Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director
|
|
- Gilbert Welch
- 5 years ago
- Views:
Transcription
1 Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director Project No PID LUC-IR Federal Type: MAJOR RECONSTRUCTION Letting Date: 6/3/2010 Completion Date: 11/12/2012 Contract Awarded To: E S WAGNER COMPANY Award Amount: $63,881, Engineer's Estimate: $68,675, Bidder 1 E S WAGNER COMPANY 840 PATCHEN RD Lucas OREGON, OH Bid $63,881, Bidder 3 KOKOSING CONSTRUCTION COMPANY INC 886 MC KINLEY AVE Franklin COLUMBUS, OH Bid $69,139, Bidder 5 C A HULL CO INC 8177 GOLDIE RD WALLED LAKE, MI Bid $74,428, Bidder 2 GREAT LAKES CONSTRUCTION CO 2608 GREAT LAKES WAY Medina HINCKLEY, OH Bid $66,812, Bidder 4 POSEN CONSTRUCTION INC DESIGN LANE SHELBY TOWNSHIP, MI Bid $74,168, Bidder 6 MOSSER CONSTRUCTION INC/BEAVER EXCAVATING COMPANY - JV 122 S WILSON AVE DRAWER D Sandusky FREMONT, OH Bid $77,697, Page 1
2 Ref #1 201E11000 CLEARING AND GRUBBING, (LUMP SUM) Awd $59, $59, $400, $400, $100, $100, $18, $18, $15, $15, $262, $262, Ref #2 201E21800 TREE REMOVED, 18" SIZE, (207 EACH) Awd $53.41 $11, $ $82, $ $25, $ $57, $ $36, $ $27, Ref #3 201E23000 TREE REMOVED, 30" SIZE, (84 EACH) Awd $ $23, $ $50, $ $30, $ $47, $ $58, $ $31, Ref #4 201E24800 TREE REMOVED, 48" SIZE, (6 EACH) Awd $1, $9, $1, $6, $ $4, $ $5, $1, $7, $ $4, Ref #5 201E26500 STUMP REMOVED, 18" SIZE, (9 EACH) Awd $40.50 $ $60.00 $ $30.00 $ $30.00 $ $ $ $32.00 $ Ref #6 201E26510 STUMP REMOVED, 30" SIZE, (7 EACH) Awd $67.50 $ $80.00 $ $60.00 $ $45.00 $ $ $2, $63.00 $ Ref #7 202E11300 PORTIONS OF STRUCTURE REMOVED, (250 CY) Awd $66.51 $16, $50.00 $12, $85.00 $21, $ $31, $55.00 $13, $80.00 $20, Page 2
3 Ref #8 202E20010 HEADWALL REMOVED, (1 EACH) Awd $ $ $ $ $ $ $ $ $1, $1, $ $ Ref #9 202E23000 PAVEMENT REMOVED, ( SY) Awd $4.15 $558, $5.00 $673, $7.50 $1,009, $6.50 $874, $5.50 $740, $10.00 $1,346, Ref #10 202E23010 PAVEMENT REMOVED, ASPHALT, (49559 SY) Awd $2.70 $133, $3.00 $148, $2.00 $99, $2.70 $133, $3.20 $158, $8.00 $396, Ref #11 202E30000 WALK REMOVED, (69899 SF) Awd $0.50 $34, $0.45 $31, $1.00 $69, $1.00 $69, $0.25 $17, $0.35 $24, Ref #12 202E30500 CONCRETE MEDIAN REMOVED, (787 FT) Awd $9.72 $7, $4.00 $3, $1.50 $1, $3.00 $2, $2.50 $1, $4.00 $3, Ref #13 202E30700 CONCRETE BARRIER REMOVED, (13510 FT) Awd $8.00 $108, $6.00 $81, $9.00 $121, $7.80 $105, $6.50 $87, $16.00 $216, Ref #14 202E30800 TRAFFIC ISLAND REMOVED, (1010 SY) Awd $13.00 $13, $20.00 $20, $9.00 $9, $3.25 $3, $3.65 $3, $7.00 $7, Page 3
4 Ref #15 202E32000 CURB REMOVED, (21535 FT) Awd $1.00 $21, $0.90 $19, $1.50 $32, $3.50 $75, $3.00 $64, $2.00 $43, Ref #16 202E35100 PIPE REMOVED, 24" AND UNDER, (7655 FT) Awd $11.00 $84, $8.00 $61, $11.00 $84, $15.00 $114, $6.50 $49, $27.00 $206, Ref #17 202E35200 PIPE REMOVED, OVER 24", (316 FT) Awd $14.00 $4, $25.00 $7, $13.50 $4, $30.73 $9, $8.00 $2, $48.00 $15, Ref #18 202E38000 GUARDRAIL REMOVED, (13688 FT) Awd $1.00 $13, $1.00 $13, $1.00 $13, $1.00 $13, $1.00 $13, $2.00 $27, Ref #19 202E42206 ANCHOR ASSEMBLY REMOVED, (4 EACH) Awd $83.00 $ $85.00 $ $83.00 $ $ $ $ $ $ $ Ref #20 202E58000 MANHOLE REMOVED, (18 EACH) Awd $ $6, $ $7, $ $3, $ $2, $ $5, $ $7, Ref #21 202E58100 CATCH BASIN REMOVED, (52 EACH) Awd $ $18, $ $22, $ $10, $ $8, $ $13, $ $11, Page 4
5 Ref #22 202E58200 INLET REMOVED, (71 EACH) Awd $ $24, $ $31, $ $36, $ $11, $ $14, $ $18, Ref #23 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, (6062 FT) Awd $18.50 $112, $10.00 $60, $8.50 $51, $6.45 $39, $6.00 $36, $28.00 $169, Ref #24 202E75000 FENCE REMOVED, (20117 FT) Awd $2.69 $54, $1.60 $32, $2.50 $50, $2.66 $53, $2.66 $53, $1.75 $35, Ref #25 202E98400 REMOVAL MISC.:REMOVAL OF NOISE BARRIER, (75275 SF) Awd $1.39 $104, $1.80 $135, $2.00 $150, $3.50 $263, $1.65 $124, $0.75 $56, Ref #26 203E10001 EXCAVATION, AS PER PLAN, ( CY) Awd $10.00 $1,886, $6.50 $1,226, $9.00 $1,697, $6.50 $1,226, $7.50 $1,414, $17.00 $3,206, Ref #27 203E20000 EMBANKMENT, ( CY) Awd $2.00 $215, $2.60 $280, $3.70 $399, $3.00 $323, $3.00 $323, $11.70 $1,263, Ref #28 204E10000 SUBGRADE COMPACTION, (50371 SY) Awd $1.39 $70, $1.00 $50, $1.10 $55, $1.00 $50, $0.35 $17, $1.90 $95, Page 5
6 Ref #29 204E30010 GRANULAR MATERIAL, TYPE B, (22597 CY) Awd $19.00 $429, $21.00 $474, $25.50 $576, $22.00 $497, $23.00 $519, $24.00 $542, Ref #30 204E30020 GRANULAR MATERIAL, TYPE C, (9735 CY) Awd $16.70 $162, $19.00 $184, $26.00 $253, $20.00 $194, $18.00 $175, $24.00 $233, Ref #31 204E30030 GRANULAR MATERIAL, TYPE D, (20019 CY) Awd $15.00 $300, $19.00 $380, $26.50 $530, $20.00 $400, $18.00 $360, $23.00 $460, Ref #32 204E45000 PROOF ROLLING, (107 HOUR) Awd $ $21, $ $21, $ $16, $ $13, $ $10, $ $28, Ref #34 206E10500 CEMENT, (6465 TON) Awd $95.25 $615, $95.00 $614, $92.50 $598, $92.50 $598, $95.25 $615, $95.25 $615, Ref #35 206E11000 CURING COAT, ( SY) Awd $0.35 $56, $0.25 $40, $0.25 $40, $0.24 $38, $0.22 $35, $0.22 $35, Ref #36 206E15000 CEMENT STABILIZED SUBGRADE, (16" DEEP), ( SY) Awd $1.66 $266, $2.30 $368, $2.37 $379, $2.50 $400, $1.68 $269, $3.01 $482, Page 6
7 Ref #37 206E30000 CONTRACTOR DESIGNED CHEMICALLY STABILIZED SUBGRAD, (LUMP SUM) Awd $22, $22, $12, $12, $30, $30, $20, $20, $22, $22, $22, $22, Ref #38 604E38500 MONUMENT ASSEMBLY, (24 EACH) Awd $ $16, $ $10, $ $14, $ $10, $1, $24, $ $12, Ref #39 606E13000 GUARDRAIL, TYPE 5, (14450 FT) Awd $12.00 $173, $12.00 $173, $12.00 $173, $12.35 $178, $11.80 $170, $11.80 $170, Ref #40 606E13001 GUARDRAIL, TYPE 5, AS PER PLAN, (75 FT) Awd $47.60 $3, $48.00 $3, $47.60 $3, $12.35 $ $52.50 $3, $52.50 $3, Ref #41 606E22000 ANCHOR ASSEMBLY, TYPE B-98, (7 EACH) Awd $1, $10, $1, $10, $1, $10, $1, $11, $1, $9, $1, $9, Ref #42 606E22010 ANCHOR ASSEMBLY, TYPE E-98, (16 EACH) Awd $1, $30, $1, $30, $1, $30, $1, $28, $1, $28, $1, $28, Ref #43 606E26500 ANCHOR ASSEMBLY, TYPE T, (13 EACH) Awd $ $8, $ $8, $ $8, $ $8, $ $7, $ $7, Page 7
8 Ref #44 606E35000 BRIDGE TERMINAL ASSEMBLY, TYPE 1, (28 EACH) Awd $1, $31, $1, $31, $1, $31, $2, $56, $1, $29, $1, $29, Ref #45 606E35100 BRIDGE TERMINAL ASSEMBLY, TYPE 2, (17 EACH) Awd $ $6, $ $6, $ $6, $ $8, $ $5, $ $5, Ref #46 606E60020 IMPACT ATTENUATOR, TYPE 2-98 (UNIDIRECTIONAL)(60 M, (1 EACH) Awd $19, $19, $18, $18, $17, $17, $20, $20, $16, $16, $16, $16, Ref #47 606E60020 IMPACT ATTENUATOR, TYPE 2-98 (UNIDIRECTIONAL)(60 M, (4 EACH) Awd $20, $80, $19, $76, $18, $74, $20, $80, $17, $68, $17, $68, Ref #48 607E20000 FENCE, TYPE CL, (7109 FT) Awd $12.54 $89, $12.50 $88, $13.30 $94, $11.90 $84, $11.90 $84, $14.50 $103, Ref #49 607E20001 FENCE, TYPE CL, AS PER PLAN, (2382 FT) Awd $14.16 $33, $14.00 $33, $12.80 $30, $14.00 $33, $14.00 $33, $14.50 $34, Ref #50 608E " CONCRETE WALK, (48798 SF) Awd $2.30 $112, $3.25 $158, $3.50 $170, $2.45 $119, $2.45 $119, $3.85 $187, Page 8
