1 Decision New 500-kW Emergency Back-up Generator for Wal-Mart Perishable Foods Distribution Centre Balzac, Alberta December 17, 2010

2 ALBERTA UTILITIES COMMISSION Decision : Wal-Mart Canada New 500-kW Emergency Backup Generator for Wal-Mart Perishable Foods Distribution Centre Balzac, Alberta Application No Proceeding ID. 893 December 17, 2010 Published by Alberta Utilities Commission Fifth Avenue Place, 4th Floor, Street SW Calgary, Alberta T2P 3L8 Telephone: (403) Fax: (403) Web site:

3 ALBERTA UTILITIES COMMISSION Calgary Alberta WAL-MART CANADA CORP. 500-KW EMERGENCY BACKUP GENERATOR FOR Decision PERISHABLE FOODS DISTRIBUTION CENTRE Application No BALZAC, ALBERTA Proceeding ID INTRODUCTION 1. (Wal-Mart) filed Application No on October 18, 2010, (Application) with the Alberta Utilities Commission (Commission) for an order pursuant to section 11 of the Hydro and Electric Energy Act, seeking an approval for construction and operation of a 500-kilowatt (kw), 600-volt (V) diesel-powered emergency backup generator in Balzac, Alberta (Power Plant). 2. The Power Plant would consist of one Detroit Diesel Engine Generator 500-kW Series 60. The Power Plant would be housed within a Crystal Quiet enclosure, which would be located adjacent to the Wal-Mart Canada Perishable Foods Distribution Centre at Wagon Wheel Crescent, in the Wagon Wheel Industrial Park, Balzac, Alberta. The legal land description of the Power Plant is the southwest quarter of Section 11, Township 26, Range 29, West of the 4th Meridian. 2 DISCUSSION 3. Wal-Mart stated that the Power Plant will only be used in emergency situations when electric power supply, normally provided by the utility to the distribution centre, is interrupted. Further, in the event that Wal-Mart must operate the Power Plant, the power generated will be used solely for its own use. 4. Subsequently, Wal-Mart indicated that it was seeking an exemption for its proposed Power Plant under section 13 of the Hydro and Electric Energy Act. 5. A two-page Noise Impact Assessment Summary Form (NIA Summary) was submitted with the Application. The noise impact assessment was conducted by Stirling Engineering Inc. The nearest residence is located 950 metres northwest of the proposed Wal-Mart facility. The Permissible Sound Level (PSL) is 50 dba L eq nighttime and 60 dba L eq daytime, which was based on a dwelling density of 1-8 dwellings and a category 3 designation of the dwelling because the dwelling is subject to frequent aircraft flyovers. The predicted sound level, including the prescribed ambient sound levels is 46 dba L eq, which is below both the daytime and nighttime PSL and would comply with the requirements of AUC Rule 012: Noise Control. In addition, Wal-Mart submitted that the sound from the proposed power plant would not be discernable beyond 100 metres from the power plant. 6. Wal-Mart submitted in the NIA Summary that the Power Plant would be scheduled for 30 minutes of routine testing once a week in the daytime, for a total of 26 hours per year, excluding power outages. AUC Decision (December 17, 2010) 1

