1 NWEMS Harris nstitute of echnical raining nstallation Planning (or what didn t learn at meter school) Presented by Brad Harris
2 nstallation #1 A three phase commercial customer has the following installation requirements for a new service and meter installation - Voltage 240 three phase, three wire DELA service otal connected load = 380 kw with an overall efficiency of 85% at unity power factor. How would you meter this customer and what are the metered values and metering components necessary to meter this load correctly? Please solve for the number of amps per phase that will be delivered to the customer s load at 380 kw (and 85% efficiency) amps nstalled meter information: Voltage Form Number Class
3 nstallation #1 Will current transformers be necessary to meter this load? Yes or No and WHY? f current transformers are necessary: What C ratio would be needed? : How many Cs will be needed? What minimum C rating factor would be necessary? f Cs are used, what would the secondary current from the Cs be when measured at the test switch at full load? amps What is the correct billing multiplier (billing K r ) for this meter installation? (meter K r = 1) Under what condition do we have to de-rate the rating factors of current transformers?
4 nstallation #2 You are to install a solid state meter with a pulse board that is programmed with a K e constant of.3 watt-hours per pulse. he installation has the following parameters: Meter Kh = 1.8 Current transformer ratio = 100:5 Voltage transformer = 60:1 Demand interval is 15 minutes Please solve for the following: Customer s kwhc = (3 wire pulse) Customer s kwc = (3 wire pulse) How many pulses will this meter send to the customer s receiving equipment per equivalent meter disk revolution? pulses
5 nstallation #3 A large single phase residential customer has the following installation requirements for a new service and primary metering installation volt single phase primary service (phase to phase voltage from a phase to phase, single phase primary line) otal connected load = 120 kw with an overall efficiency of 80% at unity power factor How would you meter this customer and what are the metered values and metering components necessary to meter this load correctly? Please solve for the number of primary amps delivered to the customer s load at 120 kw (and 80% efficiency) amps nstalled meter information: Voltage Form Number Class
6 nstallation #3 Current transformer What C ratio would be needed? : What minimum C rating factor would be necessary? Voltage transformer What V ratio would be needed? : How many bushings will the V(s) have? 1 or 2 or will this matter? At full load what would the secondary current from the C be when measured at the test switch? amps What is the correct billing multiplier (billing K r ) for this meter installation? (meter K r = 1)
7 nstallation #4 What is the efficiency of a 120 volt, ¾ horsepower single phase pump which draws 12 amps from the 120 volt service to operate? % efficient (the motor runs at unity PF) nstallation #5 Please solve for the load factor for the following three phase commercial customer. he customer s demand and energy use for the previous month are: Peak demand read from the meter = 24 kw Energy use read from the meter = 5760 kwhs With the above meter reads what was this customer s load factor last month? (30 day month) %
8 nstallation #6 A single phase 240 volt, 40 kw electric motor pump load (100% efficient) is connected and running. his motor is running at a power factor of 75% (.7500) - What is the total kva of this motor load? kva What are the total amps being delivered to this motor load? amps How many kvar are flowing to this motor load? kvar With the information given and solved for, can this load be safely metered using a Class 200, Form 2S meter? Yes or No
9 nstallation #7 A customer is requesting 120/208 volt, three phase secondary power and related transformer bank connection. hey have a large amount of three phase load and a smaller amount of single phase load. Would this customer be connected to an Open or Closed primary bank connection? (Open/Closed) bank
10 nstallation #8 Given: A 125 horsepower, three-phase pump. What is the kw rating of this pump if it is 100% efficient, running at full load and 100% power factor? kw What would be the kva, kw and kvar magnitudes for this pump when operating at 80% (.8000) power factor? 80% = 80% = 80% =
11 nstallation #9 New Customer Service Order Requested Secondary Voltage Single Phase Required Number of Secondary Wires - Connected Load in KW Amps Delivered to the Customer - New Meter nstall Record Meter Voltage - Meter Form Number - Meter Class - Current ransformer Ratio : 5 (if required) Number of Cs Required Minimum C Rating Factor Voltage ransformer Ratio : 1 (if required) NWEMS
DS-1 (Residential) Customer Charge Per electric service account $ 8.23 $ 8.23 $ 8.23 Meter Charge Per electric service account $ 6.06 $ 6.06 $ 6.
