TOMS RIVER REGIONAL SCHOOLS PHASE II INTERMEDIATE NORTH FACILITY ENERGY REPORT 150 INTERMEDIATE N. WAY TOMS RIVER, NJ 08753

Size: px
Start display at page:

Download "TOMS RIVER REGIONAL SCHOOLS PHASE II INTERMEDIATE NORTH FACILITY ENERGY REPORT 150 INTERMEDIATE N. WAY TOMS RIVER, NJ 08753"

Transcription

1 TOMS RIVER REGIONAL SCHOOLS PHASE II INTERMEDIATE NORTH 150 INTERMEDIATE N. WAY TOMS RIVER, NJ FACILITY ENERGY REPORT

2 TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY DESCRIPTION... 9 III. MAJOR EQUIPMENT LIST IV. ENERGY CONSERVATION MEASURES V. ADDITIONAL RECOMMENDATIONS Appendix A ECM Cost & Savings Breakdown Appendix B New Jersey Smart Start Program Incentives Appendix C Portfolio Manager Statement of Performance Appendix D Major Equipment List Appendix E Investment Grade Lighting Audit Appendix F Transformer Calculation September 29, 2014 FINAL Page 1 of 63

3 I. HISTORIC ENERGY CONSUMPTION/COST The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. Electric Utility Provider: Electric Utility Rate Structure: Third Party Supplier: Natural Gas Utility Provider: Utility Rate Structure: Third Party Supplier: Water Utility Provider: Utility Rate Structure: Sewer Service Suppler: Jersey Central Power & Light (JCP&L) General Service 3-Phase Direct (Hess) New Jersey Natural Gas (NJNG) General Service Large Direct (Hess) United Water WTM (Metered Service) Municipal Utilities Authority Fixed Payment The electric usage profile represents the actual electrical usage for the facility. The electric utility measures consumption in kilowatt-hours (KWH) and maximum demand in kilowatts (KW). One KWH usage is equivalent to 1000 watts running for one hour. One KW of electric demand is equivalent to 1000 watts running at any given time. The basic usage charges are shown as generation service and delivery charges along with several non-utility generation charges. Rates used in this report reflect the historical data received for the facility. The district installed an onsite solar array to generate power, reducing the amount of electric it purchases from the utility. New Jersey s net metering guidelines allow them to get an on bill credit for exported KWH, to be utilized in the months to follow, up until the annual balance date when any remaining credit of KWH is paid to the owner based on average electric market pricing for the year. The Electric Billing Data summarized reflects the net electric used by the facility based on utility purchased electric and onsite solar. Note the price for electric is only based on grid purchased power, as any reductions in energy use will reduce utility purchased power requirements. The gas usage profile within each facility report shows the actual natural gas energy usage for the facility. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy. The water usage profile for this facility shows the actual water consumption based on collected utility bills. The water utility measures consumption in gallons (gal), and converts the quantity into 1,000 gallons. September 29, 2014 FINAL Page 2 of 63

4 ELECTRIC USAGE SUMMARY Table 1 Electricity Billing Data Utility Provider: JCP&L Rate: General Service 3-Phase Meter No: S Account No: Third Party Utility Provider: Direct TPS Meter / Acct No: - MONTH OF USE CONSUMPTION KWH DEMAND KW TOTAL BILL Jul-13 93, $4,545 Aug , $16,082 Sep , $14,608 Oct , $14,203 Nov , $14,048 Dec , $12,942 Jan , $14,367 Feb , $14,944 Mar , $13,239 Apr , $9,154 May , $14,479 Jun , $16,136 Totals 1,847, Max $158,747 AVERAGE DEMAND KW average AVERAGE GRID RATE $0.124 $/kwh The figure below depicts the month to month electric profile, showing both the generated solar electric, and the net utility metered electric either as an export (negative) or import (positive). The sum of which reflects the building electric consumption. September 29, 2014 FINAL Page 3 of 63

5 Figure 1 Electricity Usage Profile September 29, 2014 FINAL Page 4 of 63

6 NATURAL GAS USAGE SUMMARY Table 2 Natural Gas Billing Data Utility Provider: New Jersey Natural Gas Rate: GSL Meter No: Account No: Third Party Utility Provider: Hess, Direct TPS Meter No: / CONSUMPTION MONTH OF USE (THERMS) TOTAL BILL Jun $1, Jul $1, Aug $ Sep $1, Oct $1, Nov-13 4, $5, Dec-13 7, $8, Jan-14 16, $17, Feb-14 11, $12, Mar-14 9, $11, Apr-14 4, $5, May $2, TOTALS 54, $68, AVERAGE RATE: $1.26 $/THERM September 29, 2014 FINAL Page 5 of 63

7 Figure 2 Natural Gas Usage Profile September 29, 2014 FINAL Page 6 of 63

8 Table 3 Water Billing Data WATER USAGE SUMMARY Utility Provider: United Water Rate: WTM Meter No: A, B Point of Delivery ID: MONTH OF USE CONSUMPTION (1,000 GALLONS) TOTAL BILL Apr $94.68 May $ Jun $33.92 Jul $33.92 Aug $ Sep $33.92 Oct $ Nov $67.85 Dec $67.85 Jan $67.85 Feb $67.85 Mar $ TOTALS $ AVERAGE RATE: $6.74 $/1000 GAL Note: Water Costs only reflect consumption charges and do not include the service charge component. September 29, 2014 FINAL Page 7 of 63

9 Figure 3 Water Usage Profile September 29, 2014 FINAL Page 8 of 63

10 II. FACILITY DESCRIPTION The Intermediate North School is located at 150 Intermediate N. Way in Toms River, New Jersey. This 178,300 SF facility was built in 1972 and is used as a public middle school. The hexagonal classroom C-wing is a two-story structure while the B-wing, D-wing and Common Areas are single-story. The facility is comprised of a main office, general classrooms, computer lab, gym, auxiliary gym, kitchen, cafetorium, faculty dining area, media center, SGI classrooms, nurse s office, restrooms, boiler room, HVAC penthouse, and utility/storage rooms. Occupancy Profile The typical hours of operation for the Intermediate North School are Monday through Friday between 7:00 am and 5:00 pm, with custodial staff on site afterhours till approximately 10:00 pm. Additional events occur throughout the year after hours in the facility. The school s normal operations span 10 months, with summer programs and community activities occurring during July and August. The school has an enrollment of 1,360 students and 150 staff. Building Envelope Exterior walls for the building are masonry brick faced with concrete block interior walls. The widow systems are single pane, operable, 1/8 glass with aluminum frames, are not thermally broken, and very energy inefficient. Many rubber gaskets on these aluminum framed windows were observed to be missing or falling out, which leads to air and water infiltration. Some windows are difficult to operate and do not lock properly. Perimeter sealants are failed and numerous muntins have pulled away from the glass. Worn weather-stripping, signs of some water damage, and air leakage were observed on several of the exterior doors. Blinds are utilized through the facility for occupant comfort. The blinds are valuable because they help to reduce heat loss in the winter and reduce solar heat gain in the summer. The windows throughout the school are in poor condition and should be replaced with new, energy efficient, commercial grade, thermally broken aluminum framed windows with low-e, insulated glass panels. Various roofing systems are installed at the school with a large portion of the roof consisting of modified bitumen roofing over asphalt and a mineral surface of white or brown granules. Another portion of the roof is a flat, built-up rubber roof with a brown water sealant sprayed over the rubber membrane. Another portion of the roof for this building is constructed of a built-up roof with rubber membrane and light color stone covering. The condition of the rubber membrane and the amount of insulation below the roof is unknown. HVAC Systems The facility is heated by a central hot water boiler plant located in the boiler room. Heating hot water is provided by two (2) Superior watertube, gas-fired boilers manufactured in 1988 with a rated input of 4,000 MBH and have an estimated thermal efficiency of 70% based on their condition and age. The gas-fired burner is a Superior Cyclonetic Model JB2C-30-D20 with a September 29, 2014 FINAL Page 9 of 63

11 maximum rating of 4,000 MBH and a minimum rating of 1,008 MBH. The burner is driven by a 3 HP Marathon motor. It is strongly recommended that these Superior boilers be replaced with high-efficiency, gasfired, modular condensing boilers and properly sized for the existing heating load. The building has two (2) sets of hot water pumps that pump hot water to various hot water coils in unit ventilators, cabinet heaters, unit heaters, fin-tube radiators, etc. in the B-wing and C-wing. One pump is an Armstrong Series 1510 base-mounted, end suction pump with a Marathon Series E high efficiency 7.5 HP motor and rated for 240 GPM at 60 feet of head. The other pump is an Armstrong Series 1510 base-mounted, end suction pump with a Marathon Series E high efficiency 10 HP motor and rated for 260 GPM at 80 feet of head. The majority of the cooling for the facility is achieved via a water-cooled chiller and four (4) split air-cooled chillers. The water-cooled chiller is a Carrier Model 30HXC161PZ rated at 155- Tons with two (2) Carlyle Model 06NW2250 screw compressors using R-134a refrigerant. Load control of this chiller is achieved via staging of the two compressors. The unit is located in the boiler room and serves the various air handling units in the common areas and B-wing. The cooling tower for this unit is on the kitchen roof and is an Evapco Model AT single cell tower with a nominal rating of 138-Tons and airflow of 29,700 CFM. The tower fan is driven by an Emerson 7.5 HP motor with an efficiency of 91.0%. The chilled water is delivered to various chilled water coils via two (2) Taco Model base-mounted end suction pumps with 15 HP motors and rated for 350 GPM at 80 feet of head. The condenser water is served by a Taco Model base-mounted end suction pumps with 10 HP motors and rated for 400 GPM at 60 feet of head. The existing four (4) split, air-cooled chillers (located on the C-wing roof) are being replaced this summer with Carrier Model 30HXA076N high-efficiency indoor screw chillers rated at 74-Ton capacity with an efficiency of 0.53 kw/ton. The remote air-cooled condensing units are also located on the C-wing roof and are Carrier Model 09DK-094 rated at Tons with 2 refrigerant circuits and four (4) 1 HP condensing fans. The chilled water is pumped to various chilled water coils in the C-wing by four (4) Taco Model FI2009E2E base-mounted end suction pumps with 5 HP motors and each rated for 155 GPM at 60 feet of head. The D-wing is cooled by an Aaon Model RK-40-3-F0 packaged cooling unit with four (4) stage cooling (4 compressors), a 7.5 HP supply fan with a variable speed drive, 5 HP power exhaust, two (2) 2 HP condenser fans, a rating of 40-Tons and an efficiency of 9.5 EER. The B6 wing classrooms are cooled by an ICP Model CAE150LA outdoor, air-cooled, two-stage, condensing unit located outdoors on a pad and an indoor unit Model BAC150. This unit is rated at Tons with an efficiency of 10.5 EER. The building is primarily conditioned by the following air handling units (AHU) made by Trane: Model No. Cooling Heating Supply Fan (HP) Capacity (CFM) L-6 Chilled Water Hot Water 2 3,000 September 29, 2014 FINAL Page 10 of 63

12 L-8 Chilled Water Hot Water 3 4,000 L-12 Chilled Water Hot Water 3 6,000 L-25 Chilled Water Hot Water 10 12,500 M-3 Chilled Water Hot Water 1.5 1,500 L-10 Chilled Water Hot Water 3 5,000 L-12 Chilled Water Hot Water 3 6,000 L-8 Chilled Water Hot Water 3 4,000 Perimeter heating of the building is achieved via fin-tube perimeter baseboard heaters. The classrooms are heated/cooled by unit ventilators with a dual temperature coil, and pneumatic 2- way valves. Entrance doorways are heated via cabinet style hot water unit ventilators. Storage areas, mechanical rooms, and the penthouse mechanical room are heated via hot water unit heaters. Exhaust System Air is exhausted from the toilet rooms, corridors, gyms, kitchen, mechanical spaces, electrical rooms, etc. through the roof exhaust fans. The exhaust fans are operated on time-clocks based on the facility occupancy schedule. The various rooftop units provide fresh air intake and exhaust capabilities. HVAC System Controls The older HVAC systems (1973) within the building are controlled through ATC with pneumatics while the boilers are controlled by a T.A.C. DDC controller located in the boiler room. The new chillers, pumps, etc. will be controlled by a T.A.C. controller. The hot water boilers, hot water pumps, and 3-way valves are controlled by outside air temperature reset. The older rooftop units have a thermostat in the rooms while the newer rooftop units have unitary controllers with Honeywell Chronotherm IV Plus 7-day programmable thermostats in the spaces. The unit ventilators have thermostats in each classroom that allows the local user limited temperature control. The local hot water terminal units are controlled by internal thermostats or wall-mounted space temperature sensors. Domestic Hot Water Domestic hot water for the entire facility is provided by an A. O. Smith Model HW domestic water boiler that feeds four (4) Stonesteel Model V200EHB storage tanks each with a capacity of 200 gallons. The water heater has an input rating of 300 MBH with an output rating of 246 MBH output for a thermal efficiency of 82%. September 29, 2014 FINAL Page 11 of 63

