2.0 ALTERNATIVES CONSIDERED

Size: px
Start display at page:

Download "2.0 ALTERNATIVES CONSIDERED"

Transcription

1 Alternatives Considered 2.0 ALTERNATIVES CONSIDERED The alternatives considered for the East Corridor are the result of agency involvement and extensive public outreach, described in Chapter 6, Public Comment and Agency Coordination, combined with detailed environmental and technical analysis. This chapter summarizes: The process used to define the goals, objectives, and evaluation criteria Development and screening of alternatives including transit alignments, station locations, and transit technologies Alternatives that were considered during the analysis but eliminated The No-Action Alternative The Transportation System Management (TSM) Alternative The Preferred Alternative and design options The commuter rail maintenance facility (CRMF) The estimated costs including capital, operation, and maintenance 2.1 SCOPING AND SCREENING OF ALTERNATIVES Numerous alternatives were proposed as transportation improvements. The project team developed these alternatives based on input from the community and affected agencies, previous studies, and new concepts. To help establish the transportation and environmental issues in the project area, project scoping was completed with stakeholders, the community, cooperating agencies, and others. Based on scoping and as defined in Chapter 1, Purpose and Need, the project purpose and need were developed and served as the basis for project-specific goals and objectives. These goals and objectives were then used to develop specific evaluation criteria that allowed for the comparison of alternatives and the determination of the Preferred Alternative for the East Corridor. The Preferred Alternative best addresses the transportation needs in the area while minimizing potential impacts on the community and environment. Table 2-1 lists the goals and objectives and the criteria used in the various screening levels Screening Process A four-level screening process, shown in Figure 2-1, was used to reduce the range of alternatives considered to the selection of the Preferred Alternative. Alternatives were evaluated with increasing levels of detailed analysis at each screening level: initial screening, comparative screening, detailed screening, and alternative refinement. Cost comparisons were occasionally used in the screening process at various levels. While the assumptions and costs may have changed, the results are still valid. September

2 Alternatives Considered Figure 2-1 Alternative Screening Process 2-2 September 2009

3 Alternatives Considered Table 2-1 Goals, Objectives, and Evaluation Criteria Goals Access (A) Provide for reasonable access to transportation facilities Capacity (CA) Provide for realistic capacity expansion and minimize future congestion Community (CO) Support community plans and avoid, minimize, and mitigate impacts to neighborhoods Objectives Balance the need for access with adverse affects on system performance A1 Bring together multiple transportation modes to maximize convenience, flexibility, and connectivity A2 Provide access to transportation facilities for a variety of users A3 Address additional capacity requirements by providing multi-modal choices CA1 Provide sufficient transportation system capacity to ensure the efficient movement of people CA2 Maximize consistency with existing local, regional, and state plans CO1 Minimize adverse impacts to residential, business, and institutional properties CO2 Minimize adverse economic impacts to local businesses CO3 Allow for economic development opportunities CO4 Address transportation-related community impacts associated with air quality, water quality, hazardous materials, and noise CO5 Allow for transit-oriented development (TOD) opportunities CO6 Evaluation Criteria 1. Initial Screening 2. Comparative Screening 3. Detailed Screening 4. Alternative Refinement Does the alternative provide adequate transportation access to and through the corridor? (A3) Does the alternative provide the ability to implement the general intent of local plans and policies? (CO1) Provides access to local residences, businesses, and activity centers within the corridor (A3) Balances local access with system performance (A1) Satisfies future system capacity needs (CA1,2) Meets the intent of existing local, regional, and state plans (CO1,4) Minimizes potential residential displacement/disruption (CO2) Minimizes potential business displacement/disruption (CO2) Minimizes potential institutional property displacement/disruption (CO2) Provides consistency of adjacent land use with TOD principles (CO6) Transit travel time between key activity centers (A1,M1) Population and employment within 0.5 mile of a transit station (A3) Population and employment within 0.25 mile of local bus service (A3) Number of linked transit trips (CA1) Meets the intent of existing local, regional, and state plans (CO1) Number of residential properties potentially physically affected (CO2) Number of institutional properties potentially physically affected (CO2) Number of business properties potentially physically affected (CO2,3) Community sentiment on the relationship between the alternative and neighborhood character (CO5) Engineering feasibility Environmental resourcespecific evaluation Cost analysis Note: Objectives are represented by alphabetical and numerical descriptors (e.g., A1) to simplify tracking throughout the screening process. The description in the parenthesis after each screening criteria (e.g., A1) shows which objective the criteria represents. September

4 Alternatives Considered Table 2-1 Goals, Objectives, and Evaluation Criteria Goals Environment (E) Avoid, minimize, and mitigate adverse impacts to the natural, social, and cultural environment Implementation (IM) Provide a costeffective transportation solution that can be implemented Objectives Minimize adverse impacts to historic resources E1 Ensure consistency with regional air quality model to help achieve federal and state air quality standards E2 Minimize disproportionately high and adverse impacts on minority and lowincome populations E3 Minimize adverse impacts to waters of the U.S., including wetlands E4 Minimize adverse impacts to recreational and open-space resources E5 Minimize public exposure to highway and transit noise and transit vibration impacts E6 Minimize adverse impacts associated with hazardous materials E7 Incorporate design standards that minimize visual impacts and enhance aesthetics E8 Provide a cost-effective, long-term transportation solution IM1 Provide flexibility for future expansion and modification IM2 Provide technologies that are practical and implementable IM3 Maximize the opportunity that federal, state, local, and/or private funding will be available to fund improvements IM4 Evaluation Criteria 1. Initial Screening 2. Comparative Screening 3. Detailed Screening 4. Alternative Refinement Does the alternative avoid clearly unacceptable environmental impacts? (All) Is the alternative a proven technology in a comparable application? (IM3) Minimizes potential impacts to historic resources (E1) Minimizes potential impacts to natural resources (E2,4,5,7) Minimizes potential impacts to natural resources (E3,6,8) Minimizes project cost (All) Facilitates ease of construction (IM1,3) Facilitates ease of operation and maintenance (IM1,4) Accommodates the potential for future transportation improvements consistent with local, regional, and state transportation plans (IM2) Number of historic resources potentially affected (E1) Tons of mobile source emissions (E2) Amount of minority and lowincome population potentially affected (E3) Acres of waters of the U.S., including wetlands potentially affected (E4) Acres of recreational and open space potentially affected (E5) Number of residential, business, and sensitive properties exposed to noise and/or vibration levels that exceed federal standards (E6) Number and nature of known hazardous material sites potentially affected (E7) Potential visual affects of alternatives (E8) Total estimated capital cost (IM1) Estimated annual operation and maintenance cost (IM1) Estimated cost per passenger mile (IM1,3) Estimated cost per rider (includes annualized operations, maintenance, and capital costs) (IM1,3) Mobility (M) Enhance mobility by providing transportation choices Facilitate connections between residential and business activity centers M1 Facilitate ease of transfer between modes M2 Provide convenient, multi-modal transportation options M3 Enhance system reliability across travel modes M4 Balance the transportation needs of local, regional, and national users M5 Does the alternative avoid precluding existing or planned transportation system improvements? (All) Reduces travel delay and congestion (M4,M5) Improves system reliability (M4,M5) Allows the ability to accommodate adverse weather conditions (M4) Number of modes available at strategic locations (M2,3,5,A2) Average wait time for transfers between modes (M2,4,5,A2) Note: Objectives are represented by alphabetical and numerical descriptors (e.g., A1) to simplify tracking throughout the screening process. The description in the parenthesis after each screening criteria (e.g., A1) shows which objective the criteria represents. 2-4 September 2009

5 Alternatives Considered Table 2-1 Goals, Objectives, and Evaluation Criteria Goals Safety (SA) Address safety needs and upgrade facilities to current standards Security (SE) Provide a secure transportation system Objectives Optimize safety and minimize accidents across all modes SA1 Conform with engineering design and safety standards and with standard practices for construction, maintenance, and operations SA2 Minimize cross modal conflicts and conflict points SA3 Provide access for emergency response and evacuation situations SA4 Maintain maximum security measures regarding access to DIA SE1 Develop and maintain a transportation system that supports national homeland security objectives SE2 Evaluation Criteria 1. Initial Screening 2. Comparative Screening 3. Detailed Screening 4. Alternative Refinement Does the alternative address existing safety issues? (All) Does the alternative support homeland security objectives? (SE2) Conforms with engineering design and safety standards (SA2) Addresses emergency response needs (SA4) Provides the ability to meet Transportation Security Administration standards for transit access to DIA (SE2) Number of instances where minimum design standards were used (SA2) Number of conflict points between modes (transit, highway, pedestrian, bicycle) (SA3) Number and type of critical design features that are potential security risks (SE1) Ability to meet Transportation Security Administration standards for transit access to DIA (SE2) Note: Objectives are represented by alphabetical and numerical descriptors (e.g., A1) to simplify tracking throughout the screening process. The description in the parenthesis after each screening criteria (e.g., A1) shows which objective the criteria represents. September