9 Ref #51 608E49000 CURB RAMP, (19 EACH) Awd $ $4, $ $4, $ $8, $ $4, $ $4, $ $5, Ref #52 622E10100 CONCRETE BARRIER, SINGLE SLOPE, TYPE B1, (3661 FT) Awd $55.87 $204, $60.00 $219, $67.00 $245, $45.23 $165, $45.25 $165, $79.60 $291, Ref #53 622E10140 CONCRETE BARRIER, SINGLE SLOPE, TYPE C1, (2043 FT) Awd $63.33 $129, $60.00 $122, $70.00 $143, $66.92 $136, $52.35 $106, $71.00 $145, Ref #54 622E10160 CONCRETE BARRIER, SINGLE SLOPE, TYPE D, (4441 FT) Awd $30.62 $135, $36.00 $159, $60.00 $266, $45.52 $202, $25.00 $111, $35.90 $159, Ref #55 622E10161 CONCRETE BARRIER, SINGLE SLOPE, TYPE D, AS PER PLA, (1924 FT) Awd $60.57 $116, $45.00 $86, $75.00 $144, $53.21 $102, $24.92 $47, $65.80 $126, Ref #56 622E25050 CONCRETE BARRIER, END ANCHOR, REINFORCED, TYPE D, (69 EACH) Awd $1, $98, $1, $69, $1, $101, $ $9, $ $58, $1, $96, Ref #57 690E12010 SPECIAL - GEOTEXTILE FABRIC, (30561 SY) Awd $1.00 $30, $1.00 $30, $1.25 $38, $0.90 $27, $1.10 $33, $1.15 $35, Page 9
10 Ref #58 690E12020 SPECIAL - GEOGRID, (14860 SY) Awd $2.96 $43, $3.00 $44, $3.50 $52, $2.32 $34, $3.50 $52, $2.90 $43, Ref # E30040 GRANULAR MATERIAL, TYPE E, (821 CY) Awd $33.26 $27, $22.50 $18, $23.50 $19, $23.56 $19, $20.50 $16, $24.00 $19, Ref # E98100 FENCE, MISC.:HAND HOLE INSTALLATION, (36 EACH) Awd $ $10, $ $10, $ $18, $ $10, $ $10, $ $10, Ref # E10060 CONCRETE BARRIER, SINGLE SLOPE, TYPE B, (444 FT) Awd $90.00 $39, $33.00 $14, $50.00 $22, $52.44 $23, $45.00 $19, $ $66, Ref # E25000 CONCRETE BARRIER END SECTION, TYPE D, (17 EACH) Awd $1, $32, $2, $42, $1, $29, $2, $42, $1, $24, $1, $32, Ref # E25014 CONCRETE BARRIER, END ANCHOR, REINFORCED, TYPE C1, (15 EACH) Awd $2, $31, $1, $15, $1, $27, $3, $59, $1, $21, $1, $29, Ref # E25020 CONCRETE BARRIER, END ANCHOR, REINFORCED, (32 EACH) Awd $2, $66, $1, $32, $1, $60, $2, $89, $1, $46, $1, $59, Page 10
11 Ref # E11000 SPECIAL - PROVIDING ELECTRONIC INSTRUMENTATION, (1 EACH) Awd $28, $28, $20, $20, $20, $20, $75, $75, $50, $50, $27, $27, Ref # E11100 SPECIAL - TECHNICAL ASSISTANCE, (24 HOUR) Awd $ $2, $ $2, $ $2, $85.00 $2, $ $6, $80.00 $1, Ref # E98000 SPECIAL - MISC.:ROAD WEATHER INFORMATION SYSTEM SE, (4 EACH) Awd $5, $23, $8, $34, $5, $23, $5, $23, $15, $60, $10, $40, Ref # E56000 BUILDING DEMOLISHED, PARCEL 120 WL, 1 STY. STONE R, (LUMP SUM) Awd $16, $16, $12, $12, $9, $9, $6, $6, $6, $6, $5, $5, Ref # E56000 BUILDING DEMOLISHED, PARCEL 376 WL,2 CONC. BLOCK C, (LUMP SUM) Awd $16, $16, $20, $20, $15, $15, $6, $6, $6, $6, $15, $15, Ref # E56000 BUILDING DEMOLISHED, PARCEL 378 WD, 2 STY. WOOD FR, (LUMP SUM) Awd $16, $16, $10, $10, $9, $9, $6, $6, $6, $6, $7, $7, Ref # E56000 BUILDING DEMOLISHED, PARCEL 380 WL, 1 STY. WOOD FR, (LUMP SUM) Awd $16, $16, $5, $5, $9, $9, $6, $6, $6, $6, $5, $5, Page 11
12 Ref # E10060 CONCRETE BARRIER, SINGLE SLOPE, TYPE B, (472 FT) Awd $90.00 $42, $60.00 $28, $50.00 $23, $45.52 $21, $45.00 $21, $ $70, Ref # E71000 SPECIAL - ASBESTOS ABATEMENT, (LUMP SUM) Awd $14, $14, $20, $20, $14, $14, $3, $3, $50, $50, $26, $26, Ref # E28000 SGB INSPECTION AND COMPACTION TESTING, (LUMP SUM) Awd $12, $12, $12, $12, $17, $17, $ $ $17, $17, $25, $25, Ref # E28000 SGB INSPECTION AND COMPACTION TESTING, (LUMP SUM) Awd $10, $10, $10, $10, $15, $15, $ $ $12, $12, $15, $15, Section 1 - ROADWAY - Totals Awd $7,249, $7,250, $8,509, $7,427, $6,854, $11,956, Ref #59 601E11000 RIPRAP USING 6" REINFORCED CONCRETE SLAB, (0.97 SY) Awd $1, $1, $ $ $ $ $75.00 $ $ $ $ $ Ref #60 601E21050 TIED CONCRETE BLOCK MAT, TYPE 1, (12 SY) Awd $86.96 $1, $ $2, $ $2, $16.00 $ $55.00 $ $ $2, Page 12
13 Ref #61 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH FABRIC FILTER, (21.31 CY) Awd $95.00 $2, $ $4, $ $3, $59.74 $1, $82.00 $1, $68.00 $1, Ref #62 601E32304 ROCK CHANNEL PROTECTION, TYPE D WITH FABRIC FILTER, (286 CY) Awd $52.00 $14, $65.00 $18, $ $31, $48.16 $13, $60.00 $17, $72.00 $20, Ref #63 659E00100 SOIL ANALYSIS TEST, (17 EACH) Awd $20.00 $ $15.00 $ $15.00 $ $20.00 $ $50.00 $ $15.00 $ Ref #64 659E00300 TOPSOIL, (19122 CY) Awd $15.58 $297, $15.00 $286, $6.00 $114, $15.13 $289, $8.35 $159, $8.00 $152, Ref #65 659E10000 SEEDING AND MULCHING, ( SY) Awd $0.30 $51, $0.40 $69, $0.28 $48, $0.32 $55, $0.75 $129, $0.28 $48, Ref #66 659E14000 REPAIR SEEDING AND MULCHING, (8613 SY) Awd $1.66 $14, $0.28 $2, $0.28 $2, $0.18 $1, $2.50 $21, $0.28 $2, Ref #67 659E20000 COMMERCIAL FERTILIZER, (23.26 TON) Awd $ $5, $ $5, $ $5, $ $5, $ $22, $ $5, Page 13
14 Ref #68 659E31000 LIME, (35.59 ACRE) Awd $1.00 $ $30.00 $1, $30.00 $1, $1.00 $ $ $16, $30.00 $1, Ref #69 659E35000 WATER, (645 MGAL) Awd $0.01 $ $1.00 $ $1.00 $ $0.01 $ $17.50 $11, $1.00 $ Ref #70 659E40000 MOWING, (269 MSF) Awd $3.00 $ $2.00 $ $2.10 $ $3.00 $ $32.00 $8, $2.10 $ Ref #71 670E00700 DITCH EROSION PROTECTION, (458 SY) Awd $1.25 $ $1.20 $ $1.20 $ $1.25 $ $1.65 $ $1.20 $ Ref #72 832E15000 STORM WATER POLLUTION PREVENTION PLAN, (LUMP SUM) Awd $5, $5, $40, $40, $30, $30, $81, $81, $5, $5, $27, $27, Ref #73 832E30000 EROSION CONTROL, (85000 EACH) Awd $1.00 $85, $1.00 $85, $1.00 $85, $1.00 $85, $1.00 $85, $1.00 $85, Ref #74 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING, (170 SY) Awd $3.70 $ $6.00 $1, $3.20 $ $1.25 $ $9.00 $1, $3.20 $ Page 14
15 Section 2 - EROSION CONTROL - Totals Awd $481, $519, $327, $535, $481, $350, Ref #75 509E10000 EPOXY COATED REINFORCING STEEL, (793 LB) Awd $0.75 $ $1.00 $ $1.19 $ $0.80 $ $0.90 $ $0.90 $ Ref #76 602E20000 CONCRETE MASONRY, (12.2 CY) Awd $1, $15, $1, $14, $ $10, $ $7, $ $11, $1, $14, Ref #77 603E " CONDUIT, TYPE F, (90 FT) Awd $22.00 $1, $18.00 $1, $12.00 $1, $23.00 $2, $17.00 $1, $24.00 $2, Ref #78 603E " CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS, (2694 FT) Awd $13.00 $35, $13.00 $35, $14.00 $37, $10.22 $27, $13.00 $35, $13.00 $35, Ref #79 603E " CONDUIT, TYPE B, (35 FT) Awd $30.00 $1, $27.00 $ $30.00 $1, $23.00 $ $13.00 $ $26.00 $ Ref #80 603E " CONDUIT, TYPE E, (200 FT) Awd $16.00 $3, $17.00 $3, $18.00 $3, $18.00 $3, $18.00 $3, $28.00 $5, Page 15
16 Ref #81 603E " CONDUIT, TYPE F, (200 FT) Awd $16.00 $3, $17.00 $3, $18.00 $3, $22.00 $4, $18.00 $3, $36.00 $7, Ref #82 603E " CONDUIT, TYPE B, (426 FT) Awd $38.00 $16, $37.00 $15, $37.00 $15, $31.00 $13, $42.00 $17, $52.00 $22, Ref #83 603E " CONDUIT, TYPE C, (455 FT) Awd $29.00 $13, $23.00 $10, $30.00 $13, $29.42 $13, $42.00 $19, $40.00 $18, Ref #84 603E " CONDUIT, TYPE F, OR , (8 FT) Awd $ $1, $ $2, $ $ $38.57 $ $44.00 $ $85.00 $ Ref #85 603E " CONDUIT, TYPE B, (4805 FT) Awd $41.50 $199, $41.00 $197, $40.00 $192, $34.69 $166, $44.00 $211, $62.00 $297, Ref #86 603E " CONDUIT, TYPE C, (3330 FT) Awd $41.30 $137, $33.00 $109, $35.00 $116, $48.00 $159, $44.00 $146, $39.00 $129, Ref #87 603E " CONDUIT, TYPE F, OR , (858 FT) Awd $48.10 $41, $50.00 $42, $50.00 $42, $44.00 $37, $47.00 $40, $48.00 $41, Page 16
