Electric Streetcar Alignment Options for Martin Luther King Jr. Way

Size: px
Start display at page:

Download "Electric Streetcar Alignment Options for Martin Luther King Jr. Way"

Transcription

1 Electric Streetcar Alignment Options for Martin Luther King Jr. Way Prepared for 2201 Portland Ave. Tacoma, Washington Prepared by Parametrix 2102 N Pearl Street, Suite 106 Tacoma, WA T F December

2 CITATION Parametrix Electric Streetcar Alignment Options for Martin Luther King Jr. Way. Prepared by Parametrix, Tacoma, Washington. December 2009.

3 CERTIFICATION The technical material and data contained in this document were prepared under the supervision and direction of the undersigned, whose seal, as a professional engineer licensed to practice as such, is affixed below. Prepared by Stephen W. Dorau, P.E. Checked by James K. Bunch, P.E. Approved by James K. Bunch, P.E. December

4

5 TABLE OF CONTENTS 1. INTRODUCTION UNDERSTANDING SCOPE OF WORK TASK 1 & 2 ALIGNMENT ALTERNATIVES & ANALYSIS CONCEPTUAL ALIGNMENT OPTIONS AND STREET SECTIONS HEADWAY ANALYSIS CONCEPTUAL ALIGNMENT OPTIONS MLK / J Street Loop Option Headway Analysis MLK / J Street Loop Option Figures MLK Double-Track Pinched-Loop Option Headway Analysis MLK Double-Track Pinched Loop Option Figures MLK Bypass Option Headway Analysis MLK Bypass Option Figures Alignment Comparison TASK 3 MAINTENANCE FACILITY TASK 4 OPINION OF PROBABLE COST REFERENCED SYSTEM COSTS MLK SYSTEM PROBABLE COSTS DEVELOPMENT WITH LOCAL IMPROVEMENT DISTRICT December i

6

7 1. INTRODUCTION The following section describes the intent of the work product that was completed in preparation of this report and the scope of work for which Parametrix was responsible. 1.1 UNDERSTANDING The City of Tacoma (City) is preparing a conceptual design of street and utility improvements for Martin Luther King Jr. Way (MLK) between Division Street and S. 25 th Street to support the creation of a Local Improvement District (LID). The City is considering the option of adding streetcar service to MLK in the future, potentially between Division Street and S. 19 th Street. The development of an electric streetcar system has the possibility of many conflicts with existing utility systems. In addition, the streetcar system may conflict with existing and proposed traffic and pedestrian flow. The City enlisted the services of Parametrix to provide assistance in the conceptual design of the streetcar line serving this MLK neighborhood. The conceptual design will be used by the City during the design process for the street and utility improvements and utility relocations incorporating the future location of the streetcar line. 1.2 SCOPE OF WORK This section describes the scope of work that Parametrix was responsible for on this project. The scope of work includes the following tasks. The results of Tasks 1 through 5 are included in this report. Task 6 will be completed following the submittal of this report. Task 1 Develop Potential Track Alignment Alternatives for MLK Parametrix conceived viable route alternatives for the streetcar alignment for the defined MLK corridor. Three alternatives were developed. The resulting alternatives, technical constraints, and probable advantages/disadvantages can be seen in Section 2. Task 2 Develop Potential Street Cross Section Diagrams Parametrix prepared street cross section diagrams to show the arrangement of streetcar tracks, vehicle traffic lanes, bike lanes, utility corridors, pedestrian sidewalks, and passenger stations. The sections for each alignment option defined in Task 1 can be seen in Section 2. Task 3 Vehicle Maintenance Facility Parametrix has proposed a maintenance facility location and developed a sketch plan for the facility. The results of this study can be seen in Section 3. Task 4 Preliminary Cost Opinion Parametrix prepared an Opinion of Probable Cost for the defined proposed streetcar system alternatives. See Section 4 for these results. Task 5 Memorandum Report Parametrix prepared this memorandum report, to discuss the results of Tasks 1 through 4. Task 6 - Presentations Parametrix will provide support to the City at two meetings, one with the Public Works Director and the City Manager, and one for a City Council study session. These meetings will follow the submission of this memorandum. December

8

9 2. TASK 1 & 2 ALIGNMENT ALTERNATIVES & ANALYSIS Tasks 1 and 2 included the conceptual layout of the streetcar for several alignment options. As part of the conceptual layout, alignments were drawn onto the City s MLK Way street modification plans, sections were prepared for typical alignment areas and a headway analysis was performed to estimate the performance criteria associated with each option. 2.1 CONCEPTUAL ALIGNMENT OPTIONS AND STREET SECTIONS Parametrix has reviewed the preliminary plan for the proposed LID and understands that the plan is in development. The preliminary street arrangements provided by the Department of Public Works were used as a base-line guide for this work. These tasks considered three alignment options with various service options including: Loop System Streetcar travels in a clockwise loop on MLK Way, S. 6 th Street, J Street, and S. 20 th Street. The streetcar vehicles would generally be in the automobile traffic lanes. Clockwise circulation has been selected in order to prevent the streetcars from crossing car traffic at corner intersections, as would happen if the circulation was counterclockwise. The minimum inside radius recommended by the United Streetcar Company is 18 meters, resulting in a minimum centerline radius of 61.5 feet. This radius will allow the streetcar to turn the corners from the traffic lanes with a slight reduction in the curb corner sidewalk area. If the streetcar travels counterclockwise around the outside of the loop, larger curve radii are available. In this configuration, the streetcar crosses car traffic at every corner of the loop. To provide a safe interaction with the cars, it is typical to use signalized intersections and preemptive signal control from the streetcar. For this review, S 6 th Street was selected at the first crossing street south of the Tacoma General Hospital area. It may be possible to use S 5 th Street as well but for this review, it was determined to not interfere with the hospital area. This intersection is about 1300 from the intersection at Division if a connection is to be made in the future. The arrangement of that connection and future operation will have to be considered for the final alignment. J Street is generally considered to be the best choice for the return run of the loop by City staff at this time. At the south end of the alignment, S 20 th has been used as the crossing street for this study. With the major traffic activity on S. 19 th Street, it was determined best to avoid that conflict. If all conflict with S. 19 th is to be avoided, the streetcar could cross on S. 18 th Street. This option will place the turning motion of the streetcar directly in front of St. Joseph Hospital. The final alignment and station locations will need to be determined through more detailed public review process. Double-Track Pinched-Loop System The streetcars would travel on dual parallel tracks along MLK Way. The streetcars would generally be in the vehicle travel lanes with street traffic. The streetcars would travel in a counterclockwise loop on the double-tracks along MLK Way between S. 4th Street and S. 19th Street. At each end, the streetcar would reverse directions and cross over to the other side of the street. This system could be extended to Division St. and ultimately be connected with the proposed streetcar extension on Division St with a relatively short extension. December

