WATER RESOURCES DEPARTMENT SCHEDULE OF RATES TUNNEL AND ALLIED WORKS REFERENCE DATA NOTES ON BASIC RATES DATA RATES

Size: px
Start display at page:

Download "WATER RESOURCES DEPARTMENT SCHEDULE OF RATES TUNNEL AND ALLIED WORKS REFERENCE DATA NOTES ON BASIC RATES DATA RATES"

Transcription

1 d ÀA À ÀÆä E ÁS WATER RESOURCES DEPARTMENT SCHEDULE OF RATES FOR THE YEAR : CONTENTS PAGES REFERENCE DATA NOTES ON BASIC RATES DATA RATES ANNEXURES zàgà ÀnÖ À«Äw ÄAzÀ ÀjµÀÌj À ànöz REVISED BY SCHEDULE OF RATES COMMITTEE 1

2 2

3 - REFERENCE DATA FOR THE YEAR : COST OF MATERIALS: 1 Acetylene gas per cum Rs: Air hose 25 mm dia per Rm Rs: Binding wire per kg Rs: Cement 43 Gr per kg Rs: Coarse aggregate mm / cum Rs: Coarse aggregate mm / cum Rs: Coarse aggregate40-20 mm / cum Rs: Concrete admixture( Super plasticiser ) per ltr Rs: Cross bit ( TC ) 75 mm dia per No. Rs: Detonating fuse coil per Rm Rs: Detonator delay type per No. Rs: Detonator electric per No. Rs: Detonator ordinary per No. Rs: Explosive ( small dia ) per kg Rs: Extension rod with coupling sleeve per Rm Rs: Fine aggregate/ sand ( screened ) per cum Rs: G I Pipe 80 mm dia per Rm Rs: G I Pipe100 mm dia per Rm Rs: G.I. Bolts and Nuts per kg Rs: Guniting nozzle per No. Rs: Jungle wood planks per cum Rs: Jack hammer drill rod 1.5 m per No. Rs: Jack hammer drill rod 2.5 m per No. Rs: M S Bolts & Nuts per kg Rs: Oxygen gas per cum Rs: Plain G.I. Sheet per tonne Rs: Rails 30 kg / m per tonne Rs: Reinforcement steel per kg Rs: Resin bond cement grout capsule per No. Rs: Rivets per kg Rs: Shalimastic sealing compound per kg Rs: Shutter oil per ltr Rs: Stone chips at dump yard per cum Rs: Structural steel angle / channel / beam / bar per kg Rs: Structural steel plate / flat per kg Rs: Un-coursed rubble stones at dump yard per cum Rs: Water hose 20 mm dia per Rm Rs: Welding electrodes ( general purpose ) per No. Rs: Wire rope per kg Rs: ROYALTY CHARGES : Per tonne 1 Sand / Fine aggregate Rs: Stone / Coarse aggregate / Chips Rs:

4 LEAD, LOADING & UNLOADING CHARGES: 1 km lead Loading Unloading 1 Cement Rs: Earth / Sand / Gravel Rs: Steel Rs: Stone / Coarse aggregate Rs: HIRE CHARGES OF MACHINERY: Hire charge Fuel charge Crew charges 1 Agitator car truck mounted per hour Rs: Air compressor 15 cmm ( ele ) per hour Rs: Air compressor 8.5 cmm ( ele ) per hour Rs: Bending machine per hour Rs: Batching plant 6 cum / hr rated capacity Rs: Concrete pneumatic placer pump per hour Rs: Convey mucker per hour Rs: DG set 30 KVA Rs: Diesel loco 45 hp per hour Rs: Drilling jumbo per hour Rs: Dumper 5 cum per hour Rs: Grout pump per hour Rs: Guniting equipment per hour Rs: Jack hammer per hour Rs: Pump 10 hp ( ele ) per hour Rs: Pump 20 hp ( ele ) per hour Rs: Pusher leg per hour Rs: Tipper 5 cum per hour Rs: Tipping tub 1.5 cum per hour Rs: Transformer 250 KVA per month Rs: Up-right drilling machine / Grinding machine Rs: Ventilation fan 20 hp per hour Rs: Vibrator ( ele ) per hour Rs: Waggon drill Rs: Welding transformer per hour Rs: Winch 35 hp electric per hour Rs: WAGES OF WORKERS: Per day 1 Bar bender Rs: Blasting helper Rs: Carpentor Cl- II Rs: Electrician Rs: Fitter shuttering works Rs: Mechanic Cl - I Rs: Foreman Rs: Helper fitter / erector / carpenter Rs: Khalasi Rs: Licensed Blaster Rs: Lineman Rs: Maistry Rs:

5 13 Mason Cl-I Rs: Mason Cl-II Rs: Mazdoor ( Cement handling ) Rs: Mazdoor ( Heavy) Rs: Mazdoor ( Light ) Rs: Pipe fitter Rs: Stone breaker ( Hammerman ) Rs: Stone chiseller Cl II Rs: Structural steel Marker / Erector Rs: Surveyor Rs: Tinsmith Rs: Turner / Driller Rs: Welder / Gas cutter Rs: ELECTRIC SUB-STATION MATERIALS: 1 Electric pole with fixtures per No. Rs: Flood light 500 W per Each Rs: Flood light set per Each Rs: Fluoscent tube light 40 W per Each Rs: Fluoscent tube light set per Each Rs: Circuit breaker with accessories per set Rs: HT / LT Line conductor per 1000 Rm Rs: PVC Armoured cable 10 sqmm and below per Rm Rs: PVC Armoured cable 16 sqmm per Rm Rs: PVC Armoured cable 25 sqmm per Rm Rs: PVC Armoured cable 70 sqmm per Rm Rs: Transformer 250 kva Rs: OTHER DATA : 1 Contractor's Overheads on Materials / Machinery / Labour % Contractor's Profit on Materials / Fuel & Energy charges / Labour % Demand charges on power supply per KVA / month Rs: Electric Energy charges per kwhr Rs: Insurance charges on machinery per annum % Hidden cost on Labour % Hidden cost on Labour ( additional for Tunnel works ) % Rate of interest per annum % Small Tools & Plant on Materials / Machinery / Labour % Structural steel fabrication cost per kg Rs: Sundries ( Lump sum rate for unquantified inputs ) Rs: Cost of Electric sub-station & Demand charges ( Annexure - 1 ) % Cost of Air and Water lines ( Annexure - 2 ) % Cost of Ventilation ( Annexure - 3 ) % Cost of Lighting inside / out side tunnel ( Annexure - 4 ) % Cost of Other enabling works ( Annexure - 5 ) %

6 NOTES ON SCHEDULE OF RATES FOR THE YEAR : All notes under General Notes on Schedule of Rates and Notes on Lead, Lift, Loading and un-loading Charges are applicable to Tunnel and Allied Works also to the extent they are relevant. 2. The basic rates are inclusive additional costs for working inside tunnel. 3. The basic rates are inclusive of scaling loose material, removal of under-cuts, cleaning bed and lighting and ventilation inside tunnel. 4. Unless otherwise specified the basic rates are inclusive of all lifts. 5. Unless otherwise specified the basic rates are inclusive of standard finish required for concrete surface. 6. For excavation and concrete lining works of approach / exit channels the basic rates as provided under ' Canal and allied works ' and ' Canal cross drainage works ' shall be adopted. 7. For intake structure, tunnel portals, retaining walls, pitching etc., the rates as provided under ' Dam and allied works ' shall be adopted. 8. The lead charges, wherever applicable, for all materials under various items shall be considered only between quarry/ source of supply and batching plant / fabrication site. Further conveyance of concrete / fabricated parts / other materials upto final placing site inside tunnel is included in the basic rates upto 1 km. 9. Cement content specified for cement concrete works in the item description is based on theoritical design mix computations and is exclusive of wastage and requirement for any incidentals. The actual cement content may vary based on trial mix studies. A suitable clause shall be included in tender for regulating payment for any upword or downword variation in cement content. 10. The quantities of materials including wastage, requirements for incidentals etc., for working out additional lead charges shall be as per the statement of requirement of materials under this section. 6

7 - DATA RATES SECTION:. YEAR: ITEM No: 1 ITEM: Excavation for adit by tunnelling methods in all types of rock including cost of all materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and hauling the excavated muck outside adit upto specified dump area and all other ancillary operations etc., complete with initial lead upto 500 m and all lifts. DATA:Size of adit assumed ( finished section ) : 4.50 m dia Shape of adit assumed for excavation : D - shape Height of adit assumed ( finished section ) : 4.50 m Pay-line margin assumed : 0.20 m Diameter of adit upto pay line for excavation : 4.90 m Distance of dump yard from face : within 500 m Haulage of excavated muck : By dumpers Excavated profile Pay line Minimum excavation line TYPICAL CROSS SECTION OF ADIT / TUNNEL 1. Checking alignment and marking hole locations : Deploy drilling jumbo for 1 hour for marking hole locations. 2. Drilling holes : Full face method of excavation is assumed. Area of adit upto pay-line ( 0.5 x x 4.9 x 4.9 )+( 4.9 x 2.45 ) : sqm The drilling pattern for excavation of tunnel / adit depends on the size and shape of tunnel, rock formation, type of explosive and the fragmentation of rock required to suite the type of mucking equipment. The drilling pattern shall ensure minimum over-break. Cut holes Easers Trimmers TYPICAL DRILLING PATTERN FOR ADIT / TUNNEL 7

8 Generally, the cut holes and easers will be spaced at 650 to 750 mm grid and the trimmers will be spaced at 500 to 600 mm apart along the periphery of excavation area. Considering this, the number of holes for tunnel excavation will be generally in the range of 2.5 to 3 per sqm of cross sectional area upto pay line for small tunnels ( cross sectional area less than 45 sqm ) and in the range of 2.0 to 2.5 per sqm of cross sectional area for large tunnels. For rate analysis 2.5 holes per sqm of cross sectional area upto pay line considered for adit. Number of holes for full face excavation ( x 2.5 ) : 54 Nos Depth of holes : 2 m Extra drilling considered at 10 percent for inclined cut holes and for any secondary blasting of large fragments during mucking. Depth of drilling for 54 holes ( 54 x 2 x 1.10 ) : 119 m Average rate of drilling per hour per jack hammer : 5 m Time for 4 jack hammers with pusher leg for drilling. ( 119 / 4 / 5 ) say : 6 hours Time for 1 air compressor 15 cmm for air supply to 4 jack hammers : 6 hours Time for drilling jumbo for drilling : 6 hours Time for 10 hp pump for water supply to drilling work. : 6 hours 3. Loading explosive and blasting : Depth of pull per blast for 2 m deep holes : 1.80 m Quantity of in-situ excavation per blast ( x 1.80 ) : 38.6 cum Quantity of explosive small dia per 1.00 kg per cum : 38 kg Quantity of explosive for secondary 5 % : 2 kg Quantity of delay detonators per blast : 54 Nos. Quantity of electric detonators for secondary blasting ( LS ) : 5 Nos. Fuse coil : 120 Rm Time for drilling jumbo for loading explosives. : 1 hour 4. Defuming and scaling loose materials: No machinery other than ventilation fans are required. For defuming adit ventilation fans are installed in duct system at about 300 m interval and are run for about 1 hour after each blast. Consider 20 hp fan 1 No. for 1 hour for defuming. 5. Mucking excavated rock : Quantity of muck to be removed per blast considering 40 % bulkage : 54 cum Capacity of dumper per load : 5.00 cum Quantity of muck per load considered under adit working conditions : 4.50 cum Loading cycle time: Turning / moving and spotting : 1 minute Loading muck by convey mucker and work force : 20 minutes Cycle time of loading dumper per load of 4.50 cum : 21 minutes Haulage cycle time: Running time from loading point to dump av 10 km / hr : 3.0 minutes Turning and unloading : 2.0 minutes Return trip to reversing av 15 km / hr : 2.0 minutes Cycle time for haulage per load of 4.5 cum : 7.0 minutes Since the waiting time will be more than the running time if 2 dumpers are deployed deploy 1 dumper for conveying muck. Round trip cycle time of dumper say : 30 minutes Quantity of muck disposal per hour / dumper : 9.00 cum Time for 1 dumper for conveying 9 cum per hour : 6 hours Time for convey mucker and labour force for loading : 6 hours 8

