NY5 Bus Rapid Transit Conceptual Design Study. Deliverable Q Implementation Phasing Plan

Size: px
Start display at page:

Download "NY5 Bus Rapid Transit Conceptual Design Study. Deliverable Q Implementation Phasing Plan"

Transcription

1 Capital District Transportation Committee Capital District Transportation Authority NY5 Bus Rapid Transit Conceptual Design Study Deliverable Q Implementation Phasing Plan with CREIGHTON MANNING ENGINEERING Logitrans Herbert Levinson January, 2005

2 1 Introduction This report presents a preliminary phasing plan for the proposed services that are discussed in further detail in other deliverables. The BRT service described in those deliverables represents full implementation of the BRT concept, a process that would take several years. This document presents a phasing plan for BRT in the New York Route 5 corridor so that the critical elements of the BRT service can be in place as soon as possible. First, all of the elements associated with the BRT system are identified along with their capital costs. Phase I is then defined as those critical elements that would constitute a BRT application. Because the BRT concept represents a flexible package of features that have been applied in various combinations in North America and around the world, it is necessary to define what would constitute BRT in the Route 5 corridor. Phase II includes other elements that would further enhance the operations of the BRT system but are not critical to begin operations. Phase III includes those elements that have potential to enhance the system but that for particular reasons in this case, could be delayed for longer term implementation without hampering the success of the system. Finally, a matrix identifies the organizations responsible for the implementation of each element as well as other parties that should be involved because they will be affected by the changes. As with all previous deliverables and reports, none of the investments described here represent final decisions on the part of CDTA or any of the other interested parties. Such decisions will be made during Phase 2 of the Design Study preliminary engineering and in accordance with the Transit Development Plan that is being conducted by CDTA. Thus, although this document presents specific information regarding the phasing plan and the cost of its implementation, this information is subject to change upon further study and review in the context of the Transit Development Plan. 2

3 2 BRT Elements and Costs Three types of elements can be found in the proposed BRT system: capital (infrastructure), operations (services), and system (support systems and management) elements. The specific elements examined in this conceptual design study can be grouped into these three categories as follows: Capital Stations shelters and other amenities Roadway improvements queue jumpers, bulbouts, and improvements at Colonie Center Vehicles retrofitting existing vehicles or acquiring new vehicles Park-and-Ride facilities Operations Mainline services BRT express, Local route, revised Route 1 Feeder routes System AVL/GPS/Communication systems Transit Signal Priority Off-vehicle fare collection Marketing and Promotion 2.1 Capital elements Stations The stations are described in detail in Deliverable H/K. Table 1 shows the costs estimated for the stations including amenities, bulbouts, site costs, and traffic management during construction. Note that not all amenities are recommended for all locations. For example, since the areas around Broadway Street and North Robinson Street in Schenectady have recently been renovated, new sidewalks are not proposed for these locations in the short term. There are four possible types of shelters : small, medium, large, and transfer station. The transfer station is a large shelter (at least 12 ft. by 30 ft.) with added amenities. Although five stations have been identified as transfer stations (i.e. Washington, New Karner, Colonie Center, Colvin, and Lark) only Colonie Center and New Karner are planned to receive new transfer shelters. Lark Street westbound and Washington Street eastbound already have substantial shelters that are not recommended to be replaced by new BRT shelters and the level of investment of a large shelter is considered sufficient for the shelter at Colvin station. The resulting figures in the table are the cost per station and the total cost for all stations. 3

4 Table 1 Station costs ITEM COSTS STATION Initial Contin gency Design Final Cost & Engine ering Washington EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB Boardings [boarding passengers per weekday] Small Shelter (~7' x 12')* $20,000 10% 10% $24, Medium Shelter (~12' x 18')* $25,000 10% 10% $30, Large Shelter (~12' x 30')* $30,000 10% 10% $36,000 1 Transfer Shelter (~ 25' x 50') $80,000 20% 15% $108, Station sign $1,000 10% 10% $1, Renovated sidewalks (a) $37,500 20% 15% $50, Pedestrian lighting $6,000 20% 15% $8, Benches ^ $400 5% 5% $ Trash receptacles $400 5% 5% $ Newspaper boxes $500 5% 5% $ Real-time next bus info (b) $5,000 20% 15% $6, Broadway 1 Static system information $500 5% 15% $ Map of the area $1,500 5% 15% $1, Bike racks Regular $800 5% 5% $ Bike racks Large (c) $3,000 20% 10% $3, Public Phones $1,600 5% 5% $1, Emergency Phones $600 5% 5% $ Bulletin boards $500 5% 15% $ Vending machines (d) $0 1 Security camera/cc TV $4,000 10% 10% $4, Restrooms $20,000 20% 10% $26,000 Bulbouts (e) $7,500 20% 15% $10,125 Site costs $30,000 20% 15% $40, Traffic management $20,000 20% 15% $27, Total cost of stations $6,352,255 $247,180 $30,810 $128,070 $345,450 $355,350 $224,980 $336,430 $342,430 $509,670 $336,430 ITEM COSTS STATION Initial Contin gency Final Cost Design & Engine ering Veeder/Nott Steuben McClellan EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB Boardings [boarding passengers per weekday] Small Shelter (~7' x 12')* $20,000 10% 10% $24,000 1 Medium Shelter (~12' x 18')* $25,000 10% 10% $30, Large Shelter (~12' x 30')* $30,000 10% 10% $36, Transfer Shelter (~ 25' x 50') $80,000 20% 15% $108, Station sign $1,000 10% 10% $1, Renovated sidewalks (a) $37,500 20% 15% $50, Pedestrian lighting $6,000 20% 15% $8, Benches ^ $400 5% 5% $ Trash receptacles $400 5% 5% $ Newspaper boxes $500 5% 5% $ Real-time next bus info (b) $5,000 20% 15% $6, Static system information $500 5% 15% $ Map of the area $1,500 5% 15% $1, Bike racks Regular $800 5% 5% $ Bike racks Large (c) $3,000 20% 10% $3,900 Public Phones $1,600 5% 5% $1, Emergency Phones $600 5% 5% $ Bulletin boards $500 5% 15% $ Vending machines (d) $ Security camera/cc TV $4,000 10% 10% $4, Restrooms $20,000 20% 10% $26, Bulbouts (e) $7,500 20% 15% $10, Site costs $30,000 20% 15% $40, Traffic management $20,000 20% 15% $27, Total cost of stations $6,352,255 $566,910 $370,470 $359,435 $358,995 $381,560 $369,560 $266,735 $353,670 $239,680 $228,440 Notes * Small shelter if boardings are less than or equal to 50, Medium shelter if boardings are betw een 51 and 199, Large shelter if boardings are more than or equal to 200 ^ 1 bench if boardings are less than 100, 2 benches if boardings are more than or equal to 100 a) Assumed on average 100 ft x 15 ft of area at a cost of $25/sq ft b) Cost of electronic sign/monitor, assumes that capital costs to provide real-time information are included in AVL system purchased by CDTA c) Weather protection prov ided for bikes d) No cost to CDTA for full-service vending. Service is dependent on vending company 's assessment of security and potential demand at the desired location. e) Assumed on average 50 ft x 6 ft of area at a cost of $25/ft Colonie Center Colvin N. Allen N. Manning Quail N. Robinson Lexington Lawnwood Lark Balltown S. Swan New Karner Pearl V. of Colonie SUNY 1 2 4

