1 MAINTENANCE STANDARD PROCEDURE Ontario Operations TITLE Department Energized Work Procedure VALE # MPROC DATED PAGE Page 1 of 17 REV. 4 Table of Contents 1.0 PURPOSE APPLICATION EXCEPTIONS REFERENCE DOCUMENTATION COMMITMENTS DEFINITIONS THE NEED FOR ELECTRICALLY SAFE WORKING CONDITIONS REASONS FOR PERMITTING ENERGIZED ELECTRICAL WORK CSA Z462-15, ) PERMIT REQUIREMENT (CSA Z462-15, ) ENERGIZED ELECTRICAL WORK PERMITS (CSA Z462-15, ) EXEMPTIONS TO WORK PERMITS (CSA Z462-15, ) APPENDICES... 9 Appendix A: National Fire Protection Association Approach boundaries Appendix B: Vale - Energized Work Permit Form Appendix C: Sample Completed Energized Work Permit Appendix D: Sample Generic Energized Work Permit Appendix E: Revision Notes and Approvals Page 1 of 17

2 Department MPROC Energized Work Procedure Rev PURPOSE Since 2009, Vale has been working towards compliance with CSA Z462 (Workplace electrical safety). One of the requirements of this effort is to greatly reduce energized electrical work when feasible; however, when this effort cannot be realized, the issuance of Energized Work Permits (permits) needs to be instituted. These permits are risk assessments which complement Vale s general safety management systems such as HomeSafe (Ontario) and SafeProduction (Manitoba) using SLAM or a JHA to drive hazards down to manage risk. Overall as a business, energized electrical work should be avoided whenever possible. This procedure provides clarity on energized electrical work and provides both generic and task-specific work permit templates for performing energized work. 2.0 APPLICATION It is the Vale electrical plant authority s responsibility to make this procedure known at site and to assist in its implementation. (Equal Code EL305) It is a requirement to have an electrical authority review the permit before it is signed off by management. This procedure, applies at any Vale locations indicated with approval on the cover page, with the following exceptions: 2.1 EXCEPTIONS This procedure excludes the Power Department performing utility work that follows IHSA (EUSA) rules. This procedure excludes the following Vale jurisdictions which have their own procedure: Thompson, Manitoba - SPI 32-4 Energized Work Port Colborne Refinery, Ontario - SPI PCR 6-0 Energized Work Page 2 of 17

3 3.0 REFERENCE DOCUMENTATION Department MPROC Energized Work Procedure Rev.4 The following documents were used in the development of this document. They shall be used in their most recent revision. CSA Z Workplace electrical safety CSA Z Guideline on maintenance of electrical systems O.Reg#854 Mines and Mining Plants (Ontario) each province has its own regulation CSA C Canadian Code, Part I CSA M Use of electricity in mines O.Reg#213 Construction Projects (Ontario) each province has its own regulation ZES Zero Energy State Program Locking & Tagging Variance EMOC#7977 (Ontario only) Page 3 of 17

4 4.0 COMMITMENTS Department MPROC Energized Work Procedure Rev.4 This procedure is committed to align with the following: Vale s general safety management systems such as HomeSafe (Ontario) and SafeProduction (Manitoba) The energized work portion of CSA Z462, Workplace electrical safety 5.0 DEFINITIONS Boundary, Limited Approach: an approach limit at a distance from an exposed energized electrical conductor or circuit part within which a shock hazard exists. Boundary, Restricted Approach: an approach limit at a distance from an exposed energized electrical conductor or circuit part within which there is an increased likelihood of electric shock, due to electrical arc over combined with inadvertent movement, for personnel working in close proximity to the energized electrical conductor or circuit part. ly-safe working condition: A state in which an electrical conductor or circuit part has been disconnected from energized parts, locked out in accordance with established standards, tested to ensure the absence of voltage, and grounded (if grounding is determined to be necessary). Energized: ly connected to or having a source of voltage FAQs: Frequently Asked Questions JHA: Joint Hazard Assessment PPE: Personal Protective Equipment SLAM: Stop, Look, Assess and Manage. Page 4 of 17

5 Department MPROC Energized Work Procedure Rev THE NEED FOR ELECTRICALLY SAFE WORKING CONDITIONS Applicable codes, standards and regulations recognize that there are occasions when energized work is warranted providing that the proper methods are followed and the proper tools and protective equipment are used. Ontario Regulation 213, Construction projects (sections 181 to 195), more specifically section 190 stipulates that written measures and procedures are established to ensure that workers are adequately protected from electrical shock and burn; power supply to the electrical equipment, installation or conductor shall be disconnected, locked out of service and tagged before the work begins, and kept disconnected, locked out of service and tagged while the work continues hazardous stored electrical energy shall be adequately discharged or contained before the work beings and shall be kept discharged or contained while the work continues. Ontario Regulation 854, Mines and Mining Plants (sections 155 to 180), stipulates in section 159 that work shall not be performed on live equipment except where CSA-Z Workplace electrical safety, stipulates in section that Energized electrical conductors or circuit parts shall be put into an electrically safe work condition before a worker works within the limited approach boundary CSA-Z Guideline on maintenance of electrical systems, covers safe working conditions in section 6.7. CSA C , Canadian Code, Part I, stipulates in section 2-304(1) No repairs or alterations shall be carried out on any live equipment except where complete disconnection of the equipment is not feasible. CSA-M421-11, Use of electricity in mines, section makes stipulations on energized work as well. Vale Golden Rules, HomeSafe or SafeProduction Program (as is applicable at site) 7.0 REASONS FOR PERMITTING ENERGIZED ELECTRICAL WORK CSA Z462-15, ) Energized work may be performed when the employer can demonstrate the following: de-energizing introduces additional hazards or increased risk; the task to be performed is infeasible in a de-energized state because of equipment design or operational limitations; Page 5 of 17

