Executive Summary. Project Overview. Existing System. Study Summary

Size: px
Start display at page:

Download "Executive Summary. Project Overview. Existing System. Study Summary"

Transcription

1 APPENDIX A CONNECTION ASSESSMENT

2

3

4 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta), in its capacity as the legal owner of distribution facilities (DFO), has submitted a system access service request (SASR) to the Alberta Electric System Operator (AESO), to reliably serve industrial load growth in the Town of Edson area. The SASR includes a request for a Rate DTS, Demand Transmission Service, contract capacity of 18 MW and a request for transmission development in the Town of Edson area (collectively, the Project). Specifically, the DFO requested a new point-of-delivery (POD) substation with one 138/6 kv transformer to serve new and existing loads at the Kinder Morgan Edson pump station terminal. The scheduled in-service date for the Project is February 1, This report presents the system performance studies undertaken to assess the impact of the Project on the Alberta interconnected electric system (AIES). Existing System Geographically, the Project is located in the AESO planning area of Hinton/Edson (Area 29), which is part of the AESO Central Region. The Hinton/Edson area (Area 29) is surrounded by the Wabamun (Area 40), Swan Hills (Area 26), Fox Creek (Area 24), Grande Cache (Area 22) and Drayton Valley (Area 30) planning areas. From a transmission system perspective, the Hinton/Edson area consists primarily of 138 kv and 69 kv transmission systems. The Hinton/Edson area is connected to adjacent planning areas by the two 240 kv transmission lines 973L and 974L and by the three 138 kv transmission lines 854L, 744L, and 202L. There are no existing transmission constraints in the study area. Study Summary Study Area for the Project The study area for the Project consists of Hinton/Edson (Area 29) and Drayton Valley (Area 30), including the tie lines that connect these two planning areas to the rest of the AIES (i.e., the tie lines include the four 138 kv transmission lines 672L, 834L, 854L, 744L and the three 240 kv transmission lines 973L, 974L and 995L). All transmission facilities within the study area were studied and monitored to assess the impact of the Project on the AIES, including any violations of the Reliability Criteria (as defined in Section.1). Studies Performed for the Project Power flow analysis was performed for the 2017 winter peak (WP) pre-project scenario, and the 2017 WP and 2018 summer peak (SP) post-project scenarios. Voltage stability analysis was performed for the 2017 WP and 2018 SP post-project scenarios. Results of the pre-project Studies Under Category A conditions and Category B contingency conditions, no Reliability Criteria violations were observed for the 2017 WP scenario. AltaLink Page I August 2016

5 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Connection Alternatives Examined for the Project FortisAlberta, as the DFO, examined and ruled out the use of distribution solutions to serve the new and existing loads in the Town of Edson area. This report examines five transmission alternatives to meet the DFO s request for system access service. Alternative 1: Modify the existing Edson 58S substation, including adding a 25 kv feeder breaker. Alternative 1 would also require 11 km of new 25 kv distribution feeders along with additional upgrades to the distribution system. Alternative 2: Add a new POD substation, to be named Hornbeck 345S substation, and add approximately 2 km of new 138 kv circuit to connect the Hornbeck 345S substation to the existing 138 kv transmission line 854L with an in/out connection configuration. The Hornbeck 345S substation would include two 138 kv circuit breakers, one 138/6 kv transformer, and other associated equipment. Alternative 3: Add a new POD substation, to be named Hornbeck 345S substation, and add approximately 1 km of new 138 kv circuit to connect the Hornbeck 345S substation to the existing 138 kv transmission line 745L with an in/out connection configuration. The Hornbeck 345S substation would include two 138 kv circuit breakers, one 138/6 kv transformer, and other associated equipment. Alternative 4: Upgrade the existing Marlboro 348S substation by adding a new 138/25 kv transformer and associated equipment, and modify the connection configuration from T-tap to an in/out connection configuration by adding approximately 11 km of new 138 kv circuit. Alternative 5: Upgrade the existing Edson 58S substation, including adding a new 138/25 kv transformer. Connection Alternatives Selected for Further Examination Alternative 1 and Alternative 3 were selected for further study. Both Alternative 2 and Alternative 4 involve additional transmission facility development and hence, additional cost compared to Alternative 1 and Alternative 3. Alternatives 2 and 4 were not selected for further study. The DFO determined that Alternative 5 was not technically feasible due to space constraints; therefore, Alternative 5 was not selected for further study. Results of the post-project Studies Alternative 1 Under Category A conditions and Category B contingency conditions, no Reliability Criteria violations were observed for any of the post-project scenarios. Alternative 3 Under Category A conditions and Category B contingency conditions, no Reliability Criteria violations were observed for any of the post-project scenarios. Conclusions and Recommendation Based on the study results, both Alternative 1 and Alternative 3 are technically viable. The studies show that the connection of the Project using Alternative 1 or Alternative 3 would not adversely impact the performance of the AIES. Cost estimates prepared by the TFO and DFO indicate that Alternative 3 has a lower estimated cost than Alternative 1. While both Alternative 1 and Alternative 3 are technically viable, Alternative 3 is the preferred alternative based on cost. AltaLink Page II August 2016

6 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation It is recommended to proceed with the Project using Alternative 3 (adding the new Hornbeck 345S substation) as the preferred option to respond to the DFO s request for system access service. AltaLink Page III August 2016

