Maine Turnpike Authority

Size: px
Start display at page:

Download "Maine Turnpike Authority"

Transcription

1 York Toll Plaza Mile Clearing AC Removing Existing Manhole or Catch Basin EA Abandoning Existing Manhole or Catch Basin EA Removing Existing Pipe LF Abandoning Existing Pipe LF Removing Pavement Surface 88, SY Rumble Strips - Shoulder 35, LF Removing Rumble Strips 6, LF Abandon Monitoring Well 2.00 EA Common Excavation 128, CY Rock Excavation 47, CY Presplitting Rock LF Drilling and Blasting of Solid Rock Subgrade 5, SY Clay Borrow CY Granular Borrow 7, CY Crushed Stone Fill 3/4-Inch CY Widening of Existing Shoulder, Plan Quantity SY Structural Rock Excavation - Drainage & Minor Structures 3, CY Structural Earth Excavation - Major Structures, Plan Quantity 2, CY Structural Rock Excavation - Major Structures 1, CY Aggregate Subbase Course-Gravel 115, CY Aggregate Base Course - Type A 26, CY Aggregate Base Course - Type B CY Hot Mix Asphalt, 19.0 mm Nominal Maximum Size 39, T Hot Mix Asphalt, 12.5 mm Nominal Maximum Size T Hot Mix Asphalt mm Nominal Maximum Size (Polymer Modified) 14, T Hot Mix Asphalt 9.5 mm Nominal Maximum Size (sidewalks, drives, islands & incidentals) T Hot Mix Asphalt (Shim) 11, T Hot Mix Asphalt 12.5 mm Nominal Maximum Size (Binder) 14, T Bituminous Tack Coat - Applied 17, G Saw Cutting Bituminous Pavement 3, LF Structural Concrete, Space Frame and Overhead Sign Structure Pedestals CY Structural Concrete, Canopy Column Foundations CY Structural Concrete, ORT Slabs CY Structural Concrete, Plaza Structural Slabs CY Structural Concrete, Toll Islands CY Page 1 of 10

2 Structural Concrete, Utility Pits CY Structural Concrete, CCTV Pole Foundations CY Structural Concrete, Rigid Frame Structures [Tunnel] CY Epoxy-Coated Reinforcing Steel, Fabricated and Delivered 136, LB Epoxy-Coated Reinforcing Steel, Placing 136, LB Glass Fiber Reinforced Polymer (GFRP) Reinforcing Bars, Fabricated and Delivered 48, LB Glass Fiber Reinforced Polymer (GFRP) Reinforcing Bars, Placing 48, LB Synthetic Fiber Reinforcement 2, LB Space Frame Canopies, Fabricated and Delivered 1.00 LS Space Frame Canopies, Erection 1.00 LS Space Frame Steel Support Posts and Anchorage Assemblies 1.00 LS Mounting Bracket Assemblies 1.00 LS Shop Coating of New Steel 1.00 LS Galvanizing 1.00 LS High Performance Waterproofing Membrane 1, SY Membrane Waterproofing 1.00 LS Temporary Earth Support Systems 1.00 LS Pigmented Concrete Protective Coating - Tunnel Walls & Ceiling 1, SY Pigmented Concrete Protective Coating - Tunnel Floor SY Clear Protective Coating for Concrete Surfaces 1, SY Epoxy Overlay SY Temporary Concrete Barrier Type I - Supplied by the Authority 1.00 LS Median Barrier Type I -Precast 7, LF Median Barrier Type IA - Precast 1, LF Median Barrier Type IB - Precast LF Median Barrier Type II - Precast LF Median Barrier Type II - Cast in Place LF Median Barrier Type IIIA - Precast LF Median Barrier Type IIIB - Precast LF Median Barrier Transition Type I - Precast 4.00 EA Median Barrier Transition Type IA - Precast 2.00 EA Median Barrier Transition Type IB - Precast 2.00 EA Median Barrier Transition Type LP-A 8.00 EA Median Barrier Transition Type LP-B EA Median Barrier Transition Type II - Precast EA Median Barrier With Mounted Light Pole Type LP-A - Cast in Place 4.00 EA Median Barrier With Mounted Light Pole Type LP-B - Cast in Place 5.00 EA Page 2 of 10

3 Center Barrier Crash Attenuator 2.00 EA Work Zone Crash Cushions - TL UNIT Precast Concrete Tunnel and Tunnel Staircase Structures 1.00 LS Inch Reinforced Concrete Pipe - Class III LF Inch Culvert Pipe Option III LF Inch Reinforced Concrete Pipe - Class III 2, LF Inch Culvert Pipe Option III LF Inch Reinforced Concrete Pipe - Class III LF Inch Culvert Pipe Option III LF Inch Culvert Pipe Option III LF Inch Reinforced Concrete Pipe - Class III LF Inch Reinforced Concrete Pipe - Class III LF Inch Reinforced Concrete Pipe - Class V LF Concrete Collar for Reinforced Concrete Pipe EA Inch Ductile Iron Storm Drain LF Catch Basin Type B EA Catch Basin Type B1 with Flat Top EA Inch Manhole 7.00 EA Inch Outlet Control Structure 5.00 EA Inch Doghouse Manhole 1.00 EA Inlet Control Structure 1.00 EA Catch Basin Type B EA Inch Underdrain Type B 1, LF Inch Underdrain Outlet LF Inch Underdrain Type C 1, LF W-Beam Guardrail Mid-way Splice 5, LF Bridge Transition - Type III Modified 2.00 EA Terminal End - Anchored End EA Terminal End - Anchored End, Thrie Beam 2.00 EA Reflectorized Beam Guardrail Delineator 9.00 EA Reflectorized Flexible Guardrail Marker EA Underdrain Delineator Post EA Delineator Post - Remove and Stack EA Guardrail - Remove, Modify, and Reset, Single Rail LF Guardrail - Remove, Modify, and Reset Thrie Beam, Single Rail LF Guardrail - Remove, Modify, and Reset Thrie Beam, Double Rail LF Page 3 of 10

4 Guardrail - Remove and Stack or Dispose 10, LF Single Galvanized Steel Post EA Gr - Thrie Beam - Dbl Rail LF Gr - Thrie Beam - Sgl Rail LF Widen Shoulder for Energy Absorbing End Terminal EA Guardrail Flared Terminal 31 W-Beam Guardrail (7 Steel Posts, 8 Offset Blocks, Single Faced) EA Right of Way Fencing with Habitat Barrier Fence, Metal Posts 15, LF Pipe Entry Gate 1.00 EA Chain Link Fence - 3' High LF Post Assembly for Sign or Chain Link Fence EA Dumpster Enclosure 1.00 LS Reinforced Concrete Sidewalk/Site Concrete Slabs SY Curb Ramp Detectable Warning Field SF Vertical Curb Type 1 1, LF Vertical Curb Type 1 - Circular LF Terminal Curb Type 1-8' 8.00 EA Stone Fill CY Plain Riprap CY Temporary Stone Check Dam CY Permanent Stone Check Dam CY Erosion Control Blanket 40, SY Loam 14, CY Seeding Method Number UN Seeding Method Number UN Mulch UN Temporary Mulch 1.00 LS Bark Mulch CY Drainage Geotextile SY Erosion Control Geotextile 14, SY Evergreen Tree (5'-6') Group GP A 8.00 EA Large Deciduous Tree (4" Cal) GP A 1.00 EA Deciduous Shrub (No. 3 Cont) GP A EA " Copper Tubing LF " Non-Metallic Pipe Sleeve LF " Non-Metallic Pipe LF Barrier Junction Box EA Page 4 of 10

