Considerations Regarding the Reconductoring Opportunity Analysis of 220 kv OHL D.C. Porţile de Fier Reşiţa

Size: px
Start display at page:

Download "Considerations Regarding the Reconductoring Opportunity Analysis of 220 kv OHL D.C. Porţile de Fier Reşiţa"

Transcription

1 Considerations Regarding the Reconductoring Opportunity Analysis of 220 kv OHL D.C. Porţile de Fier I. Ardelean, N. Chiosa, B. Sinca and M. Mihai Abstract-- This paper is a study case for considering whether reconductoring of OHL 220 kv dc Porţile de Fier - Resita, in order to reduce energy losses (CPT). Although this line has the largest contribution to total energy losses of ST Timisoara outline, reconductoring not prove a feasible solution in anticipation of transition to 400 kv of Portile de Fier - Resita - Timisoara - Arad axis and building a new 400 kv interconnection line with Serbia, Resita - Pancevo. Index Terms-- overhead electricity line, electricity system, uprating, HTLS, the maximum allowable current, increasing transport capacity, reconductoring. I. NOMENCLATURE HTLS high temperature low sag LEA d.c. double circuit overhead electricity line SEE electro-energetic power system CHE hydroelectric power plant CEE wind power plant CPT own technological consumption ATR technical advice for connection CTES Economic and Scientific-Technical Commission (of approval in Transelectrica) II. INTRODUCTION HL 220 kv d.c. Portile de Fier - Resita is the only power O evacuation line of 220 kv from Portile de Fier 1 node, this beeing accomplished towards the west of the country. Portile de Fier 1 node is a very strong node, with power surplus, having a local production of more than 1000 MW, which collects the surplus power from the CHE Portile de Fier 2 area, approx. 200 MW and CET Halânga, approx. 150 MW. At this junction, the power groups are connected at the voltage of 220 kv, into a with double bus-bar system and transfer bus-bar, recently repaired. OHL 220 kv d.c. Portile de Fier - Resita is built on metallic, double circuit posts (422 posts) and was completely repaired during the This is the most loaded line between those in the management of ST Timisoara and has the largest contribution to total energy losses in branch s outline. The maximum dr.ing. Ilie ARDELEAN, dr.ing. Nicolae CHIOSA, ing. Bogdan SINCA, ing. Marian MIHAI - CNTEE Transelectrica S.A. Timişoara Transport Branch transport capacity of this line is about 600 MW, required by the static stability criteria. In 2008 it commenced the transition to 400 kv Portile de Fier - Resita - Timisoara Arad axis, in conjunction with building a new 400 kv OHL interconnection with Serbia. In the year 2008, Fichtner Engineering SA prepared and CTES Transelectrica approved, an SPF seeking to achieve the two objectives above. After taking those steps, a potential investor, Wind A3 Eolica Trade Bucharest, asked Transelectrica a technical issue opinion of connection to system (ATR), for an EEC 600 MW, located in the Socol. This request requires a new analysis of SPF aforementioned solutions and hence delay the action started in In this context, S.T. Timisoara management called Technical Service to make an analysis on OHL 220 kv d.c. Portile de Fier Resita reconductoring, in order to reduce energy losses (CPT) and increase its transport capacity [2]. III. LOCATION AND CONSTRUCTIVE CHARACTERISTICS OF THE LINE 220 kv OHL Portile de Fier - Resita route crosses almost the entire length a hill region. From Portile de Fier Power Station the line follows a N-NW direction, crossing in 1-2 opening DN 6 and electrified Drobeta Turnu Severin Orsova railroad, overcome Verbunului peak and cross Slatinicului, Vodiţa and Bahnei valleys. Next, line route cross Baldovin top, Balabanului peak, Predediul Mic and Padesului peaks and after Stragierul hill go down the Cerna Valley near the confluence with the river Belareca. In the opening 39 to 40, OHL crosses DC Bahna - Ilovita. In the opening 92 to 93 the line crosses the river Cerna. In the opening the OHL cross DN 67 Orsova - Tg. Jiu. In the opening 96 to 97 the line crosses DJ towards Băile Herculane and Belareca river, and in openings and crosses again Belareca river. Further, it aims Belareca valley to S of Mehadia, which passes east, continuing to Plugova village. North of Plugova, the line crosses the Belareca river in 149 to 150 opening and enter into the hill zone, in the area of Cornea, Domaşnea, Feneş şi Sat Bătrân villages. Next line bound for NV, across the opening 277 to 278 crosses electrified railroad Slatina-Timiş Caransebes, in the opening crosses DN 6 and the opening 279 to 280 passes across the Timis river. North of S Slatina-Timiş, the line bound for Bucoşniţa and Petroşniţa villages keeping N direction to Prisian village. It continue to NW by Rugi village, then west to Delineşti. Passes near 24