5 The station costs vary from $30,800 at Broadway where recent renovation of the sidewalks and existing shelters make unnecessary the implementation of several amenities proposed for the BRT stations to $567,000 at Colonie Center, which includes the construction of a significant transfer station in each direction and the provision of extra amenities such as restrooms. The total cost for the stations is approximately $6,352,000. This total cost will be allocated into implementation phases in section 3 of this report Roadway Improvements The proposed roadway improvements include two queue jumpers, seven bulbouts, and roadway changes to introduce the new transfer station at Colonie Center Queue jumpers A queue jumper is a short exclusive bus lane leading to a congested intersection which allows a bus to jump to the head of the queue and make it through the intersection ahead of the rest of the traffic. A few seconds of advance green time, provided by Transit Signal Priority equipment, would allow the bus to lead the platoon of traffic through the intersection, rather than being caught behind the rest of the traffic. A queue jumper can save an entire traffic light cycle for a bus at a congested intersection, leading to a potential travel time savings of 2 to 3 minutes. Two queue jumpers are proposed westbound on ROUTE 5, one at the Wolf Road intersection and one at the New Karner Road intersection. These queue jumpers and their costs are described in further detail in Deliverables L/M and I/J. The cost estimate resulted in $455,000 for the Wolf Road queue jumper and $420,000 for the New Karner Road queue jumper both figures include right-of-way costs. A shorter version of the New Karner Road queue jumper has also been studied at a lower cost including right-ofway, in case problems arise with the land acquisition and engineering design for the longer and more desirable alternative. These costs may be higher due to potential environmental remediation to the sites Bulbouts Seven bulbouts are proposed along the ROUTE 5 corridor; all of them are located in Albany between North Allen Street and Lark Street. These bulbouts were proposed where the narrow sidewalks do not provide sufficient space to hold the BRT shelters and the buses would benefit from not leaving the travel lanes to stop at the stations. In all cases, there are existing parking lanes that protect the bulbout and an extra traffic lane in the same direction to avoid a complete blockage of the street while the bus is at the station. The proposed locations are: North Allen, eastbound North Manning, eastbound Quail, eastbound and westbound Lexington, eastbound and westbound Lark, westbound 5

6 The bulbouts were estimated at an average of 50 feet long and 6 feet wide with a cost of $25 per square foot, for a total cost per bulbout of $7,500. A 20% contingency and a 15% Design and Engineering cost were added to estimate the final costs of the bulbouts at $71,000. These costs are embedded in the cost of the stations presented in the previous table Improvements at Colonie Center Two alternatives were studied at the Colonie Center station and are discussed in Deliverable L/M. The first alternative considers one bi-directional station on the northern side of ROUTE 5 and the second alternative considers two uni-directional stations, one at each side of the route. For the purpose of this phasing plan, the latter alternative has been assumed, primarily because the travel time penalty imposed to through customers in the former alternative (two to three minutes) was considered too high and it would not outweigh the convenience of only one transfer station. In the preliminary engineering phase of this study, more detailed data should be collected to study the pattern of the riders at this location to determine whether the preponderance of bus riders using the Colonie Center stop are destined to Colonie Center. If indeed many more riders are going to Colonie Center than Northway Mall, this issue may be revisited, though the time penalty to through riders will still be the most important consideration. For the uni-directional stations, two alternatives were also studied. The first one considers the vehicles stopping in a bus lane, which allows the stations to be offset with respect to one another and leaves space for a mid-block crosswalk. In this layout, there would still be two travel lanes in each direction for general traffic. The second layout proposes bus bays for the vehicles with the stations practically facing each other, which provides a better visual connection between the two sides of the street but to some extent encourages jay walking because no mid-block crosswalk could be provided. The estimated cost for the improvements required to build the two uni-directional stations is $268,000 for the first alternative and $98,000 for the second alternative, including right-of-way costs in both cases. The first alternative is assumed for the purpose of this phasing plan primarily because of the possibilities for improved pedestrian accommodations. For reference, the estimated cost for the improvements required to build the bi-directional station is $415,000, including right-of-way. None of these costs include the cost of the physical station structure itself, just the roadway costs Downtown Albany Bus Lanes Deliverable L/M discusses various options for exclusive bus lanes in downtown Albany. At this point in the process, no decision has been made on the feasibility of this potential element of the BRT system. Because of the large uncertainty involved, no cost estimate for such a facility is provided here. It is recommended that the concept be further studied for possible implementation in the longer term Vehicles In a BRT system, the buses, along with the stations, represent a key opportunity to convey a desired image and standard of service to users. Upgrading to newer and appealing buses is usually recommended when implementing a BRT route. This however, could be very expensive, as each new 40-foot bus with a more stylish and environmentfriendly design costs around $450,000. An alternative to replacing the fleet specifically 6

