VOLUME III. Draft Power Purchase Agreement ADDENDUM - 2
|
|
- Noah Byrd
- 5 years ago
- Views:
Transcription
1 GOVERNMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA Ministry of Power and Renewable Energy Ceylon Electricity Board REQUEST FOR PROPOSALS FOR THE DEVELOPMENT OF A 300MW COMBINED CYCLE POWER PLANT AT KERAWALAPITIYA ON BOOT BASIS BID NO: CEB/AGM(Pr)/PD-KCCPP2016 International Competitive Bidding (ICB) VOLUME III Draft Power Purchase Agreement ADDENDUM - 2 March 2017 i
2 1. Clause 5.8 Replace the sub clause (i) (a) with the following: (a) the Commissioning on an open cycle basis (the "Open Cycle Commissioning Date") or on a combined cycle basis (the "Combined Cycle (L) Commissioning Date") or (the Combined Cycle (N) Commissioning Date ) (as the case may be); 2. Clause 13.1 Replace the sub clause with the following: following termination of the: (i) (ii) Implementation Agreement by the Government; or Lease by the CEB; in each case pursuant to the respective provisions thereof. 3. Clause 13.2 Replace the sub clause with the following: following termination by the Company of the Implementation Agreement, the Liquid Fuel Supply Agreement or the Lease, in each case, pursuant to the respective provisions thereof. 4. Schedule 1. Replace the Definition of Combined Cycle (L) Operation Date or CCLOD with the following: "Combined Cycle (L) Operation Date" or "CCLOD" means the Day following the date of receipt by the CEB of the Completion Certificate certifying that the Facility is capable of combined cycle operation (with Liquid Fuel) in accordance with Clause 5.8.9; 5. Schedule 1. Insert the definition of Combined Cycle Commissioning Date RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
3 "Combined Cycle Commissioning Date" means Combined Cycle (L) Commissioning Date; 6. Schedule 1. Insert the definition of Combined Cycle Operation Date "Combined Cycle Operation Date" or CCOD means Combined Cycle (L) Operation Date or CCLOD; 7. Schedule 1. Insert the definition of Open Cycle Commissioning Period "Open Cycle Commissioning Period" means the period commencing at 0000 Hours on the Open Cycle Commissioning Date and ending at 0000 Hours on the Open Cycle Operation Date; 8. Schedule 5 Replace the first line of the second para of paragraph 5.3. (i) with the following: The Generating Set shall be capable of rapid starting and withstanding repeated full load rejection. 9. Schedule 5 Replace the first para of paragraph (i) with the following: A single steam turbine shall be offered, which shall be capable to accommodate the total output of all HRSG s. Full turbine steam flow bypass system to the condenser shall be provided. The steam turbine shall have at least HP and LP sections, including: 10. Schedule 5 Replace the last two sentences of the second para of paragraph (ii) with the following: RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
4 The generator shall be capable of supplying their rated power within plus or minus ten percent of normal rated voltages within the power factor range of 0.8 lagging and 0.95 leading. The generator shall be able to operate at any point within the generator capability curve. 11. Schedule 5 Replace the first para of paragraph with the following: The cooling system shall be a mechanical draft cooling tower system using sea water. The cooling water system shall be designed to return all cooling water or blow down water to the sea within the allowable temperature rise and chemical concentration limits. 