BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS

Size: px
Start display at page:

Download "BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS"

Transcription

1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO IN THE MATTER OF THE APPLICATION OF TRI-STATE GENERATION AND TRANSMISSION ASSOCIATION, INC. FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE BURLINGTON LAMAR KV TRANSMISSION LINE PROJECT AND FOR SPECIFIC FINDINGS WITH RESPECT TO MAGNETIC FIELDS AND AUDIBLE NOISE ) ) ) ) PROCEEDING NO. ) ) ) ) DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS Section Page I. INTRODUCTION AND QUALIFICATIONS... II. PURPOSE OF TESTIMONY... III. TRI-STATE'S EXISTING TRANSMISSION SYSTEM IN THE PROJECT AREA... IV. PROJECT PURPOSE AND NEED... V. ALTERNATIVES ANALYSIS... VI. PROPOSED PROJECT... VII. PROJECT COORDINATION... 0_

2 I. INTRODUCTION AND QUALIFICATIONS Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: My name is Christopher E. Pink. My business address is 10 West th Avenue, Westminster, Colorado 0. Q: BY WHOM ARE YOU EMPLOYED AND IN WHAT CAPACITY? A: I am employed by Tri-State Generation and Transmission Association, Inc. ( Tri- State ) as Manager, Technical Services/Bulk System Planning. Q: ON WHOSE BEHALF ARE YOU TESTIFYING IN THIS DOCKET? A: I am testifying on behalf of Tri-State. Q: HAVE YOU PREPARED A STATEMENT OF YOUR EXPERIENCE AND QUALIFICATIONS? A: Yes. A statement of my experience and qualifications is attached to my testimony as Exhibit No. CEP-1. Q: PLEASE DESCRIBE BRIEFLY YOUR BACKGROUND AND EXPERIENCE IN THE ELECTRIC UTILITY INDUSTRY. A: I have over years of experience in the electric utility industry. In my present position, I am responsible for planning, coordinating, directing, and providing engineering support for the development of Tri-State s transmission network utilizing my knowledge of bulk power systems. Prior to joining Tri-State, I worked as a system engineer at a distribution cooperative, a research engineer at a national lab, and an electrical engineer at a consulting firm. I have undergraduate and master s degrees in engineering from the Colorado School of Mines. I am a registered Professional Engineer in the State of Colorado. 0_

3 II. PURPOSE OF TESTIMONY Q: WHAT IS THE PURPOSE OF YOUR DIRECT TESTIMONY? A: My testimony discusses the purpose and need for the Burlington Lamar Transmission Line Project (the Project ). Specifically, I will discuss the needs related to load serving, reliability, and constraints on planned renewables that give rise to the Project. I will also discuss the system studies that have been performed which confirm and support the need for the Project. I will also introduce Tri-State's other witnesses whose testimony supports the issuance of a Certificate of Public Convenience and Necessity ( CPCN ) for the Project as described in Tri-State s Application. Q. IS TRI-STATE PRESENTING TESTIMONY FROM OTHER WITNESSES IN SUPPORT OF ITS CPCN APPLICATION? A. Yes. In addition to my own testimony, Tri-State is sponsoring the direct testimony of the following witnesses in support of its Application: - Grant D. Lehman, Tri-State's Senior Manager, Transmission Engineering and Construction, will describe the details of the proposed transmission line design, the Project schedule, and estimated cost; - Karl W. Myers, Tri-State's Manager of Transmission Siting and Environmental Planning, will describe the land use, right-of-way, siting, and permitting issues associated with the Project; and - Dr. Robert Pearson, a consulting engineer, will address issues related to magnetic fields and audible noise. 0_

4 III. Together, my testimony and the testimony of these witnesses provide a comprehensive explanation of the Project and its underlying purpose and need. TRI-STATE'S EXISTING TRANSMISSION SYSTEM IN THE PROJECT AREA Q: PLEASE PROVIDE A BRIEF DESCRIPTION OF THE PROJECT. A: The Project is a new single-circuit, kv transmission line interconnecting Tri- State s existing Burlington and Lamar substations. The new transmission line will be approximately 0-1 miles long and will be constructed on wood H-frame structures. Project facilities are shown in electric one-line diagram format in Exhibit No. CEP-. Q: PLEASE DESCRIBE THE LOCATION OF THE PROJECT. A: The Project will be located in Kit Carson, Cheyenne, Kiowa, and Prowers counties and will cross areas served by Tri-State Member Systems K.C. Electric Association and Southeast Colorado Power Association. A map of the Project Area is included as Exhibit G to the CPCN Application. Q: PLEASE DESCRIBE THE EXISTING TRANSMISSION AND GENERATION SYSTEMS IN THE LAMAR AREA. A: The transmission network in the Lamar area consists of two systems: 1) a kv load serving network; and ) the Boone - Lamar kv line. The kv network is owned and operated by Black Hills/Colorado Electric Utility Company, L.P. and Tri-State. It serves all the load centers between Boone and Lamar, including Rocky Ford, Las Animas, Vilas, Lamar, Holly, and La Junta, among others. Transmission assessments have shown that the kv network 0_

