B.6 Construction Equipment Utilization and Workforce

Size: px
Start display at page:

Download "B.6 Construction Equipment Utilization and Workforce"

Transcription

1 Appendix B.6 Construction ment Utilization and Workforce B.6 Construction ment Utilization and Workforce To support environmental impact assessments, a preliminary estimate was prepared for construction equipment utilization and construction workforce. This appendix summarizes equipment and staffing for each of the major project features; it also provides this information in tabular format in Table B.6-1 through Table B ment numbers and utilization hours are based on the earthwork and material quantities developed for the project features to support cost estimating. Conservative hourly equipment production rates were used to estimate the number of pieces of construction equipment and the number of operating hours required to complete major tasks within schedule limits. Support equipment was also included in the evaluation. For example, this evaluation would include excavators and loaders to fill haul vehicles and water trucks, bulldozers, and compactors to spread and compact fills. Estimates were also included for the support equipment (e.g., cranes and hoists) needed for pipelines, buildings, and other facilities. Haul equipment was also included for each facility where appropriate for an item such as filter and drain material, concrete aggregates, aggregate base and other material. The equipment numbers are based on the need to import such materials from an off-site quarry approximately 30 to 35 miles from the project. A reasonable estimate was also included to haul major equipment components to the facilities, including pumps, motors, generators, mechanical equipment, and embedded items, and other items. Haul equipment for construction material (e.g., reinforcing steel, structural steel, readymix concrete, and on-site fabricated pipe) was also estimated. Typically, equipment numbers and hours were based on 10-hour, single-shift work, 6 days per week. The only exception to this scheduling would be the tunneling work at Sites Dam; that effort was assumed to be double-shift work (22 hours per day, 6 days per week). Staff numbers shown for each facility include equipment operators and other construction personnel needed to complete construction. Staff estimates do not include owner or engineer staff that would be supervising construction. The equipment utilization and staff estimated represent construction of Alternative C, which would require the most equipment and staff. North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report B.6-1

2 B.6-2 North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report Table B.6-1. Tunnel Inlet and Outlet, Including Sites Pumping/Generating Plant Tunnel Lake Outlet Inlet area Total ment Count Count Count Bulldozer ,330 1,760 Compactor Concrete Pump Concrete Trucks ,030 Crane Dump Truck Tunnel Fork Lift Fuel Truck Generator Grader Highway Trucks ,172 Loader Tunnel Material Trucks - Concrete , ,736 Off-Road Truck Roller Scissor Lift Scraper ,660 3,090 Tunnel Boring Machine Water Trucks Welding Truck Staff All equipment other than tunnels assumed 10 hr. day. Tunnels assumed 22 hours/day. Appendix B.6 Construction ment Utilization and Workforce

3 Table B.6-2. Pipelines Delevan and TRR North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report B.6-3 Excavation Backfill ment Count Count Pipe & Manhole Installation Count Backfill Loader Bulldozer , ,086 Compactor Conc. Material Trucks Concrete Trucks Crane Fabrication 1 1,000 1,000 1,000 Crane Installation Dump Truck 20% Exc , ,000 Dump Truck Comp. BF ,670-4,670 Excavation Loader Excavator Fork Lift - Installation Fork Lift Yard 1 1,000 1,000 1,000 Fuel Truck Generator Grader Highway Trucks ,990 5,190 Jacking ment Pipe Fabrication. 1 1,000 1,000 1,000 Pipe Transport Truck ,100 1,100 Scraper 80% Exc , ,670 Scraper Common Bf ,064-3,064 Water Trucks Staff Total Appendix B.6 Construction ment Utilization and Workforce

4 B.6-4 North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report Table B.6-3. Dams and Sites Reservoir Inundation Excavation & Fill ment Count Count Drilling & Grouting Concrete Total Count Bulldozer 10 1,774 17,740 17,740 Compactor 10 1,535 15,350 15,350 Conc. Material Trucks ,720 1,720 Concrete Pump Concrete Trucks Crane - - Drilling Machine ,952 1,952 Dump Truck Filter Material Loader 3 1,160 3,480 3,480 Excavator - - Fork Lift Yard Fuel Truck 2 1,774 3,548 3,548 Generator Grader 5 1,535 7,675 7,675 Grout Pump ,952 1,952 Highway Trucks , ,328 Off-Road Trucks 24 1,160 27,840 27,840 Scraper - Excavation ,800 6,800 Waste/Tree Loader Water Trucks 4 1,774 7,096 7, Staff Appendix B.6 Construction ment Utilization and Workforce

