ASSEMBLY INSTALLATION STUDIES FOR THE ITER CRYOLINE SYSTEM

Size: px
Start display at page:

Download "ASSEMBLY INSTALLATION STUDIES FOR THE ITER CRYOLINE SYSTEM"

Transcription

1 ASSEMBLY INSTALLATION STUDIES FOR THE ITER CRYOLINE SYSTEM S Badgujar 1, N Shah 2, A Forgeas 1, N Navion-Maillot 1, E Monneret 1, D Grillot 1, L. Benkheira 1 and B Sarkar 2 1 ITER Organization, Route de Vinon-sur-Verdon, CS , St. Paul Lez Durance Cedex, France 2 ITER-India, Institute for Plasma Research, Bhat, Gandhinagar , India The views and opinions expressed herein do not necessarily reflect those of the ITER Organization Page 1

2 OUTLINE INTRODUCTION THE CRYOLINE SYSTEM BRIEF SPECIFICATION INSTALLTION PLAN CONFIGURATION, TRANSPORTATION SEQUENCE, ASSEMBLY SITE WORK STATISTICS SCHEDULE INSTALLTION CHALLENGES AND RISKS CONCLUSION Page 2

3 Magnets: PF Magnets: CS ITER CRYOGENIC SYSTEM Magnets: TF Magnets: STR Magnets: C Leads Cryo Pumps Thermal Shields K 3 Plants Avg K 300K to 80K: LN2 PLANTS (1,2) LHe 1 LHe 2 LHe 3 80K: Ghe Loops (1,2) EU-DA IO IN-DA IN-DA Cryoplants 4K: LHe Distribution 80K: GHe Distribution Cryodistribution 8 boxes CryoLines ~ 5 km 4K USERS 80K USERS Page 3

4 LAYOUT ITER CRYOGENIC SYSTEM Page 4

5 THE CRYOLINE SYSTEM IN TOKAMAK BUILDING South West Shaft L3 level From Plant bridge North West Shaft Y B1 level B2M level X X Y+W B2 level W TOKAMAK BUILDING Page 5

6 TECHNICAL SPECIFICATION OF CLs and WLs Specifications Cryolines (CLs) Warm lines (WLs) No. of process pipes (PP) 1 to 7 1 Length ~ 5000 m ~ 6000 m No, Type of lines 21 multi, 16 single PP 55 single process Outer jacket (OVJ) Size DN 100 to DN 1000 DN 50 to DN 1600 Segments Straight, Tee, Elbow, Z Straight, Tee, Elbow, Z Temperature levels 4.5 K (3.8 K), 50 K, 80 K, 300 K 300 K, 423 K, 473 K Fluids Helium(He), Nitrogen(N2) Helium, Nitrogen, He+N2+Oil Pressure of process fluid Maximum 21 bar Maximum 42 bar Materials of PP/OVJ ,14435 (304L,316L) 304/304L (or eq. EN) Quality Classes (QC) QC 1, QC 2 QC 2, QC 3, QC 4 Seismic Classes (SC) SC1 (SF), SC1 (S), SC2, NSC SC2, NSC Safety Classes SIC-II, SR, Non-SIC SR, Non-SIC DN 500 OVJ most common among complex cryolines (X) Biggest DN of the process pipe DN300 C/s of 342CM0 Page 6

7 INSTALLATION PLAN 3 different buildings B50x, Plant bridge, Tokamak building Area by area installation in building [Parallel installation] Given area Construction work package [1-2-3 CLs] Modular approach for installation of the CLs Straight Tee Elbow [90 ] Elbow [>90 ] Step Max. dimensions as per site constraints ~ 10 m Max weight of spool ~ 10 ton C1 C2 (Cryolines Group-X) Design, Mgf, Supply Installation* (Cryolines Group-Y) Design, Mgf, Supply, installation (Warmlines Group- W) Design, Mgf, Supply, installation Installation contractor - 1 Installation contractor -2 Page 7

8 SITE WORK FLOW Upstream ACB Downstream ACB WITH TEST END CAPS Page 8

9 ARRIVAL ON SITE AND TRANSPORTATION ROAD FOR DELIVERY STORAGE ROADS FOR PRE-ASSEMBLY WORKSHOPS ROADS FOR INSTALLATION NORTH Spools inside container on truck Delivery Packaging: Closed containers (~ISO 40 feet) Approximate estimation based on present schedule and scope 300 nos [X,Y,W] ITER incoming inspection Documentation, Pressure gauge, Accelerometer Page 9

10 NORTH ENTRY TO TOKAMAK BUILDING B2 B11 Tokamak Bldg. B14 Tritium Bldg. Mobile crane near the platform in seismic pit 5.3 m H x 6.6 m L 5.3 m H x 6.6 m L 12 m L x 9 W x 3.3 high Page 10

11 MOVEMENT IN TOKAMAK BUILDING Opening at B2 L3 B2 SOUTH-WEST Opening at L3 ALL BUILDING OPENINGS, CONSTRAINTS AND LIMITATIONS HAVE BEEN STUDIED POSSIBLE TO MANOEUVRE IN B11- AT ALL THE LEVELS: B2,B2M,B1 and L3 Page 11

12 SEQUENCE IN TOKAMAK BUILDING From farthest point from the entrance of spools to nearest point From top (close to ceiling) to bottom (floor) From inner wall (centre of Tokamak) to outer wall (external wall of tokamak building) From bigger to smaller line NORTH Material movement Installation progress B D Point of entry at B2 E WEST EAST Section S-S A S S SOUTH C Area in the level Seque nce No. Prefered installation sequence among the lines [CLs-WLs] Building Level Tokamak B2 South 1 342CTS - TF cryoline 2 342CPL - PF cryoline 3 342SQL - Quench line 4 342WP0 - Purge line WCL - Current lead line 6 342WDH - He distribution line 7 342SR0 - Relief line Page 12

13 Outer Wall Inner Wall SEQUENCE IN TOKAMAK BUILDING Installation starts once the building are ready for equipment (RFE) CLs first equipment to be installed in most of the areas in B11 Other systems will follow the installation after 4 weeks General principal Specific situations! Ceiling B D Slab A C B2M QUADRANT B2 Page 13

14 SPOOL INTERCONNECTIONS Internal pipe welds TEST Shield Outer jacket welds Global TEST B2M AMONG CRYOLINE SPOOLS A Tests on PP Install MLI on PP Shield assembly and MLI WITH INTERFACE EQUIPMENTS B CVB B1 TYPE I WITH BELLOW TYPE II - WITHOUT Page 14