5 will be unable to serve all the Lamar area loads after a loss of the Boone Lamar kv line. The Boone - Lamar kv line serves no distribution systems directly. Its primary purpose is to transfer bulk power into and out of the area. Tri-State imports power from Boone kv to Lamar kv to serve Tri-State s kv loads in the area. Public Service Company of Colorado ( PSCo ) utilizes the kv line to transfer their Lamar area generation to their Front Range loads. PSCo has MW of generation connected at Lamar kv, including the Lamar DC Tie (± MW), Colorado Green East and West Wind ( MW), and Twin Butte Wind ( MW). The underlying kv system is insufficient to transfer this much power; thus, a scheme is in place to automatically trip all Lamar area generation for an outage of the Boone Lamar kv line. Loss of the Boone Lamar kv element is the most severe single contingency in the area. Q: PLEASE DESCRIBE THE EXISTING TRANSMISSION AND GENERATION SYSTEMS IN THE BURLINGTON AREA. A: Like Lamar, the Burlington area transmission system presently consists of two systems: 1) an underlying kv load serving network; and ) a single kv line. There are several owners of the various kv load serving networks, including Western Area Power Administration, PSCo, Tri-State, and K.C. Electric Association Inc. These networks serve the majority of the eastern Colorado load centers, including Yuma, Wray, Idalia, and Burlington, among others. 0_

6 1 The kv line connects Burlington, via Landsman Creek, to the Big Sandy Lincoln Midway kv system. A second line, called Burlington Wray kv, is presently under development and expected to be in service by. It will connect Burlington to the Wray North Yuma kv system to the North. A sizable amount of conventional and renewable generation is connected and is planned to be connected at or near Burlington. The Burlington system is generation rich and transmission constrained. The most significant issue is its ability to safely export power following an outage of the Burlington Big Sandy Lincoln Midway kv system. During periods of high generation, significant overloads on the underlying kv network occur following kv outages. This condition is exacerbated during low-load, highwind conditions. To ensure kv overloads do not occur, the Burlington area 1 generation is restricted through operating procedures and agreements. This situation presently restricts any new renewable generation in the Burlington area. The future Burlington Wray kv project significantly relieves these restrictions. It does not, however, provide sufficient relief to accommodate all planned future generation. For example, Tri-State has plans for a 10 MW network resource, named Carousel Wind, to be connected at Burlington kv in 1. Lacking a significant transmission project, the output of Carousel Wind will be limited during light load conditions to protect against kv outages, much like today s existing Burlington area generation. 0_

7 In summary, even with the new Burlington - Wray kv line, the Burlington area transmission system still needs another outlet for planned generation. Q: PLEASE DESCRIBE TRI-STATE S RELATIONSHIP TO ITS MEMBER SYSTEMS AND ITS LOAD SERVING AND RELIABILITY OBLIGATIONS. A: Tri-State is a regional, wholesale electric power supplier owned by the electric cooperatives and public power districts (the Member Systems ) that it serves in Colorado, New Mexico, Nebraska, and Wyoming. Tri-State is obligated to provide reliable, efficient, cost-based, wholesale power to these Member Systems, who in turn provide retail electric service to their end-use member- consumers. Tri-State, as a regional transmission provider, also has the IV. obligation to provide reliable transmission service to its other network customers, such as Public Service Company of New Mexico, the Municipal Energy Agency of Nebraska, Arkansas River Power Authority, and PSCo, and to comply with all North American Electric Reliability Corporation ( NERC ) and Western Electricity Coordinating Council ( WECC ) transmission reliability standards. PROJECT PURPOSE AND NEED Q: WHAT IS THE PURPOSE OF THE PROPOSED PROJECT? A: The purpose of the Project is to alleviate existing and reasonably anticipated future transmission system constraints and reliability issues in a manner that aligns with elements of larger, strategic transmission initiatives in eastern Colorado. Q: ARE THERE SPECIFIC NEEDS THAT ARE ADDRESSED BY THE PROJECT? 0_

8 A: Yes, several reliability issues must be addressed in the eastern and southeastern Colorado transmission systems that are mitigated by the Project: 1) Unacceptable voltages and voltage deviations in the Lamar area following a Boone Lamar kv line outage; ) Transmission constraints in the Lamar area; and ) Transmission constraints in the Burlington area. Q: ARE THERE OTHER BENEFITS OF THE PROJECT? A: Yes. The Project provides increased operational flexibility for maintenance outages, better transmission system performance following multiple contingencies, reduced regional losses, and more stable voltages across a wide range of system conditions. The Project also increases transmission capacity in regions with a high potential for new wind resources. This benefits stakeholders developing such projects, supports public policy goals (e.g., SB1-), and possibly increases competition, thereby providing Tri-State a more diverse portfolio of generation resources from which to choose. Another benefit is that a new Burlington Lamar transmission element aligns with other major, strategic transmission projects in the region. Constructing the Project is an important first step to ultimately meet some of the objectives of these larger transmission projects. Q: DESCRIBE HOW THE PROJECT ALIGNS WITH OTHER STRATEGIC TRANSMISSION INITIATIVES IN EASTERN COLORADO? 0_

9 A: There are two major transmission initiatives in eastern Colorado that include new infrastructure between the Lamar and Burlington areas. One is the Lamar Front Range Project. It includes new transmission lines interconnecting Lamar, Burlington, Big Sandy, Missile Site, Story, Pawnee, and Vilas. It is described as a multi-faceted transmission project designed to enhance the high-voltage transmission network in eastern Colorado. More details for the Lamar Front Range project are included in the Lamar Front Range Transmission Project Feasibility Study Report attached as Exhibit No. CEP-. Another is the High Plains Express initiative. Its goals are to significantly strengthen the eastern portion of the Western grid. Larger than the Lamar Front Range Project, it also includes transmission ties between Wray, Burlington, Lamar, and Vilas, among others. More details for the High Plains Express project are included in the High Plains Express Transmission Project Feasibility Study Report attached as Exhibit No. CEP-. While the Burlington Lamar Project does not by itself accomplish all of the objectives of the Lamar Front Range or High Plains Express projects, it is an important first step to ultimately meet some of the objectives of those initiatives. Q: WHAT STUDIES HAVE BEEN CONDUCTED THAT HAVE IDENTIFIED AND CONFIRMED OR OTHERWISE SUPPORTED THE NEED FOR THE PROJECT? A: There have been many, including: 1) Tri-State s various transmission performance assessments; ) the Lamar Front Range Project study (Exhibit 0_

