Power System reinforcements the hardanger connection

Size: px
Start display at page:

Download "Power System reinforcements the hardanger connection"

Transcription

1 Power System reinforcements the hardanger connection E. HILLBERG, A. HOLEN G. ANDERSSON L. HAARLA NTNU, (NO) ETH Zürich, (CH) Aalto University, (FIN 1 - The following minimum security criterion is applied in the Norwegian power system: a single fault may result in the disconnection of up to 200 MW load (500 MW in situations during maintenance), [3]. Summary In order to increase the transmission capacity and security of supply to the Bergen region in Norway, the Norwegian government granted the concession of a new 90 km 400 kv overhead line into the Bergen region in July This decision has been considered highly controversial since the new line is planned to go through the picturesque landscape of the national romantic region of Hardanger. Due to public resistance, the Norwegian government established four independent committees to evaluate the feasibility of a 70 km 400 kv submarine cable connection, as an alternative to the proposed overhead line. Not only the length of this cable was challenging but also the fact that it had to be laid at a depth of 800 meters in the Hardanger fjord. This paper describes the work performed by the committee nominated to assess the power system related aspects of installing the new transmission line as a submarine AC- or DCpower cable, and the consequences of increased cabling in the Norwegian grid. The full report of this committee is described in [5]. The paper includes an adequacy and security assessment of the power system in the Bergen region, with and without the new line. 1. Introduction It is a well-established fact that modern society is dependent on a safe and reliable supply of electrical energy. Several investigations show that the electricity power system is the most important infrastructure, on which all other systems depend. Most customers tolerate short interruptions, but long and widespread interruptions can have serious consequences on society and are related with great costs. This fact has clearly been established after the major interruptions affecting different systems around the world in recent decades, [1]. Many power systems worldwide utilise the N 1 criterion to operate the systems in a sound and reliable manner. This is also typically the case in the Norwegian main grid, but in some parts of the system, this criterion cannot always be fulfilled 1. One such area is on the west coast of Norway, the Bergen region, including the second largest city in Norway: Bergen. The annual consumption in the Bergen region is approximately 8.8 TWh, with a maximum peak load of 1.8 GW. Installed production has a total capacity of 1.0 GW and the region is normally connected to the main grid via two 300 kv transmission lines with an N 1 secure transmission capacity of around 0.9 GW. In 2010, a CHP (Combined Heat and Power Plant) with a total installed electric capacity of MW was put into operation. However, electricity as well as heat generation is for the plant only, and the current Norwegian governmental policy generally excludes thermal generation in the power market if the plant does not have CCS (Carbon Capture and Storage) technology implemented. There are a few exceptions where concession has already been given. Since the power generation in the region is primarily hydropower, with limited water storage capacity, the region is very sensitive to the level of precipitation. Several actions have been taken to decrease the vulnerability of the region: 4 No February 2012 ELECTRA electra 260.indd 4 13/01/12 16:09

2 Increased regulation of the power generation within the region, through market control by the Norwegian TSO (Transmission System Operator) Statnett, in order to limit the required power transfer to the region Implementation of System Integrity Protection Schemes (SIPS) in order to have an increased secure power transfer capacity to the region while keeping the effects of disturbances limited to controlled load shedding Radial operation of the system in times with limited generation capacity within the region, decreasing the risk of total blackout but increasing the risk of partial blackout. In addition to these actions, a new transmission line is planned, which would improve the interconnection between the region and the main grid. This paper is organised as follows: In section 2, the background to the work is described, with the methodology and methods described in section 3. A reliability assessment of today s situation and the reinforced system are found in sections 4 and 5, respectively. Conclusions and recommendations are included in section 6, with an epilogue of the work given in section background The Norwegian power system is a part of the Nordic synchronous system, which also includes the power systems in Sweden, Finland, and Eastern Denmark. The Norwegian system is strongly interconnected with Sweden in the south, and further north the system is interconnected with Sweden and Finland. There are also connections to Western Denmark and the Netherlands through HVDC links. The main transmission system in Norway is shown in Figure 1b. The Norwegian power system is facing a massive expansion, with plans to install or upgrade around 3500 km of power lines until The goal of this expansion plan is to increase the power transfer capacity and to ensure a reliable power supply in Norway, and to reinforce the grid in order to serve existing and planned international connections [3]. One focus area is the transmission system feeding Bergen and the surrounding region, in this paper referred to as the Bergen region, see Figure 1a. At present, this region is fed through two 300 kv lines, which constitute a limit on the power transfer to and from the region. During the winter, the region is characterised by high load and low precipitation, and restricted power import. On the other hand, during the summer, generation surplus is exported from the region. With plans of increased hydro and wind production, fast generation curtailment may be needed to avoid overloading in the case of line fault during heavy export situations. Fig. 1: The transmission system in a) the Bergen region (blue and red lines represent 300 kv and 400 kv lines, respectively, dotted and dashed lines are planned system extensions) [9] and b) Norway [3] 6 No February 2012 ELECTRA electra 260.indd 6 13/01/12 16:09

