QUESTIONS AND RESPONSES FROM THE MARCH 11, 2015 PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD JOINT MEETING
|
|
- Julie Ross
- 5 years ago
- Views:
Transcription
1 QUESTIONS AND RESPONSES FROM THE MARCH 11, 2015 PLANNING COMMISSION AND HISTORIC LANDMARKS QUESTIONS FROM THE PUBLIC (NOS. 1-41) PGS 2-9 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD (NOS ) PGS RESPONSES PREPARED BY THE GOLDEN GATE BRIDGE HIGHWAY AND TRANSPORATION DISTRICT
2 QUESTIONS FROM THE PUBLIC GENERAL PROJECT QUESTIONS 1. Q: What is the purpose and scope of the project? A: The project purpose is to replace the aged ferry terminal structures with new structures designed to the current codes, including the Americans with Disabilities Act guidelines for offshore ferry passenger facilities. The scope includes removal and replacement of the existing float, gangway and access pier. 2. Q: Why/how was the 10 minute turnaround target service time selected? A: The ferry turnaround time covers, in addition to disembarking and boarding of passengers, securing the vessel to the dock, verifying that the doors are securely positioned to be opened, opening the doors, verifying that all passengers are off the vessel and conducting a security sweep of the vessel, and, after the boarding, closing the doors, and tying off the vessel. The turnaround times are set by the schedule and they are tighter earlier and later during the day due to more frequent work commute sailings. The 10 minutes included in the District presentation regarding the new facility does not represent the total ferry vessel turnaround time. The 10 minutes represents only the calculated time of disembarking and boarding of passengers at the new Sausalito terminal facility. Similar calculations have been done for the existing facility using the same volume of passengers, with the result of 30 minutes. As observed and as reflected by the calculations, disembarking and boarding at the existing facility is slow. This is caused by a narrow passage way and one door access to the vessel. To stay on schedule, the boarding must ceasee at a specified time without fully utilizing the vessel capacity while often leaving passengers behind. The new facility is designed to increase speed of disembarking and boarding to achieve full utilization of the vessel capacity. 3. Q: Will this project make Sausalito into an undesirably large transportation hub? A: Sausalito has traditionally served as a ferry terminal for southern Marin County. This project is intended to replace the existing deteriorated facilities with new upgraded facilities that meet the current federal accessibility guidelines for passenger ferry access and accommodate the current trends in use, which have featured a steady growth in ridership. No other changes to the District s operations are planned or contemplated at this time. Page 2
3 QUESTIONS FROM THE PUBLIC 4. Q: What is the impact of increase in cars in the parking lot? A: Currently, the existing adjacent parking lot appears to operate at capacity. All the parking lots are owned and operated by the City. This project does not include any increase to the size of the parking lot. 5. Q: What is the increase in the amount of passengers able to be accommodated by this project? A: The replacement facility has been designed to accommodate a projected 4% per year growth in number of passengers through year Q: What happens when demand increases even greater? Will the ferry landing then be enlarged to match? A: The District has no plans for such terminal expansion. The replacement facility is intended to have a useful life of years. The facility has been designed to accommodate a projected 4% per year growth in number of passengers through year It is not possible to meaningfully predict what will happen after DESIGN QUESTIONS 7. Q: Can more attention be paid to the color of the structure? A: Based on the feedback received, the District included two alternatives for the color in its March 24 submittal. 8. Q: Can other designs be explored for the structure to be lighter and have less massing? A: The District has studied alternative designs of the gangway truss, including a redesigned square steel truss, a three-truss gangway, two independent side-by-side gangways and aluminum gangways. The last three alternatives have been found to be not feasible. The profile of the redesigned square steel truss gangway has been lowered to 5-1 above the walkway as presented in the District s March 24 submittal. 9. Q: Can the design be more reflective of Sausalito s Historic Downtown District? A: We have reviewed the Sausalito General Plan, the Sausalito Historic Design Guidelines, the Bicycle Master Plan, Historic Overlay District and Local Register, and the Harbor and Page 3
4 QUESTIONS FROM THE PUBLIC Downtown Action Committee Final Report. We consider our design to be in accordance with these City documents. 10. Q: Can a dark color (e.g. bronze, black) be considered? A: Based on the feedback received at the March 11 meeting and our evaluation, the District is proposing either grey or combination of grey and dark blue. 11. Q: Can the flat truss design be refined to have a smaller profile? A: See answer to question no. 8 above. 12. Q: Can the gate position be located in a different manner to be less visually obtrusive? A: We have investigated different locations/angles for the gate and the visual effect of it changes depending on the location of the viewer. For example, when the proposed orientation of the gate is viewed from the south end of the plaza area, one sees the edge of the gate, whereas from the area near the current landside pier more of the gate is visible. We believe locating the gate at the end of the access pier results in the least visual impact. 13. Q: Is the scale appropriate for Sausalito? A: The scale of the new facility is a result of compliance with the ADA guidelines and the necessity to improve efficiency of the operations. That said, we have revised the design of various elements, such as the width of the access pier and the access gate design, to reflect comments received during the March 11 meeting. 14. Q: Can we take design cues from other ferry landings? A: The District has visited many ferry landings, both in San Francisco Bay, and in other states (see below for locations) to determine what in those facilities could be used in Sausalito. Recognizing that each terminal is unique to its setting, we did find that ferry terminals are being upgraded and that the newer facilities follow the line of thought that has gone into the Sausalito terminal. We were asked if we had looked at the Tiburon terminal and terminals in Washington state. We found the Tiburon terminal too small and it did not seem to fit the character of Sausalito. Washington ferries carry passengers and vehicles and are end loading. As a result, from a layout point of view the Washington ferry system did not provide a great deal of information regarding the layout and design. They do have other mechanical features which are being incorporated in the float design. The District has looked at ferry landings in San Francisco (Downtown Ferry Terminal, China Page 4
