ASSEMBLY INSTALLATION STUDIES FOR THE ITER CRYOLINE SYSTEM
|
|
- Louise Bradley
- 5 years ago
- Views:
Transcription
1 ASSEMBLY INSTALLATION STUDIES FOR THE ITER CRYOLINE SYSTEM S Badgujar 1, N Shah 2, A Forgeas 1, N Navion-Maillot 1, E Monneret 1, D Grillot 1, L. Benkheira 1 and B Sarkar 2 1 ITER Organization, Route de Vinon-sur-Verdon, CS , St. Paul Lez Durance Cedex, France 2 ITER-India, Institute for Plasma Research, Bhat, Gandhinagar , India The views and opinions expressed herein do not necessarily reflect those of the ITER Organization Page 1
2 OUTLINE INTRODUCTION THE CRYOLINE SYSTEM BRIEF SPECIFICATION INSTALLTION PLAN CONFIGURATION, TRANSPORTATION SEQUENCE, ASSEMBLY SITE WORK STATISTICS SCHEDULE INSTALLTION CHALLENGES AND RISKS CONCLUSION Page 2
3 Magnets: PF Magnets: CS ITER CRYOGENIC SYSTEM Magnets: TF Magnets: STR Magnets: C Leads Cryo Pumps Thermal Shields K 3 Plants Avg K 300K to 80K: LN2 PLANTS (1,2) LHe 1 LHe 2 LHe 3 80K: Ghe Loops (1,2) EU-DA IO IN-DA IN-DA Cryoplants 4K: LHe Distribution 80K: GHe Distribution Cryodistribution 8 boxes CryoLines ~ 5 km 4K USERS 80K USERS Page 3
4 LAYOUT ITER CRYOGENIC SYSTEM Page 4
5 THE CRYOLINE SYSTEM IN TOKAMAK BUILDING South West Shaft L3 level From Plant bridge North West Shaft Y B1 level B2M level X X Y+W B2 level W TOKAMAK BUILDING Page 5
6 TECHNICAL SPECIFICATION OF CLs and WLs Specifications Cryolines (CLs) Warm lines (WLs) No. of process pipes (PP) 1 to 7 1 Length ~ 5000 m ~ 6000 m No, Type of lines 21 multi, 16 single PP 55 single process Outer jacket (OVJ) Size DN 100 to DN 1000 DN 50 to DN 1600 Segments Straight, Tee, Elbow, Z Straight, Tee, Elbow, Z Temperature levels 4.5 K (3.8 K), 50 K, 80 K, 300 K 300 K, 423 K, 473 K Fluids Helium(He), Nitrogen(N2) Helium, Nitrogen, He+N2+Oil Pressure of process fluid Maximum 21 bar Maximum 42 bar Materials of PP/OVJ ,14435 (304L,316L) 304/304L (or eq. EN) Quality Classes (QC) QC 1, QC 2 QC 2, QC 3, QC 4 Seismic Classes (SC) SC1 (SF), SC1 (S), SC2, NSC SC2, NSC Safety Classes SIC-II, SR, Non-SIC SR, Non-SIC DN 500 OVJ most common among complex cryolines (X) Biggest DN of the process pipe DN300 C/s of 342CM0 Page 6
7 INSTALLATION PLAN 3 different buildings B50x, Plant bridge, Tokamak building Area by area installation in building [Parallel installation] Given area Construction work package [1-2-3 CLs] Modular approach for installation of the CLs Straight Tee Elbow [90 ] Elbow [>90 ] Step Max. dimensions as per site constraints ~ 10 m Max weight of spool ~ 10 ton C1 C2 (Cryolines Group-X) Design, Mgf, Supply Installation* (Cryolines Group-Y) Design, Mgf, Supply, installation (Warmlines Group- W) Design, Mgf, Supply, installation Installation contractor - 1 Installation contractor -2 Page 7
8 SITE WORK FLOW Upstream ACB Downstream ACB WITH TEST END CAPS Page 8
9 ARRIVAL ON SITE AND TRANSPORTATION ROAD FOR DELIVERY STORAGE ROADS FOR PRE-ASSEMBLY WORKSHOPS ROADS FOR INSTALLATION NORTH Spools inside container on truck Delivery Packaging: Closed containers (~ISO 40 feet) Approximate estimation based on present schedule and scope 300 nos [X,Y,W] ITER incoming inspection Documentation, Pressure gauge, Accelerometer Page 9
10 NORTH ENTRY TO TOKAMAK BUILDING B2 B11 Tokamak Bldg. B14 Tritium Bldg. Mobile crane near the platform in seismic pit 5.3 m H x 6.6 m L 5.3 m H x 6.6 m L 12 m L x 9 W x 3.3 high Page 10
11 MOVEMENT IN TOKAMAK BUILDING Opening at B2 L3 B2 SOUTH-WEST Opening at L3 ALL BUILDING OPENINGS, CONSTRAINTS AND LIMITATIONS HAVE BEEN STUDIED POSSIBLE TO MANOEUVRE IN B11- AT ALL THE LEVELS: B2,B2M,B1 and L3 Page 11
12 SEQUENCE IN TOKAMAK BUILDING From farthest point from the entrance of spools to nearest point From top (close to ceiling) to bottom (floor) From inner wall (centre of Tokamak) to outer wall (external wall of tokamak building) From bigger to smaller line NORTH Material movement Installation progress B D Point of entry at B2 E WEST EAST Section S-S A S S SOUTH C Area in the level Seque nce No. Prefered installation sequence among the lines [CLs-WLs] Building Level Tokamak B2 South 1 342CTS - TF cryoline 2 342CPL - PF cryoline 3 342SQL - Quench line 4 342WP0 - Purge line WCL - Current lead line 6 342WDH - He distribution line 7 342SR0 - Relief line Page 12
13 Outer Wall Inner Wall SEQUENCE IN TOKAMAK BUILDING Installation starts once the building are ready for equipment (RFE) CLs first equipment to be installed in most of the areas in B11 Other systems will follow the installation after 4 weeks General principal Specific situations! Ceiling B D Slab A C B2M QUADRANT B2 Page 13
