1 AUTOMATION Hydro Thermal Al Qaim (Iraq) Al Shemal (Iraq) Jorf Lasfar (Morocco) Petkim (Turkey) Aswan High Dam (Egypt) Kidatu (Tanzania) Kihansi (Tanzania) Three Gorges (China) NEK (Bulgaria) Ertan (China) Karun (Iran) Yali (Vietnam) Manantali (Mali) Gas/Diesel Nouadhibou (Mauritania) EDD Boulaos (Djibouti) Omar (Syria) Control Systems

2 Aswan High Dam - Egypt AHD power plant generates 2100 MW. Main functional units are: 12 generating units - each consisting of turbine (Frances type, max. gross head 74 m) generator (60 pole, 100 rpm, 180 MW max, kv) unit transformer (500 kv) 2 switchyards: 500 kv (2 exit lines) 132 kv (4 exit lines and 2 feeders) 2 auto-transformers: reducing the voltage from 500 kv to 132 kv and 6 kv controller's cabinets design, specification and manuf. supervision DCS design documentation and site survey process controllers application design, programming and testing operator stations application design and customizing factory acceptance test with client wiring supervision, I/O check, synchronization, transducers adjusting and installation, unit & switchyard circuit breakers synchronization commissioning and start-up training for operation and maintenance personnel Entire power plant is controlled by ABB DCS - process controllers and runs fully automatic. Control includes: turbines, generators, breakers, transformers, subsystems etc. Number of wired I/O signals: Configuration Process controllers - AdvantController 450 (17 units) Operator stations - AdvantStation 500 OS (3 units) Operator stations - Windows NT based PC application (2 units) Information Management Station - PC based application (2 units) Local Viewers - PC based application (26 units) Event/alarm printers, hardcopy printers and report printers. 17 January 2001 September 2001, 6 INTEA s engineers worked in Alstom, Denver-USA, on project design, cubicle production supervision and factory acceptance tests. October 2001 November 2003, 6 INTEA s engineers worked on site (in shifts) until successful handover , DCS HW and SW deliveries: extensions, modifications, site activities and commissioning due to Voith- Siemens scheduled overhauls of generating units. INTEA s work was recognized, by ALSTOM project management and end-user HPGC, as outstanding and highly professional.

3 Kidatu - Tanzania Kidatu Dam is Tanzania's largest Hydro Power Plant. Total generating capacity: 200 MW No. of units: 4 HD About the Project Partial upgrade/migration of existing Simatic S5 control system to S7 was selected by the end user as optimal, cost-effective solution. It included upgrade of processors, communication modules and SCADA, without replacement of the I/O modules. INTEA Delivery Engineering services project management design engineering application engineering factory acceptance tests onsite training site works Hardware & Software Delivery Process controllers, operator panels, eng. workstation, Step7 and WinCC, Equipment for communication between process controllers and SCADA, Industrial time synchronization central plant clock with GPS radio clock, SCADA system software license, Commissioning spare parts. The system controls and monitors: 4 generating units, Auxiliary PS, Auxiliary building, Switchyard, Dam, Overall Station functions. Control system is based on 9 Siemens SIMATIC process controllers (Unit1, Unit2, Unit3, Unit4, Aux PS, Aux Building, Switchyard, Dam and Station Controller) and IGSS 32 SCADA running on standard PCs with MS Windows. 4 Outcome With minimal upgrade costs and plant downtime, the control system is now based on up-to-date HW & SW, completely in accordance with recognized, international standards. The upgrade has increased reliability and availability of the plant and improved its operation and performance. End user's satisfaction was confirmed by awarding further contracts related to similar overhauls of their other powerplants.

4 Kihansi - Tanzania Total generating capacity: 180 MW No. of units: 3 (Pelton turbines) Facility has been in operation since December Concrete gravity dam on the Kihansi River has a height of 25m and a length of 200m, which creates a reservoir with a storage volume of 1 million m³. The turbines use the 900m drop in the Kihansi Gorge over a distance of about 3km, and return the water to the river about 6km downstream. control system hardware (ABB IndustrialIT: 8 x AC 800M controller, 2 x 800xA operator's workplace + 1 x 800xA engineering workplace; 3 servers, printers, GPS clock) system software & licenses engineering works (Project management, Application engineering, F.A.T.) technical training site works (pre-commissioning and commissioning of process controllers, start-up of operator and engineering workplaces, testing of the complete DCS, site acceptance test) Control system (CS) provides integrated control and monitoring of the overall plant operation from central control room. It is based on ABB 800xA Extended Automation and AC800M process controllers. CS controls and monitors: three generating units G1-G3 (unit controllers), auxiliaries and common devices (common controller), station control (station controller), 33kV and 220kV switchyard (switchyard controllers), Intake and dam RTU (intake RTU). Outcome With minimal upgrade costs and plant downtime, the control system is now based on up-to-date HW & SW. The upgrade has increased reliability and availability of the plant as well as improved its operation and performance. At the same time, maintenance costs are significantly decreased. Client's satisfaction was confirmed in a formal, written record.

5 Three Gorges - China The Three Gorges Hydropower Station is comprised of two power plants, situated on each side of the central spillway, with a total of 26 generating units. Each generating unit has a capacity of 700 MW, the size of a baseload powerplant. The total capacity will be MW, with a planned annual power generation of 84.7 billion kilowatt-hours. When completed, it will be the single greatest power plant in the world. DCS design documentation - specifications for Information Management System process controllers - "Transit node" application design, programming and testing training for operation and maintenance personnel site support - technical expertise Information Management System specification Design and development of "Transit node" - ABB AdvantController 450 application to support and manage data communication Documentation and technical training for end-user's personnel Site intervention - technical support

6 NEK - Bulgaria s NEK system project covers 3 hydro power plants: Belmeken (375MW), Momina Klisura (120MW) and Sestrimo (240MW). Distributed control system - SW design specification and other documentation process controllers application design, programming and testing operator stations application design and customizing SW lead engineering and coordination Power plants are controlled by ABB DCS - process controllers and run fully automatic. Control includes: turbines, generators, breakers, transformers, subsystems etc. Number of wired I/O signals: Configuration Process controllers - AdvantController 450 (12 units) Operator stations - AdvantStation 500 OS (6 units) Information Management Stations - AS500 IMS (3 units) Control network MasterBus 300 and Plant network TCP/IP Event/alarm printers, hardcopy printers and report printers DCS SW - project leading INTEA s work was recognized, by ABB project management as outstanding and highly professional.

