Figure 14: Simulation Result Figure 15: Power Supply Overview Figure 17: Prototype and Design Comparison (2)

Size: px
Start display at page:

Download "Figure 14: Simulation Result Figure 15: Power Supply Overview Figure 17: Prototype and Design Comparison (2)"

Transcription

1

2 Contents Introduction Needs Statement Objectives Statement Background Overview Technical Additional Description Marketing Requirements Objective Tree Table 1 Table 2 Figure 1 (Objective Tree Diagram) Requirement Specification Table 3 Table 4 Table 5 Table 6 Alternate Features Design Figure 2: Block Diagram of system. Figure 3: Detailed Block Diagram showing components. Mechanical Construction Figure 4: Mechanical CAD drawing of the air intake and fan enclosure. Figure 5: Back view of enclosure showing air intake. Figure 6: Side view of enclosure. Figure 7: Dowel rods at the top of each tube. Electrical Construction Figure 8: Basic electrical circuit for the switches and blowers. Figure 9: Four controllers with switched mounted. Figure 10: Board used for connections of blowers, switches, and resistors. Design for 12 Volt AC to DC wall outlet power supply Description of concept Circuit Design Figure 11: Power Supply Circuit Diagram Figure 12: Zener Diode Physics Explanation Requirements and Specifications for power supply Figure 13: Blower Power Consumption at 12V Table 7: Power Supply Requirements Circuit Simulation

3 Figure 14: Simulation Result Figure 15: Power Supply Overview Figure 16: Prototype and Design Comparison (1) Figure 17: Prototype and Design Comparison (2) Alternate Designs Lab Instruction Documentation Analysis and Applicability of Constraints Standards and Regulatory Issues Single Tube Prototype Figure 18: Single Tube prototype lifting pingpong ball Test Results Project Management Milestones Task List Gantt Chart Figure19: Gantt Chart (Red line represents today s date) Required Resources Table8: Cost of mechanical components used Table9: Cost of electrical components used Table10: Tools used to build the apparatus Table11: Total cost and budget Table12: cost for testing the apparatus Risks Challenges, issues, and problems encountered Conclusion

4 Introduction Needs Statement In the meeting that our team held with Professor Passino, he mentioned that...the current state of [electrical engineering] education in developing countries is governed by book-based learning. This method, while beneficial in its own right, needs to be accompanied by a hands-on, lab based approach for best results. Professor Anderson, who operates and designs experiments that K-12 students from around Columbus use, quoted a lab cost of a couple hundred dollars as an arbitrary experiment cost. This cost is reasonable for areas that have people with the resources to support both methods. It proves difficult, however, in lower income areas because of the costs of running appropriate labs. There needs to be alternative lower-cost labs that can be performed to help in the education process of these areas. In order to help reduce this cost, and as a means to provide alternatives for the learning process in low income areas, we need to make a feedback control lab that can be built, transported, performed, and maintained cheaply. Objectives Statement The team will design and build a low-cost, hands-on engineering laboratory experience based on a mechanical juggler that uses human as feedback control to manipulate ping pong balls inside four tubes. The lab will teach students the concepts of open loop and closed loop feedback control as well as team cooperation. Moreover the cost will be maintained under 85 U.S dollars as it will be constructed from plastic and portable. Background The Juggler also referred to as the balls-in-tubes experiment was created to be an inexpensive test experiment for dynamic resource allocation strategies that exploit information from the plant in feedback. The dynamic resource allocation involves the limit on the amount of air the whole system can use at a given time. The feedback involves the sensors used which will be mentioned later. There exists a larger model of the Juggler in the Distributed Dynamical Systems Laboratory in Dreese labs.

5 The February 2005 issue of IEEE Control Systems Magazine, states the cost of this setup is around $200 plus the cost of the power supply and wires. The system allows for the use of feedback to be shown visually through the use of Devantech SRF04 ultrasonic sensors, Dynatron DF1209BB dc fans, and a DS1104 dspace card. An issue faced with this system that we could also face would be the fact that the time it takes for a ball to rise a fixed distance in a tube is generally greater than the time it takes the ball to drop the same distance. Another issue would be if 4 tubes are used, the two in the center tend to have greater airflow due to the input manifold being in the center of the model. Our group aims to recreate this setup in a cheaper form. This will be achieved by using human feedback instead of the sensors. The dynamic resource allocation strategies through juggling or balancing the balls forcing the users to cooperate with each other to complete the objective will still be implemented. The purpose of the Juggler Lab is to make sure students have interactive exposure to how electrical apparatus can teach you physical principles. The lab is designed in a manner to make the students understand feedback as well as cooperation. The lab aims to target these concepts by allowing the students themselves to be the feedback. This is achieved with the task of trying to balance the Ping-Pong ball at a certain height. The switches play as mode to allow the students to use their feedback response. Another concept the Juggler Lab teaches students is to act and perform the experiment as a team. This is incorporated by having 4 switches with 4 different people controlling them and the aim is to try and balance the balls at a specific height level while cooperating with other users of the apparatus. This makes the lab fun as well as intuitive. Overview The remainder of this document will give in detail the specifications and requirements that the juggler was designed to meet. Following this, we will present our final design as well as the iterations that we went through. Next, a report is given of testing and results showing how the design met the desired specifications. Finally, some project management considerations will be given such as design and implementation costs and issues faced.

6 Technical Additional Description A major factor in engineering is teamwork. The lab is designed to help with working together as a unit. This will be achieved through three factors of the lab: 1) Personal tasks, 2) The bigger picture and 3) Communication. On a team, each member has a job that they need to perform. For the juggler, each student must balance a ball in a given region. This mirrors the concept sufficiently. The second factor that must be realized is the big picture. Since the airflow into the device is finite, how an individual ball performs is dependent on the other tubes. It is designed to simulate the need for cooperation. Cooperation leads to communication. For a team to succeed a channel of communication must be opened. This will hopefully be a way to show the collaborative nature of engineering work. Marketing Requirements 1. The lab should be designed on a low cost budget. 2. The apparatus should be light-weight. 3. The apparatus should be compact to fit easily on a lab bench. 4. The product should be interactive. 5. The product must be challenging for the students to perform. 6. The lab should be usable in a reasonable classroom. 7. Easy manual and instruction set should be provided for the lab such that it can be understood in any country across the globe. The proposed requirements are to be able to market the product as a WeLab. The purposes of these labs are to make electrical engineering more accessible. This is especially true in under

7 developed countries. The lab should be low-cost. The lab is to be marketed as portable. The set-up should be light weight and useable in a reasonable classroom. Last the lab will be moderately fun. This is taken as interactive and challenging. A breakdown of these requirements is provided in the objective tree section. Table 1 shows how the group weighted each of these goals in reference to the final product. The main conflicting goals were between cost, interactivity, and challenge. Challenge was weighted as the most important at 65%. Interactivity and cost of production followed at 25 and 11 percent respectively. The items in table 2 were independent from those in table 1. Ease of manual is the most important here. Objective Tree Table 1 Low-Cost Interactive Challenging GMean Weight Low-Cost Interactive Challenging Table 2 Advanced application Easy manual GMean Weight Advanced application Easy manual

8 Figure 1 (Objective Tree Diagram) Requirement Specification Table 3 Engineering Requirements Marketing Requirements Engineering Requirements Justification 1 Total cost < $85 Developing countries may not have much money for lab equipment

9 1, 4, 5, 7 Controls with < 6 buttons 1, 2 Total weight < 50 lbs. 3, 6 Fit within a 1x1x1 meter box 6, 4, 7 Manual with pictures 2 Use of a 12V batteries To keep the use simple and interactive there should be a controller with minimal buttons Flights out of the country have a baggage weight limit of 50 pounds to keep from getting extra fees (1). To keep the size manageable for a lab bench To keep the manual simple as well as getting the point across To provide easy replacement of batteries. Batteries readily available in the respective country. Table 3 shows the requirements that were designed to meet. The price was kept under $85. This ideally would have been under $50. Due to some changes in design however the baseline price was increased. The other big change was the use of 12V batteries. A self-produced power supply was used instead. The implementation will still be functional with a battery source. The other requirements have not changed.

