HELIOS Injector Shielding in the Free Electron Laser Equipment Room

Size: px
Start display at page:

Download "HELIOS Injector Shielding in the Free Electron Laser Equipment Room"

Transcription

1 HELIOS Injector Shielding in the Free Electron Laser Equipment Room Scott O. Schwahn, Radiation Control Group Introduction The HELIOS injector (a.k.a., FEL Injector Test Area) project is intended to take place in the equipment room in the back room of the Free Electron Laser (FEL) facility, building 18, at Jefferson Lab. In order to run the injector, an area has to be built that has adequate shielding to prevent excessive personnel exposure. This Tech Note describes the calculations that were done to ensure that the estimated shielding is adequate for that purpose. HELIOS Injector Parameters and Source Term Assumptions The HELIOS injector is assumed to have the following parameters, which are based on the literature and on conversations with Ron Lauzé of Jefferson Lab and s Lorraine Marceau-Day of Louisiana State University s Center for Advanced Microstructures & Devices (CAMD). Energy: Current: Duty Factor: Ring fill time: Injection: 100 MeV 10 ma peak 2x10-7 (200 ns, 1Hz) ~6 minutes, including ramping time 3 times per day Shielding Calculations The first step in the process was to make some rough estimates of shielding needs, based on both photon production and on neutron production. This step was principally done using NCRP 51. It is fairly routine to make these calculations, and the final results were not based on these calculations, rather on Monte Carlo simulation, so the steps will not be detailed here. Suffice it to say that the estimates based on NCRP 51 matched reasonably closely to the Monte Carlo simulation (which is considered to be more accurate), so as to verify the Monte Carlo calculation. The latter will be presented in this tech note, along with a summary of the NCRP 51 calculations. The initial design idea of the HELIOS injector (an idea other than that of the author s) was to dig out the dirt between the FEL and the equipment room and to use that area as the injector test cave. However, initial Monte Carlo calculations demonstrated that the amount of shielding needed to protect workers in the HELIOS injector area from radiation from the FEL (as the dirt was a part of the integral FEL shielding), as well as that necessary to protect the FEL workers from HELIOS injector radiation, was not reasonable. Essentially, it required a very large amount of concrete or steel to be mounted on the ceiling of the FEL along the south wall. In addition to the shielding needs, there were concerns regarding the mounting of the shield and other issues such as ventilation, personnel access, cost for digging, etc. It was decided to look at other alternatives. Page 1 of 24

2 The final design involves building a cave in the existing equipment room. The wall thickness was estimated in the original NCRP-51 calculations to be 2 thick. This figure was estimated from the parameters above and also from the following personnel exposure limitations: Jefferson Lab Design Goal: Radiation Area Posting: 250 mrem per year 5 mrem per hour While it was relatively easy to determine the electron and photon source term, it was more difficult to determine the neutron component. The neutrons are generated mostly from the so-called Giant Photonuclear Resonance interaction of high-energy photons with machine components and shielding. The low energy threshold of the production in iron is about 10 MeV, and in aluminum about 13 MeV. The neutron spectrum was estimated using MCNPX, a code under development at Los Alamos National Laboratory. The beta version of MCNPX used was version ld=thu Mar 23 15:30:22 MST For conservatism, a thick copper target was assumed. The output neutron spectrum was then used as source term input to MCNP version 4b. It had already been predetermined that shielding for the neutrons would provide adequate photon shielding, though also attached are the photon results. After iterative design modifications that allowed for adequate ventilation, lighting, egress, radiation shielding etc., the final design was presented and was modeled in MCNP. It was assumed that 5% of the beam would be lost along the length of the injector with the last 95% in the dumplet itself. The results follow on page 5. Dose points were determined at all apparent worse-case spots. The results are in Table 1 below. The calculation uses 30 cm of concrete as dump shielding, which is very effective at removing neutrons of the energies involved. The dose rates are worst-case scenarios when the injector is being filled with electrons. The dose rates drop off dramatically (essentially to zero) when the machine is simply storing the electrons. TABLE 1 Neutron Dose Equivalent Rates 0 degree dump 24" Wall concrete shield 12" tally position Dose rate (mrem/h) Error (1 sigma) 5 outer door - FEL labyrinth % 15 outside bldg - main labyrinth (south) % 25 outside bldg - HELIOS labyrinth (south) % 35 FEL Door % 55 outside HELIOS labyrinth door % 65 equip. room - outside thin shielding % 75 below proposed duct % 85 above 0 degree dumplet % 95 dose inside vault (@ injector) % 105 ceiling, thin part % 115 in proposed duct % 125 Pen # % 135 Pen # % 145 Pen # % 155 Pen # % 165 Pen # % Page 2 of 24

3 As can be seen, the only accessible areas that become Radiation Areas (greater than 5 mrem/hr) during the injection are directly above the dumplet, and above Penetration #5, which is the one closest to the dumplet. These locations may need to be locally shielded if posting proves to be impracticable. The equipment room itself is best exemplified by tallies 55 and 65, which show dose rates of about 0.17 mrem/hr. This dose rate is consistent with a Radiologically Controlled Area, which is the posting originally assumed. The photon dose equivalent rates are relatively inconsequential, with a maximum of about 10% contribution at the hottest accessible spot (tally 85). The results of the calculation are in Table 2. Note that the errors cited are so large due to the very small photon flux at the positions. TABLE 2 Photon Dose Equivalent Rates 0 degree dump 24" Wall concrete shield 12" photon tally position mrem/h Error 5 outer door - FEL labyrinth % 15 outside bldg - main labyrinth (south) % 25 outside bldg - HELIOS labyrinth (south) % 35 FEL Door % 55 outside HELIOS labyrinth door % 65 equip. room - outside thin shielding % 75 below proposed duct % 85 above 0 degree dumplet % 95 dose inside vault (@ injector) % 105 ceiling, thin part % 115 in proposed duct % 125 Pen # % 135 Pen # % 145 Pen # % 155 Pen # % 165 Pen # % Outside of the building, dose rates approach 0.4 mrem/hr on the south side of the building (Tally 25) and even up to almost 0.8 mrem/hr outside the existing FEL door on the southwest side of the building. Clearly, these dose equivalent rates are undesirably high. If one uses the in one hour posting criterion, and assumes that during the injection, the higher dose rates occur for 10% of the time (as were the initial assumptions), the area approaches 80 µrem/h, which exceeds the Radiologically Controlled Area posting limit. Some localized shielding may have to occur to prevent this condition. Originally, there were plans to put some sort of baffle in the air intake to the HELIOS injector, or some shadow shielding in the injector itself, as this is the area where the radiation escapes. That action will likely still be necessary. The 30 cm of concrete around the dump was a rough cut of the amount of local shielding that may be necessary to achieve the design goals. If some more shielding, perhaps even a combination of concrete and steel were used, some of the problems identified above may be solved. However, even with the above proposed shielding, the dose rate objections are not insurmountable. Page 3 of 24