9 6. Overall cycle time : Checking alignment and marking hole locations : 2.00 hours Drilling holes : 6.00 hours Loading explosive and blasting : 2.00 hours Defuming and scaling loose rock fragments : 2.00 hours Mucking excavated rock : 6.00 hours Bed cleaning, support fixing, rock bolting, lighting etc say : 6.00 hours Total cycle of excavation per blast of 1.8 m length : hours 7. Requirement of materials : Explosive small dia ( ) : 40 kg Electric short delay detonators ( 54 x 1 ) : 54 Nos Electric detonators for secondary blasting ( 1 x 5 ) : 5 Nos Fuse coil : 120 Rm 8. Requirement of machinery : Deploy drilling jumbo for marking (1 hr) / drilling (6 hrs) / loading explosive (1 hr) : 8 hours Deploy air compressor 15 cmm for air supply to 4 jack hammers : 6 hours Deploy 4 jack hammers with pusher leg for drilling. : 6 hours Deploy 10 hp pump for water supply to drilling work. : 6 hours Deploy 20 hp ventilation fan for defuming : 1 hour Deploy convey mucker for loading excavated rock : 6 hours Deploy 1 dumper for conveying muck : 6 hours 9. Requirement of workforce ( other than machinery crew ) : Surveyor for checking alignment and marking hole locations for drilling : 0.5 No. Foreman for supervising drilling of holes and other operations : 1 No. Fitter / Mechanic for extending air / water lines : 2 Nos. Blaster ( Licensed ) : 1 No. Helper blasting : 2 Nos. Hammerman for scaling : 2 Nos. Maistry 1 in each shift : 3 Nos. Khalasi for mucking shift : 4 Nos. Heavy mazdoor for mucking shift : 4 Nos. for other 2 shifts 1 No each shift : 2 Nos. Light mazdoor for cleaning & miscellaneous : 1 No. 10. Use rate of materials: Cost of drill rod 2.5 m Rs: / No. Rs: Life of drill rod with reconditionong : 150 m Use rate of drill rod per Rm drilling ( cost / life ) Rs: Length of air and water hose assumed : 25 m each Cost of 25 mm dia air hose 25 Rs: / Rm Rs: Life of air hose : 800 hours Use rate of air hose per hour ( cost / life ) Rs: 5.16 Cost of water hose 25 m Rs: / Rm Rs: Life of water hose : 800 hours Use rate of water hose per hour ( cost / life ) Rs:

10 RATE ANALYSIS UNIT : cum A. MATERIALS: Sl No Perticulars 1 Small dia explosive kg Delay detonators Nos Electric detonators Nos Detonating fuse coil Rm Use rate of drill rod 2.5 m long Rm Reconditioning 10% Use rate of air hose Hour Use rate of water hose Hour Sundries( paint / template etc ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for Contractor's 5% Rs: Total cost of Materials : Rs: B. MACHINERY: 1 Drilling jumbo Hour Fuel / Energy charges Hour Air compressor 15 cmm ( ele ) Hour Fuel / Energy charges Hour Jack hammer ( 4 x 6 hrs ) Hour Fuel / Energy charges Hour Pusher leg Hour Fuel / Energy charges Hour Convey mucker Hour Fuel / Energy charges Hour Dumper ( 1 x 6 hrs ) Hour Fuel / Energy charges Hour Pump 10 hp ( ele ) ( 1 x 6 hrs ) Hour Fuel / Energy charges Hour Ventilation fans 20 hp ( 1 x 1 hr ) Hour Fuel / Energy charges Hour Sundries(explosive van / magazine ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's Profit on DPOL / 10% Rs: Add for Contractor's 5% Rs: Total hire charges of Machinery : Rs: C. LABOUR: 1 Crew for Drilling jumbo Hour

11 C. LABOUR ( ) : 2 Crew for Air compressor Hour Crew for Jack hammer Hour Crew for Convey mucker Hour Crew for Dumper Hour Crew for Pump Hour Crew for ventilation fans Hour Surveyor Day Foreman Day Fitter / Mechanic Day Blaster ( Licensed ) Day Helper blasting Day Hammerman Day Maistry 1 in each shift Day Khalasi for mucking shift 4 Nos Day Heavy mazdoor for mucking shift 4 Nos Day for other 2 shifts 1 No each shift Day Light mazdoor for cleaning & miscellaneous Day Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for hidden cost on 15% Rs: Add for additional hidden cost on 10% Rs: Add for Contractor's 5% Rs: Total cost of Labour : Rs: ABSTRACT: A. Cost of Materials Rs: B. Hire charges of Machinery Rs: C. Cost of Labour Rs: TOTAL Rs: Add for Air and Water 0.50% Rs: Add for 6.10% Rs: Add for 1.90% Rs: Add for Ele sub-station / Demand 3.90% Rs: Add for other Enabling 1.70% Rs: Total cost for cum Rs: Rate per cum Rs: Rate approved per cum Rs: SECTION:. YEAR: ITEM No: 2 ITEM: Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all materials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting, 11

12 drainage, removing and hauling excavated muck outside shaft upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. DATA:Size of shaft assumed : 5.00 m dia Shape of shaft assumed for excavation : Circular Depth of shaft assumed : m Pay-line margin assumed : 0.20 m Diameter of shaft upto pay line for excavation : 5.40 m Distance of dump yard from face : within 500 m Average lift assumed for excavation of shaft upto tunnel level : 40 m 1. Checking alignment and marking hole locations : Use of winch & cradle during marking hole locations : 1 hour 2. Drilling holes : Area of excavation upto payline ( x 5.4 x 5.4 ) : sqm Depth of drilling : 1.50 m Depth of pull : 1.30 m No.of peripheral 0.65 m spacing ( 20 times dia ) : 24 Nos. No. of holes in shaft 2 per sqm ( x 5 x 5 x 2 ) : 40 Nos. Depth of drilling for 64 holes ( 64 x 1.5 ) : 96 m Extra drilling considered at 5 percent for secondary blasting of large fragments. Total depth of drilling ( 96 x 1.05 ) say : 101 m Average rate of drilling per hour per jack hammer : 5 m Time for 4 jack hammers for drilling. ( 101 / 4 / 5 ) say : 5 hours Time for 1 air compressor 15 cmm for air supply to 4 jack hammers : 5 hours Time for 10 hp pump for pumping water to storage tank. : 5 hours Time for 20 hp sludge pump for removing drill water from pit : 2 hours Total time for drilling including preparation for drilling : 5 hours 3. Loading explosive and blasting : Quantity of in-situ excavation per blast ( x 1.30 ) : 30 cum Quantity of explosive small dia per 1.0 kg per cum : 30 kg Quantity of explosive for secondary 5 % : 2 kg Quantity of electric detonators for blasting : 69 Nos. Detonating fuse coil : 120 Rm Use of winch & cradle during loading of explosives : 1 hour 4. Defuming shaft: Generally for shafts defuming is carried out by leaving compressed air by air hose for about 0.5 hour to remove blasting gases and dust. Use air compressor for 0.5 hour. 5. Mucking excavated rock : Winch and 0.5 cum bottom / side opening bucket are considered for removing the muck from shaft and rail mounted tipping tubs are considered for further haulage and disposal. Quantity of muck to be removed per blast considering 40 % bulkage : 42 cum Deploy 8 heavy mazdoors for mucking in the shaft. Consider out-put of each mazdoor at 3 cum / day for working on rocky surface. Time for loading 0.5 cum bucket ( 0.5 x 8 x 60 / 3 / 8 ) : 10 min Cycle time for operating mucking bucket by winch : Lowering bucket by 15 m / minute for av. 40 m : 3.00 min Loading muck by work force : min Lifting by 15 m / minute for av. 40 m : 3.00 min Unloading to tipping tub : 1.50 mun 12

13 Over all cycle time for mucking 0.5 cum by deploying 2 buckets say : min Quantity of muck per mucking bucket : 0.50 cum Time required for mucking 42 cum ( 42 x 10 / 0.50 / 60 ) : 14 hours Considering time for shift change etc., total time required for mucking : 16 hours Considering use of winch during marking / drilling / blasting / time for shift change / etc., deploy winch for 24 hours with fuel / energy charges for 16 hours. Use 2 mucking buckets for 16 hours for removing muck from shaft. Use 1 tipping tub for 16 hours for disposal of muck outside shaft. 6. Overall cycle time : Marking hole locations and preparation for drilling : 0.50 hours Drilling holes : 5.00 hours Loading explosive and blasting : 2.00 hours Defuming by leaving compressed air : 0.50 hours Mucking excavated rock : hours Total cycle of excavation per blast of 1.3 m depth : hours 7. Requirement of materials : Explosive small dia ( ) : 32 kg Electric detonators for main / secondary blasting ( ) : 69 Nos Fuse coil : 120 Rm 8. Requirement of machinery : Deploy winch for various operations : 24 hours ( marking holes 1 hr + drilling 5 hrs + loading explosives 1 hr + mucking 16 hrs + misc 1 hr) Deploy air compressor 15 cmm for air supply to 4 jack hammers : 5.5 hours ( drilling 5 hrs + defuming 0.5 hr ) Deploy 4 jack hammers for drilling. : 5 hours Deploy 10 hp pump for water supply to drilling work. : 5 hours Deploy 20 hp sludge pump for removing drill water : 2 hours Deploy 1 tipping tub for conveying muck : 16 hours 9. Requirement of workforce ( other than machinery crew ) : Surveyor for checking alignment and marking hole locations for drilling : 0.5 No. Foreman for supervising winch and other operations ( 1 in each shift ) : 3 Nos. Fitter / Mechanic for arranging air / water lines / sludge pump etc. : 2 Nos. Blaster ( Licensed ) : 1 No. Helper blasting : 2 Nos. Hammerman for scaling / breaking large stones ( 4 in 2 mucking shifts ) : 4 Nos. Maistry ( 1 in each shift ) : 3 Nos. Khalasi ( 8 in 2 mucking shifts ) : 8 Nos. Heavy mazdoor for mucking shift ( 8 in each shift for 2 shifts ) : 16 Nos. for other 1 shift ( 2 Nos ) : 2 Nos. Light mazdoor for cleaning & miscellaneous : 2 Nos. 10. Use rate of materials: Cost of drill rod 1.5 m Rs: / No. Rs: Life of drill rod with reconditioning : 150 m Use rate of drill rod per Rm drilling ( cost / life ) Rs: Length of air and water hose assumed : 100 m each 13