7 Ertan - China The plant is located near Panzhihua on the Yalong river (a tributary of the Yangtze) in Sichuan province. Total installed plant capacity is 3300MW (6x550MW). Construction began in Ertan power plant produced 3.9 billion kilowatt hours of power in the first year of operation since August 1998, when its first generating unit went into operation. Completed at the end of 1999, it has set a new record for speed of installation of a hydroelectric project. INTEA took part in: process controllers application design, programming and testing operator stations application design and customizing communication troubleshooting intervention control system upgrade, extension and modifications Power plants are controlled by ABB DCS - process controllers and run fully automatic. Control includes: turbines, generators, breakers, transformers, subsystems etc. Configuration Process controllers - AdvantController 450 (12 units) Process controllers - AdvantController 110 (2 units) Process controllers - AdvantController 410 (3 units) Operator stations - AdvantStation 500 OS (5 units) Information Management Stations - AS500 IMS (3 units) Control network MasterBus 300 and Plant network TCP/IP Event/alarm printers, hardcopy printers and report printers F.A.T. with the client Application development Intervention, communication problems analysis Control system upgrade Control system upgrade Site interventions and technical support System extensions, interventions and technical support

8 Karun I - Iran Location: Karun river, Iran Operator: Khuzestan Regional Electric Power Configuration: 8 X 250 MW Francis Operation: since INTEA took part in: process controllers application design, programming and testing F.A.T. with the client technical training for client's operation and maintenance personnel Power plant is controlled by ABB DCS - process controllers and runs fully automatic. Control includes: turbines, generators, breakers, transformers, subsystems etc. Number of wired I/O signals: Configuration Process controllers - AdvantController 450 (9 units) Process controllers - AdvantController 110 (7 units) Operator stations - UNIX based PC (5 units) Control network MasterBus 300 and Plant network TCP/IP Event/alarm printers, hardcopy printers and report printers Application development F.A.T., technical training for the client, commissioning

9 Yali - Vietnam Yali Falls Dam was the first of the proposed dams in the Se San River basin to be constructed. Construction of the dam commenced in 1993, and was completed in December The 69 meter-high dam was sealed in The 64.5 km2 reservoir was filled by Yali HPP is composed of 4 units totaling 720 MW and highvoltage 500kV switchyard (6 lines). DCS site survey process controllers application design, programming and testing operator stations application design and customizing factory acceptance test with client DCS commissioning training for operation and maintenance personnel Entire power plant is controlled by ABB DCS - process controllers and runs fully automatic. Supervision and control includes turbines, generators, breakers, transformers, subsystems, e.g.: 4 units high-voltage switchyard water intake gates spillway structure auxiliaries and station service Number of wired I/O signals: Configuration Process controllers - AdvantController 450 (6 units) Process controllers - AdvantController 110 (5 units) Operator stations - AdvantStation 500 OS (2 units) Control network MasterBus 300, Plant Network TCP/IP Event/alarm printers, hardcopy printers and report printers technical trainig for clients personnel site survey DCS commissioning

10 MANANTALI - Mali Manantali consists of the Manantali dam on the Bafing river, a power station and a network of transmission lines. The dam is 1460m long and 65m high. It created a reservoir with a storage capacity 11,3 million m 3 and a surface of 477km MW hydro power plant consists of: 5 units - 40MW each and 2 switchyards - 225kV and 90kV. Three 225kV lines run to Bamako (Mali capital, 322km), Dakar (Senegal, 820km) and Nouakchott (Mauritania capital) (226km). One 90kV line connects Manantali HPP and a town of Kaedi (Mali, 87km). process controllers application design, programming and testing operator stations application design and customizing factory acceptance test with client Entire power plant is controlled by ABB DCS - process controllers and runs fully automatic. Supervision and control includes turbines, generators, breakers, transformers, subsystems, e.g.: 5 unit groups 2 high-voltage switchyards water intake gates auxiliaries Number of wired I/O signals: Configuration Process controllers - AdvantController 410 (8 units) Process controllers - AdvantController 70 (5 units) Operator stations - AdvantStation 500 OS (3 units) Control network MasterBus 300, Plant Network TCP/IP Event/alarm printers, hardcopy printers and report printers. May 2000 August 2000, process controller and operator station - application design, programming and FAT with the client.

11 Power Generation - Circulating Water System Al Qaim - Iraq Thermal Power Plants Chemical complex "State Company for Phosphate" - Al Qaim, Iraq - consists of integrated and interrelated plants to produce different kinds of phosphate fertilizers as a final product. Local power plant 2x14 MW is based on two steam turbine generating units TG1 and TG2. INTEA has delivered complete control system, including: design engineering, application engineering, HW manufacturing and assembling, factory acceptance test with the client, site works and commissioning, end user technical training. Main parts of Al Qaim SCP steam turbines control system are: Process controllers - ABB AdvantController 160 (4 units), Operator stations - ABB IndustrialIT 800xA (2 units), Engineering station - ABB 800xA Engineering Workplace (1 unit), Communication networks, printers and uninterruptible power supplying units. INTEA is present on Al Qaim SCP plant since Even before the project start, INTEA was engaged in site survey and finding optimal solutions for steam turbines control system modernization.

