1 PRESERVATION IN THE NATIONAL PARK SERVICE Northeast Pavement Preservation Partnership Meeting Portsmouth, NH November 8-10,

2 Pavement Management Implementation FY

3 1. Northeast Region (NER) 2. Road System 3. Pavement Condition 4. Comparisons 5. Preservation Approach 6. Projections 7. Conclusions 3

4 1. Northeast Region 4

5 NPS NER Park Units or 20% States/Territories or 26% Population 311 M 73 M or 24% Annual Visitation 285 M 54 M or 19% Economic Impact $ 11.6 B $ 1.5 B or 13% Alternate Transportation Systems or 22% Major Metropolitan areas in the Northeast Corridor 5

6 NER Transportation Assets 6

7 Road Network: Scenic, Historic and Unchanged

8 Transportation Assets 8

9 API API /FCI Transportation Assets NER Transportation Assets by Asset Category Good Fair Poor Serios Restore/Replace Roads Parking Road Bridge Road Tunnel Trails 60 Trail Bridge Trail Tunnel Transp Bldg Fuel 30 Marina Consider Removal Aviation Railroad 0 Excess FCI Source: FMSS 2/10 9

10 Total Deferred Maintenance Needs including Roads, Bridges and Multi-Modal Transportation NER $2.9 B = 18% of NPS PWR $ 3,416M IMR MWR $ 826M NER $ 2,879M $ 3,267M $ 3,220M SER NCR $ 1,654M AKR $ 357M Total Need: $15.6B 10

11 2. Road System 11

12 Paved Road and Equivalent Miles of Parking NER vs. NPS 12

13 NER Road Facts 1,204 Total Miles: 478 Paved Road Miles 397 Paved Parking Miles 329 Gravel Road Miles 88% Asphalt, 12% PCC Parking is 45% of Pavement 186 Bridges & Tunnels Longest Road is 105 Miles Historic and Non-historic Urban and Rural High, Low and Seasonal Use Increased Commuter Traffic Minimal Heavy Truck Traffic

14 NER Paved Miles by Functional Class 478 Road Miles and 379 Parking Miles Equivalent Principal miles 2 Connector - 77 miles 3 Special Purpose - 81 miles 4 Primitive - 0 miles 5 Admin 6 Restricted Access miles miles 7 Urban Parkway - 0 miles 8 City Street - 2 miles 9 Parking miles 14

15 NER Funding $15M FY10 Program Budget $12M Construction Awards Surface & Light 3R Treatments $3M or 20% Planning, Design, Contracting and Supervision 15

16 3. Pavement Condition 16

17 FHWA Collects Standard Condition Data for all NPS Parks 17

18 Collected on Cycles Parking Manually Rated Four Condition Categories 18

19 The Surface Condition Rating (SCR) and Roughness Condition Index (RCI) are combined to define the Pavement Condition Rating (PCR): 60% SCR + 40% RCI = PCR

20 NER 2009 Network Condition Excellent Condition = 95 to 100 PCR Good Condition = 85 to 94 PCR - Roads 8% or 36 Miles - Roads 42% or 193 Miles - Parking 7% - Parking 23% (NER Goal is 85 PCR or Better) Fair Condition = 61 to 84 PCR Poor Condition = 0 to 60 PCR - Roads 29% or 135 Miles - Roads 21% or 97 Miles - Parking 35% - Parking 35% 20

21 Figure 10 NER Pavement Condition Rating Breakdown Base Year 2009 NER Pavement Condition Rating

22 4. Comparisons 22

23 Servicewide Breakdown by Condition Category

24 National-NER Comparison 100% 90% % % % 50% Excellent Good Fair 40% Poor 30% 20% % 0% 2007 National 2007 NER 2009 National 2009 NER 24

25 40% Construction Design (PE) to Construction (CN) Costs 35% 30% 25% 20% 15% Northeast 11.40% 10% 6 Regions % 0%

26 Construction Supervision (CE) to Net Construction (CN) Costs 16% 14% 12% 10% 8% 6% Northeast 6.94% 4% 2% 6 Regions 12.90% 0%

