System Impact Study 2009 T12 Badwater (Moneta)

Size: px
Start display at page:

Download "System Impact Study 2009 T12 Badwater (Moneta)"

Transcription

1 System Impact Study 2009 T12 Badwater (Moneta) Studies Performed by: Joseph Liberatore March 2010 Rocky Mountain Region

2 Index Executive Summary...3 I. Introduction...4 II. Methodology...5 A. TOT Description...5 B. Study Area...7 III. Base Case...8 A. Inclusions to request/study...8 IV. Criteria...8 A. System Intact...8 B. Contingencies...8 C. Dynamics...8 V. Results...9 A. Benchmark Case...9 B. Energy Resource...9 C. Network Resource...9 D. Stability Results...9 VI. Cost Estimates...10 VII. Conclusion...11 Appendices...12 A. Overload Spreadsheet...12 B. Single Line Diagrams Voltage Legend System intact without project System Intact with Project, no reactive support added System Intact with Project and 70 MVAr capacitance added System Intact with Project connected to 115 kv bus Connection to 115 kv feed only with N-1 CopperMtn-MonetaSW...14 C. Contingency Legend(full)...15 D. Monitored Buses...16 E. Monitored Branches...17 F. Code for system additions, load and generation changes

3 Executive Summary Customer 2009-T12 requested load service ranging from 58 MW to 120 MW over a ten year period at Western s Badwater 230 kv substation. The proposed interconnection requires adding a breaker position at Western s Badwater 230 kv bus, a 230/115 kv transformer, approximately 17 miles of transmission line and associated load infrastructure. An informal request to explore an alternate and/or back up connection to Western s Copper Mountain Alcova line was simulated and determined to be highly inadequate for reasonable consideration. Simulating 120 MW of load at 0.95 power factor produces low voltages for system in-tact conditions at Badwater substation. Per Western interconnection requirements, the customer will bear costs associated with capacitor additions necessary to return the per unit voltages at Badwater to pre-load values. This study distributed 75 MVAr of capacitors at the proposed 115 kv buses. The customer may choose power factor correction on the low side bus, providing that Western s system voltages are returned to pre-load conditions. Proper analysis and design by a qualified entity would need to be submitted to, and approved by Western engineering staff. Analysis for Category B and selected Category C contingencies reveal no overload violations when connected to the Badwater 230 kv bus. Interconnection costs estimate total $1,470,000. Estimate includes the addition of a position on the ring bus, capacitance at 115 kv and revenue quality metering. Estimate does not include the approximate 17 miles of transmission line and substations or switch yards located at the load facilities. 3

4 I. Introduction Interconnection customer 2009-T12 requested service for new load at Western s Badwater substation to begin in The 2009-T12 load will range between 58 and 120 MW depending on year of operation. See Table 1 for yearly projections. The Interconnection Customer requested simulation of a 230/115 kv transformer located at Badwater substation serving two substations via 17 miles of 115 kv transmission. A back-up tie to Western s Copper Mountain Raderville 115 kv line, adjacent to Moneta #6761 switch, will be explored per customer suggestion. See Figure 1 for overview map. Table 1 Load Forecast by Year Year Load (MW)

5 Figure 1: Overview map of proposed interconnection II. Methodology A. TOT Description Within the Western power grid there are 80 defined constrained transmission paths. A path s constraint is due to a power branch limitation. The limitation can be either a thermal, voltage or stability constraint. The 2009-T12 request lies north of the WECC path 38, known as TOT 4B. This path and its rating are currently under review due to infrastructure additions in North Central Wyoming. The path s current and proposed (future) elements are as follows: TOT 4B Transmission Path OLD NEW Wyodak* Carr Draw 230 kv Carr Draw* Buffalo 230 kv Carr Draw* Teckla 230 kv Sheridan* Tongue River 230 kv Carr Draw 230 kv load Sheridan 230*/41 kv #1(+), #2 ( ) Spence* Thermopolis 230 kv Spence* Thermopolis 230 kv Alcova* Raiderville 115 kv Alcova* Raiderville 115 kv Casper* Claim Jumper 230 kv Casper* Claim Jumper 230 kv Riverton* Thermopolis 230 kv Riverton* Thermopolis 230 kv Riverton 230*/115 kv transformer Riverton 230*/115 kv transformer 5

6 Due to location of the request and because this is a load, not generation, a path re-rating need not be performed. If the suggested alternate tie to the Copper Mountain Raderville 115 kv system were a formal request (permanent service) and not merely a back up, that topology would add a parallel element to the 4B cut plane which would initiate a path re-rate study. Permanent connection of the proposed loads to the Badwater 230 kv bus AND Copper Mountain Raderville 115 kv system introduces additional issues that are not path related. For the non-radial system, any contingency that disconnects the Badwater 230 kv feed to the proposed load forces service entirely from the suggested Copper Mtn. - Raderville115 kv tap. The 115 kv system is unable to supply the requirements of the request and an extensive rebuild of the 115 kv system would be required. As this is not a practical alternative, it will not be fully explored in this study, but basic simulations will be shown for informational purposes. This option could be fully explored at a later date if the customer chooses to do so by submitting a separate formal request. 6

7 B. Study Area For analysis, contingencies considered consist of the 230 and 115 kv transmission system within a Central/West Central Wyoming triangle surrounded by the following substations: Grass Creek Thermopolis Riverton Rock Springs Point of Rocks Jim Bridger Spence - Dave Johnston Midwest Badwater. See Figure 2 for a graphical representation of the area. Figure 2 This area was chosen in an effort to analyze the contingencies that have the potential to produce overloads on the system. 7

8 III. Base Case IV. Criteria A. Inclusions to request/study The base case used is a WECC 2012 Light Winter (2012LW PTI format) developed for the TOT4A/4B nomogram update. This case has been modified to reflect best known configuration during the 2012 time period and is being utilized as it contains the most accurate system topology. Additionally, loads and generation from zones : 650, 651, 679, 750, 751, 753 and 756 (the bulk of Wyoming) were pulled from a modified WECC 2012 Heavy Summer (2012HS) case and replaced those in the original LW case. The intention is to match the best know (future) topology with the best calculated (future) HS load data. Because actual impedance values for a non-existing transformer are unobtainable, assumptions are made to simulate a rough equivalent. Typically, data from a similarly sized/rated transformer contained within the case will be copied with a new number and name given. For this case, Western s 230/115 kv 150 MVA located at Weld substation was copied and re-named/numbered. Transmission lines using Western s standard 230/115 kv configuration were simulated. Western used its standard 230- kvdesign for the 17 miles of transmission (operated at 115-kV in this case); utilizing wood pole H, strung with 1272 ACSR and spaced for 230 kv operation. Additionally, a power factor of 0.95 pu at the load is simulated as a Western requirement from the customer. In the event significant changes occur to assumptions above, the study should be re-run to capture those changes. Please refer to the commented script (.idev files) located at the end of this report for generation/load values and topology additions. These files could be modified to explore changes or other proposals. A. System Intact Voltages will remain within the required 0.95 to 1.05 per unit range. Transmission lines and transformers may not exceed 100 % of their nominal rating. B. Contingencies Voltages will remain between 0.90 and 1.10 per unit. Transmission lines and transformers may not exceed either 100% of their nominal rating or an established emergency rating. C. Dynamics 8

