Rocky Reach Bridge Crane Repair. Commission Presentation February 1, 2016
|
|
- Evangeline Alexander
- 5 years ago
- Views:
Transcription
1 Rocky Reach Bridge Crane Repair Commission Presentation February 1, 2016
2 Overview Rocky Reach Bridge Crane Rehab Main Hoist Drum Inspections Impacts to Projects and Plant Operations Alternatives Considered Recommendation Risks and Opportunities Requesting Board approval to declare emergency to accelerate repair schedule 2
3 Bridge Crane Rehab Two Bridge Cranes Each has a 250T main hoist & 25T auxiliary hoist (de-rated to 8.5T) Used to move equipment throughout the powerhouse. Use of mobile cranes limited Advertisement for Bid for Rehabilitation Approved by Board on 1/18/16. Rehab project budget $4M Work Follows completion of C8 turbine repairs. Field work Dec. 9, 2016 to April 8,
4 Main Hoist Drum Inspections Drum inspections Experienced contractor suggested drum inspection beneath the paint Jan. 18. Inspections performed Jan. 19. Numerous cracks found. Evaluations conducted Jan 20 to 22. Operations declared Bridge Cranes unavailable until repaired on 1/23 due to risk of injury and catastrophic failure. Main Hoist Drum 4
5 Main Hoist Drum 5
6 Inspection Results Magnetic particle (MT) with ambient light MT with black light 6
7 Inspection Results MT with ambient light MT with black light 7
8 Impact to Project Schedules Three major ongoing projects under contract that are impacted if bridge cranes remain unavailable after 3/15/2016. C-8 Permanent Turbine Repair C-10 Interim Winding Repair C-8 Permanent Winding Replacement Schedule delays result in Lost incremental generation revenue Increased contract costs Increased operational impacts associated with blades operated in full steep position 8
9 Potential Impact to Plant Operations Labor force work plan C8 re-assembly delay (5000 man hours) Blade block inspections Scheduled maintenance gets deferred Lose ability to react to any other unplanned repairs 9
10 Alternatives Considered Option A Start repairs immediately: Waive bidding; negotiation with contractor(s). Option B Include repair in bridge crane overhaul contract currently scheduled for Fall Option C Competitively bid the repairs now Recommendation: Option A 10
11 Risks / Opportunities Considered (+/-) Option A Emergency Safety (+) expediting return to service promotes safety at the plant for unexpected events. Maintenance (+) expediting return essential to maintain the ability to perform scheduled maintenance and respond to generating equipment concerns or unplanned repairs Schedule (+) immediate negotiation for repair prevents schedule delays for C-8 turbine and C-10 winding repair / replacement Contract (+) preventing significant schedule delays mitigates risk of contract delay claims and potential for breach claim Lost Revenue (+) supports a C-10 return to service after interim winding repair in advance of spring run-off for opportunity at incremental value. Risk of premature C-10 failure still exists after winding repair, however risk adjusted value still supports performing winding repair. 11
12 Risks / Opportunities Considered (+/-) Option A - Emergency Revenue Loss Mitigation (+) returning C-10 for spring runoff mitigates revenue risk of losing a 3rd unit, thus helps protect value. Resources (-) District work to remove and install drums was not in the work plan where labor and other projects may be delayed. Repair (-) more damage to crane could be revealed impacting cost, small risk that repairs may not be successful, or repairs may not last long. Values (+) expediting work supports the District s Core Values providing a safe work environment, reliable generation by maximizing opportunity for unit availability, and acting as stewards for our stakeholders and customer owners. 12
13 Resolution Requesting approval from the Board by resolution: Declaring an emergency Competitive bidding requirements waived per RCW Authorize General Manager to negotiate and execute contract(s) for lowest responsible price practical under the circumstances. 13
14 QUESTIONS? 14
