1 Demand Response Auction () Minutes of Meeting Date held: October 1, 2014 Time held: 1:00 pm 4:00 pm Location held: Toronto Congress Centre Invited/Attended Company Name Attendance Status (A)ttended; (T)eleconference Fonger, Jim Ameresco A Mortage, Hamza AMPCO A Wu, Julien Brookfield Renewable Energy Group A Villegas, Gabriel Bruce Power A Chihata, Bill City of Toronto A Morris, Richard City of Toronto A Koff, Chaim City of Toronto T Dobson, Jonathan Conestoga Cold Storage A Scott, Trevor Conestoga Cold Storage A Chintapalli, Raj Customized Energy Solutions T Tinkler, Mark Customized Energy Solutions A Wang, Cynthia Delta Energy LLC T Silva, Carlos Enbala A Jayaraman, Jay Enbridge A Pieniazek, Marie Energy Curtailment Specialists Inc. A Griffiths, Sarah EnerNOC, Inc. A Paul, Rob Goreway Station Partnership T Martell, Ed Holcim (US) Inc. T Plante, Matthieu HQ Energy Marketing Inc. A Yakupova, Kelima London Economics T Ronson, Peter Markham District Energy T Kersman, Paul Ministry of Energy A Qureshi, Musab Ministry of Energy A Tuck, Jennifer NextEra Energy Canada, ULC A DiRuscio, Carmine NRG Matters Corp. A Gibbons, Jack Ontario Clean Air Alliance A Brown, David Ontario Energy Board A Chen, Simon Ontario Power Authority A Byers, Darren Ontario Power Authority A McNally, Julia Ontario Power Authority A Peterson, David Ontario Power Generation A Kuriychuk, Michael Pathchoice Energy Consulting Inc. A October 28, 2014 Public Page 1 of 5
2 Date held: October 1, 2014 Time held: 1:00 pm 4:00 pm Location held: Toronto Congress Centre Invited/Attended Company Name Attendance Status (A)ttended; (T)eleconference Cumming, Alison Power Advisory LLC A Burnham, Steve RBC Capital Markets T Doolittle, Robin RBC Capital Markets T Degelman, Cara Resolute Forest Products A Langill, Jane Rodan Energy Solutions Inc. T Ingram, Rachel Rodan Energy Solutions Inc. A Dudka, Marko Rodan Energy Solutions Inc. A Grod, Paul Rodan Energy Solutions Inc. T Kerr, Paul Shell Energy T Soufi, Safouh SMS Energy Engineering A Hilbig, Tom Sygration A Laflamme, Serge Tembec A Clarke, Alan The New Energy Group A Nguyen, Thanh TransAlta T Kuntz, Margaret TransCanada A Lithgow, Michael The Regional Municipality of York A Alford, Mike Z3 Controls Inc. A Backman, Karen IESO T Bruno, Juliana IESO A Campbell, Alexandra IESO T De Matos, Nuno IESO A Dow, Andrew IESO T Drake, Gordon IESO A Grbavac, Jason IESO A Harrison, Susan IESO A Kwok, Jason IESO A Murray, Patricia IESO T Wright-Hilbig, Rhonda IESO A Scribe: Brennan Louw, Market Development Advisor, IESO Please report any corrections, additions or deletions to scribe. All meeting material is available on the IESO web site at: October 28, 2014 Public Page 2 of 5
3 This was the first meeting of the Demand Response (DR) Auction Stakeholder Engagement. The session introduced how the auction would be developed, proposed a number of design features, and gave stakeholders an opportunity to provide input on the specific elements introduced. Item 1 Welcome Remarks Susan Harrison and Brian Rivard of the IESO welcomed attendees to the session. Introductory remarks included an update on the IESO s progress with DR to date and comments on how development of the DR Auction and Capacity Auction would be occurring in parallel. Best efforts will be made to align the two initiatives but, at times, different solutions for each may be most appropriate. Item 2 Presentations Gordon Drake of the IESO presented on timelines for the stakeholder engagement. The presentation highlighted the need for regular SE meetings throughout the fall of 2014 in order to move to the design and implementation phase in January Jason Kwok and Juliana Bruno of the IESO presented on a number of the design elements to be included in the DR Auction. Presentations focused on the MW target, participant authorization, and capacity qualification for the DR Auction. Gordon Drake of the IESO presented on DR Auction reports. The presentation outlined the type of information that would be included in both pre- and post-auction reports. Stakeholder Questions and Comments, with IESO responses in italics: An attendee asked how DR Auction design elements will align with the Capacity Auction stakeholder engagement. The IESO responded that the DR Auction will be designed based on the same principles as the Capacity Auction but with