10 Table 4 Table 5

11 Table 6 Tables 4, 5 and figure 6 show the feasibility analysis of the project. The house diagram in figure 6 wraps up the goals and how well they would work together. The positive 1 s show goals that can be performed simultaneously, negative 1 s are conflicting. It shows cost, total weight and total size all can be improved at once. It is interesting to note that reducing the number of buttons also reduces interactivity. Also, if the manual is too easy, then challenge is adversely affected. An easy manual is one that gives students the exact procedure to balance the balls. Alternate Features There were many possible features the team investigated. From electrical to mechanical options some we rejected immediately and others we tested and chose the best route based on our results. In terms of the electrical design we sketched up many different designs the for features we wanted. We contemplated adding an electrical feedback system incorporating sensors at the top of each tube similar to the original Juggler. This system would utilize a microcontroller to control each sensor. The team rejected this idea early due to the fact that we wanted the system to be interactive for the users and this was accomplished through the users being the mode for feedback which will be explained later. The group also investigated adding color L.E.D. to mark

12 each tube with a different color and the same color to mark each controller. This was rejected because it was easier to just number each tube and their corresponding controller. Another electrical feature of the system the group investigated involved adding a momentary switch instead of the normal flip switches. We rejected this in the beginning because we thought we would need a 3 state switch for high/low/off but ended up only using high and low power. In light of this using a momentary switch would have been a better option after testing. If the group had more time to work on the project we would have experimented with implementing this type of switch. As for the mechanical features, due to the fact that our design was based off a previously designed lab, the design of our apparatus was straightforward and therefore did not involve any extra features. Design The main concept that fueled the design of our teams project was feedback. The interaction of the user allows the juggling to occur. Figure 2 below details how the user input to the system affects the apparatus. Figure 3 below is a more detailed block diagram of the system showing the major components.

13 Figure 2: Block Diagram of system. Figure 3: Detailed Block Diagram showing components. Mechanical Construction The air intake and the enclosure that houses the fans was constructed with plexiglass and the CAD drawing displaying the measurements is shown below in Figure 4. We were aided in the cutting of the plexiglass by Mr. Thalgott in the basement shop. Once we acquired the needed

14 pieced we assembled the structure using PVC glue. The completed enclosure is shown below with fans inside in Figures 5 and 6.

15 Figure 4: Mechanical CAD drawing of the air intake and fan enclosure. Figure 5: Back view of enclosure showing air intake.

16 Figure 6: Side view of enclosure. The next step in the construction process was to attach the 4 tubes to the base which is also shown completed in Figures 5 and 6. Figure 7 display the tops of each tube. The team glued dowel rods on the bottom of each lid for the tubes. This prevents the ping pong balls from getting stuck in the tops of the tubes which was a problem we ran into. Figure 7: Dowel rods at the top of each tube. Electrical Construction The electrical construction involved the basic circuit below in Figure 8. The components were four blowers, four switches for low and high power mode, and four 50 ohm resistors. The

17 switches were mounted on their controller so the user could easily operate the switch displayed in Figure 9. Testing multiple resistances allowed us to choose 50 ohms as the best option. Figure 10 shows the board we used to construct the circuit with the big red and yellow connectors being the location where the power supply is connected. As can be seen in Figure 9, there is an enclosure on the side of the box which can be used to house the circuit board.

18 Figure 8: Basic electrical circuit for the switches and blowers.

19 Figure 9: Four controllers with switched mounted.

20 Figure 10: Board used for connections of blowers, switches, and resistors. Design for 12 Volt AC to DC wall outlet power supply Description of concept As team members realized using 1.5V batteries in series to provide 12V DC power would not be practical. In addition for the sake of increasing design complexity and reliability, team members decided to adapt an AC/DC converter design that outputs 12V DC power for four blowers team acquired. Circuit Design In order to achieve the goal of providing 12V DC voltage, design below is considered. Figure 11: Power Supply Circuit Diagram

21 The ultimate goal of the power supply is to provide 12V DC voltage for the sub circuit of the design. To accomplish our goal we first use a transformer to stepdown AC voltage from 110V to roughly 30V. Follow by Diode Bridge, negative voltage cycle will be folded to positive region. After adding a capacitor, Voltage ripple will be smoothed out dramatically. At last a 12V Zener diode regulator design will be utilized in order to achieve a 12V DC output. A Zener diode is a diode which allows current to flow in the forward direction in the same manner as an ideal diode, but also permits it to flow in the reverse direction when the voltage is above a certain value known as the breakdown voltage. When operating at reverse bias, voltage across diode will be 12V. Figure below explains the physics of Zener Diode. Figure 12: Zener Diode Physics Explanation Requirements and Specifications for power supply Since the purpose of the power supply is to provide reliable power source for four blowers solely to lift ping pong balls, the power supply is required being able to output 12V DC voltage. In addition, as tested in the lab each fan will consumed 0.17A current at 12V (shown below). Therefore, the power supply will also be able to provide a minimum current at 0.68A.

22 Figure 13: Blower Power Consumption at 12V Engineering requirements Justification Power Supply Output 12V DC & Minimum 0.68A 0.68A is the nominal current consumption of all four fans and 12V is fan's operating voltage Capacitor Being able to handle up to 36V Transformer outputs 36V Voltage Pull up resistor 20ohms & being able to handle up to 6.8W All current will flow through the pull up resistor. W=I*R=0.68A*10ohms=6.8W Zener Diode Being able to handle up to 0.68A Nominal current flowing through will be 0.68A

23 Table 7: Power Supply Requirements Circuit Simulation Before construction team member ran software simulations for the sake of circuit reliability and being able to fully understand the circuit. Below is the simulation result. Figure 14: Simulation Result Red line presented in the graph represents input AC voltage. Voltage across capacitor is being presented by blue line. At last, green line is the output voltage of the power supply

24 Figure 15: Power Supply Overview

25 Figure 16: Prototype and Design Comparison (1) Figure 17: Prototype and Design Comparison (2) Alternate Designs Throughout the design of our project the team ran into many problem we had to work though in order to get to our final successful design. The first problem we ran into was both mechanical and electrical. The team had difficulty implementing our initial design for the prototype and successfully lifting the ping pong ball. This was due to the fact that the first set of fans we purchased were 4.7 in length and we used a pyramid design for the base. Due to both the mechanical design of the base and the size of the fan, there was not enough force at the bottom of the tube to lift the ball. The team realized we needed to reject both the large computer fans and the pyramid base design. The teams solution to this problem was to change from using a computer fan to a blowers. We got our idea to experiment with a blower from research on the internet. The blower was a positive addition to our apparatus because it applied its entire output force at the base of the tube so lifting the ball was much easier. Additionally it was much smaller in size than the previous fans, so this allowed for a much smaller rectangular design for our base. This made it much more structurally sound by decreasing the overall size of the base and gluing

26 together a rectangular box was much easier than the previous pyramid design. In addition the change made the apparatus cheaper which was a requirement of our project. The second problem was the fact that our choice of power for the system was not sufficient for the force we needed to come out of the fans. After testing the eight D batteries, which was our original idea, the team decided to build the power supply mentioned above and this was a much better solution than the batteries. First because is supplied then additional power needed to keep the balls lifted and second it was a reusable source that did not need to be replaced like the batteries. Lab Instruction Documentation The WeLab will also come with instructions similar to those given in a class period. The proposed lab procedure is defined in a stand alone document that is included with the lab. The purpose is to allow them to be posted separately from the machine itself. This will allow the most people to view and use the product. Structurally the instructions are divided into two parts: A teacher s manual, and a student version. The teachers manual outlines the purpose of the lab. It will give what concepts are being taught and how. Additionally, the teacher version contains a parts list as well as details on constructing a juggler. This is to allow multiple people to build a cost effective lab. Finally the teacher version will give several troubleshooting tips. The student portion gives a walkthrough on how to perform the lab. Analysis and Applicability of Constraints Economical: The lab is designed to be less than $80 to provide a cheap, but also provide an intuitive lab experience for students in developing countries. This economical lab explains the different concepts by providing the students with hands-on experience. Environmental: The materials used for the lab are environment safe. The tubes are made from recyclable plastic. The ping pong balls are also biodegradable and can be disposed of easily