15 ASSEMBLY OF THE LINE Finish Joining of spools one by one to form the complete cryoline Start INSTALLATION TIME FOR ONE INTER-CONNECTION ~24 hrs DN 500 lines ~36 hrs for DN lines ~48 hrs DN 1000 line Page 15

16 Process pipes WELDS MAJOR IN PROCESS INSEPCTION Radiography All weld joints on PP during assembly and installation Visual test All weld joints on PP during assembly and installation VT RT Visual QC VT RT LT LN % 100% 100% * 2 100% 20% 20% * 3 100% 10% 10% NA LT Radiography LN2 Helium leak tightness test Liquid nitrogen thermal shock test - *SAMPLE Helium leak testing All weld joints assembly and installation at room temperature Overall leak testing at warm and cold (for complete line) Thermal Shock test Sample welds during assembly and installation Pressure test All independent sub-assemblies (e.g. one complete cryoline) at room temperature Cold test (for cryolines only) Overall performance at cold temperature (thermal performance measurement, leak test, checking for cold spot on OVJ) Page 16

17 SITE WORK STATISTICS Summary of the spools for all ITER CLs and WLs Building/Area Area/level in building CLs WLs Total L NW Shaft (L2, L1) Tokamak SW Shaft (L2, L1) Building (B11) B B2 / B2M Plant Bridge Cryoplant building/area 51 (Compressor building) (Cryoplant building) Area Total WELDS >11000 ~7000 CLs ~1300 WLs ~3000 Supports Summary estimated welding length (meter) CLs + WLs + Building/Area Total supports supports Tokamak Building Plant Bridge Cryoplant building/area Total Summary of estimated test length (meter) Building/Area CLs WLs Total PP OVJ Tokamak Building Plant Bridge Cryoplant building/area 900 Total Page 17

18 SITE WORK STATISTICS - TIME Level No. of No. of interfa element ce to s to be be connect connec ed ted Total Total intercon nections 1 working day per intercon nection 1 shift installati on [1 working day=3 shifts=3d ays] 10 days overlap, 10 days test 22 working days in 1 month Factor used for single and multi normalizat ion Days Days Days Months Months Years Tokamak Building L NW Shaft SW 0 15 Shaft B B2M B ~3/4 teams working in parallel in Tokamak building to meet the schedule Night shift for RT Second shift (if needed) to accelerate the installation Page 18

19 1 Typical Assembly & Installation Team Welder(s) (manual welds) stainless steel/carbon steel 2 Welders / Operator(s) (orbital welding machine) 3 Fitter(s) Rigger(s)/ Helper(s) transport of pipe 4 spools/supports, Material handling 5 Technician - MLI 6 Technician NDT [RT, LT, VT, LN2 shock] 7 Engineer(s) technical/construction 8 Inspector(s)/Controller(s) - Inspections agencies 9 QA Officer 10 Safety Officer 11 Site in-charge 12 Office Support Staff RESOURCES 3-4 team ~6-8 person per team per location >30 people on site during the peak installation period To be adapted: Based on the site requirements/constraints Contractor execution plan Page 19

20 TOOLS Portable small crane Forklift-stacker Arrangement from EP Mini spider crane A type cranes Platform + specific forklift Use of Embedded plates for fixation of Lifting equipment + Chain pulley block Page 20

21 Bldg 51.1 C&W lines B51 upper Trench W C&W lines B52 Fire Wall Bldg 51.2 CRYOPLANT INSTALLATION SUMMARY Area 53: Building 51: Bldg 51.1 Building 51: Bldg 51.2 Building 51: Bldg 51.3 Building 52: Name PBS Date Name PBS Date Name PBS Date Name PBS Name PBS Date Name PBS Date Name PBS Date Name PBS Date 1 C&W lines Area 53 Part Apr-17 9 Test heater 34.1W.E k CB L.B1 25 LHe tanks valve box 34.1S.HB 1 He CS (CPs) 34.4H.C2 21-Apr He CS 1 (CPs) 34.4H.C1 21-Apr C&W lines B51 Fire Wall Apr-17 1 C&W lines B52 Fire Wall Apr-17 2 GHe Storage 34.1S.HG 10 GAN Purifier 34.1G.B k CB L.B K heaters 34.1W.E 2 He CS (CPs) 34.4H.C3 22 Cryolines 80K Junction 34.2S.L0 32 Gasbag Storage 34.1S.B0 2 He Cold box H.B1 3 GN2 Storage 34.1S.NG 11 Air Compressor 34.1G.C0 19 He Purifaction 34.1P.B0 27 C&W lines Area 53 Final Cnt He CS 2 (ORS) 34.4H.C1 23 He CS 1 (ORS) 34.4H.C1 33 He CS 1 (FORS) 34.4H.C1 3 He Cold box H.B2 4 N2 CB N.B1 12 Liquid disposal Atmo. He Heater 34.1W.AH 4 He CS 3 (ORS) 34.4H.C k CS L.C2 34 He CS 2 (FORS) 34.4H.C2 4 He Cold box H.B3 5 C&W lines Area 53 Part LN2 Storage Warm Skid 34.1S.NL 21 C&W lines Area 53 Part IN-DA 5 N2 CS N.C k CS L.C1 35 Dryers 34.1P.D1 5 Test Cryostat 34.4H.T0 6 N2 CB N.B2 14 LN2 Storage Vaporizer 34.1W.AN 22 Quench Tank 34.1S.Q0 IN-DA 6 N2 CS N.C2 26 Helium Recovery System 34.1P.R0 36 He CS 3 (FORS) 34.4H.C3 6 CTCB Y 7 LN2 Storage 34.1S.NL 15 Casing Pump 34.1S.NL 23 LHe storage 34.1S.HL F4E 7 C&W lines B51 upper Trench W Leak treatment 34.1P.T0 37 C&W lines B51 upper Trench N/S C&W lines B52 Final Cnt Air Separation Column 34.1G.D0 16 C&W lines Area 53 Part Quench tanks cold box 34.1S.QB IO 28 C&W lines B51 upper Trench N C&W lines B52 CTCB Area C&W lines Area Part C&W lines Area 53 Part 1 5 C&W lines Area 53 Part 2 16 C&W lines Area 53 Part C&W lines Area CRYOLINES AND WARM LINES IN B50s X Y+W C&W lines B51 Fire Wall Bldg 51.3 Bldg 52 Area 53: Name PBS Date Name PBS Date Name PBS Date Name PBS Date 1 C&W lines Area 53 Part Building 1 51: Bldg Apr-17 9 Test heater Building 51: 34.1W.E0 Bldg k CB 1 Building 34.1L.B1 51: Bldg LHe tanks valve box Building 34.1S.HB 52: 2 GHe Storage Name 34.1S.HG PBS Date 10 GAN Purifier Name 34.1G.B0 PBS Date18 80k CB 2 Name 34.1L.B2 PBS Date K heaters Name34.1W.E0 PBS 3 GN2 Storage 1 He CS 2 (CPs) 34.1S.NG 34.4H.C2 21-Apr Air Compressor 21 He CS 1 (CPs) 34.1G.C0 34.4H.C1 21-Apr He Purifaction 31 C&W lines B51 Fire Wall 34.1P.B Apr C&W lines 1Area C&W 53 lines Final B52 CntFire Wall N2 CB 12 He CS 3 (CPs) 34.1N.B1 34.4H.C3 12 Liquid 22 disposal Cryolines 80K Junction S.L0 20 Atmo. He 32Heater Gasbag Storage 34.1W.AH 34.1S.B0 2 He Cold box H.B1 5 C&W lines 3 He Area CS 253 (ORS) Part H.C1 13 LN2 Storage 23 He Warm CS 1 (ORS) Skid 34.1S.NL 34.4H.C1 21 C&W lines 33 Area He CS 531 Part (FORS) H.C1 IN-DA 3 He Cold box H.B2 6 N2 CB 24 He CS 3 (ORS) 34.1N.B2 34.4H.C1 14 LN2 Storage 24 80k Vaporizer CS W.AN 34.1L.C2 22 Quench 34 Tank He CS 2 (FORS) 34.1S.Q0 34.4H.C2 IN-DA 4 He Cold box H.B3 7 LN2 Storage 5 N2 CS S.NL 34.1N.C1 15 Casing 25 Pump 80k CS S.NL 34.1L.C1 23 LHe storage 35 Dryers 34.1S.HL 34.1P.D1 F4E 5 Test Cryostat 34.4H.T0 8 Air Separation 6 N2 CS Column G.D0 34.1N.C2 16 C&W lines 26 Helium Area 53 Recovery Part 3 System P.R0 24 Quench 36 tanks He cold CS 3 box (FORS) 34.1S.QB 34.4H.C3 IO 6 CTCB Y 7 C&W lines B51 upper Trench W Leak treatment 34.1P.T0 37 C&W lines B51 upper Trench N/S C&W lines B52 Final Cnt C&W lines B51 upper Trench N C&W lines B52 CTCB Page 21