9 Western Electricity Coordinating Council (WECC) criterion requires bus voltages to not fall below a 30% deviation for the first voltage swing after the fault has cleared. Western criterion further limits this voltage swing to not drop below 0.70 per unit on base voltages. Transient frequencies at buses shall be no lower than 59.6 Hz for 6 cycles or more. However, load requests typically do not require dynamics simulations and as such, none were performed for this study. V. Results A. Benchmark Case The benchmark case utilizes the base case as described in section III (above), and runs contingencies described in Study Area, II.B (Figure 2). After contingencies are run, the benchmark case results must satisfy the criteria as listed under section IV (Criteria). If any criteria are violated, they must be corrected or future corrective actions must be included in the planning horizon to permit omission from results. For the 2009-T12 benchmark case, no criteria violations were found when contingency analysis was performed on the study area. B. Modified Case The Modified Case refers to the Benchmark Case (above) with 2009-T12 request added into the simulation. Upon re-running contingency analysis, no power flow or bus voltage violations were encountered. However, addition of load negatively impacts the per unit bus voltage at Badwater. As such, simulation estimates the addition of 75 MVAr of capacitance to return Badwater 230 kv bus to its pre-addition voltage. As stated in III. Methodology (above), loads cannot be supported by the neighboring 115 kv system alone. C. Stability Results None performed. 9

10 VI. Cost Estimates Moneta is currently a 3-breaker ring. Western would require the addition of a breaker, two switches, site prep, controls, bus work, footings and steel installed to Western design standards at $550,000 Any addition to Western's system should not negatively impact bus voltage at Badwater and require it to remain at least 1.0 p.u. at customers cost. Because actual line lengths, conductor type(s), transformer impedances and unknown power factor at load, assumptions as to VAr requirements have been made. Assumed 17 miles of Western's Standard wood pole-h with 1272 conductor for simulation purposes and loads with 0.95 power factor. Based on these values, estimate a need up to 75 MVAr of capacitance to bring Badwater bus voltage back to its 1.0 p.u. Adding caps on the low (load) side is generally more cost effective and can be proposed by the customer. 115 kv caps add $170,000 per 15 MVAr. 75/15 x 170,000 = $850,000 for caps An additional requirement would be a meter, plan for a revenue quality boundary meter at $70,000 Without the 230/115 kv transformer, transmission line or switch gear at the loads, costs include: Ring Breaker Addition: $550,000 Capacitance: $850,000 Metering $70, $1,470,00 10

11 VII. Conclusion Interconnection customer 2009-T12 requested load service for up to 120 MW of load at Western s Badwater substation. Addition of load produces low voltages for system in-tact conditions at Badwater substation. Per Western interconnection requirements, the customer will bear costs associated with capacitor addition necessary to return the per unit voltages at Badwater to preload values. This study distributed these additions to the proposed 115 kv buses. The customer may choose to add capacitors closer to the load, providing that Western s system voltages are returned to pre-load conditions. Proper analysis and design by a qualified entity would need to be submitted to, and approved by Western engineering staff. Analysis for Category B and selected Category C contingencies reveal no overload violations. An informal request to connect to Western s Copper Mountain Raderville 115 kv system as alternative or back-up was determined impractical and not considered an option. Further exploration would require a formal request from the customer. As outlined above in VI, Costs, an interconnection estimate of $1,470,000 includes the addition of a position on the ring bus, capacitance at 115 kv and metering. This does not include the approximate 17 miles of transmission line and substations or switch yards located at the load areas. It was considered the customer would install or contract that portion of the project out. 11

12 Appendices A. Overload Spreadsheet No overloads found in contingency analysis. B. Single Line Diagrams 1. Voltage Legend 2. System intact without project

13 3. System Intact with Project, no reactive support added. 4. System Intact with Project and 70 MVAr capacitance added. 13

14 5. System Intact with Project connected to 115 kv bus. 6. Connection to 115 kv feed only with N-1 CopperMtn-MonetaSW. Voltage collapse and overloads present 14

15 C. Contingency Legend(full) DOUBLE 1 :OPEN LINE FROM BUS [THERMOPL 230] TO BUS [THERPACE 115] CKT 1 OPEN LINE FROM BUS [THERMOPL 230] TO BUS [THERPACE 115] CKT 2 DOUBLE 2 :OPEN LINE FROM BUS [THERPACE 115] TO BUS [THERMOPL 115] CKT 1 OPEN LINE FROM BUS [THERPACE 115] TO BUS [THERMOPL 115] CKT 2 DOUBLE 3 :OPEN LINE FROM BUS [ALCOVA 115] TO BUS [CASPERLM 115] CKT 1 OPEN LINE FROM BUS [ALCOVA 115] TO BUS [CASPERLM 115] CKT 2 AU_LRS*G.RE :TRIP LINE FROM BUS [AULT 345] TO BUS [LAR.RIVR 345] CKT 1 DECREASE BUS [MBPP-1 24] GENERATION BY 210 MW DECREASE BUS [MBPP-2 24] GENERATION BY 210 MW LRS_STY*G.RE:TRIP LINE FROM BUS [LAR.RIVR 345] TO BUS [STORY 345] CKT 1 DECREASE BUS [MBPP-1 24] GENERATION BY 210 MW DECREASE BUS [MBPP-2 24] GENERATION BY 210 MW BADWA_SPENC :TRIP LINE FROM BUS [BADWATER 230] TO BUS [SPENCE 230] CKT 1 BADWA_THERM :TRIP LINE FROM BUS [BADWATER 230] TO BUS [THERMOPL 230] CKT 1 ATLAN_ROCKS :TRIP LINE FROM BUS [ATLANTIC 230] TO BUS [ROCKSPGS 230] CKT 1 ATLAN_WYOPO :TRIP LINE FROM BUS [ATLANTIC 230] TO BUS [WYOPO 230] CKT 1 RVRTN_WYOPO :TRIP LINE FROM BUS [RIVERTON 230] TO BUS [WYOPO 230] CKT 1 RIVER_THERM :TRIP LINE FROM BUS [RIVERTON 230] TO BUS [THERMOPL 230] CKT 1 CAS.P_RIVERT:TRIP LINE FROM BUS [CASPERPP 230] TO BUS [RIVERTON 230] CKT 1 MUSTA_SPENC :TRIP LINE FROM BUS [BRIDGER 230] TO BUS [ROCKSPGS 230] CKT 1 BRIDG_MUSTA :TRIP LINE FROM BUS [BRIDGER 230] TO BUS [MUSTANG 230] CKT 1 JBRDG_RKSPGS:TRIP LINE FROM BUS [PT ROCKS 230] TO BUS [ROCKSPGS 230] CKT 1 DJ_CAS.PACE :TRIP LINE FROM BUS [DAVEJOHN 230] TO BUS [CASPERPP 230] CKT 1 CAS.PP_SPNCE:TRIP LINE FROM BUS [CASPERPP 230] TO BUS [SPENCE 230] CKT 1 THRMP_GRS.CK:TRIP LINE FROM BUS [THERMOPL 230] TO BUS [GRASS CK 230] CKT 1 GRS.CK_OBSN :TRIP LINE FROM BUS [GRASS CK 230] TO BUS [OREBASIN 230] CKT 1 CPMTN_MONTIE:TRIP LINE FROM BUS [COPPERMT 115] TO BUS [MON_ALT_TIE 115] MONTIE_RDRVL:TRIP LINE FROM BUS [MON_ALT_TIE 115] TO BUS [RADERVIL 115] KPLNT_CPSTAT:TRIP LINE FROM BUS [KANSASPLNT 115] TO BUS [COMPRES_STAT115] CPSTAT_BW115:TRIP LINE FROM BUS [COMPRES_STAT115] TO BUS [BADWATER ] BDW-230_115 :TRIP LINE FROM BUS [BADWATER 230] TO BUS [BADWATER ] CPMTN_RDRVLE:TRIP LINE FROM BUS [COPPERMT 115] TO BUS [MON_ALT_TIE 115] TRIP LINE FROM BUS [MON_ALT_TIE 115] TO BUS [RADERVIL 115] ALCVA_RDRVLE:TRIP LINE FROM BUS [ALCOVA 115] TO BUS [RADERVIL 115] CKT 1 BOYSE_COPPE :TRIP LINE FROM BUS [BOYSEN 115] TO BUS [COPPERMT 115] CKT 1 BOYSE_HARRS :TRIP LINE FROM BUS [BOYSEN 115] TO BUS [HARRSBRG 115] CKT 1 BOYSE_THERM :TRIP LINE FROM BUS [BOYSEN 115] TO BUS [THERMOPL 115] CKT 1 PILOT_HARRS :TRIP LINE FROM BUS [PILOT BU 115] TO BUS [HARRSBRG 115] CKT 1 PILOT_WINDR :TRIP LINE FROM BUS [PILOT BU 115] TO BUS [WINDRIVT 115] CKT 1 RVRTN_WDRVTP:TRIP LINE FROM BUS [RIVERTON 115] TO BUS [WINDRIVT 115] CKT 1 15