15 Hydro Stationary Cranes Rocky Reach North Bridge Crane: Main Hoist Tagged out Auxiliary Hoist Available for loads up to 8.5 tons South Bridge Crane: Main Hoist Tagged out Auxiliary Hoist Tagged out Intake Gantry: Available for use Tail Race Gantry: Tagged out; Scheduled for inspection 15
16 Hydro Stationary Cranes Rock Island Spillway Gantry #2(P&H): Inspected and cleared for use Gantry #1 (Whiting): Tagged out; Scheduled for inspection PH1 Tail Race Deck Gantry: Inspected and cleared for use PH2 Intake Gantry: Inspected and cleared for use PH2 Bridge Cranes: Inspected and cleared for use Chelan Powerhouse Bridge Crane: Tagged out; Scheduled for inspection 16
Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014
Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project NWHA Spokane October 30, 2014 0 The Wells Project WELLS Chief Joseph Rocky Reach East Wenatchee Wells Dam Location Columbia
More informationWestern Alberta Transmission Line (WATL) HVDC Project
Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment
More informationMcNary Northshore Fishway Hydro Project. History & Lessons Learned
McNary Northshore Fishway Hydro Project History & Lessons Learned May 6, 2017 21 th Annual TECHNICAL SEMINAR Machines, Maintenance, and Management: Keeping Hydro Facilities Up and Running History & Lessons
More informationCushman & Adams Substations MOU March 28, Cushman & Adams Substations April, 1937
Cushman & Adams Substations MOU March 28, 2018 Cushman & Adams Substations April, 1937 Joint Staff Task Force Terry Coggins, Tacoma Power Ward Groves, Legal Jennifer Hines, Real Property Services Peter
More informationChelan County Public Utility District No Active Major Capital Projects First Quarter
Finish Var. versus 1/1/15 Cost Variance Vs. Current Approved Project Name Phase Baseline Finish as of 1/1/15 Expected Finish Baseline Budget as of 1/1/15 Current Approved Project Budget Estimated Cost
More informationA REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. System Planning. Overhaul Diesel Engines.
A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES Electrical Mechanical ( Protection Civil & Control & Distribution System Planning Overhaul Diesel Engines Various Locations July 2012 newfoundland
More information2017 EXTENDED LOCK MAINTENANCE CLOSURE ON THE COLUMBIA SNAKE RIVER WATERWAY
EXTENDED LOCK MAINTENANCE CLOSURE ON THE WATERWAY 2 2 2 8 11 12 12 13 12 13 12 Sheryl Carrubba Northwestern Division, Navigation Inland Waterways Users Board Meeting No. 84 19 July The views, opinions
More informationFund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6b ACTION ITEM Date of Meeting August 4, 2015 DATE: TO: FROM: Dave Soike, Director, Aviation Facilities and Capital Programs Wayne Grotheer, Director,
More informationTransit Project Delivery Status Report. Significant Issues
Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda
More informationCalifornia Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016
California Energy Storage Policies Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Storage Law and Policy l California has supported energy storage through
More informationCONTAINER CRANE UPGRADE AND RELOCATION: THREE CASE STUDIES ARUN K. BHIMANI 1, M. ASCE
Reprinted from PORTS 95 Proceedings, sponsored by the Committee on Ports and Harbors of the Waterway, Port, Coastal, and Ocean Engineering Division/ASCE Held March 13-15, 1995, Tampa, Florida CONTAINER
More informationTel metro. net
One Gateway Plaza Los Angeles, CA 90012-2952 34 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: ELECTRIC FAN SYSTEM APPROVE CONTRACT AWARD RECOMMENDATION
More informationThe Magazine of the North American Hydroelectric Industry HYDRO REVIEW. NHA Annual Conference details pg. 69
March 2012 www.hydroworld.com The Magazine of the North American Hydroelectric Industry HYDRO REVIEW NHA Annual Conference details pg. 69 Rehabilitation What began as a unit inspection at a vintage hydroelectric
More informationHave you saved 70% for tank cleaning, inspection and repair costs by using robotics?
