TRANSMITTAL MEMORANDUM. Whitman Lake Hydroelectric Project- Construction Meeting Minutes of August 21, 2013
|
|
- Rudolf Hutchinson
- 6 years ago
- Views:
Transcription
1 ~ ~ I ' c ~-,- ~...,, ~ Genl.'ral Maungt"".r 334 From Sm:cr I<etchik:ul, AK 9990 I Phone (9on 228-%03 Fax (907) b(4) TRANSMITTAL MEMORANDUM TO: FROM: The Honorable Mayor and City Council David Martin, Assistant General Manager DATE: August 26, 2013 Re: Whitman Lake Hydroelectric Project- Construction Meeting Minutes of August 21, 2013 At its meeting of June 7, 2012, the City Council adopted a motion accepting the bid of Burke Electric LLC in the amount of $2,803,433 for Contract No , Supply of Turbine and Generator Equipment for the Whitman Lake Hydroelectric Project. At its meeting of December 20, 2012, the City Council adopted a motion approving Contract No , Whitman Lake Hydroelectric Project General Construction, between the City of Ketchikan d/b/a Ketchikan Public Utilities and Dawson Construction, Inc. in the amount of $15,354,000. The motion adopted by the City Council also established a nine percent (9%) contingency in the amount of $1,381,860, bringing the total project cost to $16,735,860. At its meeting of December 20, 2012, the City Council adopted a motion approving Contract No , Whitman Lake Hydroelectric Project Power House Equipment Installation, between the City of Ketchikan d/b/a Ketchikan Public Utilities and Burke Electric LLC in the amount of $1,198, The motion adopted by the City Council also established a nine percent (9%) contingency in the amount of $107,835.10, bringing the total project cost to $1,306,004. Construction Meeting No. 30 was held on Tuesday, August 21, A copy of the meeting minutes is attached for City Council review.
2 WHITMAN LAKE HYDROELECTRIC PROJECT Weekly Site Meeting Minutes Phase 1 -Pipelines and Powerhouse CONTRACTORS: Dawson Construction Burke Electric ATTENDEES: Jon Pulver, Jolene Mosher, Jim Rogers, Mark Fairhart; by phone: Gary Hovde, Ben Bottoms, Carl Mannheim, David Martin, Randy Burke DISTRIBUTION: Tim Jurczak, Tim Eddy, Dominic Burke, Jennie Holstrom, Bill Smith, Ray Trudgeon, Andy Donato, Karl Amylon, Tim McConnell SAFETY: MEETING DATE: Report No: 30 August 21, Page 1 of3 KPU CONTRACTS: Dawson Construction Burke Electric & Ph access code NEXT MEETING: Tuesday, August 27, 2013 I O:OOAM Alaska time Action By: Safety issues for past week: No issue. Continue watching for tourists along Powerhouse Road. Safety issues for upcoming work: Dawson will post "No Swimming" and "Valve Caution" signs at dam. Dawson ENVIRONMENTAL: Environmental issues for past week: The dam release valve was closed on 19Aug at KGB's request to allow downstream construction Jolene continues to monitor Whitman Creek on a daily basis. Environmental issues for upcoming work: Continue monitoring ofbmp's and maintain as necessary Dawson SECURITY: Yield to tourists along Powerhouse Road All PROJECT ADMINISTRATION & ENGINEERING Construction Contracts: Burke Supply- Randy requested confirmation of the status of Burke's July payment Burke Install DawsonGC Submittals: Burke Submittals #81.1 (Valve House Instrumentation), #113 (480 Volt Panels) and #115 (PH Layout) remain open and need response. RFI's: Responses to RFis # regarding Upper Corridor rock remain open. A response to RFI #144 (flow meters) is pending RFI #137 (Valve Change@ Dam) Carl is reviewing the proposed valve change and reuse of valve from demo work RFI #104 (penstock drains)- remains open. Jon and Carl discussed a potential solution Burke RFI #24 (RTD's) requires a formal response RFI #134.1 (pipeline sections) requires a quick response so that work can continue RFI #75 (siphon system)- Jim suggested moving the equipment to the shoreline and Routing electrical to that location as a way to avoid routing tubing up and over the dam WLH Daily Report form Rev 02/05/13
