Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Size: px
Start display at page:

Download "Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study"

Transcription

1 Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Study Performed by El Paso Electric Company System Planning Section - 1

2 I. Introduction Short Circuit Analysis with New Generation Connected to Luna 345 kv Bus On March 17, 2000, El Paso Electric Company (EPE) and XXXXXXXXXXXXXXXXXXXXX (XXXX) signed an Agreement for a Transmission and Facilities Study with regard to the construction and interconnection of MW of new generation (two gas turbines and a steam turbine in a combined cycle arrangement) at the Luna 345 kv bus. The powerflow and stability analysis of this study is being performed by EPE and will be issued under a separate cover. When generation is added to a system, the available fault current of that system increases. Therefore, a study has been performed to determine if the Southern New Mexico existing substation circuit breakers in the substations electrically near the new generation have adequate short circuit interruption duties. II. Short Circuit Study The new generation proposed by XXXX is sited near the Luna 345 kv substation and will be interconnected to the Luna 345 kv Substation bus through a 345 kv circuit of approximately 3200 feet in length consisting of 954 kcmil 45/7 ACSR Rail, 2-conductor bundles per phase. The positive sequence impedance of this line is: Z 1 = J per unit (100 MVA base) EPE determined an estimated zero sequence impedance, based on standard construction and spacing, of: Z 0 = J per unit (100 MVA base) The generators will be connected to the 345 kv transmission through two (2) 193 MVA and a 308 MVA, 18/345 kv step-up transformers, for the gas turbines and the steam turbine, respectively. The step-up transformers have impedances of 10 % on a 116 and 185 MVA for each of the gas turbine and the steam turbine step-up transformer, respectively. These impedances were modeled in the short circuit analysis as: Z(gas turbines) = J per unit (100 MVA base) Z (steam turbine) = J per unit (100 MVA base) - 2

3 The new generators have the following reactance values on the generator MVA base: Gas Turbines: X d = Direct Axis Synchronous Reactance = 1.90 per unit X d = Direct Axis Transient Reactance = per unit X d = Direct Axis Subtransient Reactance = per unit Steam Turbine: X d = Direct Axis Synchronous Reactance = 2.13 per unit X d = Direct Axis Transient Reactance = per unit X d = Direct Axis Subtransient Reactance = per unit These reactance values were converted to a 100 MVA base and used to model the new generators in the short circuit study. Maximum fault currents were then determined at the Luna 345 kv and the Luna 115 kv buses, and the substations immediately connected to Luna: Arroyo 345 kv Diablo 115 kv Mimbres 115 kv Newman 115 kv Diablo 345 kv Hidalgo 345 kv Newman 345 kv The resulting fault current was then compared to the circuit breaker interruption ratings of the breakers at each of the above mentioned substations. III. Results of the Short Circuit Analysis The circuit breakers used in the Southern New Mexico System at 345 kv and 115 kv buses vary between the substations. The following is a list of the existing circuit breakers, along with the interruption rating, at each of the pertinent substations: Breaker Breaker Interruption Substation Voltage Number Rating (Amps) Arroyo B 40, B 40, B 40,000-3

4 B 40, B 40, B 40, B 40,000 Diablo B 40, B 40, B 40,000 Hidalgo , , , ,000 Luna , , , , , , , , ,000 Newman B 40, B 40, B 40, B 40,000 Diablo B 40, B 40, B 40, B 40, B 40, B 31,500 Breaker Breaker Interruption Substation Voltage Number Rating (Amps) Luna , , ,000-4

5 Mimbres , , , , ,500 Newman , , , N , , , N , , N , , , N , , , N , , N , N , , N , N , , N , N ,000 The short circuit analysis was first performed with no new generation. This gave the base case fault duties of the circuit breakers. Then the three new generators and the modifications determined from the results of the powerflow part of the study were modeled and the short circuit study was re-run. The incremental between these two studies gave the impact of the new generators on the existing circuit breakers in the Southern New Mexico system. The short circuit (fault) currents for each case at all of the possibly impacted substations are: - 5