10 No. CEP-); ) the High Plains Express Project study (Exhibit No. CEP-); and ) recent generator interconnection studies for Tri-State wind resources to be connected at Burlington. While each study addressed slightly different needs, they all confirm and support improvements that include interconnecting the Burlington and Lamar transmission systems. The following exhibits are relevant studies that describe the need or benefits of transmission system improvements between Burlington and Lamar: 1) Exhibit No. CEP-: Lamar Front Range Transmission Project Feasibility Study Report. This study describes a major transmission project in eastern Colorado that includes a transmission connection between Burlington and Lamar, among other elements. ) Exhibit No. CEP-: High Plains Express Transmission Project 1 Feasibility Study Report. This study describes another strategic transmission project in eastern Colorado that includes a transmission connection between Burlington and Lamar, among other elements. ) Exhibit No. CEP-: Tri-State Transmission Planning Assessment (Per TPL-001a, TPL-00a, TPL-00a, and TPL-00). This study identified, among other things, unacceptable voltages and voltage deviations in the Lamar area following a Boone Lamar kv outage. ) Exhibit No. CEP-: Burlington Lamar / kv Impact and 1 Post TPL Assessment Study. A follow up to the TPL assessment, this study compared alternatives and ensured the adequacy of a new 0_

11 Burlington Lamar kv line in solving the Lamar area performance issues. ) Exhibit No. CEP-: Interconnection System Impact Re-Study Final Report April, 1. This study identified transmission system constraints around Burlington following the installation of a new 10 MW wind resource during light load, high wind conditions (1 light autumn). It concluded that a new Burlington Lamar kv line would relieve the identified constraints. ) Exhibit No. CEP-: Supplemental Study to the Burlington Lamar / kv Impact and 1 Post TPL Assessment Study. A new transmission line between Burlington and Lamar will improve the transmission capacity in both areas. This study analyzed potential new generation injection levels after installation of a single Burlington Lamar kv line. ) Exhibit No. CEP-: Burlington Lamar kv Losses Evaluation. A new transmission line in the area will reduce the system s overall impedance, which will reduce losses and thus increase overall system efficiency. This study enumerates the potential impact of the Project on system losses and determines if an upgraded project is economically justifiable based on reduced losses. ) Exhibit No. CEP-: Interconnection System Impact Study Final Report Generator Interconnection Request No. TI-1-01 (POI Lamar Substation). This study identified reliability issues around Lamar both 0_

12 prior to and following the installation of a new 0 MW wind resource at Lamar. A dynamic stability sensitivity case was run, and it concluded that with a Burlington Lamar kv element modeled, all simulated contingencies resulted in acceptable system performance. V. ALTERNATIVES ANALYSIS Q: BEFORE WE DISCUSS THE PROPOSED PROJECT, DID TRI-STATE CONSIDER ANY NON-TRANSMISSION ALTERNATIVES TO MEET THE IDENTIFIED NEEDS? A: Yes. Tri-State considered at a high level whether the identified needs could be met through a generation solution or a solution involving energy efficiency or demand side management ( EE/DSM ) measures. Tri-State also considered whether it was feasible to take no action at all. Q: WHAT CONCLUSIONS DID TRI-STATE REACH WITH REGARD TO WHETHER A GENERATION ALTERNATIVE COULD SATISFY THE IDENTIFIED NEEDS? A: Since two of the needs being addressed by the Project are to relieve transmission constraints imposed on existing and planned generation, it was determined early on that additional generation would not be a viable solution. Q: WHAT CONCLUSIONS DID TRI-STATE REACH WITH REGARD TO WHETHER AN EE/DSM ALTERNATIVE COULD SATISFY THE IDENTIFIED NEEDS? A: Being generation rich, the transmission constraints in the Burlington and Lamar areas are exacerbated by reduced local loads. With less power consumed 0_

13 locally, more power is exported over the limited transmission networks. EE/DSM alternatives would reduce loads and therefore, would not mitigate the transmission constraint issues. Q: IS IT FEASIBLE FOR TRI-STATE TO TAKE NO ACTION WITH REGARD TO THE IDENTIFIED NEEDS? A: No. Tri-State, WECC, and NERC transmission performance criteria require levels of system performance that will not be met if no action is taken. Q: WHAT CONCLUSION DID TRI-STATE REACH WITH REGARD TO THE APPROPRIATE MEANS TO ADDRESS THE IDENTIFIED NEEDS IN EASTERN COLORADO? A: Consistent with the various studies previously identified, Tri-State determined that the most appropriate means to address the present and future needs in eastern Colorado is through transmission system improvements between Burlington and Lamar. Q: PLEASE DESCRIBE TRI-STATE S GENERAL ASSUMPTIONS AND METHODOLOGY. A: As discussed earlier, Tri-State utilized many different studies, covering a range of alternatives, to determine the best solution. The final decision was based on a broad spectrum of potential future scenarios. The Tri-State Transmission Planning Assessment (Exhibit No. CEP-), for example, utilized five base case assumptions spanning nine years under heavy and light, winter and summer scenarios. Likewise, the Burlington Lamar / kv Impact and 1 Post 0_ 1

