Worlds highest rated shields design and installation

Size: px
Start display at page:

Download "Worlds highest rated shields design and installation"

Transcription

1 Worlds highest rated shields design and installation Ismet Canbulat OUTLINE Introduction to Moranbah North Mine Geotechnical requirements Design phase Installation phase 1

2 ACKNOWLEDGEMENTS Bruce Robertson AMC Consultants Terry Medhurst Johan Laubscher Anglo American MORANBAH NORTH MINE Current and unapproved future workings 2

3 ROOF AND FLOOR LITHOLOGY ROOF AND FLOOR LITHOLOGY 3

4 HISTORICAL PERSPECTIVE Joy 980 tonne PRS were specified and purchased for 8 blocks 4 Southern Blocks (LW101 to 104); and Note: also these were much shorter blocks than subsequently adopted 4 short Northern Blocks (LW 201 to 204) Equated with about 30,000 cycles Joy tendered 8 design options with increasing Factors of Safety and capacity MNC elected to purchase one to suit the shallow mine reserves Plan seems to have been to purchase another set of PRS (and learn from initial installation) HISTORICAL PERSPECTIVE The mine plan requires recognition and an approach to jumping around faulted and bad ground Leads to more longwall face moves (and subsequent lost production) Plan was developed for Walk Off and Walk On twin faces by using existing spares (AFC, BSL and Shearer) New face to arrive for LW108 The aim was to reduce 4+ week longwall moves to 1 week or less Inadequate support capacity has become an issue 4

5 HISTORICAL PERSPECTIVE Ongoing Engineering problems with existing 980t Leg failures due to PRS twisting and leg side loads The design Fix seems to have worked no similar failures 980t PRS have increased to 1,006t/1,034t Structures are being subjected to greater loads than original design/testing Distracts significant resources from day-to-day basics 300m face extension requirements (with 1,200t and mixed 980t/1,033t PRS fully procured Many other issues ranging from niggling to major DA ram lugs (14 left to change) HISTORICAL PERSPECTIVE Ongoing Engineering problems with existing 980t Increasing risk of fatigue induced PRS structural failure/s No spare supports (post-300m face) to effect any refurbishment program 5

6 HISTORICAL PERSPECTIVE Ongoing Engineering efforts to address problems with existing 980t PRS recent 1,200t purchase 1,200t PRS seem to have addressed some earlier shortcomings Increased absolute capacity (1,200t vs. 980t) Increased (pre-cut) support density at yield (125t/m 2 vs. 105t/m 2 ) Improved canopy ratio (2.3:1 vs. 2.65:1) Side shield performance improved (spillage reduces hose failures and steering benefits) Solenoids operating on low pressure (250bar) Hose routing and cylinder design changes (e.g. Sprag hose porting) HISTORICAL PERSPECTIVE Ongoing Operational problems with existing 980t PRS Difficult Geology and Geotechnical in Goonyella Middle Seam Cutting height reductions trialled to improve control Inadequate rating/performance of PRS Operational experience with 1,200t shields 1,200 tonne PRS purchased for 300m Face extension Improved stability Regularly on yield Impact on overall face is still uncertain 6

7 GEOTECHNICAL CONSIDERATIONS What do we require to control caving? Past performance: Almost always on yield Lose control of the roof when >40-50mm of convergence When we get cavities we lose the ability to fully set shields (however, is this chicken or the egg!) Joy S-curves Aim for a Support that is in yield less than 5-10% of the time Joy unable to replicate S-curve data for MNC because of significant time existing Supports are on yield Leg reliability and maintenance issues leading to lower effective density Essential to have adequate set/yield load and stability under yield GEOTECHNICAL CONSIDERATIONS What do we require to control caving? Process used for determining capacity Previously, database approach find similar expected conditions and estimate relative success/changes Ask the OEMs (Joy/DBT) Used to have their own experts to review all the available information No longer interested due to Fitness for Purpose legal arguments Modelling: Ground reaction curves FE Analysis Expert opinions: Callan/Truman Medhurst Frith In-house analysis (BCO and site) 7

8 GEOTECHNICAL CONSIDERATIONS GEOTECHNICAL CONSIDERATIONS 120 Start Posi Set Posi Set Yield pressure % Cumulative % of Time This portion not available, due to being in yield Support Pressure (bar) Ideal Rating Over rated Under rated Very under rated Pressure at Yield 8