27 Project Miles as Pct. of Route Miles 10.0% 9.0% 8.0% 7.0% 6.0% 5.0% 4.0% 3.0% 2.0% NCRO NERO SERO MWRO IMRO PWRO AKRO 1.0% 0.0%

28 Difference in Pavement Condition Ratings (Northeast - National) Excellent +2% +1% Good +4% +26% Fair +3% -16% Poor -9% -11% 28

29 5. Preservation Approach 29

30 Approach: RIP Data Collection HPMA Modeling 100% Field Validation ROS Prioritization (Roadway Objective Score) Program Formulation Key Assumptions: Focus on Primary Roads Stay Between the White Lines Minimize Investment in Parking Lots Demolish Non Performing Assets Minimize Design and Supervision Costs Follow Established Priorities 30

31 6. Projections 31

32 Route Miles Pre and Post Pavement Management Prior to Miles Per Year - 65 PCR in thru Miles Per Year - 76 PCR in 2010 Continue Approach Through 2017 with Increase in Surface Treatments to achieve minimum 85 PCR to optimum 94 PCR 32

33 $50 Funding and Reauthorization Scenarios $45 $40 $35 $30 $25 $20 $15 Level PCR $10 Low PCR $5 $ ARRA + L/B 10 + ARRA + L/B Medium PCR High PCR

34 A Comparison of 4 funding levels over a 9-year analysis period PCR, Avg, NER10 01, NE PCR, Avg, NER10 01, NE11 PERFORMANCE SUMMARY PLOT PCR, Avg, NER10 01, NE12 PCR, Avg, NER10 01, NE13 PCR Avg Do Nothing Index Year Subset: NER_FC_

35 By 2013 Excellent and Good Categories will exceed 55% of the NER network (FC 12378) 100% 90% 80% 70% Low Funding + 4% Inflation FC % 90% 80% 70% Low Funding + 4% Inflation All Function Classes % Excellent 60% Excellent 50% 40% 30% 20% Good Fair Poor 50% 40% 30% 20% Good Fair Poor 10% 0% % 0%

36 Miles of Treatment Northeast Region -- Low Funding Scenario Treatment Breakdown by Rte-Miles Treatment Breakdown By Route Miles Preservation Light 3R Heavy 3R R Reconstruct

37 7. Conclusions 37

38 Summary Continue Pavement Management & Preservation Program Increase Condition Data Collection Cycle Preserve Investment Thru Increased Preservation Focus - High Priority Roads - Where 80% of Visitors Travel Outside the White Lines - Only as Necessary Improve Highest Priority Visitor Parking Limited Heavy 4R Construction if Funding Allows Integrate Safety Countermeasure Priorities, Congestion Mitigation Priorities and Multi Modal Priorities 38

39 Questions? 39

The State of SCDOT. Presented: February 1, 2017 Secretary Christy A. Hall, P.E.

The State of SCDOT. Presented: February 1, 2017 Secretary Christy A. Hall, P.E. The State of SCDOT Presented: February 1, 2017 Secretary Christy A. Hall, P.E. As we enter our Centennial Year, we have much to do together. 2 Looking # Back # over # the # past # 12 # months Y Y Y Y Y

More information

Northeast Pavement Preservation Partnership Burlington, Vermont. Rhode Island DOT

Northeast Pavement Preservation Partnership Burlington, Vermont. Rhode Island DOT Northeast Pavement Preservation Partnership Burlington, Vermont Rhode Island DOT April 8, 2014 SHRP2 R26 (Preservation of High-Traffic Volume Roadways) and MAP-21 Impacts to RIDOT Pavement Management David

More information

Arkansas State Highway and Transportation Department. ASCE Conference Wyndham Hotel North Little Rock Thursday, October 16, 2014

Arkansas State Highway and Transportation Department. ASCE Conference Wyndham Hotel North Little Rock Thursday, October 16, 2014 Arkansas State Highway and Transportation Department ASCE Conference Wyndham Hotel North Little Rock Thursday, October 16, 2014 Recent Voter Approved Programs November 2011 November 2012 Complete: 11 Miles:

