1 National Power Rodding Corp FM 969 Austin, TX Austin Constructors, LLC S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price LF Remove Concrete Curb $5.00 $ $1.00 $ $ SY Remove Sidewalks and Driveways $9.00 $1, $6.00 $ $ SY Flexible Base (Complete in place) $50.00 $2, $40.00 $2, $ GAL Tack Coat $36.00 $1, $10.00 $ $30.00 Hot Mix Asphalt Concrete Type "D" Two SY (2) Inch Thickness $40.00 $20, $ $60, $ CY Salvage, Haul, Stockpile Asphalt Concrete Pavement $41.00 $1, $10.00 $ $ LF Concrete Curbing $13.00 $1, $30.00 $3, $ LF Concrete Gutter $22.00 $ $30.00 $ $ SY Concrete Sidewalks $45.00 $2, $60.00 $3, $ SY Concrete Driveways $74.00 $5, $70.00 $5, $ SY Commercial Driveways $82.00 $4, $ $5, $ LF Relocate Fence $22.00 $4, $30.00 $6, $ SY SY Cutting and replacing pavements (10" ATB & 3" HMAC) $75.00 $3, $ $11, $90.00 Cutting and replacing pavements (6" ATB & 2" HMAC) $64.00 $3, $ $8, $80.00 Page 1 of12
2 National Power Rodding Corp FM 969 Austin, TX Austin Constructors, LLC S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price CY Topsoil $28.00 $ $20.00 $ $ SY Bermuda Sodding $14.00 $ $20.00 $1, $ SY St. Augustine Sodding $14.00 $ $20.00 $1, $ EA Barricades, Signs and Traffic Handling $1, $50, $ $35, $ LF Temporary Sediment Control Fence $4.00 $1, $3.00 $ $ LF Trench Excavation Safety Protection $4.00 $2, $3.00 $1, $ EA Traffic Control Plan $1, $2, $1, $2, $2, HR Police Officer $40.00 $4, $50.00 $5, $ EA Adjust Manholes $ $15, $1, $70, $ EA Replace Manhole Ring and Cover $ $3, $1, $6, $ VF Manhole Coating $ $42, $ $45, $ LF Sanitary Sewer laterals $25.00 $11, $60.00 $27, $ EA One Way Sanitary Sewer Clean-Out $ $20, $ $12, $ EA Bypass Pumping (8" diameter) $2, $20, $ $4, $1, EA Bypass Pumping (10" diameter) $2, $10, $ $3, $1, EA Bypass Pumping (12" diameter) $2, $5, $ $1, $1, EA Bypass Pumping (15" diameter) $3, $6, $1, $2, $2, Page 2 of12
3 National Power Rodding Corp FM 969 Austin, TX Austin Constructors, LLC S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price EA Bypass Pumping (18" diameter) $3, $6, $2, $4, $2, EA Bypass Pumping (21" diameter) $3, $6, $2, $5, $2, EA Bypass Pumping (24" diameter) $3, $6, $4, $8, $2, EA EA EA EA EA Open Cut Point Repairs for 8" or 10" Pipe Sizes, (0'-10' depth) $2, $37, $3, $45, $4, Open Cut Point Repairs for 8" or 10" Pipe Sizes, (10'-16' depth) $2, $14, $5, $25, $4, Open Cut Point Repairs for 8" or 10" Pipe Sizes, (>16' depth) $3, $7, $7, $14, $5, Open Cut Point Repairs for 12" or 15" Pipe Sizes, (0'-10' depth) $3, $6, $4, $8, $4, Open Cut Point Repairs for 12" or 15" Pipe Sizes, (10'-16' depth) $3, $6, $6, $12, $5, Page 3 of12
4 National Power Rodding Corp FM 969 Austin, TX Austin Constructors, LLC S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price EA EA EA EA EA EA EA , LF LF Open Cut Point Repairs for 12" or 15" Pipe Sizes, (>16' depth) $4, $4, $10, $10, $5, Open Cut Point Repairs for 18" or 21" Pipe Sizes, (0'-10' depth) $3, $7, $6, $12, $5, Open Cut Point Repairs for 18" or 21" Pipe Sizes, (10'-16' depth) $4, $9, $8, $16, $5, Open Cut Point Repairs for 18" or 21" Pipe Sizes, (>16' depth) $5, $5, $11, $11, $6, Open Cut Point Repairs for 24" Pipe Size, (0'-10' depth) $3, $7, $8, $16, $4, Open Cut Point Repairs for 24" Pipe Size, (10'-16' depth) $4, $4, $9, $9, $4, Open Cut Point Repairs for 24" Pipe Size, (>16' depth) $6, $6, $12, $12, $4, Extra length point repair, 8" -10" pipe diameter, all depths $82.00 $205, $51.00 $127, $90.00 Extra Length Point Repair, 12" -18" pipe diameter, all depths $ $83, $90.00 $68, $ Page 4 of12
5 National Power Rodding Corp FM 969 Austin, TX Austin Constructors, LLC S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price LF EA Extra length point Repair, 21" - 24" pipe diameter, all depths $ $3, $ $2, $ Open Cut Lateral Reconnection, all sizes, all depths $ $7, $1, $8, $ EA Protruding Tap Removal $ $2, $ $1, $2, EA EA EA EA EA EA CIPP Point Repair for 8" Pipe Size, all depths $5, $5, $2, $2, $4, CIPP Point Repair for 10" Pipe Size, all depths $5, $5, $2, $2, $4, CIPP Point Repair for 12" Pipe Size, all depths $6, $6, $2, $2, $7, CIPP Point Repair for 15" Pipe Size, all depths $6, $6, $2, $2, $7, CIPP Point Repair for 18" Pipe Size, all depths $6, $6, $2, $2, $8, CIPP Point Repair for 21" Pipe Size, all depths $7, $7, $2, $2, $9, Page 5 of12
6 National Power Rodding Corp FM 969 Austin, TX Austin Constructors, LLC S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price EA CIPP Point Repair for 24" Pipe Size, all depths $8, $8, $3, $3, $10, EA Remote Service Reconnection, Internal Cut $ $1, $ $1, $1, CY Flowable Backfill (TxDOT Spec) $ $7, $ $7, $ Total Bid $737, $767, CALENDAR DAYS TO COMPLETE Page 6 of12
