency Hot gas expander replacement Enhanced Process Efficiency Technical complexity and tight schedule With increasing operational problems and the declining reliability of a 30-year-old

More information

CHAPTER 7 CONCLUSION

CHAPTER 7 CONCLUSION 125 CHAPTER 7 CONCLUSION 7.1 CONCLUSION Motors of rating less than 15 HP form 80 % of the motor population in India. In agriculture, the commonly used ratings of motors are 5 HP (3.7 kw) and 3 HP. The

More information

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2 BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR 1.00.00 GENERAL 1.01.00 Make : Jinan Power Equipment Factory 1.02.00 Type : WX21Z-073LLT 1.03.00 Reference Standard : GB/T7064-2002

More information

Boiler Feed Booster Pump YNK. Type Series Booklet

Boiler Feed Booster Pump YNK. Type Series Booklet YNK Type Series Booklet Legal information/copyright Type Series Booklet YNK All rights reserved. The contents provided herein must neither be distributed, copied, reproduced, edited or processed for any

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

REAP CARE ROTATING ELECTRICAL ASSET PROGNOSTIC CARE

REAP CARE ROTATING ELECTRICAL ASSET PROGNOSTIC CARE REAP CARE ROTATING ELECTRICAL ASSET PROGNOSTIC CARE Longevity approach Assess & Avoid Failures ROTATING ELECTRICAL ASSET PROGNOSTIC CARE Failure Statistics Failure Statistics Failure Statistics BEARING

More information

A Homopolar Inductor Motor/Generator and Six-step Drive Flywheel Energy Storage System

A Homopolar Inductor Motor/Generator and Six-step Drive Flywheel Energy Storage System A Homopolar Inductor Motor/Generator and Six-step Drive Flywheel Energy Storage System Perry Tsao, Matt Senesky, Seth Sanders University of California, Berkeley Perry s thesis defense presented www-power.eecs.berkeley.edu

More information

PWM APi 610 BB3 Multistage Pump

PWM APi 610 BB3 Multistage Pump PWM APi 610 BB3 Multistage Pump HyDrAUliC PerfOrMAnCe COVerAge FLOW (m 3 /h) 60 Hz Performance Coverage Visit our web site at www.pumpworks610.com and specify flow and performance needs and obtain pump

More information

Configuration of a generator

Configuration of a generator Configuration of a generator Machinery Generator assembly, outline of generator Functional 1 Describe processes. Prepositions and verbs Suez Manual Guillermo Montoya G. Color: None Duplex: 1-4 What is

More information

Customer presentation, PG Service, BU Motors and Generators ABB LEAP Stator Winding-Condition & Lifetime assessment

Customer presentation, PG Service, BU Motors and Generators ABB LEAP Stator Winding-Condition & Lifetime assessment Customer presentation, PG Service, BU Motors and Generators ABB LEAP Stator Winding-Condition & Lifetime assessment ABB LEAP Overview ABB LEAP - Benefits for customer Motivation to perform LEAP Failures

More information

Derrick Boltt Southern Region Hydro Generation Eskom South Africa

Derrick Boltt Southern Region Hydro Generation Eskom South Africa Derrick Boltt Southern Region Hydro Generation Eskom South Africa Hydro Power in the S/Region. History of Hydro in the S/Region. In 198 the former Transkei government financed the development of Hydro

More information

Latest Developments in Siemens Large Gas Turbine Portfolio. Matthias Fränkle 8000H Product Manager

Latest Developments in Siemens Large Gas Turbine Portfolio. Matthias Fränkle 8000H Product Manager Latest Developments in Siemens Large Gas Turbine Portfolio Matthias Fränkle 8000H Product Manager siemens.com/power-gas Table of content Power Market Challenges for Large Gas Turbines The Siemens Heavy

More information

PWM. API 610 BB3 Multistage Pump

PWM. API 610 BB3 Multistage Pump PWM API 610 BB3 Multistage Pump HYDRAULIC PERFORMANCE COVERAGE FLOW (m 3 /h) 60 Hz Performance Coverage Visit our web site at www.pumpworks610.com and specify flow and performance needs and obtain pump