12 Power Generation - Circulating Water System Al Shemal - Iraq Thermal Power Plants Al Shemal TPS is a new 1400 MW thermal power plant consisting of 4 units (4x350MW). Circulating water system (CWS) Primary task of the CWS is to provide cooling water from Tigris river for main condenser and closed cycle cooling water heat exchangers. The circulating water intake structure also provides river water for screen wash system, service water system, fire fighting system and raw water treatment plant. The circulating water intake structure and pump station are sized for four 350 MW units with possibility of extension with two similar units. Main CWS parts water intake accessories circulating water pumps lubrication water pumps swing check valves design documentation process controllers - application design and development operator stations - application design and development control cubicles and other equipment delivery system integration F.A.T. - testing with the client training for operation and maintenance personnel "As manufactured" - documetation delivery Main CWS parts listed above are supervised and controlled by process control software applications running in 8 ABB process controllers AdvantController 800M and auxilliary electrical equipment mounted in 8 control cubicles. Number of wired I/O signals: DCS Configuration Process controllers - AdvantController 800M (8 units) Operator interface - Process Panel 245 (2 units) Control network and Plant Network TCP/IP Control system design, final design project documentation Distributed process control and supervision system, integration, programming, testing and equipment delivery.

13 Power Generation - Process Utilities Thermal Power Plants Jorf Lasfar - Morocco Jorf Lasfar power plant consists of 4x330 MW coal-fired/steambased turbo-generators. With total production capacity of 1320MW this is the largest independent power plant in Africa. Process utilities - control and supervision system: process controllers application design, programming and testing operator stations application design and customizing commissioning ABB DCS Configuration Process controllers - AdvantController 450 Process controllers - AdvantController 160 Operator stations - AdvantStation 500 OS Control network MasterBus 300, Plant Network TCP/IP application design, programming and commissioning coal handling intervention, program modifications, system maintenance program modifications & commissioning

14 Gas and/or Diesel Power Plants Nouadhibou - Mauritania Diesel power plant Nouadhibou configuration: 4 x 5,5 MW; 12PC2.5V400D engines, 500 rpm, 2 x 11 MW, 600 rpm; Voltage: 15 kv/50 Hz INTEA scope of supply for the project was: ABB 800xA distributed control system (DCS) equipment, ABB DCS system software, DCS application software, DCS engineering and site works, end user DCS technical training. DCS controls and monitors: two new diesel generators G5 & G6, 15kV switchyard - protection relays, common systems and equipment. DCS Configuration Main ABB equipment comprises: Process controller - AC800M with remote I/O & local panel, Operator/Engineering stations 800xA (5 servers + 3 clients), Control network - ModuleBus, TCP/IP plant network, Separate network segments for G5&G6 and 15kV switchyard, MODBUS communication with panel instruments, GPS clock, UPS, printers, large display; Control System Upgrade Delivery of additional HW Control System Extension Delivery of additional HW Delivery of additional HW

15 Gas and/or Diesel Power Plants Centrale de Boulaos - Djibouti BOULAOS power plant operates in Djibouti grid with 100 MW of total power. Main parts of the system are: 13 generators (6 more in Marabout), 63 and 20kV overhead lines (246 km), 279 transformer locations INTEA scope of supply related to the ABB DCS since 1999 was: design engineering, ABB 800xA and other equipment delivery, system software delivery, application software, engineering and site works, end user technical training. Power generation is controlled by process controllers. Control includes: turbines, generators, transformers, subsystems etc. DCS Configuration Presently, automation subsystems originate from various manufacturers, mostly ABB and Siemens. Main ABB equipment comprizes: Process controllers - AdvantController 110 (4 units), Process controllers - AdvantController 160 (4 units), Process controllers - AC800M (2 units) Operator stations 800xA (8 servers + 5 clients), Control network - Advant Fieldbus 100, TCP/IP plant network. 16 Most significant DPP Boulaos projects: Commissioning and system optimizing DCS visualization system upgrade Integration of G22 in the DCS xA extension and training DCS extension - G24 alarms Upgrade of 4 x ABB AC110 to 4 x ABB AC160

16 Gas and/or Diesel Power Plants OMAR - Syria OMAR power system network operates in island mode, covering area of some 100km2, with 200MW of total power. Main parts are: 18 distributed generators with dual fuel turbines (gas/diesel), double 66kV overhead lines to 4 major remote sites, 400 major devices (transformers, breakers, motors, etc) Entire power system is controlled by ABB DCS - process controllers and runs fully automatic. Control includes: turbines, generators, breakers, transformers, subsystems etc. Number of wired I/O signals: Power Management System is a special group of dedicated programs in ABB DCS controller. Main functions are: monitoring interconnection status of the power system coordination of generators, frequency/voltage regulation calculation of consumption per load, island, area and site monitoring spare capacity of running generator sets load-shedding (disconnecting) preselected loads within 100ms disabling start of large loads if exceeding spare capacity monitoring and recording power consumption peaks warning and suggesting messages for the operator reports: production, consumption, running hours, peaks,... DCS Configuration Process controllers - AdvantController 450 (9 units) Operator stations - AdvantStation 500 OS (10 units) Information Management Station - AS500 IMS (2 units) X terminals - (2 units) Control network MasterBus 300, Plant Network TCP/IP, MODBUS serial links etc. 7 Power Management System - application development Process utilities (fuel gas, water treatment, instrument air, diesel fuel, etc.) - application design and development process controllers application design, programming and testing operator stations application design and customizing factory acceptance test with client wiring supervision, I/O check commissioning and start-up training for operation and maintenance personnel Application development, programming and commissioning, technical training Onsite baby sitting and extensive customer technical training Y2000 compliance survey and corrections Maleh extension adding AC450 controller in a new location System extensions to support new G4 generator Tanak extensions system modifications to support new equipment in Tanak location System extensions to support new G5 generator