9 GROUND RESPONSE CURVE STRATA / SUPPORT CHARACTERISTICS IN EARLY PANELS 9

10 NUMERICAL 300 m MNC 980 tonne 1.75m wide at 4.5m cut MNC 1,080 tonne MNC 1,215 tonne MNC 1,350 tonne (= 1, m wide) NUMERICAL 350 m MNC 980 tonne 1.75m wide at 4.5m cut MNC 1,080 tonne MNC 1,215 tonne MNC 1,350 tonne (= 1, m wide) 10

11 1,500t, 2m WIDE ROOF SUPPORTS at 300 and 350m 1,750t, 2m WIDE ROOF SUPPORTS at 300 and 350m 11

12 ESTIMATED ROOF CONVERGENCE FOR VARIOUS SUPPORT CAPACITY ROOF CONVERGENCE 12

13 INSTALLATION BRIEF HISTORY Feasibility Study done in 2006 and concluded that: To mine deeper panels - require 2m wide x 1750t rated Powered Roof Supports Project approved in April 2007 Contract awarded to Joy Mining Machinery to supply: 151 x PRS (2050mm wide by 1750t rated, 135t/m 2 ) 2 x Armoured Face Conveyor 2 x Shearer Contract awarded to Industria Mining Equipment to supply: 5 x Carriers 2 x Dozers 2 x Retrievers Mini-build at site Rear walkway 13

14 PLANNING Overlapped engineering dimensions of equipment with mine design to determine:- Required height and width of installation face Identify possible height / width issues with proposed Transport Route from Surface to Installation Face Necessary road works to accommodate size and weight of loads (Concreting of critical areas) Relocation of pipes, cables, fire hydrants, etc in the Mains to minimise damage Ventilation restrictions Installation face Transport route (size of loads in roadway) RISK ASSESSMENTS Conducted 18 RA s on Transportation, Installation and Commissioning of complete Longwall system Tracked action completion in SiteSafe Required Safe Work Guideline reviews 14

15 RISK ASSESSMENTS Industrea Mining Equipment supplier of Carriers, Dozers and Retrievers Trials conducted at Dartbrook Mine (Close to IME facilities) Surface trials at Moranbah North Underground trials Drift to face 24/7 OEM Expertise at site during install 70t Roof Support Carrier Specifications: 33.7t Tare Weight with 70t Carry Capacity 190kW 3126 Cat Engine Hydrostatic Drives 1800 x R33 Tyres with Hutchinson Inserts 15

16 70t Roof Support Carrier Loaded Chain Lifting Mechanism Carrier with Lifting Plate Mechanism 16

17 Carrier Cockpit with Camera Screens SETCO Camera Off-driver side 17

18 Carrier Trial Down Drift Measuring Clearances on Trial Run 18

19 Carrier Turning at Intersection Clearance Between Carrier and Rib 19

20 Installing Roof Supports on Face First Supports on the Face 20

21 Last Roof Support Entering Mine ED40 and 936 Transporting Tail Gate Drive 21

22 70t Dozer Surface Trials Shearer Installed at Tail Gate 22

23 Face Installation Complete Training Committee Meeting 2 nd Tuesday Each Month Contractor Safety & Health Committee Meeting 3 rd Thursday Each Month Daily Muster Brief 0600 & 1800 MNC Crew Toolbox Talks & Pass Meetings Weekly Pit Planning Meeting Thursday 1430 Schedule Update Weekly Longwall Planning Meeting Wednesday 1200 Weekly Safety Team Meeting Monday

24 ACHIEVEMENTS DURING INSTALL PROCESS Anglo American s commitment to Zero Harm was maintained at all times: Zero Lost Time Injuries (LTIs) or High Potential Incidents (HPIs) Expenditure within budget Equipment damage was minimal Progress was good (Delays: Drift closures, BSL Overhaul, Goaf gas) Remained focussed on critical path CONCLUSIONS Selection of a support system is a complex task It requires a detailed assessment of conditions, geotechnical requirements, productivity and financial evaluation Moranbah s 1,750t support system has been a success story from the start to date. 24

Abstract. General N BANDA

Abstract. General N BANDA Abstract General For mining operations, both underground and open cast, there are generally accepted criteria used to arrive at the optimum mining method with which to exploit the ore body economically.