16 D. Monitored Buses BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS BUS

17 E. Monitored Branches FROM TO CKT RATE A ATLANTIC ROCKSPGS ATLANTIC WYOPO BADWATER SPENCE BADWATER THERMOPL BADWATER BADWATER BRIDGER MUSTANG BRIDGER ROCKSPGS CASPERPP CASPERPP CASPERPP RIVERTON CASPERPP SPENCE CASPERPP CENTERST CASPERPP CASPERLM CASPERPP REFNRYTP GRASS CK OREBASIN GRASS CK THERMOPL MUSTANG SPENCE RIVERTON THERMOPL RIVERTON WYOPO RIVERTON RIVERTON THERMOPL THERPACE THERMOPL THERPACE THERPACE WORLAND THERPACE THERMOPL THERPACE THERMOPL CENTERST BRYAN BRYAN REFNRYPP REFNRYPP REFNRYTP ALCOVA CASPERLM ALCOVA CASPERLM ALCOVA RADERVIL BOYSEN COPPERMT BOYSEN THERMOPL BOYSEN HARRSBRG CARTERMT THERMOPL CASPERLM DAVEJTPN COPPERMT MON_ALT_TIE DAVEJTPS REFNRYTP PILOT BU WINDRIVT PILOT BU HARRSBRG RADERVIL ERVAYBAS RADERVIL MON_ALT_TIE RIVERTON WINDRIVT TCAPS THERMOPL WINDRIVR WINDRIVT DUTONBAS ERVAYBAS KANSASPLNT COMPRES_STAT COMPRES_STAT BADWATER

18 F. Code for system additions, load and * THIS FILE WILL ADD THE PROPOSED BADWATER(MONETA) COMPRESSOR * STATION AND TREATMENT PLANT HANGING OFF THE BADWATER 230 KV BUS. * FOR 2009 T-12. (02/2010) * QUESTIONS? CONTACT: * JOE LIBERATORE - liberto@wapa.gov ******************************************************************** TAP THE COPPER MOUNTAIN - RAIDERVILLE LINE(POSSIBLE ALTERNATE BUS ENERGIZED BUT LINE SECTION TO KANSAN PLANT WILL SCHEDULED BAT_LTAP,73045,73162,'1', ADD kv BUSES TO ACCOMODATE THE PROPOSED BAT_BUS_DATA,94096,1,73,750,26,,, 115.0,,,'KANSANPLNT' BAT_BUS_DATA,94097,1,73,750,26,,, 115.0,,,'COMPRES_STAT' INSERT 230/115 kv TRANSFORMER AT TRANSFORMER STOLEN FROM WELD BAT_TWO_WINDING_DATA,94098,65095,'1',,,,,,,,,94098,,0,0,2,2,, , ,, 115.0, 115.0,, 230.0, 230.0, 150.0, 150.0, 150.0,,,,,,, 128.8, 105.8, CONNECT THE PROPOSED SYSTEM TOGETHER AT 115 kv, BUT, THE ALTERNATE TIE TO THE COPPER MOUNTAIN - RADERVILLE LINE BAT_BRANCH_DATA,94095,94096,'1',0,94095,73,0,0,0, , , , 221.0, 221.0, 221.0,,,,,,,,,,; BAT_BRANCH_DATA,94096,94097,'1',1,94096,73,0,0,0, , , , 221.0, 221.0, 221.0,,,,,,,,,,; BAT_BRANCH_DATA,94097,94098,'1',1,94097,73,0,0,0, , , , 221.0, 221.0, 221.0,,,,,,,,,,; ADD THE PROPOSED LOADS AT THE COMPRESSOR STATION (60 MW) KANSAN PLANT (TREATEMENT). TREATMENT PLANT ESTIMATED SIMULATED AT 60 MW FOR THIS STUDY (WORST BAT_LOAD_DATA,94096,'KP',,,,73, 60.0, 19.7,,,,,; BAT_LOAD_DATA,94097,'CO',,,,73, 60.0, 19.7,,,,,; BAT_SWITCHED_SHUNT_DATA,94097,9,0,0,0,0,0,0,0,1,0, 6.0,0.0,0.0,0.0,0.0,0.0,0.0,0.0, 1.0, 1.0, 30.0, 100.0,,; BAT_SWITCHED_SHUNT_DATA,94096,9,0,0,0,0,0,0,0,1,0, 6.0,0.0,0.0,0.0,0.0,0.0,0.0,0.0, 1.0, 1.0, 30.0, 100.0,,; BAT_FDNS,0,0,0,0,0,0,99,0 BAT_FDNS,0,0,0,0,0,0,99,0 18

