1 Capital Metro Downtown Multimodal Station Stakeholder Briefing December 11, 2015

2 Agenda Project Summary Downtown Station Concept Evaluation 4 th Street Traffic Analysis 5 th Street Traffic Analysis Next Steps 2

3 Project Summary Downtown Multimodal Station 3

4 Project Goals & Objectives Address near- and long- term MetroRail operational needs Address existing safety issues and modal conflicts (pedestrian, bicycle, transit, auto) Accommodate future multimodal needs Improve aesthetics and compatibility with urban context 5-minute terminal arrival / departure headway Platforms to accommodate longer 2-vehicle consists Movements of various modes are not compatible in constrained space Additional rail and local circulator routes Great Streets principles PROJECT SUMMARY 4

5 Concept 1 3 platform positions that accommodate (future) 2-car consists Vacate auto access on 4 th St (between Red River and Trinity) Pedestrian and transit queuing Plaza (Neches to Trinity) Lance Armstrong Bikeway (modified for enhanced safety and awareness through platform/plaza area) PROJECT SUMMARY 5

6 Concept 2 3 platform positions that accommodate (future) 2-car consists Shared-use auto/bicycle access on 4 th St (Sabine to Neches) Pedestrian and transit queuing Plaza (Neches to Trinity) Lance Armstrong Bikeway (modified for enhanced safety and awareness through platform/plaza area) PROJECT SUMMARY 6

7 Project Context PROJECT SUMMARY 7

8 Downtown Station Concept Evaluation Downtown Multimodal Station 8

9 Concept Confirmation Process 1 2 Concept Confirmation Strategy Technical Evaluation Criteria Concept Confirmation Process Building Support Public Involvement Public & Stakeholder Input Safety Station Operations Traffic & Accessibility Context Sensitive Compatibility DOWNTOWN STATION CONCEPT EVALUATION 9

10 Concept Confirmation Process Stakeholder/Agency Input Public Input Technical Evaluation Criteria Concept Confirmation Preferred Concept DOWNTOWN STATION CONCEPT EVALUATION 10

11 Building Support Recent Stakeholder Coordination Austin Transportation Department Austin Fire Department, Police Department and EMS Austin Convention Center Austin Energy Hilton Hotel City of Austin Economic Development City of Austin Parks and Recreation City of Austin Public Works City of Austin ROW City of Austin Special Events City of Austin Urban Design / Great Streets City of Austin Watershed Protection Downtown Austin Alliance TxDOT Waller Creek Conservancy DOWNTOWN STATION CONCEPT EVALUATION 11

12 Public & Stakeholder Input Many recognize the benefits of a conflict-free pedestrian space Stakeholders and coordinating agencies in favor of safety improvements and supporting multimodal mobility improvements Some public input has expressed traffic concerns with removing autos from this segment 4 th street. I like the idea of having more pedestrian area. The vehicle lane isn t really that useful anyway. Citizen Feedback I lean more toward this concept to free more space for pedestrians and bikes. Seems like a better use of space but worried about flow of extra traffic displaced from lane of street. Good park space. Concept Preference No Preference 12% Concept 2 19% Concept 1 69% DOWNTOWN STATION CONCEPT EVALUATION 12

13 Concept Confirmation - Technical Evaluation Criteria 1. Safety Station Operations 3. Traffic & Accessibility 4. Context- Sensitive Compatibility a. Mitigation of Multimodal Conflicts b. Rail Crossing Protection Requirements a. MetroRail Station and Platform b. Multimodal Access to Project Area a. Pedestrian, Bicycle and Auto Circulation b. Lane Configurations and Utility a. Mitigate Impacts to Adjacent Projects and Stakeholders b. Great Streets Compatibility c. Stakeholder Accessibility c. Supportive of Future Development DOWNTOWN STATION CONCEPT EVALUATION 13

14 Technical Evaluation Safety Evaluation Metric Multimodal conflict mitigation Emergency access / egress Rail crossing protection Description Concept 1 (Vacate Auto Access on 4 th ) Concept 2 (Restricted Auto Access on 4 th ) Minimize pedestrian / bicycle conflicts through platform boarding area Minimize pedestrian / auto conflicts Minimize bicycle / auto conflicts Supports efficient access / egress to/from platform area Supports efficient access / egress to/from adjacent facilities Minimize train control / signalization needs Minimize intersection crossing protection needs Concept 1 is preferred: Reduces potential automobile conflicts with pedestrians and bicycles Allows wider boarding areas and pedestrian passage at platforms in front of Convention Center and Hilton Austin DOWNTOWN STATION CONCEPT EVALUATION 14

15 Technical Evaluation Station Operations Evaluation Metric MetroRail station platform Multimodal access in project area Description Concept 1 (Vacate Auto Access on 4 th ) Concept 2 (Restricted Auto Access on 4 th ) Number of boarding locations supports CMTA long-term needs Center platform width Minimize station platform access / egress conflicts Auxiliary passenger queuing / ticketing area Proximity of relocated bus stations Metro Bus Operations Car 2 Go access Transit gateway / information / wayfinding Concept 1 is preferred: Fewer multimodal conflicts in near boarding areas & widest possible boarding platform DOWNTOWN STATION CONCEPT EVALUATION 15