3 In order to increase the transfer capacity between the Bergen region and the main grid, thus improving the reliability of the power supply, the Norwegian TSO planned an overhead line between Sima and Samnanger, as indicated in Figure 1a. The new line would create a third connection to the region, enabling N 1 secure operation during periods with limited local generation, maintenance or upgrade of existing lines. The region with mountains and fjords where this line would be installed, the Hardanger region, is regarded a national heritage Due to massive resistance against the overhead line solution, the Norwegian government established four committees to assess the feasibility of a submarine cable connection. The tasks of the committees were to investigate the following: First committee: Technology, economy and other aspects related to the submarine cable connection Second committee: Power system related aspects of a cable connection Third committee: Consequences of a delay in the construction of the connection Fourth committee: Economic consequences on the society due to a cable connection The installation of such a cable is however not a trivial task; a depth of up to 800 meters, steep gradients, and a length of 70 km all form technological and economic challenges. The submarine cable would not completely replace the overhead line, since a 20 km overhead line would be needed to connect the submarine cable with the Samnanger station. Furthermore, large reactive compensation installations would be needed at both cable termination points, with considerable local impact on the landscape and community. The committees started their work in September 2010 and delivered their final reports to the government on 1 February 2011, see [4]-[7]. This paper describes the work performed by the committee nominated to assess the power system related aspects of installing the new transmission line as a submarine AC- or DCpower cable. The committee focused its work on how the power flow and the reliability of the power supply to the Bergen region would be affected by different solutions for the Sima- Samnanger connection. The results have been compared with an assessment of the present situation, in order to quantify the level of impact of the different solutions. A full description of the mandate of the four committees is found in [2]. 3. Methodology and reliability analysis models As shown in Figure 1a, the transmission system connecting the Bergen region to the rest of the Norwegian power system consists at present of two 300kV lines: North: Aurland Fardal Modalen South: Mauranger Samnanger These two lines, collectively referred to as the BKK corridor, are the main contributors to the reliability of the power system in the Bergen region. The line lengths used in this study, when quantifying the reliability level related to the north and south links, are 150 km and 100 km, respectively. In this study, simplified models, limited to the present and future interconnections in the BKK corridor, are used to quantify: the adequacy (power flow) of the transmission system, the probability (hours per year) that the Bergen region will face a situation where system is not N 1 secure (i.e. vulnerable to the loss of one of the lines feeding the region) the return period (years) of power interruption in the Bergen region due to faults on the transmission lines combined with insufficient local generation In order to assess the probability of power interruption in the Bergen region, statistical data describing the number of hours per year with reduced security has been used. The 8 No February 2012 ELECTRA electra 260.indd 8 13/01/12 16:09

4 Fig. 2: Actual number of hours during years where the N 1 security criterion was not satisfied in the Bergen region, [10] number of hours for the years with reduced operational security, i.e. where the N 1 criterion was not satisfied, observed by the TSO (Statnett) are presented in Figure 2. This data is used as a base to define the probability space (p) of having a reduced operational security: : 1300 h / 5 years p = : h / 1 year p = 0.15 The lower limit 0.03 excludes the year 2010, while the upper limit 0.15 assumes that year 2010 is a typical year. A reinforcement of the transmission system, including a third connection to the Bergen region (Sima Samnanger) is studied for the following solutions: Overhead line, dimensioned for 2000 MVA, approximate length: 90 km Submarine cable, AC, single set, dimensioned for 1000 MW, approximate length 70 km, in series with a 20 km overhead line (faults on this line have only minor influence and are neglected from the calculations) Submarine cable, AC, dual set, dimensioned for 2000 MW, approximate length 70 km, in series with a 20 km overhead line. The faults on this line have only minor influence and are neglected from the calculations in this paper) Submarine cable, HVDC, single bipole, dimensioned for 1000 MW, approximate length: 70 km cable and 20 km overhead line (faults on this line have only minor influence and are ne- glected from the calculations in this paper) Submarine cable, HVDC, dual bipole, dimensioned for 1500 MW, approximate length: 70 km cable and 20 km overhead line (faults on this line have only minor influence and are neglected from the calculations in this paper) The motivation for the reinforcement is to allow N 1 secure operation under different operating situations: In the winter season during periods with heavy import into the Bergen region and limited local generation available due to limited hydro storage During maintenance and planned upgrading of the existing 300 kv overhead lines into the Bergen region In the summer season with surplus local generation and heavy export from the Bergen region 4. reliability assessment of the present situation 4.1 System Operation Winter In Norway, when the day ahead power market is settled, the TSO (Statnett) will check if the N 1 operation can be maintained without exceeding transmission limitations. This may not be possible without buying so-called special regulating power from 2 - In 2010, the total number of hours with reduced operational security was actually around 1700, [9]. In this study however, 1300 h has been used. No February 2012 ELECTRA 9 electra 260.indd 9 13/01/12 16:09