5 QUESTIONS FROM THE PUBLIC Basin, South San Francisco, and Vallejo), Oakland (Jack London Square, Alameda), and Marin County (Tiburon). Terminals viewed in Washington include Vashon Island, Pier 50, Kingston, Edmonds, and others. We also have experience with terminals in British Columbia, Alaska, Massachusetts, New York and New Jersey. If there are other terminals that the District should look at please bring them to the District s attention. 15. Q: I m concerned that there s only one design. Can there be other choices for the community to consider? A: Both the existing and the replacement facilities of the Sausalito Ferry Terminal have to have four elements: the landside pier, the access pier, the gangway and the float. The landside pier will not be replaced. The District has presented alternative designs of the gangway truss, the railing, the gate and the colors. The width of the access pier has been decreased to the degree that allows operations to accommodate the projected passenger volumes. 16. Q: Can the design be transformed to be more akin to the Sausalito aesthetic? A: We have modified the design based on the feedback received from the public at the March 11 meeting. We have considered aesthetic of Sausalito and the area surrounding the Ferry Terminal in our previous design. For example, the curved elements of the gangway and the gate and the blue and white color combination was intended to replicate the colors and curved elements used on existing Sausalito buildings. 17. Q: Can a naval architect and sustainability-trained professionals be included in the design dialogue? A: Both a naval architect and sustainability-trained professionals are on the team and have contributed to the project. 18. Q: Is the proposed design final or is there a chance still for improvement to design? A: The design has been revised to incorporate the public comments received to-date while maintaining structural and operational requirements. Except for possible further comments on colors, the submitted design is final to enable City consideration under the terms of the lease. Page 5
6 QUESTIONS FROM THE PUBLIC TECHNICAL QUESTIONS 19. Q: What is the dimension of the jog to gate? A: We understand this question to be what is the distance between the end of the existing landside pier and the new gate?' The distance is approximately 75 feet. 20. Q: Is 12:1 the absolute minimum criteria for a ferry landing? A: The 1:12 slope for the ramps and gangway are the maximum allowable slopes according to current federal ADA guidelines. They may not be made steeper. 21. Q: Can the width of the structure be reduced? A: The width of the structure is being reduced nearly 16%, from 25 feet to 21 feet. This means the proposed access pier will align with the existing landside pier width. Further reducing the width would create a bottle neck for passengers loading and disembarking and negatively impact operations. 22. Q: How often do we have a -2.5 tide? A: Based on the historic tide data as well as projected changes in the sea level, -2.5 foot low tide has been calculated to be the lowest tide to occur during the design life of the new facility design and, as such, it is the controlling parameter of the design. 23. Q: Are the ADA compliance requirements carved in stone? Is there room to reduce the scale of the project? A: The 1:12 slope is the maximum slope allowed per federal ADA requirements. 24. Q: What is the potential of having two smaller, lighter gangways? A: The District has studied this option and found it to be not feasible. We have also looked at having an additional truss in the center of one gangway and have also found this to be not feasible. 25. Q: Why is the width of the access pier necessary to be 21 feet? A: See response to question 21 above. Page 6
7 QUESTIONS FROM THE PUBLIC 26. Q: Could the area where the float would locate be dredged to collapse the project down in scale? A: No, the area may not be dredged to allow the float to be located closer to shore due to the environmental impacts associated with dredging. This project was designed to minimize impacts to the environment. 27. Q. Why can ferries berth on both sides of the concrete float if only one ferry can load and unload at one time? A: Depending on the weather and navigational conditions, it is necessary for the vessels to have the two options for berthing and tying off on the float. 28. Q. If the ferries have two doors on each side, why can t the ferries berth bow in or stern in and eliminate having to ramps on each side of the float? A: See answer to question no. 27 above. OPERATIONAL QUESTIONS 29. Q: Why doesn t the District use catamarans? A: We believe this question was asked in relation to moving the float closer to shore because the catamarans require less water depth. However, it is the float that needs the water depth, so changing the ferries would not affect the float location. 30. Q: Why isn t the District investing in new vessels instead of retrofitting existing vessels? A: It is more cost effective to retrofit existing vessels than to purchase new vessels. 31. Q: Can more boats be directed towards Sausalito to alleviate demand for more thoroughfare? A: The District does not at this time have the resources during the peak weekday commute times to increase the number of trips to and from Sausalito. The District currently runs additional trips on weekends when demand is high at Sausalito by diverting vessels from Larkspur. Page 7
8 QUESTIONS FROM THE PUBLIC 32. Q: Can the structure be located to give more relief water space to the Sausalito Yacht Club? A: The structure is located as far from the Sausalito Yacht Club as possible within the boundaries of the District's lease area. 33. Q: The City s 1995 lease with the District said the lease was $600 per year with an increase related to the increase in the Consumer Price Index. What is the current lease price? Has the increase been maintained? A: The lease states that the City may request that the lease amount be increased by the CPI at specified intervals. The City has never requested an increase to the yearly lease amount, therefore the current lease amount is the same as the original. 34. Q: The proposed ticket location is on City-property. Will this area be included in the leased area? Who will maintain it? A: The District will request an encroachment permit from the City for locating the ticket machine outside the current lease area. The District will continue to maintain the ticket vending machines. ENVIRONMENTAL QUESTIONS 35. Q: What are the light pollution impacts of this project? A: The proposed lighting on the pier, gangway and float is down lit. Lighting will be reduced during non-service hours to the minimum level needed for security purposes. 36. Q: What are the environmental impacts of the vessels in the water? A: The ferry impacts resulting from this project will not change from the existing conditions. 37. Q: What is more environmentally sound? Traveling by automobiles or ferry? A: The answer to this question is outside of the project scope. There have been numerous studies on necessity of public transportation, including ferry service, to mitigate road traffic congestion. Page 8