6 Alternatives Considered This page intentionally left blank. 2-6 September 2009

7 Alternatives Considered Initial Screening (Level One) Alternatives were evaluated within categories for initial screening and comparative screening levels. The first level of evaluation, initial screening, was a reality check that eliminated transit alignment, technology, and station location alternatives that did not have a realistic chance of being designed and built because they would either result in significant environmental impacts, were not located in the project area, or were not a technology that was in revenue service. A series of yes-or-no questions were used to evaluate alternatives during this step. Alternatives not eliminated in initial screening were refined and evaluated in comparative screening. Comparative Screening (Level Two) Comparative screening continued to look at transit alignments and technologies relative to each other within categories to determine if some were clearly better than others. A qualitative (good 1/better 3/best 5) approach was used to identify the alternatives in each category that were more effective at meeting the purpose and need. Detailed Screening (Level Three) Alignments, station locations, and technologies remaining after comparative screening were combined to create several corridor-wide transit alternatives for analysis in detailed screening. A quantitative (measure-based) analysis was used to identify the strengths and weaknesses of the alternatives. Alternative Refinement (Level Four) Alternatives that remained after detailed screening were developed in more detail and further analyzed as part of alternative refinement. The evaluation was more in depth than the detailed screening analysis and was used to determine the alternatives most responsive to the project purpose and need. This fourth level of screening considered engineering feasibility; potential impacts on social, environmental, and economic resources; and an analysis of capital, operation, and maintenance costs Alternatives Considered More than 100 transportation elements were evaluated during the screening process. As discussed previously, the first two screening levels (initial screening and comparative screening) considered alternative elements within categories including alignments, station locations, and technologies to determine which best met the corridor needs and should be advanced for further analysis. Following comparative screening, the remaining alignments, station locations, and technologies were combined to form corridor alternatives that were further evaluated and refined in subsequent screening levels. Transportation demand management (TDM)/TSM strategies were not evaluated as stand-alone alternatives because they do not individually address the project purpose and need. TDM/TSM strategies represent operating policies applicable to any build alternative to better address project goals and objectives Transit Alignments Figure 2-2 shows potential corridors considered for a rapid transit alignment between downtown Denver and DIA. Alignments were also suggested to extend the Central Corridor from 30th Avenue and Downing Street to connect to the East Corridor. Alignments are described by three subareas: Downtown Alignments Alignments to downtown Denver (specifically DUS), generally south of I-70 and west of Franklin Street. September

8 Alternatives Considered East-West Alignments Alignments east of downtown and generally west of Airport Boulevard. Airport Connection Alignments Alignments running north-south through the eastern portion of the project area that connect east-west alignments to DIA. The corridor crosses each of these three alignment subareas; therefore, an alignment from each subarea is necessary to develop a complete alternative that connects downtown Denver to DIA. A separate category for other alignments was created to address improvements that are not specific to a subarea and alignments outside of the project area. This subsection describes the alignment subareas and the other alignment categories in more detail. Downtown alignments. Connect downtown Denver to east-west alignments: Brighton Boulevard Extend from DUS north along the Union Pacific railroad (UPRR) corridor and then along Brighton Boulevard. Broadway Extend from existing light rail at 18th Avenue/California Street north along Broadway to the UPRR corridor or along Brighton Boulevard to I-70. Washington Street Extend from Broadway or Brighton Boulevard north along Washington Street. California Street Place a track along California Street parallel to Welton Street from downtown Denver to 30th/Downing (Central Corridor alignment). Welton Street/Downing Street Place a second track along Welton Street and then extend along Downing Street to 40th Avenue (Central Corridor alignment). East-west alignments. Run east-west through the project area and connect downtown alignments to airport connection alignments: Along I-70 (in the right of way [ROW]) Connect with one of the downtown alignments and run along I-70. Existing UPRR tracks/smith Road Run from DUS or other downtown alignment to the UPRR corridor/smith Road and run east along UPRR corridor/smith Road. 35th Avenue Connect one of the downtown alignments and run east along 35th Avenue. Martin Luther King Boulevard Connect with one of the downtown alignments and run east along Martin Luther King Boulevard. Colfax Avenue Connect from existing downtown light rail south to Colfax Avenue and then east along Colfax Avenue. Bruce Randolph Avenue/35th Avenue Connect with one of the downtown alignments and run east along Bruce Randolph Avenue to Dahlia Street, south on Dahlia Street to Martin Luther King Boulevard, and then east on Martin Luther King Boulevard. 38th Avenue Connect with one of the downtown alignments and run east along 38th Avenue. Montview Boulevard Connect with either the 38th Avenue, 35th Avenue, Martin Luther King Boulevard, or Bruce Randolph Avenue alignments and run south on Colorado Boulevard and then east along Montview Boulevard. Havana Street Connect with one of the east-west alignments between Martin Luther King Boulevard and I-70 and then run north along Havana Street and east along 56th Avenue. 2-8 September 2009

9 Alternatives Considered Figure 2-2 Alignments September

10 Alternatives Considered This page intentionally left blank September 2009

11 Alternatives Considered 56th Avenue/north of 56th Avenue Connect with one of the downtown alignments north to 56th Avenue and run east along 56th Avenue. 64th Avenue median Connect with one of the downtown alignments and run north to 64th Avenue and then east in the median of 64th Avenue. BNSF Market Lead Divert from an alignment along the existing UPRR corridor/smith Road to 40th Street, east along the BNSF Market Lead corridor to Colorado Boulevard, then back to the UPRR corridor/smith Road. Sand Creek Divert from one of the east-west alignments between Martin Luther King Boulevard and the UPRR corridor/smith Road through the Stapleton Redevelopment area along Sand Creek and then continue along the UPRR corridor/smith Road. Airport connection Alignments. Run north-south through the eastern portion of the project area to connect east-west alignments to DIA: Tower Road Connect with one of the east-west alignments and run north along Tower Road, then east along Peña Boulevard and/or 78th Avenue to DIA. Peña Boulevard Connect with one of the east-west alignments and run north along Peña Boulevard, then east along Peña Boulevard and/or 78th Avenue to DIA. Run farther east of DIA Connect DIA to the town of Strasburg located approximately 40 miles east of downtown Denver. Picadilly Road Connect with one of the east-west alignments and run north along Picadilly Road, then east along Peña Boulevard and/or 78th Avenue to DIA. E-470 Connect with one of the east-west alignments and run north along E-470, then east along Peña Boulevard and/or 78th Avenue to DIA. Telluride Street Connect with one of the east-west alignments and run north along the future Telluride Street, then east along Peña Boulevard and/or 78th Avenue to DIA. Other alignments. Are either not located in the subareas mentioned previously or are other types of transit connections or improvements: Keep the opportunity open for connection to North Front Range area Connect to an alternative to the North Front Range. 30th Avenue and Downing Street to 40th Avenue/40th Street Extend the existing alignment north along Downing Street to 40th Avenue/40th Street (Central Corridor alignment). Downtown Brighton to National Western Complex Provide a connection from proposed alignments at 40th Avenue/40th Street along Brighton Boulevard to the National Western Complex. Connection between Northwest Rail Corridor (formerly called US 36) and East Corridor before DUS Provide a direct connection from the Northwest Rail Corridor alternative to an East Corridor alternative bypassing DUS. From Montbello to downtown Denver to DIA Provide a connection from Montbello to downtown and DIA. Connection between I-225 and East Corridor transit alternatives Provide a connection from an I-225 alternative to a potential East Corridor alternative. Depressed alignment Construct an alignment below existing ground. Elevated alignment Construct an alignment above existing ground. September

12 Alternatives Considered Station locations Stations allow passenger boarding and alighting and may include parking. They may also serve as bus transfer facilities. Station locations were developed during the scoping process based on input from the community, affected agencies, previous studies, and other alternatives developed by the project team. Stations were suggested at the following locations and areas. DUS Five Points Area Blake Street 33rd Avenue/ Downing Street 31st Street Cole Area 40th Avenue/40th Street National Western Complex Globeville Area Brighton Boulevard Swansea/ Globeville Area 47th Avenue/ Brighton Boulevard Swansea Area York Street Steele Street Clayton Area Northeast Denver 40th Avenue/ Colorado Boulevard Colorado Boulevard Dahlia Street Northeast Park Hill Holly Street Quebec Street Former Stapleton Within Stapleton Redevelopment Havana Street Smith Road/ Peoria Street Fitzsimons Gateway Peña Boulevard/ Tower Road 40th Avenue/ Peña Boulevard Airport Boulevard/ Smith Road 68th Avenue/ Tower Road 56th Avenue/ Tower Road 48th Avenue/ Tower Road 45th Avenue/ Tower Road Smith Road/ Tower Road DIA 1 to 2 miles apart with park-n-rides Ballpark Area (29th and 33rd) Monaco Parkway 2-12 September 2009

