GRID SYSTEM INVESTMENTS

Size: px
Start display at page:

Download "GRID SYSTEM INVESTMENTS"

Transcription

1 EB-0-0 Exhibit D Page of GRID SYSTEM INVESTMENTS SUSTAINING PORTFOLIO OVERHEAD SYSTEM The THESL overhead distribution system supplies power to customers at three primary voltages:. kv,. kv, and. kv. The main components of the overhead system are poles, pole-top transformers, switches and other overhead assets such as conductors, fuses, lightning arresters, insulators, and grounding devices. 0 The overhead system has been steadily deteriorating over the past five years. Figure shows the five-year Customers Interrupted ( CI ) numbers directly caused by defective overhead equipment have increased approximately percent. Figure : Customers Interrupted Overhead System The overhead system is also very susceptible to other outage causes such as tree contacts, animal contacts, lightning, and adverse weather conditions.

2 EB-0-0 Exhibit D Page of Figure illustrates the percentage of CI attributable to the overhead system, and that the overhead system is responsible for the majority of the overall CI. Figure : Customers Interrupted Comparison of Overhead and Overall Systems 0 As stated in the 0-0 Electrical Distribution Capital Plan ( EDCP ) in Exhibit D, Tab, Schedule, THESL will address ageing infrastructure as well as system enhancement initiatives in order to maintain and improve reliability. Like-for-like replacement of aging assets is performed on the assets at or beyond their useful lives. Each asset is replaced in accordance with new standard specifications. This provides for better performance, reduced environmental impacts, and mitigates employee and public safety risks. System Enhancement initiatives are based on reconfiguration of system assets. The major focus is on reconfiguring the trunk portion of a feeder. A trunk portion of the feeder is a main distribution line which supplies power directly from a station. A lateral portion of the feeder is a distribution line which branches out form the trunk. Should an

3 EB-0-0 Exhibit D Page of outage occur on a trunk, approximately,000 customers will be out of power whereas less than 00 customers will be affected if the outage occurs on a lateral. Figure illustrates that the majority of CI is attributable to trunk rather than lateral portions. Figure : Lateral vs Trunk CI Contribution 0 THE OVERHEAD WORK PROGRAM Figure illustrates the overhead projects to be undertaken during 0-0. A summary description of these projects is provided below.

4 EB-0-0 Exhibit D Page of Figure : Map of Planned Overhead Projects for 0-0 The following Table illustrates the capital budget of the Overhead Sustaining portfolio for the historical, bridge and test years. Table : Overhead Sustaining Capital Summary ($ millions) 00 Actual 00 Actual 00 Actual 0 Bridge 0 Test 0 Test 0 Test Overhead Substantial additional capital expenditures are required for overhead systems starting in year 0. The 0 overhead capital budget is $. million. This amount is necessary to address the steep trend of declining overhead reliability and reduce the portion of overall system interruptions attributable to the overhead system. The 0 figure

5 EB-0-0 Exhibit D Page of 0 represents an additional $0. million over 0 to meet the following requirements: Increase ageing asset replacement Increase system enhancement reconfiguration needs Address rear lot conversion that had been initially driven through the underground portfolio during 0 Remove box construction plant Expand feeder automation Address insufficient tree-proof conductor Remedy improper protection Increase fault circuit indicators 0 During 0, an additional $. million is required compared to 0. This increase is primarily needed to address the following overhead system conditions: Lack of sufficient feeder tie-points Overloaded feeders Undersized primary wire Insufficient lateral ties Coordination of lateral fuses Insufficient animal guard protection Overloaded pole mounted transformers Conversion of trunk portion of feeders to fused laterals During 0, an additional $. million is required compared to 0. This increase is primarily needed to address the following conditions: Insufficient feeder tie-points Additional requirements for removal of box construction plant Relocation of assets away from high salt contamination areas

6 EB-0-0 Exhibit D Page of Table illustrates the major units and quantities required during 0-0. Table : Planned Investment Schedule Poles,,, Remote Switches Conductors (km) Fuses 0,0, Animal Guards 0,, Fault Circuit Indicators ( FCIs ),,, Insulators,,0, Pole Mounted Transformers, Box Construction - kv Feeder Removal (km) Ageing Assets Poles Spot replacements are determined from a pole testing program, from field assessment conducted by experienced field crew members, and by engineers. As a result of this data, THESL will replace approximately,000 end-of-life poles during 0-0. These poles are distributed across the city specifically in the areas of Fairbanks TS, Bathurst TS, Horner TS, Finch TS and municipal stations. The remaining poles mentioned in Table will be replaced through other themes described below. In deciding whether to replace a pole that has reached the end of its useful life, THESL considers several alternative approaches. THESL compares like-for-like replacement of ageing assets against upgrading the circuit to a higher primary voltage. Figure illustrates a typical residential area where field data indicates the existence of end-of-life poles requiring replacement.

7 EB-0-0 Exhibit D Page of Figure : Replacement of End-of-Life Assets 0 Figure illustrates a proposed project relating to a Finch TS feeder, namely NYM. As is evident from the field data above, more than percent of the poles in this area require replacement. It is important to note that during replacements of the poles, other under-performing assets are also replaced such as the porcelain insulators. Furthermore, the NYM feeder has sustained eight outages in the past year and is in the worst six percent of the feeders with respect to CI and CHI contribution. THESL uses the rebuild of ageing assets as an opportunity to address system enhancement issues. This approach will improve system reliability, efficiency, and safety. Replacement of Underperforming Assets The 0-0 overhead capital program s focus is to replace porcelain insulators on feeders near Leslie TS, Agincourt TS, Leaside TS, Runneymede TS and Fairbanks TS.

8 EB-0-0 Exhibit D Page of Much of the equipment in these areas is under-performing. The majority of replacements will occur on the.kv system. Underperforming porcelain insulators are replaced with polymeric type insulators as part of aging assets rebuild and/or enhancement projects. Figure illustrates the existence of porcelain insulators on poles in good condition. Figure : Replacement of Underperforming Insulators 0 In the area shown in Figure, out of 0 locations contain porcelain insulator that are underperforming. This feeder, YKM, is supplied by Runnymede TS. During a recent insulator related outage in 0 on this feeder,, customers experienced an outage that lasted over two hours. Rehabilitation of Worst Performing Feeders As the overhead distribution plant gets older, the probability of failure increases rapidly. This has resulted in a large number of sustained outages on older feeders. Furthermore,

9 EB-0-0 Exhibit D Page of certain feeders have sustained many more outages than others. In the 0-0 capital program, rehabilitation of feeders is conducted across the city with particular focus on the worst performing feeders ( WPF ). These areas include feeders related to Agincourt TS, Bathurst TS, Bermondsey TS, Cavanagh TS, Fairbanks TS, Fairchild TS, Finch TS, Leslie TS, Runnymede TS, Warden TS and some municipal stations. As part of the rehabilitation of the feeders, efforts are made to combine resources and also replace under-performing and aging assets. Table lists some of the feeders where overhead projects relating to worst performing feeders are planned for Table : Worst Performing Feeders Feeder FESI CI CHI SAIFI SAIDI Contribution Contribution M,, M,, M,0, M 0,0, SS-F,, M,, M0,0, M,, M 0,, M 0,, M 0,, M, M,, NTM,0, M, M,, NA0M,0, NARM 0,0, 0.0. SS-F,

10 EB-0-0 Exhibit D Page 0 of Feeder FESI CI CHI SAIFI Contribution SAIDI Contribution M, M,, M, SS-F,, Total,, The feeders shown on Table have high number of sustained outages, high CI and CHI values, and include Feeders Experiencing Sustained Interruptions ( FESI ). Based on the FESI and WPF analysis, capital projects have been identified to address these feeders over the next three years. 0 Voltage Conversion Many parts of the.kv system have been in service since the mid 0s. Based on the age of these assets, heath index information, feeder patrols, and crew expertise, most of them are past their useful life. As part of the 0-0 overhead capital program, THESL plans to rehabilitate and convert portions of the. kv-system across the city to a higher voltage. During 0-0, these conversions will be conducted such that after conversion the feeders will be supplied by Manby TS, Richview TS, Bermondsey TS, Sheppard West TS and Dupont MS. Figure illustrates the end-of-life condition for assets slated for a. kv conversion project.