17 Ref #88 603E " CONDUIT, TYPE B, (2555 FT) Awd $38.00 $97, $47.00 $120, $45.00 $114, $43.00 $109, $48.00 $122, $64.00 $163, Ref #89 603E " CONDUIT, TYPE C, (253 FT) Awd $30.00 $7, $45.00 $11, $38.00 $9, $44.00 $11, $48.00 $12, $41.00 $10, Ref #90 603E " CONDUIT, TYPE F, OR , (65 FT) Awd $67.00 $4, $63.00 $4, $68.00 $4, $55.00 $3, $51.00 $3, $48.00 $3, Ref #91 603E " CONDUIT, TYPE B, (1877 FT) Awd $52.00 $97, $50.00 $93, $53.00 $99, $46.84 $87, $54.00 $101, $68.00 $127, Ref #92 603E " CONDUIT, TYPE C, (185 FT) Awd $48.00 $8, $56.00 $10, $50.00 $9, $52.18 $9, $54.00 $9, $50.00 $9, Ref #93 603E " CONDUIT, TYPE F, OR , (98 FT) Awd $56.00 $5, $77.00 $7, $55.00 $5, $55.79 $5, $58.00 $5, $65.00 $6, Ref #94 603E " CONDUIT, TYPE B, (267 FT) Awd $70.00 $18, $ $27, $ $28, $66.00 $17, $65.00 $17, $ $28, Page 17
18 Ref #95 603E " CONDUIT, TYPE C, (347 FT) Awd $65.00 $22, $58.00 $20, $55.00 $19, $62.00 $21, $65.00 $22, $85.00 $29, Ref #96 603E " CONDUIT, TYPE F, OR , (32 FT) Awd $81.00 $2, $89.00 $2, $83.00 $2, $69.00 $2, $70.00 $2, $80.00 $2, Ref #97 603E " CONDUIT, TYPE B, (124 FT) Awd $84.00 $10, $ $16, $ $13, $75.00 $9, $88.00 $10, $90.00 $11, Ref #98 603E " CONDUIT, TYPE C, (953 FT) Awd $62.00 $59, $64.00 $60, $65.00 $61, $65.21 $62, $88.00 $83, $70.00 $66, Ref #99 603E " CONDUIT, TYPE B, (164 FT) Awd $58.00 $9, $83.00 $13, $78.00 $12, $82.00 $13, $ $16, $90.00 $14, Ref # E " CONDUIT, TYPE B, (363 FT) Awd $97.00 $35, $96.00 $34, $85.00 $30, $70.16 $25, $ $43, $94.00 $34, Ref # E " CONDUIT, TYPE C, (4 FT) Awd $ $1, $ $2, $ $1, $95.56 $ $ $ $ $ Page 18
19 Ref # E " CONDUIT, TYPE A, (16 FT) Awd $ $3, $ $3, $ $2, $ $2, $ $2, $ $2, Ref # E " CONDUIT, TYPE B, (19 FT) Awd $ $3, $ $7, $ $3, $ $2, $ $2, $ $13, Ref # E96600 CONDUIT, BORED OR JACKED:15", (278 FT) Awd $ $41, $ $44, $ $51, $ $75, $ $54, $ $61, Ref # E96600 CONDUIT, BORED OR JACKED:18", (191 FT) Awd $ $30, $ $34, $ $27, $ $69, $ $47, $ $52, Ref # E96600 CONDUIT, BORED OR JACKED:21", (99 FT) Awd $ $18, $ $19, $ $21, $ $34, $ $25, $ $29, Ref # E96600 CONDUIT, BORED OR JACKED:24", (105 FT) Awd $ $20, $ $21, $ $22, $ $35, $ $29, $ $30, Ref # E96600 CONDUIT, BORED OR JACKED:30", (153 FT) Awd $ $39, $ $55, $ $39, $ $75, $ $50, $ $57, Page 19
20 Ref # E00400 CATCH BASIN, NO. 3, (14 EACH) Awd $2, $35, $2, $32, $2, $32, $1, $21, $1, $23, $2, $35, Ref # E00800 CATCH BASIN, NO. 3A, (37 EACH) Awd $1, $66, $1, $66, $2, $74, $1, $50, $1, $46, $2, $74, Ref # E01600 CATCH BASIN, NO. 5, (2 EACH) Awd $1, $3, $2, $5, $2, $4, $2, $4, $1, $3, $1, $3, Ref # E02000 CATCH BASIN, NO. 6, (2 EACH) Awd $1, $2, $1, $3, $1, $3, $1, $3, $1, $2, $1, $2, Ref # E02800 CATCH BASIN, NO. 8, (4 EACH) Awd $1, $7, $2, $10, $1, $7, $2, $8, $1, $7, $1, $7, Ref # E04500 CATCH BASIN, NO. 2-2B, (27 EACH) Awd $1, $27, $1, $29, $1, $27, $1, $27, $ $24, $ $21, Ref # E04900 CATCH BASIN, NO. 2-3, (13 EACH) Awd $1, $16, $1, $16, $1, $14, $1, $17, $1, $14, $1, $16, Page 20
21 Ref # E05700 CATCH BASIN, NO. 2-5, (1 EACH) Awd $3, $3, $4, $4, $3, $3, $2, $2, $3, $3, $2, $2, Ref # E20514 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE B1, (11 EACH) Awd $5, $58, $6, $66, $6, $66, $2, $30, $5, $59, $7, $86, Ref # E20524 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE C1, (5 EACH) Awd $5, $28, $6, $30, $6, $30, $2, $13, $5, $27, $8, $40, Ref # E20530 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE D, (33 EACH) Awd $4, $161, $5, $165, $5, $178, $2, $90, $4, $151, $6, $207, Ref # E31500 MANHOLE, NO. 3, (30 EACH) Awd $2, $63, $3, $90, $2, $75, $2, $60, $1, $52, $2, $63, Ref # E31501 MANHOLE, NO. 3, AS PER PLAN, (3 EACH) Awd $1, $4, $2, $6, $1, $5, $1, $5, $1, $5, $2, $6, Ref # E31800 MANHOLE, NO. 4, (1 EACH) Awd $12, $12, $6, $6, $17, $17, $2, $2, $2, $2, $9, $9, Page 21
22 Ref # E32100 MANHOLE, NO. 5, (1 EACH) Awd $4, $4, $6, $6, $9, $9, $3, $3, $2, $2, $4, $4, Ref # E34500 MANHOLE ADJUSTED TO GRADE, (3 EACH) Awd $ $1, $ $1, $ $1, $ $1, $ $1, $ $ Ref # E35500 MANHOLE RECONSTRUCTED TO GRADE, (4 EACH) Awd $1, $4, $2, $8, $1, $5, $ $3, $ $1, $1, $6, Ref # E35501 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN, (10 EACH) Awd $ $8, $2, $20, $1, $12, $2, $20, $ $4, $1, $19, Ref # E36600 PRECAST REINFORCED CONCRETE OUTLET, (20 EACH) Awd $ $7, $ $5, $ $3, $ $2, $ $3, $ $5, Ref # E50000 SPECIAL - MISCELLANEOUS METAL, (1500 LB) Awd $1.61 $2, $1.00 $1, $1.25 $1, $1.67 $2, $5.00 $7, $2.00 $3, Ref # E " SHALLOW PIPE UNDERDRAINS WITH FABRIC WRAP, (6816 FT) Awd $4.80 $32, $6.00 $40, $5.75 $39, $6.33 $43, $7.45 $50, $6.50 $44, Page 22
23 Ref # E " DEEP PIPE UNDERDRAINS WITH FABRIC WRAP, (29291 FT) Awd $8.00 $234, $8.00 $234, $8.75 $256, $13.61 $398, $11.35 $332, $8.00 $234, Ref # E " UNCLASSIFIED PIPE UNDERDRAINS WITH FABRIC WRAP, (4948 FT) Awd $12.80 $63, $7.50 $37, $6.60 $32, $6.36 $31, $8.50 $42, $5.80 $28, Ref # E " BASE PIPE UNDERDRAINS WITH FABRIC WRAP, (39376 FT) Awd $4.40 $173, $5.00 $196, $5.50 $216, $5.27 $207, $6.25 $246, $5.20 $204, Ref # E " UNCLASSIFIED PIPE UNDERDRAINS WITH FABRIC WRAP,, (14 FT) Awd $21.00 $ $9.50 $ $22.50 $ $6.16 $ $10.50 $ $11.00 $ Ref # E96600 CONDUIT, BORED OR JACKED:36", (161 FT) Awd $ $44, $ $46, $ $53, $ $88, $ $57, $ $64, Section 3 - DRAINAGE - Totals Awd $2,075, $2,181, $2,193, $2,253, $2,331, $2,524, Ref # E46000 ASPHALT CONCRETE BASE, PG64-22, (452 CY) Awd $ $56, $ $56, $ $53, $ $56, $ $56, $ $61, Page 23
24 Ref # E46000 ASPHALT CONCRETE BASE, PG64-22, (56788 CY) Awd $93.00 $5,281, $93.00 $5,281, $95.00 $5,394, $93.00 $5,281, $93.00 $5,281, $ $5,678, Ref # E20000 AGGREGATE BASE, (35262 CY) Awd $25.50 $899, $27.50 $969, $33.00 $1,163, $25.24 $890, $24.50 $863, $25.00 $881, Ref # E98010 TACK COAT, MISC.:TRACKLESS TACK COAT, (13367 GAL) Awd $5.00 $66, $4.25 $56, $4.00 $53, $5.00 $66, $5.00 $66, $4.25 $56, Ref # E98010 TACK COAT, MISC.:TRACKLESS TACK COAT FOR INTERMEDI, (10578 GAL) Awd $5.00 $52, $4.50 $47, $4.00 $42, $5.00 $52, $5.00 $52, $4.50 $47, Ref # E98010 SEALING, MISC.:LONGITUDINAL JOINT SEALER, (30236 LB) Awd $1.25 $37, $1.25 $37, $1.25 $37, $1.25 $37, $1.25 $37, $1.45 $43, Ref # E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5MM, TYPE A (4, (929 CY) Awd $ $162, $ $162, $ $155, $ $162, $ $162, $ $181, Ref # E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19MM, TYPE A, (9629 CY) Awd $ $1,319, $ $1,309, $ $1,319, $ $1,319, $ $1,319, $ $1,299, Page 24