22 SCHEDULE Line PBS Connections O N D J F M A MY J JL A S O N D J F M A MY J JL A S O N D T&C North 342CHN 11 T&C South 342CHS 10 TF South 342CTS 17 T&C South 342CHS 1 T&C North 342CHN 1 TF North 342CTN 21 Quench Lower 342CQL 47 PF Lower 342CPL 16 Structure Lower 342CSL 3 CS Lower 342CCL 12 Relief Line 342WR0 42 T&C North 342CHN 4 T&C South 342CHS 4 Top down approach to meet sub-system commissioning Installation RFE - Building is ready to receive the equipment Reasonable duration for each activity detailed schedule for one CL Used mainly to assign the duration for installation of certain length of CL with certain number of interconnections Detailed sequence with co-activities INSTALLATION TIME (ONE INTER-CONNECTION) ~24 hrs DN 500 TF,PF,T&C ~18 hrs DAY STR ~12 hrs QL, RELIEF ~ 12 hrs for spool transfer, position, alignment Constant Avg. Time Vicinity dependent! Major Assumption: Availability of installation window without any major interruptions Site authorizations are given within reasonable time 10% rework Not considered - Complete failure of CL during testing phase that follows the site installation Page 22

23 SUMMARY SCHEDULE PA, CDR Preliminary Design 1 st PTCL (prototype cryoline) test completed 2 nd PTCL test completion (planned) Final Design Fabrication Delivery Installation and connection to clients Connection to feeders at L3 Preliminary acceptance, COLD tests with end caps Cryoline ready to be connected to clients, sub-system commissioning Final acceptance after final connection to clients Final integrated pressure and leak test B2 L3 All Cryolines ready for integrated commissioning 1 st Cryo-plant ready SAT ACB CP ready Page 23

24 CHALLENGES AND RISKS Difficult installation and maintenance due to space limitation Sequencing among lines and with other systems in buildings More than one industrial partner for installation of CLs Co-activity, Starts Stops during installation Very limited in-service inspection and repair during operation - Detailed sequence and priority definition Stringent quality and testing requirements to avoid intervention in situ RISKS Non-availability or delayed availability of storage area / pre-assembly Non-availability of allotted timeslot for material movement/installation or radiography Slow installation at start due to learning curve and site adaptation Failure of welding during testing (non-destructive test or pressure test) Under estimation of installation process, complicacies and duration Civil work and equipment position tolerance more than considered in design Priority change due to the project decisions Page 24

25 CONCLUSION Conceptual assembly and installation plan respecting ITER CMS has been developed with detailed sequence Modular approach has been foreseen with sequential deliveries and continuous supply chain management to minimize on site inventory Site to suit interconnections with interface equipment planned Parallel installation foreseen with multiple teams at different areas Further detailed installation plan will be worked out with industrial partners Skilled teams from industries will execute the work as per work instruction, strict inspection-control and oversight of technical teams form IO-CT/IN DA Overall success for installation will depend on efficient co-ordination among all the concerned actors at ITER site Page 25

26 FEB 2016 THANK YOU FOR YOUR ATTENTION TOKAMAK BUILDING B2 B2M B52 CRYOPLANT BUILDING B51 Authors would like to thank the colleagues from ITER Organization in Cadarache, ITER-India in Gandhinagar as well as industrial partners for their contribution to ITER cryolines project Page 26

27 Extra slides Page 27

28 Two main lines - Magnets - Cryopumps COLD TEST Q Pipe = m(h 2 -H 1 ) Q Loop = m(h 4 -H 1 ) Lines from ACBs to the clients - Magnets (TF, PF, CS, STR) - Cryopumps WITH DEDICATED TEST CAPS Q Pipe = m(h 6 -H 1 ) Q Loop = m(h 8 -H 1 ) Page 28