5 Table B.6-4. Gravel Roads Tunnel Lake Outlet Inlet area Total North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report B.6-5 ment Count Count Count Bulldozer Compactor Concrete Trucks Crane Dump Truck Excavator Fork Lift - Yard Fuel Truck Generator Grader Grout Pump Highway Trucks Loader Off-Road Trucks Paving Machine Roller Scraper - Excavation Water Trucks Staff Max Appendix B.6 Construction ment Utilization and Workforce

6 B.6-6 North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report Table B.6-5. TRR Pumping/Generating Plant Excavation & Backfill ment Count Concrete & Rock Count Other Activities Count Batch Plant ment Bulldozer , ,165 Compactor Concrete Pump Concrete Trucks Crane Dump Truck , ,250 Fork Lift Fuel Truck Generator Grader Highway Trucks , ,760 Loader Off-Road Trucks Paving Machine Roller Scraper Excavation & Bf , ,165 Water Trucks Total Appendix B.6 Construction ment Utilization and Workforce Staff Max Peak staff for other activities is set at 80 for building construction. Duration for buildings should be about two years.

7 Table B.6-6. TRR Reservoir and Connections Clear & Excavation Backfill AC Lining & Structures Total North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report B.6-7 ment Count Count Count Backfill Loader Bulldozer Compactor Concrete Trucks Crane Dump Truck Excavation Loader Fork Lift Yard Fuel Truck Generator Grader Grout Pump Highway Trucks Off-Road Trucks , ,520 Paving Machine Scraper - Excavation Water Trucks Staff Max Staff allowed for structures is 40 for a period of 16 months Appendix B.6 Construction ment Utilization and Workforce

8 B.6-8 North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report Table B.6-7. Holthouse Reservoir (Enlarged Funks Reservoir) Excavation & Fill ment Count Count Drilling & Grouting Concrete Total Count Bulldozer - Dam , ,850 Dozers For Clear/Grub Dozers For Channel , ,600 Compactor Conc. Material Trucks Concrete Pump Concrete Trucks Crane Drilling Machine Dump Truck Backfill Loader Fork Lift Yard Fuel Truck Generator Grader Grout Pump Highway Trucks , ,036 Off-Road Trucks , ,490 Scraper For Dam Scraper For Dam , ,600 Waste/Tree Loader Water Trucks , , Staff Appendix B.6 Construction ment Utilization and Workforce

9 Table B.6-8. Delevan Intake Pumping/Generating Plant on Sacramento River (Including Fish Screening Facilities) Excavation & Backfill Concrete & Rock Other Activities Total North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report B.6-9 ment Count Count Count Batch Plant ment Bulldozer , ,165 Compactor Concrete Pump Concrete Trucks Crane Dump Truck , ,250 Fork Lift Fuel Truck Generator Grader Highway Trucks , ,760 Loader Off-Road Trucks Paving Machine Roller Scraper-Excavation & Bf , ,165 Water Trucks Staff Peak staff for other activities is set at 80 for building construction. Duration for buildings should be about two years. Appendix B.6 Construction ment Utilization and Workforce

10 B.6-10 North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report Table B.6-9. Paved Roads and Bridges Grading Agg Base & Paving Bridges Total ment Count Count Count Backhoe/Drill , Caisson Drill Rig Bulldozer , ,770 Compactor Concrete Trucks ,400 2,246 Concrete Material Trucks Concrete Pump Crane ,000 1,000 Dump Truck , ,775 Excavator Fork Lift Yard Fuel Truck ,126 Generator Grader ,260-2,104 Grout Pump Highway Trucks ,056 1,291 Loader ,235 Off-Road Trucks , ,560 Paving Machine Roller Scraper , ,736 Water Trucks , , Staff Max Appendix B.6 Construction ment Utilization and Workforce

11 Table B GCID Canal and Headworks Modifications North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report B.6-11 Grading & Paving ment Count Count Concrete Work Miscellaneous Total Count Bulldozer Compactor Concrete Trucks Crane Dump Truck Fork Lift - Yard Fuel Truck Generator Grader Grout Pump Highway Trucks Loader Off-Road Trucks Paving Machine Roller Scraper - Excavation Water Trucks Staff Max Appendix B.6 Construction ment Utilization and Workforce

12 B.6-12 North-of-the-Delta Offstream Storage Investigation Draft Feasibility Report Table B Recreational Facilities Grading & Paving ment Count Bobcat Count Concrete Work Miscellaneous Total Count Bulldozer Compactor Concrete Trucks Concrete Material Trucks 4 44 Crane Dump Truck Fork Lift - Yard Fuel Truck Generator Grader Grout Pump Highway Trucks Loader Off-Road Trucks Paving Machine Roller Scraper - Excavation Water Trucks Staff Max Appendix B.6 Construction ment Utilization and Workforce