5 the separate market for regulating power. The price for special regulating power can be high, and, according to [11], the accumulated cost to the TSO from mid December 2009 to 22 February 2010 was 36 M NOK (approximately 4.5 M ), in the Bergen region alone. Due to low levels in the hydro storage and the uncertainty of the precipitation and load in the remaining winter period, the local generation company (BKK) decided on 22 February to save water instead of selling regulating power. This meant that there was no more special regulating power available in the Bergen region. The effect of this was that the N 1 criterion could no longer be fulfilled, which is shown by the actual power flow on the BKK corridor displayed in Figure 3a. At this stage, Statnett considered the best solution to be a separation of the transmission system, dividing the Bergen region in two sub-regions, each fed by a single line (i.e. radial operation). A single line fault could thus have led to a power interruption of considerable size, up to 1750 MW of load with up to customers, [8]and [11]. The cumulative probability of power interruption can be described by the curve 3 in Figure 3b, where the assumed fault frequency is 0.8 faults per 100 km of line per year, [12], and the total line length where a fault may lead to interruption is 830 km 4, [11]. The estimated probability of interruption is %, depending on the duration of this situation as indicated in Figure 3b. Although the assumption may be discussed, it is obvious that the risk was substantial. 4.2 Power System Operational Security Assessment An assessment of the probability of future power interruptions in the 3 - Faults are assumed to be exponentially distributed, with cumulative probability of interruption calculated as: F(t) = 1 -e -λt Where λ is the total fault frequency of the lines that lead to interru ption. 4 - Radial operation increased the systems vulnerability to faults, and the region was considered to be affected by failures on a considerably larger number of lines than the afore mentioned BKK corridor. Figure 3: System operation winter : a) Actual power flow and transfer capacity limits (short time and continuous N 1 limit) on the BKK corridor [8] b) Calculated probability of a power interruption in the Bergen region related to faults on the feeding transmission lines [5] 10 No February 2012 ELECTRA electra 260.indd 10 13/01/12 16:09

6 Figure 4: Calculated probability of future power interruption in the Bergen region related to faults on the feeding transmission lines, without changes in the present state grid, production or load, for the two previously specified values of the probability space (p), [5] Bergen region, due to faults occurring during periods with reduced operational security, is performed using a simplified system model (limited to the present and future interconnections in the BKK corridor) and the probability space (p) defined in section 3. Since only permanent faults are presumed to lead to an interruption, the fault frequency used in these calculations is approximated to 0.1 faults per 100 km of line per year (according to fault statistics [12] approximately 10% of all faults are of a permanent nature). The results, presented in Figure 4, show an estimated probability of interruption between 4-20 % for the coming five-year period, depending on the probability space (p) of having a reduced operational security. For the coming 15-year period, the estimated probability of interruption is %. It is important to keep in mind that these calculations are limited to the probability of failures only on the transmission lines in the BKK corridor, during reduced operational security, for the scenario of an unchanged system from the present state. 4.3 System Integrity Protection Schemes System Integrity Protection Schemes (SIPS), such as load shedding, generation curtailment, and/or network separation schemes, are utilised in the Bergen region to limit the consequences of faults at times of reduced system security. The SIPS are triggered by events, such as the disconnection of critical lines, transformers or buses; or by system response such as line overloading, bus under-voltage or underfrequency. This implies that, in cases where the N 1 criterion is not fulfilled, the system operation depends on the efficiency and reliability of the automatic SIPS. Such an operation scenario is referred to by Statnett as N ½ secure, relating to the inadequacy regarding the N 1 criteria, although more secure than the N 0 operation. 5. reliability assessment of the reinforced situation 5.1 Power System Adequacy Assessment The N 1 adequacy of the reinforced network is assessed using a simplified model of the power system in the Bergen region 5. The loss of the Mauranger Samnanger line is identified as giving the worst-case post-fault loading of the two remaining connections. A high transfer scenario is studied, with an import of 1800 MW 5 - A comprehensive power flow study described in [13] verifies the results achieved by the simplified model No February 2012 ELECTRA 11 electra 260.indd 11 13/01/12 16:09