4 Another scenario to be considered is that of a temporary dump that is near the temporary south wall of the HELIOS injector facility, essentially a last stop before it is transported to the HELIOS storage ring. Dose rates from neutrons at the points of interest are in Table 3. TABLE 3 Neutron Dose Equivalent Rates 90 degree dump 24" Wall Tally Position Dose rate (mrem/h) 5 outer door - FEL labyrinth outside bldg - main labyrinth (south) outside bldg - HELIOS labyrinth (south) FEL Door outside HELIOS labyrinth door equip. room - outside thin shielding below proposed duct above 0 degree dumplet dose inside vault (@ injector) ceiling, thin part in proposed duct Pen # Pen # Pen # Pen # Pen # Essentially, dose rates are fairly similar, with the main difference being directly outside the south wall. This situation may be acceptable if there is a building there at the time and the area can be adequately controlled. Conclusions The HELIOS injector project, as currently designed, should result in personnel dose equivalents within the Jefferson Lab design goal of 250 mrem/yr. Area postings will not need to be greater than the Radiologically Controlled Area posting if a bit of localized shielding or direct access control is employed during injection. Areas that need to be considered for local shielding are the ceiling above the dump and the ventilation duct between the injector area and the FEL stairwell on the west side. The dump itself needs to be shielded, and 30 cm of concrete was proposed as a first cut. Further specification of the dump shielding was not made due to uncertainty in the space requirements. Page 4 of 24

5 1mcnpx version ld=thu Mar 23 15:30:22 MST /19/** 16:26:33 *************************************************************************************** probid = 01/19/** 16:26:33 i=helios2 ***************************************************** * * * Copyright Notice for MCNPX * * * * This program was prepared by the Regents of the * * University of California at Los Alamos National * * Laboratory (the University) under contract number * * W-7405-ENG-36 with the U.S. Department of Energy * * (DOE). The University has certain rights in the * * program pursuant to the contract and the program * * should not be copied or distributed outside your * * organization. All rights in the program are * * reserved by the DOE and the University. Neither * * the U.S. Government nor the University makes any * * warranty, express or implied, or assumes any * * liability or responsibility for the use of this * * software. * * * ***************************************************** 1- HELIOS Estimate - including neutron production 2- c $ concrete wall 3- c #4 $ air spaces (void) 4- c 3 0-6:-12:-10:11:13:14 $ outside interest 5- c $ tungsten target $ copper target 7- c $ Tantalum target 8- c $ ceiling 9- c $ wall detector region 10- c $ ceiling detector region #4 $ 1-meter sphere $outside px px pz pz cz py py py pz pz px px py sz warning. this surface has been replaced by a surface of type so c sdef erg=45 x=0 y=0 z= vec=0 0 1 dir=1 par=3 $electron beam 31- c material 1 - ordinary concrete 32- c m c c c c material 2 - tungsten 37- c m $tungsten 38- c mpn c **************************************************************************** 40- c TALLIES HERE. FORMAT: FAB5, where A is distance (m), B is type (0 = flux, 41- c 1 = dose, 2 = detector response). Distance 0.8 -> A= c **************************************************************************** 43- m $copper 44- mpn c m u 1 $tantalum Page 5 of 24

6 warning. m 3:photonuclear event sees ZA= in place of ZA= f2:n e2 2.50E E E E E E E E E f102:n fc102 Dose (Sieverts) 52- c de E E E E E E E E df E E E E E E E E mode n p e 62- IMP:e IMP:n IMP:p phys:p phys:n phys:e c LCA 69- cut:e 1.e cut:n 1.e cut:p 1.e nps 1e5 73- mplot tally 102 tfc e freq print Page 6 of 24

7 INPUT DECK FINAL CALCULATION HELIOS injector neutron analysis ( ) $dirt between HELIOS and FEL ( #13):( #23) $west wall $east wall $FEL south wall $NORTH HELIOS WALL ( ):( ) $south equip room wall ( ) $ceiling left of plane ( ): ( #15 #35 #39 #40 #41 #42 #43) $ceiling right of plane ( ):( ): ( ):( ) $floor left of plane #5 #3 #6 $floor right of plane ( ) $big east wall :-56:-47:53:-60:(10 #24) $void E $vent hole ( ):( ) $MAIN HELIOS shield wall E-3 ( #37):( ): ( #37 #38) $HELIOS RANGE $EAST HELIOS SHIELD WALL ( ):( )$labyrinth wall for HELIOS E-3 ( ):( ): ( #38): ( #38) $HELIOS LABYRINTH E-3 ( ):( ): ( ):( ) $labyrinth E-3 ( ) $alcove (occupiable) ( ):( #23): ( ) $walls in labyrinth E-3 ( ):( ): ( #36 #35) $equipment room ( ):( ) $dirt areas E $outside dose zone E #34 $FEL vault $concrete above FEL $dirt above FEL $user lab floor E $user lab air space #2 #3 #4 #5 #6 #11 #21 #23 $subfloor helios, etc $concrete floor of FEL $concrete HELIOS injector floor (NOT) $dirt HELIOS injector floor c $copper target E $AIR target c $concrete shield c $iron shield c $water shield c E $air shield (none) c $5% borated poly c ( ) $duct through wall - B-poly e-3 ( ) $duct through wall - air ( ):( ): ( ):( ) $"DUCT LABYRINTH" $main dump shield ( ):( ) $8-inch concrete external wall e $penetration # e $penetration # e $penetration # e $penetration # e $penetration #5 1 pz 0 2 pz pz pz px px px px 0 Page 7 of 24

8 9 px px 580 $FAR SOUTH EXTREME 100 px 730 $south dose zone 11 py 272 $ceiling 110 py 287 $thinner ceiling 111 py 234 $top of east shield wall 1111 py 277 $borated poly zone/air zone 112 py $bottom of duct 113 py $bottom shielding of duct 12 py 310 $floor upstairs 13 py 0 $floor 14 py $subfloor 15 pz pz 2027 $FAR EAST EXTREME 17 pz pz px pz pz px px 198 $VENT HOLE LIMIT 24 px 381 $VENT HOLE LIMIT 25 py 10 $VENT HOLE LIMIT 26 py $VENT HOLE LIMIT 27 c/z pz p p p p py pz pz pz px px px pz $FAR WEST EXTREME 48 pz px pz px pz py 640 $overall ceiling 54 py $FEL ceiling 55 py -213 $FEL floor 56 px $FEL north wall 57 py 183 $top of concrete above FEL 58 py 295 $top of dirt above FEL 60 py -305 $bottom of FEL floor 61 py c 101 c/z c/z pz pz py px -365 c 300 s px px pz pz pz pz px pz pz px pz pz pz 1209 Page 8 of 24

9 213 px s s px c/y c/y c/y c/y c/y c sdef pos=d2 erg=d1 $straight ahead config si E E E E E E E E E E+01 sp e E E E E E E E E E-10 si2 L $discrete values of position sp c material 1 - ordinary concrete m c material 2 - air m $air m $iron m $water m $5% borated polyethylene c material 7 - pseudo-dirt m e e-012 m $copper fc5 Dose at Outer Door (Sieverts) f5:n de5 2.50E E E E E E E E-02 df5 2.32E E E E E E E E-11 fc15 Dose outside labyrinth (south) (Sieverts) f15:n de E E E E E E E E-02 df E E E E E E E E-11 fc25 Dose outside HELIOS inj. labyrinth (south) (Sieverts) f25:n de E E E E E E E E-02 df E E E E E E E E-11 fc35 Dose just inside FEL door (Sieverts) Page 9 of 24