7 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Contents Executive Summary... I 1. Introduction Project Project Overview Load Component Generation Component Study Scope Study Objectives Study Area Studies Performed Report Overview Criteria, System Data, and Study Assumptions Criteria, Standards, and Requirements Transmission Planning Standards and Reliability Criteria Authoritative Documents (ADs) Study Scenarios Load and Generation Assumptions Load Assumptions Generation Assumptions Intertie Flow and HVDC Assumptions System Projects Customer Connection Projects Facility Ratings and Shunt Elements Voltage Profile Assumptions Study Methodology Connection Studies Carried Out Power Flow Analysis Contingencies Studied Voltage Stability Analysis Contingencies Studied Pre-Project System Assessment Pre-Project Power Flow Analysis Scenario 1: 2017 Winter Peak Connection Alternatives Overview Connection Alternatives Identified Connection Alternatives Selected for Further Studies Connection Alternatives Not Selected for Further Studies Technical Analysis of the Connection Alternatives Power Flow Alternative Scenario 2: 2017 Winter Peak Scenario 3: 2018 Summer Peak Alternative Scenario 2: 2017 Winter Peak Scenario 3: 2018 Summer Peak Voltage Stability Alternative AltaLink Page IV August 2016

8 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Scenario 2: 2017 Winter Peak Scenario 3: 2018 Summer Peak Alternative Scenario 2: 2017 Winter Peak Scenario 3: 2018 Summer Peak Results Summary Project Interdependencies Conclusion and Recommendation AltaLink Page V August 2016

9 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Attachments Attachment A Attachment B Attachment C Attachment D Attachment E Pre-Project Power Flow Diagrams Alternative 1: Post-Project Power Flow Diagrams Alternative 3: Post-Project Power Flow Diagrams Alternative 1: Post-Project Voltage Stability Diagrams Alternative 3: Post-Project Voltage Stability Diagrams Figures Figure 1-1: Existing Study Area Transmission System... 3 Figure 5-1: Alternative 2 New Substation with In/Out Connection to 854L Figure 5-2: Alternative 3 New Substation with In/Out Connection to 745L Tables Table -1: Post Contingency Voltage Deviation Guidelines... 6 Table -1: List of the Connection Study Scenarios... 6 Table -1: Forecast Area Load (2014 LTO at Alberta Internal Load Peak)... 6 Table -2: Local Generation (MW) in the Study Cases... 7 Table -1: Summary of Customer Connection Assumptions... 7 Table 2.6-1: Summary of Transmission Line Ratings in the Study Area (MVA on Voltage Class Bases)... 8 Table 2.6-2: Summary of Key Transformer Ratings in the Study Area... 8 Table 2.6-3: Summary of Shunt Elements in the Study Area... 9 Table 2.7-1: Summary of Voltage Operating Ranges at Key Nodes in the Study Area... 9 Table 3.1-1: Summary of Studies Performed Table -1: Overview of Pre-Project Study Results Table -2: Overview of Pre-Project Study Results Table 6.1-1: Overview of Post-Project Studies Results Table 6.2-1: Scenario 2: 2017 WP Voltage stability analysis results (Minimum transfer = 16.9 MW) Table 6.2-2: Scenario: 2018 SP Voltage stability analysis results (Minimum transfer = 16.1 MW) Table 6.2-3: Scenario: 2017 WP Voltage stability analysis results (Minimum transfer = 16.9 MW) Table 6.2-4: Scenario: 2018 SP Voltage stability analysis results (Minimum transfer = 16.1 MW) AltaLink Page VI August 2016

10 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 1. Introduction This engineering study report (ESR) presents the results of the studies conducted to assess the impact of the Project (as defined below) on the performance of the Alberta interconnected electric system (AIES) Project Project Overview FortisAlberta Inc. (FortisAlberta), in its capacity as the legal owner of distribution facilities (DFO), has submitted a system access service request (SASR) to the Alberta Electric System Operator (AESO) to reliably serve industrial load growth in the Town of Edson area. The SASR includes a request for a Rate DTS, Demand Transmission Service, contract capacity of 18 MW and a request for transmission development in the Town of Edson area (collectively, the Project). Specifically, the DFO requested a new point-of-delivery (POD) substation with one 138/6 kv transformer to serve new and existing loads at the Kinder Morgan Edson pump station terminal. The scheduled in-service date for the Project is February 1, Load Component The DFO-requested DTS contract capacity for system access service is 18.0 MW, which includes 13 MW of new industrial load and 5 MW of industrial load transferred from Edson 58S Substation. This connection assessment will assume a 0.9 lagging power factor (pf) for the load associated with the Project Generation Component There is no generation component associated with the Project Study Scope 1.. Study Objectives The objective of this study is as follows: Assess the impact of the Project on the performance of the AIES. Identify any violations of the relevant criteria, standards, or requirements of the AESO both pre-project and post-project. Recommend mitigation measures, if required, to enable the reliable connection of the Project to the AIES. AltaLink Page 1 August 2016

11 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 1.. Study Area Study Area Description Geographically, the Project is located in the AESO planning area of Hinton/Edson (Area 29), which is part of the AESO Central region. The Hinton/Edson area (Area 29) is surrounded by the Wabamun (Area 40), Swan Hills (Area 26), Fox Creek (Area 24), Grande Cache (Area 22) and Drayton Valley (Area 30) planning areas. From a transmission system perspective, Hinton/Edson area consists primarily of 138 kv and 69 kv transmission systems. The Hinton/Edson area is connected to adjacent planning areas by the two 240 kv transmission lines 973L and 974L and by the three 138 kv transmission lines 854L, 744L, and 202L. The study area for the Project consists of the AESO planning areas of Hinton/Edson (Area 29) and Drayton Valley (Area 30), including the tie lines connecting these two planning areas to the rest of the AIES (i.e., the tie lines include the four 138 kv transmission lines 672L, 834L, 854L, 744L and the three 240 kv transmission lines 973L, 974L and 995L that connect the Hinton/Edson and Drayton Valley areas to the rest of the AIES). All transmission facilities within the study area were studied and monitored to assess the impact of the Project on the AIES, including any violations of the Reliability Criteria (as defined in Section.1). The existing transmission system in the study area is shown in Figure 1-1. AltaLink Page 2 August 2016