16 Technical Evaluation Traffic and Accessibility Evaluation Metric Pedestrian circulation Bicycle circulation Auto circulation Description Appropriate access to and circulation through platform Concept 1 (Vacate Auto Access on 4 th ) Concept 2 (Restricted Auto access on 4 th ) boarding area and plaza Appropriate access to and circulation through platform boarding area and plaza Maintains access to Hilton & Convention Center Austin Energy and Waller Creek (Public Works) access 4th St capacity Maintains auto capacity from Red River to Trinity Concept 1 is preferred: Better pedestrian & bicycle level-of-service in the plaza area with fewest conflicts and best accessibility However, stakeholders have expressed additional access concerns DOWNTOWN STATION CONCEPT EVALUATION 16

17 Technical Evaluation Context Sensitive Compatibility Evaluation Metric Description Concept 1 (Vacate Auto Access on 4 th ) Concept 2 (Restricted Auto access on 4 th ) Stakeholder needs Minimize Convention Center and Hilton Hotel emergency egress conflicts Maintains definition of Lance Armstrong Bikeway Convention Center expansion Supports future development Great Streets compatibility Future development parcel access needs (Perry Lorenz) Sabine St Promenade Dedicated spaces for pedestrian, transit, bicycle and auto uses Walkability, wayfinding, and ease of use Concept 1 is preferred: More consistent with a multimodal vision for bringing all modes together in one place harmoniously DOWNTOWN STATION CONCEPT EVALUATION 17

18 Technical Evaluation Overall Evaluation Metric Concept 1 (Vacate Auto Access on 4th) Concept 2 (Restricted Auto Access on 4 th ) Safety Best reduction of conflicts Auto and bikeway conflicts remain Transit Operations Meets requirements May compromise platform width to fit shared-use lane and emergency access Traffic and Accessibility Reduces auto accessibility Maintains accessibility; requires bikes & autos to share Context Sensitive Compatibility Consistent with multimodal vision & hierarchy Diminishes multimodal vision Concept 1 is the best solution for reducing safety conflicts, meeting transit operational requirements, improving multimodal accessibility, and is consistent with the urban context DOWNTOWN STATION CONCEPT EVALUATION 18

19 Technical Evaluation Overall Concept 1 is the best solution for reducing safety conflicts, meeting transit operational requirements, improving multimodal accessibility, and is consistent with the urban context DOWNTOWN STATION CONCEPT EVALUATION 19

20 4th Street Traffic Evaluation Downtown Multimodal Station 20

21 Traffic Data Collection Video camera set up at the corner of 4th Street and Neches 7-day, 24-hour counts (Thursday 9/3 to 9/10) Data for auto, pedestrian, and bike Historical counts on Cesar Chavez, 5 th, and 6 th Streets 4 TH STREET TRAFFIC ANALYSIS 21

22 Evaluation Findings Part 1 Heavy pedestrian & bicycle volumes Combined more than auto traffic Pedestrian counts only include the intersection of 4th and Neches E-W pedestrian movements along Convention Center sidewalk not included Doesn t take into account the people passing through on MetroRail Restricted vehicular access on 4th Street will provide a better environment for the many pedestrians already using this area Auto & Pedestrian Daily Volumes on 4 th Street Auto, Pedestrian & Bicycle Peak Hourly Volumes on 4 th Street 4 TH STREET TRAFFIC ANALYSIS 22

23 Data Summary Hourly Volumes on Typical Weekday* 1, , Vehicles / Pedestrians per Hour 1, Auto Capacity of 4th Bicycles per Hour 0 0 Time of Day 4th St, E of Neches (WB Auto) 4th Neches (Pedestrian) Cesar Chavez, W of S 1st St (WB Auto) 6th St, W of IH 35 (WB Auto) 4 TH STREET TRAFFIC ANALYSIS 4th Neches (Bicycles) * - Cesar Chavez and 6 th St traffic volumes from City of Austin historical data 23

24 Data Summary Hourly Volumes on Typical Weekday* 1, , Vehicles / Pedestrians per Hour 1, Auto Capacity of 4th Bicycles per Hour 0 0 Time of Day 4th St, E of Neches (WB Auto) 4th Neches (Pedestrian) Cesar Chavez, W of S 1st St (WB Auto) 6th St, W of IH 35 (WB Auto) 4 TH STREET TRAFFIC ANALYSIS 4th Neches (Bicycles) * - Cesar Chavez and 6 th St traffic volumes from City of Austin historical data 24

25 Data Summary Hourly Volumes on Typical Weekend* (Saturday) 1, , Vehicles / Pedestrians per Hour 1,200 1, Auto Capacity of 4th Bicycles per Hour 0 0 Time of Day 4th St, E of Neches (WB Auto) 4th Neches (Pedestrian) Cesar Chavez, W of S 1st St (WB Auto) 6th Red River (WB Auto) 4th Neches (Bicycles) * - Cesar Chavez and 6 th St traffic volumes from City of Austin historical data 4 TH STREET TRAFFIC ANALYSIS 25

26 Data Summary Hourly Volumes on Typical Weekend* (Saturday) 1,600 6 th Street entertainment period lane closure 160 1, Vehicles / Pedestrians per Hour 1,200 1, Auto Capacity of 4th Bicycles per Hour 0 0 Time of Day 4th St, E of Neches (WB Auto) 4th Neches (Pedestrian) Cesar Chavez, W of S 1st St (WB Auto) 6th Red River (WB Auto) 4th Neches (Bicycles) * - Cesar Chavez and 6 th St traffic volumes from City of Austin historical data 4 TH STREET TRAFFIC ANALYSIS 26