4 New 500-kW Emergency Backup Generator 7. Wal-Mart stated that it had conducted a participant involvement program for the distribution centre, which includes the Power Plant and that there were no concerns as a result. Wal-Mart added that, as the proposed power plant is on its distribution site and will be enclosed, it submitted that the proposed power plant would have negligible impact on the residents near the proposed power plant. 8. Due to the nature of the application and the location of the proposed power plant, the Commission did not issue a notice of application as it did not appear from the application that resident in the area might be directly and adversely affected by the Commission s decision on this application. 3 FINDINGS 9. The Commission considered that Wal-Mart filed the Application pursuant to section 11 of the Hydro and Electric Energy Act, which states: 11 No person shall construct or operate a power plant unless the Commission, by order, has approved the construction and operation of the power plant. 10. However, subsequent to the filing of its application, Wal-Mart requested an exemption under section 13 of the Hydro and Electric Energy Act which states: 13(1) Sections 9, 10 and 11 do not apply to a person generating or proposing to generate electric energy solely for the person s own use, unless the Commission otherwise directs. (2) Notwithstanding subsection (1), a person generating or proposing to generate electric energy solely for the person s own use, if required by regulation to do so, immediately notify the Commission of the use or proposed use and provide any details of the generation and use that the Commission requires. 11. The Commission has reviewed the Application and considers it important that the proposed power plant will be located in an industrial area on land that has been disturbed by the construction of a distribution centre. Also, the proposed power plant will be enclosed in a Crystal Quiet enclosure. The Commission is satisfied that the submitted Noise Impact Assessment Summary Form and the subsequent information responses meet the requirements of AUC Rule 012: Noise Control. 12. Due to the nature of the Application and its location, the Commission was of the opinion that its decision on this application would not directly and adversely affect the rights of a person, pursuant to section 9 of the Alberta Utilities Commission Act. 13. The Commission finds that the Application meets the requirements of section 13 of the Hydro and Electric Energy Act because the Power Plant will be used to generate electric energy solely for Wal-Mart s own use in the event of an emergency that is in the event of a power outage at its distribution centre. 2 AUC Decision (December 17, 2010)

5 New 500-kW Emergency Backup Generator 4 DECISION 14. Pursuant to section 13 of the Hydro and Electric Energy Act, the Commission approves the Application and grants the requested Exemption to, as set out in Appendix 1 Power Plant Exemption No. U on December 17, 2010 to construct and operate the Power Plant at its perishable foods distribution centre (Appendix 1 will be distributed separately). Dated on December 17, ALBERTA UTILITIES COMMISSION (original signed by) Tudor Beattie, QC Commissioner AUC Decision (December 17, 2010) 3

Brion Energy Corporation

Brion Energy Corporation Decision 20907-D01-2015 MacKay River Commercial Project October 29, 2015 Alberta Utilities Commission Decision 20907-D01-2015 MacKay River Commercial Project Proceeding 20907 Application 20907-A001 October

More information

Decision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station.

Decision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station. Decision 2011-424 (Errata) Access Pipeline Inc. Errata to Decision 2011-424 Temporary Generation at Smoky Lake Pump Station January 4, 2012 The Alberta Utilities Commission Decision 2011-424 (Errata):

More information

Decision The City of Calgary. 30-kW Solar Power Plant. March 8, 2012

Decision The City of Calgary. 30-kW Solar Power Plant. March 8, 2012 Decision 2012-065 30-kW Solar Power Plant March 8, 2012 The Alberta Utilities Commission Decision 2012-065: 30-kW Solar Power Plant Application No. 1607869 Proceeding ID No. 1563 March 8, 2012 Published

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act. Decision 2014-108 Application for an Exemption under Section 24 of the Hydro and Electric Energy Act April 17, 2014 The Alberta Utilities Commission Decision 2014-108: Application for an Exemption under

More information

Coalspur Mines (Operations) Ltd.

Coalspur Mines (Operations) Ltd. Decision 22744-D01-2017 Application for an Exemption Under Section 24 of the Hydro and Electric Energy Act October 5, 2017 Alberta Utilities Commission Decision 22744-D01-2017 Application for an Exemption

More information

University of Alberta

University of Alberta Decision 2012-355 Electric Distribution System December 21, 2012 The Alberta Utilities Commission Decision 2012-355: Electric Distribution System Application No. 1608052 Proceeding ID No. 1668 December

More information

Noise Impact Assessment

Noise Impact Assessment Noise Impact Assessment Deer Creek Energy Limited Joslyn North Mine Prepared For Millennium EMS Solutions Prepared By Mr. James Farquharson, CET Mr. Clifford Faszer, P. Eng. Faszer Farquharson & Associates