12 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Figure 1-1: Existing Study Area Transmission System 24 - Fox Creek 26 - Swan Hills 29 - Hinton / Edson DALEHURST 975S COLD CREEK 602S 615L WATSON CREEK 104S 762L MOUNTAIN COALOBED 411S CARDINAL RIVER 302S 742AL MANALTA COAL GREGG RIVER 476S 745L CHEVIOT 101S 745A1L Weldwood #1 (WWD1) MARLBORO 348S 745AL COALSPUR 426S 501L FICKLE LAKE 406S 847L CADOMIN 983S 685L (to 501CL Benbow 397S) DEER HILL 1012S 743L 740L 854L 854AL 30 - Drayton Valley 740L BICKERDIKE 39S COAL VALLEY 527S Talisman Edson (TLM2) 740AL 671L WEST PEMBINA 477S 844L BRAZEAU 358S EDSON 58S GULF ROBB 414S PINEDALE 207S 890L 202L 841L 801AL ELK RIVER 445S 801L 828L T.M.P.L. NITON 228S PETRO CANADA BRAZEAU RIVER 489S BRAZEAU RUBBER DAM 3E 973L/974L (to Sundance 310P) CYNTHIA 178S PADDLE RIVER 106S 801L 202AL BRAZEAU OUTLET WORKS 294S 744L (to Entwistle 235S) 202L BRAZEAU 62S Entwistle 672L (to WEST PEMBINA 359S Brazeau Hydro (BRA) G1-G Wabamun LODGEPOLE 61S 836L 235S) 673L VIOLET GROVE 283S Benalto 995L (to 17S) 34 - Abraham Lake 38 - Caroline 744AL This diagram contains a simplified version of the system configuration. Technical detail has been simplified for illustration purposes. It does not indicate geographical locations of facilities. 922L/926L (to Sundance 310P) 922L/926L (to MOON LAKE 131S Drayton Valley (DV1) 835AL 995AL Benalto 17S) Genesee 330P) 1325L (to Langdon 102S) 835L BUCK LAKE 454S BuckLake (PW01) WILLESDENGREEN 68S 1325L (to Gas Generator Hydro Generator Other Generator 69 or 72 kv Substation 138 or 144 kv Substation 240 kv Substation 500 kv Substation Keephills 190L/930L 320P) (to KEYSTONE 384S 190L/930L (to Benalto 17S) 31 - Wetaskiwin 69/72 kv 69/138 kv Double Circuit 138/144 kv 240 kv 240 kv Double Circuit 500 kv P1460 Project Area AESO Planning Areas Currency Date: P1460 Area Transmission System 35 - Red Deer Benalto 922L ( AltaLink Page 3 August 2016

13 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Existing Constraints There are no existing transmission constraints in the study area AESO Long-Term Transmission Plans No system development projects the Hinton/Edson and Drayton Valley areas were modelled. The AESO 2015 Long-term Transmission Plan (2015 LTP) 1 includes the following system developments that are in the vicinity of the study area in the near term (by 2020): 2 Increase 240/144 kv transformer capacity at Little Smoky substation; Add new 240 kv transmission lines from Little Smoky 813S Substation to Fox Creek 741S Substation; Expand Fox Creek 741S Substation to include 240/144 kv transmission facilities; Add new 240 kv transmission lines from Fox Creek 741S Substation to Bickerdike 39S Substation near Edson 58S Substation; Open 144 kv line between Fox Creek 741S Substation and Little Smoky 813S Substation; and Add voltage support at Fox Creek 741S Substation. 1.. Studies Performed The following studies were performed for the pre-project analysis: Power flow analysis The following studies were performed for the post-project analysis: Power flow analysis Voltage stability analysis 1.3. Report Overview The Executive Summary provides a high-level summary of the study and its conclusions. Section 1 introduces this engineering study report. Section 2 describes the reliability criteria, system data, and other study assumptions used in this study. Section 3 describes the methodology used for this study. Section 4 discusses the pre-project assessment of the system. Section 5 presents all the connection alternatives contemplated. Section 6 provides a technical analysis of the connection alternatives considered for further study. Section 7 presents any dependencies the Project may have on other AESO plans to expand or enhance the transmission system. Section 8 presents the conclusions and recommendations of this study. 1 The 2015 LTP document is available on the AESO website. 2 The 2015 LTP identifies the near-term transmission developments in the Fox Creek-Valley View subregion on page 51. AltaLink Page 4 August 2016