27 without harming the environment. The case that is used to enclose the apparatus is made out of plexiglass and is a material that are also biodegradable. The power supply is the only part of the apparatus that could harm the environment if disposed of incorrectly. Social: The lab is designed in a way to provide a very social experience to all the users that perform the lab. The users have to communicate with each other in an interactive manner to balance the Ping-Pong balls inside the tubes. The users each have access to each of the switches on the apparatus that controls the fan in each of the tube. Thus, this lab provides a really social and team based experience which helps the students learn more about team coordination and communication skills. Health and safety: Since the lab is targeted to the students the health and safety has been the number one priority in designing the lab. The tubes are made up of plastic instead of using glass to make sure no one gets injured in case the apparatus was to break. The wires and the circuitry of the apparatus are not easily accessible to ensure none of the students get injured by a shock. The apparatus is designed in a way such that it has a lower center of gravity and thus making it hard for it to topple over and hurting some students foot. Sustainability: The tubes and the fans in the apparatus are designed and placed in a way such that they are easily replaceable in case they go defective. The ping pong balls can also be replaced easily. In addition the power supply should last a very long time are the parts are rated for long term use. Standards and Regulatory Issues Safety standard: Occupational Safety and Health Standards (f) Power Supply Standard: IEC/TS Ed. 1.0 en:2014

28 IEC TS 62700:2014(E) states the minimum requirements for DC power supply for notebook computers. Specifically, it gives an electrical specification (performance characteristics), an ID pin method and a connector for DC power output. Lab standard: IEC / IEC The IEC / IEC Electrical Equipment Package provides safety and EMC requirements for electrical equipment in a laboratory setting. It also provides general requirements for electrical test and measurement equipment, electrical industrial process-control equipment and electrical laboratory equipment. The IEC / IEC Electrical Equipment Package includes: IEC Ed. 3.0 b:2010 IEC Ed. 2.0 b:2012 All designs team used will follow standards listed above to comply our safety and voltage supply requirement. Single Tube Prototype Our prototype although successful, opened our eyes to a lot of issues our system had that through changes allowed us to have a better final product. The ultimate goal of our single-tube prototype was to successfully lift the pingpong ball. We accomplished this and our prototype is shown in Figure 10 below lifting the ball. Our prototype was built using the larger fans mentioned earlier that were later replaced with blowers. This is when the team first realized that a smaller solution was needed. In addition the base for the tube and enclosure for the fan was constructed in a pyramid design out of plexiglass, which was very hard to construct and keep stable. This was mentioned earlier when talking about changes the team made in design. The use of blowers allowed for a square base. With our prototype we also tested the use of eight D batteries and this

29 also failed so we ended up using a power supply in the lab for the prototype and decided to build our own for the final system. Figure 18: Single Tube prototype lifting pingpong ball

30 Test Results During the time of building this lab design, the team encountered many problems. To make sure the design can run correctly, the team did following tests and experiments. 1. Power Supply: The team planned to use D-batteries as the power supply before the team decided to use blowers instead of regular computer fans. But after the testing, the D-batteries did not give the computer fans enough power to lift the ping pong balls. So the team decided to use the in-wall power supply. Since voltage from the in-wall power supply is 110V, the team also design a AC-DC step-down converter circuit. After testing, the team converted the 110V AC voltage into a 12V DC voltage. 2. Fan Experiment: When the team built the single tube prototype, the regular computer fans did not work very well. They did not have enough concentrated strength to lift the balls under the 12V DC voltage. Instead of using the regular computer fans, the team decided to use the more powerful blowers. The blowers can easily lift the balls under 12V DC voltage. 3. Resistor Experiment: In order to create the low power settings, which makes the balls drop very slow, the team did the voltage experiment first and found the acceptable voltage range for the design was between 6.5V to 7.5V. After series of calculations, the team found the demand resistance - 50Ω. In case the resistor might burn, the team decided to use a 50Ω resistor with a higher rating. 4. Single Tube Prototype Experiment After all the above experiments, the team decided to put all the parts together and make a single tube prototype. The purpose of this experiment is to test whether each part of this design can work well together. During this experiment, the design easily lifted the ping pong balls. Under the low power setting the ping pong ball can drop down very slow. So single tube prototype work pretty well. 5. Final testing Based on the single tube prototype, the team built the final design. In the final design, there are four tubes and four blowers, and each of them has the high mode and low mode. They are constructed in parallel as the team planned. Before the team sealed all the pieces of the design, the team did the

31 final testing. Before turning on the master switch, all the blowers were set to default mode, which is high mode. After turning on the master switch, all the ping pong balls were successfully lifted up and hit the top. The the team tested the low mode for each blower, and they all worked correctly. Under the low mode, all the ping pong balls drop down very slow. So the final testing was very successful. Project Management Milestones To keep the project organized and finish it in a timely order. These milestones were chosen: 1. Completing the electrical blueprint for four multiple speed fans. 2. Prototype for a single tube completed. To make sure hardware setup is feasible 3. Full system prototype completed. This will be the finished product completion Task List Each of the milestones had tasks and subtasks under it. 1) Electrical Power Distribution Circuit a) Design i) Layout ii) Calculations b) Purchase Components i) List ii) Place the order c) Construct/Test 2) Single Tube Prototype a) Mechanical Design/Construction b) Electrical Construction For Single Tube c) Testing 3) Full System Prototype a) Construction i) Electrical

32 ii) Mechanical iii) Air-manifold b) Testing i) Safety ii) Stability iii) Performance Gantt Chart

33 Required Resources Figure19: Gantt Chart (Red line represents today s date) Mechanical Construction Item Price Plexi Glass $8.32 Tubes $5.00 4, Pingpong Balls $1.00 ea. Glue Varies (According to use) 4, Blowers $8.56 ea. 4, Nuts and Screws: $0.25 ea Electrical Components Table8: Cost of mechanical components used Item Price 5, Switches $1.00 ea. Bridge-Diode $0.62 ea. 12 Volt Zeiner Diode $0.54 Step-Down Transformer $ , 20-Ohm Resistors $0.64 ea. 4, 50 ohm Resistor $1.72 ea. 50 Volt Capacitor $0.90 Power Adapter Varies (Any power adapter works)

34 Table9: Cost of electrical components used Tools Item Sodder Multimeter Wire-cutters/Wire-strippers Band-saw 6, Circuit Boards Wire to connect Table10: Tools used to build the apparatus Total cost of apparatus $79.15 Requirement cost estimation $85.00 (We Lab) Total Budget for the project $ Table11: Total cost and budget Cost for testing(not used in the final apparatus): Item Price Boost, Flyback, SEPIC and Inverting Controller $ V N-Channel MOSFET $ , D-batteries $8.39 4, computer super quiet Fans $5.00 ea 4, computer fans $2.38 ea. Plexiglass $2.45

