1

2 Agenda Electrical Transformers (Quality Control) Order Obtaining BIS Licence Requirements of Guidelines / IS : 1: 2014 / STI Concerns in Getting BIS Licence Experience with BEE Regulations Recommendations Conclusion

3 Electrical Transformers (Quality Control) Order, 2014

4 Electrical Transformers (Quality Control) Order, 2014: Came in to Force: Electrical Transformers (Quality Control) Amendment Order, 2014 : Coming in to Force:

5 Salient points of Electrical Transformers Quality Order: Obligation for certification: All manufacturers of electrical Transformers shall make an application to the Bureau for obtaining licence, within a period of six months from the date of coming into force of this order. No person shall commence manufacture, without obtaining a valid licence from the Bureau On obtaining certification marks licence, no person shall by himself or through any person on his behalf manufacture or store for sale, sell or distribute any electrical transformers specified in column (3) of the schedule, which do not confirm to the specified standards and do not bear Standard Mark of Bureau

6 Pros Improvement in Manufacturing Quality Reduction in failure rate Qualification of Manufacturers by BIS Confidence levels of clients will get increased Cons Commercial impact with Marking fee Delay in tendering activities if cycle time is more in getting the Licence

7 Few Concerns DTRs are made against order. If customer requirement is not in line with the requirements of IS :2014, what manufacturer has to do? Lack of awareness to all customers and hence purchase policies are yet to be aligned with the obligations of the Quality Order (Till date no tender is floated with new requirements). BIS Guidelines & STI as per IS : 2014 were issued lately in 1 st week of Dec-14 Lack of Clarity on some Guidelines to Manufacturers / BIS

8 BIS Licence

9 Obtaining Licence Submission of application BIS inspection Evaluation of Manufacturing facilities and Drawl of Sample for testing at BIS approved laboratories Receipt of Licence Operation of Licence Surveillance inspections Extension of Scope of Licence Tests on Market Samples

10 Licence Scope: Standard ratings as per IS : 2014 Voltage Class > 200 kva and kva,3-ph,dtrs 25 kva, 1-Ph DTRs kva, 3-Ph DTRs 11 kv 250, 315, 400, 500, 6.3, 10, 16, 20, 25, 40, 630, 1000, 1250, 1600, 5, 10, 16 & 25 63, 100, 160 & & 2500 > 11 kv and 22 kv 63, 100, 160 & , 315, 400, 500, 630, 1000, 1250, 1600, 10, 16 & & 2500 > 22 kv and 33 kv 100, 160 & , 315, 400, 500, 630, 1000, 1250, 1600, 16 & & 2500 No. of Ratings: voltage classes (3.3, 6.6, 11, 22 & 33kV) and Sealed & Non sealed Total Grand Total 2*(10* ) = 74 2*(10* )=100 (4* ) = = 191 (Without considering Energy Efficiency Levels) 3 * 191 = 573 (If Energy Efficiency Levels are considered)

11 Action Plan

12 BIS Licence - Documents Guidelines for Certification IS : 2014 Scheme of Testing & Inspection (STI)

13 Guidelines for Certification

14 As per Guidelines, all applications shall be recorded as per IS 1180 (Part 1):2014. (Note: As per the amendment of Quality Order, schedule (3) is substituted the ratings as per New Standard. ) Clarity is needed on how to execute running orders / tenders floated as some of the designs may not be meeting all the requirements of IS : 2014

15 Grant of Licence (Cl B.I) Following details to be submitted along with application - Ratings of the transformers for which BIS licence is required. - Relevant drawings and - Technical parameters of the said ratings Clarity is required on - whether Drawings to be submitted for all the ratings - list of drawings to be submitted

16 Grant of Licence, (Cl. B.I): Change in following parameters shall be taken as a change in the design, which would require type testing again: - Flux density - Current density and type of winding material (Cu/Al) - Tank design - Type of construction (core type/shell type) - Type of connection (star/delta) & Vector Group - Total loss and - Method of cooling The requirement may need to be reviewed for simplification. Ex: - Change in only vector group ----> Terminations will get changed. - Change in only method of cooling ----> Will effect only Temp. rise, but not SC, Impulse, etc.

17 Drawl of Samples and Conformity of Product, (Cl B.III): During Preliminary Inspection, samples shall be drawn from the following group to cover all the ratings Three phase transformers Nominal System Voltage 200 kva, 3 Phase > 200kVA and 2500 kva, 3 Phase 3.3 kv One sample of highest rating One sample of highest rating 6.6 kv -do- -do- 11 kv -do- -do > 11 kv and 22 kv -do- -do- > 22 kv and 33 kv -do- -do- Single phase transformers Nominal System Standard Ratings Voltage 11 kv One sample of highest rating 22 kv -do- 33 kv -do-

18 Drawl of Samples and Conformity of Product, During Preliminary Inspection (Cl B.III): - One sample of highest rating, offered by the firm to cover the entire range for which licence has been applied for, as per the above table. - Separate samples for sealed and non-sealed type DTRs - Scope of licence with higher energy efficiency level DTR shall also cover DTRs with lower energy efficiency levels To obtain Licence for entire range at once, is it acceptable to get the tests done on below 5 samples having Energy Efficiency Level-3 1) 200 kva, 33 kv, 3-ph, Sealed DTR 2) 200 kva, 33 kv, 3-ph, Non-Sealed DTR 3) 2500 kva, 33 kv, 3-ph, Sealed DTR 4) 2500 kva, 33 kv, 3-ph, Non-Sealed DTR 5) 25 kva, 33 kv, 1-ph, Sealed DTR

19 Drawl of Samples and Conformity of Product, (Cl B.III): The licenceshall be granted once the product passes in both the type tests and the routine tests as indicated. It is presumed that only type & routine tests are to be conducted and special tests are not required. Ex: SC test is required only up to 200 kva T/Fs

20 A. Type of Tests Routine Tests Type Tests Special Tests a) Measurement of winding resistance a) Lightning a) Determination of sound b) Measurement of voltage ratio & impulse test levels check of phase displacement b) Temperature-rise b) Short-circuit withstand c) Measurement of short-circuit test test (above 200 kva) impedance (principal tapping, when applicable) & load loss at 50 c) Short-circuit withstand test c) No load current at percent voltage percent and 100 percent load (up to 200 kva). d) Paint adhesion tests. d) Measurement of no-load loss & d) Pressure test e) BDV and moisture current e) Measurement of insulation resistance f) Induced over-voltage withstand test g) Separate-source voltage withstand test h) Pressure Test i) Oil Leakage Test content of oil in the transformer