More information

INFRASTRUCTURE REPORT CARD FOR NEVADA -2018

INFRASTRUCTURE REPORT CARD FOR NEVADA -2018 INFRASTRUCTURE REPORT CARD FOR NEVADA -2018 August 2018 The National Report Card Infratructure Report Card for - 2018 2014 Infrastructure RC Infratructure Report Card for - 2018 Coming Soon -Fall 2018

More information

March 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming

March 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming COORDINATION WITH VDOT DISTRICTS TO DELIVER IMPLEMENTABLE IMPROVEMENT PROJECTS March 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming PRESENTATION OUTLINE What

More information

Green Line Long-Term Investments

Green Line Long-Term Investments Enhancements Short-term improvements to keep Austin moving. Investments Long-term projects to support our future. Mobility Hubs MetroRapid MetroRail MetroExpress Connectors Circulators Project Connect

More information

Click to edit Master title style

Click to edit Master title style P3s Come In All Shapes And Sizes Mr. Greg Slater, Administrator 7/26/2018 1 1 Customer-Driven Customer First TODAY S DISCUSSION Introduction to MDOT MDOT P3 Experience Full Delivery Stream Restoration

More information

MPO Staff Report Technical Advisory Committee: July 12, 2017

MPO Staff Report Technical Advisory Committee: July 12, 2017 MPO Staff Report Technical Advisory Committee: July 12, 2017 RECOMMENDED ACTION: 2 nd TAC Meeting with Kimley-Horn/WSB in Updating the Street/Highway Element of 2045 Metropolitan Transportation Plan. Matter

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

ECONOMIC AND FINANCIAL ANALYSIS: PROJECT 1

ECONOMIC AND FINANCIAL ANALYSIS: PROJECT 1 Integrated Road Investment Program (RRP SRI 47273) A. Introduction ECONOMIC AND FINANCIAL ANALYSIS: PROJECT 1 1. Sri Lanka s road network is dense and well laid out, providing basic access to the country

More information

EXCEPTION TO STANDARDS REPORT

EXCEPTION TO STANDARDS REPORT EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,

More information

Recommended Transportation. Capital Improvement Program

Recommended Transportation. Capital Improvement Program Recommended 2018-2022 Transportation Capital Improvement Program 1 Overview 2017 Review 2018-2022 Considerations 2018-2022 Recommended CIP 2 Limited Resources are Directed to the Highest Priority Number

More information

Dixie Transportation Planning Office

Dixie Transportation Planning Office A project must be given a yes rating on items 1 & 2 in order to be prioritized. Sponsor: St. George City Project: Pioneer Parkway Type: Road Widening and Reconstruction Rev. 9/17/2010 Dixie Transportation

More information

Bow-Concord Interstate 93 Transportation Planning Study

Bow-Concord Interstate 93 Transportation Planning Study Bow-Concord Interstate 93 Transportation Planning Study Presentation to: Greater Concord Chamber of Commerce and Concord 2020 June 21, 2006 Transportation in New Hampshire NH Transportation Business Plan

More information

City of Freeport Water & Sewer Capital Improvement Program FY2019-FY2024

City of Freeport Water & Sewer Capital Improvement Program FY2019-FY2024 City of Freeport Water & Sewer Capital Improvement Program FY2019-FY2024 Current Issues $210 million in depreciated water & sewer assets are in need of replacement Many items: Production Wells, Treatment

More information

Call for Projects Congestion Mitigation and Air Quality (CMAQ) Emissions Formulas Technical Advisory Committee

Call for Projects Congestion Mitigation and Air Quality (CMAQ) Emissions Formulas Technical Advisory Committee Call for Projects Congestion Mitigation and Air Quality (CMAQ) Emissions Formulas Technical Advisory Committee July 18, 2018 Formula Coordination DRCOG under review, considering FHWA toolkit RAQC Argonne

More information

Funding Scenario Descriptions & Performance

Funding Scenario Descriptions & Performance Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion

More information

Transportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1

Transportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1 Transportation portion of the city s stormwater utility, and state road and fuel taxes. Background The transportation needs of the City of Lacey and its planning areas are met by a growing multimodal network