14 TPL Assessment Study (Exhibit No. CEP-), focused on 1 heavy summer and light autumn cases. Other studies similarly included diverse assumptions, which are outlined in their respective reports. The various analyses identified an assortment of issues, but all pointed to alternatives involving a new transmission line between Burlington and Lamar. The methodologies employed power flow analyses under system intact, single contingency, and in some cases, multiple outage conditions. System performance was judged against Tri-State s planning criteria and applicable NERC and WECC reliability criteria. Q: PLEASE DESCRIBE THE GENERAL TRANSMISSION ALTERNATIVES THAT WERE CONSIDERED. A: The alternatives considered varied from study to study. Having determined that a transmission solution was most appropriate, Tri-State primarily based its decision on the consideration of two studies and their corresponding alternatives. The first study was the Burlington Lamar / kv Impact and 1 Post TPL Assessment Study (Exhibit No. CEP-). The study focused on mitigating reliability and transmission constraint issues in and around the Lamar area. It analyzed the following three alternatives: 1) A 0-1 mile transmission line between the Burlington and Lamar substations. One option of this alternative considered construction of a new single-circuit transmission line on steel lattice structures capable of operating at kv but operated initially at kv. A second option 0_ 1

15 considered construction of a single-circuit kv transmission line on wood H-frame structures. ) A single-circuit kv transmission line on wood H-frame structures extending approximately miles between the Lamar and Lincoln substations. ) A single-circuit kv transmission line on wood H-frame structures extending approximately 1 miles between the Lamar and Midway substations. The second study was the Interconnection System Impact Re-Study Final Report April, 1 (Exhibit No. CEP-). This study assessed impacts and mitigation of specific transmission constraints for Tri-State s planned 10 MW network wind resource in the Burlington area. The study considered three approaches to eliminate kv overloads that the additional generation caused: 1) Reduce the project generation size; ) Increase the ratings of the overloaded lines by upgrading them; and ) Construct a new transmission line into the project area. In addition to the primary studies, Tri-State also considered the results of the Lamar Front Range Study (Exhibit No. CEP-) and High Plains Express Study (Exhibit No. CEP-). While the range of their alternatives went beyond the scope of Tri-State s specific requirements, the Lamar Front Range and High Plains Express conclusions were considered when evaluating how Tri-State s needs fit in a larger context. 0_ 1

16 Q: PLEASE SUMMARIZE THE RESULTS OF TRI-STATE S BURLINGTON LAMAR / KV IMPACT AND 1 POST TPL ASSESSMENT STUDY (EXHIBIT NO. CEP-). A: This study confirmed the load serving, reliability, and generation delivery concerns associated with an outage of the Boone Lamar kv transmission line. The analysis determined that all three alternatives studied, including both options associated with the Burlington - Lamar alternative, mitigated the concerns around Lamar. The analysis also showed negligible performance differences between constructing the Burlington Lamar transmission alternative for either kv or kv operation. Q: PLEASE SUMMARIZE THE RESULTS OF TRI-STATE S INTERCONNECTION SYSTEM IMPACT RE-STUDY FINAL REPORT APRIL, 1 (EXHIBIT NO. CEP-). A: Overloads on the kv load serving network around Burlington were identified with the generation facility at full output following various kv line outages. Proposed mitigation included reduction in generation output, rebuilding existing kv lines, or construction of a new transmission line to the Burlington area. The Burlington Lamar kv line was modeled and the results demonstrated that it mitigates the identified kv overloads. Q: PLEASE SUMMARIZE THE RESULTS OF TRI-STATE S INTERCONNECTION SYSTEM IMPACT STUDY FINAL REPORT GENERATOR INTERCONNECTION REQUEST NO. TI-1-01 (POI LAMAR SUBSTATION). (EXHIBIT NO. CEP-). 0_

17 A: Loss of the Boone - Lamar kv line (with cross-trip scheme) failed to converge in the model. A dynamic stability sensitivity case was run modeling the planned Burlington - Lamar kv line. A solution was obtained for loss of the Boone - Lamar kv line (no cross trip), and the study results confirmed that all simulated contingencies were compliant with the NERC/WECC criteria. Q: PLEASE SYNTHESIZE THE RESULTS OF TRI-STATE S BURLINGTON LAMAR / KV IMPACT AND 1 POST TPL ASSESSMENT STUDY (EXHIBIT NO. CEP-), INTERCONNECTION SYSTEM IMPACT RE-STUDY FINAL REPORT APRIL, 1 (EXHIBIT NO. CEP-), AND INTERCONNECTION SYSTEM IMPACT STUDY FINAL REPORT GENERATOR INTERCONNECTION REQUEST NO. TI-1-01 (POI LAMAR SUBSTATION) (EXHIBIT NO. CEP-). A: Each study was performed independently and evaluated alternatives unique to their focus. The Burlington Lamar / kv Impact and 1 Post TPL Assessment Study concentrated on resolving problems caused by an outage of the Boone Lamar kv line. The study found three kv alternatives that mitigate the reliability issues in the Lamar region: Lincoln Lamar kv, Midway - Lamar kv, or Burlington Lamar kv. It concluded that a new Burlington Lamar kv element was preferred and would greatly improve the transmission system in eastern Colorado. The Interconnection System Impact Re-study Final Report April, 1 identified constraints on a new 10 MW wind farm near Burlington. The study 0_ 1