35 tubes $2.50 2, 20 Volt Zeiner diode $0.54 ea. Table12: cost for testing the apparatus Risks 1. Durability: Since the apparatus is going to be used by students, the apparatus must be durable. The team faced several design problems to make the apparatus durable and reusable by the students. One of the key design changes that the team used to resolve this issue was to have a separate panel for the implementation of the switches. This would not only allow easy access to the switches but will also refrain the students from touching the circuit board. 2. Resistor getting hot: The power going through the resistor was very high. This caused the resistor to become very hot. Since the apparatus had to be safe to use the team had to tackle this problem and make it safe to use. Thus, the team decided to add another 20-ohm resistor in parallel. This reduced the load on each of the resistor and thereby made them less hot. 3. The diode: During testing the final apparatus, the team realized that the diode being used is of low rating. This meant that it is not capable of allowing or handling a lot of power. The team decided that the problem wasn't very severe and need not be resolved. Challenges, issues, and problems encountered The semester went as well as one might expect. We feel like our intended goal was met. There were, however, several issues that came up. The issues ranged from circuit problems to construction issues. The circuit challenges were fairly few. The first issue encountered was determining the resistance values for LOW power mode. This was determined through performance testing and was resolved. The next distinct problem we faced was complexity. This design is culminating from our collegiate experience. The original circuit that was proposed was too trivial. This was a

36 problem because it didn t show what was learned through school. To combat this, the group produced a working power supply to accompany the juggler. Adding the power supply gave rise to a final issue. Some components initially had too much power going across them. To resolve this two methods were employed. The first was to order better rated components. The second was to put devices in parallel to reduce the current flow through an individual device. All the construction issues were due to the fact that our group was all electrical engineers. Actual physical system tasks were not as practiced as the electrical ones. The first issue was how to actually build the parts. This was resolved thanks to Mr. Thalgott who machined all of our pieces. In the talks with Thalgott, it was discovered that some dimensions on the initial design were off. He helped us rectify this. Once everything was cut the group had to construct the final prototype. We did not want to drill any holes in the plexiglass. The risk of breaking a piece was too high. To combat this, we screwed the blowers directly together instead of attaching them to a wall. The result was the same. We then used the pieces for stabilizing the tubes. Conclusion To conclude, the team builds an apparatus called the juggler that helps schools in developing countries to have inexpensive interactive labs. The juggler is an apparatus that uses human as feedback control to manipulate ping pongs balls inside tubes. The lab will teach students about the concepts of open loop and close loop feedback control as well as team cooperation. The apparatus also teaches the students a handful of different concepts that help them develop skills like problem solving, communication, co-ordination with the team members, etc. The project is designed to be economical, safe for students, intuitive, social, sustainable and environmentally safe. This is achieved by using different design techniques to build the juggler. The problem that developing countries currently have is that they cannot afford to conduct labs that are intuitive enough to make the students understand abstract concepts by providing students with a hands on experience on these abstract concepts. The labs are generally really

37 expensive and thus, the school decides not to hold labs for the students. This makes it harder for students to understand the concepts. The solution that the team provides is an affordable apparatus that is sustainable and can be used multiple times in a year. The apparatus called the juggler provides the schools a lab and benefits the students to learn and understand the different concepts that the apparatus teaches. This experience of the juggler can be enhanced in a lot of ways. Firstly, the juggler s control feedback mechanism can completely be completely automated. This would be achieved by adding laser sensors on the top of each of the tubes to find out the level at which the Ping-Pong ball is floating. These sensors can in turn send data to a microcontroller that controls the speed of the fan and thereby keeping all four balls at the same level. The second enhancement that can be done on this apparatus is, by adding Ping-Pong balls of different weights. This makes it more challenging for the students to maintain the balls at the same level. Another enhancement that can be done in this apparatus is to have different strength fans. This has the same benefits as the previous enhancement and causes more communication and coordination among the users who serve as a control mechanism for the apparatus. Overall, this project includes many techniques, some of them are what we have learned from classes, and some of them are from online resources. During the time of building this design, every team member learned how to cooperate as a team. Although, sometimes team members had some disagreements about some problem, we could always find the best solution. From this project, the team gained experience about how to finish a real life project as a professional engineer. The team also learned the most valuable lesson about how to work as a team.

Folding Shopping Cart Design Report

Folding Shopping Cart Design Report Folding Shopping Cart Design Report EDSGN 100 Section 010, Team #4 Submission Date- 10/28/2013 Group Image with Prototype Submitted by: Arafat Hossain, Mack Burgess, Jake Covell, and Connor Pechko (in

More information

Engineering Fundamentals Final Project Engineering Lab Report

Engineering Fundamentals Final Project Engineering Lab Report Engineering Fundamentals Final Project Engineering Lab Report 4/26/09 Tony Carr Christopher Goggans Zach Maxey Matt Rhule Team Section A2-6 Engineering Fundamentals 151 I have read and approved of the

More information

Stationary Bike Generator System (Drive Train)

Stationary Bike Generator System (Drive Train) Central Washington University ScholarWorks@CWU All Undergraduate Projects Undergraduate Student Projects Summer 2017 Stationary Bike Generator System (Drive Train) Abdullah Adel Alsuhaim cwu, 280zxf150@gmail.com

More information

2 nd Generation Charging Station

2 nd Generation Charging Station 2 nd Generation Charging Station By Jasem Alhabashy, Riyadh Alzahrani, Brandon Gabrelcik, Ryan Murphy and Ruben Villezcas Team 13 Problem Definition and Project Plan Document Submitted towards partial

More information

Introduction: Problem statement

Introduction: Problem statement Introduction: Problem statement The goal of this project is to develop a catapult system that can be used to throw a squash ball the farthest distance and to be able to have some degree of accuracy with

More information

EDSGN 100: INTRODUCTION TO ENGINEERING DESIGN Section 204 Team #1 BOX CART

EDSGN 100: INTRODUCTION TO ENGINEERING DESIGN Section 204 Team #1 BOX CART EDSGN 100: INTRODUCTION TO ENGINEERING DESIGN Section 204 Team #1 BOX CART Submitted by: Chang - http://www.personal.psu.edu/cbl5289/ Vinay Murthy - http://www.personal.psu.edu/vum119/ Aidan Fitzpatrick

More information

EXPERIMENTAL VERIFICATION OF INDUCED VOLTAGE SELF- EXCITATION OF A SWITCHED RELUCTANCE GENERATOR

EXPERIMENTAL VERIFICATION OF INDUCED VOLTAGE SELF- EXCITATION OF A SWITCHED RELUCTANCE GENERATOR EXPERIMENTAL VERIFICATION OF INDUCED VOLTAGE SELF- EXCITATION OF A SWITCHED RELUCTANCE GENERATOR Velimir Nedic Thomas A. Lipo Wisconsin Power Electronic Research Center University of Wisconsin Madison

More information

M:2:I Milestone 2 Final Installation and Ground Test

M:2:I Milestone 2 Final Installation and Ground Test Iowa State University AerE 294X/AerE 494X Make to Innovate M:2:I Milestone 2 Final Installation and Ground Test Author(s): Angie Burke Christopher McGrory Mitchell Skatter Kathryn Spierings Ryan Story

More information

Stationary Bike Generator System

Stationary Bike Generator System Central Washington University ScholarWorks@CWU All Undergraduate Projects Undergraduate Student Projects Spring 2017 Stationary Bike Generator System Rakan Alghamdi Central Washington University, rk_rk11@hotmail.com

More information

ECE 480 Design Team 3: Designing Low Voltage, Low Current Battery Chargers

ECE 480 Design Team 3: Designing Low Voltage, Low Current Battery Chargers Michigan State University Electrical Engineering Department ECE 480 Design Team 3: Designing Low Voltage, Low Current Battery Chargers Application Note Created by: James McCormick 11/8/2015 Abstract: The

More information

Project Report Cover Page

Project Report Cover Page New York State Pollution Prevention Institute R&D Program 2015-2016 Student Competition Project Report Cover Page University/College Name Team Name Team Member Names SUNY Buffalo UB-Engineers for a Sustainable

More information

Project Narrative Description

Project Narrative Description 0 Project Narrative Description Charge Spot is intended to demonstrate the feasibility of an autonomous electric vehicle charging system for residential use. The goal of Charge Spot is to have no user

More information

ECSE-2100 Fields and Waves I Spring Project 1 Beakman s Motor

ECSE-2100 Fields and Waves I Spring Project 1 Beakman s Motor Names _ and _ Project 1 Beakman s Motor For this project, students should work in groups of two. It is permitted for groups to collaborate, but each group of two must submit a report and build the motor