6 Department MPROC Energized Work Procedure Rev.4 energized electrical conductors and circuit parts that operate at less than 50V shall not be required to be de-energized when the capacity of the source and any overcurrent protection between the energy source and the worker are considered and it is determined that there will be no increased exposure to electrical burns or to explosion due to electric arcs. Examples (not a complete list) of additional hazards or increased risk are as follows: Interruption of life support equipment Deactivation of emergency alarm systems (such as Chlorine, SO2, Fire, etc.); Shutdown of hazardous location ventilation equipment; Specific Vale examples from FAQs: o Adding or removing an MCC bucket within a critically important MCC connected to backup power feeding loads such as large motor lubrication systems, instrument air, furnace cooling pumps, fire protection pumps, etc.; and o Interruption of UPS fed panels (or lighting/distribution panels) feeding PLCs, DCS systems and instrumentation which would blind operators Examples (not a complete list) of infeasibility include the following: Performance of diagnostics and testing (e.g. start-up and troubleshooting) of electric circuits that can only be performed with the circuit energized; Work on circuits that form an integral part of a continuous process that would otherwise need to be completely shut down to permit work on one circuit or piece of equipment Specific Vale examples from FAQs: o Working on UPS batteries; o Working on substation/switch-room switchgear station batteries; o Smelter converter aisle emergency roll-out batteries; o Serving or removing cables within a marshaling cabinet, field junction box, PLC panel, operator console, UPS fed distribution panel, lighting/distribution panels feeding process PLCs and/or instruments controlling critical processes, etc. having voltages of 240 V or less and fed from transformers of 112.5kva or less Page 6 of 17

7 Department MPROC Energized Work Procedure Rev.4 Inconveniences and cost increases are not deemed as acceptable reasons to perform energized electrical work and place personnel at risk. 8.0 PERMIT REQUIREMENT (CSA Z462-15, ) When energized work is permitted in accordance with section #7, an energized electrical work permit shall be required under the following conditions: a) when work is performed within the restricted approach boundary; or b) when the worker interacts with the equipment when conductors or circuit parts are not exposed but an increased likelihood of injury from an exposure to an arc flash hazard exists. 9.0 ENERGIZED ELECTRICAL WORK PERMITS (CSA Z462-15, ) Permits should include concise information that ensures all parties understand the risks and controls involved in the task. Permits must have all signatures ranging from the requester of the work, up to the highest position at the site. This ensures that energized work is discouraged and that line management has every opportunity to seek, or offer, alternatives. Only truly justifiable work should attain approval. Refer to Appendix B and C for the Vale Energized Work Permit Form and example. In order to maintain the practical aspect of CSA-Z462, it is recommended that each site develop generic work permits which would pre-approve electrically energized work that could occur on a daily basis at each facility. Refer to Appendix D for an example taken from the Copper Cliff Smelter Complex. Here are examples of site generic work permits from FAQs: Serving, removing and terminating cables and wires into PLC marshaling cabinets; and Serving, removing and terminating cables and wires into UPS distribution panels Serving, removing and terminating cables and wires into lighting/distribution panels feeding process PLCs and/or instruments controlling critical processes Page 7 of 17

8 Department MPROC Energized Work Procedure Rev EXEMPTIONS TO WORK PERMITS (CSA Z462-15, ) An energized electrical work permit shall not be required if a qualified person is provided with and uses appropriate safe work practices and PPE under any of the following conditions: a) testing, troubleshooting, and voltage measuring; b) thermography, ultrasonic and visual inspections if the restricted approach boundary is not crossed; c) access and egress to an area with energized electrical equipment if no electrical work is performed and the restricted approach boundary is not crossed; and d) general housekeeping and miscellaneous non-electrical tasks if the restricted approach boundary is not crossed. Page 8 of 17

9 11.0 APPENDICES Department MPROC Energized Work Procedure Rev.4 Appendix A: National Fire Protection Association - Approach boundaries to energized electrical conductors or circuit parts for shock protection for AC or DC systems (distance from energized electrical conductors or circuit part to worker) * Appendix B: Vale - Energized Work Permit - Form Appendix C: Sample Completed Energized Work Permit Appendix D: Sample Generic Energized Work Permit Appendix E: Revision Notes and Approvals Page 9 of 17

10 Department MPROC Energized Work Procedure Rev.4 Appendix A: National Fire Protection Association Approach boundaries to energized electrical conductors or circuit parts for shock protection for AC or DC systems (distance from energized electrical conductors or circuit part to worker) Table 1A Approach boundaries to energized electrical conductors or circuit parts for shock protection for AC systems (distance from energized electrical conductors or circuit part to worker) Nominal System Voltage Range, Phaseto-Phase Limited Approach Boundary Exposed Movable Conductor Exposed Fixed Circuit Part Restricted Approach Boundary (includes inadvertent movement adder) Less than 50 V Not specified Not specified Not specified 50 V 150 V * 3.0 m (10 ft. 0 in) 1.0 m (3 ft. 6 in) Avoid contact 151 V 750 V 3.0 m (10 ft. 0 in) 1.0 m (3 ft. 6 in) 0.3 m (1 ft. 0 in) kv 3.0 m (10 ft. 0 in) 1.5 m (5 ft. 0 in) 0.7 m (2 ft. 2 in) kv 3.0 m (10 ft. 0 in) 1.8 m (6 ft. 0 in) 0.8 m (2 ft. 7 in) kv 3.0 m (10 ft. 0 in) 2.5 m (8 ft. 0 in) 0.8 m (2 ft. 9 in) kv 3.0 m (10 ft. 0 in) 2.5 m (8 ft. 0 in) 1.0 m (3 ft. 3 in) For single phase systems above 250V, select the range that is equal to the system s maximum phase-toground voltage times A condition in which the distance between the conductor and a person is not under the control of the person. The term is normally applied to overhead line conductors supported by poles. * This includes circuits where the exposure does not exceed 120V Table 1B: Approach boundaries to energized electrical conductors or circuit parts for shock protection for DC systems (distance from energized electrical conductors or circuit part to worker) Nominal System Voltage Range, Phaseto-Phase Limited Approach Boundary Exposed Movable Conductor Exposed Fixed Circuit Part Restricted Approach Boundary (includes inadvertent movement adder) Less than 100 V Not specified Not specified Not specified 100 V 300 V 3.0 m (10 ft. 0 in) 1.0 m (3 ft. 6 in) Avoid contact 301 V 1 kv 3.0 m (10 ft. 0 in) 1.0 m (3 ft. 6 in) 0.3 m (1 ft. 0 in) 1.1 kv 5 kv 3.0 m (10 ft. 0 in) 1.5 m (5 ft. 0 in) 0.4 m (1 ft. 5 in) A condition in which the distance between the conductor and a person is not under the control of the person. The term is normally applied to overhead line conductors supported by poles. Page 10 of 17