14 Cost of 25 mm dia air hose 100 Rs: / Rm Rs: Life of air hose : 800 hours Use rate of air hose per hour ( cost / life ) Rs: Cost of water hose 100 m Rs: / Rm Rs: Life of water hose : 800 hours Use rate of water hose per hour ( cost / life ) Rs: 17.5 Quantity of rails for haulage of tubs Haulage track outside : 2 x 150 m Weigth of 30R rails 300 m 30 kg / Rm : 9 tonnes Cost of 30 R rails 300 Rs: / tonne Rs: Add for 25% Rs: Total Rs: Less salvage 10% ( - ) Rs: Total Rs: Life of rails under tunnel working conditions : 15 years Use rate of rails per year ( cost / life ) Rs: Add for repairs & 10% Rs: Total Rs: Use rate of rails per shift considering 300 working days Rs: Consider use of rail track for 24 hours. Length of 16 mm dia wire rope for winch assuming 80 m deep shaft : 150 m Cost of wire rope 150 m ( 160 kg Rs: / kg Rs: Life of wire rope for lifting : 2500 hours Use rate of wire rope per hour ( cost / life ) Rs: 7.36 Weight of mucking bucket : 250 kg Cost of steel 75 Rs: / kg Rs: Cost of steel 25 Rs: / kg Rs: Cost of Rs: / kg Rs: Total Rs: Add for hooks / door arrangements 25% Rs: Total Rs: Less salvage 10% ( - ) Rs: Add for repairs / maintenance 10% Rs: Total Rs: Life of mucking bucket assumed : 2500 hours Use rate of mucking bucket per hour ( cost / life ) Rs: 6.80 RATE ANALYSIS UNIT : cum A. MATERIALS: Sl No Perticulars 1 Small dia explosive kg Electric detonator Nos Detonating fuse coil Rm Use rate of drill rod 1.5 m long Rm Reconditioning 10% Use rate of air hose ( 4 x ) Hour Use rate of water hose ( 4 x 5 ) Hour Use rate of rail track Shift Use rate of wire rope Hour

15 A. MATERIALS ( ) : Sl No Perticulars 9 Use rate of mucking bucket ( 2 x 16 ) Hour Sundries ( paint / template etc ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for Contractor's 5% Rs: Total cost of Materials : Rs: B. MACHINERY: 1 Air compressor 15 cmm ( ele ) Hour Fuel / Energy charges Hour Jack hammer ( 4 x 5 hrs ) Hour Fuel / Energy charges Hour Pump 10 hp ( ele ) Hour Fuel / Energy charges Hour Sludge pump 20 hp electric Hour Fuel / Energy charges Hour Winch 35 hp electric Hour Fuel / Energy charges Hour Tipping tub 1.5 cum Hour Fuel / Energy charges Hour Sundries ( explosive van / magazine ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's Profit on DPOL / 10% Rs: Add for Contractor's 5% Rs: Total hire charges of Machinery : Rs: C. LABOUR: 1 Crew for Air compressor Hour Crew for Jack hammer Hour Crew for Pump 10 hp Hour Crew for Sludge pump 20 hp Hour Crew for Winch Hour Surveyor Day Foreman Day Fitter / Mechanic Day Blaster ( Licensed ) Day Helper blasting Day Hammerman 2 Nos each for 2 shifts Day Maistry 1 in each shift Day

16 C. LABOUR ( ) : 13 Khalasi for mucking 4 Nos each for 2 shifts Day Heavy mazdoor for mucking 8 Nos each for 2 shifts Day for other 1 shift 2 Nos Day Light mazdoor for cleaning & miscellaneous Day Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for hidden cost on 15% Rs: Add for additional hidden cost on 10% Rs: Add for Contractor's 5% Rs: Total cost of Labour : Rs: ABSTRACT: A. Cost of Materials Rs: B. Hire charges of Machinery Rs: C. Cost of Labour Rs: TOTAL Rs: Add for Air and Water 0.50% Rs: Add for 0.00% Rs: 0.00 Add for 1.90% Rs: Add for Ele sub-station / Demand 3.90% Rs: Add for other Enabling 1.70% Rs: Total cost for cum Rs: Rate per cum Rs: Rate approved per cum Rs: SECTION:. YEAR: ITEM No: 3 ITEM: Excavation for tunnel by tunnelling methods in rock not requiring supports including cost of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation, lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia Shape of tunnel assumed for excavation : D - shape Height of tunnel assumed ( finished section ) : 4.50 m Length of tunnel assumed : 1000 m Thickness of CC lining : 0.30 m Pay-line margin assumed : 0.20 m Diameter of tunnel upto pay line for excavation : 5.50 m Distance of dump yard from face including approach / adit length : Average 1 km Haulage of excavated muck : By dumpers 16

17 Concrete lining Excavated profile Pay line Minimum excavation line Finished tunnel line TYPICAL CROSS SECTION OF TUNNEL 4.50 m dia. 1. Checking alignment and marking hole locations : Use of drilling jumbo for marking hole locations : 1 hour 2. Drilling holes : Area of tunnel upto pay-line( 0.5 x x 5.5 x 5.5 )+( 5.5 x 2.75 ) : sqm The number of holes for tunnel excavation will be generally in the range of 2.5 to 3.0 per sqm of cross sectional area upto pay line for tunnel upto 45 sqm and in the range of 2.0 to 2.5 per sqm of cross sectional area upto pay line for tunnel exceeding 45 sqm. For rate analysis 2.5 holes per sqm of cross sectional area considered. Number of holes for full face excavation ( 27 x 2.5 ) : 68 Nos Depth of holes : 2 m Extra drilling considered at 10 percent for inclination of holes and for removal of any under cuts and for secondary blasting of large fragments during mucking. Depth of drilling for 68 holes ( 68 x 2 x 1.10 ) : 150 m Average rate of drilling per hour per jack hammer : 5 m Time for 4 jack hammers with pusher leg for drilling. ( 150 / 4 / 5 ) say : 7.5 hours Time for 1 air compressor 15 cmm for air supply to 4 jack hammers : 7.5 hours Time for drilling jumbo for drilling : 8 hours Time for 10 hp pump for water supply to drilling work. : 7.5 hours 3. Loading explosive and blasting : Depth of pull per blast for 2 m deep holes : 1.80 m Quantity of in-situ excavation per blast ( x 1.80 ) : 49 cum Quantity of explosive small dia per 1.00 kg per cum : 49 kg Quantity of explosive for under cuts secondary 10 % : 5 kg Quantity of delay detonators per blast : 68 Nos. Quantity of electric detonators for secondary blasting ( LS ) : 10 Nos. Detonating fuse coil ( LS ) : 160 Rm Time for drilling jumbo for loading explosives : 1.5 hour 4. Defuming and scaling loose materials: No machinery other than ventilation fans required. For defuming tunnel ventilation fans are installed in duct system at about 300 m interval and are run for about 1 hour after each blast. For 1 km length of tunnel ventilation fans are required at 4 places at 300 m interval. As the fans are installed progressively, for rate analysis consider average 2 fans for 1 hour. 5. Mucking excavated rock : Quantity of muck to be removed per blast considering 40 % bulkage : 69 cum Capacity of dumper per load : 5.00 cum Quantity of muck per load considered under tunnel working conditions : 4.50 cum 17

18 Loading cycle time: Moving from turning pocket position and spotting : 1 minutes Loading muck by convey mucker and work force : 20 minutes Time for loaded dumper to pass waiting point say : 1 minutes Cycle time of loading dumper per load of 4.50 cum : 22 minutes Haulage cycle time: Running time from loading point to dump yard at av. 10 km / hr : 6 minutes Turning and unloading : 2 minutes Return trip to waiting av. 15 km / hr : 4 minutes Waiting time before spotting : 9 minutes Cycle time for haulage per load of 4.5 cum : 21 minutes Round trip cycle time of dumper ( ) say : 45 minutes Quantity of muck disposal per hour / dumper : 6.00 cum Deploy 2 dumpers for conveying 12 cum per hour say : 6 hours Deploy convey mucker and labour force for loading : 6 hours 6. Overall cycle time : Checking alignment and marking hole locations : 2.00 hours Drilling holes : 7.50 hours Loading explosive and blasting : 2.00 hours Defuming and scaling loose rock fragments : 2.00 hours Mucking excavated rock : 6.00 hours Bed cleaning, support fixing, rock bolting, lighting etc say : 4.50 hours Total cycle of excavation per blast of 1.8 m length : hours 7. Requirement of materials : Explosive small dia ( ) : 32 kg Electric short delay detonators ( 68 x 1 ) : 68 Nos Electric detonators for secondary blasting ( 10 x 1 ) : 10 Nos Fuse coil : 160 Rm 8. Requirement of machinery : Deploy drilling jumbo for various operations 11 hours ( marking holes 1 hr + drilling 7.5 hrs + loading explosives 1.5 hrs + misc 1 hr ) Deploy air compressor 15 cmm for air supply to 4 jack hammers : 7.5 hours Deploy 4 jack hammers with pusher leg for drilling. : 7.5 hours Deploy 10 hp pump for water supply to drilling work. : 7.5 hours Deploy 20 hp ventilation fan for defuming : 2 hours Deploy convey mucker for loading excavated rock : 6 hours Deploy 2 dumper for conveying muck : 6 hours 9. Requirement of workforce ( other than machinery crew ) : Surveyor for checking alignment and marking hole locations for drilling : 1 No. Foreman for supervising drilling of holes and other operations : 1 No. Fitter / Mechanic for extending air / water lines : 2 Nos. Blaster ( Licensed ) : 1 No. Helper blasting : 2 Nos. Hammerman for scaling : 2 Nos. Maistry 1 in each shift : 3 Nos. Khalasi for mucking shift : 4 Nos. 18