7 for the BRT route is to retrofit the buses with an exterior paint scheme that matches the brand design of the BRT system at an estimated cost of $5,000 per bus. In the case of CDTA, which has well-maintained and relatively new buses in its fleet, operations could start with the newest buses in the existing fleet, but it is recommended to acquire new vehicles that fit the BRT brand image at some point during Phase I. Operations of the feeder routes could also start with the existing mini-buses painted with the BRT paint-scheme approximately $3,000 for each mini-bus. Later, when the minibuses need replacement due to normal wear and tear, new vehicles can be acquired specifically for the BRT system. An average of $200,000 was estimated for new minibuses for the feeder routes. The BRT operations plan requires 10 full-size buses for the BRT express route and 21 minibuses for the feeder routes. With a standard 20% spare ratio, the total cost for new buses would be $5.4 million for the full-size buses and $5 million for the minibuses. The repainting could be accomplished for $60,000 for the full-size buses and $75,000 for the minibuses Park-and-Ride facilities One of the goals of introducing a fast, high-performance transit service to the Route 5 corridor is to bring new riders onto the system. One of the ways to improve access to the transit system is to provide park-and-ride spaces at the proposed BRT stations. In this way, people who do not live along the Route 5 corridor but who work along the corridor, particularly in downtown Albany where parking is at a premium, can drive to a station and use the BRT to reach their destination. Assuming that 10% of the expected ridership in the corridor will access the services using park-and-ride spaces, approximately 1,250 spaces are required along the corridor. These spaces are to be distributed among several stations identified in Deliverable H/K as desirable locations to introduce park-and-ride. The provision of spaces can usually be done through leasing and agreements with current owners of parking lots near the stations or through acquisition of land and construction of the facilities. The cost per space for the first option is approximately $2,000. Providing park-and-ride spaces through land acquisition and construction costs approximately $6,000 per space. While improving access to the BRT service is important, and the park-and-ride spaces must be built in a location convenient to the station, the provision of such spaces should not override the goal of improving land use in the ROUTE 5 corridor, particularly in the immediate vicinity of the stations. Thus, care must be taken in the design phase to ensure that a park-and-ride lot does not preclude a comfortable and lively pedestrian environment at the stations. 2.2 Operation Elements The operation elements of the BRT system are the actual routes. The capital costs to support this operation are described under the capital and system elements. The services 7

8 themselves will generate operational and maintenance costs, which are described in Deliverable F Annual Operating Costs and result in a total a net cost of $1.8 million per year. It is desirable for all services to start operations in Phase I; however if there are constraints from an operational cost standpoint, the feeder services could be delayed into a second phase. 2.3 System Elements AVL/GPS/Communication systems An AVL/GPS/Communication System has already been procured, purchased, and is under implementation by CDTA. This system will have the capabilities of providing the BRT service with real-time information about the operations to relay to the customers and use in the control center to improve the performance of the service. This system will also provide the support necessary to the Transit Signal Priority system Transit Signal Priority (TSP) A TSP system is also currently being implemented. That system, however, does not cover the entire ROUTE 5 corridor between SUNY and Washington stations; only 35 intersections are included in the current project. It was estimated that an extra $520,000 would be necessary to expand the TSP system to the entire corridor covering an additional 40 intersections. It is desirable to make this expansion all at once during the first implementation phase of the BRT project; however, in case there are budget constraints, the expansion could be performed in phases, giving priority to the most congested segments downtown Albany to Colonie Center, and downtown Schenectady. The segment between Colonie Center and Schenectady (Lawnwood Avenue) could be delayed for a second phase Off-vehicle fare collection Off-vehicle fare collection is a desired element in mass transit systems to decrease the boarding and alighting times and their variability. However, its implementation is expensive due to the hardware, software, and infrastructure involved. Two main alternatives to achieve off-vehicle fare collection were discussed in this project, closed stations and proof-of-payment. The latter was recommended due mainly to the high infrastructure and space requirements of the former. To implement proof-ofpayment, Ticket Vending Machines (TVM) must be deployed at least at all station locations sometimes extra TVMs are placed at popular locations such as supermarkets, office complexes, etc. and a control strategy must be put in place, typically random onboard checks. Although highly desirable, this element is expensive and it is most costeffective at places with very high ridership per station. Thus, based on cost constraints and the impact that this element may have on the actual boarding times in the corridor, the implementation of off-vehicle fare collection was recommended to be delayed to later phases of the implementation. The cost of each TVM is approximately $35,000, however if software and support costs are included, this cost per TVM increases to approximately $60,000. The total number of 8

9 TVMs for the BRT stations was estimated based on the expected ridership at each location as follows: Locations with less than 100 boardings per day are assigned 1 TVM Locations with 100 to 250 boardings per day are assigned 2 TVMs Locations with more than 250 boardings per day are assigned 3 TVMs The last stops in each direction (Washington westbound and SUNY eastbound) do not have TVMs Based on this criterion, a total of 63 TVMs are required to cover the 20 stations on the BRT express service for a total cost of $3,780, Marketing and Promotion Brand Image Marketing and promotion of the new service should accompany its implementation. This element is critical to establish the BRT brand on the market and ensure its recognition and interest by potential passengers. Including various elements of the system in the branding effort helps to convey an identity for the BRT system, making it easier for users and the public at large to recognize it and feel at ease when using it. The branding design of the system should include: - Graphic image (color scheme and logo to be used in other elements) - Short statement that characterizes the service (to be used in printed and audio information) - Signage and way-finding design using the graphic image which includes station name signs, hand-out maps, maps of the system, maps of the area, signs on the bus, and other signs at stations (i.e. restrooms, exit, crosswalk, feeder bus, etc) - Graphic image applied to vehicles, stations, fare collection media, and any other elements used for marketing (i.e. flyers, commercials, etc) Often, the marketing campaign to start this type of service includes: - Flyers for current users of the CDTA system - Flyers for the public at large - Flyers for neighboring communities (with information targeted to their nearest stop) - Public open houses with information in different communities - Newspaper and TV news articles - Audio commercials for local radio stations - TV commercials for local channels - Display of new buses on the route - Free rides on weekends previous to live operations to familiarize passengers with new system The costs of the branding design and marketing campaign vary greatly depending on the scale of the effort and they should be determined according to CDTA s knowledge of its market and budget. In terms of implementation schedule, this element should begin several months before the service starts operation but after critical decisions have been made (i.e. stations locations, bus frequencies, etc) to avoid providing information to the public that could change later. 9