2 Apadia, heading the direction of SV to Tarnova, after that entering the 220 kv Resita. The line was build under the ISPE design project no. 6727/1968, based on LI 1 67 norm. Calculation parameters considered when designing the line, are Meteorological area 2 nd ; t max. +40[ C] t min. -30[ C] t frost formation -5[ C] wind max. 40[m/s] wind + frost 20[m/s] frost thickness 25[mm] Constructive characteristics of the line are: putting into operation year 1971 line length 116,5 km total no. of posts 428 pcs. active wire Al/Ol 2x(3x450/75) mm 2 protection wire OPGW 160/95 mm and posts, OPGW 95 mm posts, Al/Ol 1x450/75 mm posts, OlZn 1x95 mm şi posts; insulation CTS 120-2p şi posts, composite 1-89 şi posts. IV. IMPORTANT OFFICIAL EVENTS JOURNAL 1971 replacing IN post from 212 terminal, with a pole type ICN , which due to heavy frost deposits led to deformation of the lower segment of the pole; 1978 protection wire ALOLS 160/95 mm 2, was replaced with a 95 mm 2 conductor type OLZn between posts, due to inadequate reaction to mechanical loads; 1980 due to landslides in the pillar 32 area, it was moved 45 m in line to the terminal 33 and the existing pole was replaced with a pole type Sc sc - M1; due to landslides in the pillar 154 area, a modified route was done; K3 insulation type was replaced with CTS 120-2p and PSG 12 A type insulation; 1985 after heavy frost deposits the active conductor was deteriorated and was replaced in panel , S-phase; 1993 due to mechanical overload, top-cap of pillar 25 broke, being replaced; 1995 due to mechanical overload, thrusts console terminal 237, phase T was strengthend. V. RECONDUCTORING SOLUTIONS AND TYPES OF CONDUCTORS USED Replacing conductors is one of the most common techniques for increasing the carrying capacity of the OHL. Different variants are possible, consisting of installing a conductor or a bundle of conductors, having a larger transport capacity and, if possible, with a higher ratio H/w (obtained by increasing horizontal pressure into conductor, or by decreasing conductor unit weight). There are two possible approaches: replacing existing conductors with new ones, all conventional, but with a larger section and/or higher conductivity, which operate at the same temperature, or compact conductors having a higher cross-section, but without increasing the beam diameter exposed to the wind; replacing existing conductors with special conductive HTLS (High Temperature Low Sag), capable of operating at higher temperatures without increasing the arrows, with a lower thermal expansion coefficient. There are many types of HTLS conductors that can be used to increase the transmission capacity of an OHL. Choosing the most appropriate type for specific cases, depends on initial conditions for sizing the line. Overhead power lines in Romania with rated voltage of 220 kv are equipped, with few exceptions, with Al/Ol 450/75 mm 2 conductors, one conductor per phase. The inclusion of Romania in the European transport network, on the one hand and the implementation of wind turbines in large groups on the other hand, involves the growth of transport capacity in some lines, forced to evacuate or to carry power over existing capacity. Table 1 shows both the type of conductor used in fitting conventional overhead power lines and conductors with increased transmission capacity, achieved through optimization of the geometry, the use of new materials, or by increasing the operating temperature of the conductor [5], [6] [7], [8]. Maximum capacity of transport for non-conventional conductors, is reported at the conventional type ACSR conductor, whose capacity is considered 100 [%]. Addressing increasing transport capacity is different from new lines to existing lines. at new lines, increasing transport capacity is made either by increasing the aluminum section or by increasing the number of conductors beam. There are also possible some solutions fitting the line with HTLS conductors, optimal approach beeing based on technical-economic analysis; for existing lines, increasing the transmission capacity can be achieved successfully at present, through the process of uprating. Uprating means increased transport capacity of the OHL, by increasing the current or voltage, or by increasing the values of both sizes [1]. Increase current value is achieved either by increasing the temperature of existing conductors or by replacing them with new ones, capable of operating at high temperatures. Increasing the amount of voltage involves increasing the insulation level of the OHL (corresponding to a new stage of voltage), increasing the distances between phases and ground gauge. On existing lines, when reconductoring using unconventional conductive type HTLS, in order to maintain safety in its operation, there must be followed the next restrictions: the new conductor diameter must be less than or equal to the existing conductor (29.25 mm); maximal horizontal thrust for new conductor, must not exceed the existing one (Tmax = 5362 dan), in order to reduce the impact on the pillars and foundations; The final arrow of the new conductor, at the maximum operating temperature should be limited to the final arrow for the existing ACSR conductor 450/75 type; breaking force for the new conductor, must be greater or at least equal to that of the existing conductor AlOl 450/75 mm 2 type; 25