3 Change Proposals: WHITMAN LAKE HYDROELECTRIC PROJECT Weekly Site Meeting Minutes Phase 1 -Pipelines and Powerhouse ~ HATCHTM COP's #31 and 34 have been received and are currently being reviewed. Gary noted that COP #47 is now void KPU! YARD & HATCHERY ISSUES: The second (cold water) bypass line was restored to service on Monday RECENT PROGESS: Dawson continued SWPPP BMP maintenance. Continued placing subgrade and bedding material for pipelines in lower and upper corridor Continued upper corridor access road construction Continued PH concrete pedestal reinforcing and forming. Continued fusing HDPE penstock pipe Began OH bridge crane installation REVIEW OF SHORT INTERVAL SCHEDULE- WORK NEXT PERIOD: Continue upper corridor access road construction. Place and compact bedding material in upper corridor Continue fusing pipe. Continue OH bridge crane installation Continue installation of PH roofing and siding panels. Begin substation construction. QUALITY: OTHER The seed mix was approved last week. Jennie will be away for inspection of turbine component fabrication from Aug 21 to Sept 3. FERC will perform project site inspection on Aug 28th. HATCH MANAGER: Mark E. Fairnart Title: Site Construction Representative his is intended to be an accurate account of the issues discussed at this meeting. Please notify the manager of any errors immediately WLH Daily Report fonn Rev 02/05/13
4 WHITMAN LAKE HYDROELECTRIC PROJECT- PHASE 1 oawson Updated: 8/20/ ~ON. It V( t io M t N'( DATE 8/19/2013 THRU 9/8/2013 I SHORT INTERVAL SCHEDULE 3 Week Look Ahead Distributed: AUGUST AUGUST AUGUST/SEPTEMBER SEPTEMBER ACTIVITY Scheduled Contractor M T w Th F s s M T w Th F s s M T w Th F s s M T w Th F s s PROJECT OVERVIEW! SWPPP MAINTENANCE /S&S X X X X X X X X X X X X X X X L X X X X X A WHITMAN DAM CONDUIT B UPPER CORRIDOR CLEAR AND GRUB S&S 0 UPPER CORRIDOR ROCK EXCAVATION S&S X X X X X X X X X X X R UPPER CORRIDOR GRADE S&S X X X X X X X X X X X X X X UPPER CORRIDOR CONDUIT TRENCH S&S X X X X X X X X X X X X X X X X X X X X D X X X X X MIDDLE CORRIDOR GRADE S&S A MIDDLE CORRIDOR CONDUIT TRENCH S&S y FUSE AND LAY CONDUITS S&S X X X X X X X X X X X X X X X X X X X X X X TEMPORARY BY.PASS UNE INSPECT I MAINTAIN TB LINES 0 N G 0 I N G 0 N G 0 I N G LAYDOWN AREA HATCHERY POWERHOUSE PH DEWATER FORM AND REINFORCE EQIUPMENT PEDESTALS X X X X X X X X X CONFIRM PEDESTAL LOCATIONS, ANCHORS, ETC... BURKE X PEDESTAL CONCRETE X ERECT METAL BUILDING X X X X X X X X X X X X X X X X X X X OH CRANE INSTALL BENCHMARK/Del X X X X X TAILRACE LAYOUT BACKFILL AROUND TAILRACE S&S MISC. TAILRACE METAL X X X X X X X X X SUBSTATION LAYOUT SUBGRADE S&S X X X X X X X X X X L GROUND RODS BURKEIFCE A FG&S B FORM & REINFORCE FOUNDATIONS 0 INSTALL CONDUIT BURKEIFCE R INSTALL GROUNDING W IRE BURKEIFCE Page 1 of2
5 WHITMAN LAKE HYDROELECTRIC PROJECT - PHASE 1 oaw,son Updated: 8120/ c o " t "" c ".,.c DATE 8/ THRU 9/ SHORT INTERVAL SCHEDULE 3 Week Look Ahead Distributed: ACTIVITY AUGUST AUGUST AUGUST/SEPTEMBER SEPTEMBER Scheduled Contractor M T w Th F s s M T w Th F s s M T w Th F s s M T w Th F s s EMBEDS & ANCHOR BOLTS D CONCRETE FOUNDATIONS A y HEADTANKFOUNDAnoN LAYOUT X SUBGRADE S&S X X INSTALL HEAD TANK OVERFLC'iW TO TAILRACE BACKFILL & COMPACT OVERFLOW PIPE FG&~S FOUNDATION FORM & REINFORCE FOUNDATION GROI UN DING & CONDUIT BURKE/FCE CONCRETE FOUNDATION WORKATDAII 1-r-- MOBILIZE EQUIPMENT, FLOATS, ETC... TO DAM JACD X REMOVE SUBMERGED DEBRIS JACD X X X VEl WORK INCLUDING IN WATER /ACD X X X X X X X X X X X X UNIT 1 INTAKE WORK INCLUDING IN WATER JACD X X X X X X X X X X X X PIPING /ACD X X X --- VALVE INSTALL X X X REPAIR VEl TB LINE AND CONNECT TO NEW X X X X PIPING JACD X X VALVE INSTALL X X AS-BUlL T MEASURE CWI FOR NOVEMBER /ACD X VALVE HOUSE - - J~'NL3-~ wiiiJKR - Page 2 of2
FINAL LICENSE APPLICATION Exhibit A Description of Project
FINAL LICENSE APPLICATION Exhibit A Description of Project PacifiCorp Portland, Oregon April 2004 Copyright 2004 by PacifiCorp Reproduction in whole or in part without the written consent of PacifiCorp
More informationProject Description - 1 -
Project Description The Mother Ann Lee Hydroelectric Station is located at Lock and Dam 7 on the Kentucky River. This dam is part of a system of 14 lock and dams installed on the Kentucky River between
More informationUTILITY CROSSING DETAIL
6" OF CSBC COMPACTED TO A FIRM AND UNYIELDING CONDITION. NOTE: - SILT FENCE SHALL CONFORM TO 8-01.3(9)A - SILT FENCES SHALL BE INSTALLED ALONG CONTOUR WHENEVER POSSIBLE. - POST SPACING MAY BE INCREASED