More information

Installation Instructions

Installation Instructions Installation Instructions Durametallic Double CRO Dual single coil spring friction drive for applications with water lubrication properties 1 Equipment Check 1.1 Follow plant safety regulations prior to

More information

FCR asynchronous brake motors LS FCR. General information

FCR asynchronous brake motors LS FCR. General information General information LIFTING USE : U.L. Enclosed three-phase asynchronous brake motors, LS series with failsafe brake, according to IEC 34, 72, EN 50281. Single speed : 0.55 to 15, frame size from 80 to

More information

Brakes. KNOTT Electromagnetic Release Spring-Applied Dual-Surface Fail-Safe Brakes TYPE ERA, ERB, ERC ELECTROMAGNETIC

Brakes. KNOTT Electromagnetic Release Spring-Applied Dual-Surface Fail-Safe Brakes TYPE ERA, ERB, ERC ELECTROMAGNETIC Brakes ELECTROMAGNETIC KNOTT Electromagnetic Release Spring-Applied Dual-Surface Fail-Safe Brakes TYPE ERA, ERB, ERC www.knott.de We make your brake 1 KNOTT manufacture a wide range of electromagnetic

More information

OPERATION & MAINTENANCE MANUAL HANGZHOU FLYING TECHNOLOGY CO., LTD.

OPERATION & MAINTENANCE MANUAL HANGZHOU FLYING TECHNOLOGY CO., LTD. CENTRIFUGAL PUMP ZPD6-25*7 OPERATION & MAINTENANCE MANUAL HANGZHOU FLYING TECHNOLOGY CO., LTD. CONTENTS 1. GENERAL (1) 2. NOMENCLATURE OF THE TYPE (1) 3. MAIN TECHNICAL SPECIFICATIONS RANGE (1) 4. STANDARD

More information

DETECTION & RECTIFICATION OF TURBINE BALANCE DRUM LABYRINTH SEAL FAILURE OF TDBFP: A CASE STUDY

DETECTION & RECTIFICATION OF TURBINE BALANCE DRUM LABYRINTH SEAL FAILURE OF TDBFP: A CASE STUDY DETECTION & RECTIFICATION OF TURBINE BALANCE DRUM LABYRINTH SEAL FAILURE OF TDBFP: A CASE STUDY P r e s e n t e d b y U j j w a l S a r k a r, S u p d t ( O & M / T M D ) S a n a t a n P a l, S u p d t

More information

SPECIFY THE RIGHT HOT OIL PUMP FOR YOUR APPLICATION

SPECIFY THE RIGHT HOT OIL PUMP FOR YOUR APPLICATION SPECIFY THE RIGHT HOT OIL PUMP FOR YOUR APPLICATION Hot oil pumps are used in a range of industries, with their main user being the heat transfer oil customer. Often, oil temperatures will exceed 500 F

More information

Steam Turbine Generator Core Isolation Issues at the Redhawk Combined Cycle Plant

Steam Turbine Generator Core Isolation Issues at the Redhawk Combined Cycle Plant Steam Turbine Generator Core Isolation Issues at the Redhawk Combined Cycle Plant Marques Montes Arizona Public Service Company Phoenix, AZ Includes material provided by John Demcko Redhawk Power Plant

More information

PWM API 610 BB3 Multistage Pump

PWM API 610 BB3 Multistage Pump PWM API 610 BB Multistage Pump PWM API 610 BB MULTISTAGE PUMP HYDRAULIC PERFORMANCE COVERAGE 60 Hz Performance Coverage FLOW (m /h) Visit our web site at www.pumpworks610.com and specify flow and performance

More information

Motor Technology Mounting Design Guide

Motor Technology Mounting Design Guide Motor Technology Mounting Design Guide TN-2101 REV 160701 INTRODUCTION This document details the installation and integration of Celera Motion frameless kit motors into our customers applications. It provides