9 QUESTIONS FROM THE PUBLIC PROCEDURAL QUESTIONS 38. Q: Why have story poles not been provided? A: Due to the need to keep the waters near the existing terminal clear to allow ferry operations, it is not possible to install and leave story poles in place in the water. On March 21 and 22, the District attempted to make a similar presentation on water by using ropes to show the width of the new access pier and lines between buoys placed in the water to show the outline of the new float. The ropes indicating the width of the new access pier will stay in place for a minimum of 10 days beginning March 20 th. The lines and buoys were placed in the water between 8:00 am and 10:00 am on March 21 st and March 22 nd. The demonstration was photographed and the photos will be made available to those who were not able to see the demonstration in person. 39. Q: Can the subsequent public hearings be held at a location to accommodate greater community turnout? A: We understand that the April 1st meeting will be held at a larger venue. 40. Q: Can a 3D model be created in addition to the supplied photographs? A: The District is investigating creating a 3D model. 41. Q: What land-side improvements are required? How will they be paid for with increased taxes or bonds? A: The landside areas are owned by the City and are outside the District s leased area. The District has secured a federal grant and has offered to pass through $2.0 million for landside improvements, which scope is to be developed during a future public participation process led by the City. Page 9
10 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD 42. Q: What is the purpose of the truss system? Can the height be brought down to the height of the railing? A: The truss is to hold up the gangway. The height of the flat gangway truss adopted in the final design has been lowered to 5 feet and 1 inch above the walkway. This height is required to make the structure sound. 43. Q: Do you have views of the gate from the Plaza? We are interested in seeing impact from center of the plaza. A: Not at this time. A follow up: Views from the Plaza are included in our March 24 submittal to the City. 44. Q: Is BCDC anticipating any increase in number of boat trips? A: No. This is outside of the purview of BCDC. 45. Q: Why was the truss system selected? A: Truss system is the lightest and most open design. 46. Q: The belvederes increase the mass. Have you consulted BCDC about this? A: BCDC has two missions one being maximizing access to the bay. The District will consult with BCDC. 47. Q: What is the estimated lifespan of this? A: years. Concrete float design is much more durable. 48. Q: Were Sausalito s General Plan and Bicycle Task Force findings incorporated into the design? A: No. A follow up: The Sausalito General Plan was reviewed during the development of the project. The District considers the project to be in compliance with the General Plan. 49. Q: What are the other feasible alternatives to the truss system? A: The District is looking at the loads that need to be carried over the length of the structure. The long structure requires a system that can support this load. A steel box may be possible but would be all enclosed, therefore offering less visibility and being much heavier. Page 10
11 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD The steel girder system would be too susceptible to corrosion and have too short lifespan. A precast concrete structure will be too heavy. 50. Q: Can a support be placed in the middle of the truss system? A: No. A follow-up: The District has studied a three-truss gangway and found it to not be feasible structurally. 51. Q: The District stated that the current turnaround time is 30 minutes. Looking at the schedules, it appears the turnaround time is less than that, unless the ferries are always behind schedule. Can the District comment? A: Further research is required to answer this question and data will be brought back to the Planning Commission and Historic Landmarks Board. A follow-up: The ferry turnaround time covers, in addition to disembarking and boarding of passengers, securing the vessel to the dock, verifying that the doors are securely positioned to be opened, opening the doors, verifying that all passengers are off the vessel and conducting a security sweep of the vessel, and, after the boarding, closing the doors, and tying off the vessel. The turnaround times are set by the schedule. They are tighter earlier and later during the day due to more frequent work commute sailings. The 30 minutes included in the District presentation does not represent the ferry vessel turnaround time. The 30 minutes represents calculated time of disembarking and boarding of passengers. Similar calculations have been done for the existing Sausalito facility using the same volume of passengers, with the result of 10 minutes. The study of disembarking/boarding times was done to assess improvement in the times between the existing and replacement facility. These times do not represent the actual turnaround times. As observed and reflected by the calculations, disembarking and boarding at the existing facility is slow. This is caused by a narrow passage way and one door access to the vessel. To stay on schedule, the boarding must close at a specified time without fully utilizing the vessel capacity while often leaving passengers behind. The new facility is designed to increase speed of disembarking and boarding to achieve full utilization of the vessel capacity. Page 11