27 Evaluation Findings Part 3 Impact on Alternate Routes Traffic time distribution on 4th Street is very different from the rest of the downtown network 4th Street is not a major commuter route Weekday peak period volumes: Street Control Lanes (WB) WB Lane Capacity Late night volumes (entertainment period): WB Total Capacity AM Peak: 8-9a V/C PM Peak: 5-6p 6th Street signal 4 900* ** ** 0.1 4th Street stop sign 1 400* Cesar Chavez signal 2 900* ** ** 0.7 Street Control Lanes (WB) WB Lane Capacity WB Total Capacity Entertainment Peak: 11p-12a 6th Street signal 4 900* th Street stop sign 1 400* Cesar Chavez signal 2 900* ** 0.4 V/C V/C * Based on CAMPO s roadway capacity look-up table ** COA Traffic Data Report 4 TH STREET TRAFFIC ANALYSIS 27

28 5 th Street Traffic Analysis Downtown Multimodal Station 28

29 Data Summary Hourly Volumes on Typical Weekday* 1,600 2-lane, CBD Principal Arterial capacity 1,400 1,200 Vehicles per Hour 1, lane, CBD Local Street capacity th St, E of Neches (WB Auto) Wed '15 Cesar Chavez, W of S 1st St (WB Auto) Wed '13 6th St, W of IH 35 (WB Auto) Mon '11 5th St, W of IH 35 (EB Auto) Thur '09 5th St, E of Red River (EB Auto) Tue '09 * - Cesar Chavez, 5 th St. and 6 th St. traffic volumes from City of Austin historical data 5 TH STREET TRAFFIC ANALYSIS Time of Day 29

30 Data Summary Hourly Volumes on Typical Weekday* 1,600 2-lane, CBD Principal Arterial capacity 1,400 1,200 Vehicles per Hour 1, lane, CBD Local Street capacity th St, E of Neches (WB Auto) Wed '15 Cesar Chavez, W of S 1st St (WB Auto) Wed '13 6th St, W of IH 35 (WB Auto) Mon '11 5th St, W of IH 35 (EB Auto) Thur '09 5th St, E of Red River (EB Auto) Tue '09 * - Cesar Chavez, 5 th St. and 6 th St. traffic volumes from City of Austin historical data 5 TH STREET TRAFFIC ANALYSIS Time of Day 30

31 Data Summary Hourly Volumes on Typical Weekend* (Saturday) 1,600 2-lane, CBD Principal Arterial capacity 1,400 1,200 Vehicles per Hour 1, lane, CBD Local Street capacity TH STREET TRAFFIC ANALYSIS Time of Day 4th St, E of Neches (WB Auto) Sat '15 Cesar Chavez, W of S 1st St (WB Auto) Sat '13 6th Red River (WB Auto) Sat '09 5th St, E of San Jacinto (EB Auto) Sat '03 * - Cesar Chavez, 5 th St. and 6 th St. traffic volumes from City of Austin historical data 31

32 Data Summary Hourly Volumes on Typical Weekend* (Saturday) 1,600 6 th Street entertainment period lane closure 2-lane, CBD Principal Arterial capacity 1,400 1,200 Vehicles per Hour 1, lane, CBD Local Street capacity TH STREET TRAFFIC ANALYSIS Time of Day 4th St, E of Neches (WB Auto) Sat '15 Cesar Chavez, W of S 1st St (WB Auto) Sat '13 6th Red River (WB Auto) Sat '09 5th St, E of San Jacinto (EB Auto) Sat '03 * - Cesar Chavez, 5 th St. and 6 th St. traffic volumes from City of Austin historical data 32

33 Proposed 5 th Street 2-way Conversion Minimum Lane Configuration 2 EB auto lanes, 1 WB auto lane Limits of 2-way conversion (TBD): Trinity to Red River Short Term Solution o Resolves local circulation for Hilton Hotel and Convention Center Congress to IH-35 Long-Term Vision o Opportunity for multimodal repurposing of Downtown arterial; connection to E Austin 5 TH STREET TRAFFIC ANALYSIS 33

34 5 th Street 2-way Conversion Lane Configuration Options - Limits of 2-way conversion - Protected bicycle lanes 5 TH STREET TRAFFIC ANALYSIS 34

35 5 th Street 2-Way Conversion Traffic and Accessibility Concept 1 5 th St. Trinity St. Neches St. Red River St. Sabine St. 4 th St. Elimination of auto/ped. conflict points and reduction of bike conflicts Conversion of Trinity and 5 th St. to two-way has additional accessibility benefits 5 TH STREET TRAFFIC ANALYSIS 35

36 5 th Street 2-Way Conversion Additional Considerations Dedicated LT lanes and signal phases Center turning lane at intersections with high turning movements Additional study needed Repurposing 5 th Street to multimodal priority (pedestrian, bicycle, transit, auto) Bike lane installation in place of parallel parking Convert angled to parallel parking where possible Reduction in parking encourages alternate modes Existing garage/surface parking capacity at Brazos and Red River 5 TH STREET TRAFFIC ANALYSIS 36