More information

Alternative Power Source for Dental Hygiene Device. Project Proposal

Alternative Power Source for Dental Hygiene Device. Project Proposal Alternative Power Source for Dental Hygiene Device By: Nizar Almansouri, Francisco Health, Ningbao Jiang Jin Niu, and Jiaqi Xie Team 15 Project Proposal Submitted towards partial fulfillment of the requirements

More information

Predicting Solutions to the Optimal Power Flow Problem

Predicting Solutions to the Optimal Power Flow Problem Thomas Navidi Suvrat Bhooshan Aditya Garg Abstract Predicting Solutions to the Optimal Power Flow Problem This paper discusses an implementation of gradient boosting regression to predict the output of

More information

Your web browser (Safari 7) is out of date. For more security, comfort and. the best experience on this site: Update your browser Ignore

Your web browser (Safari 7) is out of date. For more security, comfort and. the best experience on this site: Update your browser Ignore Your web browser (Safari 7) is out of date. For more security, comfort and Activitydevelop the best experience on this site: Update your browser Ignore Circuits with Friends What is a circuit, and what

More information

External Hard Drive: A DFMA Redesign

External Hard Drive: A DFMA Redesign University of New Mexico External Hard Drive: A DFMA Redesign ME586: Design for Manufacturability Solomon Ezeiruaku 4-23-2013 1 EXECUTIVE SUMMARY The following document serves to illustrate the effects

More information

GNEG 1103 Introduction to Engineering Spring Assignment. Team Design Project. Selected Topic. Electric Boat. Team Members.

GNEG 1103 Introduction to Engineering Spring Assignment. Team Design Project. Selected Topic. Electric Boat. Team Members. Course 1 GNEG 1103 Introduction to Engineering Spring 2015 Assignment Team Design Project Selected Topic Electric Boat Team Members Alex Bonin Mario Diaz Instructor Dr. A. Stratigakis 2 Abstract As a team

More information

Autonomously Controlled Front Loader Senior Project Proposal

Autonomously Controlled Front Loader Senior Project Proposal Autonomously Controlled Front Loader Senior Project Proposal by Steven Koopman and Jerred Peterson Submitted to: Dr. Schertz, Dr. Anakwa EE 451 Senior Capstone Project December 13, 2007 Project Summary:

More information

Capstone Design Project: Developing the Smart Arm Chair for Handicapped People

Capstone Design Project: Developing the Smart Arm Chair for Handicapped People Capstone Design Project: Developing the Smart Arm Chair for Handicapped People Kwang Sun Kim 1, Jun Young Kim 2, Kyung Min Jang 3 and Kang Wo Joo 4 1 School of Mechatronics Engineering, Korea University

More information

INTRODUCTION Team Composition Electrical System

INTRODUCTION Team Composition Electrical System IGVC2015-WOBBLER DESIGN OF AN AUTONOMOUS GROUND VEHICLE BY THE UNIVERSITY OF WEST FLORIDA UNMANNED SYSTEMS LAB FOR THE 2015 INTELLIGENT GROUND VEHICLE COMPETITION University of West Florida Department

More information

Alternative Power Source for Dental Hygiene Device

Alternative Power Source for Dental Hygiene Device Alternative Power Source for Dental Hygiene Device By Nizar Almansouri Francisco Heath Ningbao Jiang Jiaqi Xie Jin Niu Submitted towards partial fulfillment of the requirements for Mechanical Engineering

More information

Common Bus and Line Regeneration

Common Bus and Line Regeneration Common Bus and Line Regeneration Addressing VFD applications when Regenerative Energy is Present Steve Petersen, Drives Technical Training Yaskawa America, Inc. Variable frequency drives (VFDs) are implemented

More information

Development of the automatic machine for tube end forming

Development of the automatic machine for tube end forming Development of the automatic machine for tube end forming Matjaž Sotler, machine manufacturing TPV d.d. ABSTRACT In this article I tried to demonstrate how company TPV d.d. progresses from stage of demand

More information

GNEG 1103 Introduction to Engineering FALL Team Design Project. Portable Phone Charger. Project Presentation. December 2, 2013, 8:00-9:15 A.

GNEG 1103 Introduction to Engineering FALL Team Design Project. Portable Phone Charger. Project Presentation. December 2, 2013, 8:00-9:15 A. 1 GNEG 1103 Introduction to Engineering FALL 2013 Team Design Project Portable Phone Charger Project Presentation December 2, 2013, 8:00-9:15 A.M Derek Richard, Jarod Brunick, Luis Ramirez, Mason Torgerson

More information

A device that measures the current in a circuit. It is always connected in SERIES to the device through which it is measuring current.

A device that measures the current in a circuit. It is always connected in SERIES to the device through which it is measuring current. Goals of this second circuit lab packet: 1 to learn to use voltmeters an ammeters, the basic devices for analyzing a circuit. 2 to learn to use two devices which make circuit building far more simple:

More information

NOTE All entries must be checked in upon arrival at MESA Day.

NOTE All entries must be checked in upon arrival at MESA Day. Hovercraft Challenge Level: Middle School Type of Contest: Team Composition of Team: 2 4 students per team Number of Teams: One entry per school Next Generation Science Standards: MS-ETS1-1., MS-ETS1-2.,

More information

Orbital Test Stand. By Mary Begay, Brett Booen, Calvin Boothe, James Ellis and Nicholas Garcia. Team 7. Project Proposal Document

Orbital Test Stand. By Mary Begay, Brett Booen, Calvin Boothe, James Ellis and Nicholas Garcia. Team 7. Project Proposal Document Orbital Test Stand By Mary Begay, Brett Booen, Calvin Boothe, James Ellis and Nicholas Garcia Team 7 Project Proposal Document Submitted towards partial fulfillment of the requirements for Mechanical Engineering

More information

SAE Mini BAJA: Suspension and Steering

SAE Mini BAJA: Suspension and Steering SAE Mini BAJA: Suspension and Steering By Zane Cross, Kyle Egan, Nick Garry, Trevor Hochhaus Team 11 Progress Report Submitted towards partial fulfillment of the requirements for Mechanical Engineering

More information

Detailed Design Review

Detailed Design Review Detailed Design Review Reciprocating Friction Tester : Armature Subsystem Thursday December 4th, 2014 1 : Armature Subsystem Eric Kutil (ME): Project Manager Specialty: Solid Modeling and Machining Chris

More information

ABB life cycle services Uninterruptible power supplies

ABB life cycle services Uninterruptible power supplies ABB life cycle services Uninterruptible power supplies 2 ABB Life cycle brochure UPS service portfolio Life cycle services for uninterruptible power supplies As your service partner, ABB guarantees you

More information

Basic voltmeter use. Resources and methods for learning about these subjects (list a few here, in preparation for your research):

Basic voltmeter use. Resources and methods for learning about these subjects (list a few here, in preparation for your research): Basic voltmeter use This worksheet and all related files are licensed under the Creative Commons Attribution License, version 1.0. To view a copy of this license, visit http://creativecommons.org/licenses/by/1.0/,

More information

Implementation of a Grid Connected Solar Inverter with Maximum Power Point Tracking

Implementation of a Grid Connected Solar Inverter with Maximum Power Point Tracking ECE 4600 GROUP DESIGN PROJECT PROGRESS REPORT GROUP 03 Implementation of a Grid Connected Solar Inverter with Maximum Power Point Tracking Authors Radeon Shamilov Kresta Zumel Valeria Pevtsov Reza Fazel-Darbandi

More information

Test Plans & Test Results

Test Plans & Test Results P10227 Variable Intake System for FSAE Race Car Test Plans & Test Results By: Dave Donohue, Dan Swank, Matt Smith, Kursten O'Neill, Tom Giuffre Table of contents 1. MSD I: WKS 8-10 PRELIMINARY TEST PLAN...