12 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD 52. Q: Does the District intend to increase the number of trips, regardless of authority? A: Not at this time. 53. Q: Are high speed vessels proposed to be used in Sausalito? A: Currently, the Spaulding vessel is typically used. However, in the case of emergencies, additional vessel types could be used. Therefore, all vessel designs must be planned for. 54. Q: If you had more trips, how would that affect the design? Would that thereby reduce the need for an enlarged ferry landing? A: The District does not have the resources to increase the number of trips to and from Sausalito during the peak weekday commute times. When the demand is high in Sausalito on weekends, the District runs additional trips. As described in the answer to question no. 51 above, narrowness of the existing facility impedes the use of the ferry vessels to their capacity. The replacement facility will enable this currently unused capacity to be utilized without adding trips. 55. Q: Please discuss the bayfill associated with project. A: Bayfill is considered by BCDC to be a shadow over the water. This is different than what is actually placed into the water. Approx 131 square feet of newly placed pilings is proposed. The shadowing (what is considered to be bayfill) is increased from 8,000 square feet to 14,943 square feet with the 25-foot wide pier and 14,381 with the 21-foot wide pier. 56. Q: How many passengers/bikes can each vessel hold? A: Further research is required to answer this question and data will be brought back to the Planning Commission and Historic Landmarks Board. A follow-up: See answer to question no. 66 below. 57. Q: What is the lifespan of the each vessels (catamarans/spauldings)? A: With renovations, it is projected that they last approximately 40 years. 58. Q: Will the hydraulics have a redundancy and be manually operable as well? A: Yes. There will be a redundant control system on the float and if they are both out of service there will be a manual way to raise and lower the facility. Page 12
13 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD 59. Q: Low tide data. How often does it occur? If not often, may not need a design like this. A: Further research is required to answer this question and data will be brought back to the Planning Commission and Historic Landmarks Board. A follow-up: The slope of the existing gangway exceeds 1:12 when the tide is -1.1MLLW or lower, which, depending on the year, occurs between 30 to 50 times a year. 60. Q: Has a three-part truss system explored? A: No A follow-up: The District has studied a three-truss gangway and found it to not be feasible structurally. 61. Q: Have there been other design materials explored? A: Yes. Timber was investigated at the top of the railings but this material is not very durable and prone to damage. Similarly glass was investigated for the railings but this is also prone to damage and is a maintenance issue. 62. Q: Will there be land improvements in addition to the waterside improvements? A: The scope of the project is the waterside improvements. The City will be responsible for designing the landside improvements. $2.0M will be passed through to the City from the District to make landside improvements. 63. Q: Will the access piers will be open to the public? Who s responsible for policing? Will fishing allowed? A: Yes public access will be allowed. Agreements will be needed with the City for the other two issues. 64. Q: Is it possible for a size reduction and still have the level of service envisioned? A: The access pier has been reduced from 25 to 21 feet in width. The widths of other areas cannot be reduced. 65. Q: What is the difference between the previous 1996 design? Did ADA rules change? Page 13
14 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD A: The 1996 design contemplated ADA issues (guidelines at that time) but was not able to achieve them. The existing facility is not in compliance with the present ADA guidelines. 66. Q: Please provide data on how many passengers/bikes each vessel can hold. A: The District has 3 Spaulding class vessels and 4 high speed catamaran vessels. The District typically runs the Spaulding class vessels between San Francisco and Sausalito. For the Spaulding class, the M.S. Marin holds 750 passengers and the M.S. Sonoma and M.S. San Francisco hold 630 passengers. The Spaulding class can carry bikes and occasionally up to 250 bicycles depending on the total number of passengers onboard. The total number of bicycles allowed to board is at the discretion of the vessel Captain and the Terminal Supervisor and depends on the scheduled turnaround time and the number of passengers with and without bikes. Bicycle capacity is subject to several factors; scheduled time at the dock; total number of passengers on a particular trip and the designated bicycle stowage area. The Captain of the vessel has great discretion in determining the bicycle count on any given trip. For the catamarans, three of the vessels hold 450 passengers and one holds 400 passengers. The AMD 385 class vessels (Napa and Golden Gate) can carry bikes and occasionally up to 45 bicycles depending on the total number of passengers onboard. M.V. Mendocino can carry bikes and occasionally up to 60 bicycles depending on the total number of passengers onboard. M.V. Del Norte can carry bikes and occasionally up to 150 bicycles depending on the total number of passengers onboard. The total number of bicycles allowed to board is at the discretion of the vessel Captain and the Terminal Supervisor and depends on the scheduled turnaround time and the number of passengers with and without bikes. 67. Q: Please provide data on what Blue & Gold pays the District for a sublease. A: The Public Utilities Commission ordered the District to allow Harbor Carriers (then Red & White and now Blue & Gold) to use the District s passenger ferry terminal and determined the rent that Harbor Carriers pays to the District. The rent was established at $2,639/month. 68. Q: Please provide a copy of the District s maintenance plan. A: The District is developing its maintenance plan for the new facilities. 69. Q: Please provide data on how many times the 1:12 slope is exceeded due to a low tide. Page 14
15 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD A: See response to question no.59 above. 70. Q: Please provide data on the capacity of the Spaulding vs the catamarans. A: See response to question no. 66 above. 71. Q: Please provide information on actual turnaround times. A: See response to question no.51 above. The turnaround times vary during a day. 72. Q: Are there circulation diagrams concerning pedestrians and cyclists? A: Circulation of passengers with and without bicycles at the ferry terminal has been studied and used to develop the configuration and size of the replacement facility. The circulation at the landside Plaza is outside the project scope. 73. Q: Can the belvederes be removed? A: They are not structural necessity, but they accommodate the increased public access on the new access pier. 74. Q: Is a duel gangway structure that has smaller diameter trusses feasible? A: The District has studied this option and found it to require a larger footprint and significant enlargement of the gangway support at the access pier and the float, and to impede operations. 75. Q: What is the BCDC Access Easement on Exhibit 2? A: This is the area within 100 feet of the shoreline that BCDC has jurisdiction over. In addition, BCDC has jurisdiction over a public access easement along the shore and plaza area which also extends into the bay within the District s lease area. 76. Q: Can we see a design with more historical elements? A: The District would like feedback from the Commission and Board regarding what historical elements should be included. 77. Q: Was there a request in the original bid documents for the design to pay attention to historical elements? Page 15