More informationSEAPA Board of Director s Meeting Director of Special Projects Report Petersburg, Alaska September 14, 2015
SEAPA Board of Director s Meeting Director of Special Projects Report Petersburg, Alaska September 14, 2015 Dam Powerhouse Falls Cr. Discharge into Carroll Inlet Photo Taken May 2015 9/15/2015 SEAPA Board
More informationSteese Rd - Curb & Sidewalk Improvement
REF. NO. ITEM NO. Steese Rd - Curb & Sidewalk Improvement DESCRIPTION QTY UNITS UNIT COST SUB-TOTAL 1 103.05 Requirement of Contract Bid 1 LS 24,048.00 24,048.00 2 201 Clearing and Grubbing 1 LS 11,077.00
More informationALL AMERICAN CANAL LINING PROJECT. CM Status as of July 31, 2008
ALL AMERICAN CANAL LINING PROJECT CM Status as of 1 AACLP STATIONS 2 Reach 1A Reach 1B Reach 2 Reach 3 Reach 2 2 SAFETY 3 Monthly Injury/Illness Data KPC 0 Recordable accidents for the month of 1 Recordable
More informationCTA Capital Construction Update December 12, 2006
Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction
More informationCity of Grand Island Tuesday, February 13, 2018 Council Session
City of Grand Island Tuesday, February 13, 2018 Council Session Item G-7 #2018-34 - Approving Certificate of Final Completion for the Construction of North Interceptor Phase I; Project No. 2012-S-6 Staff
More informationRate Schedules. Effective 1/1/2019
Rate Schedules 2019 Effective 1/1/2019 SUMMARY OF RATE SCHEDULES REVISIONS FOR RATES EFFECTIVE JANUARY 1, 2019 (1) Rate component changes for Residential and Heating Service rate schedules. (2) General
More informationNORTHERN INDIANA PUBLIC SERVICE COMPANY NORWAY AND OAKDALE HYDRO ELECTRIC PLANTS MONTICELLO, INDIANA
NORTHERN INDIANA PUBLIC SERVICE COMPANY NORWAY AND OAKDALE HYDRO ELECTRIC PLANTS MONTICELLO, INDIANA INTRODUCTION: NIPSCO is the proud owner of two Hydro Electric Plants located near Monticello, Indiana.
More informationWentzville Parkway South Phase 2 & 2A
Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total
More informationMichigan City Department of Water Works West Intake Extension. Presented By: Stanley S. Diamond Ohio Section AWWA September 28, 2017
Michigan City Department of Water Works West Intake Extension Presented By: Stanley S. Diamond Ohio Section AWWA September 28, 2017 Michigan City s Intakes - 2003 West Intake & Crib N Abandoned Intake
More information5. Underground Requirements
Un d e rg ro u n d Re q u ire me n ts Section 5 2016 Electric Service Requirements, 3rd Edition Section 5 Underground Requirements Directory Page 5.1 General 34 5.2 Conduit Requirements 34 5.3 Trench and
More informationPlease Refer to Attached Sample Form
Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32105-E Cancelling Revised Cal. P.U.C. Sheet No. 28313-E Electric Sample Form No. 62-0686 Application for Service
More informationCENTURY MONTHLY DEVELOPMENT UPDATE JUNE 2018
ASX / MEDIA ANNOUNCEMENT ASX: NCZ 02 July 2018 CENTURY MONTHLY DEVELOPMENT UPDATE JUNE 2018 New Century continues strong progress toward restarting Century operations, with planned refurbishment activities
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of
More informationSimson Haulofu Divisional Manager. NamPower Namibia
Simson Haulofu Divisional Manager NamPower Namibia Agenda Overview of Ruacana Some interesting facts about Ruacana Ruacana s contribution to Namibia Ruacana operating regime Unit 4: Business case & feasibility
More informationBid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013
Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D4-1102 November 21, 2013 Doughtie Construction Co., Elliott Construction Dudley Construction Ltd. SUBTOTAL GENERAL ITEMS : $191,713.00
More informationALBENI FALLS DAM AND LAKE PEND OREILLE
ALBENI FALLS DAM AND LAKE PEND OREILLE Fall Public Meeting 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122 Aug. 7, 2017 255 255 255 239 65 53 80 119 27 252 174.59 83 36 118 110 135 120
More informationWHITE POINT LANDSLIDE
Gary Lee Moore, PE, ENV SP Alfred L. Mata, P.E., Deputy City Engineer WHITE POINT LANDSLIDE Status Report Recommended Immediate Measures (Estimate $12.96 Million) FUNDING APPROVED BY CITY COUNCIL ON: AUGUST