More information

Penn West Petroleum Ltd. Well Blowout W5M August 17, 2010

Penn West Petroleum Ltd. Well Blowout W5M August 17, 2010 Penn West Petroleum Ltd. Well Blowout 14-20-065-10W5M August 17, 2010 ERCB Investigation Report August 24, 2011 ENERGY RESOURCES CONSERVATION BOARD ERCB Investigation Report: Penn West Petroleum Ltd.,

More information

Direct Energy Regulated Services

Direct Energy Regulated Services Decision 23986-D01-2018 Application for True-Up of the 2017 and 2018 Interim Rates for the Default Rate Tariff and the Regulated Rate Tariff December 4, 2018 Alberta Utilities Commission Decision 23986-D01-2018

More information

Decision D Finlay Group. Complaint Regarding FortisAlberta Inc. Distribution Line Rebuild Project. February 3, 2016

Decision D Finlay Group. Complaint Regarding FortisAlberta Inc. Distribution Line Rebuild Project. February 3, 2016 Decision 20799-D01-2016 Complaint Regarding FortisAlberta Inc. Distribution Line Rebuild Project February 3, 2016 Alberta Utilities Commission Decision 20799-D01-2016 Proceeding 20799 Application 20799-A001

More information

Bohn to Kettle River Transmission Project

Bohn to Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

Kettle River Transmission Project

Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

Included in this Stakeholder Information Package:

Included in this Stakeholder Information Package: Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Permit Holder. Permitted Equipment

Permit Holder. Permitted Equipment Air Quality Registration Stationary Compression Ignition Internal Combustion Engine (Less than 400 Brake Horsepower) Permit No. Project No. Description Date Testing No Plant Number: Under the Direction

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Willingdon Substation Decommission

Willingdon Substation Decommission November 2012 Why are you receiving this project information package? New transmission facilities have been proposed in central east Alberta. As a result, some existing facilities are no longer needed.

More information

CITY COUNCIL AGENDA REPORT

CITY COUNCIL AGENDA REPORT CITY COUNCIL AGENDA REPORT Subject: RV PARKING ON PUBLICLY ACCESSIBLE PRIVATE PROPERTY Recommendation(s): That Administration bring forward amendments to the Traffic and Land Use Bylaw as per the concepts

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

Explaining AER Setbacks

Explaining AER Setbacks Explaining AER Setbacks This EnerFAQs explains setbacks in the energy industry, how they are determined, and how they may affect Albertans and their communities. What is a setback? A setback is the absolute

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 23157-D01-2018 Downtown Calgary Transmission Reinforcement Project November 9, 2018 Alberta Utilities Commission Decision 23157-D01-2018 Downtown Calgary Transmission Reinforcement Project Proceeding

More information

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES 220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering Credits 18.06:

More information

Joint Operating Procedures for First Nations Consultation on Energy Resource Activities

Joint Operating Procedures for First Nations Consultation on Energy Resource Activities Joint Operating Procedures for First Nations Consultation on Energy Resource Activities October 31, 2018 Contents Revision History... iv Definitions of Key Terms... v 1 Background... 1 2 Roles and Responsibilities...

More information

National Grid. Narragansett Electric Company INVESTIGATION AS TO THE PROPRIETY OF COMPLIANCE TARIFF CHANGES. 2 nd Amended Compliance Filing

National Grid. Narragansett Electric Company INVESTIGATION AS TO THE PROPRIETY OF COMPLIANCE TARIFF CHANGES. 2 nd Amended Compliance Filing National Grid Narragansett Electric Company INVESTIGATION AS TO THE PROPRIETY OF COMPLIANCE TARIFF CHANGES 2 nd Amended Compliance Filing Attachment 1: Book 2 of 2 April 2010 Submitted to: Rhode Island

More information

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

CITY OF PLACENTIA RESIDENTIAL PERMIT PARKING PROCEDURES AND GUIDELINES 2017

CITY OF PLACENTIA RESIDENTIAL PERMIT PARKING PROCEDURES AND GUIDELINES 2017 CITY OF PLACENTIA RESIDENTIAL PERMIT PARKING PROCEDURES AND GUIDELINES 2017 INTRODUCTION Permit parking in the City of Placentia is available to regulate and manage residential curb parking problems within

More information

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue.

