Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

Size: px
Start display at page:

Download "Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer"

Transcription

1 Electrical Transmission System Analysis EE 456 project Team Members Abdulaziz Almarzouqi Hamzah Abeer Due December 14, 2012

2 Changes: MW Wind added 2. N-1 Contingency limits changed to Generator Contingency 4. Transformer Contingency 5. Updated solution o 32 Mvar CAP at bus 13 o 10 Mvar CAP at bus 5 o 10 Mvar CAP at bus 10 o New transmission from 1 to 5 o New transformer from 19 to Updated Cost Analysis 7. Cost of Electricity( Extra Credit) 2

3 8. Table of Contents Executive Summary... 4 Bas Case System... 5 System Description... 5 Lines... 5 Loads... 6 Generators... 6 Transformer... 6 System map... 7 System Outlook... 7 System Description... 7 Non-Emergency-Voltage and Current Violations... 8 N-1- Voltage and Current Violations Generator Contingency Transformer Contingency Solution Cost Analysis Government Incentives Capital Costs Running Cost Transmission Line and Capacitor Cost Overall Cost of Electricity Constraints Conclusion Appendix References

4 Executive Summary For the sake of simplicity, we have named our project Ames power system and we are assuming that the beautiful city of Ames comprise of 15 bus transmission system. In 2012, the total real power demand is 585MW and both the generators at bus 2 and 3 are operating at max 490MW, this gives -355MW at the swing bus. Generating more power than required may overheat the transmission wire and consequently damaging the system. As the excess power is not being consumed, the wastage will also reduce the overall profit margin. So to eliminate this wastage of power and for bus 1 (swing bus) to be zero, generators at bus 2 and bus 3 should operate at 299MW and 298 MW, respectively. In 2030, the real power demand increases by around 130MW. This calls for induction of more power generation capacity into the system. In our project, we have added 120.6MW Natural Gas Combined Cycle power plant and 134MW of Wind to the system in MW of Natural gas fired power plant has been installed at bus2 and Wind is added to bus 3, To fix the contingencies we have added a 32Mvar capacitor at bus Mvar Cap have been added at bus 5 and 10. A new transmission line of length 36.7 has been added from bus 1 to bus 5 to maintain the voltage level in urban area. A new transmission line of length 10.7miles has been added to induct a new transformer at bus 10. This will maintain voltage level at 69KV lines. Also, the new transformer was added because previously when one of the transformer were taken offline all the load was put on the other one causing the thermal limits to exceed the limits. As the project is being down in 2012 all the cost analysis is in current dollar value. Though, the calculated cost values might differ from other online sources because of availability of several different kinds of Natural gas power plant and transmission lines. At the end of the project, we have also calculated the amount of dollar it will require to execute the very same project in

5 1. Base Case System 1.1. System Description Ames Power System is a 15 bus transmission system and specifications of this system are as follows: Lines Conductor Ampacity The system is currently using three types of conductors, Dove, Drake, and Hawk.[1] The ampacities of these conductors are listed below( Ampacity Chart is attached at the end). o Dove: 726 A o Drake: 907 A o Hawk: 659 A Voltages All most all of the lines operate on 161kv lines except 16 and 17. 5

6 Table 1: Existing line data Loads Load data for 2012 and MW MVAR MW MVAR 'LARK' 'LARK' 'JAY' 'JAY' 'RAVEN' 'RAVEN' WREN WREN 'ROBIN' 'ROBIN' 'SISKIN' 'SISKIN' 'JUNCO' 'JUNCO' 'QUAIL' 'QUAIL' 'HERON' 'HERON' 'EGRET' 'EGRET' 'GULL' 'GULL' 'CROW' 'CROW' Total Total Total Increase from 2012 to Difference MW MVAR Increase in MW 6

7 Increase in MVAR Generators Buses 1-3 are generation buses. Bus 1 is assumed to be the swing bus. Each generator is rated at 490 MW with a minimum volt-amperes reactive limit of -100 Mvar and a maximum volt-ampere reactive limit of 250 Mvar Transformers Ames Power System contains two 69kV-161kV transformers located at the Siskin and Crow buses. It is assumed that these transformers are rated at 60 MVA in open air System Map The following shows the one line diagram of the Ames Power System. 7