12. Schedule 5 Replace the second para of paragraph with the following: 13. Schedule 5 The low voltage system shall be effectively earthed and should be rated for 3 phase fault level of 40 ka. The low voltage switchgear shall have air circuit breakers for incomers and bus couplers. The outgoing feeders shall be with switches, fuses and contactors/thermal overload relays in case of motor feeders. The low voltage switchgear shall be of the full draw-out type. Replace the second para of paragraph with the following: All control cables shall be 1000 volt grade, multi-core, stranded, copper conductor, PVC insulated PVC sheathed. Size and armour of the cable shall be selected appropriately, as per wiring regulations. 14. Schedule 5 Replace the paragraph with the following: 15. Schedule 5 The Facility shall be provided with an diesel engine driven generator(s) of adequate capacity to be able to take care of the start-up of the Facility using the GT during black-out conditions. The Emergency Diesel Generator (EDG) set shall also be provided as a reliable source of power supply to important equipment to enable safe shutdown of the Generating Set in the event of failure of complete AC supply in the station. Replace the 3 rd para of the paragraph (ii) with the following: RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
5 The load ramping shall be limited to a maximum of 10% of NDC per minute, as the case may be, for step load increase at any load above the minimum stable load and also for a step load reduction from any load in the range of NDC to 40% of NDC. 16. Schedule 5 Replace the paragraph (v) with the following: 17. Schedule 5 To be adjustable over the range as indicated in the Grid Code. The Facility shall be able to operate on the specific droop settings given by CEB as and when required within the Grid Code range. Replace the paragraph (vi) with the following: (vi) Reactive load capability -5% of rated capacity 18. Schedule 5 Insert following at the end of paragraph 5.6.9: ANNEX 1 i. INDICATIVE SITE PLANS (Showing the Cooling Water Corridor and Fuel Supply Corridor proper plans will be included at the time of signing the PPA) a) Site Survey Plan b) General Layout of the Plant Area ii. SINGLE LINE AND INTERFACING DIAGRAM iii. CODE FOR INTERCONNECTION RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
6 i. (a) INDICATIVE SITE PLANS (PDF file name Annex 1 (i) (a) Site Survey Plan in enclosed separately) RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
7 i. (b) INDICATIVE SITE PLANS (PDF file name Annex 1 (ii) (b) General Layout of the Plant Area in enclosed separately) RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
8 (ii) SINGLE LINE AND INTERFACING DIAGRAM (PDF file name Annex 1 (ii) Single Line and Interfacing Diagram in enclosed separately) RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
9 (iii) CODE FOR INTERCONNECTION (PDF file name Annex 1 (iii) Code for Interconnection in enclosed separately) RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
10 19. Schedule 8 Replace the first para of Section 8.2 with the following: The Actual Available Capacity for any one Hour (AA h) shall not be more than NDC OL, NDC ON, NDC CL or NDC CN as applicable and shall be determined according to the following provisions: RFP for the Development of a 300 MW CCPP at Kerawalapitiya on BOOT Basis Addendum 2 of Volume III Mar
REQUEST FOR PROPOSALS FOR THE ESTABLISHMENT OF SOLAR PV POWER PLANT ON BUILD, OWN AND OPERATE BASIS. International Competitive Bidding (ICB)
REQUEST FOR PROPOSALS FOR THE ESTABLISHMENT OF SOLAR PV POWER PLANT ON BUILD, OWN AND OPERATE BASIS International Competitive Bidding (ICB) Polonnaruwa Solar PV Power Project (10 MWp) Tender No: CEB/EPT/SP/RFP1
More information045 : 2000 CEB STANDARD
045 : 2000 CEB STANDARD LOW VOLTAGE FUSE SWITCH DISCONNECTOR CEYLON ELECTRICITY BOARD SRI LANKA Specification for LOW VOLTAGE FUSE SWITCH DISCONNECTOR CEB Standard 045 : 2000 CEYLON ELECTRICITY BOARD No.