a unique DR-specific perspective. In some cases the approach taken in the DR Auction will differ from the Capacity Auction. An example of this is the forward period. In the DR Auction a forward period can be chosen to meet DR-specific requirements while in a Capacity Auction the forward period will consider all resource types. The internal DR Auction and Capacity Auction design teams are working closely together to coordinate their efforts. An attendee asked if DR resources that clear in the auction would be paid the price at which they bid or the price at which the auction clears. The IESO indicated that cleared resources will receive the same auction clearing price unless there are locational constraints. October 28, 2014 Public Page 3 of 5
4 An attendee asked if the DR Auction will continue after the Capacity Auction and how DR Auction elements might be incorporated into the Capacity Auction. The IESO responded that once the Capacity Auction is in place, the DR Auction will not continue and DR resources will move into the Capacity Auction. The Capacity Auction will consider what is developed in the DR Auction as a starting point but design elements may ultimately differ between the two. An attendee asked how the Long-Term Energy Plan target for DR is reflected in the Capacity Auction. The IESO responded that the Long-Term Energy Plan target for DR is 10% of peak demand and that this target was set based on the expected competitiveness of DR in meeting system needs. With the DR Auction the cost curve for DR will continue to be bent and we will move away from a proscribed quantity to a more competitive process. An attendee asked how new aggregators will enter the auction process and what type of information they will need to provide. The IESO answered that the process will be similar for new or existing aggregators which will both need to provide data on the loads that will be included in their portfolios. While new entrants will be welcomed, eligibility requirements will be established to provide reasonable assurance that a resource can provide the capacity to which it has committed. An attendee asked how resources that clear in the DR Auction will participate in the energy market. The IESO responded that resources that clear in the auction will be required to participate in the energy market. Revenue from the DR Auction will provide an availability-type payment and resources will offer into the energy market and operating reserve market at a price that will allow them to be effectively dispatched relative to other resources. How DR resources will participate in the energy market will be discussed in more detail in meeting 3. An attendee asked if there will be a minimum requirement for what a resource can bid into the DR Auction. The IESO indicated that there will be a minimum size to participate in the auction, the size will be specified later in the design process, and stakeholder feedback on this question would be welcome. An attendee asked if a baseline methodology has been defined yet and if it will be the same as the DR3 baseline. The IESO responded that a baseline has not yet been set. The topic will be discussed at a later meeting and the DR3 baseline will provide a starting point for considering the appropriate methodology. October 28, 2014 Public Page 4 of 5
5 An attendee asked how a resource s response time might be reflected in the DR Auction. The IESO answered that the DR Auction will not consider operational characteristics. The purpose of the auction is to procure capacity not ramp ability. While ramp ability certainly has value it should be reflected in other markets not through DR Auction capacity payments. Participants will need to consider all potential revenue streams when establishing an offer price for the DR Auction. An attendee asked how potential shorter response times for automated dispatchable load are being considered. The IESO responded that DR pilot programs are looking at load response on different timelines. Learnings from those programs will be incorporated into future auctions. Item 3 Wrap up and Next Steps Susan Harrison of the IESO thanked members for their participation and noted that, given the tight timelines for the engagement, the IESO s goal is to provide materials by three days before meetings. October 28, 2014 Public Page 5 of 5
Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic
1. Introduction The Canadian Solar Industries Association (CanSIA) is a national trade association that represents the solar energy industry throughout Canada. CanSIA s vision is for solar energy to be
More informationOverview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only
Overview of Electricity Trade Agreement between Québec and Ontario May 10, 2017 For Information Purposes Only Purpose To provide an overview of the electricity trade agreement between the Independent Electricity
More informationSolar-Wind Specific Request for Proposals
Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality
More informationProviding Options: Program Design Focusing on Customer Choice
www.peakload.org Providing Options: Program Design Focusing on Customer Choice Jason Hall, Colorado Springs Utilities Greg Wassel, Franklin Energy November 14, 2018 Colorado Springs Utilities Four-service
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationEvaluating Stakeholder Engagement
Evaluating Stakeholder Engagement Peace River October 17, 2014 Stakeholder Engagement: The Panel recognizes that although significant stakeholder engagement initiatives have occurred, these efforts were
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationUnitil Energy Demand Response Demonstration Project Proposal October 12, 2016
Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Fitchburg Gas and Electric Light Company d/b/a Unitil ( Unitil or the Company ) indicated in the 2016-2018 Energy Efficiency
More informationConsiderations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016
Considerations for Municipal Solar Projects Ben Frevert Larsen Engineers November 16, 2016 Topic Areas Benefits of going green / solar Actions local governments can take Programs and incentives Implementation
More informationSunnyside Yard Master Plan. RFQ Information Session September 13, 2017
Sunnyside Yard Master Plan RFQ Information Session September 13, 2017 Agenda 1. Introduction by Tom McKnight 2. Context for the Sunnyside Yard Master Plan 3. RFQ Process 4. Questions Sunnyside Yard in
More informationEnergy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities
Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities By: Nasser Kutkut, PhD, DBA Advanced Charging Technologies
More informationUpdates. Pat Reiten President and CEO, PacifiCorp Transmission
PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand
More informationWelcome. PJM 2016
Welcome 1 Welcome, Overview of Agenda and Housekeeping Stu Bresler Senior VP, Operations and Markets PJM Interconnection Agenda- Morning 8:00 a.m. Continental Breakfast 9:00 a.m. Plenary Session Opening
More informationSouthern California Edison
Recent Energy Storage Projects November 8, 2017 Presented by Kern Economic Development Corporation 1 Agenda 1. California Energy Trends and Recent Events 2. SCE s Storage Projects California Energy Trends
More informationEnergy Storage Integration
Energy Storage Integration Market Concepts James Pigeon Senior Market Design Specialist, Distributed Resources Integration MIWG September 29, 2016 Krey Corporate Center, Rensselaer, NY 2000-2016 New York
More informationRecharge Kick-off Meeting Recharge Activity Review Process for
Recharge Kick-off Meeting Debra Fry Executive Director, Operating Budget and Recharge Review Gabriella Hato Manager, Recharge Review Sarah Hislen Analyst, Recharge Review Charet Wynn Analyst, Recharge
More informationGenbright LLC. AEE Technical Round Table 11/15/2017
Genbright LLC AEE Technical Round Table 11/15/2017 About Genbright Founded in 2013, Genbright was created to develop and monetize distributed energy technologies across the power industry including distributed
More informationThe Gambia National Forum on
The Gambia National Forum on Renewable Energy Regulation Kairaba Hotel, The Gambia January 31 February 1, 2012 Tariff and Price Regulation of Renewables Deborah Erwin Public Service Commission of Wisconsin
More informationFlexible Ramping Product Technical Workshop
Flexible Ramping Product Technical Workshop September 18, 2012 Lin Xu, Ph.D. Senior Market Development Engineer Don Tretheway Senior Market Design and Policy Specialist Agenda Time Topic Presenter 10:00
More informationAGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.
AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome
More informationElectricity Demand Reduction Pilot BSRIA. Charlie Lewis, DECC 25 March 2014
Electricity Demand Reduction Pilot BSRIA Charlie Lewis, DECC 25 March 2014 Efficiency at the heart of a low carbon economy Energy Efficiency belongs at the heart of a lowcarbon economy. By reducing energy
More informationEnergy Storage and Distributed Energy Resources Phase 3 (ESDER 3)
Energy Storage and Distributed Energy Resources Phase 3 (ESDER 3) Straw Proposal Technical Working Group March 9, 018 10 a.m. 4 p.m. (Pacific Standard Time) Agenda Time Item Speaker 10:00-10:10 Stakeholder
More informationDistributed Energy Storage John Steigers Generation Project Development Energy / Business Services
1 Distributed Energy Storage John Steigers Generation Project Development Energy / Business Services 2 2 Distributed Energy Storage Sited within Utility & Serving One or More Value Propositions Peak Shaving
More informationISO on Background. Energy-efficiency forecast. Anne George. Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING DECEMBER 12, 2012
DECEMBER 12, 2012 ISO on Background Energy-efficiency forecast Anne George VICE PRESIDENT, EXTERNAL AFFAIRS &CORPORATE COMMUNICATIONS Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING Agenda 11:00-11:05
More informationElectricity Transmission Infrastructure Development in New England
Electricity Transmission Infrastructure Development in New England NPCC Governmental/Regulatory Affairs Advisory Group Paul G. Afonso March 4, 2008 Transmission Infrastructure is Playing An Increasingly
More informationCalifornia s RPS Program: Progress Towards California s 33% RPS Goal and the Role of Concentrating Solar Power CSP Conference
California s RPS Program: Progress Towards California s 33% RPS Goal and the Role of Concentrating Solar Power CSP Conference Presented by Edward Randolph Energy Division Director, California Public Utilities
More informationRhode Island Division of Public Utilities and Carriers & Office of Energy Resources. Power Sector Transformation
1 Rhode Island Division of Public Utilities and Carriers & Office of Energy Resources Power Sector Transformation Notice of Inquiry into the Electric Utility Business Model and Request for Stakeholder
More informationENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO
ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO Cam Carver CEO, Temporal Power Ltd. Corporate Overview Temporal Power, a Ontario based company, is a global leader in the development
More informationCity of Philadelphia Renewable Energy Power Purchasing RFP Pre-Proposal Meeting
City of Philadelphia Renewable Energy Power Purchasing RFP Pre-Proposal Meeting City Energy Office October 25, 2017 For Participants on the Phone Follow along with slides posted at: http://www.philaenergy.org/public_bids/renewable-energypower-purchasing-agreement-request-for-proposal/
More informationNet Metering and Solar Incentive Proposed Framework
Net Metering and Solar Incentive Proposed Framework STAKEHOLDER MEETING JUNE 11, 2014 June 12, 2014 1 Meeting Agenda June 11, 2014 2-3pm. Review framework. Today s Meeting is to EXPLAIN a compromise framework
More informationPrimary Frequency Response. Summary of Stakeholder Comments Appendix
Primary Frequency Response Summary of Stakeholder Comments Appendix October 20, 2015 1. Introduction The Frequency Response initiative s goal is to propose an option that will reduce the risk of the ISO
More information2019 BQDM Extension Auction Frequently-Asked Questions Updated January 29, 2018
2019 BQDM Extension Auction Frequently-Asked Questions Updated January 29, 2018 See 2019 BQDM Extension Auction Technical Requirements for definitions of terms in bold. General Auction Questions 1. How
More informationWhat We Heard Report - Metro Line NW LRT
What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail
More informationSmart Grid and Demand Response
Smart Grid and Demand Response Implementation ti and Pricing i Issues Akbar Jazayeri HEPG Meeting October 1, 2009 What is a Smart Grid? SOUTHERN CALIFORNIA EDISON A smart grid is capable of performing