8 8

9 2. System Outlook 2.1 System Description Ames will experience 1.1% load growth tell All the load calculations are in section To supply power to this increased load we are going to install 120.6MW Natural gas power plant at bus 2 and 130MW of Wind farm at bus (10% and 90% Capacity Credit) Voltage and Current Violations Non-Emergency Violations Under normal conditions, per unit voltage magnitudes at all buses should be higher than.95 pu. Also, lines, transformers, and generators must operate within their specified limits. Voltage Violations o Multiple buses were found to have voltage violations. Table 8 shows these violations. Current Violations: o No current violation Thermal Violation: o None Transformer Contingency: o Removing transformer from line causes thermal Violation at line and the following voltage violations 9

10 Wind Farm (134 MW) NEW GAS (120.6MW) N-1 Emergency Violations Under N-1 emergency conditions, per unit voltage magnitudes at all buses should be higher than.95 pu and lower than 1.05 times the normal ratings. Voltage Violations Multiple buses were found to have voltage violations. Shown in table below. 10

11 Voltage violations for N-1 emergency conditions Generator Contingency: Wind Farm Offline: No thermal voilation 11

12 New Gas Offline: No thermal voilation Bus 2 Gen offline: No thermal Voilation Bus 3 Gen Offline Line 2 to 12 close to 100% 12

13 Transformers Contingency: Removing either of the transformers causes extra load on the opposite side of the transmission line. Recommend adding new transformer from 7 to Solutions Solutions to the violations must be developed. To do this in the most cost effective way, capacitors will be added at the buses with the most voltage violations. Placing the capacitors at these buses will decrease the voltage drop and bring the buses within the acceptable limit. We have added a 32Mvar capacitor at bus Mvar Cap have been added at bus 5 and 10. A new transmission line of length 36.7 has been added from bus 1 to bus 5 to maintain the voltage level in urban area. A new transmission line of length 10.7miles has been added to induct a new transformer at bus 10. This will maintain voltage level at 69KV lines. Also, the new transformer was added because previously when one of the transformer were taken offline all the load was put on the other one causing the thermal limits to exceed the limits. 13

14 32 Mvar CAP at bus Mvar CAP at bus 5 10 Mvar CAP at bus 10 New transmission from 1 to 5 New transformer from 19 to 10 The updated one line diagram for the Ames Power System with solution 14

15 15

16 16

17 Cost Analysis: Following factors were considered while calculating the overall cost required for building a gas fired power plant: 1) Government Incentives 2) Capital cost( Capacity, Constructions, labor, Air emissions controls for coal and natural gas plants, financing) 3) Fuel Cost ( Running Costs) 4) Transmission Line and Capacitor Cost 5) Overall cost of Electricity 4.1. Government Incentives: Loans: Federal government provides loans through Department of Energy for carbon-control technologies that cover up to 80% of the cost of a project. [2]. Energy Investment Tax Credit: Tax credit is available for entities willing to invest in energy production. Only wind energy doesn t qualify for these tax credits Capital Cost: All the generating technologies are capital intensive, meaning they require a large amount of invest at the start. Natural gas fired plant cost $1200 per KW overnight cost, much less than its competitors nuclear, coal that cost around $3000 per KW on average. Construction Cost for power plants have escalated immensely during the last one decade. There has been 108% and 92% increase in capital cost for wind and gas, respectively. Predicting the future cost (2030) of setting up a power plant accurately is very important. This will give a clear comparison between gas and other generating options. We are assuming that we are going to start building the 135 MW gas power plant in Adding this much MWs will make the system good till

18 Table 1: Cost of building a NG power plant, all value are in current(2012) dollar value 4.3. Fuel Cost ( Running Costs) Cost of operation has been included in this section of the report. Table 2 show all the running (variable and fixed) costs for a simple NG plant and one with carbon control. Uncertainty of fuel cost and operation variable will be studied in next section. Table 2: Total cost of operation/year (2012) Future prediction (2030): Though it s very difficult to predict future value of a fossil fuel, considering the following factors remains constant and inflation remains constant at an average of 2.5% the capital and operation costs for setting up a NG power plant in 2030 are shown in table 4. 18

