Electrical Energy Audit of Electricity Bill and Few Tips Common for all industries MOHAN MENGHRAJANI

Size: px
Start display at page:

Download "Electrical Energy Audit of Electricity Bill and Few Tips Common for all industries MOHAN MENGHRAJANI"

Transcription

1 Electrical Energy Audit of Electricity Bill and Few Tips Common for all industries MOHAN MENGHRAJANI

2 Energy Audit of Electricity Bill Energy bill sent by a DISCOM should be read minutely. It gives idea: Whether all incentives are achieved/missed and reasons thereof. What is specific power consumption and departures from bench mark

3 A Sample Electricity Bill

4 Incentives & Penalties (Note: Tariff Details Referred here pertain to MSEDCL -Commercial circular 243 dated ) 1)Prompt payment incentive(within 7 days ) 2) P.F. incentive up to 7% (energy charges + FAC+ Demand charges but excluding taxes and duties) for maintaining P.F. unity There is also penalty for maintaining P.F. below 0.9 as described below:

5 P.F. Incentive in % P.F. Penalty in %

6 kvar capacity addition for improving P.F to maximum possible Formulae kvar (Capacitor capacity to be added) = Load in kw x (tan Ө1- tan Ө2) Where - Load in kw is the load recorded on energy meter for MD recording duration-30 minutes or 15 minutes interval, as applicable. Preferably this MD in kw may be the cycle which has recorded maximum MD. - tan Ө1 ( based on existing peak PF) and tan Ө2 on the improved PF - PF i.e. cos Ө1 is the peak PF, which is the ratio of MD in kw and kva. Therefore Ө1 can be found out from table and so also tan Ө1. Similarly, tan Ө2 can be found out from desired PF

7 Load Factor Incentive L.F. incentive starts from 76% load onwards and is maximum up to 15% of energy charges The incentive in table form is attached herewith. Please note that L.F. incentive will not be applicable if contract demand is exceeded

8 L.F. Incentive Load factor % Incentive % Load factor % Incentive %

9 Further Incentives No penalty for exceeding C.D. during to hrs Reduced energy charges during the period to hrs.(less Rs. 1.5/kWh) The pumping /draining job even fabrication job if possible and not associated with continuous processing should be done during this period

10 Meaning of Billing Demand For LT consumer Maximum of 1) 65% recorded during 06.00to hrs 2) 40% of contract demand For HT consumer 1) Maximum of 1) actual MD recorded during 06.to )75% of highest MD recorded during last 11 months 3) 50% of contract demand It is interesting to note that there is large difference in LT tariff for power looms between up to 20 kw and above 20kW and is discussed as under

11 Energy & Demand Charges for power looms Load up to 20 KW Load above 20 KW Energy charges Rs. 5.43/kWh Rs. 6.88/kWh Demand charges Rs. 220 per installation Rs. 150 /kva/month

12 Specific power consumption & Bench marking Specific power consumption = No. of Unit of production/ Energy bill units ( or total electricity consumption, including captive power generation). Unit of production will be different from industry to industry In some cases it can be number, in some cases it can be in kg/ton, litres, meters etc. Bench mark is the lowest energy consumed for the same production in the past under similar working conditions. More appropriate will be the figure obtainable from same reputed production manufacturers

13 How to reduce energy bill without affecting production In other words doing energy audit? 1. Know your M/C. Stitch in time to save nine 2. If possible Replace first and then Repair to reduce M/c down time 3. Arrest all types of leakages/wastages say water,air,gas,oil, heat,unused lights etc. 4. Check for proper functioning of motors compressors No noise, vibration, high temperature (All should be near to design values at the most within permissible limits). Negligence will add to power consumption. 5. Check whether right capacity of motor is used All motors etc should run above 70% capacity, of course not above 110%. unless it is designed

14 How to reduce energy bill without affecting production In other words doing energy audit? CONTD 6. The replacement programme should be chalked out for inefficient/ faulty motors. It will give return in near future. The management can be appraised giving the simple payback period (preferably not more than 3 years). Use VFD where high capacity motor which runs on partial load all the times, cannot be afforded to be replaced

15 How to reduce energy bill without affecting production In other words doing energy audit? CONTD 7. This concept also applies to transformers also for loading 8. Use wind ventilators instead of Exhaust fans wherever possible 9.Avoiding of breakdown by installing appropriate capacity of wires, cables, switch gears with reliable protection. 10.No loose contact both electrically and mechanically everywhere. They can cause havoc. 11.Install auto system wherever possible. Should be implemented asap viz: i) P.F. control Ii) Pump control using pressure/level/flow sensors Iii)Lighting,air conditioning control using occupation sensors, use of natural lights Iv)Load control. Switching on DG to monitor maximum demand.