5 'x4' Splice Box EA Quazite Junction Box (36x24) EA Primary Electric Manholes (CMP) 6.00 EA Non-Metallic Conduit 22, LF " Non-Metallic Conduit, Concrete Encased 6, LF " Non-Metallic Conduit, Concrete Encased 6, LF inch Diameter Drilled Shaft LF Inch Diameter Drilled Shaft - Rock Socket LF Light Standard Foundation EA " Solid White Pavement Marking 10, LF Pref Pave Mark Tape Line, Groove Install 2, SF Temporary 6 Inch Painted Pavement Marking Line -Yellow or White 140, LF " White Pavement Marking Line 1, LF Temporary 6 Inch Black Pavement Marking Tape 2, LF " White or Yellow Painted Pavement Marking Line 50, LF White or Yellow Pavement & Curb Marking SF Remove Existing Pavement Marking 3, SF Temporary 6 Inch Pavement Marking Tape 3, LF Temporary Raised Pavement Markers EA Pavement Marking Symbol 9.00 EA Pavement Marking Tape 2, LF Hand Labor, Straight Time HR Air Compressor (Inc Operator) HR Air Tool (Inc Operator) HR Jackhammer (Inc Operator) HR All Purpose Excavator (Inc Operator) HR Truck - Small (Including Operator) HR Chain Saw Rental (Inc Operator) HR Culvert Cleaner (Inc Operator) HR Foreperson HR Bucket Truck HR Scissor Lift HR Electrician HR Electrician's Apprentice HR Propane Service Line LF Highway Lighting 1.00 LS Conventional Light Standard with LED Fixture EA Page 5 of 10

6 Sign Light EA Field Office Type A 1.00 EA Field Office Type B 1.00 EA Aluminum Flag Pole 1.00 EA Flashing Beacon - Solar Powered 4.00 EA Lane Use Signal 9.00 EA Remove and Stack Sign EA Remove and Stack Ground Mount Guide Sign and Structure 4.00 EA Remove and Reset Sign 3.00 EA Canopy Mounted Dynamic Message Sign 1.00 EA Overhead Guide Sign 1 (Sta ) 1.00 LS Overhead Guide Sign 2 (Sta ) 1.00 LS Overhead Guide Sign 3 (Sta ) 1.00 LS Overhead Guide Sign 4 (Sta ) 1.00 LS Overhead Guide Sign 5 (Sta ) 1.00 LS Overhead Guide Sign 6 (Sta ) 1.00 LS Overhead Guide Sign 7 (Sta ) 1.00 LS Overhead Guide Sign 8 (Sta ) 1.00 LS Canopy Mounted Sign 7.00 EA Canopy Mounted DMS Remove and Reset 1.00 EA Variable Speed Limit Sign 2.00 EA Roadside Guide Signs, Type I 1, SF Regulatory, Warning, Confirmation and Route Assembly Sign, Type I SF Wood Post EA Steel H-Beam Poles 13, LB Remove and Reset Mainline Sign LS Remove and Reset Mainline Sign LS Remove and Reset Mainline Sign LS Flashing Arrow Board 6.00 EA Type III Barricade EA Drum EA Cone EA Construction Signs 1, SF Maintenance of Traffic Control Devices 1.00 LS Flagger HR Portable-Changeable Message Sign 5.00 EA Truck Mounted Attenuator CD Page 6 of 10

7 Automated Trailer Mounted Speed Limit Sign 2.00 EA Temporary Barrier 1.00 LS Installation of ORT Lane Controller Cabinet 2.00 EA Installation of Cash Lane Controller Cabinet 9.00 EA DVAS Mount Installation EA VCARS Mount Installation EA Installation of Sensor Loops 1.00 LS Installation of AVI Antennas EA Installation of AVI Readers 6.00 EA Traffic Control Pedestal Preparation Work 9.00 EA OPUS Mount Installation EA Armored Cable - 10/ LF #2/0 AWG Wire 1, LF #1/0 AWG Wire 1, LF #3/0 AWG Wire 3, LF #1 AWG Wire 5, LF #2 AWG Wire 1, LF #4 AWG Wire LF #6 AWG Wire LF #10 AWG Wire 4, LF #12 AWG Wire 80, LF #14 AWG Wire 1, LF pr/24 (Category 5e) Cable 44, LF LMR 400 Cable 1, LF Fiber Optic Cable 6 Fiber 3, LF IVIS Homerun Loop Cable (IMSA 50-2 #14) 11, LF /2" Schedule 40 PVC Conduit LF /4" Schedule 40 PVC Conduit LF " Schedule 40 PVC Conduit LF " Schedule 40 PVC Conduit LF " Schedule 40 PVC Conduit LF " Schedule 40 PVC Conduit LF " Schedule 80 PVC Conduit LF /2" Schedule 80 PVC Conduit 1, LF " Schedule 80 PVC Conduit LF " Schedule 80 PVC Conduit 3, LF " Schedule 80 PVC Conduit LF Page 7 of 10

8 " Schedule 80 PVC Conduit LF " Schedule 80 PVC Conduit LF " Galvanized Rigid Metal Conduit LF /4" Galvanized Rigid Metal Conduit LF /2" Galvanized Rigid Metal Conduit LF " Galvanized Rigid Metal Conduit LF " Galvanized Rigid Metal Conduit 1, LF /2" Liquid Tight Metallic Flexible Conduit LF /4" Liquid Tight Metallic Flexible Conduit LF /2" Liquid Tight Metallic Flexible Conduit LF " Liquid Tight Metallic Flexible Conduit LF " Liquid Tight Metallic Flexible Conduit LF /2" Electrical Metallic Tubing Conduit LF " Electrical Metallic Tubing Conduit LF " Electrical Metallic Tubing Conduit LF " Electrical Metallic Tubing Conduit LF " Electrical Metallic Tubing Conduit LF /4" Electrical Metallic Tubing Conduit LF Type A Pull Box Inside EA Type C Pull Box in Tunnel/Booth Pit EA Type D Pull Box Outdoor Canopy 4.00 EA Type E Pull Box Steel in Booth EA Type F Pull Box Outside EA " x 12" x 6" Galvanized Junction Box EA " x 18" x 6" Galvanized Junction Box 8.00 EA " x 24" x 12" Junction Box 6.00 EA " x 30" x 20" NEMA 4X Cabinet 6.00 EA AMP 3 Phase Panelboard Cabinet 4.00 EA AMP 3 Phase Panelboard Cabinets 4.00 EA " PVC Conduit Condulets EA " PVC Conduit Condulets EA /4" Rigid Metal Conduit Condulets EA " Rigid Metal Conduit Condulets EA ½" Rigid Metal Conduit Condulets EA " Rigid Metal Conduit Condulets EA " Electrical Metal Tubing Condulets EA " Electrical Metal Tubing Condulets EA Page 8 of 10