19 Table 3: Financial Assumption [[3] page 59] Table 4: Future values of capital and Running costs 4.4. Transmission Line and Capacitor Cost: All the costs values for this part is from the book. 19

20 4.5. Overall Cost of Electricity: Assuming the life of the plant to be 30 years, the cost of KWH electricity is as follows. Table 5: Cost of Electricty($/MWH) 5. Constraints: Coal is being used as a primary method to produce electricity. However, the new federal and state polices are incenting or promoting the use of natural gas to generate electricity. The following downsides of natural gas as a fuel for producing electricity are not consistent with economic policy and sound energy [4]. 1. Natural gas is more expensive fuel than coal and wind is a very close competitor. 2. Natural gas prices are highly volatile, whereas coal prices are more stable. 3. Though, North America is considered to be natural gas rich continent, there is still significant uncertainty about the amount of natural gas available at low prices. 4. The cost of developing future natural resources is expected to be much higher than current price because of the increasing labor and capital cost. 5. Using natural gas for electric power generation is going to increase the price for other sectors of industry. That will affect the economy negatively 6. Setting a natural gas plant in Ames will require significant infrastructure investment. Supporting Data: According to data from the U.S Energy Information Administration (EIA), the average cost of natural gas used in electricity generation was approximately 260 percent more expensive thab coal during the period

21 Table 6: Natural Gas VS Coal As said earlier, the price of Natural gas is much more volatile than coal. The following graph compares monthly price of natural gas and coal Table 7: Mothly price comparison 6. Conclusion The Ames Power System will now be able to support additional load until To avoid any voltage violations, a 32Mvar capacitor has been added to the system. To avoid any current violations a new generator is separately added at bus 9 instead to increasing the capacity of old generators or adding the new one at the same lines. 21

22 Appendix Ampacity Chart 22

23 References [1] A.R.Bergen, Power System Analysis: Transmission line modeling, Table D4.1.2, page 123 [2] S.Kaplan, Power plants: Characteristics and Costs, November 2008, pages 16, 17 Appendix B [3] U.S Department of Energy, Role of Alternative Energy Sources: natural gas Technology Assessment June 2012 [4] American Coalition for Clean Coal Electricity. Displacement of Coal with Natural gas to Generate Electricity, August 2012 [5] U.S Energy Information Administration, U.S. Crude Oil, Natural Gas, and NG Liquids Proved Reserves, August

EE 456 Design Project

EE 456 Design Project F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution...

More information

Electric Vehicles: Opportunities and Challenges

Electric Vehicles: Opportunities and Challenges Electric Vehicles: Opportunities and Challenges Henry Lee and Alex Clark HKS Energy Policy Seminar Nov. 13, 2017 11/13/2017 HKS Energy Policy Seminar 1 Introduction In 2011, Grant Lovellette and I wrote

More information

The Role of Nuclear Power

The Role of Nuclear Power The Role of Nuclear Power Chris Larsen Vice President, Nuclear Power June 23, 2009 Our Mission To conduct research on key issues facing the electricity sector on behalf of its members, energy stakeholders,

More information

West Virginia Energy Plan and Becoming an Electric Generator

West Virginia Energy Plan and Becoming an Electric Generator West Virginia Energy Plan and Becoming an Electric Generator June 25 th, 2013 Electricity Exports, 2010 2010 EIA Data 1 1 Costs are expressed in terms of net AC power available to the grid for the installed

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 14, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

Net Metering in Missouri

Net Metering in Missouri Net Metering in Missouri Make A Good Policy Great (AGAIN) Executive Summary More and more Americans every year are able to produce their own electricity. As the cost of solar continues to plummet, homeowners

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

CONTRIBUTION OF THE BIODIESEL INDUSTRY TO THE ECONOMY OF THE UNITED STATES

CONTRIBUTION OF THE BIODIESEL INDUSTRY TO THE ECONOMY OF THE UNITED STATES CONTRIBUTION OF THE BIODIESEL INDUSTRY TO THE ECONOMY OF THE UNITED STATES Prepared for the National Biodiesel Board With Funding Support from the United Soybean Board 1 John M. Urbanchuk Director LECG,

