Kevin Duffin - Martime Assurance & Consulting John Flynn- Stena Drilling

Size: px
Start display at page:

Download "Kevin Duffin - Martime Assurance & Consulting John Flynn- Stena Drilling"

Transcription

1 DYNAMIC POSITIONING CONFERENCE October 11-12, 2016 RISK DP Undesired Events - Investigation and Methodology Kevin Duffin - Martime Assurance & Consulting John Flynn- Stena Drilling

2 DP Undesired Events Investigation and Methodology 11 October 2016

3 Summary Stena IceMAX - undesired events offshore Nova Scotia, Canada, 4 th December, 2015 Effective investigation strategy Root cause identified Remedial actions verified through proving trials Lessons learned

4 Stena IceMAX. Length ~ 750ft Breadth ~ 138ft Depth ~ 62ft Gross tonnage ~ 58, 295t World s 1 st DP, dual mast, ice class drillship Delivered 2012 from SHI, Korea Water depth ~ 9,800ft Drilling depth ~ 35,000ft DP 3 (DYNPOS AUTRO) notation Winterised Cold ( 30 C, 20 C) notation

5 Commissioning and Assurance. UK Flag State Registration Stena IceMAX Commissioned 2012 SHI Korea Stena Technical Commissioning Team Attendance IMCA standard, DNV approved FMEA DNV witnessed Proving Trials Annual DP Trials in accordance with IMCA M 191 Accepted by the Shell Assurance Team In line with Industry Best Practice

6 Stena IceMAX Worst Case Failure Design Intent (WCFDI) Port Redundancy Group DG 1 DG 2 Centre Redundancy Group DG 3 DG 4 Starboard Redundancy Group DG 5 DG 6 No single failure, as defined for DYNPOS AUTRO notation, will have a greater effect on the vessel s ability to maintain position and heading than the loss of one of the three power system redundancy groups (port, centre or starboard engine rooms / switchboard rooms) with the resulting loss of the associated 11kV switchboard, two diesel generators and two thrusters. Thruster 1 (centre bow) Thruster 3 (starboard bow) Thruster 2 (port bow) Thruster 4 (port stern) Thruster 6 (centre stern) Thruster 5 (starboard stern)

7 Location Cheshire Well, Offshore Nova Scotia, Canada

8 December 4 th, 2015 Wind speed 46kts 1.15am Several small vessel excursions (<5m) Vessel reverts to Blue (Advisory) status, as per WSOG G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

9 December 4 th, 2015 Wind speed 46kts 2.15am Five power limitation alarms on centre switchboard (ECR alarms) Drilling rate reduced to slow G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

10 December 4 th, 2015 Wind speed 46kts 3.40am Average power consumption ~ 40% G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

11 December 4 th, 2015 Large Wave ~ 10 mtr Wind speed 46kts 3.46am Vessel hit by rogue wave moves 13m astern Thrusters ramp up and load on each swbd increases (80 90%) G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

12 December 4 th, 2015 Wind speed 46kts 3.48am As vessel approaches original set point, thruster and bus load decreases rapidly Approaching set point, CBs for DGs 1 & 2 trip, blacking out swbd 1 DGs 1 & 2 remain running Vessel goes to Yellow status and prepares for disconnection G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

13 December 4 th, 2015 Wind speed 46kts 3.50am DG 4 also trips All thrusters operating at max and swbd load at 90 95% G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

14 December 4 th, 2015 Wind speed 46kts 3.55am High temps on DGs 1 & 2 so have to be stopped. DG 4 was still running after trip and was successfully reconnected to swbd G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

15 December 4 th, 2015 Wind speed 58kts 4.05am Wind increases to 58kts Vessel moves 35m from set point Thrusters ramp up and swbd load increases G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

16 December 4 th, 2015 Wind speed 58kts 4.05am When 1m away from set point, reduced power demand results in DG3 trip Power limitation alarms DG 3 reconnected Vessel regains position G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

17 December 4 th, 2015 Wind speed 46kts 6.00am DG 2 reconnected (05:36) DG 1 reconnected (05:43) Swbd 1 recovered and thrusters 1 and 4 back in DP G1 G2 G3 G4 G5 G6 Thruster Load 50% 75% 100%

18 Immediate Response Stena DP Marine / Technical Team Notified Canadian authorities Initiated investigation Mobilised multi-disciplined investigation team (OEM vendors, third party consultancies) Organised and led Bi-Daily technical meetings with Client Engaged MAC as independent for investigation in line with MTS TECHOP_GEN_03

19 Investigation MTS TECHOP_GEN_03, Conducting Effective and Comprehensive DP Incident Investigations 2AA 3AA 4AA 5AA Incident DATA 1 LFI PATHWAY SHORT TERM ACTIONS 6A 2BB 3BB 4BB 5BB

20 Investigation DESIGN OPERATIONS PROCESS PEOPLE DP PMS AVRs Protection relays Governors Environment DP FMEA Proving Trials Annual Trials DP Checklists WSOG Crew Response

21 Design - DP Control System DP system dynamically allocates thrust in response to weather Faults with system may result in thrust demand issues DP vendor technician mobilised to vessel to inspect DP control system configuration WIND POSITION REFs & SENSORS DP Control System and monitor trends Trends, event lists and alarm lists concluded DP system was operating as designed. Did not contribute to undesired events ALLOCATION OF THRUST