More information020: 2013 CEB SPECIFICATION MINIATURE CIRCUIT BREAKER (MCB)
020: 2013 CEB SPECIFICATION MINIATURE CIRCUIT BREAKER (MCB) CEYLON ELECTRICITY BOARD SRI LANKA Telephone: +94 11 232 0953 Fax: +94 11 232 3935 CONTENTS Page 1.0 Scope 3 2.0 System Parameters 3 3.0 Service
More information013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS
013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS FOR OVERHEAD NETWOKS CEYLON ELECTRICITY BOARD SRI LANKA Specification for MOULDED CASE CIRCUIT BREAKERS FOR OVERHEAD NETWOKS CEB Specification
More informationUnified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) (Corr.1 June 2018) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements
More information017: 1998 CEB STANDARD RING MAIN UNIT CEYLON ELECTRICITY BOARD SRI LANKA
017: 1998 CEB STANDARD RING MAIN UNIT CEYLON ELECTRICITY BOARD SRI LANKA CONTENTS PAGE 1. Scope 2 2. System Parameters 2 3. Service Conditions 2 4. Applicable Standards 3 5. Basic Features 4 6. Quality
More informationCLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001
CLP POWER HONG KONG LIMITED SUPPLY March 2001 ADVISORY SERVICE Advice concerning matters relating to the supply of electricity may be obtained free of charge from the Company. OTHER COMPANY PUBLICATIONS
More informationKERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007
KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No.1/1/KSERC-2006/ Dated, Thiruvananthapuram 6 th August,2007 KSERC (Supply of Power from Captive Generating Plants to Distribution Licensees)
More informationGHA. Gas-Insulated Switchgear. Gas-Insulated Switchgear. Switchgear extension and replacement of a panel
Gas-Insulated Switchgear GHA Gas-Insulated Switchgear Switchgear extension and replacement of a panel During this work, essential parts of the switchgear remain in operation No. AGS 535 066-01 Edition
More informationCHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.
25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements
More informationGUIDELINES ON ELECTRICAL SAFETY AT WORKPLACES
MINISTRY OF LABOUR, INDUSTRIAL RELATIONS AND EMPLOYMENT GUIDELINES ON ELECTRICAL SAFETY AT WORKPLACES Occupational Safety & Health Inspectorate These guidelines should be used with approved standards:
More informationGas Insulated Metal-clad Switchgear, HMGS!
Medium Voltage HMGS-G10 HYUNDAI Medium Voltage Gas Insulated Metal-clad Switchgear, HMGS! SF6 Gas Insulated Metal-clad Switchgear is an integrated assembly of vacuum circuit breaker, 3-position switch,
More informationStandards, Procedures and Policies for Grid Connection
Standards, Procedures and Policies for Grid Connection CONTENTS 1 INTRODUCTION 1 2 EMBEDDED GENERATION 1 2.1.1 OUTLINE OF EMBEDDED GENERATION 1 2.1.2 CHANGES IN EMBEDDED GENERATION 1 2.1.3 ASPECTS OF EMBEDDED
More information026-2 : 1996 CEB STANDARD
026-2 : 1996 CEB STANDARD COMPRESSION CONNECTORS & TERMINATIONS FOR OVERHEAD LINE CONDUCTORS CEYLON ELECTRICITY BOARD SRI LANKA CONTENTS 1. Scope 2 2. System Parameters 2 3. Service Conditions 2 4. Applicable
More informationNet +Plus Connection Code
Net +Plus Connection Code LANKA ELECTRICITY COMPANY (PRIVATE) LIMITED 1.0 BACKGROUND The existing Net Metering Concept launched in the year 2010 noticed an exponential growth in the recent year and at
More informationBharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA CAPITAL EQUIPMENT / MATERIALS MANAGEMENT
An ISO 9001 Company Bharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli 620014, TAMIL NADU, INDIA CAPITAL EQUIPMENT / MATERIALS MANAGEMENT ENQUIRY NOTICE INVITING TENDER Phone:
More informationCustomer Requirements Downtown Secondary Network Service
Application This standard describes the limitations and requirements for receiving service from the Tacoma Power secondary network system within the City of Tacoma downtown core area. In This Standard
More informationBHARAT HEAVY ELECTRICALS LIMITED, JHANSI
BHARAT HEAVY ELECTRICALS LIMITED, JHANSI DESIGN, MANUFACTURING, TESTING, SUPPLY INSTALLATION AND COMMISSIONING OF 11KV VACUUM CIRCUIT BREAKER NOTE : 1 VENDOR must submit complete information against clause
More information37-SDMS-04 SPECIFICATIONS FOR INTERFACE LOW VOLTAGE MAIN CIRCUIT BREAKERS
SPECIFICATIONS FOR INTERFACE LOW VOLTAGE MAIN CIRCUIT BREAKERS This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Page 1.0 SCOPE 3 2.0 CROSS
More information9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.
