Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad
|
|
- Bryan Sullivan
- 5 years ago
- Views:
Transcription
1 Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad
2 The Driver (TPL-001, R2.3) With apologies to Protection folks this is all about a Planner s perspective. And from a single utility! But to be clear Protection is the ultimate authority. Avista Planners talk to Avista Protection folks ALL THE TIME
3 Fundamental Point FERC told us to study and document short circuit analysis Why? They believed that we (Transmission Owners) had over-dutied circuit breakers in-service They were correct! We continue to be poor advocates for ourselves My take Do not fear doing more studies (full employment!) Software is more willing than we seem to be Submit the data please Data needs are modest
4 Some Observations (TPL-001-4, R2.3) Avista Discovery (oil filled breakers get rid of them) Six 230 kv breakers that are over Two 115 kv breakers that are over Actions Others Short circuit analysis are now done routinely We now spec a 253 kv class breaker for 230 kv (Type F ) Breakers are not that expensive ($109K) Foreign utility results indicate others need breaker replacements (some vocal critics had issues) FERC & NERC were right!
5 SCWG Endstate Is this just to check breaker duties? The existing WECC tools are likely adequate Talking powerflow here We can do better on the data Subtransient reactances and mutuals Do we want a single data source for coordination? Tools are up to the job (communicate our needs) Data grooming might be needed Match powerflow bus nomenclature (WECC and/or WSM) We already do this in the Northwest btw
6 Challenge the SCWG statement The software is quite capable But mapping the few to the many is fraught with peril We can easily perform short circuit duty analysis using the present WECC data formats Just need to submit mutual and check for subtransient data submissions These should come with gen testing
7 If you will indulge me What are we talking about? The ability to interrupt and extinguish the arc
8 The Basic Approach Identify the data needs Topology Buses, stations, lines, transformers, breakers, impedances, mutual coupling, etc Hmmm, this data ALL fits in our power flow software Identify the desired outcome Apply most conservative test and measure breaker fault interrupting capability against results 3 phase bus faults deemed most conservative (yes?) Document the results, replace breakers ASAP, and feed the TPL beast
9 Assumptions The short-circuit current occurs simultaneously on all three phases (no arc resistance). During the short circuit, the number of phases involved does not change, i.e. a three-phase fault remains three-phase. During the short circuit, the voltages responsible for the flow of the current and the short-circuit impedance do not change significantly. All WECC generation is statused on MW output=0 for units whose status was changed from OFF to ON.
10 Avista Data Stream Same data Planning & Protection Impedances System Data Book (test reports, etc single source) Basic Topology (same bus numbers mostly) Substation level is ok Different data Planning & Protection Protection adds buses for their own purposes These appear to be driven by software limitations Software seems to be undergoing upgrades Protection likes to equivalence at the seams With modern hardware is this even needed?
11 Existing Fault Duty Data Capabilities epc file Has everything we need for 3 phase bus faults What data might be submitted Seq file Gen record: Zgenr, Zgenx, Mbase If you have huge short circuit currents R & X are likely missing This appears to be THE place for short circuit data What data might be submitted Gen record: Zgenr, Zgenx, Mbase Clobbers power flow data Branch data Transformers, mutual, etc
12 Data Needs Subtransient reactances WECC data submission (*.epc/*.seq/*.dyd) has this In maybe three places Power flow Sequence data Transient stability Various impedances Generally power flow and sequence data Mutuals Transformers
13 PowerWorld Environment Loading sequence data, IF it is available
14 But, No *.seq data is available So just run it using the power flow data No R might want that X is submitted
15 Branch Data (just positive sequence)
16 Choose a Method (PowerWorld)
17 Various Options
18 Avista: ASPEN vs Powerworld (6 over) Circuit Breaker Rated Maximum Voltage (kv) Circuit Breaker Interrupt Capacity (ka) Aspen Short Circuit Phase Current (ka) PowerWorld Short Circuit Phase Current (ka) Flat voltages (solved voltages) % delta (14.02) -2.3% (-2.03%) (14.02) -2.3% (-2.03%) (14.02) -2.3% (-2.03%) (14.02) -2.3% (-2.03%) (14.02) -2.3% (-2.03%) (14.02) -2.3% (-2.03%) (18.79) -9.3% (-7.07%) (18.79) -9.3% (-7.07%) Powerflow programs can do short circuit fault duty. The entire fault study took 2 minutes to perform.
