PROJECT MANAGEMENT OVERSIGHT

Size: px
Start display at page:

Download "PROJECT MANAGEMENT OVERSIGHT"

Transcription

1 June 2017 PROJECT MANAGEMENT OVERSIGHT Prepared by the Department of Finance, Innovation & Technology

2 Executive Summary This semi-annual Report on Project Management Oversight details Service Board efforts in implementing their capital programs. Included are details on all state-funded projects, regardless of budget, and all systemwide projects with budgets of $10 million or more, regardless of funding source. Information in this report was collected by direct interviews, project meetings, and documented submissions from Service Board project management teams. The State of Good Repair backlog for the region currently stands at $19.4 billion, and the 10- year capital need for normal reinvestment is $18.3 billion, which results in total 10-year capital need of $37.7 billion. The 51 projects detailed in this report together represent $3,546,443,875 worth of construction, maintenance, and procurement. Many of these projects will address outstanding capital needs, while others are directed to compliance with federal requirements or enhancing customer experience, safety, and security. Uncertainty of state funding continues to affect the capital program, and while all projects are within budget, only 48% of the state funded projects are on schedule. As part of the revisions to the State Bond program requested by IDOT, some of these projects will proceed with a delay and some of them will be deferred until other funding sources are identified. If these funding delays were not considered, 95% of the projects would be on schedule. Regarding change orders, some of the added budget came from decisions by the Service Boards to add value to projects or comply with federal requirements. The remaining change orders were mostly for unforeseen conditions, and a minimal amount was due to errors and omissions. Although the progress being made on these projects is significant, current capital funding will not support much needed renewal of the region s aging transit infrastructure. Deferring infrastructure maintenance and replacement has negative impacts on the quality of service provided, including deteriorating service reliability. RTA, in accordance with the Strategic Plan, is committed to seeking stable, long-term capital funding solutions critical to renewing and maintaining the region s transit system. RTA and the Service Boards must collectively work to educate the public on the region s transit needs and advocate for funding. RTA recognizes the commitment, collaboration, cooperation, and level of effort each Service Board provided for the Report on Project Management Oversight to be a success. RTA is appreciative and pleased to note the exemplary and ongoing commitment of transit agency personnel during this process. RTA will continue to work with the CTA, Metra, and Pace to advocate for more capital funding at both the state and federal level to ensure our transit system continues to prioritize and work towards a State of Good Repair.

3 Table of Contents Section I State-Funded Projects...1 Project List...2 CTA...3 Metra...15 Pace...21 Budget Performance...26 Schedule Performance...27 Change Orders...31 Section II Systemwide Projects over $10,000, Systemwide...35 CTA...42 Metra...54 Pace...67

4 Section I State-Funded Projects 1

5 Systemwide STATE-FUNDED PROJECTS SERVICE BOARD PROJECT TITLE BUDGET CTA Wilson Transfer Station $169,959,391 CTA 95 th Street Terminal Improvements $85,451,332 CTA Perform Rail Car Overhaul (3200 Series) $53,132,149 CTA O Hare Blue Line Station Improvements Addison to Cumberland $37,334,803 CTA North Red Line Stations Sheridan $24,000,000 CTA Jefferson Park Intermodal Facility Renovations $15,236,957 CTA Rail Shop Roofs and Bus Washer Replacements $13,457,053 CTA 98th Shop Replace Hoist and Spin Jacks $7,325,000 CTA 74th, 98th, and Midway Shops Tuckpointing $1,930,340 CTA Dearborn Subway Station Improvements Grand, Chicago, and Division $1,028,240 Metra Positive Train Control System Integrator $85,000,000 Metra Union Pacific West Line Expansion $44,500,000 Metra Auburn Park New Station Rock Island District $21,500,000 Metra Healy Station Milwaukee District North Line $7,167,498 Metra Hazel Crest Station Metra Electric District $5,000,000 Metra Peterson Ridge New Station UPR North Line $5,000,000 Pace Purchase 40 Compressed Natural Gas Buses $49,000,000 Pace Purchase 40 Fixed Route Buses $7,891,804 Pace Purchase Approximately 84 Paratransit Vehicles $7,290,500 Pace Construct Toyota Park Transportation Center $2,000,000 Pace Bus Stop Improvements Joliet Multi-Modal Transportation Center $1,709,500 Note: Amounts shown represent only the IDOT/RTA-funded portions of overall project budgets. 2

6 Wilson Transfer Station Description: Replace the Wilson Street Station and elevated track structure from Montrose Avenue to Leland Avenue with a four track station and platforms between the express and local tracks. The elevated track structure between Sunnyside Avenue on the south to Leland Avenue on the north will be replaced with steel columns and concrete track bed. The elevated track structure over Broadway Street will be full span, eliminating piers in the street right-of-way. The architectural facades of historic buildings will be preserved. Status: Construction of Phase 5 commenced. Trains were cutover from existing Track 4, which facilitated demolition of Track 4 track structures. Drilled shafts and building foundations were installed and infrastructure is being constructed for Track 4 and the east half of the station. Budget: Project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $169,959,391 $166,592,364 $116,232,750 68% Overall Project Total $206,070,539 $184,221,551 $131,366,950 64% Schedule: The project is on schedule. To complete the three-track operation, northbound trains were cutover from the east track. Milestone Baseline Schedule Actual (A) / Forecast Advertise for Proposals March 2014 March 2014 A Environmental Clearance April 2013 June 2014 A Notice to Proceed July 2014 July 2014 A Start Three-Track Operations March 2015 March 2015 A End Three-Track Operations March 2017 March 2017A Substantial Completion January 2018 January 2018 *Obligated and Expended amounts as of March

7 Wilson Transfer Station (continued) Highlights: The $206 million dollar project will be one of the largest elevated track projects performed by CTA: Covered platforms will be provided on all tracks. Commuters will have access between Purple Line express trains and Red Line local trains. Concrete constructed track beds will reduce noise. Station access will be provided to persons with disabilities in accordance with ADA. Both sides of Wilson Avenue will have station entrances. Sunnyside Avenue will have a station entrance for the first time. Broadway Street will be clear of elevated track structure columns. Terracotta facades of the Gerber Building and Majestic Menswear will be restored. Transit Oriented Development is being pursued for the Gerber Building. Construction Phase 5 includes Track 4 reconstruction and ongoing station and building work: Revenue train service was switched onto Track 3. Existing trackwork and elevated track structure was demolished. Track structure caissons were drilled. Track structure footings are being constructed. Steel track structure east of station platforms is being erected and to be painted. Track decks and trackwork are to be installed. The east station structures and the vehicle storage building are being constructed. The east station platform is to be constructed. The Gerber Building reconstruction work continues. The ADA ramp is being constructed at the Sunnyside Auxiliary entrance. Casting of Building Foundations Construction of Drilled Shafts *Obligated and Expended amounts as of March

8 Rail Car Overhaul and Mid-Life Rehabilitation Description: A programmed rail car overhaul program will provide for renewal of truck, propulsion, and other subsystem equipment on rail cars in the CTA 2600-Series and 3200-Series rail car fleets to maintain a state of good repair. CTA is also retrofitting the 3200 Series cars with new air conditioning units, auxiliary power supply, destination signs, LED lighting, and security cameras. Status: Skokie Shop has completed all 100 cars in the 2600 Series cars project. The 3200 Series project covers 257 cars. The component rebuild, car overhaul work, and equipment installation is being done by CTA Skokie Shop staff. To date, 134 of the 257 cars have undergone the overhaul and returned to revenue service. There has been an increase in the scope of repairs based on car condition observed during the program. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $53,182,149 $53,173,729 $39,274,887 74% Overall Project Total $180,491,856 $156,976,350 $116,999,394 65% Schedule: For the 3200 Series cars, parts kits were first received in March The Yellow Line closure disrupted and delayed the project about 12 months. To mitigate this delay and maintain continuous employment of the staff assigned to this project, CTA assigned some staff to work in the maintenance shops to get an early start on some modifications. Reliability issues with some subsystems have impacted production but solutions have been developed and production is returning to the expected rate of 8 cars per month. However, the effect of delays has caused the completion date, based on this production rate, to be 21 months delayed. Milestone Baseline Schedule Actual (A) / Forecast Complete Series Cars December 2014 June 2015 A First 3200-Series Kits Received March 2015 March 2015 A Complete Series Cars July 2017 March 2019 *Obligated and Expended amounts as of March

9 Rail Car Overhaul and Mid-Life Rehabilitation (continued) Highlights: In addition to the purchase of new rail cars, CTA has embarked on an aggressive rail car overhaul program to restore these cars to a state of good repair. Performing overhauls as scheduled reduces unscheduled maintenance, improves reliability, and preserves comfort and ride quality. Many underfloor components will not require overhaul for another 12 to 15 years. A Quality Assurance process is in place both at the Contractor and at CTA for this project. CTA s innovative use of an outside contractor to provide kitted material has reduced the workload on CTA Procurement and Materials Management and has avoided mixing program material with CTA spare parts. All material was procured from CTA pre-approved vendors. For the 3200 Series project, CTA is modernizing subsystems to increase reliability and security including: Air Conditioning System o New Air Conditioning Unit o New AC Controller Propulsion System o Rebuilt Cam Control Group o New Resistor Bank Trucks o New Wheels o Rebuilt Motors, new Armatures Interiors o New LED Lighting o End Door Floor Panels o New Ribbed Flooring Doors o New Door Motors o New Door Hangers o New Thresholds Cab o Rebuilt Master Controller o Rebuilt Hydraulic Pressure Control Auxiliary Power Supply Systems o Security Cameras o Programmable Message Signs o LED Side and End Signs o Digital Route Number Signs CTA has found that they needed to increase the scope of the floor renewal and is renewing most of the ribbed flooring on the car in addition to floor panels near the end doors. CTA needed to rebid the replacement air-conditioning units and controls. Notice to proceed was given in September Prototype units were received in September 2016 and the first production units arrived in November The delay in receiving new air-conditioning units has necessitated returning 100 cars to Skokie Shop to complete the installation of that system and its controls. CTA is using some contingency in this project to apply new resistor banks to 80 additional 2600-Series cars that had not received new components on a previous overhaul program. An issue discovered recently with deterioration of some undercar wiring has caused renewal of that wiring to be added to the scope of work and a modification to be made to the Auxiliary Power Supply. *Obligated and Expended amounts as of March

10 95th Street Terminal Improvements Description: This project will expand and greatly improve the 95th/Dan Ryan Red Line station as well as its bus terminal with a new stationhouse comprising north and south bus terminal facilities for the 14 CTA and 5 Pace bus routes that serve the station, in addition to improved pedestrian access. Status: The main terminal design-build contract has continued design, bid and construction activities. The north terminal design is being advanced. Award of construction work orders and south terminal construction activities are on-going. The south terminal foundations are constructed. Track adjacent to the south terminal is being reconstructed. The retaining wall advance package contract is being closed out. Negotiations for land acquisitions continued. The closing for the final 2 of 8 total parcels remains on-target for this year. Budget: The project is on budget. Budget Obligated * Expended * Expended % State-Funded Budget $90,000,000 $22,035,149 $14,082,517 16% Overall Project Total $280,000,000 $119,461,027 $87,354,973 31% Schedule: Project schedule updates continue to show construction of the south terminal to be behind schedule and project completion on schedule. Milestone Baseline Schedule Actual (A) / Forecast Prime Contract Award March 2015 December 2015 A Complete Construction Phase 1 September 2017 January 2018 Substantial Completion December 2018 December 2018 Highlights: The terminal design features improvements in safety and amenities for CTA and Pace customers: Pedestrian overpass bridge between terminals to avoid the need for street level crossings. Wider bus lanes and increased spacing between bus bays for upgraded traffic flow. Expanded platforms and wider sidewalks to ease passenger congestion. Bright, airy and glass enclosed station for clear sightlines in a comfortable space. Additional escalators, elevators and pay area space for reduced wait times. Sound panels at platform level to provide noise mitigation. * Obligated and Expended amounts as of March