11 EB-0-0 Exhibit D Page of Figure :. kv Conversion Project Figure shows a planned project for the voltage conversion for Queensway MS. It shows that all poles are required to be replaced based on field data. In addition, these feeders have reached or are approaching end-of-life conditions. 0 Feeder Automation ( FA ) For 0-0 THESL will continue grid modernization initiatives to integrate proven automation solutions into the existing distribution system. Grid modernization has evolved into an integrated planning and operational model. THESL plans to install FA schemes for overhead trunk portions of feeders to improve reliability. Automated remote fault sensing switches will be installed on feeders throughout THESL s distribution system. This will continue the successful implementation of FA started in 00. Figure illustrates the areas where THESL plans to expand FA schemes during 0-0.

12 EB-0-0 Exhibit D Page of Figure : Map of Planned Feeder Automation Areas (00-0) 0 Lack of Sufficient Feeder Tie-points THESL plans to extend feeders to ensure there are adequate distinct tie-points for each feeder. This will have an effect of improving reliability. Distinct tie-points will be constructed on feeders that do not currently have sufficient tie-points. The focus between 0 and 0 is specifically for areas where feeder automation is planned. This will enable the feeder automation schemes to be more effective. The following Figure shows the areas with insufficient feeder tie-points.

13 EB-0-0 Exhibit D Page of Figure : Map of Feeder Tie-points Overloaded Feeders To relieve overloaded feeders, THESL plans to rearrange and extend feeders. This will reduce CMOs (Customer Minutes Off). In some cases, feeders will have to be reconfigured in order to provide suitable points of load transfer. In other cases, feeder positions will have to be extended from new circuit breaker positions. Figure 0 shows the location of overloaded feeders.

14 EB-0-0 Exhibit D Page of Overloaded Feeders Figure 0: Map of Overloaded Feeders Insufficient Tree-Proof Conductors THESL plans to install tree-proof conductor along the overhead trunk portion of feeders to reduce CIs. In areas that are heavily treed in close proximity to overhead conductors, tree-proof conductor will replace bare wires. One of the most heavily treed areas is the feeders supplied by Runnymede TS. Table illustrates the areas of focus for 0-0.

15 EB-0-0 Exhibit D Page of Table : List of Feeders Requiring Tree Proof Conductors Station Feeders OH Length Requiring Tree Proof (kilometres) Runnymede TS YKM. Runnymede TS YKM. Runnymede TS YKM. Runnymede TS YKM. Runnymede TS YKM 0. Runnymede TS YKM. Runnymede TS YKM. Undersized Primary Wire THESL plans to replace under-sized wire along the trunk portion of feeders to increase capacity and improve reliability. In areas where there are undersized wires on the overhead trunk portion of feeders, the wires will be replaced with conductor as per THESL s standard construction. In 0-0, THESL plans to prioritize the replacement of undersized conductors on overloaded feeder areas. Figure illustrates areas where undersized conductors are present.

16 EB-0-0 Exhibit D Page of Undersized Wire Figure : Map of Undersized Wire Relocation of Assets from Areas with Salt Spray Contamination THESL plans to relocate overhead assets away from areas where salt exposure is highly probable, such as major highways, to reduce CIs. This will be done in areas where the overhead trunk portion of a feeder is in close proximity to areas susceptible to salt contamination. Figure below illustrates areas whereby overhead trunk wire is susceptible to high salt exposure.

17 EB-0-0 Exhibit D Page of Figure : Map of Overhead Assets Near Highway crossings Insufficient Fault Circuit Indicators Fault Circuit Indicators ( FCIs ) are devices which indicate the passage of fault current on a section of cable during momentary interruptions and forced outages. Table illustrates the feeder locations where THESL plans to install FCIs during 0-0.

18 EB-0-0 Exhibit D Page of Table : List of Stations and Feeders Requiring Fault Circuit Indicators STATION FEEDER STATION FEEDER BERMONDSEY TS NYM RICHVIEW TS ETM NYM YKM NYM ETM NYM ETM EYM ETM NYM ETM NYM ETM EYM ETM NYM ETM NYM ETM NYM0 ETM NYM ETM FINCH TS NYM ETM NYM ETM ETM ETM NYM ETM NYM ETM NYM LESLIE TS NYM MALVERN TS SCNARM NYM SCNARM NYM SCNARM NYM SCNARM NYM SCNARM NYM SCNARM NYM SCARBOROUGH SCNAE-M0 NYM0 WEST TS SCNAE-M NYM SCNAE-M NYM SCNAE-M NYM

19 EB-0-0 Exhibit D Page of STATION FEEDER STATION FEEDER WARDEN TS EYNARM NYM SCNARM RUNNYMEDE TS YKM SCNARM YKM EYNARM NYM EYNARM YKM SCNARM YKM SCNARM0 YKM SCNARM YKM SCNARM YKM SCNARM Total of Stations SCNARM Insufficient Lateral Ties THESL plans to provide lateral ties when a large number of overhead customers are supplied by feeders in a radial configuration. Projects typically include the installation of one or more fuses and a small quantity of poles and conductors. In 0-0, THESL plans to install lateral ties in areas that have high probabilities of failure on the lateral portion of feeders. 0 Conversion of Trunk Portion of Feeders to Fused Laterals Where applicable, THESL plans to reduce the trunk portion of feeders and convert them to fused laterals in order to improve reliability. Areas of focus for 0-0 will be low cost applications requiring a small quantity of fuses, poles and conductors. Co-ordination of Lateral Fuses THESL plans to install adequate and appropriate fuse co-ordination on the lateral portion of feeders. During 0-0, THESL plans to install appropriate fuses in areas that have a high probability of failure. Figure illustrates locations requiring fuses.

20 EB-0-0 Exhibit D Page 0 of Location Requiring Fusing Figure : Locations Require Fuses Insufficient Animal Guard Protection THESL plans to install, animal guard protectors between 0 and 0 on transformers to improve reliability. Priority will be given to the areas where animal contacts during the past five years have caused a high number of sustained outages. Table illustrates the feeders that will be given priority.

21 EB-0-0 Exhibit D Page of Table : Animal Guard Installation 0-0 # of Animal Contacts by Year # of # of Animal Contacts by Year # of Feeder Transformers FESI # Feeder Transformers FESI # Total on Feeder Total on Feeder NYSS F 0 YKM NYSS F 0 0 EYM 0 SCSGF TOADN SCNARM0 ETR0M 0 SCYBF SCNARM SCNAHM0 0 ETNF 00 SCREF SCPJF SCREF ETM 0 NYSS F NYM 0 NYSS F YKM NYSS F NYM NYM 0 0 ETR0M0 0 NYM 0 NYM0 SCNAE M 0 ETM SCNARM 0 ETM SCXJF 0 ETM SCNARM ETRM NYSS F NYM SCNHF 0 SCXGF SCPJF 0 0 TOA0E EYNARM TOA0GL SCKHF TOA0GD ETR0M TOADN NYM 0 ETDAF 0 NYM EYM 0 NYM 0 NYM NYM0 NYM ETRM NY0M NYM NY0M TOADN NYM NYM NY0M0 ETM YKM SCXGF 0 ETM 0 TOA0GD 0 SCNAM TOA0DX 0 0 ETEHF NYM NYM 0 NYSS F SCNAE M ETM YKM NYM ETM ETR0M ETR0M NYM NYM 0 NYM 0 NYSS F NY0M 0 SCNARM NYM TOA0BN 0 TOA0DX TOADN NYSS F YKM 0 SCNAHM NYM ETRM TOAE 0 EYM 0 TOADN NYM ETM 0 NYSS F ETM 0 SCNHF ETM 0 0 EYNARM ETM 0 NY0M SCNAHM 0 0 NYSS F SCXJF 0 ETM TOA0GD 0 NYM TOA0GL 0 0 NYM NYM ETR0M NYM NYM NYM 0 Overloaded Pole-Mounted Transformers Between 0 and 0 THESL plans to replace, overloaded pole-mounted transformers. These transformers are located throughout the city.