11 Appendix B: Vale - Energized Work Permit Form Department MPROC Energized Work Procedure Rev.4 Page 11 of 17

12 Department MPROC Energized Work Procedure Rev.4 Page 12 of 17

13 Department MPROC Energized Work Procedure Rev.4 Appendix C: Sample Completed Energized Work Permit Page 12 of 17

14 Department MPROC Energized Work Procedure Rev.4 Jason Chalut Gord Legault Janet James Page 13 of 17

15 Appendix D: Sample Generic Energized Work Permit Department MPROC Energized Work Procedure Rev.4 Page 14 of 17

16 Department MPROC Energized Work Procedure Rev.4 Page 15 of 17

17 Appendix E: Revision Notes and Approvals Department MPROC Energized Work Procedure Rev.4 Revision notes describe what was changed, and if applicable, why it was changed, and the plan to implement the change, including whether changes are retroactive. The revision notes are a summary of the changes and may not necessarily be a complete list. A risk code is entered each revision and if applicable, the revision notes will describe how risk was addressed for the revision Page 16 of 17

Energized Electrical Work

Energized Electrical Work Manitoba STANDARD PROCEDURE INSTRUCTION Title Energized Electrical Work Department Supersedes SPI Dated N/A SPI 32-4 Effective Date MAR 30, 2012 Energized Electrical Work SPI 32-4 Page 1 of 9 STANDARD

More information

Appendix A: Authorization to Work around Energized Overhead Conductors Form... 7 Appendix B: Revision Notes & Approvals... 8

Appendix A: Authorization to Work around Energized Overhead Conductors Form... 7 Appendix B: Revision Notes & Approvals... 8 of 8 Training Code: (If Applicable) Document Owner Name: Brian Koltun Position: Process Superintendent Department: Ontario Operations, Power Department TABLE OF CONTENTS. PURPOSE... 2 2. APPLICATION...

More information

Electrical Safety CSA Z462 & NB Regulations

Electrical Safety CSA Z462 & NB Regulations Electrical Safety CSA Z462 & NB Regulations WorkSafeNB s 2014 Health and Safety Conference Daniel Roberts Senior Manager, Electrical Safety Consulting at Schneider Electric Vice-chair CSA Z462 daniel.roberts@schneider-electric.com

More information

This specification describes the minimum requirements for a hoist maintenance safeguard (HMS) system for mine hoists.

This specification describes the minimum requirements for a hoist maintenance safeguard (HMS) system for mine hoists. /2.0 PURPOSE This specification describes the minimum requirements for a hoist maintenance safeguard (HMS) system for mine hoists. The HMS system is a means of preventing hoist operation or movement to

More information

BP-Husky Refinery Toledo, OH

BP-Husky Refinery Toledo, OH BP-Husky Refinery Toledo, OH Document Type: Procedure Refinery Wide Procedure No.: SAF 095 Effective Date: 2/25/16 Owner: D. Clark Working on or near Energized Electrical Equipment Rev. No.: 6 Auth. By:

More information

OSHA Update. Electric Power Generation, Transmission and Distribution Standard (Part 1910 & 1926)

OSHA Update. Electric Power Generation, Transmission and Distribution Standard (Part 1910 & 1926) OSHA Update Electric Power Generation, Transmission and Distribution Standard (Part 1910 & 1926) 5/14/2014 Significant Changes to the Standards General Training Host Employer & Contractor Responsibilities

More information

Working in Proximity to Overhead Power Lines

Working in Proximity to Overhead Power Lines Document Number: FHOS-TD0017A Revision Date: 2015/04/17 Revision: 0 Review Cycle: 3 Working in Proximity to Overhead Power Lines Standard Administrative Document Owner (Title): Manager HV C&SU/OPS Fort

More information

BP OIL -- TOLEDO REFINERY

BP OIL -- TOLEDO REFINERY BP OIL -- TOLEDO REFINERY Document Type: Procedure Effective Date: August 31, 2017 Owner: Dane P. Clark Refinery Wide Electrical Distribution System Switching and Isolation Auth. By: Rick J. Chmelovski

More information

AVOIDING ELECTROCUTION HAZARDS

AVOIDING ELECTROCUTION HAZARDS Print AVOIDING ELECTROCUTION HAZARDS MODULE DESCRIPTION This module will provide information that helps you recognize and avoid common electrocution hazards in your work environment. OBJECTIVES After completing

More information

NFPA 70E Standard for Electrical Safety Requirements for Employee Workplaces. Table Hazard Risk Category Classification

NFPA 70E Standard for Electrical Safety Requirements for Employee Workplaces. Table Hazard Risk Category Classification Table 3-3.9.1 Hazard Risk Classification Table 3-3.9.1 Hazard Risk Classification Panelboards rated 240 V and below Notes 1 and 3 - - - Circuit breaker (CB) or fused switch operation with covers on 0 N

More information

Illinois State University. Electrical Safety Procedure

Illinois State University. Electrical Safety Procedure Illinois State University Electrical Safety Procedure Illinois State University Facilities Management Revision Date: May 2014 Illinois State University Facilities Management Electrical Safety Procedure

More information

Electrical Safety Program

Electrical Safety Program Electrical Safety Program Medford Area Public School District 124 West State St School District: Medford, WI 54451 715 748 4620 Review Date(s): January 2018 Program Dave Makovsky Coordinator: Purpose and