37 Next Steps Downtown Multimodal Station 37

38 Concept to Reality 2015 Complete Concept Confirmation Public and Stakeholder Vetting 2016 Final Design Execution of Agreements 2016 CMTA Board Adoption Construction Procurement 2016 City Council Adoption Preliminary Design and Environmental Approval Project Construction 38 NEXT STEPS 38

Making Mobility Better, Together

Making Mobility Better, Together Making Mobility Better, Together Austin Transportation Department Gordon Derr, P.E., for Robert J. Spillar, P.E Director, Austin Transportation Department 1 AUSTIN TRANSPORTATION DEPARTMENT Our Mission

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Green Line Long-Term Investments

Green Line Long-Term Investments Enhancements Short-term improvements to keep Austin moving. Investments Long-term projects to support our future. Mobility Hubs MetroRapid MetroRail MetroExpress Connectors Circulators Project Connect

More information

Click to edit Master title style

Click to edit Master title style Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment

More information

Service Quality: Higher Ridership: Very Affordable: Image:

Service Quality: Higher Ridership: Very Affordable: Image: Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to

More information

Existing Traffic Conditions

Existing Traffic Conditions May 14, 2014 Ms. Lorraine Weiss City of San Mateo 330 West 20 th Avenue San Mateo, CA 94403 Subject: Traffic Operational Study for the Proposed Tilton Avenue Residential Development in San Mateo, California

More information

Kandy Transport Improvement Project (KTIP) Ministry of Defense & Urban Development

Kandy Transport Improvement Project (KTIP) Ministry of Defense & Urban Development Under Strategic Cities Development Project (SCDP) Kandy Transport Improvement Project (KTIP) Ministry of Defense & Urban Development Amal S. Kumarage May 2014 P: 217,678 V: 34,317 P: 8,310 V: 4,051 Map

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

Transportation Sustainability Program

Transportation Sustainability Program Transportation Sustainability Program Photo: Sergio Ruiz San Francisco 2016 Roads and public transit nearing capacity Increase in cycling and walking despite less than ideal conditions 2 San Francisco

More information

CORE AREA SPECIFIC PLAN

CORE AREA SPECIFIC PLAN only four (A, B, D, and F) extend past Eighth Street to the north, and only Richards Boulevard leaves the Core Area to the south. This street pattern, compounded by the fact that Richards Boulevard is

More information

Traffic Feasibility Study

Traffic Feasibility Study Traffic Feasibility Study Town Center South Robbinsville Township, Mercer County, New Jersey December 19, 2017 Prepared For Robbinsville Township Department of Community Development 2298 Route 33 Robbinsville,

More information

Jihong Cao, PE, Parsons Brinckerhoff Arnab Gupta, PE, Parsons Brinckerhoff Jay Yenerich, PE, Valley Metro

Jihong Cao, PE, Parsons Brinckerhoff Arnab Gupta, PE, Parsons Brinckerhoff Jay Yenerich, PE, Valley Metro Jihong Cao, PE, Parsons Brinckerhoff Arnab Gupta, PE, Parsons Brinckerhoff Jay Yenerich, PE, Valley Metro Outline Background Predictive Priority Algorithm Simulation Analysis Measure of Effectives (MOE)

More information

CTA Blue Line Study Area

CTA Blue Line Study Area CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

Escondido Marriott Hotel and Mixed-Use Condominium Project TRAFFIC IMPACT ANALYSIS REPORT

Escondido Marriott Hotel and Mixed-Use Condominium Project TRAFFIC IMPACT ANALYSIS REPORT Escondido Marriott Hotel and Mixed-Use Condominium Project TRAFFIC IMPACT ANALYSIS REPORT Prepared for Phelps Program Management 420 Sixth Avenue, Greeley, CO 80632 Prepared by 5050 Avenida Encinas, Suite

More information

Address Land Use Approximate GSF

Address Land Use Approximate GSF M E M O R A N D U M To: Kara Brewton, From: Nelson\Nygaard Date: March 26, 2014 Subject: Brookline Place Shared Parking Analysis- Final Memo This memorandum presents a comparative analysis of expected

More information

Agenda. Preliminary Station Footprint High Speed Train Station in the City of Millbrae

Agenda. Preliminary Station Footprint High Speed Train Station in the City of Millbrae Agenda Preliminary Station Footprint High Speed Train Station in the City of Millbrae Open House 7:00 7:30 Presentation 7:30 8:00 Community Question/Answer 8:00 9:00 Adjourn 2 Preliminary Station Footprint

More information

SERVICE DESIGN GUIDELINES

SERVICE DESIGN GUIDELINES VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation

More information

Background Information about the Metrobus 29 Lines Study

Background Information about the Metrobus 29 Lines Study Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and

More information

L. A. Metro s Parking Management Program Principles Applied. October 17, 2011 Rail-Volution, Washington D.C.

L. A. Metro s Parking Management Program Principles Applied. October 17, 2011 Rail-Volution, Washington D.C. Los Angeles County Metropolitan Transportation Authority L. A. Metro s Parking Management Program Principles Applied October 17, 2011 Rail-Volution, Washington D.C. What is Parking Management? Various