More informationCrane Inspection Log. Mailing Address: P.O. Box Tulsa, OK Phone: (918) Fax: (918)
999978000 Crane Inspection Log Mailing Address: P.O. Box 581510 Tulsa, OK 74158-1510 Physical Address: 4707 North Mingo Road Tulsa, OK 74117-5904 Phone: (918) 836-0463 Fax: (918) 834-5979 www.autocrane.com
More informationSTATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES
STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 17-058 LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES Request for Approval of Energy Supply Solicitation and Resulting Rates
More informationREGULATIONS GOVERNING WATER SERVICE
200 South Ivy St. Room 177 Medford, Oregon 97501 Tel: 541-774-2430 Fax: 541-774-2555 wtrcom@ci.medford.or.us www.medfordwater.org REGULATIONS GOVERNING WATER SERVICE January 1, 2016 EXHIBIT A - RESOLUTION
More informationAppendix 5 Sample Specifications. Specifications for Socioeconomic Survey in Rural Areas in Myanmar
Part 6-2 Appendix 5 Appendix 5 Sample Specifications Appendix 5-1 Appendix 5-2 Appendix 5-3 Appendix 5-4 Appendix 5-5 Appendix 5-6 Specifications for Socioeconomic Survey in Rural Areas in Myanmar Technical
More informationTank Farm Additional Storage Site Layout
MONTREAL TRUDEAU INTERNATIONAL AIRPORT MIFFC Fuel Committee Meeting Montreal Airport Marriott Hotel, June 15, 2017 Tank Farm Additional Storage Site Layout 1 Tank Farm Additional Storage - Construction
More informationFasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016
July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit
More informationAir Quality Permit File SOOP # Lindy Paving, Inc. I Homer City Plant
OffiCIAL FILE COPY SOUTHWEST REGIONAL OFFICE MEMO TO FROM THROUGH DATE Air Quality Permit File SOOP # 32-00311 Lindy Paving, Inc. I Homer City Plant Sheila A. Shaffer~ Air Quality Engineering S~ecialist
More informationMcNary Northshore Fishway Hydro Project. History & Lessons Learned
McNary Northshore Fishway Hydro Project History & Lessons Learned May 6, 2017 21 th Annual TECHNICAL SEMINAR Machines, Maintenance, and Management: Keeping Hydro Facilities Up and Running History & Lessons
More information*iiiii. May 31, 2017 VIA ELECTRONIC FILING
*iiiii. PUBLIC UTILITY DISTRICT NO. I of CHELAN COUNTY P.O. Box 1231, Wenatchee, WA 98807-1231 327 N. Wenatchee Ave., Wenatchee, WA 98801 (509) 663-8121 Toll free 1-888-663-8121 www.chelanpud.org May 31,
More informationLAKE CHELAN ANNUAL FLOW AND WATER TEMPERATURE REPORT Final
LAKE CHELAN ANNUAL FLOW AND WATER TEMPERATURE REPORT 2013 LICENSE ARTICLES 405 & 408 Final LAKE CHELAN HYDROELECTRIC PROJECT FERC Project No. 637 April 30, 2014 Public Utility District No. 1 of Chelan
More informationAPPENDIX B. POTENTIAL CONSTRUCTION EQUIPMENT
. POTENTIAL CONSTRUCTION EQUIPMENT Table B-1. Alternative 1 (Options A and B) and Alternative 3 Alternative 1 (Options A and B) and Alternative 3 Overhead Transmission Line and Poles Removal of conductors
More informationCity of Grand Island Tuesday, June 26, 2018 Council Session
City of Grand Island Tuesday, June 26, 2018 Council Session Item G-21 #2018-188 - Approving Change Order No. 3 for Sanitary Sewer Collection System Rehabilitation Various Locations; Project No. 2017-S-2A
More informationAsia Pacific Research Initiative for Sustainable Energy Systems 2012 (APRISES12)
Asia Pacific Research Initiative for Sustainable Energy Systems 2012 (APRISES12) Office of Naval Research Grant Award Number N00014-13-1-0463 Crissy Field Center Wind Power Study Phase II: Wind Turbine
More informationAlternative Delivery as a Form of Risk Mitigation
Alternative Delivery as a Form of Risk Mitigation Erika P. Moonin, P.E. Lake Mead Intake No. 3 Access Shaft - 400 Low feet Lake deep Level Pumping Station November 29, 2017 Outline Project Background -
More informationCity of Grand Island Tuesday, October 10, 2017 Council Session
City of Grand Island Tuesday, October 10, 2017 Council Session Item G-12 #2017-276 - Approving Change Order No. 1 for Lift Station No. 20 Upgrade and Force Main Rehabilitation & Lift Station No. 14 Abandonment;
More informationTABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:
TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design
More informationEnergy Technical Memorandum
Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter
More informationBroken Hill Solar Plant. Community Information Session 9 September 2015
1 Broken Hill Solar Plant Community Information Session 9 September 2015 Agenda 2 1 2 3 4 5 Welcome September CIS Overview of project status AGL / First Solar Employment Project planning Next meeting >
More informationK2 Wind Community Liaison Committee Meeting #2 Wednesday, May 28, 2014
K2 Wind Community Liaison Committee Meeting #2 Wednesday, May 28, 2014 K2 Wind Background The K2 Wind Power Project is a 270 megawatt (MW) wind project being developed in the Township of Ashfield-Colborne-Wawanosh
More informationA REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning
A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical 4v ^c 0:01'1 S0^O c.. ^ '^ W E. G. PIERCY i^ x zoto/off/zq,.'ftrif4^#ft^^,' r Mechanical Civil Protection & Control Transmission &
More informationAPRROVED DONNER SUMMIT PUBLIC UTILITY DISTRICT P.O. BOX 610 SODA SPRINGS CALIFORNIA TELEPHONE (530) FAX (530)
APRROVED DONNER SUMMIT PUBLIC UTILITY DISTRICT P.O. BOX 610 SODA SPRINGS CALIFORNIA 95728 TELEPHONE (530) 426-3456 FAX (530) 426-3460 Minutes of the Regular Meeting of the Board of Directors Held: September
More informationElectric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections. Minnesota North Dakota South Dakota
Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections Page 1 of 7 17-02-420 Electric Service Conversion Overhead-to-Underground Overview and process of converting residential
More informationTHE CALIFORNIA STATE UNIVERSITY Commercial Paper Equipment Financing (CPEF) Fiscal Year Financing Schedules *
Updated 4-10-09 Fiscal Year 2009-10 Financing Schedules * Round of CPEF Call Response CP Issuance Funding Thirteenth March 10, 2009 June 3, 2009 June 4, 2009 Fourteenth June 9, 2009 September 1, 2009 September
More informationATTACHMENT I BID SCHEDULE IFB NO , CHURCH FARMS EAST STORAGE TANK AND BOOSTER PUMP STATION
ATTACHMENT I BID SCHEDULE IFB NO. 19-021, CHURCH FARMS EAST STORAGE TANK AND BOOSTER PUMP STATION Item No. Description Qty Unit Unit Cost Amount Pump Station Site Work 1 Site Demolition / Removals / Haul
More informationTransit Project Delivery Status Report. Significant Issues
Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda
More informationWVDP Project Update. Scott Anderson. Deputy General Manager. Citizen Task Force Meeting July 25, 2018
WVDP Project Update Scott Anderson Deputy General Manager Citizen Task Force Meeting July 25, 2018 www.energy.gov/em 1 Safety Metric June 2018 12-Month Rolling Average TRC (12-Month Rolling Average) DART
More informationDepartment of the Environment. Moving Away From Stage II Vapor Recovery
Department of the Environment Moving Away From Stage II Vapor Recovery 2013 Stage II Regulations Stakeholder Meeting November 12, 2013 Topics Covered Background The technical analyses What does it tell
More informationMINUTES OF THE MEETING OF THE BOARD OF DIRECTORS OF THE BRAZORIA COUNTY GROUNDWATER CONSERVATION DISTRICT
MINUTES OF THE MEETING OF THE BOARD OF DIRECTORS OF THE BRAZORIA COUNTY GROUNDWATER CONSERVATION DISTRICT August 15, 2012 The Board of Directors of the Brazoria County Groundwater Conservation District
More informationOhio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director
Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director Project No. 100281 PID 77255 LUC-IR-475-14.18 Federal Type: MAJOR RECONSTRUCTION Letting Date: 6/3/2010 Completion
More informationB.6 Construction Equipment Utilization and Workforce
Appendix B.6 Construction ment Utilization and Workforce B.6 Construction ment Utilization and Workforce To support environmental impact assessments, a preliminary estimate was prepared for construction
More informationGenerator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014
Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project NWHA Spokane October 30, 2014 0 The Wells Project WELLS Chief Joseph Rocky Reach East Wenatchee Wells Dam Location Columbia
More informationCT Consultants, Inc.