22 EB-0-0 Exhibit D Page of Highway Overhead Crossings THESL plans to relocate overhead crossings over major highways. During 0-0, THESL will focus on assets in the areas of QEW to Diesal Drive, QEW and Wickman Road, as well as HWY and North Queen Street. Box Construction Phase Out Box construction is an obsolete construction standard for overhead.kv distribution, found mainly in the downtown Toronto area as shown in Picture below. 0 Picture : Box Construction There are approximately 00 kilometres of box construction.kv circuits in the THESL distribution system. These feeders are shown in Figure below.

23 EB-0-0 Exhibit D Page of Figure : Existing Box Construction Design in THESL s Distribution System Through 0-0, THESL plans to decommission several MS stations and convert their associated kv feeders. MSs to be decommissioned by 0 are College MS, Dufferin B MS, Eglinton MS, Keele & St Clair MS, Overdale MS, Rennie Park MS, Dupont MS, Hazelwood MS, Junction MS, Millwood MS, Kingsway MS, Merton MS, Parkdale MS and Queensway MS. A total of kv box construction feeders from these stations will be converted to.kv/.kv circuits. These stations are shown below in Figure.

24 EB-0-0 Exhibit D Page of Figure : MSs and Associated kv Feeders to be Converted by 0 0 Rear Lot Phase Out Conversion of rear lot distribution plant to front lot has been ongoing since 00 and continues through to 0. Existing rear lot feeders are prioritized for conversion based primarily on age and reliability of the assets. Rear lot feeders exist primarily in the former distribution service area of Etobicoke. The existing feeders are mostly kv and are either overhead or direct-buried underground. As is the standard approach with other proposed kv rebuilds, rear lot is converted to front lot. kv system wherever feasible. This is due to the flexibility this approach provides in configuring load and the marginal reduction in maintenance costs gained by eventually decommissioning the kv station. THESL plans that rear lot areas will be addressed during 0-0. Several of the areas will only be partially converted in this time period due to their relative size. The following Figure shows Planned Rear Lot Conversion Projects.

25 EB-0-0 Exhibit D Page of Figure : Planned Rear Lot Conversion Projects THE DRIVERS OF THE OVERHEAD WORK PROGRAM Ageing Assets Poles Ageing poles with reduced strength not only impact reliability, but can also pose a serious public safety hazard. Picture and Picture below illustrate poles breaking and falling to the ground resulting in high risk to the public.

26 EB-0-0 Exhibit D Page of Picture : Poles After Breaking Picture : Poles After Breaking Based on available asset condition assessment data, shown in Exhibit D, Tab, Schedule, approximately percent of poles will reach end-of-life within the next ten years. As such, a total of approximately,000 poles or,00 poles per year will require replacement during this ten-year period. THESL is scheduled to replace only 0,0 poles during 0-0 due to pole end-of-life condition. THESL will need to accelerate pole replacements in order to avoid unmanageable backlog in future years. 0 In addition to having reduced strength, many poles are cracked or feathered at the top. Picture and Picture illustrate cracked pole conditions at the top and bottom of poles respectively. Cracks are clearly visible at the top of the pole shown in Picture. This portion of the pole holds overhead hardware such as conductors, switches, and transformers and as such supports equipment critical to the operation of distribution infrastructure.

27 EB-0-0 Exhibit D Page of Picture : Poles at End-of-Life (Top) Picture : Poles at End-of-Life (Bottom) 0 Replacement of Under-Performing Assets Under-performing assets in the overhead distribution system are found throughout THESL. Efforts to replace these assets are undertaken to improve reliability. As obsolete equipment, such as porcelain insulators and arrestors, ages it becomes more contaminated. This results in a lower resistance path across the equipment that eventually allows for a voltage discharge, which eventually leads to a semi-conductive track that worsens over time and further weakens the insulator. Furthermore, porcelain insulators are more likely to break, shatter or explode compared to polymeric types. When this happens, fragments of the insulator disperse to the ground. In some cases, this leads to pole fires. Picture shows a broken insulator. Broken insulators can cause outages. For example, the broken insulator shown in Picture resulted in an outage for, customers and a CHI of,.

28 EB-0-0 Exhibit D Page of Picture : Broken Porcelain Insulator Figure illustrates the CI contributions due to insulators and lighting arrestors. Figure : Defective Equipment CI Furthermore, the vast majority of defective insulators are the under-performing porcelain type. Figure shows that the majority of insulator related CI shown in Figure is attributable to porcelain insulators and that there is a trend of increasing failures for porcelain insulators.

29 EB-0-0 Exhibit D Page of Figure : Insulator CI 0 Between 0 and 0 about,000 insulators will be replaced while addressing FESI, WPF and overhead rebuilt in the areas of Fairbanks, Leslie, Bermondsey, Fairchild, Cavanagh, Bathurst, Finch, Richview, Runnymede and Horner station. Rehabilitation of Worst Performing Feeders ( WPFs ) During 0-0, THESL plans to rehabilitate the WPFs. Expenditures on this group of feeders are necessary because they have experienced excessive outages. In fact, almost 00 outages (approximately percent of total outages) occurred on the worst 0 feeders and these feeders are significant contributors to both overall CI and CHI. Continuing outages on these feeders are attributable in part, to ageing equipment, poor condition of equipment, and under-performing inferior asset material.

30 EB-0-0 Exhibit D Page 0 of Table : Outage cause for Worst Performing Feeders Total Outages Outage Source Total Defective Equipment Animal Contacts 0 Adverse Weather Tree Contacts Unknown 0 Lightning Adverse Environment Table illustrates the overhead-related causes of outages on the WPFs. This table shows that defective overhead equipment is a major contributor to outages on the WPFs. THESL currently plans to repair of the 0 WPFs between 0 and 0. 0 Voltage Conversion Expenditures for voltage conversion are necessary because these assets generally cannot be replaced on a like-for-like basis because kv equipment is no longer in general use. As a result, this type of assets has to be custom-made, considerably increasing costs and supply times. When kv circuits are converted to a higher voltage, related assets, such as circuit breakers and station transformers, will no longer need to be replaced. Replacing ageing kv infrastructure and converting to a higher voltage will result in a lower probability of failure. This is because existing higher voltage assets are not as old and are in better condition. The stations that are planned for voltage conversion in the next three years are supplied from Manby TS, Richview TS, Bermondsey TS, Sheppard West TS and Dupont MS, addressing percent of the kv feeders on the system.

31 EB-0-0 Exhibit D Page of 0 Feeder Automation Feeder Automation expenditures are necessary as they provide for effective reliability improvement. Figure, provided above, shows that the trunk portion of the feeder is the main contributor to poor reliability. FA leads to the reduction of the duration of trunk related outages since the self-healing switches quickly isolate the faulted area and restore power within one minute to customers elsewhere on the feeder. In 00, a feeder automation pilot project was successfully completed. This project consisted of creating an FA network of ten feeders. The pilot demonstrated noticeable improvement in reliability under an outage condition. With the expansion to a larger network of feeder automation, typically percent of the customers will be restored within one minute should there be an outage on the trunk portion of their feeder. Picture shows a Supervisory Control and Data Acquisition ( SCADA ) switch located at the trunk of a feeder. Picture : SCADA Switch and Antenna The feeder automation system utilizes S&C SCADA (SCADA-Mate) and Vista switches along with IntelliTEAM II software loaded in each switch controller both of which are shown in Pictures and. Dynamic loading conditions are communicated between the