22 Design - Power Management System PMS interacts with DGs, thruster and drilling loads for a stable, balanced power system Configuration issues may result in mismanagement of the generators. PMS/VMS vendor technician mobilised to inspect PMS G1 Power Management System G2 G3 G4 G5 G6 Trends, event lists and alarm lists concluded that PMS did not contribute to undesired events

23 Design AVRs Reactive load sharing issues may lead to spurious tripping of generators OEM vendor technician mobilised to vessel to collect data from AVRs for off-site analysis On site inspection confirmed AVRs were configured correctly Did not contribute to undesired events

24 Design Protection Relays Incorrectly configured protection relays could lead to premature tripping of DGs OEM vendor technician collected data from protection relays Relays were reset and cleared while recovering DGs resulting in the loss of trip flags and data. Configuration files confirmed relays were set according to coordination study. Reverse power trip setting: -4% for 5s Reverse power trip reset: positive power for 1s Did not contribute to undesired events

25 Design - Engine Governors (Mechanical) Technicians from a local vendor investigated governor performance - simulated loads Hz and kw trends monitored during step load testing at 20% increments from 0% to 100% Mechanical calibration of actuator and fuel rack checked Performance stable across all loads and within tolerances Did not identify cause of undesired events Load Fuel rack position Set point actual DG 1 DG 2 DG 3 Time DG 4 DG 5 DG 6 Actuator Index

26 Design Engine Governors (Electrical) Technicians from OEM vendor investigated governor performance. Increased weather during investigation induced oscillation within power system identifying root cause of undesired event. Trending during this weather event indicated that paralleled generators were hunting between zero and 70-90%.

27 Generator Hunting Contributory Factors 1. Proportional gain set low resulting in speed deviations between reference and actual for minor load changes 2. Gain multiplier set for a narrow band (from 3 4rpm) resulting in small deviations in speed being significantly amplified High gain Medium gain Low gain Amplified load fluctuations may take longer to reach equilibrium Under significant load changes, generator response is amplified resulting in increased hunting across the set point reference

28 Design - Potential Root Cause Example plot of DG3 Over Power and References Heavy weather gives rise to rapid load changes 100 Power (%) Frequency of oscillation greater than the sample rate of the protection relay Hunting on parallel DGs oscillating in and out of reverse power Each trip relay sees 4 threshold 5s reverse power condition and trips DG 0 Time (s)

29 Operations - Environment Increased weather resulted in large and significant load changes on the vessel power plant as the DP System responded to maintain position Operated in harsh environments previously without incident The significant load changes highlighted governor tuning issues Cannot be considered a root cause

30 Process Key DP Documents Industry standard FMEA. Industry standard Proving Trials Industry standard Annual Trials. Industry standard DP Checklists... WSOG... All vessel documentation in compliance with rules, guidelines and industry best practice Industry standard documentation does not require that a vessel be tested / verified under extreme dynamic load conditions

31 People Crew Actions Experienced drilling and marine crew no previous incidents onboard the IceMAX The following can be concluded from review of crew witness statements: Post failure recovery of switchboards could have been better Vessel Master/OIM could have been alerted earlier to enable a faster response No human element contributed to the undesired events

32 Investigation Actions MTS TECHOP_GEN_03, Conducting Effective and Comprehensive DP Incident Investigations 2AA 3AA 4AA 5AA Incident DATA 1 LFI PATHWAY Root Cause governor tuning SHORT TERM ACTIONS 6A 2BB 3BB 4BB 5BB

33 Short Term Actions Investigation completed Governor tuning to dynamic load conditions Verifying trials created Interaction with Regulator and Client Amendment of WSOG (while Investigation in process) Incident reporting (IMCA)

34 Short Term Actions - Verifying Trials Proving trials offshore Nova Scotia 1 st and 2 nd January, 2016 Objective - demonstrate power plant stability under rapid and severe load changes: 1. Active (kw) load sharing.. 2. Reactive (kvar) load sharing.. 3. Verify reverse power protection.. 4. Verify PMS functionality... Governor tuning improved stability of power plant in response to dynamic load changes

35 Medium and Long Term Actions Lessons learned recorded in Stena Drilling HSE recording system Included in Stena Drilling Processes for the future: Governor tuning to be optimised during commissioning of new vessels OEM vendor approved training on specialist equipment Advanced drills for simulated DP failures and response

36 Conclusions Governor tuning issues hidden until significant load changes highlighted power system instability Stena Drilling initiated a thorough Incident Investigation, based on MTS TECHOP and identified root cause Remedial action was verified through proving trials

37 Conclusions (cont.) Stena Fleet DP trials updated to include significant step change testing. Regulator requesting step change testing for all DP vessel entry. Client adopted testing for on-hire DP Vessels. Open dialogue with Industry bodies for improvement.

38 Thanks for your time Kevin Duffin John Flynn UK Office +44 (0) America Office 1 (920) John.flynn@stena.com Direct No +44 (0) Mobile +44 (0)

POWER SESSION. DP3 Class Power System Solutions for Dynamically Positioned Vessels

POWER SESSION. DP3 Class Power System Solutions for Dynamically Positioned Vessels Return to Session Menu DYNAMIC POSITIONING CONFERENCE October 9-10, 2012 POWER SESSION DP3 Class Power System Solutions for Dynamically Positioned Vessels Stig Settemsdal and Damir Radan Integrated Systems

More information

DP INNOVATION. A Novel Solution to Common Mode Failures in DP Class 2 Power Plant

DP INNOVATION. A Novel Solution to Common Mode Failures in DP Class 2 Power Plant DP INNOVATION A Novel Solution to Common Mode Failures in DP Class 2 Power Plant Dr. Steven Cargill Noble Denton Consultants, Ltd October 7-8, 2008 Return to Session Directory A Novel Solution to Common