19 @! plug 12HS_FH load values into 12LW topology From 4A/4B study case Load values from the 12HS FH mod case BAT_LOAD_DATA,65060,'1',1,,,, 9.34, 3.07,,,,,; / ANT MINE BAT_LOAD_DATA,65095,'1',1,,,, 4.93, 1.62,,,,,; / BADWATER BAT_LOAD_DATA,65101,'1',1,,,, 0.83, 0.27,,,,,; / BAIROIL BAT_LOAD_DATA,65102,'1',1,,,, 6.82, 2.24,,,,,; / BAIROIL BAT_LOAD_DATA,65106,'1',1,,,, 10.1, 3.32,,,,,; / BAR-X BAT_LOAD_DATA,65215,'1',1,,,, 10.4, 3.42,,,,,; / BRDGR PP BAT_LOAD_DATA,65221,'1',1,,,, 8.70, 2.85,,,,,; / BRIDGER BAT_LOAD_DATA,65235,'1',1,,,, 6.91, 2.27,,,,,; / BUFFALO BAT_LOAD_DATA,65293,'BA',1,,,, 16.4, 5.39,,,,,; / CARR DRA BAT_LOAD_DATA,65305,'1',1,,,, 14.7, 4.84,,,,,; / CASPERPP BAT_LOAD_DATA,65306,'1',1,,,, 64.4, 21.1,,,,,; / CASPERPP BAT_LOAD_DATA,65426,'1',1,,,, 11.4, 3.75,,,,,; / DAVEJOHN BAT_LOAD_DATA,65460,'1',1,,,, 0.36, 0.11,,,,,; / DIFICULT BAT_LOAD_DATA,65502,'1',1,,,, 19.1, 2.57,,,,,; / ELAYTON1 BAT_LOAD_DATA,65556,'1',1,,,, 13.6, 4.49,,,,,; / FIREHOLE BAT_LOAD_DATA,65576,'1',1,,,, 18.7, 6.17,,,,,; / FRANNIE BAT_LOAD_DATA,65621,'1',1,,,, 20.0, 6.60,,,,,; / GARLAND BAT_LOAD_DATA,65721,'1',1,,,, 8.53, 2.81,,,,,; / GRASS CK BAT_LOAD_DATA,65731,'1',1,,,, 1.51, 0.49,,,,,; / GREATDIV BAT_LOAD_DATA,65772,'1',1,,,, 7.73, 3.68,,,,,; / HILLFLD BAT_LOAD_DATA,65875,'1',1,,,, 5.69, 1.87,,,,,; / KAYCEE BAT_LOAD_DATA,65895,'1',1,,,, 3.39, 1.11,,,,,; / LITTLEMT BAT_LOAD_DATA,65956,'1',1,,,, 30.1, 9.91,,,,,; / MIDWEST BAT_LOAD_DATA,65976,'1',1,,,, 4.28, 1.40,,,,,; / MINERS BAT_LOAD_DATA,66239,'1',1,,,, 7.73, 2.57,,,,,; / PLAINCTY BAT_LOAD_DATA,66246,'1',1,,,, 10.2, 3.36,,,,,; / PLATTE BAT_LOAD_DATA,66251,'1',1,,,, 5.24, 1.72,,,,,; / PT ROCKS BAT_LOAD_DATA,66305,'1',1,,,, 35.6, 11.7,,,,,; / RIVERTON BAT_LOAD_DATA,66316,'1',1,,,, 20.8, 6.84,,,,,; / ROCKSPGS BAT_LOAD_DATA,66336,'1',1,,,, 21.3, 7.02,,,,,; / SHERIDAN BAT_LOAD_DATA,66336,'BH',1,,,, 61, 20,,,,,; / SHERIDAN BAT_LOAD_DATA,66462,'1',1,,,, 8.84, 2.21,,,,,; / SWEBER BAT_LOAD_DATA,66685,'1',1,,,, 11.5, 3.80,,,,,; / WHISKEYP BAT_LOAD_DATA,66720,'1',1,,,, 19.3, 6.36,,,,,; / WORLAND BAT_LOAD_DATA,66741,'1',1,,,, 8.82, 2.90,,,,,; / WYOPO BAT_LOAD_DATA,66745,'1',1,,,, 6.78, 2.22,,,,,; / YELLOWCK BAT_LOAD_DATA,66750,'1',1,,,, 3.76, 1.23,,,,,; / YELOWTLP BAT_LOAD_DATA,67531,'1',1,,,, 13.7, 5.50,,,,,; / CLAIMJPR BAT_LOAD_DATA,73004,'TS',1,,,, 2.12, 0.69,,,,,; / ALCOVA BAT_LOAD_DATA,73019,'MU',1,,,, 1.4, 0.46,,,,,; / BASIN BAT_LOAD_DATA,73019,'PP',1,,,, 2.8, 0.92,,,,,; / BASIN BAT_LOAD_DATA,73019,'TS',1,,,, 6.7, 2.20,,,,,; / BASIN BAT_LOAD_DATA,73029,'MU',1,,,, 3.04, 1.00,,,,,; / BRIDGEPT BAT_LOAD_DATA,73029,'NP',1,,,, 3.86, 1.27,,,,,; / BRIDGEPT BAT_LOAD_DATA,73029,'TS',1,,,, 6.2, 2.04,,,,,; / BRIDGEPT BAT_LOAD_DATA,73032,'PP',1,,,, 0.12, 0.03,,,,,; / BUFFBILL BAT_LOAD_DATA,73037,'TS',1,,,, 2.80, 0.92,,,,,; / BUSHNELL BAT_LOAD_DATA,73040,'TS',1,,,, 8.91, 2.93,,,,,; / CARTERMT BAT_LOAD_DATA,73042,'PP',1,,,, 19.7, 6.51,,,,,; / CASPERLM BAT_LOAD_DATA,73042,'TS',1,,,, 4.28, 1.41,,,,,; / CASPERLM BAT_LOAD_DATA,73043,'BH',1,,,, 79.9, 11.4,,,,,; / CHEYENNE BAT_LOAD_DATA,73043,'TS',1,,,, 0.55, 0.18,,,,,; / CHEYENNE BAT_LOAD_DATA,73045,'PP',1,,,, 1.6, 0.52,,,,,; / COPPERMT BAT_LOAD_DATA,73045,'WA',1,,,, 0.02, 0.00,,,,,; / COPPERMT BAT_LOAD_DATA,73046,'TS',1,,,, 14.9, 4.91,,,,,; / DALTON BAT_LOAD_DATA,73064,'TS',1,,,, 1.25, 0.41,,,,,; / GARLAND BAT_LOAD_DATA,73064,'WA',1,,,, 0.3, 0.09,,,,,; / GARLAND BAT_LOAD_DATA,73067,'MU',1,,,, 22.9, 7.55,,,,,; / GERING BAT_LOAD_DATA,73067,'TS',1,,,, 16.9, 5.58,,,,,; / GERING BAT_LOAD_DATA,73068,'WM',1,,,, 7.92, 2.60,,,,,; / GLENDLTP 19

