Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. College Strategic Execution Plan Update

Size: px
Start display at page:

Download "Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. College Strategic Execution Plan Update"

Transcription

1 Los Angeles Community College District PROGRAM MANAGEMENT SERVICES College Strategic Execution Plan Update District Citizens Oversight Committee October 9, 205

2 Los Angeles City College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 2 Total Value (-Expended): $30 M Infra & Other 48% 43% New 9% A Holmes Hall ernization $.6 M $6.6 M $4.55 M A Student Services Center & Demo of LRC New $39.68 M $4.55 M $25.3 M A Physical Plant (M&O Building) New $8.97 M $6.8 M $2.7 M A Tennis Courts Infra $.6 M $0.54 M $0.62 M A RWGPL Traffic Mitigation Infra $7.94 M $2.25 M $5.69 M 3 RWGPL Central Plant Phase II Infra $6.8 M $0.39 M $5.79 M 4 40J Renewable Energy Chilled Water Storage Infra $ $ $ 4 M&O Facilities $0.3 M $0.07 M $0.25 M 2 City Cafeteria Bldg Renovation $.57 M $0.002 M $.57 M 2 Monroe Street Plaza Infra $.33 M $0.08 M $.24 M 8 Demo of Men's Gym, Pool, Maint. & Misc Bungalows Other $.34 M $ $.34 M Chemistry Building Improvements $0.60 M $ $0.60 M 7 Emergency Lighting, Fire Alarm, & Security Sys. Infra $0.60 M $ $0.60 M 5 Temporary Facilities/3020 Wilshire Other $5.7 M $0.57 M $4.6 M 2

3 Los Angeles City College Strategic Execution Plan, June 205 RWGPL Landscaping/Hardscape 0 Improvements Infra $7.65 M $3.80 M $3.85 M 9 40J Trans and Accessibility Improvements $2.89 M $0.37 M $2.52 M 5 40J Storm water Quad & CDC & Biofiltration Infra $2.90 M $ $2.90 M 6 Cesar Chavez Admin Building ernization $27.46 M $.60 M $25.86 M Da Vinci Hall $24.0 M $2.33 M $2.77 M 3 South Gym ernization $3.47 M $.9 M $2.27 M A Clausen Hall ernization $23.9 M $9.93 M $3.26 M TOTAL $ M $73.4 M $30.44 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 3

4 East Los Angeles College Strategic Execution Plan, June 205 Total SEP Sub-Projects : Total Value (-Expended): $ M Infra & Other 27% 8% New 55% A Student Success &Retention Center (SSRC) New $77.88 M $60.45 M $7.43 M 3 Site Restorations at Bungalow Complexes Infra $2.45 M $0.007 M $2.44 M A Campus Student Center / Book Store Complex New $40.0 M $26.2 M $3.98 M A Science Career & Mathematics Bldg G5 (Ph. ) New $57.92 M $6.94 M $40.98 M A Science Career & Mathematics Bldg G7 (Ph. ) New $3.60 M $0.33 M $3.28 M A Science Career & Mathematics Bldg G8 (Ph.2) New $.73 M $0.53 M $.20 M A Science Career & Mathematics Bldg H8 (Ph.2) New $5.74 M $0.6 M $5.57 M 4 Site Restorations, Bungalow Complexes (SCMB) Infra $2.7 M $ $2.7 M 5 40J Storm water West &Central Section Infra $2.72 M $ $2.72 M 40J ADA Improvements Phase Exterior $5.89 M $0.54 M $5.35 M 2 40J ADA Improvements Phase 2 Interior $6.56 M $0.29 M $6.27 M TOTAL $26.76 M $05.38 M $.38 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 4

5 Los Angeles Harbor College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 6 Total Value (-Expended): $63 M Infra & Other 63% 3% New 6% A Theater Drama Speech Building $7.20 M $5.65 M $.56 M A Campus Marque ernization $2.5 M $.88 M $0.27 M 2 Old Administration ernization $6.84 M $4.34 M $2.50 M 3 Campus Wide ADA Transition $.4 M $0.3 M $0.83 M 3 Harbor Trans and Accessibility Improvements $2.32 M $0.23 M $2.09 M S.A.I.L.S. Student Union New S.A.I.L.S. Demolition Physics Bldg Other S.A.I.L.S. Demolition Old Library Other $52.98 M $2.96 M $40.02 M S.A.I.L.S. Demolition Seahawk Center Other S.A.I.L.S. Demolition General Classroom Bldg Other S.A.I.L.S. Demolition Old Science Bldg. Other $0.04 M $0.03 M $0.0 M S.A.I.L.S. Infrastructure/Land/Hardscape/ Security Other $22.7 M $6.74 M $5.43 M 40J Storm Water Student Services & Science 4 Later Infra $0.04 M $ $0.04 M 5

6 Los Angeles Harbor College Strategic Execution Plan, June J Stormwater Location # City Outfall Infra $0.2 M $ $0.2 M 4 40J Stormwater Location #2 Basin Bioretention Infra $0.9 M $ $0.9 M 4 40J Stormwater Pre Treatment Infra $0.08 M $ $0.08 M TOTAL $5.32 M $52.0 $63.22 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 6

7 Los Angeles Mission College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 5 Total Value (-Expended): $44 M Infra & Other 67% New 6% 27% A Media Arts Center New $39.55 M $22.69 M $6.86 M A Campus Wide Accessible Improvements $2.54 M $8.53 M $3.0 M A Campus Building Improvements $6.57 M $4.5 M $2.06 M A Campus Demand Side Management $5.24 M $3.57 M $.67 M A RWGPL Roadway Improvement $0.4 M $0.0 M $0.04 M 2 Health & PE, Fitness Center Electrical Interconnect Infra $.20 M $0.02 M $.8 M 3 East Campus Water Utility Interconnect Infra $0.70 M $0.03 M $0.67 M Central Energy Plant Infra $.20 M $0.54 M $0.67 M 5 RWGPL Pedestrian Access & Street Improvements Infra $0.46 M $0. M $0.35 M 6 Traffic Mitigation Infra $3.00 M $0.05 M $2.95 M 4 40J Transportation, Accessibility Parking, RWGPL Infra $3.48 M $0.02 M $3.46 M 7 40J Storm Water Implementation Infra $0.82 M $0.09 M $0.73 M 7

8 Los Angeles Mission College Strategic Execution Plan, June J East Campus Storm Water Mitigation Infra $0.63 M $ $0.63 M 9 40J Zone 4 Storm Chamber Retention System Infra $0.24 M $ $0.24 M 0 40J Zone 5 Swale with Gravel Detention Basin Infra $0.7 M $ $0.7 M TOTAL $94.94 M $50.25 M $44.69 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 8