7 Figure 5: Results from simplified power flow calculations, [5], for grid reinforcements with: a) overhead line, and b) single set submarine AC cable The return period of power interruption is assessed here using statistical data for fault frequency and fault duration, see [12], [14], and [15]. The fault frequency (of permanent faults) for both an overhead line and a subto the Bergen region. In Figure 5, postfault power flow results are shown, with the Sima-Samnanger connection as both an overhead line and a submarine cable. Approximately 2/3 of the total transmitted power to the Bergen region would flow on the new connection, if it were to be constructed as an overhead line. In the case of a submarine cable, the power flow on the new connection would increase to over 5/6 of the total transferred power. The reason for this highly asymmetric power flow distribution is due to the low reactance of the cable compared to the parallel path. This means that the single submarine cable set, rated 1000 MW, would be overloaded in the studied scenario. A solution to create a better power flow distribution would be to install a phase shifting transformer in series with the submarine cable. In such a case, it would be possible to distribute the load flow between the remaining lines in order not to overload any of the connections. The results achieved using simplified calculations are supported by the more detailed study described in [13]. 5.2 Power System Operational Security Assessment Table I: Overview of thermal capacity for: N 0 (intact grid), N 1 (single fault), and N 2 (two independent faults); and return period for insufficient transfer capacity for studied grid reinforcement alternatives for the two previously specified values of the probability space (p) 12 No February 2012 ELECTRA electra 260.indd 12 13/01/12 16:09

8 Figure 6: Return period for power interruption for grid reinforcements, [5], with: a) overhead line, and b) dual set of submarine AC cables marine (AC or DC) cable is approximated to 0.1 faults per 100 km of line per year. The fault duration for a line is assumed to be between hours, while for a cable it is assumed to be between hours 6. The fault frequency and duration for a phase shifting transformer is assumed to be in the same range as a 70 km long submarine cable, i.e faults per year with duration of hours. Similar assumptions are made for the HVDC system (excl. cable), i.e faults per year with a duration of hours. In Table I, the assessed return period of power interruptions is shown, for the studied grid reinforcement alternatives, together with approximate thermal capacities of each alternative. Here, the repair times are assumed to 50 hours for lines and 1000 hours for cables transformer and HVDC sys- tem. The impact of the time span of reparation time is shown in Figure 6, where the case with one overhead line is shown together with the case of a dual set of AC submarine cables. 6. Conclusions and recommendations The analysis presented in this paper shows that the following reinforcement alternatives would give a very high reliability: one overhead line, a dual AC cable set, two bipole HVDC cables. Adequate reliability would also be achieved with the alternatives: a single AC cable set with a phase shifting transformer, a single bipole HVDC cable. 6 - Due to the limited statistical data, the repair time of sub-marine cables is represented by a wide time span. In this way, the significance of having a very long repair time is shown in the reliability assessment 7- Due to the uneven distribution of power flow between the cable and the remaining line. No February 2012 ELECTRA 13 electra 260.indd 13 13/01/12 16:09