More information

Optimizing Energy Efficiency for DP Vessels for Variable Operational Risks

Optimizing Energy Efficiency for DP Vessels for Variable Operational Risks Return to Session Menu DYNAMIC POSITIONING CONFERENCE October 14-15, 2014 GREEN INITIATIVES Optimizing Energy Efficiency for DP Vessels for Variable Operational Risks Damir Radan & Steven Mankevich Optimizing

More information

Appendix A. Power Management System Test Guidelines

Appendix A. Power Management System Test Guidelines Appendix A Power Management System Test Guidelines The MTS DP Committee wants to thank Don Wilkes of Minden Engineering Company for his authorship of this appendix to the Test Guidelines Table of Contents

More information

Regulatory frameworks for Dynamically Positioned vessels operating in closed bustie mode: the grey zone

Regulatory frameworks for Dynamically Positioned vessels operating in closed bustie mode: the grey zone Regulatory frameworks for Dynamically Positioned vessels operating in closed bustie mode: the grey zone Abstract For many years the design of DP vessels operating in closed bustie mode has been evaluated

More information

POWER. Improving Engine Utilization in DP Vessels

POWER. Improving Engine Utilization in DP Vessels POWER Improving Engine Utilization in DP Vessels John J. May P.E., Transocean Offshore Deepwater Drilling, Inc. Session Chair Don Wilkes, GlobalSantaFe September 16-17, 2003 Houston, Texas Improving Engine

More information

Using cloud to develop and deploy advanced fault management strategies

Using cloud to develop and deploy advanced fault management strategies Using cloud to develop and deploy advanced fault management strategies next generation vehicle telemetry V 1.0 05/08/18 Abstract Vantage Power designs and manufactures technologies that can connect and

More information

Keynote Address. DPPS A Petrobras DP Safety Program

Keynote Address. DPPS A Petrobras DP Safety Program Keynote Address DPPS A Petrobras DP Safety Program Afonso André Pallaoro Petrobras/E&P Service 1 Return to Session Directory DPC DYNAMIC POSITIONING CONFERENCE DPPS A Petrobras Dynamic Positioning Safety

More information

Alf Kåre Ådnanes; ABB BU Marine & Cranes, 2010-November Energy efficiency and fuel consumption of marine and offshore vessels Technical possibilities

Alf Kåre Ådnanes; ABB BU Marine & Cranes, 2010-November Energy efficiency and fuel consumption of marine and offshore vessels Technical possibilities Alf Kåre Ådnanes; ABB BU Marine & Cranes, 2010-November Energy efficiency and fuel consumption of marine and offshore vessels Technical possibilities and a case study Outline Energy efficiency and fuel

More information

DP Conference, Houston October 17-18, Challenges related to propulsion equipment and their interface to the Dynamic Positioning System

DP Conference, Houston October 17-18, Challenges related to propulsion equipment and their interface to the Dynamic Positioning System DP Conference, Houston October 17-18, 2000 Challenges related to propulsion equipment and their interface to the Dynamic Positioning System By: Lars Kristian Moen, Kongsberg Simrad Inc. 1 The Challenge

More information

A Novel Solution to Common Mode Failures in DP Class 2 Power Plant

A Novel Solution to Common Mode Failures in DP Class 2 Power Plant Return to Session Directory DYNAMIC POSITIONING CONFERENCE October 9-10, 2007 DP Innovation A Novel Solution to Common Mode Failures in DP Class 2 Power Plant Dr. Steven Cargill Noble Denton Consultants,

More information

Optimization of Power and Station Keeping Installations by a Total System Design Approach

Optimization of Power and Station Keeping Installations by a Total System Design Approach Optimization of Power and Station Keeping Installations by a Total System Design Approach Dynamic Positioning Conference DPC October 1999, Houston Alf Kåre Ådnanes Introduction Integrated Systems Total

More information

Developments on Remote DP Control and Autopilot with Collision Avoidance System

Developments on Remote DP Control and Autopilot with Collision Avoidance System Developments on Remote DP Control and Autopilot with Collision Avoidance System and Possible Stepping Stones Towards Autonomous Ships? Exhibition 1 For more than seven years MT has worked steadfastily

More information

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance I Abdulhadi*, A Dyśko *Power Networks Demonstration Centre, UK, ibrahim.f.abdulhadi@strath.ac.uk University of Strathclyde,

More information

REDUNDANT PROPULSION SHIPS RULES FOR CLASSIFICATION OF NEWBUILDINGS DET NORSKE VERITAS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2

REDUNDANT PROPULSION SHIPS RULES FOR CLASSIFICATION OF NEWBUILDINGS DET NORSKE VERITAS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2 RULES FOR CLASSIFICATION OF SHIPS NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2 REDUNDANT PROPULSION JANUARY 2011 CONTENTS PAGE Sec. 1 General Requirements... 4 Sec. 2 System

More information

SA Power Networks Commissioning Witnessing Checklist

SA Power Networks Commissioning Witnessing Checklist SA Power Networks Commissioning Witnessing Checklist CUSTOMER NAME: SOLAR PV APPROVED CAPACITY: BATTERY APPROVED CAPACITY: kw (AC) kw (AC) OPERATING PHILOSOPHY: MAXIMUM EXPORT: Non-Export/Export kw (AC)