16 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD A: No historical elements applicable to the terminal were identified. 78. Q: The 1995 plan for the ferry landing contemplated a covered waiting area. Did the District contemplate such an area in this design? A: No. 79. Q: Can the gate be rotated perpendicular to the shore? A: We have investigated different angles for the gate orientation and the visual effect of it changes depending on the location of the viewer. For example, when the proposed orientation of the gate is viewed from the south end of the plaza area one sees the edge of the gate whereas from the area near the current landside pier more of the gate is visible. 80. Q: Can the District explore the concept of two gangways to reduce the height of one individual gangway? A: See response to question no. 74 above. 81. Q: Did the District consider Sausalito s General Plan, bicycle plan or the Historic Overlay District? A: We have reviewed the Sausalito General Plan, the Sausalito Historic Design Guidelines, the Bicycle Master Plan, Historic Overlay District and Local Register, and the Harbor and Downtown Action Committee Final Report. We consider our design to be in conformance with these City documents. 82. Q: What other companies share the use of the landing A: Blue and Gold, no others. 83. Q: Could the gangway be lowered closer to the water? A: No. The truss gangway is located so that the steel truss elements will not be in the water to minimize corrosion. 84. Q: If the gangway was narrower could the truss be smaller? Page 16
17 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD A: The gangway width is necessary for operations. Please see answer to question no. 74 above regarding two side-by-side gangways. 85. Q: Why was Sausalito selected first out of San Francisco and Larkspur for an upgrade? A: The Sausalito facility requires a smaller scope of work than the other two, and it is in need of safety upgrades. 86. Q: The District states that the standardization will eliminate the need for wheelchair lifts is the District implying that those in wheelchairs will not be able to have equal access on all levels of the boat? A: The District will provide equal access on all boat levels. The standardization will allow passengers in wheelchairs to board and disembark from the same level without being forced to change levels. 87. Q: Can the District provide guidance on the landside improvements? A: The landside improvements are a standalone City project and separate from the District waterside improvements. The public process for the landside improvements has not begun yet. 88. Q: What does Blue and Gold pay the District for a sublease? A: See answer to question no. 67 above. 89. Q: Is precast concrete a feasible option for the gangway? A: No, it would be too heavy. 90. Q: The design is based on a 10 minute disembarkation/embarkation time. Could the District consider a longer disembarkation/embarkation time such as 15 minutes? A: This would require an increase in turnaround times, which would decrease the number of crossings, as such, lowering capacity of the service. Also, please see answer to question no. 51 above. \\ASTROBOY\data\CDD\PROJECTS - ADDRESS\E\El Portal - Foot\Ferry Landing\ \Joint Hearing \Staff Report and Materials\Questions and Responses from 3-11 Meeting.docx Page 17
FERRY TERMINAL IMPROVEMENTS PROJECT City of Sausalito. 1 st Joint Hearing April 1, 2015
FERRY TERMINAL IMPROVEMENTS PROJECT City of Sausalito Planning Commission/Historic i i Landmarks Board 1 st Joint Hearing April 1, 2015 Golden Gate Ferry Provides Public Transportation Service Between
More informationSAUSALITO FERRY TERMINAL REPLACEMENT PROJECT. Item 5A- PPT Presentation Page 1 of 23
SAUSALITO FERRY TERMINAL REPLACEMENT PROJECT OCTOBER 10, 2017 CITY OF SAUSALITO CITY COUNCIL MEETING Page 1 of 23 PROPOSED PROJECT SUMMARY EXISTING PROPOSED (ACCESS PIER WITHOUT BELVEDERES) Gate Location
More informationTechnical Question and Answer No November 2017 Rachel Rowe, Skagit County Public Works FROM: Will Moon, Glosten JOB/FILE NO
GUEMES ISLAND FERRY REPLACEMENT TO: Rachel Rowe, Skagit County Public Works FROM: Will Moon, Glosten JOB/FILE NO. 17097.01 Specific questions raised by the Ferry Committee Question 1 Will reliability of
More informationSTAFF REPORT. To: Planning Commission Meeting date: April 12, 2017 Item: UN Prepared by: Robert Eastman
# 5 ) UN-15-17 LA SIERRA AUTO SALES SPECIAL USE PERMIT VEHICLE SALES PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: April 12, 2017 Item: UN-15-17 Prepared by: Robert Eastman GENERAL
More informationANDERSON PROPERTY SITE ANALYSIS
ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion
More informationTable Station Elements
The overall layout of the station in the Preferred Alternative (Modified Alternative 2) is described in Table 7.5-1. Table 7.5-1 Station Elements Ground Level Mezzanine Level Platform Level Existing/Upgraded
More informationSTAFF REPORT SAUSALITO CITY COUNCIL
STAFF REPORT SAUSALITO CITY COUNCIL MEETING DATE: AGENDA TITLE: LEAD DEPARTMENT: March 27, 2018 Report on the National Park Service's Proposal for New Ferry Service from Pier 31 ½ in San Francisco to Fort
More informationSan Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors
Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting
More informationPlanning and Green Port Marine Debris Mitigation
Planning and Green Port Marine Debris Mitigation Port Supports Innovative Debris Removal System through Innovation Partnership A new approach to support new technologies to help solve issues facing ports
More informationTRAIN, BUS & TRANSIT
TRAIN, BUS & TRANSIT Input Metra 1 Metra does not want to add parking because of space; maxed out on number of cars per train. Developments on Rt. 59 will affect. 2 Should do studies regarding what the
More informationFunding Scenario Descriptions & Performance
Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion
More informationSPECIAL LEGISLATIVE COMMISSION TO STUDY POTENTIAL ECONOMIC OPPORTUNITIES IN THE DEVELOPMENT OF PORT FACILITIES IN THE STATE OF RHODE ISLAND
Quonset Update April 7, 2011 SPECIAL LEGISLATIVE COMMISSION TO STUDY POTENTIAL ECONOMIC OPPORTUNITIES IN THE DEVELOPMENT OF PORT FACILITIES IN THE STATE OF RHODE ISLAND QUONSET BUSINESS PARK 8,800 Jobs
More informationWhat does Sustainability mean?