9 A single AC cable set gives only a small benefit compared with today s system, mainly due to the uneven distribution of power between the cable and the lines. The overhead line and the dual AC cable set are both identified as robust solutions, based on established technology, and they satisfy the requirements for the future scenarios described in [13]. The solution with dual bipole HVDC does also satisfy these requirements, if a satisfactory control strategy is developed. This committee did not assess the cost of the different cable alternatives; however, evaluations described in [4] shows that the relevant cable alternatives have an expected cost in the magnitude of 4 to 6 times the proposed overhead line. Furthermore, socioeconomic consequences and possible justification of spending this money to avoid an overhead line is discussed in [7], however without stating a specific conclusion. Briefly summarized: the proposed overhead line provides sufficient transmission capacity, is robust and reliable, and is definitely the most cost effective alternative. 7. Epilogue After the committees submitted their final reports, the Norwegian government decided on 1 March 2011 to adhere to the previously given concession of the overhead line connection between Sima and Samnanger. This decision was mainly based on the security of supply situation during the winter seasons, combined with the fact that a cable alternative was expected to take at least five additional years to complete, further extending the current vulnerable supply situation. Additionally, the extra cost was of course not in favour of a cable alternative. Local impact from the quite large reactive compensation installations needed for HVAC, or alternatively the AC/DC converter stations needed for HVDC, showed that cable alternatives might also be controversial. Finally, opting for a cable alternative in Hardanger could have given precedence to submarine cables elsewhere in Norway where conflicts between network expansion and nature conservation are likely. The importance of media involvement in this concession procedure has been analysed in [16]. The report concludes that the Hardanger connection was the fourth most reported news in Norway during 2010, and the question is raised whether informal information channels are replacing formal procedures. Anyway, results from scientific based methods to quantify the fundamental power system aspects, such as adequacy and security of supply, must always be carefully considered in the decision process, also in controversial cases, but getting the message through might be a challenge. Bibliography [1] D. Cooke, Learning from the Blackouts - Transmission System Security in Competitive Electricity Markets, International Energy Agency (IEA), 2007, available at: [2] The mandate of the four committees related to the submarine cable solution (Norwegian: Mandatet for de fire utvalgene knyttet til sjøkabelløsning), webpage: www. regjeringen.no/nb/dep/oed/aktuelt/ nyheter/2010/mandatet-for-de-fireutvalgeneknyttet-t.html?id=613179, accessed: [3] Network development plan 2010 (Norwegian: Nettutviklingsplan Nasjonal plan for neste generasjon kraftnett), Statnett, 2010, available at: [4] Report by committee 1 of the submarine cable study (Norwegian: Rapport fra sjøkabelutredningen Utvalg 1: Teknologi, økonomi og andre forhold knyttet til en sjøkabelløsning), , available at: 14 No February 2012 ELECTRA electra 260.indd 14 13/01/12 16:09

10 [5] Report by committee 2 of the submarine cable study (Norwegian: Rapport fra sjøkabelutredningen Utvalg 2: Virkninger for kraftsystemet ved kabling), , available at: www. regjeringen.no [6] Report by committee 3 of the submarine cable study (Norwegian: Rapport fra sjøkabelutredningen Utvalg 3: Konsekvensene av at man trenger lenger tid på en ny overføringsforbindelse til Bergensområdet), , available at: [7] Report by committee 4 of the submarine cable study (Norwegian: Rapport fra sjøkabelutredningen Utvalg 4: Samfunnsøkonomiske virkninger av sjøkabelalternative), , available at: [8] Updated assessment of security of supply in the Bergen area winter (Norwegian: Oppdatert vurdering av forsyningssikkerheten inn mot Bergensområdet vinteren ), Statnett, , available at: [9] Assessment of the need of Sima- Samnanger (Norwegian: Vurdering av behov for Sima-Samnanger), Statnett, , available at: [10] A. Lont, Next-generation transmission network - the path to increased capacity and improved security of supply (Norwegian: Neste generasjon sentralnett veien til øktnettkapasistet og høyre forsyningssikkerhet), Statnett, , avai- lable at: [11] Documentation of operating conditions in the BKK area winter (Norwegian: Dokumentasjon av driftsforhold inn mot BKKområdet vinteren ), Statnett, , available at: www. statnett.no [12] Annual statistics 2009: Interruptions and faults in the kv network (Norwegian: Årsstatistikk 2009 Driftsforstyrrelser og feil i kv nettet), Statnett, available at: www. statnett.no [13] Draft Memo - comparison of solutions Sima-Samnanger (Norwegian: Utkast til notat - samanlikning av systemløsninger Sima-Samnanger), Statnett, [14] Grid disturbance and fault statistics, Nordel, 2008, available at: www. entsoe.eu [15] CIGRE Working Group B1.21, Third-Party Damage to Underground and Submarine Cables, 2009, ISBN: [16] A. Ruud, Case Hardanger - An analysis of the formal concession process and media coverage related to the applied overhead line Sima-Samnanger (Norwegian: Case Hardanger - En analyse av den formelle konsesjonsprosessen og mediedekningen knyttet til den omsøkte luftledningen Sima-Samnanger), SINTEF Energy Research, , available at: www. cedren.no No February 2012 ELECTRA 15 electra 260.indd 15 13/01/12 16:09

Wide area monitoring and control activities in Norway and the Nordic power system

Wide area monitoring and control activities in Norway and the Nordic power system Working Group Meeting North American SynchroPhasor Initiative June 8-9, 2010, Vancouver, British Columbia Wide area monitoring and control activities in Norway and the Nordic power system Kjetil Uhlen,