13 Alternatives Considered Transit Technologies Technology refers to the specific mode (e.g., rail or bus) and type of propulsion (e.g., diesel, natural gas, or electric) that would be used. It also refers to operating characteristics for both guideway and guidance types. Technologies were identified during the scoping process based on input from the community, affected agencies, previous studies, and other alternatives developed by the project team. The following technologies were evaluated as potential rapid transit alternatives. Bus rapid transit (BRT) This rubber tire technology combines the operating concepts of rail transit and buses. It can operate in exclusive ROW, high-occupancy vehicle lanes, or along city streets. BRT uses technologies (such as intelligent transportation systems) to increase operating efficiency. Commuter rail This technology typically operates on tracks shared with freight trains or on parallel tracks in or along the railroad ROW and serves longer distance trips. It may use locomotives with passenger cars or self-propelled passenger cars, known as diesel multiple units (DMU) or electric multiple units (EMU). Bus Rapid Transit Heavy rail This technology is commonly referred to as metro or subway. It operates in exclusive ROW using electricity from a third rail alongside the track. Commuter Rail Heavy Rail September

14 Alternatives Considered High-speed rail This technology typically provides intercity service, operating in exclusive ROW that can be located at grade, elevated, or below ground, but without at-grade crossings with roadways or other rail lines. Range of speed is from 100 miles per hour (mph) to 200 mph. High Speed Rail Light rail transit (LRT) This technology can operate in exclusive ROW, either private or along city streets. LRT is usually powered by electricity from overhead wires. Light Rail Transit Magnetic levitation This is an emerging technology that can provide very high-speed service in metropolitan areas as well as longdistance intercity service. Magnetic levitation trains float on a magnetic field and are propelled by magnets located on the guideway. Magnetic Levitation Monorail This technology is elevated on a concrete or steel guideway. Monorail vehicles are supported and guided by rubber tires that run along the guideway. It is powered by electricity from a rail along the guideway. Trains can be fully automated or driver-operated and typically operate at lower speeds. Monorail 2-14 September 2009

15 Alternatives Considered Personal rapid transit This technology is designed to provide direct, non-stop service between specific origins and destinations. Personal rapid transit is an automated system of small vehicles that travel on elevated guideways and operates on demand without intermediate stops. It typically operates at lower speeds. Personal Rapid Transit Sky tram This technology uses vehicles suspended from a cable. The cable is driven by a motor and moves the vehicle from station to station. Sky Tram Streetcar/trolley Streetcars and trolleys operate on rails in city streets with traffic. Streetcars provide limited-stop service on medium to long routes, whereas trolleys typically provide circulation or connector service. This technology is usually powered by electricity from overhead wires. Many trolleys in operation are historic and serve as tourist attractions. Streetcar Trolley Bus This technology can provide either local/circulator service within neighborhoods and connect to a rail fixed guideway alignment at a transit station or can provide express or limited-stop service along a street or exclusive guideway. Bus September

16 Alternatives Considered Double-deck bus This technology provides higher passenger capacity than a standard 40-foot bus, but would not require as much curb space as an articulated bus (usually 55 feet or more in length with two connected passenger compartments that bend at the connecting point when the bus turns a corner). Double-deck buses are used extensively in the United Kingdom and other locations. Double-deck Bus Call-n-Ride service This technology provides curb-to-curb service that uses smaller buses and taxis and covers a specified geographic area. Passengers call the transit agency to request a small bus or taxi pick them up and deliver them to their destination within the service territory Transportation Demand Management/Transportation System Management Strategies TDM/TSM strategies are programs designed to reduce travel demand and improve the use of the current transportation system. TDM strategies would address traffic congestion by reducing travel demand rather than increasing transportation capacity. TSM strategies would help improve traffic flow on the existing transportation system. These strategies were identified during the scoping process based on input from the community, affected agencies, previous studies, and other alternatives developed by the project team. These strategies could be added to any alternative to enhance operations. Improved pedestrian facilities Improve pedestrian facilities and allow users to walk to destinations rather than drive. Improved bicycle facilities Improve bicycle facilities and allow users to bike to destinations that are typically farther away than users are willing to walk. Enhanced bus service Create new bus services, modify existing bus routes, and/or increase bus frequencies. Ride sharing Encourage using ride-sharing programs that allow travelers with common destinations to travel together and share costs associated with traveling. Ridesharing programs reduce the total number of vehicle trips by reducing the number of single occupant vehicular trips. DRCOG already has RideArrangers, which provides this service in the metropolitan area. Vary business work schedules (Flex time) Encourage using flex time, a varied work schedule where employees may go to work later or earlier in the day to reduce traffic during peak commuter travel periods. Intelligent transportation systems Incorporate intelligent transportation systems technology applications to move traffic more efficiently Initial Screening and Comparative Screening Table 2-2 through Table 2-4 describe the alignment, station location, and technology alternatives eliminated during initial screening and comparative screening, including the rationale for eliminating each alternative. Figure 2-3 through Figure 2-5 summarize the results of the first two levels of the screening process. The last column of each of these figures highlights 2-16 September 2009

17 Alternatives Considered that each alternative remaining after comparative screening was combined with other alternatives to form the eight corridor-wide alternatives (numbers in green) outlined in detail in Subsection 2.1.4, Detailed Screening. TDM/TSM results are shown in Figure 2-6. Table 2-2 Transit Alignment Alternatives Eliminated in Initial and Comparative Screening Alternative Downtown Transit Alignments Washington Street East-West Transit Alignments 35th Avenue 38th Avenue Montview Boulevard Colfax Avenue Havana Street 56th Avenue/North of 56th Avenue 64th Avenue median Airport Transit Alignments Run farther east of DIA Reason Eliminated Eliminated during comparative screening because it would have more impacts on residential and historical properties due to the limited amount of ROW available as compared to other more reasonable alternatives on wider streets such as Brighton Boulevard and Broadway. Eliminated during comparative screening because it would have more residential and business property impacts, and does not support community plans or other more reasonable on-street east-west transit alignments such as Bruce Randolph Avenue/35th Avenue. Eliminated during comparative screening because it would run through a primarily industrial area that would not provide access to local residences, businesses, or activity centers in the corridor or other more reasonable, onstreet, east-west transit alignments such as Martin Luther King Boulevard and Bruce Randolph Avenue. Eliminated during initial screening because it is not in the project area. Eliminated during initial screening because it is not in the project area. Eliminated during comparative screening because it would run through a primarily industrial area that would not provide access to local residences, businesses, or activity centers in the corridor or other more reasonable, onstreet, east-west transit alignments such as Martin Luther King Boulevard and Bruce Randolph Avenue. Eliminated during comparative screening because it would run through a primarily industrial area that does not provide access to local residences, businesses, or activity centers in the corridor or other more reasonable, onstreet, east-west transit alignments. The alignment also does not fit within local plans to expand 56th Avenue. Eliminated during initial screening because of environmental impacts on the Rocky Mountain Arsenal National Wildlife Refuge. Eliminated during initial screening because it is not in the project area. E-470 Eliminated during initial screening because it is not in the project area. Other Transit Alignments Keep the opportunity open for connection to North Front Range area Eliminated during initial screening because it is not in the project area. This alternative is being considered in the North I-25 EIS. September

18 Alternatives Considered Table 2-3 Station Location Alternatives Eliminated in Initial and Comparative Screening Fitzsimons Alternative Reason Eliminated Eliminated during initial screening because it is not in the project area. This alternative will be considered as part of the I-225 environmental evaluation. Table 2-4 Transit Technology Alternatives Eliminated in Initial and Comparative Screening Heavy rail Alternative High speed rail (bullet train) Magnetic levitation Monorail Personal rapid transit Sky tram Reason Eliminated Eliminated during comparative screening because it has substantially higher construction and maintenance costs than other more reasonable transit technology alternatives. Eliminated during initial screening because it is not a proven technology for this type of transit service. This technology is meant for longer-distance trips. Eliminated during initial screening because it is not a proven technology for shorter-distance transit service with multiple stops. This technology would not provide reasonable local access and is meant for longer trips. Eliminated during comparative screening because it would not balance access with acceptable transit operations and would have substantially higher construction and operational costs than other more reasonable transit technology alternatives. Eliminated during initial screening because it is not a proven technology for providing service between a downtown and an airport more than 20 miles apart. Eliminated during initial screening because it is not a proven technology for providing service between a downtown and an airport more than 20 miles apart. This technology is not a realistic application for this corridor and is meant for shorter trips September 2009

19 Alternatives Considered Figure 2-3 Transit Alignment Alternatives Initial and Comparative Screening Results September

20 Alternatives Considered Figure 2-4 Station Location Alternatives Initial and Comparative Screening Results 2-20 September 2009

21 Alternatives Considered Figure 2-5 Transit Technology Alternatives Initial and Comparative Screening Results Figure 2-6 TDM/TSM Alternatives Initial and Comparative Screening Results September

