1 NTPC RENEWABLE ENERGY PROJECTS SUCCESS, CHALLENGES AND PERSERVERANCE September 15-17, 2015 Remote Microgrid Conference Yellowknife, NT Geraldine Byrne, Acting Manager, Energy Service, NTPC Ian Flood, Project Manager, Engineering, NTPC ntpc.com 1
2 NTPC Electrical Energy hydro: 264 GWH diesel/gas: 85 GWh ntpc.com 2
3 NTPC 2013/14 Power Generation Hydro 75% Diesel 22% Natural Gas <1% Purchased 3%* Solar <1% ntpc.com 3
4 NTPC 2014/15 Power Generation Hydro 61% Diesel 34% Natural Gas 3% Purchased 3%* Solar <1% ntpc.com 4
5 NTPC 2015/16 Q1 Power Generation Hydro 54% Diesel 40% Natural Gas 4% Purchased Power 3% Solar <1% ntpc.com 5
6 Energy Supply Large Wind Wind Energy Feasibility (GNWT) Inuvik and outside Yellowknife (Snare System) Inuvik: Storm Hills & Inuvik High Point Monitoring at Snare and Inuvik Potentially 7-10MW Expression of Interest ntpc.com 6
7 Solar Photovoltaic (PV) Power How are we doing? Existing Solar PV Installations Sachs Harbour- 4.3kW Inuvik- 5kW; 7kW; 2kW; 3.5kW; 10 kw;10kw Paulatuk- 5kW; 1.7kW Fort Good Hope- 5kW Norman Wells- 2.9kW Fort Simpson kW; 5kW; 5kW Nahanni Butte- 4.8kW Jean Marie River- 1.3kW Gameti- 5kW Wekweeti- 4.2kW Whati- 5kW Behchoko- 4.8kW; 5kW Yellowknife- 2kW; 5kW; 5kW; 1.8kW; 1.3kW; 33.5kW Hay River- 1kW; 1.7kW Fort Smith- 0.5kW kwh/kw Total: kw (2103) Total: NOW > 545kW
8 Renewable Energy Initiatives Net Billing 2010 / Net Metering 2013 Success: NTPC 55kW of installed solar capacity (NUL 40kW) Customer: Positive return banking credit at 1:1 Utility: Capacity building Challenge /Perseverance: Slow uptake / Administration IPP Lutsel K e Dene First Nation Success: PPA flexible option to meet community needs; Solar Energy Strategy Challenge /Perseverance: Policy ntpc.com 8
9 104kW Solar PV Fort Simpson Success: (2012) First Utility-Scale Low Penetration (solar system production 12% average community load) Saves 27,900 L diesel fuel or 76 tonnes GHG / Yr. Made possible through GNWT funding No vandalism Challenge: Solar production is less that 2% annual consumption 2.2 million L / Yr. in diesel fuel required to meet load ntpc.com 9
10 Colville Lake Community Located: Sahtu Region 745 km by air NW of Yellowknife Population: 147 Average Load: 50 kw Peak Load: 150 kw Challenge: Remote, economies of scale, during summer months air access only; one of the highest cost communities to serve ntpc.com 10
11 Challenge Why New Power Plant? Oldest NTPC plant 24 years Settling issues Reliable, stable power challenging to provide Load size Changing load characteristics No longer meeting (Required Firm Capacity) RFC criteria ntpc.com 11
12 Success: Meeting some needs of the community: Relocate diesel plant Reduced noise /odour in community/ reduce GHG s Employment during construction and decommissioning of old plant and relocation of fuel tanks ntpc.com 12
13 136.5kW Solar PV Colville Lake Solar / Diesel Production Modelling dec nov oct Solar sep aug jul Diesel jun may apr mar feb jan 0% 20% 40% 60% 80% 100% ntpc.com 13