9 /2" Electrical Metal Tubing Condulets EA /4" Electrical Metal Tubing Condulets EA " Electrical Metal Tubing Condulets EA inch x 4-inch PVC NEMA 3R Wireway LF inch x 6-inch PVC NEMA 3R Wireway LF inch x 8-inch PVC NEMA 3R Wireway LF inch x 12-inch PVC NEMA 3R Wireway LF Concrete Encased Conduit CY Lightning Suppression System 1.00 LS Key Switch EA Duplex Receptacle EA NEMA L5-30R Receptacle 6.00 EA Quadplex Receptacle EA Space Frame Lighting 1.00 LS LED Canopy Light Fixture EA Toll Booth Electrical Installation 1.00 LS LED Bumper Beacon 9.00 EA Baled Hay, In Place EA Temporary Berms LF Temporary Slope Drains LF " Temporary Silt Fence 24, LF Mobilization 1.00 LS Communications 1.00 LS Toll Administration Building 1.00 LS HVAC Tunnel and Booths 1.00 LS Tunnel and Toll Stairway Lighting, Fire Alarm, and House Power 1.00 LS Toll Administration Building Standby Generator 1.00 LS Tunnel Stair Enclosures 1.00 LS Tunnel Access Hatch 1.00 LS Southbound and Northbound Plaza Canopies 1.00 LS Metal Stairs at Tunnel Staircases 1.00 LS New Toll Booth Installation 1.00 LS Radon Mitigation System 1.00 LS Test Pits 2.00 EA Inch Force Main LF " PVC Sanitary Sewer (SDR-35) LF Subsurface Wasterwater Leach Field With Geotextile Sand Filter (GSF) 1.00 LS Page 9 of 10

10 Gallon Precast Septic Tank with Pump 1.00 LS " Ductile Iron Pipe 1, LF Water Meter Pit 1.00 LS " Air Release Valve 1.00 EA " Gate Valve 2.00 EA Type A Steel Site Bollard 9.00 EA Page 10 of 10

Maine Turnpike Authority

Maine Turnpike Authority Interchange 44 Barrier Toll Plaza Open Road Tolling Conversion Mile 44.3 201.11 CLEARING 3.50 AC 202.071 REMOVING ASBESTOS CONTAINING MATERIALS, TOLL BOOTH LAB TOPS 1.00 LS 202.081 REMOVING EXISTING BUILDING

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount Sargent Corporation - Stillwater, ME $29,888,765.79 Reed & Reed, Inc. - Woolwich, ME $34,900,974.90 Page 1 of 25 Sargent Corporation Stillwater, ME 201.11 CLEARING AC 4.00

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount R J Grondin & Sons - Gorham, ME $1,436,720.00 Shaw Brothers Construction, Inc. - Gorham, ME $1,476,398.83 Pratt & Sons, Inc. - Minot, ME $1,733,615.00 Page 1 of 13 R J Grondin

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount Shaw Brothers Construction, Inc. - Gorham, ME $659,771.50 R J Grondin & Sons - Gorham, ME $690,828.50 Gendron & Gendron - Lewiston, ME $753,187.00 Gordon Contracting - Sangerville,

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount CPM Constructors - Freeport, ME $1,309,765.25 Scott Construction Corporation - Portland, ME $1,528,840.00 Wyman & Simpson Inc. - Richmond, ME $1,674,845.00 Page 1 of 10 CPM

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount Liddell Brothers, Inc. - Halifax, MA $1,590,213.00 Northeast Traffic Control Services, Inc. - Plymouth, MA $1,932,117.00 Page 1 of 5 Liddell Brothers, Inc. Halifax, MA 202.2061

More information

Project Book Worksheet for Cost Estimation

Project Book Worksheet for Cost Estimation 001.01 MOBILIZATION LS $34,716.18 007 3/17/2039 001.02 INCIDENTAL LS $23,929.43 019 3/17/2039 001.03 CONSTRUCTION STAKING LS $10,504.39 201 5/9/2013 001.04 REESTABLISH PROPERTY CORNERS EA $496.08 201 5/9/2013

More information

MoDOT 2016 UNIT BID PRICES Northwest District

MoDOT 2016 UNIT BID PRICES Northwest District MoDOT 2016 UNIT BID PRICES Northwest District 2013000 CLEARING AND GRUBBING ACRE 7.95 20 1926.49132 20000 1 159 2022010 REMOVAL OF IMPROVEMENTS L.S. 1.00 56 24479.13304 201719 750 56 2024043 REMOVAL OF

More information

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity 202-00019 Removal of Inlet 15 EA 202-00035 Removal of Pipe 121 LF 202-00200 Removal of Sidewalk 1,057 SY 202-00203 Removal of Curb and Gutter 2,142 LF 202-00206 Removal of Concrete Curb Ramp 320 SY 202-00207

More information

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Engineering Division PROJECT NO INCA STREET MULTI-USE PATH 38 TH AVE. TO 43 RD AVE.

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Engineering Division PROJECT NO INCA STREET MULTI-USE PATH 38 TH AVE. TO 43 RD AVE. 201-00000 Clearing and Grubbing 1 LS 202-00010 Removal of Tree 9 EA 202-00019 Removal of Inlet 8 EA 202-00034 Removal of Pipe (6 Inch) 196 LF 202-00035 Removal of Pipe (18 Inch) 10 LF 202-00036 Removal

More information

Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director

Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director Ohio Department of Transportation Official Bid Tabulation Jolene M. Molitoris, Director Project No. 100281 PID 77255 LUC-IR-475-14.18 Federal Type: MAJOR RECONSTRUCTION Letting Date: 6/3/2010 Completion

More information

Steese Rd - Curb & Sidewalk Improvement

Steese Rd - Curb & Sidewalk Improvement REF. NO. ITEM NO. Steese Rd - Curb & Sidewalk Improvement DESCRIPTION QTY UNITS UNIT COST SUB-TOTAL 1 103.05 Requirement of Contract Bid 1 LS 24,048.00 24,048.00 2 201 Clearing and Grubbing 1 LS 11,077.00

More information

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 05/01/00 PAGE : 1 TABULATION OF BIDS

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 05/01/00 PAGE : 1 TABULATION OF BIDS PAGE : 1 CONTRACT DESCRIPTION : MILL & OVERLAY, GRADING, BIT SURFACING, BR NO 02038 ETC CONTRACT LOCATION: LOCATED ON TH 47 FROM 153RD AVE NW IN RAMSEY TO 180TH LANE NW AND AT FORD BROOK IN BURNS TOWNSHIP

More information

HILLS MATERIALS COMPANY UNIT COST TOTAL COST UNIT COST TOTAL COST UNIT COST $294, $294, $74, $74, $35, $35,000.

