The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including:

Size: px
Start display at page:

Download "The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including:"

Transcription

1 Public Report To: From: Report Number: Community Services Committee Ron Diskey, Commissioner, Community Services Department CS Date of Report: March 24, 2017 Date of Meeting: March 30, 2017 Subject: Generators at City Facilities File: F Purpose The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including: 1. An updated status on portable generators for Fire Halls 2, 3 and 4 including a strategy on how these generators will be deployed in an emergency, for example: if all three stations are out at one time, etc.; and, 2. An update and funding strategy for a generator at Fire Hall 6; and, 3. An update on how we plan to have generators for recreation facilities in case of emergencies. 2.0 Recommendation That the Community Services Committee recommend to City Council: That as outlined in Report CS dated March 24, 2017 concerning Generators at City Facilities: 1. Fire Halls 2, 3 and 4 be fitted with permanent generators funded through the 2016 Approved Capital Budget (Project ) and the Fire Equipment Reserve; 2. That Fire Hall 6 be fitted with a permanent generator funded through the project variance from the approved Fire Hall 6 Project (Project ) and the Fire Equipment Reserve; and, 3. That a strategy for generators at recreation facilities is delayed until further investigation and options are reviewed for installing Combined Heat and Power units.

2 Meeting Date: March 30, 2017 Page Executive Summary Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, directed staff to investigate the installation of generators at Fire Halls 2, 3, 4 and 6 and also to review a generator strategy for the City including generators at recreation facilities. Staff has determined that installing permanent generators with the ability to fully operate the fire halls would be the best option based on considerations that would allow Fire Services staff to rehabilitate after calls and events and would allow for equipment such as bunker gear to be dried and prepared for the next call or event. Staff is currently investigating opportunities for a Combined Heat and Power (C.H.P.) project at the Legends Centre in partnership with Oshawa Power & Utilities Corporation (O.P.U.C.). O.P.U.C. has indicated an interest in other recreation facilities including Donevan Recreation Complex, Civic Recreation Complex and the South Oshawa Community Centre (S.O.C.C.). The installation of C.H.P. s at recreation facilities would eliminate the need for emergency generators and staff recommend delaying a decision to install emergency generators at these facilities until a complete review of C.H.P. s is completed. 4.0 Input From Other Sources Facilities Management Services Finance Services Fire Services Recreation and Culture Services O.P.U.C. 5.0 Analysis 5.1 Current Generator Inventory The following facilities have permanent generators that power the facility to varying degrees and are fueled by either natural gas or diesel. 1. Fire Hall 1 houses the communication and dispatch infrastructure for Oshawa Fire Services. The generator located at this facility is 135 kw s, fueled by diesel and it can supply power to the entire facility. 2. Fire Hall 5 is the Emergency Operations Centre for the City. The generator located at this facility is 200 kw s, fueled by natural gas and it can supply power to the entire facility. 3. Northview Community Centre was previously used as the City s Emergency Operations Centre. The generator located at this facility is 135 kw s, fueled by natural gas and supplies power to the portion of the facility added in The Consolidated Operations Depot houses many City assets and staff that would be deployed from this site during an emergency event. The generator located at this

3 Meeting Date: March 30, 2017 Page 3 facility is 120 kw s, fueled by diesel and it can supply power to the entire facility and site. 5. The Legends Centre is used as a Reception Centre in the event of a Nuclear Emergency. The generator located at this facility is 80 kw s and currently supplies power to 10% of the facility. Emergency power is supplied for emergency lighting, essential building systems and life safety equipment Mobile Generators for Fire Halls 2, 3 and 4 Currently, Fire Halls 2, 3 and 4 do not have generators. Council, as part of the 2016 Capital budget, approved $250,000 in funding to purchase a mobile generator and complete electrical modifications to each Fire Hall (project ). The mobile generator would provide full power to each facility in the event of a major emergency scenario (i.e. power outage, ice storm or flooding). This project has been delayed to review options in consideration of Notice of Motion CS Staff reviewed how a mobile generator would be deployed in an emergency, for example: if all three stations are out at one time and determined it would not be feasible if two or more fire halls required use of the mobile generator at the same time. In order to mitigate this risk, an additional mobile generator(s) would need to be purchased. This would include additional maintenance and site storage requirements. 5.3 Proposed Generators for Fire Halls 2, 3, 4 and 6 Fire Hall 2 and 4 would require a 100 kw single-phase diesel generator to supply power to the entire facility. Cost for the generator including a fenced enclosure, electrical modifications to connect the generator, installation, contingency, consulting, permits and taxes are estimated at $95,000 each or $190,000 for both locations. Staff recommends this option. Fire Hall 3 would require a 100kW multi-phase diesel generator to supply power to the entire facility. Cost for the generator including a fenced enclosure, electrical modifications to connect the generator and installation, contingency, consulting, permits and taxes are estimated at $95,000. Staff recommends this option. Fire Hall 6 was designed to contain a 100kW multi-phase natural gas generator to supply power to the entire facility. During the course of the project, the generator was removed from the scope of the project to keep within the approved budget. The generator room, gas line, and electrical infrastructure for the generator are complete. The cost for the generator including installation is estimated at $100,000 including taxes. Currently there is a positive variance of $19,000 that could be used for the installation of a permanent generator for Fire Hall 6. Additional funding of $81,000 would be required to complete this project. Staff recommends this option.