More information

Ekip Link logic- zone discrimination protection system

Ekip Link logic- zone discrimination protection system 54 ABB REVIEW Ekip Link logic- zone discrimination protection system A modern dynamically positioned () vessel will have a sophisticated electrical power system driving the propulsion that keeps it on

More information

Offshore Application of the Flywheel Energy Storage. Final report

Offshore Application of the Flywheel Energy Storage. Final report Page of Offshore Application of the Flywheel Energy Storage Page 2 of TABLE OF CONTENTS. Executive summary... 2 2. Objective... 3 3. Background... 3 4. Project overview:... 4 4. The challenge... 4 4.2

More information

Efficient and flexible solution

Efficient and flexible solution Efficient and flexible solution for the most demanding clients Bourbon PX 105 MACS Series of Large Platform Supply Vessels Bourbon Front - Bourbon Clear - Bourbon Calm - Bourbon Rainbow Bourbon PX 105

More information

From academia to industry Commercializing research on propulsion and hydrodynamics. Øyvind Smogeli Chief Operating Officer

From academia to industry Commercializing research on propulsion and hydrodynamics. Øyvind Smogeli Chief Operating Officer 1 From academia to industry Commercializing research on propulsion and hydrodynamics Øyvind Smogeli Chief Operating Officer 2 Motivation Demand for vessels to conduct allyear operation in harsh environment

More information

REDUNDANT PROPULSION SHIPS RULES FOR CLASSIFICATION OF NEWBUILDINGS DET NORSKE VERITAS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2

REDUNDANT PROPULSION SHIPS RULES FOR CLASSIFICATION OF NEWBUILDINGS DET NORSKE VERITAS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2 RULES FOR CLASSIFICATION OF SHIPS NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2 REDUNDANT PROPULSION JANUARY 2003 This booklet includes the relevant amendments and corrections

More information

The Benefits of Podded Propulsion in the Offshore Market

The Benefits of Podded Propulsion in the Offshore Market DYNAMIC POSITIONING CONFERENCE THRUSTERS AND DRIVE SYSTEMS The Benefits of Podded Propulsion in the Offshore Market S J Raynor Cegelec Projects Limited (United Kingdom) Synopsis Over the last few years,

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

FURTHER TECHNICAL AND OPERATIONAL MEASURES FOR ENHANCING THE ENERGY EFFICIENCY OF INTERNATIONAL SHIPPING

FURTHER TECHNICAL AND OPERATIONAL MEASURES FOR ENHANCING THE ENERGY EFFICIENCY OF INTERNATIONAL SHIPPING E MARINE ENVIRONMENT PROTECTION COMMITTEE 74th session Agenda item 6 8 March 2019 Original: ENGLISH FURTHER TECHNICAL AND OPERATIONAL MEASURES FOR ENHANCING THE ENERGY EFFICIENCY OF INTERNATIONAL SHIPPING

More information

Nobert Bulten Petra Stoltenkamp Wärtsilä Propulsion Technology

Nobert Bulten Petra Stoltenkamp Wärtsilä Propulsion Technology DYNAMIC POSITIONING CONFERENCE October 11-12, 2016 THRUSTERS Improved DP-Capability with Tilted Thrusters and Smart Controls Algorithims Nobert Bulten Petra Stoltenkamp Wärtsilä Propulsion Technology Improved

More information

Artesis MCM Case Studies. March 2011

Artesis MCM Case Studies. March 2011 Artesis MCM Case Studies March 2011 Case 1 Automotive Company: Automobile Manufacturer A Equipment: Pump Stator Isolation Breakdown Decreasing current unbalance level Case 1 Automotive Company: Automobile

More information

Dynamic Adjustment Procedure for 700-series Digital Controls. Application Note (Revision A,8/1998) Original Instructions

Dynamic Adjustment Procedure for 700-series Digital Controls. Application Note (Revision A,8/1998) Original Instructions Application Note 01304 (Revision A,8/1998) Original Instructions Dynamic Adjustment Procedure for 700-series Digital Controls (700, 701, 701A, 702, 705, 721, 723, 723PLUS, 828) General Precautions Read

More information

Response to Surabaya incident

Response to Surabaya incident Response to Surabaya incident 13 th April 2010 Flight CX 780 from Surabaya to Hong Kong with 320 crew and pax Experienced engine thrust control problems in flight Made a high speed landing in HKG, but

More information

MARINE. Decrease fuel consumption and emissions with shaft generators and drives

MARINE. Decrease fuel consumption and emissions with shaft generators and drives MARINE Decrease fuel consumption and emissions with shaft generators and drives 3 Table of contents 004 Your investment is safe with ABB 006 Helping to decrease fuel consumption and emissions 007 Improving

More information

A new era in asset protection

A new era in asset protection LinerSCAN A new era in asset protection The worlds first real time liner alarm Early warning system for main engine damage The world s first real-time alarm system for engine liner wear. LinerSCAN marks

More information

Marine Technology Society

Marine Technology Society Marine Technology Society Dynamic Positioning Conference 21-22 October, 1997 Session 7 Power Plant Electrical Power Plant and Thruster Systems Design Considerations for Dynamically Positioned Vessels By:

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

Onboard DC Grid. Jan Fredrik DP Conference 2011; Houston. for enhanced DP operation in ships

Onboard DC Grid. Jan Fredrik DP Conference 2011; Houston. for enhanced DP operation in ships Onboard Grid Jan Fredrik Hansen @ DP Conference 2011; Houston for enhanced DP operation in ships Traditional System Onboard Grid Up to 20% fuel saving potential Quicker and more dynamic system performance