21 For inclusion of new rating of the transformer - If rating < Scope of Licence: Licensee shall submit a complete test report from BIS approved laboratories - If rating > Scope of Licence: testing. BIS shall plan preliminary inspection and draw a sample for Time limit may be defined by BIS for review of test reports / extension of scope of License as any delay will affect the tendering activities

22 For Operation of Licence Type Tests also be carried out, periodically, from a BIS recognized/group-2 category of laboratories. (The frequency of type test is to be decided in consultation with Ministry of Power.) Clarity is yet to be given on the below - Frequency of type tests - Methodology to be followed for selection - To ensure same sampling against all Manufacturers across India

23 For Operation of Licence Compliance of Market Samples: One of the following, in consultation with Ministry of Power: a. Buyers (Electricity Utilities) to send samples directly to BIS recognized laboratories b. BIS recognized Laboratory can draw samples on behalf of the Electricity Utilities c. BIS can draw samples as per the current practice prevailing in case of other products Clarity is yet to be given on the below - Methodology to be followed (Field/store sampling, data sharing, Compliance to the other clause of standards in addition to the testing, etc) - Frequency of testing on Market samples - To ensure same sampling against all manufacturers across India - Consideration of inter lab variations

24 IS : 2014

25 If Customer specification calls for a deviation with IS :2014.????

26 Standard Tapping range (For 3 Phase DTRs) : 200 kva: +2.5% to -5% in steps of 2.5% variation > 200 kva & 2500 kva: +5% to -10% in steps of 2.5% variation > 500 kva& 2500 kva: +5% to -15% in steps of 2.5% variation(oltc-optional) If customer wants a range of +5% to -5% in steps of 2.5%Terms.????

27 Terminal arrangements for 3-ph, Sealed type DTRs: Terminal arrangement shall be such that it shall be possible to replace bushings (external) without opening the top cover and affecting the sealing of the transformer. HV & LV Bushings: The bushing shall be made in two parts. The outer bushing shall be of porcelain. The internal bushing shall be of either porcelain or tough insulating material, like epoxy and shall have embedded stem. Note: Any other suitable arrangement can be used subjected to agreement b/w user & supplier. - Availability of huge quantities two part HV bushings.???? - It is Different from the IS standard and hence replacement may become difficult for utilities - Clarity on note is needed as without using two part bushing, effectiveness of sealing can t be ensured.

28 Transformer Tank: All nuts/bolts/washers exposed to atmosphere shall be of Stainless Steel if the size 12mm (Cl 15.3) If customer insist to take deviation to reduce cost.???? Is BIS going to ensure compliance of this requirement for all the quantities.????

29 Standard Fittings: Inspection hole, for DTRs above 200 kva rating. (Cl 20.1.r) If customer insist to take deviation to avoid additional welding / source of leakage.????

30 Scheme of Testing & Inspection (STI)

31 As per STI, from every lot Temperature Rise Test to be performed on one sample of 50 transformers (of identical design/ construction and of same nominal system voltage and rating) or part thereof. The sampling need to be amended as follows: One sample each of identical design/construction and of same nominal system voltage and rating once in five years (Like other type tests).

32 Experience with BEE Regulations

33 Requirements: - Every DTR being manufactured, commercially purchased or sold in India shall meet the compliance requirements - Sampling for verification and challenges would be carried out after the deliveries are made to the utility on the basis of tender. - BEE would conduct label verification survey in the market about the availability of registered models at various authorized dealers/retailers/warehouse of user. - Till date, some of the clients are not calling for such requirements - No evidence for conducting label verification survey uniformly across India. - It has become burden to the manufacturers those who are following rules honestly

34 Recommendations

35 User Guidelines for usage of BIS certified DTRs may be required for Site operations Storage / Handling Installation Maintenance Proper usage of Overloading / over voltage / over current protection system

36 Good Practices followed by some Utilities Better Handling System Proper storage

37 Proper Storage with elevated Platform

38 Improper Handling / Storage Dumped on road Dumped all material without any gap

39 Improper handling

40 Non Usage of Protection System MCCB is bypassed Arcing horns are not in place

41 Conclusions

42 Support Expecting from BIS Instant technical / administrative support from all BIS offices (Branch / Regional) Simplification of certification process for numerous varieties of DTRs BIS may take ownership on the products those are having BIS marking so that confidence levels of clients goes up and additional testing at factory / sites may intended to get reduced Ex: (1) Some customers are asking to conduct temp. rise test on 1 sample per 100 nos lot. Ex: (2) Routine tests to be conducted on all samples as part of Acceptance tests BIS to take lead in bridging the gaps with the requirements of customers Guidelines for site operations to be formulated and made mandatory for users of BIS certified product BEE label to be eliminated as BIS product meets the efficiency standards defined by BEE

43

7 The revised IS 8034:2002 and revised STI be implemented w.e.f. 1 Feb 2005.

7 The revised IS 8034:2002 and revised STI be implemented w.e.f. 1 Feb 2005. BUREAU OF INDIAN STANDARDS (CENTRAL MARKS DEPARTMENT-III) Our Ref: CMD-III/16:8034 25 Oct 2004 Subject: Implementation of revised IS 8034:2002 Submersible Pump Sets and revised STI (Doc:STI/8034/5 ) IS

More information

(i) in paragraph 9, for sub-paragraph (i) the following shall be substituted, namely:-

(i) in paragraph 9, for sub-paragraph (i) the following shall be substituted, namely:- Revision 3 Date: 28/01/2016 Amendment to Schedule 6 for Induction Motor In the said schedule, (i) in paragraph 9, for sub-paragraph (i) the following shall be substituted, namely:- Effective from 1 st

More information

PRESENTATION ON STANDARDSDISTRIBUTION TRANSFORMERS BUREAU OF INDIAN STANDARDS BHOPAL

PRESENTATION ON STANDARDSDISTRIBUTION TRANSFORMERS BUREAU OF INDIAN STANDARDS BHOPAL PRESENTATION ON STANDARDSDISTRIBUTION TRANSFORMERS BUREAU OF INDIAN STANDARDS BHOPAL BIS Act WTO Principle on Standard Process for development of Indian Standard Standards on Transformers Detailed provision

More information

2. 0 Test Records - All records of analysis and tests shall be kept in suitable forms approved by the Bureau of Indian Standards.