4 Meeting Date: March 30, 2017 Page 4 Other options considered for the fire halls included installing permanent smaller kw generators at each facility. The intent of the smaller generator would be to supply power to the buildings lights, overhead doors, emergency lights, and exit signs and communications equipment in order to maintain crucial functions at the facility. Staff does not recommend this option even though it is less costly. The existing electrical infrastructure would need replacing to separate the emergency only equipment from the balance of the buildings electrical requirements. Also partial power would not provide Heating, Ventilation, or Air Conditioning. These amenities are essential to allow staff to recover from calls or events during their shift and to allow them to dry their gear and prepare for the next call or event. Attachment 1 illustrates three options for a generator at the Fire Hall 2 which can act as a model for the other halls. Option 1 is for a 100KW permanent generator that will supply power to the entire Hall, Option 2 is for a 19.5 KW generator that will provide power to basic functions at the Fire Hall but would not include HVAC and only provide 20% of the lighting. Option 3 is for a mobile generator. 5.4 Power outages at Fire Halls The O.P.U.C. has provided data on the number of sustained power outages to Fire Halls 2, 3 and 4 from 2011 up to and including During this time period sustained power outages for Fire Halls 2, 3 and 4 were 35, 24 and 22 respectively during the 6 year period. During the ice storm of 2013 the issues encountered at the fire halls due to prolonged power outages were: 1. Delayed response times due to manual operation of bay doors for exiting fire trucks. During power outages, doors have to be manually pulled up and lowered before crews can respond. The doors and building were left unsecured as a result of the manual operation. 2. No area for warm / hot food preparation; the food industry was shut down so staff had no back-up food resources other than outdoor barbeques. Staff had no heat inside the fire hall, after returning from operations, crews had no warming area for rehabilitation or the ability to dry bunker gear. 3. Lighting after dark became an issue as back-up battery emergency lighting is short term only, approximately 90 minutes. This also posed a Health & Safety risk for staff operating inside the building after dark. 4. Radio / Alerting backup systems were jeopardized after their batteries run out of power. Portable radio batteries have a working cycle of approximately 6-8 hours based on a full charge, dependent on usage. Batteries would require cycling though Fire Hall 1 or 5 with on line power. 5.5 Recreation Facilities As noted previously in Section 5.1 of this report, the Legends Centre and Northview Community Centre are two recreation facilities that contain permanent generators. Recreation facilities can and have been utilized during community emergencies as evacuation locations or warming or cooling centers. It is not recommended that fire halls

5 Meeting Date: March 30, 2017 Page 5 or other City facilities be used for these purposes, as they do not have staff present to coordinate and deploy emergency measures and resources. Legends Centre is the designated Nuclear Reception Centre in the event of a nuclear incident. As part of the City s overall Emergency Plan, there would be benefit to having generator capabilities for South Oshawa Community Centre to ensure evacuation center capabilities in this sector of the city. 5.6 Combined Heat and Power (C.H.P.) As noted earlier in the report, the Legends Centre has a back-up generator that supplies limited power to the facility. City staff may bring forward a report for Council consideration of a partnership with the O.P.U.C. to install and operate a Combined Heat and Power (C.H.P.) unit at the Legends Centre. This unit would supply power to the Legends Centre, reducing dependency from the grid and will also include heat recovery to supply hot water and heated air to the building. The O.P.U.C. has expressed an interest in other City facilities as well. A C.H.P. unit at Legends would provide the building with sufficient power in the event of a power outage allowing the facility to be used as an evacuation centre if required. 5.7 Generator Strategy Currently, the City of Oshawa has generators at Fire Halls 1 and 5, at the Legends Centre and the Northview Community Centre. It is recommended that permanent generators be placed at Fire Halls 2, 3, 4 and 6. It is also recommended that plans for a mobile generator for the South Oshawa Community Centre be delayed until other options such as C.H.P. are fully explored. The O.P.U.C. has indicated if the City moves forward with the Legends Centre C.H.P. that other projects at S.O.C.C., Donevan and the Civic Recreation Complex would be considered to implement similar technology. Installation of a C.H.P. at other facilities could eliminate the need for back-up generators. This strategy would allow for recreation facilities in the north and south quadrants of the city to act as evacuation centers and allow all fire halls to maintain power during a power outage and during emergency events. 6.0 Financial Implications Staff investigated the option of purchasing all four generators at one time that could save the City approximately 7 percent. If alternate installation schedules are considered such as installation of two units in 2017 and two units in 2018, these savings may be lost. Staff are recommending all four units be purchased and installed at the same time under one project. As shown in the following chart, the 2016 capital budget approved funding in the amount of $250,000 for generators at Fire Halls 2, 3 and 4 (Project ). Project estimates for the three generators have exceeded the approved budget by $35,000. The generator for Fire Hall 6 requires an additional $81,000 in funding.