Aswan high dam - Distributed control system AUTOMATION

Aswan high dam - Distributed control system AUTOMATION Aswan high dam - Distributed control system AUTOMATION Power System Overview Aswan High Dam (AHD) -Hydro Power Plant was erected and commissioned in 1972. At the time it was the world's greatest, as well

More information

OMAR - Power Generation AUTOMATION

OMAR - Power Generation AUTOMATION OMAR - Power Generation AUTOMATION SYRIA Power System Overview POWER GENERATION & DISTRIBUTION SYSTEM - OMAR in Al Furat oil fields - Omar, Syria Location: Gas Plant Generators: 2 Devices: 18 Large consumers:

More information

Guri Dam. Ingenuity and energy

Guri Dam. Ingenuity and energy Guri Dam Modernization of the Guri hydroelectric plant s control, protection and instrumentation system Eduardo Colmenares, Daniel Rubinstein, Miguel Florez In 2005, ABB was awarded a contract to design,

More information

B. Sc., Mechanical power science Engineering, May 1987, Monofia University. - Construction Safety Health 30 hours Administration Training by (OSHA).

B. Sc., Mechanical power science Engineering, May 1987, Monofia University. - Construction Safety Health 30 hours Administration Training by (OSHA). PM-SOM-E-0137-1987 Mechanical Commissioning Manager He is an expert in fossil fuel power generating plants operation and commissioning. He has 23 years of experience in this field (in Egypt, KSA, Syria

More information

a u t o m a t i o n : s y s t e m s - p a r t s - s e r v i c e s

a u t o m a t i o n : s y s t e m s - p a r t s - s e r v i c e s a u t o m a t i o n : s y s t e m s - p a r t s - s e r v i c e s INTEA Reference list - projects per industries 1991-2014 www.intea.hr INTEA carried out or significantly contributed the following projects:

More information

KONČAR Group. Research and Development

KONČAR Group. Research and Development production program 2 KONČAR Group KONČAR Group consists of 20 companies and has around 4000 employees. Annual sales account for more than 300 million euros, with almost half the amount in exports. KONČAR

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

UNITROL 6800 excitation systems Proven performance solutions

UNITROL 6800 excitation systems Proven performance solutions UNITROL 6800 excitation systems Proven performance solutions Setting the standard ABB is the world leading volume supplier of UNITROL automatic voltage regulators (AVR) and static excitation systems (SES)

More information

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Modular Standardized Electrical and Control Solutions for Fast Track Projects Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive

More information

Introduction worldcement.com 41

Introduction worldcement.com 41 Vietnam s largest cement production plant, the Cam Pha Cement plant of the Vietnam Construction and Import- Export Corporation (Vinaconex), has been electrified by ABB. Max Tschurtschenthaler, Project

More information

SEL Microgrid Lessons Learned

SEL Microgrid Lessons Learned SEL Microgrid Lessons Learned Will Edwards (SEL Engineering Services Division) Copyright SEL 2016 Essential Keys to Successful Microgrid Projects? Comprehensive HIL testing Subcycle fast controls Adaptive

More information

Supplement to the Histelect News No. S58 December 2014 CHINA S THREE GORGES DAM HYDRO-ELECTRIC POWER PLANT

Supplement to the Histelect News No. S58 December 2014 CHINA S THREE GORGES DAM HYDRO-ELECTRIC POWER PLANT Supplement to the Histelect News No. S58 December 2014 CHINA S THREE GORGES DAM HYDRO-ELECTRIC POWER PLANT by Peter Luxton Last September Peter Luxton went on a thirteen day tour of China, which involved

More information

Static frequency converter couples US paper mill s 25-Hz and 60-Hz electricity grids

Static frequency converter couples US paper mill s 25-Hz and 60-Hz electricity grids Static frequency converter couples US paper mill s 2-Hz and 0-Hz electricity grids Before 0 Hz was adopted as the standard frequency for electricity distribution in the USA, power companies across the

More information

production program 1

production program 1 production program 1 Končar Group Founded in 1921, KON AR nowadays consists of 19 companies and one subsidiary company, employing more than 4,000 people. Annual sales account for EUR 350 million, with

More information

Simson Haulofu Divisional Manager. NamPower Namibia

Simson Haulofu Divisional Manager. NamPower Namibia Simson Haulofu Divisional Manager NamPower Namibia Agenda Overview of Ruacana Some interesting facts about Ruacana Ruacana s contribution to Namibia Ruacana operating regime Unit 4: Business case & feasibility

More information

Electric Utility Power Systems. Generation of Electricity

Electric Utility Power Systems. Generation of Electricity Electric Utility Power Systems Generation of Electricity 1 Demand of an Electrical System The total power drawn by a customer of a large utility system fluctuates between wide limits, depending on the

More information

ELE-PT-E-2003 Senior Electrical Protection & Commissioning Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS

ELE-PT-E-2003 Senior Electrical Protection & Commissioning Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS 104660-ELE-PT-E-2003 Senior Electrical Protection & Commissioning Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has about 14 years hands-on experience in low, medium voltage and

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Substation automation for a better Baltic power supply

Substation automation for a better Baltic power supply Substation automation for a better Baltic power supply Jarmo Pöhö, Jan Skogeby Three Baltic states Estonia, Latvia and Lithuania have undertaken major upgrade projects to improve the capacity and reliability

More information

Alstom Role in the Romanian Power Industry

Alstom Role in the Romanian Power Industry Alstom Role in the Romanian Power Industry Dumitru Manea ECS Romania Location Manager March 23, 2012 Alstom Group 3 main activities in 4 sectors Thermal Power 9.7 bn 17% Grid 3.6 bn 46% 10% 27% Transport

More information

Unit C of the Scholven Power Plant Automated with System 800xA

Unit C of the Scholven Power Plant Automated with System 800xA Unit C of the Scholven Power Plant Automated with The plant Originally, the plant was intended to serve as a power generation facility supplying auxiliary power to a mine located in a Gelsenkirchen district.