22 Alternatives Considered Detailed Screening Using the alternative elements remaining after the initial and comparative screening, eight alternatives were developed for additional screening. These alternatives follow various alignments between DUS and DIA and assume both on-street and separate ROW operations. All alternatives except Alternative 1 include the extension of the Central Corridor from 30th Avenue and Downing Street to the East Corridor alignment (later in the study the RTD 2007 Annual Program recommended the Central Corridor Extension in a separate environmental evaluation document apart from the East Corridor EIS). For Alternative 1 there was no logical connection point between the Central Corridor and I-70. Three technologies were evaluated: BRT, LRT, and commuter rail. Corridor-wide transit alternatives evaluated in detailed screening included: Alternative 1: I-70 BRT Alternative 2: UPRR Commuter Rail Alternative 3: UPRR LRT Alternative 4: UPRR BRT Alternative 5: Bruce Randolph Avenue LRT Alternative 6: Bruce Randolph Avenue BRT Alternative 7: Martin Luther King Boulevard LRT Alternative 8: Martin Luther King Boulevard BRT These eight alternatives included four alignment connection options (A, B, C, and D) to access DIA. Alignment variations (m, s q, s u, and s p ) include smaller deviations within the overall alignments between York Street and Peoria Street. Option A Peña Boulevard This option runs along the eastern and southern edges of the Peña Transportation Corridor, crossing E-470 just south of the E-470/Peña Boulevard interchange. The alignment then runs north along Picadilly Road to 78th Avenue and continues east along 78th Avenue turning north to connect to the first level of the DIA terminal. This option was analyzed with seven of the eight transit alternatives (detailed screening alternatives 2 through 8). Option B Telluride Street This option runs along the future Telluride Street alignment to the southern edge of the Peña Transportation Corridor, crossing E-470 just south of the E-470/Peña Boulevard interchange. The alignment then runs north along future Picadilly Road to 78th Avenue and continues east along 78th Avenue turning north to connect to the first level of the DIA terminal. This option was analyzed with seven of the eight transit alternatives (detailed screening alternatives 2 through 8). Option C Tower Road This option runs along Tower Road north of I-70 to the southern edges of the Peña Transportation Corridor, crossing E-470 just south of the E-470/Peña Boulevard Interchange. The alignment then runs north along future Picadilly Road to 78th Avenue and continues east along 78th Avenue turning north to connect to the first level of the DIA terminal. This option was analyzed with detailed screening alternatives 3 through 8. Option D Picadilly Road This option runs along future Picadilly Road north of I-70 and then crosses E-470 to 78th Avenue. The alignment then continues east along 78th Avenue and turns north to connect to the 2-22 September 2009

23 Alternatives Considered first level of the DIA terminal. This option was analyzed with detailed screening alternatives 3 through 8. Variation m BNSF Market Lead This variation diverges south from the UPRR corridor just west of York Street and connects back to the UPRR corridor at Colorado Boulevard. This variation was analyzed with detailed screening alternatives 3 and 4. Variation s q Stapleton Access along Quebec Street This variation leaves the UPRR corridor and follows Quebec Street south and then continues east along Martin Luther King Boulevard, 33rd Avenue, and Sand Creek Parkway to Peoria Street. The alignment then continues north along Peoria Street to connect back to the UPRR corridor. This variation was analyzed with detailed screening alternatives 3 and 4. Variation s u Stapleton Access along Ulster Street This variation leaves the UPRR corridor and follows Ulster Street south and then continues east along 33rd Avenue and Sand Creek Parkway to Peoria Street. The alignment then continues north along Peoria Street to connect back to the UPRR corridor. This variation was analyzed with detailed screening alternatives 3 and 4. Variation s p UPRR Access along Peoria Street This variation stays on Martin Luther King Boulevard east along Sand Creek Parkway to Peoria Street. The alignment then continues north along Peoria Street to connect back to the UPRR corridor. This variation was analyzed with detailed screening alternatives 5 through 8. Transit alternatives evaluated in detailed screening are shown in Figure 2-7 through Figure September

24 Alternatives Considered Alternative 1 I-70 BRT As shown in Figure 2-7, this alternative would include running BRT in special purpose lanes in the median of I-70 to Peña Boulevard. To access DUS, the BRT would run either along Brighton Boulevard or I-25 to I-70. At Peña Boulevard, the BRT would use Peña Boulevard general purpose lanes to DIA. Figure 2-7 Alternative 1 I-70 BRT 2-24 September 2009

25 Alternatives Considered Alternative 2 UPRR Commuter Rail As shown in Figure 2-8, this alternative would include running commuter rail along the UPRR corridor starting at DUS and would continue east to Airport Boulevard where two options could connect the alignment to DIA: Peña Boulevard or Telluride Street. Figure 2-8 Alternative 2 UPRR Commuter Rail September

26 Alternatives Considered Alternative 3 UPRR LRT As shown in Figure 2-9, this alternative would include running LRT along the UPRR corridor starting at DUS and would continue east to Airport Boulevard where four options could connect the alignment to DIA: Peña Boulevard, Telluride Street, Tower Road, and Picadilly Road. Figure 2-9 Alternative 3 UPRR LRT 2-26 September 2009

27 Alternatives Considered Alternative 4 UPRR BRT As shown in Figure 2-10, this alternative would include running BRT on Wewatta Street to 23rd Street. At 23rd Street, the alignment would turn south using 23rd Street to Market Street/Blake Street. The alignment would use Market Street/Blake Street to Broadway and then would use Broadway to the UPRR corridor. The alignment would then run along the UPRR corridor to Airport Boulevard where four options could connect the alignment to DIA: Peña Boulevard, Telluride Street, Tower Road, and Picadilly Road. Figure 2-10 Alternative 4 UPRR BRT September

28 Alternatives Considered Alternative 5 Bruce Randolph Avenue LRT As shown in Figure 2-11, this alternative would include running LRT along the UPRR corridor, crossing along 34th Street, and continuing east along Bruce Randolph Avenue to Dahlia Street. At Dahlia Street, the alignment would turn south and connect to Martin Luther King Boulevard. The alignment would then continue along Martin Luther King Boulevard and would run north along Ulster Street to the UPRR corridor. Four options could connect the alignment to DIA: Peña Boulevard, Telluride Street, Tower Road, and Picadilly Road. Figure 2-11 Alternative 5 Bruce Randolph Avenue LRT 2-28 September 2009

29 Alternatives Considered Alternative 6 Bruce Randolph Avenue BRT As shown in Figure 2-12, this alternative would include running BRT on Wewatta Street to 23rd Street. At 23rd Street, the alignment would turn south using 23rd Street to Champa Street and Stout Street, depending on the direction of travel. The alignment would use Champa Street or Stout Street to connect to Bruce Randolph Avenue near Downing Street. The alignment would then continue east along Bruce Randolph Avenue to Dahlia Street. At Dahlia Street, the alignment would turn south and connect to Martin Luther King Boulevard. The alignment would then continue along Martin Luther King Boulevard and would run north along Ulster Street to the UPRR corridor. Four options could connect the alignment to DIA: Peña Boulevard, Telluride Street, Tower Road, and Picadilly Road. Figure 2-12 Alternative 6 Bruce Randolph Avenue BRT September

30 Alternatives Considered Alternative 7 Martin Luther King Boulevard LRT As shown in Figure 2-13, this alternative would include running LRT along the UPRR corridor, crossing along 33rd Street, and continuing east along Martin Luther King Boulevard to Ulster Street. The alignment would then turn north along Ulster Street to the UPRR corridor. Four options could connect the alignment to DIA: Peña Boulevard, Telluride Street, Tower Road, and Picadilly Road. Figure 2-13 Alternative 7 Martin Luther King Boulevard LRT 2-30 September 2009

31 Alternatives Considered Alternative 8 Martin Luther King Boulevard BRT As shown in Figure 2-14, this alternative would include running BRT on Wewatta Street to 23rd Street. At 23rd Street, the alignment would turn south using 23rd Street to Champa Street and Stout Street depending on the direction of travel. The alignment would use Champa Street or Stout Street to connect to Martin Luther King Boulevard at Downing Street. The alignment would then continue east along Martin Luther King Boulevard to Ulster Street. The alignment would then turn north along Ulster Street to the UPRR corridor. Four options could connect the alignment to DIA: Peña Boulevard, Telluride Street, Tower Road, and Picadilly Road. Figure 2-14 Alternative 8 Martin Luther King Boulevard BRT September