19 Heavy mazdoor : for mucking shift : 8 Nos. for other 2 shifts 2 No each shift : 4 Nos. Light mazdoor : for cleaning & miscellaneous : 2 Nos. 10. Use rate of materials: Cost of drill rod 2.5 m Rs: / No. Rs: Life of drill rod with reconditioning : 150 m Use rate of drill rod per Rm drilling ( cost / life ) Rs: Length of air and water hose assumed : 25 m each Cost of 25 mm dia air hose 25 Rs: / Rm Rs: Life of air hose : 800 hours Use rate of air hose per hour ( cost / life ) Rs: 5.16 Cost of water hose 25 m Rs: / Rm Rs: Life of water hose : 800 hours Use rate of water hose per hour ( cost / life ) Rs: 4.38 RATE ANALYSIS UNIT : cum A. MATERIALS: Sl No Perticulars 1 Small dia explosive kg Delay detonators Nos Electric detonators Nos Detonating fuse coil Rm Use rate of drill rod 2.5 m long Rm Reconditioning 10% Use rate of air hose Hour Use rate of water hose Hour Sundries ( paint / template etc ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for Contractor's 5% Rs: Total cost of Materials : Rs: B. MACHINERY: 1 Drilling jumbo Hour Fuel / Energy charges Hour Air compressor 15 cmm ( ele ) Hour Fuel / Energy charges Hour Jack hammer ( 4 x 7.5 hrs ) Hour Fuel / Energy charges Hour Pusher leg Hour Fuel / Energy charges Hour Convey mucker Hour Fuel / Energy charges Hour

20 B. MACHINERY ( ) : 6 Dumper ( 2 x 6 hrs ) Hour Fuel / Energy charges Hour Pump 10 hp ( ele ) Hour Fuel / Energy charges Hour Ventilation fans 20 hp ( 2 x 1 ) Hour Fuel / Energy charges Hour Sundries ( explosive van / magazine ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's Profit on DPOL / 10% Rs: Add for Contractor's 5% Rs: Total hire charges of Machinery : Rs: C. LABOUR: 1 Crew for Drilling jumbo Hour Crew for Air compressor Hour Crew for Jack hammer Hour Crew for Convey mucker Hour Crew for Dumper Hour Crew for Pump Hour Crew for ventilation fans Hour Surveyor Day Foreman Day Fitter / Mechanic Day Blaster ( Licensed ) Day Helper blasting Day Hammerman Day Maistry 1 in each shift Day Khalasi for mucking shift 4 Nos Day Heavy mazdoor for mucking shift 8 Nos Day for other 2 shifts 2 No each shift Day Light mazdoor for cleaning & miscellaneous Day Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for hidden cost on 15% Rs: Add for additional hidden cost on 10% Rs: Add for Contractor's 5% Rs: Total cost of Labour : Rs:

21 ABSTRACT: A. Cost of Materials Rs: B. Hire charges of Machinery Rs: C. Cost of Labour Rs: TOTAL Rs: Add for Air and Water 0.50% Rs: Add for 6.10% Rs: Add for 1.90% Rs: Add for Ele sub-station / Demand 3.90% Rs: Add for other Enabling 1.70% Rs: Total cost for cum Rs: Rate per cum Rs: Rate approved per cum Rs: SECTION:. YEAR: ITEM No: 4 ITEM: Excavation for tunnel by tunnelling methods including excavation for supports in all types of soil / rock strata requiring supports ( excluding cost of providing supports ) including cost of all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia Shape of tunnel assumed for excavation : D - shape Height of tunnel assumed ( finished section ) : 4.50 m Length of tunnel assumed : 1000 m Thickness of CC lining : 0.30 m Extra excavation for supports : 0.25 m Pay-line margin assumed : 0.20 m Diameter of tunnel upto pay line for excavation : 6.00 m Distance of dump yard from face including approach / adit length : Average 1 km Haulage of excavated muck : By dumpers 1. Checking alignment and marking hole locations : Use drilling jumbo for 1 hour for marking hole locations. 2. Drilling holes : Area of tunnel upto pay-line (0.5x0.7857x6x6) + (6x2.75) : sqm The number of holes for tunnel excavation will be generally in the range of 2.5 to 3.0 per sqm of cross sectional area upto pay line for tunnel upto 45 sqm and in the range of 2.0 to 2.5 per sqn of cross sectional area upto pay line for tunnel exceeding 45 sqm. For rate analysis 2.5 holes per sqm of cross sectional area considered. Number of holes for full face excavation ( x 2.5 ) : 77 Nos Assuming spacing of supports at 0.75 m the depth of pull is considered at 1.5 m. Depth of holes for 1.5 m pull : 1.7 m Extra drilling considered at 10 percent for inclination of holes and for removal of any under cuts and for secondary blasting of large fragments during mucking. Depth of drilling for 77 holes ( 77 x 1.7 x 1.10 ) : 144 m Average rate of drilling per hour per jack hammer : 5 m Time for 4 jack hammers with pusher leg for drilling. : 7 hours Time for 1 air compressor 15 cmm for air supply to 4 jack hammers : : 7 hours 21

22 Time for drilling jumbo for drilling : 7 hours Time for 10 hp pump for pumping water to storage tank. : 7 hours 3. Loading explosive and blasting : Depth of pull per blast for 1.7 m deep holes : 1.50 m Quantity of in-situ excavation per blast ( x 1.50 ) : 46 cum Quantity of explosive small dia per 0.8 kg per cum : 37 kg Quantity of explosive for secondary 10 % : 4 kg Quantity of delay detonators per blast : 77 Nos. Quantity of electric detonators for secondary blasting ( LS ) : 10 Nos. Detonating fuse coil : 175 Rm Use drilling jumbo for 2 hour for loading explosives. 4. Defuming and scaling loose materials No machinery other than ventilation fans required. For defuming tunnel ventilation fans are installed in duct system at about 300 m interval and are run for about 1 hour after each blast. For 1 km length of tunnel ventilation fans are required at 4 places at 300 m interval. As the fans are installed progressively, for rate analysis consider average 2 fans for 1 hour. 5. Mucking excavated rock : Quantity of muck per blast considering 40 % bulkage ( 46 x 1.4 ) : 65 cum Capacity of dumper per load : 5 cum Quantity of muck per load considered under tunnel working conditions : 4.5 cum Loading cycle time: Moving from pocket position and spotting : 1 minutes Loading muck by convey mucker and work force : 20 minutes Time for loaded dumper to pass waiting point say : 1 minutes Cycle time of loading dumper per load of 4.5 cum : 22 minutes Haulage cycle time: Running time from loading point to dump yard at av. 10 km / hr : : 6 minutes Turning and unloading : 2 minutes Return trip to waiting av. 15 km / hr : 4 minutes Waiting time before spotting : 9 minutes Cycle time for haulage per load of 4.5 cum Total : 21 minutes Round trip cycle time of dumper say : 45 minutes Quantity of muck disposal per hour / dumper : 6 cum Time for 2 dumpers for conveying 12 cum per hour say : 6 hours Time for convey mucker and labour force for loading say : 6 hours 6. Overall cycle time : Checking alignment and marking hole locations : 2.00 hours Drilling holes : 7.00 hours Loading explosive and blasting : 2.00 hours Defuming and scaling loose rock fragments : 2.00 hours Mucking excavated rock : 6.00 hours Bed cleaning, Jumbo movements, rock bolting, lighting etc say : 4.00 hours Erection of temperary / permanent supports : 9.00 hours Total cycle of excavation & supporting / blast of 1.5 m length : hours 7. Requirement of materials : Explosive small dia ( ) : 41 kg Electric short delay detonators ( 77 x 1 ) : 77 Nos Electric detonators for secondary blasting ( 1 x 5 ) : 10 Nos Fuse coil : 175 Rm 22

23 8. Requirement of machinery : Deploy drilling jumbo for various operations 11 hours ( marking holes 1 hr + drilling 7 hrs + loading explosives 2 hr + misc 1 hr ) Deploy air compressor 15 cmm for air supply to 4 jack hammers : 7 hours Deploy 4 jack hammers with pusher leg for drilling. : 7 hours Deploy 10 hp pump for water supply to drilling work. : 7 hours Deploy 20 hp ventilation fan for defuming ( 2 x 1 ) : 1 hour Deploy convey mucker for loading excavated rock : 6 hours Deploy 2 dumper for conveying muck : 6 hours 9. Requirement of workforce ( other than machinery crew ) : Surveyor for checking alignment and marking hole locations for drilling : 1 No. Foreman for supervising drilling of holes and other operations : 1 No. Fitter / Mechanic for extending air / water lines : 2 Nos. Blaster ( Licensed ) : 1 No. Helper blasting : 2 Nos. Hammerman for scaling : 2 Nos. Maistry 1 in each shift : 3 Nos. Khalasi for mucking shift : 4 Nos. Heavy mazdoor for mucking shift : 8 Nos. for other 2 shifts 1 No each shift : 4 Nos. Light mazdoor for cleaning & miscellaneous : 3 Nos. 10. Use rate of materials: Cost of drill rod 2.5 m Rs: / No. Rs: Life of drill rod with reconditioning : 150 m Use rate of drill rod per Rm drilling ( cost / life ) Rs: Length of air and water hose assumed : 25 m each Cost of 25 mm dia air hose 25 Rs: / Rm Rs: Life of air hose : 800 hours Use rate of air hose per hour ( cost / life ) Rs: 5.16 Cost of water hose 25 m Rs: / Rm Rs: Life of water hose : 800 hours Use rate of water hose per hour ( cost / life ) Rs: 4.38 RATE ANALYSIS UNIT : cum A. MATERIALS: Sl No Perticulars 1 Small dia explosive kg Delay detonators Nos Electric detonators Nos Detonating fuse coil Rm Use rate of drill rod 2.5 m long Rm Reconditioning 10% Use rate of air hose Hour

24 A. MATERIALS ( ) : Sl No Perticulars 7 Use rate of water hose Hour Sundries( paint / template etc ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for Contractor's 5% Rs: Total cost of Materials : Rs: B. MACHINERY: 1 Drilling jumbo Hour Fuel / Energy charges Hour Air compressor 15 cmm ( ele ) Hour Fuel / Energy charges Hour Jack hammer ( 4 x 7 hrs ) Hour Fuel / Energy charges Hour Pusher leg Hour Fuel / Energy charges Hour Convey mucker Hour Fuel / Energy charges Hour Dumper ( 2 x 6 hrs ) Hour Fuel / Energy charges Hour Pump 10 hp ( ele ) Hour Fuel / Energy charges Hour Ventilation fans 20 hp ( 2 x 1 hr ) Hour Fuel / Energy charges Hour Sundries(explosive van / magazine ) LS Total Rs: Add for small Tools and 1% Rs: Add for Contractor's Profit on DPOL / 10% Rs: Add for Contractor's 5% Rs: Total hire charges of Machinery : Rs: C. LABOUR: 1 Crew for Drilling jumbo Hour Crew for Air compressor Hour Crew for Jack hammer Hour Crew for Convey mucker Hour Crew for Dumper Hour Crew for Pump Hour Crew for ventilation fans Hour Surveyor Day