HILLS MATERIALS COMPANY UNIT COST TOTAL COST UNIT COST TOTAL COST UNIT COST $294, $294, $74, $74, $35, $35,000. PROJECT NAME: Anamosa Street Reconstruction - Midway Street to Miiwuakee Street PROJECT NUMBER: PROJECT NO. 07-1473 / CIP NO. 50559 LET DATE: April 11, 2017 LOW BID AMOUNT: $3,941,397.20 ENGINEER'S ESTIMATE

More information

METRO Magnolia Transit Center - Bid Tab

METRO Magnolia Transit Center - Bid Tab Section A - GENERAL ITEMS A-1 01505 Mobilization LS 1 $ 100,000.00 $ 100,000.00 A-2 -- Payment and Performance Bonds LS 1 A-3 01310 Document Control LS 1 A-4 01311 CPM Schedule LS 1 A-5 01590 Engineer's

More information

ALABAMA DEPARTMENT OF TRANSPORTATION DATE : 06/14/13 PAGE : VENDOR RANKING

ALABAMA DEPARTMENT OF TRANSPORTATION DATE : 06/14/13 PAGE : VENDOR RANKING PAGE : 001-1 VENDOR RANKING CONTRACT TIME : 09/01/13 COMPLETION DATE CONTRACT DESCRIPTION : PROJECT(S) : IM-I059(370) for constructing the Ramp Widening and Auxiliary Lane (Grade, Drain, Base, Pave and

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 140123 PID 82645 LOR- SR 0057 19.42 Federal Type: INTERCHANGE Letting Date: 4/17/2014 Completion Date: 7/15/2016

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 110146 PID 82278 HAM-IR-75-5.58 Federal Type: INTERCHANGE Letting Date: 5/5/2011 Completion Date: 7/31/2014 Contract

More information

McCRORY & WILLIAMS, INC. HILLCREST ROAD CONNECTOR MCR ROADWAY ITEMS

McCRORY & WILLIAMS, INC. HILLCREST ROAD CONNECTOR MCR ROADWAY ITEMS BID TABULATION Hillcrest Road Connector John G. Walton Construction M. C. Williams Contracting Hosea. Weaver & Sons, Inc. BID OPENING: March 25, 29 Company, Inc. Company, Inc. QTY DESCRIPTION DOLLARSjCTS

More information

Macomb County Department of Roads Bid Comparison

Macomb County Department of Roads Bid Comparison Macomb County Department of Roads Bid Comparison Contract ID: 1643 Description: M-53 Freeway to 33 Mile Road Connector to the proposed 33 Mile Road & McKay Road Roundabout Location: Projects(s): M-53 &

More information

2017 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR ENGLISH (10)

2017 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR ENGLISH (10) 106.05100 FIELD LABORATORY EA 33 33.00 $12,605.17 201.03201 CLEARING AND GRUBBING ACRE 2 76.00 $1,269.74 201.03206 CLEARING TREES 6 in EA 1 53.00 $122.27 201.03210 CLEARING TREES 10 in EA 3 66.00 $227.33

More information

CT Consultants, Inc.

CT Consultants, Inc. Cost 1 202 AHRESTY DRIVE REMOVAL 1 LS 2 202 EXISTING SILO DEMOLISHED AND REMOVED, AS PER PLAN 1 LS 3 203 EXCAVATION (NOT INCLUDING UNDERCUT) 2,372 CY 4 203 EMBANKMENT 3,306 CY 5 204 PROOF ROLLING 10 HRS

More information

2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH

2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH Page 1 2015 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2015 ENGLISH ITEM ITEM DESCRIPTION UNITS N TOTAL QUANTITY AVERAGE PRICE 106.05100 FIELD LABORATORY

More information

2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH

2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH Page 1 2016 WEIGHTED AVERAGE BID PRICES WYOMING DEPARTMENT OF TRANSPORTATION AVERAGE UNIT BID PRICES FOR 2016 ENGLISH ITEM ITEM DESCRIPTION UNITS N TOTAL QUANTITY AVERAGE PRICE 106.05100 FIELD LABORATORY

More information

BIDDER'S PROPOSAL (continued) CITY OF BERKELEY BID PROPOSAL ITEM NO. A: BASE BID

BIDDER'S PROPOSAL (continued) CITY OF BERKELEY BID PROPOSAL ITEM NO. A: BASE BID SPECIFICATION 16-11031-C CITY OF BERKELEY BID PROPOSAL A: BASE BID 1 MOBILIZATION 1 LS 2 TRAFFIC CONTROL 1 LS 3 CONTRACTOR INFORMATION SIGN 2 EA 4 CONSTRUCTION AREA SIGN 18 EA 5 PROJECT IDENTIFICATION

More information

Fertilizer Type B 2 CWT $ $ $60.00 $ $60.00 $ Sod Water 60 MGAL $60.60 $3, $30.00 $1, $30.00 $1,

Fertilizer Type B 2 CWT $ $ $60.00 $ $60.00 $ Sod Water 60 MGAL $60.60 $3, $30.00 $1, $30.00 $1, BID TABS PROJECT 18-1029 22 nd AVENUE RECONSTRUCTION BID DATE: MAY 9, 2018 Stark Pavement Corp. Lalonde Contractors Cornerstone Pavers LLC Brookfield, WI Waukesha, WI Racine, WI Item Number Roadway Quantity

More information

BID ITEM ESTIMATED UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. QUANTITY UNIT ITEM COST COST COST COST COST COST

BID ITEM ESTIMATED UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. QUANTITY UNIT ITEM COST COST COST COST COST COST PAGE 1 BID OPENING: AUGUST 11, 2011 ENGINEER'S ESTIMATE: $3,108,320.60 CONTRACT NO.110269 SABINO CANYON AND TANQUE VERDE INTERSECTION IMPROVEMENTS *FOR A MORE DETAILED ITEM DESCRIPTION* *REFER TO PROPOSAL

More information

(1 ) Active Construction Inc River Road East Tacoma, WA AMOUNT , , ,

(1 ) Active Construction Inc River Road East Tacoma, WA AMOUNT , , , 78th Avenue Eastl184th Street EastlCRP 5661 I hereby certify this to be a true copy of the tabulation of the bids as received and opened. BID OPENING: FRIDAY, March 3, 2017 County Engine (1 ) Active Construction