More information

CMAL Hybrid Ferries. Hybrid Ferries. Conference on electric mobility. Andrew Flockhart Caledonian Maritime Assets Ltd

CMAL Hybrid Ferries. Hybrid Ferries. Conference on electric mobility. Andrew Flockhart Caledonian Maritime Assets Ltd CMAL Hybrid Ferries Hybrid Ferries Conference on electric mobility Andrew Flockhart Caledonian Maritime Assets Ltd HISTORY Routes and Ports The Fleet Finlaggan May 2011 The Fleet Loch Shira 36 Cars 250

More information

Power Quality. Power Factor Wiring and Service. Background. Introduction. bchydro.com

Power Quality. Power Factor Wiring and Service. Background. Introduction. bchydro.com Power Quality Power Factor Wiring and Service Scope Power factor is a major consideration in efficient building or system operation. It is the measure of how effectively your equipment is converting electric

More information

Grid Impacts of Variable Generation at High Penetration Levels

Grid Impacts of Variable Generation at High Penetration Levels Grid Impacts of Variable Generation at High Penetration Levels Dr. Lawrence Jones Vice President Regulatory Affairs, Policy & Industry Relations Alstom Grid, North America ESMAP Training Program The World

More information

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 NERC Load Modeling Activities Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 Introduction Kickoff January 2016 LMTF webpage Chair: Dmitry Kosterev,

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

MARINE VESSEL REPOWER APPLICATION

MARINE VESSEL REPOWER APPLICATION CARL MOYER MEMORIAL AIR QUALITY STANDARDS ATTAINMENT PROGRAM MARINE VESSEL REPOWER APPLICATION Revised 08/2016 1 of 10 CARL MOYER RURAL ASSISTANCE PROGRAM Instruction Sheet The California Air Pollution

More information

LOW VOLTAGE WIND CONVERTERS. ABB wind turbine converters ACS880, 800 kw to 8 MW

LOW VOLTAGE WIND CONVERTERS. ABB wind turbine converters ACS880, 800 kw to 8 MW LOW VOLTAGE WIND CONVERTERS ABB wind turbine converters ACS880, 800 kw to 8 MW 2 ABB WIND CONVERTERS, ACS880 WIND TURBINE CONVERTERS ACS880 wind turbine converter Flexible solution The ACS880 converter

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

Navis NavDP 4000 Series

Navis NavDP 4000 Series Navis NavDP 4000 Series DYNAMIC POSITIONING SYSTEM Navis NavDP 4000 Series THE PROFESSIONAL S CHOICE Navis Engineering OY is one of the few world experts in dynamic positioning. Having supplied DP systems

More information

Experiences in a Motor Protection Retrofit

Experiences in a Motor Protection Retrofit Special Feature by Kyle Craig, Ontario Power Generation Amy Sinclair, Schweitzer Engineering Laboratories, Inc. Experiences in a Motor Protection Retrofit Introduction The initial stage of any project

More information

Certain Model Year Tacoma 2TR-FE Vehicles Exhaust Pipe Replacement for Catalytic Converter

Certain Model Year Tacoma 2TR-FE Vehicles Exhaust Pipe Replacement for Catalytic Converter To: Subject: All Toyota Dealer Principals, Service Managers, and Parts Managers Special Service Campaign (SSC) F0U Certain 2010-2014 Model Year Tacoma 2TR-FE Vehicles Exhaust Pipe Replacement for Catalytic

More information

E-15 Uninterruptible Power Systems (UPS)

E-15 Uninterruptible Power Systems (UPS) Guideline No.E-15 (201510) E-15 Uninterruptible Power Systems (UPS) Issued date:20 October, 2015 China Classification Society Foreword This Guide is a part of CCS Rules, which contains technical requirements,

More information

Risk. Analyzing Petrobras DP Incidents

Risk. Analyzing Petrobras DP Incidents Risk Analyzing Petrobras DP Incidents Marcelo Santa Rosa Costa and Gilberto Behuhn Machado Petrobras October 17-18, 6 Return to Session Directory Analyzing Petrobras DP Incidents Marcelo Santa Rosa Costa

More information

Model Tests for the DP System of a Drilling Semi-Submersible

Model Tests for the DP System of a Drilling Semi-Submersible Author s Name, Company Title of the Paper DYNAMIC POSITIONING CONFERENCE October 17-18, 26 Design Model Tests for the DP System of a Drilling Semi-Submersible Jitendra Prasad and Hatem Elgamiel Noble Drilling

More information

Power Solutions Manager Generac Power Systems, Inc.

Power Solutions Manager Generac Power Systems, Inc. Engine Generator Paralleling Concepts Gen. #1 Gen. #2 Gen. #3 Gen. #4 Gen. #5 Presenter: Daniel Barbersek Power Solutions Manager Generac Power Systems, Inc. RUNNING HEADLINE What Topics Will Be Covered

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 PREPARED BY: System Performance and Commercial DATE: 7 March 2013 FINAL Disclaimer Purpose This

More information

Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience

Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience Y. Sun 1, 2,*, W. G. Kuijpers 3, E. C. W. de Jong 1,2, and H. Pustjens 3 1 Electrical Energy System, Eindhoven University

More information

Low Loss Concept Comparison Study

Low Loss Concept Comparison Study Author s Name Name of the Paper Session DYNAMIC POSITIONING CONFERENCE October 12-13, 2010 NEW APPLICATIONS SESSION Low Loss Concept Comparison Study By Brian Cheater, Peter Lammers Friede & Goldman, Houston,