6 Meeting Date: March 30, 2017 Page 6 Facility Current funding Additional Funding Additional Funding Source Fire Hall 6 $ 19,000 (Fire Hall 6 Project funding) $81,000 Fire Equipment Reserve Fire Hall 2, 3 and 4 $250,000 (2016 Capital) $35,000 Fire Equipment Reserve The additional funding requirements can be accommodated from the uncommitted balance in the Fire Equipment Reserve. The Fire Equipment Reserve will have an uncommitted balance over $200,000 remaining if the generators are funded from the reserve. An annual contribution to the Fire Equipment Reserve will be required to provide funding for the future replacement of these assets on completion of their life cycle. Annual maintenance and fuel costs are estimated at $2,300 per generator for an approximate increase to the operating budget of $9,200 per year. 7.0 Relationship to the Oshawa Strategic Plan This report responds to the Oshawa Strategic Plan by responding to the goal of Social Equity, Ensure an inclusive, healthy and safe community and Accountable Leadership ensuring respect, responsiveness and transparency. Ron Diskey, Commissioner, Community Services Department

7 CS Attachment 1 Facility Generator Options Example Location: Fire Hall 2 Service Level Generator Installati Installation Vehicle Kitche Option Capacity Multi-Voltage Fuel Type Mobile Cost on Cost Duration Communication Doors HVAC Lights n 1 100kw No Diesel No $ 53,000 $ 22,000 1 Week Yes Yes Yes Yes Yes ** kw No Natural Gas No $ 8,500 $ 32,000 3 Weeks Yes Yes No 20% Yes 3 100kw Yes Diesel * Yes $ 92,500 $ 22,000 1 Week Yes Yes Yes Yes Yes * The mobile generator can be used to provide 100% back-up service at the other Fire Hall's, and support major components of other large City Facilities ** Option 2 - this is an off-the-shelf residential sized generator similar to the ones at Home Depot The mobile generator will require one parking space to be available, adjacent to the exterior connection Installation cost includes electrical modifications to install the automatic transfer switch and to rewire the facility to provide power to specific circuits for Op Installation costs doesn't include perimeter fencing for the generator Pricing provided are estimates only Option 1 Generator $ 53,000 Installation $ 22,000 includes electrical modifications, concrete pad and fence Subtotal $ 75,000 25% $ 18,750 consulting, permits and contingency Subtotal $ 93,750 HST $ 1,650 non-rebated portion Total $ 95,400

Feasibility of Establishing an E85 Fuelling Station in Oshawa

Feasibility of Establishing an E85 Fuelling Station in Oshawa (Oshawa Report To: From: Subject: Strategic Initiatives Committee Bob Duignan City Manager Item: SIC-09-54 File: B-1100-0082 Feasibility of Establishing an E85 Fuelling Station in Oshawa PUBLIC REPORT

More information

Public and Fleet Electric Vehicle Charging Infrastructure Strategy

Public and Fleet Electric Vehicle Charging Infrastructure Strategy CoQuitlam For Council Our File: 11-5210-01/000/2018-1 Doc#: 3187569.V3 To: From: Subject: For: City Manager General Manager, Engineering and Public Works Public and Fleet Electric Vehicle Charging Infrastructure

More information

City of Delta COUNCIL REPORT Reg ular Meeting. Metro Vanco uver Electri c Vehi cle Charging Infrastru cture Feasibility Studies

City of Delta COUNCIL REPORT Reg ular Meeting. Metro Vanco uver Electri c Vehi cle Charging Infrastru cture Feasibility Studies . I To: Mayor and Coun cil City of Delta COUNCIL REPORT Reg ular Meeting F.08 From: Corporate Servi ces Departm ent Date: November 30 2017 Metro Vanco uver Electri c Vehi cle Charging Infrastru cture Feasibility

More information

Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000

Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6b ACTION ITEM Date of Meeting August 4, 2015 DATE: TO: FROM: Dave Soike, Director, Aviation Facilities and Capital Programs Wayne Grotheer, Director,

More information

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Fitchburg Gas and Electric Light Company d/b/a Unitil ( Unitil or the Company ) indicated in the 2016-2018 Energy Efficiency

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) Presenter: National Treasury 18 November 2015 90 day Action Plan In November 2014, the Ministers

More information

Late Starter. Tuesday, November 6, 2018

Late Starter. Tuesday, November 6, 2018 Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,

More information

An Asset Management Plan for Transit And Access Transit Fleet

An Asset Management Plan for Transit And Access Transit Fleet Header Title ATTACHMENT 1 Building Better Transit: An Asset Management Plan for Transit And Access Transit Fleet 2 June 2016 Transit & Access Transit Fleet INTRODUCTION The Saskatoon Transit fleet is currently

More information

Solar is Part of a Larger Energy Initiative

Solar is Part of a Larger Energy Initiative BRIDGE SOLAR TEAM PRESENTATION UPDATE FOR ANNUAL CONGREGATIONAL INFORMATION MEETING 11 23 2015 1 Solar is Part of a Larger Energy Initiative Conducted detailed energy audits of Church facilities Solar

More information

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MOTION NO. M2016-66 Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee 07/07/16