Page 1 of 6 DS-1 (Residential) Customer Charge Per electric service account $ 8.23 $ 8.23 $ 8.23 Meter Charge Per electric service account $ 6.06 $ 6.06 $ 6.06 Distribution Delivery Charge (per kwh) Summer
More information2019 LCMU Electric Utility Rate Schedule
2019 LCMU Electric Utility Rate Schedule Residential Service APPLICABLE TO: Residential customers for all domestic uses in single-family dwellings and individually metered apartments within the service
More informationNon-Summer, First 800 kwh $ $ $ Non-Summer, Over 800 kwh $ $ $
Page 1 of 5 DS1 (Residential) Customer Charge Per electric service account $ 11.95 $ 11.95 $ 11.95 Meter Charge Per electric service account $ 5.00 $ 5.00 $ 5.00 Distribution Delivery Charge (per kwh)
More informationElectrical Power Electric power electrical electric power Electric power electric electric
Power Calculations Electrical Power Electric power is the rate at which electrical energy is transferred by an electric circuit. The SI unit of power is the watt, one joule per second. Electric power is
More informationResidential Rates January 1, 2016
Residential Rates TOU Rates off- peak $ 0.0830 mid- peak $ 0.1280 on- peak $ 0.1750 RPP **First 1000 kwh $ 0.0990 **Balance of kwh $ 0.1160 Fixed Distribution Charge (monthly) $ 11.8700 Distribution Volumetric
More informationWater Heater Flat Rate Connections May 1, 2017
Water Heater Flat Rate Connections Monthly charges for cost of power are based on the "Cost of Power" billed for the Flat Rate kwh consumption level determined on the wattage size of the tank. All other
More information9200 Revenue Meter. Model Certification Current Inputs. Complies with the accuracy requirements of the ANSI C Revenue Metering Standard
9200 Revenue Meter This document applies to 9200 meters with firmware version 205 or greater, and explains how to set up and seal the meter for revenue functionality. Revenue meters provide power measurements
More informationTVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies. Gerald Johns, P.E. Power Utilization Engineer, TVA
TVA Distributor Retail Rates and Comprehensive Services Program Power Factor Case Studies Gerald Johns, P.E. Power Utilization Engineer, TVA 1 TVA Comprehensive Services Power Factor Studies/Recommendations
More informationResidential Rates July 1, 2017
Residential Rates Electricity TOU Rates off-peak $ 0.0650 mid-peak $ 0.0950 on-peak $ 0.1320 RPP **First 600 kwh $ 0.0770 **Balance of kwh $ 0.0900 **Retailer Contract (signed after Dec 9, 2002) fixed
More informationLUNERA BALLASTLED TECHNOLOGY AND POWER FACTOR
LUNERA BALLASTLED TECHNOLOGY AND POWER FACTOR Replacing metal halide lamps in magnetic ballast-driven fi xtures with the Lunera MH HID LED Gen 2, a LED plug-and-play replacement, causes the ballast to
More informationWegmans Fairfax Joseph B. Lookup Electrical System Existing Conditions Report & Building Load Summary Report. Appendix Tech Assignment # 2
Wegmans Fairfax Joseph B. Lookup Electrical System Existing Conditions Report & Building Load Summary Report Appendix Tech Assignment # 2 I Wegmans Fairfax Joseph B. Lookup Electrical System Existing Conditions
More informationLUNERA BALLASTLED TM TECHNOLOGY AND POWER FACTOR
LUNERA BALLASTLED TM TECHNOLOGY AND POWER FACTOR Replacing metal halide lamps in magnetic ballast-driven fi xtures with the Lunera Susan Lamp, a LED plug-and-play replacement, causes the ballast to have
More informationAN INTRODUCTION TO THE USE OF INVERTER POWER SUPPLIES IN GLOBAR APPLICATIONS HOW TO IMPROVE THE POWER FACTOR OF THE SYSTEM.
AN INTRODUCTION TO THE USE OF INVERTER POWER SUPPLIES IN GLOBAR APPLICATIONS HOW TO IMPROVE THE POWER FACTOR OF THE SYSTEM. Stanley F. Rutkowski lll, Senior Applications Engineer, RoMan Manufacturing The
More informationPower Quality. Power Factor Wiring and Service. Background. Introduction. bchydro.com
Power Quality Power Factor Wiring and Service Scope Power factor is a major consideration in efficient building or system operation. It is the measure of how effectively your equipment is converting electric
More informationRate No , 17 Residential Service Rate
Princeton, Minnesota 763-389-2252 www.princetonutilities.com Rate No. 2019-14, 17 Residential Service Rate Available to any residential customer in a private residence for domestic purposes only where
More informationHOKKIM. Control & Protection Relays. giving you control. Utilization: Power Factor Regulator : 14-STEP CYCLIC POWER FACTOR REGULATOR.