14 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 2. Criteria, System Data, and Study Assumptions. Criteria, Standards, and Requirements.1. Transmission Planning Standards and Reliability Criteria The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO s Transmission Planning Criteria Basis and Assumptions 3 (collectively, the Reliability Criteria) were applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B contingencies (i.e., single element outage), prior to and following the studied alternatives. Below is a summary of Category A and Category B system conditions. Category A, often referred to as the N-0 condition, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of service, result in the loss of any single specified system element under specified fault conditions with normal clearing. These elements include a generator, a transmission circuit, a transformer or a single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers. The TPL standards, TPL-001-AB-0 and TPL-002-AB-0, have referenced Applicable Ratings when specifying the required system performance under Category A and Category B events. For the purpose of applying the TPL standards to the studies documented in this report, Applicable Ratings are defined as follows: Seasonal continuous thermal rating of the line s loading limits. Highest specified loading limits for transformers. For Category A conditions: Voltage range under normal operating condition per AESO Information Document ID# RS, General Operating Practices - Voltage Control, which relates to Section 30 of the ISO rules, Maintaining Network Voltage. For the busses not listed in ID# RS, Table 2-1 in the Transmission Planning Criteria Basis and Assumptions applies. For Category B conditions: The extreme voltage range values per Table 2-1 in the Transmission Planning Criteria Basis and Assumptions. Desired post-contingency voltage change limits for three defined post event timeframes as provided in Table Filed under a separate cover AltaLink Page 5 August 2016

15 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Table -1: Post Contingency Voltage Deviation Guidelines Time Period Parameter and reference point Voltage deviation from steady state at POD low voltage bus Post Transient (up to 30 sec) Post Auto Control (30 sec to 5 min) Post Manual Control (Steady State) ±10% ±7% ±5%.2. Authoritative Documents (ADs) AESO Information document ID# RS, was applied to establish system normal (i.e., pre-contingency) voltage profiles in the study area and its vicinity. The TCM Rule was followed to assess any criteria violations identified as a result of the connection studies.. Study Scenarios Table -1 provides a list of the study scenarios. This connection assessment will assume a 0.9 lagging power factor for the load associated with the Project. Table -1: List of the Connection Study Scenarios Scenario Year/Season Load Condition Project Load (MW) Project Generation (MW) System Generation Dispatch Conditions WP Pre-Project 0 0 Market dispatch WP Post-Project 18 0 Market dispatch SP Post-Project 18 0 Market dispatch. Load and Generation Assumptions.1. Load Assumptions The study area load forecasts used for this connection study are shown in Table -1, and are based on the AESO 2014 Long-term Outlook (2014 LTO). Table -1: Forecast Area Load (2014 LTO at Alberta Internal Load Peak) Area Name Season Forecast Peak Load (MW) Hinton/Edson Drayton Valley Alberta Internal Load w/o Losses 2017 WP SP WP SP WP 12, SP 12,017.4 AltaLink Page 6 August 2016

16 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation.2. Generation Assumptions The generation conditions for this connection assessment are described in Table -2. The Weldwood Generator unit #2 connected to Cold Creek 602S substation, is considered to be the critical generating unit for the purpose of the studies, and is assumed to be offline for the power flow and voltage stability analyses. Table -2: Local Generation (MW) in the Study Cases Existing /Future Existing Unit Name 602SG1 (Weldwood 1) 602SG2 (Weldwood 2) 58SG1 (Edson 1) Bus Number Area Pmax (MW) 2017 WP Unit Net Generation* (MW) 2018 SP Unit Net Generation (MW) *Unit Net Generation refers to Gross Generating unit MW output less Unit Service Load..3. Intertie Flow and HVDC Assumptions The Alberta-BC, Alberta-Montana, and Alberta-Saskatchewan intertie points are deemed to be too far away to have any material impact on the connection assessment for the Project. Therefore, the intertie flows were dispatched the same as in the AESO s base cases. The Western Alberta Transmission HVDC Line (WATL) and the Eastern Alberta Transmission HVDC Line (EATL) assumptions were expected to have minimal impact for the connection studies. Therefore, HVDC assumptions were kept consistent with that in the AESO planning base cases and not adjusted for this study.. System Projects No system projects were included in the study scenarios.. Customer Connection Projects The list of customer projects included in the study is shown in Table -1. Table -1: Summary of Customer Connection Assumptions Planning Area Queue Position* Planned In-Service Date Project Name Project # Gen (MW) Load (MW) Included/Excluded from Studies** 29 N/A In service Fortis Deer Hill 1012S substation Included Aug ATCO Jasper Interconnection Project Capacity Increase Included * Per the AESO Connection Queue posted in June ** These projects are dispatched per the load and generation levels set out in Section 1 and Section.2. AltaLink Page 7 August 2016

17 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 2.6. Facility Ratings and Shunt Elements The Transmission Facility Owner (TFO) provided the ratings for the existing transmission lines (Table 2.6-1) and the existing key transformers (Table 2.6-2) in the study area. Table 2.6-1: Summary of Transmission Line Ratings in the Study Area (MVA on Voltage Class Bases) Line ID Line Description Voltage Class (kv) Nominal Rating (MVA) Short-term * Rating (MVA) Summer Winter Summer Winter 615L Cold Creek 602S Watson Creek 104S L Bickerdike 39S Cold Creek 602S L Bickerdike 39S Edson 58S L Bickerdike 39S Cold Creek 602S L Bickerdike 39S Coalspur 426S L Bickerdike 39S Edson 58S OT** 135 OT L Bickerdike 39S Marlboro 348S Tap CT*** 263 CT L Benbow 397S Marlboro 348S Tap OT 201 OT L Edson 58S Cynthia 178S L Fox Creek 347S Benbow 397S L Edson 58S Pinedale 207S L Pinedale 207S Entwistle 235S L Bickerdike 39S Sundance 310P CT 333 CT 499 CT 499 CT 974L Bickerdike 39S Sundance 310P CT 333 CT 499 CT 499 CT * When line loading in post Category B contingency is observed to exceed nominal rating and is less than the shortterm (emergency) rating, it is assumed that AESO and TFO operating practices can manage the constraint within the time requirements of TFO short-term (emergency) rating. ** The limitation factor for the line rating is due to other terminal equipment. *** The limitation factor for the line rating is due to a current transformer. Table 2.6-2: Summary of Key Transformer Ratings in the Study Area Substation Name and Number Transformer ID Transformer Voltages (kv) MVA Rating Bickerdike 39S 39ST1 240/ Bickerdike 39S 39ST2 240/ The details of shunt elements in the Study Area are given in Table Capacitors are the only shunt elements within the Study Area; no reactors or Static VAR Compensators (SVC) are present. AltaLink Page 8 August 2016