32 EB-0-0 Exhibit D Page of switches via a peer-to-peer mesh communication network. Upon fault conditions, all switches within the affected segments would initially open to isolate the fault. Picture : Control Unit Picture : Repeater Radio The IntelliTEAM II logic would then analyze the conditions prior to the fault to determine the failed segment. It would then check the available spare capacity on alternate feeders before restoring power to healthy segments. All of this is accomplished through a sequence of automated switch operations without overloading the alternate feeders. 0 Between 0 and 0, THESL plans to focus on the expansion of the existing network of switches within the Fairbanks TS, Bathurst TS, Horner TS, Manby TS, Cavanagh TS, Malvern TS and Scarborough TS. This will allow THESL to utilize the dead open points on the periphery of the existing network. A dead open point is one which has an FA-enabled feeder on one side of the open point and a non-enabled FA feeder on the other side. This open point cannot be used in a self-healing manner to transfer load across the open point. Furthermore, expansion of the existing network also utilizes the

33 EB-0-0 Exhibit D Page of existing base of repeater radios installed from prior implementations. Since a mesh network has already been established, fewer repeater radios will be required. As an illustration, for Bathurst TS and Fairchild TS feeder selection, several criteria were taken into account. These include analysis of trunk outages and the total number of CHI affected. Table illustrates the high contribution of trunk portion of feeder CHI versus the lateral portion of CHI. Table : Trunk CHI and Total CHI Bathurst TS Feeder OH Tie Points UG Tie Points Trunk CHI # of Interruptions Total CHI Total # of interruptions M M M M,, M M M M M,, M M M0 M M M0 M M M,, M M M M0 0M M M M M0 0M 0, M M M M M0 0M 0M 0M 0 M0 M M M M M M 0M M M M M M0 M 0,0 M M M M - 0,0 M M M - 0 Fairchild TS Feeder OH Tie Points UG Tie Points Trunk CHI # of Interruptions Total CHI Total # of interruptions 0M 0M 0M 0M0 0M M M M,0, 0 0M 0M 0M 0M 0M0 M,, 0M0 0M 0M M M 0M 0M 0M, 0, 0M 0M 0M 0M 0M 0M,0, 0M 0M 0M 0M 0M,0, 0M 0M 0M 0M 0M M,, 0M 0M M M - 0 0M 0M0 M 0M - 0,0 0M 0M 0M M - 0 0M 0M 0M 0M M - 0 0, 0 Table also shows the tie-points available for each feeder. The greater the availability of tie-points on a feeder, the more effective restoration will be in the event of an outage. This is due to greater flexibility in load transfer options as well as the lower amount of load required to be transferred to each feeder. Furthermore, focus will also be in the western part of the city where obsolete MOSCAD Remote Terminal Units ( RTUs ) and DARCOM radio systems are still installed. These are no longer supported by the vendor so it is necessary to replace these end-of-life remote switches with FA schemes.

34 EB-0-0 Exhibit D Page of 0 Lack of Sufficient Tie-Points In a looped electrical power distribution system, tie-points are used to restore power to customers during power outages or planned load transfers. Having an adequate number of unique tie-points on each feeder is important to the proper operation of the system. For many feeders, having three distinct tie-points is considered the minimum requirement. Currently, there are a number of feeders in the looped distribution system that have less than three tie-points. These feeders operate properly under normal conditions. However, when a fault occurs and sections of a feeder need to be restored through other feeders, the lack of sufficient tie-points restricts the options for load transfer. Figure illustrates the number of feeders and their associated distinct tiepoints. Figure : Feeder Ties Figure shows that feeders throughout the system do not have adequate tie-points. Of these, feeders have less than two tie-points. A total of feeders without adequate tie-points will be addressed in between 0 and 0.

35 EB-0-0 Exhibit D Page of A tie-point is a critical location whereby two feeders are electrically isolated by a normally open switch. In the event of an outage, the switch can be closed in order to allow for load restoration from one feeder to another. For each unavailable tie-point during an outage on the trunk portion of a feeder, up to percent of customers (typically in excess of 0 customers) will not have their power restored efficiently. Figures 0 and illustrate the effectiveness of installing tie-points. Figure 0: Before Adding Tie-point Figure : After Adding Tie-point 0 0 These figures show the benefits of adding a new tie point and creating section D. Initially,000 customers would be required to be restored from section C in the event of an outage in section B. In this case, there is a risk of the tie-point associated with section C not being able to efficiently restore the entire load. By adding an additional tie-point, section C can be split into two sections (C and D). In this way, there is a better probability of restoring all customers via the two tie-points. Overloaded Feeders Expenditures to relieve overloaded feeders are required. As with feeders with inadequate tie points, highly loaded feeders (i.e. feeders loaded over percent of their rated capacity) do not present a problem under normal operating conditions. However, under a fault condition on the trunk portion of the feeder, an already highly loaded feeder may not be able to accept additional load without experiencing overloading. This prolongs the

36 EB-0-0 Exhibit D Page of outage to the faulted feeder until either repair is complete or lengthy switch operations on other feeders are conducted to re-route power. Figure : Feeder Loading Figure shows feeders that are presently loaded above percent. From 0 to 0, THESL will address of these feeders, which are located across the system. 0 Insufficient Tree-proof Conductor Investment in tree-proof conductors will permanently reduce operating costs for tree trimming. This will be done in many areas within the City of Toronto where mature trees overlap THESL distribution lines. Many outages are caused by tree contact with the overhead lines. When the contact is made on the trunk portion of the feeder, an outage affecting all customers on that feeder will result. An outage of this type typically affects more than,000 customers. In cases where there is a potential for tree contact on the trunk portion of the feeder, the overhead conductor will be replaced by a tree-proof conductor. THESL has identified feeders that have mature trees in close proximity to their trunks. A minimum of eight feeders will be addressed during the 0-0 period. Figure illustrates the CIs due to tree contacts.

37 EB-0-0 Exhibit D Page of Figure : Tree Contact CI 0 Undersized Primary Wire Expenditures to remove undersized wire are required because they impede efficient service restoration. During a fault condition, load is typically transferred from one feeder to another in order to restore as many customers as possible. When a fault occurs on a feeder, the tie-point feeder will be required to carry a higher load than under normal loading conditions. The ability to transfer load may be limited due to an undersized conductor present on the feeder accepting the additional load. Many segments of the overhead system have pockets of undersized conductors. These pockets are weak links preventing efficient restoration of load. Approximately percent of the feeders with undersized wires will be addressed in the three-year period of 0-0. Relocation of Assets from Salt Spray Contamination Areas Distribution assets in proximity to major highways are highly susceptible to salt spray contamination. Insulators break down from contamination. For example, polymer insulators will split or burn (called tracking) when they fail. Glass and porcelain

38 EB-0-0 Exhibit D Page of insulators, however, will break, shatter or explode when they fail potentially producing dangerous shards. At these areas, the overhead distribution usually dips down (via cable riser) to an underground system in order to traverse the major highways. As such, many critical components such as switches and terminations are present. Should an outage occur on these components, typically a total of,000 customers on the feeder will experience an outage. A total of locations were found with assets in close proximity to highways. Approximately percent of these areas will be addressed in the period of Insufficient Fault Circuit Indicators Fault Circuit Indicators reduce the time required to locate the causes of faults, which is usually a time-consuming and costly task. They provide a reliable mean of fault location and isolation to improve the efficiency of service restoration. The presence of fault circuit indicators can also lead to a better understanding of the root cause of momentary outages. When a momentary outage occurs, field crews are not able to determine its root cause as the outage s causal factor is not readily apparent. With the installation of the fault circuit indicators, the crews will know in what section of the feeder the momentary outage occurred, resolve the problem and restore the power to THESL s customers faster. A total of,000 Fault Circuit Indicators will be installed in feeders around Warden TS, Bermondsey TS, Richview TS, Leslie II TS, Runnymede TS, Finch TS, Marlvern TS and Scarborough West TS from 0-0. Insufficient Lateral Ties Low cost solutions can be applied to provide a lateral tie-point where large numbers of overhead customers are supplied by equipment in a radial configuration. Figures and illustrate the before and after scenarios of installing appropriate lateral ties. Figure also shows that any outage on the lateral portion of the outage will affect at least 0