18 recommended three possible approaches to mitigate the constraints: 1) a new Burlington - Lamar kv line; ) significant rebuilds to other kv lines; or ) curtailing the wind farm output. The last being the least desirable approach, obviously. The Interconnection System Impact Study Final Report Generator Interconnection Request No. TI-1-01 (POI Lamar Substation) found that the system model failed to converge for a loss of the Boone Lamar kv line, even before the proposed generation project was included. A new Burlington Lamar kv element was modeled in dynamic simulations and proper transmission system performance was achieved both with and without the additional generation. New transmission facilities are large and expensive endeavors. Preferably, they meet several needs and address multiple issues. In the case of the proposed Project, three independent studies demonstrated that this single transmission line would significantly improve two relatively independent transmission systems an ideal outcome for any transmission project. Q: PLEASE SUMMARIZE THE RELEVANT RESULTS OF THE LAMAR FRONT RANGE TRANSMISSION PROJECT FEASIBILITY STUDY REPORT (EXHIBIT NO. CEP-) AND THE HIGH PLAINS EXPRESS TRANSMISSION PROJECT FEASIBILITY STUDY REPORT (EXHIBIT NO. CEP-). A: Both studies describe major conceptual transmission projects in eastern Colorado. They each include a transmission circuit between Burlington and Lamar, as part of a larger transmission project. The studies contemplate 0_ 1

19 generation injection, import and export capability, and access to energy resource zones, among other things. For purposes of this testimony, the salient point is that a high voltage path from Story to Wray to Burlington to Lamar was deemed necessary by these studies. Q: GIVEN THAT BOTH BURLINGTON TRANSMISSION OPTIONS PERFORMED WELL RELATIVE TO THE IDENTIFIED PROJECT NEEDS IN THE BURLINGTON LAMAR / kv IMPACT AND 1 POST TPL ASSESSMENT STUDY (EXHIBIT NO. CEP-), HOW DID TRI-STATE SELECT A PREFERRED PROJECT AMONG THESE ALTERNATIVES? A: Tri-State first considered rough, plus-or-minus 0%, cost estimates for each alternative for comparative purposes. These estimates are set forth below and in Table 1 of Exhibit No. CEP-. I note that these cost estimates differ from the actual engineering level cost estimates as provided in Grant Lehman s testimony. Planning studies require relative ranking, so instead of creating detailed costs for each alternative, plus or minus 0% costs allow relative ranking while avoiding the expense of developing detailed facility estimates. Conductor Alternative Description (ACSR) 1 ($000) 1 Burlington Lamar kv Lattice Steel (0 miles) (operate at kv without Burlington / kv transformer) -,000 1A Burlington Lamar kv Wood H-Frame (0 miles) 1,000 Lamar-Lincoln kv Wood H-Frame ( miles),000 Lamar-Midway kv Wood H-Frame (1 miles),000 Tri-State next considered its presently identified needs as well as the reasonably anticipated transmission system needs in the Project area. Based on costs and transmission system needs, Tri-State determined that Alternative 1A was the 0_ 1

20 most appropriate, and as no other parties expressed interest in an expansion of the project, Alternative 1A was deemed the preferred alternative. Q: YOU MENTIONED THE REASONABLY ANTICIPATED TRANSMISSION SYSTEM NEEDS IN THE PROJECT AREA. DID TRI-STATE CONSIDER ANY ALTERNATIVES TO THE PROPOSED PROJECT THAT MIGHT ACCOMMODATE FUTURE TRANSMISSION SYSTEM NEEDS IN THE PROJECT AREA? A: Yes. Tri-State recognizes that other stakeholders may have immediate and longer-term needs in the Project area, so Tri-State reached out in public forums, planning forums, and by solicitation letter that was published in the CCPG venue and was picked up by industry media. None of the responses to the solicitation letter identified any need for increasing the capacity of the Project. Tri-State considered the possibility of constructing the Burlington Lamar transmission line to be capable of kv operation, but operating it initially at kv. Tri-State determined that the relative cost of such construction more than twice the estimated cost of the Project as per Exhibit No. CEP- could not be justified based on Tri-State s present and reasonably anticipated needs. Furthermore, since the transmission systems at either end only include kv infrastructure, the benefits of kv construction cannot be realized without multiple surrounding transmission system improvements that may or may not occur. Tri-State also considered the possibility of installing the proposed singlecircuit kv transmission line on double-circuit structures with the other side of the structure left vacant to accommodate potential future generation. 0_

21 Nevertheless, it was found that the additional cost of such structures would be more than double the original costs. This is an increase that Tri-State cannot justify based on its own needs and without financial participation in the Project by other stakeholders. I discuss Tri-State s efforts and outreach to solicit participation in the Project by other stakeholders in Section VII, below, of my testimony. Q: DID TRI-STATE STUDY THE CAPABILITIES OF THE PROPOSED PROJECT WITH RESPECT TO ACCOMMODATING EXISTING AND FUTURE GENERATION IN THE AREA? A: Yes. Tri-State performed a supplemental study to its post TPL Assessment called Supplemental Study to the Burlington Lamar / kv Impact and 1 Post TPL Assessment Study (Exhibit No. CEP-). This study analyzed potential new generation injection levels after installation of a single-circuit Burlington Lamar kv line. Based on evaluations of varying generation injection levels at Lamar, Tri-State s studies found that the system could accommodate approximately MW of combined generation at the Burlington and Lamar kv buses. The studies also demonstrated that with the new Burlington Lamar kv line, between and MW of generation could remain connected at Lamar following a loss of the Boone Lamar kv transmission line. This is a significant improvement since at present, all generation at Lamar is tripped for the same outage. The exact amount of new generation that could be installed following the Project depends on the manner in which the existing generation portfolio is managed 0_ 1