More information

City Transfer Stations: Loading Services and Fees

City Transfer Stations: Loading Services and Fees STAFF REPORT ACTION REQUIRED City Transfer Stations: Loading Services and Fees Date: March 24, 2009 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Solid Waste

More information

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION MOTION No. M2015-71 Purchase of Five 40-foot Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee 08/06/2015 Final Action Bonnie Todd, Executive Director of Operations

More information

MOTION NO. M Light Rail Vehicle Oil-less Rotary Scroll Air Compressor Upgrade PROPOSED ACTION

MOTION NO. M Light Rail Vehicle Oil-less Rotary Scroll Air Compressor Upgrade PROPOSED ACTION MOTION NO. M2017-152 Light Rail Vehicle Oil-less Rotary Scroll Air Compressor Upgrade MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 12/07/2017 Final

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

Subject: Ontario Regulation 191/11, Integrated Accessible Standards Accessible Parking

Subject: Ontario Regulation 191/11, Integrated Accessible Standards Accessible Parking Public Report To: From: Report Number: Community Services Committee Jag Sharma, Commissioner, Community Services CS-15-71 Date of Report: March 9, 2015 Date of Meeting: April 16, 2015 Subject: Ontario

More information

OATAC On March 14, 2018 the E-Bike Working Group met at the Northview Community Centre.

OATAC On March 14, 2018 the E-Bike Working Group met at the Northview Community Centre. OATAC-18-10 E-bike Working Group Report March 23, 2018 On March 14, 2018 the E-Bike Working Group met at the Northview Community Centre. There were seven members of the O.A.T.A.C. in attendance. Councillor

More information

Ministry of Transportation of Ontario's Off-Peak Deliveries Initiative and Noise By-law

Ministry of Transportation of Ontario's Off-Peak Deliveries Initiative and Noise By-law Public Report To: From: Report Number: Corporate Services Committee Jacqueline Long, Interim Commissioner, Corporate Services Department & HR CORP-15-23 Date of Report: March 19, 2015 Date of Meeting:

More information

Electric Vehicle Charging Station Installation and Eco-Pass Updates. Report Prepared by: A. Rolston, Parking Operations Coordinator

Electric Vehicle Charging Station Installation and Eco-Pass Updates. Report Prepared by: A. Rolston, Parking Operations Coordinator Report to Council Date: File: 1862-01 To: From: Subject: City Manager D. Duncan, Manager, Parking Services Electric Vehicle Charging Station Installation and Eco-Pass Updates Report Prepared by: A. Rolston,

More information

The Regional Municipality of York. Purchase of Six Battery Electric Buses

The Regional Municipality of York. Purchase of Six Battery Electric Buses 1. Recommendations The Regional Municipality of York Committee of the Whole Transportation Services January 10, 2019 Report of the Commissioner of Transportation Services Purchase of Six Battery Electric

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS EB-00-0 Exhibit D Schedule Page of EMERGING REQUIREMENTS 0 EQUIPMENT STANDARDIZATION THESL plans, designs and constructs distribution system assets in accordance with approved standards. The standards

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

LADWP Energy Storage Update. Board of Water and Power Commissioners August 15, 2017

LADWP Energy Storage Update. Board of Water and Power Commissioners August 15, 2017 LADWP Energy Storage Update Board of Water and Power Commissioners August 15, 2017 Energy Storage Overview Energy Storage (ES) is the capture and re-dispatch of already produced energy using various technologies.

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 27, 2017

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 27, 2017 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 27, 2017 Item 6, Report No. 26, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan on

More information

Memorandum. Project Administration Department. 324 East Pine Street Tarpon Springs FL (727)

Memorandum. Project Administration Department. 324 East Pine Street Tarpon Springs FL (727) Project Administration Department 324 East Pine Street Tarpon Springs FL 34689 (727) 942-5638 Memorandum Date: March 19, 2019 To: Mayor, and Board of Commissioners Through: Mark LeCouris, City Manager

More information

Chief Operating Officer. Nigel Bell, Energy Resource Manager

Chief Operating Officer. Nigel Bell, Energy Resource Manager Policy and Resources Committee 14 October 2015 Title Report of Wards All Status Public Urgent Yes Key Yes Enclosures None Officer Contact Details Crown Commercial Services (CCS) Liquid Fuel framework RM

More information

Possible Locations for EV Chargers

Possible Locations for EV Chargers Possible Locations for EV Chargers RECOMMENDATION: THAT Council approve the installation and locations for two electric vehicle (EV) Level 2 chargers at each of the following locations: Eustace Road near

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 H DATE: August 10, 2017 ****************************************************************************** SUBJECT: SDSU Pugsley Center Renovation

More information

AND THAT Bylaw No , being Amendment No. 27 to Traffic Bylaw No. 8120, be forwarded for reading consideration.