10 f35:n de E E E E E E E E-02 df E E E E E E E E-11 c fc45 Dose behind FEL labyrinth wall c f45:n c c de E E E E E E E E-02 c c c c df E E E E E E E E-11 c c fc55 Dose outside HELIOS labyrinth f55:n de E E E E E E E E-02 df E E E E E E E E-11 fc65 Dose in equipment room, general area f65:n de E E E E E E E E-02 df E E E E E E E E-11 fc75 dose in equipment room, below duct f75:n de E E E E E E E E-02 df E E E E E E E E-11 fc85 dose above injector(sieverts) f85:n de E E E E E E E E-02 df E E E E E E E E-11 fc95 dose at injector itself f95:n de E E E E E E E E-02 df E E E E E E E E-11 fc105 dose on ceiling, thin part f105:n Page 10 of 24

11 de E E E E E E E E-02 df E E E E E E E E-11 fc115 Dose in duct (Sieverts) f115:n de E E E E E E E E-02 df E E E E E E E E-11 fc125 Dose in PEN#1 (Sieverts) f125:n de E E E E E E E E-02 df E E E E E E E E-11 fc135 Dose in PEN#2 (Sieverts) f135:n de E E E E E E E E-02 df E E E E E E E E-11 fc145 Dose in PEN#3 (Sieverts) f145:n de E E E E E E E E-02 df E E E E E E E E-11 fc155 Dose in PEN#4 (Sieverts) f155:n de E E E E E E E E-02 df E E E E E E E E-11 fc165 Dose in PEN#5 (Sieverts) f165:n de E E E E E E E E-02 df E E E E E E E E-11 imp:n c Page 11 of 24

12 c c wwg:n c wwp:n c wwe:n E+02 c wwn1:n E E E E E+01 c E E E E E-01 c.0000e e e e E+09 c E E E E E+00 c.0000e e E E E-03 c.0000e e e E+31 mplot tally 65 tfc e freq prdmp 5e5 j j 4 j nps 1e8 Page 12 of 24

13 tally 5 tally 15 tally 25 nps mean error vov slope fom mean error vov slope fom mean error vov slope fom E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E-01 tally 35 tally 55 tally 65 nps mean error vov slope fom mean error vov slope fom mean error vov slope fom E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E-02 tally 75 tally 85 tally 95 nps mean error vov slope fom mean error vov slope fom mean error vov slope fom E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E Page 13 of 24

14 tally 105 tally 115 tally 125 nps mean error vov slope fom mean error vov slope fom mean error vov slope fom E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E-01 tally 135 tally 145 tally 155 nps mean error vov slope fom mean error vov slope fom mean error vov slope fom E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E-01 tally 165 nps mean error vov slope fom E E E E E E E E E E E E E E E E E E E E E E-01 Page 14 of 24

15 Figure 1: Overhead view including surface numbers 10/11/** 16:07:24 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: (.00, 30.00,.00) extent = ( , ) JLAB-TN Page 15 of 24

16 Figure 2: Cross section including ventilation duct 10/11/** 16:09:07 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: ( ,.00,.00) extent = ( , ). JLAB-TN Page 16 of 24

17 Figure 3: Close up view of exit air vent /11/** 16:09:48 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: ( , , ) extent = ( , ) Page 17 of 24

18 Figure 4: Close up view of exit air vent with surface numbers /11/** 16:10:00 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: ( , , ) extent = ( , ) Page 18 of 24

19 Figure 5: Close up view of exit air vent with volume numbers /11/** 16:10:20 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: ( , , ) extent = ( , ) cell labels are cell names Page 19 of 24

20 Figure 6: Cross sectional view with dump shielding and volume numbers 10/11/** 16:11:52 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: ( 91.50,.00,.00) extent = ( , ) cell labels are cell names JLAB-TN Page 20 of 24

21 Figure 7: Cross sectional view with dump shielding 10/11/** 16:12:01 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: ( 91.50,.00,.00) extent = ( , ). JLAB-TN Page 21 of 24

22 Figure 8: Overhead view including dump shielding and ventilation duct 10/11/** 16:13:28 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: (.00, ,.00) extent = ( , ). JLAB-TN Page 22 of 24

23 Figure 9: Overhead view including dump shielding and ventilation duct and surface numbers 10/11/** 16:13:41 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: (.00, ,.00) extent = ( , ) JLAB-TN Page 23 of 24

24 Figure 10: Overhead view including dump shielding and ventilation duct and volume numbers 10/11/** 16:13:54 HELIOS injector neutron analysis probid = 10/11/** 16:04:40 basis: ( , , ) ( , , ) origin: (.00, ,.00) extent = ( , ) cell labels are cell names Page 24 of 24

Experiences from First Top-Off Injection At The Stanford Synchrotron Radiation Lightsource

Experiences from First Top-Off Injection At The Stanford Synchrotron Radiation Lightsource Experiences from First Top-Off Injection At The Stanford Synchrotron Radiation Lightsource Johannes Bauer, James Liu, Alyssa Prinz, Sayed Rokni Radiation Protection Department SLAC National Accelerator

More information

DESCRIPTION OF THE DELPHI SUBCRITICAL ASSEMBLY AT DELFT UNIVERSITY OF TECHNOLOGY

DESCRIPTION OF THE DELPHI SUBCRITICAL ASSEMBLY AT DELFT UNIVERSITY OF TECHNOLOGY IRI-131-2003-008 DESCRIPTION OF THE DELPHI SUBCRITICAL ASSEMBLY AT DELFT UNIVERSITY OF TECHNOLOGY J.L. Kloosterman October, 2003 INTRODUCTION For educational purposes, the Reactor Physics Department of

More information

Cassini-Huygens Power Conversion Technology

Cassini-Huygens Power Conversion Technology Cassini-Huygens General Purpose Heat Source Radioisotope Thermoelectric Generator (GPHS-RTG) The GPHS-RTG is the first standardized RTG design using GPHS modules to encase the fuel. In today s mission,

More information

VISBREAKER MONITORING FOR MAXIMUM CONVERSION

VISBREAKER MONITORING FOR MAXIMUM CONVERSION Petrocontrol Advanced Control & Optimization VISBREAKER MONITORING FOR MAXIMUM CONVERSION Z. Friedman, Petrocontrol W. A. Kuijl, RUHR-OL K. Wolfsgruber, Maraven S.A. Paper presented at the PDVSA Deep Conversion

More information

NLCTA Accelerator Safety Envelope

NLCTA Accelerator Safety Envelope NLCTA Accelerator Safety Envelope Approved by (signature/date) NLCTA Operations Manager:... Janice Nelson Test Facilities Department Head:... Carsten Hast Director of Accelerator Research Division:...