HOKKIM giving you control Control & Protection Relays Model Description : HL-14c : 14-STEP CYCLIC POWER FACTOR REGULATOR. Utilization: Power Factor Regulator LEDs to indicate power on, capacitive or inductive
More informationRobert Greenwald, P.Eng., MBA. Twitter hashtag: #psforum
UNDERSTANDING YOUR ENERGY BILL Robert Greenwald, P.Eng., MBA Pi Prism Engineering i Ld Ltd. LET S START WITH A QUESTION HOW MUCH WILL THE ELECTRICITY COST TO RUN A 150 HP MOTOR FULL TIME FOR A YEAR? $12,000
More informationTECHNICAL TERMS AND ABBREVIATIONS
THIRD REVISED SHEET NO. 3.1 CANCELS SECOND REVISED SHEET NO. 3.1 TECHNICAL TERMS AND ABBREVIATIONS ALTERNATING CURRENT (A-C): AMPERE: BASE RATES: BRITISH THERMAL UNIT (BTU): CAPACITOR or CAPACITANCE: CAPACITY
More informationGENERATOR INTERCONNECTION APPLICATION
GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW Also Serves as Application for Category 3 Net Metering (Note:
More informationPower Metrics International INC Richmond Terrace Staten Island, NY 10302
Synopsis In the following case study, a poultry processing plant with 7 SP1000 (predecessor to SP2000) units installed experienced monthly reductions in their electricity consumption ranging from 12.5%
More informationSingle-Phase Meter Components
Single-Phase Meter Components S T U D E N T M A N U A L March 2, 2005 2 STUDENT TRAINING MANUAL Prerequisites: None Objectives: From memory, you will be able to explain the parts and function of a single-phase
More informationElectric Rates for Utah
Electric Rates for Utah DIXIE ESCALANTE RURAL ELECTRIC ASSOCIATION BERYL, 84714 RESIDENTIAL SERVICE Service made available to residential members of the Cooperative under this rate schedule shall be single
More informationRATE 724 RATE FOR ELECTRIC SERVICE GENERAL SERVICE LARGE
NORTHERN INDIANA PUBLIC SERVICE COMPANY Original Sheet No. 53 TO WHOM AVAILABLE Sheet No. 1 of 5 Available for service to General Service Customers located on the Company s electric supply lines suitable
More informationSchedule GS-3 LARGE GENERAL SERVICE SECONDARY VOLTAGE I. APPLICABILITY AND AVAILABILITY
I. APPLICABILITY AND AVAILABILITY A. Except as modified herein, this schedule is applicable only to a non-residential secondary voltage Customer (as defined in Paragraph XII.) who (1) elects (a) to receive
More informationPanola-Harrison Electric Cooperative, Inc. Louisiana Tariff Effective: March 3, 2004
Rate Schedule: R Page 1 of 1 RESIDENTIAL RATE SCHEDULE R Available in all territory served by the Cooperative, in accordance with the established rules and regulations of the Cooperative. Residential uses
More informationCUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)
GENERATOR INTERCONNECTION APPLICATION Category 2 (Combined) For All Projects with Aggregate Generator Output of More Than 20 kw but Less Than or Equal to 150 kw Also Serves as Application for Category
More informationGlossary. * Credit for glossary starter: Florida Solar Energy Center. August 2015 PV Installer's Course: Glossary 1
ALTERNATING CURRENT (AC): Electric current (flow of electrons) in which the direction of flow is reversed at constant intervals, such as 60 cycles per second. AMORPHOUS SILICON: silicon with no crystal
More informationCHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS
CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS CHOPTANK ELECTRIC COOPERATIVE, INC. TERMS AND CONDITIONS TABLE OF CONTENTS PAGE NO. GENERAL 1 100 ELECTRIC SERVICE 101 Application
More informationSchedule GS-2 INTERMEDIATE GENERAL SERVICE
I. APPLICABILITY AND AVAILABILITY A. Except as modified herein, this schedule is applicable only to a non-residential Customer (1) who elects (a) to receive Electricity Supply Service and Electric Delivery
More informationNHPUC No. 3 - Electricity Delivery Thirtieth Revised Page 4 Unitil Energy Systems, Inc. Superseding Twenty-Ninth Revised Page 4
NHPUC No. 3 - Electricity Delivery Thirtieth Revised Page 4 Unitil Energy Systems, Inc. Superseding Twenty-Ninth Revised Page 4 SUMMARY OF DELIVERY SERVICE RATES (Includes Electricity Consumption Tax)