14 SPOOL INTERCONNECTIONS Internal pipe welds TEST Shield Outer jacket welds Global TEST B2M AMONG CRYOLINE SPOOLS A Tests on PP Install MLI on PP Shield assembly and MLI WITH INTERFACE EQUIPMENTS B CVB B1 TYPE I WITH BELLOW TYPE II - WITHOUT Page 14
15 ASSEMBLY OF THE LINE Finish Joining of spools one by one to form the complete cryoline Start INSTALLATION TIME FOR ONE INTER-CONNECTION ~24 hrs DN 500 lines ~36 hrs for DN lines ~48 hrs DN 1000 line Page 15
16 Process pipes WELDS MAJOR IN PROCESS INSEPCTION Radiography All weld joints on PP during assembly and installation Visual test All weld joints on PP during assembly and installation VT RT Visual QC VT RT LT LN % 100% 100% * 2 100% 20% 20% * 3 100% 10% 10% NA LT Radiography LN2 Helium leak tightness test Liquid nitrogen thermal shock test - *SAMPLE Helium leak testing All weld joints assembly and installation at room temperature Overall leak testing at warm and cold (for complete line) Thermal Shock test Sample welds during assembly and installation Pressure test All independent sub-assemblies (e.g. one complete cryoline) at room temperature Cold test (for cryolines only) Overall performance at cold temperature (thermal performance measurement, leak test, checking for cold spot on OVJ) Page 16
17 SITE WORK STATISTICS Summary of the spools for all ITER CLs and WLs Building/Area Area/level in building CLs WLs Total L NW Shaft (L2, L1) Tokamak SW Shaft (L2, L1) Building (B11) B B2 / B2M Plant Bridge Cryoplant building/area 51 (Compressor building) (Cryoplant building) Area Total WELDS >11000 ~7000 CLs ~1300 WLs ~3000 Supports Summary estimated welding length (meter) CLs + WLs + Building/Area Total supports supports Tokamak Building Plant Bridge Cryoplant building/area Total Summary of estimated test length (meter) Building/Area CLs WLs Total PP OVJ Tokamak Building Plant Bridge Cryoplant building/area 900 Total Page 17
18 SITE WORK STATISTICS - TIME Level No. of No. of interfa element ce to s to be be connect connec ed ted Total Total intercon nections 1 working day per intercon nection 1 shift installati on [1 working day=3 shifts=3d ays] 10 days overlap, 10 days test 22 working days in 1 month Factor used for single and multi normalizat ion Days Days Days Months Months Years Tokamak Building L NW Shaft SW 0 15 Shaft B B2M B ~3/4 teams working in parallel in Tokamak building to meet the schedule Night shift for RT Second shift (if needed) to accelerate the installation Page 18
19 1 Typical Assembly & Installation Team Welder(s) (manual welds) stainless steel/carbon steel 2 Welders / Operator(s) (orbital welding machine) 3 Fitter(s) Rigger(s)/ Helper(s) transport of pipe 4 spools/supports, Material handling 5 Technician - MLI 6 Technician NDT [RT, LT, VT, LN2 shock] 7 Engineer(s) technical/construction 8 Inspector(s)/Controller(s) - Inspections agencies 9 QA Officer 10 Safety Officer 11 Site in-charge 12 Office Support Staff RESOURCES 3-4 team ~6-8 person per team per location >30 people on site during the peak installation period To be adapted: Based on the site requirements/constraints Contractor execution plan Page 19
20 TOOLS Portable small crane Forklift-stacker Arrangement from EP Mini spider crane A type cranes Platform + specific forklift Use of Embedded plates for fixation of Lifting equipment + Chain pulley block Page 20
21 Bldg 51.1 C&W lines B51 upper Trench W C&W lines B52 Fire Wall Bldg 51.2 CRYOPLANT INSTALLATION SUMMARY Area 53: Building 51: Bldg 51.1 Building 51: Bldg 51.2 Building 51: Bldg 51.3 Building 52: Name PBS Date Name PBS Date Name PBS Date Name PBS Name PBS Date Name PBS Date Name PBS Date Name PBS Date 1 C&W lines Area 53 Part Apr-17 9 Test heater 34.1W.E k CB L.B1 25 LHe tanks valve box 34.1S.HB 1 He CS (CPs) 34.4H.C2 21-Apr He CS 1 (CPs) 34.4H.C1 21-Apr C&W lines B51 Fire Wall Apr-17 1 C&W lines B52 Fire Wall Apr-17 2 GHe Storage 34.1S.HG 10 GAN Purifier 34.1G.B k CB L.B K heaters 34.1W.E 2 He CS (CPs) 34.4H.C3 22 Cryolines 80K Junction 34.2S.L0 32 Gasbag Storage 34.1S.B0 2 He Cold box H.B1 3 GN2 Storage 34.1S.NG 11 Air Compressor 34.1G.C0 19 He Purifaction 34.1P.B0 27 C&W lines Area 53 Final Cnt He CS 2 (ORS) 34.4H.C1 23 He CS 1 (ORS) 34.4H.C1 33 He CS 1 (FORS) 34.4H.C1 3 He Cold box H.B2 4 N2 CB N.B1 12 Liquid disposal Atmo. He Heater 34.1W.AH 4 He CS 3 (ORS) 34.4H.C k CS L.C2 34 He CS 2 (FORS) 34.4H.C2 4 He Cold box H.B3 5 C&W lines Area 53 Part LN2 Storage Warm Skid 34.1S.NL 21 C&W lines Area 53 Part IN-DA 5 N2 CS N.C k CS L.C1 35 Dryers 34.1P.D1 5 Test Cryostat 34.4H.T0 6 N2 CB N.B2 14 LN2 Storage Vaporizer 34.1W.AN 22 Quench Tank 34.1S.Q0 IN-DA 6 N2 CS N.C2 26 Helium Recovery System 34.1P.R0 36 He CS 3 (FORS) 34.4H.C3 6 CTCB Y 7 LN2 Storage 34.1S.NL 15 