Progress of the JT-60SA Project

Progress of the JT-60SA Project Progress of the JT-60SA Project P. Barabaschi, Y. Kamada, H. Shirai For the JT-60SA Integrated Project Team EU: F4E-CEA-ENEA-CNR/RFX-KIT-CIEMAT-SCKCEN JA: QST C.R.FRASCATI- ITALY 1 JT-60SA Project Agreement

More information

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon September 2018

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon September 2018 GENERAL ATOMICS ITER Central Solenoid Module Fabrication September 2018 ITER Central Solenoid The heart of the international fusion energy device The Central Solenoid (CS) is the heart of ITER. The 5-story,

More information

GENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION

GENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION GENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION January 2018 ITER Central Solenoid The heart of the international fusion energy device The Central Solenoid (CS) is the heart of ITER. The 5-story,

More information

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011 Low Beta Cryomodule Development at Fermilab Tom Nicol March 2, 2011 Concepts of SC CW 3GeV, 1mA Linac H - gun RFQ MEBT SSR0 SSR1 SSR2 β=0.6 β=0.9 ILC RT (~15m) 325 MHz 2.5-160 MeV 650 MHz 0.16-2 GeV 1.3

More information

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon August 2016

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon August 2016 GENERAL ATOMICS ITER Central Solenoid Module Fabrication August 2016 ITER Central Solenoid The heart of the international fusion energy program The Central Solenoid (CS) is the heart of ITER. The 5-story,

More information

ITER Magnets Update European perspective

ITER Magnets Update European perspective ITER Magnets Update European perspective Hannu Rajainmaki, Boris Bellesia, Alessandro Bonito-Oliva, Eva Boter, Thierry Boutboul, Eugen Bratu, Marc Cornelis, John Fanthome, Robert Harrison, Peter Readman,

More information

PF Coil 2-6 Supply. Main technical aspects. P. Valente

PF Coil 2-6 Supply. Main technical aspects. P. Valente PF Coil 2-6 Supply Main technical aspects P. Valente PF Coils EI Information Meeting Cadarache, 19 February 2013 This presentation is intended for reference purposes only and is not a legally binding document

More information

Technical Summary for BOP-Group 5 Installation Works The BOP Group 5 works include installation and commissioning of all the Items included in

Technical Summary for BOP-Group 5 Installation Works The BOP Group 5 works include installation and commissioning of all the Items included in IDM UID T244BP VERSION CREATED ON / VERSION / STATUS 03 May 2017 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Summary for BOP-Group 5 Installation

More information

EU Procurement of In Vessel Components for ITER

EU Procurement of In Vessel Components for ITER EU Procurement of In Vessel Components for ITER State of progress and next steps Patrick Lorenzetto ITER Business Forum 2013, Toulon, 21 22 March 2013 1 Content Blanket First Wall Procurement Package Blanket

More information

Costing of Test Articles Ancillary Equipment and Costing Methodology

Costing of Test Articles Ancillary Equipment and Costing Methodology Costing of Test Articles Ancillary Equipment and Costing Methodology 0.504 m x 1.71 m x 0.413 m C. Wong, S. Malang, M. Youssef, N. Morley, M. Ulrickson and the TBM design team US ITER-TBM Meeting August

More information

THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE

THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE EPAC08, Genoa (Italy) 26 June 2008 1451 1506 1918 1977 Norbert Holtkamp Principal Deputy

More information

KSTAR Assembly. National Fusion Research Center, Daejeon, Korea

KSTAR Assembly. National Fusion Research Center, Daejeon, Korea 1 FT/2-2 KSTAR Assembly H. L. Yang, H. K. Kim, K. M. Kim, J. W. Sa, S. T. Kim, H. T. Kim, K. H. Hong, W. C. Kim, K. H. Kim, Y. S. Kim, J. Y. Kim, C. H. Choi, Y. K. Oh, Y. M. Park, M. Kwon, J. S. Bak, G.

More information

JT-60SA Newsletter. Cryoplant arrives at the JAEA Naka Site. No. 65, 31 May Headline

JT-60SA Newsletter. Cryoplant arrives at the JAEA Naka Site. No. 65, 31 May Headline JT-60SA Newsletter Headline Cryoplant arrives at the JAEA Naka Site No. 65, 31 May 2015 After the successful discharge at the port of Hitachi on 21 March 2015, the refrigerator cold box (RCB) and the auxiliary

More information

Technical Specifications (In-Cash Procurement)

Technical Specifications (In-Cash Procurement) IDM UID VLHSLE VERSION CREATED ON / VERSION / STATUS 12 Feb 2018 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Summary for BOP-Group 6 Installation

More information

Status of ITER at the Transition to Construction

Status of ITER at the Transition to Construction Status of ITER at the Transition to Construction Guenter Janeschitz Deputy Head of Central Integration Office ITER Organisation Page 1 Outline Fusion Basics and History of ITER (very brief): ITER and its

More information

ITER PROJECT J. FARINEAU ITER ORGANIZATION. September 29th, 2010 SOFT PORTO: ITER-ORG 1

ITER PROJECT J. FARINEAU ITER ORGANIZATION. September 29th, 2010 SOFT PORTO: ITER-ORG 1 ITER PROJECT J. FARINEAU ITER ORGANIZATION September 29th, 2010 SOFT PORTO: ITER-ORG 1 Contents ITER Context and Background ITER Technical Systems ITER: Organization & Contractual Rules New ITER Project

More information

EU TF coils status. A.Bonito Oliva F4E Magnets Project Manager

EU TF coils status. A.Bonito Oliva F4E Magnets Project Manager EU TF coils status A.Bonito Oliva F4E Magnets Project Manager Slide 1 Presentation Outline TF coils Main Manufacture Steps Procurement strategy Status of the production Contracts and industries involved

More information

ATS CHEM EQUIPMENTS PVT. LTD.,

ATS CHEM EQUIPMENTS PVT. LTD., ATS CHEM EQUIPMENTS PVT. LTD., AN ISO 9001:2015 CERTIFIED COMPANY Unit 1, C 27, SIDCO Industrial Estate, Hosur 635 126, Tamil Nadu, India. Phone No: 04344 276731, Mail ID: atschem@gmail.com Unit II, 16

More information

9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning

9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning 9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning L. Ronayette, G. Caplanne, P. Hanoux, R. Pfister, M. Pissard, P. Pugnat CNRS-LNCMI, Grenoble,

More information

The Results of the KSTAR Superconducting Coil Test

The Results of the KSTAR Superconducting Coil Test 1 FT/3-2 The Results of the KSTAR Superconducting Coil Test Y. K. Oh, Y. Chu, S. Lee, S. J. Lee, S. Baek, J. S. Kim, K. W. Cho, H. Yonekawa, Y. Chang, K. R. Park, W. Chung, S. H. Lee, S. H. Park, I. S.