3 electrical distances must be maintained. S.C. Fichtner Engineering S.A developed for C.N. "Transelectrica" SA a SF phase documentation regarding the 220 kv d.c. OHL Bucuresti Sud-Fundeni reconductoring and 220 kv d.c. OHL Lacul Sărat-Fileşti-Barboşi Focşani [3],[4]. Calculation of the carrying capacity of conductors was carried out with a design and verification software PLS-CADD for overhead power lines. This program is widely used worldwide, the calculation of the maximum allowable current is in accordance with IEEE Std After technical and economic analysis, was proposed for reconductoring ACSS conductor type [3]. Inside S.T. Timişoara, due to absence of dedicated software for performing such technical-economic analisys, we did consider the opportunity of reconductoring the 220 kv d.c. OHL Porţile de Fier [2], taking into account the ACSS conductor type, proposed by Fichtner Engineering in SF study on the 220 kv OHL Bucuresti- Fundeni reconductoring [3]. Hypothesis is correct because both lines were designed under the same regulatory, LI TABLE I Characteristics No. Conductor type Material View Temperature [ C] Max. transport capacity [% from ACSR] 1 ACSR Al + Steel 75 C 100% 2 ACSR/ACS Al + ACS 75 C 107% 3 SLAC/ACS Al + SBAl + ACS 113% 4 ACSR/TW TW + ACS/St 115% 5 AeroZ ZW + ACS/steel 75 C 116% 6 TACSR/AS TAl + ACS 150 C 150% 7 60% ZTACIR/ACS ZTAl + IR (ACS) 8 58% ZTACIR/ACS 9 XTACIR/ACS XTAl + IR(AS) 230 C 200% 10 60% ZTACEIR/ACS 11 58% ZTACEIR/ACS SBZTAl / IR (AS) 230 C 200% 12 XTACEIR/ACS SBXTAl / IR(AS) 230 C 200% 13 GTACSR TAl + TZ + EST 150 C 150% 14 GZTACSR ZTAl + TZ + EST 120 C 180% 15 ACCC Al (1350) + Composite 200 C 150% (without structure change) 16 3 M ACCR Al+Zr melt, + Composite 210 C 200% 17 ACSS Al (1350) + steel 250 C 200% VI. CALCULATION OF ENERGY LOSSES (CPT) For calculation of lost energy for 220 kv OHL Portile de Fier-Resita, for a comparative analysis between the situation with conductors OlAl 450/75 mm 2 and the variant of equipping it with ACSS type conductors, were considered following simplifying assumptions [2]: there will be taken into account only the losses by Joule effect, others are neglected; it is considered a constant voltage i.e. 220 kv on the line (neglecting the voltage drop between the ends of the line); line resistance at ambient temperature of 20 C (neglecting the resistance change with conductors temperature, and also with the load and weather conditions) 26

4 Analysis of energy losses for 220 kv d.c. OHL Portile de Fier-Resita, was made for one year respectively September 2008-August As input data were used: active and reactive energy measured monthly in Portile de Fier, active and reactive energy measured monthly in Resita, the maximum active and reactive powers. For comparison was retained the average energy losses calculated with measured quantities of end s. Calculation relations used are: 2 S med ΔW a =R T 2 U where: ΔW a - active power losses, R line resistance, T operating time, U line voltage, S med average apparent power. W 2 2 a + Wr S med = T where: W a active energy, W r reactive energy For the same line load, for all types of conductors, energy losses amount depends on the value of resistance of conductors. In Table 2 are presented energy losses calculated for the circuit 1 of the 220 kv d.c. OHL Portile de Fier-Resita, in the existing situation and in the variant of reconductoring. In Table 3 are the same calculations for circuit 2, and in Table 4 are presented cumulative losses on the two circuits. TABLE II Calculated ACSR existing conductor ACSS proposed conductor losses [MWh] Month, ΔWa ΔWa ΔWa ΔWa ΔWa ΔWa Year average average September October November December January February March April May June July August TOTAL Calculated losses [MWh] TABLE III ACSR - existing conductor ACSS - proposed conductor P. de Fier ΔWa ΔWa ΔWa ΔWa ΔWa ΔWa Month, Year calculated calculated average calculated calculated average September October November December January February March April May June July August TOTAL

5 TABLE IV Calculated ACSR - existing conductor ACSS - proposed conductor losses [MWh] Month, ΔWa ΔWa ΔWa ΔWa ΔWa ΔWa Year calculated calculated average calculated calculated average September October November December January February March April May June July August TOTAL VII. ECONOMIC ANALYSIS Economic analysis refers to the calculation efficiency of reconductoring action upon 220 kv d.c. OHL Portile de Fier- Resita, that the length of payback. There are estimated direct total costs and annual cost of lost energy. VII.1 DIRECT TOTAL COST Direct total costs C C+M, result from the estimating the following categories of expenses: C P - the direct cost of purchasing the conductors and their accessories C i - cost of labor for installation of conductors and accessories C m - cost of maintenance, after mounting the conductors on the line Therefore: C C+M = C P + C i + C m Note that C P and C i are costs made in the new conductor installation year, and C m are annual maintenance costs. This last ones costs C m, beeing approximately equal to the existing ACSR conductor and new ACSS conductor, were not considered. Evaluation of total direct costs was done with average prices [euro/km] used by Fichtner in SF study regarding reconductoring 220 kv d.c. OHL Bucureşti Sud- Fundeni [3]. In Fig. 1 are shown the costs to purchase the conductor and in Fig. 2 are given installation labor costs. Using specific costs shown in Fig. 1 and Fig. 2, for reconductoring 220 kv d.c. OHL Portile de Fier- Resita, result the following charges: conductor procurement costs x (116, ,5) = euro cost for installing the conductor 3000 x (116, ,5) = euro total direct costs = euro Costul procurării Euro/ (km si circuit) ACSS ZTACIR GZTACSR ACCR ACCC/TW Conductor Fig. 1 Costul instalării (Euro/km) ACSS ZTACIR GZTACSR ACCR ACCC/TW Conductor Fig.2 VII.2 ANNUAL COST OF ELECTRICITY LOSSES Now, to cover energy losses (CPT) in RET, Transelectrica buy energy at a rate imposed by ANRE, 250 lei/mwh. At a rate of 4,15 lei/euro, results a fee for lost power at 60,24 euro/mwh. By reconductoring energy losses became lower, in accordance with Table 4, from ,40 MWh/year at ,69 MWh/year, i.e ,71 MWh/year. In cost terms, this economy means: 2 195,71 x 60,24 = euro/year. Length of payback time for reconductoring, only by the bases of difference of losses, is: 28