39 EB-0-0 Exhibit D Page of customers. Under adverse weather conditions, the outage duration for these customers could be in excess of two hours. Figure shows that reconfiguration to provide lateral ties mitigates the outage exposure. In this case only 00 customers are affected. Between 0 and 0, THESL plans to install. percent of the total number lateral ties required on the system. Lateral with 0 customers Before Lateral Tie installation Figure : Before Lateral Tie Installation

40 EB-0-0 Exhibit D Page 0 of Lateral with 00 customers After Lateral Tie installation Figure : After Lateral Tie Installation Lateral Fusing THESL plans to re-configure and install normally-closed fuses on both halves of a lateral portion of a feeder as opposed to supplying the customers from only one end. This will reduce the CIs by approximately 0 percent should an outage occur. In the period of 0-0, THESL will install percent of the total lateral fusing required. 0 Conversion of Trunk Portion of Feeders to Laterals In some cases, outages occur on a portion of the feeder lateral that can be fused, but is presently not fused. In this case, more customers than necessary will experience the outage. With a proper fuse installed, typically less than 00 customers will be affected by an outage on the lateral. Without the fuse, all customers on the feeder (more than,000 customers) will be affected by the outage. Approximately 0 percent of the conversion of trunk portions of feeders to laterals will be address in the period of 0-0. Figures and below illustrate the scenario before the conversion of the trunk portion of feeders and after conversion to laterals.

41 EB-0-0 Exhibit D Page of Before Conversion of Trunk Portion CI=000+ Figure : Before Conversion After Conversion of Trunk Portion to Laterals CI=00 Figure : After Conversion

42 EB-0-0 Exhibit D Page of Animal Guard Protection Animal contacts accounted for nine percent of overall outages in 00. THESL plans to install animal guard protection on all transformers to improve reliability. Without this protection, animal contacts usually results in outages, death of the animals and damage to the equipment. Animal guards provide great benefit with respect to costs. From 0 to 0, 0 percent of the required animal guards will be installed. Pictures 0 and illustrate how animal guards work. 0 Picture 0: Transformer without Animal Guard Picture : Animal Guard Standard Overloaded Pole-Mounted Transformers Overloaded pole-mounted transformers are usually the result of growth in customer load. The past decades have seen a large increase in the use of air conditioners, computers and other household appliances. During hot summer days, heavily-loaded transformers can overheat causing outages. Under some conditions, this could result in rupture or fire.

43 EB-0-0 Exhibit D Page of From 0 to 0, 0 percent of the overloaded pole-mounted transformer will be addressed. 0 Highway Overhead Crossings At a number of locations overhead distribution lines cross over major highways. These crossings create an increased concern for public safety should energized lines break and fall onto the road. For example, in one instance an overhead conductor crossing the Gardiner Expressway near Royal York Road failed and fell onto the road. THESL is planning to re-route these overhead highway crossings to minimize the potential for such incidents. This is typically done by undergrounding a portion of the circuit. A total of overhead highway crossings have been identified with approximately 0 percent of these scheduled to be addressed in Box Construction Phase-Out Converting kv box construction to existing.kv overhead or underground construction standards will significantly improve workplace safety for crews. This conversion will inherently eliminate the associated hazards of multiple circuits going through a typical box pole, as well as eliminate the hazard of working in the vicinity of shielded primary cable (found only on kv feeders). In addition, a majority of the box construction feeder assets are old and past their useful life.

44 EB-0-0 Exhibit D Page of Table : Assets Past Useful Life in MSs to be Decommissioned MS Station Number Total number of Total number of Number of nonlinear Number of of non-linear linear assets assets linear assets feeders assets past past useful life past useful life past useful life useful life (m) per feeder per feeder(m) Rennie Park Merton Runnymede Millwood Queensway Dupont Junction Overdale,.. Hazelwood 0.. Eglinton Kingsway Keele & St Clair College Dufferin Parkdale NOTE: Linear assets represent cable past useful life. Non-linear assets represent all other equipment on feeders, and are represented in counts.

45 EB-0-0 Exhibit D Page of There are currently a high number of assets past useful life on the feeders in the MS stations, as outlined in Table. Choosing to first decommission the MSs identified in Figure will result in maintenance cost savings. Eliminating maintenance in these stations will reduce THESL s inventory and maintenance costs for obsolete kv equipment, and result in less station maintenance overall. 0 Figure : Feeders to be decommissioned Decommissioning of these stations will also allow THESL to use the MS land for other projects. Of particular interest is part of the downtown contingency plan to use decommissioned MS land as switching stations between various TSs in the event of a complete TS outage. MSs identified as possible switching points are Hazelwood MS, and Dufferin MS, and those two are to be decommissioned by 0. Some MSs have equipment in need of maintenance and replacement in the near future. One such station is Hazelwood MS. Rather than maintain and/or replace obsolete

46 EB-0-0 Exhibit D Page of 0 equipment in this station by 0, all associated feeders will be converted to.kv and Hazelwood MS will be decommissioned. In addition, historical outage data from shows that average outage duration on.kv feeders is. minutes and on kv feeders is. minutes, demonstrating that outages are typically resolved more quickly on.kv feeders than kv feeders. Rear Lot Phase-Out Outages related to rear lot feeders on average tend to last approximately twice as long as outages related to front lot feeders. This is due to difficulty in accessing and repairing the rear lot feeder equipment as well as the presence of old and non-standard assets and feeder configurations. The lack of access also presents safety hazards to crews during emergency outage situations. 0 Areas for rear lot conversion between 0 and 0 were identified based on reliability and age concerns. Rear lot projects are also driven by the short-term need to convert kv feeders supplied by stations that are reaching the end of their serviceable lives (e.g., conversions near Lawrence and Leslie identified for 0 are driven by the need to decommission Lesmill MS in the short-term). Converting the rear lot areas will improve reliability, specifically lessening outage duration, improve crew safety and reduce inventory and maintenance costs related to the maintenance of obsolete kv distribution equipment and stations. The rear lot areas targeted for conversion in 0-0 due to decreased reliability have each experienced one to three outages per year for the last nine years, with typical outage durations lasting between four to eight hours. Nine of the feeders being addressed in these rear lot areas have experienced at least one outage over hours in duration during the last five years.

47 EB-0-0 Exhibit D Page of THE CONSEQUENCES OF DEFERRING THE OVERHEAD WORK PROGRAM Figure shows the annual risk cost for major overhead asset classes from 0 to 0. Risk Cost Annual Risk Cost $00,000,000 $0,000,000 $0,000,000 $0,000,000 $0,000,000 $0,000,000 $0,000,000 $0,000,000 $0,000,000 $0,000,000 $ Year OH Switches OH Tx Poles Figure : Annual Risk Cost from 0 to0 0 This risk cost is derived from the Feeder Investment Model ( FIM ) that THESL has developed for capital project identification and justification. The economic model takes into account total life cycle cost of each asset including capital installation, operation & maintenance and decommissioning costs. In addition, the model also takes into account failure cost of the asset if it is left to run to fail. Failure cost is based on the condition and age of the asset, the probability of failure based on the risk curve established for each asset class, and social impact and economic loss from each asset failure. It is composed of various direct and indirect cost attributes associated with in-service asset failures including the costs of customer interruptions, the costs of emergency repairs and replacement, and the costs associated with potential catastrophic failures of assets.