22 and future load levels. Nevertheless, the Project is certain to provide some level of opportunity for increased renewable generation in the region. Exhibit No. CEP- provides more details. Q: DID TRI-STATE STUDY THE IMPACT OF THE PROPOSED PROJECT ON REGIONAL LOSSES AND CONSIDER ALTERNATIVES THAT COULD FURTHER REDUCE LOSSES IN THE AREA? A: Yes. Tri-State performed the Burlington Lamar kv Losses Evaluation study (Exhibit No. CEP-) to quantify the proposed Project s benefit to regional transmission system losses and to consider alternatives that could potentially reduce losses further. The study found that with the proposed Project installed, area losses would be reduced by 0. MW to MW depending on seasonal loading and generation dispatch conditions. The study also determined that losses could be further reduced by 0. MW if bundled, rather than single, ACSR conductors were used. Unfortunately, 0. MW is a very small improvement considering the bundled-conductor s significantly higher construction costs. All the regional transmission stakeholders, including Tri- State, will benefit from the reduced system losses that single ACSR construction would provide. While bundled-conductor construction could provide even more benefits, given the marginal amount of those benefits, the significant costs, and the absence of participation by other stakeholders in this regard, it was concluded by inspection that the benefits do not justify the additional costs in the context of this Project. Tri-State cannot justify bundled-conductor construction in light of Tri-State s needs. 0_

23 VI. PROPOSED PROJECT Q: PLEASE DESCRIBE THE TRANSMISSION SYSTEM IMPROVEMENTS THAT WILL BE CONSTRUCTED AS PART OF ALTERNATIVE 1A. A: The Project will include a new, single-circuit kv transmission line extending approximately 0-1 miles between the Burlington and Lamar substations. The Project will also entail the installation of certain new equipment in each of the existing substations, which may require their expansion. Further, as discussed in the testimonies of Mr. Lehman and Mr. Myers, a singlecircuit, kv transmission line is typically constructed on a right-of-way 10 feet wide. While Tri-State believes that the Project as proposed will meet its needs into the reasonably foreseeable future, Tri-State is exploring the costs and feasibility of acquiring additional rights-of-way that may facilitate the construction of a second Burlington Lamar transmission circuit should that be necessary in the future. Tri-State intends to pay particular attention during the siting and permitting process to any locations where right-of-way bottlenecks might impair the ability to construct future transmission system improvements between Burlington and Lamar. 1 VII. PROJECT COORDINATION 1 1 Q: DID TRI-STATE SOLICIT INTEREST FROM OTHER TRANSMISSION STAKEHOLDERS FOR PARTICIPATION IN THE PROJECT? A: Yes. On April, 1, Tri-State sent a letter to various transmission owners and operators and to independent transmission companies soliciting their interest in expanding the capacity of the Project. A copy of Tri-State s solicitation letter is 0_

24 attached as Exhibit No. CEP- to my testimony. Tri-State informed the recipients that it was considering a new kv transmission line between the existing Burlington and Lamar substations, and solicited interest from parties who may be interested in expanding the capacity of the Project to accommodate additional needs and purposes. Two stakeholders expressed interest in building the Project for Tri-State; however, no stakeholders expressed an interest in participating to expand the capacity of the Project. Q: DID TRI-STATE COORDINATE THE PROJECT WITH OTHER TRANSMISSION OWNERS, OPERATORS, AND STAKEHOLDERS? A: Yes, this Project has been discussed and coordinated in numerous venues. The need for a new transmission element between Burlington and Lamar has been discussed either explicitly or in the context of the larger Lamar Front Range project in each of Tri-State s public FERC 0 and CO PUC Rule stakeholder outreach meetings since October, including: October 1, ; December, ; January 1, 1; April, 1; August, 1; and November, 1. Further, this Project was either specifically mentioned, or on the list of projects open for discussion at all Colorado Coordinated Planning Group meetings during that time. It has been included in each of Tri-State s list of projects in the WestConnect year reports since. Lastly, it has been posted on Tri- State s webpage of projects since. Stakeholders have had the opportunity to or comment through the webpage directly with Tri-State staff with any concerns, questions, or recommendations. 0_

25 Q: WAS THE PROJECT INCLUDED IN TRI-STATE S 1 TEN-YEAR TRANSMISSION PLAN? A: Yes. I would note, however, that the Burlington Lamar transmission project included in the 1 Ten-Year Plan contemplated construction of a kv transmission line that would be operated initially at kv. For the reasons discussed above, Tri-State has determined that the identified needs can be met appropriately through construction of a single-circuit kv transmission line. Q: WAS THE PROJECT INCLUDED IN TRI-STATE S TEN-YEAR TRANSMISSION PLAN? A: Yes, as an element in the larger Lamar Front Range Transmission Project. In Decision No. R-, the Commission found that Tri-State s Ten-Year Transmission Plan, as part of the Joint Ten-Year Plan coordinated with PSCo and Black Hills Energy, complied with Rule and was adequate for purposes of that rule. Q: IS THE PROJECT CONSISTENT WITH THE COORDINATED TRANSMISSION PLANNING GOALS OF COMMISSION RULE? A: Yes. The Project was developed through an open, transparent, and coordinated process that considered the needs and plans of other transmission owners, operators, and stakeholders, so as to evaluate the possibility of a joint project that could meet the needs of other transmission providers and stakeholders. In developing the Project, Tri-State also actively solicited the input of other transmission system stakeholders and ensured they had a meaningful opportunity to participate in and provide input to the development of the Project. 0_