More information

Control System for a Diesel Generator and UPS

Control System for a Diesel Generator and UPS Control System for a Diesel Generator and UPS I. INTRODUCTION In recent years demand in the continuity of power supply in the local distributed areas is steadily increasing. Nowadays, more and more consumers

More information

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions SYSTEM INTEGRATION Railway and urban transport electrification Energy-efficient and reliable solutions 2 R A I LWAY & U R B A N T R A N S P O R T E L E C T R I F I C AT I O N S O L U T I O N S ABB s substation

More information

HOOVER DAM MODERNIZATION PROJECT FIRST OF ITS KIND

HOOVER DAM MODERNIZATION PROJECT FIRST OF ITS KIND HOOVER DAM MODERNIZATION PROJECT FIRST OF ITS KIND By Chau Nguyen, engineering manager, Hoover Dam and Terry Bauman, senior controls engineer, L&S Electric, Inc. ABSTRACT The U.S. Department of the Interior

More information

High-current and generator switchgear from Siemens siemens.com/generatorswitchgear

High-current and generator switchgear from Siemens siemens.com/generatorswitchgear High performance for the power supply of tomorrow High-current and generator switchgear from Siemens siemens.com/generatorswitchgear Generator switchgear With matured vacuum switching technology As one

More information

Study Tour H: Dams and Energy (Post-tour) 21 to 23 May 2016

Study Tour H: Dams and Energy (Post-tour) 21 to 23 May 2016 Study Tour H: Dams and Energy (Post-tour) 21 to 23 May 2016 Introduction South Africa has various pumped storage schemes to assist in balancing electricity demand during peak periods. This tour takes you

More information

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1 Overview Gas Insulated Switchgear Modular and flexible, 52-1100kV April 17, 2009 Slide 1 Tradition and Innovation Milestones from more than 40 Years of Experience Pioneer & Leader in GIS-Technology 1956

More information

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1 Overview Gas Insulated Switchgear Modular and flexible, 52-1100kV May 15, 2013 Slide 1 Tradition and Innovation Milestones from more than 40 Years of Experience Pioneer & Leader in GIS-Technology 1956

More information

Modernization of the Rüdersdorfer cement plant a quantum leap in technology

Modernization of the Rüdersdorfer cement plant a quantum leap in technology Modernization of the Rüdersdorfer cement plant a quantum leap in technology A large-scale modernization programme undertaken by German cement producer Rüdersdorfer Zement GmbH between 1991 and 1996 has

More information

Conveying progress. ABB delivers reliable and almost maintenance-free gearless conveyor drives for high-power and high-torque applications

Conveying progress. ABB delivers reliable and almost maintenance-free gearless conveyor drives for high-power and high-torque applications Conveying progress ABB delivers reliable and almost maintenance-free gearless conveyor drives for high-power and high-torque applications MARCELO PERRUCCI With mining activities advancing into ever-remoter

More information

ABB Wind Care Service Offering

ABB Wind Care Service Offering ABB Wind Care Service Offering ABB Wind Care Service Offering ABB is the largest supplier of electrical components, systems, and services to the wind power industry. With continued investment and expansion

More information

Low voltage AC drives. ABB component drives ACS to 2.2 kw / 0.25 to 3 hp Catalog

Low voltage AC drives. ABB component drives ACS to 2.2 kw / 0.25 to 3 hp Catalog Low voltage AC drives ABB component drives ACS55 0.18 to 2.2 kw / 0.25 to 3 hp Catalog ABB component drives ABB component drives ABB component drives are designed to be incorporated into a wide variety

More information

Jiri Prochazka (BASF) & Jim Luffman (ABB), April 25, 2012 Session 12 APW C551I BASF Windsor - Harmony system evolution success to System 800xA

Jiri Prochazka (BASF) & Jim Luffman (ABB), April 25, 2012 Session 12 APW C551I BASF Windsor - Harmony system evolution success to System 800xA Jiri Prochazka (BASF) & Jim Luffman (ABB), April 25, 2012 Session 12 APW C551I BASF Windsor - Harmony system evolution success to System 800xA April 25, 2012 Slide 1 C551I BASF Windsor - Harmony system

More information

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada Making Electricity since December 2015 Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada Cambridge 1 Company Culture Vision Woodstock TMMC's goal is to maintain a

More information

Kontakt. Turnkey solutions for hydropower plants An overview of the ABB portfolio

Kontakt. Turnkey solutions for hydropower plants An overview of the ABB portfolio Kontakt Turnkey solutions for hydropower plants An overview of the ABB portfolio ABB is the world s leading provider of products and integrated solutions for power and automation technologies for hydropower

More information

ABB MEASUREMENT & ANALYTICS. Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry

ABB MEASUREMENT & ANALYTICS. Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry ABB MEASUREMENT & ANALYTICS Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry 2 P R E D I C T I V E E M I S S I O N M O N I T O R I N G S Y S T E M S M O N

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

Profile. Company Presentation. Supply details. Plants and. The Workshop. The References. Contacts and. Network

Profile. Company Presentation. Supply details. Plants and. The Workshop. The References. Contacts and. Network Company Presentation THE COMPANY AIS was founded in 2003 and its operations are in Vicenza, in the heart of the Italian northern east region, one of the most important European industrial districts.