10 Single Track with Bypass System Streetcar travels on a single lane track system on MLK Way between S. 4th Street and S. 19th Street. Because of bi-directional travel, the streetcar track must be isolated from the vehicle lanes. In order to allow streetcars to travel in both directions, the track is split into a double track by-pass near the center. The two tracks diverge to allow for vehicles traveling in opposite directions to pass between S. 11 th Street and Earnest S. Brazill. This system could be extended to Division St. and ultimately be connected with the proposed streetcar extension on Division St, also with a relatively short extension. Detailed drawings of the above alignment options can be seen in Figures A-1, B-1 and C-1 respectively in the Appendixes. The City of Tacoma has developed Complete Streets Design Guidelines for future planning and development of the urban area. The objective of the Complete Streets program is to provide a livable space in mixed-use centers for pedestrians, bicycles, transit, and not just automobiles. Each of the proposed streetcar arrangements have different interactions with vehicle traffic, pedestrians, and passengers that must be carefully considered. Some assumptions have been made for this report. Some tradeoffs will need to be made between the desired components of wide sidewalks, bike lanes, transit lanes, passenger stations, commercial access, and personal automobile convenience. These issues will need to be considered prior to final design. The selection of a Preferred Alternative would typically include stakeholder and general public involvement sessions. The advantages and disadvantages of the above three alignment options are discussed in Section 2.3.4, but, the selection of a Preferred Alternative must wait until future phases of the project. The following key factors were considered in development of the options: Station Locations The utility and performance of the system is closely related to the location of passenger stations. Each of the options above assumed passenger station platforms every two blocks, but station location is typically the subject of alternatives review and selection. Stakeholder and public involvement will likely be a key factor in the selection of the actual station locations. For this study, we will assume that stations are positioned at intervals of about 2 blocks. Station Platforms Generally, the station platforms were assumed to consist of a concrete platform offering a reduced step height for passengers entering the streetcar. The step-down distance would be probably be a few inches. This height will be determined by the wheel chair access system for the streetcar. The Skoda/Oregon Iron Works vehicle that is similar to the existing Tacoma Link cars uses a mechanical bridge plate that can accommodate some differential level. Level changes and ramps must be considered in planning for station locations and arrangements. This issue is one that needs careful consideration prior to entering final design. The stations in this study are generally shown on the driver s-right side and just prior to the stop bar at an intersection. The platforms would be simple in nature and be minimalistic in their offerings. It was assumed that the platforms would potentially be covered and would contain basic amenities such as benches and information boards, but would primarily service standing passengers waiting for the streetcar and disembarking passengers. Ramps of minimal length would allow for transition between the platform 2-2 December

11 surface and the adjacent sidewalk surface. All transitions were considered in conjunction with the recommendations and requirements of ADA. Bike Lanes It is understood that bicycle lanes will be an integral part of the LID design concept in each direction of MLK Way and on adjacent streets. The presence of bike lanes challenges the layout of tracked vehicle systems due to the potential safety concerns over bicycles crossing the gap next to the tracks at any angle other than perpendicular. The gap is the flangeway for the streetcar wheel and approximately 2 in width and depth. The narrow wheels of bicycles can be trapped in this gap and potentially cause falls. In each of the above options the bike lanes were placed to the outside of all traffic lanes and the streetcar alignment. At station locations the bike lanes were redirected behind the station platforms as to avoid track crossings at station deviations. The bike lanes parallel the sidewalks and cause a potential conflict as patrons attempting to move from the sidewalk to the platform or visa versa must cross the bike lane. Proper signage and pavement design is critical for safety for both the pedestrians and bicycle riders. Utility Corridor As part of a streetcar installation, the track would be installed in close proximity existing or proposed utilities and often crossing utilities. These potential conflicts make planning for a streetcar alignment challenging. The utility infrastructure along the MLK corridor is planned to be renovated in the LID process. Existing sanitary sewer is planned to occupy the alleyway as existing. The electric and telecom utilities are currently on overhead poles generally along the alleyways. Redevelopment of the electric utility is planned to use east-west crossing streets to bring the primary lines to near the alleyways. Underground vaults will provide distribution to smaller underground distribution conduits along the alleys. This will not cause any linear conflict with the proposed streetcar installation or operations. Provisions will need to be made for the streetcar crossing of the utility corridors at cross streets. Typical track slab designs can span over utility ducts without any significant issues. Vertical separation will need to be provided. Typical electrical underground installations are several feet deep. The track slab will probably not exceed 18 of structure and 24 of excavation, so the interaction with a modern electric utility installation should not be significant. Cost is often a controlling issue in development plans. It will almost certainly be less expensive to maintain the utility feeder lines on overhead poles at strategic cross streets. The streetcar overhead contact wire will be about 18 feet above the rail. High voltage utility distribution can cross above the contact wire as necessary. The general rule of overhead wires is the lowest voltage at the lowest position on the pole, and progressing up to the highest voltage at the top. For this reason, telephone and Cable TV are the lowest wires, then local power feeders, then distribution lines, and major power lines on the top. Where the streetcar contact wire passes, the telecommunications utilities will need to be routed underground. The utility lines need to be high enough to not contact any part of the streetcar contact system, which is about 25 feet. As shown in this study, the streetcar could operate in a loop system on MLK Way, S. 6th Street, J Street, and S. 20th Street. The electric utility currently has a major corridor along S. 6th Street on overhead poles on the south side of the street. The redevelopment effort may December

12 call for placing this major feeder underground. In order to minimize future interaction with the power feeder, the City should consider locating the power feeder on the northern side of S. 6th Street in this area if the underground approach is selected. The power may remain overhead if it is high enough on the pole. The telecommunication utilities are currently sharing the overhead poles with the electric power in the alley ways. Typically, the telecom providers would join the electric power in a joint trench during a major construction project. Because the sewer is in the alley, there may or may not be adequate room for power and telecom along with the sewer easement. It is recommended that a corridor for telecom be established in the street along MLK Way, and along J Street if a loop option is desired. The Tacoma general utility plan calls for the telecom and power to be located in the planting strip along the sidewalk. The conduit plan will be required on both sides of the street for street lighting and for telecom to reach all of the users. The biggest challenge for coordinated corridors will be where there is a double-track system and a station stop, or the bypass area of the single-track system. At these locations the placement of telecom vaults or hand holes may be constrained. At these areas, the sidewalk width is shown at 8 to 10. This probably will not allow for a planting strip and open walking area. Natural gas is also designated in the planting strip by the City utility plan. If the telecom and gas utilities can share the sidewalk / planting strip on both sides, there should be little conflict with the streetcar installation. Photograph 1 OCS System at Corner The streetcar will require overhead installation of the power wire, referred to as overhead contact system (OCS). The OCS can generally be supported by street light poles. The supports are required at intervals of less than 100. Because the forces at corners are larger, 2-4 December

13 the poles are generally bigger and the support wires are more visible. (See Photograph 1.) In some situations, the OCS has been supported by nearby buildings. (See Photograph 2.) This is very common in Europe, but less common in the U.S.A. Due to the necessity of the OCS, which operates at 600 volts DC, all telecom crossing the tracks must be placed underground. Where the streetcar track is generally along one side of the street, as in the loop system or the single track by-pass arrangement, the opposite side of the street is generally available for utilities. The water utility will need to be under a traffic lane on the opposite side of the street. In order to allow for the clockwise loop system on MLK Way and J Street, it is recommended that the water line be located on the westerly side of MLK Way and the easterly side of J Street. If a single track bypass system is selected, the route would naturally be on the easterly side of MLK Way in a generally clear area. It is more challenging to locate the water utility in the case of the double-track system. The water utility will need to be located far enough to one side to avoid the traffic lanes where the streetcar is expected to operate. The water line will probably be partially under the sidewalk / planting strip in many areas. Photograph 2 OCS Supported by Building An additional conflict may exist with the storm drain. The City utility plan shows the storm drain at a single location near one curb line. It is anticipated that the storm drain will need to run in straight lines, generally from intersection to intersection. Curb inlets at the intersections will need to drain to manholes near the intersections. The drain routes will need to cross under the streetcar track slab. Depending on the track arrangement, track drains from the track will need to connect into the storm drain system as well. Future connections to the drain system may need additional manholes. In the single track bypass and loop systems, it is anticipated that the water line and storm drain can be located in the vehicle and bike lane that December