More information

Powered Industrial Truck Safety Program

Powered Industrial Truck Safety Program Powered Industrial Truck Safety Program 0 TABLE OF CONTENTS Forklift Safety Program 1.0 Overview.. 2 2.0 Purpose....2 3.0 Procedures..2 4.0 Responsibilities. 4 5.0 Training Requirements......5 Appendix

More information

Future Proof Your Arc Flash Assessment

Future Proof Your Arc Flash Assessment Future Proof Your Arc Flash Assessment 2017 ENERGY CONNECTIONS CONFERENCE TRADE SHOW Presented by: Keith Mullen, P.E. November 9, 2017 Agenda > Utility requirements > Study objectives > Applicable standards

More information

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE 2.0 OVERHEAD CRANES

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE 2.0 OVERHEAD CRANES 1/5 1.0 PURPOSE This specification describes the minimum requirements for all activities involving hoisting, moving or transporting cargo using equipment such as mobile cranes, hoisting equipment in underground

More information

In general this document presents specific safety procedures for systems with potentially lethal voltages on bare or exposed conductors.

In general this document presents specific safety procedures for systems with potentially lethal voltages on bare or exposed conductors. 1. Introduction All safety rules presented in this document are intended to ensure safe working conditions while working with potentially dangerous voltages. It is assumed that all personnel working with

More information

ELECTRICAL AREA CONTROLLED ACCESS PROCEDURE SP-18 NATIONAL HIGH MAGNETIC FIELD LABORATORY NHMFL FLORIDA STATE UNIVERSITY SAFETY PROCEDURE SP-18

ELECTRICAL AREA CONTROLLED ACCESS PROCEDURE SP-18 NATIONAL HIGH MAGNETIC FIELD LABORATORY NHMFL FLORIDA STATE UNIVERSITY SAFETY PROCEDURE SP-18 NATIONAL HIGH MAGNETIC FIELD LABORATORY NHMFL FLORIDA STATE UNIVERSITY SAFETY PROCEDURE SP-18 CONTROLLED ACCESS PROCEDURE HEAD of MAGNET OPERATIONS Bryon Dalton EH&S MANAGER Angela Sutton HEAD OF FACILITIES

More information

REVISIONS. App Thom. App Sud. App PC DD 2015/06/24

REVISIONS. App Thom. App Sud. App PC DD 2015/06/24 /7 REVISIONS Rev Description Rev n by Sud PC Thom VB LH Clyd r Act Issue Date YYYY/MM/DD First Issue DD 205/06/24 DD 205/06/24 Pending Pending Pending Pending Pending Pending 205/06/24 Sud = Sudbury, Ontario,

More information

January 30, Ms. Safety Director Sample Medical Corp. PO Box X Somewhere, CT. Re: NFPA 70E Hazard Assessment. Date of Visit.

January 30, Ms. Safety Director Sample Medical Corp. PO Box X Somewhere, CT. Re: NFPA 70E Hazard Assessment. Date of Visit. 3018 Eastpoint Parkway Louisville, KY 40223 (502) 716-7073 January 30, 2006 Ms. Safety Director Sample Medical Corp. PO Box X Somewhere, CT Re: NFPA 70E Hazard Assessment Date of Visit January 24, 2006

More information

REVISIONS. App Thom. App Sud. App PC T.C. 2013/10/01

REVISIONS. App Thom. App Sud. App PC T.C. 2013/10/01 REQUIREMENTS / REVISIONS Rev Description Rev n by Sud PC Thom VB LH Clyd Act Issue Date YYYY/MM/DD Standard Created T.C. 203/0/0 T.C. 203/0/0 Pending Pending Pending Pending Pending Pending 203/0/0 Sud

More information

RADIATION CONTROL - RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS NOT USED IN THE HEALING ARTS

RADIATION CONTROL - RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS NOT USED IN THE HEALING ARTS DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT RADIATION CONTROL - RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS NOT USED IN THE HEALING ARTS 6 CCR 1007-1 Part 09 [Editor s Notes follow the text

More information

Electrical Safety in the Workplace

Electrical Safety in the Workplace Electrical Safety in the Workplace Increasing Electrical Safety in the Workplace through Purchasing and Procurement Robert Mitchell, Safety and Technical Safety Advisor Safety Risk, Policy and Innovation

More information

REVISIONS. App Sud. App PC. App Thom DD 2015/07/13 DD 2015/12/23

REVISIONS. App Sud. App PC. App Thom DD 2015/07/13 DD 2015/12/23 WHEEL CHOCKS FOR 1/5 REVISIONS Rev Description Rev n by Sud PC Thom VB LH Clyd Act Issue Date YYYY/MM/DD 1 New Specification BTP 015/07/13 Removed Wheel Chock Data and Table See endix A BTP 015/11/4 DD

More information

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Robert P. Hansen, P.E., PhD GE Specification Engineer Introduction Switchboards are a widely used type of equipment

More information

EDS FUSE RATINGS AT DISTRIBUTION SUBSTATIONS

EDS FUSE RATINGS AT DISTRIBUTION SUBSTATIONS Document Number: EDS 05-4001 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 05-4001 FUSE RATINGS AT DISTRIBUTION SUBSTATIONS EPN, LPN, SPN This design standard details the HV and LV fuse ratings

More information

Arc-Flash Mitigation Technologies. Dennis Balickie

Arc-Flash Mitigation Technologies. Dennis Balickie Arc-Flash Mitigation Technologies Dennis Balickie The purpose of the session is to provide an overall understanding of the strategic impact of arc-flash. Special focus is on the tactical means to minimize

More information

take to complete our safety compliance

take to complete our safety compliance This presentation is one of three steps you will take to complete our safety compliance requirements ECR Energizer Contractor Representative Primaryliaison between Energizer and the contractor for matters

More information

MAINTENANCE AND TESTING OF PORTABLE ELECTRICAL EQUIPMENT, RCDS AND TOOLS CS-OHS-33

MAINTENANCE AND TESTING OF PORTABLE ELECTRICAL EQUIPMENT, RCDS AND TOOLS CS-OHS-33 CS ENERGY OPERATIONS PROCEDURE FOR MAINTENANCE AND TESTING OF PORTABLE ELECTRICAL EQUIPMENT, RCDS AND TOOLS CS-OHS-33 Responsible Officer: Electrical Services Engineering Manager Responsible Manager: Group