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue. January 8, 2017 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: Electric Vehicle Charging Stations New Park Board Locations RECOMMENDATION

More information

Currant Lake Transmission Project

Currant Lake Transmission Project Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Concerning Energy Efficiency Rolling Portfolios, Policies, Programs, Evaluation, and Related Issues. R.13-11-005

More information

HydroGenerations PROGRAM HANDBOOK

HydroGenerations PROGRAM HANDBOOK HydroGenerations PROGRAM HANDBOOK TABLE OF CONTENTS Please ensure you are reading the most recent version of this handbook by visiting the NV Energy website, www.nvenergy.com/hydro. Contents HydroGenerations

More information

FISCHER, FRANKLIN & FORD Attorneys and Counsellors GUARDIAN BUILDING, SUITE GRISWOLD STREET DETROIT, MICHIGAN

FISCHER, FRANKLIN & FORD Attorneys and Counsellors GUARDIAN BUILDING, SUITE GRISWOLD STREET DETROIT, MICHIGAN ARTHUR J. LeVASSEUR MATTHEW M. PECK TROY C. OTTO SIDNEY M. BERMAN* LAUREN J. McGILL* *Of Counsel FISCHER, FRANKLIN & FORD Attorneys and Counsellors GUARDIAN BUILDING, SUITE 3500 500 GRISWOLD STREET DETROIT,

More information

conversation SHAPE the May 2015 The AUC

conversation SHAPE the May 2015 The AUC SHAPE the conversation May 2015 Thickwood Hills Transmission PROJECT The Thickwood Hills Transmission Project is needed to connect planned critical transmission infrastructure, that will reinforce the

More information

MICRO-GENERATION NOTICE SUBMISSION GUIDELINE

MICRO-GENERATION NOTICE SUBMISSION GUIDELINE www.auc.ab.ca MICRO-GENERATION NOTICE SUBMISSION GUIDELINE (Version 2.0) September 20, 2017 Table of Contents 1. Introduction... 2 2. Purpose... 2 3. Differences between micro-generation and distributed

More information

Tariff cover sheets reflecting all rates approved for April 1 in Dockets 4218 (ISR) and 4226 (Reconciliation Filing).

Tariff cover sheets reflecting all rates approved for April 1 in Dockets 4218 (ISR) and 4226 (Reconciliation Filing). Thomas R. Teehan Senior Counsel April 4, 2011 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick, RI 02888 RE:

More information

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application

More information

EXECUTIVE SUMMARY. 28-Sep-15

EXECUTIVE SUMMARY. 28-Sep-15 28-Sep-15 EXECUTIVE SUMMARY HGC Engineering was retained by Union Gas ed to undertake an Acoustic Assessment of their Electrical Power Generators in Ontario. This assessment applies to power generators

More information

November 29, 2017 BHEC-RES ALBERTA LP

November 29, 2017 BHEC-RES ALBERTA LP BHEC-RES ALBERTA LP Forty Mile Wind Power Project - Noise Impact Assessment Update Submitted to: Lucas Reindler Project Development Manager Renewable Energy Systems Canada Inc. as agent for BHEC-RES Alberta

More information

Declaration naming Richard J. Nixon and Dale Brand under section 106 of the Oil and Gas Conservation Act

Declaration naming Richard J. Nixon and Dale Brand under section 106 of the Oil and Gas Conservation Act November 30, 2017 By email and registered mail To: Richard J. Nixon Dale Brand Declaration naming Richard J. Nixon and Dale Brand under section 106 of the Oil and Gas Conservation Act Dear Messrs. Nixon

More information

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Policy Bulletin No. 25 Net Metering Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Interconnection Standards For Residential Net Energy Metering With Electric

More information

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section 7-207.1 and 7-207.2 APPLICABILITY The Public Service Commission of Maryland ( Commission

More information

E) That the General Manager be authorized to execute and deliver such documentation on behalf of the Park Board.