25 Ref # E12001 STONE MATRIX ASPHALT CONCRETE, 12.5MM, PG76-22M, (, (7142 CY) Awd $ $1,514, $ $1,506, $ $1,464, $ $1,514, $ $1,514, $ $1,428, Ref # E47020 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, PG64-22, (601 CY) Awd $ $90, $ $90, $ $88, $ $90, $ $90, $ $96, Ref # E " REINFORCED CONCRETE PAVEMENT, (3512 SY) Awd $44.65 $156, $48.00 $168, $50.00 $175, $11.89 $41, $48.00 $168, $49.50 $173, Ref # E " NON-REINFORCED CONCRETE PAVEMENT, (371 SY) Awd $26.35 $9, $31.00 $11, $39.00 $14, $28.00 $10, $30.50 $11, $32.80 $12, Ref # E " NON-REINFORCED CONCRETE PAVEMENT, (565 SY) Awd $31.30 $17, $35.00 $19, $38.00 $21, $33.50 $18, $35.20 $19, $37.50 $21, Ref # E12000 COMBINATION CURB AND GUTTER, TYPE 2, (4161 FT) Awd $12.45 $51, $12.00 $49, $18.00 $74, $13.00 $54, $11.15 $46, $12.90 $53, Ref # E24511 CURB, TYPE 4-C, AS PER PLAN, (3251 FT) Awd $10.90 $35, $11.00 $35, $11.00 $35, $11.25 $36, $11.25 $36, $13.25 $43, Page 25
26 Ref # E26000 CURB, TYPE 6, (4060 FT) Awd $10.00 $40, $11.00 $44, $12.00 $48, $10.50 $42, $11.25 $45, $13.35 $54, Ref # E28000 CURB, TYPE 7, (130 FT) Awd $12.00 $1, $15.00 $1, $20.00 $2, $12.50 $1, $15.00 $1, $16.60 $2, Ref # E " CONCRETE TRAFFIC ISLAND, (430 SY) Awd $40.80 $17, $50.00 $21, $42.00 $18, $42.80 $18, $48.60 $20, $52.60 $22, Ref # E40100 RUMBLE STRIPS, (ASPHALT CONCRETE), (53037 FT) Awd $0.13 $6, $0.20 $10, $0.11 $5, $0.26 $13, $0.23 $12, $0.26 $13, Ref # E01000 PAVEMENT PLANING, ASPHALT CONCRETE, (3344 SY) Awd $2.75 $9, $3.00 $10, $4.50 $15, $2.75 $9, $2.75 $9, $2.85 $9, Ref # E20100 ASPHALT CONCRETE INTERMEDIATE COURSE, 9.5MM, TYPE, (139 CY) Awd $ $27, $ $27, $ $35, $ $27, $ $27, $ $28, Section 4 - PAVEMENT - Totals Awd $9,854, $9,919, $10,220, $9,745, $9,844, $10,209, Page 26
27 Ref # E " WATER MAIN DUCTILE IRON PIPE ANSI CLASS 52, PUS, (756 FT) Awd $67.00 $50, $90.00 $68, $75.00 $56, $63.00 $47, $85.00 $64, $ $75, Ref # E " WATER MAIN DUCTILE IRON PIPE ANSI CLASS 52, PU, (425 FT) Awd $ $99, $ $106, $ $116, $ $136, $ $138, $ $138, Ref # E /2" COPPER SERVICE BRANCH, (10 FT) Awd $ $1, $ $2, $38.00 $ $ $1, $40.00 $ $29.00 $ Ref # E06200 POLYETHYLENE ENCASEMENT, (1181 FT) Awd $3.40 $4, $0.50 $ $1.25 $1, $2.00 $2, $0.80 $ $1.00 $1, Ref # E " GATE VALVE AND VALVE BOX, (3 EACH) Awd $1, $3, $1, $3, $1, $3, $1, $3, $2, $6, $1, $4, Ref # E " FIRE HYDRANT, (1 EACH) Awd $5, $5, $5, $5, $4, $4, $4, $4, $4, $4, $4, $4, Section 5 - WATER WORK - Totals Awd $163, $184, $183, $194, $214, $223, Page 27
28 Ref # E " CONDUIT, TYPE B, AS PER PLAN, (673 FT) Awd $ $71, $70.00 $47, $93.00 $62, $75.00 $50, $80.00 $53, $ $148, Ref # E " CONDUIT, TYPE C, AS PER PLAN, (413 FT) Awd $49.00 $20, $40.00 $16, $49.00 $20, $67.00 $27, $85.00 $35, $ $47, Ref # E31501 MANHOLE, NO. 3, AS PER PLAN, (7 EACH) Awd $2, $17, $4, $31, $2, $18, $2, $17, $2, $14, $4, $30, Section 6 - SANITARY SEWER - Totals Awd $109, $95, $101, $95, $103, $226, Ref # E00500 CONNECTOR KIT, TYPE II, (216 EACH) Awd $65.00 $14, $65.00 $14, $65.00 $14, $65.00 $14, $65.00 $14, $65.00 $14, Ref # E01500 CABLE SPLICING KIT, (207 EACH) Awd $64.00 $13, $64.00 $13, $64.00 $13, $64.00 $13, $64.00 $13, $64.00 $13, Ref # E10481 LIGHT POLE, DECORATIVE, AS PER PLAN, DESIGN 8B16., (15 EACH) Awd $3, $52, $3, $52, $3, $52, $3, $52, $3, $52, $3, $52, Page 28
29 Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT1, (1 EACH) Awd $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT1, (7 EACH) Awd $2, $14, $2, $14, $2, $14, $2, $14, $2, $14, $2, $14, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT1, (9 EACH) Awd $2, $19, $2, $19, $2, $19, $2, $19, $2, $19, $2, $19, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT1, (5 EACH) Awd $2, $12, $2, $13, $2, $12, $2, $12, $2, $12, $2, $12, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT1, (19 EACH) Awd $2, $45, $2, $45, $2, $45, $2, $45, $2, $45, $2, $45, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT2, (1 EACH) Awd $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT2, (1 EACH) Awd $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, $2, Page 29
30 Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN AT2, (3 EACH) Awd $2, $7, $2, $8, $2, $7, $2, $7, $2, $7, $2, $7, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN A8BB, (41 EACH) Awd $3, $130, $3, $131, $3, $130, $3, $130, $3, $130, $3, $130, Ref # E10491 LIGHT POLE, CONVENTIONAL, AS PER PLAN, DESIGN A8BB, (6 EACH) Awd $4, $24, $4, $24, $4, $24, $4, $24, $4, $24, $4, $24, Ref # E10614 LIGHT POLE ANCHOR BOLTS ON STRUCTURE, (60 EACH) Awd $40.00 $2, $40.00 $2, $40.00 $2, $40.00 $2, $40.00 $2, $40.00 $2, Ref # E11200 LIGHT TOWER, BB100, (1 EACH) Awd $10, $10, $11, $11, $10, $10, $10, $10, $10, $10, $10, $10, Ref # E13400 LIGHT TOWER, BBBBBB100, (5 EACH) Awd $11, $55, $11, $55, $11, $55, $11, $55, $11, $55, $11, $55, Ref # E14101 LIGHT POLE FOUNDATION, 24" X 8' DEEP, AS PER PLAN, (40 EACH) Awd $ $33, $ $33, $ $33, $ $33, $ $33, $ $33, Page 30
31 Ref # E14201 LIGHT POLE FOUNDATION, 24" X 10' DEEP, AS PER PLAN, (6 EACH) Awd $ $5, $ $5, $ $5, $ $5, $ $5, $ $5, Ref # E14307 MEDIAN LIGHT POLE FOUNDATION, 10' DEEP, AS PER PLA, (47 EACH) Awd $1, $92, $3, $141, $2, $111, $2, $139, $2, $135, $2, $135, Ref # E15300 LIGHT TOWER FOUNDATION, 36" X 30' DEEP., (6 EACH) Awd $5, $33, $5, $33, $5, $33, $5, $33, $5, $33, $5, $33, Ref # E23300 NO. 2 AWG 5000 VOLT DISTRIBUTION CABLE, (33360 FT) Awd $1.10 $36, $1.00 $33, $1.10 $36, $1.10 $36, $1.10 $36, $1.10 $36, Ref # E23304 NO. 8 AWG 600 VOLT DISTRIBUTION CABLE, (3906 FT) Awd $1.05 $4, $1.00 $3, $1.05 $4, $1.05 $4, $1.05 $4, $1.05 $4, Ref # E23400 NO. 10 AWG POLE AND BRACKET CABLE, (17370 FT) Awd $0.75 $13, $0.75 $13, $0.75 $13, $0.75 $13, $0.75 $13, $0.75 $13, Ref # E /2" DUCT CABLE WITH THREE NO. 2 AWG 5000 VOLT C, (10912 FT) Awd $1.20 $13, $1.20 $13, $1.20 $13, $1.20 $13, $1.20 $13, $1.20 $13, Page 31
32 Ref # E25500 CONDUIT, 3", , (3227 FT) Awd $18.50 $59, $18.00 $58, $18.50 $59, $18.50 $59, $18.50 $59, $18.50 $59, Ref # E25910 CONDUIT CLEANED AND CABLES REMOVED, (50 FT) Awd $4.25 $ $4.00 $ $4.25 $ $4.25 $ $4.25 $ $4.25 $ Ref # E26261 LUMINAIRE, HIGH MAST, AS PER PLAN, 400W, HPS, TYPE, (62 EACH) Awd $ $36, $ $37, $ $36, $ $36, $ $36, $ $36, Ref # E27501 LUMINAIRE, UNDERPASS, AS PER PLAN, 150W, HPS, TYPE, (458 EACH) Awd $ $224, $ $229, $ $224, $ $224, $ $224, $ $224, Ref # E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, 100W, HPS, TYP, (12 EACH) Awd $ $7, $ $7, $ $7, $ $7, $ $7, $ $7, Ref # E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, 100W, HPS, TYP, (3 EACH) Awd $ $1, $ $1, $ $1, $ $1, $ $1, $ $1, Ref # E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, 250W, HPS, TYP, (128 EACH) Awd $ $81, $ $81, $ $81, $ $81, $ $81, $ $81, Page 32