Chapter 3 TRANSMISSION SYSTEMS 1 Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution
More information023 : 2006 CEB STANDARD. 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA
023 : 2006 CEB STANDARD 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA Specification for 12kV & 36kV LOAD BREAK SWITCHES CEB Standard 023 : 2006 CEYLON ELECTRICITY BOARD No. 50, Sir
More informationUniversity of Houston Master Construction Specifications Insert Project Name
SECTION 26 13 13 MEDIUM VOLTAGE SWITCHGEAR PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical General
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationCompany Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements
Company Directive STANDARD TECHNIQUE: SD4O/1 Standard HV Connection Arrangements Policy Summary This document specifies the standard arrangements for HV metered connections. NOTE: The current version of
More informationINTERPLANT STANDARD - STEEL INDUSTRY
INTERPLANT STANDARD - STEEL INDUSTRY IPSS SPECIFICATION FOR MAGNETIC OVER- CURRENT RELAYS FOR ac AND dc MOTORS PROTECTION UP TO 650 V (FIRST REVISION) CORRESPONDING INDIAN STANDARD DOES NOT EXIST IPSS:1-04-008-11
More informationDate Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS
Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...
More informationDESIGN GUIDELINES LOW VOLTAGE SWITCHGEAR PAGE 1 of 5
DESIGN GUIDELINES LOW VOLTAGE SWITCHGEAR PAGE 1 of 5 1.1. APPLICABLE PUBLICATIONS 1.1.1. Publications listed below (including amendments, addenda, revisions, supplements, and errata), form a part of this
More informationE-12 Low-voltage Switchboard
Guideline No.E-12 (201510) E-12 Low-voltage Switchboard Issued date: 20 October 2015 China Classification Society Foreword This Guide is a part of CCS Rules, which contains technical requirements, inspection
More informationBharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA CAPITAL EQUIPMENT / MATERIALS MANAGEMENT
An ISO 9001 Company Bharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli 620014, TAMIL NADU, INDIA CAPITAL EQUIPMENT / MATERIALS MANAGEMENT ENQUIRY Phone: +91 431 257 79 38 Fax
More informationTechnical Specification For Outdoor Substation Harmonic Filter Banks
Technical Specification For Outdoor Substation Harmonic Filter Banks One of Three 5th, 11th & 23rd, 34.5 kv, Rated Harmonic Filter Assemblies Provided for a Central Venezuela Heavy Oil Production Field
More informationTENDER FOR FOR 2 X 1010 KVA, 1500 RPM, 415 V DG SETS FOR CONSTRUCTION OF NEW CDRI CAMPUS AT SITAPUR ROAD, LUCKNOW (U.P.) SUMMARY OF PRICE BID
TENDER FOR FOR 2 X 1010 KVA, 1500 RPM, 415 V DG SETS FOR CONSTRUCTION OF NEW CDRI CAMPUS AT SITAPUR ROAD, LUCKNOW (U.P.) SUMMARY OF PRICE BID S.NO. HEAD DESCRIPTION AMOUNT (Rs.) 1 A DG SETS & ACCESSORIES
More informationA member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.
Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative
More informationRULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)
- (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility
More informationCONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation
CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent
More informationSGT5-8000H / Irsching 4 Siemens H class gas turbine Pioneering efficiency with world class flexibility
SGT5-8000H / Irsching 4 Siemens H class gas turbine Pioneering efficiency with world class flexibility W. Fischer Program Director 8000H Evolution of Siemens Combined Cycle Technology 1991 1996 2007 2011
More informationE-12 Low-voltage Switchboard
Guideline No.E-12 (201705) E-12 Low-voltage Switchboard Issued date: May 9, 2017 China Classification Society Foreword This Guideline is a part of CCS Rules, which contains technical requirements, inspection
More informationCalculation of the Cross-sectional Areas of Circuit Live Conductors
Calculation of the Cross-sectional Areas of Circuit Live Conductors MOTOR CIRCUITS SUBJECT TO FREQUENT STOPPING AND STARTING Regulations requires that where a motor is intended for intermittent duty and
More informationResearch Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims
Research Brief Impact of higher 25kV fault currents Background Increasing the maximum fault levels at traction feeder stations has the potential to reduce the costs of electrification schemes. The potential
More informationLevel 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)
Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different
More information7 The revised IS 8034:2002 and revised STI be implemented w.e.f. 1 Feb 2005.
BUREAU OF INDIAN STANDARDS (CENTRAL MARKS DEPARTMENT-III) Our Ref: CMD-III/16:8034 25 Oct 2004 Subject: Implementation of revised IS 8034:2002 Submersible Pump Sets and revised STI (Doc:STI/8034/5 ) IS
More informationLegal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:
Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationBeyond 60% - Pioneering H-class Efficiency with World Class Flexibility
SCC5-8000H / Irsching 4 Beyond 60% - Pioneering H-class Efficiency with World Class Flexibility Irsching General Manager for GT Power Plant Solutions Europe, Africa, Asia and Australia Siemens AG 2011.
More information2018 Consultant s Handbook Division 26 Electrical 2413 Switchboards
1 General 1.1 Switchboards shall be U.L. listed and labeled. 1.2 Each switchboard shall have its own main disconnecting means unless it is located in the same room as its source of origin. In most cases
More informationNPS/003/010 - Technical Specification for 400V Assemblies (LVAC Boards) utilised in Major Substations
Version:- 3.0 Date of Issue:- Dec 2013 Page 1 of 13 NPS/003/010 - Technical Specification for 400V Assemblies (LVAC Boards) utilised in Major Substations 1. Purpose This document is the technical specification
More informationMedium Voltage Standby non-paralleling Control GUIDE FORM SPECIFICATION
Medium Voltage Standby non-paralleling Control 1. GENERAL GUIDE FORM SPECIFICATION A. The requirements of the contract, Division 1, and part 16 apply to work in this section. 1.01 SECTIONS INCLUDE A. Medium
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationRenewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd
Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Power Systems Project and Consultancy Services (PCS) Ltd
More informationAFTER GAZETTING (WORKING DOCUMENT FOR A 3 YEAR PERIOD) DATE PAGE PARAGRAPH DESCRIPTION ORIGINATOR APPROVED
PART B-07 TITLE: SERVICE CONNECTIONS SPECIFICTION NO: B-07 INCEPTION DATE: AFTER GAZETTING (WORKING DOCUMENT FOR A 3 YEAR PERIOD) AMENDMENTS / REVISIONS DATE PAGE PARAGRAPH DESCRIPTION ORIGINATOR APPROVED
More informationPSNH INTERCONNECTION REQUEST
PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.
More informationJEA Distributed Generation Policy Effective April 1, 2018
Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The
More informationSUBSTATION DESIGN TRAINING
2017 SUBSTATION DESIGN TRAINING ADVANCE ELECTRICAL DESIGN & ENGINEERING INSITUTE (Registered under MSME& An ISO 9001:2008 CERTIFIED) Training Centre: Advance Group of Institutions C-1, Second Floor Near
More informationShort Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study
Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Study Performed by El Paso Electric Company System Planning Section - 1 I.