More informationWorking Principle of Power Saver as per Manufacture:
Analysis the Truth behind Household Power Savers Introduction: A House hold power saving devices has recently received a lot of attention from both consumers and manufacturers. It is generally used in
More informationCATEGORY 2 GENERATOR INTERCONNECTION APPLICATION
CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category 2 Net Metering
More informationElectric Utility Contact Information Indiana Michigan Power
CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category 2 Net Metering
More informationElectric Rates for Arizona
Electric Rates for Arizona DIXIE ESCALANTE RURAL ELECTRIC ASSOCIATION RESIDENTIAL SERVICE Service made available to residential customers of the Cooperative under this rate schedule shall be single phase
More informationTransmission & Distribution Glossary of Electrical Terms
Transmission & Distribution Glossary of Electrical s Breaker Panel Bushing Circuit Circuit Breaker Conductor Conduit Consumption Current Distribution Electricity (Static vs. Current) Electron Feeder The
More informationChapter 3.1: Electrical System
Part-I: Objective type Questions and Answers Chapter 3.1: Electrical System 1. The heat input required for generating one kilo watt-hour of electrical output is called as. a) Efficiency b) Heat Rate c)
More informationWhite Paper. Application of Resistive/Reactive Load Banks for kva Testing
White Paper Application of Resistive/Reactive Load Banks for kva Testing Application of Resistive/Reactive Load Banks for kva Testing Resistive load banks are the most commonly used load banks for the
More informationR07 SET - 1
R07 SET - 1 II B. Tech II Semester Supplementary Examinations April/May 2013 ELECTRICAL MACHINES - II (Electrical and Electronics Engineering) Time: 3 hours Max. Marks: 80 Answer any FIVE Questions All
More informationSteve Schouten. Donna Densmore
March 12, 2013 2 Steve Schouten Donna Densmore 3 Mike Carter Justin Kale 4 Basics Motor Loads Operation Advantages/ Disadvantages Sizing a VFD Power Quality Issues Source: Emerson Industrial Automation
More informationEXPERIMENT CALIBRATION OF 1PHASE ENERGY METER
EXPERIMENT CALIBRATION OF PHASE ENERGY METER THEORY:- Energy Meters are integrating instruments used to measure the quantity of electrical energy supplied to a circuit in a given time. Single phase energy
More informationRATE 725 RATE FOR ELECTRIC SERVICE METAL MELTING SERVICE
NORTHERN INDIANA PUBLIC SERVICE COMPANY Original Sheet No. 58 TO WHOM AVAILABLE Sheet No. 1 of 5 Available to Industrial Customers who have substantial requirement for electric metal melting and/or holding
More informationRESOLUTION NO
RESOLUTION NO. 2018-72 A RESOLUTION ESTABLISHING A SCHEDULE OF ELECTRICAL RATES TO BE CHARGED CUSTOMERS FOR ENERGY AND POWER FROM THE ELECTRIC DISTRIBUTION SYSTEM OF THE CITY; TO REPEAL CONFLICTING RATES
More informationVariable Frequency Drives
We Make Energy Engaging Variable Frequency Drives Questline Academy Meet Your Panelist Mike Carter questline.com 2 Contents Basics Motor Loads Operation Advantages/ Disadvantages Sizing a VFD Power Quality
More informationSingle Phase Meter Components
NWEMS Single Phase Meter Components August 21, 2017 Track A Scott Sutton, Snohomish County PUD PURPOSE of this class:» What is an electro mechanical Watt hour meter» The basic parts of the meter The function
More informationCorrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections
Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections One-Line / Riser Diagrams Drawings are not reviewed prior to submission. Because of
More informationVolume 2 Charts, Formulas, and Other Useful Information
Volume 2 Charts, Formulas, and Other Useful Information Aluminum Conductor Conductor Terminations 61 Compact Aluminum (Conduit Fill Tables) 68-79 Ampacity Dwelling Services 48 1-phase Loads on a 3-phase
More informationQ1. (a) The diagram shows the information plate on an electric kettle. The kettle is plugged into the a.c. mains electricity supply.
Q1. (a) The diagram shows the information plate on an electric kettle. The kettle is plugged into the a.c. mains electricity supply. 230 V 2760 W 50 Hz Use the information from the plate to answer the
More informationTHE PUBLIC SERVICE COMMISSION OF WYOMING
NAME: Powder River Energy Corporation WY PSC Tariff No. 7 ADDRESS:, Sundance, WY 82729 THE PUBLIC SERVICE COMMISSION OF WYOMING TARIFF RATE RIDER 5th Revised Sheet No. 1 Cancels 4th Revised Sheet No. 1
More informationPower Factor Correction
AE9-1249 R10 August 2008 Power Factor Correction Index Page 1. Introduction... 1 2. Electrical Fundamentals... 1 3. Electrical Formulas... 2 4. Apparent Power and Actual Power... 2 5. Effects of Poor Power
More informationUNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1. UNIT 2 ELECTRICAL CIRCUITS...49 Introduction...49
UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1 PART A ELECTRICIAN S MATH...1 Introduction...1 1.1 Whole Numbers...1 1.2 Decimal...1 1.3 Fractions...1 1.4 Percentages...2 1.5
More informationCARTHAGE WATER & ELECTRIC PLANT ELECTRIC RATES RESIDENTIAL SERVICE
RESIDENTIAL SERVICE This rate is available by contract for single-phase 120/240 volt service to a single family dwelling through one meter for domestic use, and to separate structures on the same parcel
More informationFRENCH BROAD ELECTRIC MEMBERSHIP CORPORATION RATE SCHEDULES
FRENCH BROAD ELECTRIC MEMBERSHIP CORPORATION RATE SCHEDULES Effective for Bills Rendered on or after April 1, 2017 Table of Contents Title Page Primary Residential (Rate Schedule A-17) 3 Secondary Residential
More informationMIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation
MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation David Aldrich Beckwith Electric Company Goals Flatten voltage profile across entire
More informationkvah Billing - Frequently Asked Questions (FAQs)
kvah Billing - Frequently Asked Questions (FAQs) 1. What is kvah billing? a. Electrical Energy has two components viz. Active Energy (kwh) and Reactive Energy (kvarh). Vector sum of these two components
More informationStreet Address. City-Village-Township
Schedule Designation D11 Primary Supply Agreement D11 963-1816 8/18 THIS AGREEMENT, dated, 20, by and between (Name) a, (Legal Entity and State of Organization) herein called the "Customer", and DTE Electric
More informationCalifornia PUC Rule 21 Generating. Facility Interconnection Application Guide. Technical Note
California PUC Rule 21 Generating Facility Interconnection Application Guide Technical Note Revision 1.3 December 15, 2004 Bill Reaugh Revision History 1.2 August 6, 2004 Bill Reaugh Original Posted Version
More informationENERGY MANAGEMENT 4/22/2014. What are your approximate yearly energy costs? (Electricity, natural gas, etc.)
MICHIGAN CHAMBER OF COMMERCE ENERGY MANAGEMENT Webinar Electricity - Natural Gas April 23, 2014 10:00 A.M. - 11:00 A.M. EDT Presented by John M. Studebaker, Ph.D. www.studebakerenergy.net JStudebaker 4/23/14
More informationProper Application of Power Factor Capacitors and How They Can Reduce Energy Costs Eaton Corporation. All rights reserved.
Proper Application of Power Factor Capacitors and How They Can Reduce Energy Costs 1 2008 Eaton Corporation. All rights reserved. Learning Objectives At the end of this web session, you will be able to:
More informationADAMS-COLUMBIA ELECTRIC COOPERATIVE. Rates. Board Approved 1/27/16
ADAMS-COLUMBIA ELECTRIC COOPERATIVE Rates Board Approved 1/27/16 TABLE OF CONTENTS RATE CODE DESCRIPTIONS...2 RATE CODE DESCRIPTIONS (continued)...3 RATE DESCRIPTIONS (continued)...4 RATE SCHEDULE AVAILABILITY
More informationProduct Overview. Product Identification. Amps One CT Two CTs Three CTs
AH06 (optional mounting bracket for small, medium, and large CTs) DANGER HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH Follow safe electrical work practices. See NFPA 70E in the USA, or applicable
More informationELECTRIC WATER SEWER STORMWATER 3 Industrial Loop Drive PO Box 1589 Hannibal, MO (573)
ELECTRIC WATER SEWER STORMWATER 3 Industrial Loop Drive PO Box 1589 Hannibal, MO 63401 (573)-221-8050 www.hannibalbpw.org GENERAL PROVISIONS ELECTRIC SERVICE SCHEDULE Effective with usage beginning July
More informationSUMMARY OF TOTAL CURRENT PRICES - ELECTRIC
Electric Summary Sheet No. S-1 HOW A CUSTOMER BILL IS CALCULATED 7 RESIDENTIAL SERVICE For a customer who used 1,000 kwh during one month (assuming 30 days of service). Schedule 7 is referred to on customer
More informationStreet Address. City-Village-Township
Schedule Designation D11 Primary Supply Agreement D11 963-1816 77/15 THIS AGREEMENT, dated, 20, by and between (Name) a, (Legal Entity and State of Organization) herein called the "Customer", and DTE Electric
More informationRATE APPLICATION MANUAL. Kansas City Board of Public Utilities
RATE APPLICATION MANUAL Kansas City Board of Public Utilities APPROVED BY THE BPU BOARD February 1, 2017 RATES EFFECTIVE January 1, 2018 RATE APPLICATION MANUAL BOARD OF PUBLIC UTILITIES PAGE TABLE OF
More informationSolar PV Standard Electrical Plan
*** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Permit Number: SCOPE: Standard plan for installation of solar PV systems utilizing 2 wire
More informationCSDA Best Practice. Hi-Cycle Concrete Cutting Equipment. Effective Date: Oct 1, 2010 Revised Date:
CSDA Best Practice Title: Hi-Cycle Concrete Cutting Equipment Issue No: CSDA-BP-010 : Oct 1, 2010 Revised : Introduction Hi-cycle/high frequency concrete cutting equipment has become more prevalent in
More informationPeace River Electric Cooperative, Inc.
ELEVENTH REVISED SHEET NO. 7.0 CANCELING TENTH REVISED SHEET NO. 7.0 Peace River Electric Cooperative, Inc. INDEX OF RATE SCHEDULES Designation Description Sheet Number R-S Residential Service 8.0 RS-TOU
More informationEPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010
EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010 Community Energy Storage Presentation & Simulation Results Thomas J. Walker Emeka Okafor 1 Energy Storage Applications in
More informationMay 3, 2017 ESI. Utility Bills: Finding Buried Treasure Department of Environmental Quality
May 3, 2017 ESI Utility Bills: Finding Buried Treasure Department of Environmental Quality Utility Bills 101 Typical Electric Bills Regulated Utilities Energy & Demand in kwh; kw Billed, Actual, Contract,
More informationBeaver Power Factor Correction Capacitors
Beaver Power Factor Correction Capacitors Beaver Low Voltage Power Factor Correction Capacitors are designed for long life and are made with the highest quality materials. All units are assembled in Canada
More informationMYRON ZUCKER CALMANUAL POWER FACTOR CORRECTION APPLICATION GUIDE INC.
MYRON ZUCKER CALMANUAL POWER FACTOR CORRECTION APPLICATION GUIDE INC. CALMANUAL HOW TO APPLY CAPACITORS TO LOW VOLTAGE POWER SYSTEMS. SECTION INDEX SECTION I POWER FACTOR UNDERSTANDING POWER FACTOR...
More informationCITY OF GRAND ISLAND UTILITIES DEPARTMENT ELECTRIC RATE SCHEDULE Effective October 1, Ordinance No. 9133
010, RESIDENTIAL SERVICE CITY OF GRAND ISLAND UTILITIES DEPARTMENT ELECTRIC RATE SCHEDULE Effective October 1, 2007 - Ordinance No. 9133 Applicable in urban and rural distribution areas. Available in single
More informationA Solar Power System for a Residential Application
A Solar Power System for a Residential Application Osman N. Muneer ECET 490 Final Presentation Due: 12/18/08 Instructor: Paul I-Hai Lin, P.E. (EE) Faculty Advisor: Iskandar Hack, P.E. (EE) 1 Introduction
More informationTECHNOLOGY AND MARKET TRIALS PROGRAM. Final Report Motorboss Motor Controller Field Test
Las Vegas, Nevada TECHNOLOGY AND MARKET TRIALS PROGRAM Final Report Motorboss Motor Controller Field Test Levi Strauss and McCarran Airport Test Sites Prepared By: Prepared For: Larry Holmes Program Manager,
More informationElectrical power. Objectives. Assessment. Assessment. Equations. Physics terms 5/27/14
Electrical power Objectives Use the equation for electrical power to solve circuit problems. Understand basic concepts for home electricity usage and wiring. Calculate the power used by electric circuit
More information2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code
2. DEFINITIONS 2.1 ACCEPTABLE Acceptable to the Company. 2.2 ADVANCED METER A meter that is capable of remote reading, and is capable of storing electric consumption data at specified time intervals of
More informationTED 5000 USER MANUAL
TED 5000 USER MANUAL The Energy Detective (TED) is an accurate electricity monitor that provides real-time feedback on electricity usage. TED will lower utility bills, reduce electric waste, and save the
More informationUltravar TM AUTOMATIC POWER FACTOR CORRECTION & HARMONIC SOLUTIONS
AUTOMATIC POWER FACTOR CORRECTION & HARMONIC SOLUTIONS Contents Benefits of Power Factor Improvement... 4 ACCU-VAR Plus - AVC (50 to 600 KVAR) Standard and Optional Features... 5 240, 480, 600 Volt Equipment...
More informationOSC is your electric meter expert. When you have questions or need assistance in selecting the proper meter for the job, call us!
Socket Watthour Meters ASK THE EXPERTS OSC is your electric meter expert. When you have questions or need assistance in selecting the proper meter for the job, call us! NEW METERS OSC offers several different
More informationForm G5-1 PACIFIC GAS AND ELECTRIC COMPANY GENERATION PRE-PARALLEL INSPECTION
Form G5-1 Page 1 of 3 PACIFIC GAS AND ELECTRIC COMPANY PG&E LOG WO/GM D&C Name of Project: Location: Transmission Line No. Distance Circuit No. 1. Maintenance Data: Generation Customer s Maintenance Chief
More informationPower Quality Luis Vargas Research Engineer 9/18/2008
Page: 1 of 5 Luis Vargas Research Engineer 9/18/2008 Page: 2 of 5 As we make advances on green technology, we get a better understanding of the efficiencies and deficiencies on how we consume electricity.
More informationIgnition Coil Current Waveforms 2007 Honda Accord SE 4CYL
P a g e 1 Ignition Coil Current Waveforms 2007 Honda Accord SE 4CYL With a current clamp and a cheap scope, it is easy to monitor the ignition coil currents and quickly diagnose a bad ignition coil. The
More informationRATE 624 RATE FOR ELECTRIC SERVICE GENERAL SERVICE LARGE
NORTHERN INDIANA PUBLIC SERVICE COMPANY Original Sheet No. 56 TO WHOM AVAILABLE No. 1 of 5 Sheets Available to General Service Customers for electric service who are located on the Company s electric supply
More informationELECTRICAL MACHINES-II LABORATORY MANUAL
ELECTRICAL MACHINES-II LABORATORY MANUAL T. ANIL KUMAR Associate Professor Department of Electrical and Electrical Engineering N. SINDHU Assistant Professor Department of Electrical and Electrical Engineering
More informationINCREASE YOUR POWER FACTOR Manufactured By XZERES Corp.
M A D E I N T H E U S A INCREASE YOUR POWER FACTOR Manufactured By XZERES Corp. Endelos family of Power Efficiency products are designed to improve the power factor and reduce the amount of reactive power
More informationsmartvar Dynamic VAR Compensator
smartvar Dynamic VAR Compensator DOES YOUR BUSINESS NEED TO SAVE MONEY? Discover a quick and easy way to identify cost saving opportunities. Improve the dynamic processes in your facility with smartvar.
More informationAmerican Journal of Science, Engineering and Technology
American Journal of Science, Engineering and Technology 017; (4): 10-131 http://www.sciencepublishinggroup.com/j/ajset doi: 10.11648/j.ajset.017004.14 Application of Distribution System Automatic Capacitor
More informationORTRONIC System GREEN PLANET COMPANY.
ORTRONIC System A Totally New Concept In Power Generation The Ortronic System is the Best Solution for Off Grid or Off Generator Electrification as well as Back Up Emergency Generation in On Grid Applications
More informationAPUA TARIFFS ELECTRICITY TARIFFS
APUA TARIFFS ELECTRICITY TARIFFS General Purposes Tariff (G.P.T.): Applicable to general lighting of all premises and temporary supplies: o All units @.45 cents per unit o Minimum Charge: $15.00 per month
More informationTable of Contents. CHAPTER 1 ElECTRiCAl THEoRY Mike Holt enterprises, inc neC.Code ( )
CHAPTER 1 ElECTRiCAl THEoRY... 1 UniT 1 electrician s MaTH and BasiC electrical formulas... 3 Introduction to Unit 1... 3 Part A Electrician s Math... 3 Introduction... 3 1.1 Whole Numbers... 3 1.2 Decimals...
More informationH. J. Arnett Industries, LLC SW Avery Court Tualatin, OR 97062
H. J. Arnett Industries, LLC 20460 SW Avery Court Tualatin, OR 97062 Phone: 503-692-4600 Fax: 503-692-4661 Toll free: 800-684-9844 Web address: www.arnettindustries.com USE OF THE MEGA BEAST SERVICE CONDUCTOR
More informationOFF-GRID Hybrid (BI-DIRECTIONAL) SOLAR INVERTER SOLAR INVERTER SOLAR UPS
OFF-GRID Hybrid (BI-DIRECTIONAL) SOLAR INVERTER SOLAR INVERTER SOLAR UPS ITS Power & Infrastructure Pvt. Ltd. is a leading designs, manufacturer & supplier of power product. ITS Power Company is in Bavdhan,
More informationPower Line Communications Metering Systems. RSM-5c RSM-5. Installation Manual
Power Line Communications Metering Systems RSM-5c RSM-5 Installation Manual Table of Contents Chapter 1 Introduction 1 Chapter 2 Installation 2 Chapter 3 Fuse Block Connections 6 Chapter 4 Menu Navigation
More informationWelcome. Power Survey International
Welcome Company profile Established in 1948 Exclusively manufacture capacitor banks and harmonic filters Manufacturer of low and medium voltage products: Power Factor correction system Harmonic Filter
More informationSchedule GS-1 SMALL GENERAL SERVICE
I. APPLICABILITY AND AVAILABILITY II. A. Except as modified herein, this schedule is applicable only to a non-residential Customer (1) who elects (a) to receive Electricity Supply Service and Electric
More informationInstallation and Maintenance Instructions. World Leader in Modular Torque Limiters. PTM-4 Load Monitor
World Leader in Modular Torque Limiters Installation and Maintenance Instructions PTM-4 Load Monitor 1304 Twin Oaks Street Wichita Falls, Texas 76302 (940) 723-7800 Fax: (940) 723-7888 E-mail: sales@brunelcorp.com
More informationMichigan Commercial and Industrial Service Rates. Effective Jan. 1, 2017, for Xcel Energy electric and natural gas customers.
Michigan Commercial and Industrial Service Rates Effective Jan. 1, 2017, for Xcel Energy electric and natural gas customers. Electric service The Supply Energy charge indicated for each type of service
More informationIndianapolis Power & Light Company I.U.R.C. No. E-18 Original No. 17 One Monument Circle Indianapolis, Indiana
Indianapolis Power & Light Company I.U.R.C. No. E-18 Original No. 17 RATE UW WATER HEATING -- UNCONTROLLED SERVICE AVAILABILITY: This Rate is closed and not available for service to new installations after
More informationTORONTO HYDRO-ELECTRIC SYSTEM LIMITED TARIFF OF RATES AND CHARGES
Page 1 of 6 APPLICATION - The application of these rates and charges shall be in accordance with the Licence of THESL and any Codes, Guidelines or Orders of the Board, and amendments thereto as approved
More informationABB n.v PQF LV Active Filters: Bringing energy savings to you
ABB n.v. - 1-2GCS617011A0070 PQF LV Active Filters: Bringing energy savings to you Key elements of poor LV Power Quality Harmonics Reactive power Load imbalance ABB n.v. - 2 - Energy losses and high running
More information