33 Ref # E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, 250W, HPS, TYP, (12 EACH) Awd $ $7, $ $7, $ $7, $ $7, $ $7, $ $7, Ref # E29000 TRENCH, (11013 FT) Awd $2.40 $26, $2.40 $26, $2.40 $26, $2.40 $26, $2.40 $26, $2.40 $26, Ref # E29910 TRANSITION JUNCTION BOX, (4 EACH) Awd $1, $5, $2, $8, $1, $6, $1, $5, $1, $5, $1, $6, Ref # E29920 STRUCTURE JUNCTION BOX, (11 EACH) Awd $1, $15, $2, $23, $1, $15, $1, $15, $1, $15, $1, $15, Ref # E29930 MEDIAN JUNCTION BOX, (3 EACH) Awd $2, $6, $2, $8, $2, $7, $2, $8, $2, $8, $2, $8, Ref # E30706 PULL BOX, , 24", (29 EACH) Awd $ $16, $ $17, $ $16, $ $16, $ $16, $ $16, Ref # E32000 GROUND ROD, (121 EACH) Awd $ $15, $ $15, $ $15, $ $15, $ $15, $ $15, Page 33
34 Ref # E33000 STRUCTURE GROUNDING SYSTEM, (5 EACH) Awd $1, $7, $1, $7, $1, $7, $1, $7, $1, $7, $1, $7, Ref # E34001 POWER SERVICE, AS PER PLAN, (8 EACH) Awd $5, $42, $5, $44, $5, $42, $5, $42, $5, $42, $5, $42, Ref # E36000 PLASTIC CAUTION TAPE, (11013 FT) Awd $0.10 $1, $0.25 $2, $0.10 $1, $0.10 $1, $0.10 $1, $0.10 $1, Ref # E37101 SERVICE TO UNDERPASS LIGHTING, AS PER PLAN, (2 EACH) Awd $249, $498, $250, $500, $249, $498, $249, $498, $249, $498, $249, $498, Ref # E40000 SPECIAL - MAINTAIN EXISTING LIGHTING, (LUMP SUM) Awd $84, $84, $85, $85, $84, $84, $84, $84, $84, $84, $84, $84, Ref # E75350 LIGHT TOWER REMOVED, (1 EACH) Awd $1, $1, $1, $1, $1, $1, $1, $1, $1, $1, $1, $1, Ref # E75400 LIGHT POLE REMOVED, (61 EACH) Awd $ $14, $ $14, $ $14, $ $14, $ $14, $ $14, Page 34
35 Ref # E75500 LIGHT POLE FOUNDATION REMOVED, (61 EACH) Awd $ $17, $ $17, $ $17, $ $17, $ $17, $ $17, Ref # E75506 LUMINAIRE REMOVED, (89 EACH) Awd $80.00 $7, $80.00 $7, $80.00 $7, $80.00 $7, $80.00 $7, $80.00 $7, Ref # E75510 POWER SERVICE REMOVED, (4 EACH) Awd $ $1, $ $1, $ $1, $ $1, $ $1, $ $1, Ref # E75540 LIGHT TOWER FOUNDATION REMOVED, (1 EACH) Awd $ $ $ $ $ $ $ $ $ $ $ $ Ref # E75801 DISCONNECT CIRCUIT, AS PER PLAN, (19 EACH) Awd $42.00 $ $42.00 $ $42.00 $ $42.00 $ $42.00 $ $42.00 $ Ref # E98000 LIGHTING, MISC.:LUMINAIRE RING REPLACED, (6 EACH) Awd $1, $7, $1, $7, $1, $7, $1, $7, $1, $7, $1, $7, Section 7 - LIGHTING - Totals Awd $1,834, $1,902, $1,855, $1,884, $1,879, $1,881, Page 35
36 Ref # E10010 RPM, LOW PROFILE, WHITE, (260 EACH) Awd $17.00 $4, $25.00 $6, $27.02 $7, $24.40 $6, $24.40 $6, $24.40 $6, Ref # E10020 RPM, LOW PROFILE WHITE/RED, (284 EACH) Awd $17.00 $4, $25.00 $7, $27.02 $7, $24.40 $6, $24.40 $6, $24.40 $6, Ref # E10030 RPM, LOW PROFILE YELLOW/RED, (220 EACH) Awd $17.00 $3, $25.00 $5, $27.02 $5, $24.40 $5, $24.40 $5, $24.40 $5, Ref # E02100 GROUND MOUNTED SUPPORT, NO. 2 POST, (409 FT) Awd $6.00 $2, $6.00 $2, $6.00 $2, $5.00 $2, $6.00 $2, $6.00 $2, Ref # E03100 GROUND MOUNTED SUPPORT, NO. 3 POST, (1090 FT) Awd $6.80 $7, $7.00 $7, $6.80 $7, $5.00 $5, $6.80 $7, $6.80 $7, Ref # E04100 GROUND MOUNTED SUPPORT, NO. 4 POST, (59 FT) Awd $10.00 $ $10.00 $ $10.00 $ $7.00 $ $10.00 $ $10.00 $ Ref # E06100 GROUND MOUNTED SUPPORT, NO. 6 POST, (177 FT) Awd $11.50 $2, $12.00 $2, $11.50 $2, $9.00 $1, $11.50 $2, $11.50 $2, Page 36
37 Ref # E06400 GROUND MOUNTED SUPPORT, S4X7.7 BEAM, (34 FT) Awd $11.00 $ $12.00 $ $11.00 $ $16.00 $ $11.00 $ $11.00 $ Ref # E06500 GROUND MOUNTED SUPPORT, W6X9 BEAM, (184 FT) Awd $12.50 $2, $13.00 $2, $12.50 $2, $17.00 $3, $12.50 $2, $12.50 $2, Ref # E07600 GROUND MOUNTED SUPPORT, W10X12 BEAM, (235 FT) Awd $15.50 $3, $16.00 $3, $15.50 $3, $20.00 $4, $15.50 $3, $15.50 $3, Ref # E08004 ONE WAY SUPPORT, NO. 3 POST, (21 FT) Awd $10.50 $ $11.00 $ $10.50 $ $55.00 $1, $10.50 $ $10.50 $ Ref # E08600 SIGN POST REFLECTOR, (17 EACH) Awd $30.00 $ $32.00 $ $30.00 $ $40.00 $ $30.00 $ $30.00 $ Ref # E09000 BREAKAWAY BEAM CONNECTION, (22 EACH) Awd $ $4, $ $5, $ $4, $ $7, $ $4, $ $4, Ref # E11103 OVERHEAD SIGN SUPPORT, TYPE TC-16.21, DESIGN 11, A, (1 EACH) Awd $8, $8, $8, $8, $8, $8, $10, $10, $8, $8, $8, $8, Page 37
38 Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 20'-0" S, (2 EACH) Awd $23, $47, $25, $50, $23, $47, $20, $40, $23, $47, $23, $47, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 29'-0" S, (1 EACH) Awd $37, $37, $40, $40, $37, $37, $30, $30, $37, $37, $37, $37, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 31'-0" S, (2 EACH) Awd $44, $89, $46, $93, $44, $89, $37, $74, $44, $89, $44, $89, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 33'-0" S, (1 EACH) Awd $43, $43, $45, $45, $43, $43, $40, $40, $43, $43, $43, $43, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 36'-0" S, (1 EACH) Awd $42, $42, $45, $45, $42, $42, $40, $40, $42, $42, $42, $42, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 37'-0" S, (1 EACH) Awd $46, $46, $48, $48, $46, $46, $42, $42, $46, $46, $46, $46, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:TWO POST, 110'-0" SPA, (2 EACH) Awd $84, $169, $88, $176, $84, $169, $103, $206, $84, $169, $84, $169, Page 38
39 Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 26'-0" S, (1 EACH) Awd $33, $33, $35, $35, $33, $33, $20, $20, $33, $33, $33, $33, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:SINGLE POST, 34'-0" S, (1 EACH) Awd $44, $44, $46, $46, $44, $44, $45, $45, $44, $44, $44, $44, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:TWO POST, 72'-0" SPAN, (1 EACH) Awd $79, $79, $83, $83, $79, $79, $75, $75, $79, $79, $79, $79, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:TWO POST, 75'-0" SPAN, (1 EACH) Awd $87, $87, $91, $91, $87, $87, $90, $90, $87, $87, $87, $87, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:TWO POST, 88'-6" SPAN, (1 EACH) Awd $78, $78, $81, $81, $78, $78, $94, $94, $78, $78, $78, $78, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:TWO POST, 90'-0", AS, (1 EACH) Awd $102, $102, $106, $106, $102, $102, $101, $101, $102, $102, $102, $102, Ref # E74500 OVERHEAD SIGN SUPPORT, MISC.:TWO POST, 96'-0", AS, (1 EACH) Awd $83, $83, $87, $87, $83, $83, $98, $98, $83, $83, $83, $83, Page 39
Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director
Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Project No. 080598 PID 21272 CUY-SR-237-4.93 - PART I (FRONT STREET); CUY-237-4.55 - P Federal Type: RAILROAD
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 110146 PID 82278 HAM-IR-75-5.58 Federal Type: INTERCHANGE Letting Date: 5/5/2011 Completion Date: 7/31/2014 Contract
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 140123 PID 82645 LOR- SR 0057 19.42 Federal Type: INTERCHANGE Letting Date: 4/17/2014 Completion Date: 7/15/2016
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 180573 PID 93496 FRA-IR 71-01.53 Federal Type: BRIDGE REPLACEMENT (2 BRIDGES) Letting Date: 12/20/2018 Completion
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 170607 PID 85146 CUY-SR 21-10.04L Federal Type: BRIDGE REPLACEMENT (1 BRIDGE) Letting Date: 12/14/2017 Completion
More informationCT Consultants, Inc.