26 The Project does not negatively impact the system of any other transmission provider or the overall transmission system in the near-term or within the longterm transmission planning horizon. The Project does not duplicate the existing or planned facilities of any other transmission provider. As discussed in greater detail in Tri-State s February 1, 1 Rule filing, the Project, as part of Tri- State s coordinated ten-year transmission plan, contributes to the efficient utilization of the transmission system on a best-cost basis, meets all applicable regulatory criteria, complies with or supports compliance with all legal and regulatory requirements, including Tri-State s renewable electricity standard obligations and resource adequacy requirements, and is consistent with applicable transmission planning requirements under Federal Energy Regulatory Commission Order 0. Q: HOW DOES THE PROJECT COMPLEMENT TRI-STATE S LONGER RANGE PLANS IN EASTERN COLORADO? A: In addition to the near-term load serving, reliability, and generation benefits I have discussed, the Project also complements Tri-State s long-range plans for improvements to the bulk electric system in eastern Colorado. While Tri-State s anticipated resource needs do not justify a project the size of Lamar Front Range, staged elements of the Lamar Front Range project do accommodate more reasonably anticipated resource injection needs. Tri-State has studied various scenarios in eastern Colorado, including increased Lamar injection levels from 0 MW to 0 MW. In each of these scenarios, a new kv transmission element between Burlington and Lamar was a critical first piece 0_

27 of any final build-out. Other elements could include increased transmission between Lamar and Comanche and Burlington and Big Sandy. In summary, the Burlington Lamar kv line aligns with, and is the appropriate first step for most reasonable transmission build-out scenarios for eastern Colorado. Q: WAS THE PROJECT INCLUDED IN TRI-STATE S 1 RULE FILING? A: As a component of the larger Lamar Front Range Project, yes, it was, but as a separate, stand-alone project, it was not individually identified. As discussed previously, the Burlington Lamar transmission line was originally proposed as part of the larger Lamar Front Range Project. The Lamar Front Range Project was included in Tri-State s Rule filing, and in Decision No. C-0, the Commission determined that a CPCN was required for that project. The Lamar Front Range Project was included as an Ongoing Project in Tri-State s 1 Rule filing. Consistent with the Commission s previous Decision and the Commission s CPCN rules, Tri-State is applying for a CPCN for the Burlington Lamar kv Transmission Line Project as a stand-alone project. Q: DOES THIS CONCLUDE YOUR DIRECT TESTIMONY? A: Yes. 0_

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Tri-State December 2013 Board Meeting

Tri-State December 2013 Board Meeting 1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO. STATE OF MINNESOTA Direct Testimony and Schedule OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION Amanda King IN THE MATTER OF THE ROUTE PERMIT APPLICATION FOR THE CAPX00 HAMPTON ROCHESTER

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO.

PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO. PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL 07-100 DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO. 15M- E October 30, 2015 TABLE OF CONTENTS Section Page I. INTRODUCTION...

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

The Development of Competitive Renewable Energy Zones in Texas

The Development of Competitive Renewable Energy Zones in Texas The Development of Competitive Renewable Energy Zones in Texas Warren Lasher Manager, System Assessment 4/23/2008 North American Electric Grids The ERCOT Region is one of 3 NERC grid interconnections.

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO. Direct Testimony and Schedules Grant Stevenson STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION FOR A ROUTE PERMIT FOR THE PLEASANT

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016 Public Service Company of Colorado Transmission Projects Status CCPG May 5, 2016 1 Transmission Ownership Colorado 2016 Transmission Planning Drivers Load Service / Near-Term (1-5 years) TPL Studies (5

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES EXHIBIT JC-2 BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE OCEANVIEW

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

best to you all Gail Carbiener Page 1 of 5

best to you all Gail Carbiener Page 1 of 5 Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects

More information

WestConnect Regional Planning Update

WestConnect Regional Planning Update WestConnect Regional Planning Update WRP Energy Committee May 4, 2015 Webinar Outline WestConnect Overview Membership, Structure & Footprint Planning process and regulatory status Order 890 Update (2014)

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 17-058 LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES Request for Approval of Energy Supply Solicitation and Resulting Rates

More information

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations SPP OVERVIEW Mike Ross Senior Vice President, Government Affairs and Public Relations 1 Our Mission Helping our members work together to keep the lights on today and in the future. 2 NORTH AMERICAN INDEPENDENT

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST MEGAN O REILLY COALITION FOR CLEAN AFFORDABLE ENERGY EPE IRP STAKEHOLDER

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

Docket No EI Date: May 22, 2014

Docket No EI Date: May 22, 2014 Docket No. 140032-EI Big Bend Units 1 through 4 are pulverized coal steam units that currently use distillate oil 2 for start-ups and for flame stabilization. The Company seeks to use natural gas in place

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN-12-1053 OAH DOCKET NO. 60-2500-30782 REBUTTAL TESTIMONY OF RANDALL PORTER, PE SUBMITTED ON BEHALF OF: WIND ON THE

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail Application No. -0- Exhibit PAC/00 Witness: Richard A. Vail BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Investment in Distribution and Transmission Systems April 0 PAC/00

More information

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section 7-207.1 and 7-207.2 APPLICABILITY The Public Service Commission of Maryland ( Commission

More information

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING TUESDAY AUGUST 17, 2010 4:00 PM 8:00 PM CAVAZOS ELEMENTARY SCHOOL CAFETERIA 9301 WEST 16 TH STREET ODESSA, TEXAS