48 EB-0-0 Exhibit D Page of Given that a large percentage of overhead assets have passed or are approaching the end of their useful service lives, the risk cost for the overhead system is very high. Delay of planned overhead capital work serves only to increase the risk cost in subsequent years. The result of such postponements is higher operations and maintenance costs, increased capital replacement cost and greater customer outage cost and inconvenience. In addition, further postponement of capital work will call into question the availability of sufficient resources in future years to complete needed work. Figure 0: Duration of Outages Caused by Overhead Assets 0 Ageing Assets Poles Deferral of replacement will lead to continued ageing and deterioration of equipment ultimately leading to an increasing probability of failure. As noted earlier in Figure, CI contributions related to overhead system failures have increased by percent since 00. This is illustrated in Figure 0, which shows that CHI has increased by almost percent between 00 and 00. This increase is an indication that restorations of

49 EB-0-0 Exhibit D Page of outages caused by aged end-of-life assets are becoming more difficult and requiring more time to complete. This is due to reactive replacement of assets that are part of inferior older designs and the additional time required to operate older distribution assets. A reduction of expenditures related to end-of-life equipment replacement between 0 and 0 will certainly result in worsening overhead reliability statistics. Customers will continue to experience an increase in disruptive forced outages. Further deferral of asset replacement will also result in a rapidly increasing backlog of assets requiring attention in the future. 0 The quantified risk of not proactively undertaking pole replacement projects and allowing the poles to fail is approximately $0 million between 0 and 0. This figure includes the costs of customer interruptions, the costs of emergency repairs and replacements, and the indirect costs associated with potential catastrophic failures of assets. Figure shows the risk cost if there is no investment for pole replacement. Figure : Risk Cost Replacement of under-performing assets Consequences of deferral will lead to increasingly poor reliability due to under-

50 EB-0-0 Exhibit D Page 0 of performing assets. For example, industry tests have shown that polymeric type assets have better performance than porcelain type. As these under-performing assets continue to deteriorate, there will be an increased probability of outages. Figure below illustrates the increasing quantity of outages related to insulators. Figure : Insulators Number of Outages 0 Rehabilitation of Worst Performing Feeders Ageing and deteriorating equipment is often the reason that certain feeders have experienced a high number of sustained outages year after year. Currently, more than 0 feeders have sustained seven outages or more during the past year. Depending on outage location, more than,000 customers can be affected. The feeders listed in Table require long-term solutions and significant capital investment in order to reduce the number of outages. Deferring the replacement of the feeders identified in the WPF projects will lead to continued poor, or even worsening,

51 EB-0-0 Exhibit D Page of performance. Figure illustrates the number of outages from 00-0 for the WPF. WPF Outages Figure : WPF 0-0 Outages Voltage Conversion Consequences of deferral would be high station maintenance costs since circuit breakers and station transformers will eventually need to be replaced at the station due to deteriorating asset conditions. The electrical equipment industry has moved away from

52 EB-0-0 Exhibit D Page of.kv equipment and as a result, spare parts for these assets are more expensive and more difficult to obtain. Thus the age of this equipment, its condition and the difficulty of repairing together mean that it will continue to negatively impact both CI and CHI until it is replaced as part of voltage conversion. 0 Feeder Automation Deferral of Feeder Automation (FA) expenditures will result in many peripheral open points in the areas where FA has already been implemented remaining as dead open point nodes. These nodes will not allow the feeders within the current FA scheme to effectively and automatically transfer load. On average, the presence of a dead open point on a feeder will lead to a percent reduction in potential reliability savings. FA is one of the most effective ways to reduce CI/CHI on the overhead system and its widespread adoption should help to mitigate deterioration of the overhead system. As a result, deferral of investment will decrease reliability in the future years. 0 As noted in Figure trunk-related outages are a major contributor to poor reliability. FA is a very effective means of improving reliability performance since the self-healing FA switches efficiently restore customers affected by trunk outages. The 0-0 capital plans for FA will complete the work undertaken since 00. In addition, the MOSCAD system in the western part of the city currently presents a high risk and requires replacement with FA. Not only are the existing automation switches at end-of-life, but the master radio system also is no longer supported by the manufacturer. Failure of the MOSCAD master radio system will lead to more than 0 switch locations becoming incapable of remote operation. Lack of Sufficient Tie-Points Additional tie-points are required to effectively implement FA and reduce the number of

53 EB-0-0 Exhibit D Page of 0 customers impacted by outages on feeders with an inadequate number of tie points. FA improves reliability by significantly reducing the restoration time for the majority of segments of the trunk portion of the feeder. In order to reduce restoration time, sufficient tie points must exist to support the required switching. Deferring investment in additional tie points would increase both the duration of outages and the number of customers likely to be impacted by certain outages. Overloaded Feeders There are presently feeders that have been identified as overloaded within the THESL distribution system. Deferring the work to relieve the feeders will result in longer than normal restoration times in the event of an outage. Insufficient Tree-proof Conductor The following Picture illustrates the close proximity of trees to critical overhead assets. Picture : Trees in Proximity to Distribution Equipment

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS EB-00-0 Exhibit D Schedule Page of EMERGING REQUIREMENTS 0 EQUIPMENT STANDARDIZATION THESL plans, designs and constructs distribution system assets in accordance with approved standards. The standards

More information

GRID SYSTEM INVESTMENTS

GRID SYSTEM INVESTMENTS EB-0-0 Exhibit D Schedule Page of GRID SYSTEM INVESTMENTS 0 0 SUSTAINING PORTFOLIO UNDERGROUND SYSTEM The underground distribution system consists of assets connected to the.kv,.kv and.kv primary voltage

More information

PROJECTS $500K AND OVER FOR 2014

PROJECTS $500K AND OVER FOR 2014 Page of PROJECTS $00K AND OVER FOR 0 STANDARDIZATION PORTFOLIO Table : Standardization Projects Estimate Estimated Cost Project Title Number ($ Millions) Grounding Compliance Program. Porcelain Insulator

More information

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO EB-0-0 Tab Schedule Page of CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO THESL s DOWNTOWN CONTINGENCY WORK PROGRAM The purpose of this portfolio is to provide distribution load transfer capability from

More information

PROJECTS $500K AND OVER FOR 2012

PROJECTS $500K AND OVER FOR 2012 EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions)

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This

More information

2016 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT

2016 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT 2016 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT Contents Overview... 3 1.0 Electric System Reliability... 4 1.1 Annual Reliability Data with Utility Comparisons... 4

More information

Insulator Replacements

Insulator Replacements A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Insulator Replacements Electrical Mechanical. Civil Protection & Control Transmission & Distribution Telecontrol System Planning HYDRO THE POWER

More information

Pike County Light & Power Company Summer Reliability Outlook

Pike County Light & Power Company Summer Reliability Outlook Pike County Light & Power Company 2013 Summer Reliability Outlook June 28, 2013 System Overview Pike County Light & Power Company ( PCL&P or the Company ) is an electric distribution company ( EDC ) which

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD May 1, 2017 Table of Contents 1.0 Introduction...3 2.0 Summary...3 3.0 Purpose...3 4.0 Definitions...4 5.0 Analysis...5

More information

Technology Roadmap for zzzzzzzzz Grid Automation

Technology Roadmap for zzzzzzzzz Grid Automation IEEE Nashville Chapter Technology Roadmap for zzzzzzzzz Grid Automation November 2010 2010 by R. W. Beck, An SAIC Company. All Rights Reserved. Projected Expenditures 2010-2030 Substation Transmission

More information

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD June 1, 2018 Table of Contents 1.0 Introduction...3 2.0 Summary...3 3.0 Purpose...3 4.0 Definitions...4 5.0 Analysis...5

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical.1_ UFSS#p A:_. DAVID/ IC, L re Mechanical Civil Protection & Control an LAND& 4^ Transmission & Distribution Telecontrol System Planning

More information

When power interruptions happen.