Christopher Cannon, Chief Sustainability Officer June 28, 2017 What does Sustainability mean? The ability to meet today s global economic, environmental and social needs without compromising the opportunity
More informationCalifornia s Emission Reduction Plan for Ports and International Goods Movement
California s Emission Reduction Plan for Ports and International Goods Movement Alternative Maritime Power Conference Los Angeles Harbor Hotel April 24, 2006 California Environmental Protection Agency
More informationRECOMMENDATION APPROVED; RESOLUTION NO (PERMIT 930) ADOPTED BY THE BOARD OF HARBOR COMMISSIONERS. August 17, 2017
RECOMMENDATION APPROVED; RESOLUTION NO. 17-8154 (PERMIT 930) ADOPTED BY THE BOARD OF HARBOR COMMISSIONERS August 17, 2017 LA THE PORT OF LOS ANGELES Executive Director's Report to the Board of Harbor Commissioners
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz A Comprehensive Approach to Growing Sustainably Public Investment and Strategies for Existing and Future Population Underway Transit capital and
More informationParking Management Element
Parking Management Element The State Transportation Planning Rule, adopted in 1991, requires that the Metropolitan Planning Organization (MPO) area implement, through its member jurisdictions, a parking
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco 2016 Roads and public transit nearing capacity Increase in cycling and walking despite less than ideal conditions 2 San Francisco
More informationEL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD
EL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD EMERGENCY APPARATUS ACCESS WAYS STANDARD #B-003 EFFECTIVE 05-05-2009 PURPOSE To establish a consistent guideline for fire access roadways required by
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationTerminal Alternatives
Chapter 5 Terminal Alternatives Missoula International Airport Master Plan Update Prepared for Missoula County Airport Authority OCTOBER 2008 Contents Section Page 5 Terminal Alternatives...5-1 5.1 Terminal
More informationNAU DESIGN GUIDELINES FOR DISABLED ACCESS PARKING AND ACCESSIBLE ROUTE AT VEHICULAR TRAFFIC AREAS
NAU DESIGN GUIDELINES FOR DISABLED ACCESS PARKING AND ACCESSIBLE ROUTE AT Intent, Purpose And Goals: The intent and purpose of these NAU technical requirements is to establish minimum requirements to safeguard
More informationSH 249 IN GRIMES COUNTY. Open House April 3, 2014
SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss
More informationIMPROVEMENT CONCEPTS
IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationPreliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae
Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Dominic Spaethling Regional Program Manager Bethany Williams Public Involvement Manager, HNTB April
More informationPublic Information Workshop
Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More informationRegulation Motor Vehicles and Traffic
Regulation - 1.14 Motor Vehicles and Traffic Public Meeting NOVA Parks Fairfax County Park Authority Thursday, February 7, 2019 Background An Emerging Technology E-Bike use has emerged as a viable transportation
More informationMiddle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400
Middle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400 Richard D. Cameron Director of Environmental Planning, Port of Long Beach CEQA/NEPA Process Summary The
More informationMaine Medical Center Campus-Wide Parking Study
Overview Maine Medical Center (MMC) retained VHB to conduct a campus-wide parking study that includes an analysis of demand and supply for patient, visitor, and employee parking on MMC s Bramhall Campus.
More informationLilly Whalen. Sausalito City Council, If we are headed for a similar monster terminal, I urge you to oppose it.
Lilly Whalen From: Sent: To: Subject: Attachments: Vernel Larner Friday, September 22, 2017 4:56 PM City Council Fwd: South San Francisco's WETA Passenger Ferry Terminal Site Visit
More informationCommunity Design Standards
In accordance with the Zoning Ordinance Update Parking and Loading Standards Adopted December 15, 2015 PARKING AND LOADING Sections: 4.1 Purpose and Intent 4.2 Definitions 4.3 Parking Plan Required 4.4
More informationTreasure Island Toll Policy, Affordability and Transit Pass Programs. TIMMA Board Meeting December 11, 2018
Treasure Island Toll Policy, Affordability and Transit Pass Programs TIMMA Board Meeting December 11, 2018 Avoiding Island Gridlock 2 Island Mobility Goals Incentivize transit, walking, and biking Discourage
More informationLetter EL652 City of Mercer Island. Page 1. No comments n/a
Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists
More informationBUS STOP DESIGN & PLANNING GUIDE
BUS STOP DESIGN & PLANNING GUIDE Prepared by the Operations and Planning Departments 2011 PURPOSE OF GUIDE The design of passenger waiting areas plays a significant role in a person s decision of whether
More informationContinued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.
Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS
More informationCOMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT
FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR
More information5 June 12, 2013 Public Hearing APPLICANT: BARTON HERITAGE, LLC T/A SANDBRIDGE BEACH BUGGIES PROPERTY OWNER: LOWER 40, LLC
REQUEST: Conditional Use Permit (motor vehicle rentals low speed vehicles) ADDRESS / DESCRIPTION: 3713 Sandpiper Road 5 June 12, 2013 Public Hearing APPLICANT: BARTON HERITAGE, LLC T/A SANDBRIDGE BEACH
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay
More informationTreasure Island Mobility Management Program
Treasure Island Mobility Management Program Preliminary Toll Policy Recommendations For Buildout Year (2030) Draft TIDA CAB June 2, 2015 About the Treasure Island Mobility Management Program 2003 2008
More informationImproving Accessibility of Regional Bus Stops and Pathways
Customer Service and Operations Committee Board Information Item III-A March 13, 2014 Improving Accessibility of Regional Bus Stops and Pathways Page 3 of 17 Washington Metropolitan Area Transit Authority
More informationDowntown Lee s Summit Parking Study
Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis
More informationWELCOME. Nanaimo Harbour and Gabriola Island Terminal Development Plans (TDPs)
WELCOME Nanaimo Harbour and Gabriola Island Terminal Development Plans (TDPs) Introduction Purpose of this Information Session INFORM you about the Terminal Development Planning process and how to get
More informationDRIVEWAY STANDARDS EXHIBIT A. The following definition shall replace the definition of driveway in Section 62:
1365 S. Camino del Rio Durango, CO 81303 970-382-6363 DRIVEWAY STANDARDS Resolution 2014-40 EXHIBIT A The following definition shall replace the definition of driveway in Section 62: Driveway means a roadway,
More informationLimerick, Colbert Station and Plaza
Limerick, Colbert Station and Plaza Colbert Station Redevelopment Proposed Design April 2014 IARNROD EIREANN ARCHITECTS SECTION 1 LIMERICK, COLBERT The proposal for Colbert Station and Plaza consist of
More informationStrategies to keep people and goods moving in and through Seattle
Strategies to keep people and goods moving in and through Seattle SR 99 Closure and the Seattle Squeeze 2018-2024 DON Information Session Department of Transportation Delridge Community Center November
More informationOFF-STREET PARKING REFORM IN MINNEAPOLIS AND ST. PAUL
OFF-STREET PARKING REFORM IN MINNEAPOLIS AND ST. PAUL MINNESOTA APA October 1, 2014 Minneapolis Zoning Codes 1924 City s first zoning code 1963 City s second zoning code, which included the city s first
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More informationBedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015
Bedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015 SUBJECT: Bedford Amtrak Station Why an Amtrak station in Bedford makes sense. I. BACKGROUND: In January
More information2019 BQDM Extension Auction Frequently-Asked Questions Updated January 29, 2018
2019 BQDM Extension Auction Frequently-Asked Questions Updated January 29, 2018 See 2019 BQDM Extension Auction Technical Requirements for definitions of terms in bold. General Auction Questions 1. How
More informationQUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N
QUALITY OF LIFE EXECUTIVE SUMMARY REPORT UN I O N S TAT I O N T R AV E L by TR A I N Published September 2017 2015 PROGRESS MAP This document reports FasTracks progress through 2015 BACKGROUND RTD The
More informationEMERGENCY ACCESS POLICY
Cowlitz 2 Fire & Rescue Policies and Operating Guidelines Policy: EMERGENCY ACCESS POLICY Number Effective Date Approved and Issued: 4001 8/28/02 8/28/02 1.0 REFERENCE 23 CFR Part 650 Subpart C Code of
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationRailyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY
Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY RAB Citizen Working Group Meeting, August 1 st 2016 CITIZEN WORKING GROUP (CWG)
More informationTHE PORT OF LOS ANGELES OCCUPIES 4,300 ACRES OF LAND ALONG 43 MILES OF WATERFRONT. THE PORT OF LOS ANGELES IS THE LARGEST PORT IN THE
THE PORT OF LOS ANGELES OCCUPIES 4,300 ACRES OF LAND ALONG 43 MILES OF WATERFRONT. THE PORT OF LOS ANGELES IS THE LARGEST PORT IN THE U.S. AND 13TH LARGEST WORLDWIDE. THE PORT OF LONG BEACH IS THE SECOND
More informationCostco Gasoline Fuel Station Transportation Characteristics
Exhibit A MEMORANDUM Date: May 23, 2013 Project #: I-10 To: Jennifer Murillo, Costco Wholesale Terry Odle, Mulvanny G2 Architecture From: Sonia Hennum, PTOE Project: Subject: Signal Hill Costco Gasoline
More informationEXECUTIVE SUMMARY. Introduction
EXECUTIVE SUMMARY Introduction The purpose of this study is to ensure that the Village, in cooperation and coordination with the Downtown Management Corporation (DMC), is using best practices as they plan
More informationRequest for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV
Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Issued: Monday, Site Tour: Friday, January 30, 2015 at 10:00 a.m. Submittal Deadline: 5:00 p.m. on Friday,
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More informationSECTION 500. PARKING, LOADING AND STORAGE REGULATIONS
SECTION 500. PARKING, LOADING AND STORAGE REGULATIONS 501. Off-Street Parking Requirements Intent. The intent of this section is to provide for off-street parking adequate to each type of development in
More informationWillamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee
Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee 05.28.09 09 Bridge Type - Cost Vertical Clearance Bicycle Pedestrian Path Width Bridge Type - Cost WRBAC
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationTHE WAY WE MOVE LRT FOR EVERYONE
THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an
More informationMARINE VESSEL REPOWER APPLICATION
CARL MOYER MEMORIAL AIR QUALITY STANDARDS ATTAINMENT PROGRAM MARINE VESSEL REPOWER APPLICATION Revised 08/2016 1 of 10 CARL MOYER RURAL ASSISTANCE PROGRAM Instruction Sheet The California Air Pollution