Why? Faster To reduce the duration of the process

Why? Faster To reduce the duration of the process BUTE Department of Construction Management and Technology 20.10.2015 Why? Faster To reduce the duration of the process Cheaper To reduce costs (where labour is expensive) Easier To reduce (heavy) manual

More information

APPENDIX F. Air Quality Modeling Results

APPENDIX F. Air Quality Modeling Results APPENDIX F Air Quality Modeling Results PHASE 2 NLIP Emissions Summary Unmitigated 2008 Emissions Sutter County Worst-Case lb/day Tons/year Sacramento County Worst-Case lb/day Tons/year ROG NOX PM10 ROG

More information

Appendix C Noise and Vibration Worksheets

Appendix C Noise and Vibration Worksheets PUBLIC WORKS BUREAU OF ENGINEERING Appendix C Noise and Vibration Worksheets Central Outfall Sewer at 59 th Street Page C-1 CEQA Initial Study and 4 th Avenue Project January 2012 Receptor Noise Level

More information

Construction Noise Worksheets

Construction Noise Worksheets Appendix F Construction Noise Worksheets Al Larson Boat Shop Improvement Project Draft EIR January 2012 ADP# 080627-072 SCH# 2010091041 This page left intentionally blank ADP# 080627-072 SCH# 2010091041

More information

Appendix D. Noise Calculations

Appendix D. Noise Calculations Appendix D Noise Calculations Summary of Boating Activity Changes Associated with each Alternative Peak Day Boating Trips Structure Existing With Alt increase with alt 2 increase with alt 3 increase with

More information

Table C-1. POLB Middle Harbor Redevelopment Construction/Demolition Activities and Noise Data

Table C-1. POLB Middle Harbor Redevelopment Construction/Demolition Activities and Noise Data Appendix C Noise Table C-1. POLB Middle Harbor Redevelopment Construction/Demolition Activities and Noise Data Activity Equipment HP Wharf Demolition Landside (A) Wharf Demolition Marine (B) Sheet Pile

More information

Appendix H: Construction Impacts H-3 Air Quality

Appendix H: Construction Impacts H-3 Air Quality Appendix H: Construction Impacts H-3 Air Quality Rockland Landing-Reconstruction of the South Broadway Bridge Nonroad s Engine Size (hp) Compressors - surface tools 275 2 1 8 10% 0.043 0.045 1.107 0.263

More information

H.1 Construction Emissions

H.1 Construction Emissions Appendix H. Air Quality Analysis The methods used to calculate emissions of carbon monoxide (CO), volatile organic compounds (VOCs), oxides of nitrogen (NO X ), sulfur oxides (SO X ), particulate matter

More information

T.A.T Minimum Wage Scale

T.A.T Minimum Wage Scale T.A.T Minimum Wage Scale General Construction: Construction projects that are funded by the Three Affiliated Tribes or an Enrolled member of the Fort Berthold Reservation. Rates Fringes Electrician $29.24

More information

This appendix describes various types of equipment that can

This appendix describes various types of equipment that can Appendix GENERAL ENGINEER SUPPORT EQUIPMENT This appendix describes various types of equipment that can be used to support general engineer missions. This information is provided to help planners choose

More information

On-the-Job Training Program. Overview of Training Programs

On-the-Job Training Program. Overview of Training Programs On-the-Job Training Program Overview of Training Programs The training programs are as follows: Code Training Program Hours (Up to) 901 Carpenter, Rough 1040 902 Concrete Finisher (Paving) 1040 903 Concrete

More information

DOZERS. Tractor equipped with a front mounted earthmoving blade is known as bulldozer or dozer.

DOZERS. Tractor equipped with a front mounted earthmoving blade is known as bulldozer or dozer. DOZERS Tractor equipped with a front mounted earthmoving blade is known as bulldozer or dozer. Blade is lowered to cut the soil and push the soil in front of blade. It unloads the soil by pushing it over

More information

http://www.dir.ca.gov/oprl/pwd/determinations/northern/nc-023-102-1.pdf http://www.dir.ca.gov/oprl/pwd/determinations/northern/nc-023-63-1.pdf. COST ESTIMATE FOR PACIFICA QUARRY

More information

ATTACHMENT E: CONSTRUCTION EQUIPMENT SUMMARY

ATTACHMENT E: CONSTRUCTION EQUIPMENT SUMMARY ATTACHMENT E: CONSTRUCTION EQUIPMENT SUMMARY Equipment Use Improve Access Roads (per mile) Bulldozer Grade access roads 1 4 10 Road Grader Grade access roads 1 4 10 Loader Load haul trucks, transport materials

More information

Kansas Department of Transportation

Kansas Department of Transportation Kansas Department of Transportation STANDARD JOB CLASSIFICATIONS AND DESCRIPTIONS ASPHALT PAVER SCREED OPERATOR (Power Equipment Operator) Makes sure paver is in proper position before moving off the joint.