More information

ELECTRICAL SAFETY-RELATED WORK PRACTICES

ELECTRICAL SAFETY-RELATED WORK PRACTICES ELECTRICAL SAFETY-RELATED WORK PRACTICES This checklist is provided to assist organizations in reviewing compliance with OSHA Standard 29 CFR 1910.331 through 1010.335. Refer to the complete Standard for

More information

ELECTRICAL. 60 Minutes

ELECTRICAL. 60 Minutes ELECTRICAL 60 Minutes AGENDA Electrical definitions Electrical shocks, burns and secondary injuries Electrical hazards in the workplace Safety devices and prevention steps Do s and Don ts INTRODUCTORY

More information

Guidance on Changes to ASTM D1655 and Def Stan to Increase Allowable FAME Limits to 50 mg/kg

Guidance on Changes to ASTM D1655 and Def Stan to Increase Allowable FAME Limits to 50 mg/kg Guidance on Changes to ASTM D1655 and Def Stan 91-91 to Increase Allowable FAME Limits to 50 mg/kg The latest revisions to the two major western jet fuel specifications, ASTM D1655-15 (primarily used in

More information

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and Guidance WASHING HIGH VOLTAGE INSULATORS USING PORTABLE WASHING EQUIPMENT Copyright National Grid plc 2014, all rights reserved.

More information

Appalachian Power Company Policy No. 2 Cover Up Procedures. Policy Summary:

Appalachian Power Company Policy No. 2 Cover Up Procedures. Policy Summary: Appalachian Power Company Policy No. 2 Cover Up Procedures Policy Summary: A. When a worker is in a position where the worker or a conductive object in the worker s hand can go or reach within the minimum

More information

Non-Beam Hazard - Electricity

Non-Beam Hazard - Electricity Non-Beam Hazard - Electricity 2013 DOE LSO Workshop - NIST Heath Garrison September 1, 2013 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy,

More information

Permit for Charging Equipment Installation Electric Vehicle Supply Equipment (EVSE)

Permit for Charging Equipment Installation Electric Vehicle Supply Equipment (EVSE) Permit for Charging Equipment Installation Electric Vehicle Supply Equipment (EVSE) Town of Lake George, New York Compliance with the following permit will allow the installation and operation of electric

More information

The Use of Electricity In Mines Regulations

The Use of Electricity In Mines Regulations The Use of Electricity In Mines Regulations Repealed by Chapter E-6.3 Reg 4 (effective February 28, 1996). Formerly Chapter E-7.1 Reg 5. Table of Contents 1 Title 2 CSA Standard adopted with amendment

More information

The following documents were used in the development of this document or are related to it. The most recent revision shall be used.

The following documents were used in the development of this document or are related to it. The most recent revision shall be used. 1/1 1.0 PURPOSE This guideline describes the standards for Construction Trailers. The purpose is to assist contractors, ERM personnel, and other Vale staff to implement these standards. 2.0 REFERENCE DOCUMENTATION

More information

Wind and Temperature Tip Over Hazard Do not add notice boards or similar

Wind and Temperature Tip Over Hazard Do not add notice boards or similar Lift & Work Platform Safety Information Safety Information: Boom Lifts Safety Information: Scissor Lifts Safety Information: Boom Lifts Power Lines Electrocution Hazard Maintain safe clearance from Electrical

More information

REVISIONS App PC. App Sud. App Thom TC 2014/03/25

REVISIONS App PC. App Sud. App Thom TC 2014/03/25 /9 Rev Description Document format and number changed. Previous number 543-0.0.30 Rev n by TC 204/03/25 Sud TC 204/03/25 REVISIONS PC Thom VB LH Clyd r Act Issue Date YYYY/MM/DD Pending Pending Pending

More information

UNIVERSITY. MANITOBA PHYSICAL PLANT Aerial Work. Safe Work. Practice # Platform Operations

UNIVERSITY. MANITOBA PHYSICAL PLANT Aerial Work. Safe Work. Practice # Platform Operations UNIVERSITY OF MANITOBA PHYSICAL PLANT Aerial Work Safe Work Practice # Platform Operations 1.15.4 Edited by: pproved by: Created by: Created: Sept 2014 John Evinger M- Lloyd Peacock M - NIA W. Cory Sliworski

More information

ELECTRICAL HAZARD EXAMPLES

ELECTRICAL HAZARD EXAMPLES ELECTRICAL HAZARD EXAMPLES UNFORTUNATELY, THE EVENTS LISTED BELOW ARE MORE COMMON THAN YOU WOULD EXPECT Circuit breaker does not open the circuit when operated manually or remotely. The contacts within

More information

Energized. Need to access completely for Ebook PDF energized

Energized. Need to access completely for Ebook PDF energized ENERGIZED PDF - Are you looking for energized Books? Now, you will be happy that at this time energized PDF is available at our online library. With our complete resources, you could find energized PDF

More information

Electrical Safety. Electrical Safety Webinar. Electrical. Printing Industries Alliance Printing Industries Alliance 1

Electrical Safety. Electrical Safety Webinar. Electrical. Printing Industries Alliance Printing Industries Alliance 1 Webinar 1 Electrical 2 1 Webinar Introduction An average of one worker is electrocuted on the job every day There are four main types of electrical injuries: Electrocution (death due to electrical shock)

More information

Unrestricted. S.Mukhopadhyay

Unrestricted. S.Mukhopadhyay Unrestricted S.Mukhopadhyay 10.09.15 Electrical safety A report says that every year 5500 Indians die due to electric shock and 800 due to electric fire. 12% work place death due to electrocution ELECTRICAL

More information

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and HIGH VOLTAGE METAL CLAD SWITCHGEAR WITH SPOUTS Copyright National Grid plc 2014, all rights reserved. No part of this publication