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE APPLICATION FOR A CUSTOMER RELEASE FROM WOODRUFF ELECTRIC COOPERATIVE CORPORATION TO OF PIVOT WELLS BELONGING TO WAYNE WILKISON PREPARED

More information

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which: DATE: July 16,2007 TO: FROM: SUBJECT: CITY COUNCIL CITY MANAGER CONSIDERATION OF ADOPTION OF NEW FEDERAL STANDARDS RELATING TO ELECTRIC UTILITIES UNDER THE PUBLIC UTILITIES REGULATORY POLICIES ACT AND

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Capacity Market Rules for Energy Storage Resources

Capacity Market Rules for Energy Storage Resources Capacity Market Rules for Energy Storage Resources Zachary T Smith Manager, Capacity Market Design ICAPWG August 23 rd, 2018 Agenda Background Energy Storage Resource (ESR) overview Capacity Market Rules

More information

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE In this Section: Overview Evaluation of Initial Requests Rollover Request Competing Request Competing Examples 1.0 OVERVIEW Pursuant to Section 2.2

More information

Proposed New Construction for

Proposed New Construction for Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects

More information

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION The Nevada Hydro Company, Inc. Docket No. EL18-131-000 SOUTHERN CALIFORNIA EDISON COMPANY'S COMMENTS AND PROTEST TO THE NEVADA HYDRO

More information

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES 220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering Credits 18.06:

More information

FILED. IN THE MATfER OF THE APPLICATION OF 1 AND CONSTRUCT A 161 KV TRANSMISSION LINE )

FILED. IN THE MATfER OF THE APPLICATION OF 1 AND CONSTRUCT A 161 KV TRANSMISSION LINE ) BEFORE THE ARKANSAS PUBLlC SERVCE COMMSSON N THE MATfER OF THE APPLCATON OF 1 OKLAHOMA GAS AND ELECTRC COMPANY 1 FOR A CERTFCATE OF PUBLC CONVENENCE ) DOCKET NO. AND NECESSTY TO UPGRADE, OPERATE 1 AND

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

Examinations of Working Places in Metal and Nonmetal Mines. AGENCY: Mine Safety and Health Administration, Labor.

Examinations of Working Places in Metal and Nonmetal Mines. AGENCY: Mine Safety and Health Administration, Labor. This document is scheduled to be published in the Federal Register on 05/22/2017 and available online at https://federalregister.gov/d/2017-10474, and on FDsys.gov 4520.43-P DEPARTMENT OF LABOR Mine Safety

More information

THE TRES AMIGAS PROJECT

THE TRES AMIGAS PROJECT UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,

More information

Department of Market Quality and Renewable Integration November 2016

Department of Market Quality and Renewable Integration November 2016 Energy Imbalance Market March 23 June 3, 216 Available Balancing Capacity Report November 1, 216 California ISO Department of Market Quality and Renewable Integration California ISO i TABLE OF CONTENTS

More information

DEPARTMENT OF TRANSPORTATION. Commercial Driver s License Standards: Application for Exemption; Daimler Trucks North America (Daimler)

DEPARTMENT OF TRANSPORTATION. Commercial Driver s License Standards: Application for Exemption; Daimler Trucks North America (Daimler) This document is scheduled to be published in the Federal Register on 08/17/2017 and available online at https://federalregister.gov/d/2017-17393, and on FDsys.gov DEPARTMENT OF TRANSPORTATION [4910-EX-P]

More information

GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT

GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT 2 What s the Problem? Constrained grid is an issue that impacts many new renewables developments. A quick look at the distribution heat maps published by

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Storage Participation in ) Markets Operated by Regional ) Docket Nos. RM16-23; AD16-20 Transmission Organizations and )

More information

Energy Storage Interconnection Initiative

Energy Storage Interconnection Initiative Energy Storage Interconnection Initiative Stakeholder Call November 25, 2014 Agenda Time Agenda Item Speaker 10:00-10:10 Introduction, Stakeholder Process Tom Cuccia 10:10-10:30 Applying the GIDAP to energy

More information

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets

More information

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications 1. Who is a self-generation or Net Metering Member? This is a Member who has installed grid-connected renewable generation, such

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 1 CPUC Staff Rate Design Proposals Restructure the High-Voltage TAC

More information

Minnesota Public Utilities Commission Staff Briefing Papers

Minnesota Public Utilities Commission Staff Briefing Papers Minnesota Public Utilities Commission Staff Briefing Papers Meeting Date: September 9, 2004................................ Agenda Item # Company: Docket No. Issue(s): Mankato Energy Center IP-6345/CN-03-1884

More information

Eyre Peninsula electricity supply options investigation

Eyre Peninsula electricity supply options investigation 20 November 2017 South Australia s electricity transmission specialist Eyre Peninsula electricity supply options investigation Project Assessment Draft Report Port Lincoln Public Forum electranet.com.au

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By ABN 70 250 995 390 180 Thomas Street, Sydney PO Box A1000 Sydney South NSW 1235 Australia T (02) 9284 3000 F (02) 9284 3456 18/10/2018 Mr Peter Adams General Manager, Wholesale Markets Australian Energy

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

February 13, Docket No. ER ; ER Response to Request for Additional Information

February 13, Docket No. ER ; ER Response to Request for Additional Information California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re : : Docket No. SB-00-0 () : Testimony of David M. Campilii, P.E. June, 00 PROV-- 0 0 TESTIMONY OF DAVID M. CAMPILII,

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information