Casing Pump 34.1S.NL 23 LHe storage 34.1S.HL F4E 7 C&W lines B51 upper Trench W Leak treatment 34.1P.T0 37 C&W lines B51 upper Trench N/S C&W lines B52 Final Cnt Air Separation Column 34.1G.D0 16 C&W lines Area 53 Part Quench tanks cold box 34.1S.QB IO 28 C&W lines B51 upper Trench N C&W lines B52 CTCB Area C&W lines Area Part C&W lines Area 53 Part 1 5 C&W lines Area 53 Part 2 16 C&W lines Area 53 Part C&W lines Area CRYOLINES AND WARM LINES IN B50s X Y+W C&W lines B51 Fire Wall Bldg 51.3 Bldg 52 Area 53: Name PBS Date Name PBS Date Name PBS Date Name PBS Date 1 C&W lines Area 53 Part Building 1 51: Bldg Apr-17 9 Test heater Building 51: 34.1W.E0 Bldg k CB 1 Building 34.1L.B1 51: Bldg LHe tanks valve box Building 34.1S.HB 52: 2 GHe Storage Name 34.1S.HG PBS Date 10 GAN Purifier Name 34.1G.B0 PBS Date18 80k CB 2 Name 34.1L.B2 PBS Date K heaters Name34.1W.E0 PBS 3 GN2 Storage 1 He CS 2 (CPs) 34.1S.NG 34.4H.C2 21-Apr Air Compressor 21 He CS 1 (CPs) 34.1G.C0 34.4H.C1 21-Apr He Purifaction 31 C&W lines B51 Fire Wall 34.1P.B Apr C&W lines 1Area C&W 53 lines Final B52 CntFire Wall N2 CB 12 He CS 3 (CPs) 34.1N.B1 34.4H.C3 12 Liquid 22 disposal Cryolines 80K Junction S.L0 20 Atmo. He 32Heater Gasbag Storage 34.1W.AH 34.1S.B0 2 He Cold box H.B1 5 C&W lines 3 He Area CS 253 (ORS) Part H.C1 13 LN2 Storage 23 He Warm CS 1 (ORS) Skid 34.1S.NL 34.4H.C1 21 C&W lines 33 Area He CS 531 Part (FORS) H.C1 IN-DA 3 He Cold box H.B2 6 N2 CB 24 He CS 3 (ORS) 34.1N.B2 34.4H.C1 14 LN2 Storage 24 80k Vaporizer CS W.AN 34.1L.C2 22 Quench 34 Tank He CS 2 (FORS) 34.1S.Q0 34.4H.C2 IN-DA 4 He Cold box H.B3 7 LN2 Storage 5 N2 CS S.NL 34.1N.C1 15 Casing 25 Pump 80k CS S.NL 34.1L.C1 23 LHe storage 35 Dryers 34.1S.HL 34.1P.D1 F4E 5 Test Cryostat 34.4H.T0 8 Air Separation 6 N2 CS Column G.D0 34.1N.C2 16 C&W lines 26 Helium Area 53 Recovery Part 3 System P.R0 24 Quench 36 tanks He cold CS 3 box (FORS) 34.1S.QB 34.4H.C3 IO 6 CTCB Y 7 C&W lines B51 upper Trench W Leak treatment 34.1P.T0 37 C&W lines B51 upper Trench N/S C&W lines B52 Final Cnt C&W lines B51 upper Trench N C&W lines B52 CTCB Page 21
22 SCHEDULE Line PBS Connections O N D J F M A MY J JL A S O N D J F M A MY J JL A S O N D T&C North 342CHN 11 T&C South 342CHS 10 TF South 342CTS 17 T&C South 342CHS 1 T&C North 342CHN 1 TF North 342CTN 21 Quench Lower 342CQL 47 PF Lower 342CPL 16 Structure Lower 342CSL 3 CS Lower 342CCL 12 Relief Line 342WR0 42 T&C North 342CHN 4 T&C South 342CHS 4 Top down approach to meet sub-system commissioning Installation RFE - Building is ready to receive the equipment Reasonable duration for each activity detailed schedule for one CL Used mainly to assign the duration for installation of certain length of CL with certain number of interconnections Detailed sequence with co-activities INSTALLATION TIME (ONE INTER-CONNECTION) ~24 hrs DN 500 TF,PF,T&C ~18 hrs DAY STR ~12 hrs QL, RELIEF ~ 12 hrs for spool transfer, position, alignment Constant Avg. Time Vicinity dependent! Major Assumption: Availability of installation window without any major interruptions Site authorizations are given within reasonable time 10% rework Not considered - Complete failure of CL during testing phase that follows the site installation Page 22
23 SUMMARY SCHEDULE PA, CDR Preliminary Design 1 st PTCL (prototype cryoline) test completed 2 nd PTCL test completion (planned) Final Design Fabrication Delivery Installation and connection to clients Connection to feeders at L3 Preliminary acceptance, COLD tests with end caps Cryoline ready to be connected to clients, sub-system commissioning Final acceptance after final connection to clients Final integrated pressure and leak test B2 L3 All Cryolines ready for integrated commissioning 1 st Cryo-plant ready SAT ACB CP ready Page 23
24 CHALLENGES AND RISKS Difficult installation and maintenance due to space limitation Sequencing among lines and with other systems in buildings More than one industrial partner for installation of CLs Co-activity, Starts Stops during installation Very limited in-service inspection and repair during operation - Detailed sequence and priority definition Stringent quality and testing requirements to avoid intervention in situ RISKS Non-availability or delayed availability of storage area / pre-assembly Non-availability of allotted timeslot for material movement/installation or radiography Slow installation at start due to learning curve and site adaptation Failure of welding during testing (non-destructive test or pressure test) Under estimation of installation process, complicacies and duration Civil work and equipment position tolerance more than considered in design Priority change due to the project decisions Page 24