9 Pierce Los Angeles College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 37 Total Value (-Expended): $86 M Infra & Other 38% 5% New % A Photovoltaic Arrays for Parking Lots & 8 Infra $0.88 M $.27 M $9.6 M Life Science, Chemistry, Physics Building $2.0 M $2.7 M $8.84 M Phase II Renovations Administration Building Interior and Exterior $.39 M $6.68 M $4.7 M Phase II Renovations Computer Science and Computer Learning $0.40 M $3.24 M $7.6 M Phase II Renovations Behavioral Science, Social science, Mathematics, and English $7.5 M $3.73 M $3.42 M Buildings Campus Center (Existing) General $2.58 M $2.53 M $0.05 M SLE Faculty Center/Campus Center $3.94 M $.50 M $2.43 M SLE North of Mall Classroom ernization/technology/low Voltage $9.27 M $3.44 M $5.83 M SLE North of Mall ADA/Landscaping Infra $7.6 M $.32 M $6.29 M 2 Stadium ADA Improvements $5.3 M $.83 M $3.47 M 3 SLE Community Services/Agriculture Science Building Renovation $6.04 M $2.7 M $3.87 M 9

10 Pierce Los Angeles College Strategic Execution Plan, June Campus wide Telecommunications Upgrade (VoIP) Infra $4.27 M $0.89 M $3.38 M 8 Infrastructure Campus Wide Utilities Extensions Infra $2.52 M $0.6 M $.9 M 9 Central Plant Expansion West Central Plant Infra $6.30 M $0. M $6.9 M Expanded Automotive and New Technical 0 Education Facilities New $27.33 M $.4 M $25.92 M 0 Mason Reroute Infra $3.69 M $.9 M $2.50 M 0 Campus Fire Access Road Improvements Infra $0.38 M $0.06 M $0.32 M 0 Parking Lots and Roadways Anthro/Geo Infra $2.53 M $0.22 M $2.3 M N/A 40J Pierce Storm water Infra $3.4 M $0.0 M $3.4 M 7 Horticulture Facility [excluding Demolition] $7.75 M $2.68 M $5.08 M 4 Digital Arts and Media Building New $32.95 M $.50 M $3.45 M 4 Lot 5 & 6 East Infra $4.95 M $0.07 M $4.88 M SLE South of Mall Classroom 3 ernization/technology/low Voltage $9.62 M $0.76 M $8.86 M 3 SLE South of Mall ADA/Landscaping Infra $2.38 M $0.07 M $2.3 M 6 Agricultural Education Center New $4.77 M $0.2 M $4.65 M 0

11 Pierce Los Angeles College Strategic Execution Plan, June 205 Parking Lots and Roadways Village Road & 7 Parking Lot Infra $2.83 M $ $2.83 M 40J Pierce Trans and Accessibility N/A Improvements $4.96 M $0.30 M $4.66 M N/A Restrooms Renovations Campus $0.4 M $0.24 M $0.7 M Landscaping Park, Access Road, DeSoto & 5 Mason Entrances Infra $5.94 M $0.02 M $5.92 M 4 P.E. Facilities General $2.88 M $2.4 $0.47 M 7 Horticulture Facility [Demolition]* $ $ $ 8 Campus wide Security Upgrade** Infra $ $ $ 5 Center for the Sciences New $62.7 M $6.36 M $0.8 M SLE Center for the Sciences Tech Upgrades $.8 M $0.4 M $0.77 M 2 P.E. Facilities Improvements $.06 M $0.0 M $0.96 M Early Renovations Theater Building N/A Performing Arts $.74 M $.38 M $0.35 M N/A Performing Arts Building Improvements $6.3 M $5.89 M $0.24 M TOTAL $ M $60.7 M $86.02 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. *Part of Horticulture project Priority 7. ** transfer pending from Owners Building Reserve bucket. for tomorrow s leaders

12 Los Angeles Southwest College Strategic Execution Plan, June 205 Total SEP Sub-Projects : Total Value (-Expended): $37 M Infra & Other 36% 46% New 8% A Cox Building Upgrade $44.84 M $39.52 M $5.32 M A Cox Little Theatre Upgrade $8.07 M $6.72 M $.35 M A School of Career and Technical Education New $35.88 M $33.59 M $2.29 M A 40J Storm Water Campus Wide Collection System $.02 M $.00 M $0.0 M A 40J Storm Water Pony Wall $0.50 M $0.27 M $0.23 M Campus wide Infrastructure Central Plant & Infra HVAC $4.26 M $.03 M $3.22 M 7 Campus wide Infra. Phase II (HV Campus Loop) Infra 8 Campus wide Security Upgrade Infra $0.85 M $0.38 M $0.48 M 2 School of Math & Sciences New $43.09 M $20.20 M $22.88 M 4 MTA Transit Center Infra $.38 M $0.02 M $.36 M 5 40J Trans and Accessibility Improvements $0.93 M $0.38 M $0.55 M TOTAL $50.82 M $3.3 M $37.69 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 2

13 Los Angeles Trade-Tech College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 29 Total Value (-Expended): $32 M Infra & Other 59% 3% New 0% Learning Assistance Center/Library Renovation $39.86 M $38.83 M $.03 M Campus Wide Improvements General Phase 3 $9.30 M $7.83 M $.47 M 2 Demolition of Buildings E and R** Other $3.6 M $2.96 M $0.64 M 3 Remove Swing Space Trailers Infra $0.67 M $0.28 M $0.39 M 4 South Campus Upgrade Security Doors $0.25 M $0.08 M $0.7 M East Parking Structure Increment & B Permit New $27.3 M $4.95 M $2.36 M 40J East Parking Structure Additional PV New $.04 M $0.35 M $0.69 M East Campus Substation and Electrical Distribution System New $5.25 M $.48 M $3.77 M East Campus Grounds Improvements* Infra $ $ $ 5 Art and Culinary Arts Building Phase 2** New $54.57 M $.6 M $53.4 M 8 Upgrade Temporary South Tent $ $ $ 8 Demolish Temporary North Tent Other $ $ $ * Projects in Programming; transfer pending from Owner s Reserve. ** transfer pending. 3

14 Los Angeles Trade-Tech College Strategic Execution Plan, June 205 South Campus Athletic Field* Infra $5.85 M $0.6 M $5.69 M 3 Grand Avenue Enhancement Infra $2.33 M $0.30 M $2.03 M 3 Blue Line Station Extension Infra $2.0 M $0.6 M $.94 M 6 Upgrade Child Development Center Weatherproofing* $ $0.0 M $(0.0) M 40J Transportation and Accessibility 4 Improvements ADA Transition $7.79 M $.30 M $6.49 M 40J Storm Water North Quad & Grand Ave Infra $3.9 M $ $3.8 M 5 40J Trade Olive Street Parking Structure PV Infra $2.8 M $ $2.80 M 8 Miscellaneous Improvements* Infra $ $ $ Facilities Management and Operations 7 Headquarters * New $ $ $ 40J Campus Wide Energy Management 6 Infrastructure and System Improvements ** Infra $ $ $ 2 Demo of Toyon Hall Other $0.79 M $0.0 M $0.78 M 7 Grand Theater * $ $0.0 M $(0.0) M * Projects in Programming; transfer pending from Owner s Reserve. ** Project budget pending transfer from the F building renewable energy project. 4