14 Demonstration Project Challenge: Permit Application? What is a demonstration project? Perseverance: Projected 1% rate increase to thermal region. (. 6% power plant;. 4% Solar and BESS) ntpc.com 14
15 136.5kW Solar PV Colville Lake Phase I Solar 54kW (October 2014) Phase II Solar 82.5kW (June 2015) 112MWh expected solar generation Success: No shipment damage to solar panels On schedule on budget Capacity building / relationship building Cost/ kw installed solar reduced $12.20/W from Fort Simpson (Phase I) to Colville Lake (Phase II) $6.34/W 31,600 L diesel fuel or 86 tonnes GHG / year Average diesel consumption is 160,000L ntpc.com 15
16 Challenges Edmonton plant build duration: Deteriorating winter road conditions Switch gear build wrong parts Engine testing before dispatch ntpc.com 0
17 Challenges Short construction season: Early June before work starts on solar phase II Predetermined location rather than choose a site Load bearing survey of whole runway - exact location unspecified ntpc.com 1
18 Challenges Schedule on site: Shipping damage assessed Further engine testing On site availability of SAFT & ABB field engineers ntpc.com 2
19 Challenges Meeting the budget: Demonstration/pilot project Extras not initially envisioned NTPC Labour costs 570 Transporation & accommodation 244 Consultants 224 Contractors 2,648 Diesel engines 196 Accessory electrical equipment 436 Battery bank 984 Solar panels 934 Federal funding -150 Territoral funding -1,145 Overhead (22%) 1,311 Sub-total 6,252 IDC (5.68%) 353 Total 6,605 ntpc.com 3
20 PERSERVERANCE: Sourcing a Battery Supplier: First winning proponent declared bankruptcy RFP process repeated Engine testing: Usual bugs in systems before real progress Shipping date brought forward Reduced time to dismantle and pack plant Damage After Shipping: Reduced speed during shipping Damage to switch gear and some engine systems ntpc.com 4
21 SUCCESSES: Contractors: Plant build - Adco Power Ltd northern experience Solar - Azgard Corporation and Green Sun Rising Battery Module &Controls - SAFT Batteries & ABB Inc B.A.F.N. construction support Testing and commissioning: Successful testing of batteries and diesel Successful testing of PV curtailment Powering community soon: ntpc.com 5
22 From This. ntpc.com 6
23 To This.. ntpc.com 7
24 THANK YOU ANY QUESTIONS? ntpc.com 8
Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017
Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering
More informationCommercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow
Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107
More informationSolar. Solar Electricity. Solar Hot Water. Solar Air Heating. Passive Solar
Solar Solar Electricity Solar Hot Water Solar Air Heating Passive Solar Who s Ken? Joined AEA November, 2012 Past Employers include Green Venture, Sun Life, TransCanada Pipelines, Great West Life EGH,
More information2016 UC Solar Research Symposium
2016 UC Solar Research Symposium Beyond UCR s Sustainable Integrated Grid Initiative: Energy Management Projects in Southern California October 7, 2016 Presented by: Alfredo A. Martinez-Morales, Ph.D.