More information

Richmond Area MPO Regional Priority Transportation Projects

Richmond Area MPO Regional Priority Transportation Projects Regional Priority Transportation Projects September 27, 2007 HANOVER GOOCHLAND ASHLAND POWHATAN RICHMOND HENRICO NEW KENT CHESTERFIELD CHARLES CITY 9211 Forest Hill Avenue, Suite 200 Richmond, Virginia

More information

CATEGORY 500 PAVING SECTION 535 PAVEMENT SURFACE PROFILE

CATEGORY 500 PAVING SECTION 535 PAVEMENT SURFACE PROFILE CATEGORY 500 PAVING 1 of 9 SECTION 535.01 DESCRIPTION. This work shall consist of measuring the roughness of the final surface of hot mix asphalt (HMA) or portland cement concrete (PCC) pavements. The

More information

Performance-Based Communication Tools for Maintenance Budgets. 11th National Conference on Transportation Asset Management July 12th, 2016.

Performance-Based Communication Tools for Maintenance Budgets. 11th National Conference on Transportation Asset Management July 12th, 2016. Performance-Based Communication Tools for Maintenance Budgets 11th National Conference on Transportation Asset Management July 12th, 2016 Rob Zilay Presentation Outline Performance-based maintenance tools

More information

2030 Multimodal Transportation Study

2030 Multimodal Transportation Study 2030 Multimodal Transportation Study City of Jacksonville Planning and Development Department Prepared by Ghyabi & Associates April 29,2010 Introduction Presentation Components 1. Study Basis 2. Study

More information

An Overview of High Speed Rail. David Randall Peterman Congressional Research Service

An Overview of High Speed Rail. David Randall Peterman Congressional Research Service An Overview of High Speed Rail David Randall Peterman Congressional Research Service 1 Defining High Speed Rail in the U.S. What is High Speed Rail? Allusions to world-class European and Asian systems

More information

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master

More information

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future January 13, 2012 AACE Annual Meeting, Wickenburg, AZ I-15 in Arizona. Its Past, Present, and Future Jean A. Nehme, Ph.D., P.E. State Bridge Engineer, ADOT Presentation Overview Location, History, and Photographs

More information

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Second Jharkhand State Road Project (RRP IND 49125) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The project involves capacity augmentation and rehabilitation of four state highway sections in the

More information

RTID Travel Demand Modeling: Assumptions and Method of Analysis

RTID Travel Demand Modeling: Assumptions and Method of Analysis RTID Travel Demand Modeling: Assumptions and Method of Analysis Overall Model and Scenario Assumptions The Puget Sound Regional Council s (PSRC) regional travel demand model was used to forecast travel

More information

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital Needs Assessment Riders Advisory Council July2, 2008 Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair

More information

JTA S MOBILITY CORRIDORS. Improving System Performance Through Urban Design

JTA S MOBILITY CORRIDORS. Improving System Performance Through Urban Design JTA S MOBILITY CORRIDORS Improving System Performance Through Urban Design Overview Agenda Overview of Jacksonville & JTA Catalysts for a Transit Driven Complete Streets Program Process Countermeasures

More information

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis High Speed Intercity Passenger Rail Technical Appendix Prepared by HDR August 5, 2010 The Boston South Station HSIPR Expansion Project

More information

MARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018

MARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline

More information

Greater Cleveland Regional Transit Authority. Joe Calabrese CEO/General Manager

Greater Cleveland Regional Transit Authority. Joe Calabrese CEO/General Manager Greater Cleveland Regional Transit Authority Joe Calabrese CEO/General Manager Greater Cleveland RTA Overview Service Area Population of 1.5 million Customers Served 200,000 on a typical weekday 1.6 million

More information

AMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph)

AMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph) FOR IMMEDIATE RELEASE September 28, 2010 ATK-10-130a Contact: Media Relations 202 906.3860 AMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph)

More information

Metropolitan Council Transit Capital Improvement Plan. September 23, 2009

Metropolitan Council Transit Capital Improvement Plan. September 23, 2009 1 Metropolitan Council 2010-2015 Transit Capital Improvement Plan September 23, 2009 2 Current Situation Capital facilities require longer range view Recent infusion of UPA, CTIB, and State funds have

More information

Is there an alternative solution?