2. 0 Test Records - All records of analysis and tests shall be kept in suitable forms approved by the Bureau of Indian Standards. SCHEME OF TESTING AND INSPECTION FOR CERIFICATION OF LABORATORY GLASSWARE GRADUATED MEASURING CYLINDERS ACCORDING TO IS 878:2008/ISO 4788:2005 (Second Revision) DOC: STI/878/2 1.0 Laboratory - A laboratory

More information

TABLE OF CONTENTS FOREWORD... 2 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS... 3

TABLE OF CONTENTS FOREWORD... 2 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS... 3 TITLE SPECIFICATION FOR MEDIUM VOLTAGE DATE: FEBRUARY 2015 PAGE: 1 OF 25 TABLE OF CONTENTS Page FOREWORD... 2 INTRODUCTION... 3 1 SCOPE... 3 2 NORMATIVE S... 3 3 DEFINITIONS AND ABBIATIONS... 3 4 REQUIREMENTS...

More information

013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS

013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS 013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS FOR OVERHEAD NETWOKS CEYLON ELECTRICITY BOARD SRI LANKA Specification for MOULDED CASE CIRCUIT BREAKERS FOR OVERHEAD NETWOKS CEB Specification

More information

020: 2013 CEB SPECIFICATION MINIATURE CIRCUIT BREAKER (MCB)

020: 2013 CEB SPECIFICATION MINIATURE CIRCUIT BREAKER (MCB) 020: 2013 CEB SPECIFICATION MINIATURE CIRCUIT BREAKER (MCB) CEYLON ELECTRICITY BOARD SRI LANKA Telephone: +94 11 232 0953 Fax: +94 11 232 3935 CONTENTS Page 1.0 Scope 3 2.0 System Parameters 3 3.0 Service

More information

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. PAGE 1 OF 7 TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH 1.0 SCOPE:

More information

SPECIFICATION FOR REWIRABLE FUSES (KITKAT FUSES) 100A & 200A SPECIFICATION NO.: DIST/ A- KIT /

SPECIFICATION FOR REWIRABLE FUSES (KITKAT FUSES) 100A & 200A SPECIFICATION NO.: DIST/ A- KIT / SPECIFICATION FOR REWIRABLE FUSES (KITKAT FUSES) 100A & 200A SPECIFICATION NO.: DIST/ A- KIT / 2005-06 SR.NO ITEM PAGE 1. SCOPE 2 2. WEATHER CONDITIONS 2 3. RATED VOLTAGE & FREQUENCY 2 4. GENERAL REQUIREMENT

More information

TECHNICAL SPECIFICATIONS FOR 11KV AIR BREAK (A.B.) SWITCHES :

TECHNICAL SPECIFICATIONS FOR 11KV AIR BREAK (A.B.) SWITCHES : TECHNICAL SPECIFICATIONS FOR 11KV AIR BREAK (A.B.) SWITCHES : 1. SCOPE : This specification covers design, manufacturing, testing at manufacturer s works, inspection, packing & delivery of 11 KV Air Break

More information

TECHNICAL SPECIFICATION FOR 11 KV CAPACITOR BANK

TECHNICAL SPECIFICATION FOR 11 KV CAPACITOR BANK TECHNICAL SPECIFICATION FOR 11 KV CAPACITOR BANK MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. PAGE 1 OF 7 TECHNICAL SPECIFICATION FOR 11 KV.CAPACITOR BANK 1.0 SCOPE: This specification covers

More information

TECHNICAL SPECIFICATION FOR 11 KV AIR BREAK (A.B.) SWITCHES:

TECHNICAL SPECIFICATION FOR 11 KV AIR BREAK (A.B.) SWITCHES: TECHNICAL SPECIFICATION FOR 11 KV AIR BREAK (A.B.) SWITCHES: 1. SCOPE : This specification covers design, manufacturing, testing at manufacturer s works, inspection, packing & delivery of 11 KV Air Break

More information

BUREAU OF INDIAN STANDARDS (Western Region Office, Mumbai) DRAFT PRODUCT CERTIFICATION MANUAL FOR COMMENTS. Our Ref: DDGW Sectt(PCO/RD) 23 Jan 2014

BUREAU OF INDIAN STANDARDS (Western Region Office, Mumbai) DRAFT PRODUCT CERTIFICATION MANUAL FOR COMMENTS. Our Ref: DDGW Sectt(PCO/RD) 23 Jan 2014 BUREAU OF INDIAN STANDARDS (Western Region Office, Mumbai) DRAFT PRODUCT CERTIFICATION MANUAL FOR COMMENTS Our Ref: DDGW Sectt(PCO/RD) 23 Jan 2014 Sub: Preparation & review of draft manuals for product

More information

SCHEME OF TESTING AND INSPECTION FOR CERTIFICATION OF COPPER ALLOY GATE, GLOBE AND CHECK VALVES FOR WATER WORKS PURPOSES ACCORDING TO IS 778:1984

SCHEME OF TESTING AND INSPECTION FOR CERTIFICATION OF COPPER ALLOY GATE, GLOBE AND CHECK VALVES FOR WATER WORKS PURPOSES ACCORDING TO IS 778:1984 SCHEME OF TESTING AND INSPECTION FOR CERTIFICATION OF ACCORDING TO DOC:STI/778/4 1 LABORATORY - A laboratory shall be maintained which shall be suitably equipped and staffed, where different tests given

More information

Bus bar Bushings up to 1.1kV and from 1.6kA to 4kA for Liquid Filled Transformers:

Bus bar Bushings up to 1.1kV and from 1.6kA to 4kA for Liquid Filled Transformers: 4 (Four) Pole Monoblock: Bus bar Bushings up to 1.1kV and from 1.6kA to 4kA for Liquid Filled Transformers: Designed and manufactured in accordance with EN 50336:2002 and BS 2562: 1979 1 Introduction:

More information

Schedule No.: 13. Diesel Engine Driven Monoset Pumps for Agricultural Purposes

Schedule No.: 13. Diesel Engine Driven Monoset Pumps for Agricultural Purposes Revision-1 Date: 08.01.2016 Schedule No.: 13 Diesel Engine Driven Monoset Pumps for Agricultural Purposes 1. Scope 1.1 This schedule specifies the Fuel Consumption norms leading to Star Labeling Programme

More information

Guideline No.: E-03(201806) E-03 MOTORS. Issued date: June 7, China Classification Society

Guideline No.: E-03(201806) E-03 MOTORS. Issued date: June 7, China Classification Society Guideline No.: E-03(201806) E-03 MOTORS Issued date: June 7, 2018 China Classification Society Foreword: This Guideline is a part of CCS Rules, which contains technical requirements, inspection and testing

More information

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society Guideline No.: E-07(201610) E-07 TRANSFORMERS Issued date: October 28,2016 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection and

More information

SKN_N0106AnnexJ_R2. Annex J - Specific requirements for PVT collector Certification. 1. Introduction and definition

SKN_N0106AnnexJ_R2. Annex J - Specific requirements for PVT collector Certification. 1. Introduction and definition Annex J - Specific requirements for PVT collector Certification 1. Introduction and definition PVT collectors (named hybrid collectors in ISO 9806) generate heat and electric power at the same time. They

More information

Guideline No.: E-07(201712) E-07 TRANSFORMERS. Issued date: December 26, China Classification Society

Guideline No.: E-07(201712) E-07 TRANSFORMERS. Issued date: December 26, China Classification Society Guideline No.: E-07(201712) E-07 TRANSFORMERS Issued date: December 26, 2017 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection

More information

Construction and Connection of Street Light Assets

Construction and Connection of Street Light Assets Construction and Connection of Street Light Assets 1. INTRODUCTION... 2 2. FURTHER INFORMATION... 3 3. DEFINITIONS... 3 3.1 Designer... 3 3.2 Street Light Asset Owner... 3 3.3 Road Owner... 4 3.4 Developer...

More information

Dakshin Gujarat Vij Company Limited

Dakshin Gujarat Vij Company Limited Dakshin Gujarat Vij Company Limited CIN U40102GJ2003SGCO42909 Regd. & Corporate Office: Urja Sadan, Nana Varachha Road, Kapodara Char Rasta,Surat 395 006 C & R DEPARTMENT Phone No.: 0261 2506100-200-175

More information

Guideline No.: E-03(201610) E-03 MOTORS. Issued date: October 28,2016. China Classification Society

Guideline No.: E-03(201610) E-03 MOTORS. Issued date: October 28,2016. China Classification Society Guideline No.: E-03(201610) E-03 MOTORS Issued date: October 28,2016 China Classification Society Foreword: This Guideline is a part of CCS Rules, which contains technical requirements, inspection and

More information

Distribution transformers Efficiency over life-cycle

Distribution transformers Efficiency over life-cycle Distribution transformers Efficiency over life-cycle ABB a global leader ABB is a global leader in Power and Automation technologies that enable utility and industry customers to improve performance while

More information

1.1 All testing apparatus shall be periodically checked and calibrated and records of such checks/calibration shall be maintained.

1.1 All testing apparatus shall be periodically checked and calibrated and records of such checks/calibration shall be maintained. SCHEME OF TESTING AND INSPECITON FOR CERTIFICATION OF ELECTRICAL ACCESSORIES CIRCUIT BREAKERS FOR OVER CURRENT PROTECTION FOR HOUSEHOLD AND SIMILAR INSTALLATIONS PART1 CIRCUIT BREAKERS FOR ac OPERATION

More information

Technical Specification of GECOL. Packaged Transformers

Technical Specification of GECOL. Packaged Transformers GES 26211 Technical Specification of GECOL Packaged Transformers (Revision history) Issued on: Jan. 01, 2007 General Electricity Company of Libya Contents 1 SCOPE AND SERVICE CONDITIONS... 6 1.1 SCOPE...

More information

Exceeding the standards with MNS

Exceeding the standards with MNS Exceeding the standards with MNS Exceeding the standards with MNS 5 essentials of switchgear solutions Since ABB first introduced MNS the modular low voltage switchgear platform over forty years ago, MNS

More information

Technical Specification for 12kV and 24kV Current Limiting Fuse- Links for Overhead Applications

Technical Specification for 12kV and 24kV Current Limiting Fuse- Links for Overhead Applications Ergon Energy Corporation Limited Technical Specification for 12kV and 24kV Current Limiting Fuse- Links for Overhead Applications ETS12-01-04 Specification ETS12-01-04 Ver 3 Contents 1. Purpose and Scope...

More information

Technical Specification for 12kV Powder Filled Current Limiting Fuse-Links for Use in Switchgear (In Oil)

Technical Specification for 12kV Powder Filled Current Limiting Fuse-Links for Use in Switchgear (In Oil) Ergon Energy Corporation Limited Technical Specification for 12kV Powder Filled Current Limiting Fuse-Links for Use in Switchgear ETS12-01-03 Specification ETS12-01-03 Ver 3 Contents 1. Purpose and Scope...

More information

023 : 2006 CEB STANDARD. 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA

023 : 2006 CEB STANDARD. 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA 023 : 2006 CEB STANDARD 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA Specification for 12kV & 36kV LOAD BREAK SWITCHES CEB Standard 023 : 2006 CEYLON ELECTRICITY BOARD No. 50, Sir

More information

S.No. Tender Queries BRPL Reply 1 For 11KV(E) 3Cx300sqmm A2XWY High Ampacity cable conductor details specification not

S.No. Tender Queries BRPL Reply 1 For 11KV(E) 3Cx300sqmm A2XWY High Ampacity cable conductor details specification not S.No. Tender Queries BRPL Reply 1 For 11KV(E) 3Cx300sqmm A2XWY High Ampacity cable conductor details specification not clear.please provide Specification for High ampacity HT Cable with Trapezoidal wire

More information

Technical Specification for 12kV and 24kV Powder Filled Current Limiting Fuse Links for Use in Switchgear (In Air)

Technical Specification for 12kV and 24kV Powder Filled Current Limiting Fuse Links for Use in Switchgear (In Air) Ergon Energy Corporation Limited Technical Specification for 12kV and 24kV Powder Filled Current Limiting Fuse Links for Use in Switchgear ETS12-01-02 Specification ETS12-01-02 Ver 3 Contents 1. Purpose

More information

Guideline No.: E-07(201501) E-07 TRANSFORMERS. Issued date: October 20,2015. China Classification Society

Guideline No.: E-07(201501) E-07 TRANSFORMERS. Issued date: October 20,2015. China Classification Society Guideline No.: E-07(201501) E-07 TRANSFORMERS Issued date: October 20,2015 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection and

More information

Louisville Gas and Electric Company

Louisville Gas and Electric Company P.S.C. Electric No. 11, Original Sheet No. 57 APPLICABLE In all territory served. AVAILABILITY OF SERVICE Available to any customer-generator who owns and operates a generating facility located on Customer

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, 2015- DRAFT 1. PREAMBLE 1.1 To harness the potential of renewable energy resources in the state, Government of Madhya Pradesh

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

क न द र य म ह व भ ग भ स द भ- स ए ड -III/16: IS न म बभ ग षय म ह- आई एस : 2003 क परभप लन ललए एस ट आई Doc: STI/12406/3, October 2017

क न द र य म ह व भ ग भ स द भ- स ए ड -III/16: IS न म बभ ग षय म ह- आई एस : 2003 क परभप लन ललए एस ट आई Doc: STI/12406/3, October 2017 क न द र य म ह व भ ग - III भ स द भ- स ए ड -III/16: IS 12406 07 न म बभ 2017 ग षय म ह- आई एस 12406 : 2003 क परभप लन ललए एस ट आई Doc: STI/12406/3, October 2017 इस उपर क त व षय क स दर भ ह सक षम प र ध क र न

More information

045 : 2000 CEB STANDARD

045 : 2000 CEB STANDARD 045 : 2000 CEB STANDARD LOW VOLTAGE FUSE SWITCH DISCONNECTOR CEYLON ELECTRICITY BOARD SRI LANKA Specification for LOW VOLTAGE FUSE SWITCH DISCONNECTOR CEB Standard 045 : 2000 CEYLON ELECTRICITY BOARD No.

More information

4. MARKING: Each cistern shall be provided with a label containing the following information or the information paper strip pasted to it.

4. MARKING: Each cistern shall be provided with a label containing the following information or the information paper strip pasted to it. SCHEME OF TESTING AND INSPECTION FOR CERTIFICATION OF PLASTIC FLUSHING CISTERNS FOR WATER CLOSETS AND URINALS (SECOND REVISION) ACCORDING TO IS: 7231-1994 1. LABORATORY: A testing laboratory shall be maintained

More information

MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING, URBAN DEVELOPMENT AND PUBLIC WORKS

MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING, URBAN DEVELOPMENT AND PUBLIC WORKS MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING, URBAN DEVELOPMENT AND PUBLIC WORKS STATE DEPARTMENT OF INFRASTRUCTURE KS 2295 IMPLEMENTATION GUIDELINE FOR LICENSING SPEED LIMITER SUPPLIERS 1. Preamble

More information

Understanding BS 1363 Amendment No.4

Understanding BS 1363 Amendment No.4 Intertek Hilton House, Corporation Street, Rugby, Warwickshire, CV21 2DN UK info.uk@intertek.com 01788 578435 www.intertek.com Introduction A new Amendment applying to several parts of the BS 1363 standard

More information

Appendix Item Addendum

Appendix Item Addendum Addendum to ESAH Version 3 Supply Application Appendix Item Addendum 1 Electrical System Item 1.4.5 Short Circuit Ratings Addendum for type of short circuit rating for system voltage of 275kV. 2 Types

More information

56-SDMS-07 REV. 01 SPECIFICATIONS FOR

56-SDMS-07 REV. 01 SPECIFICATIONS FOR 56-SDMS-07 REV. 01 SPECIFICATIONS FOR UNIT SUBSTATIONS UP TO 36 kv ALUMINUM TRANSFORMER ALUMINUM BUS BARS LVDP This specification is property of SEC and subject to change or modification without any notice

More information

Maximum temp. rise in oil by 40 thermometer above design ambient (deg C) specified time Short circuit rating (Sec) for As per IS 2026

Maximum temp. rise in oil by 40 thermometer above design ambient (deg C) specified time Short circuit rating (Sec) for As per IS 2026 TECHNICAL PERTICULAR FOR 1.6 MVA 6.6/0.433 KV SERVICE TRANSFORMER 1.00.00 GENERAL 1.01.00 Service SERVICE 1.02.00 Make ASHOK/VOLTAMP/DANKE/CGL 1.03.00 Type CORE 1.04.00 Location OUTDOOR 1.05.00 Specification

More information

Marina Bay Sands Guidelines for Electrical and Wiring Service

Marina Bay Sands Guidelines for Electrical and Wiring Service Marina Bay Sands Guidelines for Electrical and Wiring Service 1) The supply of electrical mains in the licensed area of the event is an exclusive service offered by Marina Bay Sands (MBS). In the event

More information

क न द र य म ह व भ ग भ स द भ- स ए ड -III/16: IS न म बभ ग षय म ह- आई एस : 1998 क परभप लन ललए एस ट आई Doc: STI/14587/3, October 2017

क न द र य म ह व भ ग भ स द भ- स ए ड -III/16: IS न म बभ ग षय म ह- आई एस : 1998 क परभप लन ललए एस ट आई Doc: STI/14587/3, October 2017 क न द र य म ह व भ ग - III भ स द भ- स ए ड -III/16: IS 14587 07 न म बभ 2017 ग षय म ह- आई एस 14587 : 1998 क परभप लन ललए एस ट आई Doc: STI/14587/3, October 2017 इस उपर क त व षय क स दर भ ह सक षम प र ध क र न

More information

ABB Transformers Egypt

ABB Transformers Egypt Kamel Elhamy, 2013 ABB Transformers Egypt Our transformers support the systems that keep our world running ABB January 31, 2012 Slide 1 Factory Information Key data 2012 Annual volume 40 MUSD Employees

More information

Amendment to Schedule 15 for Ballasts Electromagnetic & Electronic ballasts

Amendment to Schedule 15 for Ballasts Electromagnetic & Electronic ballasts Revision 1 Date: 28/01/2016 Amendment to Schedule 15 for Ballasts Electromagnetic & Electronic ballasts In the said schedule, (i) in paragraph 7, for sub-paragraph (i) the following shall be substituted,

More information

Technical Specifications

Technical Specifications LT Distribution Box Technical Specifications 1. SCOPE 1.1 This specification covers design, manufacture, testing at manufacturer works before dispatch and supply of L.T. Distribution Cabinet suitable for

More information

ST. VINCENT AND THE GRENADINES

ST. VINCENT AND THE GRENADINES ST. VINCENT AND THE GRENADINES MARITIME ADMINISTRATION CIRCULAR N POL 022 FUEL OIL CONSUMPTION DATA COLLECTION SYSTEM Amendments to MARPOL Annex VI, MEPC.278(70) TO: APPLICABLE TO: EFFECTIVE AS FROM: SHIPOWNERS,

More information

TECHNICAL SPECIFICATION FOR 11 KV DROP OUT (D.O.) FUSE with Polymeric Insulators:

TECHNICAL SPECIFICATION FOR 11 KV DROP OUT (D.O.) FUSE with Polymeric Insulators: TECHNICAL SPECIFICATION FOR 11 KV DROP OUT (D.O.) FUSE with Polymeric Insulators: (1) SCOPE: This specification covers outdoor, open, drop out expulsion type fuse cut outs suitable for installation in

More information

DEPARTMENT OF TRADE AND INDUSTRY NO APRIL 2016

DEPARTMENT OF TRADE AND INDUSTRY NO APRIL 2016 Trade and Industry, Department of/ Handel en Nywerheid, Departement van 438 National Regulator for Compulsory Specifications Act (5/2008): Amendments to the Compulsory Specification for Earth Leakage Protection

More information

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS Originated 1/85 Revised 6/95 Revised 6/02 Revised 11/05 Revised 4/08 Revised 11/09 Revised 1/12 Revised 11/12 Revised

More information

شركة كهرباء محافظة القدس المساهمة المحدودة

شركة كهرباء محافظة القدس المساهمة المحدودة Our Ref: Date: Messrs. Dear Sir, Tender 22/2017 (re-bidding) 11& 33Kv Fuse Cutouts and Links You are kindly requested to bid for supply and delivery (DDP) for the medium voltage overhead line accessories

More information

Technical Specification for 12kV and 24kV Powder Filled Fuse-Links and Fuse Holders

Technical Specification for 12kV and 24kV Powder Filled Fuse-Links and Fuse Holders Ergon Energy Corporation Limited Technical Specification for 12kV and 24kV Powder Filled Fuse-Links and Fuse Holders ETS12-01-01 Specification ETS12-01-01 Ver 3 Contents 1. Purpose and Scope... 1 2. References...

More information

A. Three-phase, oil filled self-cooled, padmounted transformers are installed outdoors on pads in the EWEB distribution system.

A. Three-phase, oil filled self-cooled, padmounted transformers are installed outdoors on pads in the EWEB distribution system. 1. APPLICATION A. Three-phase, oil filled self-cooled, padmounted transformers are installed outdoors on pads in the EWEB distribution system. 2. REFERENCE STANDARDS A. The transformers supplied shall

More information

: DGVCL/11KV D.O.FUSE/SPECIFICATION : : 11KV DROP OUT FUSE CUTOUTS :

: DGVCL/11KV D.O.FUSE/SPECIFICATION : : 11KV DROP OUT FUSE CUTOUTS : : DGVCL/11KV D.O.FUSE/SPECIFICATION : : 11KV DROP OUT FUSE CUTOUTS : FOREWORD : Even though 11KV Drop Cut Fuse Cut Outs are widely used for protection / isolation of distribution transformers, their quality

More information

Doc:TED 11(794)W 1 September 2012 Draft Standard Automotive Vehicles - Windscreen Wiping System for 3 Wheeler Vehicles - Specification

Doc:TED 11(794)W 1 September 2012 Draft Standard Automotive Vehicles - Windscreen Wiping System for 3 Wheeler Vehicles - Specification For Comments only Doc:TED 11(794)W 1 September 2012 Draft Standard Automotive Vehicles - Windscreen Wiping System for 3 Wheeler Vehicles - Specification Not to be reproduced without permission Last date

More information

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G.Road, Bangalore-560 001 Present: Shri M.R. Sreenivasa Murthy Chairman Shri H. D. Arun Kumar Shri D.B. Manival

More information

37-SDMS-04 SPECIFICATIONS FOR INTERFACE LOW VOLTAGE MAIN CIRCUIT BREAKERS

37-SDMS-04 SPECIFICATIONS FOR INTERFACE LOW VOLTAGE MAIN CIRCUIT BREAKERS SPECIFICATIONS FOR INTERFACE LOW VOLTAGE MAIN CIRCUIT BREAKERS This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Page 1.0 SCOPE 3 2.0 CROSS

More information

COMMISSION REGULATION (EU) / of XXX

COMMISSION REGULATION (EU) / of XXX EUROPEAN COMMISSION Brussels, XXX [ ](2018) XXX draft COMMISSION REGULATION (EU) / of XXX amending Regulation (EU) No 548/2014 of 21 May 2014 on implementing Directive 2009/125/EC of the European Parliament

More information

Certification Scheme

Certification Scheme Certification Scheme Water-based surface-embedded heating and cooling systems in accordance with DIN EN 1264 (Version: November 2009) DIN CERTCO Alboinstraße 56 12103 Berlin Tel: +49 30 7562-1131 Fax:

More information

REFERENCE CP_TSSPEC_138 0 DATE: JUNE 2006 PAGE: 1 OF 17 TITLE SPECIFICATION FOR POLE- MOUNTED AUTO-RECLOSERS TABLE OF CONTENTS

REFERENCE CP_TSSPEC_138 0 DATE: JUNE 2006 PAGE: 1 OF 17 TITLE SPECIFICATION FOR POLE- MOUNTED AUTO-RECLOSERS TABLE OF CONTENTS TITLE SPECIFICATION FOR POLE- MOUNTED DATE: JUNE 2006 PAGE: 1 OF 17 TABLE OF CONTENTS Page FOREWORD...2 INTRODUCTION...3 1 SCOPE...3 2 NORMATIVE S...3 3 DEFINITIONS AND ABBIATIONS...3 4 REQUIREMENTS...3

More information

CENTRAL MARKS DEPARTMENT II (Legal) Our Ref: CMD-II/16: July 2014

CENTRAL MARKS DEPARTMENT II (Legal) Our Ref: CMD-II/16: July 2014 CENTRAL MARKS DEPARTMENT II (Legal) Our Ref: CMD-II/16: 8034 21 July 2014 Subject: Implementation of Amendment No 3 December 2013 to IS 8034:2002 Submersible Pumpsets - Specification Amendment No 3 December

More information

2. TEST RECORDS - All records of tests, inspection and calibration shall be kept in suitable forms approved by the Bureau.

2. TEST RECORDS - All records of tests, inspection and calibration shall be kept in suitable forms approved by the Bureau. SCHEME OF TESTING AND INSPECTION FOR CERTIFICATION OF AUTOMOTIVE VEHICLES PNEUMATIC TYRES FOR PASSENGER CAR VECHICLES DIAGONAL AND RADIAL PLY ACCORDING TO IS 15633:2005 1. LABORATORY A laboratory shall

More information

MGVCL//11KV D.O.FUSE/SPECIFICATIONS -:11KV DROP OUT FUSE CUTOUTS:-

MGVCL//11KV D.O.FUSE/SPECIFICATIONS -:11KV DROP OUT FUSE CUTOUTS:- MGVCL//11KV D.O.FUSE/SPECIFICATIONS -:11KV DROP OUT FUSE CUTOUTS:- 01) SCOPE: This specification covers outdoor, open, drop out expulsion type fuse cut outs suitable for installation in 50Hz, 11KV distribution

More information

DOC: STI/10322(Part 5/Sec 3)/2, September 2016

DOC: STI/10322(Part 5/Sec 3)/2, September 2016 क न द र य म ह व भ ग 3 भ स द भ- क न द र य म ह व भ ग -3/16: आई एस IS 10322 5(Part /sec3) 04 अक त बभ 2016 ग षय म ह- आईएस IS 10322 5 (Part /sec3): 2012 क पवनभ क ष त एसट आई (एसट आई/10322 Part 5/Sec (3)/2, ससत

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

Amendment No th September 2016 To AIS 037: Procedure for Type Approval and Establishing Conformity of Production for Safety Critical Components

Amendment No th September 2016 To AIS 037: Procedure for Type Approval and Establishing Conformity of Production for Safety Critical Components Amendment No. 6 28 th September 2016 To AIS 037: Procedure for Type Approval and Establishing Conformity of Production for Safety Critical Components 1. Page 6/15, Clause 9.6.2 Substitute following text

More information

ABB Ltd. FACTORY IN HANOI

ABB Ltd. FACTORY IN HANOI ABB LTD. ABB Ltd. was originally a JVC between the Vietnamese Transformers Manufacture CTBT and the International Electromechanical group ABB Company was established 1st Sep. 1994 Distribution Transformers

More information

E/ECE/324/Rev.2/Add.102/Rev.1 E/ECE/TRANS/505/Rev.2/Add.102/Rev.1

E/ECE/324/Rev.2/Add.102/Rev.1 E/ECE/TRANS/505/Rev.2/Add.102/Rev.1 30 August 2011 Agreement Concerning the adoption of uniform technical prescriptions for wheeled vehicles, equipment and parts which can be fitted and/or be used on wheeled vehicles and the conditions for

More information

1ZSC AAA EN, REV. 7. Transformer bushings type GSBK Technical guide

1ZSC AAA EN, REV. 7. Transformer bushings type GSBK Technical guide 1ZSC563-AAA EN, REV. 7 Transformer bushings type GSBK Technical guide Original instruction The information provided in this document is intended to be general and does not cover all possible applications.

More information

TGK Prefabricated Substation Technical Data

TGK Prefabricated Substation Technical Data TGK Prefabricated Substation Technical Data Ref Item Data 1 General Technical 1.1 Frequency (Hz) 50 1.2 Transformer Rating (kva) 315/750 1.3 Transformer Primary Voltage (kv) 11 1.4 Transformer Secondary

More information

017: 1998 CEB STANDARD RING MAIN UNIT CEYLON ELECTRICITY BOARD SRI LANKA

017: 1998 CEB STANDARD RING MAIN UNIT CEYLON ELECTRICITY BOARD SRI LANKA 017: 1998 CEB STANDARD RING MAIN UNIT CEYLON ELECTRICITY BOARD SRI LANKA CONTENTS PAGE 1. Scope 2 2. System Parameters 2 3. Service Conditions 2 4. Applicable Standards 3 5. Basic Features 4 6. Quality

More information

TABLE OF CONTENTS FOREWORD...3 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS REQUIREMENTS...

TABLE OF CONTENTS FOREWORD...3 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS REQUIREMENTS... TITLE SPECIFICATION FOR PORTABLE DATE: JULY 2006 PAGE: 1 OF 25 TABLE OF CONTENTS Page FOREWORD...3 INTRODUCTION...4 1 SCOPE...4 2 NORMATIVE S...4 3 DEFINITIONS AND ABBIATIONS...4 4 REQUIREMENTS...5 4.1

More information

Bushings for High Voltage AC Applications

Bushings for High Voltage AC Applications Bushings for High Voltage AC Applications Selection guide 1ZSE 2750-100 en, Rev. 3, 2006-03-15 During selection of for high voltage applications several important factors have to be considered to ensure

More information

Power and Distribution Transformers

Power and Distribution Transformers Power and Distribution Transformers VRT Power Ltd. We Enable Energy VRT is a modern manufacturer for high-performance oil-immersed power transformers up to 800 MVA 500 kv. Customized design and the development

More information

abb SafeLink SF 6 Insulated Ring Main Unit Installation and Operating Instructions Switchgear Division Auckland, New Zealand SLMIO ver 2.

abb SafeLink SF 6 Insulated Ring Main Unit Installation and Operating Instructions Switchgear Division Auckland, New Zealand SLMIO ver 2. Installation and Operating Instructions Switchgear Division Auckland, New Zealand SLMIO ver 2.12 Product Overview ABB's type-tested ring main unit (RMU) is an SF 6 insulated RMU utilising the latest developments

More information

INDUSTRIAL HAUL AGREEMENT

INDUSTRIAL HAUL AGREEMENT INDUSTRIAL HAUL AGREEMENT PUBLIC WORKS MEMORANDUM OF AGREEMENT entered into this day of, A.D., 20(yr). BETWEEN: PARKLAND COUNTY a County incorporated under the laws of the Province of Alberta, (hereinafter

More information

Diesel Exhaust Fluid Certification Program Overview FEBRUARY 2009 REVISION 01

Diesel Exhaust Fluid Certification Program Overview FEBRUARY 2009 REVISION 01 Diesel Exhaust Fluid Certification Program Overview Foreword This overview describes the voluntary and is intended to explain to marketers how the API Diesel Exhaust Fluid Certification Mark is licensed

More information

Draft Indian Standard FUSIBLE PLUG FOR DISSOLVED ACETYLENE GAS CYLINDER SPECIFICATION (first revision of IS 13497) (ICS )

Draft Indian Standard FUSIBLE PLUG FOR DISSOLVED ACETYLENE GAS CYLINDER SPECIFICATION (first revision of IS 13497) (ICS ) DRAFT STANDARD IN WIDE CIRCULATION DOCUMENT DESPATCH ADVICE Ref: MED 16 :3/T- 14 Date: 06-01-2015 Gas Cylinders, Sectional Committee, MED 16 TO: a) The interested members of Mechanical Engineering Division

More information

ANNEX 3. RESOLUTION MEPC.278(70) (Adopted on 28 October 2016)

ANNEX 3. RESOLUTION MEPC.278(70) (Adopted on 28 October 2016) Annex 3, page 1 ANNEX 3 RESOLUTION MEPC.278(70) (Adopted on 28 October 2016) AMENDMENTS TO THE ANNEX OF THE PROTOCOL OF 1997 TO AMEND THE INTERNATIONAL CONVENTION FOR THE PREVENTION OF POLLUTION FROM SHIPS,

More information

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS Originated 1/85 Revised 6/95 Revised 6/02 Revised 11/05 Revised 4/08 Revised 11/09 Revised 1/12 Revised 11/12 Revised

More information

2. TEST RECORDS: All records of tests, inspection and calibration shall be kept in suitable forms approved by the Bureau.

2. TEST RECORDS: All records of tests, inspection and calibration shall be kept in suitable forms approved by the Bureau. SCHEME FOR TESTING AND INSPECTION FOR CERTIFICATION OF DOMESTIC GAS STOVE FOR USE WITH LIQUIFIED PETROLEUM GASES ACCORDING TO IS 4246:2002 (FIFTH REVISION) 1. LABORATORY: A laboratory shall be maintained

More information

Principle Decision by the Central Experience Exchange Circle of the Notified Bodies and the GS Bodies according to the Product Safety Act ZEK

Principle Decision by the Central Experience Exchange Circle of the Notified Bodies and the GS Bodies according to the Product Safety Act ZEK -GB-2017-01: Defining the requirements for a GS mark approval Principle Decision by the Central Experience Exchange Circle of the Notified Bodies and the GS Bodies according to the Product Safety Act about

More information

TECHNICAL SPECIFICATIONS FOR LT DISTRIBUTION BOX MADE FROM THERMOSETTING PLASTIC HAVING 200 /400 AMP CAPACITY.

TECHNICAL SPECIFICATIONS FOR LT DISTRIBUTION BOX MADE FROM THERMOSETTING PLASTIC HAVING 200 /400 AMP CAPACITY. TECHNICAL SPECIFICATIONS FOR LT DISTRIBUTION BOX MADE FROM THERMOSETTING PLASTIC HAVING 200 /400 AMP CAPACITY. 1.0 SCOPE: This specification covers the design, manufacturing and testing of LT Distribution

More information

CAST RESIN DISTRIBUTION TRANSFORMERS 2016 EDITION

CAST RESIN DISTRIBUTION TRANSFORMERS 2016 EDITION CAST RESIN DISTRIBUTION TRANSFORMERS 2016 EDITION TMC TRANSFORMERS - GLOBAL NETWORK UK & IRELAND SPAIN NORTH AMERICA & CANADA GERMANY SWITZERLAND BENELUX & AUSTRIA ITALY POLAND INDIA CENTRAL & SOUTH AMERICA

More information

Marking Fee for IS 636:1988 Non-percolating Flexible Delivery Hose for Fire Fighting

Marking Fee for IS 636:1988 Non-percolating Flexible Delivery Hose for Fire Fighting Marking Fee for IS 636:1988 Non-percolating Flexible Delivery Hose for Fire Fighting Description Value Unit 100 METRE L S Marking Fee 34000 S S Marking Fee 29000 Slab 1 Rate 17.3 Slab 1 Qty All Enforcement

More information

Technical Specification

Technical Specification Section - 7 Technical Specification OF 33KV OUTDOOR DROP OUT FUSE CUT-OUT AND FUSE LINK AND 33KV OUTDOOR TYPE SINGLE PHASE METAL OXIDE (ZNO) GAPLESS LIGHTNING ARRESTER 84 7.1. TECHNICAL SPECIFICATION OF

More information

Generating unit functional document submission form

Generating unit functional document submission form Generating unit functional document submission form The below form must be completed and returned to generator.reports@aeso.ca. Supporting information to assist generating unit owners to complete this

More information

Electrical District No. 3 SOLAR Q & A

Electrical District No. 3 SOLAR Q & A D3 Electrical District No. 3 SOLAR Q & A What are some things I should consider before going solar? Leasing verses owning: Know the Pros and Cons of each, as well as the Short-term and Long-Term effects

More information

Microgeneration Installation Standard: MCS

Microgeneration Installation Standard: MCS Microgeneration Installation Standard: MCS 001-01 MCS Contractor Certification Scheme Requirements Part 1: Requirements for MCS Contractors Issue 3.1 This Microgeneration Installation Standard is the property

More information

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: Alternative Contact Information

More information

IMO fuel oil consumption data collection system

IMO fuel oil consumption data collection system No. Subject: IMO fuel oil consumption data collection system IMO fuel oil consumption data collection system A similar scheme to EU MRV has also been adopted by IMO; according to Regulation 22A of MARPOL

More information

SFI SPECIFICATION 35.2 EFFECTIVE: DECEMBER 29, 2014 *

SFI SPECIFICATION 35.2 EFFECTIVE: DECEMBER 29, 2014 * SFI SPECIFICATION 35.2 EFFECTIVE: DECEMBER 29, 2014 * PRODUCT: Heavy Duty Stock Car Steel Wheels 1.0 GENERAL INFORMATION 1.1 This SFI Specification establishes uniform test procedures and minimum standards

More information

INTER PLANT STANDARD STEEL INDUSTRY SPECIFICATION FOR STATIC EXCITATION CONVERTORS FOR SYNCHRONOUS MOTORS (FIRST REVISION)

INTER PLANT STANDARD STEEL INDUSTRY SPECIFICATION FOR STATIC EXCITATION CONVERTORS FOR SYNCHRONOUS MOTORS (FIRST REVISION) INTER PLANT STANDARD STEEL INDUSTRY I P S S SPECIFICATION FOR STATIC EXCITATION CONVERTORS FOR SYNCHRONOUS MOTORS (FIRST REVISION) Corresponding IS does not exist IPSS: 1-10-036-12 0 FOREWORD 0.1 This

More information

E/ECE/324/Rev.2/Add.108/Rev.1/Amend.3 E/ECE/TRANS/505/Rev.2/Add.108/Rev.1/Amend.3

E/ECE/324/Rev.2/Add.108/Rev.1/Amend.3 E/ECE/TRANS/505/Rev.2/Add.108/Rev.1/Amend.3 16 January 2019 Agreement Concerning the Adoption of Harmonized Technical United Nations Regulations for Wheeled Vehicles, Equipment and Parts which can be Fitted and/or be Used on Wheeled Vehicles and

More information

Amendment No August, 2015 To AIS-037 Procedure for Type Approval and Establishing Conformity of Production for Safety Critical Components

Amendment No August, 2015 To AIS-037 Procedure for Type Approval and Establishing Conformity of Production for Safety Critical Components Amendment No. 5 19 August, 2015 To AIS-037 Procedure for Type Approval and Establishing Conformity of Production for Safety Critical Components 1. Page No. 6/15, Clause 9.1 At the end of clause 9.1, insert

More information

34-SDMS-02 SPECIFICATIONS FOR

34-SDMS-02 SPECIFICATIONS FOR SPECIFICATIONS FOR M V & L V FUSE LINKS This specification is property of SEC and subject to change or modification without any notice TABLE OF CONTENTS 1.0 SCOPE 3 2.0 CROSS REFERENCES 3 3.0 APPLICABLE

More information