10 3 Phasing Plan Based on the discussion of each element provided in the previous section, an analysis was conducted to determine which elements would be a priority, desirable, or not a priority for short, medium and long term implementation. The summary of this analysis is presented in Table 2. Element Stations Bulbouts Table 2 Short, Medium and Long Term Priorities for BRT Elements Short term 1 3 years (Phase I) (establish 20- station BRT service using existing shelters, begin construction) (with station construction) Medium term 4 6 years (Phase II) (complete construction of formal stations with unified design) (completed with station construction) Queue Jumpers Desirable Improvements at Colonie Center Vehicles Park and Ride facilities (capital leases) (additional capital leases) Long-term 7 10 years (Phase III) (construction) Mainline services Feeder routes Desirable AVL/GPS Under implementation TSP Under implementation Off-vehicle fare collection No Desirable Marketing and Promotion It is the conclusion of this conceptual design study that the essential capital and system elements to support the BRT operations are the following, in descending order of importance: Clearly identifiable stations with a rich set of amenities Brand image applied to vehicles and signage New vehicles Transit signal priority At least one queue jumper Park and ride spaces Implementation of these six elements in Phase I would allow the limited-stop BRT express service to be operated efficiently with a significant travel time advantage over the local service and without the customer confusion and complaints that arose with past efforts at limited-stop service in the corridor. If budget constraints arise, delaying the park-and-ride spaces would be recommended, which would not hold up the operations of 10

11 the BRT express service. The following sections provide more detail on the contents of the three recommended implementation phases. 3.1 Phase I (1 to 3 years) The immediate term phase would consist of as many of the six elements, mentioned above, that could be funded. The preliminary phasing plan estimates that the total cost of Phase I would be $12.0 million. Its implementation within the next three years would allow the BRT, as described in the study s Operating Plan, to be put into service. The primary new element of this plan is the BRT express route itself, but there are related changes to other routes in the corridor that will be further considered in the context of CDTA s Transit Development Plan. The BRT stations, brand image, vehicles, signal priority, a queue jumper, and park and ride spaces will provide a visible and distinctive service in the Capital District. This service will improve the overall image of transit and increase ridership. It will also provide a solid foundation for further implementation in later phases Stations It is recommended that at least some treatment be provided in all locations during Phase I to establish the 20-station BRT service. Lawnwood and Village of Colonie (Locust Street) stations would be the stations receiving the least investment in Phase I. These two stations were forecast to have much lower ridership than the other stations and depend to a much greater extent on new development to spur new ridership. Each of the 20 stations would be outfitted with the following: Shelter Static system information Station sign Map of the area Renovated sidewalks Bike rack Pedestrian lighting Emergency phone Benches Bulletin board Trash receptacles Vending machines (transfer stations Newspaper boxes only) Real-time next bus information sign However, there will be some exceptions: Public phones are recommended to be delayed at all stations except for Washington, New Karner, Colonie Center, Colvin, and Lark (the transfer stations) Renovated sidewalks and pedestrian lighting are recommended to be delayed at the five inner stations in Albany (Lexington through SUNY) since these locations already have adequate pedestrian environments. For Lawnwood and Village of Colonie it is recommended to start operations in Phase I with the station sign, pedestrian lighting, real-time next bus information, static system information, and map of the area. The rest of the amenities would be added during Phase II. 11

12 The estimated cost for implementation of all of the above, including site costs, traffic management costs during construction, design, engineering, and contingency, is approximately $4.9 million as shown in Table 3. The highlighted cells in the table represent those items that have been delayed to Phase II. Table 3 Phase I station amenities and costs PHASE I ITEM COSTS STATION Initial Contin gency Design & Engine ering Final Cost Washington Broadway EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB Boardings [boarding passengers per weekday] Small Shelter (~7' x 12')* $20,000 10% 10% $24, Medium Shelter (~12' x 18')* $25,000 10% 10% $30, Large Shelter (~12' x 30')* $30,000 10% 10% $36,000 Transfer Shelter (~ 25' x 50') $80,000 20% 15% $108, Station sign $1,000 10% 10% $1, Renovated sidewalks (a) $37,500 20% 15% $50, Pedestrian lighting $6,000 20% 15% $8, Benches ^ $400 5% 5% $ Trash receptacles $400 5% 5% $ Newspaper boxes $500 5% 5% $ Real-time next bus info (b) $5,000 20% 15% $6, Static system information $500 5% 15% $ Map of the area $1,500 5% 15% $1, Bike racks Regular $800 5% 5% $ Bike racks Large (c) $3,000 20% 10% $3, Public Phones $1,600 5% 5% $1, Emergency Phones $600 5% 5% $ Bulletin boards $500 5% 15% $ Vending machines (d) $0 0% 0% $0 1 Security camera/cc TV $4,000 10% 10% $4,800 Restrooms $20,000 20% 10% $26,000 Bulbouts $7,500 20% 15% $10,125 Site costs $30,000 20% 15% $40, Traffic management $20,000 20% 15% $27, Total $4,878,805 $137,120 $17,690 $124,550 $338,410 $348,310 $217,940 $36,900 $335,390 $501,350 $36,900 PHASE I ITEM COSTS STATION Initial Contin gency Design & Engine ering Final Cost Colonie Center Colvin EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB EB WB Boardings [boarding passengers per weekday] Small Shelter (~7' x 12')* $20,000 10% 10% $24,000 1 Medium Shelter (~12' x 18')* $25,000 10% 10% $30, Large Shelter (~12' x 30')* $30,000 10% 10% $36, Transfer Shelter (~ 25' x 50') $80,000 20% 15% $108, Station sign $1,000 10% 10% $1, Renovated sidewalks (a) $37,500 20% 15% $50, Pedestrian lighting $6,000 20% 15% $8, Benches ^ $400 5% 5% $ Trash receptacles $400 5% 5% $ Newspaper boxes $500 5% 5% $ Real-time next bus info (b) $5,000 20% 15% $6, Static system information $500 5% 15% $ Map of the area $1,500 5% 15% $1, Bike racks Regular $800 5% 5% $ Bike racks Large (c) $3,000 20% 10% $3,900 Public Phones $1,600 5% 5% $1, Emergency Phones $600 5% 5% $ Bulletin boards $500 5% 15% $ Vending machines (d) $0 0% 0% $ Security camera/cc TV $4,000 10% 10% $4,800 Restrooms $20,000 20% 10% $26,000 Bulbouts $7,500 20% 15% $10, Site costs $30,000 20% 15% $40, Traffic management $20,000 20% 15% $27, Total $4,878,805 $501,790 $357,350 $352,395 $351,955 $374,520 $245,070 $139,205 $224,380 $122,010 $115,570 Veeder/Nott N. Allen Steuben N. Manning McClellan Quail N. Robinson Lexington Lawnwood Lark Balltown S. Swan New Karner Pearl V. of Colonie SUNY 12