More information

CONSTRUCTION and OFF ROAD EQUIPMENT

CONSTRUCTION and OFF ROAD EQUIPMENT CONSTRUCTION and OFF ROAD EQUIPMENT QUICK REFERENCE GUIDE Vehicle Valuation Services, Inc. 1 South 450 Summit Avenue Suite 185 Oakbrook Terrace, IL 60181 888.475.9975 Fax: 888.475.9935 www.vvsi.com Vehicle

More information

Appendix 4-2-C Project Air Emissions Inventory

Appendix 4-2-C Project Air Emissions Inventory Appendix A CALPUFF and CALMET Methods and Assumptions Appendix 4-2-C Project Air Emissions Inventory C.1 Introduction For the purposes of estimating effects on air quality associated with the Project,

More information

Eligibility Criteria to Undertake an Advanced Technical Test

Eligibility Criteria to Undertake an Advanced Technical Test Eligibility Criteria to Undertake an Advanced Technical Test 1. The Scheme is supported by a cache of trained, experienced and qualified testers. It is essential that testers working within the Scheme

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

2a. Excavating and Lifting

2a. Excavating and Lifting Construction Methods 110401542 2a. Excavating and Lifting Dr. Khaled Hyari Department of Civil Engineering Hashemite University Introduction Excavator: A power-driven digging machine Three Major types

More information

**Equipment production**

**Equipment production** Construction operations And methods **Equipment production** The Equipment that will be covered on the exam and in this section are; Dozers Graders Scrapers Loaders Excavators Cranes(will discuss another

More information

Western Land Area Programmatic Environmental Assessment. APPENDIX K: Climate

Western Land Area Programmatic Environmental Assessment. APPENDIX K: Climate APPENDIX K: Climate Climate Prepared by: KB Environmental Sciences, Inc. December 2017 This page is left intentionally blank. Table of Contents Page 1 Introduction... 1 2 Construction... 1 2.1 On-Road

More information

Appendix G Aquilla Lake Pool Rise Recreational Resources

Appendix G Aquilla Lake Pool Rise Recreational Resources Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative

More information

CITY OF REDLANDS EQUIPMENT OPERATOR IN TRAINING (OIT) EQUIPMENT OPERATOR I/II

CITY OF REDLANDS EQUIPMENT OPERATOR IN TRAINING (OIT) EQUIPMENT OPERATOR I/II CITY OF REDLANDS EQUIPMENT OPERATOR IN TRAINING (OIT) EQUIPMENT OPERATOR I/II DEFINITION Under immediate supervision (Equipment Operator in Training) or general supervision (Equipment Operator I) or direction,

More information

FAIR WAGE SCHEDULE Road Building

FAIR WAGE SCHEDULE Road Building City Manager's Office Fair Wage Office Human Resources Division 100 Queen treet West City Hall, 18 th Floor, West Tower Toronto, Ontario M5H 2N2 Tel: 416-392-7300 Fax: 416-392-0801 fairwage@toronto.ca

More information

APPENDIX B. POTENTIAL CONSTRUCTION EQUIPMENT

APPENDIX B. POTENTIAL CONSTRUCTION EQUIPMENT . POTENTIAL CONSTRUCTION EQUIPMENT Table B-1. Alternative 1 (Options A and B) and Alternative 3 Alternative 1 (Options A and B) and Alternative 3 Overhead Transmission Line and Poles Removal of conductors

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

APPENDIX C AIR QUALITY

APPENDIX C AIR QUALITY C.1 CONSTRUCTION APPENDIX C AIR QUALITY Construction activities associated with the Proposed Action are set to begin July 2020 and be completed by May 2023. Potential sources of construction emissions

More information

*Due to the shift of $1.00 from H&W to Pension below is the corrected rates for 6/1/17 APPENDIX 1

*Due to the shift of $1.00 from H&W to Pension below is the corrected rates for 6/1/17 APPENDIX 1 *Due to the shift of $1.00 from H&W to Pension below is the corrected rates for 6/1/17 APPENDIX 1 SCHEDULE A CLASSIFICATIONS AND WAGE SCALES On all work covered by this Agreement, and in all instances

More information

Pearson Edexcel Level 2 NVQ Certificate in Plant Operations (Construction) (QCF) 601/6018/4