Cost 1 202 AHRESTY DRIVE REMOVAL 1 LS 2 202 EXISTING SILO DEMOLISHED AND REMOVED, AS PER PLAN 1 LS 3 203 EXCAVATION (NOT INCLUDING UNDERCUT) 2,372 CY 4 203 EMBANKMENT 3,306 CY 5 204 PROOF ROLLING 10 HRS
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 170559 PID 102381 SCI-US 52-19.01 Federal Type: TWO LANE RESURFACING Letting Date: 11/2/2017 Completion Date:
More informationSteese Rd - Curb & Sidewalk Improvement
REF. NO. ITEM NO. Steese Rd - Curb & Sidewalk Improvement DESCRIPTION QTY UNITS UNIT COST SUB-TOTAL 1 103.05 Requirement of Contract Bid 1 LS 24,048.00 24,048.00 2 201 Clearing and Grubbing 1 LS 11,077.00
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 190109 PID 96986 CUY-SR 10-16.13 Steel Federal Type: BRIDGE REPAIR Letting Date: 3/21/2019 Completion Date: 9/30/2020
More informationFranklin County Engineer's Office - Highway Design ALKIRE RD & DEMOREST RD ROUNDABOUT CR NO. 11 & CR NO. 25 Bid Tabulation
7/07/2015 Page 1 of 20 Strawser Paving Co., Inc. Shelly & Sands, Inc. Double Z Construction Co Columbus Asphalt Paving, Inc. 1595 Frank Road P.O.Box 2469 2550 Harrison Road 1196 Technology Dr Columbus,
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 130407 PID 88799 AUG-VA-VAR-BRIDGES Federal Type: BRIDGE REPAIR Letting Date: 7/18/2013 Completion Date: 8/31/2014
More informationMaine Turnpike Authority
Company Name Total Bid Amount R J Grondin & Sons - Gorham, ME $1,436,720.00 Shaw Brothers Construction, Inc. - Gorham, ME $1,476,398.83 Pratt & Sons, Inc. - Minot, ME $1,733,615.00 Page 1 of 13 R J Grondin
More informationBARRETT ROAD (C.R. 178) ROADWAY RESURFACING FROM LEWIS ROAD TO SPAFFORD ROAD IN OLMSTED TOWNSHIP, OHIO ITEMIZED UNIT PRICE BID ROADWAY
IZED PRICE BID DESCRIPTION PRICE BID ROADWAY 1 201 11000 CLEARING AND GRUBBING 1 - - LUMP 2 202 23000 PAVEMENT REMOVED NR SQ YD 20 3 202 35100 PIPE REMOVED, 24" AND UNDER NR FT 134 4 202 58000 MANHOLE
More informationS T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 05/01/00 PAGE : 1 TABULATION OF BIDS
PAGE : 1 CONTRACT DESCRIPTION : MILL & OVERLAY, GRADING, BIT SURFACING, BR NO 02038 ETC CONTRACT LOCATION: LOCATED ON TH 47 FROM 153RD AVE NW IN RAMSEY TO 180TH LANE NW AND AT FORD BROOK IN BURNS TOWNSHIP
More informationHILLS MATERIALS COMPANY UNIT COST TOTAL COST UNIT COST TOTAL COST UNIT COST $294, $294, $74, $74, $35, $35,000.
PROJECT NAME: Anamosa Street Reconstruction - Midway Street to Miiwuakee Street PROJECT NUMBER: PROJECT NO. 07-1473 / CIP NO. 50559 LET DATE: April 11, 2017 LOW BID AMOUNT: $3,941,397.20 ENGINEER'S ESTIMATE
More informationBIDDER'S PROPOSAL (continued) CITY OF BERKELEY BID PROPOSAL ITEM NO. A: BASE BID
SPECIFICATION 16-11031-C CITY OF BERKELEY BID PROPOSAL A: BASE BID 1 MOBILIZATION 1 LS 2 TRAFFIC CONTROL 1 LS 3 CONTRACTOR INFORMATION SIGN 2 EA 4 CONSTRUCTION AREA SIGN 18 EA 5 PROJECT IDENTIFICATION
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 170480 PID 100480 BRO-US 52-00.00 Federal Type: TWO LANE RESURFACING Letting Date: 8/10/2017 Completion Date:
More informationMcCRORY & WILLIAMS, INC. HILLCREST ROAD CONNECTOR MCR ROADWAY ITEMS
BID TABULATION Hillcrest Road Connector John G. Walton Construction M. C. Williams Contracting Hosea. Weaver & Sons, Inc. BID OPENING: March 25, 29 Company, Inc. Company, Inc. QTY DESCRIPTION DOLLARSjCTS
More informationProject Book Worksheet for Cost Estimation
001.01 MOBILIZATION LS $34,716.18 007 3/17/2039 001.02 INCIDENTAL LS $23,929.43 019 3/17/2039 001.03 CONSTRUCTION STAKING LS $10,504.39 201 5/9/2013 001.04 REESTABLISH PROPERTY CORNERS EA $496.08 201 5/9/2013
More informationMoDOT 2016 UNIT BID PRICES Northwest District
MoDOT 2016 UNIT BID PRICES Northwest District 2013000 CLEARING AND GRUBBING ACRE 7.95 20 1926.49132 20000 1 159 2022010 REMOVAL OF IMPROVEMENTS L.S. 1.00 56 24479.13304 201719 750 56 2024043 REMOVAL OF
More informationMaine Turnpike Authority
Interchange 44 Barrier Toll Plaza Open Road Tolling Conversion Mile 44.3 201.11 CLEARING 3.50 AC 202.071 REMOVING ASBESTOS CONTAINING MATERIALS, TOLL BOOTH LAB TOPS 1.00 LS 202.081 REMOVING EXISTING BUILDING
More informationMaine Turnpike Authority
Company Name Total Bid Amount Shaw Brothers Construction, Inc. - Gorham, ME $659,771.50 R J Grondin & Sons - Gorham, ME $690,828.50 Gendron & Gendron - Lewiston, ME $753,187.00 Gordon Contracting - Sangerville,
More informationSTATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/15/17 Comp. Dt: 08/04/17. Contract Time: Min: Max:
Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 1401-171 Contract ID: Contract Description: Contract Location: Recommendation: 170002 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationFertilizer Type B 2 CWT $ $ $60.00 $ $60.00 $ Sod Water 60 MGAL $60.60 $3, $30.00 $1, $30.00 $1,
BID TABS PROJECT 18-1029 22 nd AVENUE RECONSTRUCTION BID DATE: MAY 9, 2018 Stark Pavement Corp. Lalonde Contractors Cornerstone Pavers LLC Brookfield, WI Waukesha, WI Racine, WI Item Number Roadway Quantity
More informationMaine Turnpike Authority
Company Name Total Bid Amount Sargent Corporation - Stillwater, ME $29,888,765.79 Reed & Reed, Inc. - Woolwich, ME $34,900,974.90 Page 1 of 25 Sargent Corporation Stillwater, ME 201.11 CLEARING AC 4.00
More informationFederal Project No.: STP-5128(388)
Order : M48 Schedule of Items Page: 2 Oversight/State Project : (NFO) 0460-129-105, C501 Federal Project : STP-5128(388) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION)
More information(1 ) Active Construction Inc River Road East Tacoma, WA AMOUNT , , ,
78th Avenue Eastl184th Street EastlCRP 5661 I hereby certify this to be a true copy of the tabulation of the bids as received and opened. BID OPENING: FRIDAY, March 3, 2017 County Engine (1 ) Active Construction
More information2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH
Page 1 2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH ITEM ITEM DESCRIPTION UNITS N TOTAL QUANTITY AVERAGE PRICE 106.05100 FIELD LABORATORY
More informationFederal Project No.: OC-095-1(348)
Order : N83 Schedule of Items Page: 2 Oversight/State Project : (NFO)0095-127-857, C501 Federal Project : OC-095-1(348) 0010 513 00100 MOBILIZATION LUMP SUM LUMP SUM 0020 517 00101 CONSTRUCTION SURVEYING
More information2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH
Page 1 2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH ITEM ITEM DESCRIPTION UNITS N TOTAL QUANTITY AVERAGE PRICE 106.05100 FIELD LABORATORY
More informationLicensed Class C Virginia Contractor No.
month period is seven hundred and fifty thousand dollars (750,000) or more, the Bidder is required under Title 54.11100, Code of Virginia (1950), as amended, to be licensed by the State Board of Contractors
More informationMaine Turnpike Authority
York Toll Plaza Mile 8.8 201.11 Clearing 17.00 AC 202.15 Removing Existing Manhole or Catch Basin 22.00 EA 202.151 Abandoning Existing Manhole or Catch Basin 10.00 EA 202.16 Removing Existing Pipe 575.00
More informationALABAMA DEPARTMENT OF TRANSPORTATION DATE : 06/14/13 PAGE : VENDOR RANKING
PAGE : 001-1 VENDOR RANKING CONTRACT TIME : 09/01/13 COMPLETION DATE CONTRACT DESCRIPTION : PROJECT(S) : IM-I059(370) for constructing the Ramp Widening and Auxiliary Lane (Grade, Drain, Base, Pave and
More information2017 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR ENGLISH (10)
106.05100 FIELD LABORATORY EA 33 33.00 $12,605.17 201.03201 CLEARING AND GRUBBING ACRE 2 76.00 $1,269.74 201.03206 CLEARING TREES 6 in EA 1 53.00 $122.27 201.03210 CLEARING TREES 10 in EA 3 66.00 $227.33
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Engineering Division PROJECT NO INCA STREET MULTI-USE PATH 38 TH AVE. TO 43 RD AVE.