More information

Electric Vehicles and Solar PV A Total Cost of Ownership Approach"

Electric Vehicles and Solar PV A Total Cost of Ownership Approach Electric Vehicles and Solar A Total Cost of Ownership Approach" Makena Coffman" Associate Professor, Urban Planning" Research Fellow, UHERO" " Sherilyn Wee" PhD Candidate, Economics" RA, UHERO" " Paul

More information

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Discussing the Ratepayer Benefits of EVs On the Electrical Grid

Discussing the Ratepayer Benefits of EVs On the Electrical Grid Discussing the Ratepayer Benefits of EVs On the Electrical Grid Webinar Series on Transportation Electrification Sponsored by Edison Electric Institute and the U.S. Department of Energy Ed Kjaer, CMK Consulting

More information

Agenda. Industry Rate Trends Summary of Financial Targets Cost of Service Information. Valuation of Solar

Agenda. Industry Rate Trends Summary of Financial Targets Cost of Service Information. Valuation of Solar Agenda Industry Rate Trends Summary of Financial Targets Cost of Service Information Customer charges Residential Demand Charges Time of Use Rates Valuation of Solar Industry Trends Increasing demand charges

More information

MEDIA RELEASE. June 16, 2008 For Immediate Release

MEDIA RELEASE. June 16, 2008 For Immediate Release MEDIA RELEASE June 16, 2008 For Immediate Release Recommendations to Keep Trolleys Released Alternative Proposal for Trolleys Ensures City s Sustainability The Edmonton Trolley Coalition, a non-profit

More information

The Supply of Oil. Projections to Oil and the Macroeconomy in a Changing World Federal Reserve Bank of Boston June 9, 2010 Boston, MA

The Supply of Oil. Projections to Oil and the Macroeconomy in a Changing World Federal Reserve Bank of Boston June 9, 2010 Boston, MA The Supply of Oil Projections to 2035 Oil and the Macroeconomy in a Changing World Federal Reserve Bank of Boston June 9, 2010 Boston, MA Howard Gruenspecht, Deputy Administrator Near-term oil price uncertainty

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Building a Stronger and Smarter Electrical Energy Infrastructure. Smart Grid. A Necessary Component in the Remaking of America

Building a Stronger and Smarter Electrical Energy Infrastructure. Smart Grid. A Necessary Component in the Remaking of America Building a Stronger and Smarter Electrical Energy Infrastructure Smart Grid A Necessary Component in the Remaking of America Thomas J Gentile Chair - Energy Policy Committee IEEE-USA 2009 IEEE-USA Annual

More information

ALBERTA SOLAR MARKET OUTLOOK. CanSIA Solar West 10 May 2017

ALBERTA SOLAR MARKET OUTLOOK. CanSIA Solar West 10 May 2017 ALBERTA SOLAR MARKET OUTLOOK CanSIA Solar West 10 May 2017 Current Alberta Based Solar Programs 2 Residential and Commercial Solar Program Alberta Municipal Solar Program On-Farm Solar PV Program (Growing

More information

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E.

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E. Evaluating Losses in Electrical Equipment Focus on Transmission Utilities CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E. Contents Introduction Present Value of ongoing energy costs

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

SOLAR DISTRIBUTED GENERATION PROGRAM UPDATE

SOLAR DISTRIBUTED GENERATION PROGRAM UPDATE SOLAR DISTRIBUTED GENERATION PROGRAM UPDATE PRESENTED BY: CRIS EUGSTER ACTION: APPROVAL DATE: MAY 19, 2014 EXECUTIVE SUMMARY CPS Energy proposes to significantly expand its Solar Distributed Generation

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Electric Vehicle Cost-Benefit Analyses

Electric Vehicle Cost-Benefit Analyses Electric Vehicle Cost-Benefit Analyses Results of plug-in electric vehicle modeling in eight US states Quick Take M.J. Bradley & Associates (MJB&A) evaluated the costs and States Evaluated benefits of