More informationCalifornia s Energy Storage Summit California Energy Storage Association and Association of California Water Agencies
California s Energy Storage Summit California Energy Storage Association and Association of California Water Agencies Molly Sterkel, CPUC Energy Division March 30, 2017 California Storage Laws Procurement
More informationThe Modernized Green Commercial Vehicle Program
The Modernized Green Commercial Vehicle Program 1 Government Commitment Ontario s Climate Change Strategy set the long term vision for meeting GHG pollution reduction targets of 15% below 1990 levels in
More informationInternational Approaches for an Integrated Grid
International Approaches for an Integrated Grid Matt Wakefield Director, Information, Communication and Cyber Security (ICCS) mwakefield@epri.com June 15, 2016 Together Shaping the Future of Electricity
More informationRenewable Energy System Tariffs and Pricing
Renewable Energy System Tariffs and Pricing National Association of Regulatory Utility Commissioners Energy Regulatory Partnership Program with The National Commission for Energy State Regulation of Ukraine
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationSteve Rubin, Managing Director, Finance and Support Services. It is requested that the Board or Harbor Commissioners approve the following actions:
Memorandum Date: To: From: Subject: Board of Harbor Commissioners Steve Rubin, Managing Director, Finance and Support Services Requested Action It is requested that the Board or Harbor Commissioners approve
More informationReview of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items
Review of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items Stakeholder Meeting January 30, 2018 Keith Johnson Infrastructure and Regulatory Policy
More informationCommercial Distributor Incentive Project: Regional Roll-Out
Commercial Distributor Incentive Project: Regional Roll-Out April 2014 Argonne National Laboratory/DOE Building Energy Decision and Technology Research (BEDTR) Program Southeast Energy Efficiency Alliance
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationReview of Fees for Accident Tows and Tows from Private Property
STAFF REPORT ACTION REQUIRED Review of Fees for Accident Tows and Tows from Private Property Date: October 27, 2011 To: From: Wards: Reference Number: Licensing and Standards Committee Acting Executive
More informationRATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); AND IN THE MATTER OF a motion by the Ontario Energy Board to
More informationPepco Holdings, Inc. Blueprint for the Future and the Mid-Atlantic Regulatory. Steve Sunderhauf PHI Regulatory Group June 11, 2009
Pepco Holdings, Inc. Blueprint for the Future and the Mid-Atlantic Regulatory Landscape Steve Sunderhauf PHI Regulatory Group June 11, 2009 Who We Are Pepco Holdings, Inc. ( PHI ) is a public utility holding
More informationPOSTING OFFICIAL DAY AND DATE MEETING TIME: 3. Unanticipated. 6. New Businesss. 7. Old Business. a. Financials. 9. Correspondence
TOWN OF MIDDLEBOROUGH OFFICIAL MEETING POSTING NAME OF PUBLIC BODY: Middleborough Gas & Electric Commission DAY AND DATE OF MEETING: Wednesday, October 19, 2016 TIME OF MEETING: 6:000 PM LOCATION OF MEETING
More informationEnergy Savings Variable Frequency Drives and Cooling Tower Fan Motors
Contacts: Head Office: Ecodyne Limited 4475 Corporate Drive Burlington, ON L7L 5T9 Phone: (905) 33-1404 Fax: (905) 33-676 1-888-ECODYNE Paul Holmes Manager Cooling Products paul.holmes@ecodyne.com Jim
More informationEvolving our Customer Relationship: Edison SmartConnect Programs & Services Mark Podorsky, Sr. Manager Business Design
Edison SmartConnect Evolving our Customer Relationship: Edison SmartConnect Programs & Services Mark Podorsky, Sr. Manager Business Design Southern California Edison An Edison International Company Southern
More informationProposal Concerning Modifications to LIPA s Tariff for Electric Service
Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: LIPA Staff proposes revisions to the Tariff for Electric Service under Service Classification No. 11 ( SC-11 ),
More information1. ESWG had an update regarding the SPP Probabilistic Assessment.