25 CONCLUSION Conceptual assembly and installation plan respecting ITER CMS has been developed with detailed sequence Modular approach has been foreseen with sequential deliveries and continuous supply chain management to minimize on site inventory Site to suit interconnections with interface equipment planned Parallel installation foreseen with multiple teams at different areas Further detailed installation plan will be worked out with industrial partners Skilled teams from industries will execute the work as per work instruction, strict inspection-control and oversight of technical teams form IO-CT/IN DA Overall success for installation will depend on efficient co-ordination among all the concerned actors at ITER site Page 25
26 FEB 2016 THANK YOU FOR YOUR ATTENTION TOKAMAK BUILDING B2 B2M B52 CRYOPLANT BUILDING B51 Authors would like to thank the colleagues from ITER Organization in Cadarache, ITER-India in Gandhinagar as well as industrial partners for their contribution to ITER cryolines project Page 26
27 Extra slides Page 27
28 Two main lines - Magnets - Cryopumps COLD TEST Q Pipe = m(h 2 -H 1 ) Q Loop = m(h 4 -H 1 ) Lines from ACBs to the clients - Magnets (TF, PF, CS, STR) - Cryopumps WITH DEDICATED TEST CAPS Q Pipe = m(h 6 -H 1 ) Q Loop = m(h 8 -H 1 ) Page 28
Progress of the JT-60SA Project
Progress of the JT-60SA Project P. Barabaschi, Y. Kamada, H. Shirai For the JT-60SA Integrated Project Team EU: F4E-CEA-ENEA-CNR/RFX-KIT-CIEMAT-SCKCEN JA: QST C.R.FRASCATI- ITALY 1 JT-60SA Project Agreement
More informationGENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon September 2018
GENERAL ATOMICS ITER Central Solenoid Module Fabrication September 2018 ITER Central Solenoid The heart of the international fusion energy device The Central Solenoid (CS) is the heart of ITER. The 5-story,
More informationGENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION
GENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION January 2018 ITER Central Solenoid The heart of the international fusion energy device The Central Solenoid (CS) is the heart of ITER. The 5-story,
More informationLow Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011
Low Beta Cryomodule Development at Fermilab Tom Nicol March 2, 2011 Concepts of SC CW 3GeV, 1mA Linac H - gun RFQ MEBT SSR0 SSR1 SSR2 β=0.6 β=0.9 ILC RT (~15m) 325 MHz 2.5-160 MeV 650 MHz 0.16-2 GeV 1.3
More informationGENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon August 2016
GENERAL ATOMICS ITER Central Solenoid Module Fabrication August 2016 ITER Central Solenoid The heart of the international fusion energy program The Central Solenoid (CS) is the heart of ITER. The 5-story,
More informationITER Magnets Update European perspective
ITER Magnets Update European perspective Hannu Rajainmaki, Boris Bellesia, Alessandro Bonito-Oliva, Eva Boter, Thierry Boutboul, Eugen Bratu, Marc Cornelis, John Fanthome, Robert Harrison, Peter Readman,
More informationPF Coil 2-6 Supply. Main technical aspects. P. Valente
PF Coil 2-6 Supply Main technical aspects P. Valente PF Coils EI Information Meeting Cadarache, 19 February 2013 This presentation is intended for reference purposes only and is not a legally binding document
More informationTechnical Summary for BOP-Group 5 Installation Works The BOP Group 5 works include installation and commissioning of all the Items included in
IDM UID T244BP VERSION CREATED ON / VERSION / STATUS 03 May 2017 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Summary for BOP-Group 5 Installation
More informationEU Procurement of In Vessel Components for ITER
EU Procurement of In Vessel Components for ITER State of progress and next steps Patrick Lorenzetto ITER Business Forum 2013, Toulon, 21 22 March 2013 1 Content Blanket First Wall Procurement Package Blanket
More informationCosting of Test Articles Ancillary Equipment and Costing Methodology
Costing of Test Articles Ancillary Equipment and Costing Methodology 0.504 m x 1.71 m x 0.413 m C. Wong, S. Malang, M. Youssef, N. Morley, M. Ulrickson and the TBM design team US ITER-TBM Meeting August
More informationTHE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE
THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE EPAC08, Genoa (Italy) 26 June 2008 1451 1506 1918 1977 Norbert Holtkamp Principal Deputy
More informationKSTAR Assembly. National Fusion Research Center, Daejeon, Korea
1 FT/2-2 KSTAR Assembly H. L. Yang, H. K. Kim, K. M. Kim, J. W. Sa, S. T. Kim, H. T. Kim, K. H. Hong, W. C. Kim, K. H. Kim, Y. S. Kim, J. Y. Kim, C. H. Choi, Y. K. Oh, Y. M. Park, M. Kwon, J. S. Bak, G.