6 Three Phase Line to Ground: No XXXX Generators With 3 XXXX Generators Substation Faulted Fault Current (Amps) Fault Current (Amps) Arroyo 345 kv Bus 5, ,767.5 Diablo 345 kv Bus 4, ,512.0 Hidalgo 345 kv Bus 6, ,387.3 Luna 345 kv Bus 7, ,935.3 Newman 345 kv Bus 6, ,796.1 Diablo 115 kv Bus 17, ,657.9 Luna115 kv Bus 8, ,523.5 Mimbres 115 kv Bus 7, ,279.6 Newman 115 kv Bus 22, ,649.2 Single Phase Line to Ground: No XXXX Generators With 3 XXXX Generators Substation Faulted Fault Current (Amps) Fault Current (Amps) Arroyo 345 kv Bus 4, ,119.9 Diablo 345 kv Bus 4, ,362.5 Hidalgo 345kV Bus 5, ,851.3 Luna 345 kv Bus 6, ,124.9 Newman 345 kv Bus 6, ,385.8 Diablo 115 kv Bus 17, ,693.9 Luna 115 kv Bus 9, ,129.0 Mimbres 115 kv Bus 7, ,563.6 Newman 115 kv Bus 26, ,670.3 Comparing these fault currents to the appropriate existing circuit breaker interruption ratings shows that the interconnection of the new generators at the Luna 345 kv Substation, in the configuration and parameters as given by XXXX, will not cause any existing circuit breaker to operate outside its design rating. IV. Results and Conclusions A short circuit study was performed on the Southern New Mexico system comparing the maximum fault current on the system at various substations: Luna Substation (both 345 kv and 115 kv) and each substation directly connected to Luna, both with and without the three new generators proposed by XXXX. The - 6

7 results of this study show that the maximum fault current with the three new generators is less than the minimum interruption rating of any effected existing circuit breaker: Maximum Minimum Circuit Breaker Fault Current with 3 Substation Interruption Rating (Amps) New Generators (Amps) Arroyo 345 kv 40,000 5,767.9 Diablo 345 kv 40,000 5,512.0 Hidalgo 345 kv 40,000 7,387.3 Luna 345 kv 40,000 11,124.9 Newman 345 kv 40,000 8,385.8 Diablo 115 kv 31,500 19,693.9 Luna 115 kv 40,000 11,129.0 Mimbres 115 kv 17,500 8,563.6 Newman 115 kv 40,000 29,670.3 Therefore, the operation of the three new generators with the parameters as given by XXXX connected to the Luna 345 kv bus will not cause any existing circuit breaker to operate outside its interruption rating limit. - 7

8 V. Certification This Short Circuit Analysis was performed pursuant to the Agreement for a Transmission and Facilities Study, dated March 17, 2000 requested by XXXXXXXXXXXXXXXXXXXXXXXXXXXXXX. The generator, step-up transformer and new transmission line parameters were supplied by XXXXXXXXXXXXXXXXXXXXXXXXXX. The Short Circuit Analysis was performed by El Paso Electric Company. Name: Title: Dennis H. Malone Supervisor, System Planning Signature: Dennis H. Malone Company: El Paso Electric Company Date: January 10, 2001 AGREEMENT OF RESULTS: Name: Jeff Mechenbier Name: Kenneth Houston Title: Manager, Transmission Analysis Title: Director, Engineering Signature: Jeff Mechenbier Signature: Kenneth Houston Company: Public Service Company of NM Company: Texas-New Mexico Power Company Date: January 15, 2001 Date: January 10,

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 Short Circuit

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY . 120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION May 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXXXXXXXX by System Planning at El Paso Electric Company.

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY September 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXX (XXX) of XXXXXXXX by

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY 300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY El Paso Electric Company System Planning August 2006 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY...Page 1 2.0 PURPOSE...Page 7 3.0

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different

More information

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Generating Facility Interconnection Application (Application) is used to request the interconnection of a Generating Facility to Southern California

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad

Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad The Driver (TPL-001, R2.3) With apologies to Protection folks this is all about a Planner s perspective.

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Section 466.APPENIX C Levels 2 to 4 Application Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Interconnection Customer Contact Information

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

PSNH INTERCONNECTION REQUEST

PSNH INTERCONNECTION REQUEST PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.

More information

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...

More information

Request for Payment Instructions Rule 21 Export Submittal Instructions

Request for Payment Instructions Rule 21 Export Submittal Instructions Grid Interconnection & Contract Development Request for Payment Instructions Rule 21 Export Submittal Instructions Prior to submitting your application and fee or deposit, please complete and submit this

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: Alternative Contact Information

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

If any further information is required for CHELCO to fulfill its reporting requirements, please let us know.

If any further information is required for CHELCO to fulfill its reporting requirements, please let us know. c o January 20, 2009 l'v1a rk Futrell Public Utility Supervisor Florida Public Service Commission 2540 Shumard Oak Boulevard Tallahassee, Florida 32399-0850 Dear Mr. Futrell, The documents accompanying

More information

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: City: Telephone (aytime):

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

CHAPTER 4 PROTECTION REQUIREMENTS

CHAPTER 4 PROTECTION REQUIREMENTS CHAPTER 4 PROTECTION REQUIREMENTS CHAPTER 4 PROTECTION REQUIREMENTS 4.1 General Means of protection for automatic disconnection against phase and earth faults shall be provided on the customer main switch.