More information

Franklin County Engineer's Office - Highway Design ALKIRE RD & DEMOREST RD ROUNDABOUT CR NO. 11 & CR NO. 25 Bid Tabulation

Franklin County Engineer's Office - Highway Design ALKIRE RD & DEMOREST RD ROUNDABOUT CR NO. 11 & CR NO. 25 Bid Tabulation 7/07/2015 Page 1 of 20 Strawser Paving Co., Inc. Shelly & Sands, Inc. Double Z Construction Co Columbus Asphalt Paving, Inc. 1595 Frank Road P.O.Box 2469 2550 Harrison Road 1196 Technology Dr Columbus,

More information

McCRORY & WILIJAMS, INC. PROJECT NO. MCR-2008-OO1

McCRORY & WILIJAMS, INC. PROJECT NO. MCR-2008-OO1 McCRORY & WILIJAMS, INC. THEODORE DAWES ROADISCHILLINGER ROAD SOUTH BID TABULATION: Theodore DaweslSchillingor Road PROJECT NO.: M5700-2033 BIDDER #1 BIDDER #2 BIDDER #3 Hosea 0. Weaver & Sons, Inc. John

More information

Federal Project No.: OC-095-1(348)

Federal Project No.: OC-095-1(348) Order : N83 Schedule of Items Page: 2 Oversight/State Project : (NFO)0095-127-857, C501 Federal Project : OC-095-1(348) 0010 513 00100 MOBILIZATION LUMP SUM LUMP SUM 0020 517 00101 CONSTRUCTION SURVEYING

More information

THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E

THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E Each bidder shall bid each item of the Base Bid Schedule and Alternate A Bid Schedule. Failure to bid an item shall be just cause

More information

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Estimated Quantity 202-00001 Removal of Structure 24 EA 202-00019 Removal of Inlet 24 EA 202-00195 Removal of Median cover 930 SY 202-00200 Removal of Sidewalk 1,188 SY 202-00201 Removal of Curb Head 273 LF 202-00203 Removal

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 180573 PID 93496 FRA-IR 71-01.53 Federal Type: BRIDGE REPLACEMENT (2 BRIDGES) Letting Date: 12/20/2018 Completion

More information

Federal Project No.: HSIP-5A27(567)

Federal Project No.: HSIP-5A27(567) Order : A11 Schedule of Items Page: 2 Oversight/State Project : (NFO)0001-020-S82,C501 Federal Project : HSIP-5A27(567) 0010 513 00100 0020 517 00101 MOBILIZATION LUMP SUM LUMP SUM CONSTRUCTION SURVEYING

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 170559 PID 102381 SCI-US 52-19.01 Federal Type: TWO LANE RESURFACING Letting Date: 11/2/2017 Completion Date:

More information

Federal Project No.: STP-5128(388)

Federal Project No.: STP-5128(388) Order : M48 Schedule of Items Page: 2 Oversight/State Project : (NFO) 0460-129-105, C501 Federal Project : STP-5128(388) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION)

More information

DESCRIPTION QUANTITY PRICE TOTAL

DESCRIPTION QUANTITY PRICE TOTAL GENERAL 1 TRAFFIC CONTROL LS 1 $40,000 $40,000 $8,500.00 $8,500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $15,000.00 $15,000.00 2 MOBILIZATION LS 1 $557,000 $557,000 $629,500.00 $629,500.00 $350,000.00

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 170607 PID 85146 CUY-SR 21-10.04L Federal Type: BRIDGE REPLACEMENT (1 BRIDGE) Letting Date: 12/14/2017 Completion

More information

DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/10 AND 12/31/10 BY ITEM GROUP 211 CONTRACTS - AWARDED TOTAL: $649,895,273

DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/10 AND 12/31/10 BY ITEM GROUP 211 CONTRACTS - AWARDED TOTAL: $649,895,273 AVERAGE BID PRICES FOR AWARDED PROJECTS 06:54 Friday, February 18, 2011 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 9 $276 $30,713.33 9 2011.601/00010 VIBRATION MONITORING LS 2 $73 $36,700.00 2 2011

More information

CONTRACTOR'S REQUEST FOR PAYMENT CHASKA VETERANS PARK IMPROVEMENTS STANTEC PROJECT NO

CONTRACTOR'S REQUEST FOR PAYMENT CHASKA VETERANS PARK IMPROVEMENTS STANTEC PROJECT NO Owner: City of Chaska, 1 City Hall Plz., Chaska, mn 55318 Date: December 12, 2017 For Period: 12/1/2017 to 1/31/2018 Request No: 1 Contractor: Blackstone Contractors, LLC, 9520 County Rd. 19, Ste. D, Loretto,

More information

Project # & Name: # CDBG - Pugh Street Streetscape - East College Ave to East Beaver Ave & East Beaver Ave/Locust Lane Improvements

Project # & Name: # CDBG - Pugh Street Streetscape - East College Ave to East Beaver Ave & East Beaver Ave/Locust Lane Improvements Bid Opening Date: May 6, 2014 Time: 11:00 a.m. Surety NCA Surety NCA Yes Yes Yes Yes Total Amount Bid: $1,358,851.00 Total Amount Bid: $1,386,098.72 Item Nos. Approx. Quantities Unit Item & Unit Prices

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/15/17 Comp. Dt: 08/04/17. Contract Time: Min: Max:

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/15/17 Comp. Dt: 08/04/17. Contract Time: Min: Max: Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 1401-171 Contract ID: Contract Description: Contract Location: Recommendation: 170002 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP. 1 OF 1 P:\8417\ Bridge A\AT\Albany A.MDB 7/21/2014 7:32:31 AM REVISION NO COUNTY

SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP. 1 OF 1 P:\8417\ Bridge A\AT\Albany A.MDB 7/21/2014 7:32:31 AM REVISION NO COUNTY 7/18/2014 - UCTURE REVISION NO REVISIONS DATE BY DIICT COUNTY ROUTE SECTION SHEET - SEE SPECIAL PROVISIONS SUMMARY 3-0 BRADFORD ALBANY TOWNSHIP T-410 4 OF 8 QUANTITY ITEM NO UNIT DESCRIPTION DESIGN NO

More information

BID TABULATION REPORT McKINNEY STREET DRAINAGE IMPROVEMENTS PROJECT No. PWDR10012 BID OPENED : TUESDAY, AUGUST 13, :00 P.M.