32 Alternatives Considered Table 2-5 highlights the transit alternatives, DIA connection options, alignment variations eliminated during detailed screening, and the rationale for elimination. Table 2-5 Detailed Screening Results Alternative Transit Alternatives Alternative 1 I-70 BRT Alternative 2 UPRR Commuter Rail Alternative 3 UPRR LRT Alternative 4 UPRR BRT Alternative 5 Bruce Randolph Avenue LRT Alternative 6 Bruce Randolph Avenue BRT Alternative 7 Martin Luther King Boulevard LRT Alternative 8 Martin Luther King Boulevard BRT Reason Eliminated Eliminated because it has the lowest ridership of all alternatives (24,100 riders per day, which is 35 percent lower than other alternatives), the lowest population and employment within 0.5 mile of stations (39,800 and 84,600, respectively), a larger number of buildings potentially affected than the UPRR corridor (78 on I-70 versus 43 to 45 on the UPRR corridor), one of the highest total estimated capital costs ($1.29 billion represents cost of special purpose lanes on I-70), and the highest estimated annual cost per rider (i.e., lowest cost/benefit ratio) ($16.95). Evaluated in more detail in alternative refinement. Evaluated in more detail in alternative refinement. Eliminated because it does not maximize connections to other transportation modes, has the potential for major traffic impacts on downtown streets, requires several at-grade crossings with traffic signals and slower speeds, and has lower ridership than other alternatives on the UPRR corridor. Eliminated because it has a slower travel time between DIA and downtown Denver (56 minutes minimum), lower ridership than the UPRR corridor with higher potential community impacts, the highest number of buildings potentially affected (170 to 181), and significant community opposition. Eliminated because it has a slower travel time between DIA and downtown Denver (65 minutes minimum), lower ridership than the UPRR corridor with higher potential community impacts, the highest number of buildings potentially affected (170 to 181), and significant community opposition. Eliminated because it has a slower travel time between DIA and downtown Denver (56 minutes minimum), lower ridership than the UPRR corridor with higher potential community impacts, a higher number of buildings potentially affected (167 to 178), and significant community opposition. Eliminated because it has a slower travel time between DIA and downtown Denver (61 minutes minimum), lower ridership than the UPRR corridor with higher potential community impacts, a higher number of buildings potentially affected (167 to 178), and significant community opposition. DIA Connection Options Option A Peña Boulevard Evaluated in more detail in alternative refinement September 2009

33 Alternatives Considered Table 2-5 Detailed Screening Results Alternative Option B Telluride Street Option C Tower Road Option D Picadilly Road Reason Eliminated Eliminated because it has similar costs to the Peña Boulevard options but has additional impacts to potential development and access. Commuter rail is not consistent with the existing and planned development along Telluride Street because it creates a barrier for future development and limits the ability to construct the planned street network in the area. Considered with alternative 3 until the alternative (which included light rail technology) was eliminated. Eliminated because of plans to widen Tower Road from 68th Avenue to 71st Avenue, which would affect the ability to incorporate transit into the Tower Road corridor without major impacts to existing development. Eliminated because it has the slowest travel time compared to other DIA connection options (21 to 23 minutes between 40th/Airport and DIA), the lowest ridership compared to other DIA connection options (daily boardings and alightings between 2,200 to 2,400 for three stations), and a lack of stakeholder support for this alignment (CCD and Aurora staff prefer other alignments that better meet future plans in the area). Alignment Variations Variation m BNSF Market Lead Eliminated because it has lower daily ridership than the UPRR corridor alternative (37,300 versus 37,800), an additional two to three minutes in travel time, an additional $100 million in cost, six instances where minimum design standards would be required, and 15 hazardous material sites that could potentially be affected. Variation s q Stapleton Access along Quebec Street Variation s u Stapleton Access along Ulster Street Variation s p UPRR Access along Peoria Street Both were eliminated because they have longer travel times than the UPRR corridor alternative (barrier separated travel times are 11 to 13 minutes longer and non-barrier separated travel times are 15 to 17.5 minutes longer), 10 instances where minimum design standards would be required, lower ridership than the UPRR corridor, and an additional $170 to $220 million in capital cost. Eliminated because all Bruce Randolph Avenue and Martin Luther King Boulevard mainline alternatives were eliminated Alternative Refinement Following detailed screening, the remaining alternatives went through alternative refinement that included additional engineering; social, economic, and environmental resource evaluation; and cost analysis. These two alternatives are shown in Figure 2-15: Alternative 2 UPRR Commuter Rail Alternative 3 UPRR LRT The alternative refinement resulted in the determination of the alignment, vehicle technology, maintenance facility, and stations for the Preferred Alternative. Alternative 3 UPRR LRT was eliminated as part of the alternative refinement evaluation. September

34 Alternatives Considered Figure 2-15 Alternatives Evaluated in Alternative Refinement Elimination of Alternative 3 UPRR LRT The DUS Master Plan and DUS Master Plan Supplement (CCD, CDOT, DRCOG, FTA, & RTD, 2004; 2008) identified commuter rail technology for the East Corridor. Since LRT had not been considered previously at DUS for the East Corridor, additional studies were required to evaluate how LRT on the East Corridor would affect DUS operations. Additional issues evaluated during alternative refinement included the use of non-federal Railroad Administration (FRA) compliant equipment within UPRR ROW and the cost differential between LRT and commuter rail for the East Corridor. The I-70 East Corridor Access to Denver Union Station, A Technical Evaluation Study for the I-70 East Environmental Impact Statement (2005) examined capacity and operational issues with introducing LRT from the East Corridor into DUS. The throat of DUS is defined as the existing trackwork currently used for passenger rail between 18th Street and Park Avenue. The current throat has three tracks. The proposed throat for the DUS Master Plan anticipates five tracks through this area, all dedicated to commuter rail. While LRT tracks could be accommodated in the throat area approaching DUS, they would require a 25-foot separation from the commuter rail tracks, as opposed to the 15-foot separation between commuter rail tracks. This would result in a decrease in the number of commuter rail tracks in the throat from 2-34 September 2009

35 Alternatives Considered five to three, thereby reducing operational reliability for other commuter rail trains accessing the station. The reduction of the throat passenger rail tracks available for commuter rail from five to three increases the number of trains using these tracks by 31 percent. The increased use of these tracks would consequently require more maintenance, while also making the scheduling of this maintenance less flexible. The study also examined the introduction of LRT into DUS in regard to platform layouts. The potential East Corridor LRT alignments allow for only one viable platform layout, which would require major infrastructure changes and reconstruction at DUS. The platform layout widths and access required to safely accommodate the passenger volumes of the at-grade LRT alternative do not meet the physical site constraints. There is not sufficient room to place the needed additional LRT platforms at grade without reducing the commuter rail tracks in the platforms from four to three, or eliminating the bus high-occupancy vehicle lane. This is considered to be a fatal flaw for LRT due to the operating requirements needed for commuter rail. Concurrently, the project team examined issues regarding the allowance of non-fra compliant equipment (light rail vehicles) to operate within the UPRR ROW. In 2005, RTD presented design concepts to UPRR including barrier walls, vertical alignment separations, and signal systems to address their concerns. UPRR determined that these concepts did not address their concerns, and on November 11, 2005, they issued a letter to RTD stating that they would not allow noncompliant vehicles in their ROW. As engineering advanced for the alternatives, more detailed cost estimates were created. These estimates identified a cost differential of approximately $250 million between LRT and commuter rail. The cost per user is approximately 35 percent higher for LRT than for commuter rail. With the elimination of Alternative 3 UPRR LRT, the LRT-related station locations were also eliminated. The closer spacing proposed for LRT stations is not practical for commuter rail technology; however, station locations identified for both LRT and commuter rail technologies were not eliminated Selection of Commuter Rail Vehicle Technology Following the elimination of Alternative 3 UPRR LRT and the selection of Alternative 2 UPRR Commuter Rail, a separate study was conducted to evaluate different types of FRAcompliant commuter rail vehicle technologies. These technologies included: Diesel locomotive hauled coaches passenger coach cars that are pushed or pulled by a diesel locomotive. Dual-mode locomotive hauled coaches passenger coach cars that are pushed or pulled by a locomotive that can be powered by both diesel and electricity. DMU individually powered cars that use diesel engines and can run as single-unit or in multiple-unit trains. EMU individually powered cars that use an overhead electric system and can run as single-unit or in multiple-unit trains. The Lifecycle Cost and Payback Analysis of Candidate Technologies for Commuter Rail Corridors in the Denver Regional Transportation District (Front Range Systems Consultants, 2006) study concluded that both DMU and EMU would be more cost-effective than locomotive hauled coach technologies for the East Corridor. An additional analysis was completed for the DMU and EMU technologies. As a result of this analysis, it was determined that EMU is the September