Is there an alternative solution? From Manned Toll Collection to All Electronic Tolling Is there an alternative solution? Alexis ZASS President of the managing board - GEA 1 Toll collection operations on bridges, tunnels, or for town access

More information

BRT: A solution to an urban transport crisis or a financial burden?

BRT: A solution to an urban transport crisis or a financial burden? BRT: A solution to an urban transport crisis or a financial burden? SABOA Conference 28 February 2013 Content 1. Our opinion of BRT 2. BRT Perceptions 3. Why the disconnect? 4. Population density vs Cost

More information

HURON COUNTY ENGINEER S OFFICE

HURON COUNTY ENGINEER S OFFICE HURON COUNTY ENGINEER S OFFICE 2017 ENGINEER S ANNUAL REPORT The Ohio Revised Code requires that each Ohio County Engineer publish an annual report to the commissioners outlining the general condition

More information

Railroad Impact Study

Railroad Impact Study Railroad Impact Study Ryan Huebschman, PE, PTOE Jason O Neill November 21, 2016 Study Impetus CSXT to lease and improve rail line between Louisville and Indianapolis Rail improvements will allow CSXT to

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

Kenosha-Racine-Milwaukee (KRM)

Kenosha-Racine-Milwaukee (KRM) Kenosha-Racine-Milwaukee (KRM) Commuter Rail #147925 November 6, 2009 1 Guidance of KRM Commuter Rail Studies Intergovernmental Partnership Technical Steering Committee Temporary and Limited Authority

More information

Bella Vista Bypass Benefit Cost Analysis

Bella Vista Bypass Benefit Cost Analysis Bella Vista Benefit Cost Analysis The Benefit Cost Analysis (BCA) was performed in accordance with the ARRA guidance provided in the Federal Register. These benefits and costs were quantified in accordance

More information

The Case for. Business. investment. in Public Transportation

The Case for. Business. investment. in Public Transportation The Case for Business investment in Public Transportation Introduction Public transportation is an enterprise with expenditure of $55 billion in the United States. There has been a steady growth trend

More information

HMA Thin Lifts for Pavement Preservation in Tennessee

HMA Thin Lifts for Pavement Preservation in Tennessee HMA Thin Lifts for Pavement Preservation in Tennessee The Tennessee Program 5,109 Interstate Lane Miles 26,244 State Route LM 31,353 Total* MARK WOODS, P.E. TDOT DIV. OF MATERIALS AND TESTS * As of 2008

More information

The Northeast Corridor Master Plan Amtrak s Next Generation High-Speed Rail and Northeastern Maryland

The Northeast Corridor Master Plan Amtrak s Next Generation High-Speed Rail and Northeastern Maryland The Northeast Corridor Master Plan Amtrak s Next Generation High-Speed Rail and Northeastern Maryland Chesapeake Science & Security Corridor Regional Rail Committee Meeting October 20, 2010 Drew Galloway

More information

Subarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County.

Subarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County. Subarea Study Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project Final Version 1 Washington County June 12, 214 SRF No. 138141 Table of Contents Introduction... 1 Forecast Methodology

More information

Clarksville Street Department. Fiscal Year 2018 Budget Presentation

Clarksville Street Department. Fiscal Year 2018 Budget Presentation Clarksville Street Department Fiscal Year 2018 Budget Presentation Clarksville Street Department FY 2018 Proposed Budget 4.2% 42.0% Salaries/Benefits 53.8% Operating Expenses Capital Outlay Clarksville

More information

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

Performance Measure Summary - Omaha NE-IA. Performance Measures and Definition of Terms

Performance Measure Summary - Omaha NE-IA. Performance Measures and Definition of Terms Performance Measure Summary - Omaha NE-IA There are several inventory and performance measures listed in the pages of this Urban Area Report for the years from 1982 to 2014. There is no single performance

More information

Performance Measure Summary - Boston MA-NH-RI. Performance Measures and Definition of Terms