14 does not have tracks. With the double-track system, there is a limited amount for space for storm drain and water supply. Track Bed As part of Task 2, Parametrix also developed street cross sections based on the street arrangements and dimensions shown in the preliminary LID drawings by the City. The primary purpose of the street sections was to identify and plan for a utility corridor(s) that would minimize interference with the proposed streetcar system, and allow for function installation and maintenance. The location and placement of utilities was based on the information gathered from the City for types and locations of utility services. Since the system technology and design details have not been determined, the track bed shown on the street sections is a representative section and not designed for the specific project or location. Site specific geotechnical data and system details will be required in future phases to design a track bed. There are several potential options for the track bed which should be considered in future phases. There are different types of rail that can be used. The rail is used as the negative return for the electric power. When the DC current flows in the ground it can cause corrosion of steel pipes and other metal systems in the ground. To prevent corrosion, the track needs to be insulated from the earth. The insulation system can be provided by different methods. With the streetcar running in the traffic lanes, the street surface must be flush with the top of the tracks. The support structure for the tracks can be done in different ways. There are different choices for the rail system that the streetcar runs on. The most common is the traditional T rail that supports most of the railroads in the U.S.A. and the world. (See Photograph 3.) In this case, the flangeway for the wheels on the car must be formed in the road surface or a flanged boot must be used. (See Photograph 4.) 2-6 December

15 Photograph 3-115RE Rail Flangeway Photograph 4 - Trak Slab with Concrete Flangeway Many streetcar systems use girder rail where the rail is embedded in the street. The slot for the wheel flange of the rail car is formed in the rail head and no additional flange way needs to be formed when placing the street surface. (See Photograph 5.) The size of the two rail December

16 systems is about the same. There is a rubber insulating boot available for both rail sections. Girder rail is very convenient for street-running systems with a continuous steel flangeway and guidance for the wheels in curves. It is preferred for this application by many designers. It is not rolled by any rail suppliers in the U.S.A. and must come from off-shore suppliers. For any project that must comply with the provisions of the Buy America Act, it is not available. Photograph 5 - Girder Rail In order to provide insulation from the ground, a rubber boot is typically used to separate the steel rail from the structure. (See Photograph 6.) The boot is an extruded rubber wrapper that matches the track section shape. It is wrapped around the rail and then the concrete is placed to hold the entire assembly. The boot can also provide the flangeway form if desired as shown in Photograph 7. The rubber is flexible and can be damaged during the installation by the heavy rail and equipment used to handle it. It must be tested with a high voltage tester before placing the concrete and it must be tested again after placement for ground leaks. 2-8 December

17 Rubber Boot Photograph 6 - Track Slab Construction w/ Rubber Boot An alternative method of insulation is nonconductive fill material. There are different types. Photograph 8 shows an epoxy stabilized granular rubber material referred to as FX. Another manufacturer makes an epoxy cement grout. These are generally considered to be more expensive because the material is more expensive than redi-mix concrete and the installation requires multiple processes. The pavement must be formed with a block-out prior to placing the rail and then the insulating material is placed to fill the block-out. This type of process is often used for smaller areas around special trackwork or for repairs. December

18 Photograph 7 Boot-Formed Flangeway Photograph 8 - FX Rail Insulation 2-10 December

19 The track section can be installed using typical rail on cross-ties and then the pavement placed as brick or asphalt concrete up to the edge of the rail as seen in Photograph 9 and Photograph 10. When streetcar systems and paved streets were first placed together, this method was common. Because asphalt concrete tends to deform in warm weather and with moisture, this method often leads to very rough transitions between the street and rails. It is likely less expensive to install cross-ties and pave over to the edge of the rail, particularly if girder rail is used. Where the traffic is lightweight and slow-moving, this may be an acceptable method. However, the pavement will probably need repair at some point in the future and removal and replacement of the old pavement will probably damage the insulating boot and cause current leakage. Note that in the referenced photographs, no rubber boot is in place. An engineering review of the costs may be advisable to review this option. Photograph 9 Brick Paved Trackbed December

20 Photograph 10 Asphalt Paved Trackbed The most common installation method today is a structural concrete track slab placed continuously along the track. The rail path is excavated to a depth of about 18 inches. The streetcar is about 8 wide, consequently the slab is typically about the same width as the car to clearly mark the lane. The rail and boot are supported by cross-ties at about 10 spacing. Reinforcing steel is placed around the rail and the slab is filled with concrete. After the rail section is installed, the roadway is finished to the edge of the concrete slab. The slab can be finished in any style to match to location. Where the street is consistent and regular slope, the concrete can be placed to the edge of the existing pavement. Typically the asphalt needs to be resurfaced for a clean finished look. The depth of the track slab excavation is typically required to be in order to provide some prepared subbase for the track slab. The subbase will be determined from geotechnical investigation and design engineering. The track structure is about 7 tall. The cross-tie structure is about another 7 tall and is completely sacrificial. It does not contribute to the track strength. The depth of the concrete slab is about depending on the design. It is a very permanent structure but because of the strength, it can bridge over almost any of the utility structures that must pass under. It will be possible to bore future utilities as necessary December

21 Photograph 11 - Construction of Concrete Track Slab w/ Rubber Flangeway December

22 Photograph 12 - Construction of Concrete Track Slab w/ Cast in Place Flangeway Photograph 13 Concrete Track Slab 2-14 December

23 Photograph 14 Track Slab w/ Rubber Flangeway and Stamped Concrete Surface Photograph 15 Installed Girder Rail December

24 2.2 HEADWAY ANALYSIS Parametrix conducted a headway analysis of the alignment options to determine an estimate of the time required for a streetcar to travel the length of each alignment. From this data an estimate of headway was computed for each scenario based on an assumed number of vehicles. The headway analysis considered vehicle acceleration and deceleration, stopping and waiting times, and the average number of disruptions per cycle due to traffic signals and stop signs. A summary of the analysis results can be seen in Sections , and An approximate operation schedule would be based on a vehicle starting the alignment from a specific hold point at the top of the hour and subsequent vehicles would leave the hold point at even intervals so that a consistent headway is achieved. For this analysis it was assumed that the streetcars would have preemptive access to the signalized intersections such that the vehicles could pull away from the station platforms located prior to signalized intersections such that uninhibited access to traffic merging could be achieved. It was not assumed that the signalized intersections would be timed to allow for unimpeded travel along MLK Way or J Street. This could be implemented, but at possible impact to other signalized intersection systems. One future consideration of the possible timed signals is the potential increase in cross traffic should the MLK Way corridor be developed. The headway analysis utilized the following parameters for computation: Analysis Parameter Calculation Value Maximum Speed (tangent) 25 mph Maximum Speed (curve) 8 mph Acceleration Rate 1.0 mph/s (0.05 g) Deceleration Rate 1.0 mph/s (0.05 g) Station Dwell Time 15 sec Avg. Signal Stop Time 35 sec Avg. Stop Time at Intersection 15 sec Time to Merge w/ Traffic 10 sec 2.3 CONCEPTUAL ALIGNMENT OPTIONS Parametrix chose three alignment options to study further. The three options include a loop system traveling in a clockwise loop on MLK Way, S. 6 th Street, J Street, and S. 20 th Street (MLK/ J Street Loop); a double-track pinched-loop system traveling in a counterclockwise loop on MLK Way between S. 4 th Street and S. 19 th Street (MLK Double-Track Pinched- Loop); and a bypass system traveling in a single isolated track on MLK Way between S. 4 th Street and S. 19 th Street (MLK Bypass). The following sections describe the three alignment options studied: 2-16 December

25 2.3.1 MLK / J Street Loop Option The loop option consists of the Streetcars traveling along a single track in street traffic in a clockwise loop on MLK Way, S. 6th Street, J Street, and S. 20th Street. A conceptual layout of this alignment option can be seen in Appendix A. This loop option generally consists of the following layout: Typical Mid-Block Section Typical Signalized Intersection (at platform) Typical Non-Signalized Intersection (at platform) Design Minimums Vehicle Lanes 2x12 2x11 2x12 10 Turn Lane N/A 10 N/A 10 Bike Lanes 2x5 2x5 2x5 5 Parking Lanes 2x7 N/A N/A 7 Streetcar Lane (in traffic) Streetcar Platform N/A Sidewalks 16 (west) 16 (east) 11 (west) 8 (east) 19 (west) 8 (east) Total Right-of-Way See Figures A-3 and A-4 in Appendix A for diagrams of the alignments and the corresponding sections. This option had a number of parameters that were influential in the preparation of the conceptual alignment. These issues were as follows: Travel Direction In this option, clockwise travel was selected over counterclockwise travel as to avoid the necessity of crossing traffic at the corners. By traveling on the inside of the loop, the streetcar will have less stop-time throughout the loop and a shorter travel distance. The disadvantage of this option is the ability of the United (Skoda) streetcar to navigate tight turn radii which is exacerbated by traveling on the inside of the loop. The vehicle has a minimum functional centerline travel radius of 61.5 feet. The clockwise loop option will require the design of the four corners of the loop to accommodate the streetcar. A diagram of the streetcar turn radius can be seen in Figure A-2 in Appendix A. Travel with Traffic The streetcar will travel with traffic at all times with the exception of station pull-outs and accessing the maintenance facility which would utilize maintenance personnel as flaggers as required. Since the streetcar will travel in the same direction as the street traffic on its side of the street, the placement of parking lanes and in-traffic streetcar operation are made possible, decreasing the total right-of-way required for the streetcar system. Additional pedestrian space will be available if the streetcar stops in the traffic lane. This will slow traffic operations further. December

26 Platform Position The conceptual alignment of the loop option places all station platforms on the driver s-right side. This arrangement provides for consistent operations and driver observations. Platform arrangement will need to be compliant with ADA requirements. The platforms will need to provide the attractive pedestrian spaces and transit access targeted by Complete Streets. Station Locations The proposed alignment is based on the assumption that the station platforms are located approximately every other block along MLK Way and J Street. This is to assign a pattern for operations timing. No specific station stops are being recommended Headway Analysis The headway analysis completed for the loop option resulted in the following data: Analysis Parameter Result Maximum Speed Achieved 25 mph (constrained) Average Speed w/o Stops 9 mph Average Speed w Stops 5 mph *Total Number of Stops 36 Travel Distance 2.2 mi (11,600 ft) Travel Time: Time in Motion Time Stopped Total Time 14 min 11 min 25 min Trips per Hour per Vehicle Assumed Number of Vehicles (typical operating schedule) Headway min *Includes stops at signalized intersections, non-signalized intersections and at station platforms MLK / J Street Loop Option Figures See the MLK / J Street Loop Option figures in Appendix A: - Figure A-1 Overall Alignment - Figure A-2 Corner Alignment - Figure A-3 Signalized Intersection Plan - Figure A-4 Non- Signalized Intersection Plan 2-18 December

27 2.3.2 MLK Double-Track Pinched-Loop Option The double-track pinched-loop option consists of the Streetcar traveling in a counterclockwise loop on MLK Way between S. 4 th Street and S. 19 th Street. This system could be extended to Division St. and ultimately be connected with the proposed streetcar extension on Division St. relatively easily. A conceptual layout of this alignment option can be seen in Appendix B. This double-track pinched-loop option generally consists of the following layout: Typical Mid-Block Section Typical Signalized Intersection (at platform) Typical Non-Signalized Intersection (at platform) Design Minimums Vehicle Lanes 2x12 2x12 2x12 10 Turn Lane N/A N/A N/A 10 Bike Lanes 2x5 2x5 2x5 5 Parking Lanes 2x7 N/A N/A 7 Streetcar Lane (in traffic) Streetcar Platform N/A Sidewalks 13 (west) 19 (east) 19 (west) 8 (east) 19 (west) 8 (east) Total Right-of-Way See Figures B-2, B-3 and B-4 in Appendix B for diagrams of the alignments and the corresponding sections. This option had a number of parameters that were influential in the preparation of the conceptual alignment. These issues were as follows: Travel with Traffic The streetcar will travel with traffic at all times with the exception of station pull-outs and accessing the maintenance facility which would utilize maintenance personnel as flaggers as required. Since the streetcar will travel in the same direction as the street traffic on its side of the street, the placement of parking lanes and in-traffic streetcar operation are made possible, decreasing the total right-of-way required for the streetcar system. Platform Position Due to the nature of a double-track pinched-loop system, the station platforms will always be placed on the driver s-right side. Given that the streetcar reverses direction at the ends of the alignment, the platforms will actually be on one side of the vehicle for one direction of travel and on the opposite side of the vehicle for the other direction of travel. Platform arrangement will need to be compliant with ADA requirements. The double track option will make wide sidewalk spaces desired by Complete Streets difficult, unless the streetcar stops directly in traffic lanes. December

28 Station Locations The proposed alignment is based on the assumption that the station platforms are located approximately every other block along MLK Way. To maximize the width of the traffic lanes and sidewalks, it was assumed that the stations would alternate intersections such that the width of the elements could be maximized Headway Analysis The headway analysis completed for the double-track pinched-loop option resulted in the following data: Analysis Parameter Result Maximum Speed Achieved 25 mph (constrained) Average Speed w/o Stops 9 mph Average Speed w/ Stops 5 mph *Total Number of Stops 31 Travel Distance 1.8 mi (9,400 ft) Travel Time: Time in Motion Time Stopped Total Time 11 min 10 min 21 min Trips per Hour per Vehicle Assumed Number of Vehicles (typical operating schedule) Headway min *Includes stops at signalized intersections, non-signalized intersections and at station platforms MLK Double-Track Pinched Loop Option Figures See the MLK Double-Track Pinched-Loop Option figures in Appendix B: - Figure B-1 Overall Alignment - Figure B-2 Alignment End Location Plan - Figure B-3 Signalized Intersection Plan - Figure B-4 Non- Signalized Intersection Plan 2-20 December

29 2.3.3 MLK Bypass Option The bypass option consists of the Streetcar traveling in a single isolated lane on MLK Way between S. 4 th Street and S. 19 th Street. The guideway diverges to allow for a bypass of vehicles traveling in opposite directions between S. 11 th Street and Earnest S. Brazill Street. The bypass track needs to be near the middle, but could be adjusted a short distance either direction if desired. The first car to reach the bypass track must wait for the other to proceed. Additionally, this system could be extended to Division St. and ultimately be connected with the proposed streetcar extension on Division St. This option assumes a single track along the east side of MLK, separated from the traffic lanes by some type of barrier. A conceptual layout of this alignment option is show in Appendix C. This bypass option generally consists of the following layout: Typical Mid-Block Section Typical Signalized Intersection (at platform) Typical Non-Signalized Intersection (at platform) Design Minimums Vehicle Lanes 2x12 2x11 2x12 2x10 Turn Lane N/A 10 N/A N/A Bike Lanes 2x5 2x5 2x5 2x5 Parking Lanes 7 (west) N/A 7 (west) N/A Streetcar Lane (west) 9 (east) Streetcar Platform N/A Sidewalks 11 (west) 17 (east) 11 (west) 8 (east) 10 (west) 10 (east) 10.5 (west) 10.5 (east) Total Right-of-Way See Figures C-2, C-3 and C-4 in Appendix C for diagrams of the alignments and the corresponding sections. This option had a number of parameters that were influential in the preparation of the conceptual alignment. These issues were as follows: Isolated Travel The streetcar will travel in an isolated lane for the length of the alignment. The primary reason for this isolation is the need to separate traffic traveling in opposing directions. The separation will likely be by use of a concrete barrier. The barrier design could be a raised curb and reflector posts or more solid structure depending on design choice. This option limits street parking to the west side of the street, and probably limits driveway access along the east side. It is assumed that bike lanes will be available along both sides of the street. December

30 Platform Position Due to the nature of a bypass system, the station platforms will always be placed on the east side of MLK Way except for the possibility of a center platform at the bypass location. This option will require about half the number of platforms of the other options, since the same platforms will be used in both directions. The platforms will be on the driver s right in one direction of travel and the left in the other. Platform arrangement will need to be compliant with ADA requirements. The platforms will need to provide the attractive pedestrian spaces and transit access targeted by Complete Streets. Station Locations The proposed alignment is based on the assumption that the station platforms are located approximately every other block along MLK Way. The single track system is less obtrusive to traffic, therefore the number of station platforms is more flexible Headway Analysis The headway analysis completed for the bypass option resulted in the following data: Analysis Parameter Result Maximum Speed Achieved 25 mph (constrained) Average Speed w/o Stops 9 mph Average Speed w/ Stops 5 mph *Total Number of Stops 31 Travel Distance 2.2 mi (11,600 ft) Travel Time: Time in Motion Time Stopped Total Time 11 min 9 min 20 min Trips per Hour per Vehicle Assumed Number of Vehicles (typical operating schedule) Headway min *Includes stops at signalized intersections, non-signalized intersections and at station platforms MLK Bypass Option Figures See the MLK Bypass Option figures in Appendix C: - Figure C-1 Overall Alignment - Figure C-2 Bypass Location Plan - Figure C-3 Signalized Intersection Plan - Figure C-4 Non- Signalized Intersection Plan 2-22 December

31 2.3.4 Alignment Comparison The following table describes the advantages and disadvantages of each system type: Loop System Double-Track Pinched-Loop Advantages Disadvantages Considerations Increased development Greatest cost option. Is J Street to be opportunity. Requires corner modification. included in the On-street parking is possible on The number of intersections development of both sides of MLK Way and J and the length of street MLK Way? Costs Street. impacted is double that of the and potential Potential for system scalability. other options. benefits are Impact area of the streetcar Utility conflicts have the significant. influence is expanded and potential to be greater since additional block width. an additional street is Single trackway allows room for affected. underground utility development. Return trips are less Trolley wire can generally be convenient to the passenger supported from one side of the street, reducing the impact of developing poles on both sides. On-street parking is possible on both sides of MLK Way. Potential for system scalability. Passengers can easily ride and return along the route. Greater cost option. Options for utility corridor greatly reduced. Much more street area on MLK is conflicted by the streetcar track. Pedestrian areas are reduced by track and platforms both sides. Pinched-loops at ends of alignment have potential to cause traffic conflicts. Proper signalization at ends of alignment is critical. Bypass System Lowest cost option. Streetcar separated from traffic. Passengers can easily ride and return along the route. Single trackway allows room for underground utility development Trolley wire can generally be supported from one side of the street, reducing the impact of developing poles on both sides. Vehicles can use the same platforms traveling both directions. On-street parking not possible on east side of MLK Way. System scalability is limited due to requirement for additional bypasses when additional vehicles are added. Driveway access would be restricted on the trackway side of the street. Possible to extend single track system into a loop system in the future. December

32

33 3. TASK 3 MAINTENANCE FACILITY Parametrix has selected two lots for potential maintenance facility locations. An existing parking lot on the northwest corner of J Street and S. 20 th St. is a potential location for the loop system. A parking lot along on the southwest corner of MLK Way and S. 10 th St. is a potential location for the double-track pinched-loop system and the bypass system. There are likely alternate facility locations that may be more appropriate considering right-of-way and other considerations. Parametrix selected these sites for their spatial relationship to the various alignments and their apparent current usage. Depending on the timing of the streetcar development, it may be possible to utilize the existing Link maintenance facility by extending any of the three alignment options to the north and connecting to the proposed streetcar system along Division Street. The existing Link facility is probably too small to support the existing system and expansion to MLK. The cost of a new or expanded facility will be required for the system. For each of the alignment options considered and the associated headway analyses, Parametrix has assumed that each alignment would utilize two streetcar vehicles for operating service. A system with two operating vehicles would likely require a third streetcar vehicle such that major maintenance could be accomplished without decreasing service. For this reason, it has been assumed that the maintenance facility required to service each of the three alignment options would have space for three vehicles. The schematic layout of a maintenance facility for each of the three alignment options can be seen in Figures A-1, B-1 and C-1 respectively in the Appendixes. Functions required for the maintenance facility are storage of the vehicles, maintenance of the machinery, spare parts, and staff facilities. A dedicated power substation for the yard area will be required. Often, a main line traction power substation is also located in the maintenance yard. It is anticipated that as a minimum, the whole maintenance facility will be on the order of 200 feet long to park 2 trains, and on the order of 100 feet wide for all of the necessary functions. Many choices are available for related functions that can be located with the maintenance facility. Some streetcar projects have carwash systems. Some have parks or museum facilities located near the yard. December

34

35 4. TASK 4 OPINION OF PROBABLE COST The project team reviewed the available constructed cost of similar systems to define probable construction costs. The opinions of probable costs assume that the LID has responsibility for the street improvements and utility relocations. The streetcar project would install track, overhead electric, and make the modifications necessary for station platforms. The overall cost of the system depends heavily on the cost of the vehicles. The type of vehicle, features, and number are important variables in the system cost. Basic assumptions have been made regarding these factors. 4.1 REFERENCED SYSTEM COSTS In order to define probable costs for a streetcar project on MLK, data from similar systems have been compared. Some of the comparable built and proposed projects are shown in Table 1 with the dates the project was bid. PROJECT LENGTH - Mi. STATIONS BUDGET - $M $M / Track Mile Tucson, AZ (proposed) Portland Loop 2009 So. Lake Union 2005 Little Rock, AR (Double track) 19 $159 $ $147 $ $54 $ $21 $8 Table 1 - Comparable System Costs A more detailed look can be seen from the three systems that have actually been bid. The Portland Loop is just starting construction. The South Lake Union and Little Rock are based on the actual final costs. To the extent possible based on the available details, the costs for all three have been allocated according to the FTA Standard Cost Categories schedule, as shown in Table 2. To account for differences in available details, some assumptions have been made. As can be seen from the cost per linear track foot, the cost of the three systems varies widely. The Little Rock project is older and geographically separated from the area. Those costs may not reflect the construction cost in the Tacoma area. The Portland Loop system includes track on an existing bridge and an elevated structure. The details of utility street work are not known. For this cost analysis, the general costs from the South Lake Union system are believed to more closely represent the MLK project. December

36 Cost Category Portland Loop So. Lake Union Little Rock Guideway & Track $55,642,000 $6,962,000 $9,512,000 Stations $1,805,000 $249,000 (in track) Site Work, Conditions $17,994,000 $13,083,000 (in track) Systems $22,876,000 $6,972,000 $3,070,000 Construction Total $98,317,000 $27,266,000 $12,582,000 System Length Track Ft 36,025 14,784 13,728 Cost - $ / Track Ft $2,729 $1,844 $917 Utility Relocation $10,214,000 $4,750,000 $0 Table 2 - Construction Cost Categories The purchase of vehicles can have a major impact on the cost of the system. The costs for vehicles for the three referenced systems are shown in Table 3 The Gomaco car is a new car body built on renovated rail bogies using an antique body style. It is available with electronic controls, but has the old high floor style and must use chair lifts for ADA compliance. Oregon Iron Works has entered into an arrangement with the Skoda group of the Czech Republic to produce the Skoda streetcar under the name of United Streetcar. The car is now made in the USA and is compliant with the Buy American Act. It has a modern style car body, electronic controls and articulated body design. This is the car used for the Tacoma Link streetcar and it is anticipated that the same car would be used for the MLK system. Budget prices for this vehicle have been provided by United Streetcar. Vehicles Portland Loop So. Lake Union Little Rock Manufacturer Skoda/OIW Skoda Gomaco Number of Units Cost / Vehicle $3 M $2.8 M $850 K Table 3 - Project Vehicle Costs 4.2 MLK SYSTEM PROBABLE COSTS In order to develop a probable cost for a streetcar system in Tacoma, the costs from the South Lake Union project have been escalated for inflation and used for unit cost basis. Professional services for the referenced projects varied between 16% and 28% of complete system costs. This estimate has applied a 30% increase to the system costs for services and an additional 30% for contingencies based on the level of details at this time. The cost assumptions and unit requirements for the three options are shown in Table December

37 ITEM DESCRIPTION MLK SYSTEM OPTIONS LOOP OPTION DOUBLE TRACK SINGLE TRACK UNIT UNIT COST QUANT TOTAL QUANT TOTAL QUANT TOTAL GUIDEWAY AND TRACK LFT $710 12,000 $8,520,000 10,000 $7,100,000 5,700 $4,047,000 STATION STOPS EA $30, $480, $390,000 7 $210,000 SITE WORK, GENERAL CONDITIONS, NO UTILITY LFT $450 12,000 $5,400,000 10,000 $4,500,000 5,700 $2,565,000 SYSTEMS, OCS, SIGNALS LFT $475 12,000 $5,700,000 10,000 $4,750,000 5,700 $2,707,500 SUBSTATIONS EA $1,500,000 2 $3,000,000 2 $3,000,000 1 $1,500,000 SUBTOTAL, Construction Items $23,100,000 $19,740,000 $11,029,500 VEHICLE LS $3,500,000 3 $10,500,000 3 $10,500,000 3 $10,500,000 MAINTENANCE FACILITY LS $2,500,000 1 $2,500,000 1 $2,500,000 1 $2,500,000 SUBTOTAL, Complete System $36,100,000 $32,740,000 $24,029,500 PROFESSIONAL SERVICES: Prelim Design, Environ., Constr. Mgt., Owner Costs 30.00% $10,800,000 $9,800,000 $7,200,000 CONTINGENCIES 30.00% $10,800,000 $9,800,000 $7,200,000 TOTAL SYSTEM COST $57,700,000 $52,340,000 $38,429,500 Notes: It is assumed that all roadway and sidewalk reconstruction, utility relocation, R.O.W., landscaping, and street lighting is costed as part of the MLK Way reconstruction. Station platforms are assumed to be similar to the South Lake Union system The estimates of probable cost are in 2009 dollars and do not consider inflation. LFT = linear feet of track Table 4 - Probable Cost of MLK systems ($) 4.3 DEVELOPMENT WITH LOCAL IMPROVEMENT DISTRICT The City is planning a Local Improvement District redevelopment project which is expected to renovate much of the utility and street system along MLK Way between S 25 th and Division. The timing and financing of the LID is not anticipated to be able to support complete development of the streetcar system at the same time. If the project were to be completed in two phases, first completing the LID and second building the street car, the magnitude of the disturbances to the businesses and surrounding area would be of equal magnitude in both phases. Therefore, construction of the most invasive part of the project in one phase would minimize the impact to the residents. To assist with planning for the project, a probable cost has been developed for construction of the trackway only. If the December

Pace Bus Depot Location Analysis

Pace Bus Depot Location Analysis Pace Bus Depot Location Analysis Key Notes 1. Options refer to conceptual sketches prepared by Kimley Horn. 2. The depot is assumed to accommodate Pace routes as they currently exist: 17 routes on the

More information

CONCEPTUAL ENGINEERING REPORT

CONCEPTUAL ENGINEERING REPORT CONCEPTUAL ENGINEERING REPORT May 2013 CONTENTS 1 Introduction... 1 1.1 Project Background... 1 1.2 Purpose of Document... 1 2 Design Principles... 2 2.1 Track / Guideway Element... 2 2.2 Roadway... 3

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

Streetcar and Light Rail Design Differences. March 2015

Streetcar and Light Rail Design Differences. March 2015 Streetcar and Light Rail Design Differences March 2015 How Are Streetcar and Light Rail Different? The design differences between streetcar and light rail are tied to the distinctions in the markets served

More information

TRAFFIC MANAGEMENT STANDARDS CITY OF GARLAND TRANSPORTATION DEPARTMENT

TRAFFIC MANAGEMENT STANDARDS CITY OF GARLAND TRANSPORTATION DEPARTMENT TRAFFIC MANAGEMENT STANDARDS CITY OF GARLAND TRANSPORTATION DEPARTMENT JUNE 1996 TABLE OF CONTENTS 1.0 Street Design Standards 1.1 Right-of-Way Requirements 1.2 Median Openings 1.3 Sidewalks 1.4 Traffic

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior

More information

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

Appendix F-1 Description of the Long-Term Alternatives

Appendix F-1 Description of the Long-Term Alternatives Appendix F-1 Description of the Long-Term Alternatives Memorandum Page 1 of 21 Project No. 9309 Phase 280 Date June 2, 2015 From Chris Sidlar (LEA) To Edward Presta / City of Toronto C.C. Terry Wallace

More information

Greater Cleveland Regional Transit Authority. Bus Stop Design Guidelines

Greater Cleveland Regional Transit Authority. Bus Stop Design Guidelines Greater Cleveland Regional Transit Authority Bus Stop Design Guidelines Contents Purpose... I Bus Stop Design & Location... 1 Bus Stop Planning... 1 Bus Stop Safety & Consolidation... 1 As Needed Basis...

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

BUS STOP DESIGN & PLANNING GUIDE

BUS STOP DESIGN & PLANNING GUIDE BUS STOP DESIGN & PLANNING GUIDE Prepared by the Operations and Planning Departments 2011 PURPOSE OF GUIDE The design of passenger waiting areas plays a significant role in a person s decision of whether

More information

appendix 4: Parking Management Study, Phase II

appendix 4: Parking Management Study, Phase II appendix 4: Parking Management Study, Phase II A4-1 A4-2 Eastlake Parking Management Study Final Phase 2 Report Future Parking Demand & Supply January 6, 2017 Submitted by Denver Corp Center III 7900 E.

More information

DESIGN STANDARDS SECTION DS 3 STREETS

DESIGN STANDARDS SECTION DS 3 STREETS DESIGN STANDARDS SECTION DS 3 STREETS DS 3-01 GENERAL: A. INTENT: The intent of these Design Standards is to provide minimum standards for the design of public streets. These standards are intended to

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016

I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016 I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016 INTRODUCTION As part of the I-290 reconstruction phase I study, IDOT has coordinated with the CTA regarding

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

CHAPTER 9: VEHICULAR ACCESS CONTROL Introduction and Goals Administration Standards

CHAPTER 9: VEHICULAR ACCESS CONTROL Introduction and Goals Administration Standards 9.00 Introduction and Goals 9.01 Administration 9.02 Standards 9.1 9.00 INTRODUCTION AND GOALS City streets serve two purposes that are often in conflict moving traffic and accessing property. The higher

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

Streetcar and Light Rail Design Differences. February 2015

Streetcar and Light Rail Design Differences. February 2015 Streetcar and Light Rail Design Differences February 2015 How Are Streetcar and Light Rail Different? The design differences between streetcar and light rail are tied to the distinctions in the markets

More information

Appendix C Preferred Solution

Appendix C Preferred Solution Appendix C Preferred Solution C.1 Conceptual Design Drawings C.2 Preferred Option Ideas and Inspiration C.3 Concept Renderings C.4 Cost Estimate Appendix C.1 Conceptual Design Drawings Plan View Brock

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Streetcar Level Boarding Background Memo

Streetcar Level Boarding Background Memo Level Boarding Background Memo Introduction This memo has been prepared by the and the Community Coalition to facilitate industry discussion on the application of level boarding concepts to US modern streetcar

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

ORDINANCE NO

ORDINANCE NO ORDINANCE NO. 07-5424 AN ORDINANCE OF THE CITY OF BILLINGS, PROVIDING THAT THE BILLINGS, MONTANA CITY CODE BE AMENDED BY REVISING SECTION 6-1208; PROVIDING CHANGES TO CERTAIN CURB CUT LENGTHS AND REGULATIONS.

More information

CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 III. SPEED HUMP INSTALLATION PROCEDURE... 7 APPENDIX A... 9 APPENDIX B...

CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 III. SPEED HUMP INSTALLATION PROCEDURE... 7 APPENDIX A... 9 APPENDIX B... Speed Hump Program CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 1. GENERAL... 3 2. ELIGIBILITY REQUIREMENTS... 3 A. PETITION... 3 B. OPERATIONAL AND GEOMETRIC CHARACTERISTICS OF

More information

Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z Hillside Drive, Dallas, TX October 27, 2015

Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z Hillside Drive, Dallas, TX October 27, 2015 Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z145-235 2720 Hillside Drive, Dallas, TX October 27, 2015 Introduction: The Lakehill Preparatory School is located on the northeast

More information

SPEED CUSHION POLICY AND INSTALLATION PROCEDURES FOR RESIDENTIAL STREETS

SPEED CUSHION POLICY AND INSTALLATION PROCEDURES FOR RESIDENTIAL STREETS SPEED CUSHION POLICY AND INSTALLATION PROCEDURES FOR RESIDENTIAL STREETS CITY OF GRAND PRAIRIE TRANSPORTATION SERVICES DEPARTMENT SPEED CUSHION INSTALLATION POLICY A. GENERAL Speed cushions are an effective

More information

STANDARD DRAWING INDEX

STANDARD DRAWING INDEX ATTACHMENT B STANDARD DRAWING INDEX DESCRIPTION EXISTING DRAWING NO. GENERAL Typical Layout for Improvement Plans City of Stockton Standard Border and Title Block for 8 1/2 x11 Sheet City of Stockton Standard

More information

Cost to extending KC Streetcar north approximately ½ mile

Cost to extending KC Streetcar north approximately ½ mile Technical Memorandum September 22, 2015 Attention: Jason Waldron, PE From: Lucas L. Olson, PE; Cory Imhoff, PE RE: Cost to extending KC Streetcar north approximately ½ mile HDR was asked for their opinion

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

CORE AREA SPECIFIC PLAN

CORE AREA SPECIFIC PLAN only four (A, B, D, and F) extend past Eighth Street to the north, and only Richards Boulevard leaves the Core Area to the south. This street pattern, compounded by the fact that Richards Boulevard is

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

Construction Realty Co.

Construction Realty Co. MEMORANDUM TO: FROM : Jeff Pickus Construction Realty Co. Luay R. Aboona, PE Principal 9575 West Higgins Road, Suite 400 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 DATE: May 22, 2014 SUBJECT:

More information

COST ESTIMATES: Curb-Running

COST ESTIMATES: Curb-Running COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program

More information

2.0 Development Driveways. Movin Out June 2017

2.0 Development Driveways. Movin Out June 2017 Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

1 Downtown LRT Connector: Draft Concept

1 Downtown LRT Connector: Draft Concept Downtown LRT Connector: Draft Concept Plan November 2010 We re moving forward. Get involved. On June 21, 2010, City Council approved a street-level downtown LRT route, including a connector for the future

More information

2. ELIGIBILITY REQUIREMENTS

2. ELIGIBILITY REQUIREMENTS Speed Hump Policy 1. GENERAL The purpose of this policy is to provide guidelines for the application of speed humps. A "speed hump" is a gradual rise and fall of pavement surface across the width of the

More information

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas

More information

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No TECHNICAL MEMORANDUM TO: FROM: Transit Advisory Group Jeff Rhoda DATE: RE: I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P. 2785-330B SEH No. 123252 04.00 I-494/I-35W Interchange

More information

Access Management Standards

Access Management Standards Access Management Standards This section replaces Access Control Standards on Page number 300-4 of the Engineering Standards passed February 11, 2002 and is an abridged version of the Access Management

More information

14.0 Capital Cost Estimate Methodology

14.0 Capital Cost Estimate Methodology 14.0 Capital Cost Estimate Methodology 14.1 Purpose of the Memorandum This memorandum documents the major assumptions that inform the conceptual capital cost estimates for the transit improvement alternatives

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency

More information

Stormwater and sanitary sewer lines 8 inches in diameter or greater

Stormwater and sanitary sewer lines 8 inches in diameter or greater 3.8 UTILITIES 3.8.1 Affected Environment This section describes the utility crossings and utilities located in the vicinity of the Preferred Alternative. The utilities include electricity, communication,

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

Appendix C. Parking Strategies

Appendix C. Parking Strategies Appendix C. Parking Strategies Bremerton Parking Study Introduction & Project Scope Community concerns regarding parking impacts in Downtown Bremerton and the surrounding residential areas have existed

More information

CATEGORY 500 PAVING SECTION 535 PAVEMENT SURFACE PROFILE

CATEGORY 500 PAVING SECTION 535 PAVEMENT SURFACE PROFILE CATEGORY 500 PAVING 1 of 9 SECTION 535.01 DESCRIPTION. This work shall consist of measuring the roughness of the final surface of hot mix asphalt (HMA) or portland cement concrete (PCC) pavements. The

More information

800 Access Control, R/W Use Permits and Drive Design

800 Access Control, R/W Use Permits and Drive Design Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled

More information

NORTHWEST HIGHWAY S-CURVE PEDESTRIAN/BICYCLE ACCESS FEASIBILITY STUDY. Northwest Highway (US 14) From Seegers Road to Western Avenue

NORTHWEST HIGHWAY S-CURVE PEDESTRIAN/BICYCLE ACCESS FEASIBILITY STUDY. Northwest Highway (US 14) From Seegers Road to Western Avenue NORTHWEST HIGHWAY SCURVE PEDESTRIAN/BICYCLE ACCESS FEASIBILITY STUDY Northwest Highway (US 14) From Seegers Road to Western Avenue Northwest Highway SCurve Pedestrian/Bicycle Access Feasibility Study City

More information

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2

More information

H' f'~7~ :; DOWNTOWN UTILITY UNDERGROUNDING FEASIBILITY STUDY DRAFT. City of Roseburg, Oregon. December Engineers/Pbnners

H' f'~7~ :; DOWNTOWN UTILITY UNDERGROUNDING FEASIBILITY STUDY DRAFT. City of Roseburg, Oregon. December Engineers/Pbnners DRAFT DOWNTOWN UTILITY UNDERGROUNDING FEASIBILITY STUDY ----... --- -.- - - 11 - - - I- - -I. -- -= H' f'7 :; -- -. -. - -. Mumy, Smilh & Associates, Inc. Engineers/Pbnners City of Roseburg, Oregon December

More information

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &

More information

This letter summarizes our observations, anticipated traffic changes, and conclusions.