Southwest Power Pool ECONOMIC STUDIES WORKING GROUP January 10, 2013 Web Conference SUMMARY OF ACTIONS TAKEN 1. ESWG had an update regarding the SPP Probabilistic Assessment. 1 of 18 Southwest Power Pool
More informationBasic tariff guiding principles
Basic tariff guiding principles Small-scale Embedded Generation (SSEG) tariffs This brief outlines the basic guiding principles in tariff design for municipalities, to support and adapt to a changing electricity
More informationUTILITY-SCALE SOLAR & THE EVOLVING GRID
GRID FLEXIBLE SOLAR UTILITY-SCALE SOLAR & THE EVOLVING GRID As a least-cost new resource, more solar is added to the power grid every day As solar penetration increases, grid operators face new challenges
More informationIncreasing Access: Low Income Community Shared Solar 101
Increasing Access: Low Income Community Shared Solar 101 Metropolitan Area Planning Council (MAPC) April 26, 2017 Solar Webinar Series Webinar Agenda 1 2 3 4 5 Brief Introduction to MAPC & the Clean Energy
More informationThe Tools to Engage The Consumer in the Future Utility
The Tools to Engage The Consumer in the Future Utility Results of the Grid4EU French Demo European Utility Week Session 19 «Winning the Consumer's Trust Patrick LESBROS, EDF Vienna, November 5 th, 2015
More informationNon-BM Balancing Services Volumes and Expenditure
Non-BM Balancing Services Volumes and Expenditure Contents 1 Introduction... 2 1.1 What are Balancing Services or Ancillary Services?... 2 1.2 What are Balancing Mechanism (BM) and Non-Balancing Mechanism
More informationCommunity Solar Workshop & Fair. Woodbury
Community Solar Workshop & Fair Woodbury Agenda 1. Energy Efficiency best bang for your buck 2. Context for Clean Energy in Minnesota 3. Renewable Energy Options 4. Questions 5. Chat with resource experts
More informationDMM 2017 Q4 Report Highlights
DMM 2017 Q4 Report Highlights Gabe Murtaugh Senior Analyst Department of Market Monitoring Conference Call February 21, 2018 Outline Real-time market performance Higher prices in the 15-minute market Large
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationOverview of ISO New England and the New England Wholesale Power Markets
Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England
More informationPARKING LOT QUESTIONS FROM TRAINING PDR REGISTRATION AND FULL MARKET TRAINING MODULES
3/23/10 Trainers Notes: During the Full Market Training on March 18 th, there was some discussion on Slide 10 pertaining to a Demand Response Provider requesting system access on behalf of their Scheduling
More informationToronto Parking Authority Fleet Vehicle Replacement
PA12.5 REPORT FOR ACTION Toronto Parking Authority Fleet Vehicle Replacement - 2018 Date: June 8, 2018 To: Board of Directors, Toronto Parking Authority From: Acting President, Toronto Parking Authority
More informationCoordinating Process Improvement in Multiple Geographically Dispersed Development Organizations Using CMMI. Aldo Dagnino and Andrew Cordes
Coordinating Process Improvement in Multiple Geographically Dispersed Development Organizations Using CMMI Aldo Dagnino and Andrew Cordes ABB Inc. US Corporate Research Center Raleigh, NC ABB Group - 1
More informationExecutive Summary October 2013
Executive Summary October 2013 Table of Contents Introduction... 1 Rider Transit and Regional Connectivity... 1 Plan Overview... 2 Network Overview... 2 Outreach... 3 Rider Performance... 4 Findings...