25 C. LABOUR ( ) : 9 Foreman Day Fitter / Mechanic Day Blaster ( Licensed ) Day Helper blasting Day Hammerman 2 Nos Day Maistry 1 in each shift Day Khalasi for mucking shift 4 Nos Day Heavy mazdoor for mucking shift 8 Nos Day for other 2 shifts 2 No each shift Day Light mazdoor for cleaning & miscellaneous Day Total Rs: Add for small Tools and 1% Rs: Add for Contractor's 10% Rs: Add for hidden cost on 15% Rs: Add for additional hidden cost on 10% Rs: Add for Contractor's 5% Rs: Total cost of Labour : Rs: ABSTRACT: A. Cost of Materials Rs: B. Hire charges of Machinery Rs: C. Cost of Labour Rs: TOTAL Rs: Add for Air and Water 0.50% Rs: Add for 6.10% Rs: Add for 1.90% Rs: Add for Ele sub-station / Demand 3.90% Rs: Add for other Enabling 1.70% Rs: Total cost for cum Rs: Rate per cum Rs: Rate approved per cum Rs: SECTION:. YEAR: ITEM No: 5 ITEM: Excavation for tunnel by heading and benching tunnelling methods including excavation for supports in all types of soil / rock strata requiring supports ( excluding cost of providing supports ) for roof before benching including cost of all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muck outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia Shape of tunnel assumed for excavation : D - shape 25

26 Height of tunnel assumed ( finished section ) : 4.50 m Length of tunnel assumed : 1000 m Thickness of CC lining : 0.30 m Extra excavation for supports : 0.25 m Pay-line margin assumed : 0.20 m Diameter of tunnel upto pay line for excavation : 6.00 m Distance of dump yard from face including approach / adit length : Average 1 km Haulage of excavated muck : By dumpers 1. Checking alignment and marking hole locations : Use drilling jumbo for 1 hour for marking hole locations. 2. Drilling holes : Pay line Heading portion Excavated profile Minimum Drill holes Benching portion excavation line TYPICAL CROSS SECTION OF TUNNEL FOR HEADING & BENCHING In case of tunnel, where the height is more or where the chances of over excavation due to full face blasting is more, the excavation will be generally carried out by heading and benching method. For week strata arch rib supports are also to be erected before benching. Excavation of arch portion is carried out first and the supports are fixed wherever necessary. Depth of hole and explosive charge per cum are also controlled to minimise over excavation. Assuming spacing of arch supports at 0.75 m interval the effective depth of pull per blast is considered at 1.5 m. The depth of hole for 1.5 m pull is considered at 1.7 m. Extra drilling considered at 10 percent for inclination of holes and for removal of any under cuts and for secondary blasting of large fragments during mucking. Heading portion : Area of excavation upto payline : sqm Depth of drilling : 1.70 m No. of holes considering 2.5 holes / sqm : 35 Nos. Depth of drilling for 35 holes ( 35 x 1.7 x 1.1 ) : 65.5 m Haunch portion on either side : Area of excavation upto payline : 2.60 sqm Depth of drilling : 1.70 m No. of holes considering 3 holes / sqm : 8 Nos Depth of drilling for 8 holes ( 8 x 1.7 x 1.1 ) : 15 m Benching portion : Area of excavation upto payline ( 6 x 2.75 ) : sqm No. of holes considering 2.5 holes / sqm : 41 Nos. Depth of drilling : 1.70 m Depth of drilling for 41 holes ( 41 x 1.7 x 1.1 ) : 76.5 m Total depth of drilling ( ) : 157 m Average rate of drilling per hour per jack hammer : 5 m 26

GOVERNMENT OF KARNATAKA WATER RESOURCES DEPARTMENT SCHEDULE OF RATES TUNNEL AND ALLIED WORKS REFERENCE DATA NOTES ON BASIC RATES

GOVERNMENT OF KARNATAKA WATER RESOURCES DEPARTMENT SCHEDULE OF RATES TUNNEL AND ALLIED WORKS REFERENCE DATA NOTES ON BASIC RATES RATES IN THIS FILE ARE LINKED WITH RATES IN BASIC DATA / HIRE CHARGES / LEAD CHARGES FILES TO THE EXTENT THEY ARE RELEVANT. IN THE DIALOG BOX THAT APPEARS ON THE MONITOR SCREEN ON OPENING THIS FILE CLICK

More information

d ÀA À ÀÆä E ÁSÉ WATER RESOURCES DEPARTMENT CHAPTER- WRD: 6 SCHEDULE OF RATES TUNNEL AND ALLIED WORKS FOR THE YEAR : REFERENCE DATA

d ÀA À ÀÆä E ÁSÉ WATER RESOURCES DEPARTMENT CHAPTER- WRD: 6 SCHEDULE OF RATES TUNNEL AND ALLIED WORKS FOR THE YEAR : REFERENCE DATA d ÀA À ÀÆä E ÁSÉ WATER RESOURCES DEPARTMENT CHAPTER- WRD: 6 SCHEDULE OF RATES TUNNEL AND ALLIED WORKS FOR THE YEAR : 2016-17 CONTENTS PAGES REFERENCE DATA 1 -- 3 NOTES ON BASIC RATES 4 -- 4 DATA RATES

More information

GOVERNMENT OF KARNATAKA WATER RESOURCES DEPARTMENT SCHEDULE OF RATES CANAL AND ALLIED WORKS FOR THE YEAR : REFERENCE DATA

GOVERNMENT OF KARNATAKA WATER RESOURCES DEPARTMENT SCHEDULE OF RATES CANAL AND ALLIED WORKS FOR THE YEAR : REFERENCE DATA RATES IN THIS FILE ARE LINKED WITH RATES IN BASIC DATA / HIRE CHARGES / LEAD CHARGES FILES TO THE EXTENT THEY ARE RELEVANT. IN THE DIALOG BOX THAT APPEARS ON THE MONITOR SCREEN ON OPENING THIS FILE CLICK

More information

B.6 Construction Equipment Utilization and Workforce

B.6 Construction Equipment Utilization and Workforce Appendix B.6 Construction ment Utilization and Workforce B.6 Construction ment Utilization and Workforce To support environmental impact assessments, a preliminary estimate was prepared for construction

More information

On-the-Job Training Program. Overview of Training Programs

On-the-Job Training Program. Overview of Training Programs On-the-Job Training Program Overview of Training Programs The training programs are as follows: Code Training Program Hours (Up to) 901 Carpenter, Rough 1040 902 Concrete Finisher (Paving) 1040 903 Concrete

More information

Suggested improvements to existing decanting station at Anna stadium Trichy

Suggested improvements to existing decanting station at Anna stadium Trichy Suggested improvements to existing decanting station at Anna stadium Trichy April 2018 TECHNICAL SUPPORT UNIT: IN ASSOCIATION WITH: Document History and Status Sheet S. No. Issue Issued by Issued Date

More information

List of materials for 1Km. Of L.T line 1-Ph., 2-Wire AB cable (1 X 25+1X16) sq.mm using 8M X 200 KG. PSC Pole

List of materials for 1Km. Of L.T line 1-Ph., 2-Wire AB cable (1 X 25+1X16) sq.mm using 8M X 200 KG. PSC Pole List of materials for 1Km. Of L.T line 1-Ph., 2-Wire AB cable (1 X 25+1X16) sq.mm using 8M X 200 KG. PSC Pole 1 L.T Stay set Complete Set 5 2 7/12 GI stay wire kg 50 3 Concreting of stay NO 5 4 Stay clamp

More information

INDEX ( ( ( (Brick superstructure) Model 1 (Brick superstructure) Size: 4 feet length X 4 feet breadth X 6.5 feet height Gramalaya - Tiruchirappalli Model 1 Individual household toilet (Brick superstructure)

More information

Total Ex. Tax/VAT. (Rs.) (if any) in Rs. (Bought out/direct) length 587M 226M

Total Ex. Tax/VAT. (Rs.) (if any) in Rs. (Bought out/direct) length 587M 226M ORISSA POWER TRANSMISSION CORPORATION LIMITED Supply & Laying of 132 KV XLPE Double Circuit (4 cable per Circuit including one spare) underground 1000 Sq. mm annealed Copper XLPE EHV Cable with Associated

More information

ABSTRACT OF COST FOR PAVEMENT

ABSTRACT OF COST FOR PAVEMENT CHAPTER - 5 ABSTRACT OF COST FOR PAVEMENT Name of Work :- CONSTRUCTION OF TRANS - ARUNACHAL HIGHWAY (SH:- Road from Khodaso (Ch. 110.450 Km) to Dakte Hoj (Ch. 212.450 Km) via Sagalee, Toru, Kheel - 102.000

More information

SALE PROPOSAL ROBBINS TBM UG1B-JAIPUR

SALE PROPOSAL ROBBINS TBM UG1B-JAIPUR SALE PROPOSAL ROBBINS TBM UG1B-JAIPUR INDEX Sl No Description Remarks 1 Index 2 Specification of TBM- Robbins 3 List of Rolling Stock attached to TBM & Other Equipments SPECIFICATION OF TBM ROBBINS f 6550

More information

Sand & Gravel, Inc. Job Demands Analysis. Purpose of Activities:

Sand & Gravel, Inc. Job Demands Analysis. Purpose of Activities: Job Demands Analysis Sand & Gravel, Inc. Company: Thelen Sand & Gravel, Inc. Job Title: Maintenance / Welder Location: Maintenance Shop Classification: Regular Duty Purpose of Activities: The maintenance

More information

Working Estimate for Construction of Goat Shed II at Jaring

Working Estimate for Construction of Goat Shed II at Jaring Working Estimate for Construction of Goat Shed II at Jaring 1 Excavation of foundation in all kinds of soil including dressing & leveling the bed and depositing the soil away from working area within all

More information

CONVEYOR BELTING For The Construction Industry

CONVEYOR BELTING For The Construction Industry CONVEYOR BELTING For The Construction Industry Your Source for Construction Conveyor Belting PROFILE BELTING Profile belts contain specific patterns and have cleats for the purpose of carrying materials

More information

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate (An Undertaking of Government of Nepal) Project Management Directorate KATHMANDU VALLEY EAST AND SOUTH DISTRIBUTION SYSTEM ENHANCEMENT PROJECT (A Component of ) BIDDING DOCUMENT FOR Enhancement of Distribution

More information

WORKERS' COMPENSATION AND EMPLOYERS LIABILITY TENNESSEE NCCI CONTRACTING INDUSTRY GROUP As of March 1, 2013.

WORKERS' COMPENSATION AND EMPLOYERS LIABILITY TENNESSEE NCCI CONTRACTING INDUSTRY GROUP As of March 1, 2013. WORKERS' COMPENSATION AND EMPLOYERS LIABILITY TENNESSEE NCCI CONTRACTING INDUSTRY GROUP 50-6-113 As of March 1, 2013 Class Code Sort CODE DESCRIPTION 0042 LANDSCAPE GARDENING & DRIVERS 0050 FARM MACHINERY

More information

INDIAN INSTITUTE OF TECHNOLOGY KANPUR

INDIAN INSTITUTE OF TECHNOLOGY KANPUR INDIAN INSTITUTE OF TECHNOLOGY KANPUR Tender Notice No. 40/Elect./2018 SCHEDULE OF QUANTITY Name of Work: Electrical work for the Clean Room at NCFlexE IIT Kanpur. Name of the Contractor S. No Description

More information

PRICE BID - PART: I I

PRICE BID - PART: I I T E N D E R S P E C I F I C A T I O N NO: BHE/PW/PUR/PLT-ELE/603 FOR HANDLING AT SITE STORES/STORAGE YARD, TRANSPORTATION TO SITE OF WORK, COMPLETE ERECTION, CHECKING OF CALIBRATION, TESTING, COMMISSIONING

More information

1 GENERAL Project Description Labrador Island Transmission Link (LIL) Language and Units Site Climate Data...

1 GENERAL Project Description Labrador Island Transmission Link (LIL) Language and Units Site Climate Data... SLI Doc. No. 505573-8600-40EW-0001 02 26-Aug-2014 iii TABLE OF CONTENTS PAGE 1 GENERAL... 1 1.1 Project Description... 2 1.1.1 Labrador Island Transmission Link (LIL)... 3 1.2 Language and Units... 4 1.3

More information

T.A.T Minimum Wage Scale

T.A.T Minimum Wage Scale T.A.T Minimum Wage Scale General Construction: Construction projects that are funded by the Three Affiliated Tribes or an Enrolled member of the Fort Berthold Reservation. Rates Fringes Electrician $29.24

More information

Earthing UNIT. Learning Objectives. Introduction. To understand purpose of Earthing. To learn system of earthing.

Earthing UNIT. Learning Objectives. Introduction. To understand purpose of Earthing. To learn system of earthing. 274 Electrical Technician UNIT 10 Earthing Learning Objectives To understand purpose of Earthing. To learn system of earthing. Introduction The very purpose of earthing is to safe against dangers of shock

More information

Estimate of Under Ground Electrification Work

Estimate of Under Ground Electrification Work S.No. Description of Items Unit Rate Qty Amount 1 Supply, Installation, Testing and Commissioning of 3C x 300 Sq. mm. Al. conductor, armoured, XLPE insulated, PVC sheathed, 11KV cable in ready made underground

More information

TENDER DOCUMENT PART-II

TENDER DOCUMENT PART-II 1 NATIONAL BANK FOR AGRICULTURE AND RURAL DEVELOPMENT TAMILNADU REGIONAL OFFICE TENDER DOCUMENT PART-II (PRICE BID) Supply, Installation, Testing and Commissioning of 25 kva DG Sets with Acoustic Enclosure

More information

Tender Schedule for Electrical Works at Varagani Branch. Sl. No. Particulars Quantity Unit Rate Amount

Tender Schedule for Electrical Works at Varagani Branch. Sl. No. Particulars Quantity Unit Rate Amount Tender Schedule for Electrical Works at Varagani Branch Sl. No. 1 Particulars Quantity Unit Rate Amount SITC of following rated Indoor operated wall/floor mounted, cubicle type MV cum APFC Panel suitable

More information

SEWER AND WATERMAIN CONSTRUCTION

SEWER AND WATERMAIN CONSTRUCTION Corporate Services Fair Wage Office 18 th Floor, West Tower, City Hall Tel: 416-392-7300 Fax: 416-392-0801 Hotline: 416-392-FAIR E-mail: fairwage@toronto.ca Visit us at www.toronto.ca/fairwage FAIR WAGE

More information

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate (An Undertaking of Government of Nepal) Project Management Directorate KATHMANDU VALLEY EAST AND SOUTH DISTRIBUTION SYSTEM ENHANCEMENT PROJECT (A Component of ) BIDDING DOCUMENT FOR Enhancement of Distribution

More information

TENDER SPECIFICATION. Rayalaseema Thermal Power Project (Muddanur) V.V.Reddy Nagar, Kalamalla Post,Cuddapah Dt, AP

TENDER SPECIFICATION. Rayalaseema Thermal Power Project (Muddanur) V.V.Reddy Nagar, Kalamalla Post,Cuddapah Dt, AP TENDER SPECIFICATION BHEL: PSSR: SCT: 1336 FOR Handling at Site Stores / Storage yard, Transportation to Site of Work, Erection, Testing and Commissioning of HT and LT Electrical Package for Unit 5-1x

More information

Occupations (Construction)

Occupations (Construction) Qualification Title: Level 2 NVQ Diploma in Sub-structure Work Occupations (Construction) Pathway 1: Level 2 NVQ Diploma in Sub-structure Work Occupations (Underpinning Operations Excavated Underpinning)

More information

INDIAN INSTITUTE OF TECHNOLOGY KANPUR

INDIAN INSTITUTE OF TECHNOLOGY KANPUR INDIAN INSTITUTE OF TECHNOLOGY KANPUR Tender tice. 21/Elect./2018 SCHEDULE OF QUANTITY Name of Work: Construction of second floor above central block at ACES building (SH: Electrical works). Name of the

More information

CONDUCTOR Plain bright annealed copper! alluminium, solid! stranded conductor confirming to IS: 8130: INSULATION INNER SHEATH

CONDUCTOR Plain bright annealed copper! alluminium, solid! stranded conductor confirming to IS: 8130: INSULATION INNER SHEATH c A B L E 5 [B) Techno Flex manufacture high quality heavy duty power cable confirming to IS: 1554 (Part -1) L.T. 1100 volts grade CONSTRUCTION DETAILS:- Power Cable CONDUCTOR Plain bright annealed copper!

More information

A PROJECT PROFILE ON ROLLING SHUTTERS

A PROJECT PROFILE ON ROLLING SHUTTERS A PROJECT PROFILE ON ROLLING SHUTTERS 2010-2011 Prepared by : MSME-DEVELOPMENT INSTITUTE (GOVT. OF INDIA, MINISTRY OF MICRO, SMALL & MEDIUM ENTREPRISES) A Wing, 3 rd Floor, CGO Complex, Sanjay Place, AGRA

More information

Blank Price bid (Bill of Quantity) for Part B contract

Blank Price bid (Bill of Quantity) for Part B contract Blank Price bid (Bill of Quantity) for Part B contract First Year Second Year Third Year Sr.No Job Description UOM Qty per annum Unit rate Total Amount Qty per annum Unit rate Total Amount Qty per annum

More information

SCHEDULE OF QUANTITIES ITEM DESCRIPTION

SCHEDULE OF QUANTITIES ITEM DESCRIPTION SCHEDULE OF QUANTITIES ITEM DESCRIPTION A. SUBSTATION EQUIPMENT Suplly, installation, Testing and Commissiong of kv, 350 MVA ( 8.4 ka ), 630A, HT Panel Vacuum circuit breaker Switchboard, cubicle type,

More information

OPERATING COSTING. Q.3. Sainath Travels provide you the following in respect of a fleet of 15 taxies run by them Cost of each taxi

OPERATING COSTING. Q.3. Sainath Travels provide you the following in respect of a fleet of 15 taxies run by them Cost of each taxi PASSENGER TRANSPORT SERVICES OPERATING COSTING Q.1. Mr. A owns a bus, which runs between Mumbai and Pune and back for 10 days in a month. The distance from Mumbai to Pune is 200 kms. The bus completes

More information

Phone:

Phone: KERALA AGRICULTURAL UNIVERSITY AGRICULTURAL RESEARCH STATION MANNUTHY 68065. THRISSUR Phone: 0487-37076 Email : arsmannuthy@kau.in RE-TENDER NOTICE No. B/400/ dated 0/03/06 Sealed tenders are invited for

More information

Appendix 4-2-C Project Air Emissions Inventory

Appendix 4-2-C Project Air Emissions Inventory Appendix A CALPUFF and CALMET Methods and Assumptions Appendix 4-2-C Project Air Emissions Inventory C.1 Introduction For the purposes of estimating effects on air quality associated with the Project,

More information

JURONG ROCK CAVERNS. Workshop on the Optimisation of Shaft Design 4 June 2013

JURONG ROCK CAVERNS. Workshop on the Optimisation of Shaft Design 4 June 2013 JURONG ROCK CAVERNS Development of Underground Rock Caverns for Hydrocarbon Storage on Jurong sland Workshop on the Optimisation of Shaft Design 4 June 2013 The Flow Journey of Jurong Rock Caverns Access

More information

SEWER AND WATERMAIN CONSTRUCTION

SEWER AND WATERMAIN CONSTRUCTION Fair Wage Office 100 Queen Street West City Hall, 18 th Floor, West Tower Toronto, ON M5H 2N2 Tel: 416-392-7300 Fax: 416-392-0801 Hotline: 416-392-FAIR E-mail: fairwage@toronto.ca Visit us at www.toronto.ca/fairwage

More information

Introduction of drill and blast utilizing pneumatic rock-drills in a Rwandan artisanal underground mine

Introduction of drill and blast utilizing pneumatic rock-drills in a Rwandan artisanal underground mine http://dx.doi.org/10.17159/2411-9717/2017/v117n4a1 Introduction of drill and blast utilizing pneumatic rock-drills in a Rwandan artisanal underground mine by T.A. Sethu*, T.P. Letsebe*, L. Magwaza*, and

More information

Earthing. PowerPoint Presentation, Markers and Whiteboard

Earthing. PowerPoint Presentation, Markers and Whiteboard Session: Earthing Learning Objective Explain the process of earthing and testing the earth resistance Evaluation Criterion Interactive Questioning Duration Resources Facilitator s Notes 30 Minutes PowerPoint

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION COST DATA BOOK FOR RECOVERY OF EXPENSES & OTHER CHARGES FROM PROSPECTIVE CONSUMERS FOR TAKING ELECTRIC SUPPLY (APPLICABLE TO ALL DISTRIBUTION LICENSEES IN

More information

TRENCH SHIELDING AND SHORING

TRENCH SHIELDING AND SHORING TRENCH SHIELDING AND SHORING PROSERIES SHIELDS PERFORMANCE DESIGNED FOR TOP PRODUCTIVITY The ProSeries line of trench shields from PRO-TEC incorporates performance features that help deliver outstanding

More information

GAMMA Septic Tanks Installation & Operation Guidelines

GAMMA Septic Tanks Installation & Operation Guidelines 017906 GAMMA Septic Tanks Installation & Operation Guidelines Kingspan Environmental Service Contact Numbers: UK: 0844 846 0500 NI: +44 283025 4077 IRL: +44 283025 4077 NOR : +47 22 021 920 Enclosed Documents

More information

STANDARD TIME AND MATERIAL RATE SHEET 1/01/12 12/31/12

STANDARD TIME AND MATERIAL RATE SHEET 1/01/12 12/31/12 STANDARD TIME AND MATERIAL RATE SHEET 1/01/12 12/31/12 Straight Time Time and One-Half Double Time Superintendent $80.52 $103.32 $126.12 Foreman $73.91 $93.46 $113.00 Pusher $68.85 $87.74 $106.64 Mechanic/Welder

More information

PERMANENT RESIDENTIAL UNDERGROUND SERVICE

PERMANENT RESIDENTIAL UNDERGROUND SERVICE CITY OF RICHLAND ENERGY SERVICES DEPARTMENT 505 Swift Boulevard, MS-21 Richland, WA 99352 Telephone (509) 942-7403 Fax (509) 942-7405 PERMANENT RESIDENTIAL UNDERGROUND SERVICE A. INTRODUCTION This guide

More information

Appendix H: Construction Impacts H-3 Air Quality

Appendix H: Construction Impacts H-3 Air Quality Appendix H: Construction Impacts H-3 Air Quality Rockland Landing-Reconstruction of the South Broadway Bridge Nonroad s Engine Size (hp) Compressors - surface tools 275 2 1 8 10% 0.043 0.045 1.107 0.263

More information

Scale of Inspection Fees of Electrical Inspectorate Schedule. I. Fees for Initial Inspections:

Scale of Inspection Fees of Electrical Inspectorate Schedule. I. Fees for Initial Inspections: PART 7 Scale of Inspection Fees of Electrical Inspectorate Schedule I. Fees for Initial Inspections: SCALE A For an inspection or test of any generating station, receiving station or other places in which

More information

Tender Schedule. Sl. No. Particulars Quantity Unit Rate `

Tender Schedule. Sl. No. Particulars Quantity Unit Rate ` Tender Schedule Estimate for Electrical Works at Savalyapuram Branch(18901) Guntur(District). Sl. No. Particulars Quantity Unit Rate ` 1 Wiring for light point/ fan point/ exhaust fan point/ call bell

More information

Corrigendum-I. Bill of Quantity

Corrigendum-I. Bill of Quantity Tender :CON/EP/Balli/EW & CC Pav./T-I/2016 Corrigendum-I Bill of Quantity Name of Work :- Construction of CC Pavement, Earthwork/formation, Approach Road, Warehouse, Administrative Building, Boundary Wall,

More information

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA TENDER FOR

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA TENDER FOR GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA - 390 007 TENDER FOR Design,Engineering, manufacturing, supply, erection, testing & commissioning of 66

More information

People. Passion. Performance. Portable Diesel Compressors Built for Reliable Performance

People. Passion. Performance. Portable Diesel Compressors Built for Reliable Performance People. Passion. Performance. Portable Diesel Compressors Built for Reliable Performance ROBUST AND READY FOR THE MOST DEMANDING CONDITIONS Demanding conditions demand power you can count on. Chicago Pneumatic

More information

FAIR WAGE SCHEDULE Sewer and Watermain

FAIR WAGE SCHEDULE Sewer and Watermain City Manager's Office Fair Wage Office Human Resources Division 100 Queen Street West City Hall, 18 th Floor, West Tower Toronto, Ontario M5H 2N2 Tel: 416-392-7300 Fax: 416-392-0801 fairwage@toronto.ca

More information

BALCONES QUARRY November 2014

BALCONES QUARRY November 2014 BALCONES QUARRY November 2014 New Braunfels, Texas - 0 - Description of the Facility The Balcones Facility is situated in New Braunfels, Texas and was opened in the mid 1960 s. The geologic structure in

More information

Index. 1 Mmakgoge Group Structure. 2 Industrial Cleaning Industrial Cleaning and Waste Removal Dry Ice Cleaning Storage Plant Cleaning and Rehab

Index. 1 Mmakgoge Group Structure. 2 Industrial Cleaning Industrial Cleaning and Waste Removal Dry Ice Cleaning Storage Plant Cleaning and Rehab Index 1 Mmakgoge Group Structure 2 Industrial Cleaning Industrial Cleaning and Waste Removal Dry Ice Cleaning Storage Plant Cleaning and Rehab 3 Purification Services Material Drying (Sludge) Dewatering

More information

Drilling Workshop. Roy Rathner and Arne Lislerud

Drilling Workshop. Roy Rathner and Arne Lislerud Drilling Workshop Roy Rathner and Arne Lislerud Optimisation of quarrying Pit-to-Product Mine-to-Mill Mine-to-Metal => requires a overview of operations, technology and markets Overview of basic topics

More information

HDD ASSIST OVERCOMING DIFFICULT SITUATIONS

HDD ASSIST OVERCOMING DIFFICULT SITUATIONS HDD ASSIST OVERCOMING DIFFICULT SITUATIONS Presented by: Venue: Amanda Kitchin Business Development Trenchless Technology UKSTT Roadshow Reading ABOUT US Mammoth Equipment Ltd and MTS Suction Systems UK

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS

San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS 834.1 DESCRIPTION: This item shall consist of fire hydrant installations using joint restraints in accordance

More information

QUARRYING PROCESS AND QUARRY PRODUCTS

QUARRYING PROCESS AND QUARRY PRODUCTS NORTHSTONE (NI) Ltd. QUARRY & ASPHALT DIVISION QUARRYING PROCESS AND QUARRY PRODUCTS We take many things in the material world for granted, not realising or appreciating their presence or value. Construction

More information

Backhoe & Hoe Ram (under 3/4 Yd.) $26.11 $34.81 $ Backhoes & Hoe Ram (3 Yds & Over) $26.44 $35.25 $44.06

Backhoe & Hoe Ram (under 3/4 Yd.) $26.11 $34.81 $ Backhoes & Hoe Ram (3 Yds & Over) $26.44 $35.25 $44.06 2018 SPOKANE TRIBAL WAGE RATES FOR CONTRACTORS All rates are based on 100% of Washington State prevailing wage rates for Stevens County All wage rates are subject to annual adjustments by the TERO Commission

More information

2460 / 2472 / Series Simplex Grinder Systems

2460 / 2472 / Series Simplex Grinder Systems Installation Manual 5651000I 2460 / 2472 / 2484 - Series Simplex Grinder Systems Features: LSG or LSGX Series 2HP Grinder Pump 24 dia. Basin available in 60, 72, or 84 depths Guide Rail System Preassembled

More information

6 Hour Backhoe Loader (CAT 415F2/ 415F2 IL, 416F/ 416F2, 420F/420F IT, 420F2/ 420F2 IT, 430F/430F IT, 430F2/ 430F2 IT, 450F or Equiva $32.

6 Hour Backhoe Loader (CAT 415F2/ 415F2 IL, 416F/ 416F2, 420F/420F IT, 420F2/ 420F2 IT, 430F/430F IT, 430F2/ 430F2 IT, 450F or Equiva $32. PROJECT 2506; 2017 ANNUAL REPAIR CONTRACT; J.C. DILLON, INC., CONTRACTED SCHEDULE OF ITEMS, QUANTITIES AND COSTS 1 Hour Lowboy Including Both Permits and Paid Driver $75.00 2 Hour Single Axle Dump Truck

More information

Alquiler y venta de maquinaria para la construcción. products catalogue

Alquiler y venta de maquinaria para la construcción. products catalogue products catalogue 1 Index 3 Air compresors and accesories Drilling equipment 11 Transport service Diverse equipment 4 5 6 Electric Hammers Lifting equipment Mixers Generators Lightning towers Water pumps

More information

ATS CHEM EQUIPMENTS PVT. LTD.,

ATS CHEM EQUIPMENTS PVT. LTD., ATS CHEM EQUIPMENTS PVT. LTD., AN ISO 9001:2015 CERTIFIED COMPANY Unit 1, C 27, SIDCO Industrial Estate, Hosur 635 126, Tamil Nadu, India. Phone No: 04344 276731, Mail ID: atschem@gmail.com Unit II, 16

More information

CONSTRUCTION TIRES & WHEELS LOCS. Lowest Operating Cost Solution

CONSTRUCTION TIRES & WHEELS LOCS. Lowest Operating Cost Solution LOCS Lowest Operating Cost Solution In today s economy, good business means making your money go a long way. This is why we are committed to: Find out more at camoplastsolideal.com or contact your authorized

More information

Side Cutter Kit (Left and Right - fits all 68", 72", 80" Buckets) 48" Pallet Fork

Side Cutter Kit (Left and Right - fits all 68, 72, 80 Buckets) 48 Pallet Fork Side Cutter Kit (Left and Right - fits all 68", 72", 80" Buckets) These Bolt On Side Cutters (BOSC) greatly extend bucket service life and improve penetration power into hard packed soil or stock piled

More information

BID No.SE/O&M/Amt./T/14-15/T-27 DPDC Full Turnkey SN Description Unit Unit Rate (Rs) Qty

BID No.SE/O&M/Amt./T/14-15/T-27 DPDC Full Turnkey SN Description Unit Unit Rate (Rs) Qty Full Turnkey Contract for Street light Works covered under DPDC Scheme under Achalpur Division under Amravati circle. BID No.SE/O&M/Amt./T/14-15/T-27 DPDC Full Turnkey 2014-15 SN Description Unit Unit

More information

QA Mobile Crushing & Screening. Stu Gamble - Sandvik

QA Mobile Crushing & Screening. Stu Gamble - Sandvik QA 200 - Mobile Crushing & Screening Stu Gamble - Sandvik Presentation Overview This is a presentation on the functionality and role that mobile plants may play within the construction and mining industries.

More information

Fair Wage Office 18 th Floor, West Tower, City Hall FAIR WAGE SCHEDULE * I.C.I. WORK

Fair Wage Office 18 th Floor, West Tower, City Hall FAIR WAGE SCHEDULE * I.C.I. WORK Corporate Services * Industrial, Commercial, Institutional Fair Wage Office 18 th Floor, West Tower, City Hall FAIR WAGE SCHEDULE 2003-2004 * I.C.I. Tel: 416-392-7300 Fax: 416-392-0801 Hotline: 416-392-FAIR

More information

DELETE first sentence of first paragraph that reads: REPLACE with the following:

DELETE first sentence of first paragraph that reads: REPLACE with the following: To Bidder of Record: SAN ANTONIO WATER SYSTEM Addendum 2 To Construction Documents For 2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB NO. 12-5001 SAWS SEWER JOB NO. 12-5501 Solicitation

More information

Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks)

Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks) Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks) 1. Personal Info: Ensure your legal company name is on the form. 2. Equipment Info: Ensure you complete all

More information

EN TRA ENGINEERING AND TRADING SRL

EN TRA ENGINEERING AND TRADING SRL Foundation Equipment Grabs for diaphragm wall and piling Hydraulic Casing oscillators Power Packs Casing joints Stop-end pipes Water stop elements Hydraulic extractors Piling tools and accessories MADE

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS

San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS 834.1 DESCRIPTION: This item shall consist of fire hydrant installations using joint restraints in accordance

More information

Technical Information. (Innovative Transport Technology for Open Pit Mines)

Technical Information. (Innovative Transport Technology for Open Pit Mines) Technical Information TruckLift System (Innovative Transport Technology for Open Pit Mines) WWW.sieMaG-tecBerG.coM Technical Information SIEMAG TECBERG TruckLift Ore deposits close to the surface are generally

More information

TENDER DOCUMENTS SUPPLY OF ELECTRICAL EQUIPMENT FOR BHADRAK MUNICIPALITY FOR THE YEAR LAST DATE OF RECEIVED OF TENDER DOCUMENTS :

TENDER DOCUMENTS SUPPLY OF ELECTRICAL EQUIPMENT FOR BHADRAK MUNICIPALITY FOR THE YEAR LAST DATE OF RECEIVED OF TENDER DOCUMENTS : TENDER DOCUMENTS SUPPLY OF ELECTRICAL EQUIPMENT FOR BHADRAK MUNICIPALITY FOR THE YEAR 2016 17 PERIOD OF SALE OF TENDER DOCUMENTS : 27.05.2016 LAST DATE OF RECEIVED OF TENDER DOCUMENTS : 10.06.2016 DATE

More information

Conveyor Belt Group. Cleat Brochure 2017 Profiled and Cleated Belts.