More information

VAN NESS AVENUE BUS RAPID TRANSIT

VAN NESS AVENUE BUS RAPID TRANSIT VAN NESS AVENUE BUS RAPID TRANSIT Peter Gabancho Project Manager III Capital Programs & Construction SFMTA Shari Tavafrashti Principal Engineer SFCTA 1 Project Purpose and Need Improve transit reliability,

More information

Diablo Vista Pumping Plant Replacement

Diablo Vista Pumping Plant Replacement Diablo Vista Pumping Plant Replacement Traffic Study PHA Transportation Consultants 12-05-359 October 2012 Diablo Vista Pumping Plant Replacement Traffic Study For EBMUD October 2012 PHA Transportation

More information

Proposed Program of Interrelated Projects

Proposed Program of Interrelated Projects DALLAS AREA RAPID TRANSIT Proposed Program of Interrelated Projects Federal Transit Administration Capital Investment Program Summer 204 INTRODUCTION The current federal transportation bill, Moving Ahead

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting

More information

Lacey Gateway Residential Phase 1

Lacey Gateway Residential Phase 1 Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West

More information

TABLE OF CONTENTS SECTION PAGE. Executive Summary... xii

TABLE OF CONTENTS SECTION PAGE. Executive Summary... xii TABLE OF CONTENTS SECTION PAGE Executive Summary... xii 1.0 Introduction... 1 1.1 Study Area... 2 1.2 Traffic Impact Analysis Scenarios... 4 1.3 Study Area - City of Orange... 4 2.0 Project Description

More information

AUDI URBAN PARTNERSHIP

AUDI URBAN PARTNERSHIP Smart Mobility How Technological Innovations are Streamlining the Way We Move NASEO Providence, RI, September 13, 2016 AUDI URBAN PARTNERSHIP City of Somerville, MA Janne Corneil Corneil Collaborative,

More information

Tempe Streetcar. March 2, 2016

Tempe Streetcar. March 2, 2016 Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

Knoxville Area Transit (KAT) Transit Development Plan Downtown Transit Plan

Knoxville Area Transit (KAT) Transit Development Plan Downtown Transit Plan Knoxville Area Transit (KAT) Transit Development Plan Submitted to: Knoxville Area Transit and Knoxville Knox County Metropolitan Planning Commission Submitted by: Connetics Transportation Group Under

More information

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Site Evaluation & Recommendation. October 18, 2016

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Site Evaluation & Recommendation. October 18, 2016 MANASSAS PARK STATION PARKING EXPANSION Site Evaluation & Recommendation October 18, 2016 1 INFORMATION ITEM Project Overview Parking Demand Site Evaluation VRE Recommended Preferred Alternative Next Steps

More information

Intermodal Regional Planning INTERCITY BUS PILOT PROGRAM. October 1, 2010 Presentation Bob Kuhns, Clark Nexsen (Washington, DC)

Intermodal Regional Planning INTERCITY BUS PILOT PROGRAM. October 1, 2010 Presentation Bob Kuhns, Clark Nexsen (Washington, DC) Intermodal Regional Planning INTERCITY BUS PILOT PROGRAM October 1, 2010 Presentation Bob Kuhns, Clark Nexsen (Washington, DC) Intercity Bus (Service) Features FTA Definition Over-the-road bus Regularly

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

Basic Project Information

Basic Project Information FY 2015-16 PROJECT DESCRIPTION FORM (7B) Submitting Agency: Fairfax County Basic Project Information Project Title: South Van Dorn Street and Franconia Road Interchange 7B Project Type (check one): Roadway

More information

Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville

Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville 1. Introduction During the stakeholder input sessions of Charlottesville Area Transit s (CAT) Transit Development

More information

Link Light Rail Operations and Maintenance Satellite Facility

Link Light Rail Operations and Maintenance Satellite Facility September 2015 Link Light Rail Operations and Maintenance Satellite Facility TRANSPORTATION TECHNICAL REPORT Appendix E1 Central Puget Sound Regional Transit Authority Appendix E.1 TABLE OF CONTENTS PROJECT

More information

DETAILED DEFINITION OF ALTERNATIVES. July 2014 FINAL

DETAILED DEFINITION OF ALTERNATIVES. July 2014 FINAL DETAILED DEFINITION OF ALTERNATIVES July 2014 Table of Contents 1.0 Introduction... 1 1.1 Detailed Mode Alternatives... 1 1.2 Detailed Alignment Alternatives... 1 1.3 Key Physical and Service Elements...

More information

The Smart Growth Countywide Transit Master Plan

The Smart Growth Countywide Transit Master Plan Choose the Future The Smart Growth Transit Master Plan What is the Transit Master Plan? A robust and integrated plan to establish countywide public transportation priorities over the next thirty years

More information

Railroad Impact Study

Railroad Impact Study Railroad Impact Study Ryan Huebschman, PE, PTOE Jason O Neill November 21, 2016 Study Impetus CSXT to lease and improve rail line between Louisville and Indianapolis Rail improvements will allow CSXT to

More information

Exposition Corridor Transit Project

Exposition Corridor Transit Project Exposition Corridor Transit Project Phase 2 Environmental Planning Community Meeting June 9, 2008 Exposition Corridor Transit Project Phase 2 AGENDA Remaining Grade Crossing Recommendations June 9, 2008

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

Halifax Commuter Rail Feasibility Study

Halifax Commuter Rail Feasibility Study Halifax Commuter Rail Feasibility Study Open House Halifax Regional Municipality February 26, 2015 Study Team The team is led by CPCS: A global management consulting firm (formerly the consulting arm of