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

The Case for. Business. investment. in Public Transportation

The Case for. Business. investment. in Public Transportation The Case for Business investment in Public Transportation Introduction Public transportation is an enterprise with expenditure of $55 billion in the United States. There has been a steady growth trend

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

TRANSFORMING TRANSPORTATION

TRANSFORMING TRANSPORTATION TRANSFORMING TRANSPORTATION WITH ELECTRICITY: STATE ACTION MARCH 3, 2014 KRISTY HARTMAN ENERGY POLICY SPECIALIST NCSL NCSL OVERVIEW Bipartisan organization Serves the 7,383 legislators and 30,000+ legislative

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Impact of Energy Efficiency and Demand Response on Electricity Demand

Impact of Energy Efficiency and Demand Response on Electricity Demand October 26, 2009 Impact of Energy Efficiency and Demand Response on Electricity Demand Perspectives on a Realistic United States Electric Power Generation Portfolio: 2010 to 2050 Presented by Lisa Wood

More information

NEW-VEHICLE MARKET SHARES OF CARS VERSUS LIGHT TRUCKS IN THE U.S.: RECENT TRENDS AND FUTURE OUTLOOK

NEW-VEHICLE MARKET SHARES OF CARS VERSUS LIGHT TRUCKS IN THE U.S.: RECENT TRENDS AND FUTURE OUTLOOK SWT-2017-10 JUNE 2017 NEW-VEHICLE MARKET SHARES OF CARS VERSUS LIGHT TRUCKS IN THE U.S.: RECENT TRENDS AND FUTURE OUTLOOK MICHAEL SIVAK BRANDON SCHOETTLE SUSTAINABLE WORLDWIDE TRANSPORTATION NEW-VEHICLE

More information

SOLAR ELECTRIC INVESTMENT ANALYSIS

SOLAR ELECTRIC INVESTMENT ANALYSIS PART 2: Assessing System Cost SOLAR ELECTRIC INVESTMENT ANALYSIS Eric Romich Milton Geiger Benjamin S. Rashford PHOTO: ERIC ROMICH B-1291.2 August 2016 SOLAR ELECTRIC INVESTMENT ANALYSIS PART 2: ASSESSING

More information

RNG Production for Vehicle Fuel. April 4, 2018

RNG Production for Vehicle Fuel. April 4, 2018 RNG Production for Vehicle Fuel April 4, 2018 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section

More information

Electricity Technology in a Carbon-Constrained Future

Electricity Technology in a Carbon-Constrained Future Electricity Technology in a Carbon-Constrained Future March 15, 2007 PacifiCorp Climate Working Group Bryan Hannegan Vice President - Environment EPRI Role Basic Research and Development Collaborative

More information

Additional Transit Bus Life Cycle Cost Scenarios Based on Current and Future Fuel Prices

Additional Transit Bus Life Cycle Cost Scenarios Based on Current and Future Fuel Prices U.S. Department Of Transportation Federal Transit Administration FTA-WV-26-7006.2008.1 Additional Transit Bus Life Cycle Cost Scenarios Based on Current and Future Fuel Prices Final Report Sep 2, 2008

More information

Part V Finance: Incentives and ROI

Part V Finance: Incentives and ROI Part V Finance: Incentives and ROI Financial Incentives utility rebates, tax incentives and other rebates The National Database for State Incentives for Renewable Energy - DSIRE Methods of determining

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

World on the Edge - Energy Data - Coal

World on the Edge - Energy Data - Coal World on the Edge - Energy Data - Coal Coal Consumption in Top Ten Countries and the World, 1980-2009 GRAPH: World Coal Consumption, 1980-2009 GRAPH: Coal Consumption in Selected Countries, 1980-2009 Coal

More information

The Value of Travel-Time: Estimates of the Hourly Value of Time for Vehicles in Oregon 2007

The Value of Travel-Time: Estimates of the Hourly Value of Time for Vehicles in Oregon 2007 The Value of Travel-Time: Estimates of the Hourly Value of Time for Vehicles in Oregon 2007 Oregon Department of Transportation Long Range Planning Unit June 2008 For questions contact: Denise Whitney