36 Alternatives Considered most effective technology for the East Corridor because it best addresses the purpose and need and goals and objectives of the project. Key discriminators included: Community/environmental impacts EMU is a non-diesel technology that minimizes potential air quality impacts, which were expressed as a major community concern during scoping. Capacity EMU is the faster commuter rail technology. Implementation EMU can be implemented more cost-effectively than DMU. Because of the corridor s high passenger demand and frequency of service, the lifecycle and operating costs for the East Corridor are lower for EMU than for DMU. Since EMU has the ability to climb steeper grades, it also has shorter bridge approaches and walls than DMU. The Commuter Rail Vehicle Technology Analysis (RTD, 2007b) examined EMU, DMU, and DMU double-deck technologies. It included a lifecycle cost analysis of all alternatives under consideration that examined both the differential capital costs and operating and maintenance costs for the entire RTD FasTracks system. The analysis included a review of four possible technology alternatives regarding various combinations for the East Corridor, Gold Line, North Metro Corridor, and Northwest Rail Corridor. Technology Alternative 1 all corridors EMU Technology Alternative 2 all corridors DMU Technology Alternative 3 all corridors DMU double-deck Technology Alternative 4 mixed fleet of two EMU and two DMU corridors The study recommended Technology Alternative 4, identifying EMU as the vehicle technology for the East Corridor and Gold Line, and DMU as the vehicle technology for North Metro and Northwest Rail corridors. Technology Alternative 4 was identified as the most cost-effective alternative for all corridors, while also meeting the strong community and agency support established during the Gold Line and East Corridor alternative evaluation process. Since the completion of the Commuter Rail Vehicle Technology Analysis, a sensitivity analysis was conducted for the North Metro corridor, which concluded that EMU is also the most costeffective vehicle technology for that corridor. The Updated EMU and DMU Technology Analysis (Goldman Sachs & JP Morgan, 2007) analyzed differential costs of EMU and DMU. The results of the analysis concluded that total annual operations, maintenance, and debt service costs for EMU are lower than the corresponding DMU cost for the East Corridor. Since then, diesel fuel prices have increased significantly, which reinforces these findings. Based on the analysis and EIS process, the RTD Board supported the staff recommendation of EMU as the preferred commuter rail vehicle technology for the East Corridor Commuter Rail Maintenance Facility Alternatives Considered The CRMF site selection process began in 2004 with the identification of 24 candidate sites, as shown in Figure 2-16, to identify a location for a facility that would support the operations and maintenance of the commuter rail components of the FasTracks transit system. The site selection process has been influenced by railroad negotiations, peer reviews, and later by opportunities resulting from property acquisition required for the Gold Line and Northwest Rail projects alignment. This has resulted in adjustments to the process and decision during the process September 2009

37 Alternatives Considered Figure 2-16 CRMF Candidate Sites September

38 Alternatives Considered The following subsection presents the criteria used for the CRMF evaluation and the results from each level of screening. The first level evaluation looked for fatal flaws and was focused on the transportation function of the site. The second level evaluation looked at the site s relationship and compatibility with its surroundings. The third level evaluation examined impacts to environmental resources Commuter Rail Maintenance Facility Screening Criteria As shown in Table 2-6, criteria were developed for each level of the screening process. Screening Level Level 1 Level 2 Level 3 Table 2-6 Screening Process Criteria Screening Criteria 1. Is the site located within 5 miles of DUS or end-of-line terminal station? 2. Does the site meet size and configuration requirements? 3. Is the site able to accommodate a double-ended yard and shop rather than a stubended facility? 4. Is rail access into the site at grade? 5. Is site access from tracks on an RTD transit corridor? 6. Does the site avoid conflicts with freight trains? 7. Does the site avoid impacts to major public roadways? 8. Does the site avoid substantial environmental impacts? 9. Does the site accommodate part of a split central maintenance facility if a site for the entire facility cannot be identified? For example, train storage and running maintenance could be accommodated on one site with heavy maintenance accommodated at another site. 1. Can the functions and uses of the existing property owner be relocated? 2. Can rail and vehicle access be provided? 3. Does the site avoid significant environmental issues? 4. Does the site require minimal property acquisitions? 5. Are there minimal railroad crossings into the site? 6. Are there minimal impacts on vehicle traffic? Environmental Resource Impacts or Benefits Land Use Economic Conditions ROW and Relocations Social Impacts and Community Facilities Environmental Justice Cultural Resources Parks and Open Space Safety and Security Visual Resources Air Quality Noise and Vibration Biological Resources Mineral Resources Farmland Hazardous Materials Transportation Utilities Energy Water Resources Wetlands Construction Property Acquisition Cost 2-38 September 2009

39 Alternatives Considered Commuter Rail Maintenance Facility Screening Results through 2007 As the process advanced through the three levels of screening, the number of alternatives decreased while being subjected to an increasing level of detailed analysis. The results of this process are shown in Table 2-7. A check mark in the table indicates that the site passed that level of screening and was carried through to the next level. Recommendation from 2007 Screening: The UPRR 36th Street Yard/Properties West site (later renamed the 40th/40th site) was selected due to good access and reduced environmental impacts. Table 2-7 Summary of Screening Results in 2007 Site No. C1 Site Location Screening Level Level 1 Level 2 Level 3 Reason for Retention/Elimination BNSF Rennick Yard/Properties East a a Dropped at Level 3 Higher acquisition costs. C2 BNSF Trail-on-Flat- Car (TOFC) Facility a a Dropped at Level 3 Size/configuration; conflicts with freight; impacts to public roadways. Brought back at second level due to public support. Eliminated in third level due to higher acquisition costs. C3 BNSF 31st Street Yard a a Dropped at Level 3 Higher acquisition costs. C4 RTD District Shops/ Platte Facility a a Dropped at Level 3 Potential conflict: planning documents indicate future mixed use development; three households affected. C5 UPRR 36th Street Yard/Properties West 1 a a a Selected as Preferred Alternative. C6 UPRR North Yard a Dropped at Level 2 Existing property owner cannot be relocated. C7 C8 C9 C10 C11 UPRR Moffat Station National Western Stock Show Stockyards Suncor Refinery UPRR Boulder Industrial Subdivision UPRR Burnham Yard Dropped at Level 1 Not on RTD transit corridor; conflicts with freight; impacts to public roadways; substantial environmental impacts. Dropped at Level 1 Conflicts with freight; substantial environmental impacts. Dropped at Level 1 Conflicts with freight; impacts to public roadways; substantial environmental impacts. Dropped at Level 1 Not on RTD transit corridor; conflicts with freight; impacts to public roadways; substantial environmental impacts. Dropped at Level 1 Not on RTD transit corridor; conflicts with freight. September

40 Alternatives Considered Table 2-7 Summary of Screening Results in 2007 Site No. C12 Site Location Screening Level Level 1 Level 2 Level 3 Reason for Retention/Elimination UPRR 36th Street Yard/Properties East a Dropped at Level 2 Conflicts with freight. C13 Smith Road (south side) Dahlia Street to Quebec Street Dropped at Level 1 Impacts to public roadways. C14 Smith Road (north side) Dahlia Street to Quebec Street Dropped at Level 1 Conflicts with freight; impacts to public roadways. C15 UPRR Rock Island Alignment Dropped at Level 1 Not on RTD transit corridor; substantial environmental impacts. C16 Smith Road (south side) Quebec Street to Central Park a Dropped at Level 2 Significant environmental issues; major property acquisitions; vehicle traffic impacts. C17 Smith Road (north side) Quebec Street to Central Park Dropped at Level 1 Not within 5 miles to end of transit corridor; conflicts with freight; substantial environmental impacts. C18 Smith Road (south side) Peoria Street/ I-225 Dropped at Level 1 Not within 5 miles to end of transit corridor; size/configuration requirements. C19 Smith Road (north side) Chambers Road to Airport Road Dropped at Level 1 Not within 5 miles to end of transit corridor; size/configuration requirements; conflicts with freight. C20 Smith Road (north side) Airport Road to Tower Road Dropped at Level 1 Not within 5 miles to end of transit corridor; conflicts with freight. C21 Smith Road (south side) Airport Road to Tower Road Dropped at Level 1 Not within 5 miles to end of transit corridor. C22 BNSF 23rd Street Yard Dropped at Level 1 Size/configuration requirements; not on RTD transit corridor; conflicts with freight. C23 North Metro East a Dropped at Level 2 Significant environmental issues; major property acquisitions; impacts to public roadways; vehicle traffic impacts. C24 Denver Water Treatment Plant Dropped at Level 1 Not on RTD transit corridor; conflicts with freight; impacts with public roadways; substantial environmental impacts. 1 This site was renamed 40th/40th after it was reconfigured and expanded after this level of screening. a indicates site location was carried through to next screening level September 2009

41 Alternatives Considered Commuter Rail Maintenance Facility Screening Results after Railroad Negotiations Table 2-8 provides a summary of screening results for the reevaluation that took place during the CRMF project planning process after November 2007, when railroad negotiations for property acquisition of the 40th/40th site (previously called the UPRR 36th Street yard/properties West site but renamed to 40th/40th) did not proceed. Several issues factored into the discontinuation of negotiations for the 40th/40th site: high acquisition costs; schedule risks with the uncertainty that approval of an alternate location for the UPRR maintenance yard facility would be achieved; and secondary impacts at the relocation site. Previously eliminated alternatives that passed second level screening were reintroduced for this evaluation. A check mark in the table indicates that the site passed that level of screening and was carried through to the next level. Recommendation from Screening after Railroad Negotiations: The RTD District Shops/Platte Division Site was selected due to RTD ownership of the majority of the property. Table 2-8 Results of Reevaluation of Remaining Sites after Railroad Negotiations Site No. Site Location Reevaluation Screening Findings after Reevaluation C1 BNSF Rennick Yard/Properties East Dropped Higher acquisition costs due to operational link to TOFC facility that would require purchase and relocation of both TOFC and Rennick facilities. C2 BNSF TOFC Facility Dropped Higher acquisition costs due to operational link to Rennick Yard that would require purchase and relocation of both TOFC and Rennick facilities. Dropped Higher acquisition costs associated with operational link to the BNSF 23rd Street Yard that would require purchase and relocation of both 23rd Street and 31st Street Yards. C3 BNSF 31st Street Yard C4 RTD District Shops/ Platte Division Site a Selected Majority of site owned by RTD and acquisition costs fall within RTD budget; potential to resolve land-use conflicts with extensive coordination efforts. a indicates site location was carried through to next screening level Commuter Rail Maintenance Facility Screening Results after the Peer Review Table 2-9 summarizes the findings after a reevaluation that occurred due to a peer review suggestion that a smaller CRMF was feasible. This evaluation reintroduced sites previously eliminated for size/configuration issues. A check mark in the table indicates that the site passed that level of screening and was carried through to the next level. Recommendation from Screening after Peer Review: The Modified BNSF TOFC Fox North Site (hereafter referred to as the Fox North site) was selected as the most cost effective and with the fewest environmental impacts. September