More informationThe Jack A. Markell Trail Delaware s Bicycle Highway New England Bike- Walk Summit
The Jack A. Markell Trail Delaware s Bicycle Highway 2018 New England Bike- Walk Summit The Jack A. Markell Trail Sometimes a very difficult project, including significant investment and perseverance,
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationPresentation Overview. Stop, Station, and Terminal Capacity
Stop, Station, and Terminal Capacity Mark Walker Parsons Brinckerhoff Presentation Overview Brief introduction to the project Station types & configurations Passenger circulation and level of service Station
More informationROCHESTER, MINNESOTA
ROCHESTER, MINNESOTA Rochester Public Works TRANSIT AND PARKING DIVISION Transit and Parking Manager Tony Knauer tknauer@rochestermn.gov SERVICE ATTITUDE CONSISTENCY - TEAMWORK ROCHESTER TRANSIT & PARKING
More informationAMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph)
FOR IMMEDIATE RELEASE September 28, 2010 ATK-10-130a Contact: Media Relations 202 906.3860 AMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph)
More informationPace Bus Depot Location Analysis
Pace Bus Depot Location Analysis Key Notes 1. Options refer to conceptual sketches prepared by Kimley Horn. 2. The depot is assumed to accommodate Pace routes as they currently exist: 17 routes on the
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationJCP&L Verbatim Response to Middletown Township s Questions
JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses
More informationSUMMARY AND ANALYSIS: FMCSA Notice of Proposed Rule-Making (NPRM)
SUMMARY AND ANALYSIS: FMCSA Notice of Proposed Rule-Making (NPRM) Minimum Training Requirements for Entry-Level Commercial Motor Vehicle Operators Issued: March 7, 2016 PURPOSE To provide members of NYAPT
More informationWave Power Generating Ships
International Journal of Advancements in Research & Technology, Volume 2, Issue4, April 2013 388 Wave Power Generating Ships Environmental Hazards by ship on port Ships stay on power generated internally
More informationDockless Micromobility Regulatory Framework
Dockless Micromobility Regulatory Framework Transportation and Municipal Infrastructure Committee March 19, 2019 Dockless Micromobility was last discussed at the February 5 th committee meeting TMI committee
More informationPlanning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014
Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential
More informationService Quality: Higher Ridership: Very Affordable: Image:
Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to
More informationUNIVERSITY OF CALIFORNIA, SAN DIEGO
BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSIST ANT VICE CHANCELLOR 9500 GILMAN DRIVE #0916 CAMPUS ARCHITECT- FACILITIES DESIGN
More informationCity of Alameda Capital Improvement Projects Fiscal Years Proposed Project Descriptions
Drainage Southshore Lagoon Dredging $525,000 74 Prepare drawings and design deepening or removal of sediment from lagoons. Marina Village Park $580,500 70 Resolve the drainage issue in the Marina Village
More informationI-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange
I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet
More informationRight-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001
Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas
More informationBi-County Transitway/ Bethesda Station Access Demand Analysis
Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco is a popular place to work, live and visit, straining the existing transportation network Roads and transit vehicles nearing capacity
More informationIncrease Rail Service to the Mid City Green Line Stations
Washington Metropolitan Area Transit Authority Increase Rail Service to the Mid City Green Line Stations P D E C Presented to the Board of Directors: Planning and Development Committee by Planning, Development,
More informationBackground. Request for Decision. Pedestrian Lighting Standards for Road Right-of-ways. Recommendation. Presented: Monday, Mar 17, 2014
Presented To: Operations Committee Request for Decision Pedestrian Lighting Standards for Road Right-of-ways Presented: Monday, Mar 17, 2014 Report Date Thursday, Mar 06, 2014 Type: Presentations Recommendation
More informationFresno County. Sustainable Communities Strategy (SCS) Public Workshop
Fresno County Sustainable Communities Strategy (SCS) Public Workshop Project Background Senate Bill 375 Regional Transportation Plan (RTP) Greenhouse gas emission reduction through integrated transportation
More informationNeeds and Community Characteristics
Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by
More informationAppendix G Aquilla Lake Pool Rise Recreational Resources
Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative
More informationCapital Metro Downtown Multimodal Station
Capital Metro Downtown Multimodal Station Stakeholder Briefing December 11, 2015 Agenda 1 2 3 4 5 Project Summary Downtown Station Concept Evaluation 4 th Street Traffic Analysis 5 th Street Traffic Analysis
More informationJohn Glenn Columbus International Airport. New terminal and midfield development program
John Glenn Columbus International Airport New terminal and midfield development program New airport terminals come around once every few generations. This is our time. It was 1958 when Columbus last opened
More informationTABLE OF CONTENTS 1.0 INTRODUCTION AND SUMMARY Purpose of Report and Study Objectives... 2
TABLE OF CONTENTS 1.0 INTRODUCTION AND SUMMARY 1 1.1 Purpose of Report and Study Objectives... 2 1.2 Executive Summary... 3 1.2.1 Site Location and Study Area... 3 1.2.2 Development Description... 3 1.2.3
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationDockless Micromobility Regulatory Framework
Dockless Micromobility Regulatory Framework Transportation and Municipal Infrastructure Committee February 5, 2019 Dockless Micromobility was introduced at the January 8 th committee meeting TMI committee
More information