11 O Hare Blue Line Station Improvements Addison to Cumberland Description: The scope of work included rehabilitation of the stations at Addison, Irving Park, Montrose, Harlem, and Cumberland to improve access, safety and convenience. At the station houses, the existing damaged curtainwall was replaced. At the platforms, the existing canopies were renewed and sections of the damaged platform edge were repaired. An elevator was added at Addison Station. Status: The construction contract is being closed out. Punch list work was performed at all stations. Record documents, operating manuals and warranties were submitted. A final project observation was coordinated among IDOT, RTA and CTA and has been performed. This is the final report on this project. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $37,334,803 $30,931,325 $26,898,266 72% Overall Project Total $43,000,000 $36,607,147 $32,021,010 74% Schedule: A time extension was approved. The project was completed on schedule considering this time extension. Milestone Baseline Schedule Actual (A) / Forecast Design-Build Notice to Proceed April 2015 April 2015 A Construction Start October 2015 October 2015 A Substantial Completion October 2016 November 2016A Highlights: This project is part of a larger capital improvement program known as Your New Blue for the O Hare Blue Line. The program includes track and station renewal and has an estimated overall budget of $492 million: Upgraded lighting, security cameras and platforms for safer stations. Track rehabilitation to provide faster service between downtown and O Hare airport. Additional elevators for more accessible stations. Preserved historic features to maintain the architectural character of the stations. Enhanced entrances, deep cleans and new public artwork for a better customer experience. *Obligated and Expended amounts as of March

12 North Red Line Stations Sheridan Description: Improvements will be made to Sheridan Station and adjacent track structure to provide safe and dry conditions and aesthetic improvements. Various components will be renewed, including lighting, roofs and canopies, platform decking, painting, and accessibility features. Status: CTA Structure Maintenance forces are continuing with the structure renewal work, which is part of the project scope. CTA in-house forces are replacing 162 track and platform stringers, 11 cross girders, 18 platform canopy channels, 4 platform structural sections, and other various secondary structural components. Phase 4 of the structure renewal work has started in March This work is being coordinated with Wilson Transfer Station for track access. Due to changes in the availability of state funding, only the structure renewal work will be completed. Improvements to the station are deferred. Budget: The project is on budget. Most expenditures are for CTA force account work. Budget Obligated* Expended* Expended % Project Total $24,000,000 $10,282,617 $9,571,333 40% Schedule: The project is on schedule for the structure renewal work. Milestones have been modified to coordinate with the Red and Purple Modernization and Wilson Transfer Station. Milestone Baseline Schedule Actual (A) / Forecast Started Structure Renewal July 2015 July 2015 A Structure Renewal Completion December 2017 December 2017 Highlights: Sheridan is one of the oldest stations in the CTA system and is exhibiting signs of deterioration, having reached the end of its useful life. The station structure was built in the 1920s. Historic preservation measures are being taken to maintain the stationhouse façade. *Obligated and Expended amounts as of March

13 Jefferson Park Intermodal Facility Renovations Description: The proposed scope of work includes improvements at the bus turnaround, station and platform. Bus turnaround improvements include new paving, new lighting, replacement of the existing entry canopy with a new canopy to improve access both the Metra and CTA stations, and public art. Station improvements include replacement of the curtain wall, repainting the stationhouse exterior, and rehabilitation of lighting, escalators and stairs. Platform improvements include the replacement of the canopy skylight system, replacement of lighting, and repairing and refinishing of surfaces. Status: The procurement for this project was combined with the Belmont Gateway Project. The Project Master Plan and bridging documents for procurement of a design-build contractor were developed and finalized. An invitation for bids has been advertised on May 1, Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $15,236,957 $1,459,567 $145,275 1% Overall Project Total $25,000,000 $1,459,567 $145,275 1% Schedule: The project is on schedule. Milestones have been revised for inclusion of the Belmont Gateway Project and to coordinate with other projects in the Your New Blue program. Milestone Baseline Schedule Revised Baseline Schedule Actual (A) / Forecast Design-Build Notice to Proceed April 2017 September 2017 September 2017 Design Complete November 2017 February 2018 February 2018 Complete Station Work -- November 2018 November 2018 Substantial Completion December 2018 May 2019 May 2019 Highlights: This project is part of a larger capital improvement program known as Your New Blue for the O Hare Blue Line, which includes additional projects involving track and station renewal. The estimated overall budget for the entire program is $492 million. Jefferson Park is a multi-modal station that provides a vital link between CTA rail, CTA bus, Metra, and Pace. * Obligated and Expended amounts as of March

14 Rail Shop Roofs and Washer Replacements Description: This project will provide for improvements at the Green Line Harlem Rail Shop and Blue Line Des Plaines Rail Shop, and 77th Bus Garage. The roofing component will replace existing roofs at Harlem and Des Plaines Shops. Washer upgrades will be at 77 th Garage with existing bus washer replacements and at Harlem Shop with a new exterior rail car washer. Status: The roof replacements are complete. Bids for construction services were solicited for the bus washer replacements. State funds will no longer be used for the bus washer replacements. The design for the rail car washer at Harlem Shop is being advanced from 60% to 90% and further developed for inclusion of yard trackwork improvements. Due to changes in the availability of state funding, other funding sources will need to be identified for the construction of the rail washer. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $13,457,053 $4,859,892 $1,643,572 12% Overall Project Total $32,523,142 $8,432,568 $4,809,943 15% Schedule: The project is on schedule and has phases for the 3 elements being replaced: roofs, bus washers and rail washers. Milestone Baseline Schedule Actual (A) / Forecast Roof Replacement Start June 2015 June 2015 A Roof Replacement Complete June 2016 June 2016 A Bus Washer Replacement Start March 2017 March 2017 Bus Washer Replacement Complete October 2017 October 2017 Rail Washer Design Complete May 2018 May 2018 Highlights: The existing roofs at the Harlem and Des Plaines Shops are approaching the end of their useful lives, both having been installed when the rail shops were first opened. Harlem Shop was constructed in 1965 and Des Plaines Shop was constructed in At 77th Garage, only one of the two bus washers is currently functional, putting a strain on the servicers at this facility to perform their duties on a daily basis. Rail car washers at Harlem Shop are located exterior to the rail shop and are in poor condition, with much of their structures coated in rust. *Obligated and Expended amounts as of March

15 98th Shop Replace Hoist and Spin Jacks Description: CTA will replace the existing carriage hoists, spin posts, body hoists, turntables, and associated controls on two tracks, each of which can accommodate up to two cars at a time. This equipment is used to elevate and support rail cars during standard and special maintenance procedures. Status: Fabrication and assembly of equipment continued. The equipment was primed, painted, tested and prepared for shipping. Field activities consisted of shop electric relocation and selective demolition. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $7,325,000 $6,935,011 $3,189,003 44% Overall Project Total $8,535,000 $8,116,546 $3,891,860 46% Schedule: The project is on schedule. Early site access and updated work activity relationships resulted in an earlier forecasted substantial completion date/ Milestone Baseline Schedule Actual (A) / Forecast Work Order Award April 2015 April 2015 A Construction Start April 2016 April 2016 A Substantial Completion August 2017 July 2017 Highlights: The equipment at 98th Shop was installed when the shop was opened in 1967, is considerably past its useful life, and has become difficult for CTA to maintain and repair. Replacing this equipment will not only improve reliability, but will also provide flexibility, as both tracks used to service rail cars will have the same equipment after the project is completed. * Obligated and Expended amounts as of March

16 74th, 98th, and Midway Shops Tuckpointing Description: CTA will replace the mortar and sealant joints at the exterior masonry or precast. Additionally, repairs to the building caused by sealant degradation will be included. Key areas of concern are at the junctions of precast panels, dissimilar materials (e.g., masonry and steel), and at wall openings, such as windows and doors. Status: Repair work at 98th Shop started in May 2015, was substantially complete in September 2015 and has been closed out. Another funding source was secured for a more comprehensive building envelope repair design. Design documents for Midway Shop and 74th Garage were updated and have been approved. At the request of the Illinois Department of Transportation, CTA has prioritized projects and is in the process of revising their State Bond program. With the revision of the State Bond program, other funding sources will need to be identified for the construction phase of this project. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $1,930,340 $383,198 $118,343 6% Overall Project Total $3,046,746 $731,160 $383,331 13% Schedule: The project is behind schedule. The construction phase is on hold until other funding sources are identified. Milestone Baseline Schedule Actual (A) / Forecast 98th Shop Work Complete May 2015 May 2015 A Midway and 74th Design Complete May 2016 May 2016 A Highlights: 74th Garage and Midway Rail Shop were constructed in 1993, and 98th Rail Shop was constructed in Replacement of the existing mortar and sealant joints is needed to avoid continued damage to the exterior construction, which would eventually migrate into the interior of the buildings. *Obligated and Expended amounts as of March

17 Dearborn Subway Station Improvements Grand, Chicago, and Division Description: The proposed work includes improvements at the street, mezzanine, and platform levels. At the street level, new entry canopies will be installed at each stair opening with repairs to the stairs, new glazed tile walls, new lighting and repainted ceilings. At the mezzanine level, improvements include new finishes, lighting, and exit roto-gates. At the platform level, improvements include new finishes, lighting, and furniture. Additional scope may include repairs to the elevators and stairs between the mezzanine and platform levels. Status: The project is in the later stages of planning and coordination with other projects in the Your New Blue program. Site visits were conducted to verify scope of work. The Project Master Plan was finalized in October Documents are in preparation for solicitation of a design-build contractor. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $1,028,240 $961,099 $324,508 32% Overall Project Total $39,000,000 $1,154,454 $357,751 1% Schedule: CTA plans to advertise this project for bids in the fall of this year. The scheduling for this project needs to be coordinated with other Your New Blue projects for track access time. Milestone dates will be developed once the project is further along in the procurement planning process. Highlights: The Dearborn Subway opened in 1951, and these stations are in need of upgrades and improvements to improve operations and customer experience. This project is part of a larger capital improvement program known as Your New Blue for the O Hare Blue Line, which includes additional projects involving track and station renewal. The estimated overall budget for the entire program is $492 million. *Obligated and Expended amounts as of March

18 Positive Train Control System Integrator Description: The Positive Train Control (PTC) system is comprised of wayside, onboard, and central equipment, including signals, GPS, computer hardware and software, and various other communications components. The system integrator functions to combine these components through design, testing, and implementation. Status: System integrator planning and work activities to support PTC implementation continued. Hardware installation and configuration and software configuration is on-going. Station signal strength testing was performed to confirm the limits for track mapping using GPS. Training for PTC mechanical was performed. Locomotives and cab car types antenna testing was completed. Budget: The project is on budget. The state-funded budget amount dedicated to the System Integrator is currently $85,000,000. Including additional federal and local funding, the overall funded budget for PTC is $280,983,346; however, the final cost for PTC is expected to reach over $350 million. Metra continues to seek additional funding to complete the required scope. Budget Obligated* Expended* Expended % State-Funded Budget $85,000,000 $83,589,355 $20,406,777 24% Overall Project Total $280,983,346 $233,772,918 $132,363,914 47% Schedule: The project is on schedule. The federally-mandated revised implementation plan allowed for a time extension. Milestone Baseline Schedule Actual (A) /Forecast Contract Award August 2015 August 2015 A Begin Implementation August 2015 August 2015 A Subdivision Commissioned --- December 2018** Substantial Completion December 2018 September 2020** Highlights: There are 4 core elements of the PTC system: Prevent train-to-train collisions. Stop over speed derailments Inhibit movement of a train through a switch left in the wrong position. Block unauthorized incursion into roadway work zones. * Obligated and Expended amounts as of March ** Assumes full funding availability. 15