13 Kitchen Equipment The full-cooking kitchen consists of an upright refrigerator, two (2) Vulcan double stack electric convection ovens, Vulcan 4kW electric range, Blodgett Model BX-14 combination oven steamer, Jamison walk-in refrigerator, Jamison walk-in freezer, two (2) Scotsman CM 3 ice makers, Insinger Admiral dishwasher, Hobart 54kW electric booster water heater, etc. The two (2) walk-in refrigerator/freezers are Bally Model TLP62A The condenser for the walkin refrigerator/freezers is located on the roof and is a Trenton Refrigeration Model TEZA060 aircooled condensing unit with a nominal 6 HP compressor. The unit coolers are Bohn Model ADT520A with a single fan and a Trenton Refrigeration Model TPLP419L with four (4) 490 watt fans. The kitchen also includes a Kenmore Model washing machine and an Estate Model TEDS840JQ2 dryer. The large kitchen hood is exhausted by a Greenheck exhaust fan located on the kitchen roof. Lighting Refer to the Investment Grade Lighting Audit Appendix for a detailed list of the lighting throughout the facility and estimated operating hours per space. September 29, 2014 FINAL Page 12 of 63

14 III. MAJOR EQUIPMENT LIST The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix. Refer to the Major Equipment List Appendix for this facility. September 29, 2014 FINAL Page 13 of 63

15 IV. ENERGY CONSERVATION MEASURES Conservation Measures are developed specifically for this facility. The energy savings and calculations are highly dependent on the information received from the site survey and interviews with operations personnel. The assumptions and calculations should be reviewed by the owner to ensure accurate representation of this facility. The following ECMs were analyzed: Table 1 ECM Financial Summary ENERGY CONSERVATION MEASURES (ECM's) ECM NO. DESCRIPTION NET INSTALLATION COST A ANNUAL SAVINGS B SIMPLE PAYBACK (Yrs) SIMPLE LIFETIME ROI ECM #1 Lighting Upgrade $336,481 $45, % ECM #2 Lighting Controls Upgrade $32,360 $2, % ECM #3 Exterior Lighting Upgrade $7,503 $1, % ECM #4 Boiler Upgrade $264,000 $13, % ECM #5 ECM #6 Domestic Hot Water Upgrade Star Refrigerator Replacement $169,200 $12, % $2,800 $ % ECM #7 Vending Miser Controls $500 $ % ECM #8 CRT Monitor Replacement $6,380 $ % ECM #9 Computer Power Management $13,500 $4, % ECM #10 CRT TV Replacement $14,500 $ % ECM #11 NEMA Premium Motor Replacement $8,408 $ % ECM #12 Water Conservation $2,230 $2, % ECM #13 Window Replacement $195,000 $2, % ECM #14 DDC Controls Upgrade $375,000 $8, % ECM #15 High Efficiency Transformer $46,000 $3, % ECM #16 Clothes Washer Replacement $850 $ % ECM #17 Cooling Tower VFD $18,720 $ % Notes: A. Cost takes into consideration applicable NJ Smart StartTM incentives. B. Savings takes into consideration applicable maintenance savings. September 29, 2014 FINAL Page 14 of 63

16 Table 2 ECM Summary ENERGY CONSERVATION MEASURES (ECM's) ECM NO. DESCRIPTION ELECTRIC DEMAND (KW) ANNUAL UTILITY REDUCTION ELECTRIC CONSUMPTION (KWH) NATURAL GAS (THERMS) WATER USAGE (kgal) ECM #1 Lighting Upgrade , ECM #2 Lighting Controls Upgrade , ECM #3 Exterior Lighting Upgrade , ECM #4 Boiler Upgrade ,853 0 ECM #5 ECM #6 Domestic Hot Water Upgrade Star Refrigerator Replacement ,921-3, , ECM #7 Vending Miser Controls 0.0 4, ECM #8 CRT Monitor Replacement 3.1 6, ECM #9 Computer Power Management , ECM #10 CRT TV Replacement 0.0 6, ECM #11 NEMA Premium Motor Replacement ECM #12 Water Conservation 0.0 6, ECM #13 Window Replacement ,785 0 ECM #14 DDC Controls Upgrade ,564 2,442 0 ECM #15 High Efficiency Transformer , ECM #16 Clothes Washer Replacement ECM #17 Cooling Tower VFD 0.0 8, September 29, 2014 FINAL Page 15 of 63

17 Table 3 ECM Emissions Summary ENERGY CONSERVATION MEASURES (ECM's) ECM NO. ECM #1 Lighting Upgrade 556,364 1,025 2,379 ECM #2 Lighting Controls Upgrade 29, ECM #3 Exterior Lighting Upgrade 16, ECM #4 Boiler Upgrade 126, ECM #5 ECM #6 Domestic Hot Water Upgrade Star Refrigerator Replacement 166, , ECM #7 Vending Miser Controls 6, ECM #8 CRT Monitor Replacement 9, ECM #9 Computer Power Management 50, ECM #10 CRT TV Replacement 10, ECM #11 DESCRIPTION NEMA Premium Motor Replacement GREENHOUSE GAS EMISSIONS REDUCTION CO 2 EMISSIONS (LBS) NO X EMISSIONS (LBS) SO 2 EMISSIONS (LBS) 1, ECM #12 Water Conservation 12, ECM #13 Window Replacement 20, ECM #14 DDC Controls Upgrade 100, ECM #15 High Efficiency Transformer 46, ECM #16 Clothes Washer Replacement ECM #17 Cooling Tower VFD 12, Notes: A. Emissions Reduction based on NJCEP published factors for electric & gas. September 29, 2014 FINAL Page 16 of 63

18 Table 4 Facility Project Summary FACILITY PROJECT SUMMARY TABLE ENERGY CONSERVATION MEASURES ANNUAL ENERGY SAVINGS ($) PROJECT COST ($) SMART START INCENTIVES CUSTOMER COST SIMPLE PAYBACK Lighting Upgrade $45,388 $355,269 $18,788 $336, Lighting Controls Upgrade $2,378 $33,950 $1,590 $32, Exterior Lighting Upgrade $1,382 $10,123 $2,620 $7, Boiler Upgrade $13,457 $270,000 $6,000 $264, Domestic Hot Water Upgrade Star Refrigerator Replacement $12,348 $170,000 $800 $169, $360 $2,800 $0 $2, Vending Miser Controls $565 $500 $0 $ CRT Monitor Replacement $795 $6,380 $0 $6, Computer Power Management $4,105 $13,500 $0 $13, CRT TV Replacement $842 $14,500 $0 $14, NEMA Premium Motor Replacement $107 $8,408 $0 $8, Water Conservation $2,019 $2,230 $0 $2, Window Replacement $2,249 $195,000 $0 $195, DDC Controls Upgrade $8,975 $375,000 $0 $375, High Efficiency Transformer $3,764 $46,000 $0 $46, Clothes Washer Replacement $33 $850 $0 $ Cooling Tower VFD $997 $18,720 $0 $18, Total Project $99,764 $1,523,230 $29,798 $1,493, Note the measure totals in this table do not take into account interactive effects of measures; see Method of Analysis Section III in Executive Report for further explanation. The facility peak electrical demand and total project savings meet the qualifications for the Pay for Performance Program. If the owner were to pursue this program option they would receive an estimated $ in incentive dollars, see the Installation Funding Options Section for more detail. September 29, 2014 FINAL Page 17 of 63

19 ECM #1: Lighting Upgrade General Description: The majority of the interior lighting throughout the Intermediate North School is provided with fluorescent fixtures with older generation, 32W T8 lamps with electronic ballasts or 34W T12 lamps with magnetic ballasts. Additionally, there are several areas that still contain compact fluorescents and incandescent lamps. These fixtures can be replaced and retrofit with new LED type fixtures and lamps. This ECM includes replacing and retrofitting the interior lighting with new LED type lamps and fixtures. It is recommended the School District consult with a professional engineer prior to retrofitting or replacing fixtures to ensure code required minimum light levels will be met. Savings Calculations: The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building. LIGHTING UPGRADE SAVINGS SUMMARY DESCRIPTION SAVINGS Electric Demand Savings (kw) Electric Usage Savings (kwh) 366,029 Electric Cost Savings ($) $45,388 No maintenance cost savings were estimated for this measure. September 29, 2014 FINAL Page 18 of 63

20 Savings Summary: ECM #1 - ENERGY SAVINGS SUMMARY Installation Cost ($): $355,269 NJ Smart Start Equipment Incentive ($): $18,788 Net Installation Cost ($): $336,481 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $45,388 Total Yearly Savings ($/Yr): $45,388 Estimated ECM Lifetime (Yr): 15 Simple Payback 7.4 Simple Lifetime ROI 102.3% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $680,814 Internal Rate of Return (IRR) 10% Net Present Value (NPV) $205, September 29, 2014 FINAL Page 19 of 63

21 ECM #2: Lighting Controls Upgrade Occupancy Sensors Description: Some of the lights in the Intermediate North School are left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off. Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. The U.S. Department of sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways, document posted for public use April The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report: Occupancy Sensors for Lighting Control 20% - 28% energy savings. Savings resulting from the implementation of this ECM for energy management controls are estimated to be 20% of the total light energy controlled by occupancy sensors. This ECM includes installation of ceiling or switch mount sensors for mostly classrooms and offices. Sensors shall be manufactured by Sensorswitch, Watt Stopper or equivalent. The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls. Savings Calculations: Savings = Savings. = Savings (% Savings Controlled Light ( kwh/yr) ) $ kwh ( kwh) Ave ElecCost September 29, 2014 FINAL Page 20 of 63

22 Rebates and Incentives: From the NJ Smart Start Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: Smart Start Incentive = (# Wall mount sensors $20 per sensor) + (# Ceiling mount sensors $35 per sensor) Savings Summary: LIGHTING CONTROLS SAVINGS SUMMARY DESCRIPTION SAVINGS Electric Usage Savings (kwh) 19,178 Electric Cost Savings ($) $2,378 ECM #2 - ENERGY SAVINGS SUMMARY Installation Cost ($): $33,950 NJ Smart Start Equipment Incentive ($): $1,590 Net Installation Cost ($): $32,360 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $2,378 Total Yearly Savings ($/Yr): $2,378 Estimated ECM Lifetime (Yr): 15 Simple Payback 13.6 Simple Lifetime ROI 10.2% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $35,671 Internal Rate of Return (IRR) 1% Net Present Value (NPV) ($3,971.06) September 29, 2014 FINAL Page 21 of 63

23 ECM #3: Lighting Upgrade Exterior Lighting Description: The exterior lighting at the Intermediate North School is currently lit by compact fluorescents, incandescent, medium base and metal halide fixtures. The exterior would be better served with more efficient LED lighting system. Concord Engineering recommends upgrading the lighting to an energy-efficient LED lighting system that includes LED lamps and fixtures for the existing exterior lighting. This ECM would replace the existing exterior lamps and fixtures with equivalent LED lamps and fixtures. Savings Calculations: A detailed Investment Grade Lighting Audit can be found in Investment Grade Lighting Audit Appendix that outlines the proposed retrofits, costs, savings, and payback periods. LIGHTING UPGRADE SAVINGS SUMMARY DESCRIPTION SAVINGS Electric Demand Savings (kw) 2.8 Electric Usage Savings (kwh) 11,148 Electric Cost Savings ($) $1,382 No maintenance cost savings were estimated for this measure. September 29, 2014 FINAL Page 22 of 63

24 Savings Summary: ECM #3 - ENERGY SAVINGS SUMMARY Installation Cost ($): $10,123 NJ Smart Start Equipment Incentive ($): $2,620 Net Installation Cost ($): $7,503 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $1,382 Total Yearly Savings ($/Yr): $1,382 Estimated ECM Lifetime (Yr): 15 Simple Payback 5.4 Simple Lifetime ROI 176.4% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $20,735 Internal Rate of Return (IRR) 17% Net Present Value (NPV) $8, September 29, 2014 FINAL Page 23 of 63

25 ECM #4: Fire-Tube Boiler Replacement Description: The Intermediate North School has two (2) Superior bent-tube, gas-fired, hot water boilers that are 26 years old, and have not yet surpassed their ASHRAE useful life expectancy. While these units are still in operating condition, their overall efficiency has greatly diminished. The two boilers have a rated input capacity of approximately 4,000 MBH each with an estimated thermal efficiency of 70% due to their age and condition. This ECM would replace the two existing boilers with two (2) modular, condensing style boilers rated at 3,000 MBH each with an average thermal efficiency of 90%. The new boilers would come with hot water reset and outdoor air reset controls to reduce heating water temperature during low load periods. Savings Calculations: Savings were calculated utilizing the New Jersey Board of Public Utilities Protocols to Measure Resource Savings dated March, In order to evaluate the gas usage associated with the heating boilers only calculations were performed to estimate the usage of other heating equipment and domestic hot water. Based on the analysis the resultant breakdown of natural gas usage was determined for the facility. Bldg Heat Re quired = Existing Pr oposed Heating Gas Usage = Cost = Heating Gas Usage NATURAL GAS USAGE BREAKDOWN Description therm Utility Bill Usage 54,578.3 Domestic Hot Water 5,741.6 Heating Boilers 48,836.7 Nat Gas Heating Eff. BTU Therm ( Therms) Heating Eff.(%) Fuel HeatValue Bldg Heat Re quired ( BTU ) BTU (%) Fuel Heat Value Therm $ Therm ( Therms) Ave Fuel Cost September 29, 2014 FINAL Page 24 of 63

26 CONDENSING BOILER CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS ECM INPUTS Fire-Tube Boilers New Condensing Boilers Existing Nat Gas (Therms) 48,837 Boiler Efficiency (%) 70.0% 90.0% 20% Nat Gas Heat Value (BTU/Therm) Equivalent Building Heat Usage (MMBTUs) 100, ,000 3,419 3,419 Gas Cost ($/Therm) $1.24 $1.24 ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Natural Gas Usage (Therms) 48,837 37,984 10,853 Cost ($) $60,558 $47,100 $13,457 COMMENTS: Boiler Efficiency Based on age of boiler and IBR Rating September 29, 2014 FINAL Page 25 of 63