More information

Interim report on noise in F2C, October 2010 Rob Metkemeijer

Interim report on noise in F2C, October 2010 Rob Metkemeijer 1 Interim report on noise in F2C, October 2010 Rob Metkemeijer 1. Introduction. At the 2010 CIAM plenary it was decided that in 2010 a strategy for noise control in F2C team race will be prepared, aiming

More information

Proposal to establish a laboratory for combustion studies

Proposal to establish a laboratory for combustion studies Proposal to establish a laboratory for combustion studies Jayr de Amorim Filho Brazilian Bioethanol Science and Technology Laboratory SCRE Single Cylinder Research Engine Laboratory OUTLINE Requirements,

More information

RADIATION CONTROL - RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS NOT USED IN THE HEALING ARTS

RADIATION CONTROL - RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS NOT USED IN THE HEALING ARTS DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT RADIATION CONTROL - RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS NOT USED IN THE HEALING ARTS 6 CCR 1007-1 Part 09 [Editor s Notes follow the text

More information

Application of DSS to Evaluate Performance of Work Equipment of Wheel Loader with Parallel Linkage

Application of DSS to Evaluate Performance of Work Equipment of Wheel Loader with Parallel Linkage Technical Papers Toru Shiina Hirotaka Takahashi The wheel loader with parallel linkage has one remarkable advantage. Namely, it offers a high degree of parallelism to its front attachment. Loaders of this

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

Safe operation of the rotating anode x-ray generator in room 1128 ERB. Emergency power disconnect

Safe operation of the rotating anode x-ray generator in room 1128 ERB. Emergency power disconnect Safe operation of the rotating anode x-ray generator in room 1128 ERB Contact: Paul Evans, evans@engr.wisc.edu, August 13, 2008 Important Notes 1. The rotating anode x-ray generator produces x-rays by

More information

Fabrication of 12 GeV Prototype Quadrupoles 1. Introduction 2. Design 3. Fabrication

Fabrication of 12 GeV Prototype Quadrupoles 1. Introduction 2. Design 3. Fabrication Fabrication of 12 GeV Prototype Quadrupoles T. Hiatt, K. Baggett, M. Beck, L. Harwood, J. Meyers and M. Wiseman Thomas Jefferson National Accelerator Facility, Newport News, Virginia 23606 1. Introduction

More information

PART I RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS

PART I RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS PART I RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS Sec. I.1 Purpose and Scope a. This Part establishes procedures for the registration [or licensing] and the use of particle accelerators. b.

More information

Ambient Magnetic Field Compensation for the ARIEL (Advanced Rare IsotopE Laboratory) Electron Beamline. Gabriela Arias April 2014, TRIUMF

Ambient Magnetic Field Compensation for the ARIEL (Advanced Rare IsotopE Laboratory) Electron Beamline. Gabriela Arias April 2014, TRIUMF Ambient Magnetic Field Compensation for the ARIEL (Advanced Rare IsotopE Laboratory) Electron Beamline Gabriela Arias April 2014, TRIUMF Summary TRIUMF s Advanced Rare IsotopE Laboratory (ARIEL) facility

More information

Air Bearing Shaker for Precision Calibration of Accelerometers

Air Bearing Shaker for Precision Calibration of Accelerometers Air Bearing Shaker for Precision Calibration of Accelerometers NOMENCLATURE Jeffrey Dosch PCB Piezotronics 3425 Walden Avenue, Depew NY DUT Device Under Test S B DUT sensitivity to magnetic field [(m/sec

More information

Status of the DARHT 2 nd Axis Accelerator at Los Alamos National Laboratory

Status of the DARHT 2 nd Axis Accelerator at Los Alamos National Laboratory Status of the DARHT 2 nd Axis Accelerator at Los Alamos National Laboratory R.D. Scarpetti, S. Nath, J. Barraza, C. A. Ekdahl, E. Jacquez, K. Nielsen, J. Seitz Los Alamos National Laboratory, Los Alamos,

More information

Central Region Group Status and Positron Region

Central Region Group Status and Positron Region Central Region Group Status and Positron Region K. Yokoya 2016.9.14. Posipol2016, LAL 2016/9/14 Posipol2016 1 Issues Discussed in CRWG Positron-related 10Hz operation Auxiliary positron source (APS) Positron

More information

AN RPM to TACH Counts Conversion. 1 Preface. 2 Audience. 3 Overview. 4 References

AN RPM to TACH Counts Conversion. 1 Preface. 2 Audience. 3 Overview. 4 References AN 17.4 RPM to TACH Counts Conversion 1 Preface 2 Audience 3 Overview 4 References This application note provides look up tables for the calculation of RPM to TACH Counts for use with the EMC2103, EMC2104,

More information

TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA

TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA 20 March 2014 Report prepared by: Corli Havenga Transportation Engineers

More information

Development of a High Efficiency Induction Motor and the Estimation of Energy Conservation Effect

Development of a High Efficiency Induction Motor and the Estimation of Energy Conservation Effect PAPER Development of a High Efficiency Induction Motor and the Estimation of Energy Conservation Effect Minoru KONDO Drive Systems Laboratory, Minoru MIYABE Formerly Drive Systems Laboratory, Vehicle Control

More information

Application of Serpent in EU FP7 project FREYA: Fast Reactor Experiments for hybrid Applications

Application of Serpent in EU FP7 project FREYA: Fast Reactor Experiments for hybrid Applications Application of Serpent in EU FP7 project FREYA: Fast Reactor Experiments for hybrid Applications E. Fridman Text optional: Institutsname Prof. Dr. Hans Mustermann www.fzd.de Mitglied der Leibniz-Gemeinschaft

More information

A fully integrated 3 phase IGBT switching assembly with a very low loss DC Link Capacitor -- Ed Sawyer, SBE Inc. Scott Leslie, Powerex Inc.

A fully integrated 3 phase IGBT switching assembly with a very low loss DC Link Capacitor -- Ed Sawyer, SBE Inc. Scott Leslie, Powerex Inc. A fully integrated 3 phase IGBT switching assembly with a very low loss DC Link Capacitor -- Ed Sawyer, SBE Inc. Scott Leslie, Powerex Inc. Thermal characteristics of the Power Ring shape SBE has conducted

More information

NATIONAL NUCLEAR SECURITY ADMINISTRATION GLOBAL THREAT REDUCTION INITIATIVE Core Modifications to address technical challenges of conversion

NATIONAL NUCLEAR SECURITY ADMINISTRATION GLOBAL THREAT REDUCTION INITIATIVE Core Modifications to address technical challenges of conversion NATIONAL NUCLEAR SECURITY ADMINISTRATION GLOBAL THREAT REDUCTION INITIATIVE Core Modifications to address technical challenges of conversion G17 G18 G19 G20 G21 G16 F15 F16 G22 F17 F14 9.76 9.85 9.91 F18

More information

The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection.