Cost 1 202 AHRESTY DRIVE REMOVAL 1 LS 2 202 EXISTING SILO DEMOLISHED AND REMOVED, AS PER PLAN 1 LS 3 203 EXCAVATION (NOT INCLUDING UNDERCUT) 2,372 CY 4 203 EMBANKMENT 3,306 CY 5 204 PROOF ROLLING 10 HRS
More informationMemorandum October 5, 2017
614 Magnolia Avenue Ocean Springs, Mississippi 39564 228.818.9626 Memorandum October 5, 2017 To: Gary Miller, U.S. Environmental Protection Agency From: David Keith, John Laplante, Matt Henderson, and
More informationCONTRA COSTA COMMUNITY COLLEGE DISTRICT
ADDENDUM #1 CONTRA COSTA COMMUNITY COLLEGE DISTRICT Date: 11/15/2018 D 4014 Warehouse Demolition Project Diablo Valley College 321 Golf Club Road, Pleasant Hill, CA 94523 NOTICE TO ALL CONTRACTORS: You
More informationWORKERS' COMPENSATION AND EMPLOYERS LIABILITY TENNESSEE NCCI CONTRACTING INDUSTRY GROUP As of March 1, 2013.
WORKERS' COMPENSATION AND EMPLOYERS LIABILITY TENNESSEE NCCI CONTRACTING INDUSTRY GROUP 50-6-113 As of March 1, 2013 Class Code Sort CODE DESCRIPTION 0042 LANDSCAPE GARDENING & DRIVERS 0050 FARM MACHINERY
More informationTENDER FOR COUNTY ROAD 44 MULTI-USE PATHWAY PHASE 1A & 1B. Tender No.: NG16-19 ADDENDUM #1. October 31, 2016
TENDER FOR COUNTY ROAD 44 MULTI-USE PATHWAY PHASE 1A & 1B Tender No.: NG16-19 ADDENDUM #1 October 31, 2016 A copy of this addendum must be enclosed with your tender. Failure to comply with this requirement
More informationGoldwind Americas. Construction Kickoff: Landowner Presentation. Construction Kickoff Presentation April 26th 2017
Goldwind Americas Construction Kickoff: Landowner Presentation Construction Kickoff Presentation April 26th 2017 1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction
More informationSoutherly WWTC Getting the Grease Out. OWEA Plant Operations Workshop Grease Unloading Station
Southerly WWTC Getting the Grease Out OWEA Plant Operations Workshop Grease Unloading Station Presented by: Harry Shaposka, PE (216) 881-6600 Jeff Ifft, PE (216) 606-1316 6055 Rockside Woods Blvd Independence,
More informationConfederation Line West Queensway Terrace North. May 27, 2017
Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement
More informationTodd Carlson Program Coordinator Engineering MMSD PP I/I Summit 2.0 October 15,
Todd Carlson Program Coordinator Engineering MMSD PP I/I Summit 2.0 October 15, 2015 1 North Shore of Lake Superior 883 feet of Elevation Aging Sanitary/Storm Sewer System dating back to 1880 s Second
More informationCity of Grand Island Tuesday, October 23, 2012 Council Session
City of Grand Island Tuesday, October 23, 2012 Council Session Item G5 #2012-308 - Approving Bid Award - Substation Transformer Testing Services Staff Contact: Tim Luchsinger, Jason Eley Grand Island Council
More informationTahoe-Reno Industrial Center Total Bonding Amounts Engineer's Opinion of Probable Construction Costs (30% Submittal) Project No. 783.
Total Bonding Amounts Brent Farr Date: 05/05/17 Item Project Estimated Cost 1 Induction Well 1 and Britain Ave Non potable Water Line $1,084,353 2 Storage Reservoir Upgrades $11,560,463 3 Booster Station
More informationCUSHMAN HYDROELECTRIC PROJECT. Pat McCarty, Generation Manager
CUSHMAN HYDROELECTRIC PROJECT Pat McCarty, Generation Manager AGENDA A picture tour of Cushman Relicense history Relicense requirements Fisheries Flows & reservoir elevations Cultural/historical resources
More informationWIM #40 is located on US 52 near South St. Paul in Dakota county.