Pearson Edexcel Level 2 NVQ Certificate in Plant Operations (Construction) (QCF) 601/6018/4 Amendment Notification May 2015 CITB, the Sector Skills Council (SSC) for Construction, in consultation with the industry, have changed the National Occupational Standards (NOS) so it is important we update

More information

Schedule of Equipment Rates

Schedule of Equipment Rates SCHEDULE OF EQUIPMENT RATES FEDERAL EMERGENCY MANAGEMENT AGENCY RESPONSE AND RECOVERY DIRECTORATE INFRASTRUCTURE DIVISION WASHINGTON, D.C. 20472 The rates on this Schedule of Equipment s are for equipment

More information

Defense Logistics Agency Troop Support. Construction and Equipment. Heavy Equipment Procurement Program HEPP. Customer Handbook March 2017

Defense Logistics Agency Troop Support. Construction and Equipment. Heavy Equipment Procurement Program HEPP. Customer Handbook March 2017 Defense Logistics Agency Troop Support Construction and Equipment Heavy Equipment Procurement Program HEPP Customer Handbook March 2017 HEPP Table of Contents 1. Introduction... 3 2. HEPP Program... 3

More information

Contact Us: T: +27 (0) E: FTTA Building C5, Denel North, Atlas Rd, Kempton Park

Contact Us: T: +27 (0) E: FTTA Building C5, Denel North, Atlas Rd, Kempton Park Contact Us: T: +27 (0)86 196 1177 E: training@fezamax.co.za FTTA Building C5, Denel North, Atlas Rd, Kempton Park www.buildmax.co.za Training Academy Fezamax is a wholly owned subsidiary of Buildmax Limited

More information

Construction Emissions Estimates ICTF Modernization Project Long Beach, California

Construction Emissions Estimates ICTF Modernization Project Long Beach, California Construction Emissions Estimates ICTF Modernization Project Long Beach, California prepared for: Union Pacific Railroad Company October 2007 prepared by: Sierra Research, Inc. 1801 J Street Sacramento,

More information

TABLE OF CONTENTS RADIAL TYRES BIAS TYRES

TABLE OF CONTENTS RADIAL TYRES BIAS TYRES TABLE OF CONTENTS T.R.A. CLASSIFICATION OF OFF-THE-ROAD TYRES 1 TYPE OF TREAD 1 T.R.A. (Tyre and Rim Association) CODE 2 TREAD THICKNESS 2 YOKOHAMA TYRE SPECIFICATION CODE 2 CONVERSION CHART 2 RADIAL TYRES

More information

CEM 417 WEEK 6. CONSTRUCTION TECHNOLOGY & maintenance. Construction Plants 22/02/2011 WEEK 6 CONSTRUCTION PLANTS

CEM 417 WEEK 6. CONSTRUCTION TECHNOLOGY & maintenance. Construction Plants 22/02/2011 WEEK 6 CONSTRUCTION PLANTS CONSTRUCTION TECHNOLOGY & maintenance CEM 417 SOURCES FROM slide: MOHD AMIZAN MOHAMD MOHD FADZIL ARSHAD SITI RASHIDAH MOHD NASIR FKA, UiTM Shah Alam. WEEK 6 Construction Plants WEEK 6 CONSTRUCTION PLANTS

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

Appendix D Noise Data

Appendix D Noise Data Appendix D Noise Data Construction Noise Summary Lmax (dba) at Various Leq (dba) at Various Construction Phase 50 100 200 400 800 1,600 3,200 6,400 50 100 200 400 800 1,600 3,200 6,400 Phase 1 Decommissioning

More information

All Users of the City of Denver Prevailing Wage Schedules

All Users of the City of Denver Prevailing Wage Schedules Career Service Authority Denver s Human Resource Agency 201 W. Colfax, Department 412 Denver, CO 80202 p: 720.913.5751 f: 720.913.5720 www.denvergov.org/csa TO: FROM: All Users of the City of Denver Prevailing

More information

Where Quality makes the Difference...

Where Quality makes the Difference... Concept/Design/Photography : Intelligent E-Business Solutions Where Quality makes the Difference... P.O. Box: 5723-Manama - Kingdom of Bahrain, Tel.: 17 62 0551, Fax: 17 62 0833 Instagram: @ALHAIDARIYA,

More information

Teacher Assessment Blueprint. Heavy Equipment. Test Code: 5913 / Version: 01. Copyright 2007 NOCTI. All Rights Reserved.