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates For Internal Use Only. FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationPDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015
PDR Energy Baseline Alternative Proposal for Discussion October 27, 2015 Update Since Last Meeting Since the October 12 th Working Group Meeting Stem, Solar City, AMS and CESA have had over a half-dozen
More informationNorthwest Territories. Northwest Territories Highway Traffic, 1998
Northwest Territories Northwest Territories Highway Traffic, 1998 Northwest Territories Highway Traffic, 1998 Acknowledgements This report was prepared by the Transportation Planning Division of the Department
More informationJean Marie River Solar and Wind Monitoring Update
Jean Marie River Solar and Wind Monitoring Update Source: MACA Prepared for By Jean-Paul Pinard, P. Eng., PhD. 703 Wheeler St., Whitehorse, Yukon Y1A 2P6 Tel. (867) 393-2977; Email jpp@northwestel.net,
More informationMCE Napa County Cleaner energy and lower rates. Honig Winery, Rutherford
MCE Napa County Cleaner energy and lower rates Honig Winery, Rutherford Public Power by Community Choice Communities collectively purchase electricity as an alternative to investor-owned utility power
More informationMontana Renewable Energy Association
Montana Renewable Energy Association Mission & Focus areas: Education and Outreach Policy and Advocacy Industry Engagement www.montanarenewables.org SolSmart Solar Ready communities making process of going
More informationMay ATR Monthly Report
May ATR Monthly Report Minnesota Department of Transportation Office of Transportation Data and Analysis May 2011 Introduction The purpose of this report is to examine monthly traffic trends on Minnesota
More informationNew Jersey Solar Roundtable
New Jersey Solar Roundtable Transition to a Market-based REC Financing System Scott Hunter, Renewable Energy Program Administrator NJBPU, Office of Clean Energy Presented at New Jersey Institute of Technology
More informationFOR IMMEDIATE RELEASE
Article No. 7353 Available on www.roymorgan.com Roy Morgan Unemployment Profile Wednesday, 11 October 2017 2.498 million Australians (18.9%) now unemployed or under-employed In September 1.202 million
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MARCH 21 MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for uary FY 21 FINANCIAL HEALTH Standard and Poor s Bond Rating Current AA AA Budget Based Revenues
More informationThe International Cost Estimating and Analysis Association (ICEAA) Southern California Chapter September 9, 2015
Sustainable Integrated Grid Initiative (SIGI): Technical and Economic Challenges of Integrating Renewable Energy, Electric Vehicle Charging and Battery Energy Storage in a Modern Grid The International
More informationAmeren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR
Ameren Missouri AMENDED Renewable Energy Standard Compliance Report 2015 Prepared in Compliance with 4 CSR 240-20.100 June 23, 2016 NP Table of Contents Page INTRODUCTION...4 SECTION (8) (A) 1 A: TOTAL
More informationMonthly Operating Report. September 2016
Monthly Operating Report September 20 September overview» For the month of September 20 Contact recorded: Electricity, gas and steam sales of 819 GWh (September 2015: 821 GWh) Netback of $79.50/MWh (September
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY JULY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for e FY FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues
More informationOperational Opportunities to Minimize Renewables Curtailments
Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for uary FY 219 FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues
More informationThis presentation was given as part of a workshop on February 7, Presenters were:
This presentation was given as part of a workshop on February 7, 2018. Presenters were: Andrew Valainis, Montana Renewable Energy Association Bryan Von Lossberg, Renewable Energy Consultant Paul Herendeen,
More informationThomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257
Residential Solar Workshop May 7 th 2008 Thomas Alston Director of Business and Policy Development Presented By 1475 N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Workshop Agenda An Overview of
More informationNorthwest Territories Highway Traffic, 2004