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Explanatory document for the Nordic synchronous area proposal for ramping restrictions for active power output in accordance with Article 137(3) and

Explanatory document for the Nordic synchronous area proposal for ramping restrictions for active power output in accordance with Article 137(3) and Explanatory document for the Nordic synchronous area proposal for ramping restrictions for active power output in accordance with Article 137(3) and (4) of the Commission Regulation (EU) 2017/1485 of 2

More information

The Electric Power System

The Electric Power System The Electric Power System - Sweden- Swedish Power System 1 2 Basic facts 2014 Area: 450 295 km 2 Population: 9.6 Million Number of electricity consumers: 5.3 Million Number of TSOs: 1 Number of DSOs: 170

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2016

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2016 NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2016 16.11.2017 REGIONAL GROUP NORDIC Table of Contents 1 INTRODUCTION...4 1.1 DESCRIPTION OF THE REPORT... 4 1.2 HISTORY OF THE REPORT... 4 1.3 CONTACT PERSONS...

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Connection of power production. Stig Fretheim

Connection of power production. Stig Fretheim Connection of power production Stig Fretheim The project overarching objectives Reduce cost of grid connection of DG through facilitating use of new technologies and methods. (WP1) Describe background

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Regional Cooperation Infrastructure Development and Operation. EU Energy Governance. Olaf Ziemann Member of ENTSO-E s System Operations Committee

Regional Cooperation Infrastructure Development and Operation. EU Energy Governance. Olaf Ziemann Member of ENTSO-E s System Operations Committee Regional Cooperation Infrastructure Development and Operation EU Energy Governance 30 April 2014, Berlin Olaf Ziemann Member of ENTSO-E s System Operations Committee About ENTSO-E 41 TSOs from 34 countries

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Chapter 1. Overview of HVDC applications

Chapter 1. Overview of HVDC applications ELEC0445 - High Voltage Direct Current grids Part 1. Line Commutated Converters Chapter 1. Overview of HVDC applications Patricia Rousseaux t.vancutsem@ulg.ac.be Thierry Van Cutsem www.montefiore.ulg.ac.be/~vct

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

3 Existing National Grid

3 Existing National Grid 3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load

More information

NorNed. Europe s link for the future

NorNed. Europe s link for the future NorNed Europe s link for the future We take electricity for granted in our everyday lives. Without thinking about it, we switch on the lights, leave the coffee maker on and turn the vacuum cleaner on to

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

Introduction to transmission network characteristics - technical features. Slobodan Markovic EKC Athens,

Introduction to transmission network characteristics - technical features. Slobodan Markovic EKC Athens, Introduction to transmission network characteristics - technical features Slobodan Markovic EKC Athens, 06.03.2017 1 MAIN ISSUES The map shows the region that will be included in the network modelling

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

RENEWABLE ENERGY TRANSMISSION INTERCONNECTION. Line Tveter

RENEWABLE ENERGY TRANSMISSION INTERCONNECTION. Line Tveter RENEWABLE ENERGY TRANSMISSION INTERCONNECTION Line Tveter ltveter@kentlaw.edu Roadmap A. The Norwegian Electricity Sector The Basics B. The Norwegian Electricity Grid Organization and Regulation C. Grid

More information

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Report. the feasibility of

Report. the feasibility of Report on the feasibility of Additional Interconnection between India and Bangladesh Joint Technical Team (JTT) of India and Bangladesh July 2016 Contents 1.0 Background 1 2.0 Additional power export to

More information

Question Question 1.2-8

Question Question 1.2-8 Question 1.2-7 A dc transmission line running through a forest terrain is vulnerable to forest fires. If it is a bipolar line then both poles can be affected at the same time. What steps can be taken to

More information

Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University

Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University Contents Introduction Planned Network Reinforcement for 2020 The Three Machine Generic Model Subsynchronous Resonance

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Northern European power system scenarios for EMPS 2010 to 2030

Northern European power system scenarios for EMPS 2010 to 2030 Stefan Jaehnert Northern European power system scenarios for EMPS 21 to 23 Brukermøte Produksjonsplanlegging 22. Mai 213 1 Outline 1. Basic modelling assumption Northern Europe 2. 23 scenario development

More information

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Presenter: Bernard Magoro, System Operator, Transmission Division, Eskom SOC Holdings Date: 05 October 2018 Contents 1. Background

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

DG system integration in distribution networks. The transition from passive to active grids