Teacher Assessment Blueprint. Heavy Equipment. Test Code: 5913 / Version: 01. Copyright 2007 NOCTI. All Rights Reserved. Teacher Assessment Blueprint Heavy Equipment Test Code: 5913 / Version: 01 Copyright 2007 NOCTI. All Rights Reserved. General Assessment Information Blueprint Contents General Assessment Information Written

More information

Hydraulic power is the key to the utility of many excavators.

Hydraulic power is the key to the utility of many excavators. CHAPTER Construction Planning, Equipment, and Methods EXCAVATORS Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 8 By Dr. Ibrahim Assakkaf ENCE 420 Construction

More information

Highway and Heavy Master Job Classifications OLD versus NEW

Highway and Heavy Master Job Classifications OLD versus NEW Highway and Heavy Master Job Classifications OLD versus NEW Position Title Old Number New Number Laborer, common (general labor work) 101 101 Laborer, skilled (assisting skilled craft journeyman) 102 102

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING

SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING WEEKLY REPORT SPREAD 1 AUGUST 13 T H TO AUGUST 18 TH Suite 600, 214-11 Ave. SW Calgary, AB, Canada T2R 0K1 T 403.237.0606

More information

Auction Ring 1 -Ramp - North Auction Theatre

Auction Ring 1 -Ramp - North Auction Theatre Edmonton, AB, CAN - Oct 24, 2017 - Index Summary All times listed are approximate. Day 1 - Tuesday October 24 2017 Auction Ring 1 -Ramp - North Auction Auction Ring Auction Ring 1 -Ramp - North Auction

More information

INDUSTRIAL CONSTRUCTION: A Comprehensive Guide to the Heavy Equipment and Tools of the Trade

INDUSTRIAL CONSTRUCTION: A Comprehensive Guide to the Heavy Equipment and Tools of the Trade INDUSTRIAL CONSTRUCTION: A Comprehensive Guide to the Heavy Equipment and Tools of the Trade Table of Contents If you know where you re going, go ahead and click on a chapter. Introduction/Chapter 1: Understanding

More information

Auction Ring 1 -Ramp - North Auction Theatre

Auction Ring 1 -Ramp - North Auction Theatre Edmonton, AB, CAN - Jun 12, 2018 - Index Summary All times listed are approximate. Day 1 - Tuesday June 12 2018 Auction Ring 1 -Ramp - North Auction Auction Ring Auction Ring 1 -Ramp - North Auction 1-52

More information

General Decision Number: MN /04/2011 MN15. State: Minnesota. Construction Type: Highway

General Decision Number: MN /04/2011 MN15. State: Minnesota. Construction Type: Highway 1of 5 General Decision Number: MN100015 02/04/2011 MN15 State: Minnesota Construction Type: Highway Counties: Dodge, Fillmore, Freeborn, Goodhue, Houston, Mower, Olmsted, Rice, Steele, Wabasha and Winona

More information

29 CFR Material handling equipment

29 CFR Material handling equipment Earthmoving equipment; General. 1926.602(a)(1) These rules apply to the following types of earthmoving equipment: scrapers, loaders, crawler or wheel tractors, bulldozers, off-highway trucks, graders,

More information

FEMA's Schedule of Equipment Rates

FEMA's Schedule of Equipment Rates DEPARTMENT OF HOMELAND SECURITY FEDERAL EMERGENCY MANAGEMENT AGENCY DISASTER ASSISTANCE DIRECTORATE PUBLIC ASSISTANCE DIVISION WASHINGTON, D.C. 20472 www.fema.gov/government/grant/pa/eqrates.shtm (May

More information

Side Cutter Kit (Left and Right - fits all 68", 72", 80" Buckets) 48" Pallet Fork

Side Cutter Kit (Left and Right - fits all 68, 72, 80 Buckets) 48 Pallet Fork Side Cutter Kit (Left and Right - fits all 68", 72", 80" Buckets) These Bolt On Side Cutters (BOSC) greatly extend bucket service life and improve penetration power into hard packed soil or stock piled

More information

NSRBA 2017 EQUIPMENT DESCRIPTION. Purchase Price 2017 Monthly Rental % Monthly Rate Hourly Rate Daily Rate

NSRBA 2017 EQUIPMENT DESCRIPTION. Purchase Price 2017 Monthly Rental % Monthly Rate Hourly Rate Daily Rate AIR EQUIPMENT & TOOLS: Compressors: Gas or Diesel, cfm @ 100 psi Gas or Diesel, cfm @ 100 psi 85-150 cfm $27,272.70 7% $1,909.09 $13.00 $130.00 151-175 cfm $34,848.45 7% $2,439.39 $13.50 $135.00 176-250