7 7907 S. FM 973 Austin, TX Item No. Estimate Qty Unit of Issue Description Unit Price Total LF Remove Concrete Curb $5.00 $ SY Remove Sidewalks and Driveways $9.00 $1, SY Flexible Base (Complete in place) $50.00 $2, GAL Tack Coat $36.00 $1, Hot Mix Asphalt Concrete Type "D" Two SY (2) Inch Thickness $40.00 $20, Total $ $1, $3, $1, $29, CY Salvage, Haul, Stockpile Asphalt Concrete Pavement $41.00 $1, $ LF Concrete Curbing $13.00 $1, LF Concrete Gutter $22.00 $ SY Concrete Sidewalks $45.00 $2, SY Concrete Driveways $74.00 $5, SY Commercial Driveways $82.00 $4, LF Relocate Fence $22.00 $4, $1, $ $1, $4, $3, $4, SY SY Cutting and replacing pavements (10" ATB & 3" HMAC) $75.00 $3, Cutting and replacing pavements (6" ATB & 2" HMAC) $64.00 $3, Page 7 of12 $4, $4,000.00
8 7907 S. FM 973 Austin, TX Item No. Estimate Qty Unit of Issue Description Unit Price Total CY Topsoil $28.00 $ SY Bermuda Sodding $14.00 $ SY St. Augustine Sodding $14.00 $ EA Barricades, Signs and Traffic Handling $1, $50, LF Temporary Sediment Control Fence $4.00 $1, LF Trench Excavation Safety Protection $4.00 $2, EA Traffic Control Plan $1, $2, HR Police Officer $40.00 $4, EA Adjust Manholes $ $15, EA Replace Manhole Ring and Cover $ $3, VF Manhole Coating $ $42, LF Sanitary Sewer laterals $25.00 $11, EA One Way Sanitary Sewer Clean-Out $ $20, EA Bypass Pumping (8" diameter) $2, $20, EA Bypass Pumping (10" diameter) $2, $10, EA Bypass Pumping (12" diameter) $2, $5, EA Bypass Pumping (15" diameter) $3, $6, Page 8 of12 Total $ $ $ $15, $1, $4, $5, $4, $30, $4, $37, $13, $11, $10, $6, $3, $4,000.00
9 7907 S. FM 973 Austin, TX Item No. Estimate Qty Unit of Issue Description Unit Price Total Total EA Bypass Pumping (18" diameter) $3, $6, EA Bypass Pumping (21" diameter) $3, $6, EA Bypass Pumping (24" diameter) $3, $6, $5, $5, $5, EA EA EA EA EA Open Cut Point Repairs for 8" or 10" Pipe Sizes, (0'-10' depth) $2, $37, Open Cut Point Repairs for 8" or 10" Pipe Sizes, (10'-16' depth) $2, $14, Open Cut Point Repairs for 8" or 10" Pipe Sizes, (>16' depth) $3, $7, Open Cut Point Repairs for 12" or 15" Pipe Sizes, (0'-10' depth) $3, $6, Open Cut Point Repairs for 12" or 15" Pipe Sizes, (10'-16' depth) $3, $6, $61, $22, $10, $9, $10, Page 9 of12
10 7907 S. FM 973 Austin, TX Item No. Estimate Qty Unit of Issue Description Unit Price Total Total EA EA EA EA EA EA EA , LF LF Open Cut Point Repairs for 12" or 15" Pipe Sizes, (>16' depth) $4, $4, Open Cut Point Repairs for 18" or 21" Pipe Sizes, (0'-10' depth) $3, $7, Open Cut Point Repairs for 18" or 21" Pipe Sizes, (10'-16' depth) $4, $9, Open Cut Point Repairs for 18" or 21" Pipe Sizes, (>16' depth) $5, $5, Open Cut Point Repairs for 24" Pipe Size, (0'-10' depth) $3, $7, Open Cut Point Repairs for 24" Pipe Size, (10'-16' depth) $4, $4, Open Cut Point Repairs for 24" Pipe Size, (>16' depth) $6, $6, Extra length point repair, 8" -10" pipe diameter, all depths $82.00 $205, Extra Length Point Repair, 12" -18" pipe diameter, all depths $ $83, Page 10 of12 $5, $10, $11, $6, $9, $4, $4, $225, $87,400.00
11 7907 S. FM 973 Austin, TX Item No. Estimate Qty Unit of Issue Description Unit Price Total Total LF EA Extra length point Repair, 21" - 24" pipe diameter, all depths $ $3, Open Cut Lateral Reconnection, all sizes, all depths $ $7, $2, $7, EA Protruding Tap Removal $ $2, $10, EA EA EA EA EA EA CIPP Point Repair for 8" Pipe Size, all depths $5, $5, CIPP Point Repair for 10" Pipe Size, all depths $5, $5, CIPP Point Repair for 12" Pipe Size, all depths $6, $6, CIPP Point Repair for 15" Pipe Size, all depths $6, $6, CIPP Point Repair for 18" Pipe Size, all depths $6, $6, CIPP Point Repair for 21" Pipe Size, all depths $7, $7, $4, $4, $7, $7, $8, $9, Page 11 of12
12 7907 S. FM 973 Austin, TX Item No. Estimate Qty Unit of Issue Description Unit Price Total Total EA CIPP Point Repair for 24" Pipe Size, all depths $8, $8, $10, EA Remote Service Reconnection, Internal Cut $ $1, $8, CY Flowable Backfill (TxDOT Spec) $ $7, $6, Total Bid $737, $787, CALENDAR DAYS TO COMPLETE Page 12 of12
CITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS
CITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS CITY OF SAN ANTONIO DEPT. OF CAPITAL IMPROVEMENTS MANAGEMENT SERVICES N. NEW BRAUNFELS AVE. SIDEWALK PROJECT FROM RITTIMAN
More informationDELETE first sentence of first paragraph that reads: REPLACE with the following:
To Bidder of Record: SAN ANTONIO WATER SYSTEM Addendum 2 To Construction Documents For 2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB NO. 12-5001 SAWS SEWER JOB NO. 12-5501 Solicitation
More informationHILLS MATERIALS COMPANY UNIT COST TOTAL COST UNIT COST TOTAL COST UNIT COST $294, $294, $74, $74, $35, $35,000.