19 Union Pacific West Line Expansion Description: This project is part of a public-private partnership between Metra and the Union Pacific Railroad to construct a new third main line track. The segments funded under this project are located between mileposts 10.0 and 11.8 in Maywood and Melrose Park and between mileposts 32.1 and 38.4 in West Chicago and Geneva. Status: The project design and environmental work have been completed. Construction cost estimates for both segments, including land acquisition, have been prepared. As part of the latest revisions to the State Bond program the construction of the third main line track is moving forward. An Invitation for bids was issued for the east portion of the track and the bids are currently being evaluated by Union Pacific. Budget: The project is on budget. RTA/IDOT funding will provide for portions of the project design, environmental study, land acquisition, and construction. Including additional federal and local funding, as well as other components of the UP West Line Expansion, the total overall budget is $198,129,013. Metra and the Union Pacific Railroad are sharing these costs. Budget Obligated* Expended* Expended % State-Funded Budget $44,500,000 $1,375,858 $1,265,972 3% Overall Project Total $198,129,013 $138,674,208 $134,199,481 68% Schedule: Uncertainty of state capital funding has delayed this project. As part of the latest revisions to the State Bond program the construction of the third main line track is moving forward. Milestone Baseline Schedule Actual (A) /Forecast Design Completion March 2016 March 2016 A Notice to Proceed July 2016 July 2017 Substantial Completion December 2018 December 2019 Highlights: The addition of a third main line track will eliminate key bottlenecks and allow Metra to add more service, including more express trains, on the line. The potential for freight interference will also be mitigated. The expanded parking deck in Geneva and the new pedestrian underpass in Lombard were completed through separate projects as part of the overall Union Pacific West Line program. *Obligated and Expended amounts as of March

20 Auburn Park New Station Description: The Auburn Park Station will be a new station stop on the Rock Island District in the City of Chicago. The scope includes a center platform with canopy, a landscaped area at 79th Street and Lowe Avenue featuring an ADA ramp to the stationhouse, and elevator access to the platform. A small parking lot will also be constructed. The scope was enhanced after additional state funding was provided. Status: Due to changes in the availability of state funding, State Bond funds will be de-obligated from this project. This project has been deferred. Budget: The State Bond funds will be de-obligated to other projects. Budget Obligated* Expended* Expended % Project Total $21,500,000 $1,212,495 $1,212,495 6% Schedule: Due to changes in the availability of state bond funding the construction phase of this project has been deferred. Milestone Baseline Schedule Actual (A) /Forecast Design Completion January 2014 September 2016 Highlights: This project will bring a new station on the Rock Island District to the Auburn Park neighborhood in Chicago and is expected to increase transit accessibility and ridership in the community area. The station will also allow for connections to CTA buses on 79th Street. *Obligated and Expended amounts as of March

21 Healy Station Description: This project includes the elimination of the existing at-grade railway crosswalk, rehabilitation of inbound platform access and shelter facilities, construction of a new ADA-compliant ramp to the outbound platform, and rehabilitation of the outbound shelter. Status: The design has been completed. The bids were advertised and a contractor was selected. The contract award was delayed due to uncertainty of state funding. As part of the latest revisions to the State Bond program this project is moving forward. The construction contract was awarded, the NTP was issued and a ground breaking took place on May 8, Budget: The project is on budget. Budget Obligated* Expended* Expended % Project Total $7,167,498 $7,167,498 $448,942 6% Schedule: Uncertainty of state capital funding has delayed this project. As part of the latest revisions to the State Bond program this project is moving forward. Milestone Baseline Schedule Actual (A) / Forecast Design Completion May 2012 March 2013 A Substantial Completion December 2016 December 2018 Highlights: The project scope also includes relocation of the outbound shelter and stairs which will provide greater street visibility. Removal of pedestrian crossing and providing ramps will increase safety at this station. *Obligated and Expended amounts as of March

22 Hazel Crest Station Description: The project scope includes the rehabilitation of the station and entrances, and the addition of an elevator. The project will raise the depot, currently at street-level, to allow space for vendors and restrooms at street level. Metra s State Bond funding will not be applied to the new vendor spaces, however, design will allow for such improvements by the City of Hazel Crest in the future. Status: Design and final drawings are complete. As part of the latest revisions to the State Bond program this project is moving forward. Metra issued an Invitation for Bids and the bids were received and evaluated by Metra. The pre-award concurrence for construction is under review by RTA and IDOT. Budget: The project is on budget. Budget Obligated* Expended* Expended % Project Total $5,000,000 $277,789 $277,789 6% Schedule: Uncertainty of state capital funding has delayed this project. As part of the latest revisions to the State Bond program this project is moving forward. Milestone Baseline Schedule Actual (A) / Forecast Design Completion February 2013 December 2013 A Notice to Proceed April 2015 June 2017 Substantial Completion March 2016 June 2018 Highlights: Design for this station was completed under budget. *Obligated and Expended amounts as of March

23 Peterson Ridge New Station Description: Construct a new station on the Union Pacific North Line at Peterson Avenue and Ridge Avenue in the City of Chicago, including two 6-8 car platforms, lighting, ramps, sheltered warming facilities, stairs, ADA ramps, ADA parking, kiss-n-ride, and parking spaces. Status: Due to changes in the availability of state funding, State Bond funds will be de-obligated from this project. This project has been deferred. Budget: The State Bond funds will be de-obligated to other projects. Budget Obligated* Expended* Expended % State-Funded Budget $5,000,000 $0 $0 0% Overall Project Total $15,000,000 $1,121,863 $1,107,287 7% Schedule: Due to changes in the availability of state bond funding the construction phase of this project has been deferred. Milestone Baseline Schedule Actual (A) / Forecast Design Completion June 2015 June 2016 A Highlights: The project scope also includes rehabilitation work on the railroad bridges over Peterson Avenue and Ridge Avenue, extending their useful lives. *Obligated and Expended amounts as of March

24 Purchase 40 Compressed Natural Gas Buses Description: Purchase new 40 Compressed Natural Gas (CNG) buses for fixed route service. The current grant will provide for a minimum of 91 CNG buses. Fueling for these buses will be provided through a retrofit at Pace South Division in Markham, funded through other sources and completed in March Status: Pace awarded a production contract in February The first 20 buses have been delivered and received by Pace. The second order of 28 buses has been placed in August 2016 and these buses have been delivered to Pace on April 25, The third order of the remaining 43 buses is expected to be delivered by December Budget: The project is on budget. Budget Obligated* Expended* Expended % Project Total $49,000,000 $45,421,121 $9,617,190 20% Schedule: Uncertainty of state capital funding has delayed this project as orders have been put on hold after the delivery of the first 20 buses. The project was re-started and a second order of busses was placed in August Milestone Baseline Schedule Actual (A) / Forecast Contract Award February 2015 February 2015 A CNG Retrofit Complete June 2015 March 2016 A 91 Bus Delivery June 2016 December 2017 Highlights: Pace has initiated service out of the South Division for these buses, and long-term operational cost savings are expected. Although initially more expensive to procure, CNG buses have been shown to make up the cost difference prior to the end of their useful lives. *Obligated and Expended amounts as of March

25 Purchase 40 Fixed Route Buses Description: Purchase new 40 Fixed Route Buses. This project is part of a larger bus procurement. State funding was originally allocated to fund 13 of the Fixed Route buses. Pace has reallocated some unused state funds to this grant to purchase an additional 6 buses with state funds. Status: The original 13 Fixed Route Buses funded with state funds have been delivered and placed in service in An order for the additional 6 buses has been placed on December 29, The delivery of this order is expected to begin in July 2017 and continue through January These buses are part of a larger bus order funded with different funding sources. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $7,891,804 $7,878,029 $5,254,058 67% Schedule: This project in on schedule. Milestone Baseline Schedule Actual (A) / Forecast Contract Award January 2012 January 2012 A First Bus Delivery October 2012 October 2012 A 13 Bus Delivery Complete February 2013 February 2013 A 6 Additional Bus Delivery July 2017 July 2017 Highlights: The new buses will replace the existing year old buses to reduce maintenance and increase reliability and comfort, providing cleaner, newer equipment to riders. *Obligated and Expended amounts as of March

26 Purchase Approximately 84 Paratransit Vehicles Description: State funding under this project will provide for the purchase of new 15-passenger paratransit vehicles under an indefinite delivery/indefinite quantity contract, with orders placed as funding becomes available. Status: Pace had planned to award the contract for this purchase after receiving concurrence from RTA and IDOT; however, the project was on hold pending availability of state capital funding. As part of the latest revisions to the State Bond program this project is moving forward. Budget: The project is on budget. Budget Obligated* Expended* Expended % Project Total $7,290,500 $2,176 $2,176 0% Schedule: Uncertainty of state capital funding has delayed this project. Milestone Baseline Schedule Actual (A) /Forecast First Vehicle Delivery November 2015 November 2017 Last Vehicle Delivery May 2016 May 2018 Highlights: Cost savings from previous paratransit vehicle purchases have been reallocated to this project, allowing Pace to purchase more vehicles under the executed indefinite delivery/indefinite quantity contract once the funding becomes available. *Obligated and Expended amounts as of March

27 Toyota Park Transportation Center Description: Construct new bus turnaround and passenger facility near Toyota Park in the Village of Bridgeview. Status: Phase 1, site and underground work, is complete. Phase 2, building and canopy work, was re-bid in early 2015 after initially receiving high bids from a previous solicitation. The 2015 low bid was within estimates, Pace had planned to award a contract in late That award was placed on hold due to unavailability of state capital funding. At the request of the State, Pace has prioritized projects in the State Bond program. With the revision of the State Bond program, this project will be moving forward. Pace is re-reviewing the plans and specifications that were completed in 2015 for code compliance and developing of a schedule for bidding. Budget: The project is on budget. Budget Obligated* Expended* Expended % State-Funded Budget $2,000,000 $1,241,556 $1,241,556 62% Overall Project Total $2,475,000 $1,241,556 $1,241,556 50% Schedule: Uncertainty of state capital funding is delayed this project. The project was initially behind schedule due to additional duration required for multiple re-designs and a subsequent re-bid process. It is now behind schedule due to the state funding delays. With the revised State Bond Program, this project will now move forward. Pace is in the process of developing a bidding schedule. Milestone dates will be provided on the next report. Highlights: State Bond funding is providing for the construction phase only. Design services are funded and managed by the Village of Bridgeview. *Obligated and Expended amounts as of March