BID TABULATION REPORT McKINNEY STREET DRAINAGE IMPROVEMENTS PROJECT No. PWDR10012 BID OPENED : TUESDAY, AUGUST 13, :00 P.M. PAVING IMPROVEMENTS McKINNEY 101 Rightofway Preparation LS 1 75,000.00 75,000.00 200,000.00 200,000.00 67,000.00 67,000.00 110,000.00 110,000.00 102 12inch HMAC Street Pulvermix SY 11,650 3.00 34,950.00

More information

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION NOTICE TO CONTRACTORS FOR REGULAR HIGHWAY LETTING April 10, 2018 REVISED

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION NOTICE TO CONTRACTORS FOR REGULAR HIGHWAY LETTING April 10, 2018 REVISED SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION NOTICE TO CONTRACTORS FOR REGULAR HIGHWAY LETTING April 10, 2018 REVISED Rev 2: Call No. 320, File No. 0247541 - Added Rev 1: Call No. 010, File No. 0425551

More information

DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/04 AND 12/31/04 BY ITEM GROUP 201 CONTRACTS - AWARDED TOTAL: $340,971,276

DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 01/01/04 AND 12/31/04 BY ITEM GROUP 201 CONTRACTS - AWARDED TOTAL: $340,971,276 AVERAGE BID PRICES FOR AWARDED PROJECTS 14:37 Wednesday, February 2, 2005 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 17 $920 $54,140.65 17 2011.601/00040 DESIGN LS 1 $4 $3,500.00 1 2011 $924 2013

More information

BID TABULATION PAGE 1 OF 4. BL S.R. Harbins Road/Alcovy Road - Intersection Improvements Department of Transporation. CMES, Inc.

BID TABULATION PAGE 1 OF 4. BL S.R. Harbins Road/Alcovy Road - Intersection Improvements Department of Transporation. CMES, Inc. BID TABULATION PAGE 1 OF 4 E.R. Snell Contractor, Inc. G.P.'s Enterprises, Inc. Est. 1 005 Traffic Control Project No M-0679 1 LS $27,811.00 $27,811.00 $48,800.00 $48,800.00 $22,021.80 $22,021.80 2 010

More information

Federal Project No.: NHFP-081-1(346)

Federal Project No.: NHFP-081-1(346) Order : N27 Schedule of Items Page: 2 Oversight/State Project : (NFO)0081-098-778,B650-51,C501 Federal Project : NHFP-081-1(346) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION)

More information

Licensed Class C Virginia Contractor No.

Licensed Class C Virginia Contractor No. month period is seven hundred and fifty thousand dollars (750,000) or more, the Bidder is required under Title 54.11100, Code of Virginia (1950), as amended, to be licensed by the State Board of Contractors

More information

Kansas Department of Transportation DISTRICT 2. Project(s): Min: Max:

Kansas Department of Transportation DISTRICT 2. Project(s): Min: Max: Page 1 of 23 518122 SECTION: 01 COMMON ITEMS 1 020100 CONTRACTOR CONSTRUCTION STAKING 2 025602 FIELD OFFICE AND LABORATORY (TYPE C) 3 025323 MOBILIZATION 4 070626 MOBILIZATION (DBE) 5 020001 MAINTENANCE

More information

ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS

ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2016153 TRACS No. Project No. County District Gross

More information

Grays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14

Grays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14 Grays Ferry Cost Estimate Breakdown Budgetary Numbers for Machinery Drive Options 10 Nov 14 Hardesty & Hanover, LLC Alternative 1 Bogie Support System Alternative Based on AW Sketch of New Bridge Component

More information

Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director

Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Project No. 080598 PID 21272 CUY-SR-237-4.93 - PART I (FRONT STREET); CUY-237-4.55 - P Federal Type: RAILROAD

More information

Items Unit Quantity Unit Price Total Unit Price Total

Items Unit Quantity Unit Price Total Unit Price Total Engineer's Plote Construction, Inc. Estimate 1100 Brandt Drive Hoffman Estates, IL 60192 s Unit Quantity 1 SUPPLEMENTAL WATERING UNIT 4 $100.00 400.00 $40.00 160.00 2 TOP SOIL FURNISH AND PLACE, 6 INCH

More information

CITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS

CITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS CITY OF ALAMO HEIGHTS WATER, STREET AND SIDEWALK CAPITAL IMPROVEMENT PROJECTS CITY OF SAN ANTONIO DEPT. OF CAPITAL IMPROVEMENTS MANAGEMENT SERVICES N. NEW BRAUNFELS AVE. SIDEWALK PROJECT FROM RITTIMAN

More information

SUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71

SUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71 BASE BID 1.00 GENERAL CONDITIONS 1.01 Mobilization (Maximum 5% of Base Bid) LS 1 84,000.00 $ 84,000.00 100,000.00 $ 100,000.00 85,000.00 $ 85,000.00 1.02 Bonding, Insurance, Permits (including Plumbing,

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 190109 PID 96986 CUY-SR 10-16.13 Steel Federal Type: BRIDGE REPAIR Letting Date: 3/21/2019 Completion Date: 9/30/2020

More information

Date: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications:

Date: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications: DEVELOPMENT SERVICES PHONE: (209) 668-5520 ENGINEERING DIVISION FAX: (209) 668-5563 156 S. BROADWAY, SUITE 150 TDD: (800) 735-2929 TURLOCK, CA 95380 engineering@turlock.ca.us Date: 04/20/2018 City Project

More information

SPECIAL GRADING INTERSECTION IMPROVEMENT JOHN WARD RD AT IRWIN RD REVISION DATES

SPECIAL GRADING INTERSECTION IMPROVEMENT JOHN WARD RD AT IRWIN RD REVISION DATES 9/20/2017 2:39:11 PM GPLOT-V8 2016104_18-001.dgn Project Number Sheet Total Sheets djackson gplotborder-v8i-po.tbl X2802 30 118 966.5 21+00 L.P. EL. 966.34 L.P. EL. 966.58 0.29% 0.11% 965 H.P. EL. 966.54

More information

ADDENDUM #2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18

ADDENDUM #2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18 November 29, 2018 ADDENDUM 2 WATERSHED IMPROVEMENTS ON AN ANNUAL CONTRACT RP031-18 Q1. Do contractors not need to be on the Watershed Improvements Pre-Qualifications List to submit on the RP031-18 Watershed

More information

Ingham County Request for Proposals Okemos Road and Sandhill Road Widening, Packet #15-15

Ingham County Request for Proposals Okemos Road and Sandhill Road Widening, Packet #15-15 COST FORM (1 of 5) Packet #15-15, Okemos Road & Sandhill Road Widening Project (Please Type or Print Clearly in Ink) Pay Description Unit Quantity Unit Price Total 1500001 Mobilization, Max. LS 1 2020002

More information

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/27/06 PAGE : 1 TABULATION OF BIDS

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/27/06 PAGE : 1 TABULATION OF BIDS PAGE : 1 NUMBER OF DAYS: 63 BRIDGE COUNT : 9 CONTRACT DESCRIPTION : BITUMINOUS OVERLAY & BRIDGE APPROACH PANEL REPLACEMENT CONTRACT LOCATION: LOCATED ON TH 90 FROM 0.8 MILE WEST OF THE BLUE EARTH RIVER