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

ALL AMERICAN CANAL LINING PROJECT. CM Status as of July 31, 2008

ALL AMERICAN CANAL LINING PROJECT. CM Status as of July 31, 2008 ALL AMERICAN CANAL LINING PROJECT CM Status as of 1 AACLP STATIONS 2 Reach 1A Reach 1B Reach 2 Reach 3 Reach 2 2 SAFETY 3 Monthly Injury/Illness Data KPC 0 Recordable accidents for the month of 1 Recordable

More information

EQUIPMENT HIRE Stawell Road PO Box 241 Horsham Victoria 3400 Phone: (03) Facsimile: (03)

EQUIPMENT HIRE Stawell Road PO Box 241 Horsham Victoria 3400 Phone: (03) Facsimile: (03) EQUIPMENT HIRE INTRODUCTION CONTENTS Millers are a long established plant hire company with a solid foundation in Victoria. We have become established from over 2 generations and 40 years in the industry.

More information

Whatcom County Invitation to Bid Bid #17-09

Whatcom County Invitation to Bid Bid #17-09 Invitation to Bid NOTICE IS HEREBY GIVEN that sealed bids will be received by Purchasing at their fice in the Whatcom County Administrative Services Finance Office in Whatcom County Courthouse, 311 Grand

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

General Decision Number: MN /15/2012 MN10. Superseded General Decision Number: MN State: Minnesota. Construction Type: Highway

General Decision Number: MN /15/2012 MN10. Superseded General Decision Number: MN State: Minnesota. Construction Type: Highway Page 1 of 5 > General Decision Number: MN120010 06/15/2012 MN10 Superseded General Decision Number: MN20100020 State: Minnesota Construction Type: Highway Counties: Anoka, Carver, Chisago, Dakota, Hennepin,

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

SEWER AND WATERMAIN CONSTRUCTION

SEWER AND WATERMAIN CONSTRUCTION Corporate Services Fair Wage Office 18 th Floor, West Tower, City Hall Tel: 416-392-7300 Fax: 416-392-0801 Hotline: 416-392-FAIR E-mail: fairwage@toronto.ca Visit us at www.toronto.ca/fairwage FAIR WAGE

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

FarmSmart January 20,2018

FarmSmart January 20,2018 FarmSmart 2018 January 20,2018 NEW HTA subsection 1(1) definition: road-building machine means a self-propelled vehicle of a design commonly used in the construction or maintenance of highways that, (a)

More information

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical 4v ^c 0:01'1 S0^O c.. ^ '^ W E. G. PIERCY i^ x zoto/off/zq,.'ftrif4^#ft^^,' r Mechanical Civil Protection & Control Transmission &

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

ADDENDUM #2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18

ADDENDUM #2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18 November 29, 2018 ADDENDUM 2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18 Q1. Do contractors not need to be on the Watershed Improvements Pre-Qualifications List to submit on the RP031-18 Watershed

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Highway and Heavy

More information

Roadway Erosion Control 2017 CONTRACT NO ADDENDUM NUMBER ONE

Roadway Erosion Control 2017 CONTRACT NO ADDENDUM NUMBER ONE Department of Aviation Airport Office Building 8500 Peňa Boulevard Denver, Colorado (303) 342-2200 www.flydenver.com April 25, 2017 Roadway Erosion Control 2017 CONTRACT NO. 201732622 ADDENDUM NUMBER ONE

More information

CONSTRUCTION EQUIPMENT

CONSTRUCTION EQUIPMENT Your Preferred One Stop Shop for over 43 Years CONSTRUCTION EQUIPMENT CONCRETE POWER & AIR MATERIAL HANDLING QUARRYING WASTE MANAGEMENT SERVICE & PARTS DUBAI ABU DHABI AL-AIN BASRA - IRAQ cmcgulf.com CONSTRUCTION

More information

PROCEDURE. Revision: 10. Author: D Thomas CONTENTS

PROCEDURE. Revision: 10. Author: D Thomas CONTENTS PROCEDURE Title: Mobile Equipment Standards Procedure No: P314.707 Issue: 1 Revision: 10 Operative Date: 25/06/2018 Department: HSEC Sect./Classification: Vehicles/Mobile Equipment Author: D Thomas Approver

More information

Where Quality makes the Difference...