28 Bus Stop Improvements Joliet Gateway Center Description: Construct a new bus turnaround facility to serve the nine Pace routes that will connect with the upgraded transportation center in downtown Joliet on the Metra Rock Island District and Heritage Corridor lines, as well as Amtrak routes. Status: The overall Joliet Gateway Terminal project is being managed by the City of Joliet and is behind schedule, but its design is complete and prepared for bid advertisement. The bus stop component remains on hold due to unavailability of state capital funding. Budget: The project is on budget with zero expenditures. Budget Obligated* Expended* Expended % Project Total $1,709,500 $0 $0 0% Schedule: The overall Joliet Gateway Center project is behind schedule, and uncertainty of state capital funding is delaying the bus stop improvement. Milestone dates will be established in coordination with other components of the terminal project if funding becomes available. Highlights: The overall Multi-Modal Transportation Center project is being managed by the City of Joliet. Pace has committed this project budget as pass-through funding to improve the bus turnaround facility. As the project is bid and constructed, Pace will not be responsible for any additional funding, but will realize cost savings if the work is completed under budget. *Obligated and Expended amounts as of March

29 Systemwide STATE FUNDED PROJECTS BUDGET PERFORMANCE STATUS QUANTITY Under Budget 0 On Budget 21 Over Budget 0 PERCENTAGE OF TOTAL PROJECTS 0% Under Budget On Budget Over Budget 100% 26

30 Systemwide STATE FUNDED PROJECTS SCHEDULE PERFORMANCE (WITHOUT STATE FUNDING DELAYS) STATUS QUANTITY Ahead of Schedule 0 On Schedule 20 Behind Schedule 1 PERCENTAGE OF TOTAL PROJECTS 5% Ahead of Schedule On Schedule Behind Schedule 95% Projects Behind Schedule SB PROJECT REASON CTA Rail Car Overhaul Yellow Line closure, increased scope of repairs, reliability issues with some subcomponents 27

31 Systemwide STATE FUNDED PROJECTS SCHEDULE PERFORMANCE (INCLUDING 10 PROJECTS WITH STATE FUNDING DELAYS) STATUS QUANTITY Ahead of Schedule 0 On Schedule 10 Behind Schedule 11 PERCENTAGE OF TOTAL PROJECTS 52% 48% Ahead of Schedule On Schedule Behind Schedule Additional Projects Delayed by Uncertainty of State Funding SB PROJECT CURRENT STATUS CTA 74 th, 98 th, and Midway Shops Tuckpointing Construction is deferred Metra Auburn Park New Station Project is deferred Metra Hazel Crest Station Proceeding with delay Metra Peterson Ridge Station Project is deferred Metra Union Pacific West Line Expansion Proceeding with delay Metra Healy Station Proceeding with delay Pace Purchase CNG Buses Proceeding with delay Pace Purchase Paratransit Vehicles Proceeding with delay Pace Toyota Park Transportation Center Proceeding with delay Pace Joliet Bus Stop Improvements Project on hold 28

32 Systemwide STATUS OF STATE-FUNDED PROJECTS PREVIOUSLY ON HOLD The projects below have previously been reported on hold due to delays in state funding. Since then, the State of Illinois has notified the RTA and the Service Boards that the amount of funding in the State Bond program is being reduced from $2.7B to $2.05B. The Service Boards were asked to reduce their programs and to review and prioritize projects that will have significant progress toward completion made by the end of state fiscal year The results of those reviews are presented below. PROJECTS REMOVED FROM THE STATE BOND PROGRAM The following projects that were previously on hold will be removed from the State Bond program and they will be reevaluated for inclusion in future capital programs as other funding sources are identified. SERVICE BOARD PROJECT TITLE BUDGET CTA Rail Shop Fire Alarm and Fire Suppression Repair and/or Replacements $6,705,458 CTA Energy Retrofits $350,000 Metra Burr Oak Station (Design/Engineering/Construction) $600,000 Metra Romeoville Station (Construction) $2,000,000 Metra 59 th Street Station (Engineering/Construction) $8,000,000 Metra 63 rd Street Station (Engineering/Construction) $1,000,000 Metra Calumet Station (Construction) $5,500,000 Metra River Forest Station (Engineering/Construction) $5,500,000 Metra BNSF Line Yard Improvements $4,000,000 Metra Blue Island Interagency Transfer Improvements $1,350,000 Metra UPR Line Yard Improvements $2,400,000 Metra Mokena Hickory Creek Station (Design) $300,000 Metra ADA Platforms and Ramps (Electric District) $4,000,000 Metra Rock Island District Yard Improvements $750,000 Metra Hubbard Woods Station (Design) $600,000 Metra Racine Avenue Station (Design/Engineering/Construction) $560,000 Metra Mayfair Station Rehabilitation (Design/Construction) $910,000 Metra Grayland Station Rehabilitation (Design Construction) $850,

33 STATUS OF STATE-FUNDED PROJECTS PREVIOUSLY ON HOLD (CONTINUED) PROJECTS PROCEEDING WITH BUDGET REVISIONS The following projects that were previously on hold will move forward with some budget revisions. These projects are shovel-ready and can be implemented quickly. Metra is in the process of amending the grant application with RTA and IDOT. A detailed status on these projects will be provided in the next PMO report. SERVICE BOARD PROJECT TITLE BUDGET Metra UPN North 11 East Side Bridges $12,668,903 Metra Deering Bridge Repair $19,800,000 PROJECTS ADDED TO THE STATE BOND PROGRAM As part of the requested State Bond program revisions, Metra will be adding two new projects to the State Bond Program. These projects are ready to proceed and can be implemented quickly. Metra has submitted a grant application and it is currently under review by RTA and IDOT. A detailed status on these projects will be provided in the next PMO report. SERVICE BOARD PROJECT TITLE BUDGET Metra Locomotive Rehab $30,000,000 Metra Car Rehab $26,428,

34 Systemwide STATE FUNDED PROJECTS CHANGE ORDERS STATUS QUANTITY Projects With Change Orders 7 Projects Without Change Orders 14 Note: Some projects may have executed multiple change orders. PERCENTAGE OF TOTAL PROJECTS 33% Projects With Change Orders 67% Projects Without Change Orders Projects With Change Orders SB PROJECT NUMBER OF CHANGE ORDERS CTA 95 th Street Terminal Improvements 6 CTA Wilson Transfer Station 7 CTA Rail Car Overhaul 1 CTA O Hare Blue Line Addison to Cumberland 1 CTA Rail Shop Roofs and Washer Replacement 1 CTA 98 th Shop Replace Hoist and Spin Jacks 2 Metra Positive Train Control

35 Systemwide STATE FUNDED PROJECTS CHANGE ORDER REASONS REASON QUANTITY COST Added Value 2 $3,916,285 Unforeseen Conditions 15 $10,483,994 Errors and Omissions 1 $193,395 Value Engineering 1 ($1,177,000) Other 1 $0 TOTAL 20 $13,416,674 The change order quantities and cost amounts represent the cumulative total for the 21 currently ongoing state-funded projects. The total cost of change orders represents less than 1% of the overall total budget of the state funded projects. All change orders were executed within the project budgets. One change order was executed for the O Hare Blue Line Station Improvements Addison to Cumberland Project. The construction services contract was modified due to changed conditions. During construction, station elements were discovered to be advanced in deterioration from when the project work scope was initially established. Work scope was increased for removal and replacement of these station elements. Two change orders were executed for the Wilson Transfer Station Project. These change orders were in-process for the last reporting period, have been completed and were due to changed conditions. One change order added construction management services for the rebidding of the construction contract. Securing project building permits and continuity of construction management services was necessary to maintain the project schedule. The second change order modified the construction services contract work scope for owner directed changes and unanticipated permit requirements. Structure elements needed additional components, redundancy within the track system allowed for elimination of components and permanent casings were required for drilling operations. A change order was executed for the Rail Shop Washer Replacements Project for added value. The engineering services contract work scope was modified to add document review and preparation, survey and field investigations for yard track reconfiguration. Improvements to the yard reduce construction costs, enhance washer maintenance access and improve safety. Two change orders were executed for the 98 th Shop Hoist & Spin Jack Replacement Project. Changed conditions resulted in adjustments to the construction services contract. Updates were for inclusion of a cost escalation and lead paint abatement work. Construction work being 32

36 performed in 2017, instead of 2015 & 2016, required pricing revisions. Identification of additional lead based painted structure elements increased the scoped lead abatement work. A no cost time extension has been executed for the Positive Train Control (PTC) Project due to the extension of the federal mandate implementation. A second change order was executed for PTC to develop the Computer Aided Dispatching (CAD) system required for the implementation of the System Integrator (SI) for Positive Train Control. At the time of awarding the contract for the SI, Metra determined that the CAD component will be awarded to Alstom Signaling since Alstom created their most recent CAD and staff familiarity with the proprietary software would make for a smoother implementation requiring less staff training. However, Alstom has informed Metra that they will not be able to complete this work within the federally mandated deadline for PTC. The development of the CAD system is now part of the scope for the SI. As a part of their contract, Parsons, the System Integrator is required to create a test CAD component to test other PTC elements they are currently contracted to create. In addition, Parsons will not need to take additional time to research and design a fully CAD system since this will just be an expanded version of the test CAD system already created. 33

37 Section II Systemwide Projects over $10,000,

38 Systemwide PROJECTS OVER $10,000,000 SERVICE BOARD PROJECT TITLE BUDGET CTA Purchase Rail Cars Series 7000 $632,000,000 Metra Positive Train Control $280,983,346 CTA 95th Street Terminal Improvements $280,000,000 CTA Purchase Nova Buses $233,481,678 CTA Wilson Transfer Station $206,070,539 Metra UP West Line Expansion $198,129,013 CTA Perform Rail Car Overhaul and Mid-Life Rehabilitation $180,491,856 Pace Purchase 40' Fixed Route Buses $167,974,976 Metra Replace Bridges, 18th to 55th - Rock Island District $120,481,995 Pace Purchase CNG Buses $119,913,100 CTA Red Purple Modernization (RPM) Phase 1 $113,704,135 Metra Locomotive Rehabilitation - F40 (Option 1) $84,853,285 CTA East Lake, Milwaukee, and Illinois Substation Construction $68,987,861 Metra Lake Street Interlocker Modernization $66,869,804 CTA Ravenswood-Loop Connector Signal Renewal $50,000,000 Metra Fiber Optic Cable $47,022,942 CTA O'Hare Blue Line Station Improvements - Addison to Cumberland $43,000,000 CTA Dearborn Subway Station Improvements Grand, Chicago, and Division $39,000,000 Metra Financial System Replacement $37,647,000 CTA Bus State-of-Good Repair (SOGR) $37,186,698 CTA Rail Shops Roofs and Bus Washer Replacements $32,523,142 Metra Locomotive Rehabilitation - MP36 $31,459,842 Metra Lake Street Interlocker $31,334,966 Pace Purchase Paratransit Buses for Suburban Dial-A-Ride $30,098,869 Pace Purchase 40' Over The Road Buses $28,872,150 Metra Traction Power System Augmentation - MED $26,789,036 CTA Jefferson Park Intermodal Facility Renovations $25,000,000 CTA North Red Line Stations - Sheridan $24,000,000 Metra Car Rehabilitation - Nippon Sharyo $23,425,000 CTA Illinois Medical District Station Rehabilitation $23,000,000 Metra Commuter Car Rehab - Budd $22,770,649 Metra Auburn Park New Station $21,500,000 CTA Lake Line Laramie to Harlem Tactical Ballasted Trackwork Improvements $21,391,986 Pace Purchase Vanpool Vehicles $20,011,498 CTA Quincy Loop Station Upgrades $18,234,808 Metra Revenue Accounting System $17,770,000 Metra Car Rehabilitation Amerail $15,733,000 CTA Belmont Gateway $15,226,054 Metra Peterson Ridge New Station $15,000,000 Metra Head-End Power Modification $12,925,891 Metra IT Components and Services $12,611,497 Metra 47 th Street Yard Improvements $11,666,