More information

Quarterly Report to 30 June 2012

Quarterly Report to 30 June 2012 Quarterly Report to 30 June 2012 18 July 2012 Contents Highlights Operations Coal Renewable Energy Coal Projects and Resource Assessment New Developments Health, Safety and Environment Highlights Coal:

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

PDS COLLISION AVOIDANCE AACSA UNDERGROUND IMPLEMENTATION LEARNINGS

PDS COLLISION AVOIDANCE AACSA UNDERGROUND IMPLEMENTATION LEARNINGS PDS COLLISION AVOIDANCE AACSA UNDERGROUND IMPLEMENTATION LEARNINGS Coal South Africa - 11 June 2015 Prepared for the SACEA Workshop 1 PDS BACKGROUND NEW DENMARK EXAMPLE SUCCESSES CHALLENGES AACSA COLLISION

More information

Too Good to Throw Away Implementation Strategy

Too Good to Throw Away Implementation Strategy Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend

More information

Environment and Infrastructure Services

Environment and Infrastructure Services Agenda Item 5 Staff Report for Committee of the Whole Meeting Department: Division: Subject: Environment and Infrastructure Services Environment Services Waste Collection Contract Purpose: To provide Council

More information

Alfred & Plantagenet Multi-Residential Cart Recycling Program CIF Project Number # Final Report October 1, 2016

Alfred & Plantagenet Multi-Residential Cart Recycling Program CIF Project Number # Final Report October 1, 2016 Alfred & Plantagenet Multi-Residential Cart Recycling Program CIF Project Number #545.3 Final Report October 1, 2016 Prepared for: Waste Diversion Ontario Continuous Improvement Fund Office Barrie, Ontario

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Highway Construction Worker Dies When Struck By Semi-Tractor Trailer Incident Number: 03KY030

Highway Construction Worker Dies When Struck By Semi-Tractor Trailer Incident Number: 03KY030 Highway Construction Worker Dies When Struck By Semi-Tractor Trailer Incident Number: 03KY030 Kentucky Fatality Assessment and Control Evaluation Program Kentucky Injury Prevention and Research Center

More information

Sample Geographic Information System (GIS) Staffing and Response Time Report Virtual County Fire Department GIS Analysis

Sample Geographic Information System (GIS) Staffing and Response Time Report Virtual County Fire Department GIS Analysis Sample Geographic Information System (GIS) Staffing and Response Time Report Fire Department GIS Analysis Executive Summary This study examines predicted response times and geographic coverage areas for

More information

BUILDING REFERENCES IN INDIA

BUILDING REFERENCES IN INDIA BUILDING REFERENCES IN INDIA Shib Bhowmik, Joy Global, India, and Adrian Carley, Joy Global, UK, detail how the company has been helping Indian underground mining operations. P lummeting coal prices are

More information

Tendering Public Charging Infrastructure for Electric Vehicles

Tendering Public Charging Infrastructure for Electric Vehicles European Best Practices: Tendering Public Charging Infrastructure for Electric Vehicles Best Value Procurement in the city of Arnhem Authors: Peter Swart, Arnhem City Roos van der Ploeg, MA legal & EV

More information

Continuous Miner Dust Suppression. Anglo American Coal. The Problem

Continuous Miner Dust Suppression. Anglo American Coal. The Problem Continuous Miner Dust Suppression Anglo American Coal The Problem Coal workers pneumoconiosis is a potentially life threatening disease which was thought to have been eliminated in Australia. Between May

More information

Fleet Safety Initiative Status Summary

Fleet Safety Initiative Status Summary Fleet Safety Initiative Status Summary Deborah Majeski DTE Energy Company October 7, 2008 DTE Energy s Primary Subsidiaries are Gas and Electric Utilities 2 Non-Utility Energy Related Businesses 3 Impact

More information

Mine Hoist Hazards. The incidents over the past 10 years have been associated with causal factors such as, but not limited to:

Mine Hoist Hazards. The incidents over the past 10 years have been associated with causal factors such as, but not limited to: Mine Hoist Hazards WSN Disclaimer The information contained in this material is provided as a guide only. WSN recognizes that individual companies must develop health and safety policies and programs which

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the, and double deck ( dd) analysis Including: Description of the Vehicles

More information

Underground elearning Longwall Course Catalog

Underground elearning Longwall Course Catalog Underground elearning Longwall Course Catalog Contents Longwall Product Overview... 3 Powered Roof Supports Operator Training... 5 Powered Roof Supports Electrical Training... 8 Powered Roof Supports Mechanical

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the EMU, DMU and DMU double deck (DMU dd) analysis Including: Description

More information

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Report for Action Wilson Bus Garage - Upgrades Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Summary The purpose of this report is to obtain authorization for the award of Contract No.