18 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Table 2.6-3: Summary of Shunt Elements in the Study Area Substation Name and Number Voltage Class (kv) Number of Switched Shunt Blocks Capacitors Total at Nominal Voltage (MVAr) Status in Study (on or off) 2017WP (MVAr) 2018 SP (MVAr) Cold Creek 602S x 3 MVAr 3 3 (on) 3 (on) Edson 58S x 2 MVAr 2 27 (on) 27 (on) Cynthia 178S x 2 MVAr 2 27 (on) 27 (on) Amoco Brazeau 358S x 2 MVAr 2 21 (on) 21 (on) Brazeau 62S x 33.0 MVAr (off) 0.0 (off) Violet Grove 283S x MVAr (on) 0.0 (off) 2.7. Voltage Profile Assumptions The AESO ID# RS was used to establish system normal (i.e., pre-contingency) voltage profiles for key area busses prior to commencing any studies. Table 2-1 of the Transmission Planning Criteria Basis and Assumptions applies for all the busses not included in the ID# RS. These voltages were utilized to set the voltage profile for the study base cases prior to power flow analysis. The key bus voltages for the study area for the project are shown in Table Table 2.7-1: Summary of Voltage Operating Ranges at Key Nodes in the Study Area Substation Nominal Voltage (kv) Minimum Operating Limit (kv) Desired Range (kv) Maximum Operating Limit (kv) Bickerdike 39S Edson 58S Brazeau 62S Willesden Green 68S AltaLink Page 9 August 2016

19 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 3. Study Methodology The analyses performed in this connection assessment were completed using PTI PSS/E version Connection Studies Carried Out The studies to be carried out for this connection study are identified in Table Table 3.1-1: Summary of Studies Performed Scenario and Condition Project 1460 Load (MW) Generation (MW) System Conditions Power Flow 4 Voltage Stability WP Pre-project 0 0 Category A and Category B X WP Post-Project 18 0 Category A and Category B X X SP Post-Project 18 0 Category A and Category B X X. Power Flow Analysis The purpose of the power flow analysis is to quantify any incremental violations in the study area after the Project is connected. Power flow analysis was completed for all study scenarios to identify thermal overloads or transmission voltage violations as per the Reliability Criteria, and to identify any deviations from the desired limits, shown in Table -1. Transformer tap and switched shunt reactive compensation devices such as shunt capacitors and reactors were locked and continuous shunt devices were enabled when performing the Category B power flow analysis. POD low voltage bus deviations were assessed by first locking all tap changers and area capacitors to identify any post-transient voltage deviations above 10%. Second, tap changers were then allowed to adjust, while shunt reactive compensating devices capacitors remained locked; to determine if any voltage deviations above 7% would occur in the area. Third, all taps and shunt reactive compensating devices were adjusted and voltage deviations above 5% were reported for both the pre-project and post-project networks. 3.. Contingencies Studied Power flow analysis was performed for the Category A condition and all Category B contingencies in the study area, including ties to surrounding areas for all pre- and post-project scenarios. AltaLink Page 10 August 2016

20 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 3.3. Voltage Stability Analysis The objective of the voltage stability analysis is to determine the ability of the network to maintain voltage stability at all the busses in the system under normal and abnormal system conditions. The power-voltage (PV) curve is a representation of voltage change as a result of increased power transfer between two systems. The reported incremental transfers will be to the collapse point. As per the AESO requirements, no assessment based upon other criteria such as minimum voltage was made at the PV minimum transfer. Voltage stability analysis was performed for post-project scenarios. Pre-Project voltage stability analysis would only be performed if the post-project scenarios show voltage stability criteria violations. Voltage stability analysis was performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology. WECC voltage stability criteria states, for load areas, post-transient voltage stability is required for the area modeled at a minimum of 105% of the reference load level for system normal conditions (Category A) and for single contingencies (Category B). For this WECC standard, the reference load level is the maximum established planned load. Typically, voltage stability analysis is carried out assuming the worst case scenarios in terms of loading. The voltage stability analysis was performed by increasing load in the study area and by increasing the corresponding generation in the AESO planning are of Wabamun (Area 40) Contingencies Studied Voltage stability analysis was performed for the Category A condition and all Category B contingencies in study area, including ties to surrounding areas for all pre- and post-project scenarios. AltaLink Page 11 August 2016

21 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 4. Pre-Project System Assessment. Pre-Project Power Flow Analysis Table -1 provides an overview of the pre-project power flow analysis and applicable mitigation measures. Condition Table -1: Overview of Pre-Project Study Results Results Scenario Mitigation Measure Contingency Result Category A Not applicable No violations None required 2017 WP Category B All No violations None required.1. Scenario 1: 2017 Winter Peak No Reliability Criteria violations were observed under the Category A conditions. No Reliability Criteria violations were observed under the Category B contingency conditions. The results of the power flow analysis are summarized in Table -2 and are shown in the power flow diagrams in Attachment A. Table -2: Overview of Pre-Project Study Results Contingency Thermal Overloads Voltage Performance N-G- 0: System normal N-G-1: All studied contingencies None Acceptable AltaLink Page 12 August 2016