13 3.1.2 Brand Image and Vehicles In order for riders to be able to identify BRT vehicles and stations, and to recognize the difference between them and local services, a separate and distinctive BRT brand must be developed. For Phase I implementation, it is recommended to apply this brand to all station signs and BRT vehicles. In Phase I, it is assumed that a group of 10 to 12 vehicles will be acquired to operate the BRT express service. Ten buses are needed to operate the BRT express route up to 2 additional buses would be spares to replace any bus that needs to go out of service for repairs. The cost for 12 new buses would be $5.4 million Transit Signal Priority The NY 5 corridor is currently being outfitted with transit signal priority (TSP) equipment at 35 intersections. The BRT Conceptual Design Study recommends that all intersections in the corridor ultimately be equipped with TSP. It is recommended to implement full TSP in the corridor in the Phase I period. Thus an additional 40 intersections will be outfitted with TSP in the first 1 to 3 years of the project. The cost of adding TSP to these intersections is estimated to be $520, Queue Jumper In Phase I, it is recommended to implement a queue jumper at the Central Avenue/Wolf Road intersection in the westbound direction. The Roadway Priority Treatments report provides a significant amount of detail on this intersection, including two alternatives for how to implement the queue jumper. In conjunction with roadway alterations at the proposed Colonie Center BRT station (estimated at $270,000), this queue jumper will provide substantial travel time benefits for the BRT service. This location also provides high visibility for the BRT, helping to raise awareness of the improved transit service. The estimated cost of implementing the queue jumper at Wolf Road, including the construction of a new right-turn lane, is $455,000. This project will serve as a prototype for future queue jumpers in the corridor and along other state highways in New York Park and Ride Within Phase I, it is recommended to provide up to 250 park-and-ride spaces, some 20% of the ultimate total. Due to the lower cost and faster implementation of the capital leasing alternative over land acquisition and construction, it is recommended that the Phase I spaces are provided through the former. The estimated cost of providing these spaces through capital leasing ($2,000 per space) is $500,000. These spaces should be built/leased at the following stations, in descending order of importance: Balltown Colonie Center Washington (Travel Center in Schenectady) North Allen McClellan 13

14 3.2 Phase II (4 to 6 years) After the initial implementation of BRT in Phase I, the second implementation phase will include further investments in all six of the essential components. The total estimated cost for Phase II is $3.5 million. The expenditures for the individual elements in Phase II are described below. Stations All of the rest of the station investments will be made in Phase II. This will include all of the amenities that were delayed from Phase I (as listed above). The total cost for station investments in Phase II is estimated to be $1.5 million Vehicles The minibuses that operate the feeder services to the BRT corridor will be painted during this phase to help to tie them to the BRT service. The exact timing of this painting will be determined by operational considerations. These decisions will be made in the context of the Transit Development Plan. The painting cost will be approximately $75,000. Queue jumper Assuming that the Wolf Road queue jumper is successfully implemented in Phase I, a second queue jumper at New Karner Road in the westbound direction will be implemented in Phase II. The estimated cost for this project is $420,000. Park and ride An additional 30% (375 spaces) of the total park-and-ride spaces will be provided in Phase II. The estimated cost to provide these spaces is $1.5 million, assuming that half of the spaces would be provided through capital leasing and half through land acquisition and construction. It is not assumed that all spaces could be provided through capital leasing due to lack of supply of desirable spaces near the corridor. However, as redevelopment around some of the stations occurs, it may be possible to negotiate with developers to lower the construction cost of park-and-ride spaces for CDTA. Some of these spaces would be added to the locations listed for Phase I, but some will be constructed near the next set of priority stations: Lawnwood, New Karner, and Colvin. These Phase II investments will bring the BRT system close to full implementation. The travel time savings due to TSP and the queue jumpers will be able to be fully realized, leading to operating cost savings and increased ridership. The stations will be complete, enhancing the customer experience. 3.3 Phase III (7 to 10 years) The final phase of BRT implementation in the NY 5 corridor includes three elements: new vehicles for the feeder routes, additional park-and-ride spaces, and off-vehicle fare collection. The total estimated cost of these elements is $11.3 million. The BRT feeder plan, described in a separate report, estimates that 21 minibuses will be required to operate the feeder services recommended to complement the BRT express route. With a 20% spare ratio and an assumed cost of $200,000, the total cost will be $5.0 million. In the earlier phases, it was assumed that the feeders will be operated by vehicles already in the CDTA fleet that could be repainted with a BRT-related theme if so desired. For the third implementation phase, it is assumed that the remaining 625 park-and-ride spaces will be provided adding to the stations already mentioned in the previous two phases plus the Village of Colonie station. Using the same unit costs as for earlier phases, 14

15 the total cost of providing the spaces (half through capital leasing and half through land acquisition and construction) would total some $2.5 million. The new element of BRT introduced in Phase III is off-vehicle fare collection. The main benefit of this element, as described above, is that it speeds up the boarding process, allowing passengers to board at both doors, bypassing the time-consuming farebox. This is a costly element, as it would require either ticket vending machines (TVMs) to be installed at all BRT stations, or barrier-entry stations to be built at selected locations. Some or all of these barrier-entry stations would need to be attended by a fare collector, significantly raising the operating cost. TVMs would be used if a proof-of-payment policy were instituted. In this case, riders would need to show some proof of payment to roving fare inspectors either a pass or a valid ticket. It was estimated that some 63 TVMs would be needed among the 20 stations to handle the forecast passenger volume efficiently. The estimated cost of installing the recommended number of TVMs is $3.8 million. There would also be a significant operating and maintenance cost associated with the TVMs, since it would be vitally important to keep them in working order. Barrier-entry stations would be built only at the highest volume stations, such as Pearl and Lark. At other stations, riders would continue to use the farebox. The rationale here is that at lower volume stations, there would not be enough of a reduction in dwell time to justify the expense of building the barrier station and staffing it with a fare collector. The cost of building the barrier-entry stations has not been estimated. It should be noted that as an alternative to a barrier-entry station (at a location such as Pearl Street), CDTA could assign a fare inspector to the station during the afternoon peak period to allow passengers with Swiper passes to board through the rear door. This option would capture much of the dwell time benefit of a barrier-entry station without the significant capital cost. While off-vehicle fare collection is an important element of BRT in many applications and does help to distinguish it from regular local bus services, it is not considered an essential element for the NY 5 corridor. Once the rest of the recommended BRT system is put in place, the best approach to off-vehicle fare collection can be determined. At that point, a decision can be made whether the benefits would justify the cost. Continued growth in the use of Swiper passes may make the need for expensive off-vehicle fare collection systems less important. 3.4 Cost summary of phasing plan Table 4 shows the capital costs associated with each phase of the implementation plan presented above. The table shows that the total capital costs for the project in the long run are approximately $27 million. The total cost was divided into the three phases of implementation described above. The first phase includes the majority of the amenities at the station, the bulbouts, the queue jumper at Wolf Road, the uni-directional stations at Colonie Center, 20% of the park-andride spaces, the TSP expansion, and the acquisition of new 40-foot buses for the BRT express service. The cost of this phase would be approximately $12.0 million. 15