15 Los Angeles Trade-Tech College Strategic Execution Plan, June 205 Campus Wide Information Technology Upgrade Infra $8.93 M $8.30 M $0.63 M Upgrade Campus Main Electrical Distribution 0 System Infra $5.4 M $0.7 M $4.97 M 9 Renovate Sequoia Hall* $7.55 M $0.02 M $7.53 M 2 Renovate Sage Hall * $7.05 M $0.0 M $7.04 M Demolish Redwood Hall and North Quad Site Development Other $5.90 M $0.42 M $5.48 M TOTAL $22.28 M $88.8 M $32.47 M * Projects in Programming; transfer pending from Owner s Reserve. Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 5

16 Los Angeles Valley College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 20 Total Value (-Expended): $93 M Infra & Other 45% New 30% 25% A Community Workforce Development Center/New Administration New $43.0 M $5.55 M $27.56 M A Multi Purpose Community Services Center New $22.95 M $20.2 M $2.74 M A Parking Structure New $8.79 M $8.07 M $0.72 M A Monarch Center (Student Union Annex) New $36.5 M $22.89 M $3.62 M A Athletic Training Facility New $3.79 M $3.44 M $8.35 M Campus Wide Improvements Security System Infra Phase (Gates) Campus Wide Improvements Security System Infra Phase 2 (Call Box) $6.50 M $0.77 M $5.73 M Campus Wide Improvements Security System Infra Phase 3 (Locks & Access Cards) 3 Energy Infrastructure Improvements (Central Plant Expansion) Infra $9.82 M $.33 M $8.49 M 5 RWGPL General & Parking Lot H & J Infra $4.9 M $0.02 M $4.89 M 4 Valley Academic and Cultural Center New $93.67 M $7.78 M $85.89 M 6

17 Los Angeles Valley College Strategic Execution Plan, June Allied Health & Science Center $2.87 M $0.9 M $2.67 M 0 Campus Center Building Basement and F $4.8 M $0.29 M $4.52 M 8 Campus Center Alpha Data Center Upgrade $.06 M $0.0 M $.04 M 40J Valley Trans and Accessibility Improvements $.77 M $2.06 M $9.7 M 9 40J Storm Water Implementation Valley Infra $2.9 M $0.0 M $2.09 M 9 Sustainable Mall Other $3.28 M $0.7 M $3. M 6 Demolition Bungalows (Pkged w/ SM) Other $0.45 M $0.05 M $0.39 M Demolition of Theater Arts Building Other $.23 M $ $.23 M 7 Gym Complex Phase 2 $.24 M $ $.24 M TOTAL $ M $02.92 M $94.00 M Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 7

18 West Los Angeles College Strategic Execution Plan, June 205 Total SEP Sub-Projects : 23 Total Value (-Expended): $57 M Infra & Other 52% 35% New 3% 6 Plant Facilities Center New $3.45 M $0.36 M $3.09 M 7 40J Storm Water Project Phase 2 Pave Lot 7 Infra $0.75 M $0.0 M $0.74 M 8 40J West Energy Efficiency Project Infra $4.72 M $0.04 M $4.68 M 5 Campus Wide Security Upgrade Infra $3.59 M $0.2 M $3.48 M 4 Campus Wide Fire Alarm Monitoring Upgrade Infra Ph $0.49 M $0.4 M $0.35 M Technology Learning Center 2 (Incl Reloc of R7 3 & Paving of Lot 5) New $26.0 M $0.42 M $25.68 M 4 Watson Center 2 New $9.86 M $0.60 M $9.25 M 5 40J Trans and Accessibility Improvements Infra $.73 M $0.28 M $.45 M Demolition of Temporary & Obsolete Facilities 22 Other Dismantle Sound Walls $2.69 M $2.39 M $0.29 M 2 Performing Arts Amphitheater $0.84 M $0.03 M $0.82 M 9 40J Trans and Accessibility Improvements ATA Lot 2 Bridge & B4/5 Elevator $2.9 M $0.05 M $2.4 M 8

19 West Los Angeles College Strategic Execution Plan, June Physical Education & Dance Renovation $0.76 M $0.34 M $0.42 M 40J Trans and Accessibility Improvements Lot Infra 5 Elevator & Albert Vera Ramp $3.20 M $0.04 M $3.7 M 40J Trans & Accessibility Improvements Signage Other $0.0 M $ $0.0 M 3 Central Plant Ph. 2 (3rd Chiller & Tank Shelter) Infra $.73 M $0.32 M $.4 M 2 Campus Entry Signage Other $0.7 M $0.53 M $0.8 M A Campus Wide Paving Upgrade Sophomore Drive Striping & Signage Infra $0.2 M $0.2 M $ 0 Physical Education & Dance Renovation $0.76 M $0.34 M $0.42 M Science and Math Building Renovation for 6 Allied Health $0.06 M $0.06 M $ 7 Science Center Renovation College Spt. Facil. $0.05 M $0.05 M $ 8 Demo of Temp & Obsolete Facilities Bldg B Other $0.00 M $ $ Fine Arts Building Renovation Omni Acoustical 20 Performance Lab $0.04 M $0.04 M $ 2 Heldman LRC Renovation Phase 2 $0.7 M $0.7 M $ TOTAL $64.04 $6.46 $57.58 Note: the total budget remaining does not include projects in closeout and does not include the Owner s Reserve line item. 9

F A C I L I T I E S M A S T E R P L A N

F A C I L I T I E S M A S T E R P L A N SWOT / Preliminary Options M a y 4, 2 0 1 5 M o d i f i e d VP Administrative Services F A C I L I T I E S M A S T E R P L A T I M E L I E 2014 ovember Education / Facility Master Plan kick-off 2015 February

More information

SEQUOIA UNION HIGH SCHOOL DISTRICT MEASURE A

SEQUOIA UNION HIGH SCHOOL DISTRICT MEASURE A PROJECT LIST as (Draft) Description Additional Campuses Initial Spent as 943 Acquisition of 535 Old County Rd., San Carlos 3,407,259 3,407,259 3,407,259 3,407,259 0 closed 944 Acquisition of 150 Jefferson

More information

California State University Support Expenditures for Capital Outlay per Education Code 89772(f) (in 000s)

California State University Support Expenditures for Capital Outlay per Education Code 89772(f) (in 000s) This report was developed using campus financial reporting as collected in the CSU Systemwide Data Warehouse. CSU modified campus reporting requirements for capital improvement projects in July 2016 to

More information

Metropolitan Community College Proposed Plan to Administer the General Fund Budget By Area and Cost Center

Metropolitan Community College Proposed Plan to Administer the General Fund Budget By Area and Cost Center B13 Academic Affairs 10000 - INSTRUCTION REPORTING AND RECON 51 - PERSONNEL $535,845 $474,425-11.46% 52 - OPERATING $160,000 $55,000-65.63% 53 - SUPPLIES -$110,000 N/A 54 - TRAVEL $127,500 $127,500 0.00%

More information

The 2017 Program will be comprised of the following: Long Term Projects $15,295,100 Short Term Projects 18,000,100 TOTAL $33,295,200

The 2017 Program will be comprised of the following: Long Term Projects $15,295,100 Short Term Projects 18,000,100 TOTAL $33,295,200 PITTSBURGH SCHOOL DISTRICT 2017/2023 CAPITAL PROGRAM The following is the proposed 2017 / 2023 Capital Program. These projects have been identified as a result of Board Actions, input from Facilities,