27 Savings Summary: ECM #4 - ENERGY SAVINGS SUMMARY Installation Cost ($): $270,000 NJ Smart Start Equipment Incentive ($): $6,000 Net Installation Cost ($): $264,000 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $13,457 Total Yearly Savings ($/Yr): $13,457 Estimated ECM Lifetime (Yr): 25 Simple Payback 19.6 Simple Lifetime ROI 27.4% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $336,431 Internal Rate of Return (IRR) 2% Net Present Value (NPV) ($29,667.25) September 29, 2014 FINAL Page 26 of 63

28 ECM #5: High Efficiency Gas Hot Water Heater Description: The Intermediate North School has five areas which are served by separate hot water heaters. The main hot water heater, located in the main boiler room, is an A.O. Smith gas-fired heater, which serves everything except for the C-wing. In the C-wing penthouses, there are four Stonesteel electric hot water heaters which serve the respective area. The existing units have surpassed their ASHRAE service life, and upgrading to gas-fired high efficiency units may incur significant cost savings. This ECM will replace the A.O Smith and Stonesteel domestic water heaters with a Natural Gas fired Bradford White EF Series high efficiency water heaters or equal. (Before proceeding with installation of aforementioned system, Concord Engineering suggests consulting a plumber to evaluate the system fully.) Savings Calculations: Density for Education type building = 5.2 kbtu / SF / year kbtu yr DHW Heat Usage = Density Building Square Footage (SF) SF Dom HW DHW Total Usage = Heating Eff. Cost = Heating Fuel Usage Heat Cons. ( Btu) (%) Fuel Heat Value FuelUnit BTU ( FuelUnits) Ave Fuel Cost FuelUnit $ September 29, 2014 FINAL Page 27 of 63

29 Main Building Domestic Hot Water Calculation: DOM. HOT WATER HEATER CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS Existing Electric High Efficiency ECM INPUTS Water Heater Heater Building Type Education Building Square-foot 88,332 88,332 Domestic Water Usage, kbtu 459, , DHW Heating Fuel Type Gas Gas Heating Efficiency 80% 96% 16% Total Usage (kbtu) 574, ,465 95,693 Nat Gas Cost ($/Therm) $ $ ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Natural Gas Usage (Therms) 5,742 4, Cost ($) $7,234 $6,029 $1,206 COMMENTS: Savings are based on Information Administration Commercial Building Consumption Survey 2003 Information September 29, 2014 FINAL Page 28 of 63

30 C-Wing Domestic Hot Water Calculation: DOM. HOT WATER HEATER CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS Existing Electric Hot High Efficiency ECM INPUTS Water Heaters Heaters Building Type Education Building Square-foot 90,000 90,000 Domestic Water Usage, kbtu 468, , DHW Heating Fuel Type Electric Gas Heating Efficiency 98% 95% -3% Total Usage (kbtu) 477, ,632-15,081 Electric Cost ($/kwh) $ $ - Nat Gas Cost ($/Therm) $ ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Electric Usage (kwh) 139, ,921 Natural Gas Usage (Therms) 0 4,926-4,926 Cost ($) $17,350 $6,207 $11,143 COMMENTS: Savings are based on Information Administration Commercial Building Consumption Survey 2003 Information September 29, 2014 FINAL Page 29 of 63

31 Savings Summary: ECM #5 - ENERGY SAVINGS SUMMARY Installation Cost ($): $170,000 NJ Smart Start Equipment Incentive ($): $800 Net Installation Cost ($): $169,200 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $12,348 Total Yearly Savings ($/Yr): $12,348 Estimated ECM Lifetime (Yr): 15 Simple Payback 13.7 Simple Lifetime ROI 9.5% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $185,220 Internal Rate of Return (IRR) 1% Net Present Value (NPV) ($21,790.38) September 29, 2014 FINAL Page 30 of 63

32 ECM #6: Star Refrigerator Description: The Intermediate North School has several residential style refrigerators throughout the school that are 16 years or older. These units are older models that are not nearly as energy efficient as those manufactured today. The proposed replacements are one-for-one units of similar size and dimensions that has the most up-to-date Star Rating. The Frigidaire model FFHT2117LW or equivalent should be considered as the replacements for this measure. (Note: There are currently no NJ OCE incentives for residential refrigerator replacement.) Savings Calculations: ENERGY STAR REFRIGERATOR CALCULATION ECM INPUTS EXISTING EXISTING EXISTING PROPOSED SAVINGS Quantity Manufacturer RCA Frigidaire Type Top Freezer Top Freezer Top Freezer Top Freezer Model MTX21GAXBR Frigidaire Hotpoint FFHT2117LW Size (Cu-Ft) Per Unit Electric Usage (kwh) 908 1,738 1, Electric Rate ($/kwh) $0.124 ENERGY SAVINGS CALCULATIONS Electric Usage (kwh) 908 1,738 1,584 1,323 2,907 Cost ($) $113 $216 $196 $164 $360 COMMENTS: Calculations based Star Website September 29, 2014 FINAL Page 31 of 63

33 Savings Summary: ECM #6 - ENERGY SAVINGS SUMMARY Installation Cost ($): $2,800 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $2,800 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $360 Total Yearly Savings ($/Yr): $360 Estimated ECM Lifetime (Yr): 10 Simple Payback 7.8 Simple Lifetime ROI 28.6% Simple Lifetime Maintenance Savings 0 Simple Lifetime Savings $3,600 Internal Rate of Return (IRR) 5% Net Present Value (NPV) $ September 29, 2014 FINAL Page 32 of 63

34 ECM #7: Vending Miser Controls Description: The Intermediate North School currently utilizes vending machines in select areas within the building. Vending machines are located in the faculty lunch room which can be in use for a limited time during the day. The installation of the Vending Miser system will help reduce the operating hours of vending machines. Cold beverage machines regularly operate inefficiently trying to maintain a constant cool temperature within the machine and snack machines with no cooling usually have lights that operate 24/7. The VendingMiser system incorporates innovative energy-saving technology into a small plug-and-play device that in conjunction with a passive infrared sensor regulate the operation of the cold beverage and snack machines based on occupancy and room temperature. This ECM approximates the installation of two (2) for the cold beverage machines and one (1) for the snack machine. Savings Calculations: Cold Drink and Snack Vending Machine Conservation Project Input Variables Analysis Prepared For: Costs ($0.000 per kwh) $0.124 Facility Occupied Hours per Week 60 Intermediate North School Number of Cold Drink Vending Machines 2 Number of Uncooled Snack Machines 1 Power Requirements of Cold Drink Machine (avg watts) 427 Power Requirements of Snack Machine (avg watts) 100 VendingMiser Sale Price (for cold drink machines) $ OfficeMiser Sale Price (for snack machines) $ Savings Analysis Before After Cold Drink Machines $ $ Cost of Operation 7,486 3,489 kwh 53% % Savings Snack Machines $ $38.69 Cost of Operation kwh 64% % Savings Project Summary Present kwh Projected kwh kwh Savings per Year 8,360 3,801 4,558 Present Cost Projected Costs Annual Savings Per Cent Savings Total Project Cost Break Even (Months) $1, $ $ % $ September 29, 2014 FINAL Page 33 of 63

35 Savings Summary: ECM #7 - ENERGY SAVINGS SUMMARY Installation Cost ($): $500 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $500 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $565 Total Yearly Savings ($/Yr): $565 Estimated ECM Lifetime (Yr): 10 Simple Payback 0.9 Simple Lifetime ROI % Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $5,652 Internal Rate of Return (IRR) 113% Net Present Value (NPV) $4, September 29, 2014 FINAL Page 34 of 63

36 ECM #8: CRT Monitor Replacement Description: The Intermediate North School still utilizes CRT Monitors for use by its students. Typical CRT monitors throughout the building consist of 15 inch displays. These computer monitors are outdated and have several disadvantages such as; significantly higher energy consumption in operating and idle mode, use a large amount of desk space, poor picture quality, distortions and flickering image, secular glare problems, and high weight, and electromagnetic emissions. Many of the drawbacks are difficult to quantify except for the energy use. CRT monitors use considerably more energy than an alternative flat panel LCD/LED monitor. Replacement of the existing CRT monitors with LCD/LED monitors saves considerable energy as well as provides other ergonomic benefits as well. This ECM will replace all 58 existing CRT monitors with new 17 Dell LCD/LED. It is expected District IT Staff will purchase and install new monitors, therefore no labor costs were taken into account for this measure. Savings Calculations: Savings calculations were based on operating occupied hours per week of operating staff and students, and estimated idle time of monitors per week outside occupied hours. Power consumption data is based on actual monitor characteristics for a Dell CRT, and Dell LCD/LED. Savings = Quantity Operating Hours P o +Quantity Idle Hours P I Qty = Quantity Op Hrs = Operating Hours per Year Idle Hrs = Idle Hours per Year P O = Operating Power Consumption Watts P I = Idle Power Consumption Watts September 29, 2014 FINAL Page 35 of 63

37 CRT MONITOR REPLACEMENT CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS ECM INPUTS 15" CRT 17" LCD # of Monitors Power Cons. (W) Idle Power Cons. (W) Operating Hrs per Week Operating Weeks per Yr Idle Hrs per Week Idle Weeks per Yr Elec Cost ($/kwh) ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Electric Demand (kw) Electric Usage (kwh) 8,275 1,864 6,411 Cost ($) $1,026 $231 $795 COMMENTS: Savings Based on Dell 15: CRT Monitor Compared with Dell 17" LCD/LED September 29, 2014 FINAL Page 36 of 63

38 Savings Summary: ECM #8 - ENERGY SAVINGS SUMMARY Installation Cost ($): $6,380 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $6,380 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $795 Total Yearly Savings ($/Yr): $795 Estimated ECM Lifetime (Yr): 10 Simple Payback 8.0 Simple Lifetime ROI 24.6% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $7,950 Internal Rate of Return (IRR) 4% Net Present Value (NPV) $ September 29, 2014 FINAL Page 37 of 63

39 ECM #9: Computer Power Management Description: The Intermediate North School currently has approximately 205 desktop computers throughout the classrooms, offices, and computer labs. Currently these computers are on all day during the week and shut down on weekends, during summer recess, and on long holidays. While the current operating procedure has its merits, by implementing a management program with power management and maintenance management while the buildings are unoccupied as well as designating on periods for software upgrades, and wake on LAN capability to boot computers up prior to student arrival significant energy savings could be achieved. This ECM recommends installing a computer maintenance management program with a power management option to turn computer on and off without the need for manual shutdowns by staff. The system being considered should be equivalent to a Dell KACE K1000. This will not only save the School on energy costs, but also benefit IT maintenance. Savings Calculations: Savings calculations were based on existing operating conditions observed in the field, in addition to the quantity, make, and model of desktop. Idle and off power information was obtained from Star s version 5.0 Program Requirements for Computers. Usage = Idle Power Watts On Hours + Off Power Watts Off Hours September 29, 2014 FINAL Page 38 of 63

40 COMPUTER POWER MANAGEMENT CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS Walnut Street Walnut Street ECM INPUTS School School Quantity of Desktops Idle Power Cons. (W) Off Power Cons. (W) 2 2 Normal Operating ON Hours 3,806 1,830 Holiday Operating ON Hours 94 0 Summer Operating ON Hours 0 0 Normal Operating OFF Hours 2,359 4,336 Holiday Operating OFF Hours Summer Operating OFF Hours 1,651 1,651 Elec Cost ($/kwh) ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Electric Usage (kwh) 65,960 32,853 33,107 Cost ($) $8,179 $4,074 $4,105 COMMENTS: Idle and Off Power Draws based on Star Rating for Desktop Computers September 29, 2014 FINAL Page 39 of 63

41 Savings Summary: ECM #9 - ENERGY SAVINGS SUMMARY Installation Cost ($): $13,500 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $13,500 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $4,105 Total Yearly Savings ($/Yr): $4,105 Estimated ECM Lifetime (Yr): 10 Simple Payback 3.3 Simple Lifetime ROI 204.1% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $41,050 Internal Rate of Return (IRR) 28% Net Present Value (NPV) $21, September 29, 2014 FINAL Page 40 of 63

42 ECM #10: CRT TV Replacement Description: The Intermediate North School currently has older Cathode Ray Tube Televisions in its classrooms. These TV s are older technology and use a substantial amount of electricity when in use and also while powered off in idle power draw mode. The TV s appeared to be 25 screen size units; in general these units draw 95 watts or more of power while in use and 5 watts or more while in idle mode. Newer televisions such as Liquid Crystal Displays (LCD) or LED television, use power much more efficiently than older CRT models and in many cases draw nearly zero power while in idle mode. This ECM recommends that the school replace these older televisions with new LG 32 LED type units model 32LN530B or equal. Savings Calculations: Estimated Cost per LED Television = $250 Electric Usage (kwh) = Qty TV s Oper. Power (W) Operating Hours + Qty TV s Idle Power(W) Idle Op. Hours 1 kw 1000 W Cost = Electric Usage (kwh) Electric Cost $ kwh September 29, 2014 FINAL Page 41 of 63