Performance Measure Summary - Boston MA-NH-RI. Performance Measures and Definition of Terms Performance Measure Summary - Boston MA-NH-RI There are several inventory and performance measures listed in the pages of this Urban Area Report for the years from 1982 to 2014. There is no single performance

More information

Road Tolls and Road Pricing Innovative Methods to Charge for the Use of Road Systems

Road Tolls and Road Pricing Innovative Methods to Charge for the Use of Road Systems Road Tolls and Road Pricing Innovative Methods to Charge for the Use of Road Systems by Daphnée Benayoun & René P. Cousin The Louis Berger Group, Inc. Introduction Major challenges facing now the road

More information

Arkansas State Highway and Transportation Department. AAPA Annual Convention

Arkansas State Highway and Transportation Department. AAPA Annual Convention Arkansas State Highway and Transportation Department AAPA Annual Convention Hot Springs Embassy Suites Wednesday, April 2, 2014 Recent Voter Approved Programs November 2011 November 2012 COMPLETED 3 Projects

More information

Connected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology

Connected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology Connected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology Randy Iwasaki Executive Director Contra Costa Transportation Authority May13, 2016 WHO WE ARE The Contra Costa Transportation Authority

More information

Basic Project Information

Basic Project Information FY 2015-16 PROJECT DESCRIPTION FORM (7B) Submitting Agency: Fairfax County Basic Project Information Project Title: South Van Dorn Street and Franconia Road Interchange 7B Project Type (check one): Roadway

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Breakout Session. The Mobility Challenges of Our Growing & Sprawling Upstate

Breakout Session. The Mobility Challenges of Our Growing & Sprawling Upstate Breakout Session The Mobility Challenges of Our Growing & Sprawling Upstate The Mobility Challenges of Our Growing & Sprawling Upstate Why is our suburban and sprawling development pattern a challenge

More information

TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035)

TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035) TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035) Helping shape the future of rural Texas Texas Rural Transportation Plan 2035 Texas Rural Transportation Plan 2035 What is it? Component of the Statewide

More information

Travel Time Savings Memorandum

Travel Time Savings Memorandum 04-05-2018 TABLE OF CONTENTS 1 Background 3 Methodology 3 Inputs and Calculation 3 Assumptions 4 Light Rail Transit (LRT) Travel Times 5 Auto Travel Times 5 Bus Travel Times 6 Findings 7 Generalized Cost

More information

VTrans Budget by Funding Source

VTrans Budget by Funding Source Fall 2013 VTrans Budget by Funding Source 700,000,000 $658.1 $653.1 600,000,000 $557.7 $595.8 $553.6 500,000,000 $454.2 $420.9 $431.7 400,000,000 300,000,000 200,000,000 100,000,000-2007 2008 2009 2010

More information

Population Trends. US 12 Corridor Performance

Population Trends. US 12 Corridor Performance Corridor Context The corridor runs over 81 miles from Willmar to the Twins Cities metropolitan area. It connects the Twin Cities and the cities of Montrose, Howard Lake, Cokato, Dassel, Litchfield, Atwater,

More information

SRF No MEMORANDUM

SRF No MEMORANDUM SRF No. 0034686 MEMORANDUM TO: FROM: Rabinder Bains, Mn/DOT OIM Dave Montebello, P.E., Principal Mary Karlsson, Engineer SRF Consulting Group, Inc. DATE: May 5, 2004 SUBJECT: ST. CROIX RIVER CROSSING BENEFIT-COST

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Redefining Mobility. Randy Iwasaki. Executive Director Contra Costa Transportation Authority January 18, 2018

Redefining Mobility. Randy Iwasaki. Executive Director Contra Costa Transportation Authority January 18, 2018 Redefining Mobility Randy Iwasaki Executive Director Contra Costa Transportation Authority January 18, 2018 Who We Are CCTA is a public agency formed by voters in 1988 to manage the county s transportation

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Sales and Use Transportation Tax Implementation Plan

Sales and Use Transportation Tax Implementation Plan Sales and Use Transportation Tax Implementation Plan Transportation is more than just a way of getting from here to there. Reliable, safe transportation is necessary for commerce, economic development,