PROJECT NAME: Anamosa Street Reconstruction - Midway Street to Miiwuakee Street PROJECT NUMBER: PROJECT NO. 07-1473 / CIP NO. 50559 LET DATE: April 11, 2017 LOW BID AMOUNT: $3,941,397.20 ENGINEER'S ESTIMATE
More informationSUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71
BASE BID 1.00 GENERAL CONDITIONS 1.01 Mobilization (Maximum 5% of Base Bid) LS 1 84,000.00 $ 84,000.00 100,000.00 $ 100,000.00 85,000.00 $ 85,000.00 1.02 Bonding, Insurance, Permits (including Plumbing,
More informationProject Book Worksheet for Cost Estimation
001.01 MOBILIZATION LS $34,716.18 007 3/17/2039 001.02 INCIDENTAL LS $23,929.43 019 3/17/2039 001.03 CONSTRUCTION STAKING LS $10,504.39 201 5/9/2013 001.04 REESTABLISH PROPERTY CORNERS EA $496.08 201 5/9/2013
More informationDESCRIPTION QUANTITY PRICE TOTAL
GENERAL 1 TRAFFIC CONTROL LS 1 $40,000 $40,000 $8,500.00 $8,500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $15,000.00 $15,000.00 2 MOBILIZATION LS 1 $557,000 $557,000 $629,500.00 $629,500.00 $350,000.00
More informationSteese Rd - Curb & Sidewalk Improvement
REF. NO. ITEM NO. Steese Rd - Curb & Sidewalk Improvement DESCRIPTION QTY UNITS UNIT COST SUB-TOTAL 1 103.05 Requirement of Contract Bid 1 LS 24,048.00 24,048.00 2 201 Clearing and Grubbing 1 LS 11,077.00
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Engineering Division PROJECT NO INCA STREET MULTI-USE PATH 38 TH AVE. TO 43 RD AVE.
201-00000 Clearing and Grubbing 1 LS 202-00010 Removal of Tree 9 EA 202-00019 Removal of Inlet 8 EA 202-00034 Removal of Pipe (6 Inch) 196 LF 202-00035 Removal of Pipe (18 Inch) 10 LF 202-00036 Removal
More informationFertilizer Type B 2 CWT $ $ $60.00 $ $60.00 $ Sod Water 60 MGAL $60.60 $3, $30.00 $1, $30.00 $1,
BID TABS PROJECT 18-1029 22 nd AVENUE RECONSTRUCTION BID DATE: MAY 9, 2018 Stark Pavement Corp. Lalonde Contractors Cornerstone Pavers LLC Brookfield, WI Waukesha, WI Racine, WI Item Number Roadway Quantity
More informationBID TABULATION REPORT McKINNEY STREET DRAINAGE IMPROVEMENTS PROJECT No. PWDR10012 BID OPENED : TUESDAY, AUGUST 13, :00 P.M.
PAVING IMPROVEMENTS McKINNEY 101 Rightofway Preparation LS 1 75,000.00 75,000.00 200,000.00 200,000.00 67,000.00 67,000.00 110,000.00 110,000.00 102 12inch HMAC Street Pulvermix SY 11,650 3.00 34,950.00
More informationSAN ANTONIO WATER SYSTEM
SAN ANTONIO WATER SYSTEM SAWS WATER JOB NO. 17-5026 2017 SMP MERRY ANN DR. FROM FRANCES JEAN TO DEAD END G:\TXC\Projects\SAWS\SAWS - Merry Ann\03_CADD\01_Sheets\Merry Ann_Water\01_Sheets\1 MANN WATR CVR.dwg
More informationPatton Hill Road (Four Inch Main), Project No
Patton Hill Road (Four Inch Main), Project No. 2016100 MP-5.01 MOBILIZATION (3% MAX) 1 LS MP-5.02.8(d) 8" DIP (CLASS 350) ALL DEPTHS 600 LF MP-5.02.6(p) 6" PVC ALL DEPTHS, INCLUDING BEDDING 10 LF MP-5.02.4(p)
More informationRiverside County Transportation Department Summary of Bids
Company Name Dartmouth St. Base Bid Sch. Yale St. Base Bid Sch. Alternate Bid Sch. Alternate Bid Sch. Alternate Bid Sch. Alternate Bid Sch. 4 Total COUNTY'S ESTIMATE,87,.50,444,6.00 9,400.00 9,400.00 800.00,00.00
More informationMcCRORY & WILLIAMS, INC. HILLCREST ROAD CONNECTOR MCR ROADWAY ITEMS
BID TABULATION Hillcrest Road Connector John G. Walton Construction M. C. Williams Contracting Hosea. Weaver & Sons, Inc. BID OPENING: March 25, 29 Company, Inc. Company, Inc. QTY DESCRIPTION DOLLARSjCTS
More informationTHORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E
THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E Each bidder shall bid each item of the Base Bid Schedule and Alternate A Bid Schedule. Failure to bid an item shall be just cause
More informationRiverside County Transportation Department Summary of Bids
1 COUNTY'S ESTIMATE R-JS General Construction Riverside, CA 92509 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID UNIT PRICE BID ESTIMATE 1 066102 DUST ABATEMENT LS 1 3,000.00
More informationFederal Project No.: OC-095-1(348)
Order : N83 Schedule of Items Page: 2 Oversight/State Project : (NFO)0095-127-857, C501 Federal Project : OC-095-1(348) 0010 513 00100 MOBILIZATION LUMP SUM LUMP SUM 0020 517 00101 CONSTRUCTION SURVEYING
More information2150 F&I 4" PVC pipe LF 100 $ F&I 6" PVC pipe LF 100 $ F&I 8" PVC pipe LF 100 $ 90.00