More information

Service and Rehabilitation Electrical Power Systems

Service and Rehabilitation Electrical Power Systems Service and Rehabilitation Electrical Power Systems From water to wire 3 ANDRITZ HYDRO Electrical Power System Modernization and rehabilitation International technology group ANDRITZ is a globally leading

More information

78-EL-CS-E-1994 Senior Electrical Engineer. PERSONAL DATA Nationality : Egyptian

78-EL-CS-E-1994 Senior Electrical Engineer. PERSONAL DATA Nationality : Egyptian 78-EL-CS-E-1994 Senior Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and a Diploma of Electrical Switchgear and Protection. Has 16 years experience in construction, commissioning,

More information

Generation equipment cost in nominal $ million, at purchase price, at installed cost and % share of capex, World, 2000 to 2020

Generation equipment cost in nominal $ million, at purchase price, at installed cost and % share of capex, World, 2000 to 2020 GTD Capex and Markets Database, 2016 Ed 1, Contents of Spreadsheets Analysis of GTD Capex Generation equipment cost in nominal $ million, at purchase price, at installed cost and % share of capex, World,

More information

Alstom in South Africa

Alstom in South Africa Alstom s Presence Medupi Kusile Kriel Johannesburg Transport Gibela Factory Koeberg Key Data: Provided major equipment for 12 out of 13 South Africa s coal-fired power plants and for the only nuclear power

More information

93 MWe natural gas fired Combined Cycle Power Plant

93 MWe natural gas fired Combined Cycle Power Plant 93 MWe natural gas fired Combined Cycle Power Plant 1. Power Plant General Description This is a Combined Cycle Cogeneration Power Plant (CCCPP) located in (Milan) able to supply about 30 t/h of surplus

More information

Secure energy supply. Energy Automation for the Automotive Industry and First Tier Suppliers

Secure energy supply. Energy Automation for the Automotive Industry and First Tier Suppliers Secure energy supply for the Automotive Industry and First Tier Suppliers Electrical Power Supply for Automotive Industry Characteristics Has an effect directly on the core business Production Costs Availability

More information

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS Rachel Mueller, Mayo Clinic Timothy Coyle, PCT, Inc. Presented to: Minnesota Power

More information

ELE-MOS-E-2006 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ELE-MOS-E-2006 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 101162-ELE-MOS-E-2006 Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has over 7 years hands-on experience, mainly in operation, maintenance, commissioning and start-up.

More information

Hydroelectricity. Low-cost Green Energy for Your Industry

Hydroelectricity. Low-cost Green Energy for Your Industry Hydroelectricity Low-cost Green Energy for Your Industry February 2015 Presentation Hydro-Québec profile Environmentally friendly energy Long term security of supply Customized services Exceptionally low

More information

Derrick Boltt Southern Region Hydro Generation Eskom South Africa

Derrick Boltt Southern Region Hydro Generation Eskom South Africa Derrick Boltt Southern Region Hydro Generation Eskom South Africa Hydro Power in the S/Region. History of Hydro in the S/Region. In 198 the former Transkei government financed the development of Hydro

More information

ABB central inverters PVS to 1000 kw

ABB central inverters PVS to 1000 kw Solar inverters ABB central inverters PVS800 100 to 1000 kw ABB central inverters raise reliability, efficiency and ease of installation to new levels. The inverters are aimed at system integrators and

More information

ASSAM POWER GENERATION CORPORATION LIMITED. NOTICE INVITING TENDER

ASSAM POWER GENERATION CORPORATION LIMITED. NOTICE INVITING TENDER ASSAM POWER GENERATION CORPORATION LIMITED. NOTICE INVITING TENDER NO. APGCL/CGM (G)/CTPS/Disposal/2018-19/01. DISPOSAL OF 2X30 MW CTPS UNITS INCLUDING MAIN PLANT AND BUILDINGS. The Chief General Manager

More information

Sitras SCS, -RCI, -FFP, -TTU

Sitras SCS, -RCI, -FFP, -TTU Sitras SCS, -RCI, -FFP, -TTU control system for traction power supply Remote control interface Frame fault protection Transfer trip unit siemens.com/rail-electrification The Sitras SCS station control

More information

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets

More information

ADVISE DESIGN IMPLEMENT FOR ELECTROTECHNICAL EXCELLENCE

ADVISE DESIGN IMPLEMENT FOR ELECTROTECHNICAL EXCELLENCE ADVISE DESIGN FOR ELECTROTECHNICAL EXCELLENCE IMPLEMENT ADVISE DESIGN FOR ELECTROTECHNICAL EXCELLENCE Gemitech was founded in 1990 and, in just a few short years, grew to be recognized as medium and IMPLEMENT

More information

Measurement made easy. Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry

Measurement made easy. Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry Measurement made easy Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry ABB s Predictive Emission Monitoring Systems (PEMS) Experts in emission monitoring ABB

More information

MVDC PLUS Managing the future grid

MVDC PLUS Managing the future grid MVDC PLUS Managing the future grid Bridge the distance How should we connect Islands, platforms, and remote areas? Connecting weak or unstable grids How will we integrate and stabilize grids? Reduce footprint

More information

ABB Next Level Big shift in power attractive opportunities

ABB Next Level Big shift in power attractive opportunities Bernhard Jucker and Claudio Facchin, Capital Markets Day, London, ABB Next Level Big shift in power attractive opportunities Slide 1 Agenda Profitably growing ABB s power business Shifting the center of

More information

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. A GUIDE TO TRANSPOWER 2009 TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. Contents 01 Introduction 02 System Operator 24/7

More information

Interconnection between Arab countries

Interconnection between Arab countries Interconnection between Arab countries Eng. Fawzi Kharbat Secretary General AUE Enabling renewable energy in the electricity systems workshop 16 April 2014 Tunis 1 Arab Union of Electricity Date of Establishment:

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

بتروتك للمقاوالت PETROTEC

بتروتك للمقاوالت PETROTEC GM Message Since our beginning in 2002 we concentrate for not to be the largest but to be the best service provider in our field of interest through cooperation with high qualified expertise and implementing

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : June,

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

Critical Power: What s New in Electrical Engineering: Smart Grid and Transformers. Sponsored by:

Critical Power: What s New in Electrical Engineering: Smart Grid and Transformers. Sponsored by: Critical Power: What s New in Electrical Engineering: Smart Grid and Transformers Sponsored by: About the Viewer Panel Technical problems? Click on the HELP button Send a question from the Questions &