16 How to reduce energy bill without affecting production In other words doing energy audit? CONTD 12. Safety first and observe everywhere by: i)cleanliness & tidiness. This will reduce accidents, improve transport of materials inside factory and add to production. Ii) Adequate illumination at working place Use LED at passages, warehouses parking etc. similar type iii)proper tools wires slings etc. Periodical checking/testing from authorised testing agencies iv) Personal protection equipment such as helmet /goggles/breathing mask etc v)perfect electrical earthing preferably below 1 ohm All metallic parts to be earthed secularly At the end I will emphasize on developing the ATTITUDE and DETERMINATION amongst self (Owner) & employees and goal will not be far away. M.N.Menghrajani Mob Certified Energy Auditor EA -4617

17 THANKS

Chapter 3.1: Electrical System

Chapter 3.1: Electrical System Part-I: Objective type Questions and Answers Chapter 3.1: Electrical System 1. The heat input required for generating one kilo watt-hour of electrical output is called as. a) Efficiency b) Heat Rate c)

More information

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY ANNEXURE: TARIFF SCHEDULE Tariff Schedule for Adani Ports and SEZ Ltd License area of MPSEZ Utilities Pvt. Ltd. Effective from 1 st April, 2018 General Conditions 1. This tariff schedule is applicable

More information

is attached to and becomes a part of a agreement dated, 20,

is attached to and becomes a part of a agreement dated, 20, Electric Metal Melting (Alternative) Schedule Designation R1.1 Standard Contract Rider No. 1.1 DE 963-7033 8/18 THIS RIDER, dated, 20, is attached to and becomes a part of a agreement dated, 20, between

More information

is attached to and becomes a part of a agreement dated, 20

is attached to and becomes a part of a agreement dated, 20 Electric Process Heat Schedule Designation R1.2 Standard Contract Rider No. 1.2 DE 963-1635 8/18 THIS RIDER, dated, 20 is attached to and becomes a part of a agreement dated, 20 between (Legal Entity and

More information

Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning

Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning 910-09 Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler

More information

kvah Billing - Frequently Asked Questions (FAQs)

kvah Billing - Frequently Asked Questions (FAQs) kvah Billing - Frequently Asked Questions (FAQs) 1. What is kvah billing? a. Electrical Energy has two components viz. Active Energy (kwh) and Reactive Energy (kvarh). Vector sum of these two components

More information

Name and address of DISCOM with Logo. TARIFF NOTIFICATION The 22 rd March, 2018 RETAIL SUPPLY TARIFF EFFECTIVE FROM 1 st APRIL, 2018

Name and address of DISCOM with Logo. TARIFF NOTIFICATION The 22 rd March, 2018 RETAIL SUPPLY TARIFF EFFECTIVE FROM 1 st APRIL, 2018 Name and address of DISCOM with Logo TARIFF NOTIFICATION The 22 rd March, 2018 RETAIL SUPPLY TARIFF EFFECTIVE FROM 1 st APRIL, 2018 In exercise of the powers conferred under section 64(3) and other related

More information

Street Address. City-Village-Township

Street Address. City-Village-Township Schedule Designation D11 Primary Supply Agreement D11 963-1816 8/18 THIS AGREEMENT, dated, 20, by and between (Name) a, (Legal Entity and State of Organization) herein called the "Customer", and DTE Electric

More information

Roof Top Solar Power Net Metering Solution. Guidelines for implementation of Net Metering for Roof Top Solar Power System

Roof Top Solar Power Net Metering Solution. Guidelines for implementation of Net Metering for Roof Top Solar Power System Roof Top Solar Power Net Metering Solution Guidelines for implementation of Net Metering for Roof Top Solar Power System 1. Net Metering arrangement is permitted for 3 Phase connections only. The interconnection

More information

NESCO UTILITY. Januganj, Balasore TARIFF NOTIFICATION The 23 rd March, 2015 RETAIL SUPPLY TARIFF EFFECTIVE FROM 1 st APRIL, 2015

NESCO UTILITY. Januganj, Balasore TARIFF NOTIFICATION The 23 rd March, 2015 RETAIL SUPPLY TARIFF EFFECTIVE FROM 1 st APRIL, 2015 NESCO UTILITY Januganj, Balasore-756019 TARIFF NOTIFICATION The 23 rd March, 2015 RETAIL SUPPLY TARIFF EFFECTIVE FROM 1 st APRIL, 2015 In exercise of the powers conferred under section 64(3) and other

More information

Tamilnadu Trade Promotion Organisation, Chennai-89

Tamilnadu Trade Promotion Organisation, Chennai-89 Tamilnadu Trade Promotion Organisation, Chennai-89 TNTPO/ENGG-104/2016 Date: 08.11.2016 NOTICE INVITING QUOTATION The Tamilnadu Trade Promotion Organisation, Chennai-89 invites sealed item rate quotation

More information

ANNEXURE: TARIFF SCHEDULE

ANNEXURE: TARIFF SCHEDULE ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2018 GENERAL 1. The tariff figures indicated in this tariff schedule

More information

ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAVAN UNIT-VIII, BHUBANESWAR *****************

ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAVAN UNIT-VIII, BHUBANESWAR ***************** ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAVAN UNIT-VIII, BHUBANESWAR 751 012 ***************** From To Secretary I/c. The Managing Director, NESCO At/Po : Januganj Dist : Balasore - -

More information

Power Factor Correction

Power Factor Correction Power Factor Correction Power Factor Correction and Voltage Optimisation have been around since the turn of the 20 th century and although in many cases their individual benefits and attributes make them

More information

Large Power Service Time of Use

Large Power Service Time of Use Original Sheet No.: 301 Large Power Service Time of Use AVAILABILITY Available throughout the Company s entire electric service area where the facilities of the Company are of adequate capacity and are

More information

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys Irrigation energy efficiency How to analyse your energy costs Nick Bullock The Energy Guys March 2017 1 PILOT Energy Audits: Pivots AIM: data on energy use simple field data How energy efficient is system?