AND THAT Bylaw No , being Amendment No. 27 to Traffic Bylaw No. 8120, be forwarded for reading consideration. Report to Council Date: File: 1862-01 To: From: Subject: D. Duncan, Manager, Parking Services Parking Rate, Fine and Fee Adjustments Recommendation: THAT Council receives, for information, the report from

More information

City Budget Fleet Services Capital Budget Analyst Notes

City Budget Fleet Services Capital Budget Analyst Notes City Budget Capital Budget Analyst Notes The City of Toronto's budget is presented by program and service, in Analyst Note format. The City's Capital Budget funds major infrastructure. -2022 Capital Program

More information

MEDIA RELEASE. June 16, 2008 For Immediate Release

MEDIA RELEASE. June 16, 2008 For Immediate Release MEDIA RELEASE June 16, 2008 For Immediate Release Recommendations to Keep Trolleys Released Alternative Proposal for Trolleys Ensures City s Sustainability The Edmonton Trolley Coalition, a non-profit

More information

COMMUNITY DEVELOPMENT BLOCK GRANT DISASTER RECOVERY (CDBG-DR) PROGRAM SUBSTANTIAL AMENDMENT NYS CDBG-DR 2013 ACTION PLAN

COMMUNITY DEVELOPMENT BLOCK GRANT DISASTER RECOVERY (CDBG-DR) PROGRAM SUBSTANTIAL AMENDMENT NYS CDBG-DR 2013 ACTION PLAN COMMUNITY DEVELOPMENT BLOCK GRANT DISASTER RECOVERY (CDBG-DR) PROGRAM PUBLIC COMMENT PERIOD ANNOUNCEMENT In 2011 and 2012, New York State was hit hard by several natural disasters including Hurricanes

More information

PROFITABILITY THRESHOLDS OF RESILIENT MICROGRIDS (and how to exceed them) Baltimore, MD October 27th, 2018

PROFITABILITY THRESHOLDS OF RESILIENT MICROGRIDS (and how to exceed them) Baltimore, MD October 27th, 2018 PROFITABILITY THRESHOLDS OF RESILIENT MICROGRIDS (and how to exceed them) Baltimore, MD October 27th, 2018 Agenda About HARC Resilience and microgrids Microgrid Design Considerations with Uncertainty HARC

More information

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Report for Action Wilson Bus Garage - Upgrades Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Summary The purpose of this report is to obtain authorization for the award of Contract No.

More information

EVSE Impact on Facility Energy Use and Costs

EVSE Impact on Facility Energy Use and Costs EVSE Impact on Facility Energy Use and Costs Bhaskaran Gopalakrishnan Professor and Director of the Industrial Assessment Center Department of IMSE, Statler College West Virginia University Need to understand

More information

Provision of Proprietary Software Licences and Maintenance from Innovyze Inc. for Hydraulic Modelling and Asset Management

Provision of Proprietary Software Licences and Maintenance from Innovyze Inc. for Hydraulic Modelling and Asset Management PW8.9 STAFF REPORT ACTION REQUIRED Provision of Proprietary Software Licences and Maintenance from Innovyze Inc. for Hydraulic Modelling and Asset Management Date: September 18, 2015 To: From: Wards: Reference

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Environment and Infrastructure Services

Environment and Infrastructure Services Agenda Item 5 Staff Report for Committee of the Whole Meeting Department: Division: Subject: Environment and Infrastructure Services Environment Services Waste Collection Contract Purpose: To provide Council

More information

6 York Region Transit (YRT/Viva) On-board Security Camera System Upgrade Contract Award

6 York Region Transit (YRT/Viva) On-board Security Camera System Upgrade Contract Award Clause 6 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 25, 2015. 6 York Region Transit (YRT/Viva)

More information

Pump Station 7 Improvements

Pump Station 7 Improvements Project Business Case ID: C04 2/18/2017 Pump Station 7 Project Purpose: The purpose of this project is to ensure that Pump Station 7 continues to operate in an efficient and effective manner following

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Purchase Sixty (60) Low Floor Wheel-Trans Mini-Buses Date: September 5, 2017 To: From: TTC Board Chief Executive Officer Summary This report recommends

More information

From: Arthur Canafe, P.E. Approved by: /s/ General Manager

From: Arthur Canafe, P.E. Approved by: /s/ General Manager AGENDA ITEM : 3.F.1 MEETING DATE: 05/17/2010 ADMINISTRATIVE REPORT : 2010-64 To: Honorable Public Utilities Board Submitted by: /s/ Robert Streich AGM Engineering and Operations From: Arthur Canafe, P.E.

More information

Annual KRTA Report for the Year 2016

Annual KRTA Report for the Year 2016 Annual KRTA Report for the Year 2016 Tracy Golden, CPE, CPA Chief Financial Officer Board Meeting August 21, 2017 Key Ratio Trend Analysis Provided by CFC each year Numbers come from annual CFC Form 7

More information

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load Memorandum To: Municipal Light Advisory Board; Municipal Light Board; file From: Belmont Light Staff Date: June 19, 2014 Re: Solar PV Distributed Generation 1. Background & Summary Belmont Light supports

More information

Sustainable CU The Environmental Improvement Initiative. E-Ride: Zero Emissions Electric Utility Vehicle March 3, 2017 Proposal

Sustainable CU The Environmental Improvement Initiative. E-Ride: Zero Emissions Electric Utility Vehicle March 3, 2017 Proposal Sustainable CU The Environmental Improvement Initiative E-Ride: Zero Emissions Electric Utility Vehicle March 3, 2017 Proposal Description of Project CU Recycling plays an integral role to create and support