This letter summarizes our observations, anticipated traffic changes, and conclusions. Mr. David Jorschumb Project Manager Boulder Valley School District Re: Review of proposed school access improvements at the Foothills Elementary School in Boulder Dear Mr. Jorschumb, At your request, the

More information

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

1400 MISCELLANEOUS Traffic Engineering Manual

1400 MISCELLANEOUS Traffic Engineering Manual TABLE OF CONTENTS Part 14 - MISCELLANEOUS 1400 GENERAL... 14-3 1415 RUMBLE STRIPS (INCLUDING STRIPES) IN THE ROADWAY... 14-4 1415-1 General... 14-4 1415-2 Transverse Rumble Strips... 14-4 1415-2.1 General...

More information

Dixie Transportation Planning Office

Dixie Transportation Planning Office A project must be given a yes rating on items 1 & 2 in order to be prioritized. Sponsor: St. George City Project: Pioneer Parkway Type: Road Widening and Reconstruction Rev. 9/17/2010 Dixie Transportation

More information

TRANSPORTATION REVIEW

TRANSPORTATION REVIEW TRANSPORTATION REVIEW - PROPOSED MIX OF LAND USES IS CONSISTENT WITH THE CITY S UNDER THE GRANVILLE BRIDGE POLICIES THAT AIM TO MEET NEIGHBOURING RESIDENTS SHOPPING NEEDS AND REDUCE RELIANCE ON AUTOMOBILE

More information

Appendix C. 5% Design Plan and Profile Drawings/ Additional Design Information. South Oak Cliff Corridor Blue Line Extension

Appendix C. 5% Design Plan and Profile Drawings/ Additional Design Information. South Oak Cliff Corridor Blue Line Extension Appendix C 5% Design Plan and Profile Drawings/ Additional Design Information The 5% plan and profile drawings were provided in a separate volume with the Draft Local EA and have not changed. Hard copies

More information

TRAFFIC ENGINEERING ASSESSMENT MOUNT EDEN ROAD, MOUNT EDEN

TRAFFIC ENGINEERING ASSESSMENT MOUNT EDEN ROAD, MOUNT EDEN 12 September 2017 Iain McManus Civitas Planning Consultants PO Box 47020 Ponsonby AUCKLAND 1144 Dear Iain, TRAFFIC ENGINEERING ASSESSMENT 43-45 45 MOUNT EDEN ROAD, MOUNT EDEN As requested, we have prepared

More information

CTA Blue Line Study Area

CTA Blue Line Study Area CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site. Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS

More information

Purpose: General Provisions:

Purpose: General Provisions: 10-19-1 Purpose: The purpose of off-street parking requirements is to promote traffic/pedestrian safety and efficiency and to minimize hard surfaced areas to reduce storm water run-off and visual impacts

More information

CITY OF PORTSMOUTH DEPARTMENT OF PUBLIC WORKS (DPW) DRIVEWAY RULES AND PROCEDURES

CITY OF PORTSMOUTH DEPARTMENT OF PUBLIC WORKS (DPW) DRIVEWAY RULES AND PROCEDURES CITY OF PORTSMOUTH DEPARTMENT OF PUBLIC WORKS (DPW) DRIVEWAY RULES AND PROCEDURES The purpose of a driveway permit is to secure access from a private property to the public right-of-way. It is required

More information

DRIVEWAY ENTRANCES GENERAL. 1. Description

DRIVEWAY ENTRANCES GENERAL. 1. Description GENERAL 1. Description This standard identifies the minimum requirements that shall be met for all driveway entrances in the design and construction of elements for Arlington County Horizontal Design Standards.

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

IH 35 FEASIBILITY STUDY

IH 35 FEASIBILITY STUDY IH 35 FEASIBILITY STUDY COOKE COUNTY, TEXAS February 1, 2007 Prepared by: Carter & Burgess, Inc. For: The Wichita Falls District of the Texas Department of Transportation INDEX I. INTRODUCTION. 3 II. PURPOSE

More information

ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS

ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS TABLE OF CONTENTS SECTION PAGE 8.1 GENERAL STANDARDS...8-2 8.2 PRIVATE DRIVEWAY PROVISIONS...8-4 8.3 OFF-STREET PARKING STANDARDS...8-5 8.4 OFF-STREET

More information

APPENDIX VMT Evaluation

APPENDIX VMT Evaluation APPENDIX 2.7-2 VMT Evaluation MEMORANDUM To: From: Mr. Jonathan Frankel New Urban West, Incorporated Chris Mendiara LLG, Engineers Date: May 19, 2017 LLG Ref: 3-16-2614 Subject: Villages VMT Evaluation

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Mercer Island Center for the Arts Parking Management Plan

Mercer Island Center for the Arts Parking Management Plan Parking Stalls Mercer Island Center for the Arts Parking Management Plan June 15, 2016 This Parking Management Plan (P) covers all tenants at the Mercer Island Center for the Arts (MICA) campus, including

More information

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will

More information

RECOMMENDED ALTERNATIVE REPORT

RECOMMENDED ALTERNATIVE REPORT DRAFT METROCENTER CORRIDOR STUDY RECOMMENDED ALTERNATIVE REPORT JULY 12, 2005 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 2.0 TIER 1 ALTERNATIVES EVALUATION... 1 3.0 TIER 2 ALTERNATIVES EVALUATION...

More information

Essex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives

Essex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives Essex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives Village of Essex Junction Chittenden County Regional Planning Commission RSG, Inc. Scott & Partners Architectural

More information

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

MOTOR VEHICLE ORIENTED BUSINESSES.

MOTOR VEHICLE ORIENTED BUSINESSES. ARTICLE 23. MOTOR VEHICLE ORIENTED BUSINESSES. Sec. 25-23.1. Conditional Use. Motor vehicle oriented businesses (MVOB) shall require a Conditional Use Permit in all districts as indicated in Appendix B,

More information

4.2 Series Station Option Description

4.2 Series Station Option Description 4.2 Series Station Option Description The series station proposal features a new set of side platforms constructed approximately 250 feet north of the existing platforms. The two new platforms would extend

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS)

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) A: 2014 SFMTA TRANSIT SERVICE INFORMATION B: SFMTA TRAFFIC COUNT DATA C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) E: LAND USE AND VALUE

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

Terminal Alternatives

Terminal Alternatives Chapter 5 Terminal Alternatives Missoula International Airport Master Plan Update Prepared for Missoula County Airport Authority OCTOBER 2008 Contents Section Page 5 Terminal Alternatives...5-1 5.1 Terminal

More information

POLICIES FOR THE INSTALLATION OF SPEED HUMPS (Amended May 23, 2011)

POLICIES FOR THE INSTALLATION OF SPEED HUMPS (Amended May 23, 2011) (Amended May 23, 2011) 1. Speed humps are an appropriate mechanism for reducing speeds on certain streets in Pasadena when properly installed under the right circumstances. 2. Speed humps can be considered

More information

3.15 SAFETY AND SECURITY

3.15 SAFETY AND SECURITY 3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum

More information

BOARD OF ZONING ADJUSTMENT STAFF REPORT Date: November 7, 2016

BOARD OF ZONING ADJUSTMENT STAFF REPORT Date: November 7, 2016 # 2 HOLDOVER Revised ZON2016-01992 BOARD OF ZONING ADJUSTMENT STAFF REPORT Date: November 7, 2016 CASE NUMBER 6065 APPLICANT NAME LOCATION VARIANCE REQUEST ZONING ORDINANCE REQUIREMENT ZONING AREA OF PROPERTY

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) CFS:TEH 1 of 10 APPR:KPK:JFS:07-07-16 FHWA:APPR:07-15-16 a. Description. This

More information

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 6, 2018

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 6, 2018 TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 6, 2018 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER HAMILTON

More information

PN /21/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS

PN /21/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS PN 420-10/21/2016 - SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS DESCRIPTION: The surface tolerance specification requirements are modified as follows for all pavements of constant width with at least

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information