42 Alternatives Considered Site No. C2 C4 C18 Table 2-9 Results of Reevaluation of Remaining Sites Retained after Peer Review Site Location Modified BNSF TOFC Fox North Platte Site Smith Road (south side) Peoria Street/I-225 Reevaluation Screening a Findings after Reevaluation Selected Most impacts to property owners (3 out of the 4 properties required) already occur under the North West Rail and Gold Line projects; substantial cost savings to tax payers to keep bus maintenance facility in current location ($100 million); public preference for CRMF in vicinity of this site. Dropped Relocation of bus maintenance facility too costly and slow progress in bus maintenance facility site selection threatened CRMF construction schedule; peer review identified feasibility of smallersized CRMF, making other sites more attractive; CRMF would be less consistent with existing and planned land uses. Dropped Beyond 5-mile radius to DUS, resulting in operational inefficiencies. C19 Smith Road (north side) Chambers Road to Airport Road Dropped Beyond 5-mile radius to DUS, resulting in operational inefficiencies. C22 BNSF 23rd Street Yard Dropped Not in RTD transit corridor; freight conflicts. Dropped Significant environmental issues; major C23 North Metro East property acquisitions. a indicates site location was carried through to next screening level. The Fox North CRMF site was fully evaluated in a supplemental environmental assessment (SEA) (RTD, 2009a) that is herein incorporated by reference Commuter Rail Maintenance Facility Refinements after the SEA Public Hearing A public hearing was held on April 23, 2009 to present the results of the CRMF SEA. The potential acquisition of the Owens Corning (OC) facility was the issue that received the majority of the comments opposing the site. Other possible impacts such as the location of the site relative to the surrounding neighborhoods, the effects of the shared alignment, and the impacts of the CRMF itself on the environment, were not major public concerns. Many comments from OC employees were received and responded to and are referenced in Chapter 8, Response to Agency and Public Comments. Almost unanimously, the OC employees and management believed that RTD had underestimated the cost of relocating the OC facility, the facility would close, and employees would lose their jobs, including indirect employment related to OC operations. In response to concerns about potential job loss, RTD redesigned the CRMF to minimize the impact on the OC facilities (see Figure 2-17). The redesign involved some modifications to the original design and operational criteria and included the following measures September 2009

43 Alternatives Considered Figure 2-17 Revised CRMF Site Layout September

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Needs and Community Characteristics

Needs and Community Characteristics Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program

More information

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2

More information

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

Midtown Corridor Alternatives Analysis Initial Screening Analysis

Midtown Corridor Alternatives Analysis Initial Screening Analysis Midtown Corridor Alternatives Analysis Initial Screening Analysis 7/24/2013 Prepared by the SRF Consulting Group Team for Table of Contents Purpose... 1 Initial Screening Analysis Methodology... 1 Screening...

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

Independence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR

Independence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR Independence Institute 14142 Denver West Parkway, Suite 185 Golden, Colorado 80401 303-279-6536 i2i.org/cad.aspx BRT = BTR Bus-Rapid Transit Is Better Than Rail: The Smart Alternative to Light Rail Joseph

More information

2. ALTERNATIVES CONSIDERED

2. ALTERNATIVES CONSIDERED 2. ALTERNATIVES CONSIDERED 2.1 INTRODUCTION This chapter describes the decision process to develop alternatives, identify screening criteria, screen alternatives, and identify a Build Alternative. For

More information

August 2, 2010 Public Meeting

August 2, 2010 Public Meeting Public Meeting LYMMO Expansion Alternatives Analysis Study Purpose of study is to provide a fresh look at potential LYMMO expansion, following Federal Transit Administration (FTA) Alternatives Analysis

More information

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013 East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with

More information

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N QUALITY OF LIFE EXECUTIVE SUMMARY REPORT UN I O N S TAT I O N T R AV E L by TR A I N Published September 2017 2015 PROGRESS MAP This document reports FasTracks progress through 2015 BACKGROUND RTD The

More information

Development of the Preferred Option and Implementation Plan

Development of the Preferred Option and Implementation Plan Presentation To RMRA Peer Panel Day #1 Preferred Option and Risk Assessment August 25, 2009 TEMS, Inc. / Quandel Consultants, LLC 0 Development of the Preferred Option and Implementation Plan 1 1 Results

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting August 2, 2011 Introduction Key players Local lead agency: Metro Federal lead agency: Federal

More information

CONTENTS FIGURES. US 90A/Southwest Rail Corridor

CONTENTS FIGURES. US 90A/Southwest Rail Corridor CONTENTS 1.0 Corridor Overview... 2 2.0 Alternatives... 3 2.1. Evaluation Criteria... 4 2.2. Alternatives Description and Evaluation... 8 2.3. Alignment Options Received During Scoping...15 3.0 Findings...27

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

RECOMMENDED ALTERNATIVE REPORT

RECOMMENDED ALTERNATIVE REPORT DRAFT METROCENTER CORRIDOR STUDY RECOMMENDED ALTERNATIVE REPORT JULY 12, 2005 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 2.0 TIER 1 ALTERNATIVES EVALUATION... 1 3.0 TIER 2 ALTERNATIVES EVALUATION...

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

Community Advisory Committee. October 5, 2015

Community Advisory Committee. October 5, 2015 Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical

More information

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis High Speed Intercity Passenger Rail Technical Appendix Prepared by HDR August 5, 2010 The Boston South Station HSIPR Expansion Project

More information

PAWG Meeting #3a Tier 1 Evaluation

PAWG Meeting #3a Tier 1 Evaluation PAWG Meeting #3a Tier 1 Evaluation August 2, 2017 LYNX Central Station Open Area 1 Modes Screening 2 Trunk vs Feeder Trunk Modes High peak capacity Direct routes Feeder Modes Routing may be flexible Serve

More information

West Broadway Transit Study. Community Advisory Committee September 17, 2015

West Broadway Transit Study. Community Advisory Committee September 17, 2015 West Broadway Transit Study Community Advisory Committee September 17, 2015 Introductions Community Engagement Summer Outreach Fall Outreach Technical Analysis Process Update Alternatives Review Economic

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

4 Evaluation Process and Initial Alternatives Considered

4 Evaluation Process and Initial Alternatives Considered 4 Evaluation Process and Initial Alternatives Considered Introduction This chapter contains the following elements: A summary of the evaluation criteria used in general and for Screen 1 A description of

More information

Click to edit Master title style

Click to edit Master title style Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment

More information

The Engineering Department recommends Council receive this report for information.

The Engineering Department recommends Council receive this report for information. CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision

More information

appendix 4: Parking Management Study, Phase II

appendix 4: Parking Management Study, Phase II appendix 4: Parking Management Study, Phase II A4-1 A4-2 Eastlake Parking Management Study Final Phase 2 Report Future Parking Demand & Supply January 6, 2017 Submitted by Denver Corp Center III 7900 E.