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

Arkansas State Highway and Transportation Department. Rotary Club of Stuttgart Tuesday, April 7, 2015

Arkansas State Highway and Transportation Department. Rotary Club of Stuttgart Tuesday, April 7, 2015 Arkansas State Highway and Transportation Department Rotary Club of Stuttgart Tuesday, April 7, 2015 The Facts: 12 th Largest System in USA 43 rd Highway Revenue Per Mile State Highway Systems State Mileage

More information

Task Force Meeting January 15, 2009

Task Force Meeting January 15, 2009 Task Force Meeting January 15, 2009 Study Update August 14 th Task Force Meeting Update on Traffic Projections and Financial Feasibility Study presented by Kane County and WSA staff The presentation summarized

More information

SUCCESSFUL PERFORMANCE PAVEMENT PROJECTS 2015 TxAPA Annual Meeting September 23, 2015 Austin District Mike Arellano, P.E. Date

SUCCESSFUL PERFORMANCE PAVEMENT PROJECTS 2015 TxAPA Annual Meeting September 23, 2015 Austin District Mike Arellano, P.E. Date SUCCESSFUL PERFORMANCE PAVEMENT PROJECTS 2015 TxAPA Annual Meeting September 23, 2015 Austin District Mike Arellano, P.E. Date AUSTIN DISTRICT SAFETY PERFORMANCE OF HIGH- FRICTION MIXTURES Mike Arellano,

More information

Tulsa Transportation Management Area. Urbanized Area Surface Transportation Program

Tulsa Transportation Management Area. Urbanized Area Surface Transportation Program Tulsa Transportation Management Area Urbanized Area Surface Transportation Program FFY 2022 Application Information Sponsor Location Description STP Request Other Funds Broken Arrow Elm Place: Kenosha

More information

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Capital Improvement Plan FY2015/2016 through FY2020

More information

Attachment C: Benefit-Cost Analysis Spreadsheet

Attachment C: Benefit-Cost Analysis Spreadsheet Attachment C: Benefit-Cost Analysis Spreadsheet TIGER VII Application Collier Blvd. Corridor Improvements June 5 th, 2015 Collier Blvd BCA Summary The Collier Boulevard Benefit Cost Analysis (BCA) has

More information

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only METRONext Vision & Moving Forward Plans Board Workshop December 11, 2018 Disclaimer This presentation is being provided solely for discussion purposes by the Board of Directors of the Metropolitan Transit

More information

Michigan Department of Transportation

Michigan Department of Transportation Michigan Department of Transportation Michigan Department of Transportation May 5th Ballot All taxes paid at the pump would go to transportation and sales tax goes to schools & cities.. Fuel tax increase

More information

City of Marina. Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: Transportation Agency for Monterey County

City of Marina. Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: Transportation Agency for Monterey County Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: City of Marina Study Intersections: RESERVATION ROAD AT BEACH ROAD RESERVATION ROAD AT DEFOREST ROAD CARDOZA AVENUE

More information

Benefit-Cost Analysis

Benefit-Cost Analysis APPENDIX A Southern Illinois Multi-Modal Station: Benefit-Cost Analysis Location: Carbondale, Illinois July 2018 Project Type: Urban Multi-Modal Transportation Center Applicant: City of Carbondale Type

More information

Lowering Pavement Evaluation Costs Using Big Data

Lowering Pavement Evaluation Costs Using Big Data SOLVING PROBLEMS OF GLOBAL IMPORTANCE www.ara.com Lowering Pavement Evaluation Costs Using Big Data Bill Buttlar UIUC Bill Vavrik ARA T.H.E. 2016 www.ara.com 2015 2014 Applied Research Associates, Inc.