More information

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience SPIDER Modeling Sub-Group DER Modeling, CAISO Experience Irina Green, Modeling Sub-Group Chair Regional Transmission Senior Advisor, California ISO NERC SPIDER Work Group Meeting, January 2019 Presentation

More information

Philip Padfield, CEO. Sustainable shipping. 22nd October

Philip Padfield, CEO. Sustainable shipping. 22nd October Philip Padfield, CEO Sustainable shipping 22nd October 2010 1 Agenda 1. Who we are 2. Industry in change 3. Enabling sustainability: From data to intelligence 4. Key points Eniram The Company in brief

More information

ABB Power Cables Service Turnkey Cable Repairs Three Reference Cases

ABB Power Cables Service Turnkey Cable Repairs Three Reference Cases ABB Power Cables Service, ABB Power Cables Service Turnkey Cable Repairs Three Reference Cases July 16, 2013 Slide 1 ABB Power Cables Service Success Repair Story Wind Farm, United Kingdom, March 2012

More information

SHIP ENERGY EFFICIENCY MANAGEMENT PLAN SEEMP. Edilberto Peralta Operations Manager Central and South America

SHIP ENERGY EFFICIENCY MANAGEMENT PLAN SEEMP. Edilberto Peralta Operations Manager Central and South America SHIP ENERGY EFFICIENCY MANAGEMENT PLAN SEEMP Edilberto Peralta Operations Manager Central and South America SEEMP An energy management plan that aims: - To optimise the ship operational and technical management

More information

All Dealer Principals, General Managers, Service Managers, and Parts Managers

All Dealer Principals, General Managers, Service Managers, and Parts Managers April 19, 2016 To: Subject: All Dealer Principals, General Managers, Service Managers, and Parts Managers Warranty Enhancement Program - ZLG Certain 2006 2007 GS 430, 2007 2011 GS 450h, 2008 2011 GS 460,

More information

NATIONAL TRANSPORTATION SAFETY BOARD Public Meeting of February 9, 2016 (Information subject to editing)

NATIONAL TRANSPORTATION SAFETY BOARD Public Meeting of February 9, 2016 (Information subject to editing) NATIONAL TRANSPORTATION SAFETY BOARD Public Meeting of February 9, 2016 (Information subject to editing) Commercial Truck Collision with Stopped Vehicle on Interstate 88, Naperville, Illinois January 27,

More information

NC PV DG Program SEPA Presentation. December 15, 2011

NC PV DG Program SEPA Presentation. December 15, 2011 NC PV DG Program SEPA Presentation December 15, 2011 Agenda PV Industry Background PV Solar Rooftop Incident Root Cause(s) Wiring Diagrams Remedy Fire Safety Brochure Findings/Observations Recommendations

More information

Power Quality and Energy Management

Power Quality and Energy Management Power Quality and Energy Management 1 2 Contents Power Quality...2 Power Factor Correction...4 Voltage Optimisation...8 Harmonic Filters and Reactors...12 1 Captech is Power Investigation and identification

More information

Understanding the benefits of using a digital valve controller. Mark Buzzell Business Manager, Metso Flow Control

Understanding the benefits of using a digital valve controller. Mark Buzzell Business Manager, Metso Flow Control Understanding the benefits of using a digital valve controller Mark Buzzell Business Manager, Metso Flow Control Evolution of Valve Positioners Digital (Next Generation) Digital (First Generation) Analog

More information

Potential of operational saving measures Orka 2015 Summit Jacob W. Clausen, Head of Advisory

Potential of operational saving measures Orka 2015 Summit Jacob W. Clausen, Head of Advisory LEADERS IN MARITIME ENERGY EFFICIENCY Potential of operational saving measures Orka 2015 Summit Jacob W. Clausen, Head of Advisory SUPERIOR DATA. ULTIMATE SAVINGS. MAXIMUM RETURNS. AGENDA 1 2 3 4 Introduction

More information

ELECTROMECHANICAL OPTIMIZATION AGAINST TORSIONAL VIBRATIONS IN O&G ELECTRIFIED TRAINS MICHELE GUIDI [GE O&G] ALESSANDRO PESCIONI [GE O&G]

ELECTROMECHANICAL OPTIMIZATION AGAINST TORSIONAL VIBRATIONS IN O&G ELECTRIFIED TRAINS MICHELE GUIDI [GE O&G] ALESSANDRO PESCIONI [GE O&G] ELECTROMECHANICAL OPTIMIZATION AGAINST TORSIONAL VIBRATIONS IN O&G ELECTRIFIED TRAINS MICHELE GUIDI [GE O&G] ALESSANDRO PESCIONI [GE O&G] Topics INTRODUCTION - Mechanical vibrations in electrified trains

More information

Fire pumper brake work was put off

Fire pumper brake work was put off Posted on Sun, Jan. 23, 2005 Fire pumper brake work was put off Chief cites lack of backup vehicles By MATT CAMPBELL and MARK MORRIS The Kansas City Star A Kansas City fire pumper involved in a fatal accident

More information

Feasibility of Electric Propulsion for Semi-submersible Heavy Lift Vessels

Feasibility of Electric Propulsion for Semi-submersible Heavy Lift Vessels Feasibility of Electric Propulsion for Semi-submersible Heavy Lift Vessels K Kokkila, ABB Marine & Cranes, Finland SUMMARY Some of the semi-submersible heavy lift vessels have special requirements that