More information

Meeting Policy Objectives Transmission: A Path to Compliance

Meeting Policy Objectives Transmission: A Path to Compliance Meeting Policy Objectives Transmission: A Path to Compliance Rich Dewey Executive Vice President New York Independent System Operator NYISO Environmental Advisory Council Troy, NY November 20, 2015 Performance

More information

Fuel Use in Electricity Generation The changing landscape

Fuel Use in Electricity Generation The changing landscape Fuel Use in Electricity Generation The changing landscape for Bipartisan Policy Center: Understanding the New Energy Landscape June 27, 212 Washington, DC, Director, Office Electricity, Coal, Nuclear and

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

EVSE Impact on Facility Energy Use and Costs

EVSE Impact on Facility Energy Use and Costs EVSE Impact on Facility Energy Use and Costs Bhaskaran Gopalakrishnan Professor and Director of the Industrial Assessment Center Department of IMSE, Statler College West Virginia University Need to understand

More information

SUMMARY OF TOTAL CURRENT PRICES - ELECTRIC

SUMMARY OF TOTAL CURRENT PRICES - ELECTRIC Electric Summary Sheet No. S-1 HOW A CUSTOMER BILL IS CALCULATED 7 RESIDENTIAL SERVICE For a customer who used 1,000 kwh during one month (assuming 30 days of service). Schedule 7 is referred to on customer

More information

Clean Energy Policy & Procurement- Regional v. Go-It-Alone Approach

Clean Energy Policy & Procurement- Regional v. Go-It-Alone Approach Clean Energy Policy & Procurement- Regional v. Go-It-Alone Approach Dan Bosley Government Relations Executive Northeast Clean Energy Council November 17, 2016 Northeast Clean Energy Council NECEC s mission

More information

Arizona Energy Consortium Conference

Arizona Energy Consortium Conference SunZia Southwest Transmission Project SunZia and Potential Impacts of Regionalization Arizona Energy Consortium Conference SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 2018 0 SunZia: 500kV Project delivering

More information

WESTERN EIM BENEFITS REPORT Second Quarter 2018

WESTERN EIM BENEFITS REPORT Second Quarter 2018 WESTERN EIM BENEFITS REPORT Second Quarter 2018 July 31, 2018 www.westerneim.com CONTENTS EXECUTIVE SUMMARY... 3 BACKGROUND... 4 EIM BENEFITS IN Q2 2018... 4 INTER-REGIONAL TRANSFERS... 5 WHEEL THROUGH

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

Westport Innovations Inc.

Westport Innovations Inc. Energy & Environment Perspectives 2008 1 David Demers, CEO, Westport Innovations Inc. 2 Westport Innovations Inc. Recognized as the world leader in gaseous fuels technology (natural gas, hydrogen, LPG,

More information

Biennial Assessment of the Fifth Power Plan

Biennial Assessment of the Fifth Power Plan Biennial Assessment of the Fifth Power Plan Gas Turbine Power Plant Planning Assumptions October 17, 2006 Simple- and combined-cycle gas turbine power plants fuelled by natural gas are among the bulk power

More information

Michigan Public Service Commission Grid Tied Solar Photovoltaic

Michigan Public Service Commission Grid Tied Solar Photovoltaic Michigan Public Service Commission Grid Tied Solar Photovoltaic Commissioner Orjiakor N. Isiogu The Value of Grid-Connected PV Value Components Photovoltaics Energy and Generation Offset of fuel and O&M

More information

Title of presentation

Title of presentation Title of presentation Power Projects Selection, Risk, Financing & Operation by Professor Bart Nnaji Chairman & CEO ipad West Africa 2008, Abuja, NIGERIA The State of Power in Africa Installed Capacity

More information

September 21, Introduction. Environmental Protection Agency ( EPA ), National Highway Traffic Safety

September 21, Introduction. Environmental Protection Agency ( EPA ), National Highway Traffic Safety September 21, 2016 Environmental Protection Agency (EPA) National Highway Traffic Safety Administration (NHTSA) California Air Resources Board (CARB) Submitted via: www.regulations.gov and http://www.arb.ca.gov/lispub/comm2/bcsubform.php?listname=drafttar2016-ws