More information

Ampl2m. Kamil Herman Author of Ampl2m conversion tool. Who are you looking at

Ampl2m. Kamil Herman Author of Ampl2m conversion tool. Who are you looking at Who are you looking at Kamil Herman Author of conversion tool Senior automation engineer Working in Automation with ABB control systems since 1995 6 years in ABB Slovakia 2 year working for ABB Mannheim,

More information

Control & monitoring system for Siemens gas engines & gen-sets siemens.com

Control & monitoring system for Siemens gas engines & gen-sets siemens.com Siemens GCS Control & monitoring system for Siemens gas engines & gen-sets siemens.com Why Siemens engines? High performance eco-friendly engines Our commitment is to design and manufacture robust and

More information

Brochure. Modular Systems wind portfolio Power Collection and Grid Connection products

Brochure. Modular Systems wind portfolio Power Collection and Grid Connection products Brochure Modular Systems wind portfolio Power Collection and Grid Connection products Wind portfolio Background ABB is one of the few suppliers that has been deeply involved in wind power segment development,

More information

Press Release. During the third quarter of 2010/11, Alstom s order intake rose to 5.5 billion, lifted by commercial successes in emerging countries

Press Release. During the third quarter of 2010/11, Alstom s order intake rose to 5.5 billion, lifted by commercial successes in emerging countries Press Release 20 January 2011 During the third quarter of 2010/11, Alstom s order intake rose to 5.5 billion, lifted by commercial successes in emerging countries Over the third quarter 2010/11 (from 1

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

NP NLH NLH General Rate Application Page 1 of 1

NP NLH NLH General Rate Application Page 1 of 1 NP NLH 022 2013 NLH General Rate Application Page 1 of 1 1 2 3 4 5 Q. Reference: Finance Please provide detailed amortization schedules for the amortization expense for 2012, 2013 test year (provided in

More information

More power for railway lines Maximum efficiency with proven system behavior

More power for railway lines Maximum efficiency with proven system behavior TECHNOLOGY NOTE - RAIL SFC LIGHT More power for railway lines Maximum efficiency with proven system behavior For more than 40 years, ABB has been the reference in static frequency converters (SFC) for

More information

Longevity of Power Electronic Solutions in the Macro Grid historical perspective of AC (FACTS) and DC (HVDC) installations

Longevity of Power Electronic Solutions in the Macro Grid historical perspective of AC (FACTS) and DC (HVDC) installations Longevity of Power Electronic Solutions in the Macro Grid historical perspective of AC (FACTS) and DC (HVDC) installations Reginald Mendis and Neil Kirby ALSTOM Grid, Philadelphia, PA Univeristy of Pittsburgh

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

There s a new power in Solar 1500V ultra-high power string inverters for utility-scale PV applications

There s a new power in Solar 1500V ultra-high power string inverters for utility-scale PV applications PRODUCT MANAGEMENT, REV. NOVEMBER- 2018 There s a new power in Solar 1500V ultra-high power string inverters for utility-scale PV applications Andrea Genovesi, Gianluca Marri, Marco Trova [MW] Utility-scale

More information

SeaFloat SCC-A65. Technical Solution Information. Unrestricted. Vers.

SeaFloat SCC-A65. Technical Solution Information. Unrestricted. Vers. SeaFloat SCC-A65 Technical Solution Information Unrestricted Vers Version 1 www.siemens.com/seafloat Engineered for industry-leading power output and fuel savings available in SeaFloat application With

More information

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK 91 CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK CHAPTER CONTENTS: 5.1 INTRODUCTION 5.2 CONDUCTION OF VARIOUS POWER FLOW STUDIES ON THE MODEL 5.3 EXPERIMENTS CONDUCTED FOR VARIOUS POWER FLOW

More information

Decentralized Electrification of Suyuek in Xinjiang

Decentralized Electrification of Suyuek in Xinjiang Decentralized Electrification of Suyuek in Xinjiang EDF Solution for Decentralized Rural Electrification Asia Pacific Branch, EDF R&D, EDF Group CONTENT Brief introduction of EDF Activities EDF s solution

More information

Automation in Mining. Underground mining automation project Mark Yseboodt Chile November siemens.com/mining. Restricted Siemens AG 2016

Automation in Mining. Underground mining automation project Mark Yseboodt Chile November siemens.com/mining. Restricted Siemens AG 2016 Automation in Mining Underground mining automation project Chile Restricted Siemens AG 2016 siemens.com/mining Automation in Mining: Underground project Table of content Introduction 3 Block Cave 6 Deep

More information

Accelerate your grid modernization with smart RMUs. Ring main units with smart grid-ready feeder automation

Accelerate your grid modernization with smart RMUs. Ring main units with smart grid-ready feeder automation Accelerate your grid modernization with smart RMUs Ring main units with smart grid-ready feeder automation schneider-electric.com/smart-rmu Contents > Take charge of your grid evolution For deployment

More information

1x New Siemens SGT MW 50 / 60Hz (DF) Gas Turbine Mobile Generator Set

1x New Siemens SGT MW 50 / 60Hz (DF) Gas Turbine Mobile Generator Set 1x New Siemens SGT400 12.9 MW 50 / 60Hz (DF) Gas Turbine Mobile Generator Set 1. Scope of Supply Siemens Industrial Turbomachinery Ltd hereinafter Siemens offer to design,manufacture, package and despatch

More information

: Nubaria Module III - Egypt (2x250MW GE gas turbines frame 9 FA)

: Nubaria Module III - Egypt (2x250MW GE gas turbines frame 9 FA) 103956-MEC-CMOS-E-2000 Gas Turbine Maintenance Engineer Holds a B. Sc. in Mechanical Power Engineering and has over 14 years hands-on experience working in construction, maintenance, operation, commissioning

More information

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION Work Order No: File Reference: 16/2/1 This application form for the connection of small scale embedded generation is for small