More informationJT-60SA Newsletter. Cryoplant arrives at the JAEA Naka Site. No. 65, 31 May Headline
JT-60SA Newsletter Headline Cryoplant arrives at the JAEA Naka Site No. 65, 31 May 2015 After the successful discharge at the port of Hitachi on 21 March 2015, the refrigerator cold box (RCB) and the auxiliary
More informationTechnical Specifications (In-Cash Procurement)
IDM UID VLHSLE VERSION CREATED ON / VERSION / STATUS 12 Feb 2018 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Summary for BOP-Group 6 Installation
More informationStatus of ITER at the Transition to Construction
Status of ITER at the Transition to Construction Guenter Janeschitz Deputy Head of Central Integration Office ITER Organisation Page 1 Outline Fusion Basics and History of ITER (very brief): ITER and its
More informationITER PROJECT J. FARINEAU ITER ORGANIZATION. September 29th, 2010 SOFT PORTO: ITER-ORG 1
ITER PROJECT J. FARINEAU ITER ORGANIZATION September 29th, 2010 SOFT PORTO: ITER-ORG 1 Contents ITER Context and Background ITER Technical Systems ITER: Organization & Contractual Rules New ITER Project
More informationEU TF coils status. A.Bonito Oliva F4E Magnets Project Manager
EU TF coils status A.Bonito Oliva F4E Magnets Project Manager Slide 1 Presentation Outline TF coils Main Manufacture Steps Procurement strategy Status of the production Contracts and industries involved
More informationATS CHEM EQUIPMENTS PVT. LTD.,
ATS CHEM EQUIPMENTS PVT. LTD., AN ISO 9001:2015 CERTIFIED COMPANY Unit 1, C 27, SIDCO Industrial Estate, Hosur 635 126, Tamil Nadu, India. Phone No: 04344 276731, Mail ID: atschem@gmail.com Unit II, 16
More information9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning
9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning L. Ronayette, G. Caplanne, P. Hanoux, R. Pfister, M. Pissard, P. Pugnat CNRS-LNCMI, Grenoble,
More informationThe Results of the KSTAR Superconducting Coil Test
1 FT/3-2 The Results of the KSTAR Superconducting Coil Test Y. K. Oh, Y. Chu, S. Lee, S. J. Lee, S. Baek, J. S. Kim, K. W. Cho, H. Yonekawa, Y. Chang, K. R. Park, W. Chung, S. H. Lee, S. H. Park, I. S.
More informationCryogenic Improvements for the ATLAS Energy Upgrade
Cryogenic Improvements for the ATLAS Energy Upgrade Cryogenic Operations Workshop May 9-11, 2006 Presented by Steve MacDonald Argonne National Laboratory A Laboratory Operated by The University of Chicago
More informationFuture opportunities for Industry
Neutral Beam Test Facility Heating Neutral Beam Injectors Electron Cyclotron Power Supplies and Sources Tullio Bonicelli and the NB&EC PSS Project Team with thanks to all European Laboratories and Industries
More informationITER Vacuum Vessel Loads. Jake Blanchard October 2011
ITER Vacuum Vessel Loads Jake Blanchard October 2011 Introduction As we consider alternative materials for our vacuum vessel, it is natural to compare to the ITER vessel To make appropriate use of their
More informationTask Cryomodule. Paolo Pierini INFN Sezione di Milano - LASA
Task 1.3.3 Cryomodule Paolo Pierini INFN Sezione di Milano - LASA Outline Schedule borrowed from Alex Karlsruhe presentation Aim of the task & work split Comment on existing cryomodule designs, trying
More informationVacuum pumps for the ESRF EBS project Michael Hahn
3 rd Rencontres Nationales DU RESEAU TECHNOLOGIES DU VIDE SEVRIER, 10 13 October 2016 Vacuum pumps for the ESRF EBS project Michael Hahn On behalf of the EBS Accelerator Project Team OUTLINE Project definition
More informationPF Coil Fabrication Overview
PF Coil Fabrication Overview PF Coils Information Meeting Barcelona - 15 th October 2012 This presentation is intended for reference purposes only and is not a legally binding document PF Building Layout
More informationApproaches to Maintenance. S. Malang
Approaches to Maintenance S. Malang FNST Meeting, UCLA, August 12-14, 2008 Areas involved in the selection of methods for blanket maintenance: (Emphasis may be different for FNF and DEMO) - Segmentation
More informationHall C SHMS Progress
Hall C SHMS Progress Paul Brindza Hall C Senior Engineer January 25, 2013 Page 1 SHMS and Magnet Systems Overview Cryo-Control Reservoirs Cryogenics Infrastructure Power Supplies & Controls HB Q1 Q2 Q3
More informationSOFE
KOREAN R&D ON THE 6-PULSE CONVERTER UNIT FOR ITER AC/DC CONVERTERS SOFE 2011 2011. 06. 27 J. S. Oh 1), J. Choi 1), J. H. Suh 1), H. Liu 2), S. Lee 2), H. Park 2), W. Jung 2), S. Jo 2), H. Tan 3), J. Tao
More informationInterconnection Process for Generation Systems
Interconnection Process for Generation Systems I. INTRODUCTION...1 II. GENERAL INFORMATION...2 A. Definitions...2 B. Nodak Electric Cooperative, Inc. Generation Interconnection Contacts...3 C. Engineering
More informationCatalog HA Edition up to 24 kv, Air-Insulated, Extendable. Medium-Voltage Switchgear. siemens.com/simosec
Catalog HA 41.43 Edition 2018 Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear siemens.com/simosec Application Typical uses R-HA41-135.tif R-HA40-112.tif R-HA41-115.tif
More informationPRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION
PRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION X.R. Wang, C. Koehly, M. S. Tillack, S. Malang and F. Najmabadi ARIES-Pathways Project Meeting Germantown, DC May 21-22, 2013 OVERALL LAYOUT OF THE ACT-2
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationSingle, Two & Three-piece Ball Valves. ASME Class 150, 300 & mm mm (¼"- 8")
Single, Two & Three-piece Ball Valves SM Class 1, 300 & 600 8 mm - 200 mm (¼"- 8") Larsen & Toubro (L&T) is a technology, engineering, construction and manufacturing company. Seven decades of strong, customer-focused
More informationDEFECT DISTRIBUTION IN WELDS OF INCOLOY 908
PSFC/RR-10-8 DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908 Jun Feng August 10, 2010 Plasma Science and Fusion Center Massachusetts Institute of Technology Cambridge, MA 02139, USA This work was supported
More informationZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast.
ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW High performance alternative to air
More informationThe Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement. F. Albajar, T. Bonicelli (F4E)
The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement F. Albajar, T. Bonicelli (F4E) Overview Introduction: the ECRH system for ITER The 2001 technical specifications The Design
More informationMERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1
MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: 2190986ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 October 6, 2010 110-502 Report_1.doc D. J. Halpenny
More informationDr. Awad S. Hanna. Professor, Chair of Construction Engineering and Management Program University of Wisconsin- Madison
Dr. Awad S. Hanna Professor, Chair of Construction Engineering and Management Program University of Wisconsin- Madison PLANNED SCHEDULE COMPRESSION Biography Awad S. Hanna, Ph.D., P.E Awad S. Hanna is
More informationModernising the Great Western railway
Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western
More informationAvailable online at ScienceDirect. Physics Procedia 67 (2015 )
Available online at www.sciencedirect.com ScienceDirect Physics Procedia 67 (2015 ) 1181 1186 25th International Cryogenic Engineering Conference and the International Cryogenic Materials Conference in
More informationUrea Reactor Height Extension to Increase Capacity
Technical Paper June 2014 Urea Reactor Height Extension to Increase Capacity Hermann Kernberger Schoeller-Bleckmann Nitec GmbH (SBN), Austria Bob Edmondson Yara Belle Plaine, Canada Summary A discussion
More informationSwitchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable
Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear Totally Integrated Power SIMOSEC Catalog HA 41.43 Edition Sept. 2014 Answers for infrastructure and cities. Neue
More informationFRM II Converter Facility
FRM II Converter Facility Volker Zill Heiko Gerstenberg Axel Pichmaier Technical University of Munich Forschungs-Neutronenquelle Heinz Maier-Leibnitz (FRM II) Lichtenbergstrasse 1, 85748 Garching - Federal
More informationTECHNICAL PAPER ON SOLAR PV INSTALLATION & DESIGN AT IIT BHUBANESWAR
TECHNICAL PAPER ON SOLAR PV INSTALLATION & DESIGN AT IIT BHUBANESWAR 1. INTRODUCTION Sun is an amazing resource which radiates energy and provides us both heat and light by fusing hydrogen into helium
More informationLife Extension Testing of Electrical Penetration Assemblies
Nuclear Division Life Extension Testing of Electrical Penetration Assemblies EQ Conference Oct 31 Nov 2, 2018 Steve Benesh, Curtiss-Wright Nuclear 1 October 22, 2018 Curtiss-Wright Summary Life Extension
More informationModular integrated transportable substation (MITS)
Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................
More informationSwitchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable
www.siemens.com/medium-voltage-switchgear Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear Catalog HA 41.43 2012 Answers for infrastructure and cities. Neue Bilder
More informationMagnet, Support and Infrastructure. Whit Seay November 7, 2014
Magnet, Support and Infrastructure Whit Seay November 7, 2014 Engineering Progress Efforts in cost and labor estimate Contributions to pcdr document Visit to Cornell Dry Run - Magnet - Hall A Layout for
More informationGFED 1/2/3 PRODUCT CATALOGUE
A Cryogenic Industries Company GFED 1/2/3 PRODUCT CATALOGUE For enquires please contact General Manager : Bruce Van Dongen Email: vandb@cosmodyne.com Cell : (+27) 082-555-4928 Senior Engineer : Rohit Batarakhaye
More informationCVI Valve Line. Exceeds the industry s highest standards for reliability and performance
CVI Line Exceeds the industry s highest standards for reliability and performance Available in the most standard models with the shortest lead times in the industry Exceptional quality every CVI valve
More informationCRYO FTIR.
FTIR Cryostats Cryostats for FTIR Experiments Cryo Industries Variable Temperature Continuous Flow Cryostas (Models RC-102 and RC-152) are an excellent choice for Fourier Transform Infra-Red (FTIR) spectroscopy
More informationTunney s Pasture Station Bus Loop and Lay-up Area Design
2017 Canadian Consulting Engineer Award Submission Tunney s Pasture Station Bus Loop and Lay-up Area Design Presented to: Canadian Consulting Engineer 80 Valleybrook Drive Toronto, Ontario M3B 2S9 April
More informationCONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT
CONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT X.R. Wang 1, S. Malang 2, A. R. Raffray 1 and The ARIES Team 1 University of California, San Diego, CA, 9500 Gilman
More informationITER Shield Blanket Design Activities At SWIP
1 ITER Shield Blanket Design Activities At SWIP F. Zhang 1), W. S. Kang 1), J. H. Wu 1), Y. K. Fu 1), J. M. Chen 1) F. Elio 2) 1) Southwestern Institute of Physics, P. O. Box 432 Chengdu, 610041, China
More informationInstallation Instructions
GEMINI SELECT 38APS025-050,38APD025-100 Air-Cooled Condensing Units with PURON Refrigerant (R-410A) 50/60 Hz Installation Instructions CONTENTS Page SAFETY CONSIDERATIONS...................... 1 INSTALLATION................................