More information

our contribution for Sealless Magnetic Coupled Multistage Centrifugal Pumps Type HZM / HZMR / HZMB environmental protection

our contribution for Sealless Magnetic Coupled Multistage Centrifugal Pumps Type HZM / HZMR / HZMB environmental protection Sealless Magnetic Coupled Multistage Centrifugal Pumps Type HZM / HZMR / HZMB our contribution for environmental protection General DICKOW-pumps of series HZM are sealless multistage horizontal centrifugal

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

CHAPTER 4 HARDWARE DEVELOPMENT OF DUAL ROTOR RADIAL FLUX PERMANENT MAGNET GENERATOR FOR STAND-ALONE WIND ENERGY SYSTEMS

CHAPTER 4 HARDWARE DEVELOPMENT OF DUAL ROTOR RADIAL FLUX PERMANENT MAGNET GENERATOR FOR STAND-ALONE WIND ENERGY SYSTEMS 66 CHAPTER 4 HARDWARE DEVELOPMENT OF DUAL ROTOR RADIAL FLUX PERMANENT MAGNET GENERATOR FOR STAND-ALONE WIND ENERGY SYSTEMS 4.1 INTRODUCTION In this chapter, the prototype hardware development of proposed

More information

INTER PLANT STANDARD STEEL INDUSTRY

INTER PLANT STANDARD STEEL INDUSTRY INTER PLANT STANDARD STEEL INDUSTRY IPSS SPECIFICATION FOR ac CRANE (Hoist and Winches) DUTY SQUIRREL CAGE INDUCTION MOTORS (Fourth Revision) BASED ON IS 325:1996 Formerly: IPSS:1-03-004-05 0. FOREWORD

More information

Workshop on Grid Integration of Variable Renewable Energy: Part 1

Workshop on Grid Integration of Variable Renewable Energy: Part 1 Workshop on Grid Integration of Variable Renewable Energy: Part 1 System Impact Studies March 13, 2018 Agenda Introduction Methodology Introduction to Generators 2 Introduction All new generators have

More information

Simson Haulofu Divisional Manager. NamPower Namibia

Simson Haulofu Divisional Manager. NamPower Namibia Simson Haulofu Divisional Manager NamPower Namibia Agenda Overview of Ruacana Some interesting facts about Ruacana Ruacana s contribution to Namibia Ruacana operating regime Unit 4: Business case & feasibility

More information

Hydro Power Synchronous Generators. Power range MW

Hydro Power Synchronous Generators. Power range MW Hydro Power Synchronous Generators Power range 0.3-20MW Trusted Hydro Experts Over 4GW installed capacity worldwide Generators up to 20MW 50 years of experience Over 450 projects completed worldwide over

More information

UNBALANCED MAGNETIC PULL AND AIR-GAP MONITORING FOR LARGE HYDROGENERATORS

UNBALANCED MAGNETIC PULL AND AIR-GAP MONITORING FOR LARGE HYDROGENERATORS UMP - MONITORING UNBALANCED MAGNETIC PULL AND AIR-GAP MONITORING FOR LARGE HYDROGENERATORS AN INNOVATIVE MEASUREMENT DEVICE FOR THE MONITORING OF STATOR AND ROTOR MAGNETIC CIRCUITS Dr. Mai Tuxuan, Prof.

More information

III B.Tech I Semester Supplementary Examinations, May/June

III B.Tech I Semester Supplementary Examinations, May/June Set No. 1 III B.Tech I Semester Supplementary Examinations, May/June - 2015 1 a) Derive the expression for Gyroscopic Couple? b) A disc with radius of gyration of 60mm and a mass of 4kg is mounted centrally

More information

Inside the Generator

Inside the Generator NHA Hydraulic Power Committee Fall Retreat & NWHA Technical Conference October 3, 2018 Walla Walla, WA Inside the Generator W. Howard Moudy Director of Operations National Electric Coil The Classic Simplified