Northwest Territories Highway Traffic, 2004 Northwest Territories Highway Traffic, 2004 Department of Transportation Government of the Northwest Territories October 2005 Acknowledgements This report was
More informationJoint presentation by: Lead investor EPC, O&M
Rwanda 8.5 MW project -the first utility-scale solar plant in East Africa 12 months from PPA to Interconnection - the quickest power project ever in Africa? Joint presentation by: Lead investor EPC, O&M
More information40KW Solar System for Apple Sauce Co
2012 40KW Solar System for Apple Sauce Co Document Created for The Apple Sauce Co by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L For further details please contact Luke M Hardy SunUp Solar Pty
More informationDecember 2018 RenewableGenerations Monthly Report
2018 RenewableGenerations Monthly Report Ecosystem of Clean Energy Programs Contractor Training Webinar Table of Contents Solar Electric... 3 Solar Thermal Heating (Northern Nevada Gas Customers)... 5
More informationUniversity of Michigan Eco-Driving Index (EDI) Latest data: October 2017
University of Michigan Eco-Driving Index () http://www.ecodrivingindex.org Latest data: October 2017 Developed and issued monthly by Michael Sivak and Brandon Schoettle Sustainable Worldwide Transportation
More informationNorthwest Territories Highway Traffic, 2002
Northwest Territories Highway Traffic, 22 Northwest Territories Highway Traffic, 22 Department of Transportation Government of the Northwest Territories January 24 Acknowledgements This report was prepared
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for ember FY 219 FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues
More informationThis presentation was given as part of a workshop on November 14, Presenters were:
This presentation was given as part of a workshop on November 14, 2017. Presenters were: Andrew Valainis, Montana Renewable Energy Association Bryan Von Lossberg Paul Herendeen, Missoula Federal Credit
More informationSolarPACE + Storage Expanding Opportunities and Improving Project Economics. Presented By:
SolarPACE + Storage Expanding Opportunities and Improving Project Economics Presented By: Introductions GELI Geli provides software solutions to help project developers and hardware suppliers bring commercial
More informationWinnCompanies Community Solar Photovoltaic to Benefit Affordable Housing Darien Crimmin Vice President of Energy & Sustainability
WinnCompanies Community Solar Photovoltaic to Benefit Affordable Housing Darien Crimmin Vice President of Energy & Sustainability dcrimmin@winnco.com Massachusetts Solar Policy SREC I Program 2010 through
More informationGraph #1. Micro-Generation Generating Units in Alberta 20
2, Graph #1. Micro-Generation Generating Units in Alberta 2 Cumulative # of Generating Units 1,9 1,8 1,7 1,6 1,5 1,4 1,3 1,2 1,1 1, 9 8 7 6 5 4 3 2 Number of MGG Units as of 216 Mar 31 Number of Solar
More informationNJ Solar Market Update As of 10/31/15
NJ Solar Market Update As of 10/31/15 Prepared by Charlie Garrison Renewable Energy Committee Meeting November 10, 2015 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 10/31/15
More informationDMM 2017 Q4 Report Highlights
DMM 2017 Q4 Report Highlights Gabe Murtaugh Senior Analyst Department of Market Monitoring Conference Call February 21, 2018 Outline Real-time market performance Higher prices in the 15-minute market Large
More informationNorthwest Territories 2015 Highway Traffic Report
Northwest Territories 2015 Highway Traffic Report Northwest Territories Highway Traffic, 2015 Department of Transportation Government of the Northwest Territories September 2016 Acknowledgements This report
More informationAugust ATR Monthly Report
August ATR Monthly Report Minnesota Department of Transportation Office of Transportation Data and Analysis August 2011 Introduction The purpose of this report is to examine monthly traffic trends on
More informationFort Providence Solar and Wind Monitoring Analysis
Fort Providence Solar and Wind Monitoring Analysis Source: NWT Bureau of Statistics Prepared for By Jean-Paul Pinard, P. Eng., PhD. 703 Wheeler St., Whitehorse, Yukon Y1A 2P6 Tel. (867) 393-2977; Email
More informationLithium Ion Battery Energy Storage for Microgrids
Lithium Ion Battery Energy Storage for Microgrids David Mall Power Up Defense Energy Forum Fort Walton Beach, FL October 28, 215 Saft. A world leader for advanced and innovative applications Saft is the