More information

MSRC CLEAN TRANSPORTATION FUNDING LOCAL GOVERNMENT PARTNERSHIP

MSRC CLEAN TRANSPORTATION FUNDING LOCAL GOVERNMENT PARTNERSHIP MSRC CLEAN TRANSPORTATION FUNDING LOCAL GOVERNMENT PARTNERSHIP PROGRAM DUE: AUGUST 2, 2018 CITY OF "Agency Name" LOCAL GOVERNMENT PARTNERSHIP PROGRAM PROPOSAL SUBMITTED: "Month XX, 2018" TABLE OF CONTENTS

More information

Solar-Wind Specific Request for Proposals

Solar-Wind Specific Request for Proposals Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality

More information

Illegal Dumping at Tribal Churches and Longhouses

Illegal Dumping at Tribal Churches and Longhouses Illegal Dumping at Tribal Churches and Longhouses What Does It Really Cost? Yakama Nation Solid Waste Efficiency Study Tribal Lands and Environment August 20 23, 2012 1 Solid Waste Efficiency Study CONFEDERATED

More information

FROM: CITY MANAGER DEPARTMENT: PLANNING & COMMUNITY ENVIRONMENT

FROM: CITY MANAGER DEPARTMENT: PLANNING & COMMUNITY ENVIRONMENT TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PLANNING & COMMUNITY ENVIRONMENT DATE: AUGUST 9, 2004 CMR: 380:04 SUBJECT: ZONING ORDINANCE UPDATE ADOPTION OF A NEW AUTOMOBILE DEALERSHIP (AD)

More information

CS File: Community Services Department E-1400

CS File: Community Services Department E-1400 ~OShawa. CS-12-69 Report To: From: Community Services Committee Item: Jag Sharma, Commissioner File: Community Services Department E-1400 Date of Report: CS-12-59 May 2, 2012 Date of Meeting: May 10, 2012

More information

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MOTION NO. M2018-161 Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This

More information

STRATEGIC CAPITAL PANEL REPLACEMENT OF REFUSE COLLECTION FLEET

STRATEGIC CAPITAL PANEL REPLACEMENT OF REFUSE COLLECTION FLEET Report To: STRATEGIC CAPITAL PANEL Date: 14 March 2016 Reporting Officer: Subject: Report Summary: Ian Saxon Assistant Executive Director for Environmental Services REPLACEMENT OF REFUSE COLLECTION FLEET

More information

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience

More information

AGENDA REQUEST. AGENDA ITEM NO: XIV.5. BY Parking Management Mark Lyons Parking General Manager Lyons. January 4, 2016

AGENDA REQUEST. AGENDA ITEM NO: XIV.5. BY Parking Management Mark Lyons Parking General Manager Lyons. January 4, 2016 AGENDA HEADING: New Business AGENDA REQUEST COMMISSION MEETING DATE: January 4, 2016 AGENDA ITEM NO: XIV.5. BY Parking Management Mark Lyons Parking General Manager Lyons Originating Department SUBJECT:

More information

City of Philadelphia Renewable Energy Power Purchasing RFP Pre-Proposal Meeting

City of Philadelphia Renewable Energy Power Purchasing RFP Pre-Proposal Meeting City of Philadelphia Renewable Energy Power Purchasing RFP Pre-Proposal Meeting City Energy Office October 25, 2017 For Participants on the Phone Follow along with slides posted at: http://www.philaenergy.org/public_bids/renewable-energypower-purchasing-agreement-request-for-proposal/

More information

Demystifying Distributed Energy Resources and Microgrids Implications for Louisiana

Demystifying Distributed Energy Resources and Microgrids Implications for Louisiana Demystifying Distributed Energy Resources and Microgrids Implications for Louisiana Jennifer Vosburg Regional Senior Executive South Central SVP, October 21, 2015 LSU Center for Energy Studies Implications

More information

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012 ERCOT Overview Paul Wattles Senior Analyst, Market Design & Development Solar Energy Industries Association History of Electric Reliability Council of Texas, Inc. 1941 Utilities band together to aid war

More information

DEBBIE COMIS, CHIEF ADMINISTRATIVE OFFICER AERIAL LADDER FIRE RESCUE APPARATUS REPLACEMENT PURCHASE

DEBBIE COMIS, CHIEF ADMINISTRATIVE OFFICER AERIAL LADDER FIRE RESCUE APPARATUS REPLACEMENT PURCHASE September 27, 2017 REPORT TO: FROM: SUBJECT: PURPOSE: DEBBIE COMIS, CHIEF ADMINISTRATIVE OFFICER MARC NORRIS, FIRE CHIEF AERIAL LADDER FIRE RESCUE APPARATUS REPLACEMENT PURCHASE To request Council authorization

More information

Agenda. Industry Rate Trends Summary of Financial Targets Cost of Service Information. Valuation of Solar

Agenda. Industry Rate Trends Summary of Financial Targets Cost of Service Information. Valuation of Solar Agenda Industry Rate Trends Summary of Financial Targets Cost of Service Information Customer charges Residential Demand Charges Time of Use Rates Valuation of Solar Industry Trends Increasing demand charges