More information

Cryogenic Improvements for the ATLAS Energy Upgrade

Cryogenic Improvements for the ATLAS Energy Upgrade Cryogenic Improvements for the ATLAS Energy Upgrade Cryogenic Operations Workshop May 9-11, 2006 Presented by Steve MacDonald Argonne National Laboratory A Laboratory Operated by The University of Chicago

More information

Future opportunities for Industry

Future opportunities for Industry Neutral Beam Test Facility Heating Neutral Beam Injectors Electron Cyclotron Power Supplies and Sources Tullio Bonicelli and the NB&EC PSS Project Team with thanks to all European Laboratories and Industries

More information

ITER Vacuum Vessel Loads. Jake Blanchard October 2011

ITER Vacuum Vessel Loads. Jake Blanchard October 2011 ITER Vacuum Vessel Loads Jake Blanchard October 2011 Introduction As we consider alternative materials for our vacuum vessel, it is natural to compare to the ITER vessel To make appropriate use of their

More information

Task Cryomodule. Paolo Pierini INFN Sezione di Milano - LASA

Task Cryomodule. Paolo Pierini INFN Sezione di Milano - LASA Task 1.3.3 Cryomodule Paolo Pierini INFN Sezione di Milano - LASA Outline Schedule borrowed from Alex Karlsruhe presentation Aim of the task & work split Comment on existing cryomodule designs, trying

More information

Vacuum pumps for the ESRF EBS project Michael Hahn

Vacuum pumps for the ESRF EBS project Michael Hahn 3 rd Rencontres Nationales DU RESEAU TECHNOLOGIES DU VIDE SEVRIER, 10 13 October 2016 Vacuum pumps for the ESRF EBS project Michael Hahn On behalf of the EBS Accelerator Project Team OUTLINE Project definition

More information

PF Coil Fabrication Overview

PF Coil Fabrication Overview PF Coil Fabrication Overview PF Coils Information Meeting Barcelona - 15 th October 2012 This presentation is intended for reference purposes only and is not a legally binding document PF Building Layout

More information

Approaches to Maintenance. S. Malang

Approaches to Maintenance. S. Malang Approaches to Maintenance S. Malang FNST Meeting, UCLA, August 12-14, 2008 Areas involved in the selection of methods for blanket maintenance: (Emphasis may be different for FNF and DEMO) - Segmentation

More information

Hall C SHMS Progress

Hall C SHMS Progress Hall C SHMS Progress Paul Brindza Hall C Senior Engineer January 25, 2013 Page 1 SHMS and Magnet Systems Overview Cryo-Control Reservoirs Cryogenics Infrastructure Power Supplies & Controls HB Q1 Q2 Q3

More information

SOFE

SOFE KOREAN R&D ON THE 6-PULSE CONVERTER UNIT FOR ITER AC/DC CONVERTERS SOFE 2011 2011. 06. 27 J. S. Oh 1), J. Choi 1), J. H. Suh 1), H. Liu 2), S. Lee 2), H. Park 2), W. Jung 2), S. Jo 2), H. Tan 3), J. Tao

More information

Interconnection Process for Generation Systems

Interconnection Process for Generation Systems Interconnection Process for Generation Systems I. INTRODUCTION...1 II. GENERAL INFORMATION...2 A. Definitions...2 B. Nodak Electric Cooperative, Inc. Generation Interconnection Contacts...3 C. Engineering

More information

Catalog HA Edition up to 24 kv, Air-Insulated, Extendable. Medium-Voltage Switchgear. siemens.com/simosec

Catalog HA Edition up to 24 kv, Air-Insulated, Extendable. Medium-Voltage Switchgear. siemens.com/simosec Catalog HA 41.43 Edition 2018 Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear siemens.com/simosec Application Typical uses R-HA41-135.tif R-HA40-112.tif R-HA41-115.tif

More information

PRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION

PRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION PRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION X.R. Wang, C. Koehly, M. S. Tillack, S. Malang and F. Najmabadi ARIES-Pathways Project Meeting Germantown, DC May 21-22, 2013 OVERALL LAYOUT OF THE ACT-2

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Single, Two & Three-piece Ball Valves. ASME Class 150, 300 & mm mm (¼"- 8")

Single, Two & Three-piece Ball Valves. ASME Class 150, 300 & mm mm (¼- 8) Single, Two & Three-piece Ball Valves SM Class 1, 300 & 600 8 mm - 200 mm (¼"- 8") Larsen & Toubro (L&T) is a technology, engineering, construction and manufacturing company. Seven decades of strong, customer-focused

More information

DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908

DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908 PSFC/RR-10-8 DEFECT DISTRIBUTION IN WELDS OF INCOLOY 908 Jun Feng August 10, 2010 Plasma Science and Fusion Center Massachusetts Institute of Technology Cambridge, MA 02139, USA This work was supported

More information

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast.

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast. ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW High performance alternative to air

More information

The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement. F. Albajar, T. Bonicelli (F4E)

The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement. F. Albajar, T. Bonicelli (F4E) The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement F. Albajar, T. Bonicelli (F4E) Overview Introduction: the ECRH system for ITER The 2001 technical specifications The Design

More information

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: 2190986ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 October 6, 2010 110-502 Report_1.doc D. J. Halpenny

More information

Dr. Awad S. Hanna. Professor, Chair of Construction Engineering and Management Program University of Wisconsin- Madison

Dr. Awad S. Hanna. Professor, Chair of Construction Engineering and Management Program University of Wisconsin- Madison Dr. Awad S. Hanna Professor, Chair of Construction Engineering and Management Program University of Wisconsin- Madison PLANNED SCHEDULE COMPRESSION Biography Awad S. Hanna, Ph.D., P.E Awad S. Hanna is

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

Available online at ScienceDirect. Physics Procedia 67 (2015 )

Available online at   ScienceDirect. Physics Procedia 67 (2015 ) Available online at www.sciencedirect.com ScienceDirect Physics Procedia 67 (2015 ) 1181 1186 25th International Cryogenic Engineering Conference and the International Cryogenic Materials Conference in