More information

Integrated Solutions for LNG operations. Kongsberg Maritime

Integrated Solutions for LNG operations. Kongsberg Maritime Integrated Solutions for LNG operations Kongsberg Maritime International high-tech solutions, from deep sea to outer space Advanced solutions and applications for the maritime, oil & gas, defence and space

More information

To Integrate or Not to Integrate: That Is The Question NWHA Technical & Operations Seminar

To Integrate or Not to Integrate: That Is The Question NWHA Technical & Operations Seminar To Integrate or Not to Integrate: That Is The Question NWHA Technical & Operations Seminar Hood River, Oregon May 7-8, 2015 Automate and Integrate What? Unit Metering Start/Stop Sequences Unit Auxiliaries

More information

Product brochure. Medium voltage AC drive ACS 2000, 4kV 6.9kV HP

Product brochure. Medium voltage AC drive ACS 2000, 4kV 6.9kV HP Product brochure Medium voltage AC drive ACS 2000, 4kV 6.9kV 300-2000 HP 2 ACS 2000 brochure ABB ACS 2000 simple and reliable motor control The ACS 2000 is the latest member of the ABB medium voltage AC

More information

SECTION ROLLER WINDOW SHADES

SECTION ROLLER WINDOW SHADES SECTION ROLLER WINDOW SHADES Specifier: The Specifier/Design Professional is responsible for the accuracy of all project specifications, including system application and coordination with related sections.

More information

Smart Grid Automation and Centralized FISR

Smart Grid Automation and Centralized FISR Smart Grid Automation and Centralized FISR March 21, 2016 Mike Colby Senior Engineer Distribution Control Center Smart Grid Automation and Centralized FISR Remote Controlled Devices & Communication Distribution

More information

CATALOG. ABB micro drives ACS55, 0.18 to 2.2 kw

CATALOG. ABB micro drives ACS55, 0.18 to 2.2 kw CATALOG ABB micro drives ACS55, 0.18 to 2.2 kw 2 ABB MICRO DRIVES, ACS55, 0.18 TO 2.2 KW/0.25 TO 3 HP Ease of integration. ACS55 drives. 3 Table of contents 004 ABB micro drives, ACS55 005 Easily integrated

More information

Background information

Background information Industry Sector Background information Drive Technologies Division Nuremberg, February 13, 2014 Cement webcast A strong partner for the cement industry today and into the future Cementability reliable

More information

Precision Station Stopping Progress Update

Precision Station Stopping Progress Update Washington Metropolitan Area Transit Authority Precision Station Stopping Progress Update Presented to: The Board of Directors; Customer Service, Operations and Safety Committee By PlanninghDevelopmenthEngineeringhConstruction

More information

BULB TYPE GENERATORS.

BULB TYPE GENERATORS. BULB TYPE GENERATORS 1 Bulb Generator VA TECH is the global leader in bulb-type generators. More than 160 designed units in operation worldwide. Selected References: Ma Jin Tang (China) 3 x 20.0 MVA 75.0

More information

TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS

TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS INSTRUCTION MANUAL TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS September 2000 TOWER UPS DISTRIBUTION (PTY) LTD 1 1. INTRODUCTION T A B L E O F C O N T E N T S 1.1 General Description... 3 1.2 Features...

More information

Appendix G Examples and Recommended Methods

Appendix G Examples and Recommended Methods Reporting Outages to the Generating Availability Data System (GADS) Introduction The examples in this appendix illustrate the reporting of outages and deratings to GADS. They are based on a fictional 600

More information

Protection & Control / Commissioning Engineer

Protection & Control / Commissioning Engineer Protection & Control / Commissioning Engineer Are you ready to be a technology pioneer? Oil and gas factories 3000 meters underwater, heavy locomotive traction motors, electric vehicle chargers that deliver

More information

Low voltage AC drives. ABB micro drives ACS to 3 hp/0.18 to 2.2 kw Catalog

Low voltage AC drives. ABB micro drives ACS to 3 hp/0.18 to 2.2 kw Catalog Low voltage AC drives ABB micro drives ACS55 0.25 to 3 hp/0.18 to 2.2 kw Catalog ACS55 IP20 Overview ACS55 micro drives are designed for use in a wide variety of simple machinery applications where only

More information

ELECTRIC TRACTION.

ELECTRIC TRACTION. ELECTRIC TRACTION www.koncar.hr MODERNISATION ELECTRIC TRACTION VEHICLES Company KON AR - ELECTRIC VEHICLES Inc. upgrades electric locomotives, electric multiple unit and electric tramcars. Upgrading proceedings

More information

ABB central inverters PVS to 2000 kva

ABB central inverters PVS to 2000 kva Solar inverters ABB central inverters 1818 to 2000 kva ABB central inverters raise reliability, efficiency and ease of installation to new levels. The inverters are aimed at system integrators and end

More information

GEAR UNITS IN FOCUS. PROCESSES UNDER CONTROL.

GEAR UNITS IN FOCUS. PROCESSES UNDER CONTROL. FLENDER SERVICES GEAR UNITS IN FOCUS. PROCESSES UNDER CONTROL. DIAGNOSTEX: sensors, diagnostics, services flender.com DIAGNOSTEX Securing process stability requires condition-based maintenance of the drive

More information

Implementation of a Wide Area Monitoring System (WAMS) for Austria's Power Grid

Implementation of a Wide Area Monitoring System (WAMS) for Austria's Power Grid Implementation of a Wide Area Monitoring System (WAMS) for Austria's Power Grid Dr. Michael Weixelbraun Austrian Power Grid AG (APG) International Synchrophasor Symposium, March 22-24, 2016 1 Austrian

More information

95 MW Wartsila Natural Gas Generator Power Plant

95 MW Wartsila Natural Gas Generator Power Plant 95 MW Wartsila Natural Gas Generator Power Plant Plant comprises of (12) 8730 KW Wartsila, 20V34SG Natural Gas Engines and ABB Alternators, Fuel: Natural Gas, Year /2009, 11 KV, 50 HZ, Complete plant with

More information