Have you saved 70% for tank cleaning, inspection and repair costs by using robotics? All tank owners have performed inspections that have negative effects on staff, the environment and their operational
More informationVirginia Offshore Wind Port Readiness Study
Virginia Offshore Wind Port Readiness Study Briefing to Virginia Offshore Wind Development Authority Richmond, VA 23 April 2015 George Hagerman VCERC Director of Research Virginia Tech Advanced Research
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Capital Programs and Construction BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Director of Transportation to execute
More informationKontakt. Turnkey solutions for hydropower plants An overview of the ABB portfolio
Kontakt Turnkey solutions for hydropower plants An overview of the ABB portfolio ABB is the world s leading provider of products and integrated solutions for power and automation technologies for hydropower
More informationTHE COUNCIL OF STATE GOVERNMENTS RESOLUTION SUPPORTING ELECTRIC POWER GRID MODERNIZATION TO ACHIEVE ENERGY EFFICIENCY AND DEMAND REDUCTION BENEFITS
THE COUNCIL OF STATE GOVERNMENTS RESOLUTION SUPPORTING ELECTRIC POWER GRID MODERNIZATION TO ACHIEVE ENERGY EFFICIENCY AND DEMAND REDUCTION BENEFITS Resolution Summary The resolution offers numerous findings,
More informationCITY OF LOS ANGELES DEPARTMENT OF AIRPORTS
CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS COMPRESSED NATURAL GAS 35-FOOT TRANSIT BUSES CONTRACT NUMBER ML09032 FINAL REPORT APRIL 2015 SUBMITTED BY: LOS ANGELES WORLD AIRPORTS MAINTENANCE DIVISION Prepared
More informationSystem Status Briefing
System Status Briefing Phakamani Hadebe Interim Group Chief Executive 3 May 2018 Contents 1 Performance summary 2 Operational highlights 3 Generation performance 4 Distribution overview 5 Transmission
More informationDATE: MAY 3, 2007 ENVIRONMENTAL MANAGEMENT DIVISION
DATE: MAY 3, 2007 FROM: ENVIRONMENTAL MANAGEMENT DIVISION SUMMARY: This Board item requests that the Board of Harbor Commissioners approve the allocation and expenditure, from funds previously disbursed
More informationRH Electric Wire Rope Hoists
RH Electric Wire Rope Hoists Harrington RH wire rope hoists are designed and built for today s heavy-duty wire rope hoist applications including fabricating, die handling, paper mill and production line
More informationAppendix G Examples and Recommended Methods
Reporting Outages to the Generating Availability Data System (GADS) Introduction The examples in this appendix illustrate the reporting of outages and deratings to GADS. They are based on a fictional 600
More informationDepartment of Legislative Services
Department of Legislative Services Maryland General Assembly 2006 Session HB 38 FISCAL AND POLICY NOTE House Bill 38 (Delegate Hubbard) Health and Government Operations Procurement - Diesel-Powered Nonroad
More informationELECTRONIC OVERHEAD TRAVELLING CRANE DIMENSIONS & LOAD DATA
ELECTRONIC OVERHEAD TRAVELLING CRANE DIMENSIONS & LOAD DATA FOR ESTIMATING PURPOSES ONLY CONTENTS TOP RUNNING SINGLE GIRDER CRANES 2, 3 & 5 Ton 7.5 & 10 Ton PAGE 2-5 TOP RUNNING DOUBLE GIRDER CRANES 5,
More informationAlfred & Plantagenet Multi-Residential Cart Recycling Program CIF Project Number # Final Report October 1, 2016
Alfred & Plantagenet Multi-Residential Cart Recycling Program CIF Project Number #545.3 Final Report October 1, 2016 Prepared for: Waste Diversion Ontario Continuous Improvement Fund Office Barrie, Ontario
More informationBEFORE THE GUAM PUBLIC UTILITIES COMMISSION ) ) ) ) ) ) ) ) ORDER INTRODUCTION
BEFORE THE GUAM PUBLIC UTILITIES COMMISSION IN THE MATTER OF: THE APPLICATION OF THE GUAM POWER AUTHORITY TO APPROVE THE CONTRACT FOR SUPPLY OF RESIDUAL FUEL OIL NO. 6 TO GPA GPA DOCKET 13-10 ORDER INTRODUCTION
More informationProgress and Challenges in Philippine Energy Sector Reform
Progress and Challenges in Philippine Energy Sector Reform A Presentation by: Lily Gutierrez Energy Policy Advisor Office of Energy and Environment Infrastructure for Rebuilding and Developing Countries
More information[Agreement - TEGSCO, LLC, dba San Francisco AutoReturn - Towing and Storage of Abandoned and Illegally-Parked Vehicles - Not to Exceed $65,400,000]
FLE NO. 01 RESOLUTON NO. - 1 [Agreement - TEGSCO, LLC, dba San Francisco AutoReturn - Towing and Storage of Abandoned and llegally-parked Vehicles - Not to Exceed $,00,000] Resolution approving the Agreement
More informationBoard 8/24/2017 Final Action Bonnie Todd, Executive Director of Operations Martin Young, Commuter Rail Manager
MOTION NO. M2017-103 Sounder Heating, Ventilating and Air Conditioning Service Contract MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: 8/24/2017 Final Action Bonnie Todd, Executive Director of Operations
More informationDeploying Smart Wires at the Georgia Power Company (GPC)
Deploying Smart Wires at the Georgia Power Company (GPC) January, 2015 Contents Executive Summary... 3 Introduction... 4 Architecture of the GPC Installations... 5 Performance Summary: Long-term Test...
More informationINTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY
INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application
More informationDRAFT April 9, STATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted [adoption date])
RULE 9610 STATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted [adoption date]) 1.0 Purpose The purpose of this rule is to provide an administrative mechanism
More informationShaping our utility to do the best, for the most, for the longest.
2016-2017 Public Power Benefit Projects October 17, 2016 - BOARD UPDATE Shaping our utility to do the best, for the most, for the longest. Public Power Benefit Projects (Approved projects) 1. Fiber Expansion
More informationWHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand.
WHAKAMARU POWER STATION REHABILITATION PROJECT Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. ABSTRACT Whakamaru Power Station in the North Island of New Zealand
More informationHydro Plant Risk Assessment Guide
September 2006 Hydro Plant Risk Assessment Guide Appendix E8: Battery Condition Assessment E8.1 GENERAL Plant or station batteries are key components in hydroelectric powerplants and are appropriate for
More informationHonorable Mayor Smith and members of the City Council; City Manager Brenda Fischer. Approval of Contract: Brindlee Mountain Fire Apparatus
To: From: Honorable Mayor Smith and members of the City Council; City Manager Brenda Fischer Wade Brannon, Fire Chief; Date: 6/21/2011 RE: Approval of Contract: Brindlee Mountain Fire Apparatus REQUEST
More informationFlywheel as High Power Storage Devices for Grid Load Balancing and Stabilization
Flywheel as High Power Storage Devices for Grid Load Balancing and Stabilization Matt Lazarewicz Vice President and Chief Technical Officer International Renewable Energy Storage Conference Gelsenkirchen,
More informationSUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE
æ Metro Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 9 012-2952 3~ 213-922.2000 Tel metro. net OPERATIONS COMMITTEE NOVEMBER 15, 2007 SUBJECT: CONTRACT C080S, HOIST REPLACEMENT
More informationMOBILE GANTRY CRANE. DB Series US Tons
MOBILE GANTRY CRANE DB Series 30 50 70 100 140 200 US Tons LEGENDARY QUALITY and design that s more economical than ever! The evolution continues with unmatched value. Designed with you in mind. With a
More informationTunney s Pasture to Dominion Station Traffic and Transit Detours. April 4, 2017 C. Wheeler/ C. Swail
Tunney s Pasture to Dominion Station Traffic and Transit Detours April 4, 2017 C. Wheeler/ C. Swail Purpose of Presentation Outline key principles for traffic and transit management Implementation strategies
More informationPROJECTS $500K AND OVER FOR 2012
EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions)
More informationCommuter Rail Update. October 25, 2018
Commuter Rail Update October 25, 2018 2 page page 3 State of Commuter Rail Network, July 2014 The 2014 Commuter Rail network had multiple issues and a history of neglect & under-investment FIRST UP? UPGRADES
More informationMOBILE GANTRY CRANE. DB Series US Tons. Courtesy of Crane.Market
MOBILE GANTRY CRANE DB Series 30 50 70 100 140 200 US Tons LEGENDARY QUALITY AND DESIGN THAT S MORE ECONOMICAL THAN EVER! The evolution continues with unmatched value. Designed with you in mind. With a
More informationRESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network
GE Power RESERVOIR SOLUTIONS Flexible, modular Energy Storage Solutions unlocking value across the electricity network TRENDS DISRUPTING THE POWER SECTOR FROM GENERATION TO T&D DECARBONIZATION DIGITIZATION
More informationNP NLH NLH General Rate Application Page 1 of 1
NP NLH 022 2013 NLH General Rate Application Page 1 of 1 1 2 3 4 5 Q. Reference: Finance Please provide detailed amortization schedules for the amortization expense for 2012, 2013 test year (provided in
More informationBEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER. Exhibit Accompanying Rebuttal Testimony of Dana M.