More information

STANDARD DRAWING INDEX

STANDARD DRAWING INDEX ATTACHMENT B STANDARD DRAWING INDEX DESCRIPTION EXISTING DRAWING NO. GENERAL Typical Layout for Improvement Plans City of Stockton Standard Border and Title Block for 8 1/2 x11 Sheet City of Stockton Standard

More information

ADDENDUM No. 1 Prospective Bidders

ADDENDUM No. 1 Prospective Bidders Page 1 of 1 Attachment to Addendum # 1 Revised Itemized Bid ADDENDUM No. 1 TO: Prospective Bidders FROM: Gregory Tate, Construction Contracts Administrator DATE: January 24, 2019 PROJECT: Traffic Signal

More information

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS Supplement to O.D.O.T. TRAFFIC ENGINEERING MANUAL November 26, 2013 Revisions to the June 22, 2011 edition are noted by a vertical line

More information

Schedule 18 (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES

Schedule 18 (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES Schedule (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES Schedule (Technical Requirements) DBFO Agreement EXECUTION VERSION

More information

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION NOTICE TO CONTRACTORS FOR REGULAR HIGHWAY LETTING April 10, 2018

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION NOTICE TO CONTRACTORS FOR REGULAR HIGHWAY LETTING April 10, 2018 SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION NOTICE TO CONTRACTORS FOR REGULAR HIGHWAY LETTING April 10, 2018 Letting Location: SCDOT Headquarters Building Conference Room 331 955 Park Street Columbia,

More information

2150 F&I 4" PVC pipe LF 100 $ F&I 6" PVC pipe LF 100 $ F&I 8" PVC pipe LF 100 $ 90.00

2150 F&I 4 PVC pipe LF 100 $ F&I 6 PVC pipe LF 100 $ F&I 8 PVC pipe LF 100 $ 90.00 1 of 5 2100 F&I 4" ductile iron pipe LF 200 $ 143.00 $28,600.00 2102 F&I 6" ductile iron pipe LF 200 $ 135.00 $27,000.00 2104 F&I 8" ductile iron pipe LF 200 $ 141.00 $28,200.00 2105 F&I 10" ductile iron

More information

UTILITY CROSSING DETAIL

UTILITY CROSSING DETAIL 6" OF CSBC COMPACTED TO A FIRM AND UNYIELDING CONDITION. NOTE: - SILT FENCE SHALL CONFORM TO 8-01.3(9)A - SILT FENCES SHALL BE INSTALLED ALONG CONTOUR WHENEVER POSSIBLE. - POST SPACING MAY BE INCREASED

More information

Tahoe-Reno Industrial Center Total Bonding Amounts Engineer's Opinion of Probable Construction Costs (30% Submittal) Project No. 783.

Tahoe-Reno Industrial Center Total Bonding Amounts Engineer's Opinion of Probable Construction Costs (30% Submittal) Project No. 783. Total Bonding Amounts Brent Farr Date: 05/05/17 Item Project Estimated Cost 1 Induction Well 1 and Britain Ave Non potable Water Line $1,084,353 2 Storage Reservoir Upgrades $11,560,463 3 Booster Station

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. District(s): 8 30=047 Start Dt: 05/01/17 Comp. Dt:

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. District(s): 8 30=047 Start Dt: 05/01/17 Comp. Dt: Letting: 17030200 Letting Dt: March 02, 2017 9:30 A.M. State Proj.: 5101-14 Contract ID: Contract Description: Contract Location: Recommendation: 170020 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

COST ESTIMATES: Curb-Running

COST ESTIMATES: Curb-Running COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway

More information

BID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ -

BID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ - BID FORM PART A Name & Category Unit Unit Cost (B) Cost (AxB) GENERAL REQUIREMENTS 1 Mobilization (Maximum 3.0% of the total Contract Price) 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b

More information

STREET IMPROVEMENTS PROPOSAL BID ITEMS

STREET IMPROVEMENTS PROPOSAL BID ITEMS STREET IMPROVEMENTS 1 Excavation 3,525 CY $ $ 2 A.C. Planing (2" to 4" Depth) 20,586 SY $ $ 3 Furnish & Install Asphalt Concrete 4,270 TON $ $ 4 Furnish & Install Aggregate Base 2,955 TON $ $ 5 Remove

More information

6 Hour Backhoe Loader (CAT 415F2/ 415F2 IL, 416F/ 416F2, 420F/420F IT, 420F2/ 420F2 IT, 430F/430F IT, 430F2/ 430F2 IT, 450F or Equiva $32.

6 Hour Backhoe Loader (CAT 415F2/ 415F2 IL, 416F/ 416F2, 420F/420F IT, 420F2/ 420F2 IT, 430F/430F IT, 430F2/ 430F2 IT, 450F or Equiva $32. PROJECT 2506; 2017 ANNUAL REPAIR CONTRACT; J.C. DILLON, INC., CONTRACTED SCHEDULE OF ITEMS, QUANTITIES AND COSTS 1 Hour Lowboy Including Both Permits and Paid Driver $75.00 2 Hour Single Axle Dump Truck

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/08/17 Comp. Dt:

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/08/17 Comp. Dt: Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 4308-34 Contract ID: Contract Description: Contract Location: Recommendation: 170004 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

OTTAWA COUNTY ROAD COMMISSION Bid Comparison

OTTAWA COUNTY ROAD COMMISSION Bid Comparison OTTAWA COUNTY ROAD COMMISSION Bid Comparison Contract ID: Description: Location: Projects(s): 28th & Mason Reconstruct with pavement 28th Ave. and Mason St between Adams St. and 32nd Ave. Jamestown Township

More information

Schedule of Pay Items

Schedule of Pay Items Schedule of Pay Items 4/27/2018 9:33 AM AASHTOWare Project Version 4.0 Revision 189 Report v1 Letting Call: 180601 001 Letting Date: June 1, 2018 Contract ID: 392144-202845 Description: Runway 17/35 rehabilitation

More information

STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS

STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS SUB TOTAL SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT

More information

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/26/00 PAGE : 1 TABULATION OF BIDS

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/26/00 PAGE : 1 TABULATION OF BIDS PAGE : 1 CONTRACT DESCRIPTION : LEFT & RIGHT TURN LANES AND FLASHING BEACON SYSTEM CONTRACT LOCATION: LOCATED ON TH 7 FROM 327 M WEST OF JCT TH 25 TO 445 M EAST OF JCT TH 25 RECOMMENDATION: AWARD TO LOW

More information

PAGE 1 of 18 WEIGHTED AVERAGE

PAGE 1 of 18 WEIGHTED AVERAGE UNIT PRICES PAGE 1 of 18 201 BRIDGE SITE PREPARATION L.S. 1.00 15,000.00 15,000.00 15,000.00 * 201 CLEARING ACRE 4.10 40,470.00 4,500.00 13,010.78 201 CLEARING STA 6,089.00 11,000.00 1.00 1,162.09 201