More information

Annexure III: Tariff Schedule

Annexure III: Tariff Schedule Annexure III: Tariff Schedule MINDSPACE BUSINESS PARKS PRIVATE LIMITED SCHEDULE OF ELECTRICITY TARIFFS (Effective from 1 September, 2018) The Maharashtra Electricity Regulatory Commission, in exercise

More information

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents Annexure-1-B ANNEXURE TO TARIFF ORDER PASSED BY MPERC For Financial Year 2005-06 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS Table of Contents Sr No Particulars

More information

New Rate Structure Encouraging greater efficiency

New Rate Structure Encouraging greater efficiency New Rate Structure Encouraging greater efficiency Presentation for CHENACT Project Stephen Worme Chief Marketing Officer March 31, 2010 Agenda Tariffs for Hotels Secondary Voltage Power (SVP) Large Power

More information

ANNEXURE: TARIFF SCHEDULE

ANNEXURE: TARIFF SCHEDULE ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2017 GENERAL 1. The tariff figures indicated in this tariff schedule

More information

Large General Service Time-of-Use Storage Program

Large General Service Time-of-Use Storage Program Large General Service Time-of-Use Storage Program AVAILABILITY Available throughout the Company s entire electric service area where the facilities of the Company are of adequate capacity and are adjacent

More information

COMPANY INTRO. PowerCore Engineering

COMPANY INTRO. PowerCore Engineering PowerCore Engineering COMPANY INTRO PowerCore is a Power Distribution System Engineering Company and a turnkey Automated Systems Integrator based in London Ontario. We specialize in Power Systems Engineering

More information

POWER FACTOR REBATE-BOLD DECISION FROM REGULATOR

POWER FACTOR REBATE-BOLD DECISION FROM REGULATOR 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 153 POWER FACTOR REBATE-BOLD DECISION FROM REGULATOR Shefali K.Talati, S.B.Modi, U.C.Trivedi, K.M.Dave # Electrical Research and Development

More information

PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012

PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012 PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012 Introduction Power reliability Power Quality Harmonics Distortion Poor power factor Circuit

More information

ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2016

ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2016 ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2016 GENERAL 1. The tariff figures indicated in this tariff schedule

More information

CITY OF BOWLING GREEN, OHIO MUNICIPAL UTILITIES ELECTRIC RATE SCHEDULES

CITY OF BOWLING GREEN, OHIO MUNICIPAL UTILITIES ELECTRIC RATE SCHEDULES MUNICIPAL UTILITIES S BOARD OF PUBLIC UTILITIES AMY CRAFT-AHRENS WILLIAM CULBERTSON MIKE FROST MEGAN NEWLOVE MATT PAQUETTE MAYOR RICHARD EDWARDS MUNICIPAL ADMINISTRATOR LORI TRETTER UTILITIES DIRECTOR

More information

DIRECTORATE OF TECHNICAL EDUCATION DIPLOMA IN ELECTRICAL AND ELECTRONICS ENGINEERING III YEAR M SCHEME V SEMESTER.

DIRECTORATE OF TECHNICAL EDUCATION DIPLOMA IN ELECTRICAL AND ELECTRONICS ENGINEERING III YEAR M SCHEME V SEMESTER. DIRECTORATE OF TECHNICAL EDUCATION DIPLOMA IN ELECTRICAL AND ELECTRONICS ENGINEERING III YEAR M SCHEME V SEMESTER 2015 2016 onwards ELECTRICAL ESTIMATION AND ENERGY AUDITING CURRICULUM DEVELOPMENT CENTRE

More information

Western Electricity Supply Company of Orissa Ltd., Burla, Sambalpur , Orissa

Western Electricity Supply Company of Orissa Ltd., Burla, Sambalpur , Orissa Western Electricity Supply Company of Orissa Ltd., Burla, Sambalpur-768017, Orissa Publication of Applications u/s 64(2) of the Electricity Act, 2003, read with Reg. 53(7) of the OERC (Conduct of Business)

More information

ABB n.v Power Quality in LV installations

ABB n.v Power Quality in LV installations ABB n.v. - 1 - Power Quality in LV installations PQ problems in LV installations 750 500 250 Volts 0-250 -500 Amps -750 3000 2000 1000 0-1000 -2000-3000 10:25:43.72 10:25:43.73 10:25:43.74 10:25:43.75

More information

Chapter 3.2: Electric Motors

Chapter 3.2: Electric Motors Part I: Objective type questions and answers Chapter 3.2: Electric Motors 1. The synchronous speed of a motor with 6 poles and operating at 50 Hz frequency is. a) 1500 b) 1000 c) 3000 d) 750 2. The efficiency

More information

Street Address. City-Village-Township

Street Address. City-Village-Township Schedule Designation D11 Primary Supply Agreement D11 963-1816 77/15 THIS AGREEMENT, dated, 20, by and between (Name) a, (Legal Entity and State of Organization) herein called the "Customer", and DTE Electric

More information

ENERGY MANAGEMENT 4/22/2014. What are your approximate yearly energy costs? (Electricity, natural gas, etc.)