E) That the General Manager be authorized to execute and deliver such documentation on behalf of the Park Board. Date: May 30, 2012 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Electric Vehicle Charging Stations and Cellular Infrastructure in English Bay Parks RECOMMENDATION

More information

Louisiana Net Metering Service. Customer Information Package

Louisiana Net Metering Service. Customer Information Package Louisiana Net Metering Service Customer Information Package August 1, 2013 Net Metering - The means of measuring the difference between the electricity supplied by an electric utility and the electricity

More information

MICRO-GENERATOR APPLICATION GUIDELINE

MICRO-GENERATOR APPLICATION GUIDELINE www.auc.ab.ca MICRO-GENERATOR APPLICATION GUIDELINE (Version 1.1) September 1, 2011 Table of Contents 1. Introduction... 2 2. Purpose 2 3. Legal and related matters... 2 4. Disclaimer 3 5. Micro-generators

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

SOUTHWEST CALGARY RING ROAD (SWCRR)

SOUTHWEST CALGARY RING ROAD (SWCRR) PROJECT OVERVIEW Alberta Transportation has started planning for the construction of the SW portion of the road that will complete the Calgary Ring Road. The completion of the SWCRR requires the relocation

More information

COMMERCIAL SCHEME Approval No

COMMERCIAL SCHEME Approval No COMMERCIAL SCHEME Approval No. 12806 MADE at the City of Calgary, in the Province of Alberta, on ALBERTA ENERGY REGULATOR IN THE MATTER of a commercial scheme of Imperial Oil Resources Ventures Limited

More information

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE Effective: April 2015 Billing Cycle AVAILABILITY: The E-27 Price Plan is subject

More information

APPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP)

APPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP) APPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP) Stirling Wind Project Connection PIP Summary 1.0 Participant Involvement Program (PIP) 1.1 PIP Design The AESO s Participant Involvement Program (PIP) is

More information

Crestmont Development Update 2017 AGM

Crestmont Development Update 2017 AGM Crestmont Development Update 2017 AGM West Crestmont West Crestmont Will be built in phases finally reaching about 524 residential units. Rough grading for phases 9 & 10 already underway. First show home

More information

THE UNIVERSITY OF HONG KONG LIBRARIES. Hong Kong Collection

THE UNIVERSITY OF HONG KONG LIBRARIES. Hong Kong Collection THE UNIVERSITY OF HONG KONG LIBRARIES Hong Kong Collection TECHNICAL MEMORANDUM ON NOISE FROM PERCUSSIVE PILING Environmental Protection Department Noise Control Authority This Technical Memorandum, originally

More information

DEPARTMENT OF TRANSPORTATION. Commercial Driver s License Standards: Application for Renewal of Exemption; Daimler Trucks North America (Daimler)

DEPARTMENT OF TRANSPORTATION. Commercial Driver s License Standards: Application for Renewal of Exemption; Daimler Trucks North America (Daimler) This document is scheduled to be published in the Federal Register on 04/16/2015 and available online at http://federalregister.gov/a/2015-08726, and on FDsys.gov DEPARTMENT OF TRANSPORTATION [4910-EX-P]

More information

DEPARTMENT OF TRANSPORTATION. Commercial Driver s License Standards: Application for Exemption; Daimler Trucks North America (Daimler)

DEPARTMENT OF TRANSPORTATION. Commercial Driver s License Standards: Application for Exemption; Daimler Trucks North America (Daimler) This document is scheduled to be published in the Federal Register on 08/17/2017 and available online at https://federalregister.gov/d/2017-17393, and on FDsys.gov DEPARTMENT OF TRANSPORTATION [4910-EX-P]