6 : = 53 years VIII. CONCLUSIONS kv d.c. OHL Porţile de Fier reconductoring, designed only to reduce energy losses, is not a feasible solution, the payback period of the investment beeing very high; kv d.c. OHL Porţile de Fier reconductoring in order to increase transport capacity and reduce energy losses would be a feasible solution if switching to 400 kv voltage of Porţile de Fier Timişoara Arad axis would be a long distance perspective; 3. According to SF Upgrading 220 kv d.c. OHL Bucuresti Sud Fundeni and strengthen it by using conductors with larger capacity, reconductoring has maximum efficiency at OHL with lengths of up to 50 km because of voltage losses; 4. ACSS conductor, to the other conductors with increased load capacity, has the advantage of the lowest direct costs (procurement + installation + maintenance); 5. ACSS conductorul to ACSR conductor has also an environmental advantage, in that of having a smaller diameter, the visual impact is lower. IX. REFERENCES 1. Propunere privind reconductorarea lea 220 kv Iernut-Baia Mare 3, utilizând tehnologii de LST,., Florea G., Oltean M., Mateescu E., Mărginean D., Kilyeni S., Bărbulescu C; [1] Ardelean I et.all. Propunere privind reconductorarea lea 220 kv Iernut- Baia Mare 3, utilizând tehnologii de LST. [2] Ardelean I., Şinca B., Mihai M., Notă tehnică privind analiza oportunităţii de reconductorare a LEA 220 kv d.c. Porţile de Fier. Serviciul Tehnic, S.T. Timişoara, oct. 2009; [3] ***, Modernizarea LEA 220 kv d.c. Bucuresti Sud Fundeni şi întărirea acesteia prin utilizarea de conductoare cu capacitate mărită, Studiu de Fezabilitate elaborat de S.C. Fichtner Engineering S.A. pentru C.N. Transelectrica S.A; [4] ***, Reconductorarea LEA 220 kv d.c. Lacul Sărat - Fileşti-Barboşi Focşani, Studiu de Fezabilitate elaborat de S.C. Fichtner Engineering S.A. pentru C.N. Transelectrica S.A; [5] ***, Conductors for the Uprating of Overhead Lines, WG B2.12, CIGRE, Technical Brochure No. 244, April 2004; [6] Peter Reichmeider et.all. Experience With New Methods For Live-Line Conductor Replacement, CIGRE 2008; [7] ***, How on lines are re-designed for uprating/ upgrading, WG B2.06, CIGRE, Technical Brochure No. 294, June 2006; [8] ***, Conductors for the Uprating of Overhead Lines, WG B2.12, CIGRE Technical Brochure No. 244, April

Increasing the transport capacity of 220 kv DC OHL iernut-baia mare by reconductoring using LW technologies

Increasing the transport capacity of 220 kv DC OHL iernut-baia mare by reconductoring using LW technologies Increasing the transport capacity of 220 kv DC OHL iernut-baia mare by reconductoring using LW technologies Ilie Ardelean / CN TRANSELECTRICA S.A ; Marius Oltean / SC SMART S.A. SIBIU BRANCH; George Florea

More information

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS NORTH AUCKLAND AND NORTHLAND GRID UPGRADE PROJECT ATTACHMENT J OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS UPGRADE WITH HIGH TEMPERATURE LOW SAG CONDUCTOR September 2007 Contents 1 INTRODUCTION

More information

High-Temperature Low Sag (HTLS) conductors. for easy Upgrading of Overhead Transmission Lines

High-Temperature Low Sag (HTLS) conductors. for easy Upgrading of Overhead Transmission Lines Gap-type conductor High-Temperature Low Sag (HTLS) conductors for easy Upgrading of Overhead Transmission Lines J-Power Systems (JPS) is a joint-venture of HITACHI CABLE and SUMITOMO ELECTRIC INDUSTRIES