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting August 2, 2011 Introduction Key players Local lead agency: Metro Federal lead agency: Federal

More information

Transit Hub Case Study: Owings Mills Metro Station. By: Kathleen Cary Rose, J. Luke Byrne and Catherine Buhler

Transit Hub Case Study: Owings Mills Metro Station. By: Kathleen Cary Rose, J. Luke Byrne and Catherine Buhler Executive Summary Transit Hub Case Study: Owings Mills Metro Station By: Kathleen Cary Rose, J. Luke Byrne and Catherine Buhler The purpose of the Transit Hub Case Study is to identify and evaluate the

More information

What We Heard. Edmontonians in communities Northwest of City Centre share their vision of the Metro Line NW LRT Expansion

What We Heard. Edmontonians in communities Northwest of City Centre share their vision of the Metro Line NW LRT Expansion What We Heard Edmontonians in communities Northwest of City Centre share their vision of the Metro Line NW LRT Expansion Overview The Metro Line NW LRT is part of the City s Transportation Master Plan

More information

PROJECT SCHEDULE. Plan for Implementation. Explore and Analyze. Refine Ideas. Identify Common Ideas SPRING 2016 SUMMER 2016 FALL 2016

PROJECT SCHEDULE. Plan for Implementation. Explore and Analyze. Refine Ideas. Identify Common Ideas SPRING 2016 SUMMER 2016 FALL 2016 VISION WORKSHOP MAY 25 th 2016 A COLLABORATION PROJECT SCHEDULE Explore and Analyze Identify Common Ideas Refine Ideas Plan for Implementation SPRING 2016 SUMMER 2016 FALL 2016 TODAY S AGENDA Explore and

More information

Stittsville OC Transpo Services

Stittsville OC Transpo Services Stittsville OC Transpo Services Transportation Services Department March 22, 2018 0 Ottawa s Transit Challenge 1 1 What s Coming in 2018 O-Train Network 2 2 Confederation Line - Alignment 3 3 VEHICLE AND

More information

Metropolitan Freeway System 2013 Congestion Report

Metropolitan Freeway System 2013 Congestion Report Metropolitan Freeway System 2013 Congestion Report Metro District Office of Operations and Maintenance Regional Transportation Management Center May 2014 Table of Contents PURPOSE AND NEED... 1 INTRODUCTION...

More information

2. Valley Circle Boulevard/Andora Avenue/Baden Avenue and Lassen Street

2. Valley Circle Boulevard/Andora Avenue/Baden Avenue and Lassen Street IV.J TRANSPORTATION 1. INTRODUCTION This section presents an overview of the existing traffic and circulation system in and surrounding the project site. This section also discusses the potential impacts

More information

State Avenue Corridor Bus Rapid Transit (BRT)

State Avenue Corridor Bus Rapid Transit (BRT) State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!

More information

Harrisburg Station Location Study. Allan Paul Deputy Director NCDOT Rail Division 9 th February 2015

Harrisburg Station Location Study. Allan Paul Deputy Director NCDOT Rail Division 9 th February 2015 Harrisburg Station Location Study Allan Paul Deputy Director NCDOT Rail Division 9 th February 2015 NCDOT Rail Division Who We Are Six state-supported passenger trains Carolinian: Charlotte - Raleigh -

More information

APPENDIX B Traffic Analysis

APPENDIX B Traffic Analysis APPENDIX B Traffic Analysis Rim of the World Unified School District Reconfiguration Prepared for: Rim of the World School District 27315 North Bay Road, Blue Jay, CA 92317 Prepared by: 400 Oceangate,

More information

Start Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA

Start Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA Tube Counts Type of report: Tube Count - Volume Data LOCATION: Scotts Valley Dr QC JOB #: 245667 SPECIFIC LOCATION: ft from Tabor St DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA DATE: Mar 2 24 - Mar

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC

IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC The following section summarizes the information provided in the traffic report entitled Traffic Impact Analysis for a Proposed Residential

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014 Midtown Corridor Alternatives Analysis Policy Advisory Committee Meeting February 12, 2014 Today s Agenda Introductions Outreach efforts and survey results Other updates since last meeting Evaluation results

More information

State Route 1/State Route 41/ Main Street Intersection Control Evaluation (Step 2) Report. City of Morro Bay. Prepared for: Prepared by:

State Route 1/State Route 41/ Main Street Intersection Control Evaluation (Step 2) Report. City of Morro Bay. Prepared for: Prepared by: State Route 1/State Route 41/ Main Street Intersection Control Evaluation (Step 2) Report Prepared for: City of Morro Bay Prepared by: (Caltrans Project No. 0515000104, EA 0F670) State Route 1/State Route

More information

Mr. Kyle Zimmerman, PE, CFM, PTOE County Engineer

Mr. Kyle Zimmerman, PE, CFM, PTOE County Engineer Los Alamos County Engineering Division 1925 Trinity Drive, Suite B Los Alamos, NM 87544 Attention: County Engineer Dear Kyle: Re: NM 502 Transportation Corridor Study and Plan Peer Review Los Alamos, New

More information

Essex Junction Train Station Access and Scoping Study Discussion of Transportation Alternatives