Conveyor Belt Group. Cleat Brochure 2017 Profiled and Cleated Belts. Conveyor Belt Group Cleat Brochure 2017 Profiled and Cleated Belts www.contitech.us 2017 Cleat Brochure Cleated Belts Continental Select is dedicated to equipping your operation for the most grueling conveying

More information

Blockade Services Limited Unit O, Lambs Business Park, Tilburstow Hill Road, South Godstone RH9 8LJ

Blockade Services Limited Unit O, Lambs Business Park, Tilburstow Hill Road, South Godstone RH9 8LJ Blockade Services Limited Unit O, Lambs Business Park, Tilburstow Hill Road, South Godstone RH9 8LJ Tel: 01342 893806 Fax: 01342 893158 www.blockadeservices.co.uk Steve Burrows started as a sole trader

More information

MacKellar EPSA Capability Statement

MacKellar EPSA Capability Statement MacKellar EPSA Capability Statement The Capability Statement of MacKellar EPSA Pty Ltd. Privately owned and operated contract mining and earthmoving company, with a focus of supplying flexible, yet reliable

More information

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY AND HEALTH STANDARD. Filed with the secretary of state on

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY AND HEALTH STANDARD. Filed with the secretary of state on DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY AND HEALTH STANDARD Filed with the secretary of state on These rules take effect immediately upon filing with the secretary

More information

Steel Products. 8M Series

Steel Products. 8M Series 8M Series Steel Products This trench shield is engineered to the realities of profitable pipe laying. With high tensile steel, non-rigid design and strategic reinforcements, the GME 8M Series trench shield

More information

SNO DESCRIPTION QTY UNIT RATE AMOUNT MAIN PUMP 1

SNO DESCRIPTION QTY UNIT RATE AMOUNT MAIN PUMP 1 LIC OF INDIA, EZO, KOLKATA WET RISER AT HINDUSTHAN BUILDING HB(ANNEX), KOLKATA SNO DESCRIPTION QTY UNIT RATE AMOUNT MAIN PUMP 1 SITC of electrically driven Fire fighting Pump suitable for automatic operation

More information

SupAnchor Rock Reinforcement Strategy Self-drilling hollow anchor systems

SupAnchor Rock Reinforcement Strategy Self-drilling hollow anchor systems SupAnchor Rock Reinforcement Strategy Self-drilling hollow anchor systems The SupAnchor Self-Drilling Hollow Anchor is a unique anchoring system and is today s answer to the increasing demands of the tunnelling

More information

SCHEDULE OF QUANTITY

SCHEDULE OF QUANTITY SCHEDULE OF QUANTITY ELECTRICAL WORKS PM PALEM BRANCH, VISAKHAPATNAM SL NO. DESCRIPTION OF ITEM / WORK UNIT Qty RATE AMOUNT PART - A : ELECTRICAL WORKS 1 Energy Meter Cubicle : 2 Emergency Off Box (Red

More information

SMALL CONSTRUCTION EQUIPMENTS

SMALL CONSTRUCTION EQUIPMENTS SMALL CONSTRUCTION EQUIPMENTS SR NO CONCRETE MIXERS 1 [CM-1] FULL BAG CONCRETE MIXER WITH MECHANICAL HOPPER MOUNTED ON [500 19] TYRES CONCRETE MIX 200 LTS A] 6 HP AIR COOLED DIESEL B] 3PH 5 HP ELECTRIC

More information

BILL OF QUANTITIES - ABSTRACT

BILL OF QUANTITIES - ABSTRACT PR OP OS ED L AY OU T P LA N NAME OF WORK: CONSTRUCITON OF OSTS THIRUMANGALM LOCATION : MELAKOTTAI BILL OF QUANTITIES - ABSTRACT CAPEX SL.NO Short Description Item Code Long Description Quantity Unit RATE

More information

Service Requirements

Service Requirements Service Requirements General Contact Idaho Power before beginning work on any new service. All meter installations must meet current electrical code requirements and display the proper electrical permit.

More information

Kansas Department of Transportation

Kansas Department of Transportation Kansas Department of Transportation STANDARD JOB CLASSIFICATIONS AND DESCRIPTIONS ASPHALT PAVER SCREED OPERATOR (Power Equipment Operator) Makes sure paver is in proper position before moving off the joint.

More information

SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP. 1 OF 1 P:\8417\ Bridge A\AT\Albany A.MDB 7/21/2014 7:32:31 AM REVISION NO COUNTY

SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP. 1 OF 1 P:\8417\ Bridge A\AT\Albany A.MDB 7/21/2014 7:32:31 AM REVISION NO COUNTY 7/18/2014 - UCTURE REVISION NO REVISIONS DATE BY DIICT COUNTY ROUTE SECTION SHEET - SEE SPECIAL PROVISIONS SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP T-410 4 OF 8 QUANTITY ITEM NO UNIT DESCRIPTION DESIGN NO

More information

Annexure B (1)- Engineering Instructions for Installation of Aerial OFC

Annexure B (1)- Engineering Instructions for Installation of Aerial OFC Annexure B (1)- Engineering Instructions for Installation of Aerial OFC INSTALLATION PRACTICE OF SELF SUPPORTING METAL FREE AERIAL OPTICAL FIBER CABLE 1. SCOPE: This Engineering Instruction (EI) deals

More information

MIXING CENTRE FOR DELIVERY OF CELLULAR CONCRETE

MIXING CENTRE FOR DELIVERY OF CELLULAR CONCRETE MIXING CENTRE FOR DELIVERY OF CELLULAR CONCRETE Type: MS 1000M Data Sheet No. 011.1 A machine for making and delivery of lightweight concrete (LC) filled with technical foam foam concrete (PBG) or with

More information

A Assembly Instructions Space Capsule, Art-No

A Assembly Instructions Space Capsule, Art-No A Assembly Instructions Space Capsule, Art-No. 20.01.020 T:\PLAY\Play Installation Instructions\Installation Instructions 2012-2013\20_01_020-01-en-003.doc - 1 - Revision history Revision 0 2004-06-22

More information

SPECIFICATIONS OF SINGLE GIRDER UNDER SLUNG E.O.T. CRANE CAPACITY: 5 MT

SPECIFICATIONS OF SINGLE GIRDER UNDER SLUNG E.O.T. CRANE CAPACITY: 5 MT 1 SPECIFICATIONS OF SINGLE GIRDER UNDER SLUNG E.O.T. CRANE CAPACITY: 5 MT QUALIFICATION CRITERIA Vendor has to compulsorily meet the following requirements to get qualified for consideration of the technical

More information

Bills of Quantities and Schedule for the Electrical Works at M/s.Bank of India, Madurai CPC Branch, East Aavani Moola Street, Tamil Nadu.

Bills of Quantities and Schedule for the Electrical Works at M/s.Bank of India, Madurai CPC Branch, East Aavani Moola Street, Tamil Nadu. Bills of Quantities and Schedule for the Electrical Works at M/s.Bank of India, Madurai CPC Branch, East Aavani Moola Street, Tamil Nadu. S.No Particulars Qty Unit Rate Rs Amount Rs Service Connection

More information

PLEASE NOTE: BATCH TRUCK

PLEASE NOTE: BATCH TRUCK Material Prices Saturday Hours are seasonal: April - September ½ Yard One Yard Crushed Asphalt ¾ minus $15.00 $25.00 Crushed Concrete ¾- minus $15.00 $25.00 Crushed Concrete 1-2 / 2-3 clear $18.00 $30.00

More information

S P E C I F I C A T I O N

S P E C I F I C A T I O N T E N D E R S P E C I F I C A T I O N NO: BHE/PW/PUR/KKT-ELE/627 FOR HANDLING AT SITE STORES/STORAGE YARD, TRANSPORTATION TO SITE OF WORK, COMPLETE ERECTION, CHECKING OF CALIBRATION, TESTING, COMMISSIONING

More information

DIGGER DERRICK (CRANE AND DIGGER)

DIGGER DERRICK (CRANE AND DIGGER) 120-3 : 2008 CEB SPECIFICATION DIGGER DERRICK (CRANE AND DIGGER) CEYLON ELECTRICITY BOARD SRI LANKA Specification for DIGGER DERRICK (CRANE AND DIGGER) CEB Specification 120-3 : 2008 CEYLON ELECTRICITY

More information

Total duration of course = 3 Months (12 weeks) Total training hours = 400 hrs.

Total duration of course = 3 Months (12 weeks) Total training hours = 400 hrs. 1 TRAINING OBJECTIVES: In order to reduce the unemployment and poverty in the society, the curriculum is designed to impart the technical knowledge and skill to those who are literate and.can not do the

More information

REVIEW FOR FINAL EXAM

REVIEW FOR FINAL EXAM REVIEW FOR FINAL EXAM A. J. Clark School of Engineering Department of Civil Engineering by Dr. Ibrahim A. Assakkaf Spring 2002 ENCE 420 - Construction Equipment and Methods Department of Civil Engineering

More information

FOOTBRIDGE ELEVATION SCALE 1:100

FOOTBRIDGE ELEVATION SCALE 1:100 OVERALL BRIDGE LENGTH 20000 DAIRY FLAT HIGHWAY END STEEL HANDRAIL BOTH SIDES 20 CURTAIN WALL 1900 20 CURTAIN WALL D1 RL.m A 2 B E1 RL.7m E 1% LONGITUDINAL GRADE E12 E11 E1 STEEL HANDRAIL BOTH SIDES 4 E14

More information

Excavators. Mini/Midi

Excavators. Mini/Midi Mini/Midi Excavators Hitches 1 Buckets 2-6 Earth Drills 7 Breakers 8 Hand Held Tools 9-12 Compactors 12 Rock Wheel 13 Ripper Tooth 13 Selector Grabs 13 Mini/Midi Excavators Introduction Mini/Midi Excavators

More information

SOUTHERN POWER DISTRIBUTION COMPANY OF ANDHRA PRADESH LIMITED

SOUTHERN POWER DISTRIBUTION COMPANY OF ANDHRA PRADESH LIMITED SOUTHERN POWER DISTRIBUTION COMPANY OF ANDHRA PRADESH LIMITED COMMON STANDARD SCHEDULE OF RATES FOR THE YEAR 2014 2015 INDEX Description Page No. I. Rates of Labour 1-2 II. Important note 3 III. Rates

More information