43 CRT TELEVISION REPLACEMENT CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS ECM INPUTS 25" CRT TV 32" LED TV # of Televisions TV Power Cons. (W) Idle TV Power Cons. (W) Run Time % 75% 75% Operating Hrs per Week Operating Weeks per Yr Idle Hrs per Week Idle Weeks per Yr Elec Cost ($/kwh) ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Electric Usage (kwh) 9,024 2,237 6,787 Cost ($) $1,119 $277 $842 COMMENTS: Operating Hours per week based on Run Time % times 40 hours per week. LED TV LG Model #32LN530B September 29, 2014 FINAL Page 42 of 63

44 Savings Summary: ECM #10 - ENERGY SAVINGS SUMMARY Installation Cost ($): $14,500 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $14,500 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $842 Total Yearly Savings ($/Yr): $842 Estimated ECM Lifetime (Yr): 10 Simple Payback 17.2 Simple Lifetime ROI -41.9% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $8,420 Internal Rate of Return (IRR) -9% Net Present Value (NPV) ($7,317.57) September 29, 2014 FINAL Page 43 of 63

45 ECM #11: Premium Efficiency Motors Description: The improved efficiency of the NEMA Premium efficient motors is primarily due to better designs with use of better materials to reduce losses. Surprisingly, the electricity used to power a motor represents 95 % of its total lifetime operating cost. Because many motors operate continuously 24 hours a day, even small increases in efficiency can yield substantial energy and dollar savings. The electric motors driving the pumps are candidates for replacing with premium efficiency motors. These standard efficiency motors run considerable amount of time over a year. This energy conservation measure replaces existing inefficient electric motors with NEMA Premium efficiency motors. IMPLEMENTATION SUMMARY EQMT ID FUNCTION MOTOR HP HOURS OF OPERATION EXISTING EFFICIENCY NEMA PREMIUM EFFICIENCY P-1 Hot Water 7.5 2, % 91.0% P-2 Hot Water 10 2, % 91.7% P-3 Condenser Water 10 2, % 91.7% Savings Calculations: Error! Bookmark not defined. HP LF Hours of Operation Electric Usage, kwh = Motor Efficiency where, HP = Motor Nameplate Horsepower Rating LF = Load Factor Motor Efficiency = Motor Nameplate Efficiency Electric Usage Savings kwh = Electric Usage Existing Electric Usage Proposed Electric Usage Savings, kwh = Electric Usage Existing Electric Usage Proposed Electric cost savings = Electric Usage Savings Electric Rate $ kwh September 29, 2014 FINAL Page 44 of 63

46 The calculations were carried out and the results are tabulated in the table below: PREMIUM EFFICIENCY MOTOR CALCULATIONS EQMT ID QTY MOTOR HP There are no longer incentives available through NJ Smart Start for premium efficiency motors. Savings Summary: LOAD FACTOR EXISTING EFFICIENCY PROPOSED EFFICIENCY POWER SAVINGS kw ENERGY SAVINGS kwh COST SAVINGS P % 88.5% 91.0% $32 P % 89.5% 91.7% $37 P % 89.5% 91.7% $37 TOTAL $107 ECM #11 - ENERGY SAVINGS SUMMARY Installation Cost ($): $8,408 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $8,408 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $107 Total Yearly Savings ($/Yr): $107 Estimated ECM Lifetime (Yr): 18 Simple Payback 78.6 Simple Lifetime ROI -77.1% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $1,926 Internal Rate of Return (IRR) -12% Net Present Value (NPV) ($6,936.37) September 29, 2014 FINAL Page 45 of 63

47 ECM #12: Water Conservation Description: The Intermediate North School utilizes standard plumbing fixtures. The typical water faucet consumption only meets the minimum federal required standard for water efficiency. New fixtures are available that use less water than today s requirements and can add up to significant water reduction over a long period. This ECM includes the retrofitting of the existing faucets within the facility with new low flow aerators. The estimated usage of the plumbing fixtures is based on the total population of the facility. The number of plumbing fixtures to be replaced is based on observations of the facility. (Please note that the estimate of occupants for the library is an estimate based on daily employees at the facility) The proposed retrofit includes installation of low flow aerators. For the basis of this calculation the LEED rating system was used to estimate the occupancy usage for students within the school. When water consumption information was not available, the GPF values were estimated for the existing fixtures. Savings Calculations: Faucets: Water Usage = Occupancy Days Uses yr Day Gal Duration min Use Min Electric Usage (kwh) = Faucet Water Usage (Gal) 8.33 lbs Specific Heat (1) T(70 ) Gal kwh 3,413 Btu 1 HWH Efficiency Natural Gas Usage (Therms) = Faucet Water Usage (Gal) 8.33 lbs Specific Heat (1) T(70 ) Gal Therms 100,000 Btu 1 HWH Efficiency September 29, 2014 FINAL Page 46 of 63

48 LOW FLOW WATER SAVING DEVICES ECM INPUTS EXISTING PROPOSED SAVINGS Quantity of Sinks Flow Rate (GPM) Device Usage (min per day) Facility Operation (days / year) Heat Content of Water (Btu/gal/ F) Temperature Rise ( F) Efficiency of Heating System 1 (%) 80% 80% Efficiency of Heating System 2 (%) 98% 98% Conversion Factor for Electric Conversion Factor for Gas Electric Rate ($/kwh) $0.124 $0.124 Natural Gas Rate ($/therm) $1.230 $1.230 Water Rate ($/1000gal) $6.740 $6.740 ENERGY SAVINGS CALCULATIONS Electric Usage (kwh) 7,910 1,798 6,113 Natural Gas Usage (Therm) Water Usage (gallons) 181,500 41, ,250 Cost ($) $2,613 $594 $2,019 COMMENTS: Heating Savings based on 50% Hot Cold Mix. Savings for both natural gas and electric are shown due to the facility using both electric and natural gas water heaters. The cost for installation and materials is based on 75 faucet aerators. There are no Smart Start rebates for installation of low flow plumbing fixtures. September 29, 2014 FINAL Page 47 of 63

49 Savings Summary: ECM #12 - ENERGY SAVINGS SUMMARY Installation Cost ($): $2,230 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $2,230 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $2,019 Total Yearly Savings ($/Yr): $2,019 Estimated ECM Lifetime (Yr): 10 Simple Payback 1.1 Simple Lifetime ROI 805.4% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $20,190 Internal Rate of Return (IRR) 90% Net Present Value (NPV) $14, September 29, 2014 FINAL Page 48 of 63

50 ECM #13: Window Replacement Description: Several areas of the building envelope consist of single pane windows with aluminum frames. The total area of single pane windows for the main office area, B-wing and C-wing is estimated at 2,500 SF. This area was used as the basis for calculating energy savings and formulating a cost estimate. Older inefficient windows can account for significant energy use through leakage heat loss and conductive heat loss. The age and condition of the windows contribute to the leakage rate of the building. The single pane construction allows higher thermal (conductive) energy loss. These factors lead to increased energy use in the heating season. The heating loss due to single pane glass is combined with heat loss due to poor seals at each operable window. New double pane windows with low E glazing offer a substantial improvement in thermal performance throughout the year. This ECM includes the replacement of all single pane glass in the main office area, B-wing and C-wing with double pane windows with low emissivity glass. The proposed windows include reduced outside air leakage. In addition the double pane structure will significantly increase the insulation value compared to the existing single pane window structure. The basis for this ECM is an ASHRAE equivalent window. The windows will be replaced throughout the classroom wings. Savings Calculations: Thermal Loss values were calculated for each month based on the average monthly temperature obtained for 2013/2014. The heating period used was October to April. Thermal Loss Savings (kbtu) = (U E U P ) Window Area T Indoor T Avg Outdoor Hours Month 1 kbtu 1,000 Btu Heating Savings (Therm) = Thermal Loss Savings (Heating) 1 Efficiency 1 Therm 100 kbtu September 29, 2014 FINAL Page 49 of 63

51 WINDOW REPLACEMENT CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS Existing Single Pane Double Pane Low-E Description: Windows Windows Window (SF) 2,500 2,500 U-Value (BTU/HR/SF* F) Infiltration Rate (CFM/SF) Indoor Temperature Heating ( o F) Average Thermal Loss Rate Heating (BTU/HR) 62,500 28,125 34,375 Heating Degree Days (65 o F) Thermal Losses Heating (kbtu) 227, , ,963 Heating System Efficiency (%) 70.0% 70.0% Natural Gas Cost ($/Therm) $1.26 $ ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Natural Gas Usage (Therm) 3,246 1,461 1,785 Cost Savings ($) $4,090 $1,840 $2,249 Comments: 1. Proposed window U-value Based on ASHRAE Savings Based on Avg. Monthly Temperature for 2012/2013 September 29, 2014 FINAL Page 50 of 63

52 Savings Summary: ECM #13 - ENERGY SAVINGS SUMMARY Installation Cost ($): $195,000 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $195,000 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $2,249 Total Yearly Savings ($/Yr): $2,249 Estimated ECM Lifetime (Yr): 15 Simple Payback 86.7 Simple Lifetime ROI -82.7% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $33,735 Internal Rate of Return (IRR) -17% Net Present Value (NPV) ($168,151.58) September 29, 2014 FINAL Page 51 of 63

53 ECM #14: Digital Management System (DDC EMS) Description: The Intermediate North School currently has pneumatic and electronic controls systems with no front end computer to operate the HVAC systems on in the building. The installation of a Central Management System to control the unit ventilators, exhaust fans, boilers and pumps could yield significant savings through setback and scheduling capability, and improved maintenance response time to outages and breakdowns. This ECM includes installation of a Building Automation system to include control of the HVAC equipment in the facility. The system will include new thermostats, new unit ventilator/baseboard control valves, exhaust fan on/off controllers, a front end computer and main controller. With the communication between the control devices and the front end computer interface, the facility manager will be able to take advantage of scheduling for occupied and unoccupied periods based on the actual occupancy of each space in the facility. The DDC system will also aid in the response time to service / maintenance issues when the facility is not under normal maintenance supervision, i.e. after-hours. The Central DDC system installation has the potential to provide significant savings by controlling the HVAC systems as a whole and provide operating schedules and features such as space averaging, night set-back, temperature override control, etc. The U.S. Department of sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways, document posted for public use April The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the referenced report: Management and Control System Savings: 5%-15%. Savings resulting from the implementation of this ECM for energy management controls are estimated to be 5% of the electricity and 5% for the gas utility in this building. The basis for the DDC system expansion is the Andover Management System or similar. Savings Calculations: savings for each utility is calculated with the equation below. Savings (Utility) = Current Consumption Estimated Savings, % Following table summarizes energy savings for this facility via implementation of an Management System. September 29, 2014 FINAL Page 52 of 63

54 DDC ENERGY MANAGEMENT SYSYEM CALCULATIONS ECM INPUTS EXISTING PROPOSED SAVINGS ECM INPUTS Existing Controls w/ Local Thermostats DDC Controls Existing Nat Gas Usage (Therms) 48,836 - Existing Electricity Usage for HVAC (kwh) 951,287 - Savings, Nat. Gas - 5% Savings, Electricity - 5% Gas Cost ($/Therm) $1.26 $1.26 Electricity Cost ($/kwh) $0.124 $0.124 ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Natural Gas Usage (Therms) 48,836 46,394 2,442 Electricity Usage (kwh) 951, ,723 47,564 Cost ($) $179,493 $170,518 $8,975 COMMENTS: September 29, 2014 FINAL Page 53 of 63

55 Savings Summary: ECM #14 - ENERGY SAVINGS SUMMARY Installation Cost ($): $375,000 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $375,000 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $8,975 Total Yearly Savings ($/Yr): $8,975 Estimated ECM Lifetime (Yr): 15 Simple Payback 41.8 Simple Lifetime ROI -64.1% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $134,625 Internal Rate of Return (IRR) -11% Net Present Value (NPV) ($267,857.03) September 29, 2014 FINAL Page 54 of 63

56 ECM #15: High Efficiency Transformers Description: Electrical distribution transformers play a key role in delivering electrical power to buildings as all the electrical power supplied to the building flows through them. Whether equipment is plugged in and turned on or not transformers continue to operate. Consider their impact on electricity consumption. Some transformers waste as much as 20% of billed electricity. Older transformers in existing buildings may not have been built to meet the load requirements of today. Over the years electrical distribution has changed very little, however the connected equipment has changed dramatically. This dramatic change is derived from both the type of equipment (mostly electronic in nature) and the density of installed equipment. The impact of this change has had a direct impact on power quality and transformer efficiency. When newer electronic equipment is introduced into buildings with older electrical systems power quality and transformer efficiency can suffer. According to a Department of study performed in 1996 electronic equipment can increase losses by as much as 2.7 times. In real terms this would mean that a transformer that has a name- plate efficiency of 97% in reality is operating closer to 90% or lower. The difference represents additional costs to operate the transformer. Replacing your older transformers with Power smiths energy efficient E-Saver-C3 or T1000-C3 transformers can improve the reliability of your electronic equipment and significantly reduce electricity waste. Power smith s energy efficient transformers have substantially lower losses (higher efficiency) than other transformers. These energy savings mean less kilowatt-hours (kwh) consumed and lower energy bills. Electricity demand charges also decline, thanks to reduced energy losses. These savings pay for the transformer many times over its installed life. The Intermediate North School has two GE 45 kva, one GE 50 KVA, one GE 75 KVA and one GE 75 kva rated dry type transformers located in electrical rooms. The GE transformers are nearly 10 years old. This ECM would replace four transformers with new Power Smith energy efficient units. Savings Calculations: See Appendix for Manufacturers Transformer Calculation Spreadsheet. TRANSFORMER SAVINGS SUMMARY DESCRIPTION SAVINGS Electric Demand Savings (kw) 6.2 Electric Usage Savings (kwh) 30,355 Electric Cost Savings ($) $3,764 September 29, 2014 FINAL Page 55 of 63

57 Savings Summary: ECM #15 - ENERGY SAVINGS SUMMARY Installation Cost ($): $46,000 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $46,000 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $3,764 Total Yearly Savings ($/Yr): $3,764 Estimated ECM Lifetime (Yr): 15 Simple Payback 12.2 Simple Lifetime ROI 22.7% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $56,460 Internal Rate of Return (IRR) 3% Net Present Value (NPV) ($1,065.61) September 29, 2014 FINAL Page 56 of 63

58 ECM #16: Star Clothes Washer Replacement Description: The Intermediate North School has one standard top load clothes washer in the Home Economics Classroom. The installation of a newer Star Rated high efficiency front load washer will not only reduce water and energy consumption due to washing and drying of clothes it will also reduce water heating costs. The proposed replacement is a replacement with a similar sized front load machine that is Star rated. The unit specified in this case is manufactured be GE model GFWN1100L or equal. Savings Calculations: Savings calculations are based on water consumption per load and electric consumption per load of the washer. Water Usage (gal) = Gallons Load Loads year Water Heat (Btu) = Water Usage 8.33 lbs gal Water Heat (Fuel Units) = c (110 50) T Hot/Cold Mix (50%) Water Heat (Btu) Heater Efficiency 1 Fuel Conversion Washer Electric kwh = Volts Amps Run Factor (50%) kw 1 hr Load 1000 W load September 29, 2014 FINAL Page 57 of 63

59 ENERGY STAR CLOTHES WASHER CALCULATION ECM INPUTS EXISTING PROPOSED SAVINGS Quantity of Units 1 1 Manufacturer Kenmoore GE Type Top Load Front Load Model ' GFWN1100L Loads per Day 2 2 Days Per Week 5 5 Weeks Per Year Washer Usage kwh per Load Washer Usage Gallons per Load Percent Hot / Cold Water Mix Water Heater Type Natural Gas Natural Gas Water Heater Efficiency 80% 80% Electric Rate ($/kwh) $0.124 $0.124 Natural Gas Rate ($/therm) $1.260 $1.260 Water Rate ($/1,000 Gal) $6.740 $6.740 ENERGY SAVINGS CALCULATIONS Electric Usage (kwh) Natural Gas Usage (therm) Water Usage (Gallons) 14,444 6,440 8,004 Cost ($) $632 $599 $33 COMMENTS: Home Economics Classroom September 29, 2014 FINAL Page 58 of 63

60 Savings Summary: ECM #16 - ENERGY SAVINGS SUMMARY Installation Cost ($): $850 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $850 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $33 Total Yearly Savings ($/Yr): $33 Estimated ECM Lifetime (Yr): 10 Simple Payback 25.8 Simple Lifetime ROI -61.2% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $330 Internal Rate of Return (IRR) -14% Net Present Value (NPV) ($568.50) September 29, 2014 FINAL Page 59 of 63

61 ECM #17: Install VFD on Cooling Tower Fan Description: The EVAPCO cooling tower on the Intermediate North School roof currently has a 7.5 horsepower constant speed fan. The installation of a VFD will allow the tower fan to modulate based on the required amount airflow needed to maintain the necessary condenser water temperature for the chiller. This ECM includes the installation of a variable frequency drive and inverter duty premium efficiency motor on the tower fan along with the required tower controls to modulate the fan speed. Savings Calculations: Load Factor = 75% (without VFD) Consumption (kwh) = Motor HP kw 1 Hours of operation (Hr) HP η motor Total Consumption (kwh) = Consumption of Each Motor Cost ($) = Total Comsumption(kWh) Average Cost of Electric $ kwh Affinity Laws are used in order to calculate energy savings by calculating the reduced power consumption requirement based a reduction in flow. Affinity laws, are as following: Q = Flow, n = RPM, p = total pressure Q 2 = n 2 p 2 = n 2 2 HP 2 = n 3 2 Q 1 n 1 p 1 n 1 HP 1 n 1 September 29, 2014 FINAL Page 60 of 63

62 COOLING TOWER FAN VFD CALULATION ECM INPUTS EXISTING PROPOSED SAVINGS ECM INPUTS Constant Fan VFD Fan Control On/Off VFD - Quantiy of Fans 1 1 Motor Nameplate HP Motor Efficiency (%) 91.0% 93.0% 2.0% Operating Hrs Load Factor 75.0% 75.0% Elec Cost ($/kwh) $0.124 $ ENERGY SAVINGS CALCULATIONS ECM RESULTS EXISTING PROPOSED SAVINGS Electric (kwh) 15,371 7,329 8,042 Electric Cost ($) $1,906 $909 $997 COMMENTS: Estimated Operating Profile with VFD September 29, 2014 FINAL Page 61 of 63

63 Savings Summary: ECM #17 - ENERGY SAVINGS SUMMARY Installation Cost ($): $18,720 NJ Smart Start Equipment Incentive ($): $0 Net Installation Cost ($): $18,720 Maintenance Savings ($/Yr): $0 Savings ($/Yr): $997 Total Yearly Savings ($/Yr): $997 Estimated ECM Lifetime (Yr): 15 Simple Payback 18.8 Simple Lifetime ROI -20.1% Simple Lifetime Maintenance Savings $0 Simple Lifetime Savings $14,955 Internal Rate of Return (IRR) -3% Net Present Value (NPV) ($6,817.88) September 29, 2014 FINAL Page 62 of 63

64 V. ADDITIONAL RECOMMENDATIONS The following recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the office of Clean but save energy none the less. A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency. Poorly maintained heat transfer surfaces can reduce efficiency 5-10%. B. Maintain all weather stripping on windows and doors. C. Clean all light fixtures to maximize light output. D. Provide more frequent air filter changes to decrease overall system power usage and maintain better IAQ. E. Ensure outside air dampers are functioning properly and only open during occupied mode. September 29, 2014 FINAL Page 63 of 63

65 Appendix APPENDIX A

66 APPENDIX A 1 of 1 ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY ECM NO. DESCRIPTION MATERIAL INSTALLATION COST LABOR REBATES, INCENTIVES NET INSTALLATION COST YEARLY SAVINGS ECM COST & SAVINGS BREAKDOWN CONCORD ENGINEERING GROUP Toms River Regional Schools - Intermediate North LIFETIME ENERGY SAVINGS ENERGY MAINT. / SREC TOTAL (Yearly Saving * ECM Lifetime) LIFETIME MAINTENANCE SAVINGS (Yearly Maint Svaing * ECM Lifetime) LIFETIME ROI (Lifetime Savings - Net Cost) / (Net Cost) SIMPLE PAYBACK (Net cost / Yearly Savings) INTERNAL RATE OF RETURN (IRR) ($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($) ECM #1 Lighting Upgrade $252,219 $103,050 $18,788 $336,481 $45,388 $0 $45, $680,814 $ % % $205, ECM #2 Lighting Controls Upgrade $27,600 $6,350 $1,590 $32,360 $2,378 $0 $2, $35,671 $0 10.2% % ($3,971.06) ECM #3 Exterior Lighting Upgrade $7,503 $2,620 $2,620 $7,503 $1,382 $0 $1, $20,735 $ % % $8, NET PRESENT VALUE (NPV) ECM #4 Boiler Upgrade $145,000 $125,000 $6,000 $264,000 $13,457 $0 $13, $336,431 $0 27.4% % ($29,667.25) ECM #5 Domestic Hot Water Upgrade $80,000 $90,000 $800 $169,200 $12,348 $0 $12, $185,220 $0 9.5% % ($21,790.38) ECM #6 Star Refrigerator Replacement $2,500 $300 $0 $2,800 $360 $0 $ $3,600 $0 28.6% % $ ECM #7 Vending Miser Controls $500 $0 $0 $500 $565 $0 $ $5,652 $ % % $4, ECM #8 CRT Monitor Replacement $6,380 $0 $0 $6,380 $795 $0 $ $7,950 $0 24.6% % $ ECM #9 Computer Power Management $9,500 $4,000 $0 $13,500 $4,105 $0 $4, $41,050 $ % % $21, ECM #10 CRT TV Replacement $14,500 $0 $0 $14,500 $842 $0 $ $8,420 $0-41.9% % ($7,317.57) ECM #11 NEMA Premium Motor Replacement $5,273 $3,135 $0 $8,408 $107 $0 $ $1,926 $0-77.1% % ($6,936.37) ECM #12 Water Conservation $1,500 $730 $0 $2,230 $2,019 $0 $2, $20,190 $ % % $14, ECM #13 Window Replacement $150,000 $45,000 $0 $195,000 $2,249 $0 $2, $33,735 $0-82.7% % ($168,151.58) ECM #14 DDC Controls Upgrade $200,000 $175,000 $0 $375,000 $8,975 $0 $8, $134,625 $0-64.1% % ($267,857.03) ECM #15 High Efficiency Transformer $35,000 $11,000 $0 $46,000 $3,764 $0 $3, $56,460 $0 22.7% % ($1,065.61) ECM #16 Clothes Washer Replacement $750 $100 $0 $850 $33 $0 $33 10 $330 $0-61.2% % ($568.50) ECM #17 Cooling Tower VFD $8,600 $10,120 $0 $18,720 $997 $0 $ $14,955 $0-20.1% % ($6,817.88) ECM LIFETIME Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period. 2) The variable DR in the NPV equation stands for Discount Rate 3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period.

67 Appendix APPENDIX B

68 Appendix B Page 1 of BURNT MILL ROAD VOORHEES, NEW JERSEY PHONE: (856) FAX: (856) SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives from July 1, 2013 to June 30, 2014: Electric Chillers Water-Cooled Chillers $16 - $170 per ton Air-Cooled Chillers $8 - $52 per ton Efficiency must comply with ASHRAE Gas Absorption Chillers Gas Engine-Driven Chillers Gas Cooling Desiccant Systems $1.00 per cfm gas or electric Electric Unitary HVAC $185 - $450 per ton Calculated through custom measure path) Unitary AC and Split Systems $73 - $92 per ton Air-to-Air Heat Pumps $73 - $92 per ton Water-Source Heat Pumps $81 per ton Packaged Terminal AC & HP $65 per ton Central DX AC Systems $40- $72 per ton Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat (Hospitality & Institutional Facility) $75 per thermostat A/C Economizing Controls < 5 tons $85/unit; >5 tons $170/unit Efficiency must comply with ASHRAE Gas Fired Boilers < 300 MBH Gas Fired Boilers MBH Gas Fired Boilers MBH Gas Heating $2.00 per MBH, but not less than $300 per unit $1.75 per MBH $1.00 per MBH Gas Fired Boilers > 4000 MBH (Calculated through Custom Measure Path) Gas Furnaces $400 per unit, AFUE 95% Boiler Economizing Controls $1,200 - $2,700 Low Intensity Infrared Heating $300 - $500 per unit

69 Appendix B Page 2 of 4 Ground Source Heat Pumps $450 per ton, EER 16 Closed Loop $600 per ton, EER 18 $750 per ton, EER 20 Efficiency must comply with ASHRAE Variable Air Volume Chilled-Water Pumps 20 hp Rotary Screw Air Compressors 25 hp Cooling Towers 10 hp Boiler Fans > 5 HP Boiler Feed Water Pumps > 5 HP Commercial Kitchen Hood up to 50 HP Gas Water Heaters 50 gallons, 0.67 energy factor or better Gas-Fired Water Heaters > 50 gallons Gas-Fired Booster Water Heaters Gas Fired Tankless Water Heaters Variable Frequency Drives Natural Gas Water Heating $65 - $155 per hp $60 per VFD rated hp $5,250 to $12,500 per drive $60 per VFD rated hp $65 to $155 per hp $60 to $155 per hp Retrofit $55 $300 per hp New Hood $55 - $250 per hp $50 per unit $ $2.00 per MBH $17 - $35 per MBH $300 per unit T-8 reduced Wattage (28w/25w 4, 1-4 lamps) Lamp & ballast replacement For retrofit of T-8 fixtures by permanent de-lamping & new reflectors (Electronic ballast replacement required) Prescriptive Lighting $10 per fixture $15 per fixture T-5 and T-8 High Bay s $16 - $200 per fixture Metal Halide w/pulse Start Including Parking Lot (For fixtures 150w) HID 100w Replace with new induction fixture. (must be 30% less watts/fixture than HID system) $25 per fixture $70 per fixture HID 100w Retrofit with induction lamp, power coupler and generator (must be 30% less watts/fixture than HID system) $50 per fixture

70 Appendix B Page 3 of 4 Prescriptive Lighting - LED LED Display Case Lighting $30 per display case LED Shelf-Mtd. Display & Task Lights $15 per linear foot LED Portable Desk Lamp $20 per fixture LED Wall-wash Lights LED Recessed Down Lights LED Outdoor Pole/Arm-Mounted Area and Roadway Luminaries LED Outdoor Pole/Arm-Mounted Decorative Luminaries $30 per fixture $35 per fixture $175 per fixture $175 per fixture LED Outdoor Wall-Mounted Area Luminaries $100 per fixture LED Parking Garage Luminaries LED Track or Mono-Point Directional Lighting s LED High-Bay and Low-Bay s for Commercial & Industrial Bldgs. LED High-Bay-Aisle Lighting LED Stairwell and Passageway Luminaires LED Bollard s Luminaires for Ambient Lighting of Interior Commercial Spaces (1x4, 2x2, 2x4) LED Fuel Pump Canopy LED Screw-based & Pin-based (PAR, MR, BR, R) Standards (A-Style) and Decorative Lamps LED Refrigerator/Freezer case lighting replacement of fluorescent in medium and low temperature display case LED Retrofit Kits $100 per fixture $50 per fixture $150 per fixture $150 per fixture $40 per fixture $50 per fixture $50 per fixture $100 per fixture $10 per lamp for R/PAR20,MR/PAR16,Globe,Candelabra or Misc $20 per lamp for R/BR/PAR 30, R/BR/PAR 38-40, A-Lamp $30 per 4 foot $42 per 5 foot $65 per 6 foot To be evaluated through the customer measure path

71 Appendix B Page 4 of 4 Lighting Controls Occupancy Sensors Wall Mounted (Existing Facilities Only) Remote Mounted (Existing Facilities Only) Daylight Dimming Controls Occupancy Based hi-low Dimming Control $20 per control $35 per control $45 per fixture controlled $35 per fixture controlled Occupancy Sensor Remote Mounted $35 per control -Efficient Doors/Covers for Installation on Open Refrigerated Cases Refrigeration Doors/Covers $100 per door Aluminum Night Curtains for Installation on Open Refrigerated Cases $3.50 per linear foot Refrigeration Controls Door Heater Controls $50 per control Electric Defrost Controls $50 per control Evaporator Fan Controls $75 per control Novelty Cooler Shutoff $50 per control Performance Lighting Custom Electric and Gas Equipment Incentives Custom Measures Other Equipment Incentives $1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE for New Construction and Complete Renovation not prescriptive $0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year payback on estimated savings. Minimum required savings of 75,000 KWh or 1,500 Therms and an IRR of at least 10%.

72 Appendix APPENDIX C

73 ENERGY STAR Statement of Performance 50 ENERGY STAR Score 1 Intermediate North Primary Property Function: K-12 School Gross Floor Area (ft²): 178,332 Built: 1972 For Year Ending: June 30, 2014 Date Generated: September 04, The ENERGY STAR score is a assessment of a building s energy efficiency as compared with similar buildings nationwide, adjusting for climate and business activity. Property & Contact Information Property Address Intermediate North 150 Intermediate N Way Toms River, New Jersey Property ID: Property Owner Toms River Regional Schools Board of Education 331 Newman Springs Road Suite 203 Red Bank, NJ ( ) - Primary Contact Mark Wagner 125 Walnut St Toms River, NJ cbuttitta@chacompanies.com Consumption and Use Intensity (EUI) Site EUI 65.8 kbtu/ft² Source EUI 121 kbtu/ft² Annual by Fuel Electric - Grid (kbtu) 4,465,626 (38%) Natural Gas (kbtu) 5,438,742 (46%) Electric - Solar (kbtu) 1,837,885 (16%) National Median Comparison National Median Site EUI (kbtu/ft²) 66.4 National Median Source EUI (kbtu/ft²) % Diff from National Median Source EUI -1% Annual Emissions Greenhouse Gas Emissions (Metric Tons 1,133 CO2e/year) Signature & Stamp of Verifying Professional I (Name) verify that the above information is true and correct to the best of my knowledge. Signature: Date: Licensed Professional, ( ) - Professional Engineer Stamp (if applicable)

OCEAN COUNTY ADMINISTRATION BUILDING FACILITY ENERGY REPORT 101 HOOPER AVENUE TOMS RIVER, NJ 08753

OCEAN COUNTY ADMINISTRATION BUILDING FACILITY ENERGY REPORT 101 HOOPER AVENUE TOMS RIVER, NJ 08753 OCEAN COUNTY ADMINISTRATION BUILDING 101 HOOPER AVENUE TOMS RIVER, NJ 08753 FACILITY ENERGY REPORT TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY DESCRIPTION... 7 III. MAJOR EQUIPMENT

More information

CHERRY HILL TOWNSHIP SCHOOLS CHERRY HILL HIGH SCHOOL WEST 2101 CHAPEL AVENUE WEST CHERRY HILL, NJ FACILITY ENERGY REPORT

CHERRY HILL TOWNSHIP SCHOOLS CHERRY HILL HIGH SCHOOL WEST 2101 CHAPEL AVENUE WEST CHERRY HILL, NJ FACILITY ENERGY REPORT CHERRY HILL TOWNSHIP SCHOOLS CHERRY HILL HIGH SCHOOL WEST 2101 CHAPEL AVENUE WEST CHERRY HILL, NJ 08002 FACILITY ENERGY REPORT Cherry Hill Twp BOE Cherry Hill High School West Energy Audit TABLE OF CONTENTS

More information

LENAPE REGIONAL HIGH SCHOOL DISTRICT LENAPE HIGH SCHOOL FACILITY ENERGY REPORT 235 HARTFORD ROAD MEDFORD, NJ 08055

LENAPE REGIONAL HIGH SCHOOL DISTRICT LENAPE HIGH SCHOOL FACILITY ENERGY REPORT 235 HARTFORD ROAD MEDFORD, NJ 08055 LENAPE REGIONAL HIGH SCHOOL DISTRICT LENAPE HIGH SCHOOL 235 HARTFORD ROAD MEDFORD, NJ 08055 FACILITY ENERGY REPORT LRHSD Lenape High School Energy Audit TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST...

More information

BERGEN COUNTY JUSTICE CENTER 10 MAIN ST. HACKENSACK, NJ, FACILITY ENERGY REPORT

BERGEN COUNTY JUSTICE CENTER 10 MAIN ST. HACKENSACK, NJ, FACILITY ENERGY REPORT BERGEN COUNTY JUSTICE CENTER 10 MAIN ST. HACKENSACK, NJ, 07601 FACILITY ENERGY REPORT Bergen County - Justice Center Energy Audit TABLE OF CONTENTS I. HISTORIC ENERGY CONSUMPTION/COST... 2 II. FACILITY

More information

LENAPE REGIONAL HIGH SCHOOL DISTRICT CHEROKEE HIGH SCHOOL NORTH & SOUTH FACILITY ENERGY REPORT 120 & 130 TOMLINSON MILL ROAD MARLTON, NJ 08053

LENAPE REGIONAL HIGH SCHOOL DISTRICT CHEROKEE HIGH SCHOOL NORTH & SOUTH FACILITY ENERGY REPORT 120 & 130 TOMLINSON MILL ROAD MARLTON, NJ 08053 LENAPE REGIONAL HIGH SCHOOL DISTRICT CHEROKEE HIGH SCHOOL NORTH & SOUTH 120 & 130 TOMLINSON MILL ROAD MARLTON, NJ 08053 FACILITY ENERGY REPORT LRHSD Cherokee High School Energy Audit TABLE OF CONTENTS

More information

CLINTON TOWNSHIP BOARD OF EDUCATION PATRICK MCGAHERAN ELEMENTARY SCHOOL FACILITY ENERGY REPORT 63 ALLERTON ROAD LEBANON, NJ 08833

CLINTON TOWNSHIP BOARD OF EDUCATION PATRICK MCGAHERAN ELEMENTARY SCHOOL FACILITY ENERGY REPORT 63 ALLERTON ROAD LEBANON, NJ 08833 CLINTON TOWNSHIP BOARD OF EDUCATION PATRICK MCGAHERAN ELEMENTARY SCHOOL 63 ALLERTON ROAD LEBANON, NJ 08833 FACILITY ENERGY REPORT Clinton Township BOE Patrick McGaheran Elementary School TABLE OF CONTENTS

More information

CUSTOMER SUMMARY PAGE. 600 Stillwater Rd Service Address: 800 Stillwater Rd. Customer Name: City of Mahtomedi Account Number(s):

CUSTOMER SUMMARY PAGE. 600 Stillwater Rd Service Address: 800 Stillwater Rd. Customer Name: City of Mahtomedi Account Number(s): CUSTOMER SUMMARY PAGE Customer Name: City of Mahtomedi Account Number(s): 51-5660076-3 Service Address: Additional Service Address: 600 Stillwater Rd Service Address: 800 Stillwater Rd Mahtomedi, MN Mahtomedi,

More information

HILLSDALE SCHOOL DISTRICT GEORGE G. WHITE MIDDLE SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO OCTOBER 2012

HILLSDALE SCHOOL DISTRICT GEORGE G. WHITE MIDDLE SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO OCTOBER 2012 HILLSDALE SCHOOL DISTRICT GEORGE G. WHITE MIDDLE SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24535 OCTOBER 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973)

More information

HILLSBOROUGH TOWNSHIP SCHOOL DISTRICT AMSTERDAM ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO.

HILLSBOROUGH TOWNSHIP SCHOOL DISTRICT AMSTERDAM ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. HILLSBOROUGH TOWNSHIP SCHOOL DISTRICT AMSTERDAM ELEMENTARY SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24455 October 2012 Prepared by: 6 Campus Drive Parsippany, NJ

More information

ROXBURY BOARD OF EDUCATION ROXBURY HIGH SCHOOL ENERGY ASSESSMENT. For NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO

ROXBURY BOARD OF EDUCATION ROXBURY HIGH SCHOOL ENERGY ASSESSMENT. For NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO ROXBURY BOARD OF EDUCATION ROXBURY HIGH SCHOOL ENERGY ASSESSMENT For NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24454 December 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973) 5382120

More information

POINT PLEASANT BOROUGH BOARD OF EDUCATION. October Final Energy Audit Report

POINT PLEASANT BOROUGH BOARD OF EDUCATION. October Final Energy Audit Report A POINT PLEASANT BOROUGH BOARD OF EDUCATION October 2009 Final Energy Audit Report 15 British American Boulevard Latham, New York 12110 tel: 518-782-4500 fax: 518-786-3810 October 13, 2009 Mr. Steven Corso,

More information

Delaware Valley Regional High School LOCAL GOVERNMENT ENERGY AUDIT FOR NEW JERSEY BOARD OF PUBLIC UTILITIES. October 2013.

Delaware Valley Regional High School LOCAL GOVERNMENT ENERGY AUDIT FOR NEW JERSEY BOARD OF PUBLIC UTILITIES. October 2013. Delaware Valley Regional High School LOCAL GOVERNMENT ENERGY AUDIT FOR NEW JERSEY BOARD OF PUBLIC UTILITIES October 2013 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973) 538-2120 CHA PROJECT NO.

More information

RIVERTON BOARD OF EDUCATION RIVERTON PUBLIC SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO

RIVERTON BOARD OF EDUCATION RIVERTON PUBLIC SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO RIVERTON BOARD OF EDUCATION RIVERTON PUBLIC SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24620 October 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973) 538-2120

More information

CLINTON TOWNSHIP BOARD OF EDUCATION SPRUCE RUN ELEMENTARY SCHOOL 27 BELVIDERE AVEENUE CLINTON, NJ FACILITY ENERGY REPORT

CLINTON TOWNSHIP BOARD OF EDUCATION SPRUCE RUN ELEMENTARY SCHOOL 27 BELVIDERE AVEENUE CLINTON, NJ FACILITY ENERGY REPORT CLINTON TOWNSHIP BOARD OF EDUCATION SPRUCE RUN ELEMENTARY SCHOOL 27 BELVIDERE AVEENUE CLINTON, NJ 08809 FACILITY ENERGY REPORT Clinton Township BOE Spruce Run Elementary School Energy Audit TABLE OF CONTENTS

More information

CAMDEN COUNTY COLLEGE LINCOLN HALL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO November 2012.

CAMDEN COUNTY COLLEGE LINCOLN HALL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO November 2012. CAMDEN COUNTY COLLEGE LINCOLN HALL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24364 November 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973) 538-2120 New Jersey

More information

HILLSDALE SCHOOL DISTRICT MEADOWBROOK ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO OCTOBER 2012

HILLSDALE SCHOOL DISTRICT MEADOWBROOK ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO OCTOBER 2012 HILLSDALE SCHOOL DISTRICT MEADOWBROOK ELEMENTARY SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24535 OCTOBER 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973)

More information

UPPER TOWNSHIP SCHOOL DISTRICT UPPER TOWNSHIP PRIMARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO.

UPPER TOWNSHIP SCHOOL DISTRICT UPPER TOWNSHIP PRIMARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. UPPER TOWNSHIP SCHOOL DISTRICT UPPER TOWNSHIP PRIMARY SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24145 June 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054

More information

Appendix G - Danvers Electric

Appendix G - Danvers Electric Appendix G - Danvers Electric Energy Efficiency and Conservation Programs Revision ID Date Author Notes Approval (initials and date) 1.0 9-6-2011 Clint Allen The purpose of Version 1 is to release certain

More information

Borough of Freehold Public School District DECEMBER Final Energy Audit Report. Draft Energy Audit Report

Borough of Freehold Public School District DECEMBER Final Energy Audit Report. Draft Energy Audit Report A Borough of Public School District DECEMBER 2009 Final Energy Audit Report Draft Energy Audit Report 15 British American Boulevard Latham, New York 12110 tel: 518-782-4500 fax: 518-786-3810 December 14,

More information

CAMDEN COUNTY COLLEGE CIM (COMPUTER INTEGRATED MANUFACTURING) BUILDING ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES

CAMDEN COUNTY COLLEGE CIM (COMPUTER INTEGRATED MANUFACTURING) BUILDING ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CAMDEN COUNTY COLLEGE CIM (COMPUTER INTEGRATED MANUFACTURING) BUILDING ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24364 November 2012 Prepared by: 6 Campus Drive Parsippany,

More information

Facilities Energy Report Fiscal Year 2016 Third Quarter

Facilities Energy Report Fiscal Year 2016 Third Quarter Facilities Energy Report Fiscal Year 2016 Third Quarter I. Energy Use Summary Campus energy use through the third quarter decreased 2.5%, but increased 1.3% weather adjusted, compared to the same period

More information

MSU Mankato and Ameresco. GESP Project. August 29, Ameresco, Inc. 2017, All Rights Reserved

MSU Mankato and Ameresco. GESP Project. August 29, Ameresco, Inc. 2017, All Rights Reserved MSU Mankato and Ameresco GESP Project August 29, 2017 Agenda Campus Utility Baseline GESP Review and Summary Sustainability Overview Energy Savings Achieved Overview of the Project Time Table Financial

More information

HILLSBOROUGH TOWNSHIP SCHOOL DISTRICT WOODS ROAD ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO.

HILLSBOROUGH TOWNSHIP SCHOOL DISTRICT WOODS ROAD ELEMENTARY SCHOOL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. HILLSBOROUGH TOWNSHIP SCHOOL DISTRICT WOODS ROAD ELEMENTARY SCHOOL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24455 October 2012 Prepared by: 6 Campus Drive Parsippany,

More information

Energy Conservation Efforts

Energy Conservation Efforts Hennepin County Property Services Energy Conservation Efforts MEPC Presentation September 2010 HENNEPIN COUNTY PROPERTY SERVICES DEPARTMENT MONTHLY ENERGY COSTS $1,200,000 $1,000,000 Cold 2009 October

More information

ON-SITE ASSESSMENT REPORT. <Engineering Firm> Presented to: <Customer> <Presentation Date> Funding by: <Report Date>

ON-SITE ASSESSMENT REPORT. <Engineering Firm> Presented to: <Customer> <Presentation Date> Funding by: <Report Date> ON-SITE ASSESSMENT REPORT Presented to: Funding by: This report is for sample purposes only. The customer s actual report will contain information

More information

2151 Arapahoe Ave Boulder, CO Additional Service Address: Brendan Watt Site Contact: Brendan Watt Phone: (303) Phone: (303)

2151 Arapahoe Ave Boulder, CO Additional Service Address: Brendan Watt Site Contact: Brendan Watt Phone: (303) Phone: (303) CUSTOMER SUMMARY PAGE Customer Name: Briar Rose Bed and Breakfast Account Number(s): 53-3927217-8 Service Address: Additional Service Address: 2151 Arapahoe Ave Boulder, CO 80302 Additional Service Address:

More information

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Grocery and Convenience Stores October 11, 2012

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Grocery and Convenience Stores October 11, 2012 Pepco & Delmarva Power Commercial & Industrial Energy Savings Program Grocery and Convenience Stores October 11, 2012 Housekeeping The presentation will be emailed to you after the webinar. If you have

More information

Energy Performance Information Request Timeline

Energy Performance Information Request Timeline Energy Performance Information Request Timeline Project Title: UT Project # Project Manager: Submitted by: Day Submitted: The timeline below outlines a comprehensive list of required documents and when

More information

40KW Solar System for Apple Sauce Co

40KW Solar System for Apple Sauce Co 2012 40KW Solar System for Apple Sauce Co Document Created for The Apple Sauce Co by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L For further details please contact Luke M Hardy SunUp Solar Pty

More information

Energy Efficiency Benefits

Energy Efficiency Benefits Energy Efficiency Benefits Heating and Cooling Energy Conservation Case Study 40 W 20 th Street, NRDC New York Headquarters October 2016 Authors Ryan Meinke Anthony Guerrero Contributors Milly Suarez Eileen

More information

CAMDEN COUNTY COLLEGE JEFFERSON HALL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO November 2012.

CAMDEN COUNTY COLLEGE JEFFERSON HALL ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO November 2012. CAMDEN COUNTY COLLEGE JEFFERSON HALL ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 24364 November 2012 Prepared by: 6 Campus Drive Parsippany, NJ 07054 (973) 538-2120 New Jersey

More information

Continuous Efficiency Improvement Loop

Continuous Efficiency Improvement Loop Make Data Driven, Continuous Efficiency Improvements as Standard Practice: Technical Loop Lessons Learned & Databases Update Building(s) Benchmarking (Fleet Databases) Energy Use & Performance Deviation

More information

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Small Business Program October 3, 2012

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Small Business Program October 3, 2012 Pepco & Delmarva Power Commercial & Industrial Energy Savings Program Small Business Program October 3, 2012 Housekeeping The presentation will be emailed to you after the webinar. If you have technical

More information

June 26, Ms. Rose LaFergola Purchasing Agent Township of Manalapan Manalapan, New Jersey Energy Audit for Manalapan Township

June 26, Ms. Rose LaFergola Purchasing Agent Township of Manalapan Manalapan, New Jersey Energy Audit for Manalapan Township 15 British American Boulevard Latham, New York 12110 tel: 518-782-4500 fax: 518-786-3810 June 26, 2009 Ms. Rose LaFergola Purchasing Agent Township of Manalapan Manalapan, New Jersey 07726 Subject: Energy

More information

2017 Commercial & Industrial Program K-12 Schools Program Rebate Application

2017 Commercial & Industrial Program K-12 Schools Program Rebate Application MEMBER INFORMATION Member Name Company Name Mailing Address City State ZIP Phone Email Electric Cooperative/REMC Name (MUST be completed) Electric Cooperative/REMC Account Number (MUST be completed) Check

More information

Efficiency Works Business

Efficiency Works Business Efficiency Works Business 3 rd Annual Service Provider Appreciation Networking and Social November 29, 2018 Introduction Efficiency Works is a collaboration of common efficiency programs between Platte

More information

UNDERSTANDING YOUR ENERGY BILL

UNDERSTANDING YOUR ENERGY BILL UNDERSTANDING YOUR ENERGY BILL Chris Favia Commercial Account Manager Madison Gas and Electric Company Today s Discussion Understanding your energy bill Tracking your energy use Benchmarking your energy

More information

Energy Efficiency Program Overview

Energy Efficiency Program Overview Energy Efficiency Program Overview Rick Tonielli Sr. Program Manager C O N F I D E N T I A L Who We Are and What We Do Help customers save money and energy Cash incentives Technical services Whole-building

More information

PART 2 GUIDELINES. To be eligible to receive a financial incentive, the following conditions must be met:

PART 2 GUIDELINES. To be eligible to receive a financial incentive, the following conditions must be met: PART 2 GUIDELINES 1. Program Objective and Scope The objective of the Business Incentive Program ("BIP") is for Toronto Hydro-Electric System Limited ("Toronto Hydro") to provide financial incentives to

More information

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering

More information

CHOOSE TOSAVE. Take control of your electric bill by choosing the pricing plan that is right for you. Time-of-Use. Peak Demand. Demand Time-of-Use

CHOOSE TOSAVE. Take control of your electric bill by choosing the pricing plan that is right for you. Time-of-Use. Peak Demand. Demand Time-of-Use CHOOSE TOSAVE Take control of your electric bill by choosing the pricing plan that is right for you. Time-of-Use Peak Demand Demand Time-of-Use Basic SHIFT YOUR USAGE AND SAVE Sometimes you can save money

More information

Better Buildings by Design Chuck Reiss Reiss Building and Renovation Hinesburg, Vermont

Better Buildings by Design Chuck Reiss Reiss Building and Renovation Hinesburg, Vermont Better Buildings by Design 2015 Chuck Reiss Reiss Building and Renovation Hinesburg, Vermont www.reissbuilding.com Vermont s Comprehensive Energy Plan Improve the energy efficiency of 25% of the state

More information

Water side Economizer WC chiller

Water side Economizer WC chiller Appendices Water side Economizer WC chiller Power Loading Lighting Load W/ft^2 Area (ft^2) W kw 3.5 48152 168532 Water Cooled Chiller kw/ton 0.7 UA Supply Fan BHP kw wall 1069 58 43 window 3642 roof 295

More information

Lighting and Lighting Controls Energy Savings Opportunities Technical Training Series

Lighting and Lighting Controls Energy Savings Opportunities Technical Training Series Lighting and Lighting Controls Energy Savings Opportunities 2017 Technical Training Series Agenda Solutions for Business: Overview & Successes Program Rebates: What Qualifies? Submitting an Application:

More information

Meter Insights for Downtown Store

Meter Insights for Downtown Store Meter Insights for Downtown Store Commodity: Analysis Period: Prepared for: Report Date: Electricity 1 December 2013-31 December 2014 Arlington Mills 12 February 2015 Electricity use over the analysis

More information

CHOOSE TOSAVE. Take control of your electric bill by choosing the pricing plan that is right for you. Time-of-Use. Peak Demand. Demand Time-of-Use

CHOOSE TOSAVE. Take control of your electric bill by choosing the pricing plan that is right for you. Time-of-Use. Peak Demand. Demand Time-of-Use CHOOSE TOSAVE Take control of your electric bill by choosing the pricing plan that is right for you. Time-of-Use Peak Demand Demand Time-of-Use Basic SHIFT YOUR USAGE AND SAVE Sometimes you can save money

More information

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Residential Solar Workshop May 7 th 2008 Thomas Alston Director of Business and Policy Development Presented By 1475 N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Workshop Agenda An Overview of

More information

NJ Solar Market Update

NJ Solar Market Update NJ Solar Market Update April 16, 20 Renewable Energy Committee Meeting Trenton, NJ Prepared by Charlie Garrison Solar Installed Capacity Data The preliminary installed solar capacity as of 3/31/ is approximately

More information

INDUSTRIAL EQUIPMENT INCENTIVES FOR OREGON BUSINESS CUSTOMERS

INDUSTRIAL EQUIPMENT INCENTIVES FOR OREGON BUSINESS CUSTOMERS INDUSTRIAL Standard Incentives INDUSTRIAL EQUIPMENT INCENTIVES FOR OREGON BUSINESS CUSTOMERS SAVE MONEY AND ENERGY NOW AND FOR YEARS TO COME EFFECTIVE JANUARY 2018 INCENTIVES ARE SUBJECT TO AVAILABILITY

More information

OREGON SCHEDULE 115 COMMERCIAL AND INDUSTRIAL ENERGY EFFICIENCY RETROFIT INCENTIVES 20,000 SQUARE FEET OR LESS NO NEW SERVICE Page 1

OREGON SCHEDULE 115 COMMERCIAL AND INDUSTRIAL ENERGY EFFICIENCY RETROFIT INCENTIVES 20,000 SQUARE FEET OR LESS NO NEW SERVICE Page 1 NO NEW SERVICE Page 1 Purpose Service under this Schedule is intended to maximize the efficient utilization of the electricity requirements of existing loads in Commercial Buildings and Industrial Facilities

More information

BOSS Controls provides Advanced Plug Load Control for Schools & Universities

BOSS Controls provides Advanced Plug Load Control for Schools & Universities Energy Savings Case Studies: Education BOSS Controls provides Advanced Plug Load Control for Schools & Universities Hundreds of small plug loads are often not included in campus energy management strategies.

More information

Guide for Contractors September 2016

Guide for Contractors September 2016 Guide for Contractors September 2016 PO Box 358 Halstad, MN 56548 218-456-2139 1-800-788-7784 www.rrvcoop.com Table of Contents Off-Peak Program and List of Contacts 1 Ripple Control Guidelines 2-3 Adequate

More information

Energy Rebate Programs:

Energy Rebate Programs: Energy Rebate Programs: We have a trade ally program using competent licensed contractors located locally to do the paperwork, installation and ensure that all measures qualify for TEP rebates. The alternate

More information

Impacts of Future Codes and Standards on U.S. Electricity Use ( )

Impacts of Future Codes and Standards on U.S. Electricity Use ( ) Global Energy Partners, LLC 2009 Impacts of Future Codes and Standards on U.S. Electricity Use (2010-2020) Prepared for ACEEE Energy Efficiency as a Resource Presented by Ingrid Rohmund Global Energy Partners,

More information

Texas Tech University Energy Savings Program January 2010 Update

Texas Tech University Energy Savings Program January 2010 Update Texas Tech University Energy Savings Program January 2010 Update The Texas Tech Energy Savings Update is being submitted in accordance with Governor s Executive Order RP 49, Electric Conservation by State

More information

ENERGY SAVINGS PLAN. High Point Regional High School District Revised October 10, Electronic Copy. Prepared for:

ENERGY SAVINGS PLAN. High Point Regional High School District Revised October 10, Electronic Copy. Prepared for: ENERGY SAVINGS PLAN Prepared for: High School District Revised October 10, 2011 Electronic Copy High School District District-Wide Energy Savings Plan Executive Summary and Overview Honeywell is pleased

More information

SCHOOLS MILLBUR FOR (973)

SCHOOLS MILLBUR FOR (973) MILLBUR RN TOWNSHIP PUBLIC SCHOOLS MILLBURN HIGHH SCHOOL 462 Millburn Ave., Millburn, NJ 07041 LOCALL GOVERNMENT ENERGY AUDIT PROGRAM FOR NEW JERSEY BOARD OF PUBLIC UTILITIES May 2014 Prepared by: 6 Campus

More information

Angelo State University Energy Savings Program October 30, 2014

Angelo State University Energy Savings Program October 30, 2014 The Angelo State University Energy Savings Update is being submitted in accordance with Governor s Executive Order, RP 49, Energy Conservation by State Agencies. A. Energy Goals 1. Campus Energy Use Energy

More information

Impact of Distributed Energy-Efficiency with Solar on SMUD s Peak Load

Impact of Distributed Energy-Efficiency with Solar on SMUD s Peak Load Impact of Distributed Energy-Efficiency with Solar on SMUD s Peak Load Mike Keesee, Sacramento Municipal Utility District Rob Hammon, ConSol ABSTRACT One of the advertised benefits of distributed solar

More information

Example 1MW Solar System for Fosters Yatala

Example 1MW Solar System for Fosters Yatala Example 1MW Solar System for Fosters Yatala Document Created by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L 31 December 2012 Highlights Luke M Hardy MBA, Grad Cert Carbon Management Key Points

More information

COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION

COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION 1. CUSTOMER INFORMATION (please print) Account Name Doing Business As (if different from Account Name) Installation Address City State Zip Code Mailing

More information

Thank you for requesting information on our utility auditing services!