More informationBEFORE THE PUBLIC UTILITY COMMISSION OF OREGON AR 515
BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON AR 515 In the Matter of ) ) COMMENTS OF PORTLAND A Rulemaking to Adopt Rules Related to ) GENERAL ELECTRIC COMPANY Net Metering ) Portland General Electric
More informationBILLING CODE P DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM ]
This document is scheduled to be published in the Federal Register on 03/29/2013 and available online at http://federalregister.gov/a/2013-06820, and on FDsys.gov BILLING CODE 6717-01-P DEPARTMENT OF ENERGY
More informationTaxis and Accessible Services Division Medallion Reform Background May 1, 2018
Introduction: Taxis and Accessible Services Division Medallion Reform Background May 1, 2018 SFMTA s Taxis and Accessible Services Division is responsible for the regulation of the private businesses that
More informationGreen Line LRT: Beltline Segment Update April 19, 2017
Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street
More informationSmart Metering: A driver for creating energy efficiency for households
Smart Metering: A driver for creating energy efficiency for households Rob Kool & Hans-Paul Siderius (SenterNovem) Smart Metering in the Netherlands A blueprint for European roll-out? 1 Why smart meters
More informationSustainable Biofuel Systems for Undeveloped Regions. Tyler Backman and Nikhil Prem OSU Biodiesel Initiative
Sustainable Biofuel Systems for Undeveloped Regions Tyler Backman and Nikhil Prem OSU Biodiesel Initiative Challenge Definition The lack of sustainable alternatives to petroleum fuels is a critical global
More informationGRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT
GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT 2 What s the Problem? Constrained grid is an issue that impacts many new renewables developments. A quick look at the distribution heat maps published by
More informationSouthern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1
Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated
More informationCity Transfer Stations: Loading Services and Fees
STAFF REPORT ACTION REQUIRED City Transfer Stations: Loading Services and Fees Date: March 24, 2009 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Solid Waste
More information5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE
5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the
More information2019 NYC Solar Installer Workshop: Solar and Storage. March 18, 2019
2019 NYC Solar Installer Workshop: Solar and Storage March 18, 2019 2 ConEdison Activity Since MW Block Redesign Commercial MW Block Activity 3 15 MW submitted since redesign - 6/17/2018 10 rooftop canopy
More informationKicking off Commercial and Industrial Program
Appalachian Power Virginia Kicking off Commercial and Industrial Program www.takechargeva.com/business Welcome! Explain C&I program offering and rules Showcase lighting technology upgrades Describe how
More informationDER Portfolio Optimization and Dispatch, Tertiary Control/Monitoring Strategies
DER Portfolio Optimization and Dispatch, Tertiary Control/Monitoring Strategies Maggie Clout Siemens Energy Management Digital Grid Siemens AG 2016 Three Pillars of a Microgrid System Mixed Generation
More informationDemand Response as a Power System Resource
Demand Response as a Power System Resource Richard Cowart Director, Regulatory Assistance Project www. erranet.org Major points today 1. What? What is Demand Response (DR)? 2. Why? Proven values of DR
More information... ~~dnesdj!j;w~~~f~~ ;ft:3~:~.~' :.:...
......... ~~dnesdj!j;w~~~f~~ ;ft:3~:~.~' :.:........ # 1 2 3 4 5 6 7 8 9 AD IJPC JAJL PL~NING AN]) ~PE
More informationNational Agency for Energy Regulation
National Agency for Energy Regulation Legislation in Energy Sector Institutional Capacity of Energy Sector Wholesale and Retail Market Development Third Party Access to Network Viability and Security of
More informationApril 30, Michael Schilmoeller, Senior Power Systems Analyst
Bill Bradbury Chair Oregon Henry Lorenzen Oregon W. Bill Booth Idaho James A. Yost Idaho Jennifer Anders Vice Chair Montana Pat Smith Montana Tom Karier Washington Phil Rockefeller Washington April 30,
More informationBC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014
T BC Hydro OATT - Balancing Area Transmission Service Workshop January 20, 2014 1 AGENDA Topic Time Speaker Welcome and Introduction 09:00 09:15 Gord Doyle Background 09:15 10:00 Martin Huang Enforcement
More informationILLINOIS COMMERCE COMMISSION
ILLINOIS COMMERCE COMMISSION Public Notice of Successful Bidders and Average Prices Ameren Illinois Company and Commonwealth Edison Company Spring 2015 Procurement of Standard Energy Products April 1,
More informationReview of Reliability Must Run and Capacity Procurement Mechanism
Review of Reliability Must Run and Capacity Procurement Mechanism Issue Paper and Straw Proposal for Phase 1 Items January 23, 2018 Market & Infrastructure Policy Table of Contents 1. Executive Summary...