More informationBC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014
1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers
More informationNorthwest Territories Highway Traffic, 2012
Northwest Territories Highway Traffic, 2012 Northwest Territories Highway Traffic, 2012 Department of Transportation Government of the Northwest Territories August 2013 Acknowledgements This report was
More information160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh
Presentation on 160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh by Solar Energy Corporation of India Ltd. Feb 3, 2019 2 February 2019 Solar Energy Corporation of India Ltd 1 Indian
More informationMAN engines supporting Wind power EAPIC, Nairobi, 2 nd September 2010
MAN engines supporting Wind power EAPIC, Nairobi, 2 nd September 2010 2010 Susanne S. Bech Managing Director MAN Diesel & Turbo Kenya Ltd. < 1 > Table of contents 1. MAN Diesel & Turbo Update on the strong
More informationWhat is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market
What is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market Paul M. Sotkiewicz, Ph.D President December 7, 2016 What are the ideal properties of competitive
More informationGROWTH IN TENTH DISTRICT MANUFACTURING WAS SLIGHTLY POSITIVE Federal Reserve Bank of Kansas City Releases February Manufacturing Survey
FOR RELEASE Thursday, February 27, 2014 EMBARGOED FOR 10 A.M. CENTRAL TIME CONTACT: Pam Campbell 405-270-8617 Pam.Campbell@kc.frb.org GROWTH IN TENTH DISTRICT MANUFACTURING WAS SLIGHTLY POSITIVE Federal
More informationNorthwest Territories. Northwest Territories Highway Traffic, 2001
Northwest Territories Northwest Territories Highway Traffic, 21 Northwest Territories Highway Traffic, 21 Acknowledgements This report was prepared by the Transportation Planning Division of the Department
More informationStorage in the energy market
Storage in the energy market Richard Green Energy Transitions 216, Trondheim 1 including The long-run impact of energy storage on prices and capacity Richard Green and Iain Staffell Imperial College Business
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MAY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for ch FY FINANCIAL HEALTH Standard and Poor s Bond Rating Current AA Target AA Budget Based Revenues and
More informationNorthwest Territories 2017 Highway Traffic Report
Northwest Territories 2017 Highway Traffic Report Northwest Territories Highway Traffic, 2017 Department of Infrastructure Government of the Northwest Territories September 2018 Acknowledgements This report
More informationEnergy Markets in Turmoil The Consumer Perspective
Energy Markets in Turmoil The Consumer Perspective Sonny Popowsky Consumer Advocate of Pennsylvania Illinois State University Institute for Regulatory Policy Studies 63682 Springfield, IL May 17, 2001
More informationRenewable energy. and the smart grid. Presentation 3 rd Asian IAEE. 21 February 2012 Kyoto, Japan. Perry Sioshansi Menlo Energy Economics
Renewable energy and the smart grid Presentation 3 rd Asian IAEE 21 February 2012 Kyoto, Japan Perry Sioshansi Menlo Energy Economics San Francisco CA www.menloenergy.com Pleasure to be in Kyoto Always
More informationGeneration and Reservoirs Statistics September 25, 2017
Generation and Reservoirs Statistics September 25, 2017 PUBLIC UTILITIES COMMISSION OF SRI LANKA Daily Generation Mix in MWh 1,560 4% 250 1% 8,010 10,900 28% 10,460 27% 7,820 CEB Hydro CEB Thermal Oil
More informationELECTRICITY RATES. Rates Effective October 1, 2009
ELECTRICITY RATES FOR COMMERCIAL AND INDUSTRIAL CUSTOMERS Rates Effective October 1, 2009 If you would like information about our services, details about your rights and responsibilities, or a copy of
More informationNorthwest Territories Highway Traffic, 2014
Northwest Territories Highway Traffic, 2014 Northwest Territories Highway Traffic, 2014 Department of Transportation Government of the Northwest Territories August 2015 Acknowledgements This report was
More informationModeling and Comparison of Dynamics of AC and DC Coupled Remote Hybrid Power Systems
Modeling and Comparison of Dynamics of AC and DC Coupled Remote Hybrid Power Systems Presenter: Tanjila Haque Supervisor : Dr. Tariq Iqbal Faculty of Engineering and Applied Science Memorial University
More informationNorthwest Territories Highway Traffic, 2013