201-00000 Clearing and Grubbing 1 LS 202-00010 Removal of Tree 9 EA 202-00019 Removal of Inlet 8 EA 202-00034 Removal of Pipe (6 Inch) 196 LF 202-00035 Removal of Pipe (18 Inch) 10 LF 202-00036 Removal
More informationFederal Project No.: HSIP-5A27(567)
Order : A11 Schedule of Items Page: 2 Oversight/State Project : (NFO)0001-020-S82,C501 Federal Project : HSIP-5A27(567) 0010 513 00100 0020 517 00101 MOBILIZATION LUMP SUM LUMP SUM CONSTRUCTION SURVEYING
More informationMaine Turnpike Authority
Company Name Total Bid Amount CPM Constructors - Freeport, ME $1,309,765.25 Scott Construction Corporation - Portland, ME $1,528,840.00 Wyman & Simpson Inc. - Richmond, ME $1,674,845.00 Page 1 of 10 CPM
More informationBID ITEM ESTIMATED UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. QUANTITY UNIT ITEM COST COST COST COST COST COST
PAGE 1 BID OPENING: AUGUST 11, 2011 ENGINEER'S ESTIMATE: $3,108,320.60 CONTRACT NO.110269 SABINO CANYON AND TANQUE VERDE INTERSECTION IMPROVEMENTS *FOR A MORE DETAILED ITEM DESCRIPTION* *REFER TO PROPOSAL
More informationSTATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. District(s): 8 30=047 Start Dt: 05/01/17 Comp. Dt:
Letting: 17030200 Letting Dt: March 02, 2017 9:30 A.M. State Proj.: 5101-14 Contract ID: Contract Description: Contract Location: Recommendation: 170020 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationDOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/04 AND 12/31/04 BY ITEM GROUP 201 CONTRACTS - AWARDED TOTAL: $340,971,276
AVERAGE BID PRICES FOR AWARDED PROJECTS 14:37 Wednesday, February 2, 2005 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 17 $920 $54,140.65 17 2011.601/00040 DESIGN LS 1 $4 $3,500.00 1 2011 $924 2013
More informationSTATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/08/17 Comp. Dt:
Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 4308-34 Contract ID: Contract Description: Contract Location: Recommendation: 170004 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationDESCRIPTION QUANTITY PRICE TOTAL
GENERAL 1 TRAFFIC CONTROL LS 1 $40,000 $40,000 $8,500.00 $8,500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $15,000.00 $15,000.00 2 MOBILIZATION LS 1 $557,000 $557,000 $629,500.00 $629,500.00 $350,000.00
More informationTHORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E
THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E Each bidder shall bid each item of the Base Bid Schedule and Alternate A Bid Schedule. Failure to bid an item shall be just cause
More informationMcCRORY & WILIJAMS, INC. PROJECT NO. MCR-2008-OO1
McCRORY & WILIJAMS, INC. THEODORE DAWES ROADISCHILLINGER ROAD SOUTH BID TABULATION: Theodore DaweslSchillingor Road PROJECT NO.: M5700-2033 BIDDER #1 BIDDER #2 BIDDER #3 Hosea 0. Weaver & Sons, Inc. John
More informationDOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/10 AND 12/31/10 BY ITEM GROUP 211 CONTRACTS - AWARDED TOTAL: $649,895,273
AVERAGE BID PRICES FOR AWARDED PROJECTS 06:54 Friday, February 18, 2011 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 9 $276 $30,713.33 9 2011.601/00010 VIBRATION MONITORING LS 2 $73 $36,700.00 2 2011
More informationMaine Turnpike Authority
Company Name Total Bid Amount Liddell Brothers, Inc. - Halifax, MA $1,590,213.00 Northeast Traffic Control Services, Inc. - Plymouth, MA $1,932,117.00 Page 1 of 5 Liddell Brothers, Inc. Halifax, MA 202.2061
More informationCONTRACTOR'S REQUEST FOR PAYMENT CHASKA VETERANS PARK IMPROVEMENTS STANTEC PROJECT NO
Owner: City of Chaska, 1 City Hall Plz., Chaska, mn 55318 Date: December 12, 2017 For Period: 12/1/2017 to 1/31/2018 Request No: 1 Contractor: Blackstone Contractors, LLC, 9520 County Rd. 19, Ste. D, Loretto,
More informationHOUR TRAINING UNLOCKED HOUR SURVEY CREW UNLOCKED LUMP SUM CLEARING AND GRUBBING UNLOCKED FORCE ACCOUNT CLEARING AND
1100050 HOUR TRAINING UNLOCKED 2000100 HOUR SURVEY CREW UNLOCKED 2010100 LUMP SUM CLEARING AND GRUBBING UNLOCKED 2010110 FORCE ACCOUNT CLEARING AND GRUBBING UNLOCKED 2010120 ACRE CLEARING AND GRUBBING
More informationKansas Department of Transportation DISTRICT 2. Project(s): Min: Max:
Page 1 of 23 518122 SECTION: 01 COMMON ITEMS 1 020100 CONTRACTOR CONSTRUCTION STAKING 2 025602 FIELD OFFICE AND LABORATORY (TYPE C) 3 025323 MOBILIZATION 4 070626 MOBILIZATION (DBE) 5 020001 MAINTENANCE
More informationBID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ -
BID FORM PART A Name & Category Unit Unit Cost (B) Cost (AxB) GENERAL REQUIREMENTS 1 Mobilization (Maximum 3.0% of the total Contract Price) 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity
202-00001 Removal of Structure 24 EA 202-00019 Removal of Inlet 24 EA 202-00195 Removal of Median cover 930 SY 202-00200 Removal of Sidewalk 1,188 SY 202-00201 Removal of Curb Head 273 LF 202-00203 Removal
More informationProject # & Name: # CDBG - Pugh Street Streetscape - East College Ave to East Beaver Ave & East Beaver Ave/Locust Lane Improvements
Bid Opening Date: May 6, 2014 Time: 11:00 a.m. Surety NCA Surety NCA Yes Yes Yes Yes Total Amount Bid: $1,358,851.00 Total Amount Bid: $1,386,098.72 Item Nos. Approx. Quantities Unit Item & Unit Prices
More informationFederal Project No.: NHFP-081-1(346)
Order : N27 Schedule of Items Page: 2 Oversight/State Project : (NFO)0081-098-778,B650-51,C501 Federal Project : NHFP-081-1(346) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION)
More informationMacomb County Department of Roads Bid Comparison
Macomb County Department of Roads Bid Comparison Contract ID: 1643 Description: M-53 Freeway to 33 Mile Road Connector to the proposed 33 Mile Road & McKay Road Roundabout Location: Projects(s): M-53 &
More informationS T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/27/06 PAGE : 1 TABULATION OF BIDS
PAGE : 1 NUMBER OF DAYS: 63 BRIDGE COUNT : 9 CONTRACT DESCRIPTION : BITUMINOUS OVERLAY & BRIDGE APPROACH PANEL REPLACEMENT CONTRACT LOCATION: LOCATED ON TH 90 FROM 0.8 MILE WEST OF THE BLUE EARTH RIVER
More informationSTREET IMPROVEMENTS PROPOSAL BID ITEMS
STREET IMPROVEMENTS 1 Excavation 3,525 CY $ $ 2 A.C. Planing (2" to 4" Depth) 20,586 SY $ $ 3 Furnish & Install Asphalt Concrete 4,270 TON $ $ 4 Furnish & Install Aggregate Base 2,955 TON $ $ 5 Remove
More informationBID TABULATION REPORT McKINNEY STREET DRAINAGE IMPROVEMENTS PROJECT No. PWDR10012 BID OPENED : TUESDAY, AUGUST 13, :00 P.M.
PAVING IMPROVEMENTS McKINNEY 101 Rightofway Preparation LS 1 75,000.00 75,000.00 200,000.00 200,000.00 67,000.00 67,000.00 110,000.00 110,000.00 102 12inch HMAC Street Pulvermix SY 11,650 3.00 34,950.00
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity
202-00019 Removal of Inlet 15 EA 202-00035 Removal of Pipe 121 LF 202-00200 Removal of Sidewalk 1,057 SY 202-00203 Removal of Curb and Gutter 2,142 LF 202-00206 Removal of Concrete Curb Ramp 320 SY 202-00207
More informationThe Tulalip Tribes of Washington
The Tulalip Tribes of Washington I-5/116th Street NE Interchange Improvements Phase 4 Ramps Bid Solicitation No. 17-007 ADDENDUM NO. 3 November 7, 2017 to Request for Bid Proposals The Tulalip Tribes of
More informationTown of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166
Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Date: August 10, 2016 Subject: Bid for Construction of NW 89 th Avenue, NW 93 rd Street and NW
More informationARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS
ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2016153 TRACS No. Project No. County District Gross
More informationWentzville Parkway South Phase 2 & 2A
Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total
More informationRiverside County Transportation Department Summary of Bids
1 COUNTY'S ESTIMATE R-JS General Construction Riverside, CA 92509 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID UNIT PRICE BID ESTIMATE 1 066102 DUST ABATEMENT LS 1 3,000.00
More informationS T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/26/00 PAGE : 1 TABULATION OF BIDS
PAGE : 1 CONTRACT DESCRIPTION : LEFT & RIGHT TURN LANES AND FLASHING BEACON SYSTEM CONTRACT LOCATION: LOCATED ON TH 7 FROM 327 M WEST OF JCT TH 25 TO 445 M EAST OF JCT TH 25 RECOMMENDATION: AWARD TO LOW
More informationOTTAWA COUNTY ROAD COMMISSION Bid Comparison
OTTAWA COUNTY ROAD COMMISSION Bid Comparison Contract ID: Description: Location: Projects(s): 28th & Mason Reconstruct with pavement 28th Ave. and Mason St between Adams St. and 32nd Ave. Jamestown Township
More informationBID TABULATION PAGE 1 OF 4. BL S.R. Harbins Road/Alcovy Road - Intersection Improvements Department of Transporation. CMES, Inc.