1 of 5 2100 F&I 4" ductile iron pipe LF 200 $ 143.00 $28,600.00 2102 F&I 6" ductile iron pipe LF 200 $ 135.00 $27,000.00 2104 F&I 8" ductile iron pipe LF 200 $ 141.00 $28,200.00 2105 F&I 10" ductile iron
More informationBID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ -
BID FORM PART A Name & Category Unit Unit Cost (B) Cost (AxB) GENERAL REQUIREMENTS 1 Mobilization (Maximum 3.0% of the total Contract Price) 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b
More informationTown of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166
Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Date: August 10, 2016 Subject: Bid for Construction of NW 89 th Avenue, NW 93 rd Street and NW
More informationBIDDER'S PROPOSAL (continued) CITY OF BERKELEY BID PROPOSAL ITEM NO. A: BASE BID
SPECIFICATION 16-11031-C CITY OF BERKELEY BID PROPOSAL A: BASE BID 1 MOBILIZATION 1 LS 2 TRAFFIC CONTROL 1 LS 3 CONTRACTOR INFORMATION SIGN 2 EA 4 CONSTRUCTION AREA SIGN 18 EA 5 PROJECT IDENTIFICATION
More informationDate: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications:
DEVELOPMENT SERVICES PHONE: (209) 668-5520 ENGINEERING DIVISION FAX: (209) 668-5563 156 S. BROADWAY, SUITE 150 TDD: (800) 735-2929 TURLOCK, CA 95380 engineering@turlock.ca.us Date: 04/20/2018 City Project
More informationMaine Turnpike Authority
Company Name Total Bid Amount CPM Constructors - Freeport, ME $1,309,765.25 Scott Construction Corporation - Portland, ME $1,528,840.00 Wyman & Simpson Inc. - Richmond, ME $1,674,845.00 Page 1 of 10 CPM
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity
202-00019 Removal of Inlet 15 EA 202-00035 Removal of Pipe 121 LF 202-00200 Removal of Sidewalk 1,057 SY 202-00203 Removal of Curb and Gutter 2,142 LF 202-00206 Removal of Concrete Curb Ramp 320 SY 202-00207
More informationFederal Project No.: STP-5128(388)
Order : M48 Schedule of Items Page: 2 Oversight/State Project : (NFO) 0460-129-105, C501 Federal Project : STP-5128(388) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION)
More informationCity of Grand Island Tuesday, June 26, 2018 Council Session
City of Grand Island Tuesday, June 26, 2018 Council Session Item G-21 #2018-188 - Approving Change Order No. 3 for Sanitary Sewer Collection System Rehabilitation Various Locations; Project No. 2017-S-2A
More informationCounty of Los Angeles Department of Public Works BID SUMMARY
PROJECT NAME CENTRAL AVENUE, ET AL. PROJECT ID RDC0013675 Engineer's Estimate (1) All American Asphalt (2) Sequel Contractors, Inc. (3) Sully-Miller Contracting Company (4) Palp, Inc. 5,177,177.00 5,292,979.00
More informationADDENDUM #2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18
November 29, 2018 ADDENDUM 2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18 Q1. Do contractors not need to be on the Watershed Improvements Pre-Qualifications List to submit on the RP031-18 Watershed
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity
202-00001 Removal of Structure 24 EA 202-00019 Removal of Inlet 24 EA 202-00195 Removal of Median cover 930 SY 202-00200 Removal of Sidewalk 1,188 SY 202-00201 Removal of Curb Head 273 LF 202-00203 Removal
More informationGrays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14
Grays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14 Hardesty & Hanover, LLC Alternative 1 Bogie Support System Alternative Based on AW Sketch of New Bridge Component
More informationBID PROPOSAL. Item Description Unit Quantity Unit Price Total Price No. (Unit Price to be written in Words) (Figures) (Figures)
BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions and Invitations to Bidders, the undersigned proposes
More informationCity of Grand Island Tuesday, February 13, 2018 Council Session
City of Grand Island Tuesday, February 13, 2018 Council Session Item G-7 #2018-34 - Approving Certificate of Final Completion for the Construction of North Interceptor Phase I; Project No. 2012-S-6 Staff
More informationBid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013
Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D4-1102 November 21, 2013 Doughtie Construction Co., Elliott Construction Dudley Construction Ltd. SUBTOTAL GENERAL ITEMS : $191,713.00
More informationADDENDUM NO. 1. Contractor shall fax back the recognition sheet acknowledging the receipt of this addendum, or include in their proposal.