More information

PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA

PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA Assessment of Helicopter Noise A report Prepared on behalf of: JamCo Constructions Pty Ltd PO Box 631 Yarraville Victoria 3013 Ref: 11573-3jg March 2015

More information

Frequently Asked Questions Directive 079: Surface Development in Proximity to Abandoned Wells

Frequently Asked Questions Directive 079: Surface Development in Proximity to Abandoned Wells Frequently Asked Questions Directive 079: Surface Development in Proximity to Abandoned Wells July 2018 General Q1. How can I determine if a well is abandoned? A1. A third party can see if it is abandoned

More information

NOISE ORDINANCE SUMMARY

NOISE ORDINANCE SUMMARY NOISE ORDINANCE SUMMARY Prepared by Jim Massey for the Cecil County Council July 26, 2013 I. COUNTIES WITH LOCAL NOISE ORDINANCE The following Maryland Counties have a noise ordinance: Anne Arundel, Baltimore

More information

DEPARTMENT OF TRANSPORTATION. Hours of Service of Drivers: Application for Exemption; STC, Inc.

DEPARTMENT OF TRANSPORTATION. Hours of Service of Drivers: Application for Exemption; STC, Inc. This document is scheduled to be published in the Federal Register on 01/10/2018 and available online at https://federalregister.gov/d/2018-00248, and on FDsys.gov DEPARTMENT OF TRANSPORTATION [4910-EX-P]

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of January 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential

More information

February 13, Docket No. ER ; ER Response to Request for Additional Information

February 13, Docket No. ER ; ER Response to Request for Additional Information California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22013-D01-2016 2017 Interim Distribution Access Service Rates December 22, 2016 Alberta Utilities Commission Decision 22013-D01-2016 2017 Interim Distribution Access Service Rates Proceeding 22013

More information

NOVA SCOTIA UTILITY AND REVIEW BOARD

NOVA SCOTIA UTILITY AND REVIEW BOARD ORDER 2015 NSUARB 267 M07169 NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE LOAD

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Pacific Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system to

More information

DEPARTMENT OF TRANSPORTATION. Hours of Service of Drivers: American Concrete Pavement Association, Inc.; Application for Exemption

DEPARTMENT OF TRANSPORTATION. Hours of Service of Drivers: American Concrete Pavement Association, Inc.; Application for Exemption This document is scheduled to be published in the Federal Register on 09/06/2018 and available online at https://federalregister.gov/d/2018-19257, and on govinfo.gov DEPARTMENT OF TRANSPORTATION [4910-EX-P]

More information

GST/HST Memoranda Series

GST/HST Memoranda Series GST/HST Memoranda Series 19.3.8 December 2007 New Housing Rebates and the HST This memorandum explains the GST/HST new housing rebates that are available for a portion of the federal component of the HST

More information

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS TABLE OF CONTENTS Purpose and Scope...2 Authority...2 Applicability... 2 Intent.. 2 Maximum Connected Generation Allowed. 2 Definitions.

More information

This page is intentionally left blank.

This page is intentionally left blank. This page is intentionally left blank. Bipole III Southern Ground Electrode Line Route Selection Introduction Manitoba Hydro has recently selected a route for the southern ground electrode line (Map 1).

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF APRIL 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

CITY COUNCIL OF THE CITY OF NOVATO ORDINANCE NO. 1620

CITY COUNCIL OF THE CITY OF NOVATO ORDINANCE NO. 1620 G-12 CITY COUNCIL OF THE CITY OF NOVATO ORDINANCE NO. 1620 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF NOVATO AMENDING THE NOVATO MUNICIPAL CODE BY ADDING SECTION 4-19 (ELECTRIC VEHICLE CHARGING SYSTEMS)

More information

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES Last Revised Date: October 15, 2015 Contents Chapter 1 - Purpose and Scope 2 Chapter 2 - Application of Rules 2 Chapter 3 - Definitions