ENERGY MANAGEMENT 4/22/2014. What are your approximate yearly energy costs? (Electricity, natural gas, etc.) MICHIGAN CHAMBER OF COMMERCE ENERGY MANAGEMENT Webinar Electricity - Natural Gas April 23, 2014 10:00 A.M. - 11:00 A.M. EDT Presented by John M. Studebaker, Ph.D. www.studebakerenergy.net JStudebaker 4/23/14

More information

Respondent 1) The Asst. Exe. Engineer, Electrical Sub Division, Pattanakkad

Respondent 1) The Asst. Exe. Engineer, Electrical Sub Division, Pattanakkad 1 CONSUMER GRIEVANCE REDRESSAL FORUM CENTRAL REGION (Formed under Section 42(5) of the Electricity Act 2003) 220 kv Substation Compound, HMTColony P.O. Kalamasery, Pin 683 503 Phone No. 0484-2556500 Website

More information

CITY OF BOWLING GREEN, OHIO MUNICIPAL UTILITIES ELECTRIC RATE SCHEDULES

CITY OF BOWLING GREEN, OHIO MUNICIPAL UTILITIES ELECTRIC RATE SCHEDULES MUNICIPAL UTILITIES S BOARD OF PUBLIC UTILITIES WILLIAM CULBERTSON MIKE FROST JOYCE KEPKE JOHN MEKUS MEGAN NEWLOVE MAYOR RICHARD A. EDWARDS MUNICIPAL ADMINISTRATOR JOHN S. FAWCETT UTILITIES DIRECTOR BRIAN

More information

Delaware Electric Cooperative. Solar: What You Need to Know

Delaware Electric Cooperative. Solar: What You Need to Know Delaware Electric Cooperative Solar: What You Need to Know National Solar Industry 9,000 solar companies Employing over 209,000 people Nearly 32 GW currently installed nationwide Enough solar to power

More information

Draft Detailed Project Report. Investment Grade Energy Audit. Conducted on. BEE MuDSM Programme. Name of ULB: Sagar Municipality, Madhya Pradesh.

Draft Detailed Project Report. Investment Grade Energy Audit. Conducted on. BEE MuDSM Programme. Name of ULB: Sagar Municipality, Madhya Pradesh. Draft Detailed Project Report On Investment Grade Energy Audit Conducted on BEE MuDSM Programme. Name of ULB: Sagar Municipality, Madhya Pradesh. By EPIC Energy Ltd, Mumbai. ESCO & IGE Auditors. Period

More information

Uttar Gujarat Vij Company Limited APR for FY & ARR for FY TARIFF SCHEDULE

Uttar Gujarat Vij Company Limited APR for FY & ARR for FY TARIFF SCHEDULE TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND GENERAL EXTRA HIGH TENSION Effective from 1 st April 2010 1. The tariff figures indicated in this tariff schedule are

More information

TECHNICAL TERMS AND ABBREVIATIONS

TECHNICAL TERMS AND ABBREVIATIONS THIRD REVISED SHEET NO. 3.1 CANCELS SECOND REVISED SHEET NO. 3.1 TECHNICAL TERMS AND ABBREVIATIONS ALTERNATING CURRENT (A-C): AMPERE: BASE RATES: BRITISH THERMAL UNIT (BTU): CAPACITOR or CAPACITANCE: CAPACITY

More information

Installation Planning (or what I didn t learn at meter school)

Installation Planning (or what I didn t learn at meter school) NWEMS Harris nstitute of echnical raining nstallation Planning (or what didn t learn at meter school) Presented by Brad Harris nstallation #1 A three phase commercial customer has the following installation

More information

Automatic capacitor banks and Automatic Power factor Correction Panels of inductive character loads in low voltage power networks.

Automatic capacitor banks and Automatic Power factor Correction Panels of inductive character loads in low voltage power networks. SME APFC Panels Description: APFC Panel means Automatic Power Factor Correction Panel. In some cases, in industrial applications, the loading pattern of the entire network will change from time to time.

More information

POWER FACTOR IMPROVEMENT CONCEPT FOR LARGE MOTORS

POWER FACTOR IMPROVEMENT CONCEPT FOR LARGE MOTORS POWER FACTOR IMPROVEMENT CONCEPT FOR LARGE MOTORS POWERFLOW TECHNOLOGIES Inc 4031 FAIRVIEW ST, Burlington,Ontario, CANADA, L7L-2A4 905-336 2686, www.powerflowtechnologies.com 1 POWER FACTOR REQUIREMENTS

More information

MISSOURI SERVICE AREA

MISSOURI SERVICE AREA MO.P.S.C. SCHEDULE NO. 6 3rd Revised SHEET NO. 61 CANCELLING MO.P.S.C. SCHEDULE NO. 6 2nd Revised SHEET NO. 61 LARGE PRIMARY SERVICE RATE *RATE BASED ON MONTHLY METER READINGS Summer Rate (Applicable during

More information

BOOT/OPEX/Pay As You Use Model for Rooftop Solar Projects Workshop on Getting Started on Energy Management & Solar

BOOT/OPEX/Pay As You Use Model for Rooftop Solar Projects Workshop on Getting Started on Energy Management & Solar BOOT/OPEX/Pay As You Use Model for Rooftop Solar Projects Workshop on Getting Started on Energy Management & Solar Photonergy Solutions Private Limited Key Drivers Rooftop Solar-Business Case Rising Grid