More information

High Performance Machine Design Considerations

High Performance Machine Design Considerations High Performance Machine Design Considerations High Performance Machine Design Considerations Abstract From Formula One race cars to consumer vehicles, the demand for high performing, energy efficient

More information

CRANKSHAFT REAR RADIAL SEAL

CRANKSHAFT REAR RADIAL SEAL 1B-38 CRANKSHAFT REAR RADIAL SEAL Preceding Work: Removal of flywheel or drive plate 1. Special tool 2. Special tool 3. Crankshaft rear seal Tools Required W9911 0020B (601 589 03 43 00) Crankshaft Rear

More information

Slip-ring motors MAR Series

Slip-ring motors MAR Series Slip-ring motors MAR Series ABOUT US DAC Electric is a fairly young but highly experienced combination of professionals from all over the world. The founders, from the Netherlands and the Czech Republic,

More information

Appendix G Examples and Recommended Methods

Appendix G Examples and Recommended Methods Reporting Outages to the Generating Availability Data System (GADS) Introduction The examples in this appendix illustrate the reporting of outages and deratings to GADS. They are based on a fictional 600

More information

OVERALL INSPECTION AND INTEGRITY ASSESSMENT OF OIL AND OIL PRODUCTS STORAGE TANKS R.S.

OVERALL INSPECTION AND INTEGRITY ASSESSMENT OF OIL AND OIL PRODUCTS STORAGE TANKS R.S. OVERALL INSPECTION AND INTEGRITY ASSESSMENT OF OIL AND OIL PRODUCTS STORAGE TANKS R.S. Gaspariants., G.A. Giller (JSC VNIIST, RUSSIA) L.Y. Mogilner., Y.Y. Semin (CJSC VNIIST-Diagnostika, RUSSIA) Steel

More information

SIGENTICS HV Series S-modyn

SIGENTICS HV Series S-modyn SIGENTICS HV Series S-modyn High-voltage 3-phase salient pole generators siemens.com/sigentics Answers for industry. SIGENTICS: 4-pole generators for industrial turbines The energy business is characterized

More information

ELECTRO MECHANICAL INNOVATION IN Rail

ELECTRO MECHANICAL INNOVATION IN Rail ELECTRO MECHANICAL INNOVATION IN Rail Since contract award, Houghton International has delivered the contract as agreed, mobilising within the agreed time period and supplying the product as per the agreed

More information

PULVERISERS FOR SUPER CRITICAL UNITS PRESENTAION BY: M.V.R.MURTHY & SATISH GHATGE AGM/ PULV ENGG. BHEL HYD. Pulveriser Engineering Department

PULVERISERS FOR SUPER CRITICAL UNITS PRESENTAION BY: M.V.R.MURTHY & SATISH GHATGE AGM/ PULV ENGG. BHEL HYD. Pulveriser Engineering Department PULVERISERS FOR SUPER CRITICAL UNITS PRESENTAION BY: M.V.R.MURTHY & SATISH GHATGE AGM/ PULV ENGG. BHEL HYD. RANGE OF PULVERISERS FOR SUPERCRITICAL UNITS HP1103 BOWL MILL WITH STATIC CLASSIFIER HP1103 BOWL

More information

COMMISSION REGULATION (EU) / of XXX

COMMISSION REGULATION (EU) / of XXX EUROPEAN COMMISSION Brussels, XXX [ ](2018) XXX draft COMMISSION REGULATION (EU) / of XXX amending Regulation (EU) No 548/2014 of 21 May 2014 on implementing Directive 2009/125/EC of the European Parliament

More information

Agenda of 11 th System Studies Meeting in NER

Agenda of 11 th System Studies Meeting in NER Agenda of 11 th System Studies Meeting in NER Date: 16.12.2015. Venue: Hotel Nandan, Guwahati 1. Review of SPS I, II, III & SPS IV related to Palatana GBPP, OTPC after commissioning of Palatana Module

More information

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99 Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99 Version 1 August 2018 www.energynetworks.org 2 Introduction Connection of Power Generating Modules to DNO