When power interruptions happen. When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage

More information

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT 2016 LIBERTY UTILITIES (CALPECO ELECTRIC) LLC (U 933 E) Prepared for California Public Utilities Commission July 15, 2017 EXECUTIVE SUMMARY The Electric System

More information

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Presented By: Bob Uluski Electric Power Research Institute. July, 2011 SMART DISTRIBUTION APPLICATIONS &THEIR INTEGRATION IN A SMART GRID ENVIRONMENT Presented By: Bob Uluski Electric Power Research Institute July, 2011 Key Smart Distribution Applications What are the major

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems SECTION 9: ELECTRICAL POWER DISTRIBUTION ESE 470 Energy Distribution Systems 2 Introduction The Electrical Grid 3 Three main components to the electrical grid Generation ESE 450 Transmission Transmission

More information

An Inside Look at Electric Reliability 2016 Electric Reliability Report

An Inside Look at Electric Reliability 2016 Electric Reliability Report An Inside Look at Electric Reliability 2016 Electric Reliability Report Stockton, Bakersfield, California California November November 6, 2017 3, 2016 Welcome 2 David Meier Senior Manager, Stockton Division

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

Creating a Smarter Energy Grid for Our Customers

Creating a Smarter Energy Grid for Our Customers INVESTING IN MICHIGAN S FUTURE INTRO PAGE 1 Creating a Smarter Energy Grid for Our Customers Investing in Michigan s Future Contents Preparing the Grid 3 Our Challenges The State of Our Electric Infrastructure

More information

Electrical Safety. Introduction

Electrical Safety. Introduction Electrical Safety Introduction Electrical hazards 300 electrocutions every year in the U.S. Leading cause is insufficient training ALL were preventable What is Electricity? How Electricity Works Created

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

Out of Sight Out of Mind Revisited. EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting

Out of Sight Out of Mind Revisited. EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting Out of Sight Out of Mind Revisited EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting 1 Presentation Outline Customer Expectations Storms and Outages:

More information

Grounding Of Standby & Emergency Power Systems

Grounding Of Standby & Emergency Power Systems July / August 2007 ELECTRICAL LINE 53 Grounding Of Standby & Emergency Power Systems By Andrew Cochran Power continuity is essential in many industrial and commercial installations where a trip out due

More information

Fuel Reliability: Achieving Zero Failures and Minimizing Operational Impacts Rob Schneider, Senior Engineer/Technologist, Global Nuclear Fuel

Fuel Reliability: Achieving Zero Failures and Minimizing Operational Impacts Rob Schneider, Senior Engineer/Technologist, Global Nuclear Fuel Fuel Reliability: Achieving Zero Failures and Minimizing Operational Impacts Rob Schneider, Senior Engineer/Technologist, Global Nuclear Fuel In March 2013, Global Nuclear Fuel (GNF) met the INPO challenge

More information

Utility Distribution Planning 101

Utility Distribution Planning 101 Utility Distribution Planning 101 Michael Coddington, National Renewable Energy Laboratory Webinar for National Association of State Utility Consumer Advocates June 5, 2018 1 Webinar Overview Overview

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

ABB FACTS Customer Service. FACTS Care Upgrades

ABB FACTS Customer Service. FACTS Care Upgrades ABB FACTS Customer Service FACTS Care Upgrades 2 FACTS Care Upgrades ABB FACTS FACTS Care ABB is a pioneer and the recognized market leader in the FACTS field. Developments move quickly, technical know-how

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0 ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding

More information

A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. System Planning. Overhaul Diesel Engines.

A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. System Planning. Overhaul Diesel Engines. A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES Electrical Mechanical ( Protection Civil & Control & Distribution System Planning Overhaul Diesel Engines Various Locations July 2012 newfoundland

More information

Florida Public Service Commission 2011 Hurricane Season Preparation Briefing

Florida Public Service Commission 2011 Hurricane Season Preparation Briefing Florida Public Service Commission 2011 Hurricane Season Preparation Briefing OUC The Reliable One May 4, 2011 Byron Knibbs Vice President, Sustainable Services (407) 434-2194 bknibbs@ouc.com 1 Florida

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Non-network solutions

Non-network solutions Non-network solutions EDPR Customer Forum 24 April 2018 Agenda 1. What are non-network solutions and why are we interested? 2. Summary of solutions have we implemented to date 3. Where the key opportunities

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

Welcome. Liberty Utilities Reliability Reporting Workshop. October 3 & 6, 2017

Welcome. Liberty Utilities Reliability Reporting Workshop. October 3 & 6, 2017 Welcome Liberty Utilities Reliability Reporting Workshop October 3 & 6, 2017 1 Agenda Purpose of Workshops System Overview Key Utility Initiatives Reliability Performance Plans for Reliability Improvements

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

The FREEDM System: components, main functions, system control

The FREEDM System: components, main functions, system control Short course on the FREEDM System Session L3 The FREEDM System: components, main functions, system control Dr. I. Husain, North Carolina State University Dr. G. T. Heydt, Arizona State University October,

More information

Summer Reliability Assessment Report Electric Distribution Companies Perspective

Summer Reliability Assessment Report Electric Distribution Companies Perspective Energy Association of Pennsylvania Summer Reliability Assessment Report Electric Distribution Companies Perspective to the Pennsylvania Public Utility Commission June 9, 2011 Harrisburg, PA Terrance J.

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation Integrated System Models Graph Trace Analysis Distributed Engineering Workstation Robert Broadwater dew@edd-us.com 1 Model Based Intelligence 2 Integrated System Models Merge many existing, models together,

More information

THE CURVE FOR DOUBLE PROTECTION TRANSFORMER & SYSTEM PROTECTION WITH CHANCE SLOFAST FUSE LINKS

THE CURVE FOR DOUBLE PROTECTION TRANSFORMER & SYSTEM PROTECTION WITH CHANCE SLOFAST FUSE LINKS THE CURVE FOR DOUBLE PROTECTION TRANSFORMER & SYSTEM PROTECTION WITH CHANCE SLOFAST FUSE LINKS CHANCE SLOFAST FUSE LINKS ARE DESIGNED FOR BOTH TRANSFORMER AND SYSTEM PROTECTION. For many years in the electric

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

SUMMARY OF THE IMPACT ASSESSMENT

SUMMARY OF THE IMPACT ASSESSMENT COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 13.11.2008 SEC(2008) 2861 COMMISSION STAFF WORKING DOCUMT Accompanying document to the Proposal for a DIRECTIVE OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

2014 Efficiency of Automated Collection and Performance of Compressed Natural Gas Vehicles CIF Project No

2014 Efficiency of Automated Collection and Performance of Compressed Natural Gas Vehicles CIF Project No 2014 Efficiency of Automated Collection and Performance of Compressed Natural Gas Vehicles CIF Project No. 548.11 Submitted by: City of Toronto Submitted to: Waste Diversion Ontario, Continuous Improvement

More information

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION SMART DIGITAL GRIDS For many years the European Union has been committed to the reduction of carbon dioxide emissions and the increase of the

More information

Microgrid solutions Delivering resilient power anywhere at any time

Microgrid solutions Delivering resilient power anywhere at any time Microgrid solutions Delivering resilient power anywhere at any time 2 3 Innovative and flexible solutions for today s energy challenges The global energy and grid transformation is creating multiple challenges

More information

1) Introduction. a) Name of city/utility Utilities Commission, City of New Smyrna Beach

1) Introduction. a) Name of city/utility Utilities Commission, City of New Smyrna Beach Utilities Commission, City of New Smyrna Beach Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2016 1) Introduction a) Name of city/utility

More information

Safety and Operations Committee. Action Item III-A. December 13, 2018

Safety and Operations Committee. Action Item III-A. December 13, 2018 Safety and Operations Committee Action Item III-A December 13, 2018 Preventive Maintenance Update Page 3 of 46 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

Issues Facing the Panel

Issues Facing the Panel Issues Facing the Panel Choice of technology for Sheppard Avenue (not for every corridor every where for all time!): subway vs. LRT Budget implications I would argue that procurement, construction management

More information

Downtown Lee s Summit Parking Study

Downtown Lee s Summit Parking Study Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E8: Battery Condition Assessment E8.1 GENERAL Plant or station batteries are key components in hydroelectric powerplants and are appropriate for

More information

Transmission & Distribution Glossary of Electrical Terms

Transmission & Distribution Glossary of Electrical Terms Transmission & Distribution Glossary of Electrical s Breaker Panel Bushing Circuit Circuit Breaker Conductor Conduit Consumption Current Distribution Electricity (Static vs. Current) Electron Feeder The