More information

Line using HTLS Conductors to increase

Line using HTLS Conductors to increase Upgradation of 132kV Transmission Line using HTLS Conductors to increase the load transfer capacity. By Srikrushna S. Navlakhe Executive Engineer, EHV Construction cum Operation and Maintenance Zone, MSETCL,

More information

Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad

Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad ENHANCEMENT OF POWER TRANSFER CAPABILITY OF TRANSMISSION LINES USING HTLS CONDUCTOR 1 M.SHESHAGIRI, 2 B.V.SANKER RAM Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad

More information

Enhancement of Power Transfer Capability of Existing 400kV Transmission Lines

Enhancement of Power Transfer Capability of Existing 400kV Transmission Lines 558 NATIONAL POWER SYSTEMS CONFERENCE, NPSC 22 Enhancement of Power Transfer Capability of Existing 4kV Transmission Lines Rajiv Gandhi, Anish Anand, Y. K. Sehgal, M. Krishnakumar and Anand Mohan Abstract--The

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

NEW TREND ON TRANSMISSION POWER LINES AND RELATED STRINGING EQUIPMENT DEVELOPMENT

NEW TREND ON TRANSMISSION POWER LINES AND RELATED STRINGING EQUIPMENT DEVELOPMENT NEW TREND ON TRANSMISSION POWER LINES AND RELATED STRINGING EQUIPMENT DEVELOPMENT Background Several regions of the world are facing severe pressure on transmission line infrastructure, while the trends

More information

How the choice of transmission conductor can reduce greenhouse gas emissions.

How the choice of transmission conductor can reduce greenhouse gas emissions. How the choice of transmission conductor can reduce greenhouse gas emissions. What is the scope of the impact? Complete conversion of the US grid to efficient conductor would eliminate 44 million metric

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Romania Industry structure

Romania Industry structure Country Profiles 2.4.26 Romania 2.4.26.1 Industry structure Romania was among the first few southeast European countries to initiate power sector reforms in the late 1990s as the country negotiated its

More information

CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT. September 4, 2018

CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT. September 4, 2018 CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT September 4, 2018 TODAY S DISCUSSION Understanding impact Rate considerations for residential connections Next steps Seeking direction and feedback, NO

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

D G A G R I D A S H B O A R D : A P P L E S

D G A G R I D A S H B O A R D : A P P L E S 75 79 60 56 49 74 65 59 54 42 76 63 58 53 78 55 42 43 79 44 81 63 47 83 64 59 53 48 Sources: Eurostat, MSs notifications, DG Agri, Comext, Comtrade, GTA, ITC, AMI, Expert groups, Freshfel, Wapa. 89 68

More information

VII THE EXPANSION OF ITALIAN COMPANIES IN THE EMERGING MARKETS FOR PV. TURNOVER & MARGINS CONSIDERATIONS

VII THE EXPANSION OF ITALIAN COMPANIES IN THE EMERGING MARKETS FOR PV. TURNOVER & MARGINS CONSIDERATIONS Session VII THE EXPANSION OF ITALIAN COMPANIES IN THE EMERGING MARKETS FOR PV. TURNOVER & MARGINS CONSIDERATIONS. SUITABLE BUSINESS MODELS TO PUT IN PLACE CASE STUDY: GREECE Paolo Ricci, Managing Director,

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

OPTIMISATION OF ELECTRIC POWER CONSUMPTION BY REHABILITATING THE COMPRESSOR STATIONS

OPTIMISATION OF ELECTRIC POWER CONSUMPTION BY REHABILITATING THE COMPRESSOR STATIONS 6 th INTERNATIONAL MULTIDISCIPLINARY CONFERENCE OPTIMISATION OF ELECTRIC POWER CONSUMPTION BY REHABILITATING THE COMPRESSOR STATIONS Ing. Ştefan Troacă, CNH Petroşani Ing. Daniel Surulescu, CNH Petroşani

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector HVDC Innovative Technology for Smart Grids and Super Grids CEO Power Transmission Solutions, Siemens Energy Sector BritNed: Pre-launch Press Event Maasvlakte, March 31, 2011 Siemens AG 2011 Energy Sector

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 10, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

RFP No. P3010 New l.i ght Rail Vehicles

RFP No. P3010 New l.i ght Rail Vehicles rr Los Angeles County Metropolitan Transportation Authority RFP No. P3010 New l.i ght Rail Vehicles Source Selection Committee Award Recommendation Light Rail Transit Project Requirements end P30i 0 Delivery

More information

Technical Series, Edition 16

Technical Series, Edition 16 Totally Integrated Power Technical Series, Edition 16 Transformer Selection according to Utilisation Profiles siemens.com/tip-cs 1. Regulations concerning efficiency requirements of dry-type transformers

More information

Solar Power. Demonstration Site. Annual Performance Report 2017

Solar Power. Demonstration Site. Annual Performance Report 2017 Solar Power Demonstration Site Annual Performance Report 217 Version :1. July 12, 218 Solar Power Demonstration Site 217 Performance Report Introduction INTRODUCTION The Solar Power Demonstration Site