WIM Site Location WIM #40 is located on US 52 near South St. Paul in Dakota county. System Operation WIM #40 was operational for the entire month of November 2017. Volume was computed using all monthly
More informationSUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71
BASE BID 1.00 GENERAL CONDITIONS 1.01 Mobilization (Maximum 5% of Base Bid) LS 1 84,000.00 $ 84,000.00 100,000.00 $ 100,000.00 85,000.00 $ 85,000.00 1.02 Bonding, Insurance, Permits (including Plumbing,
More informationNew Franchise Agreement: Recyclables, Organics, and Waste. Town of Truckee Town Council Meeting July 25, 2017
New Franchise Agreement: Recyclables, Organics, and Waste Town of Truckee Town Council Meeting July 25, 2017 Agenda Overview of Process, Context Review Regulatory Drivers Review of Current Services Potential
More informationPERMANENT RESIDENTIAL UNDERGROUND SERVICE
CITY OF RICHLAND ENERGY SERVICES DEPARTMENT 505 Swift Boulevard, MS-21 Richland, WA 99352 Telephone (509) 942-7403 Fax (509) 942-7405 PERMANENT RESIDENTIAL UNDERGROUND SERVICE A. INTRODUCTION This guide
More information2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000
2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, 44504 143,789 SF on 20.177 ACRES $4,300,000 BUILDING OVERVIEW PARKER HANNIFIN FACILITY GEAR PUMP DIVISION Zoning - Industrial Light Manufacturing 143,789
More informationAdd 7% to cater for any fittings/fabrication at the bridge, and anchor blocks (as directed by the Eng. On site) Total
ITEM COUNTY CONSTITUENCY SUB-COUNTY WARD PROJECT SUBJECT DESCRIPTION NAKURU SUBUKIA SUBUKIA KABAZI KABAZI WARD WATER WOR KABAZI RUGONGO WATER PROJECT(PIPELAYING AND CONSTRUCTION) RATE UNIT QTY (Kshs) PIPING
More informationQuestions and Answers to Request for Proposal
Questions and Answers to Request for Proposal Question 1 Would you please amend your RFP to include a restriction on the age of trucks? Answer 1 We will not be making that amendment to the RFP. However,
More informationRESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council
RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES January 10, 2011 Presentation to Arvada City Council CONSULTANT TEAM LBA Associates MSW Consultants Denver based recycling and waste management consultant
More informationIN THE CITY COUNCIL OF THE CITY OF LIVERMORE CALIFORNIA A RESOLUTION AMENDING WATER RATES AND CHARGES FOR FISCAL YEARS THROUGH
IN THE CITY COUNCIL OF THE CITY OF LIVERMORE CALIFORNIA A RESOLUTION AMENDING WATER RATES AND CHARGES FOR FISCAL YEARS 2017 18 THROUGH 2021 22 The City of Livermore operates the municipal water system
More informationThe Town of Oliver is implementing a cart program for the same reasons as the industry service providers as well as a few other reasons including:
Cart Program FAQ s Program Details 1. Why is the Town of Oliver adopting a cart program? The garbage and recycling industry is pursuing cart programs primarily for efficiency and worker safety reasons.
More information2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000
2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, 44504 INDUSTRIAL PROPERTY FOR SALE 143,789 SF on 20.177 ACRES $4,300,000 BUILDING OVERVIEW PARKER HANNIFIN FACILITY GEAR PUMP DIVISION Zoning - Industrial
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This
More informationWIM #37 was operational for the entire month of September Volume was computed using all monthly data.
SEPTEMBER 2016 WIM Site Location WIM #37 is located on I-94 near Otsego in Wright county. The WIM is located only on the westbound (WB) side of I-94, meaning that all data mentioned in this report pertains
More informationCapacity Market Rules for Energy Storage Resources
Capacity Market Rules for Energy Storage Resources Zachary T Smith Manager, Capacity Market Design ICAPWG August 23 rd, 2018 Agenda Background Energy Storage Resource (ESR) overview Capacity Market Rules
More informationCommunity Involvement Group North. Meeting 13
Community Involvement Group North: Meeting 13 Meeting: Community Involvement Group North Date: Monday, 4 June 2018 Time: Location: Arrive at 6.15pm for 6.30pm IBM Building 55 Coonara Road West Pennant
More informationCity Council Report. Mayor and City Council
City Council Report To: From: Mayor and City Council City Council Meeting: February 23, 2016 Agenda Item: 3.J Edward King, Director, Big Blue Bus, Transit Services Department Subject: Custodial and Maintenance
More informationOHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc.