More information

Smart Grid 2.0: Moving Beyond Smart Meters

Smart Grid 2.0: Moving Beyond Smart Meters Smart Grid 2.0: Moving Beyond Smart Meters Clean Energy Speaker Series State of the Smart Grid February 23, 2011 Prof. Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent

More information

Predicted availability of safety features on registered vehicles a 2015 update

Predicted availability of safety features on registered vehicles a 2015 update Highway Loss Data Institute Bulletin Vol. 32, No. 16 : September 2015 Predicted availability of safety features on registered vehicles a 2015 update Prior Highway Loss Data Institute (HLDI) studies have

More information

Fuses still the best form of overload protection

Fuses still the best form of overload protection Fuses still the best form of overload protection 2001 George Moraitis (Fuseco Pty. Ltd.) Often when I visit people to talk about circuit protection I hear the comments fuses are a thing of the past and

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM Hartford Rail Alternatives Analysis www.nhhsrail.com What Is This Study About? The Connecticut Department of Transportation (CTDOT) conducted an Alternatives

More information

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants

More information

Smart Grid Automation and Centralized FISR

Smart Grid Automation and Centralized FISR Smart Grid Automation and Centralized FISR March 21, 2016 Mike Colby Senior Engineer Distribution Control Center Smart Grid Automation and Centralized FISR Remote Controlled Devices & Communication Distribution

More information

Schedule Based on the City of Los Angeles, the District should be formed by April 2016 to allow the design and construction to be complete by 2019.

Schedule Based on the City of Los Angeles, the District should be formed by April 2016 to allow the design and construction to be complete by 2019. EXECUTIVE SUMMARY PURPOSE To report the findings of the Feasibility Study for an Underground Utility District along Segment C of the proposed Park to Playa Trail. BACKGROUND The City of Los Angeles Department

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

The Capital Grid Project:

The Capital Grid Project: The Capital Grid Project: Building Tomorrow s Energy Grid Today Lamond- Riggs Citizens Association October 2, 2017 Agenda Welcome How Safe, Clean, and Affordable Energy is Delivered Our Current System

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical vo1e.5s 0j 44, AMY., CK NI r. SIGNATURE Mechanical Civil Protection & Control t^ /DATE 1 o Transmission & Distribution AND Telecontrol

More information

Presentation A Blue Slides 1-5.

Presentation A Blue Slides 1-5. Presentation A Blue Slides 1-5. 1 Presentation A Blue Slides 1-5. 2 Presentation A Blue Slides 1-5. 3 Presentation A Blue Slides 1-5. 4 Presentation A Blue Slides 1-5. 5 Transit Service right. service

More information

Executive Summary. DC Fast Charging. Opportunities for Vehicle Electrification in the Denver Metro area and Across Colorado

Executive Summary. DC Fast Charging. Opportunities for Vehicle Electrification in the Denver Metro area and Across Colorado Opportunities for Vehicle Electrification in the Denver Metro area and Across Colorado Overcoming Charging Challenges to Maximize Air Quality Benefits The City and County of Denver has set aggressive goals

More information

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Fitchburg Gas and Electric Light Company d/b/a Unitil ( Unitil or the Company ) indicated in the 2016-2018 Energy Efficiency

More information

Single-Phase Underground Operating

Single-Phase Underground Operating Single-Phase Underground Operating S T U D E N T M A N U A L March 31, 2005 2 STUDENT TRAINING MANUAL Prerequisites: Introduction to Underground Systems module Objectives: Given an underground distribution

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg Experience on Realizing Smart Grids Bazmi Husain 2010-10-12 IEEE PES conference, Gothenburg IEEE PES Conference, Gothenburg, 2010-10-12. Slide 1 On the way to the smarter grid A quietly astounding evolution

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

Transitioning to Networked Microgrids: Leveraging Existing Capacity and Technologies

Transitioning to Networked Microgrids: Leveraging Existing Capacity and Technologies Transitioning to Networked Microgrids: Leveraging Existing Capacity and Technologies Chee Wooi Ten Department of Electrical and Computer Engineering, Michigan Technological University 10

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

GE Energy Management. GE s electrification and automation business

GE Energy Management. GE s electrification and automation business GE Energy Management GE s electrification and automation business MODERNIZING THE GRID FROM THE POWER PLANT TO THE POWER CONSUMER Who We Are Digital Energy, a division of GE Energy Management, is a global

More information

The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including:

The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including: Public Report To: From: Report Number: Community Services Committee Ron Diskey, Commissioner, Community Services Department CS-17-18 Date of Report: March 24, 2017 Date of Meeting: March 30, 2017 Subject:

More information

A NEW FUSE-SAVING PHILOSOPHY

A NEW FUSE-SAVING PHILOSOPHY A NEW FUSE-SAVING PHILOSOPHY Presented at DistribuTECH 2008 January 22-24, 2008 Tampa, Florida Christopher McCarthy, Ray O Leary, and Doug Staszesky S&C Electric Company Abstract Utilities generally apply

More information

SENTINEL BATTERY MONITORING

SENTINEL BATTERY MONITORING Protecting your power supply SENTINEL BATTERY MONITORING Helios Power Solutions If you re operating mission critical systems and relying on the protection of a UPS and battery bank, then it has to make

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN NRECA Cooperative Research Network Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN Electric Cooperatives... 864 distribution, 66 G&Ts in 47 states 5% of power supply 43% of distribution

More information

3.0 Radial Distribution Systems

3.0 Radial Distribution Systems 3.0 Radial Distribution Systems Radial distribution systems (RDS) are the most common design used by electric utilities, and are the least expensive to plan, construct, and maintain. They generally consist

More information

Eero Mertano, October 2012 Grid Automation Drivers, Benefits and Solutions

Eero Mertano, October 2012 Grid Automation Drivers, Benefits and Solutions Eero Mertano, October 2012 Grid Automation Drivers, Benefits and Solutions Grid Automation Content of the presentation Key drivers and benefits Communication Business case overview ABB offering ABB Group

More information

AEP Ohio Distribution Reliability and Technology Programs

AEP Ohio Distribution Reliability and Technology Programs AEP Ohio Distribution Reliability and Technology Programs Overview of Technologies and Reliability Plans gridsmart Phase II Case No. 13-1939-EL-RDR Advanced Metering Infrastructure (AMI) Distribution Automation

More information

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below:

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below: 3.5 TRAFFIC AND CIRCULATION 3.5.1 Existing Conditions 3.5.1.1 Street Network DRAFT ENVIRONMENTAL IMPACT REPORT The major roadways in the study area are State Route 166 and State Route 33, which are shown

More information

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks by Georges Barbarin Executive summary Aging electrical switchgear infrastructure is a threat to the reliability of power

More information

Solar PV and Storage Overview

Solar PV and Storage Overview Solar PV and Storage Overview Sherry Stout, Engineer National Renewable Energy Laboratory (NREL) National Adaptation Forum Pre-Conference Workshop on Solar +Storage May 8, 2017 U.S. Solar Resource for

More information

Using Active Customer Participation in Managing Distribution Systems

Using Active Customer Participation in Managing Distribution Systems Using Active Customer Participation in Managing Distribution Systems Visvakumar Aravinthan Assistant Professor Wichita State University PSERC Webinar December 11, 2012 Outline Introduction to distribution

More information

NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723

NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723 NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723 Phone: 907-852-0489 Fax: 907-852-0251 Charlie Sakeagak, Director ATQASUK TRANSMISSION LINE PROJECT INTRODUCTION The continuing

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

Transmission Switching

Transmission Switching General Application Southern States supplies a wide offering of Transmission Switching solutions in response to an increasing need for improved system reliability and reduced installation times. This range

More information

GE Critical Power. The Retrofit Case for Upgrading Legacy Power Systems at Telecom Central Offices

GE Critical Power. The Retrofit Case for Upgrading Legacy Power Systems at Telecom Central Offices GE Critical Power The Retrofit Case for Upgrading Legacy Power Systems at Telecom Central Offices Introduction If you were managing an e-commerce, banking or any other mission critical information technology

More information