More information

Urea Reactor Height Extension to Increase Capacity

Urea Reactor Height Extension to Increase Capacity Technical Paper June 2014 Urea Reactor Height Extension to Increase Capacity Hermann Kernberger Schoeller-Bleckmann Nitec GmbH (SBN), Austria Bob Edmondson Yara Belle Plaine, Canada Summary A discussion

More information

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear Totally Integrated Power SIMOSEC Catalog HA 41.43 Edition Sept. 2014 Answers for infrastructure and cities. Neue

More information

FRM II Converter Facility

FRM II Converter Facility FRM II Converter Facility Volker Zill Heiko Gerstenberg Axel Pichmaier Technical University of Munich Forschungs-Neutronenquelle Heinz Maier-Leibnitz (FRM II) Lichtenbergstrasse 1, 85748 Garching - Federal

More information

TECHNICAL PAPER ON SOLAR PV INSTALLATION & DESIGN AT IIT BHUBANESWAR

TECHNICAL PAPER ON SOLAR PV INSTALLATION & DESIGN AT IIT BHUBANESWAR TECHNICAL PAPER ON SOLAR PV INSTALLATION & DESIGN AT IIT BHUBANESWAR 1. INTRODUCTION Sun is an amazing resource which radiates energy and provides us both heat and light by fusing hydrogen into helium

More information

Life Extension Testing of Electrical Penetration Assemblies

Life Extension Testing of Electrical Penetration Assemblies Nuclear Division Life Extension Testing of Electrical Penetration Assemblies EQ Conference Oct 31 Nov 2, 2018 Steve Benesh, Curtiss-Wright Nuclear 1 October 22, 2018 Curtiss-Wright Summary Life Extension

More information

Modular integrated transportable substation (MITS)

Modular integrated transportable substation (MITS) Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................

More information

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable

Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable www.siemens.com/medium-voltage-switchgear Switchgear Type SIMOSEC, up to 24 kv, Air-Insulated, Extendable Medium-Voltage Switchgear Catalog HA 41.43 2012 Answers for infrastructure and cities. Neue Bilder

More information

Magnet, Support and Infrastructure. Whit Seay November 7, 2014

Magnet, Support and Infrastructure. Whit Seay November 7, 2014 Magnet, Support and Infrastructure Whit Seay November 7, 2014 Engineering Progress Efforts in cost and labor estimate Contributions to pcdr document Visit to Cornell Dry Run - Magnet - Hall A Layout for

More information

GFED 1/2/3 PRODUCT CATALOGUE

GFED 1/2/3 PRODUCT CATALOGUE A Cryogenic Industries Company GFED 1/2/3 PRODUCT CATALOGUE For enquires please contact General Manager : Bruce Van Dongen Email: vandb@cosmodyne.com Cell : (+27) 082-555-4928 Senior Engineer : Rohit Batarakhaye

More information

CVI Valve Line. Exceeds the industry s highest standards for reliability and performance

CVI Valve Line. Exceeds the industry s highest standards for reliability and performance CVI Line Exceeds the industry s highest standards for reliability and performance Available in the most standard models with the shortest lead times in the industry Exceptional quality every CVI valve

More information

CRYO FTIR.

CRYO FTIR. FTIR Cryostats Cryostats for FTIR Experiments Cryo Industries Variable Temperature Continuous Flow Cryostas (Models RC-102 and RC-152) are an excellent choice for Fourier Transform Infra-Red (FTIR) spectroscopy

More information

Tunney s Pasture Station Bus Loop and Lay-up Area Design

Tunney s Pasture Station Bus Loop and Lay-up Area Design 2017 Canadian Consulting Engineer Award Submission Tunney s Pasture Station Bus Loop and Lay-up Area Design Presented to: Canadian Consulting Engineer 80 Valleybrook Drive Toronto, Ontario M3B 2S9 April

More information

CONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT

CONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT CONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT X.R. Wang 1, S. Malang 2, A. R. Raffray 1 and The ARIES Team 1 University of California, San Diego, CA, 9500 Gilman

More information

ITER Shield Blanket Design Activities At SWIP

ITER Shield Blanket Design Activities At SWIP 1 ITER Shield Blanket Design Activities At SWIP F. Zhang 1), W. S. Kang 1), J. H. Wu 1), Y. K. Fu 1), J. M. Chen 1) F. Elio 2) 1) Southwestern Institute of Physics, P. O. Box 432 Chengdu, 610041, China

More information

Installation Instructions

Installation Instructions GEMINI SELECT 38APS025-050,38APD025-100 Air-Cooled Condensing Units with PURON Refrigerant (R-410A) 50/60 Hz Installation Instructions CONTENTS Page SAFETY CONSIDERATIONS...................... 1 INSTALLATION................................

More information

EIS MTM/TTM THERMAL BALANCE TEST SPECIFICATION, PROCEDURES AND PREDICTIONS

EIS MTM/TTM THERMAL BALANCE TEST SPECIFICATION, PROCEDURES AND PREDICTIONS SOLAR-B Instrument EIS MTM/TTM THERMAL BALANCE TEST SPECIFICATION, PROCEDURES AND PREDICTIONS Document No. BU/SLB-EIS/TN/020.03 Compiled by H. Mapson-Menard and C. V. Goodall The University of Birmingham

More information

UHV Flow Cryostat - Helitran

UHV Flow Cryostat - Helitran The ARS manufactured LT3B Helitran is a True UHV cold head (10-11 Torr) where all of the rubber o-ring seals have been replaced with welded joints and metal seals. Like all of our LT3 helium flow cryostats,

More information

TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U)

TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U) Revision 0 TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U) R. F. Fogle September 15, 2002 Westinghouse Savannah River Company LLC Savannah River Site Aiken, South Carolina 29802 This document was prepared

More information

Technical Summary. Contract for Procurement of Manual Valves, Relief Valves, Control Valves, and Valve Actuators (IO/15/CFT/11867/ACS CP/3)

Technical Summary. Contract for Procurement of Manual Valves, Relief Valves, Control Valves, and Valve Actuators (IO/15/CFT/11867/ACS CP/3) Purpose Technical Summary Contract for Procurement of Manual Valves, Relief Valves, Control Valves, and Valve Actuators (IO/15/CFT/11867/ACS CP/3) The purpose of this Call for Nominations is to establish

More information

Battery Technology for Data Centers and Network Rooms: Site Planning

Battery Technology for Data Centers and Network Rooms: Site Planning Battery Technology for Data Centers and Network Rooms: Site Planning White Paper # 33 Executive Summary The site requirements and costs for protecting information technology and network environments are

More information

CORRIGENDUM/ ADDENDUM 09 ADDITIONAL REQUIREMENT OF ELEVATOR.