More informationEIS MTM/TTM THERMAL BALANCE TEST SPECIFICATION, PROCEDURES AND PREDICTIONS
SOLAR-B Instrument EIS MTM/TTM THERMAL BALANCE TEST SPECIFICATION, PROCEDURES AND PREDICTIONS Document No. BU/SLB-EIS/TN/020.03 Compiled by H. Mapson-Menard and C. V. Goodall The University of Birmingham
More informationUHV Flow Cryostat - Helitran
The ARS manufactured LT3B Helitran is a True UHV cold head (10-11 Torr) where all of the rubber o-ring seals have been replaced with welded joints and metal seals. Like all of our LT3 helium flow cryostats,
More informationTANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U)
Revision 0 TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U) R. F. Fogle September 15, 2002 Westinghouse Savannah River Company LLC Savannah River Site Aiken, South Carolina 29802 This document was prepared
More informationTechnical Summary. Contract for Procurement of Manual Valves, Relief Valves, Control Valves, and Valve Actuators (IO/15/CFT/11867/ACS CP/3)
Purpose Technical Summary Contract for Procurement of Manual Valves, Relief Valves, Control Valves, and Valve Actuators (IO/15/CFT/11867/ACS CP/3) The purpose of this Call for Nominations is to establish
More informationBattery Technology for Data Centers and Network Rooms: Site Planning
Battery Technology for Data Centers and Network Rooms: Site Planning White Paper # 33 Executive Summary The site requirements and costs for protecting information technology and network environments are
More informationCORRIGENDUM/ ADDENDUM 09 ADDITIONAL REQUIREMENT OF ELEVATOR.
AMENDMENT-02 TO TECHNICAL SPECIFICATION FOR ELEVATOR (SPEC NO. PE-TS-408-502-A001) 1x800 MW WANAKBORI STPP. CORRIGENDUM/ ADDENDUM 09 ADDITIONAL REQUIREMENT OF ELEVATOR. CL. NO. 2.0 Scope of equipment supply
More informationCENTRIFUGAL LIQUID CHILLERS INSTALLATION INSTRUCTIONS Supersedes: N1 (894) Form N1 (197)
CENTRIFUGAL LIQUID CHILLERS INSTALLATION INSTRUCTIONS Supersedes: 160.49-N1 (894) Form 160.49-N1 (197) MODEL YK L1 L1 G4 THRU YK S2 S2 J4 (STYLES A & B) R-22 AND R-134a (COOLING ONLY) AND MODEL YK LB LB
More informationThe Generator Company 3MVA Bespoke Generator
The Generator Company 3MVA Bespoke Generator System for New UK Distribution Centre Nearing the end of 2016 we were contacted by a regular client to design and install a back-up generator power system to
More informationGazprom s Helium Facility in Orenburg Supply & Start-Up of a Linde Liquefier. Klaus Ohlig Twente, July 9 th, 2014
Gazprom s Helium Facility in Orenburg Supply & Start-Up of a Linde Liquefier Klaus Ohlig Twente, July 9 th, 2014 Table of Contents 1. Introduction 2. Linde s Helium Product Portfolio 3. Key Components
More informationBARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Barrhaven Fellowship CRC 3058 Jockvale Road Ottawa, ON K2J 2W7 December 7, 2016 116-649 Report_1.doc D. J.
More informationproduct catalogue Q215 ISO 9001:2008 certified
product catalogue Q215 ISO 9001:2008 certified Haelok the company Haelok Inc, the inventor of one of the world strongest mechanical pipe connection, is a Zurich, Switzerland based privately held company,
More informationATTACHMENT NO. 9 MWI FIELD TRIP REPORT DURING INTIAL TESTING OF PUMPING EQUIPMENT DTD 24 APRIL 2006
ATTACHMENT NO. 9 MWI FIELD TRIP REPORT DURING INTIAL TESTING OF PUMPING EQUIPMENT DTD 24 APRIL 2006 1 MWI FIELD TRIP REPORT By Dennis Strecker April 24, 2006 Upon arrival at the test facility on April
More informationA 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids
A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids Author Company Email Presenter T.A. Messinger BC Hydro toly.messinger@bchydro.com E. Burt BC Hydro ed.burt@bchydro.com P.Glaubitz Siemens
More informationHYDRAULIC CARTRIDGE VALVES
HYDRAULIC CARTRIDGE VALVES SOLENOID OPERATED DIRECTIONAL CONTROLS PROPORTIONAL CONTROLS MOTORIZED CONTROLS MECHANICAL DIRECTIONAL CONTROLS MECHANICAL PRESSURE CONTROLS MECHANICAL FLOW CONTROLS FEBRUARY
More informationHighway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary
Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared
More informationDevelopment of Full-size Mockup Bushing for 1 MeV ITER NB System
1 ITR/P1-15 Development of Full-size Mockup Bushing for 1 MeV ITER NB System H. Tobari 1), T. Inoue 1), M. Hanada 1), M. Dairaku 1), K. Watanabe 1), N. Umeda 1), M. Taniguchi 1), M. Kashiwagi 1), H. Yamanaka
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationExisting 400A Circuit Breaker For B Secondary Chill Water Pump. Existing Single 2.5 Conduit. Reuse As Much As Practical
New A Secondary Chill / 60V /36A Fused Disconnect For A Secondary Chill and Flex New B Secondary Chill / 60V / 36A B Secondary Chill Single 2.5 Conduit. Install New Additional 2.5 R.S.G. Conduit From 00A
More informationFOOD PROCESSING INDUSTRY
H VARLEY LIMITED CASTORS AND WHEELS CATALOGUE FPI16.1 products for the FOOD PROCESSING INDUSTRY Easy product selection! Ask for a site survey, our technical sales team will make an inventory of the products
More informationDEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance
DEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance 1.) Overview on European Blanket Concepts and Integration principles 2.) Large Module Integration 3.) Multi Module Segment (MMS) Integration
More informationTABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:
TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design
More informationSlide 1. ABB September 9, 2015
Tarak Mehta, Head of Low Voltage Products, ABB Ltd., Capital Markets Day, Next Level Stage 2 New Electrification Products division: Power & Automation for the site Slide 1 Important notices Presentations
More informationReport on Major Achievements, Significant Developments and Important events for The Month of May-2018
Report on Major Achievements, Significant Developments and Important events for The Month of May-2018 Following are the details of major achievements, significant developments and important events in the
More informationTransit City Etobicoke - Finch West LRT
Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2
More informationInstallation Instructions
GEMINI SELECT 38APS025-065, 38APD025-130 Air-Cooled Condensing Units with PURON Refrigerant (R-410A) 50/60 Hz Installation Instructions CONTENTS Page SAFETY CONSIDERATIONS...................... 1 INSTALLATION................................