More information

B-03 ELECTRICIAN TRAINING SKILL DEVELOPMENT GUIDE

B-03 ELECTRICIAN TRAINING SKILL DEVELOPMENT GUIDE B-03 ELECTRICIAN TRAINING SKILL DEVELOPMENT GUIDE Duty B: Power Distribution (600V and below) B-03: Troubleshoot 480V System Issued 06/01/98 Task Preview Troubleshoot 480V System The 480V distribution

More information

An average of one worker is electrocuted on the job every day There are four main types of electrical injuries:

An average of one worker is electrocuted on the job every day There are four main types of electrical injuries: Electrical Safety Introduction An average of one worker is electrocuted on the job every day There are four main types of electrical injuries: Electrocution (death due to electrical shock) Electrical shock

More information

Electrical Safe Work Practices

Electrical Safe Work Practices Electrical Safe Work Practices Responsible Official: Matthew Early, VP for Campus Services Administering Division/Department: Facilities Management Effective Date: April, 22 Policy Sections: I. Purpose

More information

Definitions. Exposed part. Live or energized part. De-energized part

Definitions. Exposed part. Live or energized part. De-energized part Electrical Safety Definitions Exposed part Live or energized part De-energized part 1a Definitions De-energized exposed parts that are not locked/tagged are considered to be energized exposed parts 1b

More information

Agenda / ESPS Electrical Safety Program Solutions INC.

Agenda / ESPS Electrical Safety Program Solutions INC. PEM Partners in Training Asset Management & Reliability Risk Assessment in the new CSA Z462 Electrical Power Distribution Reliability & Safety, a Valuable Balance Terry Becker, P.Eng., NFPA CESCP Owner,

More information

Table of Contents. Why An Occupational Health and Safety Program Demonstrating Commitment to Occupational Health and Safety... 1.

Table of Contents. Why An Occupational Health and Safety Program Demonstrating Commitment to Occupational Health and Safety... 1. Table of Contents Foreword... i 1. Introduction Why An Occupational Health and Safety Program... 1.1 Demonstrating Commitment to Occupational Health and Safety... 1.4 Appendix I: District Commitment to

More information

Key elements of the AS3000 Wiring standards and some of the recent changes.

Key elements of the AS3000 Wiring standards and some of the recent changes. Key elements of the AS3000 Wiring standards and some of the recent changes. Dean of Engineering Steve Mackay Worked for 30 years in Industrial Automation 30 years experience in mining, oil and gas, electrical

More information

NON-FATAL ELECTRICAL INJURIES AT WORK

NON-FATAL ELECTRICAL INJURIES AT WORK NON-FATAL ELECTRICAL INJURIES AT WORK Richard Campbell May 2018 Copyright 2018 National Fire Protection Association (NFPA) CONTENTS Findings and Trends 1 Key Takeaways 2 Background on Data Sources and

More information

Electrical Safety. Recognizing & Controlling Hazards

Electrical Safety. Recognizing & Controlling Hazards Electrical Safety Recognizing & Controlling Hazards Introduction Healthcare facilities, including hospitals, physician offices, laboratoratories, dental offices and beyond are vulnerable to a variety of

More information

CCHMP Comments on ConocoPhillips Incident Report For 10/22/10 Flaring Event

CCHMP Comments on ConocoPhillips Incident Report For 10/22/10 Flaring Event CCHMP Comments on ConocoPhillips Incident Report For 10/22/10 Flaring Event The following comments relate to reviewing ConocoPhillip s RCA report received on 12/21/10. 1. The report identified that operators

More information

The New 2017 National Electric Safety Code Overview and Significant Changes. Presented by. Mickey Gunter October 28, 2016

The New 2017 National Electric Safety Code Overview and Significant Changes. Presented by. Mickey Gunter October 28, 2016 The New 2017 National Electric Safety Code Overview and Significant Changes Presented by Mickey Gunter October 28, 2016 NESC Technical Subcommittees Subcommittee 1 Coordination, Definitions Subcommittee

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

Safety Training Topic ELECTRICAL SAFETY

Safety Training Topic ELECTRICAL SAFETY Safety Training Topic Purpose of Meeting To remind workers that electrical hazards can result in a serious injury. To reinforce electrical safety rules. To consider ways to protect yourself from electrical

More information

Electrical Work (CPC-ALL-HSE-PRC-167)

Electrical Work (CPC-ALL-HSE-PRC-167) (CPC-ALL-HSE-PRC-167) DRM Retention Code: CG01 - CA Document to be reviewed every 2 years or less versions of this document are valid to be used until notified of revision via the Document Control Process.

More information

IMPORTANT SAFEGUARDS

IMPORTANT SAFEGUARDS INSTRUCTION MANUAL NON-INTERRUPTIBLE AC INVERTER SYSTEM MODEL EAC FTM 350 FOR EMERGENCY LIGHTING POWER IMPORTANT SAFEGUARDS When using electrical equipment, basic safety precautions should always be followed,

More information

36CSR27 TITLE 36 LEGISLATIVE RULE BOARD OF COAL MINE HEALTH AND SAFETY SERIES 27 RULES AND REGULATIONS GOVERNING SURFACE AREAS

36CSR27 TITLE 36 LEGISLATIVE RULE BOARD OF COAL MINE HEALTH AND SAFETY SERIES 27 RULES AND REGULATIONS GOVERNING SURFACE AREAS TITLE 36 LEGISLATIVE RULE BOARD OF COAL MINE HEALTH AND SAFETY SERIES 27 RULES AND REGULATIONS GOVERNING SURFACE AREAS 36-27-1. General. 1.1. Scope. -- Rules and Regulations Governing Surface Areas. 1.2.