More information

LHD Working at Height Platforms

LHD Working at Height Platforms Replace with a photograph LHD Working at Height Platforms Paul Redelinghuys UG Maintenance Manager (Khutala Colliery) 15 April 2011 Slide 1 Background Working at heights in the UG Mining Industry has been

More information

The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including:

The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including: Public Report To: From: Report Number: Community Services Committee Ron Diskey, Commissioner, Community Services Department CS-17-18 Date of Report: March 24, 2017 Date of Meeting: March 30, 2017 Subject:

More information

ClearRoute Training Courses

ClearRoute Training Courses ClearRoute Training Courses Balfour Beatty Rail offers a wide range of courses designed to benefit all levels of users of its market leading clearance software, ClearRoute. See inside for full details

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

Work at height: Elevated risk

Work at height: Elevated risk Chris Wraith outlines how the powered access industry is using global fatality data to reduce serious MEWP accidents. Article date: Monday, August 7, 2017-18:00 MEWPs Falls from height are still the number

More information

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas

More information

Occupational Driving Consider the Risks. Sandra Wilson, OSACH

Occupational Driving Consider the Risks. Sandra Wilson, OSACH Occupational Driving Consider the Risks Sandra Wilson, OSACH Session Outline Who is driving for work purposes? What are the risks factors? How can I minimize these risks? 2 What do you think? True or false:

More information

Mining Machines Division BELT CONVEYORS

Mining Machines Division BELT CONVEYORS BELT CONVEYORS BELT CONVEYORS Belt conveyors are intended for transport of loose materials. They meet requirements for use in gassy coal-mines with danger of methane and coal dust explosion. Belt width

More information

2 FOREWORD. 2.1 Description of Mine 2.2 Report Preparation Process 2.3 General Acknowledgements

2 FOREWORD. 2.1 Description of Mine 2.2 Report Preparation Process 2.3 General Acknowledgements 2 FOREWORD 2.1 Description of Mine 2.2 Report Preparation Process 2.3 General Acknowledgements 2.1 Description of the Mine The unincorporated village of Sago is located in Upshur County, West Virginia.

More information

SIUC INNOVATIVE SPRAY SYSTEM FOR CONTINUOUS MINERS AND DEVELOPMENT OF LONGWALL DUST CONTROL LABORATORY

SIUC INNOVATIVE SPRAY SYSTEM FOR CONTINUOUS MINERS AND DEVELOPMENT OF LONGWALL DUST CONTROL LABORATORY SIUC INNOVATIVE SPRAY SYSTEM FOR CONTINUOUS MINERS AND DEVELOPMENT OF LONGWALL DUST CONTROL LABORATORY SIU Research Team Dr. Y. P. Chugh, Dr. Kanchan Mondal, Harrold Gurley, John Pulliam, Mike Smith, Vijaya

More information

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS 1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the

More information

Civil Engineer. Tasks

Civil Engineer. Tasks Civil Engineer Are you ready to be a technology pioneer? Oil and gas factories 3000 meters underwater, heavy locomotive traction motors, electric vehicle chargers that deliver 100kw in 30 minutes... you

More information

Selling PFIFFNER in the UK. Paul Haines

Selling PFIFFNER in the UK. Paul Haines Selling PFIFFNER in the UK. Paul Haines Contents Introduction, Country & Market Overview UK. Accessing the Market Critical Success Factors. Developing the Business Together. Proposed Pfiffner Support.

More information

MEMORANDUM. TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit. Date: May 24, Summary

MEMORANDUM. TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit. Date: May 24, Summary TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Date: May 24, 2016 MEMORANDUM To: From: Subject: File No: Chair Tom Galloway and Planning and Works Committee Thomas Schmidt Revised Bombardier Vehicle

More information

Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street

Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Department of Environmental Services, Transportation Division Sept. 27, 2018

More information

Charmec LC 605 D(V) Features. Technical data sheet AUSTRALIA

Charmec LC 605 D(V) Features. Technical data sheet AUSTRALIA Pictured machine may include options and additional equipment. Features charger with diesel hydraulic drive is designed for face and production charging in underground mines and tunnels up to 65 m 2 cross

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

Integrated Drive Systems by Siemens

Integrated Drive Systems by Siemens Integrated Drive Systems by Siemens Shift your perspective and maximize your value and efficiency. Most companies spend too much time Managing multiple vendors for multiple components of the drive train