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

Efficiency, Capacity, Reliability AND Cost-Effective Carbon Reductions: The Multiple Benefits of High Performance Transmission Conductors (HPTC)

Efficiency, Capacity, Reliability AND Cost-Effective Carbon Reductions: The Multiple Benefits of High Performance Transmission Conductors (HPTC) Efficiency, Capacity, Reliability AND Cost-Effective Carbon Reductions: The Multiple Benefits of High Performance Transmission Conductors (HPTC) WHY ARE WE HERE? The Transmission System: The Backbone of

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

National Seminar on New Generation High Performance Conductors. 4 th Dec 14

National Seminar on New Generation High Performance Conductors. 4 th Dec 14 National Seminar on New Generation High Performance Conductors 4 th Dec 14 Compulsion for alternative why? Limitation of power flow New line ROW Constraint Increasing urbanization left no inlet for critical

More information

Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4 Stroke Engine

Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4 Stroke Engine IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 08, 2015 ISSN (online): 2321-0613 Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4

More information

Timisoara Pilot Applications - Test objectives, methodology and results-

Timisoara Pilot Applications - Test objectives, methodology and results- Timisoara Pilot Applications - Test objectives, methodology and results- Integral Consulting R&D SNTFC CFR Calatori S.S Regionala de Transport Feroviar de Călători Timişoara General presentation of Timisoara

More information

Electrical Power Distribution (CDEE)

Electrical Power Distribution (CDEE) Lecturer: Ing. Martin Paar, Ph.D. paar@feec.vutbr.cz,www.ueen.feec.vutbr.cz Transmission and distribution networks in the Czech Republic Electrical Power Distribution (CDEE) e-power - Inovace výuky elektroenergetiky

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven 26.11.09 Electric grid on and off-shore: current status, obstacles and new developments November 26, 2009 Slide 1 Transmission grid The challenges Optimal

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

An Approach for Formation of Voltage Control Areas based on Voltage Stability Criterion

An Approach for Formation of Voltage Control Areas based on Voltage Stability Criterion 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 636 An Approach for Formation of Voltage Control Areas d on Voltage Stability Criterion Dushyant Juneja, Student Member, IEEE, Manish Prasad,

More information

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective 2 Storage: the DNO perspective Context to the storage boom Smarter Network Storage: What have we achieved?

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Proposed Dounreay - Mybster 275 kv / 132 kv

Proposed Dounreay - Mybster 275 kv / 132 kv Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Presented by Eric Englert Puget Sound Energy September 11, 2002

Presented by Eric Englert Puget Sound Energy September 11, 2002 Results from PSE s First Year of Time of Use Program Presented by Eric Englert Puget Sound Energy September 11, 2002 Puget Sound Energy Overview 973,489 Total Electric Customers 908,949 are AMR Capable

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

3 Existing National Grid

3 Existing National Grid 3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

THE TRES AMIGAS PROJECT

THE TRES AMIGAS PROJECT UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,

More information

Final Written Examination.

Final Written Examination. Benha University Semester (3 th year Power &Control) Faculty of Engineering Electrical Power Systems (E1331) Electrical Engineering Department Semester 2015-2016 Final Written Examination. 10/1/2016 Time

More information

Yukon Resource Gateway Project

Yukon Resource Gateway Project Yukon Resource Gateway Project Summary Application for National Infrastructure Component Funding January 2016 Introduction The Government of Yukon is seeking endorsement of the Yukon Resource Gateway

More information

Impact of Distributed Energy Resources on Transmission System Reliability

Impact of Distributed Energy Resources on Transmission System Reliability S E P T E M B E R 1 3, 2 0 1 8 W E B I N A R Impact of Distributed Energy Resources on Transmission System Reliability National Council on Electricity Policy (NCEP) Alan McBride D I R E C T O R, T R A

More information

Contact person: Pablo Taboada Mobile:

Contact person: Pablo Taboada   Mobile: Contact person: Pablo Taboada e-mail: ptaboada@aenor.es Mobile: 34 609015450 Génova 6 28004 Madrid. Spain Phone: 34 91 4326004 Fax: 34 91 3190581 CDM Executive Board RESPONSE TO REQUEST FOR REVIEW Request

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng Smarter Network Storage UK first multi-purpose application of grid scale storage Dr. Panos Papadopoulos, PhD, CEng UK Power Networks GENERATION TRANSMISSION DISTRIBUTION SUPPLY INDUSTRIAL COMMERCIAL RESIDENTIAL

More information

JSC ELECTRICITY SYSTEM COMMERTIAL OPERATOR ACTIVITY REPORT YEAR 2016

JSC ELECTRICITY SYSTEM COMMERTIAL OPERATOR ACTIVITY REPORT YEAR 2016 JSC ELECTRICITY SYSTEM COMMERTIAL OPERATOR ACTIVITY REPORT YEAR 2016 BALANCING ELECTRICITY TRADE GUARANTEED CAPACITY TRADE ELECTRICITY IMPORT AND EXPORT SUPPORT OF CONSTRUCTION OF NEW HYDRO POWER PLANTS