DG system integration in distribution networks. The transition from passive to active grids DG system integration in distribution networks The transition from passive to active grids Agenda IEA ENARD Annex II Trends and drivers Targets for future electricity networks The current status of distribution

More information

Electric Power Research Institute, USA 2 ABB, USA

Electric Power Research Institute, USA 2 ABB, USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

MVDC link in a 33 kv distribution network

MVDC link in a 33 kv distribution network 24th International Conference & Exhibition on Electricity Distribution (CIRED) 12-15 June 2017 Session 3: Operation, control and protection MVDC link in a 33 kv distribution network Chao Long 1, Jianzhong

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Robustness and Cost Efficiency through User Flexibility in the Distribution Network

Robustness and Cost Efficiency through User Flexibility in the Distribution Network Washington, April 20, 2015 Robustness and Cost Efficiency through User Flexibility in the Distribution Network Knut Samdal, Research Director SINTEF Energy Research knut.samdal@sintef.no 1 SINTEF is the

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective 2 Storage: the DNO perspective Context to the storage boom Smarter Network Storage: What have we achieved?

More information

Modelling Analysis for Optimal Integration of Solar PV in National Power Grid of Japan

Modelling Analysis for Optimal Integration of Solar PV in National Power Grid of Japan USAEE/IAEE 36th North American Conference, Concurrent Session 28, Hilton Crystal City, Washington DC USA, September 25, 2018 Modelling Analysis for imal Integration of Solar PV in National Power Grid of

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Smart EV Managed Charging

Smart EV Managed Charging Smart EV Managed Charging Temporary management of the low voltage network Bob Hopkins, SSEN Daniel Hollingworth, EA Technology SSEN overview Scottish and Southern Electricity Networks owns: two electricity

More information

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014 City Power Johannesburg: Response to Potential Load Shedding Presented by : Stuart Webb General Manager : PCM October 2014 Topics to be discussed Background Challenges Options Available Summary 2 Background

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

NYCA LOLE Violations (Methods D and E )

NYCA LOLE Violations (Methods D and E ) Proposals for Cost Allocation of Regulated Reliability Solutions Associated with NYCA LOLE Violations (Methods D and E ) Presented by Jerry Ancona National Grid For Discussion by NYISO Electric System

More information

STEADY STATE ELECTRICAL DESIGN, POWER PERFORMANCE AND ECONOMIC MODELING OF OFFSHORE WIND FARMS

STEADY STATE ELECTRICAL DESIGN, POWER PERFORMANCE AND ECONOMIC MODELING OF OFFSHORE WIND FARMS STEADY STATE ELECTRICAL DESIGN, POWER PERFORMANCE AND ECONOMIC MODELING OF OFFSHORE WIND FARMS J.T.G. Pierik 1, M.E.C. Damen 2, P. Bauer 2, S.W.H. de Haan 2 1 Energy research Centre of the Netherlands

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Energy Storage Interconnection Initiative

Energy Storage Interconnection Initiative Energy Storage Interconnection Initiative Stakeholder Call November 25, 2014 Agenda Time Agenda Item Speaker 10:00-10:10 Introduction, Stakeholder Process Tom Cuccia 10:10-10:30 Applying the GIDAP to energy

More information

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector HVDC Innovative Technology for Smart Grids and Super Grids CEO Power Transmission Solutions, Siemens Energy Sector BritNed: Pre-launch Press Event Maasvlakte, March 31, 2011 Siemens AG 2011 Energy Sector

More information

April 25 Demand Response Resources Electricity Market Impacts

April 25 Demand Response Resources Electricity Market Impacts Welcome! Programme April 25 Demand Response Resources Electricity Market Impacts Increased elasticity on the demand side in case of shortage in production and/or transmission capacity is recognized as

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Transmission Grid Reinforcement with Embedded VSC-HVDC Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Outline Introduction HVDC-Light Transmission Technologies Embedded VSC-HVDC for AC Grid

More information

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E.