The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection. 1 The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection. Two learning objectives for this lab. We will proceed over the remainder

More information

Beam Energy Absorber and

Beam Energy Absorber and ADS Workshop VirginiaTech, September 2010 Beam Energy Absorber and Converter with Moving Core Pavel Degtiarenko ESH&Q Division, JLab 1 Contents Brief review Properties of High Power and High Energy Beam

More information

Magnet, Support and Infrastructure. Whit Seay November 7, 2014

Magnet, Support and Infrastructure. Whit Seay November 7, 2014 Magnet, Support and Infrastructure Whit Seay November 7, 2014 Engineering Progress Efforts in cost and labor estimate Contributions to pcdr document Visit to Cornell Dry Run - Magnet - Hall A Layout for

More information

ESD Tests on Protektive Pak Versus Coated ESD Boxes

ESD Tests on Protektive Pak Versus Coated ESD Boxes ESD Tests on Protektive Pak Versus Coated ESD Boxes This purpose of these tests and report is to determine the effective shielding of Coated ESD boxes versus Protektive Pak boxes. Also this report will

More information

Created: 4/23/2003 Page: 1 of 12. Abstract

Created: 4/23/2003 Page: 1 of 12. Abstract Collimators and Transport Solenoid Shielding Reference Design Document No: Created: 4/23/2003 Page: 1 of 12 MECO-MUB-03-002 Modified: 10/13/03 Version: 1.01 Prepared by: M. Hebert, V. Tumakov Approved

More information

Performance of Batteries in Grid Connected Energy Storage Systems. June 2018

Performance of Batteries in Grid Connected Energy Storage Systems. June 2018 Performance of Batteries in Grid Connected Energy Storage Systems June 2018 PERFORMANCE OF BATTERIES IN GRID CONNECTED ENERGY STORAGE SYSTEMS Authors Laurie Florence, Principal Engineer, UL LLC Northbrook,

More information

CLASSIFIED 5 MAGNETISM ELECTROMAGNETIC INDUCTION GENERATOR MOTOR - TRANSFORMER. Mr. Hussam Samir

CLASSIFIED 5 MAGNETISM ELECTROMAGNETIC INDUCTION GENERATOR MOTOR - TRANSFORMER. Mr. Hussam Samir CLASSIFIED 5 MAGNETISM ELECTROMAGNETIC INDUCTION GENERATOR MOTOR - TRANSFORMER Mr. Hussam Samir EXAMINATION QUESTIONS (5) 1. A wire perpendicular to the page carries an electric current in a direction

More information

Craigieburn Employment Precinct North and English Street

Craigieburn Employment Precinct North and English Street Craigieburn Employment Precinct North and English Street METROPOLITAN PLANNING AUTHORITY Intersection Analyses 7 February 2014 Intersection Analyses Craigieburn Employment Precinct North and English Street

More information

FRM II Converter Facility

FRM II Converter Facility FRM II Converter Facility Volker Zill Heiko Gerstenberg Axel Pichmaier Technical University of Munich Forschungs-Neutronenquelle Heinz Maier-Leibnitz (FRM II) Lichtenbergstrasse 1, 85748 Garching - Federal

More information

Engineers Tables SI Units

Engineers Tables SI Units Engineers Tables SI Units 1. Introduction The following tables provide practical information to help you design or set up refrigeration systems using KLEA 407C. We've tried to make the layout as easy as

More information

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011 Low Beta Cryomodule Development at Fermilab Tom Nicol March 2, 2011 Concepts of SC CW 3GeV, 1mA Linac H - gun RFQ MEBT SSR0 SSR1 SSR2 β=0.6 β=0.9 ILC RT (~15m) 325 MHz 2.5-160 MeV 650 MHz 0.16-2 GeV 1.3

More information

Design of a mount for a new generation X-ray detector board Final Report

Design of a mount for a new generation X-ray detector board Final Report Design of a mount for a new generation X-ray detector board Final Report Fabio Rinaldi August 18, 2016 Instructor: Professor G. Varner Figure 1: 3D model of the final concept 1 1 Design specifications

More information

ASTM D4169 Truck Profile Update Rationale Revision Date: September 22, 2016

ASTM D4169 Truck Profile Update Rationale Revision Date: September 22, 2016 Over the past 10 to 15 years, many truck measurement studies have been performed characterizing various over the road environment(s) and much of the truck measurement data is available in the public domain.

More information

SMALL-SIZE BETATRONS FOR RADIOGRAPHIC INSPECTION

SMALL-SIZE BETATRONS FOR RADIOGRAPHIC INSPECTION SMALL-SIZE BETATRONS FOR RADIOGRAPHIC INSPECTION M. Stein 1, V. A. Kasyanov 1, V. L. Chakhlov 1, J. Macleod 2, P. Marjoribanks 2, and S. Hubbard 2 1 RII at TPU, Tomsk, Russia; 2 JME Ltd., Lowestoft, UK

More information

City of Minnetonka Maximum Parking Regulations Urban GIS. Group Members Brad Johnston Mark Kelley Jonathan Winge

City of Minnetonka Maximum Parking Regulations Urban GIS. Group Members Brad Johnston Mark Kelley Jonathan Winge City of Minnetonka Maximum Parking Regulations Urban GIS Group Members Brad Johnston Mark Kelley Jonathan Winge This project was supported by the Resilient Communities Project (RCP), a program at the University

More information

Battery Pack & Electrical Examples. What other teams saw that you don t need to see Steve McMullen

Battery Pack & Electrical Examples. What other teams saw that you don t need to see Steve McMullen Battery Pack & Electrical Examples What other teams saw that you don t need to see Steve McMullen Some Functions of the Pack Design Provide electrical Connection Cells to Module Modules to Pack Pack to

More information

Rain Gauge Smart Sensor (Part # RGA-M0XX, RGB-M0XX)

Rain Gauge Smart Sensor (Part # RGA-M0XX, RGB-M0XX) (Part # RGA-M0XX, RGB-M0XX) The Rain Gauge smart sensor is designed to work with the HOBO Weather Station logger. The smart sensor has a plug-in modular connector that allows it to be added easily to a

More information

ILC. CFS update for Europe (CERN): Cross Sections 3d Layout and BDS tunnel diameters CERN Resources. LCWS10 and ILC10 - Beijing

ILC. CFS update for Europe (CERN): Cross Sections 3d Layout and BDS tunnel diameters CERN Resources. LCWS10 and ILC10 - Beijing ILC CFS update for Europe (CERN): Cross Sections 3d Layout and BDS tunnel diameters CERN Resources John Osborne March 2010 LCWS10 and ILC10 - Beijing Cross section for Europe (CERN) 5.2m diameter for Kly

More information

The Landscape of Thermal Runaway Propagation Testing

The Landscape of Thermal Runaway Propagation Testing The Landscape of Thermal Runaway Propagation Testing Daniel H. Doughty, Ph.D. President, Battery 1-505-514-1717 dhdoughty@batterysafety.net Presentation at Safer Li-ion Batteries by Preventing Thermal

More information

Bimotion Advanced Port & Pipe Case study A step by step guide about how to calculate a 2-stroke engine.