20 BAT_LOAD_DATA,73069,'PP',1,,,, 4.78, 1.57,,,,,; BAT_LOAD_DATA,73069,'TS',1,,,, 0.60, 0.2,,,,,; BAT_LOAD_DATA,73075,'PP',1,,,, 3.1, 1.02,,,,,; BAT_LOAD_DATA,73077,'BH',1,,,, 23.9, 3.4,,,,,; BAT_LOAD_DATA,73081,'TS',1,,,, 9.96, 3.28,,,,,; BAT_LOAD_DATA,73092,'TS',1,,,, 12.6, 4.16,,,,,; BAT_LOAD_DATA,73093,'TS',1,,,, 0.91, 0.3,,,,,; BAT_LOAD_DATA,73096,'MU',1,,,, 5.83, 1.91,,,,,; BAT_LOAD_DATA,73096,'TS',1,,,, 5.76, 1.89,,,,,; BAT_LOAD_DATA,73104,'TS',1,,,, 4.46, 1.46,,,,,; BAT_LOAD_DATA,73107,'TS',1,,,, 15.3, 5.04,,,,,; BAT_LOAD_DATA,73107,'WM',1,,,, 8.10, 2.66,,,,,; BAT_LOAD_DATA,73109,'PP',1,,,, 24.3, 8.02,,,,,; BAT_LOAD_DATA,73109,'TS',1,,,, 0.22, 0.07,,,,,; BAT_LOAD_DATA,73112,'TS',1,,,, 2.7, 0.88,,,,,; BAT_LOAD_DATA,73112,'WM',1,,,, 0.98, 0.32,,,,,; BAT_LOAD_DATA,73123,'PP',1,,,, 3.82, 1.25,,,,,; BAT_LOAD_DATA,73123,'TS',1,,,, 2.94, 0.96,,,,,; BAT_LOAD_DATA,73126,'MU',1,,,, 1.29, 0.42,,,,,; BAT_LOAD_DATA,73126,'TS',1,,,, 9.05, 2.97,,,,,; BAT_LOAD_DATA,73128,'TS',1,,,, 3.54, 1.16,,,,,; BAT_LOAD_DATA,73129,'BA',1,,,, 35, 11.5,,,,,; BAT_LOAD_DATA,73130,'BA',1,,,, 35, 11.5,,,,,; BAT_LOAD_DATA,73131,'TS',1,,,, 8.68, 2.85,,,,,; BAT_LOAD_DATA,73134,'TS',1,,,, 2.12, 0.69,,,,,; BAT_LOAD_DATA,73137,'TS',1,,,, 0.1, 0.03,,,,,; BAT_LOAD_DATA,73139,'TS',1,,,, 5.9, 1.94,,,,,; BAT_LOAD_DATA,73141,'PP',1,,,, 3.82, 1.25,,,,,; BAT_LOAD_DATA,73141,'WA',1,,,, 1.18, 0.38,,,,,; BAT_LOAD_DATA,73141,'WM',1,,,, 11.8, 3.90,,,,,; BAT_LOAD_DATA,73151,'TS',1,,,, 22.4, 7.37,,,,,; BAT_LOAD_DATA,73152,'TS',1,,,, 8.60, 2.83,,,,,; BAT_LOAD_DATA,73152,'WM',1,,,, 2.52, 0.83,,,,,; BAT_LOAD_DATA,73153,'TS',1,,,, 11.1, 3.68,,,,,; BAT_LOAD_DATA,73153,'WM',1,,,, 3.33, 1.09,,,,,; BAT_LOAD_DATA,73157,'TS',1,,,, 0.51, 0.17,,,,,; BAT_LOAD_DATA,73157,'WM',1,,,, 10.9, 3.61,,,,,; BAT_LOAD_DATA,73161,'TS',1,,,, 4.19, 1.38,,,,,; BAT_LOAD_DATA,73162,'TS',1,,,, 0.05, 0.01,,,,,; BAT_LOAD_DATA,73163,'PP',1,,,, 5.49, 1.80,,,,,; BAT_LOAD_DATA,73163,'TS',1,,,, 3.09, 1.01,,,,,; BAT_LOAD_DATA,73168,'BA',1,,,, 92.4, 30.4,,,,,; BAT_LOAD_DATA,73178,'TS',1,,,, 13.3, 4.40,,,,,; BAT_LOAD_DATA,73179,'MU',1,,,, 13.4, 4.40,,,,,; BAT_LOAD_DATA,73179,'NP',1,,,, 2.71, 0.89,,,,,; BAT_LOAD_DATA,73179,'TS',1,,,, 2.83, 0.93,,,,,; BAT_LOAD_DATA,73183,'BH',1,,,, 47.9, 12,,,,,; BAT_LOAD_DATA,73187,'PP',1,,,, 24.9, 8.21,,,,,; BAT_LOAD_DATA,73188,'NT',1,,,, -60, 60,,,,,; BAT_LOAD_DATA,73197,'PP',1,,,, 24.9, 8.21,,,,,; BAT_LOAD_DATA,73197,'WA',1,,,, 1.44, 0.47,,,,,; BAT_LOAD_DATA,73202,'MU',1,,,, 14.5, 4.79,,,,,; BAT_LOAD_DATA,73202,'TS',1,,,, 7.3, 2.40,,,,,; BAT_LOAD_DATA,73205,'TS',1,,,, 6.60, 2.17,,,,,; BAT_LOAD_DATA,73214,'MU',1,,,, 8.16, 2.68,,,,,; BAT_LOAD_DATA,73214,'TS',1,,,, 2.97, 0.97,,,,,; BAT_LOAD_DATA,73216,'TS',1,,,, 11.3, 3.73,,,,,; BAT_LOAD_DATA,73236,'TS',1,,,, 5.26, 1.73,,,,,; BAT_LOAD_DATA,73237,'BH',1,,,, 8.1, 2.7,,,,,; BAT_LOAD_DATA,73239,'BA',1,,,, 5.21, 1.71,,,,,; BAT_LOAD_DATA,73240,'BH',1,,,, 0.5, 0.1,,,,,; BAT_LOAD_DATA,73242,'BA',1,,,, 4.32, 1.42,,,,,; BAT_LOAD_DATA,73243,'BH',1,,,, 11.3, 3.3,,,,,; / GLENDO / GLENDO / GREYBULL / HAPPYJCK / HDOME / JACINTO / JIMREADY / KIMBALL / KIMBALL / LAGRANGE / LAR.RIVR / LAR.RIVR / LARAMIE / LARAMIE / LINGLE / LINGLE / LOVELL / LOVELL / LYMAN / LYMAN / MAY / MBPP-1 / MBPP-2 / MCGREW / MED BOW / MIRACLEM / MYERS / N. CODY / N. CODY / N. CODY / PILOT BU / PINEBLUF / PINEBLUF / PODOLAK / PODOLAK / POWELLTP / POWELLTP / QUALLS / RADERVIL / RALSTON / RALSTON / RENO / SENTINEL / SIDNEY / SIDNEY / SIDNEY / SKYLINE / SPRINGCK / STEGALDC / THERMOPL / THERMOPL / TORRNGTN / TORRNGTN / TROWBRDG / WILDCAT / WILDCAT / WINDRIVR / GREENWOD / 38TH ST / ANGOSTUR / ARGYLE / BIG BEN / CAMBELL 20