More information

MAN Diesel's First VTA Application Achieves 10,000 Operating Hours

MAN Diesel's First VTA Application Achieves 10,000 Operating Hours MAN Diesel's First VTA Application Achieves 10,000 Operating Hours 05/ In 2007, MAN Diesel s Business Unit Turbocharger, based in Augsburg, Germany, equipped the first engine in a commercial application

More information

Large Air Cooled Generator Failure

Large Air Cooled Generator Failure Large Air Cooled Generator Failure Henry Tarnecky AVP - Sr. Engineering Specialist, FM Global 2017 IRIS Rotating Machinery Conference FM Global Basics Commercial/Industrial Property Insurer Mutual Co.,

More information

Ballast Water Management Surveyor checklist

Ballast Water Management Surveyor checklist Ballast Water Management Surveyor checklist Last updated: July 2017 This document is uncontrolled if printed, please refer to the Maritime New Zealand website for the latest version. Use this checklist

More information

BOURBON LIBERTY 150 SERIES. Platform Supply vessels. DP2-1,701 t DWT

BOURBON LIBERTY 150 SERIES. Platform Supply vessels. DP2-1,701 t DWT BOURBON LIBERTY SERIES Platform Supply vessels DP -,7 t DWT BOURBON LIBERTY SERIES Class ABSXA, Offshore Support Vessel, Oil Recovery, Vessel Class (OSR- S), E, XAMS, XACCU, XDPS-, Fire-Fighting Vessel

More information

ST315B. User Handbook STAFFOR. ST315B Temperature Programmer. See separate handbook for Installation Instructions Issue: 2.00

ST315B. User Handbook STAFFOR. ST315B Temperature Programmer. See separate handbook for Installation Instructions Issue: 2.00 STAFFOR D ST315B User Handbook ST315B Temperature Programmer See separate handbook for Installation Instructions Issue: 2.00 ST315B Copyright User Handbook 2009-2016 Stafford Instruments Ltd. Date: 08

More information

ABB's Energy Efficiency and Advisory Systems

ABB's Energy Efficiency and Advisory Systems ABB's Energy Efficiency and Advisory Systems The common nominator for all the Advisory Systems products is the significance of full scale measurements. ABB has developed algorithms using multidimensional

More information

Fuel Efficient Power Plant Featuring Variable Speed Generation Systems for DP Drilling Units

Fuel Efficient Power Plant Featuring Variable Speed Generation Systems for DP Drilling Units DYNAMIC POSITIONIN CONFERENCE October 11-12, 2016 OPERATIONS Fuel Efficient Power Plant Featuring Variable Speed eneration Systems for DP Drilling Units Jan Fredrik Hansen Frank Wendt John Olav Lindtjørn

More information

Towards Safer, Smarter and Greener Ships Using Hybrid Marine Power Plants. Introduction. Authors:

Towards Safer, Smarter and Greener Ships Using Hybrid Marine Power Plants. Introduction. Authors: Towards Safer, Smarter and Greener Ships Using Hybrid Marine Power Plants Authors: By Asgeir J. Sørensen 1, Roger Skjetne 1, Torstein Bø 1, Michel R. Miyazaki 1, Tor Arne Johansen 2, Ingrid B. Utne 1,

More information

WIND ENERGY DENMARK

WIND ENERGY DENMARK WIND ENERGY DENMARK - 2017 GRID CONNECTION REQUIREMENTS October 2 nd 2017 Flemming Brinch Nielsen Fbn@energient.dk 1 Flemming Brinch Nielsen: Senior Engineer System Operation Development Mobil: +45 61

More information

A numerical DP module For design and operations

A numerical DP module For design and operations A numerical DP module For design and operations A. Ledoux, B Lecuyer, C. Le Cunff Principia R.D. PRINCIPIA 1 2005 1 Summary Numerical Tool: Diodore Modeling of floating structure Modeling of environment

More information

Vehicle Management: Asset Information Basics

Vehicle Management: Asset Information Basics Vehicle Management: Asset Information Basics Host Today s Webcast Vehicle Management: Asset Information Basics Miranda Voelz Client Services Manager J. J. Keller & Associates, Inc. Support (800)327-1342

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Technology Update May Mark Hamilton - CTO

Technology Update May Mark Hamilton - CTO Technology Update May 2012 Mark Hamilton - CTO Scotrenewables 2008 Company Founded 2002 Based in Orkney 14 Staff Supported by : Scotrenewables 2008 Introduction to the Scotrenewables Tidal Turbine Design

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Kongsberg Maritime Simulation and Training. The power to excel in Dynamic Positioning training

Kongsberg Maritime Simulation and Training. The power to excel in Dynamic Positioning training Kongsberg Maritime Simulation and Training The power to excel in Dynamic Positioning training The rapidly expanding offshore fleet and move into deeper waters has created strong demand for Dynamic Positioning

More information

MEPC 71. The Impact on Ballast Water Management Compliance Plans

MEPC 71. The Impact on Ballast Water Management Compliance Plans MEPC 71 The Impact on Ballast Water Management Compliance Plans Meet Your Presenters Chris McMenemy Managing Director Naval Architect & Marine Engineer Involved in Ballast Water Management for nearly 10

More information

Power Generation Stability and Response in DP Applications An Overview of Modern Diesel Engine Performance

Power Generation Stability and Response in DP Applications An Overview of Modern Diesel Engine Performance DYNAMIC POSITIONING CONFERENCE September 16-17, 2003 Power Session Power Generation Stability and Response in DP Applications An Overview of Modern Diesel Engine Performance Magnus Miemois Wärtsilä Finland