More information

Clyde Waste Transfer Facility Quarterly Truck Noise Measurements April 2009

Clyde Waste Transfer Facility Quarterly Truck Noise Measurements April 2009 REPORT 10-6815-R3 Quarterly Truck Noise Measurements April 2009 PREPARED FOR Cnr Unwin & Shirley Street ROSEHILL NSW 2142 30 APRIL 2009 HEGGIES PTY LTD ABN 29 001 584 612 Quarterly Truck Noise Measurements

More information

Proposed Land Use Bylaw Amendments - Skateboard and Sports Ramps

Proposed Land Use Bylaw Amendments - Skateboard and Sports Ramps Proposed Land Use Bylaw Amendments - Skateboard and Sports Ramps To assist with readability, the amendments are in numerical order with preceding and following bylaw text where relevant for context. The

More information

1. The purpose of this report is to seek the Board s support to set new speed limits on the roads described in this report (refer to attached plans).

1. The purpose of this report is to seek the Board s support to set new speed limits on the roads described in this report (refer to attached plans). 7. CHRISTCHURCH CITY PROPOSED NEW SPEED LIMITS General Manager responsible: General Manager City Environment, DDI: 941-8656 Officer responsible: Transport and Greenspace Manager Author: Malcolm Taylor,

More information

MISSOURI SERVICE AREA

MISSOURI SERVICE AREA MO.P.S.C. SCHEDULE NO. 6 1st Revised SHEET NO. 171.5 CANCELLING MO.P.S.C. SCHEDULE NO. 6 Original SHEET NO. 171.5 INTERCONNECTION APPLICATION/AGREEMENT FOR NET METERING SYSTEMS WITH CAPACITY OF 100 kw

More information

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY Virtual Net Metering Application Effective November 18, 2016 This application form addresses virtual net

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of September 1, 2015 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff

More information

Dawes Substation Project

Dawes Substation Project Dawes Substation Project Why are you receiving this project information package? March 2013 New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta

More information

Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document

Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document APPENDIX C AESO PIP Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From December 2015 to May 2016, the AESO conducted a Participant

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B;

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B; Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B; AND IN THE MATTER OF an Application by Thunder Bay Hydro Electricity

More information

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5 Columbia City, Indiana Page 1 of 5 SCHEDULE DG-2 LARGE POWER DISTRIBUTED GENERATION I. AVAILABILITY This Distributed Generation Rate is available to any member in good standing of Northeastern REMC (Northeastern)

More information

SYNOPSIS OF PROPOSED GEORGIA DEPARTMENT OF PUBLIC SAFETY RULES CHAPTER TRANSPORTATION NETWORK COMPANIES AND TAXI SERVICES

SYNOPSIS OF PROPOSED GEORGIA DEPARTMENT OF PUBLIC SAFETY RULES CHAPTER TRANSPORTATION NETWORK COMPANIES AND TAXI SERVICES SYNOPSIS OF PROPOSED GEORGIA DEPARTMENT OF PUBLIC SAFETY RULES CHAPTER 570-35 TRANSPORTATION NETWORK COMPANIES AND TAXI SERVICES Purpose: The rules provide for the registration and regulation of transportation

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Rocky Mountain Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system

More information

specifying the applications each has before the AER and the AER licences and approvals such licensee or approval holder holds.

specifying the applications each has before the AER and the AER licences and approvals such licensee or approval holder holds. DECLARATION NAMING ALEXANDER JUSTIN VON GRAMATZKI, FORMERLY KNOWN AS ALEXANDER JUSTIN HANNE, PURSUANT TO SECTION 106(1) OF THE OIL AND GAS CONSERVATION ACT For the reasons set out in the accompanying letter,

More information

Application for Annual Move Permit

Application for Annual Move Permit Application for Annual Move Permit Permit Number: Permit Fee: $109.50 Date: **Expires December 31 st of the Year of Issue** Annual Permit for Moving on Grey County Highways Heavy Vehicles in Excess of