More information

ECE 740. Optimal Power Flow

ECE 740. Optimal Power Flow ECE 740 Optimal Power Flow 1 ED vs OPF Economic Dispatch (ED) ignores the effect the dispatch has on the loading on transmission lines and on bus voltages. OPF couples the ED calculation with power flow

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

System Reliability in Renewables-driven Power Systems. The political economy of cheap renewables in South Africa. Grové Steyn 19 April 2018

System Reliability in Renewables-driven Power Systems. The political economy of cheap renewables in South Africa. Grové Steyn 19 April 2018 System Reliability in Renewables-driven Power Systems The political economy of cheap renewables in South Africa Grové Steyn 19 April 2018 Background to the South African power system South Africa s national

More information

Machine Drive Electricity Use in the Industrial Sector

Machine Drive Electricity Use in the Industrial Sector Machine Drive Electricity Use in the Industrial Sector Brian Unruh, Energy Information Administration ABSTRACT It has been estimated that more than 60 percent of the electricity consumed in the United

More information

C PER. Center for Advanced Power Engineering Research C PER

C PER. Center for Advanced Power Engineering Research C PER Center for Advanced Power Engineering Research C PER 2017 Summer Research Planning Workshop Energy Storage Technologies and Application Roadmap Presented By: Johan Enslin Zucker Family Graduate Education

More information

New Ultra Low Sulfur Diesel fuel and new engines and vehicles with advanced emissions control systems offer significant air quality improvement.

New Ultra Low Sulfur Diesel fuel and new engines and vehicles with advanced emissions control systems offer significant air quality improvement. New Ultra Low Sulfur Diesel fuel and new engines and vehicles with advanced emissions control systems offer significant air quality improvement. The U.S. Environmental Protection Agency (EPA) has issued

More information

Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask. Gerald Deaver Manager Regional Transmission Policy

Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask. Gerald Deaver Manager Regional Transmission Policy Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask Gerald Deaver Manager Regional Transmission Policy Some Xcel Energy Statistics Transmission Business 19,000

More information

The Future of Electrification

The Future of Electrification BOSTON The Future of Electrification Opportunities and Challenges in Transitioning to an Electric Heating and Transportation Sector As a counter-narrative to the often-cited utility death spiral, the electrification

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

QUARTERLY REVIEW OF BUSINESS CONDITIONS: NEW MOTOR VEHICLE MANUFACTURING INDUSTRY / AUTOMOTIVE SECTOR: 2 ND QUARTER 2017

QUARTERLY REVIEW OF BUSINESS CONDITIONS: NEW MOTOR VEHICLE MANUFACTURING INDUSTRY / AUTOMOTIVE SECTOR: 2 ND QUARTER 2017 NATIONAL ASSOCIATION OF AUTOMOBILE MANUFACTURERS OF SOUTH AFRICA GROUND FLOOR, BUILDING F ALENTI OFFICE PARK 457 WITHERITE ROAD, THE WILLOWS, X82 PRETORIA PO BOX 40611, ARCADIA 0007 TELEPHONE: (012) 807-0152

More information

Net Metering (NEM) Credit Recommendation. June 5, 2018

Net Metering (NEM) Credit Recommendation. June 5, 2018 1 Net Metering (NEM) Credit Recommendation June 5, 2018 OVERVIEW NET METERING POLICIES 2 Thirty Eight (38) States, Washington D.C., and Four (4) Territories Offer Net Metering and utilities in two additional

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Electricity Supply Enterprise (ESE) Overview of ESE. Kyaw Hlaing Win Executive Engineer. July 2, 2013

Electricity Supply Enterprise (ESE) Overview of ESE. Kyaw Hlaing Win Executive Engineer. July 2, 2013 Mingalarba! 1 Overview of ESE July 2, 2013 Kyaw Hlaing Win Executive Engineer 2 Ministry s Profile Organization Chart of Ministry of Electric Power 3 Structure of Power Generation, Transmission and Distribution

More information

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS June 18, 2015 E2Tech Presentation AGENDA Energy storage as a grid solution high level Specific CEP project examples The technology