21 BAT_LOAD_DATA,73244,'BH',1,,,, 13.8, 2.8,,,,,; BAT_LOAD_DATA,73245,'BA',1,,,, 1.11, 0.36,,,,,; BAT_LOAD_DATA,73246,'BH',1,,,, 9.5, 3.1,,,,,; BAT_LOAD_DATA,73248,'BA',1,,,, 0.67, 0.22,,,,,; BAT_LOAD_DATA,73249,'BA',1,,,, 0.36, 0.11,,,,,; BAT_LOAD_DATA,73249,'BH',1,,,, 2, 0.6,,,,,; BAT_LOAD_DATA,73250,'BH',1,,,, 10, 3.3,,,,,; BAT_LOAD_DATA,73251,'BH',1,,,, 7.9, 3.1,,,,,; BAT_LOAD_DATA,73252,'BH',1,,,, 11.5, 4.9,,,,,; BAT_LOAD_DATA,73253,'BA',1,,,, 1.77, 0.58,,,,,; BAT_LOAD_DATA,73254,'BH',1,,,, 3.2, 1,,,,,; BAT_LOAD_DATA,73257,'BH',1,,,, 18.9, 5.5,,,,,; BAT_LOAD_DATA,73258,'BA',1,,,, 12.6, 4.17,,,,,; BAT_LOAD_DATA,73259,'BH',1,,,, 3.1, 1,,,,,; BAT_LOAD_DATA,73260,'BA',1,,,, 8.09, 2.66,,,,,; BAT_LOAD_DATA,73260,'BH',1,,,, 0.7, 0.2,,,,,; BAT_LOAD_DATA,73261,'BH',1,,,, 0.4, 0.1,,,,,; BAT_LOAD_DATA,73262,'BH',1,,,, 8.2, 1.2,,,,,; BAT_LOAD_DATA,73263,'BH',1,,,, 11.6, 3.8,,,,,; BAT_LOAD_DATA,73264,'BH',1,,,, 4.9, 2.4,,,,,; BAT_LOAD_DATA,73265,'BA',1,,,, 1.72, 0.56,,,,,; BAT_LOAD_DATA,73266,'BH',1,,,, 4.2, 1.2,,,,,; BAT_LOAD_DATA,73267,'BH',1,,,, 1.3, 0.4,,,,,; BAT_LOAD_DATA,73268,'BH',1,,,, 13.4, 2.7,,,,,; BAT_LOAD_DATA,73269,'BA',1,,,, 2.38, 0.78,,,,,; BAT_LOAD_DATA,73270,'BA',1,,,, 5.6, 1.84,,,,,; BAT_LOAD_DATA,73271,'BH',1,,,, 7.9, 2.6,,,,,; BAT_LOAD_DATA,73275,'BH',1,,,, 11.5, 3.8,,,,,; BAT_LOAD_DATA,73276,'BA',1,,,, 90.4, 29.7,,,,,; BAT_LOAD_DATA,73277,'BH',1,,,, 2.1, 0.3,,,,,; BAT_LOAD_DATA,73278,'BH',1,,,, 5.5, 1.6,,,,,; BAT_LOAD_DATA,73279,'BH',1,,,, 0.6, 0.2,,,,,; BAT_LOAD_DATA,73280,'BA',1,,,, 1.52, 0.5,,,,,; BAT_LOAD_DATA,73280,'BH',1,,,, 9.3, 2.7,,,,,; BAT_LOAD_DATA,73281,'BH',1,,,, 1.1, 0.4,,,,,; BAT_LOAD_DATA,73282,'BA',1,,,, 94.8, 31.2,,,,,; BAT_LOAD_DATA,73285,'SS',1,,,, 2.4, 0.8,,,,,; BAT_LOAD_DATA,73286,'BH',1,,,, 8.3, 1.7,,,,,; BAT_LOAD_DATA,73287,'BH',1,,,, 8.2, 2.1,,,,,; BAT_LOAD_DATA,73290,'BH',1,,,, 8.1, 2.7,,,,,; BAT_LOAD_DATA,73295,'BA',1,,,, 9.17, 3.01,,,,,; BAT_LOAD_DATA,73336,'TS',1,,,, 0.71, 0.23,,,,,; BAT_LOAD_DATA,73340,'PP',1,,,, 7.77, 2.55,,,,,; BAT_LOAD_DATA,73340,'TS',1,,,, 6.32, 2.08,,,,,; BAT_LOAD_DATA,73341,'SS',1,,,, 8.7, 2.9,,,,,; BAT_LOAD_DATA,73342,'BA',1,,,, 22.2, 7.32,,,,,; BAT_LOAD_DATA,73348,'BH',1,,,, 29, 5.9,,,,,; BAT_LOAD_DATA,73359,'TS',1,,,, 7.17, 2.36,,,,,; BAT_LOAD_DATA,73359,'WA',1,,,, 0.03, 0.01,,,,,; BAT_LOAD_DATA,73359,'WM',1,,,, 3.35, 1.10,,,,,; BAT_LOAD_DATA,73366,'PP',1,,,, 15.1, 4.99,,,,,; BAT_LOAD_DATA,73375,'WA',1,,,, 8, 2.63,,,,,; BAT_LOAD_DATA,73440,'BH',1,,,, 9.3, 3.4,,,,,; BAT_LOAD_DATA,73479,'TS',1,,,, 2.80, 0.92,,,,,; BAT_LOAD_DATA,73480,'BH',1,,,, 43, 20.8,,,,,; BAT_LOAD_DATA,73511,'BH',1,,,, 12.6, 4.1,,,,,; BAT_LOAD_DATA,73514,'BH',1,,,, 6.6, 2.2,,,,,; BAT_LOAD_DATA,73518,'BH',1,,,, 6.4, 2.1,,,,,; BAT_LOAD_DATA,73519,'BH',1,,,, 7.8, 1.6,,,,,; BAT_LOAD_DATA,73521,'BH',1,,,, 10.8, 5.2,,,,,; BAT_LOAD_DATA,73522,'BH',1,,,, 22.4, 5.6,,,,,; BAT_LOAD_DATA,73523,'BH',1,,,, 10.8, 2.7,,,,,; BAT_LOAD_DATA,73524,'BH',1,,,, 2.4, 1.1,,,,,; / CEMETERY / CLINTON / CUSTER / DUMONT / EDGEMONT / EDGEMONT / HILLCITY / HILLSVW / WESTHILL / JWL CAVE / KIRK / MERILLAT / MCFT PR / NSS1 / OSAGE / OSAGE / PACTOLA / PLSNTVLY / PLUMA / POPE&TAL / PRINGLE / LANGE / RICHMHIL / 5TH ST / SALT CRK / SPFSHBEC / SPFSHCIT / SUNDHILL / TEKLA / TROJAN / WESTBLVD / WTRPLANT / WHTEWOOD / WHTEWOOD / WNDYFLAT / WYODAK / BENFRNCH / ANAMOSA / 4TH ST / EASTNRTH / HUGHES / ERVAYBAS / NAHNEJEN / NAHNEJEN / NSS2 / NSS2 / CORLETT / LIMESTON / LIMESTON / LIMESTON / WAGNHNDS / WARRENLM / CENTRYRD / HARRSBRG / CROWCRK / MALL / ROBINSDL / RADIO_DR / 44TH ST / BFRNCH26 / CMNTPLNT / CROSS ST / AMCOLOID 21