More information

Welcome To Meet Our Installer Event

Welcome To Meet Our Installer Event Welcome To Meet Our Installer Event Agenda Welcome! Belmont Goes Solar Program Installer Selection How Solar Works Designing Your System Financial Benefits Program Details How to Sign Up Who is Belmont

More information

Different techniques for energy conservation and cost reduction are described below. II. SELECTION OF CHEAP AVAILABLE SOURCE

Different techniques for energy conservation and cost reduction are described below. II. SELECTION OF CHEAP AVAILABLE SOURCE 2010), 29th November 2nd December, 2010, pp. 351-355. Management and Conservation of Electrical Energy in Industrial Units Rehan Liaqat, Lecturer, Electrical Engg. Deptt. GC University Faisalabad, arehanliaqat@gmail.com

More information

Working Principle of Power Saver as per Manufacture:

Working Principle of Power Saver as per Manufacture: Analysis the Truth behind Household Power Savers Introduction: A House hold power saving devices has recently received a lot of attention from both consumers and manufacturers. It is generally used in

More information

Electrical Power Electric power electrical electric power Electric power electric electric

Electrical Power Electric power electrical electric power Electric power electric electric Power Calculations Electrical Power Electric power is the rate at which electrical energy is transferred by an electric circuit. The SI unit of power is the watt, one joule per second. Electric power is

More information

Standard retail electricity supply

Standard retail electricity supply Standard retail electricity supply Schedule of charges from 1 July 2011 Schedule of charges for standard retail electricity supply The following charges have been approved by the Independent Competition

More information

Southern California Edison Company Demand Response Appendices to SCE-1, Volumes 1-4 ERRATA Replacing Appendix D, Pages D-1 & D-3

Southern California Edison Company Demand Response Appendices to SCE-1, Volumes 1-4 ERRATA Replacing Appendix D, Pages D-1 & D-3 Application No.: Exhibit No.: Witness: A.11-03-003 SCE-1, Volume 5 (Appendices to SCE-1 Volumes 1 4) - ERRATA (U 338-E) Southern California Edison Company Demand Response Appendices to SCE-1, Volumes 1-4

More information

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow No.UPERC/ Secy/JD(G)/2018/ dated : 20 th August, 2018 Public Notice The Commission is in process of reviewing

More information

CASE NOS. 79, 80, 81 & 82 of 2017/363 Date

CASE NOS. 79, 80, 81 & 82 of 2017/363 Date ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN PLOT NO. 4, CHUNOKOLI, SHAILASHREE VIHAR, CHANDRASEKHARPUR, BHUBANESWAR-751021 ***************** CASE NOS. 79, 80, 81 & 82 of 2017/363 Date.22.03.2018

More information

11. Electrical energy tariff rating

11. Electrical energy tariff rating 799 11. Electrical energy tariff rating 800 11. ELECTRICAL ENERGY TARIFF RATING There is no universal system for billing electrical energy. Each country generally adopts its own method, taking into account

More information

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION, BHOPAL Sub : In the matter of determination of Parallel Operation Charges. Suo-Motu Petition No. 73/2012 ORDER (Date of order 31 st December, 2012) MPERC,

More information

In-House Paper on the implementation of Single Part Tariff in Power Distribution

In-House Paper on the implementation of Single Part Tariff in Power Distribution December 9, 2016 In-House Paper on the implementation of Single Part Tariff in Power Distribution Background: Tariff Introduction: Tariff is the price Structure at which electricity is sold to the consumers.

More information

Customer and Utility Energy Management Fundamentals 101

Customer and Utility Energy Management Fundamentals 101 Customer and Utility Energy Management Fundamentals 101 Minneapolis October 24 th 2016 Today s Show Brought to you by: Danny Zagotta Barry Mosser Thank you very much, Janet Booker What s your Energy Management

More information

A. Basic Customer Charge: $ B. Energy Charge: $.09316/kWh

A. Basic Customer Charge: $ B. Energy Charge: $.09316/kWh Electric Rates Residential Service (RS1) This Schedule is available for separately metered and billed electric service to any Customer for use in and about (a) a single-family residence or apartment, (b)

More information

Residential Rates January 1, 2016

Residential Rates January 1, 2016 Residential Rates TOU Rates off- peak $ 0.0830 mid- peak $ 0.1280 on- peak $ 0.1750 RPP **First 1000 kwh $ 0.0990 **Balance of kwh $ 0.1160 Fixed Distribution Charge (monthly) $ 11.8700 Distribution Volumetric

More information

Water Heater Flat Rate Connections May 1, 2017

Water Heater Flat Rate Connections May 1, 2017 Water Heater Flat Rate Connections Monthly charges for cost of power are based on the "Cost of Power" billed for the Flat Rate kwh consumption level determined on the wattage size of the tank. All other

More information

Green Practices In Electrical System. Confederation of Indian Industry

Green Practices In Electrical System. Confederation of Indian Industry Green Practices In Electrical System Electrical System venergy efficiency measures will add $505 billion to India s gross domestic product (GDP) between 2009 and 2017 vimmense energy efficiency potential

More information

TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies. Gerald Johns, P.E. Power Utilization Engineer, TVA

TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies. Gerald Johns, P.E. Power Utilization Engineer, TVA TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies Gerald Johns, P.E. Power Utilization Engineer, TVA 1 TVA Comprehensive Services Power Factor Studies/Recommendations