More information

Arc flash hazard mitigation

Arc flash hazard mitigation Low Voltage Products Arc flash hazard mitigation Each year more than 2,000 people are treated in burn centers with severe arc flash injuries. ABB designs and manufactures products and solutions to provide

More information

STANDARD OPERATING PROCEDURES. ELECTRICAL HAZARDS SAFETY PROCEDURES PURPOSE: To provide safety procedures for the removal of electric meters,

STANDARD OPERATING PROCEDURES. ELECTRICAL HAZARDS SAFETY PROCEDURES PURPOSE: To provide safety procedures for the removal of electric meters, PURPOSE: To provide safety procedures for the removal of electric meters, SCOPE: All firefighting personnel. I. ELECTRIC METERS: The following are safety procedures for the removal of an electric meter

More information

CAL/OSHA ELECTRICAL LOW VOLTAGE

CAL/OSHA ELECTRICAL LOW VOLTAGE Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to electrical exposure to low voltage (less than or equal to

More information

Electrical Equipment and Safety: Operation, Control, Maintenance and Troubleshooting

Electrical Equipment and Safety: Operation, Control, Maintenance and Troubleshooting Electrical Equipment and Safety: Operation, Control, Maintenance and Troubleshooting Page 1 of 6 Why Attend This course covers the theoretical and practical operation of common electrical equipment and

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Electrical Safety and Overcurrent Protection

Electrical Safety and Overcurrent Protection Electrical Safety and Overcurrent Protection Dave Vallier DSE Bussmann division Contact info: Phone: 586-201-1348 Email: Davemvallier@eaton.com Agenda 1. Electrical hazards overview 2. The role of the

More information

ESSENTIAL SAFETY RESOURCES

ESSENTIAL SAFETY RESOURCES ESSENTIAL SAFETY RESOURCES GS-3029 Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager s Signature: Type Name Table of Contents PURPOSE...

More information

EV-2051-M Electric Motor. Operation and Maintenance Manual

EV-2051-M Electric Motor. Operation and Maintenance Manual EV-2051-M Electric Motor Operation and Maintenance Manual Table of Contents Safety... 3 General...3 Safety Notices...6 Cautions, Warnings and Dangers...7 Cautions...8 Warnings...11 Dangers...13 Important

More information

ibusway for Data Center

ibusway for Data Center ibusway for Data Center PBPQOD Plug-In Units with 15 60 A Circuit Breakers for Use On Busway Straight Sections Class 5600 Installation S1B99523 06/2012 Hazard Categories and Special Symbols Read these

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Guidelines for Safety Training of Overhead Crane Operators and Supervisors

Guidelines for Safety Training of Overhead Crane Operators and Supervisors Guidelines for Safety Training of Overhead Crane Operators and Supervisors Purpose These guidelines present minimum recommended safety requirements for ensuring the safe and efficient operation of overhead

More information

PART I RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS

PART I RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS PART I RADIATION SAFETY REQUIREMENTS FOR PARTICLE ACCELERATORS Sec. I.1 Purpose and Scope a. This Part establishes procedures for the registration [or licensing] and the use of particle accelerators. b.

More information

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM Page 1 of 19 Table of Contents 1.0 SCOPE...4 2.0 PURPOSE...4 3.0 LIMITATIONS...5 4.0 GENERAL INTERCONNECTION

More information

Bulletin Wiring methods for solar photovoltaic systems Rules 2-034, , , , , Tables 11 and 19

Bulletin Wiring methods for solar photovoltaic systems Rules 2-034, , , , , Tables 11 and 19 Bulletin 64-4-1 Wiring methods for solar photovoltaic systems Rules 2-034, 64-066, 64-210, 64-216, 64-220, Tables 11 and 19 Scope (1) Introduction (2) Cable types RPV & RPVU (3) Wiring methods within photovoltaic

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

5.1 Design and Install Dispenser Transfer Systems Performance Based Skill Assessments 2019

5.1 Design and Install Dispenser Transfer Systems Performance Based Skill Assessments 2019 5.1 Design and Install Dispenser Transfer Systems Performance Based Skill Assessments 2019 Section One: Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Task 8 Design Dispenser Transfer System Determine

More information

FACT SHEET Standard: Electrical Safety

FACT SHEET Standard: Electrical Safety What is a Ground Fault Circuit Interrupter? FACT SHEET The ground-fault circuit interrupter, or GFCI, is a fast-acting circuit breaker designed to shut off electric power in the event of a ground-fault

More information

Arc flash solutions catalogue Australia. Safety solutions - Protecting employees and the enterprise

Arc flash solutions catalogue Australia. Safety solutions - Protecting employees and the enterprise Arc flash solutions catalogue Australia Safety solutions - Protecting employees and the enterprise The risk of an arc flash event is real An arc flash hazard is a proven significant and dangerous threat

More information

PREVIEW ONLY - FULL COPY AVAILABLE TO CONSORTIUM MEMBERS. Escalator Specific Electrical Systems. Course 209 PARTICIPANT GUIDE

PREVIEW ONLY - FULL COPY AVAILABLE TO CONSORTIUM MEMBERS. Escalator Specific Electrical Systems. Course 209 PARTICIPANT GUIDE Escalator Specific Electrical Systems Course 209 PARTICIPANT GUIDE Transit Elevator/Escalator Training Consortium Escalator: Electrical Systems Participant Guide Transit Elevator/Escalator Maintenance

More information

ELECTRICAL SAFETY A Program Development Guideline

ELECTRICAL SAFETY A Program Development Guideline ELECTRICAL SAFETY A Program Development Guideline EDITION» 1 REVISED» August 29, 2018 RELEASE DATE» June 1, 2014 Setting the standard in oil gas safety Energy Safety Canada» Electrical Safety: A Program

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

Grounding Of Standby & Emergency Power Systems

Grounding Of Standby & Emergency Power Systems July / August 2007 ELECTRICAL LINE 53 Grounding Of Standby & Emergency Power Systems By Andrew Cochran Power continuity is essential in many industrial and commercial installations where a trip out due

More information

UC Irvine Environmental Health & Safety SECTION: TITLE: Powered Industrial Truck (Forklift) Safety Program

UC Irvine Environmental Health & Safety SECTION: TITLE: Powered Industrial Truck (Forklift) Safety Program UC Irvine Environmental Health & Safety SECTION: TITLE: Powered Industrial Truck (Forklift) Safety Program INITIATOR: Desirée Villarreal REVISION DATE: 10/17/2014 1. Program Description 2. Scope 3. Definitions

More information

New 2002 NEC. Arc Flash Hazard Marking Requirement Cooper Bussmann, Inc.