16 Phase II includes the remaining amenities at the stations, the queue jumper at New Karner Road, 30% of the park-and-ride spaces, and the paint scheme of the feeder buses to amount approximately $3.5 million. Phase III consists of adding 50% of the total park-and-ride spaces, implementing the offvehicle fare collection system, and replacing the feeder vehicles at an approximate cost of $11.3 million. Table 4 Phasing plan for elements with capital costs associated Item Total Phase I Phase II Phase III Stations (a) $6,352,000 $4,879,000 $1,473,000 Queue Jumpers Wolf Road (b) $455,000 $455,000 New Karner - Long alt (b) $420,000 $420,000 Improvements at Colonie Ctr Uni-directional stations (b) $268,000 $268,000 Park and Ride (c) 20% 30% 50% Capital Leasing $1,500,000 $500,000 $375,000 $625,000 Land acquisition and Construction $3,000,000 $1,125,000 $1,875,000 TSP (d) Phase I $520,000 $520,000 Vehicles Replacement 40-foot $5,400,000 $5,400,000 Painting minibuses $75,000 $75,000 Replacement Minibuses $5,000,000 $5,000,000 Off-vehicle fare collection $3,780,000 $3,780,000 Total $26,770,000 $12,022,000 $3,468,000 $11,280,001 Notes (a) Includes Contingency, Design & Engineering, Bulbouts, Site costs, and Traffic Management costs. See Stations table for details. (b) Includes 20% Contingency, 15% Design & Engineering, and ROW cost. Does not include environmental costs. (c) Assumes 1,250 required spaces, including land acquisition and construction costs. (d) Cost of expanding TSP to entire corridor beyong what is currently under implementation. 16

17 4 Organizational Responsibilities The implementation of the elements discussed above calls for the involvement of and coordination between various organizations, institutions, and private parties. Table 5 shows the responsible organizations for the implementation of each element as well as other parties that would be affected by the project and should be involved during the planning, design, and implementation of the elements. Naturally, CDTA has the primary responsibility for all elements of the BRT implementation. Table 5 Organizational responsibilities Element Responsible Parties Other parties involved/affected Stations CDTA, CDTC, City of Land owners, neighbors. Albany, Village of Colonie, Town of Colonie, City of Schenectady. Bulbouts CDTA, CDTC, NYSDOT, City of Albany Queue Jumpers CDTA, NYSDOT, Village of Land owners. Colonie, Town of Colonie. Improvements at Colonie CDTA, CDTC, Town of Land owners. Center Colonie. Vehicles CDTA Mainline services CDTA Users, Community. Feeder routes CDTA Users, Community. AVL/GPS CDTA TSP CDTA, NYSDOT, City of Albany, City of Schenectady Off-vehicle fare collection CDTA Marketing and Promotion CDTA Users, Community. 17

NY5 Bus Rapid Transit Conceptual Design Study Executive Summary

NY5 Bus Rapid Transit Conceptual Design Study Executive Summary NY5 Bus Rapid Transit Conceptual Design Study Executive Summary Washington Broadway Veeder/Nott Steuben McClellan N. Robinson Lawnwood Balltown New Karner Village of Colonie Colonie Center Colvin N. Allen

More information

Development and Overview of the NY 5 Bus Rapid Transit Corridor. New York State MPO Conference June 5, 2009

Development and Overview of the NY 5 Bus Rapid Transit Corridor. New York State MPO Conference June 5, 2009 Development and Overview of the NY 5 Bus Rapid Transit Corridor New York State MPO Conference June 5, 2009 Bus Rapid Transit (BRT) n Enhancement of ordinary bus route to offer high quality transit at low

More information

Service Quality: Higher Ridership: Very Affordable: Image:

Service Quality: Higher Ridership: Very Affordable: Image: Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009 HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Where will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run?

Where will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run? Where will 32 65 87 223 Rosedale Transit Center 225 227 264 801 ROSEVILLE 65 Snelling & County Road B BRT run? Snelling & Roselawn FALCON HEIGHTS BRT will serve 20 stations along the line, connecting to

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis

More information

NY5 Bus Rapid Transit Conceptual Design Study. Deliverable C-2 Operations Plan

NY5 Bus Rapid Transit Conceptual Design Study. Deliverable C-2 Operations Plan Capital District Transportation Committee Capital District Transportation Authority NY5 Bus Rapid Transit Conceptual Design Study Deliverable C-2 Operations Plan with Logitrans Herbert Levinson January,

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Downtown Transit Connector. Making Transit Work for Rhode Island

Downtown Transit Connector. Making Transit Work for Rhode Island Downtown Transit Connector Making Transit Work for Rhode Island 3.17.17 Project Evolution Transit 2020 (Stakeholders identify need for better transit) Providence Core Connector Study (Streetcar project

More information

Click to edit Master title style

Click to edit Master title style Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment

More information

State Avenue Corridor Bus Rapid Transit (BRT)

State Avenue Corridor Bus Rapid Transit (BRT) State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!

More information

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014 TBARTA USF to Wesley Chapel Express Bus Service Operating Plan Draft 3/25/2014 March 2014 Table of Contents 1.0 Introduction... 1 2.0 Study Area... 1 3.0 Existing Available Service... 3 4.0 Proposed Service...