More information

D Original Sheet No. 11!81 Revised

D Original Sheet No. 11!81 Revised KANSAS CITY POWER & LIGHT COMPANY P.S.C. MO. No. 7 Third Cancelling P.S.C. MO. No. 7 Second D Original Sheet No. 11!81 Revised D Original Sheet No. 11!81 Revised For Missouri Retail Service Area LARGE

More information

In-House paper on Implementation of Telescopic Tariffs in LMV-6 category

In-House paper on Implementation of Telescopic Tariffs in LMV-6 category Date: January 23, 2017 In-House paper on Implementation of Telescopic Tariffs in LMV-6 category Background As per Section 61 of the Electricity Act, 2003, the electricity Tariff charged from any consumer

More information

Tackling Power Theft through Meter Data Management and Quality Analysis. Results from NPCL s AMR roll out and AMI trial

Tackling Power Theft through Meter Data Management and Quality Analysis. Results from NPCL s AMR roll out and AMI trial Tackling Power Theft through Meter Data Management and Quality Analysis Results from NPCL s AMR roll out and AMI trial R. C. Agarwala 23 rd May 2013 NOIDA POWER COMPANY LIMITED Greater Noida, India 1 NPCL:

More information

COMMERCIAL RATE SCHEDULES

COMMERCIAL RATE SCHEDULES COMMERCIAL RATE SCHEDULES AVAILABILITY APPLICABLE This schedule is available at points on the Cooperative s interconnected system where existing facilities of adequate capacity and desired phase and voltage

More information

Annexure 1: Category-wise Tariff for BEST's consumers for FY (effective from 1 September, 2018)

Annexure 1: Category-wise Tariff for BEST's consumers for FY (effective from 1 September, 2018) Sr. No. Annexure 1: Category-wise Tariff for BEST's consumers for FY 2018-19 (effective from 1 September, 2018) Consumer Category & Consumption Slab HIGH TENSION CATEGORIES FY 2018-19 (Existing - Approved

More information

Alternator as a voltage Generating source and its response to the leading power factor loads

Alternator as a voltage Generating source and its response to the leading power factor loads Alternator as a voltage Generating source and its response to the leading power factor loads Presentation by: Jay Deshpande (Engineered Solutions- Mission Critical) Kohler Power Systems Washington, DC

More information

Power Factor Correction

Power Factor Correction AE9-1249 R10 August 2008 Power Factor Correction Index Page 1. Introduction... 1 2. Electrical Fundamentals... 1 3. Electrical Formulas... 2 4. Apparent Power and Actual Power... 2 5. Effects of Poor Power

More information

KCP&L GREATER MISSOURI OPERATIONS COMPANY P.S.C. MO. No. 1 1st Revised Sheet No. 149 Canceling P.S.C. MO. No. 1 Original Sheet No.

KCP&L GREATER MISSOURI OPERATIONS COMPANY P.S.C. MO. No. 1 1st Revised Sheet No. 149 Canceling P.S.C. MO. No. 1 Original Sheet No. P.S.C. MO. No. 1 1st Revised Sheet No. 149 Canceling P.S.C. MO. No. 1 Original Sheet No. 149 AVAILABILITY This schedule is available for all general service use, such as combined lighting and power service

More information

Tariff Circular & Tariff Schedules

Tariff Circular & Tariff Schedules Tariff Circular & Tariff Schedules (Effective from 01 st April 2015) Madhya Gujarat Vij Company Limited Corporate Office, S.P. Vidyut Bhavan, Race Course, Vadodara-390 007 1465/2014 ANNEXURE: TARIFF SCHEDULE

More information

Realizing Energy Savings in Fan and Pump Systems using Variable Frequency Drives. Schaedler Yesco Expo 2012

Realizing Energy Savings in Fan and Pump Systems using Variable Frequency Drives. Schaedler Yesco Expo 2012 Realizing Energy Savings in Fan and Pump Systems using Variable Frequency Drives Cocoa Suite 4 April 11, 2012 09:30 AM Presenter: Dan Dillon Schaedler Yesco Expo 2012 Energy Savings no-brainer: Motor Efficiency

More information

Scale of Inspection Fees of Electrical Inspectorate Schedule. I. Fees for Initial Inspections:

Scale of Inspection Fees of Electrical Inspectorate Schedule. I. Fees for Initial Inspections: PART 7 Scale of Inspection Fees of Electrical Inspectorate Schedule I. Fees for Initial Inspections: SCALE A For an inspection or test of any generating station, receiving station or other places in which

More information

PRESS NOTE. Distribution Tariff for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015

PRESS NOTE. Distribution Tariff for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015 26 June, 2015 PRESS NOTE Distribution for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015 MSEDCL s Multi-Year Petition for the Control Period

More information

1 Low-voltage Power-factor Correction capacitors KNK APPLICATION DESIGN

1 Low-voltage Power-factor Correction capacitors KNK APPLICATION DESIGN APPLICATION The KNK capacitors are used for power - factor correction of inductive consumers (transformers, electric motors, rectifiers) in industrial networks for voltages of up to 660 V. DESIGN Cylindrical

More information

Chapter 3.10: Energy Efficient Technologies in Electrical Systems

Chapter 3.10: Energy Efficient Technologies in Electrical Systems Chapter 3.10: Energy Efficient Technologies in Electrical Systems Part-I: Objective type questions and answers 1. Maximum demand controller is used to. a) switch off essential loads in a logical sequence