19 Conclusions and Questions Avista performed short circuit fault duty analysis Using ASPEN and PowerWorld for 3 phase bus faults Source data is conceptually the same ASPEN is equivalenced (unknown WECC case origin) PowerWorld is a full WECC case Missing some subtransient reactances No mutuals, no xfmer data NO seq data We found over dutied breakers replacement program is an ASAP program (50% complete) A power flow program is adequate? Yes?
20 Discussion Items Why not submit *.seq data? Missing subtransient reactances are easily found Monster short circuit values Do we need a modeling bus feature? An object that can be reduced by software to show a real vs modeling needs system Fault duty and coordination are not the same thing The topology features are the same The data used might not be
Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study
Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Study Performed by El Paso Electric Company System Planning Section - 1 I.
More informationEL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION
EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The
More informationXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 Short Circuit
More information2018 CG Transient Stability and MOD 33 Updates
2018 CG Transient Stability and MOD 33 Updates CG Planning Meeting Oct. 4, 2018 1 Transient Stability Study Updates 2 Studied Case Study performed for 2024HS case Two Colstrip units retired, with ATR model
More informationXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
More informationXXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS
XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationPJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G
PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated
More informationAQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES
AQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES 2008-2012 April 2008 Table of Contents 1.0 INTRODUCTION... 2 2.0 RESULTS... 2 2.1 CATEGORY C NO SOLVE CASES... 2 2.2 CATEGORY C
More informationWheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation
Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction
More informationTutorial. Running a Simulation If you opened one of the example files, you can be pretty sure it will run correctly out-of-the-box.
Tutorial PowerWorld is a great and powerful utility for solving power flows. As you learned in the last few lectures, solving a power system is a little different from circuit analysis. Instead of being
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationNORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress
NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com
More informationSub Regional RTEP Committee Western Region ATSI
Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these
More informationSYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company
SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This
More informationCOMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES. A Project
COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES A Project Presented to the faculty of the Department of Electrical and Electronic Engineering California State
More informationWestern Electricity Coordinating Council Modeling and Validation Work Group
Western Electricity Coordinating Council Modeling and Validation Work Group Renewable Energy Modeling Task Force Development of Planning Models dl for Solar PV Systems November 18, 2009 Phoenix, AZ Contact:
More informationFuses still the best form of overload protection
Fuses still the best form of overload protection 2001 George Moraitis (Fuseco Pty. Ltd.) Often when I visit people to talk about circuit protection I hear the comments fuses are a thing of the past and
More informationTransmission Planning using Production Cost Simulation & Power Flow Analysis
ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationSYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company
SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationImplementation of Steady-State Power System Visualizations Using PowerWorld Simulator. Dr. Jung-Uk Lim, Department of Electrical Engineering
A. Title Page Implementation of Steady-State Power System Visualizations Using PowerWorld Simulator Dr. Jung-Uk Lim, Department of Electrical Engineering B. Statement of problem researched or creative
More informationLegal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:
Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah
More informationReview paper on Fault analysis and its Limiting Techniques.
Review paper on Fault analysis and its Limiting Techniques. Milap Akbari 1, Hemal Chavda 2, Jay Chitroda 3, Neha Kothadiya 4 Guided by: - Mr.Gaurang Patel 5 ( 1234 Parul Institute of Engineering &Technology,
More information4-Day Power System Analysis, Coordination, System Studies
4-Day Power System Analysis, Coordination, System Studies Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Our
More informationImpact of Islanding and Resynchroniza?on on Distribu?on Systems
1 Impact of Islanding and Resynchroniza?on on Distribu?on Systems Authors: Dr. Vijay Sood Damanjot Singh Kush Duggal 2 Contents Introduction System Description Rural Radial Distribution System Urban Meshed
More informationMOLDED CASE CIRCUIT BREAKER BASICS. David Castor, P.E.