New 2002 NEC. Arc Flash Hazard Marking Requirement Cooper Bussmann, Inc. 110.16 New 2002 NEC Arc Flash Hazard Marking Requirement 2001 Cooper Bussmann, Inc. 110.16 Flash Protection. Switchboards, panelboards, industrial control panels, and motor control centers in other than

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

CSDA Best Practice. Hi-Cycle Concrete Cutting Equipment. Effective Date: Oct 1, 2010 Revised Date:

CSDA Best Practice. Hi-Cycle Concrete Cutting Equipment. Effective Date: Oct 1, 2010 Revised Date: CSDA Best Practice Title: Hi-Cycle Concrete Cutting Equipment Issue No: CSDA-BP-010 : Oct 1, 2010 Revised : Introduction Hi-cycle/high frequency concrete cutting equipment has become more prevalent in

More information

Unqualified persons: People with little or no such training related to electrical equipment and safety.

Unqualified persons: People with little or no such training related to electrical equipment and safety. Electrical Safety University of Tennessee Safety Guide GS-070 Document Contact: EHS-General Safety Date effective: August 1, 2009 Revision Date: March 14, 2012 Purpose This documents serves as a guide

More information

ACHIEVING MAXIMUM BENEFITS WITH A FUSE PROTECTED MOTOR CONTROL CENTER

ACHIEVING MAXIMUM BENEFITS WITH A FUSE PROTECTED MOTOR CONTROL CENTER ACHIEVING MAXIMUM BENEFITS WITH A FUSE PROTECTED MOTOR CONTROL CENTER SYSTEM PROTECTION NOTE 2 BY MIKE LANG, PRINCIPAL FIELD ENGINEER INTRODUCTION Increasing concern for arc flash safety has grown to include

More information

1996, or for which modification is commenced on or before March 16, 1998, shall not exceed the

1996, or for which modification is commenced on or before March 16, 1998, shall not exceed the 15A NCAC 02D.1206 HOSPITAL, MEDICAL, AND INFECTIOUS WASTE INCINERATORS (a) Applicability. This Rule applies to any hospital, medical, and infectious waste incinerator (HMIWI), except: (1) any HMIWI required

More information

Mark Lyvers LLC / Cooper Bussmann Arc Flash Script Script to accompany PowerPoint on New 2002 NEC Arc Flash Hazard Marking Requirement

Mark Lyvers LLC / Cooper Bussmann Arc Flash Script Script to accompany PowerPoint on New 2002 NEC Arc Flash Hazard Marking Requirement Mark Lyvers LLC / Cooper Bussmann Arc Flash Script Script to accompany PowerPoint on 110.16 New 2002 NEC Arc Flash Hazard Marking Requirement Slide 1 Suggestion on How to Use Download both the Mark Lyvers

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E8: Battery Condition Assessment E8.1 GENERAL Plant or station batteries are key components in hydroelectric powerplants and are appropriate for

More information

Surface Regulations and Policies

Surface Regulations and Policies Surface Regulations and Policies COAL FATALITIES 1970-2002 350 300 250 200 150 100 50 0 1970 1973 1976 1979 1982 1985 1988 1991 1994 1997 2000 From January 1, 1970 through today, a total of 240 coal miners

More information

CHAPTER 40 PROFESSIONAL LICENSING AND FACILITY REGULATION. PART 13 Radiation Safety Requirements for Particle Accelerators

CHAPTER 40 PROFESSIONAL LICENSING AND FACILITY REGULATION. PART 13 Radiation Safety Requirements for Particle Accelerators 216-RICR-40-20-13 TITLE 216 DEPARTMENT OF HEALTH CHAPTER 40 PROFESSIONAL LICENSING AND FACILITY REGULATION SUBCHAPTER 20 - RADIATION PART 13 Radiation Safety Requirements for Particle Accelerators 13.1

More information

Motor Vehicle Safety and Journey Management Document Number OHS-PROC-31. Rockhampton Office Brisbane Office Tarong Site

Motor Vehicle Safety and Journey Management Document Number OHS-PROC-31. Rockhampton Office Brisbane Office Tarong Site Business Procedure Motor Vehicle Safety and Journey Management Document Number OHS-PROC-31 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron

More information

STATISTICS ELECTRICAL INCIDENTS IN ALBERTA. January 1 to December 31, 2012

STATISTICS ELECTRICAL INCIDENTS IN ALBERTA. January 1 to December 31, 2012 Safety Services 16 th floor, Commerce Place Tel: 1-866-421-6929 10155 102 nd Street Fax: 780-427-8686 Edmonton, Alberta Canada T5J 4L4 STATISTICS ELECTRICAL INCIDENTS IN ALBERTA January 1 to December 31,

More information

TABLE OF CONTENTS 1. GENERAL LABOUR COSTS EQUIPMENT COSTS...2

TABLE OF CONTENTS 1. GENERAL LABOUR COSTS EQUIPMENT COSTS...2 TABLE OF CONTENTS 1. GENERAL...2 2. LABOUR COSTS...2 3. EQUIPMENT COSTS...2 4. DISTRIBUTION MATERIAL COSTS (EDS AND OIL AND GAS FIELD SERVICE MODELS)..3 5. STREET LIGHTING...3 6. TRANSMISSION LINES...3

More information

Petitions for Modification of Application of Existing Mandatory Safety Standards. AGENCY: Mine Safety and Health Administration, Labor.

Petitions for Modification of Application of Existing Mandatory Safety Standards. AGENCY: Mine Safety and Health Administration, Labor. This document is scheduled to be published in the Federal Register on 07/21/2016 and available online at http://federalregister.gov/a/2016-17174, and on FDsys.gov Billing Code: 4520-43-P DEPARTMENT OF

More information

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE PAGE 261116-1 SECTION 261116 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Revised: April 2018 ¹ SERVICE TO WIRELESS DEVICE ANTENNA ATTACHMENTS ON CUSTOMER SERVICE POLES (SHEET 1) CUSTOMER: 1. An overcurrent protective device including a disconnect switch shall

More information