Northwest Territories Highway Traffic, 2013 Northwest Territories Highway Traffic, 2013 Department of Transportation Government of the Northwest Territories August 2014 Acknowledgements This report was
More informationMacroeconomic Outlook. Presented by Dr. Bruce A. Scherr Chairman of the Board Chief Executive Officer Emeritus
Macroeconomic Outlook Presented by Dr. Bruce A. Scherr Chairman of the Board Chief Executive Officer Emeritus Waterways Symposium Cincinnati, OH November 15-17, 2016 Topics Energy Macro Implications Inflation
More informationNorthwest Territories 2016 Highway Traffic Report
Northwest Territories 2016 Highway Traffic Report Northwest Territories Highway Traffic, 2016 Department of Infrastructure Government of the Northwest Territories September 2017 Acknowledgements This report
More informationSolar photovoltaic research: Drakenstein Municipality
Rooftop Solar PV Solar photovoltaic research: Drakenstein Municipality Karin Kritzinger and Imke Meyer, Date 22/04/2015 Dialogue on Utility and Local Scale Renewable Energy in South Africa 22 April 2015-1
More informationAdvances in Energy Storage and Implementing a Peak Shaving Battery at Fort Carson
Advances in Energy Storage and Implementing a Peak Shaving Battery at Fort Carson Travis Starns Business Development Manager - AECOM Nov. 20, 2018 Agenda Applications for energy storage Advances in energy
More informationNJ Solar Market Update As of 6/30/15
NJ Solar Market Update As of 6/30/ Prepared by Charlie Garrison July 17, 20 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 6/30/ is approximately 1,500.7 MW. Approximately
More informationMinistério de Minas e Energia. Minister Eduardo Braga. Brazil - Texas Chamber of Commerce - BRATECC May/2015
1 Minister Eduardo Braga Brazil - Texas Chamber of Commerce - BRATECC May/2015 2 3 World s 7 th largest economy; Investment grade Fiscal adjustment taking place; Inflation being controlled; Large and diversified
More informationDocket No. DE Dated: 05/04/2015 Attachment CJG-1 Page 1
Docket No. DE - Dated: 0/0/0 Attachment CJG- Page 8 9 Summary of Forecasted Energy Service 0 Cost For January 0 Through December 0 TOTAL COST Cents per KWH Reference Fossil energy costs $ 9,9 $. Attachment
More informationENERGY STORAGE. Integrating Renewables thanks to Consumers Flexibility. Energy Pool Développement SAS
ENERGY STORAGE Integrating Renewables thanks to Consumers Flexibility 1 Introduction to Energy Pool The leading European Demand Response Operator YOUNG, FAST DEVELOPING COMPANY 2009 2010 2013 Company set
More informationFOR IMMEDIATE RELEASE
Article No. 5842 Available on www.roymorgan.com Roy Morgan Unemployment Profile Thursday, 2 October 2014 Unemployment climbs to 9.9% in September as full-time work lowest since October 2011; 2.2 million
More informationMONTHLY PERFORMANCE DASHBOARD
AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues and Expenses
More informationLarge scale solar power plant in Nordic conditions. Antti Kosonen, Jero Ahola, Christian Breyer, Albert Albó
Large scale solar power plant in Nordic conditions Antti Kosonen, Jero Ahola, Christian Breyer, Albert Albó 25.8.214 Finland Finland: Location: between latitudes of 6 7 Area: 338 435 km 2 Population: 5.4
More informationMonthly Operating Report. February 2018
Monthly Operating Report February 2018 February overview» For the month of February 2018 Contact recorded: Electricity and gas sales of 534 GWh (February 20: 551 GWh) Netback of $82.16/MWh (February 20:
More informationFOR IMMEDIATE RELEASE
Article No. 6928 Available on www.roymorgan.com Roy Morgan Unemployment Profile Wednesday, 17 August 2016 Australian real unemployment jumps to 10.5% (up 0.9%) in July during post-election uncertainty
More informationNE (SE) Beam
Predicted clear day beam and diffuse irradiances (/ W m 2 ) on vertical and horizontal surfaces on specified days in northern (N) and southern (S) hemispheres (see notes at foot of table): LATITUDE 60
More informationSunrise: 05:48 N (S) Beam
Predicted clear day beam and diffuse irradiances (/ W m 2 ) on vertical and horizontal surfaces on specified days in northern (N) and southern (S) hemispheres (see notes at foot of table): LATITUDE 40
More informationMeridian Energy monthly operating report for December 2017
Release Stock exchange listings: NZX (MEL) ASX (MEZ) Meridian Energy monthly operating report for December 217 Attached is Meridian Energy Limited's monthly operating report for the month of December 217.