OHIO Department of Transportation Project #140378 Franklin County, OH ISSA Presidents Award Submission Strawser Construction Inc. Columbus, Ohio Applicant Information Strawser Construction Inc. 1392 Dublin
More informationCHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska REGULAR BOARD OF DIRECTORS MEETING AGENDA ITEM SUMMARY. May 28, 2014
CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska REGULAR BOARD OF DIRECTORS MEETING AGENDA ITEM SUMMARY May 28, 2014 ACTION REQUIRED AGENDA ITEM NO. VIII.B. X X Information Only Motion Resolution Executive
More informationCITY OF BELVEDERE RESOLUTION NO
CITY OF BELVEDERE RESOLUTION NO. 2018-23 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BELVEDERE APPROVING THE 2018 COLLECTION RATE APPLICATION FOR MILL VALLEY REFUSE FOR THE PERIOD JULY 1, 2018, TO
More informationSECTION 17 FIRE HYDRANT ASSEMBLIES General
SECTION 17 FIRE HYDRANT ASSEMBLIES 17-1.01 Scope 17-1 General This section describes the requirements for furnishing and installing as appurtenances to treated water mains. These requirements include the
More informationTechnical Advisory Committee
Technical Advisory Committee 1 Agenda Call to Order Pledge of Allegiance Confirmation of Quorum Agenda Review Tawny Olore, P.E. Agenda Review Adoption of meeting minutes Chairman s Report Phase 1 Project
More informationCity of Grand Forks Staff Report
City of Grand Forks Staff Report Committee of the Whole December 1, 016 City Council December 19, 016 Agenda Item: Bids for City Project No. 7551 Lift Station No. 17 & 17A Rehabilitation Submitted by:
More informationCity of Peachtree City
City of Peachtree City Lake Peachtree Spillway Replacement City Council Update September 15, 2016 Project Team Integrated Science & Engineering 1 Spillway Alternatives Analysis Spillway Alternatives Evaluated
More informationNeighborhood Fire Stations
Department of Public Works EARTHQUAKE SAFETY AND EMERGENCY RESPONSE BOND Neighborhood Fire Stations Projects Update Presentation to the SF Fire Commission August 22, 2013 Agenda ESER 1 Project Locations
More informationFuel for the Frozen North Alaskan Fuel Consortium Adds Capacity at Anchorage Airport
Fuel for the Frozen North Alaskan Fuel Consortium Adds Capacity at Anchorage Airport By Grant Smith, PG, Burns & McDonnell; Weston Bennett, Aircraft Service International Group Alaska s Ted Stevens Anchorage
More informationPUBLIC WORKS AND SERVICES PETROLEUM PRODUCTS DIVISION STANDARD DETAILED DRAWINGS FOR NORTHERN FUEL STORAGE AND DISTRIBUTION FACILITIES
PUBLIC WORKS AND SERVICES PETROLEUM PRODUCTS DIVISION STANDARD DETAILED DRAWINGS FOR NORTHERN FUEL STORAGE AND DISTRIBUTION FACILITIES 3rd EDITION - 01/2006 Foreword This publication, together with the
More informationDART Priorities Overview
City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee
More informationRegular Meeting PULASKI COUNTY Monday, November 8, 2004 PUBLIC SERVICE AUTHORITY FOLLOW-UP. 1. Citizen Comments (Mr. Stan Moran presented information)
AGENDA Regular Meeting PULASKI COUNTY Monday, November 8, 2004 PUBLIC SERVICE AUTHORITY 9:00 a.m. FOLLOW-UP ITEM 1. Citizen Comments (Mr. Stan Moran presented information) KEY STAFF (Mr. Jim Whited asked
More informationInformation Meeting Transfer Station Options. September 30, 2014
Information Meeting Transfer Station Options September 30, 2014 Outline of Presentation Why we are looking at changes Background on current Transfer Station Options that were considered need, function
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationEagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013
Construction of Peña Bridge - March 2013 South Platte River Bridge Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013 Today s Agenda Project background Schedule Design Systems Rail cars
More informationSECTION.1400 NITROGEN OXIDES
SECTION.1400 NITROGEN OXIDES 15A NCAC 02D.1401 DEFINITIONS (a) For the purpose of this Section, the definitions at G.S 143-212 and G.S. 143-213, and 15A NCAC 02D.0101 shall apply, and in addition the following
More informationCity-wide LED Street Light Conversion Program
City-wide LED Street Light Conversion Program Arts & Innovation Board of Public Utilities July 25, 2016 Project Description Utility 2.0 Multi-phase implementation of city-wide street light conversion program
More informationCTA Capital Construction Update May 17, 2007
Block 37 Signals Project Brown Line Howard CTA Capital Construction Update May 17, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block 37
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationMUSKRAT FALLS PROJECT OVERVIEW
CIMFP Exhibit P-00136 Page 1 MUSKRAT FALLS PROJECT OVERVIEW Stan Marshall, Nalcor CEO Presentation to MF Public Inquiry September 19, 2018 AGENDA CIMFP Exhibit P-00136 Page 2 Electrical System Basics Churchill
More informationSAINT PETERSBURG CITY COUNCIL. Consent Agenda. Meeting of September 21, "Bill" Foster, Chair, and Members o City Council
SAINT PETERSBURG CITY COUNCIL Consent Agenda Meeting of September 21, 2006 Toe The Honorable avid. "Bill" Foster, Chair, and Members o City Council Subject : Awarding a two-year blanket purchase agreement
More information