CORRIGENDUM/ ADDENDUM 09 ADDITIONAL REQUIREMENT OF ELEVATOR. AMENDMENT-02 TO TECHNICAL SPECIFICATION FOR ELEVATOR (SPEC NO. PE-TS-408-502-A001) 1x800 MW WANAKBORI STPP. CORRIGENDUM/ ADDENDUM 09 ADDITIONAL REQUIREMENT OF ELEVATOR. CL. NO. 2.0 Scope of equipment supply

More information

CENTRIFUGAL LIQUID CHILLERS INSTALLATION INSTRUCTIONS Supersedes: N1 (894) Form N1 (197)

CENTRIFUGAL LIQUID CHILLERS INSTALLATION INSTRUCTIONS Supersedes: N1 (894) Form N1 (197) CENTRIFUGAL LIQUID CHILLERS INSTALLATION INSTRUCTIONS Supersedes: 160.49-N1 (894) Form 160.49-N1 (197) MODEL YK L1 L1 G4 THRU YK S2 S2 J4 (STYLES A & B) R-22 AND R-134a (COOLING ONLY) AND MODEL YK LB LB

More information

The Generator Company 3MVA Bespoke Generator

The Generator Company 3MVA Bespoke Generator The Generator Company 3MVA Bespoke Generator System for New UK Distribution Centre Nearing the end of 2016 we were contacted by a regular client to design and install a back-up generator power system to

More information

Gazprom s Helium Facility in Orenburg Supply & Start-Up of a Linde Liquefier. Klaus Ohlig Twente, July 9 th, 2014

Gazprom s Helium Facility in Orenburg Supply & Start-Up of a Linde Liquefier. Klaus Ohlig Twente, July 9 th, 2014 Gazprom s Helium Facility in Orenburg Supply & Start-Up of a Linde Liquefier Klaus Ohlig Twente, July 9 th, 2014 Table of Contents 1. Introduction 2. Linde s Helium Product Portfolio 3. Key Components

More information

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Barrhaven Fellowship CRC 3058 Jockvale Road Ottawa, ON K2J 2W7 December 7, 2016 116-649 Report_1.doc D. J.

More information

product catalogue Q215 ISO 9001:2008 certified

product catalogue Q215 ISO 9001:2008 certified product catalogue Q215 ISO 9001:2008 certified Haelok the company Haelok Inc, the inventor of one of the world strongest mechanical pipe connection, is a Zurich, Switzerland based privately held company,

More information

ATTACHMENT NO. 9 MWI FIELD TRIP REPORT DURING INTIAL TESTING OF PUMPING EQUIPMENT DTD 24 APRIL 2006

ATTACHMENT NO. 9 MWI FIELD TRIP REPORT DURING INTIAL TESTING OF PUMPING EQUIPMENT DTD 24 APRIL 2006 ATTACHMENT NO. 9 MWI FIELD TRIP REPORT DURING INTIAL TESTING OF PUMPING EQUIPMENT DTD 24 APRIL 2006 1 MWI FIELD TRIP REPORT By Dennis Strecker April 24, 2006 Upon arrival at the test facility on April

More information

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids Author Company Email Presenter T.A. Messinger BC Hydro toly.messinger@bchydro.com E. Burt BC Hydro ed.burt@bchydro.com P.Glaubitz Siemens

More information

HYDRAULIC CARTRIDGE VALVES

HYDRAULIC CARTRIDGE VALVES HYDRAULIC CARTRIDGE VALVES SOLENOID OPERATED DIRECTIONAL CONTROLS PROPORTIONAL CONTROLS MOTORIZED CONTROLS MECHANICAL DIRECTIONAL CONTROLS MECHANICAL PRESSURE CONTROLS MECHANICAL FLOW CONTROLS FEBRUARY

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

Development of Full-size Mockup Bushing for 1 MeV ITER NB System

Development of Full-size Mockup Bushing for 1 MeV ITER NB System 1 ITR/P1-15 Development of Full-size Mockup Bushing for 1 MeV ITER NB System H. Tobari 1), T. Inoue 1), M. Hanada 1), M. Dairaku 1), K. Watanabe 1), N. Umeda 1), M. Taniguchi 1), M. Kashiwagi 1), H. Yamanaka

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

Existing 400A Circuit Breaker For B Secondary Chill Water Pump. Existing Single 2.5 Conduit. Reuse As Much As Practical

Existing 400A Circuit Breaker For B Secondary Chill Water Pump. Existing Single 2.5 Conduit. Reuse As Much As Practical New A Secondary Chill / 60V /36A Fused Disconnect For A Secondary Chill and Flex New B Secondary Chill / 60V / 36A B Secondary Chill Single 2.5 Conduit. Install New Additional 2.5 R.S.G. Conduit From 00A

More information

FOOD PROCESSING INDUSTRY

FOOD PROCESSING INDUSTRY H VARLEY LIMITED CASTORS AND WHEELS CATALOGUE FPI16.1 products for the FOOD PROCESSING INDUSTRY Easy product selection! Ask for a site survey, our technical sales team will make an inventory of the products

More information

DEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance

DEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance DEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance 1.) Overview on European Blanket Concepts and Integration principles 2.) Large Module Integration 3.) Multi Module Segment (MMS) Integration

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Slide 1. ABB September 9, 2015

Slide 1. ABB September 9, 2015 Tarak Mehta, Head of Low Voltage Products, ABB Ltd., Capital Markets Day, Next Level Stage 2 New Electrification Products division: Power & Automation for the site Slide 1 Important notices Presentations

More information

Report on Major Achievements, Significant Developments and Important events for The Month of May-2018

Report on Major Achievements, Significant Developments and Important events for The Month of May-2018 Report on Major Achievements, Significant Developments and Important events for The Month of May-2018 Following are the details of major achievements, significant developments and important events in the

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Installation Instructions

Installation Instructions GEMINI SELECT 38APS025-065, 38APD025-130 Air-Cooled Condensing Units with PURON Refrigerant (R-410A) 50/60 Hz Installation Instructions CONTENTS Page SAFETY CONSIDERATIONS...................... 1 INSTALLATION................................