More information

Metropolitan Community College Proposed Plan to Administer the General Fund Budget By Area and Cost Center

Metropolitan Community College Proposed Plan to Administer the General Fund Budget By Area and Cost Center B13 Academic Affairs 10000 - INSTRUCTION REPORTING AND RECON 51 - PERSONNEL $474,425 $249,517-47.41% 52 - OPERATING $55,000 $50,000-9.09% 53 - SUPPLIES -$110,000 -$246,000 123.64% 54 - TRAVEL $127,500

More information

FACILITIES NEEDS ASSESSMENT - FACILITY MASTER PLAN CONSTRUCTION COST ESTIMATE FULLERTON JOINT UNION HIGH SCHOOL DISTRICT

FACILITIES NEEDS ASSESSMENT - FACILITY MASTER PLAN CONSTRUCTION COST ESTIMATE FULLERTON JOINT UNION HIGH SCHOOL DISTRICT Buena Park High School 1 Deferred maintenance items Roofing NA 0 HVAC NA 0 Plumbing NA 0 Electrical - Repair Conduits on Roof $15.00 13,000 SF $ 195,000 $ 195,000 Lighting NA 0 Painting $0.20 8,608,000

More information

East Allen County Schools Facilities History Calendar Years October 5, 2015

East Allen County Schools Facilities History Calendar Years October 5, 2015 East Allen County Schools Facilities History Calendar Years 2007 2015 October 5, 2015 Heritage Attendance Area Heritage Jr./Sr. High School (includes K-12) 2007: Repaved Front Student Parking Lot; and

More information

THE CITY UNIVERSITY OF NEW YORK OVERVIEW OF FIVE-YEAR CAPITAL BUDGET REQUEST (Dollars Expressed in Thousands)

THE CITY UNIVERSITY OF NEW YORK OVERVIEW OF FIVE-YEAR CAPITAL BUDGET REQUEST (Dollars Expressed in Thousands) THE CITY UNIVERSITY OF NEW YORK OVERVIEW OF FIVE-YEAR CAPITAL BUDGET REQUEST (Dollars Expressed in Thousands) Senior Colleges 2000-01 2001-02 2002-03 2003-04 2004/05 Bonded $200,686 $208,686 $152,538 $271,456

More information

ROCKLIN UNIFIED SCHOOL DISTRICT ADDENDUM NUMBER 1 TO THE BID DOCUMENTS Amendment Date: January 25, 2019

ROCKLIN UNIFIED SCHOOL DISTRICT ADDENDUM NUMBER 1 TO THE BID DOCUMENTS Amendment Date: January 25, 2019 ROCKLIN UNIFIED SCHOOL DISTRICT ADDENDUM NUMBER 1 TO THE BID DOCUMENTS Amendment Date: January 25, 2019 E-rate Year 22 RFP 2019-115 Cabling Fiber Optic Infrastructure, 4 Sites A. This Amendment shall be

More information

THE CITY UNIVERSITY OF NEW YORK OVERVIEW OF FIVE-YEAR CAPITAL BUDGET REQUEST (Dollars Expressed in Thousands)

THE CITY UNIVERSITY OF NEW YORK OVERVIEW OF FIVE-YEAR CAPITAL BUDGET REQUEST (Dollars Expressed in Thousands) THE CITY UNIVERSITY OF NEW YORK OVERVIEW OF FIVE-YEAR CAPITAL BUDGET REQUEST (Dollars Expressed in Thousands) Senior Colleges 2001-02 2002-03 2003-04 2004-05 2005-06 Bonded $231,745 $170,455 $295,664 $215,669

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 H DATE: August 10, 2017 ****************************************************************************** SUBJECT: SDSU Pugsley Center Renovation

More information

Appendix C. Cost Estimates

Appendix C. Cost Estimates O Fallon Parks and Recreation Master Plan The cost estimates prepared for the ten year cost projections were estimated in 2010 US Dollars. The previous Implementation Strategies section of this Master

More information

MAIZE SCHOOLS USD #266 COST DATA / BOND ISSUE PROJECT DESCRIPTION MARCH 2015

MAIZE SCHOOLS USD #266 COST DATA / BOND ISSUE PROJECT DESCRIPTION MARCH 2015 1. Provide Storm Shelters at Maize High School - Grades 9-12 - 1,800 students + staff New Construction - North End (6,000 @ $190/SF) $ 1,140,000 - Expand athletic lobby - Concessions/Kitchen - Multipurpose

More information

CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN

CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN Page 1 of 3 CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN The six-year Capital Improvement Plan (CIP) includes capital projects for 2017 2022. This plan includes capital projects that add

More information

Metropolitan Council Metro Transit Project Description Budget Year

Metropolitan Council Metro Transit Project Description Budget Year Metropolitan Council Metro Transit Project Description Budget Year ADA Pad Bus Garage Maintenance Shop Cleaning and Painting Hoist Replacement Program Redundant Power Program Drivers Rest Room Program

More information

BOE Facilities Capital Project Priority List FY 17/18 Fut. Yr. Total Proj. Overall Amount Amount Project Priority Priority

BOE Facilities Capital Project Priority List FY 17/18 Fut. Yr. Total Proj. Overall Amount Amount Project Priority Priority Cat 1 Project Category BOE Safety/ Security CPB504 A) Upgrade/ Replace Doors - System Wide 200 250 450 1 10 B) Roxbury/ Toquam Safety Playground Upgrades 250 100 350 1 1 C) Vestibule- Springdale 100 100

More information

Watauga County Schools Capital Improvement Plan 2015

Watauga County Schools Capital Improvement Plan 2015 Watauga County Schools Capital Improvement Plan 2015 WATAUGA COUNTY SCHOOLS CAPITAL IMPROVEMENT PLAN 2015 In an effort to meet the standards of the North Carolina Building Code and North Carolina Public

More information

San Diego Community College District. Proposition S and N Program Schedule

San Diego Community College District. Proposition S and N Program Schedule San Diego City College 835 30/Apr/13 A 13/Aug/19 56.42% SDCCD Proposi on S 786 30/Jun/16 13/Aug/19 23.76% Child Development Center 786 30/Jun/16 13/Aug/19 23.76% 11210 100 Design 320 30/Jun/16* 20/Sep/17

More information

BOE Facilities Capital Project Priority List

BOE Facilities Capital Project Priority List Cat 1 BOE Safety/ Security CPB504 A) Upgrade/ Replace Doors - System Wide 200 250 450 1 3 B) Roxbury/ Toquam Safety Playground Upgrades 250 100 350 1 1 C) Vestibule- Springdale 100 0 100 D) Vestibule-

More information

Updated 10/16/2018. BUILDING 2100: Academic Support and Offices New Sq. Ft Existing Location Existing Area Classrooms/Labs

Updated 10/16/2018. BUILDING 2100: Academic Support and Offices New Sq. Ft Existing Location Existing Area Classrooms/Labs BUILDING 2100: Academic Support and Offices New Sq. Ft Existing Location Existing Area Classrooms/Labs Classrooms (11 @ 1,000 ASF) 11,000 408A, 408B, 403, 402,101,102, 103, 104 6467 English Staff Work