Exhibit RMP (DMR-1R) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Rebuttal Testimony of Dana M. Ralston Lakeside U12 Combustion Turbine Exhaust Cylinder
More informationNorth America s leader in Track, Transit and Systems construction & maintenance services
Your Track Investment Maintaining Your Track. It s a Smart Investment. You wouldn t think of operating your vehicle without oil. Why risk a safety hazard, costly repair bill or compromising the value of
More informationOverview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all
Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all hydro power dams have and compare the design of Revelstoke
More informationToo Good to Throw Away Implementation Strategy
Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend
More informationEMERGING REQUIREMENTS
Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This
More informationOffice of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report
Office of Transportation Bureau of Traffic Management 1997 Downtown Parking Meter District Rate Report Introduction The City operates approximately 5,600 parking meters in the core area of downtown. 1
More informationTRASH RACK CLEANING MACHINE
TRASH RACK CLEANING MACHINE 1 SCOPE The work includes the design, manufacturing, supply, transportation, handling, storage, installation (including 1 st and 2 nd Stage embedded parts and any other necessary
More informationDetermining Gearbox Service Factors for Overhead Crane Applications By Danilo Lai
Gearbox Service Factors for Overhead Crane Applications White Paper 1 Determining Gearbox Service Factors for Overhead Crane Applications By Danilo Lai Sumitomo Machinery Corp. of America March 11, 2011
More informationfor CONSTRUCTION PROJECTS HOISTS & RIGGING PRODUCTS FOR CONSTRUCTION Power Plants Commercial Construction Wind Energy Bridges & Highways
A Complete Line of Products & Solutions for CONSTRUCTION PROJECTS HOISTS & RIGGING CONSTRUCTION Power Plants Commercial Construction Wind Energy Bridges & Highways TOUGH. RELIABLE. STRONG. Keeping Projects
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationWhatcom County Invitation to Bid Bid #17-09
Invitation to Bid NOTICE IS HEREBY GIVEN that sealed bids will be received by Purchasing at their fice in the Whatcom County Administrative Services Finance Office in Whatcom County Courthouse, 311 Grand
More informationoff-grid Solutions Security of supply Basics: Off-grid energy supply
RENEWABLE OFF-GRID ENERGY COMPLETE off-grid POWER solutions off-grid Power with AEG Power Solutions Security of supply Getting renewable energy to two billion people living in the world s poorest countries
More informationSouthern California Edison
Recent Energy Storage Projects November 8, 2017 Presented by Kern Economic Development Corporation 1 Agenda 1. California Energy Trends and Recent Events 2. SCE s Storage Projects California Energy Trends
More informationAN OUTLINE HISTORY OF DANISH WIND TURBINE PRODUCTION: Output and Longevity from 1977 to 2014.
AN OUTLINE HISTORY OF DANISH WIND TURBINE PRODUCTION: Output and Longevity from 1977 to 214. Introduction The Danish Energy Agency (http://www.ens.dk/en/info/facts- figures/energy- statistics- indicators-
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 30, 2010 SUBJECT: PROCUREMENT AUTHORIZATION AMENDMENT - LOW FLOOR LIGHT RAIL VEHICLE OPTIONS: SURFACE VEHICLE SAFETY
More informationECO 250 CUTTER SUCTION DREDGER
ECO 250 CUTTER SUCTION DREDGER RELIABLE BRANDS REPLACEABLE AUGER KNIVES OPTIMIZED PRODUCTION Dredge Yard +31 85 3035 866 www.dredgeyard.com MULTI-PURPOSE DREDGERS QUALITY FROM START TO FINISH Dredge Yard
More informationEnergy Plan. Public Forum Presentation January 25, 2011
Energy Plan Public Forum Presentation January 25, 2011 Today s Methods 2 Where is Electricity Required? Today 17% 65% 18% 3 Bermuda s Demand Profile & Peaks 2010 140 Winter Summer 120 100 shift Demand
More informationLink LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion
Project Number SYS-LRT Subareas All Primary Mode Impacted Link Facility Type Link Service Version Number 4.0 Date Last Modified 7/24/2008 Project Locator Map Short Project Description Construct new light
More informationNational Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )
National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) Presenter: National Treasury 18 November 2015 90 day Action Plan In November 2014, the Ministers
More informationThe oil fields in the NCS are located in the North Sea, Norwegian Sea, and Barents Sea.
A.2 Norway Volumes of Associated Gas Flared on Norwegian Continental Shelf Norway is a major oil producer, and its oil fields are located offshore in the Norwegian Continental Shelf (NCS). 81 In 2002,
More informationLIST OF OPEN TRAINING TRAINING PLANNER 2016/2017 Course location: Lagos, Abuja, Port Harcourt.
JANUARY 2016 Credit Management and Collection of 4-6 11-15 14-27 Abuja/Lagos/PH 150,000 220,000 320,000 Receivables Developing Executive Management 4-6 11-15 14-27 Abuja/Lagos/PH 150,000 220,000 320,000
More informationSpare Parts, Instruction and Maintenance Manual for SPANCO Model 301 Jib Cranes
Manual No. 103-0007 REV. 6/10 Spare Parts, Instruction and Maintenance Manual for SPANCO Model 301 Jib Cranes ISO 9001 REGISTERED SPANCO, Inc. 2 TABLE OF CONTENTS Forward... 4 Installation... 4-6 Maintenance...
More informationNYISO Tariffs. New York Independent System Operator, Inc. Document Generated On: 2/27/2013
NYISO Tariffs New York Independent System Operator, Inc. NYISO Tariffs Document Generated On: 2/27/2013 Contents 15 ISO Market Administration and Control Area Service Tariff Rate Schedules... 8 15.1 Rate
More informationSan Joaquin Valley Air Pollution Control District Governing Board Meeting. June 15, 2017
San Joaquin Valley Air Pollution Control District Governing Board Meeting June 15, 2017 May 2015, Board approved comprehensive action plan for securing the Valley s fair share of Cap and Trade funds 20
More informationCity of Beverly Hills North Santa Monica Blvd Reconstruction. Traffic & Parking Commission June 04, 2015
City of Beverly Hills North Santa Monica Blvd Reconstruction Traffic & Parking Commission June 04, 2015 1 Overview of June 4 TPC Overview of Possible Traffic Mitigation Measures Toolbox During Construction
More informationFebruary 28, Maximizing Maintenance Dollars in a Post-PTC World
February 28, 2018 Maximizing Maintenance Dollars in a Post-PTC World What we ll discuss today Why the evolving market demands a preventative maintenance approach Key elements of a best-in-class preventative
More informationPLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION
PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Department of Public Works (DPW) to award DPW Contract
More informationP2000 RAIL CAR AUXILIARY INVERTERS
031160722012000 REGULAR BOARD MEETING DECEMBER 4, 2003 Metropolitan Transportation Authority SUBJECT: ACTION: P2000 RAIL CAR AUXILIARY INVERTERS AWARD CONTRACT FOR AUXlLARY INVERTERS One Gateway Plaza
More informationFTA Low Speed Magnetic Levitation Program
U.S. DEPARTMENT OF FTA Low Speed Magnetic Levitation Program Fourth Plenary Meeting U.S. - Republic of Korea Transportation Experts January 26 Walter Kulyk, P. E. Federal Transit Administration U.S. Department
More informationLETTER THE BARNHART S KEY TO FIT ANY LOCK PAGE 3. A Mountain Top Experience Page 2. Barnhart s Modular Lift Tower In The Motor City Page 2
A Mountain Top Experience Page 2 Barnhart s Modular Lift Tower In The Motor City Page 2 THE LIFTING LETTER 2 0 0 4 T H I R D E D I T I O N A P U B L I C A T I O N O F B A R N H A R T Barnhart s Key To
More informationChelan County PUD 2017 Adopted Budget ($000)
Chelan County PUD 2017 Adopted ($000) Combined District Integrated Electric Fiber & Telecom Water Wastewater Eliminations Service Revenue 63,168 50,258 9,114 5,894 668 (2,766) EP&T Net Wholesale 114,138
More informationOverview of S.L Competitive Energy Solutions for North Carolina
Overview of S.L. 2017-192 Competitive Energy Solutions for North Carolina JENNIFER MCGINNIS CHRIS SAUNDERS STAFF AT TORNEYS, LEGISLATIVE ANALYSIS DIVISION 1 Overview Product of extensive stakeholder process
More informationProtecting the oil & gas industry for more than half a century!
Protecting the oil & gas industry for more than half a century! your reliable partner in achieving a successful corrosion prevention strategy. Why do you need a partner in strategically preventing corrosion?
More informationv Deborah Flint - Chief ecutive e, ficer
Date 6/30/2017 6/30/2017: 6/26/2017: Approval EY MY By RW AE MT BY...jil 0.'1 1 Los Angeles World Airports REPORT TO THE B A - e OF AIRPORT COMMISSIONERS Meeting Date:, A irdro, /. Approved : aiph -,...