More informationSystem Status Briefing
System Status Briefing Phakamani Hadebe Interim Group Chief Executive 3 May 2018 Contents 1 Performance summary 2 Operational highlights 3 Generation performance 4 Distribution overview 5 Transmission
More informationElectricity Rates. For Commercial and Industrial Customers
Electricity Rates For Commercial and Industrial Customers Rates Effective May 1, 2011 If you would like information about our services, details about your rights and responsibilities, or a copy of our
More informationTABLE C-43. Manufacturers' new and unfilled orders, {Amounts in millions of dollars] Nondurable. Capital goods. Total. goods.
TABLE C-43. Manufacturers' new and unfilled orders, -74 {Amounts in millions of dollars] New orders t, I960. 27, 559 26, 903 30,672 30,115 31,086 33,005 35,322 37,952 41, 803 45, 944 46,763 50, 243 53,
More informationTENTH DISTRICT MANUFACTURING SURVEY REBOUNDED MODERATELY Federal Reserve Bank of Kansas City Releases January Manufacturing Survey
FOR RELEASE Thursday, January 23, 2014 EMBARGOED FOR 10 A.M. CENTRAL TIME CONTACT: Bill Medley 816-881-2556 Bill.Medley@kc.frb.org TENTH DISTRICT MANUFACTURING SURVEY REBOUNDED MODERATELY Federal Reserve
More informationUnalakleet Update: Lessons learned & continual improvement. Alaska WWG
Unalakleet Update: Lessons learned & continual improvement { Alaska WWG Welcome 1. System 2. Performance 3. Next steps Northwind 100 Turbines * Rated 600 kw * Predicted annual production: 1,500,000
More informationScaling Successful Mini-grid Programs: Experience of Bangladesh
Frontier Developments in Mini-grids Scaling Successful Mini-grid Programs: Experience of Bangladesh Farzana Rahman Unit Head (Investment), Renewable Energy IDCOL, Bangladesh 6 December 2017 Abuja, Nigeria
More informationELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017
ELECTRIC SERVICE RATE SCHEDULES Effective November 1, 2017 SCHEDULE 100 RESIDENTIAL SERVICE Residential Customers for all domestic uses. CHARACTER OF SERVICE: Alternating current, sixty-hertz 120/240 volts
More informationEnergy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director
Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D
More informationDesign Criteria Data
OKLAHOMA CITY OK Latitude = 35.4 N WMO No. 72353 Longitude = 97.6 W Elevation = 133 feet Period of Record = 1973 to 1996 Average Pressure = 28.62 inches Hg Design Criteria Data Mean Coincident (Average)
More informationPast Due. Account Charges. Contract Charges Security Deposit Due - Jun 09, , Customer Service. Jun 19, PAST DUE $1,693.