More information

Too Good to Throw Away Implementation Strategy

Too Good to Throw Away Implementation Strategy Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend

More information

2017 Colorado Phase 2 Regulatory Rate Review Frequently asked questions

2017 Colorado Phase 2 Regulatory Rate Review Frequently asked questions 1 What did Black Hills Energy file? We submitted a Phase 2 Rate Review proposal to the Colorado Public Utilities Commission (PUC) to complete the two-step process of updating electric rates, which were

More information

Ketchum Energy Advisory Committee Annual Update and Recommendation for Electric Vehicle Charging Station

Ketchum Energy Advisory Committee Annual Update and Recommendation for Electric Vehicle Charging Station March 21, 2016 Mayor Jonas and City Councilors City of Ketchum Ketchum, Idaho Mayor Jonas and City Councilors: Ketchum Energy Advisory Committee Annual Update and Recommendation for Electric Vehicle Charging

More information

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue.

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue. January 8, 2017 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: Electric Vehicle Charging Stations New Park Board Locations RECOMMENDATION

More information

Presented to Council November 7, :30 p.m. More images

Presented to Council November 7, :30 p.m. More images Presented to Council November 7, 2016 3:30 p.m. More images 1 1. Capital Projects - 25 Year Forecast 2. Public Works 3. Emergency Services 4. Library 5. Community Centre s 6. Parks & Recreation 7. Administration

More information

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council: Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community

More information

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee The Regional Municipality of Halton Report To: From: Chair and Members of the Planning and Public Works Committee Jim Harnum, Commissioner, Public Works Date: October 5, 2016 Report No. - Re: PW-36-16

More information

Low Carbon Green Growth Roadmap for Asia and the Pacific FACT SHEET

Low Carbon Green Growth Roadmap for Asia and the Pacific FACT SHEET Smart grid Low Carbon Green Growth Roadmap for Asia and the Pacific FACT SHEET Key point The smart grid allows small- and medium-scale suppliers and individuals to generate and distribute power in addition

More information

Fixed Asset Allocations by Budget Unit for FY

Fixed Asset Allocations by Budget Unit for FY 1100 112 Treasurer-Tax Collector Upgrading current business license program for greater Business License Software & Services 8965 Computer Software 1 10,900 10,900 10,900 efficiency for citizens and staff

More information

Electric Vehicle Adoption in the South African Context

Electric Vehicle Adoption in the South African Context Electric Vehicle Adoption in the South African Context Policy, Pilot Projects and Awareness Creation Challenges and Opportunities Sustainability Week CSIR ICC Transport Seminar 7 June 2018 Context 1. Transport

More information

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.

More information

Section 5 - Operations and Maintenance Program

Section 5 - Operations and Maintenance Program Section 5 - Operations and Maintenance Program A. Introduction The intent of this section of the SSMP is to describe the current operation of the City s wastewater collection system. There are five areas

More information

ATLAS PUBLIC POLICY WASHINGTON, DC USA PUBLISHED MAY 2017 VERSION 2.0

ATLAS PUBLIC POLICY WASHINGTON, DC USA PUBLISHED MAY 2017 VERSION 2.0 EV CHARGING FINANCIAL ANALYSIS TOOL USER GUIDE A FREE TOOL DESIGNED TO EVALUATE THE FINANCIAL VIABILITY OF EV CHARGING INFRASTRUCTURE INVESTMENTS INVOLVING MULTIPLE PRIVATE PUBLISHED MAY 2017 VERSION 2.0

More information

YUKON DEVELOPMENT CORPORATION

YUKON DEVELOPMENT CORPORATION YUKON DEVELOPMENT CORPORATION 2 http://www.ydc.yk.ca YUKON DEVELOPMENT CORPORATION ANNUAL REPORT 2016 TABLE OF CONTENTS Message from the Chair...4 Message from the President and Chief Executive Office...

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Chapter 740, Street Vending One Year Bylaw Review

Chapter 740, Street Vending One Year Bylaw Review Chapter 740, Street Vending One Year Bylaw Review Licensing and Standards Committee City Hall, 2 nd Floor, Committee Room 1 Tuesday April 21, 2015 Carleton Grant, Director, Policy and Strategic Support

More information

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE September 7, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE PURPOSE To update Council on Kamloops

More information

Future Funding The sustainability of current transport revenue tools model and report November 2014

Future Funding The sustainability of current transport revenue tools model and report November 2014 Future Funding The sustainability of current transport revenue tools model and report November 214 Ensuring our transport system helps New Zealand thrive Future Funding: The sustainability of current transport

More information

Building a Stronger and Smarter Electrical Energy Infrastructure. Smart Grid. A Necessary Component in the Remaking of America

Building a Stronger and Smarter Electrical Energy Infrastructure. Smart Grid. A Necessary Component in the Remaking of America Building a Stronger and Smarter Electrical Energy Infrastructure Smart Grid A Necessary Component in the Remaking of America Thomas J Gentile Chair - Energy Policy Committee IEEE-USA 2009 IEEE-USA Annual