Bimotion Advanced Port & Pipe Case study A step by step guide about how to calculate a 2-stroke engine. Bimotion Advanced Port & Pipe Case study A step by step guide about how to calculate a 2-stroke engine. 2009/aug/21. Bimotion. This paper is free for distribution and may be revised, for further references

More information

Application Note AN-1203

Application Note AN-1203 Application Note AN-1203 Application Note, explaining the overload/short circuit power dissipation, Remote Sense and output filtering of ARE100XXS/D By Abhijit D. Pathak, Juan R. Lopez International Rectifier,

More information

SFM/TFM Power Integrity Guidelines Samtec SFM/TFM Series Measurement and Simulation Data

SFM/TFM Power Integrity Guidelines Samtec SFM/TFM Series Measurement and Simulation Data SFM/TFM Power Integrity Guidelines Samtec SFM/TFM Series Measurement and Simulation Data Scott McMorrow, Director of Engineering Page 1 SFM/TFM Power Integrity Guidelines Modeled Section SFM Board TFM

More information

SAFETY COMPLIANCE TESTING FOR FMVSS 124 ACCELERATOR CONTROL SYSTEMS

SAFETY COMPLIANCE TESTING FOR FMVSS 124 ACCELERATOR CONTROL SYSTEMS REPORT NUMBER 124-GTL-07-003 SAFETY COMPLIANCE TESTING FOR FMVSS 124 ACCELERATOR CONTROL SYSTEMS NISSAN MOTOR CO., LTD. 2007 NISSAN VERSA, 4-DOOR PASSENGER CAR NHTSA NO. C75201 GENERAL TESTING LABORATORIES,

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

CHAPTER 40 PROFESSIONAL LICENSING AND FACILITY REGULATION. PART 13 Radiation Safety Requirements for Particle Accelerators

CHAPTER 40 PROFESSIONAL LICENSING AND FACILITY REGULATION. PART 13 Radiation Safety Requirements for Particle Accelerators 216-RICR-40-20-13 TITLE 216 DEPARTMENT OF HEALTH CHAPTER 40 PROFESSIONAL LICENSING AND FACILITY REGULATION SUBCHAPTER 20 - RADIATION PART 13 Radiation Safety Requirements for Particle Accelerators 13.1

More information

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority FINAL REPORT CATHODIC PROTECTION EVALUATION 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to 50+00 South Texas Water Authority Prepared for: South Texas Water Authority P.O. Box 1701 Kingsville,

More information

IT'S MAGNETIC (1 Hour)

IT'S MAGNETIC (1 Hour) IT'S MAGNETIC (1 Hour) Addresses NGSS Level of Difficulty: 4 Grade Range: 3-5 OVERVIEW In this activity, students will create a simple electromagnet using a nail, a battery, and copper wire. They will

More information

Ballard Power Systems

Ballard Power Systems Ballard Power Systems Ballard Power Systems Fuel Cells Current Status and Prospects for the Future David Musil, P. Eng. Project Engineer, Advanced Automotive Development March 30, 2006 Outline 1. Background

More information

Reluctance Motors Synchrel Design & Optimisation

Reluctance Motors Synchrel Design & Optimisation Reluctance Motors Synchrel Design & Optimisation A Switched Reluctance Alternative Incorporating Novel Features The End Result 1 Existing Design Procedure Electromagnetic Design A Switched Reluctance solution

More information

Thermal Unit Operation (ChEg3113)

Thermal Unit Operation (ChEg3113) Thermal Unit Operation (ChEg3113) Lecture 5- Heat Exchanger Design Instructor: Mr. Tedla Yeshitila (M.Sc.) Today Review Heat exchanger design vs rating of heat exchanger Heat exchanger general design procedure

More information

Volkswagen MKVI 2.0T ECS Tuning Kohlefaser Luft-Technik System. Installation Tutorial ES ES

Volkswagen MKVI 2.0T ECS Tuning Kohlefaser Luft-Technik System. Installation Tutorial ES ES Volkswagen MKVI 2.0T ECS Tuning Kohlefaser Luft-Technik System Installation Tutorial ES2712727 ES2739920 Required Tools: Flex Driver For Screw Type Hose Clamps* Phillips Screwdriver Torx T25 bit Torx T30

More information

Klea 410A Engineers Tables SI Units

Klea 410A Engineers Tables SI Units Klea 410A Engineers Tables SI Units 1. Introduction The following tables provide practical information to help you design or set up refrigeration systems using Klea 410A. We've tried to make the layout

More information

Model 550 Series Vibration Switches

Model 550 Series Vibration Switches OPERATION MANUAL Vibration Switches Includes: 550 550M 550-X 550M-X Page 2 SECTION TITLE PAGE 1. INTRODUCTION... 2 2. FEATURES... 3 3. WIRING... 4 4. ANALOG METER... 4 5. TESTING... 4 6. INSTALLATION...

More information

DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908

DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908 PSFC/RR-10-8 DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908 Jun Feng August 10, 2010 Plasma Science and Fusion Center Massachusetts Institute of Technology Cambridge, MA 02139, USA This work was supported

More information

A Study of EGR Stratification in an Engine Cylinder

A Study of EGR Stratification in an Engine Cylinder A Study of EGR Stratification in an Engine Cylinder Bassem Ramadan Kettering University ABSTRACT One strategy to decrease the amount of oxides of nitrogen formed and emitted from certain combustion devices,

More information

Model-Based Integrated High Penetration Renewables Planning and Control Analysis

Model-Based Integrated High Penetration Renewables Planning and Control Analysis Model-Based Integrated High Penetration Renewables Planning and Control Analysis October 22, 2015 Steve Steffel, PEPCO Amrita Acharya-Menon, PEPCO Jason Bank, EDD SUNRISE Department of Energy Grant Model-Based

More information

STEEL CASING OVERHEATING ANALYSIS OF OPERATING POWER PIPE-TYPE CABLES

STEEL CASING OVERHEATING ANALYSIS OF OPERATING POWER PIPE-TYPE CABLES STEEL CASING OVERHEATING ANALYSIS OF OPERATING POWER PIPE-TYPE CABLES F. P. Dawalibi, J. Liu, S. Fortin, S. Tee, and Y. Yang Safe Engineering Services & technologies ltd. 1544 Viel, Montreal, Quebec, Canada

More information

Proposed Solution to Mitigate Concerns Regarding AC Power Flow under Convergence Bidding. September 25, 2009

Proposed Solution to Mitigate Concerns Regarding AC Power Flow under Convergence Bidding. September 25, 2009 Proposed Solution to Mitigate Concerns Regarding AC Power Flow under Convergence Bidding September 25, 2009 Proposed Solution to Mitigate Concerns Regarding AC Power Flow under Convergence Bidding Background

More information

Automated Seat Belt Switch Defect Detector

Automated Seat Belt Switch Defect Detector pp. 10-16 Krishi Sanskriti Publications http://www.krishisanskriti.org/publication.html Automated Seat Belt Switch Defect Detector Department of Electrical and Computer Engineering, Sri Lanka Institute