More information

Glengowrie Depot Upgrade. Nick Marciano, Manager Tram Maintenance, PTS

Glengowrie Depot Upgrade. Nick Marciano, Manager Tram Maintenance, PTS Glengowrie Depot Upgrade Nick Marciano, Manager Tram Maintenance, PTS Introduction Nick Marciano Took up role of Tram Maintenance Manager in June 2009. Prior to that: 35 years in manufacturing starting

More information

MIFACE INVESTIGATION #06MI209

MIFACE INVESTIGATION #06MI209 MIFACE INVESTIGATION #06MI209 SUBJECT: Heavy Equipment Operator Dies After Being Pinned Between the Boom and Cab of an Excavator Summary On December 4, 2006, a 51-year-old male heavy equipment operator

More information

Guidelines for Battery Electric Vehicles in the Underground - Mine Design

Guidelines for Battery Electric Vehicles in the Underground - Mine Design Guidelines for Battery Electric Vehicles in the Underground - Mine Design April 30 th, 2017 Presented By: Alain Richard Cheryl Allen Electrical Engineer Principal Engineer Ventilation BESTECH Vale Ontario

More information

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population

More information

Charmec LC 605 D(V) Features. Technical data sheet

Charmec LC 605 D(V) Features. Technical data sheet Pictured machine may include options and additional equipment. Features charger with diesel hydraulic drive is designed for face and production charging in underground mines and tunnels up to 65 m 2 cross

More information

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks by Georges Barbarin Executive summary Aging electrical switchgear infrastructure is a threat to the reliability of power

More information

Charmec MC 605 D(V) Features. Technical data sheet AUSTRALIA

Charmec MC 605 D(V) Features. Technical data sheet AUSTRALIA Pictured machine may include options and additional equipment. Features Charmec MF 605 D charger with diesel hydraulic drive is designed for face and production charging in underground mines and tunnels

More information

Utimec LF 600 Agitator

Utimec LF 600 Agitator Pictured machine may include options and additional equipment. Features Utimec LF 600 Agitator with practical concrete transport capacity of 6 m 3 is designed for concrete transportation in underground

More information

Crenshaw-Prairie Transit Corridor Study Public Meetings

Crenshaw-Prairie Transit Corridor Study Public Meetings Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,

More information

NYSEG Accident-free Driving: AGA Motor Vehicle Safety Achievement

NYSEG Accident-free Driving: AGA Motor Vehicle Safety Achievement Allen Peterson, Manager Gas Operations Steven Hadcock, Health & Safety Compliance October 2016 NYSEG Accident-free Driving: AGA Motor Vehicle Safety Achievement www.avangrid.com 1 Who We Are IBERDROLA,

More information

workplace charging an employer s guide

workplace charging an employer s guide workplace charging an employer s guide taking responsibility At your business, the efficient use of energy brings benefits such as lower bills, improved comfort levels for your customers and employees,

More information

Item No Halifax Regional Council June 21, 2016

Item No Halifax Regional Council June 21, 2016 P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 14.2.2 Halifax Regional Council June 21, 2016 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Councillor Tim Outhit, Chair,

More information

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand.

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. WHAKAMARU POWER STATION REHABILITATION PROJECT Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. ABSTRACT Whakamaru Power Station in the North Island of New Zealand

More information

BETHLEHEM MISSIONS TRUST CAMPUS

BETHLEHEM MISSIONS TRUST CAMPUS BETHLEHEM MISSIONS TRUST CAMPUS Prepared For: Prepared By: Wasley Knell Consultants PO Box 5015, Mount Maunganui, 3150 BruceWRobinson@msn.com/(027) 4515685 Table of Contents Introduction... 3 Site Vicinity...

More information

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS... Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

More information

Charmec MF 605 DA. Features. Technical data sheet USA & Canada

Charmec MF 605 DA. Features. Technical data sheet USA & Canada Pictured machine may include options and additional equipment. Features Charmec MC 605 ANFO charger with diesel hydraulic drive is designed for face and production charging in underground mines and tunnels

More information

Mine Safety 101. A Complete Solution to Lost Persons Detection (LPD) in Underground Mining

Mine Safety 101. A Complete Solution to Lost Persons Detection (LPD) in Underground Mining Mine Safety 101 A Complete Solution to Lost Persons Detection (LPD) in Underground Mining Mine Safety 101 A complete solution to lost persons detection (LPD) in Underground Mining Table of Contents Common