Essex Junction Train Station Access and Scoping Study Discussion of Transportation Alternatives Essex Junction Train Station Access and Scoping Study Discussion of Transportation Alternatives Village of Essex Junction Chittenden County Regional Planning Commission, Inc. Scott & Partners Architectural

More information

NEW YORK CITY CARSHARE PILOT

NEW YORK CITY CARSHARE PILOT NEW YORK CITY CARSHARE PILOT Community Board Briefing June 2017 1 Concept and Context 1 nyc.gov/dot 2 CHALLENGE OF CONTINUED GROWTH The City must use its streets as efficiently as possible to move people

More information

Traffic Impact Study for Proposed Olive Boulevard Development

Traffic Impact Study for Proposed Olive Boulevard Development Traffic Impact Study for Proposed 11330 Olive Boulevard Development Creve Coeur, Missouri July 7, 2017 Prepared For: 11330 Olive Boulevard Development 11330 Olive Boulevard Creve Coeur, Missouri 63141

More information

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010 BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1

More information

Kendall Drive Premium Transit PD&E Study

Kendall Drive Premium Transit PD&E Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study From

More information

DART Capital Program Update

DART Capital Program Update DART Capital Program Update CMAA North Texas April 30, 2015 David Ehrlicher Assistant Vice President, Program Delivery Overview of DART System Multimodal System: 120 + bus routes 90 miles of Light Rail

More information

Madison BRT Transit Corridor Study Proposed BRT Operations Plans

Madison BRT Transit Corridor Study Proposed BRT Operations Plans Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

Sustainability SFMTA Path to Platinum

Sustainability SFMTA Path to Platinum Sustainability SFMTA Path to Platinum Ed Reiskin San Francisco Municipal Transportation Agency, Director of Transportation San Francisco, CA Timothy Papandreou Deputy Director Strategic Planning & Policy

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1.

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1. DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Subhas Bhargava July 9, 2015 115-620 Overview_1.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

COMMISSION WORKSHOP Tuesday, May 12, :00 a.m. 12:00 p.m.

COMMISSION WORKSHOP Tuesday, May 12, :00 a.m. 12:00 p.m. COMMISSION WORKSHOP Tuesday, 9:00 a.m. 12:00 p.m. AGENDA 1. Approval of the April 30, 2009 Workshop Minutes 2. Community Redevelopment Agency a. CRA Master Plan Update b. Downtown Parking Study 3. Economic

More information

Orange Line Bus Rapid Transit Project Plan Update. Metro Transit June 2014 D R A F T

Orange Line Bus Rapid Transit Project Plan Update. Metro Transit June 2014 D R A F T Orange Line Bus Rapid Transit Metro Transit D R A F T Contents 1 Background 4 2 Scope 6 2.1 Mode 2.2 Stations 2.3 Guideway 2.4 Right of Way Needs 2.5 Technology 2.6 Fare Collection 2.7 Branding and Marketing

More information

Proposed Inn at Bellefield Traffic Impact Assessment

Proposed Inn at Bellefield Traffic Impact Assessment Proposed Inn at Bellefield Traffic Impact Assessment Town of Hyde Park Dutchess County, New York Prepared for: T-Rex Hyde Park Owner LLC 500 Mamroneck Avenue, Suite 300 Harrison, NY 10528 June 21, 2017

More information

FINAL TECHNICAL MEMORANDUM

FINAL TECHNICAL MEMORANDUM Metro Amherst-Buffalo Corridor TIER 3 SCREENING RESULTS FINAL TECHNICAL MEMORANDUM Prepared for: Niagara Frontier Transportation Authority (NFTA) Prepared by: AECOM USA, Inc. In Association with Wendel

More information

ENVIRONMENTAL IMPACT ANALYSIS J. TRAFFIC, CIRCULATION AND ACCESS

ENVIRONMENTAL IMPACT ANALYSIS J. TRAFFIC, CIRCULATION AND ACCESS IV. ENVIRONMENTAL IMPACT ANALYSIS A traffic study was prepared for the Proposed Project by Linscott, Law & Greenspan, Engineers, dated August 5, 2008 (see Appendix I: Traffic Study). The traffic study

More information

Impact of Copenhagen s

Impact of Copenhagen s Impact of Copenhagen s Parking Strategy Copenhagen s parking strategy Strategy background From the 1950s, a marked increase was seen in car traffic, and streets and squares in the centre of Copenhagen

More information

Navigating in Different Rivers

Navigating in Different Rivers Navigating in Different Rivers Suburban TOD Julie Jones, Planning Manager, City of Fridley Julie Farnham, Senior Planner, City of Bloomington Kersten Elverum, Director of Planning & Development, City of

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Public Meeting. June 15, :30 7:30 p.m.