22 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 5. Connection Alternatives 5.1. Overview Five transmission alternatives were examined to meet the DFO s request for system access service, as detailed in Section Connection Alternatives Identified Below is a description of the developments associated with the transmission alternatives that were examined for the Project. 5 Alternative 1: Modify the Edson 58S substation Alternative 1 involves modifying the existing Edson 58S substation by adding a 25 kv feeder breaker. Alternative 1 would also require 1 km of new 25 kv distribution feeders along with additional upgrades to the distribution system to maintain reliability. Alternative 2: Hornbeck 345S substation connected to 138 kv transmission line 854L Alternative 2 involves the addition of a POD substation, named Hornbeck 345S. In this alternative, Hornbeck 345S substation would be connected to the existing 138 kv transmission line 854L by adding 2 km of 138 kv circuit to create an in/out connection configuration. The Hornbeck 345S substation would include two 138 kv circuit breakers, one 138/6 kv LTC transformer with a minimum transformation capacity of 20 MVA, and other associated equipment. The configuration of Alternative 2 is shown in Figure These alternatives reflect more up to date engineering design than the alternatives identified in the Fortis Need for Development, New Edson Area Load Addition Transmission Facility Upgrades, which is filed under a separate cover. AltaLink Page 13 August 2016

23 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Figure 5-1: Alternative 2 New Substation with In/Out Connection to 854L 854L Bus 830 MARLBTAP 854L 1150L Bus 472 Hornbeck 345S Bus 88 BICKERD7 Bus 910 OBED TAP 138/6 kv 15/20/25 MVA 345SD1 745L 345ST1 BUS 4725 HORNBECK9 Bickerdike 39S Alternative 3: Hornbeck 345S substation connected to transmission line 745L Alternative 3 involves the addition of a POD substation, named Hornbeck 345S. In this alternative, Hornbeck 345S substation would be connected to the existing 138 kv transmission line 745L via 1 km of new 138 kv transmission line to create an in/out configuration. The Hornbeck 345S substation would include two 138 kv circuit breakers, one 138/6 kv LTC transformer with a minimum transformation capacity of 20 MVA, and other associated equipment. The configuration of Alternative 3 is shown in Figure 5-2. AltaLink Page 14 August 2016

24 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Figure 5-2: Alternative 3 New Substation with In/Out Connection to 745L Bus 830 MARLBTAP Bus 910 OBED TAP 745L 854L 745L 1150L Bus 88 BICKERD7 Bickerdike 39S Bus 472 Hornbeck 345S 138/6 kv 15/20/25 MVA 345SD1 345ST1 BUS 4725 HORNBECK9 Alternative 4: Upgrade the Marlboro 348S substation Alternative 4 involves upgrading the existing Marlboro 348S substation to provide 25 kv service by adding a 138/25 kv 25 MVA LTC transformer and associated equipment, and adding approximately 11 km of new 138 kv circuit to change the existing T-tap connection to the 138 kv transmission line 854L to an in/out connection configuration. Alternative 5: Upgrade the Edson 58S Substation Alternative 5 involves upgrading the existing Edson 58S substation by adding a 138/25 kv 25 MVA LTC transformer and associated equipment. The DFO determined that constructing the additional distribution feeder egress cables from a third transformer would not be feasible due to space constraints. 5.. Connection Alternatives Selected for Further Studies Alternative 1 and Alternative 3 were selected for further study. 5.. Connection Alternatives Not Selected for Further Studies Both Alternative 2 and Alternative 4 involve additional transmission facility development and hence, additional cost, compared to Alternative 1 and Alternative 3. Specifically, Alternative 2 was not selected for further study because the proposed in/out connection configuration would AltaLink Page 15 August 2016

25 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation require 1 km more 138 kv circuit compared to Alternative 3. Alternative 4 was not selected for further study because the scope of transmission facility upgrades required was much larger than Alternative 1 or Alternative 3. The DFO determined that Alternative 5 was not technically feasible due to space constraints; therefore, Alternative 5 was not selected for further study. AltaLink Page 16 August 2016

26 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 6. Technical Analysis of the Connection Alternatives 6.1. Power Flow Table provides an overview of the post-project power flow analysis. Table 6.1-1: Overview of Post-Project Studies Results Alternative Scenario Contingency Thermal Overloads Voltage Performance WP 2018 SP 2017 WP 2018 SP N-G- 0: System normal N-G-1: All studied contingencies N-G- 0: System normal N-G-1: All studied contingencies N-G- 0: System normal N-G-1: All studied contingencies N-G- 0: System normal N-G-1: All studied contingencies None Acceptable Alternative 1 The following is a summary of the power flow analysis conducted for Alternative 1. Power flow diagrams are provided in Attachment B Scenario 2: 2017 Winter Peak No Reliability Criteria violations were observed under Category A conditions or Category B contingency conditions Scenario 3: 2018 Summer Peak No Reliability Criteria violations were observed under Category A conditions or Category B contingency conditions Alternative 3 The following is a summary of the power flow analysis conducted for Alternative 3. Power flow diagrams are provided in Attachment C Scenario 2: 2017 Winter Peak No Reliability Criteria violations were observed under Category A conditions or Category B contingency conditions. AltaLink Page 17 August 2016