More information

Solar*Rewards Frequently asked questions system size and customer usage

Solar*Rewards Frequently asked questions system size and customer usage Solar*Rewards 1. Will a PV system work with my home? 2. Am I eligible to participate in the Solar*Rewards program? 3. What size system should I get? 4. Can a customer at a service location apply for the

More information

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM Page 1 of 19 Table of Contents 1.0 SCOPE...4 2.0 PURPOSE...4 3.0 LIMITATIONS...5 4.0 GENERAL INTERCONNECTION

More information

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE)

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE) METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE) File: T2016-6004 METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES METRO NORTH TRANSMISSION STUDY

More information

VALIDATION OF NVIDIA IRAY AGAINST CIE 171:2006

VALIDATION OF NVIDIA IRAY AGAINST CIE 171:2006 VALIDATION OF NVIDIA IRAY AGAINST CIE 171:2006 PREPARED BY DAU DESIGN AND CONSULTING INC. JANUARY 28, 2016 Validation of NVIDIA Iray against CIE 171:2006 www.daudesignandconsulting.com ii TABLE OF CONTENTS

More information

Triple Fatal Motorcycle Crash On Wellington Road And Ferguson Line South of London, Ontario

Triple Fatal Motorcycle Crash On Wellington Road And Ferguson Line South of London, Ontario Triple Fatal Motorcycle Crash On Wellington Road And Ferguson Line South of London, Ontario Posting Date: Sept 4-2015 Motorcycles such as those pictured in this file photo continue to over represent the

More information

Presented at the 2012 Aerospace Space Power Workshop Manhattan Beach, CA April 16-20, 2012

Presented at the 2012 Aerospace Space Power Workshop Manhattan Beach, CA April 16-20, 2012 Complex Modeling of LiIon Cells in Series and Batteries in Parallel within Satellite EPS Time Dependent Simulations Presented at the 2012 Aerospace Space Power Workshop Manhattan Beach, CA April 16-20,

More information

CP-250E-60/72-208/240-MC4 Microinverter with Modular Trunk Cable

CP-250E-60/72-208/240-MC4 Microinverter with Modular Trunk Cable CP-250E-60/72-208/240-MC4 Microinverter with Modular Trunk Cable Chilicon Power Aug 2016 1 CONTENTS CP-250E Microinverter System... 3 The CP-100 Cortex Gateway... 3 Important Safety Information... 4 Inverter

More information

Applied Materials is accelerating Solar

Applied Materials is accelerating Solar Applied Materials is accelerating Solar Romain Beau de Lomenie Thin Film Module Group Head Solar Business Group Applied Materials, Inc. DERBI Conference, Perpignan, France June 6 th 2008 Safe Harbor Statement

More information

Traffic Micro-Simulation Assisted Tunnel Ventilation System Design

Traffic Micro-Simulation Assisted Tunnel Ventilation System Design Traffic Micro-Simulation Assisted Tunnel Ventilation System Design Blake Xu 1 1 Parsons Brinckerhoff Australia, Sydney 1 Introduction Road tunnels have recently been built in Sydney. One of key issues

More information

OPTIMAL BATCH DISTILLATION SEQUENCES USING ASPEN PLUS

OPTIMAL BATCH DISTILLATION SEQUENCES USING ASPEN PLUS OPTIMAL BATCH DISTILLATION SEQUENCES USING ASPEN PLUS Bradley H. Cook, Matthew J. Engel, and Anthony J. Zehnder Air Products and Chemicals, Inc. 7201 Hamilton Blvd. Allentown, PA 18195-1501 Craig S. Landis

More information

The following report discusses effect on HTHS Viscosity of Proton's Engine Oils by addition of X-1R Engine Treatment.

The following report discusses effect on HTHS Viscosity of Proton's Engine Oils by addition of X-1R Engine Treatment. Technical Report The following report discusses effect on HTHS Viscosity of 's s by addition of X-1R Engine. Introduction: Oxidation stability is a chemical reaction that occurs with a combination of the

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Synthesis of Optimal Batch Distillation Sequences

Synthesis of Optimal Batch Distillation Sequences Presented at the World Batch Forum North American Conference Woodcliff Lake, NJ April 7-10, 2002 107 S. Southgate Drive Chandler, Arizona 85226-3222 480-893-8803 Fax 480-893-7775 E-mail: info@wbf.org www.wbf.org

More information

M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA

M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA LBNL-48445 SCMAG-749 SUPERCONDUCTING MAGNETS FOR INDUCTION LINAC PHASE-ROTATION IN A NEUTRINO FACTORY M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA ABSTRACT The neutrino

More information

Approach for determining WLTPbased targets for the EU CO 2 Regulation for Light Duty Vehicles

Approach for determining WLTPbased targets for the EU CO 2 Regulation for Light Duty Vehicles Approach for determining WLTPbased targets for the EU CO 2 Regulation for Light Duty Vehicles Brussels, 17 May 2013 richard.smokers@tno.nl norbert.ligterink@tno.nl alessandro.marotta@jrc.ec.europa.eu Summary

More information

Note on preliminary cost estimate for an integrated tracker for the STAR experiment at RHIC

Note on preliminary cost estimate for an integrated tracker for the STAR experiment at RHIC Note on preliminary cost estimate for an integrated tracker for the STAR experiment at RHIC Gerrit van Nieuwenhuizen (MIT), Ernst Sichtermann (LBL) and Bernd Surrow (MIT) August 2, 2004 Abstract The following

More information

MUNTIFUNCTION SURVEY METER

MUNTIFUNCTION SURVEY METER MODEL 3020 MUNTIFUNCTION SURVEY METER MANUAL June 1990 Health Physics Instruments 330 D South Kellogg Ave Goleta, CA 93117 Tel 805.964.3615 FAX 805.964.3162 Division of Far West Technology TABLE OF CONTENTS

More information

MOTORS, VOLTAGE, EFFICIENCY AND WIRING. A Deeper Understanding

MOTORS, VOLTAGE, EFFICIENCY AND WIRING. A Deeper Understanding MOTORS, VOLTAGE, EFFICIENCY AND WIRING A Deeper Understanding An understanding of motors, voltage, efficiency, wiring, and how these concepts fit together cohesively is important for several reasons. Greater

More information

MIT ICAT M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n

MIT ICAT M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n Standard Flow Abstractions as Mechanisms for Reducing ATC Complexity Jonathan Histon May 11, 2004 Introduction Research

More information

January, 2014 Page 1 of 6

January, 2014 Page 1 of 6 Part 1 General 1.1 Summary.1 Unless otherwise indicated, follow the standards below when specifying chemical fume hood modifications or installations. These standards are not intended to restrict or replace

More information

SNS Operation and Upgrade Plans

SNS Operation and Upgrade Plans SNS Operation and Upgrade Plans Andrei Shishlo SNS Project, Oak Ridge National Lab Warm Linac Physicist On behalf of Accelerator Physics Team June 21, 2018 Presented at the HB2018, Daejeon, Korea, June

More information

MODEL PS-4 DIGITAL PORTION SCALE

MODEL PS-4 DIGITAL PORTION SCALE MODEL PS-4 DIGITAL PORTION SCALE OWNER S MANUAL CARDINAL SCALE MFG. CO. 8528-M317-O1 Rev A 203 E. Daugherty, Webb City, MO 64870 USA 07/05 Ph: 417-673-4631 Fax: 417-673-2153 www.detectoscale.com Technical