More informationBehind the Meter Net Generation Model Cost Allocation for BTM Loads
Behind the Meter Net Generation Model Cost Allocation for BTM Loads Pradip Ganesan Market Product Specialist, Energy Market Design New York Independent System Operator MIWG April 23, 2015 Rensselaer, NY
More informationGEODE Report: Flexibility in Tomorrow s Energy System DSOs approach
1 GEODE Report: Flexibility in Tomorrow s Energy System DSOs approach Report was prepared by Working Group Smart Grids of GEODE GEODE Spring Seminar, Brussels, 13th of May 2014 Hans Taus, Wiener Netze
More informationCOMPANY INTRO. PowerCore Engineering
PowerCore Engineering COMPANY INTRO PowerCore is a Power Distribution System Engineering Company and a turnkey Automated Systems Integrator based in London Ontario. We specialize in Power Systems Engineering
More informationNortheast Regional Roundup of Customer-centric Programs
Northeast Regional Roundup of Customer-centric Programs 36 th PLMA Conference Tuesday, November 14, 2017 Regional Context - ISO NE ANNUAL ENERGY USE (GWh) With and without EE and PV Savings SUMMER PEA
More informationWEST MIDLANDS ARCHERY SOCIETY REGIONAL INTER-COUNTY MATCH
OUTDOOR FITA ROUNDS UK RECORD STATUS LILLESHALL NATIONAL SPORTS CENTRE SUNDAY 13 OCTOBER 2013 Host county for 2013: SHROPSHIRE ARCHERY SOCIETY Tournament secretary: Work party: Jonathan Walton Members
More informationMMP Investigation of Arthur Kill 2 and 3
MMP Investigation of Arthur Kill 2 and 3 Requestor Consolidated Edison Company of New York, Inc. Facility Name Arthur Kill 2 and 3 Date of Request January 27, 2003 Type of Facility NG Generator Topic of
More informationLANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT
January 1, 2016 CA Public Utilities Commission Energy Division Attention: Tariff Unit 505 Van Ness Avenue, 4thFloor San Francisco, CA 94102-3298 Advice Letter LCE 001-E RE: LANCASTER CHOICE ENERGY S BIENNIAL
More informationChapter 740, Street Vending One Year Bylaw Review
Chapter 740, Street Vending One Year Bylaw Review Licensing and Standards Committee City Hall, 2 nd Floor, Committee Room 1 Tuesday April 21, 2015 Carleton Grant, Director, Policy and Strategic Support
More informationCapacity Market Rules for Energy Storage Resources
Capacity Market Rules for Energy Storage Resources Zachary T Smith Manager, Capacity Market Design ICAPWG August 23 rd, 2018 Agenda Background Energy Storage Resource (ESR) overview Capacity Market Rules
More informationDepartment of Market Quality and Renewable Integration November 2016
Energy Imbalance Market March 23 June 3, 216 Available Balancing Capacity Report November 1, 216 California ISO Department of Market Quality and Renewable Integration California ISO i TABLE OF CONTENTS
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No. ER ) )
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southwest Power Pool, Inc. ) Docket No. ER13-1748 ) ) MOTION TO INTERVENE AND COMMENTS OF THE ELECTRICITY STORAGE ASSOCIATION
More informationTransmission Charging Methodologies Forum. 10:00am 1:00pm Energy Networks Association, London
Meeting report Meeting name Date of meeting 10 th September 2013 Time Location Transmission Charging Methodologies Forum 10:00am 1:00pm Energy Networks Association, London Attendees Name Initials Company
More informationSpreadsheet and Homer Modelling :Comparison. Presented at Asia Clean Energy Forum 2015 Raj Chintapalli Emerging Technologies
Spreadsheet and Homer Modelling :Comparison Presented at Asia Clean Energy Forum 2015 Raj Chintapalli Emerging Technologies Customized Energy Solutions Customized Energy Solutions (Customized) started
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationUtility Administration & Operation of Virtually Net-Metered Generation
Solar Canada 2017 Utility Administration & Operation of Virtually Net-Metered Generation Vinay Sharma Chair, EDA Dec 5, 2017 Electricity Distributors Association 2 The EDA is the voice of Ontario s local
More information