BID TABULATION PAGE 1 OF 4 E.R. Snell Contractor, Inc. G.P.'s Enterprises, Inc. Est. 1 005 Traffic Control Project No M-0679 1 LS $27,811.00 $27,811.00 $48,800.00 $48,800.00 $22,021.80 $22,021.80 2 010
More informationGrays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14
Grays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14 Hardesty & Hanover, LLC Alternative 1 Bogie Support System Alternative Based on AW Sketch of New Bridge Component
More informationFederal Project No.: STP-5A27(380), STP-5A27(381)
Order : M42 Schedule of Items Page: 2 Oversight/State Project : (NFO)0649-020-136,C502, C503 Federal Project : STP-5A27(380), STP-5A27(381) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING
More informationPAGE 1 of 18 WEIGHTED AVERAGE
UNIT PRICES PAGE 1 of 18 201 BRIDGE SITE PREPARATION L.S. 1.00 15,000.00 15,000.00 15,000.00 * 201 CLEARING ACRE 4.10 40,470.00 4,500.00 13,010.78 201 CLEARING STA 6,089.00 11,000.00 1.00 1,162.09 201
More informationADDENDUM #2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18
November 29, 2018 ADDENDUM 2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18 Q1. Do contractors not need to be on the Watershed Improvements Pre-Qualifications List to submit on the RP031-18 Watershed
More informationCITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS
CITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS CITY OF SAN ANTONIO DEPT. OF CAPITAL IMPROVEMENTS MANAGEMENT SERVICES N. NEW BRAUNFELS AVE. SIDEWALK PROJECT FROM RITTIMAN
More informationSUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71
BASE BID 1.00 GENERAL CONDITIONS 1.01 Mobilization (Maximum 5% of Base Bid) LS 1 84,000.00 $ 84,000.00 100,000.00 $ 100,000.00 85,000.00 $ 85,000.00 1.02 Bonding, Insurance, Permits (including Plumbing,
More informationBid Tabulation City of Coralville RE-BID Coral Ridge Ave, Phase II - Oakdale Blvd to Forevergreen Rd City of Coralville, IA Engineer's OPC
, IA - 2017 DIVISION 1 - GENERAL 1.01 TRAFFIC CONTROL LS 1 $50,000.00 $50,000.00 $30,000.00 $30,000.00 $24,500.00 $24,500.00 $24,500.00 $24,500.00 $24,500.00 $24,500.00 DIVISION 2 - EARTHWORK 2.01 CLEARING
More informationDate: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications:
DEVELOPMENT SERVICES PHONE: (209) 668-5520 ENGINEERING DIVISION FAX: (209) 668-5563 156 S. BROADWAY, SUITE 150 TDD: (800) 735-2929 TURLOCK, CA 95380 engineering@turlock.ca.us Date: 04/20/2018 City Project
More informationSUMMARY 3-0 BRADFORD ALBANY TOWNSHIP. 1 OF 1 P:\8417\ Bridge A\AT\Albany A.MDB 7/21/2014 7:32:31 AM REVISION NO COUNTY
7/18/2014 - UCTURE REVISION NO REVISIONS DATE BY DIICT COUNTY ROUTE SECTION SHEET - SEE SPECIAL PROVISIONS SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP T-410 4 OF 8 QUANTITY ITEM NO UNIT DESCRIPTION DESIGN NO
More informationMETRO Magnolia Transit Center - Bid Tab
Section A - GENERAL ITEMS A-1 01505 Mobilization LS 1 $ 100,000.00 $ 100,000.00 A-2 -- Payment and Performance Bonds LS 1 A-3 01310 Document Control LS 1 A-4 01311 CPM Schedule LS 1 A-5 01590 Engineer's
More informationSTANDARD DRAWING INDEX
ATTACHMENT B STANDARD DRAWING INDEX DESCRIPTION EXISTING DRAWING NO. GENERAL Typical Layout for Improvement Plans City of Stockton Standard Border and Title Block for 8 1/2 x11 Sheet City of Stockton Standard
More informationIngham County Request for Proposals Okemos Road and Sandhill Road Widening, Packet #15-15
COST FORM (1 of 5) Packet #15-15, Okemos Road & Sandhill Road Widening Project (Please Type or Print Clearly in Ink) Pay Description Unit Quantity Unit Price Total 1500001 Mobilization, Max. LS 1 2020002
More informationSPAS Concepts Preliminary Rough Order of Magnitude Cost Estimates
Appendix G LAX SPECIFIC PLAN AMENDMENT STUDY REPORT SPAS Concepts Preliminary Rough Order of Magnitude Estimates 2011/2012 Prepared for: Los Angeles World Airports One World Way Los Angeles, California
More informationSPECIAL GRADING INTERSECTION IMPROVEMENT JOHN WARD RD AT IRWIN RD REVISION DATES
9/20/2017 2:39:11 PM GPLOT-V8 2016104_18-001.dgn Project Number Sheet Total Sheets djackson gplotborder-v8i-po.tbl X2802 30 118 966.5 21+00 L.P. EL. 966.34 L.P. EL. 966.58 0.29% 0.11% 965 H.P. EL. 966.54
More informationCounty of Los Angeles Department of Public Works BID SUMMARY
PROJECT NAME 3RD STREET - INDIANA STREET TO RECORD AVENUE PROJECT ID RDC0015034 Engineer's Estimate (1) Sully-Miller Contracting Company (2) TORO ENTERPRISES, INC. (3) Sequel Contractors, Inc. (4) All
More informationCITY OF STANDARD SPECIFICATIONS
CITY OF Published May 4, 2016 CALIFORNIA Stephan Kiefer, Community Development Director Cheri Sheets, City Engineer CITY OF LIVERMORE 1052 South Livermore Avenue Livermore, CA 94550 4DEV0001.doc 03/12
More information2, total unit $ total unit $ total unit $ total $
BD TABULATON Bid No. : 697 North Bay Trail-1st Street North Project No. 0901-212 Engineering &Capital mprovements Department, City of 1. Petersburg, Florida Bid date: February 26,2010 ",,>,',-, t~..4":;
More informationBID PROPOSAL. Item Description Unit Quantity Unit Price Total Price No. (Unit Price to be written in Words) (Figures) (Figures)
BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions and Invitations to Bidders, the undersigned proposes
More informationOaks Commerce Center
Mansour Edlin Consulting 1515 Mockingbird Lane Charlotte, NC 28209 Oaks Commerce Center Water & Sanitary Sewer Improvements Phase I - Concept Utility Plan Gravity Sanitary Sewer A1 Connect to Existing
More informationPN /21/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS
PN 420-10/21/2016 - SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS DESCRIPTION: The surface tolerance specification requirements are modified as follows for all pavements of constant width with at least
More informationAustin Constructors, LLC S FM N. Richey 9810 FM 969. Pasadena, TX Austin, TX 78724
National Power Rodding Corp. 9810 FM 969 Austin, TX 78724 Austin Constructors, LLC. 7907 S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price 103.1 125.00
More information2150 F&I 4" PVC pipe LF 100 $ F&I 6" PVC pipe LF 100 $ F&I 8" PVC pipe LF 100 $ 90.00
1 of 5 2100 F&I 4" ductile iron pipe LF 200 $ 143.00 $28,600.00 2102 F&I 6" ductile iron pipe LF 200 $ 135.00 $27,000.00 2104 F&I 8" ductile iron pipe LF 200 $ 141.00 $28,200.00 2105 F&I 10" ductile iron
More informationSchedule of Pay Items
Schedule of Pay Items 4/27/2018 9:33 AM AASHTOWare Project Version 4.0 Revision 189 Report v1 Letting Call: 180601 001 Letting Date: June 1, 2018 Contract ID: 392144-202845 Description: Runway 17/35 rehabilitation
More informationBid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013
Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D4-1102 November 21, 2013 Doughtie Construction Co., Elliott Construction Dudley Construction Ltd. SUBTOTAL GENERAL ITEMS : $191,713.00
More informationRiverside County Transportation Department Summary of Bids
Company Name Dartmouth St. Base Bid Sch. Yale St. Base Bid Sch. Alternate Bid Sch. Alternate Bid Sch. Alternate Bid Sch. Alternate Bid Sch. 4 Total COUNTY'S ESTIMATE,87,.50,444,6.00 9,400.00 9,400.00 800.00,00.00
More informationCounty of Los Angeles Department of Public Works BID SUMMARY
PROJECT NAME CENTRAL AVENUE, ET AL. PROJECT ID RDC0013675 Engineer's Estimate (1) All American Asphalt (2) Sequel Contractors, Inc. (3) Sully-Miller Contracting Company (4) Palp, Inc. 5,177,177.00 5,292,979.00
More informationItems Unit Quantity Unit Price Total Unit Price Total
Engineer's Plote Construction, Inc. Estimate 1100 Brandt Drive Hoffman Estates, IL 60192 s Unit Quantity 1 SUPPLEMENTAL WATERING UNIT 4 $100.00 400.00 $40.00 160.00 2 TOP SOIL FURNISH AND PLACE, 6 INCH
More informationOn-the-Job Training Program. Overview of Training Programs
On-the-Job Training Program Overview of Training Programs The training programs are as follows: Code Training Program Hours (Up to) 901 Carpenter, Rough 1040 902 Concrete Finisher (Paving) 1040 903 Concrete
More information800 Access Control, R/W Use Permits and Drive Design
Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled
More informationDELETE first sentence of first paragraph that reads: REPLACE with the following:
To Bidder of Record: SAN ANTONIO WATER SYSTEM Addendum 2 To Construction Documents For 2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB NO. 12-5001 SAWS SEWER JOB NO. 12-5501 Solicitation
More information2011 LOCAL STREET IMPROVEMENTS
11 LOCAL STREET IMPROVEMENTS FOR THE MARCH 11 LIST OF DRAWINGS W. MAIN STREET/STH 19 E. MAIN STREET/STH 19/STH 113 DRAWING TITLE NO. TITLE 1 PROJECT OVERVIEW 2 KLEIN DRIVE CONSTRUCTION PHASING PLAN 3 PHASE
More informationTahoe-Reno Industrial Center Total Bonding Amounts Engineer's Opinion of Probable Construction Costs (30% Submittal) Project No. 783.
Total Bonding Amounts Brent Farr Date: 05/05/17 Item Project Estimated Cost 1 Induction Well 1 and Britain Ave Non potable Water Line $1,084,353 2 Storage Reservoir Upgrades $11,560,463 3 Booster Station
More informationCITY OF DAVIS PUBLIC WORKS DEPARTMENT STANDARD SPECIFICATIONS
CITY OF DAVIS PUBLIC WORKS DEPARTMENT STANDARD SPECIFICATIONS JANUARY 1996 EDITION ADDENDA THROUGH JULY 2017 DIANNA JENSEN City Engineer 1717 Fifth Street Davis, CA 95616 530-757-5686 2017 Edition STANDARD
More informationCOST ESTIMATES: Curb-Running
COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway
More information