More information

Residential Rates July 1, 2017

Residential Rates July 1, 2017 Residential Rates Electricity TOU Rates off-peak $ 0.0650 mid-peak $ 0.0950 on-peak $ 0.1320 RPP **First 600 kwh $ 0.0770 **Balance of kwh $ 0.0900 **Retailer Contract (signed after Dec 9, 2002) fixed

More information

Best Practices in Energy Efficiency

Best Practices in Energy Efficiency Best Practices in Energy Efficiency Tom Sherman C.E.M., C.E.A., C.D.S.M. President Sustainable Energy Services, Inc. 440.773.5044 Tom@sustainable-energy-services.com How Do You Buy What You Can t Afford?

More information

Energy Auditing of a Typical Residential Building in Ibadan Metropolis

Energy Auditing of a Typical Residential Building in Ibadan Metropolis IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331, Volume 6, Issue 5 (Jul. - Aug. 2013), PP 24-29 Energy Auditing of a Typical Residential Building

More information

MYRON ZUCKER CALMANUAL POWER FACTOR CORRECTION APPLICATION GUIDE INC.

MYRON ZUCKER CALMANUAL POWER FACTOR CORRECTION APPLICATION GUIDE INC. MYRON ZUCKER CALMANUAL POWER FACTOR CORRECTION APPLICATION GUIDE INC. CALMANUAL HOW TO APPLY CAPACITORS TO LOW VOLTAGE POWER SYSTEMS. SECTION INDEX SECTION I POWER FACTOR UNDERSTANDING POWER FACTOR...

More information

2017 Colorado Phase 2 Regulatory Rate Review Frequently asked questions

2017 Colorado Phase 2 Regulatory Rate Review Frequently asked questions 1 What did Black Hills Energy file? We submitted a Phase 2 Rate Review proposal to the Colorado Public Utilities Commission (PUC) to complete the two-step process of updating electric rates, which were

More information

Energy Saving Solutions Using Variable Frequency Drives

Energy Saving Solutions Using Variable Frequency Drives Energy Saving Solutions Using Variable Frequency Drives Keystone E April 20 01:00 PM April 21 09:00 AM Presenter: Dan Dillon Energy Efficiency: What s all the fuss about? Rapidly rising energy costs Finite

More information

RATE APPLICATION MANUAL. Kansas City Board of Public Utilities

RATE APPLICATION MANUAL. Kansas City Board of Public Utilities RATE APPLICATION MANUAL Kansas City Board of Public Utilities APPROVED BY THE BPU BOARD February 1, 2017 RATES EFFECTIVE January 1, 2018 RATE APPLICATION MANUAL BOARD OF PUBLIC UTILITIES PAGE TABLE OF

More information

L45SR - L75SR - L120SR

L45SR - L75SR - L120SR L45SR - L75SR - L120SR Speed Regulated Rotary Screw Compressors Intelligent Air Technology DRIVES Speed Regulated Rotary Screw Compressors Reliable compressed air provided at maximum efficiency under all

More information

THE PROTECTION OF INDUSTRIAL CAPACITOR BANKS BY CURRENT LIMITING FUSES. By M.J. Smart and B. Wadcock

THE PROTECTION OF INDUSTRIAL CAPACITOR BANKS BY CURRENT LIMITING FUSES. By M.J. Smart and B. Wadcock 203 THE PROTECTION OF INDUSTRIAL CAPACITOR BANKS BY CURRENT LIMITING FUSES By M.J. Smart and B. Wadcock 1.0 INTRODUCTION Capacitors are widely used for industrial power factor correction throughout the

More information

UTTARAKHAND POWER CORPORATION LIMITED

UTTARAKHAND POWER CORPORATION LIMITED UTTARAKHAND POWER CORPORATION LIMITED PUBLIC-NOTICE In terms of the provisions of section 45 of the Electricity Act, 2003, the consumers and the general public are hereby informed of the tariff and charges

More information

CARTHAGE WATER & ELECTRIC PLANT ELECTRIC RATES RESIDENTIAL SERVICE

CARTHAGE WATER & ELECTRIC PLANT ELECTRIC RATES RESIDENTIAL SERVICE RESIDENTIAL SERVICE This rate is available by contract for single-phase 120/240 volt service to a single family dwelling through one meter for domestic use, and to separate structures on the same parcel

More information

May 3, 2017 ESI. Utility Bills: Finding Buried Treasure Department of Environmental Quality

May 3, 2017 ESI. Utility Bills: Finding Buried Treasure Department of Environmental Quality May 3, 2017 ESI Utility Bills: Finding Buried Treasure Department of Environmental Quality Utility Bills 101 Typical Electric Bills Regulated Utilities Energy & Demand in kwh; kw Billed, Actual, Contract,

More information

ENERGY & UTILITIES. Electricity Metering & Sub-Metering Concepts and Applications. BuildingsOne April 30, 2018

ENERGY & UTILITIES. Electricity Metering & Sub-Metering Concepts and Applications. BuildingsOne April 30, 2018 BuildingsOne April 30, 2018 The measurement of base building systems and tenantspecific equipment electricity consumption, through submetering applications, is increasing in importance within the commercial