27 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Scenario 3: 2018 Summer Peak No Reliability Criteria violations were observed under Category A conditions or Category B contingency conditions Voltage Stability Voltage stability analysis was conducted using the 2017 WP and 2018 SP post-project scenarios to investigate the system active power margins after the Project under Category A conditions and Category B contingency conditions. 6.. Alternative 1 The following is a summary of the voltage stability analysis conducted for Alternative 1. Voltage stability diagrams are provided in Attachment D Scenario 2: 2017 Winter Peak Voltage stability analysis was performed for the 2017 WP scenario. The reference load level for the Hinton/Edson area and Drayton Valley area (AESO Planning Areas 29 and 30) is MW. The minimum incremental load transfer for the Category B contingencies is 5.0% of the reference load or 16.9 MW to meet the voltage stability criteria (0.05 x MW = 16.9 MW). Table summarizes the voltage stability results for Category A and the worst five (5) Category B contingencies for voltage stability transfer margins. The voltage stability margin is met for all studied conditions. Table 6.2-1: Scenario 2: 2017 WP Voltage stability analysis results (Minimum transfer = 16.9 MW) Contingency From To Maximum incremental transfer (MW) Meets 105% transfer criteria? N-G-0 System Normal Yes 973L Sundance 310P Bickerdike 39S Yes 62ST5 Brazeau Plant 62S 240 kv to 138 kv transformer T Yes 104ST2 Watson Creek 104S 138 kv to 69 kv transformer T Yes 39ST1 Bickerdike 39S 240 kv to 138 kv transformer T Yes 745L Cold Creek 602S Bickerdike 39S Yes Scenario 3: 2018 Summer Peak Voltage stability analysis was performed for the 2018 SP scenario. The reference load level for Hinton/Edson (Area 29) and Drayton Valley (Area 30) is 32 MW. The minimum incremental load transfer for the Category B contingencies is 5.0% of the reference load or 16.1 MW to meet the voltage stability criteria (0.05 x 32 MW = 16.1 MW). Table summarizes the voltage stability results for Category A and the worst five (5) Category B contingencies for voltage stability transfer margins. The voltage stability margin is met for all studied conditions. AltaLink Page 18 August 2016

28 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Table 6.2-2: Scenario: 2018 SP Voltage stability analysis results (Minimum transfer = 16.1 MW) Contingency From To Maximum incremental transfer (MW) Meets 105% transfer criteria? N-G System Normal Yes 973L Sundance 310P Bickerdike 39S Yes 62ST5 Brazeau Plant 62S 240 kv to 138 kv transformer T Yes 104ST2 Watson Creek 104S 138 kv to 69 kv transformer T Yes 745L Cold Creek 602S Bickerdike 39S Yes 39ST1 Bickerdike 39S 240 kv to 138 kv transformer T Yes 6.. Alternative 3 The following is a summary of the voltage stability analysis conducted for Alternative 3. Voltage stability diagrams are provided in Attachment E Scenario 2: 2017 Winter Peak Voltage stability analysis was performed for the 2017 WP scenario. The reference load level for Hinton/Edson (Area 29) and Drayton Valley (Area 30) is MW. The minimum incremental load transfer for the Category B contingencies is 5.0% of the reference load or 16.9 MW to meet the voltage stability criteria (0.05 x MW = 16.9 MW). Table summarizes the voltage stability results for Category A and the worst five (5) Category B contingencies for voltage stability transfer margins. The voltage stability margin is met for all studied conditions. Table 6.2-3: Scenario: 2017 WP Voltage stability analysis results (Minimum transfer = 16.9 MW) Contingency From To Maximum incremental transfer (MW) Meets 105% transfer criteria? N-G System Normal Yes 1150L Bickerdike 39S Hornbeck 345S Yes 973L Sundance 310P Bickerdike 39S Yes 62ST5 Brazeau Plant 62S 240 kv to 138 kv transformer T Yes 104ST2 Watson Creek 104S 138 kv to 69 kv transformer T Yes 39ST1 Bickerdike 39S 240 kv to 138 kv transformer T Yes Scenario 3: 2018 Summer Peak Voltage stability analysis was performed for the 2018 SP scenario. The reference load level for Hinton/Edson (Area 29) and Drayton Valley (Area 30) is 32 MW. The minimum incremental load transfer for the Category B contingencies is 5.0% of the reference load or 16.1 MW to meet the voltage stability criteria (0.05 x 32 MW = 16.1 MW). Table summarizes the voltage stability results for Category A and the worst five (5) Category B contingencies for voltage stability transfer margins. AltaLink Page 19 August 2016

29 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation The voltage stability margin is met for all studied conditions. Table 6.2-4: Scenario: 2018 SP Voltage stability analysis results (Minimum transfer = 16.1 MW) Contingency From To Maximum incremental transfer (MW) Meets 105% transfer criteria? N-G System Normal Yes 1150L Bickerdike 39S Hornbeck 345S Yes 62ST5 Brazeau Plant 62S 240 kv to 138 kv transformer T Yes 973L Sundance 310P Bickerdike 39S Yes 104ST2 Watson Creek 104S 138 kv to 69 kv transformer T Yes 39ST1 Bickerdike 39S 240 kv to 138 kv transformer T Yes 6.3. Results Summary Power flow results confirm that both Alternative 1 and Alternative 3 are technically feasible. Both alternatives would not cause adverse impact to the AIES under Category A conditions and Category B contingency conditions. Voltage stability analysis results demonstrate that the voltage stability margins in Hinton/Edson (Area 29) and Drayton Valley (Area 30) would continue to meet the AESO requirements should the Project proceed as either Alternative 1 or Alternative 3. Based on the study results, both Alternative 1 and Alternative 3 are technically viable. AltaLink Page 20 August 2016