More information

Variable frequency transformer for asynchronous power transfer

Variable frequency transformer for asynchronous power transfer Variable frequency transformer for asynchronous power transfer by Einar Larsen, Richard Piwko and Donald McLaren, GE Energy A new power transmission technology has been developed. The variable frequency

More information

Maersk Venturer. Ultra deepwater drilling and development. Deepwater Advanced

Maersk Venturer. Ultra deepwater drilling and development. Deepwater Advanced Maersk Venturer Ultra deepwater drilling and development Deepwater Advanced Maersk Venturer TYPE Samsung 96K drillship BUILT Samsung Heavy Industries, 2014 CLASS American Bureau of Shipping FLAG Singapore

More information

MORE EFFICIENT DIESEL ELECTRIC POWER PLANT FOR DREDGES

MORE EFFICIENT DIESEL ELECTRIC POWER PLANT FOR DREDGES MORE EFFICIENT DIESEL ELECTRIC POWER PLANT FOR DREDGES Authors: Vinton Bossert, P.E. President, Bossert Dredge Consulting, LLC, vintonbossert@comcast.net John Ockerman President, Ockerman Automation Consultants,

More information

YOUR PROPULSION EXPERTS

YOUR PROPULSION EXPERTS YOUR PROPULSION EXPERTS SCHOTTEL AZIMUTH THRUSTERS THE NEW GENERATION OF LARGE SRPs/STPs 2 3 NEW THRUSTER GENERATION The SCHOTTEL Rudderpropeller is the classic product from the SCHOTTEL range. Since its

More information

Specification for 1500V DC Traction Supply WOS 01.E

Specification for 1500V DC Traction Supply WOS 01.E Discipline Engineering Standard Category Rolling Stock Specification for 1500V DC Traction Supply WOS 01.E Applicability ARTC Network wide New South Wales Western Jurisdiction Victoria Primary Source (RIC

More information

Coriolis Density Error Compensating for Ambient Temperature Effects

Coriolis Density Error Compensating for Ambient Temperature Effects Coriolis Density Error Compensating for Ambient Temperature Effects Presented by Gordon Lindsay Oil & Gas Focus Group December 2018 Contents Project aims and objectives Experiment Setup Phase 1 Exploratory

More information

IHC Holland BV IHC WFSV Brief Specifications

IHC Holland BV IHC WFSV Brief Specifications IHC WFSV 18-80 Brief Specifications Contents 1 Vessel Particulars... 4 2 Rules & Regulations... 5 3 Power and propulsion... 6 4 Cranes... 7 5 Life on board... 8 6 Internal workflow... 9 7 Motion Compensated

More information

MARINE PROPULSION CONTROL

MARINE PROPULSION CONTROL PRODUCT BULLETIN SB-8504B MARINE PROPULSION CONTROL ELECTRONIC LOGIC AND CONTROL PANEL Type MPC-E9 Control Panel APPLICATION Propulsion controls for small and large vessels with fixed pitch propellers,

More information

Transmitted by the expert from Germany

Transmitted by the expert from Germany Overview Transmitted by the expert from Germany Informal document No. GRRF-62-17 (62nd GRRF, 25-28 September 2007, agenda item 9(f)) TPMS Motivations Principles of tire pressure monitoring systems (TPMS)

More information

SeaGen-S 2MW. Proven and commercially viable tidal energy generation

SeaGen-S 2MW. Proven and commercially viable tidal energy generation SeaGen-S 2MW Proven and commercially viable tidal energy generation The SeaGen Advantage The generation of electricity from tidal flows requires robust, proven, available, and cost effective technology.

More information

EI HMC Report Spring API Committee on Petroleum Measurement Standards Meeting

EI HMC Report Spring API Committee on Petroleum Measurement Standards Meeting EI HMC Report 2017 Spring API Committee on Petroleum Measurement Standards Meeting STAC EI Technical Committee Structure STAC Health Technical Committee Environmental Management Group Safety Management

More information

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014 Solar and Smart Meter Update 1 April 2014 to 30 June 2014 Released July 2014 2 CONTENTS 1. Solar and Smart Meter Cases... 3 2. SMART METER UPDATE... 4 2.1. EWOV Smart Meter Cases Increase by 36%... 4 2.2.

More information

Gear Failures: Lessons Learned

Gear Failures: Lessons Learned Return to Session Menu DYNAMIC POSITIONING CONFERENCE October 15-16, 2013 THRUSTERS SESSION Gear Failures: Lessons Learned Timo Rauti Rolls-Royce Gear Failures: Lessons learned Dynamic Positioning Conference

More information

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society Guideline No.: E-07(201610) E-07 TRANSFORMERS Issued date: October 28,2016 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection and

More information

This qualification has been reviewed. The last date to meet the requirements is 31 December 2020.

This qualification has been reviewed. The last date to meet the requirements is 31 December 2020. NZQF NQ Ref 1117 Version 5 Page 1 of 7 National Certificate in Electricity Supply (Field Switcher) (Level 4) with optional strands in Distribution Networks, Transmission Networks, and Operational and Co-ordination

More information

Guideline No.: E-07(201712) E-07 TRANSFORMERS. Issued date: December 26, China Classification Society

Guideline No.: E-07(201712) E-07 TRANSFORMERS. Issued date: December 26, China Classification Society Guideline No.: E-07(201712) E-07 TRANSFORMERS Issued date: December 26, 2017 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection

More information

A Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk

A Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk A Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk by: Kelly Eberle, P.Eng. Beta Machinery Analysis Calgary, AB Canada keberle@betamachinery.com keywords: reciprocating

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information