More information

QUARTERLY REPORT st QUARTER. Quarter for Advert. / Contract Award Phase Status

QUARTERLY REPORT st QUARTER. Quarter for Advert. / Contract Award Phase Status or) STREET RESURFACING, WATER MAIN AND SEWER 1 ERGB Construction Engr Phase III $ 150,000 $ 723,804 1/11/16 Const Phase Status 2 ERGB Improvements $ 150,000 $ 11,173,776 2016 1Q Const Finalizing lighting

More information

FPS Project Backlog Projected Completion

FPS Project Backlog Projected Completion FPS Project Backlog - 2016 Projected Completion Project Number KUCC-0101 FAC2012-143 FR2012-123 FAC2012-063 FR2012-137 FAC2012-079 Project Description University Stadium - Replace Synthetic Turf Projected

More information

MOBILITY AND ACCESSIBILITY IN OUR COMMUNITY

MOBILITY AND ACCESSIBILITY IN OUR COMMUNITY MOBILITY AND ACCESSIBILITY IN OUR COMMUNITY MOBILITY AND ACCESSIBILITY BACKGROUND Mobility and Accessibility Working Committee Broad representation Transit, Transportation, Planning and Development, Facility

More information

Project Summary. Evanston Water Treatment Plant Upgrade. Install new water filtration equipment

Project Summary. Evanston Water Treatment Plant Upgrade. Install new water filtration equipment Project Summary *The Campus Construction Map PDF is linked to each map identification number, click the number on the map to view the corresponding project summary. Map Identification No: 1 Evanston Water

More information

City of Alameda Capital Improvement Projects Fiscal Years Proposed Project Descriptions

City of Alameda Capital Improvement Projects Fiscal Years Proposed Project Descriptions Drainage Southshore Lagoon Dredging $525,000 74 Prepare drawings and design deepening or removal of sediment from lagoons. Marina Village Park $580,500 70 Resolve the drainage issue in the Marina Village

More information

SAN JACINTO COLLEGE COMMERCIAL TRUCK DRIVING CLASS SCHEDULE

SAN JACINTO COLLEGE COMMERCIAL TRUCK DRIVING CLASS SCHEDULE SAN JACINTO COLLEGE COMMERCIAL TRUCK DRIVING CLASS SCHEDULE CVOP Day Class 2013 Monday through Thursday 7AM to 6PM -6 weeks PTD/DDC Day Defensive Driving Course Schedule January 7 - February 14 February

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

Summary of Funding Sources

Summary of Funding Sources GENERAL SOURCES General Revenue 91221 - EMS Capital Equipment 11,200 15,000 18,000 10,000 54,200 91229 - Replace & Upgrade Air Packs 22,500 22,500 91245 - Garage Door Replacement (Fire) 26,000 26,000 912xx

More information

C Tenant Improvements 2,901, C Fire Standpipe Repairs and Fire Sprinkler System Upgrade for

C Tenant Improvements 2,901, C Fire Standpipe Repairs and Fire Sprinkler System Upgrade for GENERAL FUND (01) C017060.589000 EXPO Maintenance Yard Buffer Park 440,000 - - - C019098.589000 Downtown Santa Monica Temporary Use TOD Site 836,400 - - - M014078.589000 Swim Facilities Planned Maintenance

More information

Student Membership Counts By Career Cluster

Student Membership Counts By Career Cluster 0 Administration Student Membership Counts By Career Cluster 2017-2018 Professional (Chapter) 282 50 54 386 36 Summary for Administration: 282 50 54 386 36 375 reporting: M: 62.9% F: 37.1% 1 Agriculture,

More information

MSD OF WAYNE TOWNSHIP SUSTAINABILITY PROJECTS

MSD OF WAYNE TOWNSHIP SUSTAINABILITY PROJECTS MSD OF WAYNE TOWNSHIP 2017-2018 SUSTAINABILITY PROJECTS 2017 Superintendent Goals #2 Continued work towards increasing revenue and reducing expenditures including a reduction in the M.S.D. of Wayne Township

More information

UNIFIED GOVERNMENT Proposed Capital Maintenance Improvement Program (CMIP) Capital Cash Project Summary 5/14/18 Fund/Departm ent New Annual

UNIFIED GOVERNMENT Proposed Capital Maintenance Improvement Program (CMIP) Capital Cash Project Summary 5/14/18 Fund/Departm ent New Annual - 2023 Proposed Capital Maintenance Improvement Program (CMIP) Fund/Departm ent New Original Amended 2019 2020 2021 2022 2023 FY18-23 110 - City - General Fund Chief Knowledge Office 1 9 AUTO - 1997 -

More information

Sketch Plans. for the Addition and Renovation of. BISHOP REDING CATHOLIC SECONDARY SCHOOL Milton, Ontario. September 26, 2018

Sketch Plans. for the Addition and Renovation of. BISHOP REDING CATHOLIC SECONDARY SCHOOL Milton, Ontario. September 26, 2018 Sketch Plans for the Addition and Renovation of BISHOP REDING CATHOLIC SECONDARY SCHOOL Milton, Ontario September 26, 2018 Table of Contents 1.0 Building Program...1 2.0 Site Plan...4 3.0 Floor Plans...5

More information

WINNER. Orange County Public Schools. 100% Design Community Meeting Hidden Oaks Elementary School February 21, 2017

WINNER. Orange County Public Schools. 100% Design Community Meeting Hidden Oaks Elementary School February 21, 2017 Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ WINNER 100% Design Community Meeting Hidden Oaks Elementary School February 21, 2017 Hidden Oaks Elementary School 100%

More information

The Educational Special Purpose Local Option Sales Tax (ESPLOST II) went into effect on January 1, 2012.

The Educational Special Purpose Local Option Sales Tax (ESPLOST II) went into effect on January 1, 2012. Fund 3XX Capital Projects $12,, $1,, $8,, $6,, $4,, $2,, $ Fy 11 Fy 12 Fy 13 Fund 3XX Revenue vs Expenses FY14 Modified FY15 Adopted ESPLOST I Revenue ESPLOST I Expenditures Capital Projects - Facility

More information

CAMPUS PARKING PROGRAM

CAMPUS PARKING PROGRAM Jill Stearns, President Modesto Junior College 435 College Avenue, Modesto, California 95350 Yosemite Community College District Joan Smith, Chancellor Yosemite Community College District 2201 Blue Gum

More information

Alphabetical Listing of Unified Pay Scale Positions SY Effective: July 1, 2017

Alphabetical Listing of Unified Pay Scale Positions SY Effective: July 1, 2017 Alphabetical Listing of Unified Pay Scale Positions Work Calendar Annual Hours Daily Hours Grade Exemption Status Minimum Mid Point Maximum Minimum Mid Point Maximum ADM Division Superintendent EXC Exempt