Where Quality makes the Difference... Where Quality makes the Difference... P.O. Box: 5723-Manama - Kingdom of Bahrain, Tel.: 17 62 0551, Fax: 17 62 0833 Instagram: @ALHAIDARIYA, E.mail: haidarya@batelco.com.bh - info@batelco.com 1 You have

More information

Get Your Done Anywhere In The World

Get Your Done Anywhere In The World Get Your Done Anywhere In The World Table of Contents 1 Outline of OFF-THE-ROAD TIRES 3 Tire Maintenance TRA Classification of OFF-THE-ROAD TIRES...2 Tread Pattern...2 Tread Thickness...3 Construction

More information

Appendix H TRAFFIC IMPACT ANALYSIS

Appendix H TRAFFIC IMPACT ANALYSIS Appendix H TRAFFIC IMPACT ANALYSIS Teichert Boca Quarry Expansion Traffic Impact Analysis Prepared for Teichert Aggregates Prepared by TRANSPORTATION CONSULTANTS, INC. LSC Transportation Consultants, Inc.

More information

SEWER AND WATERMAIN CONSTRUCTION

SEWER AND WATERMAIN CONSTRUCTION Fair Wage Office 100 Queen Street West City Hall, 18 th Floor, West Tower Toronto, ON M5H 2N2 Tel: 416-392-7300 Fax: 416-392-0801 Hotline: 416-392-FAIR E-mail: fairwage@toronto.ca Visit us at www.toronto.ca/fairwage

More information

Patton Hill Road (Four Inch Main), Project No

Patton Hill Road (Four Inch Main), Project No Patton Hill Road (Four Inch Main), Project No. 2016100 MP-5.01 MOBILIZATION (3% MAX) 1 LS MP-5.02.8(d) 8" DIP (CLASS 350) ALL DEPTHS 600 LF MP-5.02.6(p) 6" PVC ALL DEPTHS, INCLUDING BEDDING 10 LF MP-5.02.4(p)

More information

FEMA's Schedule of Equipment Rates

FEMA's Schedule of Equipment Rates DEPARTMENT OF HOMELAND SECURITY EMERGENCY PREPAREDNESS AND RESPONSE DIRECTORATE RECOVERY DIVISION PUBLIC ASSISTANCE BRANCH WASHINGTON, D.C. 20472 The rates on this Schedule of Equipment Rates are for applicant-owned

More information

FAIR WAGE SCHEDULE Sewer and Watermain

FAIR WAGE SCHEDULE Sewer and Watermain City Manager's Office Fair Wage Office Human Resources Division 100 Queen Street West City Hall, 18 th Floor, West Tower Toronto, Ontario M5H 2N2 Tel: 416-392-7300 Fax: 416-392-0801 fairwage@toronto.ca

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount R J Grondin & Sons - Gorham, ME $1,436,720.00 Shaw Brothers Construction, Inc. - Gorham, ME $1,476,398.83 Pratt & Sons, Inc. - Minot, ME $1,733,615.00 Page 1 of 13 R J Grondin

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks)

Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks) Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks) 1. Personal Info: Ensure your legal company name is on the form. 2. Equipment Info: Ensure you complete all

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

from OCSD Chemical Treatment Facility. Table SUM-A Maximum Daily Construction by Phase (no mitigation) Phase CO (lb/day) ROC (lb/day) NOx (lb/day) SOx (lb/day) Combustion Fugitive PM10 Total PM10 PM10

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE Construction Type: Commercial County

More information

GREASE TIME RATE SINGULARLY OPERATED MACHINES

GREASE TIME RATE SINGULARLY OPERATED MACHINES LOCAL 138 INTERNATIONAL UNION OF OPERATING ENGINEERS SCHEDULE A Heavy & Highway Construction GREASE TIME RATE SINGULARLY OPERATED MACHINES Period June 1, 2017 thru May 31, 2018 HEAVY & HIGHWAY CONSTRUCTION

More information

APPLICATION TO CONVERT FROM A FULL CPCS COMPETENT OPERATOR CARD TO AN MPQC OPERATOR CARD

APPLICATION TO CONVERT FROM A FULL CPCS COMPETENT OPERATOR CARD TO AN MPQC OPERATOR CARD APPLICATION TO CONVERT FROM A FULL CPCS COMPETENT OPERATOR CARD TO AN MPQC OPERATOR CARD This application form is appropriate for individuals applying to convert their BLUE CPCS Competent Operator card

More information

SECTION 11 Mobile work shop truck 100. SECTION 12 Amphibious dredger 12. SECTION 13 Tyre shovel 500. SECTION 14 Fork lift 300

SECTION 11 Mobile work shop truck 100. SECTION 12 Amphibious dredger 12. SECTION 13 Tyre shovel 500. SECTION 14 Fork lift 300 GENERAL ESTABLISHMENT FOR WATER AND SEWERAGE REQUIREMENT Code Description Qty. SECTION 1 Aluminuim Salphate 20000 ton SECTION 2 Chlorine gas 5000 ton SECTION 3 Bleaching powder 500 ton SECTION 4 Chlorinators

More information