More information

Pump Station 7 Improvements

Pump Station 7 Improvements Project Business Case ID: C04 2/18/2017 Pump Station 7 Project Purpose: The purpose of this project is to ensure that Pump Station 7 continues to operate in an efficient and effective manner following

More information

REPORT ON POWER FLOWS IN THE TRANSMISSION SYSTEM OF BOSNIA AND HERZEGOVINA IN 2016

REPORT ON POWER FLOWS IN THE TRANSMISSION SYSTEM OF BOSNIA AND HERZEGOVINA IN 2016 Nezavisni operator sistema u Bosni i Hercegovini Независни оператор система у Босни и Херцеговини Neovisni operator sustava u Bosni i Hercegovini Independent System Operator in Bosnia and Herzegovina REPORT

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

3M Gridlines Updates on 3M ACCR

3M Gridlines Updates on 3M ACCR 3M Aluminum Conductor Composite Reinforced 3M Gridlines Updates on 3M ACCR Download the new 3M data FREE by clicking here. PLS-CADD data files on 3M ACCR now available Users of PLS-CADD design software

More information

Indicative Gas Transportation Charges from 1 April 2012 for East of England, London, North West and West Midlands Distribution Networks

Indicative Gas Transportation Charges from 1 April 2012 for East of England, London, North West and West Midlands Distribution Networks National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA National Gas Emergency Service - 0800 111 999* (24hrs) *calls will be recorded and may be monitored Indicative Gas Transportation

More information

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017 ELECTRIC SERVICE RATE SCHEDULES Effective November 1, 2017 SCHEDULE 100 RESIDENTIAL SERVICE Residential Customers for all domestic uses. CHARACTER OF SERVICE: Alternating current, sixty-hertz 120/240 volts

More information

ILLINOIS COMMERCE COMMISSION

ILLINOIS COMMERCE COMMISSION ILLINOIS COMMERCE COMMISSION Public Notice of Successful Bidders and Average Prices Ameren Illinois Company and Commonwealth Edison Company Spring 2015 Procurement of Standard Energy Products April 1,

More information

Protecting. Grid. Integrity. More amps, more confidence. 3M Aluminum Conductor Composite Reinforced (ACCR) High-capacity transmission conductor

Protecting. Grid. Integrity. More amps, more confidence. 3M Aluminum Conductor Composite Reinforced (ACCR) High-capacity transmission conductor 3M Aluminum Conductor Composite Reinforced (ACCR) High-capacity transmission conductor Metric Units Protecting Grid Integrity More amps, more confidence 3 3M Aluminum Conductor Composite Reinforced In

More information

ANNUAL REPORT ON POWER FLOWS IN THE TRANSMISSION SYSTEM OF BOSNIA AND HERZEGOVINA IN 2015

ANNUAL REPORT ON POWER FLOWS IN THE TRANSMISSION SYSTEM OF BOSNIA AND HERZEGOVINA IN 2015 Nezavisni operator sistema u Bosni i Hercegovini Независни оператор система у Босни и Херцеговини Neovisni operator sustava u Bosni i Hercegovini Independent System Operator in Bosnia and Herzegovina ANNUAL

More information

Department of Market Quality and Renewable Integration November 2016

Department of Market Quality and Renewable Integration November 2016 Energy Imbalance Market March 23 June 3, 216 Available Balancing Capacity Report November 1, 216 California ISO Department of Market Quality and Renewable Integration California ISO i TABLE OF CONTENTS

More information

Inventory Levels - All Prices. Inventory Levels - By Price Range

Inventory Levels - All Prices. Inventory Levels - By Price Range Inventory Levels - All Prices Idaho Falls Bonneville Total 3-Nov-17 198 128 326 2-Nov-18 155 134 289-11% Inventory Levels - By Price Range 3-Nov-17 2-Nov-18 0-100,000 17 11 100,001-125,000 15 9 125,001-150,000

More information

STATE OF NEW HAMPSHIRE Inter-Department Communication

STATE OF NEW HAMPSHIRE Inter-Department Communication STATE OF NEW HAMPSHIRE Inter-Department Communication DATE: February 11, 2010 AT (OFFICE): NHPUC FROM: Torn Frantz Director, Electric Division SUBJECT: DE 09-277: Petition by Public Service Company of

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Scarborough Transit Planning

Scarborough Transit Planning Scarborough Transit Planning April 23, 2016 Transportation Planning Section City Planning Division Overview 1. Developing Toronto s Transit Network Plan 2. Scarborough Transit Planning 1. Minutes of last

More information

Water Consumption Statistics Report

Water Consumption Statistics Report Water Consumption Statistics Report Operations and Maintenance Department 29 Edition TABLE OF CONTENTS 29 Water Consumption Statistics Report October 21 SYSTEM AND MUNICIPAL CONSUMPTION 29 GVWD Statistics