More information

PSAT / NMSQT SUMMARY REPORT COLLEGE-BOUND HIGH SCHOOL SOPHOMORES NEVADA

PSAT / NMSQT SUMMARY REPORT COLLEGE-BOUND HIGH SCHOOL SOPHOMORES NEVADA PSAT / NMSQT SUMMARY REPORT 2003-2004 COLLEGE-BOUND HIGH SCHOOL SOPHOMORES Copyright 2004 by College Entrance Examination Board. All rights reserved. Student Search Service, College Board, and the acorn

More information

PSAT / NMSQT SUMMARY REPORT COLLEGE-BOUND HIGH SCHOOL SOPHOMORES MONTANA

PSAT / NMSQT SUMMARY REPORT COLLEGE-BOUND HIGH SCHOOL SOPHOMORES MONTANA PSAT / NMSQT SUMMARY REPORT 2003-2004 COLLEGE-BOUND HIGH SCHOOL SOPHOMORES Copyright 2004 by College Entrance Examination Board. All rights reserved. Student Search Service, College Board, and the acorn

More information

PSAT / NMSQT SUMMARY REPORT COLLEGE-BOUND HIGH SCHOOL SOPHOMORES MISSISSIPPI

PSAT / NMSQT SUMMARY REPORT COLLEGE-BOUND HIGH SCHOOL SOPHOMORES MISSISSIPPI PSAT / NMSQT SUMMARY REPORT 2003-2004 COLLEGE-BOUND HIGH SCHOOL SOPHOMORES Copyright 2004 by College Entrance Examination Board. All rights reserved. Student Search Service, College Board, and the acorn

More information

Metro Gold Line Eastside Extension Review Advisory Committee March 12, 2009

Metro Gold Line Eastside Extension Review Advisory Committee March 12, 2009 Review Advisory Committee March 12, 2009 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within

More information

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Capital Improvement Plan FY2015/2016 through FY2020

More information

Approved. Department & Item. Article # Requested. Requested. Requested Requested Requested Requested Requested Requested Requested

Approved. Department & Item. Article # Requested. Requested. Requested Requested Requested Requested Requested Requested Requested AMOUNT SOURCE General Government 135 Town Accountant Financial Software Package Upgrade 150,000 subtotal 0 0 0 0 150,000 0 0 0 0 0 0 155 MIS Technology Infrastructure 300,000 300,000 Tax Levy 300,000 300,000

More information

District Technology Purchase and Replacement Plan for the 4-year Levy Cycle,

District Technology Purchase and Replacement Plan for the 4-year Levy Cycle, District Technology Purchase and Replacement Plan for the 4-year Levy Cycle, 2017-2020 The following pages, 2-8, identify Technology assets and cost of purchases/replacements for the 4-year levy cycle.

More information

State Avenue Corridor Bus Rapid Transit (BRT)

State Avenue Corridor Bus Rapid Transit (BRT) State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!

More information

GENERAL GOVERNMENT ~ Municipal Buildings

GENERAL GOVERNMENT ~ Municipal Buildings Department of Development Aeronautics Building Inspection Economic Development Geographic Information Systems Planning & Zoning Building Maintenance Building Inspector Superintendent Laborer Janitor Electrician

More information

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT. WORK IN PROGRESS September 2010

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT. WORK IN PROGRESS September 2010 AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS September 2010 AUBURN RIVERSIDE HS & MT. BAKER MS HVAC IMPROVEMENTS PROGRESS: Auburn Riverside High School: New variable speed

More information

Capital Project Tracking Report

Capital Project Tracking Report BTC Annex IT Services: Installation Firm: DataPlus Communications Funding: $167,170 Start: March 2018 End: May 2018 NTP & Preconstruction Meeting. Bus Shelter Pad & Installation Phase 6 TBD Start: TBD

More information

Port of Grays Harbor Capital Improvement Plan

Port of Grays Harbor Capital Improvement Plan Marine Terminals Communication Equipment VHF Radio 3,000 3,000 3,000 3,000 3,000 Deeper Draft Deeper Draft Phase 2 4,713,000 1,172,000 Jet Array Jet Array Renovation 200,000 200,000 200,000 200,000 200,000

More information

University of Connecticut Undergraduate Degree Seeking Enrollment at Storrs Campus By School/College and Major Fall

University of Connecticut Undergraduate Degree Seeking Enrollment at Storrs Campus By School/College and Major Fall Ratcliffe Hicks: (Associate Degree) Animal Science 54 47 49 52 49 45 32 46 48 47 Ornamental Horticulture & Turfgrass Management 17 23 24 24 18 19 23 23 18 14 Total Ratcliffe Hicks: 71 70 73 76 67 64 55

More information

CRDM Projects Approved

CRDM Projects Approved Date CRDM Bldg. CRDM s Approved 5/25/10 FY07-0001 P779440 529 Science Engineering classroom shades 20,167.00 Doyle Def Maint Arch 6/21/10 FY07-0002 P779444 551 S&R 2 4th flr filter vents 3,306.65 Madrigal

More information

Mercer Island Center for the Arts Parking Management Plan

Mercer Island Center for the Arts Parking Management Plan Parking Stalls Mercer Island Center for the Arts Parking Management Plan June 15, 2016 This Parking Management Plan (P) covers all tenants at the Mercer Island Center for the Arts (MICA) campus, including

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update

More information

Report on the Annual Progress of the. Statewide Energy Partnership (SEP) Program. Legislative Report. February 2016

Report on the Annual Progress of the. Statewide Energy Partnership (SEP) Program. Legislative Report. February 2016 Report on the Annual Progress of the Statewide Energy Partnership (SEP) Program Legislative Report Budget and Capital Resources December 2009 UNIVERSITY of CALIFORNIA Office of the President UNIVERSITY

More information

GREAT NECK UNION FREE SCHOOL DISTRICT

GREAT NECK UNION FREE SCHOOL DISTRICT GREA NECK UNION FREE SCHOOL DISRIC December March 13, 12, 2017 2016 RECOMMENDED BOND IEMS BBS ARCHIECS, LANDSCAPE ARCHIECS & ENGINEERS, P.C. BBS COS ELEMENS "A LIS" GREA NECK PUBLIC SCHOOLS BOND REFERENDUM

More information

Committee Approved Critical Repairs

Committee Approved Critical Repairs Location Description Estimate Apollo Extend walk-off mats $ 5,000 Food Services Equipment $ 61,200 Apollo Total $ 66,200 Briarwood Food Services Equipment $ 17,000 Reseal all gutter seams and flashing

More information

CYPRUS HIGH SCHOOL COURSES SENIORS

CYPRUS HIGH SCHOOL COURSES SENIORS English Language Arts (4 credits required in English) English 12 569010 English, Core Year $8 Cyprus AP Language Arts 569150 English, Core Year $8 Cyprus AP Literature 569100 English, Core Year $8 Cyprus

More information

City of. Bird s Eye View of Pasadena, circa CAPitAL improvement PRoGRAM BUDGEt

City of. Bird s Eye View of Pasadena, circa CAPitAL improvement PRoGRAM BUDGEt Title pages 09 print.qnd:layout 8/7/8 : PM Page 7 City of Bird s Eye View of Pasadena, circa 890-90 CAPitAL improvement PRoGRAM BUDGEt FISCAL YEAR 09-0 The Capital Improvement Program (CIP) is a 5-year