More information

20.Cylinder Block. Cylinder Block A: REMOVAL ME(H4DOTC)-63 ST CRANKSHAFT STOPPER

20.Cylinder Block. Cylinder Block A: REMOVAL ME(H4DOTC)-63 ST CRANKSHAFT STOPPER Cylinder Block MECHANICAL 20.Cylinder Block A: REMOVAL Before conducting this procedure, drain engine oil completely. 1) Remove the intake manifold. 2)

More information

Report for CSP Joint Venture Click to edit Master text styles Second level Third level. Fifth level

Report for CSP Joint Venture Click to edit Master text styles Second level Third level. Fifth level Report for CSP Joint Venture Click to edit Master text styles Second level Third level Out of service examination, ultrasonic thickness Fourth survey and level paint evaluation for tanks T221 & T222 Fifth

More information

An Investigation into a new method to repair motor cores and improve Efficiency

An Investigation into a new method to repair motor cores and improve Efficiency An Investigation into a new method to repair motor cores and improve Efficiency Henk de Swart Marthinusen & Coutts Dennis Willemse, Gerhard Bergh, Thava Perumal Sasol Introduction A South African based

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

CHAPTER 2 MODELLING OF SWITCHED RELUCTANCE MOTORS

CHAPTER 2 MODELLING OF SWITCHED RELUCTANCE MOTORS 9 CHAPTER 2 MODELLING OF SWITCHED RELUCTANCE MOTORS 2.1 INTRODUCTION The Switched Reluctance Motor (SRM) has a simple design with a rotor without windings and a stator with windings located at the poles.

More information

HCD-135. Industrial Control Damper. Application and Design. Ratings (see page 2 and 3 for specific limitations) Standard Construction.

HCD-135. Industrial Control Damper. Application and Design. Ratings (see page 2 and 3 for specific limitations) Standard Construction. Application and Design Model is a heavy duty industrial control damper with a flanged frame. It is designed to control airflow and provide shut off in HVAC or industrial process control systems. A variety

More information

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 100 CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 6.1 INTRODUCTION Conventional energy resources are not sufficient to meet the increasing electrical power demand. The usages of

More information

Gas turbine outage Sept 2012 Bad things happen to a well planned outage

Gas turbine outage Sept 2012 Bad things happen to a well planned outage Gas turbine outage Sept 2012 Bad things happen to a well planned outage 1- Signed contract 2- All new parts ordered and received 3- All parts identified and on site 4- Scope of work complete for: Rotor

More information

25 Williamsville Road Barre, MA Tel Fax HEATER DRAIN PUMP OVERHAUL CASE NO AP-194

25 Williamsville Road Barre, MA Tel Fax HEATER DRAIN PUMP OVERHAUL CASE NO AP-194 Engineered Pumps and Services 25 Williamsville Road Barre, MA 01005 Tel 978-355-2911 Fax 978-355-2917 HEATER DRAIN PUMP OVERHAUL CASE NO AP-194 Chas G Allen received the contract to overhaul an Ingersoll-Rand

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different

More information

Sealless Magnetic Coupled Multistage Centrifugal Pumps with Priming Stage Type HZSM / HZSMB / HZSMR / HZSMA / HZSMAR

Sealless Magnetic Coupled Multistage Centrifugal Pumps with Priming Stage Type HZSM / HZSMB / HZSMR / HZSMA / HZSMAR Sealless Magnetic Coupled Multistage Centrifugal Pumps with Priming Stage Type HZSM / HZSMB / HZSMR / HZSMA / HZSMAR our contribution for environmental protection General DICKOW-pumps of series HZSM are

More information

Generator Termination Bus-bar Arrangement - Design requirements: Utility Perspective

Generator Termination Bus-bar Arrangement - Design requirements: Utility Perspective Generator Termination Bus-bar Arrangement - Design requirements: Utility Perspective D. K. Chaturvedi (NTPC) Harshvardhan Senghani (NTPC) K Venugopal (CS Electric) This paper appraise user on the termination

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information