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Bus Stop Optimization Study

Bus Stop Optimization Study Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:

More information

New Power Market Model. Activities towards market integration in compliance with the New European Legislation

New Power Market Model. Activities towards market integration in compliance with the New European Legislation New Power Market Model. Activities towards market integration in compliance with the New European Legislation 30-31 May 2012, Thessaloniki Content Bulgarian Power System. Basic Statistical Data New Energy

More information

Michigan Thumb Loop Transmission Line Project

Michigan Thumb Loop Transmission Line Project Michigan Thumb Loop Transmission Line Project ITC Holdings Corp. Simon Whitelocke VP., Regulatory and External Affairs October 30, 2013 What is Transmission? The electric transmission system is the network

More information

D G A G R I D A S H B O A R D : A P P L E S

D G A G R I D A S H B O A R D : A P P L E S Sources: Eurostat, MSs notifications, DG Agri, Comext, Comtrade, GTA, ITC, AMI, Expert groups, Freshfel, Wapa. 000 tonnes 39 41 31 22 29 22 32 27 17 18 9 27 15 12 6 6 6 4 5 6 5 4 11 25 15 9 9 93 62 51

More information

Geneva, 67th SC.2 Session October 2013 High Speed Trains Master Plan

Geneva, 67th SC.2 Session October 2013 High Speed Trains Master Plan Geneva, 67th SC.2 Session 23 25 October 2013 High Speed Trains Master Plan Work Package I Work Package II Work Package III Project Management Review of related Work Socio economic framework of the ECE

More information

PET(S) FIRST & LAST NAME: January 2019

PET(S) FIRST & LAST NAME: January 2019 January 2019 1 2 3 4 5 New Year's Day 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 SPECIAL TE We will not have Doggie available during these dates: *3/29-4/7, 4/19-4/21, 5/24-5/27,

More information

New Jersey Solar Roundtable

New Jersey Solar Roundtable New Jersey Solar Roundtable Transition to a Market-based REC Financing System Scott Hunter, Renewable Energy Program Administrator NJBPU, Office of Clean Energy Presented at New Jersey Institute of Technology

More information

Chirmorie Wind Farm Grid Connection

Chirmorie Wind Farm Grid Connection Chirmorie Wind Farm Grid Connection Welcome Welcome to this public exhibition regarding our proposals to construct a new 132 kilovolt (kv) overhead line (OHL) supported by wood poles to connect the proposed

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks D. M. Nobre W. L. A. Neves B. A. de Souza Departamento de Engenharia Elétrica - UFPB Av. Aprígio Veloso, 882 Bodocongó 58.109-970,

More information

(1) Current State and Issues of the Electricity Sector in Indonesia

(1) Current State and Issues of the Electricity Sector in Indonesia Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Java-Sumatra Interconnection Transmission Line Project (I) Loan Agreement: April 30, 2010 Loan Amount:

More information

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS 1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the

More information

LIFE CYCLE COSTING FOR BATTERIES IN STANDBY APPLICATIONS

LIFE CYCLE COSTING FOR BATTERIES IN STANDBY APPLICATIONS LIFE CYCLE COSTING FOR BATTERIES IN STANDBY APPLICATIONS Anthony GREEN Saft Advanced and Industrial Battery Group 93230 Romainville, France e-mail: anthony.green@saft.alcatel.fr Abstract - The economics

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands

Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands Transmission grid extension for Lake Turkana Wind Farm Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands wessel.bakker@dnvkema.com Contents Drivers for grid expansion Suswa and Loyangalani

More information

HVDC Systems in India

HVDC Systems in India HVDC Systems in India Outline Introduction HVDC Systems presently in operation Main Data/Salient Features Upcoming Projects Future Challenges Transmission Network - Present 765kV/400kV lines: about 1,03,000

More information

Methodology of Cost Allocation

Methodology of Cost Allocation Methodology of Cost Allocation Robin Kliethermes May 17, 2013 1 Purpose of Cost Allocation Determine whether each class of customers is providing the utility with a reasonable level of revenue necessary

More information

Study on Economic Partnership Projects. in Developing Countries in FY2010. Study on the Kiev Metro Line 4 in Kiev City, Ukraine SUMMARY.

Study on Economic Partnership Projects. in Developing Countries in FY2010. Study on the Kiev Metro Line 4 in Kiev City, Ukraine SUMMARY. Study on Economic Partnership Projects in Developing Countries in FY2010 Study on the Kiev Metro Line 4 in Kiev City, Ukraine SUMMARY March 2011 第 1 章 第 2 章 The Ministry of Economy, Trade and Industry

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Eyre Peninsula electricity supply options investigation

Eyre Peninsula electricity supply options investigation 20 November 2017 South Australia s electricity transmission specialist Eyre Peninsula electricity supply options investigation Project Assessment Draft Report Port Lincoln Public Forum electranet.com.au

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 August 15, 2017 Re: California

More information