Thank you for requesting information on our utility auditing services! - EXHIBIT A - ELECTRIC - CLIENT INVOICE: EXAMPLE #1 If we moved a client from an electrical rate 6 to a rate 6L, and, as a result, changed their KWH rate from $.06 per Kilowatt Hour to $.05 per Kilowatt

More information

Contents. 04 Overview. 05 Residential Energy Efficiency Program. 07 Heating Ventilation and Air Conditioning (HVAC) Systems

Contents. 04 Overview. 05 Residential Energy Efficiency Program. 07 Heating Ventilation and Air Conditioning (HVAC) Systems Contents 04 Overview 05 Residential Energy Efficiency Program 07 Heating Ventilation and Air Conditioning (HVAC) Systems 08 Custom Energy Efficiency Program 08 New Construction and Major Tenant Renovation

More information

250kW Solar PV System Poultry Shed Solution - Gatton

250kW Solar PV System Poultry Shed Solution - Gatton 250kW PV System Poultry Shed Solution - Gatton Document Created by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L www.smartconsult.com.au 14 June 2013 Key Points for a PV System 250kW System at

More information

Texas Tech University Energy Savings Program October 2009 Update

Texas Tech University Energy Savings Program October 2009 Update Texas Tech University Energy Savings Program October 2009 Update The Texas Tech Energy Savings Update is being submitted in accordance with Governor s Executive Order RP 49, Electric Conservation by State

More information

NJ Solar Market Update As of 6/30/15

NJ Solar Market Update As of 6/30/15 NJ Solar Market Update As of 6/30/ Prepared by Charlie Garrison July 17, 20 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 6/30/ is approximately 1,500.7 MW. Approximately

More information

Vernon Township School District JANUARY Final Energy Audit Report

Vernon Township School District JANUARY Final Energy Audit Report A Township District JANUARY 2010 Final Energy Audit Report Contents Executive Summary Section 1 Introduction 1.1 General... 1-1 1.2 Background... 1-1 1.3 Purpose and Scope... 1-2 Section 2 Facility Description

More information

Xcel Energy s Energy Efficiency Programs. Derek Shockley Trade Relations Manager Commercial and Industrial

Xcel Energy s Energy Efficiency Programs. Derek Shockley Trade Relations Manager Commercial and Industrial Xcel Energy s Energy Efficiency Programs Derek Shockley Trade Relations Manager Commercial and Industrial Driver: Colorado s Energy Needs In the last decade: Up 39% Up 15% Up 19% Number of Customers Electric

More information

Best Practices in Energy Efficiency

Best Practices in Energy Efficiency Best Practices in Energy Efficiency Tom Sherman C.E.M., C.E.A., C.D.S.M. President Sustainable Energy Services, Inc. 440.773.5044 Tom@sustainable-energy-services.com How Do You Buy What You Can t Afford?

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates For Internal Use Only. FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

The Rebate Program can change without notice. CPS Energy reserved the right to discontinue the program at any time.

The Rebate Program can change without notice. CPS Energy reserved the right to discontinue the program at any time. COMMERCIAL & INDUSTRIAL CUSTOMERS Program Overview The CPS Energy Rebate Program for Commercial and Industrial Customers (Rebate Program) was developed to provide incentives for the new installation and

More information

CITY OF GRAND ISLAND UTILITIES DEPARTMENT ELECTRIC RATE SCHEDULE Effective October 1, Ordinance No. 9133

CITY OF GRAND ISLAND UTILITIES DEPARTMENT ELECTRIC RATE SCHEDULE Effective October 1, Ordinance No. 9133 010, RESIDENTIAL SERVICE CITY OF GRAND ISLAND UTILITIES DEPARTMENT ELECTRIC RATE SCHEDULE Effective October 1, 2007 - Ordinance No. 9133 Applicable in urban and rural distribution areas. Available in single

More information

ENERGY & UTILITIES. Electricity Metering & Sub-Metering Concepts and Applications. BuildingsOne April 30, 2018

ENERGY & UTILITIES. Electricity Metering & Sub-Metering Concepts and Applications. BuildingsOne April 30, 2018 BuildingsOne April 30, 2018 The measurement of base building systems and tenantspecific equipment electricity consumption, through submetering applications, is increasing in importance within the commercial

More information

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017 ELECTRIC SERVICE RATE SCHEDULES Effective November 1, 2017 SCHEDULE 100 RESIDENTIAL SERVICE Residential Customers for all domestic uses. CHARACTER OF SERVICE: Alternating current, sixty-hertz 120/240 volts

More information

Capture The Power of Photovoltaics. IEEE Power Engineering Society Meeting May 2005

Capture The Power of Photovoltaics. IEEE Power Engineering Society Meeting May 2005 Capture The Power of Photovoltaics IEEE Power Engineering Society Meeting May 2005 Agenda Photovoltaic Basics Applications Economics Grid Interconnection and Net Metering Grid-Tied System Components Net

More information

Prescriptive Rebate Program

Prescriptive Rebate Program Prescriptive Rebate Program Black Hills Power Commercial Installing energy-efficient technology is a smart way for Commercial and Industrial customers to lower energy bills. Energy-efficient equipment

More information

Sustainability Strategies

Sustainability Strategies 17 th Annual Spring Education Seminar Minnesota Health Care Engineers Association Sustainability Strategies for Health Care Kevin Bengtson Key Account Manager Business Conservation Programs What is Sustainability?

More information

Prepared for City of Smithville Smithville, Texas. City of Smithville Investment Grade Audit

Prepared for City of Smithville Smithville, Texas. City of Smithville Investment Grade Audit Prepared for City of Smithville Smithville, Texas City of Smithville June 3, 2015 June 3, 2015 Prepared for City of Smithville, Texas Presented by Ameresco, Inc. George Rash Senior Account Executive P:

More information

PA ACT 129 UPDATE THE NEXT GENERATION OF UTILITY ENERGY EFFICIENCY PROGRAMS IN PA

PA ACT 129 UPDATE THE NEXT GENERATION OF UTILITY ENERGY EFFICIENCY PROGRAMS IN PA PA ACT 129 UPDATE 1 THE NEXT GENERATION OF UTILITY ENERGY EFFICIENCY PROGRAMS IN PA Schaedler Yesco Act 129 Update Seminar June 26 th, 2013 Pittsburgh, PA Stephen Moritz: President AllFacilities Energy

More information

PRICED BILL OF QUANTITIES Package : Air conditionning. Manhours (h) Unit (tariff) Discount Total Unit. Total. Material cost

PRICED BILL OF QUANTITIES Package : Air conditionning. Manhours (h) Unit (tariff) Discount Total Unit. Total. Material cost Spend study of price carries out by Margins ratios (rate on selling price) Mark up (coef. on cost price) - Overheads 15,00% Mark up (N1) 1,25 - Profits 2,00% - Mark up N 1 1,20 1 - Consulting firm fees

More information

Lane Community College Energy Use, Tracking, Feedback - Year Reported: 2015/2016. Summary Data

Lane Community College Energy Use, Tracking, Feedback - Year Reported: 2015/2016. Summary Data Lane Community College Energy Use, Tracking, Feedback - Year Reported: 2015/2016 Summary Data DESCRIPTION DATA Total energy use for heating, cooling, and electricity in 2015/2016. (Millions of British

More information

Electrical Power Analysis of the Cal Poly Organic Farm for the Cal Poly SuPER Project

Electrical Power Analysis of the Cal Poly Organic Farm for the Cal Poly SuPER Project Electrical Power Analysis of the Cal Poly Organic Farm for the Cal Poly SuPER Project Presentation For SARC March 21, 2008 Senior Project By Alex Liang Agenda Terminology Introduction to SuPER and This

More information

Methodology of Cost Allocation

Methodology of Cost Allocation Methodology of Cost Allocation Robin Kliethermes May 17, 2013 1 Purpose of Cost Allocation Determine whether each class of customers is providing the utility with a reasonable level of revenue necessary

More information

Watauga County Schools Capital Improvement Plan 2015

Watauga County Schools Capital Improvement Plan 2015 Watauga County Schools Capital Improvement Plan 2015 WATAUGA COUNTY SCHOOLS CAPITAL IMPROVEMENT PLAN 2015 In an effort to meet the standards of the North Carolina Building Code and North Carolina Public

More information

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys Irrigation energy efficiency How to analyse your energy costs Nick Bullock The Energy Guys March 2017 1 PILOT Energy Audits: Pivots AIM: data on energy use simple field data How energy efficient is system?

More information

Vending Machines Energy savings for the thirsty

Vending Machines Energy savings for the thirsty Vending Machines Energy savings for the thirsty Noah Horowitz Sr. Scientist Natural Resources Defense Council nhorowitz@nrdc.org Today s Lineup Vending machines 101 Market Energy Consumption Savings opportunities

More information

Residential Time-of-Day Service Rate Schedule R-TOD

Residential Time-of-Day Service Rate Schedule R-TOD I. Applicability This Rate Schedule 1-R-TOD applies to single- and three-phase service for the following types of residential premises: 1. Individual or dual metered residences with digital communicating

More information

New Jersey Solar Roundtable

New Jersey Solar Roundtable New Jersey Solar Roundtable Transition to a Market-based REC Financing System Scott Hunter, Renewable Energy Program Administrator NJBPU, Office of Clean Energy Presented at New Jersey Institute of Technology

More information

North Dakota Commercial and Industrial Electric Prices

North Dakota Commercial and Industrial Electric Prices North Dakota Commercial and Industrial Electric Prices Effective January 1, 2015 The rates below appear on your bill under Electric Charges. Basic service charge A fixed monthly charge that covers the

More information

Energy Saving Options for Small ISDs. Presented by Casey Stone, PE, CEM

Energy Saving Options for Small ISDs. Presented by Casey Stone, PE, CEM Energy Saving Options for Small ISDs Presented by Casey Stone, PE, CEM True Story*.. Big City ISD has lots of students & budget, and has been building new schools Each new school was carefully designed

More information

NEU Electric and Natural Gas Price Update

NEU Electric and Natural Gas Price Update Exelon s $24 Billion Energy Bill Senate Bill 2814 Short-Term Energy Price Outlook On November 15, 2016, Exelon, through its legislative supporters, introduced Senate Bill 2814, a massive 446 page document

More information

POST-VISIT ACTIVITY: STANDARD VERSION TEP BRIGHT STUDENTS: THE CONSERVATION GENERATION

POST-VISIT ACTIVITY: STANDARD VERSION TEP BRIGHT STUDENTS: THE CONSERVATION GENERATION POST-VISIT ACTIVITY: STANDARD VERSION TEP BRIGHT STUDENTS: THE CONSERVATION GENERATION Part A. Energy Savings Kit Go through the contents of the Energy Savings Kit with students. Make sure that all students

More information

HVAC Rebates Rebate Application

HVAC Rebates Rebate Application Rebate Application Business Member Information Business Name Installation Address City, State, Zip Contact Name Email Phone Number Account Number Rebate Recipient Please Send Rebate to: Recipient Name

More information

East Camden Regional High School District OCTOBER Final Energy Audit Report

East Camden Regional High School District OCTOBER Final Energy Audit Report A East Camden Regional High School District OCTOBER 2009 Final Energy Audit Report 15 British American Boulevard Latham, New York 12110 tel: 518-782-4500 fax: 518-786-3810 October 19, 2009 Mr. Fred Wright

More information

Working through the electric motor replacement maze

Working through the electric motor replacement maze Working through the electric motor replacement maze Taking a total cost of ownership approach to motor replacement can save big dollars -- and help save the planet The Department of Commerce currently

More information

Energy Savings and Incentives with PG&E. Chad Stout Account Manager

Energy Savings and Incentives with PG&E. Chad Stout Account Manager Energy Savings and Incentives with PG&E Chad Stout Account Manager Electric Rates: Do you have options? AG-4 For customers with moderate annual operating hours (generally 500 to 1,200). Additional savings

More information

SOLAR FEASIBILITY STUDY

SOLAR FEASIBILITY STUDY SOLAR FEASIBILITY STUDY KAKE SENIOR CENTER KAKE ALASKA June 24, 2015 Submitted By: BacGen Technologies, Inc, Maud de Bel Maud@bacgen.com 206-459-9418 Executive Summary BacGen investigated the feasibility

More information

DC Power Grid System Lighting for a Typical Conference Room Evaluation

DC Power Grid System Lighting for a Typical Conference Room Evaluation Design & Engineering Services DC Power Grid System Lighting for a Typical Conference Room Evaluation ETO 09.03 Report Prepared by: Design & Engineering Services Customer Service Business Unit Southern

More information

Operational Opportunities to Minimize Renewables Curtailments

Operational Opportunities to Minimize Renewables Curtailments Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance

More information