More information

SERVICE DESIGN GUIDELINES

SERVICE DESIGN GUIDELINES VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Submission to Greater Cambridge City Deal

Submission to Greater Cambridge City Deal What Transport for Cambridge? 2 1 Submission to Greater Cambridge City Deal By Professor Marcial Echenique OBE ScD RIBA RTPI and Jonathan Barker Introduction Cambridge Futures was founded in 1997 as a

More information

Troost Corridor Transit Study

Troost Corridor Transit Study Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1 Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

Mississauga Transit 2009 Budget

Mississauga Transit 2009 Budget Mississauga Transit 2009 Budget Budget Committee Presentation December 2, 2008 Revenue Ridership Forecasted 2008 Total Rides Including transfers 11% growth in the last 24 months Transit Service Area Business

More information

2.0 Development Driveways. Movin Out June 2017

2.0 Development Driveways. Movin Out June 2017 Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.

More information

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital Needs Assessment Riders Advisory Council July2, 2008 Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

ARTERIAL BRT OVERVIEW

ARTERIAL BRT OVERVIEW ARTERIAL BRT OVERVIEW Key Question: Could arterial Bus Rapid Transit (BRT) routes improve near-term mobility in the northwest area until rail can be built? Key Findings: 6 arterial BRT routes have been

More information

Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa

Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa Annual growth rate is 3.8% By 2020 population growth would

More information

Appendix G: Rapid Transit Technology Backgrounder July 2017

Appendix G: Rapid Transit Technology Backgrounder July 2017 Appendix G: Rapid Transit Technology Backgrounder This appendix provides additional details regarding Bus Rapid Transit and Light Rail Transit technologies, with examples from other systems, including:

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

Bus Rapid Transit: Basic Design for Non-Transit Planners

Bus Rapid Transit: Basic Design for Non-Transit Planners Bus Rapid Transit: Basic Design for Non-Transit Planners Paul Bignardi, AICP - Principal Planner San Francisco Municipal Transportation Agency Graham Carey, PE Principal careybrt Consulting Peter Gabancho,

More information

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost.

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost. Policy Note Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost Recommendations 1. Saturate vanpool market before expanding other intercity

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

GO Transit s deliverable: the 2020 Service Plan

GO Transit s deliverable: the 2020 Service Plan GO Transit s deliverable: the 2020 Service Plan GO Transit s 2020 Service Plan describes GO s commitment to customers, existing and new, to provide a dramatically expanded interregional transit option

More information

Executive Summary. Phase 2 Evaluation Report. Introduction

Executive Summary. Phase 2 Evaluation Report. Introduction , Executive Summary Executive Summary Introduction TransLink and the Province of British Columbia sponsored a multi-phase study to evaluate alternatives for rapid transit service in the Broadway corridor

More information

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2

More information

Attachment 5. High Speed Transit Planning Study REPORT SUMMARY. Prepared by: City of Edmonton Transportation Planning Branch. Stantec Consulting Ltd.

Attachment 5. High Speed Transit Planning Study REPORT SUMMARY. Prepared by: City of Edmonton Transportation Planning Branch. Stantec Consulting Ltd. Attachment 5 High Speed Transit Planning Study Prepared by: City of Edmonton Transportation Planning Branch Stantec Consulting Ltd. Transportation Management & Design, Inc. with Lea Consulting Ltd. [135-35130]

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

Update on Bus Stop Enhancements

Update on Bus Stop Enhancements Customer Service and Operations Committee Board Information Item III-A February 2, 2012 Update on Bus Stop Enhancements Page 3 of 15 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

KEY BUS ROUTE IMPROVEMENT PROJECT ROUTE 23 AGENDA

KEY BUS ROUTE IMPROVEMENT PROJECT ROUTE 23 AGENDA KEY BUS ROUTE IMPROVEMENT PROJECT ROUTE 23 December 9, 2009 Codman Tech 450 Washington Street AGENDA Introduction Key Bus Routes Program Route 23 Challenges Proposed Improvement Plan Next Steps Question

More information

Bus Rapid Transit. Jennifer Flynn and Cheryl Thole Senior Research Associates Commuter Choice Workshop January 2012 Tampa, FL

Bus Rapid Transit. Jennifer Flynn and Cheryl Thole Senior Research Associates Commuter Choice Workshop January 2012 Tampa, FL Bus Rapid Transit Jennifer Flynn and Cheryl Thole Senior Research Associates Commuter Choice Workshop January 2012 Tampa, FL What is Bus Rapid Transit? BRT is an enhanced bus system that operates on bus

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

DRAFT Evaluation Scores. Transit

DRAFT Evaluation Scores. Transit DRAFT Evaluation s The criteria for evaluating applications for new funding commitments are used to measure how well they advance the six goals identified for the MTP. Through transportation: Reduce per

More information

FACT SHEET. US 192 Alternatives Analysis Modal Technologies. Alternative Description/Overview

FACT SHEET. US 192 Alternatives Analysis Modal Technologies. Alternative Description/Overview FACT SHEET US 192 Alternatives Analysis Modal Technologies Bus Alternative Description/Overview Bus systems typically operate in mixed traffic and have minimal station infrastructure. Bus service typically

More information

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report Office of Transportation Bureau of Traffic Management 1997 Downtown Parking Meter District Rate Report Introduction The City operates approximately 5,600 parking meters in the core area of downtown. 1

More information

1.0 Detailed Definition of Alternatives

1.0 Detailed Definition of Alternatives 1.0 Detailed Definition of Alternatives 1.1 Introduction This chapter provides supplemental information on the four alternatives, including both physical and operational characteristics (e.g. service plans)

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

BUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN

BUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN APPENDIX 1 CITY OF MISSISSAUGA BUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN Executive Summary McCORMICK RANKIN May 2003 Introduction This executive summary highlights the findings and

More information

Presentation Overview. Stop, Station, and Terminal Capacity

Presentation Overview. Stop, Station, and Terminal Capacity Stop, Station, and Terminal Capacity Mark Walker Parsons Brinckerhoff Presentation Overview Brief introduction to the project Station types & configurations Passenger circulation and level of service Station

More information

Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan

Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan Page 72 of 96 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease

More information

City of Pacific Grove

City of Pacific Grove Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency

More information

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report REVISIONS 1. Table 39: New Public Investments for Operation and Maintenance Costs 2. Appendix A-10: Passenger Rail Service - Operations

More information

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for:

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for: TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY 2014 Prepared for: Hartford Companies 1218 W. Ash Street Suite A Windsor, Co 80550 Prepared by: DELICH ASSOCIATES 2272 Glen Haven Drive

More information

TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury

TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury Open House Presentation January 19, 2012 Study Objectives Quantify the need for transit service in BWG Determine transit service priorities based

More information

Opportunities to Leverage Advances in Driverless Car Technology to Evolve Conventional Bus Transit Systems

Opportunities to Leverage Advances in Driverless Car Technology to Evolve Conventional Bus Transit Systems Opportunities to Leverage Advances in Driverless Car Technology to Evolve Conventional Bus Transit Systems Podcar City 7 Symposium Emerging Transportation Technologies R&D George Mason University, October