More information

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen

More information

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li

More information

The Hybrid and Electric Vehicles Manufacturing

The Hybrid and Electric Vehicles Manufacturing Photo courtesy Toyota Motor Sales USA Inc. According to Toyota, as of March 2013, the company had sold more than 5 million hybrid vehicles worldwide. Two million of these units were sold in the US. What

More information

Illinois Renewable Energy Portfolio Net Metering Grid Interconnection Requirements Financing Options

Illinois Renewable Energy Portfolio Net Metering Grid Interconnection Requirements Financing Options Illinois Renewable Energy Portfolio Net Metering Grid Interconnection Requirements Financing Options Effective 8-10-09, Public Act 096-0159 modified the Illinois Power Agency Act to include the Renewable

More information

Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call. November 9, 2016

Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call. November 9, 2016 Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call November 9, 2016 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of Section 27A of the

More information

PGE Sustainability Report Key Metrics FISCAL YEAR 2017

PGE Sustainability Report Key Metrics FISCAL YEAR 2017 PGE Sustainability Report Key Metrics FISCAL YEAR 2017 Data in this report is from our 2017 fiscal year (Jan. 1, 2017, to Dec. 31, 2017), unless otherwise noted. CORPORATE FACTS 2013 2014 2015 2016 2017

More information

Akinwole Omoboriowo II Chief Executive Officer(CEO) Genesis Electricity Limited(GEL) Africa

Akinwole Omoboriowo II Chief Executive Officer(CEO) Genesis Electricity Limited(GEL) Africa Akinwole Omoboriowo II Chief Executive Officer(CEO) Genesis Electricity Limited(GEL) Africa Hybrid Power Solution for Large Industrial Customers DISCUSSION TOPICS Electric power availability in Nigeria

More information

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

3.17 Energy Resources

3.17 Energy Resources 3.17 Energy Resources 3.17.1 Introduction This section characterizes energy resources, usage associated with the proposed Expo Phase 2 project, and the net energy demand associated with changes to the

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

TECHNICAL TERMS AND ABBREVIATIONS

TECHNICAL TERMS AND ABBREVIATIONS THIRD REVISED SHEET NO. 3.1 CANCELS SECOND REVISED SHEET NO. 3.1 TECHNICAL TERMS AND ABBREVIATIONS ALTERNATING CURRENT (A-C): AMPERE: BASE RATES: BRITISH THERMAL UNIT (BTU): CAPACITOR or CAPACITANCE: CAPACITY

More information

NYCA LOLE Violations (Methods D and E )

NYCA LOLE Violations (Methods D and E ) Proposals for Cost Allocation of Regulated Reliability Solutions Associated with NYCA LOLE Violations (Methods D and E ) Presented by Jerry Ancona National Grid For Discussion by NYISO Electric System

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Zero Emission Bus Impact on Infrastructure

Zero Emission Bus Impact on Infrastructure Zero Emission Bus Impact on Infrastructure California Transit Association (CTA) Fall Conference Nov 17, 2016 Russ Garwacki Director, Pricing Design & Research 626.302.6673 Russell.Garwacki@sce.com Barbara

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Renewable Fuels: Overview of market developments in the US and a focus on California

Renewable Fuels: Overview of market developments in the US and a focus on California Renewable Fuels: Overview of market developments in the US and a focus on California Cynthia Obadia Cynthia Obadia Consulting Renewable fuel s growth driven by incentives from RFS and LCFS RFS - Federal

More information

This report contains an analysis of the savings which have been achieved as a result of the installation.

This report contains an analysis of the savings which have been achieved as a result of the installation. CASE STUDY Voltage Optimisation The Balmoral Hotel, Edinburgh Introduction A study of the mains voltage profile at the hotel identified that the site was being supplied with excess voltage. Calculations

More information

In 2007, with oil at $70 per barrel, the U.S. trade deficit in petroleum products was 36% of the total of $819 billion deficit.

In 2007, with oil at $70 per barrel, the U.S. trade deficit in petroleum products was 36% of the total of $819 billion deficit. 3 In 2007, with oil at $70 per barrel, the U.S. trade deficit in petroleum products was 36% of the total of $819 billion deficit. CREATION OF ARPA-E American Recovery and Reinvestment Act of 2009 (Recovery

More information