Public Meeting. June 15, :30 7:30 p.m. Public Meeting June 15, 2017 5:30 7:30 p.m. Welcome 2015 Naval Station Norfolk Transit Extension Study 2015 Naval Station Norfolk Transit Extension Study 2017 Norfolk Westside Transit Study HRT and the

More information

Travel Demand Modeling at NCTCOG

Travel Demand Modeling at NCTCOG Travel Demand Modeling at NCTCOG Arash Mirzaei North Central Texas Council Of Governments for Southern Methodist University The ASCE Student Chapter October 24, 2005 Contents NCTCOG DFW Regional Model

More information

Streetcar Level Boarding Background Memo

Streetcar Level Boarding Background Memo Level Boarding Background Memo Introduction This memo has been prepared by the and the Community Coalition to facilitate industry discussion on the application of level boarding concepts to US modern streetcar

More information

Parking & TOD around BART Stations. Jessica ter Schure November 1, 2009 Rail~Volution 2009 Boston, Massachusetts

Parking & TOD around BART Stations. Jessica ter Schure November 1, 2009 Rail~Volution 2009 Boston, Massachusetts Parking & TOD around BART Stations Jessica ter Schure November 1, 2009 Rail~Volution 2009 Boston, Massachusetts Outline Background Replacement Parking Policy South Hayward BART MacArthur BART Parking Privatization

More information

Connect. Thrive. Develop. KC Streetcar Riverfront Extension & Multi-Modal Feasibility Study

Connect. Thrive. Develop. KC Streetcar Riverfront Extension & Multi-Modal Feasibility Study Connect. Thrive. Develop. Why go to the Riverfront? KC Streetcar is a proven catalyst for development & connecting people to Downtown. < $2 billion in adjacent development: new businesses, hotels, apartments

More information

Appendix A. Project Development Decision Points

Appendix A. Project Development Decision Points Appendix A Project Development Decision Points DRAFT TECHNICAL MEMORANDUM APPENDIX A-1: PROJECT DEVELOPMENT DECISION POINTS To: Jay Kline, AICP DART Project Manager From: Jerry Smiley, AICP Project Manager

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

4.11 TRANSPORTATION AND CIRCULATION

4.11 TRANSPORTATION AND CIRCULATION 4.11 TRANSPORTATION AND CIRCULATION This section analyzes onsite development s impacts to the local transportation and circulation system. The analysis is based upon the traffic study prepared by KOA Corporation

More information

Rail~Volution 2012 R. Gregg Albright

Rail~Volution 2012 R. Gregg Albright CALIFORNIA HIGH-SPEED RAIL AUTHORITY October 16 th, 2012 Rail~Volution 2012 R. Gregg Albright WHAT IS CALIFORNIA HIGH-SPEED TRAIN PROJECT (CHSTP) and HOW WILL IT BE IMPLEMENTED? 2 CALIFORNIA HIGH SPEED

More information

LAST MILE / TERMINAL AREA PLANNING ISSUES WEBINAR SUMMARY AASHTO RAIL RESOURCE CENTER JULY 12, 2017

LAST MILE / TERMINAL AREA PLANNING ISSUES WEBINAR SUMMARY AASHTO RAIL RESOURCE CENTER JULY 12, 2017 LAST MILE / TERMINAL AREA PLANNING ISSUES WEBINAR SUMMARY AASHTO RAIL RESOURCE CENTER JULY 12, 2017 Introductory Comments Randy Wade HNTB Corporation On July 12, 2017, the AASHTO Rail Resource Center hosted

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

830 Main Street Halifax Regional Municipality

830 Main Street Halifax Regional Municipality 830 Main Street Halifax Regional Municipality Traffic Impact Statement Final Report Prepared by: GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 www.griffininc.ca Prepared

More information

Amman Green Policies Projects and Challenges. Prepared by: Eng. Sajeda Alnsour Project coordinator Sept. 20, 2017

Amman Green Policies Projects and Challenges. Prepared by: Eng. Sajeda Alnsour Project coordinator Sept. 20, 2017 Amman Green Policies Projects and Challenges Prepared by: Eng. Sajeda Alnsour Project coordinator Sept. 20, 2017 Amman: Demographics Greater AMMAN Municipality GAM Amman is the capital of Jordan with a

More information

Section 3.12 Traffic and Transportation

Section 3.12 Traffic and Transportation Section. Traffic and Transportation SECTION SUMMARY This section describes existing ground transportation within the Port and surrounding area associated with implementation of the proposed Project. An

More information

February 2012 Caltrain Annual Passenger Counts Key Findings

February 2012 Caltrain Annual Passenger Counts Key Findings February 2012 Caltrain Annual Passenger Counts Key Findings Key Findings February 2012 Caltrain Annual Passenger Counts The 2012 annual Caltrain passenger counts, which were conducted in February 2012,

More information

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease

More information

TRAFFIC IMPACT ANALYSIS. for MILTON SQUARE

TRAFFIC IMPACT ANALYSIS. for MILTON SQUARE TRAFFIC IMPACT ANALYSIS for MILTON SQUARE US Route 7 Milton, Vermont March 5, 2008 LAMOUREUX & DICKINSON 14 Morse Drive Essex Junction, Vermont 05452 (802) 878-4450 Traffic Impact Assessment EXECUTIVE

More information

Traffic Impact Statement (TIS)

Traffic Impact Statement (TIS) Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205

More information

CTA Blue Line Study Area

CTA Blue Line Study Area 1 CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas

More information

MBTA Key Bus Route Improvement Program. Community Meeting Route 66 Allston/Brighton

MBTA Key Bus Route Improvement Program. Community Meeting Route 66 Allston/Brighton MBTA Key Bus Route Improvement Program Community Meeting Route 66 Allston/Brighton January 19, 2011 Honan-Allston Library 300 North Harvard Street Agenda Welcome and introductions Safety briefing/accommodations

More information