MOLDED CASE CIRCUIT BREAKER BASICS David Castor, P.E. History of MCCBs 1904 - Cutter Manufacturing Co., Philadelphia, produces circuit breakers. They called it the Inverse Time Element breaker, or I-T-E
More informationECE 740. Optimal Power Flow
ECE 740 Optimal Power Flow 1 ED vs OPF Economic Dispatch (ED) ignores the effect the dispatch has on the loading on transmission lines and on bus voltages. OPF couples the ED calculation with power flow
More informationSmall Generator Interconnection Program Interconnection Technical Requirements
General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator
More informationSteady-State Power System Security Analysis with PowerWorld Simulator
Steady-State Power System Security Analysis with PowerWorld Simulator S3: Techniques for Conditioning Hard-to-Solve Cases 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com
More informationDistributed Energy Resources
Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired
More informationNoxon Rapids Reactor Project. Scott Wilson June 9, 2016 Tracy Rolstad
Noxon Rapids Reactor Project Scott Wilson June 9, 2016 Tracy Rolstad Voltage Performance at Noxon (ALIS) 0.000 MW 0.000 Mvar 0.000 MW 0.000 Mvar 0.000 MW 0.000 Mvar 0.000 MW 0.000 Mvar 0.000 MW 0.000 Mvar
More informationNERC-led Review Panel Decision on the Request of City of Pasadena Water and Power
NERC-led Review Panel Decision on the Request of City of Pasadena Water and Power The North American Electric Reliability Corporation (NERC)-led Review Panel (Panel) has completed its evaluation of the
More informationNational Research Council
National Research Council The Initial Sources of Power February 28, 2013, Washington DC, USA. M. M. Adibi IRD Corporation Potomac, Maryland, USA madibird@aol.com (c) IRD 2013 1 The impact of a blackout
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements
Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner
More informationDevelopment and Operational Advantages of a Solid State Circuit Breaker with Current Limiting
Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Breaker Technology Operational Advantages Development Schedule Dave Richardson, Ph.D.,P.E. Powell Power Electronic
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationCHAPTER 4 PROTECTION REQUIREMENTS
CHAPTER 4 PROTECTION REQUIREMENTS CHAPTER 4 PROTECTION REQUIREMENTS 4.1 General Means of protection for automatic disconnection against phase and earth faults shall be provided on the customer main switch.
More information400/230 Volt 60Hz UPS Power
olt 60Hz Power Using ual Voltage standby generation and in one Nothing protects quite like Piller www.piller.com Contents 1 Abstract...3 2 Introduction...4 3 Alternative Power istribution...6 4 Integrating
More informationMechanical, Electrical, Technology Engineering Firm
Mechanical, Electrical, Technology Engineering Firm Established 1995 Current staff of forty-five Twenty engineers (12 registered P.E. s) Three Registered Communications Distribution Designers - RCDD s
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationEH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map
EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids
More informationRULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)
- (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility
More informationSafe, fast HV circuit breaker testing with DualGround technology
Safe, fast HV circuit breaker testing with DualGround technology Substation personnel safety From the earliest days of circuit breaker testing, safety of personnel has been the highest priority. The best
More informationEl Paso Electric Company
Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD
More informationAMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA
AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationComposite Load Model Sensitivity Study
Composite Load Model Sensitivity Study An Analysis of the Sensitivity of WECC Grid Planning Models to Assumptions Regarding the Composition of Loads NERC LMTF Meeting Salt Lake City, UT January 12, 2016
More informationMidway/Monument Area TTC Study
Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny
More informationA Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design
A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the
More informationPUD ELECTRIC SYSTEM INTERCONNECTION
APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures
More information: ANIMATION OF A POWER SYSTEM USING POWERWORLD SIMULATOR
2006-1767: ANIMATION OF A POWER SYSTEM USING POWERWORLD SIMULATOR Frank Pietryga, University of Pittsburgh-Johnstown FRANK W. PIETRYGA is an Assistant Professor at the University of Pittsburgh at Johnstown.
More informationATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0
ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding
More informationRequest for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP
Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and
More informationAn Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks
An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks D. M. Nobre W. L. A. Neves B. A. de Souza Departamento de Engenharia Elétrica - UFPB Av. Aprígio Veloso, 882 Bodocongó 58.109-970,
More informationInterconnection System Impact Study Final Report February 19, 2018
Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationActual CFM = VE Theoretical CFM
Here is a brief discussion of turbo sizing for a 2.0 liter engine, for example, the 3-SGTE found in the 91-95 Toyota MR2 Turbo. This discussion will compare some compressor maps from the two main suppliers
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationGENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview
Part 1 Introduction and Overview A. Applicability: This Generating Facility Interconnection Application (Application) is used to request the interconnection of a Generating Facility to Southern California
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationAdvanced Protective Relay Training
Advanced Protective Relay Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq A properly designed protection
More information2015 WDC Disturbance and Protection Standards Overview
NERC Update 2015 WDC Disturbance and Protection Standards Overview Rich Bauer Senior Manager Reliability Risk Management / Event Analysis IEEE PSRC meeting Denver, Co May 12, 2016 2 System Protection and
More informationIndustry Recommendation Loss of Solar Resources during Transmission Disturbances due to Inverter Settings - II
Loss of Solar Resources during Transmission Disturbances due to Inverter Settings - II Initial Distribution: May 1, 2018 NERC has identified adverse characteristics of inverter-based resource performance
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationReview of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST
BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January
More informationNERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016
NERC Load Modeling Activities Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 Introduction Kickoff January 2016 LMTF webpage Chair: Dmitry Kosterev,
More informationDISTRIBUTION SOLUTIONS HA Breaker Retrofit. Medium Voltage Service Marketing and Sales
DISTRIBUTION SOLUTIONS HA Breaker Retrofit Medium Voltage Service Marketing and Sales Table of contents Retrofit concept General description Technical specification Necessary details for standard retrofit
More informationMulti-megawatt power protection at medium voltage
ARTICLE Multi-megawatt power protection at medium voltage 2017 marks the introduction of ABB s revolutionary ZISC technology a next generation of medium voltage (MV) uninterruptible power supply (UPS)
More informationDual Power. Protection. Protection
54 Fault Clearing Systems by Damien Tholomier., AREVA T&D Automation, Canada Dual Power Single Battery What if it? Short circuits and other abnormal power system conditions are very rear, but may result
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationFeasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation
Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationBREAKER FAILURE PROTECTION
29 th Annual HANDS-ON RELAY SCHOOL March 12-16, 2012 BREAKER FAILURE PROTECTION Brent Carper, PE Protection & Integration Engineer brent.c@relayapplication.com OUTLINE Protection System Failures and Breaker
More informationFinal Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description
Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing
More informationConnection Engineering Study Report for AUC Application: AESO Project # 1674
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System
More informationWest Station-West Cañon 115 kv Transmission Project
West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationEVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 600 volts feeder
EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 1600A @ 600 volts feeder The schematics shows that the 1600A feeder is split in 7 branches
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationThe Role of Information Flow and Power Flow in the Smart Grid Concept
The Role of Information Flow and Power Flow in the Smart Grid Concept Dr. Uwe Kaltenborn Corporate Senior Fellow Schneider Electric AREVA Energietechnik GmbH Sachsenwerk - Medium Voltage What is a Smart
More informationProposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013
Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation
More informationShippensburg University
Shippensburg University 1871 Old Main Drive Shippensburg, PA 17257 SUPPLEMENT 1 Electrical Coordination Study Professional: Entech Engineering, Inc. 4 South Fourth Street P.O. Box 32 Reading, PA 19603
More informationSYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company
SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD
More information2015 Grid of the Future Symposium
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,
More informationDOWNLOAD OR READ : ELECTRICAL POWER SYSTEM ANALYSIS PDF EBOOK EPUB MOBI
DOWNLOAD OR READ : ELECTRICAL POWER SYSTEM ANALYSIS PDF EBOOK EPUB MOBI Page 1 Page 2 electrical power system analysis electrical power system analysis pdf electrical power system analysis write about
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationCorrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections
Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections One-Line / Riser Diagrams Drawings are not reviewed prior to submission. Because of
More informationECET Distribution System Protection. Overcurrent Protection
ECET 4520 Industrial Distribution Systems, Illumination, and the NEC Distribution System Protection Overcurrent Protection One of the most important aspects of distribution system design is system protection.
More informationTargeted Application of STATCOM Technology in the Distribution Zone
Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric
More informationPOWERWORLD SIMULATOR. University of Texas at Austin By: Mohammad Majidi Feb 2014
POWERWORLD SIMULATOR University of Texas at Austin By: Mohammad Majidi Feb 2014 AGENDA Contingency Analysis OPF SCOPF Examples 2 START CONTINGENCY ANALYSIS Open case B7SCOPF from the Program Files/PowerWorld/Simulator/Sample
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More information