More information

SUBJECT AREA(S): Amperage, Voltage, Electricity, Power, Energy Storage, Battery Charging

SUBJECT AREA(S): Amperage, Voltage, Electricity, Power, Energy Storage, Battery Charging Solar Transportation Lesson 4: Designing a Solar Charger AUTHOR: Clayton Hudiburg DESCRIPTION: In this lesson, students will further explore the potential and challenges related to using photovoltaics

More information

CHOOSING THE RIGHT POWER MODULE FOR INVERTER DESIGNS. By Mark Steinmetz, Field Applications Engineer Vincotech GmbH

CHOOSING THE RIGHT POWER MODULE FOR INVERTER DESIGNS. By Mark Steinmetz, Field Applications Engineer Vincotech GmbH CHOOSING THE RIGHT POWER MODULE FOR INVERTER DESIGNS By Mark Steinmetz, Field Applications Engineer Vincotech GmbH As Solar and UPS companies start to discuss the next generation inverter products, many

More information

AC : HYBRID MINI-BAJA CAR PROJECT

AC : HYBRID MINI-BAJA CAR PROJECT AC 2007-1591: HYBRID MINI-BAJA CAR PROJECT Michael Rudisill, Northern Michigan University Jesse Racine, Northern Michigan University Tim Nelson, Northern Michigan University Michael Truscott, Northern

More information

Highly dynamic control of a test bench for highspeed train pantographs

Highly dynamic control of a test bench for highspeed train pantographs PAGE 26 CUSTOMERS Highly dynamic control of a test bench for highspeed train pantographs Keeping Contact at 300 km/h Electric rail vehicles must never lose contact with the power supply, not even at the

More information

How to: Test & Evaluate Motors in Your Application

How to: Test & Evaluate Motors in Your Application How to: Test & Evaluate Motors in Your Application Table of Contents 1 INTRODUCTION... 1 2 UNDERSTANDING THE APPLICATION INPUT... 1 2.1 Input Power... 2 2.2 Load & Speed... 3 2.2.1 Starting Torque... 3

More information

Synthesis of Optimal Batch Distillation Sequences

Synthesis of Optimal Batch Distillation Sequences Presented at the World Batch Forum North American Conference Woodcliff Lake, NJ April 7-10, 2002 107 S. Southgate Drive Chandler, Arizona 85226-3222 480-893-8803 Fax 480-893-7775 E-mail: info@wbf.org www.wbf.org

More information

M.A.R.S - Mechanized Air Refilling System

M.A.R.S - Mechanized Air Refilling System M.A.R.S - Mechanized Air Refilling System P.Omprakash 1, T.Senthil Kumar 2 1 Assistant Professor 1,2 Velammal College of Engineering and Technology, Madurai Abstract: Every section of an automobile is

More information

2 nd Generation Charging Station

2 nd Generation Charging Station 2 nd Generation Charging Station By Jasem Alhabashy, Riyadh Alzahrani, Brandon Gabrelcik, Ryan Murphy and Ruben Villezcas Team 13 Progress Report for ME486c Document Submitted towards partial fulfillment

More information

Fully Regenerative braking and Improved Acceleration for Electrical Vehicles

Fully Regenerative braking and Improved Acceleration for Electrical Vehicles Fully Regenerative braking and Improved Acceleration for Electrical Vehicles Wim J.C. Melis, Owais Chishty School of Engineering, University of Greenwich United Kingdom Abstract Generally, car brake systems

More information

SAE Baja - Drivetrain

SAE Baja - Drivetrain SAE Baja - Drivetrain By Ricardo Inzunza, Brandon Janca, Ryan Worden Team 11A Concept Generation and Selection Document Submitted towards partial fulfillment of the requirements for Mechanical Engineering

More information

Phase 1 Workshop Home Study Guide

Phase 1 Workshop Home Study Guide Phase 1 Workshop Home Study Guide Vehicle Electrical-Electronics Troubleshooting Training Written and Developed by Vince Fischelli Director of Training Veejer Enterprises Inc. / Garland, Texas U.S.A. Phone:

More information

Impact of Reflectors on Solar Energy Systems

Impact of Reflectors on Solar Energy Systems Impact of Reflectors on Solar Energy Systems J. Rizk, and M. H. Nagrial Abstract The paper aims to show that implementing different types of reflectors in solar energy systems, will dramatically improve

More information

PROJECT IDEA SUBMISSION

PROJECT IDEA SUBMISSION PROJECT IDEA SUBMISSION Team Contacts - 1 st person listed serves as the point of contact with Professor Nelson - Initial team size may be from 1 to 6 members (all members must agree to have their name

More information

DYNAMO & ALTERNATOR - B FIELD LOGIC PROBE.

DYNAMO & ALTERNATOR - B FIELD LOGIC PROBE. DYNAMO & ALTERNATOR - B FIELD LOGIC PROBE. H. HOLDEN 2010. Background: This article describes the development and construction of a simple diagnostic tool - a self powered logic probe, to assess the voltage

More information

Laser Tag Droid. Jake Hamill, Martin Litwiller, Christian Topete ECE 445 Project Proposal

Laser Tag Droid. Jake Hamill, Martin Litwiller, Christian Topete ECE 445 Project Proposal Laser Tag Droid Jake Hamill, Martin Litwiller, Christian Topete ECE 445 Project Proposal 1. Introduction 1.1 Objective Our proposed project is to design, build, and test a remote control laser tag droid

More information

Retrofitting unlocks potential

Retrofitting unlocks potential 54 ABB REVIEW SERVICE AND RELIABILITY SERVICE AND RELIABILITY Retrofitting unlocks potential A modern approach to life cycle optimization for ABB s drives delivers immediate performance improvement and

More information

SPRING (FINAL) TERM REPORT ENTITLED: THYRISTORS CONTROLLED CONVERTER FOR LINE COMPENSATION

SPRING (FINAL) TERM REPORT ENTITLED: THYRISTORS CONTROLLED CONVERTER FOR LINE COMPENSATION SPRING (FINAL) TERM REPORT SUBMITTED TO: Dr. CHIKAODINAKA NWANKPA AND THE SENIOR DESIGN PROJECT FACULTY OF DREXEL UNIVERSITY ENTITLED: THYRISTORS CONTROLLED CONVERTER FOR LINE COMPENSATION PROJECT NUMBER:

More information

M3 Design Product Teardown Ameda Purely Yours Breast Pump

M3 Design Product Teardown Ameda Purely Yours Breast Pump 28 Sep, 2010 Why do the product teardowns? M3 Design Product Teardown Ameda Purely Yours Breast Pump Part of the product development process is to apply knowledge gained from prior experience during the

More information

Lesson Plan 11 Electric Experiments

Lesson Plan 11 Electric Experiments Lesson Plan 11 Electric Experiments Brief description Students experiment with aluminium foil, batteries and cheap, readily availably low voltage light bulbs* to construct a simple conductivity tester.

More information

BASIC ELECTRICAL MEASUREMENTS By David Navone

BASIC ELECTRICAL MEASUREMENTS By David Navone BASIC ELECTRICAL MEASUREMENTS By David Navone Just about every component designed to operate in an automobile was designed to run on a nominal 12 volts. When this voltage, V, is applied across a resistance,

More information

Ensuring the Safety Of Medical Electronics

Ensuring the Safety Of Medical Electronics Chroma Systems Solutions, Inc. Ensuring the Safety Of Medical Electronics James Richards, Marketing Engineer Keywords: 19032 Safety Analyzer, Medical Products, Ground Bond/Continuity Testing, Hipot Testing,

More information

A Team-based ECET Capstone Project: Design and Implementation of a Solar Insolation Measurement System

A Team-based ECET Capstone Project: Design and Implementation of a Solar Insolation Measurement System A Team-based ECET Capstone Project: Design and Implementation of a Solar Insolation Measurement System Abstract This paper describes an example of the successful design and implementation of a Portable

More information

2020 Proposal Plan: Battery Drop Off Recycling. A Proposal Plan for ENVL 4300 Professor: Tait Chirenje

2020 Proposal Plan: Battery Drop Off Recycling. A Proposal Plan for ENVL 4300 Professor: Tait Chirenje 2020 Proposal Plan: Battery Drop Off Recycling A Proposal Plan for ENVL 4300 Professor: Tait Chirenje Matt Cole, Andrew Lindsay, Tim Pagan Environmental Issues: ENVL 4300 Stockton University April 28,

More information

Using ABAQUS in tire development process

Using ABAQUS in tire development process Using ABAQUS in tire development process Jani K. Ojala Nokian Tyres plc., R&D/Tire Construction Abstract: Development of a new product is relatively challenging task, especially in tire business area.