11983978 Jun 19, 217 1 124 958 PAST DUE $1,693.97 Meter Reading Information Meter # 55271 May 3 655 Jun 15 6642 17 days 1397 on or about Aug 15 82 Past Due Balance payable includes an amount which is payable
More informationThe impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options
The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options Electricity demand in France: a paradigm shift Electricity
More informationAlternative Energy Development Board February 2019
Hybrid Grid Solar PV Power Projects Alternative Energy Development Board February 2019 Introduction A Hybrid system can be achieved by harnessing energy through two or more different resources There are
More informationDesign Criteria Data
MEDFORD/JACKSON CO. OR Latitude = 42.37 N WMO No. 72597 Longitude =122.8 W Elevation = 1329 feet Period of Record = 1973 to 1996 Average Pressure = 28.61 inches Hg Design Criteria Data Mean Coincident
More informationCLEAN POWER HEALTHY COMMUNITIES CONFERENCE
CLEAN POWER HEALTHY COMMUNITIES CONFERENCE May 10 th, 2012 Tony Seba tony@tonyseba.com Solar Trillions Copyright 2008-2012 by Tony Seba Solar vs Conventional Power Costs Solar costs go down while conventional
More informationRegulation Update. Operating Committee September 12, PJM 2017
Regulation Update Operating Committee September 12, 2017 Regulation Market Clearing Price *Data up to Aug 22 2 Mileage Ratio Mileage Ratio has increased since the new signal implementation Larger Utilization
More informationCreating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics.
Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics December 18, 2012 Outline Learn how the solar PV market has grown in MA since 2007 Understand the policy design of the MA Solar Carve-Out
More informationUp and Down Months of the Stock Market
Up and Down Months of the Stock Market 1926-2017 Positive years (66) in the stock market were not good all year long and losing years (24) were not losers throughout the year. Winning years produce losing
More informationDesign Criteria Data
DES MOINES IA Latitude = 41.53 N WMO No. 72546 Longitude = 93.65 W Elevation = 965 feet Period of Record = 1973 to 1996 Average Pressure = 28.96 inches Hg Design Criteria Data Mean Coincident (Average)
More informationPRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN
PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN WORKSHOP ON SMALL WIND ENERGY AND HYBRID SYSTEMS & ITS RELEVANCE
More informationOperational Overview. Operational Forum, 24 th March 2010
Operational Overview Operational Forum, 24 th March 21 Weather Weather February 21 The cold weather continued throughout February with all but one day being colder than the 17-year seasonal normal CWV.
More informationENERGY STRATEGY FOR YUKON. Independent Power Production Policy
ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out
More informationCommuter Rail Update. October 25, 2018
Commuter Rail Update October 25, 2018 2 page page 3 State of Commuter Rail Network, July 2014 The 2014 Commuter Rail network had multiple issues and a history of neglect & under-investment FIRST UP? UPGRADES
More informationDesign Criteria Data
LAS VEGAS/MCCARRAN NV Latitude = 36.8 N WMO No. 72386 Longitude =115.1 W Elevation = 2179 feet Period of Record = 1973 to 1996 Average Pressure = 27.67 inches Hg Design Criteria Data Mean Coincident (Average)
More informationResidential Load Profiles
Residential Load Profiles TABLE OF CONTENTS PAGE 1 BACKGROUND... 1 2 DATA COLLECTION AND ASSUMPTIONS... 1 3 ANALYSIS AND RESULTS... 2 3.1 Load Profiles... 2 3.2 Calculation of Monthly Electricity Bills...
More informationDesign Criteria Data
PHOENIX/SKY HARBOR AZ Latitude = 33.43 N WMO No. 72278 Longitude =112. W Elevation = 116 feet Period of Record = 1973 to 1996 Average Pressure = 28.72 inches Hg Design Criteria Data Mean Coincident (Average)
More informationRojas Manyame General Manager: Regulation Electricity Control Board (ECB) Namibia
Rojas Manyame General Manager: Regulation Electricity Control Board (ECB) Namibia CONTENTS Background Renewable Resources Potential Institutional Framework Namibian ESI Current RE Procurement Status Challenges
More informationAction Requested From AMWG
Action Requested From AMWG NONE, These Two Presentations Are For Information Transfer Only The information is derived from a multi-year synthesis research effort related to existing data on flow, sediment-transport
More information