22 BAT_LOAD_DATA,73525,'BH',1,,,, 1.2, 0.7,,,,,; / BELLECRK BAT_LOAD_DATA,73526,'BH',1,,,, 6.2, 2.4,,,,,; / COLONY BAT_LOAD_DATA,73527,'BH',1,,,, 2, 0.6,,,,,; / BUTTEPMP BAT_LOAD_DATA,73528,'BA',1,,,, 7.7, 2.53,,,,,; / MTNVIEW BAT_LOAD_DATA,73528,'BH',1,,,, 5.2, 1.3,,,,,; / MTNVIEW BAT_LOAD_DATA,73530,'BH',1,,,, 6.5, 2.1,,,,,; / NEWCSTLE BAT_LOAD_DATA,73534,'TS',1,,,, 0.9, 0.29,,,,,; / MEETSETP BAT_LOAD_DATA,74000,'BH',1,,,, 18.1, 4.5,,,,,; / STURGIS BAT_LOAD_DATA,74001,'BH',1,,,, 6.5, 2.1,,,,,; / WY REFIN BAT_LOAD_DATA,74002,'BH',1,,,, 0.2, 0.1,,,,,; / 88 OIL BAT_LOAD_DATA,74006,'BH',1,,,, 3.2, 1.1,,,,,; / SPRUCEGL BAT_LOAD_DATA,74007,'BH',1,,,, 1.5, 0.5,,,,,; / OSAG CTY BAT_LOAD_DATA,74008,'BH',1,,,, 0.5, 0.2,,,,,; / BENTON BAT_LOAD_DATA,74009,'BH',1,,,, 1.6, 0.5,,,,,; / UPTON_C BAT_LOAD_DATA,74011,'BH',1,,,, 0, 0,,,,,; / CLOVIS BAT_LOAD_DATA,74012,'BH',1,,,, 38.2, 12.6,,,,,; / GILLETTE BAT_LOAD_DATA,74013,'BH',1,,,, 8, 1.1,,,,,; / PEDMNT BAT_LOAD_DATA,74014,'SS',1,,,, 1.5, 0.5,,,,,; / NSS_CT1 BAT_LOAD_DATA,74015,'SS',1,,,, 1.5, 0.5,,,,,; / NSS_CT2 BAT_LOAD_DATA,74016,'SS',1,,,, 8.7, 2.9,,,,,; / WYGEN BAT_LOAD_DATA,74017,'SS',1,,,, 8.7, 2.9,,,,,; / WYGEN2 BAT_LOAD_DATA,74018,'SS',1,,,, 8.7, 2.9,,,,,; / WYGEN3 BAT_LOAD_DATA,74019,'BH',1,,,, 38.2, 12.6,,,,,; / GILLETTS BAT_LOAD_DATA,74028,'BH',1,,,, 4.7, 1.7,,,,,; / RCSOUTH2 BAT_LOAD_DATA,74029,'SS',1,,,, 1.4, 0.9,,,,,; / LNG_CT1 BAT_LOAD_DATA,74032,'BH',1,,,, 10, 3.3,,,,,; / PRO-ECO BAT_LOAD_DATA,76398,'BA',1,,,, 3.56, 1.17,,,,,; / STURGBEC BAT_LOAD_DATA,76400,'BA',1,,,, 36.5, 12.0,,,,,; / HARTZOG BAT_LOAD_DATA,76401,'BA',1,,,, 85.1, 28.0,,,,,; / BARBERCK BAT_LOAD_DATA,76403,'BA',1,,,, 28, 9.21,,,,,; / ARVADA BAT_LOAD_DATA,76404,'BA',1,,,, 20, 6.58,,,,,; / DRYFORK1 BAT_LOAD_DATA,76409,'BA',1,,,, 17.5, 5.76,,,,,; / Machine values from the 12HS FH mod case BAT_MACHINE_DATA,67940,'1',1,,,,, 0, 21.64,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,67950,'1',1,,,,, 19.5, -1.41,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69003,'1',1,,,,, 118.5, -17.4,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69004,'1',1,,,,, 118.5, -12.7,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69019,'D',0,,,,, 0, 0,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69020,'1',1,,,,, 20, -8.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69021,'D',0,,,,, 0, 0.2,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69022,'1',1,,,,, 20, -11.3,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69027,'1',1,,,,, 118.5, 10.31,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69073,'1',1,,,,, 127.5, 6.895,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,69092,'1',1,,,,, 100.5, -2.27,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73129,'1',1,,,,, 585, -21.0,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73130,'1',1,,,,, 585, -21.0,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73181,'1',1,,,,, 200, -203.,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73188,'1',1,,,,, 60, -60,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73226,'5',1,,,,, 65.7, 1.345,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73226,'2',1,,,,, 65.7, 1.345,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73227,'3',1,,,,, 65.7, 1.345,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73227,'4',1,,,,, 65.7, 1.345,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73285,'1',1,,,,, 18.2, 2.002,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73288,'1',1,,,,, 18, 7.176,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73289,'1',0,,,,, 20, 1.9,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73291,'2',0,,,,, 20, 1.9,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73292,'3',0,,,,, 20, 1.9,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73293,'4',0,,,,, 20, 1.9,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73321,'1',1,,,,, 11, 1.548,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73322,'2',1,,,,, 11, 1.526,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73323,'3',1,,,,, 11, 1.548,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73332,'1',1,,,,, 12, -3.79,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73333,'1',1,,,,, 6, -0.50,,,,,,,,,,,,,,,; / PLATTSVC / CSPWIND4 / GLENRKG1 / GLENRKG2 / MTNWD G1 / MTNWD G2 / MTNWD G3 / MTNWD G4 / 7MIHL G1 / HIPLN_G / THREB_G / MBPP-1 / MBPP-2 / SIDNEYDC / STEGALDC / YELLO1-2 / YELLO1-2 / YELLO3-4 / YELLO3-4 / BENFRNCH / NSS1 / RCCT1 / RCCT2 / RCCT3 / RCCT4 / OSAGE1 / OSAGE2 / OSAGE3 / ALCOVA1 / BOYSEN1 22