More information

NORDAC 2014 Topic and no NORDAC

NORDAC 2014 Topic and no NORDAC NORDAC 2014 Topic and no NORDAC 2014 http://www.nordac.net 8.1 Load Control System of an EV Charging Station Group Antti Rautiainen and Pertti Järventausta Tampere University of Technology Department of

More information

The future of the space elevator

The future of the space elevator 1 The future of the space elevator JOSÉ GERARDO CHÁVEZ ROSAS gerardochav@yahoo.com.mx http://aemex.orgfree.com/ Introduction The Space Elevator is the most promising Space Transportation system on the

More information

VERIFICATION PROTOCOL FOR PARKING LOT SALT SPREADERS

VERIFICATION PROTOCOL FOR PARKING LOT SALT SPREADERS VERIFICATION PROTOCOL FOR PARKING LOT SALT SPREADERS SALT APPLICATION VERIFIED EQUIPMENT (SAVE) PROGRAM Robert Roszell / Program Director 3/8/2016 www.savesalt.ca Table of Contents Introduction... 2 Purpose

More information

Product Loss During Retail Motor Fuel Dispenser Inspection

Product Loss During Retail Motor Fuel Dispenser Inspection Product Loss During Retail Motor Fuel Dispenser Inspection By: Christian Lachance, P. Eng. Senior Engineer - ment Engineering and Laboratory Services ment Canada Date: Product Loss During Retail Motor

More information

Appendix 3. DRAFT Policy on Vehicle Activated Signs

Appendix 3. DRAFT Policy on Vehicle Activated Signs Appendix 3 DRAFT Policy on Vehicle Activated Signs Ealing Council has been installing vehicle activated signs for around three years and there are now 45 across the borough. These signs help to reduce

More information

COMPUTATIONAL FLOW MODEL OF WESTFALL'S 2900 MIXER TO BE USED BY CNRL FOR BITUMEN VISCOSITY CONTROL Report R0. By Kimbal A.

COMPUTATIONAL FLOW MODEL OF WESTFALL'S 2900 MIXER TO BE USED BY CNRL FOR BITUMEN VISCOSITY CONTROL Report R0. By Kimbal A. COMPUTATIONAL FLOW MODEL OF WESTFALL'S 2900 MIXER TO BE USED BY CNRL FOR BITUMEN VISCOSITY CONTROL Report 412509-1R0 By Kimbal A. Hall, PE Submitted to: WESTFALL MANUFACTURING COMPANY May 2012 ALDEN RESEARCH

More information

coa+y IN SITU MEASUREMENT OF CERAMIC VACUUM CHAMBER CONDUCTIVE COATING QUALITY Advanced Photon Source, Argonne National Laboratory

coa+y IN SITU MEASUREMENT OF CERAMIC VACUUM CHAMBER CONDUCTIVE COATING QUALITY Advanced Photon Source, Argonne National Laboratory R bl / ~ ~ D / C P - T ~ IN SITU MEASUREMENT OF CERAMIC VACUUM CHAMBER CONDUCTIVE COATING QUALITY coa+y70503-- C. Doose, K. Harkay, S. Kim and S. Milton Advanced Photon Source, Argonne National Laboratory

More information

Pembina Emerson Border Crossing Interim Measures Microsimulation

Pembina Emerson Border Crossing Interim Measures Microsimulation Pembina Emerson Border Crossing Interim Measures Microsimulation Final Report December 2013 Prepared for: North Dakota Department of Transportation Prepared by: Advanced Traffic Analysis Center Upper Great

More information

Enabling Utility Scale PV: Challenges for Glass Makers

Enabling Utility Scale PV: Challenges for Glass Makers Enabling Utility Scale PV: Challenges for Glass Makers Romain Beau de Lomenie Director, Module Materials Management Thin Film Products, Solar Business Group Applied Materials International Workshop on

More information

Optimising battery energy storage systems operation

Optimising battery energy storage systems operation Optimising battery energy storage systems operation 02/26/2015-5.17 pm Network management Renewables Smart Grids Storage Grid-tied battery energy storage systems (BESS) are promising smart grid solutions

More information

Study of the Performance of a Driver-vehicle System for Changing the Steering Characteristics of a Vehicle

Study of the Performance of a Driver-vehicle System for Changing the Steering Characteristics of a Vehicle 20 Special Issue Estimation and Control of Vehicle Dynamics for Active Safety Research Report Study of the Performance of a Driver-vehicle System for Changing the Steering Characteristics of a Vehicle

More information

REPLACEMENT OF THE HIGH-LEVEL WASTE OFF-GAS FILTERS AT THE WEST VALLEY DEMONSTRATION PROJECT. Dan Stevens, West Valley Nuclear Services Company

REPLACEMENT OF THE HIGH-LEVEL WASTE OFF-GAS FILTERS AT THE WEST VALLEY DEMONSTRATION PROJECT. Dan Stevens, West Valley Nuclear Services Company ABSTRACT REPLACEMENT OF THE HIGH-LEVEL WASTE OFF-GAS FILTERS AT THE WEST VALLEY DEMONSTRATION PROJECT Dan Stevens, West Valley Nuclear Services Company During high-level radioactive waste (HLW) vitrification

More information

Met One Instruments. Met One Instruments BAM-1020 Improvements

Met One Instruments. Met One Instruments BAM-1020 Improvements Met One Instruments BAM-1020 Improvements Herbert Schloesser,, Ph.D. David Gobeli, Ph.D. Met One Instruments 3/31/05 1 List of Improvements Temperature sensor for compensating Temperature gradient during

More information

[Insert name] newsletter CALCULATING SAFETY OUTCOMES FOR ROAD PROJECTS. User Manual MONTH YEAR

[Insert name] newsletter CALCULATING SAFETY OUTCOMES FOR ROAD PROJECTS. User Manual MONTH YEAR [Insert name] newsletter MONTH YEAR CALCULATING SAFETY OUTCOMES FOR ROAD PROJECTS User Manual MAY 2012 Page 2 of 20 Contents 1 Introduction... 4 1.1 Background... 4 1.2 Overview... 4 1.3 When is the Worksheet

More information

Mars Surface Mobility Proposal

Mars Surface Mobility Proposal Mars Surface Mobility Proposal Jeremy Chavez Ryan Green William Mullins Rachel Rodriguez ME 4370 Design I October 29, 2001 Background and Problem Statement In the 1960s, the United States was consumed

More information

Detection of Volatile Organic Compounds in Gasoline and Diesel Using the znose Edward J. Staples, Electronic Sensor Technology

Detection of Volatile Organic Compounds in Gasoline and Diesel Using the znose Edward J. Staples, Electronic Sensor Technology Detection of Volatile Organic Compounds in Gasoline and Diesel Using the znose Edward J. Staples, Electronic Sensor Technology Electronic Noses An electronic nose produces a recognizable response based

More information