More information

Battery to supply nonstop energy to load at the same time contingent upon the accessibility of the vitality sources. In

Battery to supply nonstop energy to load at the same time contingent upon the accessibility of the vitality sources. In ISSN: 0975-766X CODEN: IJPTFI Available Online through Research Article www.ijptonline.com MONITORING AND CONTROL OF HYBRID ENERGY SOURCE SCHEME FOR GREEN ENVIRONMENT IN CHEMICAL AND PHARMACEUTICAL INDUSTRIES

More information

Materials: 1 block of Styrofoam ruler 20 cm of magnetic tape box cutter magnetic track for testing

Materials: 1 block of Styrofoam ruler 20 cm of magnetic tape box cutter magnetic track for testing Maglev Car Design Objective: Design, build, and modify Styrofoam vehicles to race down a magnetic track at the fastest speed. Materials: 1 block of Styrofoam ruler 20 cm of magnetic tape box cutter stopwatch

More information

Can You Light the Bulb?

Can You Light the Bulb? 3-5 Physical Science Southern Nevada Regional Professional Development Program Can You Light the Bulb? INTRODUCTION Electrical energy is easily transferred through loops that we call circuits. This activity

More information

Solar Kit Lesson #13 Solarize a Toy

Solar Kit Lesson #13 Solarize a Toy UCSD TIES adapted from NYSERDA Energy Smart www.schoolpowernaturally.org Solar Kit Lesson #13 Solarize a Toy TEACHER INFORMATION LEARNING OUTCOME After designing and constructing solar electric power sources

More information

Academic Course Description

Academic Course Description BEE305- ELECTRICAL MACHINES Academic Course Description BHARATH UNIVERSITY Faculty of Engineering and Technology Department of Electrical and Electronics Engineering BEE305- ELECTRICAL MACHINES Third Semester,

More information

Battery Technology for Data Centers and Network Rooms: Site Planning

Battery Technology for Data Centers and Network Rooms: Site Planning Battery Technology for Data Centers and Network Rooms: Site Planning White Paper # 33 Executive Summary The site requirements and costs for protecting information technology and network environments are

More information

High-Voltage Power Lines - WHY?

High-Voltage Power Lines - WHY? Session 3247 High-Voltage Power Lines - WHY? Walter Banzhaf, P.E. College of Engineering, Technology, and Architecture University of Hartford, West Hartford, CT 06117 Introduction Electrical utility companies

More information

EDSGN 100. Folding Shopping Cart

EDSGN 100. Folding Shopping Cart EDSGN 100 Introduction to Engineering Design Section 0, Team #1 Folding Shopping Cart http://www.personal.psu.edu/jzb31/edsgn100_su16_section0_team1_dp1.pdf Submitted by: Jacob Barclay, Abhishek Ganta,

More information

BTX Extractive Distillation Capacity Increased by Enhanced Packing Distributors

BTX Extractive Distillation Capacity Increased by Enhanced Packing Distributors BTX Extractive Distillation Capacity Increased by Enhanced Packing Distributors Karl Kolmetz kkolmetz@yahoo.com Jeff Gray jeffngray@hotmail.com Mel Chua Sulzer Chemtech Raghu Desai Sulzer Chemtech AIChE

More information

VARIABLE DISPLACEMENT OIL PUMP IMPROVES TRACKED VEHICLE TRANSMISSION EFFICIENCY

VARIABLE DISPLACEMENT OIL PUMP IMPROVES TRACKED VEHICLE TRANSMISSION EFFICIENCY 2018 NDIA GROUND VEHICLE SYSTEMS ENGINEERING AND TECHNOLOGY SYMPOSIUM POWER & MOBILITY (P&M) TECHNICAL SESSION AUGUST 7-9, 2018 NOVI, MICHIGAN VARIABLE DISPLACEMENT OIL PUMP IMPROVES TRACKED VEHICLE TRANSMISSION

More information

RB-Mel-03. SCITOS G5 Mobile Platform Complete Package

RB-Mel-03. SCITOS G5 Mobile Platform Complete Package RB-Mel-03 SCITOS G5 Mobile Platform Complete Package A professional mobile platform, combining the advatages of an industrial robot with the flexibility of a research robot. Comes with Laser Range Finder

More information

Simple Free-Energy Devices

Simple Free-Energy Devices Simple Free-Energy Devices There is nothing magic about free-energy and by free-energy I mean something which produces output energy without the need for using a fuel which you have to buy. Chapter 5:

More information

Higher Level. Junior Certificate Technology. Design Folio. Year. Design Task. Examination Number. School Roll Number 68261G

Higher Level. Junior Certificate Technology. Design Folio. Year. Design Task. Examination Number. School Roll Number 68261G Junior Certificate Technology Higher Level Design Folio Year Design Task 2009 A Examination Number School Roll Number 148416 68261G Note: The content layout in this exemplar design folio follow the headings

More information

HOW TO MAKE YOUR OWN BATTERIES

HOW TO MAKE YOUR OWN BATTERIES HOW TO MAKE YOUR OWN BATTERIES 1 Page TABLE OF CONTENTS Introduction....3 Usage....4 Aluminum Can Batteries/Cells....8 A Long Lasting, Yet Powerful Battery....10 PVC Pipe Batteries...13 Lab Notes....17

More information

How Regenerative Braking Works

How Regenerative Braking Works Feature How Regenerative Braking Works The regenerative braking systems on Nissan hybrid vehicles can be confusing and misunderstood. Let s take a look at how these systems really work. 26 Nissan TechNews

More information

High Energy Hydrogen II Teacher Page

High Energy Hydrogen II Teacher Page High Energy Hydrogen II Teacher Page Hands-On Hydrogen Race The Chassis Student Objective The student given a problem scenario regarding the materials being used in a design, will be able to predict how

More information

IT'S MAGNETIC (1 Hour)

IT'S MAGNETIC (1 Hour) IT'S MAGNETIC (1 Hour) Addresses NGSS Level of Difficulty: 4 Grade Range: 3-5 OVERVIEW In this activity, students will create a simple electromagnet using a nail, a battery, and copper wire. They will

More information

B&W Turnover Ball Installation

B&W Turnover Ball Installation B&W Turnover Ball Installation by Flopster843 02 Jan 2012 I wanted to start this article out by stating one very important thing. Installing a gooseneck hitch is not a task to be taken lightly. If you

More information

Development of Relief Valve Automatic assembly technology

Development of Relief Valve Automatic assembly technology Development of Relief Valve Automatic assembly technology Technology Explanation Development of Relief Valve Automatic assembly technology TAKIGUCHI Masaki Abstract Construction machinery is equipped with

More information

Alan Kilian Spring Design and construct a Holonomic motion platform and control system.