More information

Net Metering Program

Net Metering Program Net Metering Program Chapter 1 Purpose and Scope. The purpose of this chapter is to establish rules for determining the terms and conditions governing the interconnection of electric generation facilities

More information

OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES

OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES October 12, 2017 PREPARED FOR: Ms. Chantly Banayan 4822 Van Nuys Blvd. Sherman Oaks, CA 91403 PREPARED

More information

Grande Cache Coal Corporation

Grande Cache Coal Corporation Decision 2010-115 Application for an Exemption Under Section 24 and a Connection Under Section 18 of the Hydro and Electric Energy Act March 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-115: Application

More information

DEPARTMENT OF TRANSPORTATION. Hours of Service; Electronic Logging Devices; Limited 90-Day Waiver; Truck Renting and Leasing Association, Inc.

DEPARTMENT OF TRANSPORTATION. Hours of Service; Electronic Logging Devices; Limited 90-Day Waiver; Truck Renting and Leasing Association, Inc. This document is scheduled to be published in the Federal Register on 01/19/2018 and available online at https://federalregister.gov/d/2018-00843, and on FDsys.gov DEPARTMENT OF TRANSPORTATION [4910-EX-P]

More information

Electric system improvements near you

Electric system improvements near you Electric system improvements near you Red Deer Area Transmission Development Stage 1 substation upgrades April 2011 Volume 1 Did you know? The average four-person family in Alberta today has 20 instant-on

More information

DEPARTMENT OF TRANSPORTATION. National Highway Traffic Safety Administration. Petition for Exemption from the

DEPARTMENT OF TRANSPORTATION. National Highway Traffic Safety Administration. Petition for Exemption from the This document is scheduled to be published in the Federal Register on 02/19/2016 and available online at http://federalregister.gov/a/2016-03443, and on FDsys.gov DEPARTMENT OF TRANSPORTATION National

More information

Dropped Crossing Service

Dropped Crossing Service Dropped Crossing Service Ringway Infrastructure Services offer a full service to install Vehicle Dropped Crossings. Our easy to follow guide will allow you to assess whether you need planning permission

More information

1996, or for which modification is commenced on or before March 16, 1998, shall not exceed the

1996, or for which modification is commenced on or before March 16, 1998, shall not exceed the 15A NCAC 02D.1206 HOSPITAL, MEDICAL, AND INFECTIOUS WASTE INCINERATORS (a) Applicability. This Rule applies to any hospital, medical, and infectious waste incinerator (HMIWI), except: (1) any HMIWI required

More information

Georgia Department of Revenue Policy Bulletin - MVD HB 170 Transportation Funding Act of 2015

Georgia Department of Revenue Policy Bulletin - MVD HB 170 Transportation Funding Act of 2015 Georgia Department of Revenue Policy Bulletin - MVD - 2015-01 HB 170 Transportation Funding Act of 2015 1) Purpose: Effective Date: July 1, 2015. 2) Authority: O.C.G.A. 40-2-11, 40-2-86.1, 40-2-151, 40-2-151.1,

More information

Southern California Edison Revised Cal. PUC Sheet No. Withdrawn Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No. Withdrawn Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 52399-E APPLICABILITY Schedule TOU-PA-5 Sheet 1 Applicable where SCE determines that 70% or more of the customer's electrical usage

More information

Resident Permit and Visitor Permit Guidelines

Resident Permit and Visitor Permit Guidelines OPERATING GUIDELINES Resident Permit and Visitor Permit Guidelines Approved by: GM, City Services May 2003 Subsequent Amendments: 9 September 2016 Associate Director (Vanessa Godden) Amended to reflect

More information

Net +Plus Connection Code

Net +Plus Connection Code Net +Plus Connection Code LANKA ELECTRICITY COMPANY (PRIVATE) LIMITED 1.0 BACKGROUND The existing Net Metering Concept launched in the year 2010 noticed an exponential growth in the recent year and at

More information