More information

OTC/MANE-VU. 19 November 2014

OTC/MANE-VU. 19 November 2014 OTC/MANE-VU 19 November 2014 Presented by Camron Gorguinpour, PhD Executive Director United States Department of Defense Plug-In Electric Vehicle Program camron.s.gorguinpour.civ@mail.mil TASK -- Increase

More information

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency

More information

Washington State Road Usage Charge Assessment

Washington State Road Usage Charge Assessment Washington State Road Usage Charge Assessment Jeff Doyle Director of Public/Private Partnerships; and State Project Director Road User Charge Assessment August 15, 2013 Tallahassee, Florida Similarities

More information

Fuel Cells and Hydrogen 2 Joint Undertaking (FCH 2 JU) Frequently Asked Questions

Fuel Cells and Hydrogen 2 Joint Undertaking (FCH 2 JU) Frequently Asked Questions Fuel Cells and Hydrogen 2 Joint Undertaking (FCH 2 JU) Frequently Asked Questions Background information: The Fuel Cells and Hydrogen Joint Undertaking was established in 2008-2013, as the first publicprivate

More information

Green Power Feasibility Study Econet Lesotho

Green Power Feasibility Study Econet Lesotho Green Power This document has been written to provide information to mobile operators who are considering or planning to deploy green renewable power resources for base station and transmission sites.

More information

THE CORPORATION OF THE TOWN OF WHITBY. MUNICIPAL BUILDING Rossland Road East. Whitby, Ontario

THE CORPORATION OF THE TOWN OF WHITBY. MUNICIPAL BUILDING Rossland Road East. Whitby, Ontario THE CORPORATION OF THE TOWN OF WHITBY Kl:.e..t;Je Cl t1 k c. J. 13/.J-1/l!:;.A In the Regional Municipality of Durham TELEPHONE MUNICIPAL BUILDING 905-668-5803 575 Rossland Road East TORONTO Whitby, Ontario

More information

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO EB-0-0 Tab Schedule Page of CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO THESL s DOWNTOWN CONTINGENCY WORK PROGRAM The purpose of this portfolio is to provide distribution load transfer capability from

More information

Fleet Department. 1 P a g e

Fleet Department. 1 P a g e Fleet Department 1 P a g e Average Ltr/Km Service Area: Fleet Management Equipment/vehicle acquisition and disposal Licensing, maintenance and repair of fleet Ensures compliance with Federal & Provincial

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 11, 2018 To: The Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee

More information

STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. DW 13-

STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. DW 13- STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. 2013 WATER INFRASTRUCTURE AND CONSERVATION ADJUSTMENT FILING DIRECT TESTIMONY OF DONALD L. WARE

More information

Is Your Water or Wastewater System Prepared? What You Need to Know About Generators. - a water system operator

Is Your Water or Wastewater System Prepared? What You Need to Know About Generators. - a water system operator Is Your Water or Wastewater System Prepared? What You Need to Know About Generators. United States Environmental Protection Agency Mid-Atlantic EPA 903-F-11-002 March 2011 Loss of electricity quickly becomes

More information

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016 DEPARTMENT OF PARKS AND RECREATION DESIGN AND CONSTRUCTION CITY OF SAINT PAUL Mayor Christopher B. Coleman 400 City Hall Annex 25 West 4 th Street Saint Paul, Minnesota 55102 www.stpaul.gov/parks Telephone:

More information

PARTIAL PROGRAM OF PROJECTS FFY

PARTIAL PROGRAM OF PROJECTS FFY PARTIAL PROGRAM OF PROJECTS FFY 2016-17 The proposed Partial Program of Projects for FFY 2016-17 is attached. The proposed Partial Program of Projects was introduced at the SCTA Board at its meeting on

More information

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE 5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the

More information

CITY OF BELLEVILLE 2017 Capital Budget

CITY OF BELLEVILLE 2017 Capital Budget CITY OF BELLEVILLE 2017 Capital Budget Proposed Financing COMBINED SERVICES 1.001 Bridge St W Coleman to Highland Design EDS 73 300.0 150.0 150.0 1.002 University Ave McFarland Dr to Tice Cres EDS 65 1,900.0

More information

7000 Series Railcar Program Overview

7000 Series Railcar Program Overview Finance, Administration and Oversight Committee Information Item IV-B November 6, 2008 7000 Series Railcar Program Overview Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Basic tariff guiding principles

Basic tariff guiding principles Basic tariff guiding principles Small-scale Embedded Generation (SSEG) tariffs This brief outlines the basic guiding principles in tariff design for municipalities, to support and adapt to a changing electricity

More information

E) That the General Manager be authorized to execute and deliver such documentation on behalf of the Park Board.

E) That the General Manager be authorized to execute and deliver such documentation on behalf of the Park Board. Date: May 30, 2012 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Electric Vehicle Charging Stations and Cellular Infrastructure in English Bay Parks RECOMMENDATION

More information

The Benefits of Having a Municipal Electric Utility

The Benefits of Having a Municipal Electric Utility The Benefits of Having a Municipal Electric Utility Karen Weeden, Sr. Rate Analyst April 20, 2015 TOPICS Goals of the Municipal Power Advantage Program Financial Benefits Non-financial Benefits MRES Membership

More information

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas

More information