23 BAT_MACHINE_DATA,73333,'2',1,,,,, 4, -0.33,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73334,'1',0,,,,, 4, 1.040,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73339,'1',0,,,,, 4, 3.3,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73341,'2',1,,,,, 90, 5.955,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73343,'1',1,,,,, 1, 0,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73347,'1',0,,,,, 2, -1,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73349,'1',0,,,,, 20, -0.18,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73350,'1',1,,,,, 20, 0.304,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73351,'1',1,,,,, 7.9, -2.5,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73352,'1',1,,,,, 8, -3.3,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73353,'1',1,,,,, 2, 0,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73356,'1',1,,,,, 6, -1.32,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73357,'1',1,,,,, 6, 0.403,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73358,'1',0,,,,, 0, 0.1,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73363,'1',1,,,,, 10, -1.08,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73363,'2',1,,,,, 10, -1.08,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73438,'1',1,,,,, 10, -3.42,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73439,'1',0,,,,, 3, 1.202,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73439,'2',1,,,,, 3, 6.228,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73441,'1',0,,,,, 0, -2.9,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73444,'2',1,,,,, 2, 0,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73462,'1',1,,,,, 3, -1.8,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73520,'1',0,,,,, 0, 7.2,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,73520,'5',0,,,,, 0, 7.2,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,74014,'1',1,,,,, 40, 11.1,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,74015,'1',1,,,,, 40, 11.1,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,74016,'1',1,,,,, 97.3, 7.700,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,74017,'1',1,,,,, 99, 9.607,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,74018,'1',1,,,,, 97, 9.4,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,74029,'1',0,,,,, 40, 5.1,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76301,'1',0,,,,, 0, 5.4,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76302,'1',0,,,,, 0, 3.7,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76303,'1',0,,,,, 0, 3.7,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76305,'1',0,,,,, 0, -0.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76306,'1',0,,,,, 0, -0.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76307,'1',0,,,,, 0, -0.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76309,'1',0,,,,, 0, -1.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76310,'1',0,,,,, 0, -1.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76311,'1',0,,,,, 0, -1.6,,,,,,,,,,,,,,,; BAT_MACHINE_DATA,76351,'1',1,,,,, 130, -6.93,,,,,,,,,,,,,,,; BAT_FDNS,0,0,0,0,0,0,99,0 BAT_FDNS,0,0,0,0,0,0,99,0 / BOYSEN1 / BBILL1-2 / HEART MT / NSS2 / PILOT BU / SHOSHONE / FREMONT1 / FREMONT2 / GLENDO1 / GLENDO2 / GUERNSY1 / KORTES1 / KORTES2 / KORTES3 / SMNOE1-2 / SMNOE1-2 / ALCOVA2 / BBILL3-4 / BBILL3-4 / SEMINOE3 / GUERNSY2 / SPIRTMTN / BFDIESEL / BFDIESEL / NSS_CT1 / NSS_CT2 / WYGEN / WYGEN2 / WYGEN3 / LNG_CT1 / ARVADA1 / ARVADA2 / ARVADA3 / BARBERC1 / BARBERC2 / BARBERC3 / HARTZOG1 / HARTZOG2 / HARTZOG3 / RCDC W 23

System Impact Study 2009 T1 Transformer Replacement at Badwater Substation

System Impact Study 2009 T1 Transformer Replacement at Badwater Substation System Impact Study 2009 T1 Transformer Replacement at Badwater Substation July 2010 Rocky Mountain Region Index Executive Summary...3 I. Introduction...4 II. Methodology...4 A. Monitored Paths...4 III.

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources Customer Name Basin Electric Cheyenne Power and Light City of Fort Morgan & Estimated Maximum Resource MW Point of Receipt Delivering Party & Voltage Antelope Valley 2 Yellowtail Basin Electric 115 kv

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting MEETING AGENDA Western Area Power Administration Rocky Mountain Region Transmission Planning Stakeholder Meeting Western s RMR Regional Office 5555 East Crossroads Boulevard, Loveland, CO 80538 June 23,

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Cheyenne Light, Fuel and Power Transmission System Impact Study

Cheyenne Light, Fuel and Power Transmission System Impact Study Cheyenne Light, Fuel and Power Transmission System Impact Study CLPT-G10 80 MW Solar Plant Interconnecting near the South Cheyenne 115 kv Substation Agreement No. 38094 Laramie County, Wyoming February

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado System Impact Study T-2007-3 Final.doc System Impact Study Report Request # T-2007-3 900 MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado Executive Summary PSCo Transmission

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Gillette Lost the Most Residents in 2017

Gillette Lost the Most Residents in 2017 FOR IMMEDIATE RELEASE Thursday, May 24, 2018 Contact: Dr. Wenlin Liu, Chief Economist Gillette Lost the Most Residents in 2017 CHEYENNE Cities that lost the most residents in Wyoming between July 1, 2016

More information

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016 New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016 New Transmission Line November 15, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Customer Charge or Minimum Bill. Total Average Annual Bill (9 Dth) Total Volumetric Rate*

Customer Charge or Minimum Bill. Total Average Annual Bill (9 Dth) Total Volumetric Rate* Residential Gas Rates for Wyoming Regulated Utilities Gas Rates are in effect as of: 11/03/17 Estimates of Seasonal Bills (illustrational purposes only) Customer Charge or Minimum Bill Total Volumetric

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Tri-State December 2013 Board Meeting

Tri-State December 2013 Board Meeting 1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)

More information

Electric Power Research Institute, USA 2 ABB, USA

Electric Power Research Institute, USA 2 ABB, USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting MEETING AGENDA Western Area Power Administration Rocky Mountain Region Transmission Planning Stakeholder Meeting Western s RMR Regional Office 5555 East Crossroads Boulevard, Loveland, CO 80538 December

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

2015 CITY/TOWN PDO CRASHES WITH COLLISION TYPE

2015 CITY/TOWN PDO CRASHES WITH COLLISION TYPE 2015 CITY/TOWN PDO CRASHES WITH COLLISION TYPE Top 5 s including ties CITY BAGGS BASIN Motor Vehicle in Transport on Roadway 3 BEAR RIVER BIG PINEY Motor Vehicle in Transport on Roadway 2 BUFFALO 7 0 Barricade

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

AQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES

AQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES AQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES 2008-2012 April 2008 Table of Contents 1.0 INTRODUCTION... 2 2.0 RESULTS... 2 2.1 CATEGORY C NO SOLVE CASES... 2 2.2 CATEGORY C

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Emerald Reactive Support Alternative Solution Expressions of interest

Emerald Reactive Support Alternative Solution Expressions of interest Emerald Reactive Support Alternative Solution Expressions of interest Publishing Date 21/02/2017 Closing Date 21/03/2017 1. Executive Summary Ergon Energy Corporation Limited (EECL) is seeking expressions

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

WYOMING COST OF LIVING FOR THE SECOND QUARTER 2010

WYOMING COST OF LIVING FOR THE SECOND QUARTER 2010 State of Wyoming Department of Administration and Information Economic Analysis Division 2800 Central Avenue Cheyenne, WY 82002-0060 E-mail: ead@wyo.gov http://eadiv.state.wy.us Ph. (307) 777-7504 Fax

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information