More informationPROJECT MANAGEMENT OVERSIGHT
June 2017 PROJECT MANAGEMENT OVERSIGHT Prepared by the Department of Finance, Innovation & Technology Executive Summary This semi-annual Report on Project Management Oversight details Service Board efforts
More informationHoists & Rigging Products for Construction Projects
Manual Hoists Have a special application? Our full line of material handling products allows us to create complete solutions rather than just offering single products. Now you have one point of contact
More informationWINNIPEG HYDRO QUICK FACTS
THE OFFER Manitoba Hydro makes the following payments and commitments: Years 1-5 $25 million per annum 6 9 $20 million per annum 10 TH in perpetuity $16 million per annum PLUS $1 million per annum in services*
More informationSenior Substation Project Lead Engineer
Senior Substation Project Lead Engineer Are you ready to be a technology pioneer? Oil and gas factories 3000 meters underwater, heavy locomotive traction motors, electric vehicle chargers that deliver
More informationRichard Herrmann, et ux. Rezoning from F-District Farming to F-1 District Rural Residential
Richard Herrmann, et ux Rezoning from F-District Farming to F-1 District Rural Residential Richard Herrmann, et ux Staff recommended Findings of Fact: 1. The intensity and current residential use of
More informationProjects in Belarus. Maxim Zubov. Siemens Belarus. Date
Projects in Belarus Maxim Zubov Date 21.05.2013 Siemens Belarus Power Generation in Belarus made by Siemens Gas Turbine installed Steam Turbine installed Gas Turbine under Construction Installed / Under
More informationunrivalled benefits In the 20-40MW range take a closer look at the EPICYCLIC ADVANTAGE
unrivalled benefits In the 20-40MW range take a closer look at the EPICYCLIC ADVANTAGE Allen Gears is the world leader in the production of epicyclic gearboxes for generator drive applications, supplying
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationINVITATION TO BID FUEL PRODUCTS
INVITATION TO BID FUEL PRODUCTS Notice is hereby given that the Aberdeen School District is accepting fuel bids and propane bids for the following: 1. Regular, unleaded and diesel fuels for district buses
More informationENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO
ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO Cam Carver CEO, Temporal Power Ltd. Corporate Overview Temporal Power, a Ontario based company, is a global leader in the development
More informationEnergy Storage Summit
Victoria Plaza London, UK 28 th February 1 st March 1 1 #storagesummit Energy Storage Summit February 28 th 1 st March Victoria Plaza London storage.solarenergyevents.com/ 2 2 WEST BURTON 49MW BATTERY
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationContract No: OASRTRS-14-H-MST (Missouri University of Science and Technology)
Smart Rock Technology for Real-time Monitoring of Bridge Scour and Riprap Effectiveness Design Guidelines and Visualization Tools (Progress Report No. 7) Contract No: OASRTRS-14-H-MST (Missouri University
More informationLow and medium voltage service. Power Care Customer Support Agreements
Low and medium voltage service Power Care Customer Support Agreements Power Care Power Care is the best, most convenient and guaranteed way of ensuring electrification system availability and reliability.
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationWorker Crushed by Vessel Date of Incident: August 3, 2007 Type of Incident: Fatal
Worker Crushed by Vessel Date of Incident: August 3, 2007 Type of Incident: Fatal TABLE OF CONTENTS SECTION TITLE PAGE 1.0 DATE AND TIME OF INCIDENT 4 2.0 NAME & ADDRESS OF PRINCIPAL PARTIES 4 2.1 Employer
More informationREQUEST FOR PROPOSAL TRUCK DRIVER TRAINING TRACTOR AND TRAILER LEASING FOR ILLINOIS VALLEY COMMUNITY COLLEGE PROPOSAL # RFP2016-P02
REQUEST FOR PROPOSAL TRUCK DRIVER TRAINING TRACTOR AND TRAILER LEASING FOR ILLINOIS VALLEY COMMUNITY COLLEGE PROPOSAL # RFP2016-P02 The Board of Trustees of Illinois Valley Community College (IVCC) District
More informationPower Purchase and Grid Connection Procedures
Building Your Biogas System Workshop and Grid Connection Procedures Aidan Foss. amfoss@ieee.org ANF Energy Solutions DG grid connection specialists No project ownership Current projects Biogas 21 Landfill
More informationCommunity Choice Aggregation A Tool for Municipalities
Community Choice Aggregation A Tool for Municipalities About The Solar Foundation Founded in 1977 and based in Washington, DC, The Solar Foundation is an independent nonprofit working to demonstrate the
More information