More information

Facilities. Presented by Jim Irby for the C-Mod Group

Facilities. Presented by Jim Irby for the C-Mod Group Facilities Presented by Jim Irby for the C-Mod Group Outline Machine History and Status 2008 run campaign Machine inspection Alternator and Flywheel Inspections Availability Chart Contributions to ITER

More information

P R O D U C T S PRODUCTS OUR PRODUCT LINE RANGES FROM:

P R O D U C T S PRODUCTS OUR PRODUCT LINE RANGES FROM: Capabilities P R O D U C T S PRODUCTS American Crane is recognized as a leader in the design and manufacture of electric overhead traveling cranes and wire rope hoists, offering equipment up to 1,000 ton

More information

INTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT

INTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT INTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT X.R. Wang 1, S. Malang 2, L.A. El-Guebaly 3, A. R. Raffray 1 and the ARIES Team 1 University of California, San

More information

Portable. Storage and Transport Dewars. CL/CLPB Series, CH Series, CFN/CFL Series

Portable. Storage and Transport Dewars. CL/CLPB Series, CH Series, CFN/CFL Series Portable Storage and Transport Dewars CL/CLPB Series, CH Series, CFN/CFL Series CL/CLPB Series Cryofab s CL series portable liquid cylinders are intended for low-pressure transport and storage of liquid

More information

Development of Two-stage Electric Turbocharging system for Automobiles

Development of Two-stage Electric Turbocharging system for Automobiles Development of Two-stage Electric Turbocharging system for Automobiles 71 BYEONGIL AN *1 NAOMICHI SHIBATA *2 HIROSHI SUZUKI *3 MOTOKI EBISU *1 Engine downsizing using supercharging is progressing to cope

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER A19 ADMINISTRATIVE REPORT Report Date: July 10, 2007 Author: Chris Darwent Phone No.: 604.873.7358 RTS No.: 6866 VanRIMS No.: 13-1400-20 Meeting Date: July 24, 2007 TO: FROM: SUBJECT:

More information

Appendix E3. Open Pit Pioneering and Pre-production

Appendix E3. Open Pit Pioneering and Pre-production Appendix E3 Open Pit Pioneering and Pre-production File Note From: George Dermer To: File Date: January 11, 2012 Re: KSM Mitchell Pit Mine Pre-Production and Start-up plan Summary: Pre-Production mining

More information

M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA

M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA LBNL-48445 SCMAG-749 SUPERCONDUCTING MAGNETS FOR INDUCTION LINAC PHASE-ROTATION IN A NEUTRINO FACTORY M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA ABSTRACT The neutrino

More information

B kv T&D GAS INSULATED SWITCHGEAR

B kv T&D GAS INSULATED SWITCHGEAR GAS INSULATED SWITCHGEAR B 105 170 300 kv The increasing demand for electrical power in cities and industrial centers necessitates the installation of a compact and efficient distribution and transmission

More information

Ball Valves. ASME Class 150 to mm mm (¼" - 8") ISO 17292/ API 6D

Ball Valves. ASME Class 150 to mm mm (¼ - 8) ISO 17292/ API 6D Ball Valves SM Class 150 to 2500 8 mm - 200 mm (¼" - 8") ISO 17292/ PI 6D L&T Valves Limited is a wholly owned subsidiary of Larsen & Toubro. Backed by a fifty-year track-record of excellence and world-leading

More information

UPDATE ON THE LHC MAIN MAGNETS. Lucio Rossi CERN - LHC MAC 15

UPDATE ON THE LHC MAIN MAGNETS. Lucio Rossi CERN - LHC MAC 15 UPDATE ON THE LHC MAIN MAGNETS Lucio Rossi CERN - LHC MAC 15 Content Cable Components Production of dipoles and learing curves Fiedl quality Collared cois CM production Results and Delivery Plan for dipoles

More information

Summary of HRS sampling and analysis in HyCoRA. HyCoRA OEM workshop Trondheim, Thor Anders Aarhaug, SINTEF Materials and Chemistry

Summary of HRS sampling and analysis in HyCoRA. HyCoRA OEM workshop Trondheim, Thor Anders Aarhaug, SINTEF Materials and Chemistry Summary of HRS sampling and analysis in HyCoRA HyCoRA OEM workshop Trondheim, 2017-06-07 Thor Anders Aarhaug, SINTEF Materials and Chemistry SINTEF sampling background SINTEF subcontracted Smart Chemistry

More information

PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4

PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4 PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4 1 2 3 4 5 6 7 8 9 Q. Please describe Hydro s terminal station and substation inspections policies and practices. In

More information

COMPANY PROFILE 0045

COMPANY PROFILE 0045 0045 COMPANY PROFILE INTRODUCTION TO THE COMPANY THE MICROFINISH WAY Microfinish Valves Pvt. Ltd. is a privately owned and managed company specializing in industrial valves for energy, process, and natural

More information

Test units for all types of: Shut-off Valves Safety (relief) Valves Control Valves

Test units for all types of: Shut-off Valves Safety (relief) Valves Control Valves Test units for all types of: Shut-off Valves Safety (relief) Valves Control Valves CALL 1800 023 859 TO SPEAK WITH ONE OF OUR TECHNICIANS Innovative Onsite Engineered Solutions 2 Ventil manufacturers test

More information

LARGE MOTOR SOLUTIONS

LARGE MOTOR SOLUTIONS LARGE MOTOR SOLUTIONS Delivering an integrated system based on a qualified architecture for high servo press productivity Customers seeking high throughput for next generation machines often experience

More information

Old Ref No. New Ref. No. Major Changes

Old Ref No. New Ref. No. Major Changes MAJOR CHANGES IN THE GENERAL SPECIFICATION FOR AIR-CONDITIONING, REFRIGERATION, VENTILATION AND CENTRAL MONITORING & CONTROL SYSTEM INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE

More information

Welded Valve Configurations

Welded Valve Configurations Welded Configurations Welded valve configurations are designed to improve the process in aseptic production facilities by reducing the dead legs in accordance to cgmp. Welded valve configurations may be

More information

LIQUID MEASUREMENT STATION DESIGN Class No

LIQUID MEASUREMENT STATION DESIGN Class No LIQUID MEASUREMENT STATION DESIGN Class No. 2230.1 Michael Frey Systems Sales Manager Daniel Measurement & Control, Inc. 5650 Brittmoore Rd. Houston, Texas 77041 INTRODUCTION The industry continues to

More information