More informationFacilities. Presented by Jim Irby for the C-Mod Group
Facilities Presented by Jim Irby for the C-Mod Group Outline Machine History and Status 2008 run campaign Machine inspection Alternator and Flywheel Inspections Availability Chart Contributions to ITER
More informationP R O D U C T S PRODUCTS OUR PRODUCT LINE RANGES FROM:
Capabilities P R O D U C T S PRODUCTS American Crane is recognized as a leader in the design and manufacture of electric overhead traveling cranes and wire rope hoists, offering equipment up to 1,000 ton
More informationINTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT
INTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT X.R. Wang 1, S. Malang 2, L.A. El-Guebaly 3, A. R. Raffray 1 and the ARIES Team 1 University of California, San
More informationPortable. Storage and Transport Dewars. CL/CLPB Series, CH Series, CFN/CFL Series
Portable Storage and Transport Dewars CL/CLPB Series, CH Series, CFN/CFL Series CL/CLPB Series Cryofab s CL series portable liquid cylinders are intended for low-pressure transport and storage of liquid
More informationDevelopment of Two-stage Electric Turbocharging system for Automobiles
Development of Two-stage Electric Turbocharging system for Automobiles 71 BYEONGIL AN *1 NAOMICHI SHIBATA *2 HIROSHI SUZUKI *3 MOTOKI EBISU *1 Engine downsizing using supercharging is progressing to cope
More informationCITY OF VANCOUVER ADMINISTRATIVE REPORT
CITY OF VANCOUVER A19 ADMINISTRATIVE REPORT Report Date: July 10, 2007 Author: Chris Darwent Phone No.: 604.873.7358 RTS No.: 6866 VanRIMS No.: 13-1400-20 Meeting Date: July 24, 2007 TO: FROM: SUBJECT:
More informationAppendix E3. Open Pit Pioneering and Pre-production
Appendix E3 Open Pit Pioneering and Pre-production File Note From: George Dermer To: File Date: January 11, 2012 Re: KSM Mitchell Pit Mine Pre-Production and Start-up plan Summary: Pre-Production mining
More informationM. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA
LBNL-48445 SCMAG-749 SUPERCONDUCTING MAGNETS FOR INDUCTION LINAC PHASE-ROTATION IN A NEUTRINO FACTORY M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA ABSTRACT The neutrino
More informationB kv T&D GAS INSULATED SWITCHGEAR
GAS INSULATED SWITCHGEAR B 105 170 300 kv The increasing demand for electrical power in cities and industrial centers necessitates the installation of a compact and efficient distribution and transmission
More informationBall Valves. ASME Class 150 to mm mm (¼" - 8") ISO 17292/ API 6D
Ball Valves SM Class 150 to 2500 8 mm - 200 mm (¼" - 8") ISO 17292/ PI 6D L&T Valves Limited is a wholly owned subsidiary of Larsen & Toubro. Backed by a fifty-year track-record of excellence and world-leading
More informationUPDATE ON THE LHC MAIN MAGNETS. Lucio Rossi CERN - LHC MAC 15
UPDATE ON THE LHC MAIN MAGNETS Lucio Rossi CERN - LHC MAC 15 Content Cable Components Production of dipoles and learing curves Fiedl quality Collared cois CM production Results and Delivery Plan for dipoles
More informationSummary of HRS sampling and analysis in HyCoRA. HyCoRA OEM workshop Trondheim, Thor Anders Aarhaug, SINTEF Materials and Chemistry
Summary of HRS sampling and analysis in HyCoRA HyCoRA OEM workshop Trondheim, 2017-06-07 Thor Anders Aarhaug, SINTEF Materials and Chemistry SINTEF sampling background SINTEF subcontracted Smart Chemistry
More informationPUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4
PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4 1 2 3 4 5 6 7 8 9 Q. Please describe Hydro s terminal station and substation inspections policies and practices. In
More informationCOMPANY PROFILE 0045
0045 COMPANY PROFILE INTRODUCTION TO THE COMPANY THE MICROFINISH WAY Microfinish Valves Pvt. Ltd. is a privately owned and managed company specializing in industrial valves for energy, process, and natural
More informationTest units for all types of: Shut-off Valves Safety (relief) Valves Control Valves
Test units for all types of: Shut-off Valves Safety (relief) Valves Control Valves CALL 1800 023 859 TO SPEAK WITH ONE OF OUR TECHNICIANS Innovative Onsite Engineered Solutions 2 Ventil manufacturers test
More informationLARGE MOTOR SOLUTIONS
LARGE MOTOR SOLUTIONS Delivering an integrated system based on a qualified architecture for high servo press productivity Customers seeking high throughput for next generation machines often experience
More informationOld Ref No. New Ref. No. Major Changes
MAJOR CHANGES IN THE GENERAL SPECIFICATION FOR AIR-CONDITIONING, REFRIGERATION, VENTILATION AND CENTRAL MONITORING & CONTROL SYSTEM INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE
More informationWelded Valve Configurations
Welded Configurations Welded valve configurations are designed to improve the process in aseptic production facilities by reducing the dead legs in accordance to cgmp. Welded valve configurations may be
More informationLIQUID MEASUREMENT STATION DESIGN Class No
LIQUID MEASUREMENT STATION DESIGN Class No. 2230.1 Michael Frey Systems Sales Manager Daniel Measurement & Control, Inc. 5650 Brittmoore Rd. Houston, Texas 77041 INTRODUCTION The industry continues to
More information