More informationDATA SHEET FOR 1 TYPE COMPARTMENTALISED / NON - COMPARTMENTALISED. ( a ) CIRCUIT BREAKER FEEDERS FULLY DRAWOUT / NON DRAWOUT
44LK-500/E.04/002A/A4 PROJECT NO 44LK-500 CHKD. BY VDV VDV A CLIMATIC CONDITIONS THIS DATA SHEET IS APPLICABLE FOR IN UTILITY BOILER PACKAGE DESIGN AMBIENT TEMPERATURE 45 C 2 ALTITUDE ( ABOVE MSL ) 6.7
More informationUmatilla Electric Cooperative Net Metering Rules
Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through
More informationTender Schedule. Sl. No. Particulars Quantity Unit Rate `
Tender Schedule Estimate for Electrical Works at Savalyapuram Branch(18901) Guntur(District). Sl. No. Particulars Quantity Unit Rate ` 1 Wiring for light point/ fan point/ exhaust fan point/ call bell
More informationTERMS AND CONDITIONS
XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,
More informationTRANSMISSION SYSTEMS
TRANSMISSION SYSTEMS Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution of electric
More informationSOUTH AFRICAN NATIONAL STANDARD
ISBN 978-0-626-31488-0 SOUTH AFRICAN NATIONAL STANDARD Switchgear Metal-enclosed ring main units for rated a.c. voltages above 1 kv and up to and including 36 kv WARNING This document references other
More informationA. This Section includes Low Voltage Switchgear Work, as indicated on the drawings, and as specified herein.
16425 SWITCHBOARD ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 24 13 An optional keynote to
More information: Material Description Quantity UOM
Page : 1 / 2 OIL INDIA LIMITED (A Govt. Of India Enterprise) Tel :033 2230 1657, 1658 4, India Exchange Place, Fax :91 33 2230 2596 Kolkata-700001 E-mail :oilcalmn@cal2.vsnl.net.in ANNEXURE-I Item No./
More informationGeneration Interconnection Facilities Study For
Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...
More informationSSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL. Estimation and Costing & Utilization of Electrical Energy
1 SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL Estimation and Costing & Utilization of Electrical Energy Estimation and Costing & Utilization of electrical Energy Estimation
More informationTABLE OF CONTENTS FOREWORD...3 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS REQUIREMENTS...
TITLE SPECIFICATION FOR PORTABLE DATE: JULY 2006 PAGE: 1 OF 25 TABLE OF CONTENTS Page FOREWORD...3 INTRODUCTION...4 1 SCOPE...4 2 NORMATIVE S...4 3 DEFINITIONS AND ABBIATIONS...4 4 REQUIREMENTS...5 4.1
More informationSeaFloat SCC-A65. Technical Solution Information. Unrestricted. Vers.
SeaFloat SCC-A65 Technical Solution Information Unrestricted Vers Version 1 www.siemens.com/seafloat Engineered for industry-leading power output and fuel savings available in SeaFloat application With
More informationTABLE OF CONTENTS FOREWORD... 2 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS... 3
TITLE SPECIFICATION FOR MEDIUM VOLTAGE DATE: FEBRUARY 2015 PAGE: 1 OF 25 TABLE OF CONTENTS Page FOREWORD... 2 INTRODUCTION... 3 1 SCOPE... 3 2 NORMATIVE S... 3 3 DEFINITIONS AND ABBIATIONS... 3 4 REQUIREMENTS...
More informationMEDIUM-VOLTAGE SWITCHGEAR
REVISION RECORD SECTION 16341 Medium-Voltage Switchgear REV DATE PAGE PARA NO. DESCRIPTION APPROVED BY 28SEP01 ALL Initial issue. 1 29SEP03 ALL General update with miscellaneous changes in entire document.
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationNORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress
NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com
More informationTOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS
INSTRUCTION MANUAL TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS September 2000 TOWER UPS DISTRIBUTION (PTY) LTD 1 1. INTRODUCTION T A B L E O F C O N T E N T S 1.1 General Description... 3 1.2 Features...