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Generating Facility Interconnection Application (Application) is used to request the interconnection of a Generating Facility to Southern California

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL Disclaimer (a) Purpose - This report

More information

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 APPENDIX 2B APPLICATION ELECTRICITY SERVICES APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 This application form for the connection of small scale embedded generation is for

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014 UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014 FACULTY OF SCIENCE AND ENGINEERING DEPARTMENT OF ELECTRICAL AND ELECTRONIC ENGINEERING TITLE OF PAPER: POWER SYSTEM ANALYSIS AND OPERATION COURSE

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives Texas A&M Microgrid and Electrical System Study Cushing Memorial Library & Archives Introduction of Texas A&M Microgrid Study Purpose Why are we studying the TAMU electrical system? Process How do we want

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN 2019-2028 Produced by System Planning 2018 GENERAL EL PASO ELECTRIC COMPANY 2019-2028 SYSTEM EXPANSION PLAN Executive Summary El Paso Electric Company s

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 25 kw)

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 25 kw) Generator Interconnection Application Long Form (For Use with Generators Greater than 25 kw) An applicant (Generator Owner) makes application to Delaware Electric Cooperative to install an operate a generating

More information

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Electrical Handbook Fault Calculations Using The Mva Method

Electrical Handbook Fault Calculations Using The Mva Method Electrical Handbook Fault Calculations Using The Mva Method In the power systems analysis field of electrical engineering, a per-unit system is the Calculations are simplified because quantities expressed

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale

More information

Generating unit functional document submission form

Generating unit functional document submission form Generating unit functional document submission form The below form must be completed and returned to generator.reports@aeso.ca. Supporting information to assist generating unit owners to complete this

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

Request for Payment Instructions form. Rule 21 Non-Exporting Generators Submittal Instructions

Request for Payment Instructions form. Rule 21 Non-Exporting Generators Submittal Instructions Grid Interconnection & Contract Development Request for Payment Instructions Rule 21 Non-Exporting Generators Submittal Instructions Prior to submitting your application and fee or deposit, please complete

More information

SP Distribution plc. and XXX

SP Distribution plc. and XXX SP Distribution plc and XXX AGREEMENT FOR CONNECTION TO THE DISTRIBUTION SYSTEM (Where the customer has generating plant and uses the Distribution System for selling electricity or exporting energy) AGREEMENT

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Revised Cal. P.U.C. Sheet No. 38215-E Cancelling Revised Cal. P.U.C. Sheet No. 37177-E U 39 San Francisco, California Electric Sample Form No. 79-1174 Sheet 1 Rule 21 Interconnection Application Please

More information

PREPARED DIRECT TESTIMONY

PREPARED DIRECT TESTIMONY Application No.: A.0-04- Exhibit No.: SDG&E-4 Witness: William V. Torre In the Matter of San Diego Gas & Electric Company s Application for Authorization to (1) to Participate in the Steam Generator Replacement

More information

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville

More information

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers Summary of Revision, IEEE C37.119-2016, Guide for Breaker Failure Protection of Power Circuit Breakers Kevin Donahoe GE Grid Solutions 2018 Texas A&M Protective Relaying Conference Agenda Introduction

More information

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2 BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR 1.00.00 GENERAL 1.01.00 Make : Jinan Power Equipment Factory 1.02.00 Type : WX21Z-073LLT 1.03.00 Reference Standard : GB/T7064-2002

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill) GENERATOR INTERCONNECTION APPLICATION Category 2 (Combined) For All Projects with Aggregate Generator Output of More Than 20 kw but Less Than or Equal to 150 kw Also Serves as Application for Category

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Breaker Technology Operational Advantages Development Schedule Dave Richardson, Ph.D.,P.E. Powell Power Electronic

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC

GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC Prepared by: Fred Kimsey Geno Price Roger Hurst Steve

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Performance Analysis of Transient Stability on a Power System Network

Performance Analysis of Transient Stability on a Power System Network Performance Analysis of Transient Stability on a Power System Network Ramesh B Epili 1, Dr.K.Vadirajacharya 2 Department of Electrical Engineering Dr. Babasaheb Ambedkar Technological University, Lonere

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

VOLUME III. Draft Power Purchase Agreement ADDENDUM - 2

VOLUME III. Draft Power Purchase Agreement ADDENDUM - 2 GOVERNMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA Ministry of Power and Renewable Energy Ceylon Electricity Board REQUEST FOR PROPOSALS FOR THE DEVELOPMENT OF A 300MW COMBINED CYCLE POWER PLANT

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

Request for Payment Instructions Rule 21 Non-Exporting Generators Submittal Instructions

Request for Payment Instructions Rule 21 Non-Exporting Generators Submittal Instructions Grid Interconnection & Contract Development Request for Payment Instructions Rule 21 Non-Exporting Generators Submittal Instructions Prior to submitting your application and fee or deposit, please complete

More information