More information

HOUR TRAINING UNLOCKED HOUR SURVEY CREW UNLOCKED LUMP SUM CLEARING AND GRUBBING UNLOCKED FORCE ACCOUNT CLEARING AND

HOUR TRAINING UNLOCKED HOUR SURVEY CREW UNLOCKED LUMP SUM CLEARING AND GRUBBING UNLOCKED FORCE ACCOUNT CLEARING AND 1100050 HOUR TRAINING UNLOCKED 2000100 HOUR SURVEY CREW UNLOCKED 2010100 LUMP SUM CLEARING AND GRUBBING UNLOCKED 2010110 FORCE ACCOUNT CLEARING AND GRUBBING UNLOCKED 2010120 ACRE CLEARING AND GRUBBING

More information

Federal Project No.: STP-5A27(380), STP-5A27(381)

Federal Project No.: STP-5A27(380), STP-5A27(381) Order : M42 Schedule of Items Page: 2 Oversight/State Project : (NFO)0649-020-136,C502, C503 Federal Project : STP-5A27(380), STP-5A27(381) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING

More information

City of Grand Island Tuesday, February 13, 2018 Council Session

City of Grand Island Tuesday, February 13, 2018 Council Session City of Grand Island Tuesday, February 13, 2018 Council Session Item G-7 #2018-34 - Approving Certificate of Final Completion for the Construction of North Interceptor Phase I; Project No. 2012-S-6 Staff

More information

Agility Service Exchanges

Agility Service Exchanges Roads - Unpaved 618-7112-01 Shaping Miles 618-7113-01 Re-stabilization Square Yard 618-7114-01 Dust Palliative-Bit/Calcium Chloride/Other Square Yard 618-7114-02 Dust Palliative-Spot Square Yard 618-7115-01

More information

ATTACHMENT I BID SCHEDULE IFB NO , CHURCH FARMS EAST STORAGE TANK AND BOOSTER PUMP STATION

ATTACHMENT I BID SCHEDULE IFB NO , CHURCH FARMS EAST STORAGE TANK AND BOOSTER PUMP STATION ATTACHMENT I BID SCHEDULE IFB NO. 19-021, CHURCH FARMS EAST STORAGE TANK AND BOOSTER PUMP STATION Item No. Description Qty Unit Unit Cost Amount Pump Station Site Work 1 Site Demolition / Removals / Haul

More information

2015 PAVEMENT MAINTENANCE SECTION 15-PVMTC-05-GM

2015 PAVEMENT MAINTENANCE SECTION 15-PVMTC-05-GM ADDENDUM NO. 1 March 17, 2015 2015 PAVEMENT MAINTENANCE SECTION 15-PVMTC-05-GM SCHEDULE OF PRICES (BLR 12000a) Replace the schedule of prices with the attached pages. SUMMARY OF QUANTITIES Replace the

More information

Federal Project No.: NHPP-967-7(083)

Federal Project No.: NHPP-967-7(083) Order : N20 Schedule of Items Page: 2 Oversight/State Project : (NFO)9999-967-430,N501 Federal Project : NHPP-967-7(083) 0010 ATTD 00124 ROCK EXCAVATION CY 0020 302 504 00525 CONCRETE CLASS A3 MISC. CY

More information

EXHIBIT C [** Subdivision Name **] (** Filing No., Phase No. '] SUMMARY

EXHIBIT C [** Subdivision Name **] (** Filing No., Phase No. '] SUMMARY EXHIBIT C [** Subdivision Name **] (** Filing No., Phase No. '] SUMMARY DESCRIPTION QTY J ] COST/ _ ] TOTAL AMOUNT STREET IMPROVEMENTS 16,271 LF $151.6 $2,467,247 WATER DISTRIBUTION SYSTEM LF $412,110

More information

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director

Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Ohio Department of Transportation Official Bid Tabulation Jerry Wray, Director Project No. 130407 PID 88799 AUG-VA-VAR-BRIDGES Federal Type: BRIDGE REPAIR Letting Date: 7/18/2013 Completion Date: 8/31/2014

More information

Riverside County Transportation Department Summary of Bids

Riverside County Transportation Department Summary of Bids 1 COUNTY'S ESTIMATE R-JS General Construction Riverside, CA 92509 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID UNIT PRICE BID ESTIMATE 1 066102 DUST ABATEMENT LS 1 3,000.00

More information

Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013

Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013 Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D4-1102 November 21, 2013 Doughtie Construction Co., Elliott Construction Dudley Construction Ltd. SUBTOTAL GENERAL ITEMS : $191,713.00

More information

2011 LOCAL STREET IMPROVEMENTS

2011 LOCAL STREET IMPROVEMENTS 11 LOCAL STREET IMPROVEMENTS FOR THE MARCH 11 LIST OF DRAWINGS W. MAIN STREET/STH 19 E. MAIN STREET/STH 19/STH 113 DRAWING TITLE NO. TITLE 1 PROJECT OVERVIEW 2 KLEIN DRIVE CONSTRUCTION PHASING PLAN 3 PHASE

More information

On-the-Job Training Program. Overview of Training Programs

On-the-Job Training Program. Overview of Training Programs On-the-Job Training Program Overview of Training Programs The training programs are as follows: Code Training Program Hours (Up to) 901 Carpenter, Rough 1040 902 Concrete Finisher (Paving) 1040 903 Concrete

More information

B E C K E R & F R O N D O R F Construction Cost Consulting Project Management

B E C K E R & F R O N D O R F Construction Cost Consulting Project Management Project: Okehocking Nature Center Number: 07142E2 Client: M2 Architecture Date: June 5, 2009 Phase: DD B E C K E R & F R O N D O R F Construction Cost Consulting Project Management ESTIMATE SUMMARY CODE

More information

800 Access Control, R/W Use Permits and Drive Design

800 Access Control, R/W Use Permits and Drive Design Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled

More information

SPAS Concepts Preliminary Rough Order of Magnitude Cost Estimates

SPAS Concepts Preliminary Rough Order of Magnitude Cost Estimates Appendix G LAX SPECIFIC PLAN AMENDMENT STUDY REPORT SPAS Concepts Preliminary Rough Order of Magnitude Estimates 2011/2012 Prepared for: Los Angeles World Airports One World Way Los Angeles, California

More information

Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166

Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Date: August 10, 2016 Subject: Bid for Construction of NW 89 th Avenue, NW 93 rd Street and NW

More information

Patton Hill Road (Four Inch Main), Project No

Patton Hill Road (Four Inch Main), Project No Patton Hill Road (Four Inch Main), Project No. 2016100 MP-5.01 MOBILIZATION (3% MAX) 1 LS MP-5.02.8(d) 8" DIP (CLASS 350) ALL DEPTHS 600 LF MP-5.02.6(p) 6" PVC ALL DEPTHS, INCLUDING BEDDING 10 LF MP-5.02.4(p)

More information