More informationSummary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System
Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System This document is intended to be a general overview of PG&E s current technical
More informationCustomer Name : Account Number: Customer Service Address (Street, City, State, ZIP Code): Customer Mailing Address: Customer Telephone Number:
Please print the following information. Interconnect Customer Information Customer Name : Account Number: Customer Service Address (Street, City, State, ZIP Code): Customer Mailing Address: Customer Telephone
More informationWest Bengal State Electricity Distribution Co. Ltd.
West Bengal State Electricity Distribution Co. Ltd. TECHNICAL SPECIFICATIONS FOR D. C. DISTRIBUTION BOARD (FOR 33 KV SUB STATIONS) Page 1 of 14 1.0 SCOPE: This specification covers the design, manufacturing,
More informationCPG.1 Gas insulated, single busbar cubicle range Up to 27 kv / 2000 A / 31.5 ka Up to 38 kv / 2000 A / 31.5 ka IEEE Standards
Medium Voltage Switchgear Primary Distribution CPG.1 Gas insulated, single busbar cubicle range Up to 27 kv / 2000 A / 31.5 ka General description Presentation Ormazabal s CPG System includes the CPG.1
More informationDESCRIPTION OF REQUIREMENTS FOR GENERATION SYSTEMS SEEKING TO PROVIDE SYSTEM RESTART SERVICES
SYSTEM RESTART SERVICES DESCRIPTION OF REQUIREMENTS FOR GENERATION SYSTEMS SEEKING TO PROVIDE SYSTEM RESTART SERVICES System Management January 2015 INTRODUCTION System Management acting as the segregated
More informationData Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931
Data Bulletin 0931DB0101 July 2001 Cedar Rapids, IA, USA Ground-Censor Ground-Fault Protection System Type GC Class 931 09313063 GT Sensor Shunt Trip of Circuit Interrupter Window Area for Conductors GC
More informationGuidelines for connection of generators:
Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...
More informationModular integrated transportable substation (MITS)
Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................
More informationDELETE first sentence of first paragraph that reads: REPLACE with the following:
To Bidder of Record: SAN ANTONIO WATER SYSTEM Addendum 2 To Construction Documents For 2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB NO. 12-5001 SAWS SEWER JOB NO. 12-5501 Solicitation
More informationList of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007
to: details Version: 2007 Technical Rules 1 16-Jan-08 2 16-Jan-08 3 29-Jan-08 Neerabup (two generating units - Units G11 and G12) Neerabup (two generating units - Units G11 and G12) Bluewaters Power Station
More informationModular Standardized Electrical and Control Solutions for Fast Track Projects
Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive
More informationModel ESV Uninterruptible Power System 1.5 KVA/KW KVA/KW Single Phase
Model ESV Uninterruptible Power System 1.5 KVA/KW - 14.0 KVA/KW Single Phase 1.0 General General Specification This specification describes the features and design of an on-line, dual conversion, uninterruptible
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationMichigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE
PAGE 261116-1 SECTION 261116 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSP Distribution plc. and XXX
SP Distribution plc and XXX AGREEMENT FOR CONNECTION TO THE DISTRIBUTION SYSTEM (Where the customer has generating plant and uses the Distribution System for selling electricity or exporting energy) AGREEMENT
More informationChapter 6 Generator-Voltage System
Chapter 6 Generator-Voltage System 6-1. General The generator-voltage system described in this chapter includes the leads and associated equipment between the generator terminals and the low-voltage terminals
More informationRecommended Procedures
Selective Coordination Study Recommended Procedures The following steps are recommended when conducting a selective coordination study.. One-Line Diagram Obtain the electrical system one-line diagram that
More informationNORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014.
NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service Effective: For bills rendered on and after January 1, 2014. SECTION 1. AVAILABILITY AND APPLICABILITY 1.1 This Rate Schedule
More informationGenerating unit functional document submission form
Generating unit functional document submission form The below form must be completed and returned to generator.reports@aeso.ca. Supporting information to assist generating unit owners to complete this
More information1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces.
SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Fusible switches. 2. Nonfusible switches. 3. Receptacle switches. 4. Shunt trip switches. 5.
More information२१७१ २-१ ४४ २०१८ २-१ २१०९-४ २०१८ २९ ०६ २०१८ २ २ १२४९ २-१ ४४ २०१८ २१ ०७ २०१८ ३ २ १७०५ २ / -१ ४४ २०१८ १० १० २०१८ १ २ ३ २ ३ १३ २०१८-१९
२१७१ २-१ ४४ २०१८ २ :- (०७१७२)२२७३८२-४४२४०३ - (०७१७२)२२७३८२ - mlidn2@rediffmail.com ३१ / १२ २०१८ - - १ २१०९-४ २०१८ २९ ०६ २०१८ २ २ १२४९ २-१ ४४ २०१८ २१ ०७ २०१८ ३ २ १७०५ २ / -१ ४४ २०१८ १० १० २०१८ ------000-----
More informationSolar Power Switchgear & Energy Storage Renewable Energy Systems
7 Solar Power Switchgear & Energy Storage Renewable Energy Systems - Solution Brochure www.apt-power.com 433 N. 36 th Street PROVIDING A COMPREHENSIVE Lafayette, IN 47905 www.apt-power.com 433 APPROACH
More informationNLC INDIA LIMITED (formerly Neyveli Lignite Corporation Limited) ('NAVARATNA'-Government of India Enterprise) MATERIALS MANAGEMENT COMPLEX
NLC INDIA LIMITED (formerly Neyveli Lignite Corporation Limited) ('NAVARATNA'-Government of India Enterprise) MATERIALS MANAGEMENT COMPLEX Dr. Rajendra Prasad Road,Block-27,Neyveli-607807.Tamilnadu,India.
More informationECET Circuit Design Motor Loads. Branch Circuits. Article 210
ECET 4520 Industrial Distribution Systems, Illumination, and the NEC Circuit Design Motor Loads Branch Circuits Article 210 210.1 Scope This article covers branch circuits except for those that supply
More informationIN2 Enclosed Switches and Circuit Breakers
Illinois Math and Science Academy DigitalCommons@IMSA Project Manuals IN2 2015 IN2 Enclosed Switches and Circuit Breakers Illinois Mathematics and Science Academy Follow this and additional works at: http://digitalcommons.imsa.edu/facility_in2_manuals
More informationINDIAN INSTITUTE OF TECHNOLOGY KANPUR
INDIAN INSTITUTE OF TECHNOLOGY KANPUR Tender Notice No. 40/Elect./2018 SCHEDULE OF QUANTITY Name of Work: Electrical work for the Clean Room at NCFlexE IIT Kanpur. Name of the Contractor S. No Description
More informationTender Schedule for Electrical Works at Varagani Branch. Sl. No. Particulars Quantity Unit Rate Amount
Tender Schedule for Electrical Works at Varagani Branch Sl. No. 1 Particulars Quantity Unit Rate Amount SITC of following rated Indoor operated wall/floor mounted, cubicle type MV cum APFC Panel suitable
More informationSenate Substitute for HOUSE BILL No. 2101
Senate Substitute for HOUSE BILL No. 2101 AN ACT concerning utilities; relating to renewable energy resources; amending K.S.A. 2013 Supp. 66-1,184, 66-1265, 66-1266, 66-1267 and 66-1271 and repealing the
More informationExemptions currently in force
exemptions by Western Power s currently in force Neerabup Units G11 & G12 3.3.3.1 (a) 16 Jan 2008 Ongoing Modified performance criteria: 0.8 Lagging 101.3 MVAr 0.9 Leading 68.5 MVAr Financial contribution
More informationMaryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)
Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: Alternative Contact Information
More information