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

Kenosha-Racine-Milwaukee (KRM)

Kenosha-Racine-Milwaukee (KRM) Kenosha-Racine-Milwaukee (KRM) Commuter Rail #147925 November 6, 2009 1 Guidance of KRM Commuter Rail Studies Intergovernmental Partnership Technical Steering Committee Temporary and Limited Authority

More information

Sound Transit East Link: Bus/LRT System Integration Study

Sound Transit East Link: Bus/LRT System Integration Study Sound Transit East Link: Bus/LRT System Integration Study Prepared For: Sound Transit King County Metro Mercer Island WSDOT Prepared By: CH2M HILL July, 2014 1 SOUND TRANSIT EAST LINK: BUS/LRT SYSTEMES

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

Travel Time Savings Memorandum

Travel Time Savings Memorandum 04-05-2018 TABLE OF CONTENTS 1 Background 3 Methodology 3 Inputs and Calculation 3 Assumptions 4 Light Rail Transit (LRT) Travel Times 5 Auto Travel Times 5 Bus Travel Times 6 Findings 7 Generalized Cost

More information

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street

More information

3.15 SAFETY AND SECURITY

3.15 SAFETY AND SECURITY 3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum

More information

Public Meeting. March 21, 2013 Mimosa Elementary School

Public Meeting. March 21, 2013 Mimosa Elementary School Public Meeting March 21, 2013 Mimosa Elementary School Today s Meeting Purpose 2 Where We Are The Process What We ve Heard and Findings Transit Technologies Station Types Break-out Session Where We Are

More information

Station Evaluation. Durham-Orange Light Rail Transit Project Spring 2012

Station Evaluation. Durham-Orange Light Rail Transit Project Spring 2012 Station Evaluation Durham-Orange Light Rail Transit Project Spring 2012 Key Ingredients for Station Development Platform Designs UNC Hospitals Station The UNC Hospitals Station Option D would be the westerly

More information

3.17 Energy Resources

3.17 Energy Resources 3.17 Energy Resources 3.17.1 Introduction This section characterizes energy resources, usage associated with the proposed Expo Phase 2 project, and the net energy demand associated with changes to the

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

Executive Summary. Phase 2 Evaluation Report. Introduction

Executive Summary. Phase 2 Evaluation Report. Introduction , Executive Summary Executive Summary Introduction TransLink and the Province of British Columbia sponsored a multi-phase study to evaluate alternatives for rapid transit service in the Broadway corridor

More information

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM Hartford Rail Alternatives Analysis www.nhhsrail.com What Is This Study About? The Connecticut Department of Transportation (CTDOT) conducted an Alternatives

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting

More information

CTA Blue Line Study Area

CTA Blue Line Study Area CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

Green Line Long-Term Investments

Green Line Long-Term Investments Enhancements Short-term improvements to keep Austin moving. Investments Long-term projects to support our future. Mobility Hubs MetroRapid MetroRail MetroExpress Connectors Circulators Project Connect

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

Service Quality: Higher Ridership: Very Affordable: Image:

Service Quality: Higher Ridership: Very Affordable: Image: Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to

More information

Public Meeting. June 15, :30 7:30 p.m.

Public Meeting. June 15, :30 7:30 p.m. Public Meeting June 15, 2017 5:30 7:30 p.m. Welcome 2015 Naval Station Norfolk Transit Extension Study 2015 Naval Station Norfolk Transit Extension Study 2017 Norfolk Westside Transit Study HRT and the

More information

North Shore Alternatives Analysis. May 2012

North Shore Alternatives Analysis. May 2012 North Shore Alternatives Analysis May 2012 Agenda Study Process and Progress to Date Short List Alternatives Screening Traffic Analysis Conceptual Engineering Ridership Forecasts Refinement of Service

More information

The Latest on Joint Development Policy Guidance

The Latest on Joint Development Policy Guidance Panelists The Latest on Joint Development Policy Guidance Moderator: Jonathan Davis Deputy General Manager and Chief Financial Officer Massachusetts Bay Transportation Authority James Blakesley, Attorney-Advisor,

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

What is the Connector?

What is the Connector? What is the Connector? The Connector is a plan for a high-capacity transit system from northeast to south Ann Arbor, connecting major destinations including downtown, commercial, and residential areas,

More information

Tempe Streetcar. March 2, 2016

Tempe Streetcar. March 2, 2016 Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use

More information

6/11/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/11/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Metro Green Line to LAX Alternatives Analysis. March 2012

Metro Green Line to LAX Alternatives Analysis. March 2012 Metro Green Line to LAX Alternatives Analysis 1 2 The Crenshaw/LAX Project Foundation for Metro Green Line to LAX 8.5 mile extension Metro Exposition Line (Crenshaw Exposition) to Metro Green Line (Aviation/LAX

More information

TIER TWO SCREENING REPORT

TIER TWO SCREENING REPORT TIER TWO SCREENING REPORT November 2012 Parsons Brinckerhoff DRAFT November 2012 1 Parsons Brinckerhoff DRAFT November 2012-2 TABLE OF CONTENTS Table of Contents...3 List of Tables...4 List of Figures...5

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

Transportation Demand Management Element

Transportation Demand Management Element Transportation Demand Management Element Over the years, our reliance on the private automobile as our primary mode of transportation has grown substantially. Our dependence on the automobile is evidenced

More information

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

Rocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation

Rocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation 2020 Transportation Plan Developed by the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration

More information

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7 Presentation Tappan Zee Bridge/I-287 Corridor Environmental Review December 4, 2008 Slide 1 Title Slide Slide 2 This presentation discusses the contents of the Transit Mode Selection Report. Slide 3 The

More information

Northeast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study

Northeast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for

More information

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle Chapter 7: Travel Demand Analysis Chapter 8 Plan Scenarios LaSalle Community Center. Image Credit: Town of LaSalle 164 Chapter 8: Plan Scenarios Moving Ahead for Progress in the 21 st Century Act (MAP

More information

Midtown Corridor Alternatives Analysis Key Issues Memo

Midtown Corridor Alternatives Analysis Key Issues Memo Midtown Corridor Alternatives Analysis Key Issues Memo 1/4/2013 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 1. Markets... 1 External Markets... 1 Intra-Corridor Travel...

More information

V03. APTA Multimodal Operations Planning Workshop August Green Line LRT

V03. APTA Multimodal Operations Planning Workshop August Green Line LRT V03 APTA Multimodal Operations Planning Workshop August 2016 Green Line LRT 2 Presentation Outline Past Present Future 3 16/03/2016 RouteAhead Update 4 4 16/03/2016 RouteAhead Update 5 5 16/03/2016 6 6

More information

Transit Alternatives Description

Transit Alternatives Description Transit lternatives escription orridor-wide meetings September 9 and 30, 004 Eight main transit alternatives were evaluated in the detailed screening. These alternatives include: lternative 1 I- us Rapid

More information

7 COMPARATIVE EVALUATION OF ALTERNATIVES

7 COMPARATIVE EVALUATION OF ALTERNATIVES 7 COMPARATIVE EVALUATION OF ALTERNATIVES 7.1 INTRODUCTION This chapter presents the comparative analysis of the four Level 2 build alternatives along with a discussion of the relative performance of the

More information

Troost Corridor Transit Study

Troost Corridor Transit Study Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit

More information

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

10/4/2016. October 6, Item #1 CITIZENS PARTICIPATION

10/4/2016. October 6, Item #1 CITIZENS PARTICIPATION October 6, 2016 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 WELCOME 2 Item #4 TRAC ROADWAY RECOMMENDATIONS UPDATE Item #4 Completed Jurisdiction Presentations Boulder City August

More information

Rapid Transit and Land-Use Integration a Reality

Rapid Transit and Land-Use Integration a Reality City of Charlotte Rapid Transit and Land-Use Integration a Reality Transportation Oversight Committee Carolyn Flowers CEO Charlotte Area Transit System April 29, 2010 Charlotte Region Statistics Mecklenburg

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

Halifax Commuter Rail: A Fresh Concept

Halifax Commuter Rail: A Fresh Concept Building Owners & Managers Association (BOMA) Nova Scotia PO Box 1597, Halifax NS B3J 2Y3 902-425-3717 info@bomanovascotia.com bomanovascotia.com Halifax Commuter Rail: A Fresh Concept The Green Interconnected

More information

Status of Plans March Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS

Status of Plans March Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS Status of Plans March 2011 Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS Transit project update Project rationale The system New Britain Hartford Busway New Haven/Hartford/ Springfield Passenger Rail

More information

Attachment 5 Eglinton West LRT Planning and Technical Update

Attachment 5 Eglinton West LRT Planning and Technical Update Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to

More information

Rocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC

Rocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC Rocky Mountain Rail Authority (RMRA) Corridor Input Team Meeting #2 Alternatives Overview December 2008 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda Introductions Study Overview Alternatives Overview

More information

Tier 2 Screening and Selection522. of the Short List Alternatives KISSIMMEE CORRIDOR. Downtown CRA. US 192 Alternatives Analysis

Tier 2 Screening and Selection522. of the Short List Alternatives KISSIMMEE CORRIDOR. Downtown CRA. US 192 Alternatives Analysis LAKE COUNTY ORANGE COUNTY Ticket and Transportation Center Walt Disney / Reedy Creek Improvement District CR 535 John Young Parkway 441 17 92 Florida s Turnpike VE 92 mee Hall JOHN YOUNG PKY 192 OAK ST

More information

Mountain View Automated Guideway Transit Feasibility Study Community Meeting September 25, 2017

Mountain View Automated Guideway Transit Feasibility Study Community Meeting September 25, 2017 Mountain View Automated Guideway Transit Feasibility Study Community Meeting September 25, 2017 Jim Lightbody, City of Mountain View Jenny Baumgartner, Lea+Elliott Eileen Goodwin, Apex Strategies 1 Agenda

More information

LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (LACMTA) AND FEDERAL TRANSIT ADMINISTRATION (FTA)

LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (LACMTA) AND FEDERAL TRANSIT ADMINISTRATION (FTA) LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (LACMTA) AND FEDERAL TRANSIT ADMINISTRATION (FTA) NOTICE OF PREPARATION (NOP)/NOTICE OF INTENT (NOI) OF AN ENVIRONMENTAL IMPACT STATEMENT (EIS)/ENVIRONMENTAL

More information