More information

Rate Schedules. Effective 1/1/2019

Rate Schedules. Effective 1/1/2019 Rate Schedules 2019 Effective 1/1/2019 SUMMARY OF RATE SCHEDULES REVISIONS FOR RATES EFFECTIVE JANUARY 1, 2019 (1) Rate component changes for Residential and Heating Service rate schedules. (2) General

More information

PORTABLE ELECTRICAL EQUIPMENT SAFE OPERATING PROCEDURE

PORTABLE ELECTRICAL EQUIPMENT SAFE OPERATING PROCEDURE PORTABLE ELECTRICAL EQUIPMENT SAFE OPERATING PROCEDURE Page 1 of 6 1. SUMMARY... 3 1.1 USE OF PORTABLE ELECTRICAL EQUIPMENT... 3 1.2 FAULTY EQUIPMENT... 3 2. PURPOSE & SCOPE... 3 3. DEFINITIONS... 3 3.1

More information

CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS

CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS CHOPTANK ELECTRIC COOPERATIVE, INC. TERMS AND CONDITIONS TABLE OF CONTENTS PAGE NO. GENERAL 1 100 ELECTRIC SERVICE 101 Application

More information

SILICONES GLOBAL SOLUTIONS

SILICONES GLOBAL SOLUTIONS SILICONES GLOBAL SOLUTIONS 2016 PROPOSAL FOR INSTALLATION OF A 25% POWER SAVING DEVICE Silicones Global Solutions, Email:info@siliconesgbsolutions.com, Contact: 0302200950/0208163888 1/1/2016 Contents

More information

Panola-Harrison Electric Cooperative, Inc. Louisiana Tariff Effective: March 3, 2004

Panola-Harrison Electric Cooperative, Inc. Louisiana Tariff Effective: March 3, 2004 Rate Schedule: R Page 1 of 1 RESIDENTIAL RATE SCHEDULE R Available in all territory served by the Cooperative, in accordance with the established rules and regulations of the Cooperative. Residential uses

More information

Uninterrupted Efficient Energy Solutions through Solar For Urban Office Building And Cold Storage Applications

Uninterrupted Efficient Energy Solutions through Solar For Urban Office Building And Cold Storage Applications Uninterrupted Efficient Energy Solutions through Solar For Urban Office Building And Cold Storage Applications TLA international Energy Conference 2016 www.statconenergiaa.com MANOJ PANDE ABOUT US SOLAR

More information

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE Sheet 1 AVAILABILITY Electric delivery service shall be taken under this rate for all purposes by any customer who is placed on the rate by the Company in accordance with this paragraph. The Company shall

More information

INTER PLANT STANDARD STEEL INDUSTRY. Corresponding IS does not exist

INTER PLANT STANDARD STEEL INDUSTRY. Corresponding IS does not exist INTER PLANT STANDARD STEEL INDUSTRY IPSS SPECIFICATION FOR ac ROLLER TABLE MOTORS (Second Revision) Corresponding IS does not exist IPSS:1-03-007-14 Formerly : IPSS:1-03-007-03 0. FOREWORD 0.1 This Inter

More information

PV SELF CONSUMPTION SCHEMES. Marie Latour. IEA-PVPS task 1 meeting, Aarhus, DK. 22 September OVERVIEW in EUROPE.

PV SELF CONSUMPTION SCHEMES. Marie Latour. IEA-PVPS task 1 meeting, Aarhus, DK. 22 September OVERVIEW in EUROPE. Marie Latour Senior National Policy Advisor Marie Latour PV SELF CONSUMPTION IEA-PVPS task 1 meeting, SCHEMES Aarhus, DK OVERVIEW in EUROPE 22 September 2012 Introduction PV self-consumption The possibility

More information

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill) GENERATOR INTERCONNECTION APPLICATION Category 2 (Combined) For All Projects with Aggregate Generator Output of More Than 20 kw but Less Than or Equal to 150 kw Also Serves as Application for Category

More information

Kvar Energy Savings, Inc.

Kvar Energy Savings, Inc. Kvar Energy Savings, Inc. presents KVAR Energy Controller (EC) It is a Desired & a Simple Solution for RISING ENERGY COSTS Everyone wants to lower their energy bills The U.S. Government is mandated to

More information

Application Case. Issued by Solution Center Date May, 2013 Pages 5

Application Case. Issued by Solution Center Date May, 2013 Pages 5 Case Application: Delta s Power Regenerative Unit for Overhead Bridge Cranes Issued by Solution Center Date May, 2013 Pages 5 Applicable to Key words AC motor drive, REG2000 Crane, hoist, Delta AC motor

More information

TITLE PAGE ELECTRIC SERVICE NORTHERN STATES POWER COMPANY, A WISCONSIN CORPORATION, AND SUBSIDIARY OF XCEL ENERGY INC.

TITLE PAGE ELECTRIC SERVICE NORTHERN STATES POWER COMPANY, A WISCONSIN CORPORATION, AND SUBSIDIARY OF XCEL ENERGY INC. M. P. S. C. No. 2 Electric 1 st Revised. A-1.0 NORTHERN STATES POWER COMPANY, Cancels Original. A-1.0 (To revise Rule Links) TITLE PAGE ELECTRIC SERVICE NORTHERN STATES POWER COMPANY, A WISCONSIN CORPORATION,

More information