ADDENDUM NO. 1 DATE: August 7, 2014 PROJECT: FROM: TO: 2014 MFT Section 14-00000-00-GM, SUPP1 United City of Yorkville Kendall County, IL Engineering Enterprises, Inc. 52 Wheeler Road Sugar Grove, Illinois
More informationBID TABULATION PAGE 1 OF 4. BL S.R. Harbins Road/Alcovy Road - Intersection Improvements Department of Transporation. CMES, Inc.
BID TABULATION PAGE 1 OF 4 E.R. Snell Contractor, Inc. G.P.'s Enterprises, Inc. Est. 1 005 Traffic Control Project No M-0679 1 LS $27,811.00 $27,811.00 $48,800.00 $48,800.00 $22,021.80 $22,021.80 2 010
More informationADDENDUM No. 1 Prospective Bidders
Page 1 of 1 Attachment to Addendum # 1 Revised Itemized Bid ADDENDUM No. 1 TO: Prospective Bidders FROM: Gregory Tate, Construction Contracts Administrator DATE: January 24, 2019 PROJECT: Traffic Signal
More informationSPECIAL GRADING INTERSECTION IMPROVEMENT JOHN WARD RD AT IRWIN RD REVISION DATES
9/20/2017 2:39:11 PM GPLOT-V8 2016104_18-001.dgn Project Number Sheet Total Sheets djackson gplotborder-v8i-po.tbl X2802 30 118 966.5 21+00 L.P. EL. 966.34 L.P. EL. 966.58 0.29% 0.11% 965 H.P. EL. 966.54
More informationSTREET IMPROVEMENTS PROPOSAL BID ITEMS
STREET IMPROVEMENTS 1 Excavation 3,525 CY $ $ 2 A.C. Planing (2" to 4" Depth) 20,586 SY $ $ 3 Furnish & Install Asphalt Concrete 4,270 TON $ $ 4 Furnish & Install Aggregate Base 2,955 TON $ $ 5 Remove
More informationLicensed Class C Virginia Contractor No.
month period is seven hundred and fifty thousand dollars (750,000) or more, the Bidder is required under Title 54.11100, Code of Virginia (1950), as amended, to be licensed by the State Board of Contractors
More informationMaine Turnpike Authority
Company Name Total Bid Amount R J Grondin & Sons - Gorham, ME $1,436,720.00 Shaw Brothers Construction, Inc. - Gorham, ME $1,476,398.83 Pratt & Sons, Inc. - Minot, ME $1,733,615.00 Page 1 of 13 R J Grondin
More information365, , , A Total of Schedule I and II 530, , A 702, A
BID ABSTRACT COUNTY OF VENTURA - PUBLIC WORKS AGENCY Page 1 of 3 Bids opened on April 2, 2019 ENGINEER'S ESTIMATE LOW BIDDER 2nd Bidder Project Name Piru Stormwater Capture For Groundwater Recharge Project
More informationMcCRORY & WILIJAMS, INC. PROJECT NO. MCR-2008-OO1
McCRORY & WILIJAMS, INC. THEODORE DAWES ROADISCHILLINGER ROAD SOUTH BID TABULATION: Theodore DaweslSchillingor Road PROJECT NO.: M5700-2033 BIDDER #1 BIDDER #2 BIDDER #3 Hosea 0. Weaver & Sons, Inc. John
More informationMaine Turnpike Authority
Company Name Total Bid Amount Shaw Brothers Construction, Inc. - Gorham, ME $659,771.50 R J Grondin & Sons - Gorham, ME $690,828.50 Gendron & Gendron - Lewiston, ME $753,187.00 Gordon Contracting - Sangerville,
More informationBID ITEM ESTIMATED UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. QUANTITY UNIT ITEM COST COST COST COST COST COST
PAGE 1 BID OPENING: AUGUST 11, 2011 ENGINEER'S ESTIMATE: $3,108,320.60 CONTRACT NO.110269 SABINO CANYON AND TANQUE VERDE INTERSECTION IMPROVEMENTS *FOR A MORE DETAILED ITEM DESCRIPTION* *REFER TO PROPOSAL
More information(1 ) Active Construction Inc River Road East Tacoma, WA AMOUNT , , ,
78th Avenue Eastl184th Street EastlCRP 5661 I hereby certify this to be a true copy of the tabulation of the bids as received and opened. BID OPENING: FRIDAY, March 3, 2017 County Engine (1 ) Active Construction
More informationMoDOT 2016 UNIT BID PRICES Northwest District
MoDOT 2016 UNIT BID PRICES Northwest District 2013000 CLEARING AND GRUBBING ACRE 7.95 20 1926.49132 20000 1 159 2022010 REMOVAL OF IMPROVEMENTS L.S. 1.00 56 24479.13304 201719 750 56 2024043 REMOVAL OF
More information2, total unit $ total unit $ total unit $ total $
BD TABULATON Bid No. : 697 North Bay Trail-1st Street North Project No. 0901-212 Engineering &Capital mprovements Department, City of 1. Petersburg, Florida Bid date: February 26,2010 ",,>,',-, t~..4":;
More informationCITY OF ESTHERVILLE, IOWA MISCELLANEOUS FEES & CHARGES. At Sewer Main.. $
CITY OF ESTHERVILLE, IOWA MISCELLANEOUS FEES & CHARGES Revised 4-6-09 UTILITY FEES Sanitary Sewer Taps: At Manhole... $ 400.00... At Sewer Main.. $ 500.00... All excavation, labor and materials by property
More informationCONTRACTOR'S REQUEST FOR PAYMENT CHASKA VETERANS PARK IMPROVEMENTS STANTEC PROJECT NO
Owner: City of Chaska, 1 City Hall Plz., Chaska, mn 55318 Date: December 12, 2017 For Period: 12/1/2017 to 1/31/2018 Request No: 1 Contractor: Blackstone Contractors, LLC, 9520 County Rd. 19, Ste. D, Loretto,
More informationMaine Turnpike Authority
Company Name Total Bid Amount Liddell Brothers, Inc. - Halifax, MA $1,590,213.00 Northeast Traffic Control Services, Inc. - Plymouth, MA $1,932,117.00 Page 1 of 5 Liddell Brothers, Inc. Halifax, MA 202.2061
More informationMETRO Magnolia Transit Center - Bid Tab
Section A - GENERAL ITEMS A-1 01505 Mobilization LS 1 $ 100,000.00 $ 100,000.00 A-2 -- Payment and Performance Bonds LS 1 A-3 01310 Document Control LS 1 A-4 01311 CPM Schedule LS 1 A-5 01590 Engineer's
More informationProject # & Name: # CDBG - Pugh Street Streetscape - East College Ave to East Beaver Ave & East Beaver Ave/Locust Lane Improvements
Bid Opening Date: May 6, 2014 Time: 11:00 a.m. Surety NCA Surety NCA Yes Yes Yes Yes Total Amount Bid: $1,358,851.00 Total Amount Bid: $1,386,098.72 Item Nos. Approx. Quantities Unit Item & Unit Prices
More informationOaks Commerce Center
Mansour Edlin Consulting 1515 Mockingbird Lane Charlotte, NC 28209 Oaks Commerce Center Water & Sanitary Sewer Improvements Phase I - Concept Utility Plan Gravity Sanitary Sewer A1 Connect to Existing
More informationUnits Est. Qty. Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price
1 1500001 Mobilization, Max. $25,000.00 LSUM 1.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 4,400.00 4,400.00 2 2020040 Tree, Rem, 6 inch to 18 inch Ea 2.00 600.00
More informationS T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 05/01/00 PAGE : 1 TABULATION OF BIDS
PAGE : 1 CONTRACT DESCRIPTION : MILL & OVERLAY, GRADING, BIT SURFACING, BR NO 02038 ETC CONTRACT LOCATION: LOCATED ON TH 47 FROM 153RD AVE NW IN RAMSEY TO 180TH LANE NW AND AT FORD BROOK IN BURNS TOWNSHIP
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS
San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS 834.1 DESCRIPTION: This item shall consist of fire hydrant installations using joint restraints in accordance
More informationCounty of Los Angeles Department of Public Works BID SUMMARY
PROJECT NAME 3RD STREET - INDIANA STREET TO RECORD AVENUE PROJECT ID RDC0015034 Engineer's Estimate (1) Sully-Miller Contracting Company (2) TORO ENTERPRISES, INC. (3) Sequel Contractors, Inc. (4) All
More informationFederal Project No.: HSIP-5A27(567)
Order : A11 Schedule of Items Page: 2 Oversight/State Project : (NFO)0001-020-S82,C501 Federal Project : HSIP-5A27(567) 0010 513 00100 0020 517 00101 MOBILIZATION LUMP SUM LUMP SUM CONSTRUCTION SURVEYING
More informationBID TALLY AND ATTENDANCE SHEET BID #B BID TITLE: Replacement of Bridge No. LR over the Larimer and Weld Canal
VENDOR BID TALLY AND ATTENDANCE SHEET BID #B15-21 BID TITLE: Replacement of Bridge LR50-0.2-17 over the Larimer and Weld Canal Addendum #1 Acknowled ged DATE: October 22, 2015 TIME: 2:00 p.m. DEPARTMENT:
More informationCT Consultants, Inc.
Cost 1 202 AHRESTY DRIVE REMOVAL 1 LS 2 202 EXISTING SILO DEMOLISHED AND REMOVED, AS PER PLAN 1 LS 3 203 EXCAVATION (NOT INCLUDING UNDERCUT) 2,372 CY 4 203 EMBANKMENT 3,306 CY 5 204 PROOF ROLLING 10 HRS
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS
San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS 834.1 DESCRIPTION: This item shall consist of fire hydrant installations using joint restraints in accordance
More informationARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS
ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2016153 TRACS No. Project No. County District Gross
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/09/19 HIGHWAY: 02/10/2016 ESTIMATE PAID: AWARD DATE: 02/25/2016 ESTIMATE PERIOD:
47,635.79 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/09/19 161 3 CONTRACT ID: 092106270 PROJECT: STP 2014(101)TE CONTRACT: 02163244 AWARD : $899,908.10 PROJECTED : $905,908.10 ADJ. PROJECTED : $953,543.89
More informationCITY OF DAVIS PUBLIC WORKS DEPARTMENT STANDARD SPECIFICATIONS
CITY OF DAVIS PUBLIC WORKS DEPARTMENT STANDARD SPECIFICATIONS JANUARY 1996 EDITION ADDENDA THROUGH JULY 2017 DIANNA JENSEN City Engineer 1717 Fifth Street Davis, CA 95616 530-757-5686 2017 Edition STANDARD
More information2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH
Page 1 2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH ITEM ITEM DESCRIPTION UNITS N TOTAL QUANTITY AVERAGE PRICE 106.05100 FIELD LABORATORY
More informationALABAMA DEPARTMENT OF TRANSPORTATION DATE : 06/14/13 PAGE : VENDOR RANKING
PAGE : 001-1 VENDOR RANKING CONTRACT TIME : 09/01/13 COMPLETION DATE CONTRACT DESCRIPTION : PROJECT(S) : IM-I059(370) for constructing the Ramp Widening and Auxiliary Lane (Grade, Drain, Base, Pave and
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 05/10/13 HIGHWAY: FM 3301 COUNTY: 09/09/2011 ESTIMATE PAID: AWARD DATE: 09/29/2011 ESTIMATE PERIOD:
CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 05/10/13 75 CONTRACT ID: 349701008 PROJECT: STP 2012(033)HES CONTRACT: 09113205 AWARD : $1,297,485.60 PROJECTED : $1,307,485.60 ADJ. PROJECTED : $1,307,485.60
More informationWHITE OAK RIDGE PROJECT NO. 53B2384 D-1 DETAIL STANDARD NOTES AND TYPICAL SECTION CITY OF MADISON
WHITE OAK RIDGE D-1 DETAIL STANDARD NOTES AND TYPICAL SECTION ORIGINATOR:, STREETS DIVISION REV. DATE: PLOT NAME: PLOT SCALE: THE LOCATION AND INFORMATION FOR PROPOSED NEW TREES, IN THE PUBLIC RIGHT OF
More informationAPPENDIX H COST ESTIMATES
APPENDIX H COST ESTIMATES H-1 HDR ENGINEERING, INC. TBPE FIRM NO. F-754 COST ESTIMATING TEMPLATE PRELIMINARY NOT TO BE USED FOR PERMITTING, BIDDING, OR CONSTRUCTION PREPARED BY: PHILIP A. FULTON, PE PE
More informationFranklin County Engineer's Office - Highway Design ALKIRE RD & DEMOREST RD ROUNDABOUT CR NO. 11 & CR NO. 25 Bid Tabulation
7/07/2015 Page 1 of 20 Strawser Paving Co., Inc. Shelly & Sands, Inc. Double Z Construction Co Columbus Asphalt Paving, Inc. 1595 Frank Road P.O.Box 2469 2550 Harrison Road 1196 Technology Dr Columbus,
More information2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH
Page 1 2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH ITEM ITEM DESCRIPTION UNITS N TOTAL QUANTITY AVERAGE PRICE 106.05100 FIELD LABORATORY
More informationDOCUMENTATION WORKBOOK FY 2017
DOCUMENTATION WORKBOOK SPECIFIC TASK TRAINING PROGRAM Conducted by the ILLINOIS CENTER FOR TRANSPORTATION (ICT) AND IDOT BUREAU OF CONSTRUCTION FY 2017 WORKBOOK TABLE OF CONTENTS Workbook Page 1... Maximum
More informationOhio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director
Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Project No. 080598 PID 21272 CUY-SR-237-4.93 - PART I (FRONT STREET); CUY-237-4.55 - P Federal Type: RAILROAD
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 110146 PID 82278 HAM-IR-75-5.58 Federal Type: INTERCHANGE Letting Date: 5/5/2011 Completion Date: 7/31/2014 Contract
More informationS T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/26/00 PAGE : 1 TABULATION OF BIDS
PAGE : 1 CONTRACT DESCRIPTION : LEFT & RIGHT TURN LANES AND FLASHING BEACON SYSTEM CONTRACT LOCATION: LOCATED ON TH 7 FROM 327 M WEST OF JCT TH 25 TO 445 M EAST OF JCT TH 25 RECOMMENDATION: AWARD TO LOW
More informationMaine Turnpike Authority
Interchange 44 Barrier Toll Plaza Open Road Tolling Conversion Mile 44.3 201.11 CLEARING 3.50 AC 202.071 REMOVING ASBESTOS CONTAINING MATERIALS, TOLL BOOTH LAB TOPS 1.00 LS 202.081 REMOVING EXISTING BUILDING
More informationCITY OF BURLINGTON SHARON AVENUE SANITARY SEWER IMPROVEMENTS - PHASE 1 - REBID CITY OFFICIALS. STEVE SEXTON Mayor JAMES STAVIG.
SKAGIT COUNTY WASHINGTON CITY OFFICIALS STEVE SEXTON Mayor TED MONTGOMERY JAMES STAVIG City Council RICK DEGLORIA JOE DEGLORIA CHRIS LOVING BILL ASLETT EDIE EDMUNDSON City Council DON ERICKSON SEWER DEPARTMENT
More informationADDENDUM NO. 3 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT GWINNETT COUNTY DEPARTMENT OF WATER RESOURCES RP031-18
DECEMBER 6, 2018 ADDENDUM 3 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT GWINNETT COUNTY DEPARTMENT OF WATER RESOURCES RP031-18 ADDITIONAL INFORMATION DOCUMENTS The following document: Questions and Responses
More informationCONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 07/11/18 HIGHWAY: FM 3151 COUNTY: 12/02/2015 ESTIMATE PAID: AWARD DATE: 12/17/2015 ESTIMATE PERIOD:
CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 07/11/18 131 CONTRACT ID: 187503022 PROJECT: C 1875-3-22 CONTRACT: 12153043 AWARD : $3,146,993.47 PROJECTED : $3,149,993.47 ADJ. PROJECTED : $3,149,993.47 CONTRACT:
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 140123 PID 82645 LOR- SR 0057 19.42 Federal Type: INTERCHANGE Letting Date: 4/17/2014 Completion Date: 7/15/2016
More informationADDENDUM 3 - JULY 24, 2015
FORM G PRICE PROPOSAL CAMINO REAL REGIONAL MOBILITY AUTHORITY ("CRRMA") The undersigned having familiarized themselves with the local conditions affecting the cost of work and with the Request for Proposals
More informationDOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/10 AND 12/31/10 BY ITEM GROUP 211 CONTRACTS - AWARDED TOTAL: $649,895,273
AVERAGE BID PRICES FOR AWARDED PROJECTS 06:54 Friday, February 18, 2011 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 9 $276 $30,713.33 9 2011.601/00010 VIBRATION MONITORING LS 2 $73 $36,700.00 2 2011
More informationOhio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director
Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director Project No. 100281 PID 77255 LUC-IR-475-14.18 Federal Type: MAJOR RECONSTRUCTION Letting Date: 6/3/2010 Completion
More informationBARRETT ROAD (C.R. 178) ROADWAY RESURFACING FROM LEWIS ROAD TO SPAFFORD ROAD IN OLMSTED TOWNSHIP, OHIO ITEMIZED UNIT PRICE BID ROADWAY
IZED PRICE BID DESCRIPTION PRICE BID ROADWAY 1 201 11000 CLEARING AND GRUBBING 1 - - LUMP 2 202 23000 PAVEMENT REMOVED NR SQ YD 20 3 202 35100 PIPE REMOVED, 24" AND UNDER NR FT 134 4 202 58000 MANHOLE
More informationBid Tabulation City of Coralville RE-BID Coral Ridge Ave, Phase II - Oakdale Blvd to Forevergreen Rd City of Coralville, IA Engineer's OPC
, IA - 2017 DIVISION 1 - GENERAL 1.01 TRAFFIC CONTROL LS 1 $50,000.00 $50,000.00 $30,000.00 $30,000.00 $24,500.00 $24,500.00 $24,500.00 $24,500.00 $24,500.00 $24,500.00 DIVISION 2 - EARTHWORK 2.01 CLEARING
More informationMaine Turnpike Authority
Company Name Total Bid Amount Sargent Corporation - Stillwater, ME $29,888,765.79 Reed & Reed, Inc. - Woolwich, ME $34,900,974.90 Page 1 of 25 Sargent Corporation Stillwater, ME 201.11 CLEARING AC 4.00
More informationFederal Project No.: STP-5A27(380), STP-5A27(381)
Order : M42 Schedule of Items Page: 2 Oversight/State Project : (NFO)0649-020-136,C502, C503 Federal Project : STP-5A27(380), STP-5A27(381) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING
More information$6, CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 03/08/17 -30, PROJECT: STP 2013(839) GRAYSON
-30,219.83 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 03/08/17 291 CONTRACT ID: 051002028 PROJECT: STP 2013(839) CONTRACT: 07133220 AWARD : $4,317,753.44 PROJECTED : $4,394,254.44 ADJ. PROJECTED : $4,364,034.61
More informationSTATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/15/17 Comp. Dt: 08/04/17. Contract Time: Min: Max:
Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 1401-171 Contract ID: Contract Description: Contract Location: Recommendation: 170002 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationWentzville Parkway South Phase 2 & 2A
Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total
More informationCIS 26.txt MIS.CIS.26 MATL VERIF & MISSING SOURCES CONTRACT MGR.NO. 055 PAGE 001
MIS.CIS.26 MATL VERIF & MISSING SOURCES CONTRACT 323216 MGR.NO. 55 PAGE 1 CONT 1 SEC 13 JOB 76 RES ENGR ICENHOWER, KENNETH PROJ MG 22(313) HWY US 67 BOX 538 TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE
More information2017 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR ENGLISH (10)
106.05100 FIELD LABORATORY EA 33 33.00 $12,605.17 201.03201 CLEARING AND GRUBBING ACRE 2 76.00 $1,269.74 201.03206 CLEARING TREES 6 in EA 1 53.00 $122.27 201.03210 CLEARING TREES 10 in EA 3 66.00 $227.33
More informationCounty of Santa Cruz 0579
County of Santa Cruz 0579 701 OCEAN STREET, ROOM 410, SANTA CRUZ, CA 95060-4070 (831) 454-2160 FAX (831) 454-2385 TOO (831) 454-2123 DIRECTOR OF PUBLIC WORKS SANTA CRUZ COUNTY BOARD OF SUPERVISORS 701
More informationOhio Department of Transportation Official Bid Tabulation Jerry Wray, Director
Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 170559 PID 102381 SCI-US 52-19.01 Federal Type: TWO LANE RESURFACING Letting Date: 11/2/2017 Completion Date:
More informationSt. Johns River State College BID-SJR Addendum Three ADDENDUM THREE DATED JUNE 13, 2016
St. Johns River State College BID-SJR-10-2016 Addendum Three ADDENDUM THREE DATED JUNE 13, 2016 TO BID-SJR-10-2016 Bid Specifications/Project Manual (Plans) PARKING LOT REHABILITATION PROJECT FOR: DRAWING
More informationCity of West Branch. Office of the City Administrator
City of West Branch Office of the City Administrator To: City Council and Mayor From: Matt Muckler, City Administrator Date: October 15, 2016 Weekly Council Update South Downey Construction Schedule: Rathje
More informationENGINEERING & ENVIRONMENTAL
1-800-292-8989 www.iowaonecall.com CITY OF WEST BRANCH, IOWA THIS ENGINEERING DOCUMENT HAS BEEN REVIEWED BY THE JURISDICTION AND IS RECOMMENDED FOR FILING WITH THE CITY CLERK ENGINEERING & ENVIRONMENTAL
More informationSTANDARD DRAWING INDEX
ATTACHMENT B STANDARD DRAWING INDEX DESCRIPTION EXISTING DRAWING NO. GENERAL Typical Layout for Improvement Plans City of Stockton Standard Border and Title Block for 8 1/2 x11 Sheet City of Stockton Standard
More informationDOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/04 AND 12/31/04 BY ITEM GROUP 201 CONTRACTS - AWARDED TOTAL: $340,971,276
AVERAGE BID PRICES FOR AWARDED PROJECTS 14:37 Wednesday, February 2, 2005 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 17 $920 $54,140.65 17 2011.601/00040 DESIGN LS 1 $4 $3,500.00 1 2011 $924 2013
More informationAMENDMENT OF SOLICITATION Old Hueco Tanks Rd. Improvements
AMENDMENT OF SOLICITATION Old Hueco Tanks Rd. Improvements The above titled solicitation is amended. All amendments must be acknowledged on the PROPOSAL ; failure to do so may be cause for rejection of
More information