More information

Request for Proposal for Trolley Security Services

Request for Proposal for Trolley Security Services Request for Proposal for Trolley Security Services April 6, 2018 Trolley Security Support Services The Loop Trolley Company The Loop Trolley Company (LTC) is requesting proposals for armed on-board security

More information

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000. Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS

More information

Risk Based Maintenance

Risk Based Maintenance Dai Richards ABB Eutech Risk Based Maintenance ABB Industries - 1 - Overview Delivering sustainable improvements is hard No time Changing priorities BU concepts appear well understood ABB Industries -

More information

Public Works and Infrastructure Committee. p:/2015/clusterb/tra/northyork/pw15086

Public Works and Infrastructure Committee. p:/2015/clusterb/tra/northyork/pw15086 PW9.10 STAFF REPORT ACTION REQUIRED Car-Share Parking in Permit Parking Areas Date: October 22, 2015 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Transportation

More information

Blasting in Underground Coal Mines. ACARP Project C20033

Blasting in Underground Coal Mines. ACARP Project C20033 Blasting in Underground Coal Mines ACARP Project C20033 Blasting in Coal Mines Modern mechanised coal mines use machines and longwall mining methods to cut solid coal and convey the broken coal out of

More information

Design of a new layout for sublevel caving at depth

Design of a new layout for sublevel caving at depth Caving 2018 Y Potvin and J Jakubec (eds) 2018 Australian Centre for Geomechanics, Perth, ISBN 978-0-9924810-9-4 https://papers.acg.uwa.edu.au/p/1815_33_quinteiro/ Design of a new layout for sublevel caving

More information

Utimec LF 600 Transmixer

Utimec LF 600 Transmixer Pictured machine may include options and additional equipment. Features Utimec LF 600 Transmixer with practical concrete carrying capacity of 5.6 m 3 is designed for heavy concrete transportation in underground

More information

Equipment Strategy for Stand By Diesel Generators Strategy

Equipment Strategy for Stand By Diesel Generators Strategy Equipment Strategy for Stand By Diesel Generators Strategy Current version: 26/06/2018 EXTERNAL USE Page 1 of 6 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 Defined terms...

More information

Safe Use of Roll Cages and Donation Chair Bespoke Trolleys

Safe Use of Roll Cages and Donation Chair Bespoke Trolleys Safe Use of Roll Cages and Donation Chair Bespoke Trolleys Module 3 Updated April 16 Estimated course delivery time: 1.5-2 hours depending on size of group. Equipment Required: 7.5 tonne Team Vehicle Roll

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

To identify and formalise the risks and control processes involved in performing daily operations checks of cranes and vehicles.

To identify and formalise the risks and control processes involved in performing daily operations checks of cranes and vehicles. Operations s - Slew Cranes Risk Assessment Name RA SOP 04 checks Slew Cranes 1. Aim of procedure To identify and formalise the risks and control processes involved in performing daily operations checks

More information

Improving predictive maintenance with oil condition monitoring.

Improving predictive maintenance with oil condition monitoring. Improving predictive maintenance with oil condition monitoring. Contents 1. Introduction 2. The Big Five 3. Pros and cons 4. The perfect match? 5. Two is better than one 6. Gearboxes, for example 7. What

More information

Boston Scientific Energy Storage Project. Final Report (PUBLIC) November 2016

Boston Scientific Energy Storage Project. Final Report (PUBLIC) November 2016 Boston Scientific Energy Storage Project Final Report (PUBLIC) November 2016 Executive Summary Kingspan ESB Limited applied for Energy RD&D funding for the Boston Scientific Solar PV Energy Storage Project

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: December 16, 2009 SUBJECT: CANADIAN CONTENT BUS PROCUREMENTS ACTION ITEM RECOMMENDATION It is recommended that the Commission

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED nsert TTC logo here STAFF REPORT ACTION REQUIRED Gap Between Subway Trains and Platforms Date: November 13, 2017 To: From: TTC Board Chief Executive Officer Summary This report is in response to an October

More information

Critical Chain Project Management (CCPM)

Critical Chain Project Management (CCPM) Critical Chain Project Management (CCPM) Sharing of concepts and deployment strategy Ashok Muthuswamy April 2018 1 Objectives Why did we implement CCPM at Tata Chemicals? Provide an idea of CCPM, its concepts

More information

Vehicle Replacement Policy - Toronto Police Service

Vehicle Replacement Policy - Toronto Police Service STAFF REPORT June 21, 2000 To: From: Subject: Policy and Finance Committee Chairman, Toronto Police Services Board and City Auditor Vehicle Replacement Policy - Toronto Police Service Purpose: The purpose

More information

LHD Vehicles. Product Line

LHD Vehicles. Product Line LHD Vehicles Product Line Load Haul Dump Diesel Multipurpose Vehicles We have a long history of designing and manufacturing diesel-powered utility vehicles for various applications in underground mining

More information

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below:

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below: 3.5 TRAFFIC AND CIRCULATION 3.5.1 Existing Conditions 3.5.1.1 Street Network DRAFT ENVIRONMENTAL IMPACT REPORT The major roadways in the study area are State Route 166 and State Route 33, which are shown

More information

TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA

TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA 20 March 2014 Report prepared by: Corli Havenga Transportation Engineers

More information

Safety and Operations Committee. Action Item III-A. December 13, 2018

Safety and Operations Committee. Action Item III-A. December 13, 2018 Safety and Operations Committee Action Item III-A December 13, 2018 Preventive Maintenance Update Page 3 of 46 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

Tank Farm Additional Storage Site Layout

Tank Farm Additional Storage Site Layout MONTREAL TRUDEAU INTERNATIONAL AIRPORT MIFFC Fuel Committee Meeting Montreal Airport Marriott Hotel, June 15, 2017 Tank Farm Additional Storage Site Layout 1 Tank Farm Additional Storage - Construction

More information

Maintaining frictional resistance on mine road surfaces. Presented by Cres Bulger Inspector Of Mines (Qld)

Maintaining frictional resistance on mine road surfaces. Presented by Cres Bulger Inspector Of Mines (Qld) Maintaining frictional resistance on mine road surfaces Presented by Cres Bulger Inspector Of Mines (Qld) Background Statistics From 1 st Jan-10 to 11th May 2015 there have been 477 High Potential Incidents

More information

CENTURY MONTHLY DEVELOPMENT UPDATE JUNE 2018

CENTURY MONTHLY DEVELOPMENT UPDATE JUNE 2018 ASX / MEDIA ANNOUNCEMENT ASX: NCZ 02 July 2018 CENTURY MONTHLY DEVELOPMENT UPDATE JUNE 2018 New Century continues strong progress toward restarting Century operations, with planned refurbishment activities

More information

Forest Hill Street Clutter study

Forest Hill Street Clutter study 1 Local Fund and Street Clutter London Borough of Lewisham Forest Hill Street Clutter study Colin Davis Associates Traffic and Urban Design consultants January 2010 020 8398 7837 colinjdavis@aol.com www.publicrealm.info

More information

FLAIL SYSTEMS LIGHT FLAIL DIGGER 2

FLAIL SYSTEMS LIGHT FLAIL DIGGER 2 FLAIL SYSTEMS LIGHT FLAIL DIGGER 2 Digger DTR Demining Technologies Switzerland GENERAL DESCRIPTION The Digger D-2 is a light-weight, remotely-controlled multi-tool mine clearance vehicle developed by

More information

Condition Based Maintenance for Maximized. October 13-14, 2009

Condition Based Maintenance for Maximized. October 13-14, 2009 POWER Condition Based Maintenance for Maximized Reliability and Life Cycle Performance Johan Pellas Wärtsilä October 13-14, 2009 Return to Session Directory CBM (Condition Based Maintenance) For Maximized

More information

ENVIRONMENTAL IMPACT STATEMENT

ENVIRONMENTAL IMPACT STATEMENT RED HILL MINING LEASE ENVIRONMENTAL IMPACT STATEMENT Section 14 Transport Section 14 Transport 14.1 Description of Environmental Values This section of the Red Hill Mining Lease Environmental Impact Statement

More information

BULK MATERIAL HANDLING SYSTEM

BULK MATERIAL HANDLING SYSTEM (PTY) Ltd BULK MATERIAL HANDLING SPECIALISTS We are proud members of the South African Institute of Materials Handling BULK MATERIAL HANDLING SYSTEM Deebar Rail-Veyor PTY (Ltd) was the first company to

More information

Tail Lift Services. Part of Bevan Group

Tail Lift Services.  Part of Bevan Group Tail Lift Services www.aftercareresponse.uk Part of Bevan Group Taking care of all of your commercial vehicle needs As established leading commercial vehicle body specialists, our comprehensive range

More information

McNary Northshore Fishway Hydro Project. History & Lessons Learned

McNary Northshore Fishway Hydro Project. History & Lessons Learned McNary Northshore Fishway Hydro Project History & Lessons Learned May 6, 2017 21 th Annual TECHNICAL SEMINAR Machines, Maintenance, and Management: Keeping Hydro Facilities Up and Running History & Lessons