Alan Kilian Spring Design and construct a Holonomic motion platform and control system. Alan Kilian Spring 2007 Design and construct a Holonomic motion platform and control system. Introduction: This project is intended as a demonstration of my skills in four specific areas: Power system

More information

(18pt) 1. Introduction. (9pt) Abstract

(18pt) 1. Introduction. (9pt) Abstract (9pt) Mechanical jigs and fixtures Solutions for more reliability and accuracy (10pt) Mechanical Engineering (12pt) (18pt) Patrick Bachmann 1* and Markus Embacher 2 (9 pt) 1 Team Schmidis Armee, HTBLA

More information

World Scientific Research Journal (WSRJ) ISSN: Multifunctional Controllable and Detachable Bicycle Power Generation /

World Scientific Research Journal (WSRJ) ISSN: Multifunctional Controllable and Detachable Bicycle Power Generation / World Scientific Research Journal (WSRJ) ISSN: 2472-3703 www.wsr-j.org Multifunctional Controllable and Detachable Bicycle Power Generation / Charging Device Yunxia Ye School of North China Electric Power

More information

Electrical Controls. Syllabus

Electrical Controls. Syllabus Instructor: Jeremie Hedges (757)651-1007 Contact Hours: 72 hours Prerequisites: None Electrical Controls Syllabus Course Description: This course is designed to present a blend of electrical theory and

More information

Reliable Reach. Robotics Unit Lesson 4. Overview

Reliable Reach. Robotics Unit Lesson 4. Overview Robotics Unit Lesson 4 Reliable Reach Overview Robots are used not only to transport things across the ground, but also as automatic lifting devices. In the mountain rescue scenario, the mountaineers are

More information

Hidden Savings in Modern Manufacturing

Hidden Savings in Modern Manufacturing JARVIS CUTTING TOOLS CAPABILITIES Hidden Savings in Modern Manufacturing Five lessons from companies that found millions in hidden savings through simple, previously-overlooked changes to their manufacturing

More information

Sensor Suit for the Visually Impaired

Sensor Suit for the Visually Impaired Sensor Suit for the Visually Impaired Proposed Completion Date 2013 People today that are visually impaired at birth or by misfortune have few options for methods of getting around in their every-day lives.

More information

AC : AC-POWERED BACKPACK PROJECT

AC : AC-POWERED BACKPACK PROJECT AC 2007-1688: AC-POWERED BACKPACK PROJECT David McStravick, Rice University DAVID MCSTRAVICK received his B. S. and Ph. D. degrees in mechanical engineering from Rice University. He worked in industry

More information

A Concept Paper. Researchers: Dr. Benjamin G. Quito Dr. Villamor S. Quebral Dr. Edna C Aquino

A Concept Paper. Researchers: Dr. Benjamin G. Quito Dr. Villamor S. Quebral Dr. Edna C Aquino Road Safety and Traffic Education (RoSTed): The Institutionalization, Certification, and Standardization of Road Safety and Traffic Education in the Philippines A Concept Paper Researchers: Dr. Benjamin

More information

PROJECT IDEA SUBMISSION STUDENT

PROJECT IDEA SUBMISSION STUDENT PROJECT IDEA SUBMISSION STUDENT Team Contacts - 1 st person listed serves as the point of contact with Professor Jensen - Initial team size may be from 4 to 6 members (all members must agree to have their

More information

A Travel Aid for the Blind. Introduction to engineering design GE105

A Travel Aid for the Blind. Introduction to engineering design GE105 A Travel Aid for the Blind Introduction to engineering design GE105 Presented by Supervised by Presentation Planning Introduction. Definition the problem. Need analysis. Primary objectives. Secondary object.

More information

Second Generation Bicycle Recharging Station

Second Generation Bicycle Recharging Station Second Generation Bicycle Recharging Station By Jasem Alhabashy, Riyadh Alzahrani, Brandon Gabrelcik, Ryan Murphy and Ruben Villezcas Team 13 Final Report For ME486c Document Submitted towards partial

More information

L-force. MF three-phase AC motors. Phone: Fax: Web: -

L-force. MF three-phase AC motors. Phone: Fax: Web:  - L-force MF three-phase AC motors Suheadline TheMix Simply B7 bold multiple negativ Optimised for frequency inverter operation 2 More than a third of newly installed three-phase AC motors are now operated

More information

Fourth Grade. Multiplication Review. Slide 1 / 146 Slide 2 / 146. Slide 3 / 146. Slide 4 / 146. Slide 5 / 146. Slide 6 / 146

Fourth Grade. Multiplication Review. Slide 1 / 146 Slide 2 / 146. Slide 3 / 146. Slide 4 / 146. Slide 5 / 146. Slide 6 / 146 Slide 1 / 146 Slide 2 / 146 Fourth Grade Multiplication and Division Relationship 2015-11-23 www.njctl.org Multiplication Review Slide 3 / 146 Table of Contents Properties of Multiplication Factors Prime

More information

ROCKET TEAM: DESIGN PACKAGE

ROCKET TEAM: DESIGN PACKAGE Reusable Ignition Tests Chemical Ignition Test- Gas and Igniter System Objective: Our team is trying to find a reusable ignition system by means of a chemical lighting Apparatus: Using a butane lighter,

More information

THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF MECHANICAL AND NUCLEAR ENGINEERING

THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF MECHANICAL AND NUCLEAR ENGINEERING THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF MECHANICAL AND NUCLEAR ENGINEERING DEVELOPMENT OF A SCALED-DOWN SERIES HYBRID VEHICLE FOR EDUCATION IN VEHICLE HYBRIDIZATION AND

More information

Fly Rocket Fly: Design Lab Report. The J Crispy and The Airbus A

Fly Rocket Fly: Design Lab Report. The J Crispy and The Airbus A Fly Rocket Fly: Design Lab Report The J Crispy and The Airbus A380 800 Rockets: Test 1 Overall Question: How can you design a water, bottle rocket to make it fly a maximum distance. It needs to be made

More information

VT2+: Further improving the fuel economy of the VT2 transmission

VT2+: Further improving the fuel economy of the VT2 transmission VT2+: Further improving the fuel economy of the VT2 transmission Gert-Jan Vogelaar, Punch Powertrain Abstract This paper reports the study performed at Punch Powertrain on the investigations on the VT2

More information

Virtual Ground for HV Boosters Calibration

Virtual Ground for HV Boosters Calibration Dear all utracer users, I m writing these lines just to share my experience building my utracer, so that maybe someone could find it useful for his design. The construction of my utracer was very simple,

More information

Supervised Learning to Predict Human Driver Merging Behavior

Supervised Learning to Predict Human Driver Merging Behavior Supervised Learning to Predict Human Driver Merging Behavior Derek Phillips, Alexander Lin {djp42, alin719}@stanford.edu June 7, 2016 Abstract This paper uses the supervised learning techniques of linear

More information

USING INSPIRE AS AN UPFRONT DESIGN, OPTIMIZATION & SIMULATION TOOL FOR EXISITNG MANUAL GEARBOX COMPONENTS

USING INSPIRE AS AN UPFRONT DESIGN, OPTIMIZATION & SIMULATION TOOL FOR EXISITNG MANUAL GEARBOX COMPONENTS USING INSPIRE AS AN UPFRONT DESIGN, OPTIMIZATION & SIMULATION TOOL FOR EXISITNG MANUAL GEARBOX COMPONENTS Lokesh Kumar Gupta Manager Drive Line Eicher Polaris Plot- SP1 & 2, Kukas Jaipur India 302028 Lkgupta@eicherpolaris.in

More information

Overcurrent protection

Overcurrent protection Overcurrent protection This worksheet and all related files are licensed under the Creative Commons Attribution License, version 1.0. To view a copy of this license, visit http://creativecommons.org/licenses/by/1.0/,

More information

ELECTRICITY ELECTRICITY. Copyright 2016 Cyber Innovation Center. All Rights Reserved. Not for Distribution.

ELECTRICITY ELECTRICITY. Copyright 2016 Cyber Innovation Center. All Rights Reserved. Not for Distribution. TEACHER STUDENT EDITION MANUAL ELECTRICITY ELECTRICITY www.nicerc.org Welcome to STEM EDA! STEM Explore, Discover, Apply (STEM EDA) is designed as a three course progression through STEM (science, technology,

More information