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E. Evaluating Losses in Electrical Equipment Focus on Transmission Utilities CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E. Contents Introduction Present Value of ongoing energy costs

More information

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Journal of American Science 2015;11(11)   Integration of wind Power Plant on Electrical grid based on PSS/E Integration of wind Power Plant on Electrical grid based on PSS/E S. Othman ; H. M. Mahmud 2 S. A. Kotb 3 and S. Sallam 2 Faculty of Engineering, Al-Azhar University, Cairo, Egypt. 2 Egyptian Electricity

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Value of the interconnectors in the Nordic countries

Value of the interconnectors in the Nordic countries Value of the interconnectors in the Nordic countries Jacopo Tattini PhD Student at Energy System Analysis Group System Analysis Division DTU Management Engineering Maurizio Gargiulo E4SMA Agenda Background

More information

Fueling Savings: Higher Fuel Economy Standards Result In Big Savings for Consumers

Fueling Savings: Higher Fuel Economy Standards Result In Big Savings for Consumers Fueling Savings: Higher Fuel Economy Standards Result In Big Savings for Consumers Prepared for Consumers Union September 7, 2016 AUTHORS Tyler Comings Avi Allison Frank Ackerman, PhD 485 Massachusetts

More information

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION SMART DIGITAL GRIDS For many years the European Union has been committed to the reduction of carbon dioxide emissions and the increase of the

More information

Smart Grid 2.0: Moving Beyond Smart Meters

Smart Grid 2.0: Moving Beyond Smart Meters Smart Grid 2.0: Moving Beyond Smart Meters Clean Energy Speaker Series State of the Smart Grid February 23, 2011 Prof. Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Power Grid & Blackouts. Prof. Ramzy R. Obaid

Power Grid & Blackouts. Prof. Ramzy R. Obaid Power Grid & Blackouts Prof. Ramzy R. Obaid With many thanks and appreciation to Professor Mohamed A. El Sharkawi Power System The electric power systems in the North America and Europe are probably the

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

MEDIA RELEASE. June 16, 2008 For Immediate Release

MEDIA RELEASE. June 16, 2008 For Immediate Release MEDIA RELEASE June 16, 2008 For Immediate Release Recommendations to Keep Trolleys Released Alternative Proposal for Trolleys Ensures City s Sustainability The Edmonton Trolley Coalition, a non-profit

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Click to edit title 18. Fachforum Netzbau und Betrieb

Click to edit title 18. Fachforum Netzbau und Betrieb The North Sea Off-Shore Grid a Vision to be Realised? Click to edit title 18. Fachforum Netzbau und Betrieb Köln, Click to 6.-7. edit Mai sub-title 2010 Dr. Matthias Luther transpower stromübertragungs

More information

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 01 July 2015 ISSN (online): 2349-784X Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC Ravindra Mohana

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

Power import, transboundary connections, Market Coupling. Grzegorz Onichimowski President of the Board, TGE S.A.

Power import, transboundary connections, Market Coupling. Grzegorz Onichimowski President of the Board, TGE S.A. Power import, transboundary connections, Market Coupling Grzegorz Onichimowski President of the Board, TGE S.A. Power import, transboundary connections, Market Coupling Conference Power Ring, December_2008

More information

Nordic co-operation when meeting System challenges

Nordic co-operation when meeting System challenges Nordic co-operation when meeting System challenges Evolving the market conference Ulla Sandborgh CEO Agenda > System challenges > System development plan > Strategies > Grid development > Tariff development

More information

Operational Objectives

Operational Objectives Module 1: Introduction Lecture 3 : Operating States Objectives In this lecture you will learn the following Operational Objectives of a Power System. Hierarchical Control in Power Systems. Issues of ownership

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

HOW OFFSHORE WIND CONCERNS THE SECURITY OF SUPPLY

HOW OFFSHORE WIND CONCERNS THE SECURITY OF SUPPLY Public funding by Programme: Research for Civil Security Maritime Security Offshore Wind Energy Safety and Security HOW OFFSHORE WIND CONCERNS THE SECURITY OF SUPPLY Presentation at the International Conference

More information

Transit Vehicle (Trolley) Technology Review

Transit Vehicle (Trolley) Technology Review Transit Vehicle (Trolley) Technology Review Recommendation: 1. That the trolley system be phased out in 2009 and 2010. 2. That the purchase of 47 new hybrid buses to be received in 2010 be approved with

More information

Technological Viability Evaluation. Results from the SWOT Analysis Diego Salzillo Arriaga, Siemens

Technological Viability Evaluation. Results from the SWOT Analysis Diego Salzillo Arriaga, Siemens Technological Viability Evaluation Results from the SWOT Analysis Diego Salzillo Arriaga, Siemens 26.04.2018 Agenda Study Objectives and Scope SWOT Analysis Methodology Cluster 4 Results Cross-Cluster

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Selective Coordination Enforcement:

Selective Coordination Enforcement: Selective Coordination Enforcement: Overcurrent Protective Device Basics by Tim Crnko The Basics of Selective Coordination Merely having a higher ampere overcurrent protective device (OCPD) feeding a lower

More information