More information

COUNCIL COMMUNICATION

COUNCIL COMMUNICATION COUNCIL COMMUNICATION TO: FROM: DEPARTMENT: Mayor and Council Larry Nimmo Public Works DATE: June 19, 2017 SUBJECT: Award Contract for 2017 Chip Seal Program DESCRIPTION: Award Contract for 2017 Chip Seal

More information

The Status of Transportation Funding, Road Charge and Vehicle Miles Traveled in California

The Status of Transportation Funding, Road Charge and Vehicle Miles Traveled in California The Status of Transportation Funding, Road Charge and Vehicle Miles Traveled in California Long-Term Policy Options for Sustainable Transportation Options NCSL State Transportation Leaders Symposium October

More information

Richmond Area MPO Regional Priority Transportation Projects

Richmond Area MPO Regional Priority Transportation Projects Regional Priority Transportation Projects October 12, 2006 Town of Ashland Counties of Charles City Chesterfield Goochland Hanover Henrico New Kent Powhatan City of Richmond Richmond Regional Planning

More information

Redefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future

Redefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future Redefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future Randy Iwasaki November 30, 2017 WHO WE ARE The Contra Costa Transportation Authority (CCTA)

More information

The Eastern Connector Study November, 2007 planning for the future

The Eastern Connector Study November, 2007 planning for the future The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team

More information

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning

More information

Jeff s House. Downtown Charlottesville. PEC Office

Jeff s House. Downtown Charlottesville. PEC Office Jeff s House Downtown Charlottesville PEC Office Year 2000 US Census Data Employed persons over 16 Percentage of Employed Persons Locality Avg Commute (in minutes) Drove Public Transit Walk/Bike Other

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

Benefit Cost Analysis

Benefit Cost Analysis Benefit Cost Analysis The Benefit Cost Analysis (BCA) was performed in accordance with the ARRA guidance provided in the Federal Register. These benefits and costs were quantified in accordance with the

More information

Performance Measure Summary - Large Area Sum. Performance Measures and Definition of Terms

Performance Measure Summary - Large Area Sum. Performance Measures and Definition of Terms Performance Measure Summary - Large Area Sum There are several inventory and performance measures listed in the pages of this Urban Area Report for the years from 1982 to 2014. There is no single performance

More information

Performance Measure Summary - Medium Area Sum. Performance Measures and Definition of Terms

Performance Measure Summary - Medium Area Sum. Performance Measures and Definition of Terms Performance Measure Summary - Medium Area Sum There are several inventory and performance measures listed in the pages of this Urban Area Report for the years from 1982 to 2014. There is no single performance

More information

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below:

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below: 3.5 TRAFFIC AND CIRCULATION 3.5.1 Existing Conditions 3.5.1.1 Street Network DRAFT ENVIRONMENTAL IMPACT REPORT The major roadways in the study area are State Route 166 and State Route 33, which are shown

More information

2018 Transportation Improvement Program (TIP) Bridge Section Summary of Proposed Changes July 24, 2018

2018 Transportation Improvement Program (TIP) Bridge Section Summary of Proposed Changes July 24, 2018 Transportation Improvement Program (TIP) Bridge Section Summary of Proposed Changes July 24, FFY Section 2A State Prioritized Reliability s Bridge Program/On-System (NHS) Increase the Cost of Holyoke (600936)

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

Head of Division for Road Traffic Technology; Road Infrastructure Safety; Routine Road Maintenance Management

Head of Division for Road Traffic Technology; Road Infrastructure Safety; Routine Road Maintenance Management BDir Dipl Ing Manfred Silvanus Head of Division for Road Traffic Technology; Road Infrastructure Safety; Routine Road Maintenance Management www.bmvi.de AGENDA - Federal Ministry of Transport and Digital

More information

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report Office of Transportation Bureau of Traffic Management 1997 Downtown Parking Meter District Rate Report Introduction The City operates approximately 5,600 parking meters in the core area of downtown. 1

More information

Performance Measures and Definition of Terms

Performance Measures and Definition of Terms Performance Measure Summary - All 471 Areas Sum There are several inventory and performance measures listed in the pages of this Urban Area Report for the years from 1982 to 2014. There is no single performance

More information

City of Pacific Grove

City of Pacific Grove Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency

More information

High-Speed Intercity Passenger Rail

High-Speed Intercity Passenger Rail September 13, 2011 LTRC Seminar Series: Congestion Management Baton Rouge New Orleans High-Speed Intercity Passenger Rail AGENDA LTRC Seminar Series: Congestion Management Baton Rouge, Louisiana Project

More information

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information