30 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 7. Project Interdependencies The Project is not dependent on other AESO plans to expand or enhance the transmission system. AltaLink Page 21 August 2016

31 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation 8. Conclusion and Recommendation Based on the study results, both Alternative 1 and Alternative 3 are technically viable. The studies show that the connection of the Project using Alternative 1 or Alternative 3 would not adversely impact the performance of the AIES. Cost estimates 6 prepared by the TFO and DFO indicate that Alternative 3 has a lower estimated cost than Alternative 1. While both Alternative 1 and Alternative 3 are technically viable, Alternative 3 is the preferred alternative based on cost. It is recommended to proceed with the Project using Alternative 3 (adding the new Hornbeck 345S substation) as the preferred option to respond to the DFO s request for system access service. The minimum transformation capacity required for the 138/6 kv transformer at the Hornbeck 345S substation is 20 MVA. 6 Cost estimates are provided under separate cover. AltaLink Page 22 August 2016

32 Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Attachment A Pre-Project Power Flow Diagrams AltaLink Page 23 August 2016

33 1 423 KEEPHIL KEYSTON S_ P C BRB W PEMBI KEYSTO P C BRA BUCK TAP 135 SUNDANC4 49 KEYSTON ELKRIVE W PEMBI P C BRA CYNTHIA HBOG BRA BICKERD AMOCO BR EDSON ELKRIVTP PINEDAL EDSON BICKERD G.ROBB T OBED TAP FICKL TP MARLBTAP MARLBOR BENBOW BRAZEAU8 154 BRAZEAA9 BRAZ# BRAZEAU EDSON A BRAZ OUT BRAZEAB LODGEPO DALEH TP DEERH MTN COA BRAZEAU BRAZEAU MARLBOR MARLBOR COLD CR7 5.1R R 151 BRAZ# DALEHUR7 995 W.GRN TP 6 25 Fortis New Hornbeck 345S Substation - P1460 SK Tie (Import): -0.1 MW BC and MATL (Import): 33 MW FIGURE A1-1-SYSTEM NORMAL 2017 WINTER PEAK PRE-DEVELOPMENT PRINTED ON MONDAY 05. OCTOBER 2015 Bus - Voltage (kv/pu) Branch - MW/Mvar Equipment - MW/Mvar 100.0%Rate B 1.200OV 0.900UV kv: <= <=69.000<= <= <= >

34 1 423 KEEPHIL KEYSTON S_ P C BRB W PEMBI KEYSTO P C BRA BUCK TAP 135 SUNDANC4 49 KEYSTON ELKRIVE W PEMBI P C BRA CYNTHIA HBOG BRA BICKERD AMOCO BR EDSON ELKRIVTP PINEDAL EDSON BICKERD G.ROBB T OBED TAP FICKL TP MARLBTAP MARLBOR BENBOW BRAZEAU8 154 BRAZEAA9 BRAZ# BRAZEAU EDSON A BRAZ OUT BRAZEAB LODGEPO DALEH TP DEERH MTN COA BRAZEAU BRAZEAU MARLBOR MARLBOR COLD CR7 6.9R R BRAZ# DALEHUR7 995 W.GRN TP 6 25 Fortis New Hornbeck 345S Substation - P1460 SK Tie (Import): -0.1 MW BC and MATL (Import): MW FIGURE A1-2 N-1: BRAZEAU PLANT 62S 240/138 KV T WINTER PEAK PRE-DEVELOPMENT PRINTED ON MONDAY 05. OCTOBER 2015 Bus - Voltage (kv/pu) Branch - MW/Mvar Equipment - MW/Mvar 100.0%Rate B 1.200OV 0.900UV kv: <= <=69.000<= <= <= >

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition

Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition Executive Summary Project Overview EPCOR Distribution & Transmission Inc. (EDTI), in its capacity as the

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014 SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Central East Region Transmission Development Needs Identification Document

Central East Region Transmission Development Needs Identification Document Executive Summary As part of its mandate, the ( AESO ) is responsible for planning the transmission system within the province of Alberta as set out in the Electric Utilities Act, SA 2003 c E-5.1 ( EUA

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

NorthernLights HVDC Project

NorthernLights HVDC Project WECC COMPREHENSIVE PROGRESS REPORT December 4, 2008 Prepared for TransCanada by Ben Williams TABLE OF CONTENTS EXECUTIVE SUMMARY... III 1.0 BACKGROUND & INTRODUCTION... 1 1.1 BACKGROUND... 1 1.2 INTRODUCTION...

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Included in this Stakeholder Information Package:

Included in this Stakeholder Information Package: Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink

More information

Alberta Remedial Actions Schemes

Alberta Remedial Actions Schemes Alberta Remedial Actions s Date: Oct. 31, 2018 20 Anderson 801s 240 kv Line 9L933, 9L934 and 9L950 Thermal Protection to Sheerness Plant ATCO Electric, Other MP Mitigates overloads on each line by sending

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

ISO Rules Part 300 System Reliability and Operations Division 304 Routine Operations Section Electric Motor Start Requirements

ISO Rules Part 300 System Reliability and Operations Division 304 Routine Operations Section Electric Motor Start Requirements External Consultation Draft February 7, 2019 Applicability 1 Section 304.2 applies to: (a) the operator of an industrial complex that is: (i) in the Empress Area with an electric motor of a size twenty

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

Decision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station.

Decision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station. Decision 2011-424 (Errata) Access Pipeline Inc. Errata to Decision 2011-424 Temporary Generation at Smoky Lake Pump Station January 4, 2012 The Alberta Utilities Commission Decision 2011-424 (Errata):

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0 ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by: FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information