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

EXECUTIVE SUMMARY. Introduction

EXECUTIVE SUMMARY. Introduction EXECUTIVE SUMMARY Introduction The purpose of this study is to ensure that the Village, in cooperation and coordination with the Downtown Management Corporation (DMC), is using best practices as they plan

More information

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &

More information

What IS BRT, Really? Not BRT and RNY

What IS BRT, Really? Not BRT and RNY What IS BRT, Really? 2007 Winter TexITE Meeting Presented by Jeff Arndt, TTI Not BRT and RNY 1 What is Bus Rapid Transit? A flexible, rubber-tired from of rapid transit that combines stations, vehicles,

More information

CORE AREA SPECIFIC PLAN

CORE AREA SPECIFIC PLAN only four (A, B, D, and F) extend past Eighth Street to the north, and only Richards Boulevard leaves the Core Area to the south. This street pattern, compounded by the fact that Richards Boulevard is

More information

2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS

2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS 2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS In the Study Area, as in most of the Metro Transit network, there are two distinct route structures. The base service structure operates all day and the peak

More information

Midtown Corridor Alternatives Analysis Key Issues Memo

Midtown Corridor Alternatives Analysis Key Issues Memo Midtown Corridor Alternatives Analysis Key Issues Memo 1/4/2013 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 1. Markets... 1 External Markets... 1 Intra-Corridor Travel...

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: COMMUNITY BUS SERVICES ACTION ITEM RECOMMENDATION It is recommended that the Board not approve any routing

More information

Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville

Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville 1. Introduction During the stakeholder input sessions of Charlottesville Area Transit s (CAT) Transit Development

More information

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle Chapter 7: Travel Demand Analysis Chapter 8 Plan Scenarios LaSalle Community Center. Image Credit: Town of LaSalle 164 Chapter 8: Plan Scenarios Moving Ahead for Progress in the 21 st Century Act (MAP

More information

More than $9 Million coming to Central Valley for transportation

More than $9 Million coming to Central Valley for transportation More than $9 Million coming to Central Valley for transportation From free bus service to electric buses Part of overall $97 Million awarded to public transportation projects A total of 152 local public

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: SUBJECT: August 19, 2014 OPPORTUNITIES TO IMPROVE TRANSIT SERVICE IN TORONTO ACTION ITEM RECOMMENDATIONS It is recommended that the

More information

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min. AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome

More information

Needs and Community Characteristics

Needs and Community Characteristics Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by

More information

Metro Transit Arterial Transitway Corridors Study

Metro Transit Arterial Transitway Corridors Study Metro Transit Arterial Transitway Corridors Study Technical Memorandum #3 Corridor Mode Development 2/1/2012 Prepared by the SRF Consulting Group Team Table of Contents Introduction... 1 Concept Plans...

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

A Transit Plan for the Future. Draft Network Plan

A Transit Plan for the Future. Draft Network Plan A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

Sound Transit East Link: Bus/LRT System Integration Study

Sound Transit East Link: Bus/LRT System Integration Study Sound Transit East Link: Bus/LRT System Integration Study Prepared For: Sound Transit King County Metro Mercer Island WSDOT Prepared By: CH2M HILL July, 2014 1 SOUND TRANSIT EAST LINK: BUS/LRT SYSTEMES

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

West Broadway Reconstruction/LRT Design. March 19, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015 West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian

More information

BUS STOP DESIGN & PLANNING GUIDE

BUS STOP DESIGN & PLANNING GUIDE BUS STOP DESIGN & PLANNING GUIDE Prepared by the Operations and Planning Departments 2011 PURPOSE OF GUIDE The design of passenger waiting areas plays a significant role in a person s decision of whether

More information

Memorandum. 1 Introduction. 2 O&M Cost Elements. 2.1 Service O&M Costs

Memorandum. 1 Introduction. 2 O&M Cost Elements. 2.1 Service O&M Costs To Barrow Emerson, SamTrans Melissa Reggiardo, SamTrans Date 9/13/2014 Copies Reference number From Subject Corey Wong, Arup Steve Crosley, Fehr + Peers ECR BRT Phasing Plan File reference 1 Introduction

More information

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS... Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

More information

APPENDIX VMT Evaluation

APPENDIX VMT Evaluation APPENDIX 2.7-2 VMT Evaluation MEMORANDUM To: From: Mr. Jonathan Frankel New Urban West, Incorporated Chris Mendiara LLG, Engineers Date: May 19, 2017 LLG Ref: 3-16-2614 Subject: Villages VMT Evaluation

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

Draft Marrickville Car Share Policy 2014

Draft Marrickville Car Share Policy 2014 Draft Marrickville Car Share Policy 2014 1. Background 1.1. Marrickville Council has supported car sharing in the LGA since 2007 as part of a holistic approach to encouraging more sustainable modes of

More information

City of El Paso: Sun Metro Legislative Agenda Briefing

City of El Paso: Sun Metro Legislative Agenda Briefing Tiger V TOD Operational 2017 City of El Paso: Sun Metro Legislative Agenda Briefing March 2016 Sun Metro FY 2016/17 Legislative Agenda First and foremost, thanks for the new transportation bill: Fixing

More information

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017 US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master

More information

Application of Autonomous Vehicle Technology to Public Transit

Application of Autonomous Vehicle Technology to Public Transit Application of Autonomous Vehicle Technology to Public Transit University Transportation Research Center 2014 Ground Transportation Technology Symposium November 19, 2014 Jerome M. Lutin, Ph.D., P.E. Senior

More information

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County

More information

The City of Toronto s Transportation Strategy July 2007

The City of Toronto s Transportation Strategy July 2007 The City of Toronto s Transportation Strategy July 2007 Presentation Outline Transportation Statistics Transportation Building Blocks Toronto s Official Plan Transportation and City Building Vision Projects

More information

An Asset Management Plan for Transit And Access Transit Fleet

An Asset Management Plan for Transit And Access Transit Fleet Header Title ATTACHMENT 1 Building Better Transit: An Asset Management Plan for Transit And Access Transit Fleet 2 June 2016 Transit & Access Transit Fleet INTRODUCTION The Saskatoon Transit fleet is currently

More information

Detailed Definition of Alternatives

Detailed Definition of Alternatives West Broadway Transit Study Detailed Definition of Alternatives 9/4/2015 DRAFT Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 2040 No-Build Alternative... 1 Build Alternatives...

More information