More information

Board 8/24/2017 Final Action Bonnie Todd, Executive Director of Operations Martin Young, Commuter Rail Manager

Board 8/24/2017 Final Action Bonnie Todd, Executive Director of Operations Martin Young, Commuter Rail Manager MOTION NO. M2017-103 Sounder Heating, Ventilating and Air Conditioning Service Contract MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: 8/24/2017 Final Action Bonnie Todd, Executive Director of Operations

More information

Measure Evaluation Results

Measure Evaluation Results Measure Evaluation Results BOL 8.1 Motorbike Pollution Reduction Mirco Armandi Daniela Cocchi Date: February 2013 Executive Summary Since 2003 an automatic system to control the main entrance point to

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

La Canada Flintridge Parents for Healthy Air November 1, 2018 Presented by Elizabeth Krider, Ph.D., Esther Kornfeld and Tamar Tujian

La Canada Flintridge Parents for Healthy Air November 1, 2018 Presented by Elizabeth Krider, Ph.D., Esther Kornfeld and Tamar Tujian Concerns regarding the Devil s Gate Sediment Removal Project 1. New science demands new assessment of health risks to 3,000 sensitive receptors nearby. a. Air pollution is the new tobacco health crisis,

More information

A Gap-Based Approach to the Left Turn Signal Warrant. Jeremy R. Chapman, PhD, PE, PTOE Senior Traffic Engineer American Structurepoint, Inc.

A Gap-Based Approach to the Left Turn Signal Warrant. Jeremy R. Chapman, PhD, PE, PTOE Senior Traffic Engineer American Structurepoint, Inc. A Gap-Based Approach to the Left Turn Signal Warrant Jeremy R. Chapman, PhD, PE, PTOE Senior Traffic Engineer American Structurepoint, Inc. March 5, 2019 - The problem: Existing signalized intersection

More information

The Regional Municipality of York. Purchase of Six Battery Electric Buses

The Regional Municipality of York. Purchase of Six Battery Electric Buses 1. Recommendations The Regional Municipality of York Committee of the Whole Transportation Services January 10, 2019 Report of the Commissioner of Transportation Services Purchase of Six Battery Electric

More information

Centerwide System Level Procedure

Centerwide System Level Procedure 5.ARC.0004.2 1 of 10 REVISION HISTORY REV Description of Change Author Effective Date 0 Initial Release J. Hanratty 7/17/98 1 Clarifications based on 7/98 DNV Audit and 6/98 Internal Audit (see DCR 98-029).

More information

The Highways Agency is working to improve the M3 between junctions 2 to 4a.

The Highways Agency is working to improve the M3 between junctions 2 to 4a. Welcome The Highways Agency is working to improve the M3 between junctions 2 to 4a. The M3 Junctions 2 to 4a is part of a major strategic road network connecting people, communities and businesses, carrying

More information

DCTC Procedure Vehicle Use

DCTC Procedure Vehicle Use DCTC Procedure 6.14.1 Vehicle Use Chapter 6 Facilities Management For purposes of clarification, this procedure includes all vehicles regardless of department affiliation or campus. Part 1. Authorized

More information

52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK)

52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK) 52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK) 52.1.1 GENERAL The Work consists of loading trucks, snowplowing and the application of sand, salt or a sand and salt mixture to roadway surfaces. 52.1.2 MATERIALS

More information

CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS

CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS COMPRESSED NATURAL GAS 35-FOOT TRANSIT BUSES CONTRACT NUMBER ML09032 FINAL REPORT APRIL 2015 SUBMITTED BY: LOS ANGELES WORLD AIRPORTS MAINTENANCE DIVISION Prepared

More information

South African Colliery Engineers Association Conveyor Safety

South African Colliery Engineers Association Conveyor Safety South African Colliery Engineers Association Conveyor Safety 29 May 2015 Supporting the Professional Engineer in a changing industry (organisational change, cost pressure, reposition) Value add, Visibility,

More information

Pyhäsalmi Mine - History, Present and Future

Pyhäsalmi Mine - History, Present and Future Pyhäjärvi Energy Storage in Mine Pyhäsalmi Mine - History, Present and Future Hilton Helsinki Airport, Vantaa, Finland 5 April 2018 Outline Pyhäsalmi Mine First Quantum Minerals Ltd Production History

More information