More information

New Hanover County Schools Capital Outlay Summary &

New Hanover County Schools Capital Outlay Summary & New Hanover County Schools Capital Outlay Summary & Summary of Capital Requests: Category Total Requests Repairs & Renovations $ 3,488,500 $ 3,529,500 $ 7,018,000 Technology 1,835,100 4,104,600 5,939,700

More information

CITY OF BELLEVILLE 2017 Capital Budget

CITY OF BELLEVILLE 2017 Capital Budget CITY OF BELLEVILLE 2017 Capital Budget Proposed Financing COMBINED SERVICES 1.001 Bridge St W Coleman to Highland Design EDS 73 300.0 150.0 150.0 1.002 University Ave McFarland Dr to Tice Cres EDS 65 1,900.0

More information

Burlington Capital Improvement Plan: FY FY 2023

Burlington Capital Improvement Plan: FY FY 2023 General Government 135 Town Accountant Financial Software Package Upgrade 150,000 subtotal 0 0 0 0 150,000 0 0 0 0 0 145 Treasurer/Collector Printer Replacement 155 MIS Software Upgrade Information Systems

More information

University of Connecticut Undergraduate Degree Seeking Enrollment at Storrs Campus By School/College and Major Fall

University of Connecticut Undergraduate Degree Seeking Enrollment at Storrs Campus By School/College and Major Fall Ratcliffe Hicks: (Associate Degree) Animal Science 47 49 52 49 45 32 46 48 47 43 Ornamental Horticulture & Turfgrass Management 23 24 24 18 19 23 23 18 14 17 Total Ratcliffe Hicks: 70 73 76 67 64 55 69

More information

SCHEDULE OF CAPITAL PROJECTS BY FUND

SCHEDULE OF CAPITAL PROJECTS BY FUND CIP Project Funding Summary 5 7 8 9 10 11 Streets & Highways Fund 3,950,541 2,148,259 1,250,000 1,290,000 1,250,000 9,888,800 Prop C Fund 20,936,435 700,000 700,000 700,000 700,000 23,736,435 Measure R

More information

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle Chapter 7: Travel Demand Analysis Chapter 8 Plan Scenarios LaSalle Community Center. Image Credit: Town of LaSalle 164 Chapter 8: Plan Scenarios Moving Ahead for Progress in the 21 st Century Act (MAP

More information

Fund 3XX Revenue vs Expenses

Fund 3XX Revenue vs Expenses Fund 3XX Capital Projects Fund 3XX Revenue vs Expenses $9,, $8,, $7,, $6,, $5,, $4,, $3,, $2,, Revenue ESPLOST Revenue Capital Projects-Phase II Expenses Capital Projects-Phase II Revenue Cap Proj-Facility

More information

Credit Hour Production by Department and School

Credit Hour Production by Department and School Sections Sections Sections Sections Sections College of Arts and Sciences Biology 1359 34.0 1003 24.7 36 3.3 2398 1707 37.0 1707 Group : 3066 71 1003 25 36 3 4105 2262 56.0 931 24.2 20 2.8 3213 804 15.0

More information

Town of Yarmouth Capital Improvement Plan FY FY2025

Town of Yarmouth Capital Improvement Plan FY FY2025 Town of Yarmouth Capital Improvement Plan FY2016 - FY2025 CONTENTS PAGE Narrative Overview 1 Recommendations for 2015 Annual Town Meeting 3 Facility Plan: Big Ticket Items FY2016 - FY2025 7 Capital Improvement

More information

Town of Middletown, RI Capital Improvement Program PROJECTS & FUNDING SOURCES BY DEPARTMENT

Town of Middletown, RI Capital Improvement Program PROJECTS & FUNDING SOURCES BY DEPARTMENT Town of Middletown, RI Capital Improvement Program FY '4 FY '8 thru PROJECTS & FUNDING SOURCES BY DEPARTMENT Department Project# Priority 0 - School Department FY '4 FY '5 FY '6 FY '7 FY '8 Floor Strippers/Burnishers

More information

Corridor Management Committee. March 7, 2012

Corridor Management Committee. March 7, 2012 Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed

More information

Carson City School District Completed School Bond

Carson City School District Completed School Bond Carson City School District 2010 Completed School Bond Discussion Projects categorized and prioritized based on: Health safety & welfare Code compliance Energy and operational efficiency Educational program

More information

Location Sample ID 10/17/2017 Response Ballenger Field House Hydration Stations Men's Locker Room BFH_HS 1 1 ND

Location Sample ID 10/17/2017 Response Ballenger Field House Hydration Stations Men's Locker Room BFH_HS 1 1 ND Potable water testing for lead was done on, October 17, 2017 at all hydrations station locations, filtered sinks, and ice machines at Mott Community College. Showers were also tested at Ballenger Field

More information

City of Fernandina Beach, Florida Annual Budget

City of Fernandina Beach, Florida Annual Budget General Fund (001) Finance KRONOS PAYROLL SOFTWARE 100% 50,000 50,000 X Human Resources KRONOS HR MODULE 100% 50,000 50,000 X NEW PHONE SYSTEM-VARIOUS GENERAL FUND DEPARTMENTS Non-Departmental 100% 125,000

More information

Campus Computing Sites Printers B254 B A B745 B727 B735 B737 B250. Printer Locations. Handicap Access RAMP CHURCH STREET

Campus Computing Sites Printers B254 B A B745 B727 B735 B737 B250. Printer Locations. Handicap Access RAMP CHURCH STREET asement 069 860 Gateway Testing Math Lab Spaces Side of East Hall 7 70 67A 67 7 860M 860I 760A 67 67 67A 65 68 67 6 66 68H 68 67C 7A 64 7 7 80A 7C 468 470 470 464 470A 464A 464 Math Lab 860 860J 860K 760

More information

Guideline for Square Footage Requirements for Educational Facilities (a) 4. Educational Facility Site, Construction, and Reimbursement

Guideline for Square Footage Requirements for Educational Facilities (a) 4. Educational Facility Site, Construction, and Reimbursement Guideline for Square Footage Requirements for Educational Facilities 160-5-4-.16 (a) 4 Educational Facility Site, Construction, and Reimbursement Facilities Services Unit Effective Date: July 25, 2010

More information

East Falls Business Unit Crosswalk Mapping

East Falls Business Unit Crosswalk Mapping New 011 Employee Benefits - East Falls 00000 General 032 Corporate Services East Falls 10200 Chief Financial Officer 032 Corporate Services East Falls 10210 Business Office 032 Corporate Services East

More information

WAYFINDING SIGNAGE STANDARDS

WAYFINDING SIGNAGE STANDARDS WAYFINDING SIGNAGE STANDARDS Environmental Graphic Design Consultants San Francisco, CA Tel: 415.773.1000 Fax: 415.773.1008 CAMUSES AGE 2 SIGN FAMILY Sola no Coll ege Roa d 1800B 1700 lle ge So lan O LOT

More information

Elevator Serial Number. Manufacturer (Controller)

Elevator Serial Number. Manufacturer (Controller) Line Item Building Name # 1 Millican Hall 0001 1 07758 Dover Simplex Hydraulic 3 E&G Main 2 Library 0002 1 33687 General Duplex Hydraulic 5 E&G Main 3 Library 0002 2 04654 Dover Duplex Hydraulic 5 E&G

More information

Request for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV

Request for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Issued: Monday, Site Tour: Friday, January 30, 2015 at 10:00 a.m. Submittal Deadline: 5:00 p.m. on Friday,

More information

PARKING AND TRAFFIC REGULATIONS

PARKING AND TRAFFIC REGULATIONS PARKING AND TRAFFIC REGULATIONS 2016-2017 Jersey Village High School 7600 Solomon Houston, Texas 77040 713-896-3400 CONTENTS Introduction Page 1 Guidelines Pages 2-7 1. Who must purchase a parking sticker?...2.............