39 Pace Purchase Vanpool Minivans $11,076,439 Metra Locomotive Rehabilitation F40 Phase 2 $11,000,

40 Systemwide PROJECTS OVER $10,000,000 BY SERVICE BOARD QUANTITY AND BUDGET SERVICE BOARD PROJECTS BUDGET CTA 18 $2,043,298,757 Metra 20 $1,089,973,842 Pace 6 $377,947,032 TOTAL 44 $3,511,219,631 PERCENTAGE OF TOTAL PROJECTS 14% 41% CTA Metra Pace 45% PERCENTAGE OF TOTAL BUDGET 11% 31% 58% CTA Metra Pace 37

41 Systemwide PROJECTS OVER $10,000,000 BY SERVICE BOARD BUDGET RANGE 500M+ CTA Metra Pace 250M-499M 100M-249M 50M-99M 20M-49M 10M-19M

42 Systemwide PROJECTS OVER $10,000,000 BY BUDGET RANGE BUDGET RANGE PROJECTS Projects over $500,000,000 1 Projects between $250,000,000 and $499,999,999 2 Projects between $100,000,000 and $249,999,999 8 Projects between $50,000,000 and $99,999,999 4 Projects between $20,000,000 and $49,999, Projects between $10,000,000 and $19,999,

43 Systemwide PROJECTS OVER $10,000,000 BY SERVICE BOARD BUDGET RANGE BUDGET RANGE CTA METRA PACE Projects over $500,000, Projects between $250,000,000 and $499,999, Projects between $100,000,000 and $249,999, Projects between $50,000,000 and $99,999, Projects between $20,000,000 and $49,999, Projects between $10,000,000 and $19,999,

44 Systemwide PROJECTS OVER $10,000,000 BY TYPE OF PROJECT TYPE OF PROJECT QUANTITY COMBINED BUDGET Construction 17 $1,288,123,441 Maintenance / Rehabilitation 14 $560,966,119 Procurement 13 $1,614,775,559 CTA TYPE OF PROJECT QUANTITY TOTAL BUDGET Construction 12 $906,223,397 Maintenance / Rehabilitation 4 $271,593,682 Procurement 2 $865,481,678 TOTAL 18 $2,043,298,757 Metra TYPE OF PROJECT QUANTITY TOTAL BUDGET Construction 5 $381,900,044 Maintenance / Rehabilitation 10 $312,039,013 Procurement 5 $396,034,785 TOTAL 20 $1,089,973,842 Pace TYPE OF PROJECT QUANTITY TOTAL BUDGET Construction 0 $0 Maintenance / Rehabilitation 0 $0 Procurement 6 $377,947,032 TOTAL 6 $377,947,

45 CTA PROJECTS OVER $10,000,000 SERVICE BOARD PROJECT TITLE BUDGET CTA Purchase Rail Cars Series 7000 $632,000,000 CTA 95th Street Terminal Improvements $280,000,000 CTA Purchase Nova Buses $233,481,678 CTA Wilson Transfer Station $206,070,539 CTA Perform Rail Car Overhaul and Mid-Life Rehabilitation $180,491,856 CTA Red Purple Modernization (RPM) Phase 1 $113,704,135 CTA East Lake, Milwaukee, and Illinois Substation Construction $68,987,861 CTA Ravenswood-Loop Connector Signal Renewal $50,000,000 CTA O'Hare Blue Line Station Improvements - Addison to Cumberland $43,000,000 CTA Dearborn Subway Station Improvements Grand, Chicago, and Division $39,000,000 CTA Bus State-of-Good-Repair (SOGR) $37,186,698 CTA Rail Shops Roofs and Bus Washer Replacements $32,523,142 CTA Jefferson Park Intermodal Facility Renovations $25,000,000 CTA North Red Line Stations - Sheridan $24,000,000 CTA Illinois Medical District Station Rehabilitation $23,000,000 CTA Lake Line Laramie to Harlem Tactical Ballasted Trackwork Improvements $21,391,986 CTA Quincy Loop Station Upgrades $18,234,808 CTA Belmont Gateway $15,226,

46 Purchase Rail Cars Series 7000 Purchase up to 846 rail cars to replace the 2600 and 3200 Series fleet. The current project budget is for the base order of 400 cars. CTA may exercise options to increase the budget and purchase additional cars if funding is available. A design consultant will assist with quality control. $632,000,000 (Budget for base quantity only 400 cars); on budget. SCHEDULE: On schedule; estimated completion December Notice to Proceed was given to the manufacturer in April The design consultant contract was awarded and the design team has held meetings with CTA to define preliminary design concepts and the preparation of submittals. The subcontractor for the rail car trucks completed test runs on CTA system to acquire field data. Preliminary Design reviews are anticipated in June The first prototype cars are expected in 2019, with full production to begin in th Street Terminal Improvements This project will rehabilitate the 95th/Dan Ryan station on the CTA Red Line and its bus terminal, which currently serves 11 CTA and Pace routes. The new design will feature an improved layout for bus and rail customers as well as improved and updated amenities. $280,000,000; on budget. SCHEDULE: On schedule; estimated completion December The main terminal design build contract has continued design, bid and construction activities. The north terminal design is being advanced. Award of construction work orders and south terminal construction activities are on going. The south terminal foundations are constructed. Track adjacent to the south terminal is being reconstructed. The retaining wall advance package contract is being closed out. Negotiations for land acquisitions continued. The closing for the final 2 of 8 total parcels remains on target for this year. 43

47 Purchase Nova Buses Funding will provide for the purchase, engineering, training (including training equipment), and inspection for a minimum of 300 and a maximum of 450 fully accessible buses. $233,481,678; on budget. SCHEDULE: On schedule; estimated completion March CTA has received the entire base order quantity of 300 buses, and has received the entire option amount of 125 buses. This will be the final report. Wilson Transfer Station Wilson Station on the Red Line will be completely reconstructed. The new facility will feature entrances on both the north and south sides of Wilson Avenue, as well as an auxiliary entrance at Sunnyside Avenue, all of which will be accessible. CTA will also preserve historical building elements. $206,070,539; on budget. SCHEDULE: On schedule; estimated completion January Construction of Phase 5 commenced. Trains were cutover from existing Track 4, which facilitated demolition of Track 4 track structures. Drilled shafts and building foundations were installed and infrastructure is being constructed for Track 4 and the east half of the station. 44

48 Perform Rail Car Overhaul and Mid Life Rehabilitation To reduce maintenance costs, 2600 Series cars are undergoing a 3/4 life overhaul and 3200 Series cars will receive a mid life overhaul. The project budget represents only the first year of a multi year overhaul program. $180,491,856; on budget. SCHEDULE: Behind schedule; estimated completion March Skokie Shop has completed all 100 cars in the 2600 Series cars project. The 3200 Series project covers 257 cars. The component rebuild, car overhaul work, and equipment installation is being done by CTA Skokie Shop staff. To date, 134 of the 257 cars have undergone the overhaul and returned to revenue service. There has been an increase in the scope of repairs based on car condition observed during the program. Red Purple Modernization (RPM) Phase 1 The RPM project will completely rebuild the northern portion of the Red Line from Belmont to Howard station and the Purple Line, which extends to Linden station in Wilmette. The RPM Phase 1 project consists of the following elements: Red Purple Bypass, Lawrence to Bryn Mawr Modernization, Corridor Signal Improvements, Advance Systems Work and Broadway Substation Upgrade. $113,704,135; on budget. SCHEDULE: On schedule; estimated completion January The preliminary engineering consultant is working on bridging documents. CTA is preparing documents for the Request for Qualifications (RFQ) for the design build contract. The RFQ is planned for advertising in second quarter of The bid opening for the design build contract for Broadway Substation took place in April Long lead time track material has been received. 45

49 East Lake, Milwaukee, and Illinois Substation Construction This project will provide for upgrades to the building envelopes as well as upgrades to interior finishes, AC power, lighting, alarms, heating, ventilation and plumbing systems at all three substations. At East Lake substation the routing of cables from the substation to the elevated structure will be coordinated around a very congested area underground. The East Lake building will be purchased from ComEd. At Milwaukee substation the project will provide for new traction power equipment with greater capacity. $68,987,861; on budget. SCHEDULE: On schedule; estimated completion March The construction contract was awarded to Clark Construction. Notice to Proceed was issued on April 10, CTA has also executed a Task Order for construction management services. Ravenswood Loop Connector Signal Renewal Replace obsolete signal equipment beyond its useful life with new state of the art equipment on the branch of the Brown and Purple Lines known as the Ravenswood Loop Connector, which comprises the area between Merchandise Mart and Armitage Stations. $50,000,000; on budget. SCHEDULE: On schedule; estimated completion July CTA is implementing this project through a design build contract. The Design Phase is near completion. The contractor has been installing cable brackets and messenger wire on the existing CTA structure. Demolition at Cleveland has commenced in preparation for concrete work and structure bonding continues. 46

50 O Hare Blue Line Station Improvements Addison to Cumberland These Blue Line stations along the O Hare branch will be rehabilitated with new canopies and replacement of damaged platforms, as well as repairs to existing damaged curtainwalls. An elevator will be added at Addison. $43,000,000; on budget. SCHEDULE: On schedule; completed November The construction contract is being closed out. Punch list work was performed at all stations. Record documents, operating manuals and warranties were submitted. A final project observation was coordinated among IDOT, RTA and CTA and has been performed. This is the final report on this project. Dearborn Subway Station Improvements Grand, Chicago, and Division The proposed scope of work includes improvements at the street, mezzanine, and platform levels. New entry canopies will be installed at each stair opening with new glazed tile walls, lighting, and repainted ceilings. Mezzanine and platform improvements will include new finishes, lighting, furniture, and exit roto gates. Elevators and stairs will also be replaced. $39,000,000; on budget. SCHEDULE: On schedule; estimated completion May The Blue Line subway was originally opened in These three stations date back to that time and are in need of renewal to restore them to a state of good repair. The project is in the later stages of planning. The Project Master Plan was finalized in October CTA plans to advertise this project for bids in the fall of this year. The scheduling for this project needs to be coordinated with other Your New Blue projects for track access time. 47

51 Bus State of Good Repair (SOGR) This project will provide rehabilitation work at existing bus garage and bus facilities across the CTA system. $37,186,698; on budget. SCHEDULE: On schedule; estimated completion June The following projects were completed: Employee Comforts at Bus Maintenance & Bus Turnarounds; Forest Glen Oil/Water Separator; Concrete Repair at South Shops Unit 9; Systemwide Bus Garage Exterior Lightning, 77 th Garage Fuel System & Remediation; Forest Glen Chassis Wash Pit; Unit 6 Pit Replacement; 103 Garage Heating; 77 th Unit 4 Tire Shop; South Shops Unit 4 Brake Stripping. The 77 th Bus Garage Washer Replacement is currently in procurement. Bids for construction services were solicited for the bus washer replacements. Rail Shop Roofs and Bus Washer Replacements This project will upgrade CTA bus and rail maintenance facilities at 77th Bus Garage, Harlem Rail Shop on the Green Line, and Des Plaines Rail Shop on the Blue Line. Scope elements include roofing work at the rail shops as well as a new rail car washer, and the replacement of two bus washers at 77th Garage. $32,523,142; on budget. SCHEDULE: On schedule; estimated completion May The roof replacements are complete. Bids for construction services were solicited for the bus washer replacements. State funds will no longer be used for the bus washer replacements and the procurement will be completed under a different project. The design for the rail car washer at Harlem Shop is being advanced from 60% to 90% and further developed for inclusion of yard trackwork improvements. Due to changes in the availability of state funding, other funding sources will need to be identified for the construction of the rail washer. 48

52 Jefferson Park Intermodal Facility Improvements Bus turnaround improvements will include new paving and lighting, replacement of the existing canopy to improve access to CTA and Metra rail stations, and public art. Station improvements will include replacement of the curtain wall, repainting of the stationhouse exterior, and rehabilitation of lighting, escalators, and stairs. Platform improvements will include canopy skylight replacement, new lighting, and refinishing of surfaces. $25,000,000; on budget. SCHEDULE: On schedule; estimated completion May The Jefferson Park Intermodal Facility is one of the few locations in the region that is served by all three Service Boards. The procurement for this project was combined with the Belmont Gateway Project. The Project Master Plan and bridging documents for procurement of a design build contractor were developed and finalized. An invitation for bids has been advertised on May 1, North Red Line Stations Sheridan Improvements to the station facilities will provide for improved maintenance, passenger comfort, and security. The project scope will include lighting, roofs and canopies, platform decking, painting, accessibility features, and structural repairs. $24,000,000; on budget. SCHEDULE: On schedule; estimated completion September CTA Structure Maintenance forces are continuing with the structure renewal work, which is part of the project scope. Due to changes in the availability of state funding, only the structure renewal work will be completed. Improvements to the station are deferred. 49

53 Illinois Medical District Station Rehabilitation Improvements to the station facilities will provide a new elevator at the Ogden Avenue stationhouse and renovations to the Damen Avenue and Paulina Street entrances with upgraded finishes throughout. Existing ramps will be modified to become ADA compliant. The platform canopy will also be repaired. $23,000,000; on budget. SCHEDULE: On schedule; estimated completion December Improvements to this station will provide for ADA access to nearby medical facilities. Construction contract was awarded and Notice to Proceed was issued in September The Damen entrance concourse portion of the platform is closed and rehabilitation work is ongoing. Foundation permit in progress, awaiting approval. Funding is provided 100% by City of Chicago TIF. Lake Line Laramie to Harlem Tactical Ballasted Trackwork Improvements This project will renew track, including ties, plates, and fasteners, on the ballasted portion of the Lake Branch of the Green Line. The last major renewal of this segment occurred in the mid 1980s, and the majority of its crossties are reaching the end of their useful lives. $21,391,986; on budget. SCHEDULE: On schedule; estimated completion December The majority of this work is being performed during weekend line closures, with bus substitution provided. Project is substantially complete. Remaining work includes installation of drip pan and replacement of damaged lighting in Harlem Yard. Final acceptance is expected in second quarter of

54 Quincy Loop Station Upgrades Improvements to the station include: elevators for both the inner loop and outer loop platforms; repair, repainting, and refinishing of interior and exterior elements of the stationhouse; and upgrades to lighting and canopies. $18,234,808; on budget. SCHEDULE: On schedule; estimated completion June Quincy Station has been designated as CTA s historic station on the elevated Loop and certain elements will be preserved. Construction contract was awarded and Notice to Proceed was issued in July Adjacent owner s 30 day excavation notifications were sent. Permit process coordination and submittal reviews continue. Funding is provided by City of Chicago TIF and CTA. Belmont Gateway This project will create a gateway that is intended to invoke a sense of community in this neighborhood via architecture as art. Along with creation of this architecture, the project will also bring customer amenities to the station including bus and train arrival signage and bus boarding technology. The scope will also address practical amenities such as infrared heaters, wind breakers, and accessible signage to improve customer experience. $15,226,054; on budget. SCHEDULE: On schedule; estimated completion November The procurement for this project was combined with the Jefferson Park Station Project. The Project Master Plan and bridging documents for procurement of a design build contractor were developed and finalized. 51

55 CTA PROJECT BUDGET BY PERCENTAGE OF ENTIRE BUDGET AND PERCENTAGE OF PROJECTS BUDGET QUANTITY % OF BUDGET % OF PROJECTS Projects over $500,000, Projects between $250,000,000 and $499,999, Projects between $100,000,000 and $249,999, Projects between $50,000,000 and $99,999, Projects between $20,000,000 and $49,999, Projects between $10,000,000 and $19,999, % of Budget % of Projects M+ 250M-499M 100M-249M 50M-99M 20M-49M 10M-19M 52

56 CTA TYPE OF PROJECT QUANTITY TOTAL BUDGET Construction 12 $906,223,397 Maintenance / Rehabilitation 4 $271,593,682 Procurement 2 $865,481,678 PERCENTAGE OF TOTAL PROJECTS 11% 22% Construction Maint./Rehab. 67% Procurement PERCENTAGE OF TOTAL BUDGET 42% 45% Construction Maint./Rehab. Procurement 13% 53

57 Metra PROJECTS OVER $10,000,000 SERVICE BOARD PROJECT TITLE BUDGET Metra Positive Train Control $280,983,346 Metra UP West Line Expansion $198,129,013 Metra Replace Bridges, 18th to 55th - Rock Island District $120,481,995 Metra Locomotive Rehabilitation - F40 (Option 1) $84,853,285 Metra Lake Street Interlocker Modernization $66,869,804 Metra Fiber Optic Cable $47,022,942 Metra Financial System Replacement $37,647,000 Metra Locomotive Rehabilitation - MP36 $31,459,842 Metra Lake Street Interlocker $31,334,966 Metra Traction Power System Augmentation - MED $26,789,036 Metra Car Rehabilitation - Nippon Sharyo $23,425,000 Metra Commuter Car Rehab - Budd $22,770,649 Metra Auburn Park New Station $21,500,000 Metra Revenue Accounting System $17,770,000 Metra Car Rehabilitation Amerail $15,733,000 Metra Peterson Ridge New Station $15,000,000 Metra Head-End Power Modification $12,925,891 Metra IT Components and Services $12,611,497 Metra 47 th Street Yard Improvements $11,666,576 Metra Locomotive Rehabilitation F40 Phase 2 $11,000,

58 Positive Train Control (PTC) Pursuant to the US Rail Safety Improvement Act of 2008, the United States railroad network, which includes all Metra lines, is required to implement PTC. In addition to this legislative mandate, justification for PTC also involves several safety improvements. Included among these are: train separation and collision avoidance, line speed enforcement, temporary speed restrictions, and rail worker wayside safety. $280,983,346; on budget. SCHEDULE: On schedule; estimated completion September System integrator planning and work activities to support PTC implementation continued. Hardware installation and configuration and software configuration is on going. Station signal strength testing was performed to confirm the limits for track mapping using GPS. Training for PTC mechanical was performed. Locomotives and cab car types antenna testing was completed. UP West Line Expansion This project, a Public Private Partnership funded 50% by Metra and 50% by the Union Pacific Railroad, involves the expansion and extension of the UP West Line, including the addition of a third main line track. $198,129,013; on budget. SCHEDULE: Behind schedule; estimated completion December The project design and environmental work have been completed. Construction cost estimates for both segments, including land acquisition, have been prepared. As part of the latest revisions to the State Bond program the construction of the third main line track is moving forward. An Invitation for bids was issued for the east portion of the track and the bids are currently being evaluated by Union Pacific. 55

59 Replace Bridges, 18th to 55th Streets Rock Island District Project funding provides for the replacement of bridges between 18th Street and 55th Street, and will also include new track and signal systems. $120,481,995; on budget. SCHEDULE: On schedule; estimated completion December Phase 1 design and construction is complete. Phase 2 design is complete. The IFB package has been advertised and bids have been received. Construction contract has been awarded and Notice to Proceed has been issued. Contractor is currently mobilizing. Locomotive Rehabilitation F40 (Option 1) The locomotives, originally delivered between 1989 and 1992, will undergo a second rehabilitation to include complete rebuilding of the diesel engine, replacement and overhaul of various traction, electrical, and control components, and body repair and painting. These locomotives are the first batch of their fleet to undergo the rehabilitation process. $84,853,285; on budget. SCHEDULE: On schedule, estimated completion December Rehabilitation of these locomotives includes fuel emission upgrades to a higher environmental standard. Six locomotives have completed the rehab process. The contractor is currently working on six more locomotives from the first batch. 56

60 Lake Street Interlocker Modernization This project features the modernization and upgrading of the Lake Street Interlocker north of Chicago Union Station. The current task is to modify the overhead ceiling plenum to provide clearance. $66,869,804; on budget. SCHEDULE: Behind schedule; estimated completion December The final site plan and specifications were submitted by Amtrak Engineering to building management at Two North Riverside Plaza. Both Metra and Amtrak are currently coordinating to finalize work schedule and costs. Fiber Optic Cable This project consists of the installation of fiber optic cable at LaVergne MP 7.1 to Lisle MP 24 and between MP 23.0 and 26.0, including intermediate signals, and at grade crossings between mileposts and on the BNSF line. The cable will provide signal communication and control system for interlockings and crossings, as well as provide the infrastructure for PTC. The project also includes the installation of Illinois Commerce Commission (ICC) mandated constant warning time equipment and signal upgrages. $47,022,942; on budget. SCHEDULE: On schedule; estimated completion September BNSF and Amtrak have developed an approach to enable trains to initialize for PTC and bumping posts. Signal upgrade at Union Avenue cutover is complete. West Eola and Eola cutover have been completed. WiFi installation at intermediate points where commuter trains switch ends for scheduled flips other than at terminal stations is mostly completed except for Fairview. 57

61 Financial System Replacement This project will provide funding for Metra to implement and Enterprise Resource Planning (ERP) system that will be compliant with current financial system Best Practices. This system will support electronic data interchange, be fully extensible and upgradeable, use integrated highly flexible analytical reporting tools and support microcomputer/network based software productivity tools. $37,647,000; on budget. SCHEDULE: On schedule; estimated completion December Phase 1 went live in January Phase 2, which includes Budget, Procurement, Inventory, Projects and Grants, Accounts Payable and Receivable Modules is in progress. Training has begun and data conversion work is in progress. Phase 2 is projected to go live in Phase 3 will include the Payroll Module. Operational reviews for phase 3 have been completed. Purchase order has been issued for servers, hardware and related equipment. Locomotive Rehabilitation MP36 This project involves the mid life rehabilitation of 26 locomotives that were delivered between 2003 and $31,459,842; on budget. SCHEDULE: On schedule; estimated completion February Work is ongoing and being performed in house. Locomotives are being strategically removed from service to undergo rehabilitation with minimal impact to revenue service. Requisition of materials is in process. Materials are released from Master Purchase Orders as needed. Seven locomotives have been completed and three are currently in Metra s shop undergoing rehabilitation. 58

62 Lake Street Interlocker This project features the renewal of turnouts at Lake Street Interlocking, including the purchase and installation of a new interlocking control machine. $31,334,966; on budget. SCHEDULE: On schedule; estimated completion December The design work on interlocking control machine is ongoing and is at 85% completion. Materials for interlocking control machine are being received and installation will follow. Overall track work is currently at 98% completion. Remaining track work will be completed after installation. Traction Power System Augmentation Metra Electric District Four existing tie stations (51st Street, 95th Street, Riverdale, and Homewood) will be converted into power substations with substantially greater power capacity and installing a new prefabricated substation at 31st Street. $26,789,036; on budget. SCHEDULE: On schedule; estimated completion December Converting the tie stations into substations and installing a new substation will increase capacity and reliability on the Metra Electric District. Construction is moving from north to south. 31st Street and 51 Street construction is complete. Design task has been awarded to design remaining substations which are Riverdale, 95 th Street and Homewood. 59

63 Car Rehabilitation Nippon Sharyo This project involves the mid life rehabilitation of 30 commuter rail cars built by Nippon Sharyo and delivered between 2002 and This is the first major rehabilitation of these cars, and is the first phase in a multi year program to complete the rehabilitation of all 302 cars. $23,425,000; on budget. SCHEDULE: On schedule; estimated completion January As with other rail car rehabilitation programs, this is also being performed inhouse. Requisition of materials is in process. Materials will be released from Master Purchase Orders as needed. Four cars have gone through the rehabilitation process but will need to return for seat installation. Five cars are currently in Metra s shop undergoing the rehabilitation process. Commuter Car Rehabilitation Budd This project involves the life extending rehabilitation of up to 41 commuter cars, originally built by the Budd Company between 1974 and 1978, last rehabilitated between 1990 and $22,770,649; on budget. SCHEDULE: On schedule; estimated completion December This project will improve the overall state of good repair for Metra rolling stock. As with the locomotive rehabilitation projects, rolling stock are being removed from service in such a manner as to not disrupt operations. Requisition of materials is ongoing and master purchase order is being released as needed. Eleven cars have been completed and rehabilitation of three more is underway. 60

64 Auburn Park New Station A new station on the Rock Island District in the Auburn Park area near 79th Street in Chicago, with two 8 car platforms, lighting, elevator access, sheltered waiting facilities, and two stair and elevator headhouse towers. $21,500,000; on budget. SCHEDULE: Behind schedule; estimated completion December Due to changes in the availability of state funding, State Bond funds will be deobligated from this project. This project has been deferred. Revenue Accounting System Metra will implement a new and updated revenue accounting system and will also provide funding for Metra to scope and release an RFP to integrate its current financial system into an Enterprise Resource Planning (ERP) system that will be compliant with current best practices. $17,770,000; on budget. SCHEDULE: On schedule; estimated completion December The revenue accounting system is live. Metra is awaiting initiation of the ERP system to determine the required integration needs for the revenue accounting system. 61

65 Commuter Car Rehabilitation Amerail This project is the last of six phases in a rehabilitation and mid life overhaul program. The entire rehabilitation program includes all 176 commuter cars built by Morrison Knudsen/Amerail. These cars were originally placed into service between 1994 and $15,733,000; on budget. SCHEDULE: On schedule; estimated completion June This project is being performed in house at Metra s 49th Street Shop on the Rock Island District. Metra is one of the few commuter railroads to have such an extensive car rebuilding program. Twenty four cars have been completed. Two cab cars are awaiting for stationary seats to be delivered and installed. Peterson Ridge New Station Construct a new commuter station on the Union Pacific North Line on the north side of Chicago near Peterson Avenue and Ridge Avenue. $15,000,000; on budget. SCHEDULE: Behind schedule; estimated completion December The design has been completed. Due to changes in the availability of state funding, State Bond funds will be de obligated from this project. The construction phase of this project has been deferred. 62

66 Head End Power Modification This project will modify 12 locomotives by replacing the main engine driven generator and inverter combination that provides power to the train consist with a separate engine/generator set. $12,925,891; on budget. SCHEDULE: On schedule; estimated completion February Material purchases have begun. Because this project will be implemented on MP36 locomotives, it is awaiting the completion of the separate rehabilitation project. When completed, improved fuel efficiency and reduced emissions are expected. IT Components and Services This project will provide for purchase of various types of computer hardware and software that will be utilized at Metra Headquarters and outlying areas. Purchases will include, but are not limited to, mainframe terminal and printer replacement, mainframe tape system, replacement of obsolete network switches, computers, printers, copiers and new servers. $12,611,497; on budget. SCHEDULE: On schedule; estimated completion December Purchase orders have been awarded for various computer hardware and software. Requisitions are being prepared for hardware and software. 63

67 47 th Street Yard Improvements This project is part of an ongoing program to make improvements to the facilities at the 47 th Street Yard and Shops. The highest priority projects will provide for the installation of a new ventilation system in the diesel shop and the replacement of the sand tower in the yard. $11,666,576; on budget. SCHEDULE: On schedule; estimated completion December Track work is ongoing. The air compressor has been installed. Metra Forces are currently building yard offices. Yard improvement activities are expected to begin end of summer Locomotive Rehabilitation F40 (Option 2) Ten locomotives, originally delivered between 1989 and 1992, will undergo a second rehabilitation to include complete rebuilding of the diesel engine, replacement and overhaul of various traction, electrical, and control components, and body repair and painting. These locomotives are the second batch of their fleet to undergo the rehabilitation process. $11,000,000; on budget. SCHEDULE: On schedule, estimated completion December Rehabilitation of these locomotives includes fuel emission upgrades to a higher environmental standard. Project funds were awarded in August These funds are for Option 2 execution for rehabilitation of 10 locomotives. 64

68 Metra PROJECT BUDGET BY PERCENTAGE OF ENTIRE BUDGET AND PERCENTAGE OF PROJECTS BUDGET QUANTITY % OF BUDGET % OF PROJECTS Projects over $500,000, Projects between $250,000,000 and $499,999, Projects between $100,000,000 and $249,999, Projects between $50,000,000 and $99,999, Projects between $20,000,000 and $49,999, Projects between $10,000,000 and $19,999, % of Budget % of Projects M+ 250M-499M 100M-249M 50M-99M 20M-49M 10M-19M 65

69 Metra TYPE OF PROJECT QUANTITY TOTAL BUDGET Construction 5 $381,900,044 Maintenance / Rehabilitation 10 $312,039,013 Procurement 5 $396,034,785 PERCENTAGE OF TOTAL PROJECTS 25% 25% Construction Maint./Rehab. Procurement 50% PERCENTAGE OF TOTAL BUDGET 36% 35% Construction Maint./Rehab. Procurement 29% 66

70 Pace PROJECTS OVER $10,000,000 SERVICE BOARD PROJECT TITLE BUDGET Pace Purchase 40 Fixed Route Buses $167,974,976 Pace Purchase CNG Buses $119,913,100 Pace Purchase Paratransit Buses for Suburban Dial-A-Ride $30,098,869 Pace Purchase 40' Over The Road Buses $28,872,150 Pace Purchase Vanpool Vehicles $20,011,498 Pace Purchase Vanpool Minivans $11,076,

71 Purchase 40 Fixed Route Buses This project involves a five year indefinite delivery/indefinite quantity contract for 40 foot buses. The minimum quantity to be purchased under this contract is 24 buses and the total number of buses procured will not exceed the maximum amount of 416. $167,974,976; on budget. SCHEDULE: On schedule; estimated completion January To date, 322 buses have been ordered under this contract, including 90 new buses ordered in Of the 90 buses ordered, all have been delivered. 25 are being used for I 90 express service, 54 for regular fixed route services and 11 will be used for Pulse Milwaukee ART Corridor. A new order of 86 buses was placed on December 29, 2016 with expected delivery beginning in July 2017 and continuing through January Purchase 40 Compressed Natural Gas Buses This project involves a five year indefinite delivery/indefinite quantity contract for 40 compressed natural gas buses. The minimum quantity to be purchased under this contract is 91 buses and the total number of buses procured will not exceed the maximum amount of 250. $119,913,100; on budget. SCHEDULE: Behind schedule; estimated completion August The first 20 buses have been delivered and received by Pace. The second order of 28 buses has been placed in August 2016 and the busses have been delivered to Pace on April 25, The third order of the remaining 43 buses is expected to be delivered by December

72 Purchase Paratransit Buses for Suburban Dial A Ride Service This project involves a five year indefinite delivery/indefinite quantity contract for 15 passenger Paratransit buses. The minimum quantity to be purchased under this contract is 20 gasoline engine and/or diesel engine buses. The total number of buses procured will not exceed the maximum amount of 432. $30,098,869; on budget. SCHEDULE: On schedule; estimated completion March To date, a total of 207 vehicles, including the current order of 50 vehicles, have all been delivered and placed in service. New requisitions have been entered for 24 and 11 replacement paratransit vehicles. Pace is currently awaiting the results of the pre award Buy America audit for these 35 vehicles. Target date for contract execution is May 24, Purchase 40 Over The Road Buses This project involves a five year indefinite delivery/indefinite quantity contract for 40 Over The Road buses. The minimum quantity to be purchased under this contract is 14 buses and the total number of buses procured will not exceed the maximum amount of 50. $28,872,150; on budget. SCHEDULE: On schedule; estimated completion April A total of 25 forty foot Over The Road Buses have been ordered. An order of 5 buses was executed in October 2016, the buses have been delivered and are now in service. A new order of 3 buses was executed in February 2017 with delivery expected in August

73 Purchase Vanpool Vehicles The vanpool procurement for conversion vehicles allowed for multiple awards based on van types. Therefore, this procurement was awarded to two vendors, each with a five year indefinite delivery/indefinite quantity contract. They have a combined minimum of 70 and maximum of 525 conversion vans. $20,011,499; on budget. SCHEDULE: On schedule; estimated completion June To date a total of 125 conversion vans have been ordered and 100 of them received. Deliveries for the remaining passenger van continues. Purchase Vanpool Minivans A new 5 year contract with a third vendor was awarded on October 9, 2016 for the vanpool procurement of minivans with a minimum quantity of 124 and maximum of 421. On October 26, 2016, FTA granted Pace a Buy America Waiver for domestic content and final assembly requirement for up to 188 Dodge Caravans. $11,076,439; on budget. SCHEDULE: On schedule; estimated completion October A new order of 188 minivans was placed on January 3, Pace has received 51 of the vans and deliveries are ongoing until all vehicles are received. 70

74 Pace PROJECT BUDGET BY PERCENTAGE OF ENTIRE BUDGET AND PERCENTAGE OF PROJECTS BUDGET QUANTITY % OF BUDGET % OF PROJECTS Projects over $500,000, Projects between $250,000,000 and $499,999, Projects between $100,000,000 and $249,999, Projects between $50,000,000 and $99,999, Projects between $20,000,000 and $49,999, Projects between $10,000,000 and $19,999, % of Budget % of Projects M+ 250M-499M 100M-249M 50M-99M 20M-49M 10M-19M 71

75 Pace TYPE OF PROJECT QUANTITY TOTAL BUDGET Construction 0 $0 Maintenance / Rehabilitation 0 $0 Procurement 6 $377,947,032 PERCENTAGE OF TOTAL PROJECTS Construction Maint./Rehab. Procurement 100% PERCENTAGE OF TOTAL BUDGET Construction Maint./Rehab. Procurement 100% 72

76 175 W. Jackson Blvd., Suite 1650 Chicago, IL Follow us on Facebook and Twitter Chicago Transit Authority 567 W. Lake St. Chicago, IL Metra 547 W. Jackson Blvd. Chicago, IL Pace 550 W. Algonquin Rd. Arlington Heights, IL

CTA Capital Construction Update December 12, 2006

CTA Capital Construction Update December 12, 2006 Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction

More information

CTA Capital Construction Update May 17, 2007

CTA Capital Construction Update May 17, 2007 Block 37 Signals Project Brown Line Howard CTA Capital Construction Update May 17, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block 37

More information

FOR IMMEDIATE RELEASE January 17, CONTACT: Mayor s Press Office

FOR IMMEDIATE RELEASE January 17, CONTACT: Mayor s Press Office FOR IMMEDIATE RELEASE January 17, 2012 CONTACT: Mayor s Press Office 312.744.3334 press@cityofchicago.org MAYOR EMANUEL OPENS NEWLY-RENOVATED GRAND AVENUE RED LINE STATION Announces New Green Line Station

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

CTA Blue Line Study Area

CTA Blue Line Study Area CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

IATF REPORT, FALL 2012 Attachment 6

IATF REPORT, FALL 2012 Attachment 6 IATF REPORT, FALL 2012 Attachment 6 6. Presentation, January 4, 2011 Meeting Infrastructure Accessibility Task Force (IATF) January 4, 2011 January Agenda Summary of Concept Plans 10 min Irving Park Overview

More information

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital Needs Assessment Riders Advisory Council July2, 2008 Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program

More information

7000 Series Railcar Program Overview

7000 Series Railcar Program Overview Finance, Administration and Oversight Committee Information Item IV-B November 6, 2008 7000 Series Railcar Program Overview Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation

More information

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015 Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In

More information

EXECUTIVE SUMMARY. Introduction

EXECUTIVE SUMMARY. Introduction EXECUTIVE SUMMARY Introduction The purpose of this study is to ensure that the Village, in cooperation and coordination with the Downtown Management Corporation (DMC), is using best practices as they plan

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program

More information

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

Existing CTA Blue Line: From Clinton Station to Forest Park Station IDOT Expansion Alternative: Forest Park Station to Mannheim Road

Existing CTA Blue Line: From Clinton Station to Forest Park Station IDOT Expansion Alternative: Forest Park Station to Mannheim Road Board 1: Blue Line Study Area History of the CTA Blue Line / I-290 system Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. Project Study Area Existing

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

FFYs Transportation Improvement Program

FFYs Transportation Improvement Program For Public Review Table 2: Draft Amendment One Summary: Five-Year MBTA Programming Overall Changes in Funding in TIP Project Proposed Change Explanation Section/Funding Source From To Difference Five Year

More information

INVEST PRIORITY PROJECTS. IN TRANSIT The Regional Transit Strategic Plan for Chicago and Northeastern Illinois

INVEST PRIORITY PROJECTS. IN TRANSIT The Regional Transit Strategic Plan for Chicago and Northeastern Illinois INVEST PRIORITY PROJECTS IN TRANSIT The 2018-2023 Regional Transit Strategic Plan for Chicago and Northeastern Illinois Transit capital investment makes sense. Transit is a central part of the region s

More information

Improving Accessibility of Regional Bus Stops and Pathways

Improving Accessibility of Regional Bus Stops and Pathways Customer Service and Operations Committee Board Information Item III-A March 13, 2014 Improving Accessibility of Regional Bus Stops and Pathways Page 3 of 17 Washington Metropolitan Area Transit Authority

More information

PUBLIC TRANSPORTATION

PUBLIC TRANSPORTATION PUBLIC TRANSPORTATION PROJECT TITLE U-MED DISTRICT MULTI-MODAL IMPROVEMENTS- PHASE II Transit Vehicles and Upgrades MUNICIPALITY OF ANCHORAGE Capital Improvement Program PROJECT LIST BY DEPARTMENT Public

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR

More information

Thank you Chairman Brown.

Thank you Chairman Brown. Chicago Transit Board March 14, 2007 Thank you Chairman Brown. Good morning. During the Olympic Selection Committee s visit to Chicago last week, CTA s recently acquired hybrid buses were provided to transport

More information

Late Starter. Tuesday, November 6, 2018

Late Starter. Tuesday, November 6, 2018 Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

CTA Blue Line Study Area

CTA Blue Line Study Area 1 CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Department of Public Works (DPW) to award DPW Contract

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the, and double deck ( dd) analysis Including: Description of the Vehicles

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

congestion management program

congestion management program congestion management program 2550 Rail Vehicle Program March 2012 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the EMU, DMU and DMU double deck (DMU dd) analysis Including: Description

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station 203 North LaSalle Street, Suite 2100 Chicago, IL 60601 (312) 558-1345 Fax: (312) 346-9603 E-Mail: cquandel@quandelconsultants.com www.quandel.com Scope of Services January 26, 2010 Project Development

More information

CPG is pleased to report the following accomplishments this quarter:

CPG is pleased to report the following accomplishments this quarter: MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED Insert TTC logo here STAFF REPORT ACTION REQUIRED Overhaul of 30 Canadian Light Rail Vehicles (CLRV) and Maintaining non-overhauled Streetcars in a State of Good Repair Date: March 23, 2016 To: From: TTC

More information

Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019

Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019 Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019 VENDOR OPEN HOUSE AGENDA Welcome and Introductions Safety Briefing NICTD Website and Plan Room Upcoming Projects Disadvantaged

More information

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County

More information

CITY OF AMES, IOWA CAPITAL IMPROVEMENTS PLAN

CITY OF AMES, IOWA CAPITAL IMPROVEMENTS PLAN CITY OF AMES, IOWA CAPITAL IMPROVEMENTS PLAN 2013-2018 The theme for this year s Capital Improvements Plan document is the Ames Intermodal Facility, opened to the public in the summer of 2012. Photographs

More information

Update on Transportation Activities in Fairfax County

Update on Transportation Activities in Fairfax County Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation

More information

Janice Fortunato Senior Director Business Partnerships

Janice Fortunato Senior Director Business Partnerships Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these

More information

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at Overview Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at www.garail.com Commuter rail service between Lovejoy and Atlanta is ready for implementation:

More information

Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates

Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates Capital and Strategic Planning Committee Item III - A May 10, 2018 FY2018 Third Quarter Capital Program Updates Page 4 of 44 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

Memorandum of Understanding

Memorandum of Understanding Memorum of Understing Between The City of Lake Forest, Metra, Amtrak, Illinois Department of Transportation, Wisconsin Department of Transportation to Collaborate in Improving Passenger Motorist Safety

More information

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion Project Number SYS-LRT Subareas All Primary Mode Impacted Link Facility Type Link Service Version Number 4.0 Date Last Modified 7/24/2008 Project Locator Map Short Project Description Construct new light

More information

Chicago Milwaukee Intercity Passenger Rail Corridor

Chicago Milwaukee Intercity Passenger Rail Corridor Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department

More information

Van Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015

Van Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015 Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min. AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome

More information

Table Station Elements

Table Station Elements The overall layout of the station in the Preferred Alternative (Modified Alternative 2) is described in Table 7.5-1. Table 7.5-1 Station Elements Ground Level Mezzanine Level Platform Level Existing/Upgraded

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

Solano County Transit

Solano County Transit AGENDA ITEM: 9 BOARD MEETING DATE: FEBRUARY 18, 2016 Solano County Transit TO: PRESENTER: SUBJECT: ACTION: BOARD OF DIRECTORS ALAN PRICE, PROGRAM ANALYST II REVIEW AND APPROVE IMPLEMENTATION OF THE FUELING

More information

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Report for Action Wilson Bus Garage - Upgrades Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Summary The purpose of this report is to obtain authorization for the award of Contract No.

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.4 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Department of Public Works (DPW) to award DPW Contract

More information

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future January 13, 2012 AACE Annual Meeting, Wickenburg, AZ I-15 in Arizona. Its Past, Present, and Future Jean A. Nehme, Ph.D., P.E. State Bridge Engineer, ADOT Presentation Overview Location, History, and Photographs

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency

More information

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation

More information

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet

More information

2013/2014 Strategic Priorities Fund Application Overview

2013/2014 Strategic Priorities Fund Application Overview 2013/2014 Strategic Priorities Fund Application Overview Bob Paddon, Executive Vice President Strategic Planning and Public Affairs TransLink 3 December 2013 Strategic Priorities Fund Application Context

More information

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010 BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1

More information

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010 BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information

Public Works Department

Public Works Department Public Works Department Fleet Maintenance Mission: To establish and maintain efficient and effective delivery of fleet services by providing customer departments with safe, reliable, economical and environmentally

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: COMMUNITY BUS SERVICES ACTION ITEM RECOMMENDATION It is recommended that the Board not approve any routing

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Pace Bus Depot Location Analysis

Pace Bus Depot Location Analysis Pace Bus Depot Location Analysis Key Notes 1. Options refer to conceptual sketches prepared by Kimley Horn. 2. The depot is assumed to accommodate Pace routes as they currently exist: 17 routes on the

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Overview Commuter rail service between Lovejoy and Atlanta is ready for implementation: $87.08 Million is in

More information

Transit in Bay Area Blueprint

Transit in Bay Area Blueprint Rail~Volution 2010 Click to edit Master title style Transit in Bay Area Blueprint October 21, 2010 0 Bottom Line State-of-Good Repair essential for reliable transit service large funding shortfalls BART

More information

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action MOTION NO. M2018-160 Purchase of Thirteen 42-foot Double Deck Expansion Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee PROPOSED ACTION 12/06/2018 12/20/2018 Recommend to Final

More information

Construction Staging Area 4 Avenue Road

Construction Staging Area 4 Avenue Road REPORT FOR ACTION Construction Staging Area 4 Avenue Road Date: September 27, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

UNION STATION MASTER PLAN STUDY

UNION STATION MASTER PLAN STUDY UNION STATION MASTER PLAN STUDY The Chicago Department of Transportation has begun a comprehensive study of issues related to Chicago s Union Station, the Union Station Master Plan. Opened in 1925, Union

More information

SUPPORTING TOD IN METRO CHICAGO

SUPPORTING TOD IN METRO CHICAGO www.rtachicago.org SUPPORTING TOD IN METRO CHICAGO Tuesdays at APA November 18, 2014 OVERVIEW OF RTA 2 11/18/2014 Tuesdays at APA: Supporting TOD in Metro Chicago RTA Region 8.5 million people 3,700 square

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

CONFEDERATION LINE EAST SEGMENT

CONFEDERATION LINE EAST SEGMENT The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit

More information

CHAPTER 5 CAPITAL ASSETS

CHAPTER 5 CAPITAL ASSETS CHAPTER 5 CAPITAL ASSETS This chapter describes the capital assets of GCTD, including revenue and nonrevenue vehicles, operations facilities, passenger facilities and other assets. VEHICLE REVENUE FLEET

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This

More information

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS 1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the

More information

O-Train Confederation Line Stage 1

O-Train Confederation Line Stage 1 O-Train Confederation Line Stage 1 Presented to: Regional Public Works Commissioners of Ontario June 23, 2017 by Steve Cripps, Director, O-Train Construction The Need Ottawa s population is projected to

More information

I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016

I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016 I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016 INTRODUCTION As part of the I-290 reconstruction phase I study, IDOT has coordinated with the CTA regarding

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

congestion management program

congestion management program congestion management program 2550 Rail Vehicle Program June 2013 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE

More information

MIAMI-DADE TRANSPORTATION PLANNING ORGANIZATION TRANSPORTATION IMPROVEMENT PROGRAM MIAMI-DADE DEPT OF TRANSPORTATION AND PUBLIC WORKS

MIAMI-DADE TRANSPORTATION PLANNING ORGANIZATION TRANSPORTATION IMPROVEMENT PROGRAM MIAMI-DADE DEPT OF TRANSPORTATION AND PUBLIC WORKS TPO Facility/ Name Prior s Detailed Description TA000100 MDT - DADE / MONROE EXPRESS BUS ROUTE COMMUTER TRANS ASSISTANCE C-6 $12,978 $7,385 4180513, 4409141 Operating assistance of Dade/Monroe Express

More information

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016 July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit

More information

2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION

2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION 2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION L o s A n g e l e s S e p t e m b e r 1 0 th & 11 th 1 General Considerations of Staff Proposal Achieve zero emission

More information

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site. Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS

More information