More information

Transportation and Facilities Report. Tuesday, January 23, 2017 Cynthia Kwiatkowski: Director of Transportation and Facilities

Transportation and Facilities Report. Tuesday, January 23, 2017 Cynthia Kwiatkowski: Director of Transportation and Facilities 1 Transportation and Facilities Report Tuesday, January 23, 2017 Cynthia Kwiatkowski: Director of Transportation and Facilities 2 The Wheatland-Chili Central School community is committed to academic excellence

More information

Fixed Asset Allocations by Budget Unit for FY

Fixed Asset Allocations by Budget Unit for FY 1100 112 Treasurer-Tax Collector Upgrading current business license program for greater Business License Software & Services 8965 Computer Software 1 10,900 10,900 10,900 efficiency for citizens and staff

More information

FAMU Completers Satisfaction Survey Results 2010

FAMU Completers Satisfaction Survey Results 2010 FAMU Completers Satisfaction Survey Results 2010 Non-Member record_type Frequency Percent Percent Cumulative Percent 35 100.0 100.0 100.0 Race: Frequency Percent Percent Cumulative Percent Black 30 85.7

More information

Public Works. Capital Projects FY

Public Works. Capital Projects FY Public Works Capital Projects FY 2015-17 Projects Completed FY 2014 All Done Projects! Residential and Collector Street Paving Lower Westside Arterial Street Rehab: Front, River St South, Soquel Hwy 1

More information

E. LAUREL HEIGHTS BACKGROUND

E. LAUREL HEIGHTS BACKGROUND E. LAUREL HEIGHTS E. LAUREL HEIGHTS BACKGROUND The Laurel Heights site is located at 3333 California Street on an approximately four-block, 10.8-acre site bounded by California Street, Masonic Avenue,

More information

GROWTH & DEVELOPMENT. Residents enjoying the newly opened Brickell City Centre on Nov. 3, 2016.

GROWTH & DEVELOPMENT. Residents enjoying the newly opened Brickell City Centre on Nov. 3, 2016. GROWTH & DEVELOPMENT Residents enjoying the newly opened Brickell City Centre on Nov. 3, 2016. 20 Growth & Development Overview With over 450,000 residents, the City of Miami is at the heart of one of

More information

Fair Park - Capital Needs Inventory

Fair Park - Capital Needs Inventory : 1: Permanent Facility with Occupant; : Year-Round Visitation; 3: Potential to Attract Year-Round or Tenants; 4:, Security, Code, ADA; 5: Urgent Major Maintenance 1 3 4 July 10, 017- DRAFT PRIORITIES

More information

CAMPUS PARKING REGULATIONS. Police and Campus Safety Department

CAMPUS PARKING REGULATIONS. Police and Campus Safety Department CAMPUS PARKING REGULATIONS P Police and Campus Safety Department Responsibilities Vehicle code violations, as well as handicapped and fire lane violations, will be enforced by the Prairie State College

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

3.14 Parks and Community Facilities

3.14 Parks and Community Facilities 3.14 Parks and Community Facilities 3.14.1 Introduction This section identifies the park and community facility resources in the study area and examines the potential impacts that the proposed Expo Phase

More information

Mobile Food Vendors Policy. 1.0 Purpose. 2.0 Policy NO Virginia Polytechnic Institute and State University

Mobile Food Vendors Policy. 1.0 Purpose. 2.0 Policy NO Virginia Polytechnic Institute and State University Mobile Food Vendors Policy NO. 5810 Policy Effective Date: 1/23/2017 Last Revision Date: Policy Owner: Sherwood Wilson Policy Author: (Contact Person) Kayla Smith Affected Parties: Faculty Staff Other

More information

FY11 OPERATING BUDGET

FY11 OPERATING BUDGET FY11 OPERATING BUDGET YEAR ENDING JUNE 30, 2011 TABLE OF CONTENTS Resolution...1 2 Budget Summary All Funds...3 4 Operating Fund...5 11 Designated Funds Summary...12 13 Dedicated Student Fees...14 15

More information

THE WAY WE MOVE LRT FOR EVERYONE

THE WAY WE MOVE LRT FOR EVERYONE THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an

More information

2016 FACILITIES IMPROVEMENT PLAN

2016 FACILITIES IMPROVEMENT PLAN 2016 FACILITIES IMPROVEMENT PLAN HIGH QUALITY FACILITIES + BEST QUALITY EDUCATORS + LOCAL SUPPORT = HIGH PERFORMING STUDENTS June 19, 2015 McCourtney Rd. Adult Center Nevada Joint Union High School District

More information

MUNCIPAL WORK PROGRAMS FY 2015/ /20. MPO Transportation Improvement Program 2015/ /20 Page 9-1

MUNCIPAL WORK PROGRAMS FY 2015/ /20. MPO Transportation Improvement Program 2015/ /20 Page 9-1 MUNCIPAL PROGRAMS BELLEAIR 2000 Curb/Sidewalk 35 2001 Roadway Projects 2,500 = ; = Local Funds 35 MPO Transportation Improvement Program 2015/16 2019/20 Page 9-1 MUNCIPAL PROGRAMS BELLEAIR BEACH 3000 Resurface/curb

More information

Capital Improvement Projects Status Report December 2014 (Actuals through October) Percent Design Complete. Design Finish. Construction Finish

Capital Improvement Projects Status Report December 2014 (Actuals through October) Percent Design Complete. Design Finish. Construction Finish Title I. Terminals Berth 90-93 - World Cruise Center 4. B. 93 - Cruise Terminal - Customs and Border Protection Improvements Conceptual (2525300) d 11/27/14 100% N/A $140,000 $73,479 52% 5. B. 91-93 -

More information

INTERNET ACCESS GOALS AND PLANS

INTERNET ACCESS GOALS AND PLANS i. Which do you consider to be your primary college* 2-year college Other 4-year Valley West Total 484 518 122 154 169 94 398 415 405 31 118 2,908 16.6 17.8 4.2 5.3 5.8 3.2 13.7 14.3 13.9 1.1 4.1 100.0

More information

Articulation Course Guide and High School Teacher Requirements

Articulation Course Guide and High School Teacher Requirements Articulation Course Guide and High School Teacher Requirements This document outlines courses approved by FV for high school articulation consideration along with teacher qualification and certification

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared